Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | gurinder-singh |
View: | 219 times |
Download: | 0 times |
of 91
7/28/2019 Cash flows and capital budgeting.pptx
1/91
Chapter 10:Cash F lows and
Other Topics inCapital Budgeting
2002, Prentice Hall, Inc.
7/28/2019 Cash flows and capital budgeting.pptx
2/91
Capital Budgeting:the process of planning
for purchases of long-term assets.
example:
Our firm must decide whether to purchase a
new plastic molding machine for $127,000.
How do we decide?
Will the machine be profitable?
Will our firm earn a high rate of return on
the investment?
The relevant project information follows:
7/28/2019 Cash flows and capital budgeting.pptx
3/91
The cost of the new machine is $127,000.
Installation will cost $20,000.
$4,000 in net working capital will be needed atthe time of installation.
The project will increase revenues by $85,000 per
year, but operating costs will increase by 35% ofthe revenue increase.
Simplified straight line depreciation is used.
Class life is 5 years, and the firm is planning tokeep the project for 5 years.
Salvage value at the end of year 5 will be $50,000.
14% cost of capital; 34% marginal tax rate.
7/28/2019 Cash flows and capital budgeting.pptx
4/91
7/28/2019 Cash flows and capital budgeting.pptx
5/91
Capital Budgeting Steps
1) Evaluate Cash Flows
0 1 2 3 4 5 n6 . . .
7/28/2019 Cash flows and capital budgeting.pptx
6/91
Capital Budgeting Steps
1) Evaluate Cash Flows
0 1 2 3 4 5 n6 . . .
Initial
outlay
7/28/2019 Cash flows and capital budgeting.pptx
7/91
Capital Budgeting Steps
1) Evaluate Cash Flows
0 1 2 3 4 5 n6 . . .
Annual Cash Flows
Initial
outlay
7/28/2019 Cash flows and capital budgeting.pptx
8/91
Capital Budgeting Steps
1) Evaluate Cash Flows
0 1 2 3 4 5 n6 . . .
Terminal
Cash flow
Annual Cash Flows
Initial
outlay
7/28/2019 Cash flows and capital budgeting.pptx
9/91
2) Evaluate the risk of the project.
well assume that the risk of the project is
the same as the risk of the overall firm. If we do this, we can use the firms cost of
capital as the discount rate for capital
investment projects.
Capital Budgeting Steps
7/28/2019 Cash flows and capital budgeting.pptx
10/91
3) Accept or Reject the Project.
Capital Budgeting Steps
7/28/2019 Cash flows and capital budgeting.pptx
11/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow attime 0?
(Purchase price of the asset)+ (shipping and installation costs)
(Depreciable asset)
+ (Investment in working capital)+ After-tax proceeds from sale of old asset
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
12/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow attime 0?
(127,000)+ (shipping and installation costs)
(Depreciable asset)
+ (Investment in working capital)+ After-tax proceeds from sale of old asset
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
13/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000)+ ( 20,000)
(Depreciable asset)
+ (Investment in working capital)+ After-tax proceeds from sale of old asset
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
14/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000)+ ( 20,000)
(147,000)
+ (Investment in working capital)+ After-tax proceeds from sale of old asset
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
15/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000)+ ( 20,000)
(147,000)
+ ( 4,000)+ After-tax proceeds from sale of old asset
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
16/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000)+ ( 20,000)
(147,000)
+ ( 4,000)+ 0
Net Initial Outlay
7/28/2019 Cash flows and capital budgeting.pptx
17/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000) Purchase price of asset+ ( 20,000) shipping and installation
(147,000) depreciable asset
+ ( 4,000) net working capital+ 0 proceeds from sale of old asset
($151,000) net initial outlay
7/28/2019 Cash flows and capital budgeting.pptx
18/91
Step 1: Evaluate Cash Flows
a) Initial Outlay: What is the cash flow at
time 0?
(127,000) Purchase price of asset+ ( 20,000) shipping and installation
(147,000) depreciable asset
+ ( 4,000) net working capital+ 0 proceeds from sale of old asset
($151,000) net initial outlay
7/28/2019 Cash flows and capital budgeting.pptx
19/91
Step 1: Evaluate Cash Flows
b) Annual Cash Flows: What
incremental cash flows occur over the
life of the project?
7/28/2019 Cash flows and capital budgeting.pptx
20/91
Incremental revenue
- Incremental costs
- Depreciation on project
Incremental earnings before taxes- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Each Year, Calculate:
7/28/2019 Cash flows and capital budgeting.pptx
21/91
Incremental revenue
- Incremental costs
- Depreciation on project
Incremental earnings before taxes- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
22/91
85,000
- Incremental costs
- Depreciation on project
Incremental earnings before taxes- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
23/91
85,000
(29,750)
- Depreciation on project
Incremental earnings before taxes- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
24/91
85,000
(29,750)
(29,400)
Incremental earnings before taxes- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
25/91
85,000
(29,750)
(29,400)
25,850- Tax on incremental EBT
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
26/91
85,000
(29,750)
(29,400)
25,850(8,789)
Incremental earnings after taxes
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
27/91
85,000
(29,750)
(29,400)
25,850(8,789)
17,061
+ Depreciation reversal
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
28/91
85,000
(29,750)
(29,400)
25,850(8,789)
17,061
29,400
Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
29/91
85,000 Revenue
(29,750) Costs
(29,400) Depreciation
25,850 EBT(8,789) Taxes
17,061 EAT
29,400 Depreciation reversal
46,461 = Annual Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
30/91
Step 1: Evaluate Cash F lows
c) Terminal Cash Flow: What is the cash
flow at the end of the projects life?
Salvage value
+/- Tax effects of capital gain/loss
+ Recapture of net working capitalTerminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
31/91
Step 1: Evaluate Cash F lows
c) Terminal Cash Flow: What is the cash
flow at the end of the projects life?
50,000 Salvage value
+/- Tax effects of capital gain/loss
+ Recapture of net working capitalTerminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
32/91
Tax Effects of Sale of Asset:
Salvage value = $50,000
Book value = depreciable asset - total
amount depreciated.
Book value = $147,000 - $147,000
= $0.
Capital gain = SV - BV
= 50,000 - 0 = $50,000
Tax payment = 50,000 x .34 = ($17,000)
7/28/2019 Cash flows and capital budgeting.pptx
33/91
Step 1: Evaluate Cash F lows
c) Terminal Cash Flow: What is the cash
flow at the end of the projects life?
50,000 Salvage value
(17,000) Tax on capital gain
Recapture of NWCTerminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
34/91
Step 1: Evaluate Cash F lows
c) Terminal Cash Flow: What is the cash
flow at the end of the projects life?
50,000 Salvage value
(17,000) Tax on capital gain
4,000 Recapture of NWC
Terminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
35/91
Step 1: Evaluate Cash F lows
c) Terminal Cash Flow: What is the cash
flow at the end of the projects life?
50,000 Salvage value
(17,000) Tax on capital gain
4,000 Recapture of NWC
37,000 Terminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
36/91
Project NPV:
CF(0) = -151,000
CF(1 - 4) = 46,461
CF(5) = 46,461 + 37,000 = 83,461
Discount rate = 14%
NPV = $27,721
We would acceptthe project.
7/28/2019 Cash flows and capital budgeting.pptx
37/91
Capital Rationing
Suppose that you have evaluated
5 capital investment projects for
your company.
Suppose that the VP of Finance
has given you a limited capital
budget. How do you decide which
projects to select?
7/28/2019 Cash flows and capital budgeting.pptx
38/91
Capital Rationing
You could rank the projects by IRR:
7/28/2019 Cash flows and capital budgeting.pptx
39/91
Capital Rationing
IRR
5%
10%
15%
20%
25%
$
1
You could rank the projects by IRR:
7/28/2019 Cash flows and capital budgeting.pptx
40/91
7/28/2019 Cash flows and capital budgeting.pptx
41/91
Capital Rationing
You could rank the projects by IRR:IRR
5%
10%
15%
20%
25%
$
1 2 3
7/28/2019 Cash flows and capital budgeting.pptx
42/91
Capital Rationing
You could rank the projects by IRR:IRR
5%
10%
15%
20%
25%
$
1 2 3 4
7/28/2019 Cash flows and capital budgeting.pptx
43/91
Capital Rationing
You could rank the projects by IRR:IRR
5%
10%
15%
20%
25%
$
1 2 3 4 5
7/28/2019 Cash flows and capital budgeting.pptx
44/91
Capital Rationing
You could rank the projects by IRR:IRR
5%
10%
15%
20%
25%
$
1 2 3 4 5
$X
Our budget is limited
so we accept onlyprojects 1, 2, and 3.
7/28/2019 Cash flows and capital budgeting.pptx
45/91
Capital Rationing
You could rank the projects by IRR:IRR
5%
10%
15%
20%
25%
$
1 2 3
$X
Our budget is limited
so we accept onlyprojects 1, 2, and 3.
7/28/2019 Cash flows and capital budgeting.pptx
46/91
Capital Rationing
Ranking projects by IRR is notalways the best way to deal with a
limited capital budget.
Its better to pick the largest NPVs.
Lets try ranking projects by NPV.
7/28/2019 Cash flows and capital budgeting.pptx
47/91
Problems with Project Ranking
1) Mutually exclusive projects of unequal
size (the size disparity problem)
The NPV decision may not agree with
IRR or PI.
Solution: select the project with the
largest NPV.
7/28/2019 Cash flows and capital budgeting.pptx
48/91
Size Dispar ity example
Project A
year cash flow
0 (135,000)
1 60,000
2 60,000
3 60,000
required return = 12%
IRR = 15.89%
NPV = $9,110
PI = 1.07
7/28/2019 Cash flows and capital budgeting.pptx
49/91
Size Dispar ity example
Project B
year cash flow
0 (30,000)
1 15,000
2 15,000
3 15,000
required return = 12%
IRR = 23.38%
NPV = $6,027
PI = 1.20
Project A
year cash flow
0 (135,000)
1 60,000
2 60,000
3 60,000
required return = 12%
IRR = 15.89%
NPV = $9,110
PI = 1.07
7/28/2019 Cash flows and capital budgeting.pptx
50/91
Size Dispar ity example
Project B
year cash flow
0 (30,000)
1 15,000
2 15,000
3 15,000
required return = 12%
IRR = 23.38%
NPV = $6,027
PI = 1.20
Project A
year cash flow
0 (135,000)
1 60,000
2 60,000
3 60,000
required return = 12%
IRR = 15.89%
NPV = $9,110
PI = 1.07
7/28/2019 Cash flows and capital budgeting.pptx
51/91
7/28/2019 Cash flows and capital budgeting.pptx
52/91
Time Dispar ity example
Project Ayear cash flow
0 (48,000)
1 1,200
2 2,400
3 39,000
4 42,000
required return = 12%
IRR = 18.10%
NPV = $9,436
PI = 1.20
7/28/2019 Cash flows and capital budgeting.pptx
53/91
Time Dispar ity example
Project Byear cash flow
0 (46,500)
1 36,500
2 24,000
3 2,400
4 2,400
required return = 12%
IRR = 25.51%
NPV = $8,455
PI = 1.18
Project Ayear cash flow
0 (48,000)
1 1,200
2 2,400
3 39,000
4 42,000
required return = 12%
IRR = 18.10%
NPV = $9,436
PI = 1.20
7/28/2019 Cash flows and capital budgeting.pptx
54/91
Time Dispar ity example
Project Byear cash flow
0 (46,500)
1 36,500
2 24,000
3 2,400
4 2,400
required return = 12%
IRR = 25.51%
NPV = $8,455
PI = 1.18
Project Ayear cash flow
0 (48,000)
1 1,200
2 2,400
3 39,000
4 42,000
required return = 12%
IRR = 18.10%
NPV = $9,436
PI = 1.20
7/28/2019 Cash flows and capital budgeting.pptx
55/91
Mutually Exclusive I nvestments with
Unequal L ives
Suppose our firm is planning to
expand and we have to select 1 of 2
machines.
They differ in terms of economic life
and capacity.
How do we decide which machine to
select?
Th ft t h fl
7/28/2019 Cash flows and capital budgeting.pptx
56/91
The after-tax cash flows are:
Year Machine 1 Machine 2
0 (45,000) (45,000)
1 20,000 12,000
2 20,000 12,0003 20,000 12,000
4 12,000
5 12,000
6 12,000
Assume a required return of 14%.
7/28/2019 Cash flows and capital budgeting.pptx
57/91
Step 1: Calculate NPV
NPV1= $1,433
NPV2 = $1,664
So, does this mean #2 is better?
No! The two NPVs cant be
compared!
St 2 E i l t A l
7/28/2019 Cash flows and capital budgeting.pptx
58/91
Step 2: Equivalent Annual
Annui ty (EAA) method
If we assume that each project will be
replaced an infinite number of times in the
future, we can convert each NPV to anannuity.
The projects EAAs can be compared to
determine which is the best project!
EAA: Simply annuitize the NPV over the
projects life.
7/28/2019 Cash flows and capital budgeting.pptx
59/91
EAA with your calculator :
Simply spread the NPV over the life
of the project
Machine 1: PV = 1433, N = 3, I = 14,solve: PMT = -617.24.
Machine 2: PV = 1664, N = 6, I = 14,
solve: PMT = -427.91.
EAA $617
7/28/2019 Cash flows and capital budgeting.pptx
60/91
EAA1 = $617
EAA2 = $428
This tells us that:
NPV1 = annuity of$617 per year.
NPV2 = annuity of$428 per year. So, weve reduced a problem with
different time horizons to a couple of
annuities.
Decision Rule: Select the highest
EAA. We would choose machine #1.
7/28/2019 Cash flows and capital budgeting.pptx
61/91
Step 3: Convert back to NPV
7/28/2019 Cash flows and capital budgeting.pptx
62/91
Step 3: Convert back to NPV
Assuming infinite replacement, theEAAs are actually perpetuities. Get the
PV by dividing the EAA by the required
rate of return.
7/28/2019 Cash flows and capital budgeting.pptx
63/91
7/28/2019 Cash flows and capital budgeting.pptx
64/91
Step 3: Convert back to NPV
Assuming infinite replacement, theEAAs are actually perpetuities. Get the
PV by dividing the EAA by the required
rate of return.
NPV 1 = 617/.14 = $4,407
NPV 2 = 428/.14 = $3,057
7/28/2019 Cash flows and capital budgeting.pptx
65/91
Step 3: Convert back to NPV
Assuming infinite replacement, theEAAs are actually perpetuities. Get the
PV by dividing the EAA by the required
rate of return.
NPV 1 = 617/.14 = $4,407
NPV 2 = 428/.14 = $3,057
This doesnt change the answer, of
course; it just converts EAA to a NPV
that can be compared.
7/28/2019 Cash flows and capital budgeting.pptx
66/91
Practice Problems:
Cash F lows & Other Topics
in Capital Budgeting
Project I nformation: Problem 1a
7/28/2019 Cash flows and capital budgeting.pptx
67/91
j
Cost of equipment = $400,000
Shipping & installation will be $20,000 $25,000 in net working capital required at setup
3-year project life, 5-year class life
Simplified straight line depreciation
Revenues will increase by $220,000 per year
Defects costs will fall by $10,000 per year
Operating costs will rise by $30,000 per year
Salvage value after year 3 is $200,000
Cost of capital = 12%, marginal tax rate = 34%
7/28/2019 Cash flows and capital budgeting.pptx
68/91
Problem 1a
I ni tial Outlay:
(400,000) Cost of asset
+ ( 20,000) Shipping & installation
(420,000) Depreciable asset
+ ( 25,000) Investment in NWC($445,000) Net Initial Outlay
For Years 1 - 3: Problem 1a
7/28/2019 Cash flows and capital budgeting.pptx
69/91
220,000 Increased revenue
10,000 Decreased defects
(30,000) Increased operating costs
(84,000) Increased depreciation
116,000 EBT
(39,440) Taxes (34%)
76,560 EAT84,000 Depreciation reversal
160,560 = Annual Cash Flow
For Years 1 3: Problem 1a
Problem 1a
7/28/2019 Cash flows and capital budgeting.pptx
70/91
Terminal Cash F low:
Salvage value
+/- Tax effects of capital gain/loss
+ Recapture of net working capital
Terminal Cash Flow
Problem 1a
7/28/2019 Cash flows and capital budgeting.pptx
71/91
Problem 1a
7/28/2019 Cash flows and capital budgeting.pptx
72/91
Terminal Cash F low:
200,000 Salvage value(10,880) Tax on capital gain
25,000 Recapture of NWC
214,120 Terminal Cash Flow
7/28/2019 Cash flows and capital budgeting.pptx
73/91
Problem 1b
7/28/2019 Cash flows and capital budgeting.pptx
74/91
Project I nformation:
For the same project, suppose wecan only get $100,000 for the old
equipment after year 3, due to
rapidly changing technology.
Calculate the IRR and NPV for theproject.
Is it still acceptable?
Problem 1b
7/28/2019 Cash flows and capital budgeting.pptx
75/91
Terminal Cash F low:
Salvage value
+/- Tax effects of capital gain/loss
+ Recapture of net working capital
Terminal Cash Flow
Problem 1b
7/28/2019 Cash flows and capital budgeting.pptx
76/91
Terminal Cash F low:
Salvage value = $100,000
Book value = depreciable asset - total
amount depreciated.
Book value = $168,000.
Capital loss = SV - BV = ($68,000) Tax refund = 68,000 x .34 = $23,120
7/28/2019 Cash flows and capital budgeting.pptx
77/91
7/28/2019 Cash flows and capital budgeting.pptx
78/91
Automation Project: Problem 2
7/28/2019 Cash flows and capital budgeting.pptx
79/91
Cost of equipment = $550,000
Shipping & installation will be $25,000
$15,000 in net working capital required at setup
8-year project life, 5-year class life
Simplified straight line depreciation Current operating expenses are $640,000 per yr.
New operating expenses will be $400,000 per yr.
Already paid consultant $25,000 for analysis.
Salvage value after year 8 is $40,000
Cost of capital = 14%, marginal tax rate = 34%
Problem 2
7/28/2019 Cash flows and capital budgeting.pptx
80/91
Problem 2
I ni tial Outlay:
(550,000) Cost of new machine
+ (25,000) Shipping & installation
(575,000) Depreciable asset
+ ( 15,000) NWC investment(590,000) Net Initial Outlay
For Years 1 5:Problem 2
7/28/2019 Cash flows and capital budgeting.pptx
81/91
240,000 Cost decrease
(115,000) Depreciation increase
125,000 EBIT(42,500) Taxes (34%)
82,500 EAT
115,000 Depreciation reversal
197,500 = Annual Cash Flow
For Years 1 - 5:
Problem 2
7/28/2019 Cash flows and capital budgeting.pptx
82/91
240,000 Cost decrease
( 0) Depreciation increase
240,000 EBIT(81,600) Taxes (34%)
158,400 EAT
0 Depreciation reversal
158,400 = Annual Cash Flow
For Years 6 - 8:
Problem 2
7/28/2019 Cash flows and capital budgeting.pptx
83/91
Terminal Cash F low:
40,000 Salvage value
(13,600) Tax on capital gain15,000 Recapture of NWC
41,400 Terminal Cash Flow
Problem 2 Solution:
7/28/2019 Cash flows and capital budgeting.pptx
84/91
NPV and IRR:
CF(0) = -590,000
CF(1 - 5) = 197,500
CF(6 - 7) = 158,400
CF(10) = 158,400 + 41,400 = 199,800
Discount rate = 14% IRR = 28.13% NPV = $293,543
We would accept the project!
Problem 3
7/28/2019 Cash flows and capital budgeting.pptx
85/91
Replacement Project:
Old Asset (5 years old):
Cost of equipment = $1,125,000
10-year project life, 10-year class life
Simplified straight line depreciation
Current salvage value is $400,000 Cost of capital = 14%, marginal tax
rate = 35%
7/28/2019 Cash flows and capital budgeting.pptx
86/91
Problem 3: Sell the Old Asset:
7/28/2019 Cash flows and capital budgeting.pptx
87/91
Salvage value = $400,000
Book value = depreciable asset - total
amount depreciated.
Book value = $1,125,000 - $562,500= $562,500.
Capital gain = SV - BV
= 400,000 - 562,500 = ($162,500)
Tax refund = 162,500 x .35 = $56,875
Problem 3I i ti l O tl
7/28/2019 Cash flows and capital budgeting.pptx
88/91
Problem 3 I ni tial Outlay:
(1,750,000) Cost of new machine
+ ( 56,000) Shipping & installation
(1,806,000) Depreciable asset
+ ( 68,000) NWC investment
+ 456,875 After-tax proceeds (soldold machine)
(1,417,125) Net Initial Outlay
Problem 3
7/28/2019 Cash flows and capital budgeting.pptx
89/91
385,000 Increased sales & cost savings
(248,700) Extra depreciation
136,300 EBT
(47,705) Taxes (35%)
88,595 EAT248,700 Depreciation reversal
337,295 = Differential Cash Flow
For Years 1 - 5:
7/28/2019 Cash flows and capital budgeting.pptx
90/91
7/28/2019 Cash flows and capital budgeting.pptx
91/91