+ All Categories

CB2 MFC

Date post: 03-Jun-2018
Category:
Upload: aamirx64
View: 220 times
Download: 0 times
Share this document with a friend

of 15

Transcript
  • 8/11/2019 CB2 MFC

    1/15

  • 8/11/2019 CB2 MFC

    2/15

    Structures and civil works Project charts and layouts Project implementation schedule Need for considering alternatives1.MANUFACTURING PROCESS/TECHNOLOGY

    A. Choice of TechnologyThe choice of technology is influenced by avariety of considerations:

    Plant capacity Principal inputs Investment outlay and production cost Use by other units Product mix Latest developments Ease of absorption

  • 8/11/2019 CB2 MFC

    3/15

    B. Appropriateness of TechnologyAppropriate technology refers to those methods ofproduction which are suitable to local economic,social, and cultural conditions. Technologyshould be evaluated in terms of the followingquestions: Whether the technology utilizes local raw materials? Whether the technology utilises local man power?

    Whether the goods and services produced cater to thebasic needs? Whether the technology protects ecological balance? Whether the technology is harmonious with social and

    cultural conditions?

  • 8/11/2019 CB2 MFC

    4/15

    4

    2. Material Inputs and Utilities

    Technical analysis is concerned with defining the materialsand utilities required. Those concerned with location,technology and equipments.

    Material inputs and utilities maybe classified into four broadcategories; (i) raw materials (ii) Processed industrialmaterials and components (iii) auxiliary materials and factorysupplies, and (iv) utilities

    a). Raw Materialsb). Processed Industrial Materials and Componentsc). Auxiliary Materials and Factory Supplies

    A manufacturing project requires various auxiliarymaterial and factory supplies like chemicals, additives,Packaging materials, paint, varnishes,

  • 8/11/2019 CB2 MFC

    5/15

    5

    Oils, grease, cleaning materials, etc. The requirement ofsuch auxiliary material and supplies should be taken intoaccount in the feasibility study.d). Utilities (Power, water, steam, fuel, etc)A broad assessment of utilities (power, water, steam, fuel,etc) may be made at the time of the input study Thefollowing question should be raised while conducting theinputs study. What quantities are required? What are thesources of supply? What would be the potentialavailability? What are the likely shortages/ bottlenecks?

    What measures may be taken to augment supplies?3. PRODUCT MIXVariations in size and quality are aimed at satisfying abroad range of customers.

  • 8/11/2019 CB2 MFC

    6/15

    6

    4. PLANT CAPACITY (also referred to as productioncapacity) refers to the volume or number of units thatcan be manufactured during a given period. Technological requirement : Based upon industry;

    there is some minimum capacity of the Plant. Input Constraints: Power Supply, Raw Material Investment Cost: Investment cost per unit decreases

    as the capacity of the plant increases.Market Conditions: Depends upon demands supply

    and economy of the country. Resources of the firm: Both managerial and

    financial limitation.

    Government Policy: Capacity level may beinfluenced by the policy of the government.

  • 8/11/2019 CB2 MFC

    7/15

    7

    LOCATION AND SITE

    Location and site follows an assessment of demand,size and input requirement. Location refers to afairly broad area like a city, an industrial zone, or acoastal Proximity to Raw Materials and Markets (refinery,

    Steel Plant, Commodity based).

    This generally implies that:- A resource-based project like a cement plant or

    a steel mill should be located close to the sourceof the basic material (for example, limestone inthe case of a cement plant and iron ore in thecase of steel plant.)

    A project based on imported material may be locatednear a port; and

  • 8/11/2019 CB2 MFC

    8/15

    8

    (iii) a Project manufacturing a perishable

    product should be close to the centre ofconsumption. Availability of Infrastructure

    Availability of power, transportation, water, andcommunications, should be carefully assessedbefore a location decision is made

    Labour SituationIn labour intensive projects, the labour

    situation in a particular location becomesimportant. The key factors to be considered inevaluating the labour situation are:

    Availability of labour, skilled, semi skilledand unskilled

    Prevailing labour rates

  • 8/11/2019 CB2 MFC

    9/15

    9

    Labour productivity State of industrial relations judged in terms of the

    frequency and severity of strikers and lockouts

    Degree of unionisation Governmental Policies

    Private sector projects, location is influenced by certaingovernmental restrictions and inducements.Inducements for establishing industries in backward

    areas. These inducements consist of subsidies, salestax loans, man power subsidy, income tax benefits,lower promoter contribution, and so on.

    Other Factors Climatic conditions

  • 8/11/2019 CB2 MFC

    10/15

    10

    General living conditions Proximity to ancillary units Ease in coping with pollution

    SITE SELECTION

    Two to three alternative sites must be considered andevaluated with respect to cost of land and cost ofthe site preparation and development. The cost ofsite preparation and development depends on the

    physical features of the site. MACHINERIES AND EQUIPMENT

    The requirement of machineries and equipment isdependent on production technology and plantcapacity.

    The equipment required for the project may beclassified into the following types:

  • 8/11/2019 CB2 MFC

    11/15

    11

    Plant (process) equipment, (ii) mechanical equipment (iii)electrical equipment (iv) instruments (v) controls (vi)internal transportation system, and (viii) others.

    CONSTRAINTS IN SELECTING MACHINERIES ANDEQUIPMENT.

    Limited availability of power to set up an electricity intensive plant like,

    Difficulty in transporting heavy equipment to a remotelocation.

    Workers may not be able to operate

    PROCUREMENT OF PLANT AND MACHINERYThe plant and machinery may be placed with differentsuppliers or a turnkey contract may be given for the entire

    plant and machinery to a single suppler. Desired quality ofmachinery, the level of

  • 8/11/2019 CB2 MFC

    12/15

    12

    Technological sophistication, the relative reputation ofthe various suppliers, the expected delivery

    schedules, the preferred payment terms. STRUCTURES AND CIVIL WORKSStructures and civil works may be divided Site Preparation and development Buildings and structures, Outdoor works

    ENVIRONMENTAL ASPECTS

    A project may cause environment pollution in various ways: it may throw gaseous emissions; it may produce liquidand solid discharges;

    What are the types of effluents and emissionsgenerated?

    What needs to be done for proper disposal of

    effluents and treatment of emissions?

  • 8/11/2019 CB2 MFC

    13/15

    13

    Will the project be able to secure all

    environmental clearances and comply with allstatutory requirements? PROJECT CHARTS AND LAYOUTS

    General Functional Layout Material Flow Diagram Production Line Diagrams Transport Layout Utility Consumption Layout Communication Layout Organizational Layout Plant Layout

    SCHEDULE OF PROJECT IMPLEMENTATIONAs part of the technical analysis, a project

    implementation schedule is also usually prepared.For preparing the project implementation schedulethe following information is required.

  • 8/11/2019 CB2 MFC

    14/15

    14

    List of all possible activities from projectplanning to commencement of production

    The sequence in which various activities have tobe performed. The time required for performing the various

    activities. The resources normally required for performing

    the various activities.

    The implications of putting more resources orless resources than are normally required. WORK SCHEDULE

    The work schedule, as its name suggests, reflectsthe plan of work concerning installation as well asinitial operations. The purpose of the workschedule is:

  • 8/11/2019 CB2 MFC

    15/15

    15

    To anticipate problems likely to ariseduring the installation phase and suggest

    possible means for coping with them. To establish the phasing of investments

    taking into account the availability offinances.

    To develop a plan of operations coveringthe initial period.


Recommended