Castleton and Heywood Masterplan Unlocking the Potential Peter Rowlinson, Rochdale Metropolitan Borough Council Ludovic Pittie, Mouchel Group Final Masterplan Presentation – Autumn 2010
Transcript
Page 1: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton and Heywood MasterplanUnlocking the Potential

Peter Rowlinson, Rochdale Metropolitan Borough CouncilLudovic Pittie, Mouchel Group

Final Masterplan Presentation – Autumn 2010

Page 2: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Contents

Castleton

Station

Heywood

Station

1. Introduction

2. Context

3. Shared Vision

4. Ideas for Changes

5. Implementation Plan

6. Next Steps

Page 3: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

1. Introduction

Project BoardEast Lancashire Railway TrustEast Lancashire light Railway CompanyRochdale Development AgencyRochdale Metropolitan Borough Council Impact partnership

Page 4: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Background

• Study by Locum Consulting for East Lancashire Railway Trust to develop a Strategy for:

– increasing the number of visitors from 107,000 to over 200,000.

– extending the line to Castleton and the main line connection

– creating further attractions along the route.

• One key recommendation was the need for coordinated development plans for Heywood and Castleton

Page 5: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Development Process

July 10 04 Aug 10 14 Sept 10

Collect & Analyse information

Review Workshop

Document sign off

Project starts

Vision development

Masterplandevelopment

Report finalisation

Design Workshop

19 Aug 10 23 Sept 10 08 Oct 10

Townships & ELR Trust

presentations

Project Board

meeting

Page 6: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

2. Strategic Context

Page 7: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Relationship with LDF

• Heywood– Strategic employment sites south of

Heywood connecting to M62 potentially frees up area around Heywood station

– Strategic housing site north of Heywood station framework supports opportunities for residential development

– Heywood regeneration area

• Castleton– ELR links to Castleton– Castleton economic growth area– Strategic mixed use sites in Castleton– Strategic employment sites in north and

west Castleton - compliments destination heritage village development around station/canal

– Retained Green belt between Castleton and Heywood - leisure/green links opportunities and gateway to landscape to north

Page 8: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

3. Shared Vision

Page 9: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Shared design principles• Develop sustainable communities;• Draw from the existing village character to inform

developments,• Develop the design of streets and alleys to link with the local

character and create streets for people;• Promote sustainable transport – canal, rail interchange;

• Build on physical heritage and green and water space assets;• Reveal buried treasures of the local heritage assets;• Retain, restore and reinvent industrial heritage character such

as mill buildings and canal;

• Connect all destination and development opportunities;• Target the correct development for successful, sustainable

communities such as live/work development;• Encourage local spend and internal investment;• Establish Learning destination and learning/skills spaces;

• Expand Green links and green and growing space throughout;• Enable Green spaces access and form gateways to wider

countryside;• Create leisure and play opportunities; and• Promote biodiversity.

Page 10: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Heywood The Vision

Shared Vision for Sustainable Living

Page 11: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Illustrative MasterplanIdeas for Change

Page 12: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

4. Ideas for change

• Castleton: The Heart

• Green Living

• Heywood Culture Park

• Castleton: Reinventing Manchester Road

Page 13: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton: The Heart

Page 14: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton: The Heart

Page 15: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton: The Heart

Page 16: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton: The Heart

Page 17: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Green Living

Page 18: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Green Living

Page 19: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Green Living: Features

Blue Pits Country Park Marina & Ecopark

Page 20: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Heywood Culture Park

Page 21: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Heywood Culture Park

Page 22: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Heywood Culture Park: Features

Page 23: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Heywood Culture Park: Long Term

Page 24: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Castleton: Reinventing Manchester Road

Page 25: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Reinventing Manchester Road

Page 26: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

5. Implementation Plan

Page 27: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

• ELR Extension and Castleton Station;

• ELR Heywood Station and restoration of Sefton Street Warehouse; and

• Planned developments on Woolworths and Whipp & Bourne site, which can foster regeneration through retail and residential developments.

Key Precursors

Page 28: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

Overall Masterplan PhasingImmediate (0-2 years): projects that are already underway and critical actions

Short term (2-5 years): proposals that have been identified as potential opportunities

Medium term (5-10 years): proposals that will require coordinated funding

Long term (10+): proposals with significant preparatory work

Page 29: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

• RMBC and ELR Trust to engage with Goods Warehouse landowner regarding the principles of a development and potential land acquisition;

• Design and development of permanent ELR Station building in former station platform site including events area;

• Consultation with Manchester Transport Museum, Rochdale Fire Museum and other potential interested parties to occupy Goods Warehouse;

• Feasibility study for re-opening Railway Street; and

• Prepare HLF Funding application for Phase 1 of the Heywood Culture Park, including ELR Station building, pedestrian bridge, Good Warehouse restoration and learning and participation venue.

Next Steps - Heywood

Page 30: Castleton and Heywood MP Final - Metropolitan Borough of ...democracy.rochdale.gov.uk/documents/s1857/Ludovic... · Castleton and Heywood Masterplan Unlocking the Potential Peter

• ELR extension and new platform – discussion and negotiations with Network Rail regarding operational and land take requirements;

• Test viability of bridge parapet design changes and extension for new cantilevered station. Design and development of station building;

• Submission of planning application for development of the Woolworths and Whipp & Bourne site; negotiations regarding contributions;

• Develop Design Guide and set up Grant system for Shop Front Improvements;

• Consultation with British Waterways regarding moorings and Marina; and

• Sustrans project for upgrade of pedestrian and cycle link along Chadwick Lane.

Next Steps - Castleton


Recommended