CASE STUDY NUVIA ROSYTH
Transcript
Page 1: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

CASE STUDYNUVIA ROSYTH

Page 2: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• High security site – limited access for personnel

• Location of final installation remote for tradesmen

• Limited lay down available for site access

RESTRICTIONS

Page 3: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down
Page 4: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down
Page 5: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• Onsite time reduced from 16 weeks to 1 day

15.8 weeks on site saving

• Overall cost of prelims on site 15.8 weeks saved

£79k saving to client

• Mechanical & Electrical equipment tested and assured

offsite prior to installation

• Modules could be removed from inside the dock & re

installed within 3 days

IMPACT OFMODULAR CONSTRUCTION

Page 6: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• Modules construction at ground level

• Modules fitted out & tested prior to delivery

• Mock up of submarine tested adjacent to modules

• Offsite construction local to specialist trades

• Installation of 5 modules completed in 1 working day

BENEFITS OFMODULAR CONSTRUCTION