+ All Categories
Home > Documents > Causes of Contractors failure for ref

Causes of Contractors failure for ref

Date post: 14-Apr-2018
Category:
Upload: andy-phuong
View: 219 times
Download: 0 times
Share this document with a friend

of 31

Transcript
  • 7/30/2019 Causes of Contractors failure for ref

    1/31

    King Fahd University of Petroleum and MineralsDepartment of Construction Engineering and

    Management

    Causes of Contractors Failures In

    Saudi Arabia

    ByAdel Abdulaziz Al - Barrak

    June 1993

    Causes of Contractorss Failures In Saudi Arabia Page 1 of 31

    Submitted to:

    Dr. Sadi Assaf.

    CEM 520.

    Submitted by:

    Tariq M. Al-Wabil.

    January 2004.

  • 7/30/2019 Causes of Contractors failure for ref

    2/31

    INDEX

    Page No.

    Thesis Abstract . 01

    Introduction ... 02

    Causes of Failures. 05

    Description of the Survey 18

    Findings and Results ... 20

    Conclusion and Recommendations 23

    Referees 25

    Appendix 27

    Causes of Contractorss Failures In Saudi Arabia Page 2 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    3/31

    THESIS ABSTRACT

    NAME: ADEL ABDULAZIZ AL-BARRAK

    TITLE: CAUSES OF CONTRACTORS FAILURE IN SAUDI ARABIA

    MAJOR: CONSTRUCTION ENGINEERING AND MANAGEMENT

    This thesis discusses the main causes of failure in the Construction industry in

    Saudi Arabia. A survey of 68 contractors from the entire Kingdom was undertaken.These contractors were classified by the Ministry of Housing and Public Works from

    grade one to four. The distribution of these contractors are as follows: 7 from grade one,

    12 from grade two, 27 from group two, and 22 from group three.

    The survey included 34 different causes of failure and their degree of importance.

    The severity factors of these causes were measured by their level of importance and wereranked according to the severity index for group one together, group two, and group

    three, and a combination of all respondents. A computer statistical package (SAS) was

    used to analyze the data.

    A hypothesis that grade one and two (group one), grade three (group two), and

    grade four (group three) generally agree on the ranking of severity indices was tested

    and shown to hold true. It was concluded that lack of experience in the line of the work,

    neglect, poor estimation practices, bad decisions in regulating companys policy, andnational slump in the economy are the most severe factors. Also, it was noted that grade

    three contractors give the most response, followed by grade four and then grade one andtwo. This reflects the true awareness of causes of failures among contractors.

    Causes of Contractorss Failures In Saudi Arabia Page 3 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    4/31

    Chapter 1

    INTRODUCTION

    1.1 GENERAL

    The construction business has very high risks. These risks, which could

    lead to failure, come from the sensitivity of the business to economic cycles, and

    from high levels of competition. Because there are large numbers of contractors, itis easy, implementation could easily be poor and unorganized, which increases

    the probability of a contractors failure.

    In construction, there are three parties involved, namely, owner,consultant, and contractor. The relationship between these parties is adversarial

    because each party has goals which conflict with the other parties goals. Forexample, the owner wants his project to be of a good quality and low cost, but thiswill reduce the profit of the contractor. The consultant wants the project to be safe

    and attractive which could cause both the contractor and the owner extra

    expenses. Also, the laborers hired by the contractor want their salary to be higher,which is not possible given the competitive prices in the contraction business. The

    relation among parties could be a major source of a contractors failure.

    There is no exact definition of the contractors failure, however, it could

    be defined as when a business:

    1. Ceases operation following assignments due to the inability to continueconstruction;

    2. Goes into bankruptcy due to failure of collecting money from customers;

    3. Voluntarily withdraws because of dissatisfaction with business or profit.

    The construction industry attracts many people because of their belief of

    high profit, but when they enter the business, they will feel the difficulty and

    complexity of it.

    Therefore, there are many contractors, but if the successful and profitable

    contractors are counted, they will be few.

    1.2 PROBLEM BACKGROUND

    During the boom years which were from 1975 to 1983, when the demandof oil increased, Saudi Arabia increased its oil export from 4 million in 1975 to 10

    million barrels in 1983. Consequently, Saudi Arabias income increased from SR

    41,705 million in 1974 to SR 368,001 million in 1983, which was the peak. Theincrease in income resulted in an increase in expenditure in all sectors. The

    government established two banks and three funds to give loans without interest

    Causes of Contractorss Failures In Saudi Arabia Page 4 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    5/31

    to support all types of business. The two banks are Saudi Credit Bank, and Saudi

    Arabia Agricultural Bank. The three funds are Saudi Industrial Fund, Real Estate

    Development Fund, and Public Investment Fund. Because of the availability of

    money, investment was in every sector. The construction industry enjoyed a largeshare in the economic boom. The number of projects offered were so large that

    the number of contractors increased and each contractor could have as manyprojects as he wanted. Although the formation of many of these contracting

    businesses had no solid basis, they were able to do business and make profit.

    After the international recession started in mid 1983, the Saudi market was

    affected. The recession had more influence in the construction industry because of

    a reduction in oil income, which affected the offering of large projects and loans.

    Also, most of the large projects had already been executed. Consequently, thecompetition was much tougher, and standards became higher. As a result of these

    factors, many contractors were exposed and some of them changed their businessand some left the business altogether.

    1.3 OBJECTIVES OF THE STUDY

    The main objectives of this thesis are as follows:

    1. To undertake a comprehensive analysis of the most important factors thatcause business failure among contractors.

    2. To identify and analyze the most severe factors causing contractors

    failure in Saudi Arabia.

    3. To test the hypothesis that different grades of contractors generally agreeon the severity of failure.

    4. To write a conclusion and recommendations.

    1.4 LIMITATION OF THE STUDY

    This study is limited to building and highway contractors who arequalified and registered in the Ministry of Housing and Public Works as of 25 th of

    Muharam, 1413H. The contractors will be from grades one to four in Saudi

    Arabia. The technical failure of projects will not be covered in this study. Thestudy will be restricted to construction phase.

    1.5 THE SIGNIFICANCE OF THE STUDY

    The number of competitors in the construction business is much higher

    than in any other business. As a result, construction business is exposed to failuremore than any other business. Therfore, the construction business should be

    studied to determine the causes of failures. The past period proves that there are

    causes which should be avoided in order to reduce the number of failures.Theconstruction business requires more attention to remedy the weak points. This is

    what the study investigated.

    Causes of Contractorss Failures In Saudi Arabia Page 5 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    6/31

    Causes of Contractorss Failures In Saudi Arabia Page 6 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    7/31

    Chapter 2

    CAUSES OF FAILURES

    2.1 GENERAL

    The causes of construction business failure are varied from a country to

    country and even from city to city, because of economic, social, and competitive

    situations of the area and the government regulations. In addition, the causes mayvary from one type of construction to another, fro example, the cause of highway

    construction is not the same for residential construction.

    2.2 CAUSES OF FAILURES IN QUESTIONNAIRE

    These causes which are included in the questionnaire are divided into fourgroups, namely, managerial, financial, expansion, and environmental

    causes. These causes are as follows:

    2.3.1 MANAGERIAL CAUSES

    The managerial causes include important causes which have strong

    influence in the contractors failures. Lack of experience in the line ofwork, bad decisions, and company organization could be important factors

    in the failures. Some of these causes could be part of others. For example,

    frauds will increase in low experience manage3ment and unorganized

    company. The managerial causes will be as follows:

    1. Lack of Experience in the line of Work

    When contractor is doing the same type of work for many years,

    this experience gives him a competitive edge in the market. The

    management is the key for the success of the company. The owner shouldemploy high degree of qualified working team in the company. The

    working team also must have good experience in the same line of work.

    Therefore, the management would be able to maximize the usage of thecompanys resources. Not only working team has experience, but also the

    owner should have experience in the line of work for two reasons. First,the owner would not be cheated from any one inside or outside the

    company. Secondly, if the owner does not have experience, he may notappreciate any improvement or any new ideas which could bring good

    income in the future. Most of the decisions which cause contractors

    failures are taken by the management.

    2. Replace Key Personnel

    The three main functional areas of construction business are

    getting the work doing the work and managing the business. The

    Causes of Contractorss Failures In Saudi Arabia Page 7 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    8/31

    responsibility of each functional area differs from one company to

    another. One person could be responsible for all functional areas or two

    people share the responsibilities. If the construction business is making a

    profit, the efforts of individuals who are responsible for functional areaswill be the key for success. Loosing one of these key persons will put the

    company immediately at risk until his replacement proves that he can runthe work for a profit.

    There are many things that could happen to the company becauseof loosing any key person. If they company looses construction operation

    manager, it will change because the quality of work of the field manger

    depends on him. Sometimes, the company may make a profit because of

    this experience in planning the work, delegation of authority, dealing withcustomers, and managing the labor force. If a company looses an

    estimating and sales manager, it will be at risk, this is because of hisexperience in preparing bids and attracting customers that eventually makeprofit for the company. This situation will be the same in the area of

    administration and accounting.

    In order to put the company in the safe side, there must be two

    relief persons for each key person. Also, a contractor must keep minutes of

    all meetings, confirm things in writing and keep all documents related tothe business. This information will help the new replacement in the future

    work. In the end, the most common cause of construction business failure

    is inadequate replacement of personnel responsible for one of the primary

    functional areas.

    3. Assigning Project Leader in the Site

    The size of construction company determines the project leader.

    The project leader could be a project manager, project engineer, resident

    engineer or a site engineer. Project leader should be qualified for the jobbecause he is the vehicle for reaching project goals.

    The leader should be an inspiring leader, for example, who

    encourages, appreciative, wants loyalty and is fair. The company mustassign the right man in the right place to assure that project will succeed.

    4. Labor Productivity and Improvement

    Productivity can be defined as the rate of production or the amount

    of goods and services that are produced by productive factor in a unit oftime. Since, there is a direct relation between productivity and cost,

    productivity is not only very important term to a contractor but also it is

    the key to success or failure. Most contractors complain from slowproductivity but non of them determine the reasons and create the

    solutions. There are many tools that can be used in productivity, for

    Causes of Contractorss Failures In Saudi Arabia Page 8 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    9/31

    example, work sampling, questionnaires and interviews, five-minute

    rating, and foreman dely survey. Also, there are tools for improving

    productivity, such as quality circle, crew balance chart, and recording.

    These methods can identify the problem and introduce the solution toimprove productivity.

    Therefore, a contractor should improve his labor moral by using

    the most applicable program because people might be motivated by

    money, or social needs, or positions. There are many elements to beconsidered in designing motivating programs. The program should be

    cover as much labor as possible. The financial compensation has to be

    guaranteed in hourly wages or bonus proportional to salary. The program

    must be strongly related to performance measures which is specific anddone periodically. A low productivity can be a fatal cause of contractors

    failure.

    5. Bad Decisions in Regulating Company Policy

    Most contractors believe that the only reasons for failure are laborproblem, inflation, high costs of equipment, and tightening of market.

    Although there are contractors who are exposed to the same factors but

    they are making profits. They do not know that they may contribute tofailure due to bad management decisions. These management decisions

    might not cause failure directly but they lead to failure.

    Decisions in regulating the company policy should not be takenunless all significant factors involved not only be considered but also

    handled in an accurate and correct manner. So that the results will be

    satisfactory from all view points. Contractor could avoid this factor byhiring consulting office or full time consultant. Consulting office or

    consultant should be chosen according to the previous experience with the

    work qualifications and capabilities.

    6. Use of Project Management Techniques

    Project management is the integral of all of the construction projectfunctions which include coordination of subcontractors, scheduling, cost

    control, labor relation, billing, purchasing, expending, and other functions

    related to the project. In construction company, project manager is incharge of these functions.

    The use of project management techniques is very important in theconstruction industry, because the coordination and use of the many types

    of labor, skills, materials, and equipments which are used in construction,

    require daily application of proper project management techniques.

    Causes of Contractorss Failures In Saudi Arabia Page 9 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    10/31

    7. Company Organization

    The organization of company is very important to do the workefficiently. The organizational structure depends on two factors. The first

    is the type of contractor and second is the size of company. However, themain structure is common between all contractors. The more common

    classification of contractors is according to he type of work performed. So,

    the type of contractors are residential, commercial, and highway. Theperforming of organizing function requires a preparation of organizational

    chart which determines he grouping of activities, the authority

    relationships, and the communication channels between groupings. There

    are two types of charts, namely, chain and circular. The decision makingin the chain is centralized by an individual or small groups of individuals,

    where in the circular structure emphasized decentralization. Thecommunication in the chain structure is faster and more accurate that thechain structure.

    Also, the responsibility and authority for each party in theorganization chart must be clearly recognized. The lack of assigning the

    responsibility and authority for each party will delay the work, because of

    the conflict between these parties. So, if the company is well organized,the contractor can manage the construction without problems. This will

    reduce the chances of failure.

    8. Procurement practices

    Construction materials can be purchased by two procedures, either

    purchasing directly, or purchasing for entire lump sum contract. However,purchasing materials before due time is very important in the construction,

    because the delay in purchasing will delay the completion date, and

    interrupt the schedule. Consequently, the contractor will be exposed topenalty which might sometimes cause contractor to fail. The latest

    information about new products should be provided to users to give him

    opportunity to choose the best. Purchasing is responsible to update

    equipment cost used in calculating the replacement costs.

    In the open country like Saudi Arabia, purchasing material with

    good quality and reasonable price is not an easy task. It is because thereare variety of trade marks for each item. For single item, price can be

    triple, In each construction company, it is recommended to have material

    specialist who can read specifications and decide the reasonable materialsrequired for the company.

    Causes of Contractorss Failures In Saudi Arabia Page 10 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    11/31

    9. Claims

    Contractors need to recognize the risks of disputes and try to

    minimize them for two reasons. First, the costs associated with them,secondly the contractors name in the market will be destroyed. The

    contractor should quit the claim, even though he missed some of his rights,because the owner will complete his building and will disappear from the

    market, but the contractor will stay.

    Construction industry will be exposed to many claims, if there are

    no planning, controlling and directing, because construction has many

    involved parties (owner, consult office and government), things must be

    done in the same time and too many materials are required in construction.Claims can cause the contractors completely running out of work.

    10. Internal Company Problems

    Most employees of contractors in Saudi Arabia are multinational.

    Each employee will have more loyalty to his nationality and will notprefer to work with another nationality which could cause problem in

    preparing schedule. Also, the problems between partners will have bad

    effect in the company because many employees will use this problem totheir benefit. Also, this problem will resist any improvement. The

    importance of strong management will reduce the internal company

    problems, which could cause failure if it is not controlled and treated

    carefully.

    11. Recruitment from one Country

    In Saudi Arabia, almost all construction contractors depend on the

    foreigners. There are contractors who depend on certain nationality which

    could cause failure in many cases. Workers from one country can buildstrong interrelation which causes problem to contractors.

    On the other hand there are many advantages in controlling certain

    nationalities. Workers will understand each other because they speak onelanguage, however, in some countries, there are many languages which

    make communication difficult. Contractors will have less friction between

    employees from one country compared with contractors who havemultinationality labor.

    12. Recruiting Murtinationality

    Most contractors prefer to recruit multinationals without

    understanding the problems behind this decision. Even though, recruitingfro more than one country can create competition between employees,

    there are problems that can be encountered. The most difficult problem are

    Causes of Contractorss Failures In Saudi Arabia Page 11 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    12/31

    wages. Each country has its own economic standing which affects the

    wages of that country.

    Recruiting multinationality in one company may create friction

    which sometimes have negative effects in the work. This problem will bemore complicated when governments have political problems with each

    other, for example, India and Pakistan. Contractors who recruitmultinationality will have problems in the communication between these

    nationalities.

    13. Owners Absence from the Company

    No one can take the place of the owner in the company. Even a full

    time manager can not manage like the owner, even if he has fullconfidence. The absence of the owner usually results in a poor supervision

    in the company, especially if the employees get their salaries regardless ofprofit of the company. This problem could be reduced by giving bothmanager and employees specific percentage of the profit.

    14. Using computer Applications

    Computers have many applications in the construction industry.

    Their applications are for cost estimation, planning and scheduling,accounting, and calculations.

    All these applications can help the contractor to do the work easily,

    quickly and accurately. The accurate date produced by the computer canbe and asset for making decisions. Computer shops can provide any

    construction company with special design package to be used for its own

    purpose. Also, there are packages in the market which are very importantin managing projects.

    15. Frauds

    Frauds can be seen easily in the company which does not use the

    business practices. When the company is not planned, organized, directed,

    and controlled, the chance of fraud will be higher. Frauds can happen fromvarious departments. In order to avoid these things the contractor should

    use the theory which stated the responsibility is equal the accountability.

    The accountability must be tough to warn employees. The authorityshould not be given to any employees unless he passed the testing period.

    As high authority is given to employee, as long the testing period. The

    management must limit the number of people who have the companyssecrets. Frauds exist in the company. A thought among the customers that

    this company is not doing the work perfectly, could cause the contractor to

    run out of the business.

    Causes of Contractorss Failures In Saudi Arabia Page 12 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    13/31

    16. Neglect

    Neglecting is another cause of failure. When the management does

    not respond to problems and suggestions, this negligence may add to coststo the company. Sometimes, employees suggest things which could help to

    improve their productivity, but the management neglects these things. Theneglect in solving the internal problem which is from employees or

    external which is from customers, will complicate these problems and will

    not be easy to solve later.

    2.3.2 FINANCIAL CAUSES

    The financial stand of the contractor is very important for runningthe business. Contractors might run the business with his own money.

    Also, work improvement sometimes needs money because improvementneeds buying new equipment or developing new techniques. All theimportant managerial causes could not keep the contractor save without

    good financial stand. The financial causes are as follows:

    1. Low Margin Profit due to Competition.

    The profit has relation with risk and uncertainty. As the riskincreases in the business, the higher potential profit is Contractors bidding

    on a single project will have different estimate of project cost because of

    the differences in structure of cost information, construction method and

    take-off procedures used by each contractor. However, the profit, whichcontractor adds to his bid, determines whether he will win the contract or

    not.

    The number of contractors would be expected to be high because

    of the simplicity of establishing new construction firm. Also, as the

    number of contractors increase, the margin of profit decreases.

    If the contractor is more specialized, the less his competition will

    be and the higher profit margin could be added. If the contractor adds a

    high profit margin, he might not win any project contract and run out ofwork. So contractor need to add very small profit margin which sometimes

    causes contractors failure. When a contractor estimates a profit to be

    added to a bid, he is faced with conflict constraints. If the contractor addsa high profit he may loose the work and if he adds a low profit it may

    cause failure. This reason is the most important factor of contractors

    failure, which is low profit margin due to excessive competition.

    2. Cash Flow Management

    Most of the contractors expenses are paid in cash. Therefore,

    availability of cash flow is very important for a contractor to run the

    Causes of Contractorss Failures In Saudi Arabia Page 13 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    14/31

    business. A contractor could find few shops which would give him credit.

    However, there are two problems associated with purchasing in credit,

    prices would not be cheap as compared to cash payment and a contractor

    is limited to items which are available in the shop which gives him credit.

    A contractor should plan for cash flow, or one day he will not havemoney to pay his expenses, and also there is no progress payment ready

    for collecting. The plan for cash flow needs cooperation between all

    companys divisions. Consequently, the cash flow will high priority in themanagement. Also, the meeting could help to solve all problems related to

    delay in progress payment. If the contractor is able to manage his cash

    flow effectively, his business will run smoothly.

    3. Bill and Collecting Effectively

    Billing and collecting effectively are the ways to get cash flow.Contract documents must state he procedures for billing and collecting

    money clearly from the customers. It is important to send the bill to

    customer on time. Adding charges to late submission of payment willencourage customers to pay on time.

    4. Poor Estimation Practices

    Cost estimation of the job for a competitive bid is not an easy task.

    The cost of labor, construction equipment, material, subcontracts, taxes

    overhead, and surety bond are calculated and combined with markup toarrive at the final bid amount This will determine whether a contractor

    gets the job or not.

    The source of the unit costs is the previous projects which were

    done before. Also, there are construction cost indexes for forecasting

    probable construction costs.

    In addition, cost estimation guides are available for the estimator.

    All these methods help the estimator for preparing the costs because the

    accuracy and bidding with reasonable price are the key for successfulbusiness.

    5. Evaluate Project Profit in one Fiscal Year

    In construction, it is extremely difficult, in one fiscal year to know

    whether or not each project is making a profit or a loss before the projectis completed. This difficulty comes from a variety of things associated

    with construction. Even though, the contractor could prepare a financial

    statement, there is no way to check or verify the accuracy of basic datawhich is prepared by contractors staff. The accountant will depend on his

    calculations in preparing the basic data for preparing the financial

    Causes of Contractorss Failures In Saudi Arabia Page 14 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    15/31

    statement without checking the accuracy because projects are far out in the

    field and materials stored and in transit are almost impossible to do

    inventory. Being able to develop contract profitability report for projects

    every month will reduce the risk of failure.

    6. Employee Benefits and Compensations

    For any business, employees should be given bonuses to improve

    their motivation toward the company. However, in Saudi Arabia, bonusesare not quite common. It is applied in large construction companies, but

    medium or small construction companies do not give bonuses. These

    bonuses should be given to the employees as part of a careful considered

    compensation plan. This must be understood and known by all of theparticipants. Bonuses have to be very effective and fair. Bonuses will

    cause more problems in the company if they are random and unorganized.Bonuses must be connected to employees performance and companysprofit.

    One common mistake in may contractors is to delay the employeesbenefits for more one month, six months or even more, this mistake could

    decrease productivity of employees. If a contractor does not pay his

    employees salaries, he will have more cash flow which he may spend fornon important things. Employees benefits will increase month by month

    until they become too much to pay. Contractor must pay his employees on

    monthly basis to avoid all problems.

    7. Controlling Equipment Cost and Usage

    Equipments are very important to contractors. They could savetime and money. There are two reasons to buy them either to replace old

    or to save money by owning equipments.

    Equipment costs which included maintenance, operation and

    replacement must be estimated well. Contractor may loose because of not

    recognizing, recording and planning for all equipment cost. In calculating

    the replacement cost, it is important to update the recent cost of theequipment. Contractor should include the cost of idle equipment in

    estimating job profitability.

    Contractor who has very expensive equipment must have very

    effective program to calculate equipment cost or he may be loosing

    money. The equipment repair cost must be accounted for from the firstmonth it is put into the service.

    Causes of Contractorss Failures In Saudi Arabia Page 15 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    16/31

    2.3.3 EXPANSION CAUSES

    The expansion is the normal growth in any business. If the

    company doesnt develop, the companies which are the same size willdevelop and become stronger than the solid company. However, the

    expansion should be done under very good researching, planning,controlling. The size of expansion should be reasonable for the business to

    avoid failure. The expansion should be done with the company long term

    planning. A lack of the work is most reason for expansion, but it needsvery careful planning. The expansion causes are defined as under:

    1. Expanding into New Geographic Locations.

    The change from geographic are in which a contractor is usually

    biding, achieving productive work and making a profit, can cause failure.The distance varies from one contractor to another.

    There are may reasons for a contractor to expand into new

    geographic areas, for example, lack of work in local area, normal growth,and opportunity to follow customers or designers. It could be done but the

    contractor must recognize and plan for the risks.

    2. Opening a Regional Office

    Opening a regional office is a new business which can do exactly

    the same function of the office, although it is a part of the company. Thetalent required at the regional office is the same when the construction

    business started with. The distance is not a great factor in locating a

    regional office as it is in expanding in a new geographic are because theregional office will depend on the market-place rather than the target

    opportunity. So the best way for a contractor, who want to expand into a

    new geographic area, is to open a regional office. However, theconstruction must plan for his regional office carefully. The reason for

    opening regional office are the same reasons for expanding into a new

    geographic area.

    When a contractor decides to open a regional office, he must have

    a plan for the office and as part of the plan is a withdrawal plan. It should

    determine in advance of how long the contractor will continue the effort ifit does no succeed, because making a profit in the first or second year is

    very difficult. If the losses exceed the planned amount, the plan should be

    reviewed. The contractor will decide to carry additional losses andcontinue or to withdraw immediately.

    Causes of Contractorss Failures In Saudi Arabia Page 16 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    17/31

    3. Increased Number of Projects

    A contractor must know his ability and the maximum volume for

    each year. The real planning for the work will determine a contractorsability and his maximum volume yearly, so each contractor must have

    maximum number of projects. There are many factors which could beconsidered in determining the maximum number of projects.

    4. Increased Size of Projects

    The most common factor of failure is the dramatic increase in the

    size of project, if the contractor is not aware of the safe ways to grow and

    expand. There is no formula and very few rules for determining the limitsof expansion. For example, if a contractors largest project is SR 1 million

    road projects or buildings, he can construct SR 2.5 million road projects orbuildings. However, the contractor will not be able to make a profit from ajob four times greater than largest ever built, unless there are additional

    resources and a huge amount of careful planning.

    5. Change in the Type of Work

    A contractor sometimes shift from one type of construction toanother or add a new type to the current work. Contractors rarely stop

    current field and start new field. However, expanding into new types of

    construction is quite common. Construction companies may add, The

    contractor should recognize the impotence of researching and planningbefore taking a new type of construction. The entrance cost which is the

    money paid for learning period during which a contractor needs to learn a

    new type of work, is always under estimated. A contractor may completeone or two losing projects before he can build a new type of construction

    profitably.

    A contractor must determine what type of work he can do best andeven in which part of work he can do better, then, he can move forward in

    the type of work with more confidence and less risks. If he wants to

    expand into other types of work, he should evaluate all the risks first, take

    a small project, and proceed with another. Expanding into a new type ofwork can cause contractors failure if he does not know his specialty.

    6. Lack of managerial Maturity

    Managerial maturity means that contractors managerial abilities

    must mature or develop as his business does. So the contractor shouldaccept the change in the management as the company grows during

    successful times to assume continuous success. There are many companies

    which start, continue, and become large and so many more fail. The onlyreal difference between the continued successful construction business and

    the early and mid time failures is the management (Schleifer, 1990). The

    Causes of Contractorss Failures In Saudi Arabia Page 17 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    18/31

    lack of managerial maturity in expanding organization can contribute to

    contractors failure.

    7. Changes from Private to Public or Vice Versa

    Changing from private to public or vice versa will exposecontractors to very high risks if the are not aware of all differences. In

    public work, a contractor should hunt every opportunity for change orders,

    or he might not make a profit. In private work, a contractor should add areasonable fee and profit into his bid to allow for minor changes and

    preserve a good relationship with the owner. Changing between private

    and public sector could be done, but it needs very careful preparing,

    planning, and estimating.

    2.3.4 ENVIRONMENTAL CAUSES

    The environmental causes affecting the local area will be included

    in this part. The environmental causes are national slump in the economy,construction industry regulation in Saudi Arabia, owner involvement in

    construction phase, and bad weather. The environmental causes are

    defined as follows:

    1. National Slump in the Economy

    Money runs in circle and the government is part of the circle. If thegovernment does not have money, they will not offer new projects and

    contractors will run out of work. Usually, government projects are large

    and require following specifications, so it costs a lot of money. This factoris very important because if the economy of the country is good, there will

    be more development which increases the chances for contractors to get

    work.

    2. construction Industry Regulation in Saudi Arabia

    The entrance to construction industry is very simple in SaudiArabia. The contractor needs to apply to the Ministry of Commerce with

    required documents. These documents are as follows: A bank certification

    which shows that the contractor has SR 150,000 or more, it depends on itsspecialty, and documents to prove that a contractor has office, storage and

    car. It is seen that the regulation does not have anything about the owner.

    The only regulation is that he is not government employee. There is nolimited education or good past experience. Consequently, may unqualified

    contractors would enter the business and increase the failure. If the

    contractor is not and engineer or doesnt have enough experience inconstruction, the government must force the contractor to have one civil

    engineer to handle the engineering work.

    Causes of Contractorss Failures In Saudi Arabia Page 18 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    19/31

    3. Owner Involvement in construction Phase

    In any construction project, the three main goals are; low cost, high

    quality, and rapid completion. It is the owners responsibilities todetermine these goals and to set their priorities for project completion. If

    the owners key roles were prepared accurately and quickly, this will helpthe contractor to do work smoothly.

    4. Bad Weather

    The Eastern Province of Saudi Arabia has weather conditions with

    temperature as high as 50C, thus the contractors must contend withextreme high temperature.

    Consequently, the contractor must expect reduction in theproductivity, which should be considered in bid estimation, during the

    summer session. In order to improve productivity, the contractor should

    adjust working hours, plan most of the work in shade or indoor if it ispossible, hurry work on enclosures of the building, provide shade, and

    schedule people to breaks. Being able to maximize the productivity will

    reduce the cost and reduce the chances of failure.

    Causes of Contractorss Failures In Saudi Arabia Page 19 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    20/31

    Chapter 3

    DESCRIPTION OF THE SURVEY

    This chapter includes the research methodology and sampling techniques used tomeasure the severity indices of the major causes of failures.

    3.1 QUESTIONNAIRE DESIGN

    This investigation was undertaken in two stages. The first stage was the

    collection of date. This stage included reviewing related literatures, and gathering

    data through site visits, interviews, and discussions with different grade of

    contractors. The second stage focused on data analysis and identification of themost relevant factors influencing causes of contractor failures. This led to the

    formation of the questionnaire (see appendix A) which was distributed tocontractors.

    3.2 STATISTICAL SAMPLING

    A. Sample Size

    In this study, the contractors who had qualified and registered in theMinistry of Housing and public Works this year 1413H will have had the chance

    to participate. The ministry of Public Works classified contractors to fields and

    activities as shown in Table of Classification.

    In this study, the population of the contracting firm has been divided into three strata:

    1. Grade one and two (Group 1)2. Grade Three (Group 2)

    3. Grade four (Group 3)

    Table 3.4 Sample Size Information

    h Strata

    Strata

    PopulationN (h)

    Sample

    Size

    Percent of

    Sample toPopulation Size

    Prop.

    Sample

    1

    2

    3

    Group One

    Group Two

    Group Three

    85

    160

    207

    19

    27

    22

    22%

    17%

    11%

    27.9%

    39.7%

    32.4%

    452 68 15% 100%

    Causes of Contractorss Failures In Saudi Arabia Page 20 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    21/31

    B. Scoring

    For questions from one to six, no scoring was used since these consist of

    general information related to the respondent companies. For the seventhquestion, the importance of the causes of contractors failures are considered.

    Thus, these causes are organized according to their priority.

    The options given for each question are on a four-point scale. Each factor has a

    severity index and the severity index is controlled by equation:

    Severity Index (Is) = 4 i=1 ax

    Where:

    i= 1,2,3,4

    The equation contains the constant a. This constant attempts to determine

    quantitative measures as an indicator of comparable responses. This simply means that

    the respondent keeps in mind a four-point scale while answering.

    The scale value assigned to each response is as follows:

    A. a1 = 0/3 for Not influenceB. a2 = 1/3 for Slightly influence

    C. a3 = 2/3 for Influence

    D. a4 = 3/3 for Very influence

    x= the variable expressing the frequency of the i-th response, for i= 1,2,3,4, and

    illustrated as follows:

    x1 = the frequency of very influence response,

    x2 = the frequency of influence response,

    x3 = the frequency of slightly influence response,

    x4 = the frequency of not influence response.

    Causes of Contractorss Failures In Saudi Arabia Page 21 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    22/31

    Specialty

    Experience

    Volume of Business

    Number of Workers

    Mean Standard

    Deviation Standard

    Error of Mean

    Confidence Interval

    Coefficient of Variation

    Spearman Partial

    Multiple

    Standard (S)

    Grade One & Two

    Contractors

    Grade ThreeContractors.

    Grade Four ContractorsFigure: Statistical Methods

    Chapter 4

    FINDINGS AND RESULTS

    This chapter presents the survey data and discusses the results obtained from these data.

    4.1 STATISTICAL METHODS

    4.1.1 The following statistical methods were used in this report:

    1. Tabulation, and Cross Tabulation.

    2. Statistical techniques.

    3. Correlation4. Ranking

    Figure Shows these statistical methods.

    4.2 MAJOR FINDINGS

    The major causes of contractor failures are divided into four major areas

    as discussed in chapter 2. The discussion of this section follows the organizationused in chapter 2 with focus on the results. The average of each area was

    calculated, then the percentage of each area was calculated. The percentage of

    each area is 27.78% for managerial, 27.27% for finance, 23.70% forenvironmental, and 21.70% for expansion causes of failure. These percentages are

    shown in Figure below:

    Causes of Contractorss Failures In Saudi Arabia Page 22 of 31

    STATISTICAL

    METHODS

    CROSSTABULATION

    STATISTICALTECHNIQUES

    CORRELATION RANKING

  • 7/30/2019 Causes of Contractors failure for ref

    23/31

    FIGURE: THE PERCENTAGE OF EACH TYPE OF CAUSES

    The percentage of the managerial and finance causes are almost equal and

    the highest, but the expansion causes make the least contribution to the failures.

    The most important causes as follows:

    1. Lack of Experience in the Line of Work

    2. Neglect

    3. Poor Estimating Practices

    4. Bad Decisions in Regulating Company Policy

    5. National Slump in the Economy

    6. Labor Productivity and Improvement

    7. Owner Absent from the Company.

    8. Collecting and Managing Cash Flow.

    9. Lack of Managerial Maturity

    10. Replacement of Key Personnel

    11. Assigning Project Leader in the Site

    12. low margin of Profit Due to Competition.

    13. Construction Industry Regulations in Saudi Arabia.

    14. Other Causes Specified and Comments

    Causes of Contractorss Failures In Saudi Arabia Page 23 of 31

    FINANCE CAUSES 27.27

    EXPANSION CAUSES 21.7

    MANAGERIAL CAUSES 27.78

    ENVIRONMENTAL CAUSES 23.7

  • 7/30/2019 Causes of Contractors failure for ref

    24/31

    The causes which are specified by the respondents are listed below:

    Lack of relationship between the management and labor force, tendency to

    recruit low payment, recruitment procedures and options, good name in the market,project follow up, and low company capital.

    The comments which are specified by the respondents are listed below:

    1. When the project cost estimation is more than the owners budge, theowner will give the lowest price, even though the owner knows that the

    price will cause the contractor to fail.

    2. comparison should be conducted among companies active in the same

    territory and similar fields.3. Proper planning for the future even though there is loss at the beginning is

    the key for the companys success.4. Allowing the business contractors who are not qualified managerially andtechnically to enter caused failure because of their low prices and

    consequent low quality.

    Causes of Contractorss Failures In Saudi Arabia Page 24 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    25/31

    Chapter 5

    CONCLUSION AND RECOMMENDATIONS

    5.1 CONCLUSIONS

    Based on the above information, the following conclusions can be drawn:

    1. Insufficient experience in the line of work is the main important

    cause of failure.

    2. Poor estimation practices are a major source of failure.

    3. One of the major causes of failure is that there is no restriction onthose entering the construction market; anyone could become acontractor.

    4. The economic impact and shortage of money in past years haveresulted in an increased number of failures.

    5. Delays in payment are the main cause of failures because theyresult in a financial problem to the contractor.

    6. The study shows that the three parties (group one, group two, and

    group three) generally agree in the rank of failure. The grade threecontractors are considered to be the party most influencing failure

    while grade four is the second. As a result, these two parties have

    the highest agreement.

    7. Labor productivity and improvement is another cause of failure.

    8. Bad decisions in regulating company policy is a source of failure.

    9. Neglect is an important cause of failure. Neglect may add extra

    cost to the project which could cause a failure.

    10. Lack of managerial maturity as the company grows could cause afailure. This cause is more influential in grade three and grade four

    contractors because they manage small companies and are lookingto become bigger.

    Causes of Contractorss Failures In Saudi Arabia Page 25 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    26/31

    5.2 RECOMMENDATIONS

    5.2.1 General Recommendations.

    1. It is recommended that a set of procedure be established to

    restrict the construction industry.

    2. contractors should improve the practices for calculating the

    project cost.

    3. It is recommended that the number of payments increase to

    reduce the amount of each. Also, the contractor shouldinclude extra charges for late payments.

    4. In each company, there should be two committees. The firscommittee would be for determining company policy and

    making the major decisions which are related to the

    companys organization. The second committee would be

    for managing the cash flow in the company.

    5. It is recommended that each contractor establish a program

    for motivating workers.

    6. Contractor development should be done with a long term

    planning.

    5.2.2 Recommendation for Future Research

    The results of this research suggest the following areaswhich could be studied in future research:

    1. The effect of the owner of a project on the failure of Saudicontractors.

    2. The effect of government regulations on the constructionindustry.

    3. Construction company organization structures and theirpolicies.

    4. Government policies that can be initiated in Saudi Arabia

    to help contractors stay in the business.

    5. The effect of the owner of a company on the failure.

    Causes of Contractorss Failures In Saudi Arabia Page 26 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    27/31

    REFERENCES

    1. Adrian, J. J., Business Practices for construction Management, Elsevir,

    New York, 1976.

    2. Adrian, J.J., Construction Estimation, Prentice-Hall, New Jersey, 1982.

    3. Al-Khaldi, A., The Labor Problems and Past Mistakes are Still Existing,

    Al-Yaw Newspaper, April 26, 1993.

    4. Al-Msaid, A., The Effect of Owners Involvement on Projects Quality,

    Thesis Proposal, Dhahran, May 31, 1989.

    5. Al-Turkistani, A. Q., Causes of Business Failure Among Saudi

    Contractors, Senior Thesis II, Dhahran, April 30, 1990.

    6. American Society of Civil Engineers (ASCE) Manual, Quality in the

    Constructed Projects, Vol. 1, New Your, 1998.

    7. Argenti, John, Corporate Collapse, The Causes and Symptoms, McGraw-

    Hill Book Company, U.K., 1976.

    8. Avots, I., Why does Project Management Fail? California Management

    Review, Vol. XII, 1969, pp. 77-82.

    9. Baker, B.N., Murphy, D.C., and Fisher, D. Factors Affecting ProjectSuccess. Project Manag. Handbook, 2nd Edition, New York, 1988, pp.

    902-919.

    10. Beckman, R. Tall Building & Urban Design consideration for Arid

    Regions, Proceedings of a Seminar, UPM Press, Dhahran, Saudi Arabia,

    pp. 263-279, November, 1984.

    11. Berenson, M.I., Levine, D.M., Statistics for Business and Economics,

    Second Edition, Prentice-Hall, Englewood Cliffs, New Jersey, 1993.

    12. Cori, K.A., The Project Team: Vehicle for Reaching the Project Goals,Project management Institute, October 1987, pp. 167-172.

    13. Clough, R.H., Construction Project Management, John Willey & Sons,

    New York, 1972.

    14. Drewin, F., Construction Productivity, Elsevier, New York, 1982.

    15. Emory, C., Business Research Methods, 3rd edition, Richard D, Irwin, Inc.,Homewood, Illinois, 1985.

    Causes of Contractorss Failures In Saudi Arabia Page 27 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    28/31

    16. Kungari, R., Business Failure in Construction Industry, Journal of

    Construction and Engineering Management, VII4, No. 2, 1988.

    17. Ministry of Municipalities and Rural Affairs, Annual Report, Riyadh 1410A.H.

    18. Oglesby, C., Parker, H., Howell, G., Productivity Improvement in

    Construction, McGraw-Hill, 1989.

    19. Pinto, J.k., and Slevin, D.P., Critical Factors in Success Project

    Implementation, IEEE Trans. Eng. Manag. Vol. EM-34, 1987. pp. 22-27.

    20. Pinto, J.K., and Mantel, S.L., Mantel, Jr. The Causes of Project Failure,IEEE Trans. Eng. Manag. Vol. 37, No.4, November 1990.

    21. Schleifer, T.C., Why Some Contractors Succeed and Some do not,Concrete Const. June, 1989.

    22. Schleifer, T.C., Construction Contractors Survival Guide, John Willey &Sons, New York, 1990.

    23. Saudi Arabian Monetary Agency, Statistical Summary, Riyadh, 1403 A.H.

    24. Saudi Arabian Monetary Agency, Annual Report, Riyadh, 1397 A.H.

    25. Thorndike, G.L., Burnhart, C.L., Advanced Dictionary, Scott, Foresmenand Company, Glenview, 1979.

    26. Walpoke, R., Myers, E., Probaility and Statistics for Engineers andScientists, 2nd Edition, Macmillan Publishing Co., Inc., New York, 1972.

    Causes of Contractorss Failures In Saudi Arabia Page 28 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    29/31

    APPENDIX

    Causes of Contractorss Failures In Saudi Arabia Page 29 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    30/31Causes of Contractorss Failures In Saudi Arabia Page 30 of 31

  • 7/30/2019 Causes of Contractors failure for ref

    31/31


Recommended