+ All Categories
Home > Documents > Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category...

Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category...

Date post: 26-Jun-2018
Category:
Upload: vuongminh
View: 215 times
Download: 0 times
Share this document with a friend
20
Onsite Generation Commercial Lighting Common Lighting Materials Commercial HVAC CO Sensors for car park vent. Naturally ventilate. Category Improved Design Strategies Organic lighting solution (motion and lux sensor). Lux sensors to reduce lamp run time. Motion sensors to reduce lamp run time. Intelligent design to maximise functionality. Increase design life through density. Roof top solar PV. Total 15 kW assumed. Page 5
Transcript
Page 1: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Onsite Generation

Commercial Lighting

Common Lighting

Materials

Commercial HVAC CO Sensors for car park vent. Naturally ventilate.

Category Improved Design Strategies

Organic lighting solution (motion and lux sensor).

Lux sensors to reduce lamp run time. Motion sensors to reduce lamp run time.

Intelligent design to maximise functionality. Increase design life through density.

Roof top solar PV. Total 15 kW assumed.

Page 5

Page 2: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

# 58

m2

870

Years 115

Occupancy (1person/15m2)To compare projects of different size, density

and functionality, commercial LC building

impacts are measured per m2 per year,

residential LC impacts are measured per

occupant per year

Net Total Covered Floor Area

Estimated Building Service Life

The life cycle impacts associated with an average new building with the above functionality have been estimated.

The purpose of this process is to effectively inform the design process and ensure the environmental goals of the

project are met without compromising other key project goals. This estimate is inherently limited in accuracy as the

project is still in the early stages of design and many of the subsequent design decisions will influence the

performance of the building significantly. However, it does effectively inform the design team on which building

elements need the most attention.

Below is a summary of the total life cycle impacts of the building which shows the largest environmental impacts

related to Commercial Operational Energy. Further detail on the breakdown of these impacts is found in the report.

For the purposes of the LCA scoping study, the development was divided into residential and commercial spaces.

The commercial portion of the building consists of 58 estimated occupants and 870m2 commercial space.

Project Summary Notes

Concept Design Summary

6

165

19

Life Cycle Impacts(kgCO2e/Occupant/year)

Embodied Impacts

Commercial Operational Energy

Common Area Operational Energy

Page 6

Page 3: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

● Increase density to reduce redevelopment potential

● Improve design quality (performance and aesthetics)

● Design for adaptability and future occupants

Project Functionality - Design Life

For office buildings, the core function is to provide a work environment to occupants. Sustainable buildings provide

more occupancy with less materials and energy. Car park and common areas are hence critical considerations for

good LC performance. Both of these factors have been trending poorly in Australia until recently with a growing

number of office buildings being built with little or no car parking. Allowing more occupants to be housed within

smaller floor areas increases the functionality of the building.

The design life of the 248 Newcastle St development is likely to benefit from the mixed use, strata breakdown of

lots. This will decrease redevelopment pressure until it becomes an equivalent low density building compared to

the surroundings. Consideration during the design phase to how the building may evolve in the future will also aid

design life.

Given the likely long design life of the project (115 years), construction materials with long term performance and

low maintenance requirements are encouraged. From a sustainability perspective the carbon intensity of these

materials must however be considered carefully.

Building design life is critical for LC performance. Unfortunately the studies indicate that less than 10% of buildings

reach their practical service life. A vast majority of demolitions are motivated by economic or aesthetic reasons with

no regard for the structural integrity of the core building. Changing functional requirements for buildings also drive

some redevelopment. Key strategies to increase building life include:

Project Functionality - Occupancy

Key Themes and Opportunities

Page 7

Page 4: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

3 1.6% 3 2.4%

0 0.2% 0 0.3%

2 1.1% 4 2.6%

1 0.3% 1 0.4%

0 0.1% 0 0.1%

59 31.3% 43 31.4%

3 1.6% 3 2.2%

34 17.9% 31 22.5%

5 2.8% 5 3.5%

22 11.4% 20 14.4%

37 19.6% 30 21.6%

4 2.2% 4 3.1%

13 7.1% 10 7.1%

1 0.4% 1 0.6%

5 2.5% 5 3.5%

- 0.0% 21- -15.7%

190 100.0% 136 100.0%

Embodied

Carbon

Materials

Materials Transport

Recurring (Building Maintenance)

Assembly (Building Construction)

Planning and Sales

Category

LC Carbon Emissions (kgCO2e / m2 / year)

Base Design Improved Building

Onsite Generation Photo Voltaics

Total (kgCO2e / m2 / Year)

Key Themes and Opportunities

The life cycle emissions of the current base design Energy monitoring are also in place to significantly reduce the

commercial electricity use. Use of roof space to produce on site electricity is also included to improve overall

environmental and cost performance, with a total 15 kW system assumed initially. Other opportunities include

engineered HVAC solutions to increase natural ventilation and system efficiency, and lighting controls.

The PV system size of 45kW total (commercial and residential) assumes a custom roof design to optimise PV

allocation. In case the total PV system can not be fitted, high efficiency panels and other recommendations will

have to be implemented to compensate.

Common

Lighting

BMS

Vertical Transport

Operational

Carbon

Emissions

Commercial

HVAC

Water Heating

Work Stations

Hydraulic Pumps

Miscellaneous

UPS

Lighting

Life Cycle Carbon Emissions Detail

Page 8

Page 5: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

CategoryImproved Design

StrategiesPotential Further

Strategies

The following table summarises stragegies already in place and lists a number of potential additional strategies to

further improve the performance of the design.

Commercial Work Stations Under further investigationCloud based servers. Behavioural Change

Programme. High Efficiency Appliance Fitout.

Commercial HVAC CO Sensors for car park vent. Naturally ventilate. VSDs for fans. High COP / EER equipment.

Improved fabric performance. Automatic Louvres

Commercial Lighting Organic lighting solution (motion and lux sensor). Increased natural light levels.

Common Vertical Transport Under further investigation

Occupancy controlled lighting and ventilation. Stairs

as first preference to vertical transport. High efficiency

drives, gearboxes and controls. Regenerative drive

mechanisms.

Common LightingLux sensors to reduce lamp run time. Motion

sensors to reduce lamp run time. Increased natural light levels. High efficiency lamps.

Under further investigation Carbon offsetting.

Onsite Generation Roof top solar PV. Total 15 kW assumed. PV facade installed. Tri-generation. Solar Thermal

Hot Water.

Recurring (Building

Maintenance)Under further investigation

Use of low carbon finishes, fittings and construction

materials. Carbon offsetting. Use of low maintenance

finishes, fittings and construction materials.

Assembly (Building

Construction)Under further investigation

Provision of alternative biofuels for construction fleet.

Carbon offsetting. Fast construction time.

Materials Transport Under further investigation

Low carbon transport methods (ship and rail).

Reduction in materials through technology (e.g.

concrete replacement technology). Carbon offsetting.

Locally produced materials.

Planning and Sales

Commercial Water Heating

Materials

Under further investigationSolar Thermal with gas top-up. Gas Heating over

electric

Intelligent design to maximise functionality.

Increase design life through density.

Low carbon local materials where possible. Reduction

in materials through technology (e.g. Bubbledeck).

Light frame construction. Carbon offsetting. Low

maintenance finishes.

Page 9

Page 6: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Page 10

Page 7: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

10%

13%

69%

8%

100%

2,329,615 32% 1,392,470 30%

117,446 2% 117,446 3%

1,333,051 19% 1,199,746 26%

205,530 3% 184,977 4%

851,483 12% 766,335 17%

1,457,460 20% 1,069,237 23%

164,349 2% 120,927 3%

528,507 7% 380,525 8%

29,361 0% 29,361 1%

185,956 3% 185,956 4%

- 0% 837,936- -18%

7,202,759 100% 4,609,045 100%

Maintenance Costs 1,231,335

Commercial Operating Energy Costs 6,458,935

Base design Project Life Cycle Costs

In order to focus design attention on cost effective solutions that lead to true savings for the building owners, the

following base design life cycle cost figures have been estimated. The values quoted below do not allow for

inflation (see later note in report regarding inflation) and hence future operating and maintenance costs are likely to

be higher than that quoted below. Further to this, the construction cost calculations only include materials, labour

and transport and hence represent only a small proportion of total site based expenditure.

Category Base design Estimated LC Costs ($)

Construction Costs 959,628

Total

Key Themes and Opportunities

The strategies identified for reducing the environmental impacts of the building will also have positive life cycle cost

impacts for the future owners. There exists an opportunity to further increase these savings with the

implementation of further strategies ranked by life cycle cost gain.

Hydraulic Pumps

Miscellaneous

Lighting

Common Area Operating Energy Costs 743,824

Photo Voltaics

UPS

Commercial

Total Life Cycle Costs (zero inflation) 9,393,722

Detailed operational energy costs have been benchmarked also for the concept project as outlined below.

Category

Estimated LC Operating Energy Costs ($)

Base Design Building Energy Efficient Building

Water Heating

Work Stations

Common

Lighting

BMS

Vertical Transport

On Site Generation

HVAC

Page 11

Page 8: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

kWp 79 15

m2 642 122

kWh / Annum 121,082 121,082

kWh / Annum 121,082 22,978

kWh / Annum - 98,104

$ / Annum 40,562 40,562

$ / Annum 16,638 32,946

$ / Annum 23,924 7,616

$ 181,798 34,500

Years 7.60 4.53

PV System Size

Improved Building

Roof Area

Matched

UnitConsumption

Matched

Solar PV System Size Calculations

Estimated Capital Cost of Solar

Total Savings

Energy Costs With Solar

Energy Costs Without Solar

Net Energy Use

Simple Payback Period

PV Energy Generation

Building Energy Use

Approx. Roof Space Requirement

The current design has a relatively large area of roof space available for PV. However, the high density and hence

high annual operational energy demand mean that achieving net zero operational carbon emissions will be very

challenging. The table below shows what solar PV generation will achieve given the current roof size (minus that

required for HVAC, Hot Water plant and Residential PV). Total roof area will enable 45 kW total capacity divided

into residential 30 kW and commercial 15 kW. To reach a target of zero operational carbon would require over 5.3

times the PV that is currently available to put on the roofspace. The area available for PV may be significantly

increased by utilising frames and pergolas over plant space, balconies and common areas. Including all possible

energy effieincy measures detailed in this study and utilising energy efficient panels would increase the impact of

the PV significantly.

Onsite Generation Potential - Solar PV

Page 12

Page 9: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Carbon Emissions Sensitivity

Base Low High

0.0% -1.0% -5.0%

0.0% -1.0% -5.0%

Sensitivity Analysis of Life Cycle Impact Scoping Study

The above estimated life cycle carbon emissions are calculated using today's carbon intensive energy and material

coefficients. Realistically, the carbon intensity of our distributed energy, construction materials and transport will

diminish over time as we move towards a low carbon economy. The following charts display the potential influence

of carbon intensity on the life cycle impacts of the average building.

The above chart highlights the importance of reducing the initial embodied impacts of the project. Without

accounting for decreases in carbon intensity of energy and materials, initial embodied impacts of a project of this

size are expected to contribute less than 15% of total carbon emissions. However, if current government's policy

commitments to reductions in greenhouse gas emissions are fulfilled and a high rate of CO2 reduction occurs, the

initial embodied carbon may account for nearly 50% of the building's total life cycle emissions.

Key Themes and Opportunities

Assumed Annual Carbon Intensity Adjustment and Inflation Figures:

Annual Reduction in Carbon Intensity

Energy Supply

Materials and Labour

Average Building Carbon Emissions versus Time (tCO2e, 100 years outlook including rebuilds):

16,246

3,442 549

10,425

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

0 20 40 60 80 100 120

Base Case CO2 High CO2 Reductions Low CO2 Reductions

Page 13

Page 10: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Base Low High

0.0% 3.1% 6.0%

0.0% 1.4% 2.8%

Cost Inflation Rates

Energy

Maintenance Materials and Labour

Average Building Cost versus Time ($1,000s, 25 Year Outlook Including rebuilds where applicable);

Key Themes and Opportunities

As inflation of energy continues, the proportion of the building's life cycle costs relating to operations increases

significantly. Within the first 25 years of operation, the operating and maintenance component of the building

increases from 191% to 423% of the initial capital cost. The inflation figures in the high inflation case are perhaps

conservative as they represent actual inflation levels for the past 10 years. With this in mind, attention may be

further focused on increasing energy efficiency of the building.

Cost Sensitivity

All costs quoted thus far in the report are calculated using today's energy, construction, freight and labour rates.

Realistically the cost of energy, goods and services are likely to rise. Energy inflation in particular has in recent

times outstripped the consumer price index significantly, and is predicted to keep doing so. The following charts

display the potential influence of inflation on the life cycle impacts of the base design project.

Assumed Annual Carbon Intensity Adjustment and Inflation Figures:

2,793

3,676

5,015

-

1,000

2,000

3,000

4,000

5,000

6,000

0 5 10 15 20 25 30

Base Case (No Inflation) Low Inflation Scenario High Inflation Scenario

Page 14

Page 11: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Once the project moves forward to the detailed design stage, we recommend that a comprehensive LCA is

conducted on the base case design. This will determine how the design performs against the benchmark, and most

importantly, identify further opportunities for improvement.

With this approach eTool has been able to deliver low carbon and zero carbon projects without compromising

affordability (in many cases improving it in life cycle terms). Having reviewed the early stage concept designs we

are confident that similar outcomes can be achieved thus giving the project an edge within the growing market for

sustainable, energy efficient and affordable dwellings.

Next Steps

Page 15

Page 12: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Author:

Reviewed:

Report Date:

eTool Environmental Impact Scoping Study

248 Newcastle St - Residential

The following notes were documented during a project scoping study and are based on concept designs.

From the concept design information, an estimated life cycle impact assessment was conducted to

understand the likely total comparative environmental impact of the project. The results highlight the

largest environmental impact areas within the concept design to be addressed in the design phase and

enable the design team to focus on areas that will yield the best environmental and cost outcomes

throughout the project life. This enables delivery of sustainable and affordable designs which can be

further improved with a streamlined LCA of detailed designs.

Henrique Mendonca

Pat Hermon

20-Nov-13

Page 1

Page 13: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Goals of LCA Scoping Study

The goal of an LCA scoping study is to understand in broad terms the likely impacts of a particular building or

infrastructure development. Key elements of the concept design are considered, however the majority of the

assessment is conducted using a weighted average combination of materials and energy inputs for like buildings

from the extensive eTool LCA database. A project specific materials take off is not conducted, and similarly,

energy inputs are not accurately calculated but rather derived from like projects. These figures are then adjusted

based on the specific initiatives that are being applied in the concept design that may lead to an improvement (or

otherwise) in the environmental performance of the design. This provides a comparison of likely performance

between the applicable benchmark, a base design, and the actual improved concept design. The purpose of this

excercise is to understand the likely performance of the design before full documentation is complete. This

enables both communciation of this result and identification of potential further improvements. It should be noted

that the results will not be as accurate as a full LCA, an LCA certificate will not be released based on these

calculations, nor will the merits of individual sustainability initiatives be quantified in terms of their environmental or

cost improvements.

Page 2

Page 14: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Disclaimer

The LCA predictions of embodied and operational impacts (including costs) conducted in eTool software, by their

very nature, cannot be exact. It is not possible to track all the impacts associated with a product or service back

through history, let alone do this accurately. The software has been built and tested to enable informed decision

making process when comparing design options. Generic cost and environmental impact coefficients do not

necessarily correspond to those of individual brands of the same product or service due to differences within

industries in the way these products and services are delivered.

eTool Life Cycle Assessments are used predominantly for improving the environmental performance of buildings

and hence always quote carbon emissions as a measure of sustainability. For the purposes of demonstrating the

life cycle cost benefits of energy efficiently buildings, costs are also calculated. This also helps prioritise efficiency

measures when detailed life cycle assessments are undertaken ensuring design teams can achieve the best

environmental and energy efficiency outcomes for the lowest cost. The costs quoted in eTool LCA reports should

never be used for estimating purposes and only serve to compare the costs of two designs analysed with eTool

LCA software.

eTool PTY LTD cannot make assurances regarding the accuracy of these reports for the above reasons.

Page 3

Page 15: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

A comprehensive list of existing design initiatives contributing to this outcome is found on the next page. Further to

this an additional list of design initiatives that can drawn on by the design team to meet the project objectives have

been provided separately. During detailed design, a full LCA will enable prioritisation of sustainability initiatives

based on environmental and life cycle cost improvements.

LCA Scoping Study Report Summary

During concept design development of 248 Newcastle St - Residential, a life cycle environmental impact scoping

study was conducted on the proposed building and compared to the eTool benchmark average new residential

building (consisting of 74% detached/semi detached and 26% apartment). This quantified and categorised the

likely environmental impacts of the project. Environmental impact hot spots are then well understood and become a

focus of the design team to improve the environmental performance of the building. The findings of the study are

documented in this report. In summary the project over its life cycle is expected to achieve the following

environmental and cost outcomes:

The estimated life cycle carbon emissions saved with the measures in place in the concept design are equivalent to

approximately 7 times the savings possible by achieving a 10 star NatHERS rating for all dwellings in the

development.

-7% saving in life cycle GHG emissions against benchmark building

-17% saving in life operating cost against benchmark building

50% saving in GHG emissions against benchmark building

41% saving in operating cost against benchmark building

Base Design

Improved Design

eTool have also modelled some initial improvements that could potentially be applied to the design including PV

(30kW), energy monitoring, CO sensors for carpark ventilation, refrigeration ventilation and solar gas boost hot

water. These measures would provide the following predicted savings.

-2,000

-1,000

-

1,000

2,000

3,000

4,000

5,000

Average New Residential Building Current Base Design Improved Design

Estimated Greenhouse Gase Savings(kgCO2e /occupant/year)

Embodied Impacts Residential Operational Energy

Common Area Operational Energy Renewable Generation

Page 4

Page 16: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

Residential Water HeatingSolar Gas Boost hot water system (approx. 80% emissions saving over electric

resistance heaters).

Category Improved Design Strategies

Residential Miscellaneous

Energy

Residential Entertainment

CO Sensors for car park vent. Naturally ventilate common areas.

Intelligent design to maximise functionality. Increase design life through density.

Improved fridge cabinetry (size and ventilation requirements). Limited fridge

cabinetry size.

Onsite Generation Individual solar systems for each dwelling as purchase option. Assumed total 30 kW.

Common HVAC

Materials

Residential Refrigeration

Energy monitoring to inform and influence occupant behaviour.

Energy monitoring to inform and influence occupant behaviour.

Page 5

Page 17: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

m2

3,528

m2

2,231

# 42.6

Years 115

Estimated Residential Occupancy

Estimated Building Service Life

The life cycle impacts associated with an average new building with the above functionality have been estimated.

The purpose of this process is to effectively inform the design process and ensure the environmental goals of the

project are met without compromising other key project goals. This estimate is inherently limited in accuracy as the

project is still in the early stages of design and many of the subsequent design decisions will influence the

performance of the building significantly. However, it does effectively inform the design team on which building

elements need the most attention.

Below is a summary of the total life cycle impacts of the building which shows the largest environmental impacts

related to Residential Operational Energy. Further detail on the breakdown of these impacts is found in the report.

For the purposes of the LCA scoping study, the development was divided into residential and commercial spaces

and residential portion consists of 3528m2 of total enclosed floor area, 2231m2 residential and the balance car

parking, common areas and outdoor / landscaping space.

Project Summary Notes

Net Total Covered Floor Area To compare projects of different size,

density and functionality, commercial LC

building impacts are measured per m2 per

year, residential LC impacts are measured

per occupant per year

Total Residential Floor Area

Concept Design Summary

599

2,886

489

Life Cycle Impacts(kgCO2e/Occupant/year)

Embodied Impacts

Residential Operational Energy

Common Area Operational Energy

Page 6

Page 18: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

● Increase density to reduce redevelopment potential

● Improve design quality (performance and aesthetics)

● Design for adaptability and future occupants

Project Functionality - Design Life

Building design life is critical for LC performance. Unfortunately the studies indicate that less than 10% of buildings

reach their practical service life. A vast majority of demolitions are motivated by economic or aesthetic reasons with

no regard for the structural integrity of the core building. Changing functional requirements for buildings also drive

some redevelopment. Key strategies to increase building life include:

Project Functionality - Occupancy

58%28%

6%

8%

Typical Reasons for Demolition From Kapambwe, M. et al Dynamics of Carbon Stocks in Timber in Australian Residential Housing, Forest

and Wood Products Australia, 2008

Demolished for Site Redevelopment

Dwelling Ceases to Suit Owners Needs

Other Reasons

Dwelling Becomes Unserviceable

50

100

150

200

250

2.4

2.5

2.6

2.7

2.8

2.9

3

1980 1985 1990 1995 2000 2005 2010 2015 New

Dw

elli

ng F

loor

Are

a (

m2)

Pers

ons P

er

Household

Residential Building Occupancy and SizeFrom Australia Bureau of Statistics

Persons / Household Dwelling Size

Page 7

Page 19: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

The design life of the 248 Newcastle St development is likely to benefit from the mixed use, strata breakdown of

lots. This will decrease redevelopment pressure until it becomes an equivalent low density building compared to

the surroundings. Consideration during the design phase to how the building may evolve in the future will also aid

design life.

Given the likely long design life of the project (115 years), construction materials with long term performance and

low maintenance requirements are encouraged. From a sustainability perspective the carbon intensity of these

materials must however be considered carefully.

For residential buildings, the core function is to provide a home to occupants. Sustainable buildings provide more

occupancy with less materials and energy. Dwelling size and occupancy rates are hence critical considerations for

good LC performance. Both of these factors have been trending poorly in Australia until recently. In 2009 it was

reported that Australia was building the largest average size residential dwellings in the world. The latest ABS data

suggests occupancy per dwelling and dwelling size are now trending in positive directions. This matches trends

from around the world where families are far more likely to occupy medium and high density dwellings. Allowing

more occupants to be housed within smaller floor areas increases the functionality of the building.

Key Themes and Opportunities

Page 8

Page 20: Category Improved Design Strategies - planning.wa.gov.au daps/metro west jdap... · Category Improved Design Strategies ... Roof top solar PV. Total 15 kW assumed. ... project are

246 6.2% 262 14.0%

32 0.8% 32 1.7%

266 6.7% 348 18.6%

42 1.1% 42 2.2%

14 0.3% 15 0.8%

1,127 28.3% 156 8.4%

395 9.9% 355 19.0%

336 8.4% 302 16.2%

255 6.4% 229 12.3%

227 5.7% 145 7.7%

548 13.8% 507 27.1%

251 6.3% 126 6.7%

131 3.3% 118 6.3%

46 1.1% 46 2.4%

61 1.5% 61 3.3%

- 0.0% 874- -46.7%

3,975 100.0% 1,869 100.0%

Onsite Generation Photo Voltaics

Total (kgCO2e / occupant / Year)

Key Themes and Opportunities

The traditional use of electric element hot water systems is a very carbon intensive way of delivering hot water on

the WA electricity grid. A central solar with gas boost hot water system would deliver significant improvements in

the building's carbon emissions. Energy monitoring is also a simple low cost measure that has been proven to

reduce the residential electricity use. Improvement in carpark ventilation and residential refrigeration also has

significant impact in the overall performance. Use of roof space to produce on site electricity is also recommended

to improve environmental and cost performance. These measures have been modelled in the improved building, a

full list of potential strategies is provided below.

Common

HVAC

Lighting

Vertical Transport

Miscellaneous Energy

Operational

Carbon

Emissions

Residential

Water Heating

Entertainment

Cooking & Prep

HVAC

Refrigeration

Miscellaneous Energy

Embodied

Carbon

Materials

Materials Transport

Recurring (Building Maintenance)

Assembly (Building Construction)

Planning and Sales

Life Cycle Carbon Emissions Detail

Category

LC Carbon Emissions (kgCO2e / occupant / year)

Base Design Improved Building

Page 9


Recommended