+ All Categories
Home > Documents > CB24_-_30_Degree_J-Rib_Manual_-_347862

CB24_-_30_Degree_J-Rib_Manual_-_347862

Date post: 03-Apr-2018
Category:
Upload: gechaves1
View: 215 times
Download: 0 times
Share this document with a friend

of 83

Transcript
  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    1/83

    02-28-08 347862 - MANUAL CHIEF42 CB24 TITAN 30< ROOF

    TITAN CB24COMMERCIAL BIN

    30

    ROOFERECTION MANUAL

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    2/83

    Page 1 MANUAL CHIEF42 CB24 TITAN

    INDEXSection 1 Grain Bin Specifications

    Section 2 Bin Erection

    Section 3 #24 Bin Roof A. Part IdentificationB. Pre-AssemblyC. Roof AssemblyD. Roof Panel AssemblyE. Cap Flashing

    Section 4 Typical Roof AccessoriesA. Top LidB. Manhole LidC. Working RingD. Roof LaddersE. Roof Vents

    Section 5 Temperature Cable Supports InstallationA. General ConsiderationB. Temperature Cable Supports

    Section 6 Sidewall and Stiffener Gauge Chart

    Section 7 Sidewall Erection A. Sidewall Sheets and StiffenersB. Laminated Sheet InstallationC. Base Angle DetailD. Titan One Ring Door E. Bin Stiffener Anchor F. Transition StiffenersG. Stiffener Upgrades for Goal Posts

    Section 8 Wind Rings

    Section 9 MiscellaneousA. Maintenance InstructionsB. Comment Sheet

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    3/83

    MANUAL CHIEF42 CB24 TITAN Page 2

    Manual Revisions

    Date: Revision Made

    10-12-05 Dimension for blocking needed to compress stiffeners added10-19-05 Changed that all rafters must be attached to a 2 ring top stiffener 10-25-05 Changed temperature cable bracket installation10-25-05 Changed roof ring connector 10-26-05 Changed door installation instructions11-11-05 Changed 3 Stiffened Bins have Roof Ring brackets at every stiffener 01-16-06 Changed to show holes added on horizontal seam of sidewall sheets between

    stiffener holes01-25-06 Updated gauge chart Removed all 20ga stiffeners02-17-06 Changed peak heights 2 higher 03-28-06 Updated Temperature Cable Installation09-20-06 Changed Standoff to 2 Parts Updated Manual10-25-06 Updated Roof Weights11-06-06 Changed Bins 25 rings and taller to show additional holes in roof panel ribs.01-29-07 Changed Rafter Clips. Updated Manual.02-06-07 Changed Working Ring Bracket.03-13-07 Changed Door 03-22-07 Added Section for Stiffener Upgrades for Goal Posts02-28-08 Changed Wind Ring Couplers

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    4/83

    Page 3 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    5/83

    MANUAL CHIEF42 CB24 TITAN Page 4

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    6/83

    Page 5 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    7/83

    MANUAL CHIEF42 CB24 TITAN Page 6

    Section 1 Grain Bin Specifications

    1. GENERAL DESIGN INFORMATION

    a) All Chief Industries grain bins are designed for storage and handling of 49.5 PCF (793 kg/m 3) free flowinggrain (52.5 PCF (841 kg/m 3) compacted grain @ 6%). Grain fill level shall not exceed 1" (25.4 mm) downfrom eave.

    b) Storage of products other than grain (products heavier than 49.5 PCF (793 kg/m 3 ),products having unusual flow characteristics or unusual corrosive properties) must beap pr ov ed by Ch ie f In du st ri es ' Engineering Department prior to quoting. Storage of soybean meal or meat scraps or other non-flowing products in standard tanks will void the warranty.

    c) Each individual sidewall ring has been designed to accommodate the vertical and horizontal wall loadsimposed by the stored grain. Sheeting gauge and design strength for each ring is individually analyzedfor all bin sizes. Also, stiffener gauges and design strengths are individually determined for each bin's fullsidewall height range. All steel materials are purchased in accordance with the applicable ASTMStandard.

    d) All bolted connections are designed using high strength bolts which meet the specifications of theapplicable ASTM or SAE Standards.

    e) All bins must be filled uniformly at the center and unloaded through the center discharge only, until grainno longer flows by gravity. Bins filled or emptied off-center will void the warranty; except approvedsidedraw systems.

    f) All Galvanized Steel used for storage and drying bins conform to ASTM specification A653 and theGalvanized coating to A924, TYPE G-115; 1.15 oz/ft. 2 (Z350; 350 gm/m 2) total for both sides as follows:

    22 Ga. Thickness & lighter = CS TYPE A; 33ksi min yield (grade 230)18 & 20 Ga Thickness = SS Grade 40, Class I; 40ksi min yield (grade 275)17 Ga. Thickness & heavier = SS Grade 50, Class I; 50ksi min yield (grade 340)

    (Please note: SS = Structural Steel)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    8/83

    Page 7 MANUAL CHIEF42 CB24 TITAN

    2. ROOF DESIGN

    All roofs are certified to withstand normally anticipated environmental and service conditions.

    IMPORTANT:Roof peak loads in excess of specified rating can cause structural roof damage and will void all binwarranties.

    A) J-Rib Roof Design 1) The CB5 thru CB11 grain bin roofs are available standard with a 35 o slope. The CB9 thru CB11bin roofs are designed to incorporate a structural bridging ring. These roofs have 4 roof panels per sidewall sheet and are certified for 90mph (145 km/hr) wind with 17 PSF (0.79 kPa) ground snowload plus roof dead load and concentrated peak load of 1000 LB (454 kg) with a 30" (762 mm) peakring diameter.

    2) Structural roof framing (grey iron roof) is available on all bins CB5-CB11. These roofs arecertified for 90 mph wind (145 km/hr) wind with a 30 PSF (1.44 kPa) ground snow load plus roof dead load and concentrated peak load of 3000 LB (1361 kg) with a 30" (762 mm) peak ringdiameter.

    3) The CB12 thru CB34 grain bin roofs have a 30 o roof slope and utilize a complete structuralframing system which supports loads independent of the roof panels. The CB12 and CB16 bin

    roofs are certified for 90 mph (145 km/hr) wind with a 30 PSF (1.44 kPa) ground snow load plusroof dead load and a concentrated peak load of 16,000 LB (7258 kg) with a 40" (1016 mm) peakring diameter. CB18 through CB34 bin roofs are certified for 90 mph (145 km/hr) wind with a 30PSF (1.44 kPa) ground snow load plus roof dead load and a concentrated peak load of 25,000 LB(11338 kg) with a 72" (1829mm) peak ring diameter.

    4) WORKING RINGS: Standard on all #5 thru #34 bins. Constructed of 1-1/2 (38mm)pipe and provides a continuous ring around the center and is attached with heavygauge brackets located on top of roof ribs, close to roof cap.

    B) V-Rib Roof Design

    1) All CBU & CBUE Storage and Drying Bins are designed for 90 mph (145 km/hr) with a30 PSF (1.44 kPa) (ground snow load plus roof deadload). Additional concentrated load may beapplied at the peak of the bin up to 3,500 lbs. (1588kg) for #5 thru #7 and 6,000 Ibs.(2722kg) for #8 thru #12 bins with a 37" (940 mm) peak ring and up to 8,500 Ibs.(2949 kg) for #14 and #16 bins with a 60" (1.5 m) peak ring.

    2) The roof pitch of CBU & CBUE Storage and Drying Bins is 35 0 for all #5 through #16bins. Roof panels are 22 gauge and have four roof panels per sidewall sheet. Onepiece roof panels are standard for all roofs and feature 2-1/2"(64mm) deep ribs for #5through #12 roofs and 4" (102 mm) deep ribs for #14 and #16 roofs. An optional eavesealer is available if desired.

    3) Roof Rib Fasteners are 5/16" (8 mm) diameter JS500 zinc plated hex head type ABself-tapping screws with 5/8" (16 mm) O.D. bonded sealing washer facilitates quicker assembly of the bin roof and a positive, structural and weather resistant rib to ribconnection.

    4) Heavy gauge formed galvanized eave clips bolt directly to roof panel and wall sheet.Clips are adjustable with slotted holes to raise or lower roof as desired. "HurricaneClips" are standard on all #14 and #16 bins. They are optional on #5 thru #12 bins for areas of prevailing high winds for added eave stability.

    5) WORKING RINGS: Standard on all #5 thru #16 bins. Constructed of 1-1/2" (38mm) pipeand provides a continuous ring around the center and is attached with heavy gaugebrackets located on top of roof ribs, close to roof cap.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    9/83

    MANUAL CHIEF42 CB24 TITAN Page 8

    6) ROOF BRIDGING RINGS: One outside roof bridging ring is standard on all #10 thru#12 bins and optional for #7 thru #9 bins. Two roof bridging rings are standard for #14and #16 bins. Rings are fabricated from heavy gauge 1-1/2" (38mm) diameter tube andthreaded connectors expand to position the ring in place.

    3. GRAIN BIN USAGE

    a) CBU & CBUE UNSTIFFENED BIN SERIES

    The Unstiffened bins are designed and intended for storage and drying of common smallgrains. This includes all models except for the 8 thru 10 rings tall bins which are used for storage (Not Drying) only. All unstiffened bins up through 7 rings tall will accommodate astirring device consisting of no more than three down augers.

    b) CB STIFFENED TO EAVE BIN SERIES

    The CB Stiffened to Eave Bins may be used for all common drying applications, thesebins are available in sizes CB #5 thru #16. If stirring devices consisting of more than sixdown augers are to be used, contact Chief Industries, Inc., for recommendations. This binmust be used when Stirway II's, Recirculating devices, and stirring devices with four or more down augers are to be installed.

    Note: See detail on using Stirring Devices

    4. THE GENERAL CONTRACTOR'S RESPONSIBILITIES

    It is the responsibility of the General Contractor to insure that the complete bin system (bin,foundation, grain transport equipment, aeration equipment, and other accessory equipment) isconstructed in a quality workmanship manner and that all equipment is installed per the respectivemanufacturer's instructions.

    In addition, the General Contractor is responsible for the fitness of use of any system which heconstructs. All accessory equipment incorporated into the system should be approved for theintended use of each respective equipment manufacturer.

    a) Field Modifications and Erection Defects

    Chief Industries, Inc., assumes no responsibility for field modifications or erection defectswhich create structural or storage quality problems. If any field modifications arenecessary which are not specifically covered by the contents of our erection manual,contact Chief Industries, Inc., for approval of the field modifications. Any unauthorizedmodification or erection defect which affects the structural integrity of the Chief bin will because for immediate nullification of the Chief Grain Bin Warranty.

    b) Concrete Information for Design and Construction

    The suggested foundation designs shown in the bin erection manuals are based on theallowable soil bearing capacity of the undisturbed soil and should be checked by alicensed engineering firm. Using soil borings to determine the allowable soil bearingcapacity, a professional engineer will need to be engaged by the contractor to design thefoundation and floor slab accordingly. All suggested foundation designs must beapproved by a licensed engineer in order to meet local governing building codes and localsoil and weather conditions. Wall loads and floor pressure for standard Chief grain binsare available from Chief Industries, Inc., upon request.IMPORTANT: THE FINISHED FLOOR SURFACE MUST BE LEVEL AT THE BIN WALLLOCATION. LOW SPOTS IN PERIMETER WALL ELEVATION WITHOUTADEQUATE SHIMMING CAN CAUSE STRUCTURAL DAMAGE TO THE BINSIDEWALL. FAULTY CONCRETE WORK OR SHIM OMISSION WILL NULLIFY THEBIN'S WARRANTY.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    10/83

    Page 9 MANUAL CHIEF42 CB24 TITAN

    The suggested concrete foundation designs must not be used in conjunction with unload andaeration tunnels. Concrete and reinforcing bar requirements must be determined by a certifiedprofessional engineer. The design must consider soil bearing capacity, soil consolidation, footingrequirements, tunnel requirements and the interaction of all foundation components under loadedcondition. Non-uniform settlement of the foundation can cause severe structural damage to binand foundation. An improperly designed or constructed foundation will void all aspects of the binwarranty. It is the responsibility of the General Contractor to insure that an adequate foundation is

    provided for the bin.

    5. ACCESSORY EQUIPMENT

    All accessory equipment should be installed and maintained in accordance with each individualsuppliers installation and operation instructions. However, if any sidewall penetrations or other modifications to Chief Industries, Inc., standard bin design are required, refer to bin erectionmanual or contact Chief Industries, Inc., for special recommendations. Do Not Modify Bin DesignWithout Chief Approval. It is the responsibility of the General Contractor to insure that allequipment is properly installed and that the equipment is compatible with the intended use. Aqualified electrician should be contracted to complete all electrical wiring and servicing.

    Chief Industries, Inc., provides no warranty concerning parts, accessories or equipment notmanufactured byChief Industries, Inc.

    a) Roof Peak Service Loads

    When determining the service loads on the roof peak, the weight of all accessoryequipment suspendedor supported by the peak should be considered. The weights should be calculated usingthe equipment dead load plus the operating load. For example, the weight of an overheadconveyor should include the catwalk, conveyor head assembly, motors, drives,downspouts, discharges and weight of grain when in operation. If conveyor and catwalkdesign is such that snow build up is likely during winter months, snow load must be addedin the peak load calculation. If a temperature cable is suspended from peak add 1000 lbs.(452 kg.) per 40 foot (12.2 m) of cable length to the peak's service load. Interpolate valuefor intermediate cable length; i.e., 60 foot (18.3 m) cable would exert 1500 lbs. (680 kg), of load.

    b) Bin Loading Equipment Center filling through the peak opening is required for all bins. Off center loading willcreate unequal pressures on the bin wall and result in structural damage. If downspoutingis to be used, it is recommended that a dead head or cushion box be used to promoteuniform filling. Also, the use of spreaders or splash plates are recommended for distributing the grain fines, promoting uniform air flow through grain and leveling the grainpeak.

    IMPORTANT: FILL CONVEYORS AND THE CATWALK MUST NOT BE SUPPORTEDBY STANDARD GRAIN BIN WALL. USE INDEPENDENT SUPPORT TOWERS TOSUPPORT OVERHEAD CONVEYORS OR CB STIFFENED BINS WITH UPGRADEDSTIFFENERS TO SUPPORT THIS TYPE OF LOAD.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    11/83

    MANUAL CHIEF42 CB24 TITAN Page 10

    c) Bin Unloading Equipment

    All bins must be unloaded through center discharge. If intermediate wells areinstalled in the floor, they must not be opened until all gravity flow through thecenter well has ceased. Therefore, center and intermediate wells must haveseparate control rods. The center well's sweep auger pivot should be centered inthe bin to insure unobstructed sweep rotation. If unloading auger exits through bin wall,thoroughly seal around auger tube to prevent moisture and airflowleakage. Reinforcing of sidewall sheets will be necessary if auger exits throughthe bin wall at a point exposed to direct grain pressure. Contact Chief Industries,Inc., for reinforcing recommendations.

    IMPORTANT: HIGH UNLOADING RATES CAN CREATE A VACUUM INSIDE BIN. IFUNLOADING RATES EXCEED 5000 BUSHELS (125 MT) PER HOUR, A MINIMUM OFONE FREE INTAKE VENT (GOOSE NECK VENT RECOMMENDED) MUST BEINSTALLED. ONE UNOBSTRUCTED STANDARD CALDWELL BIN VENT WILLPROVIDE ADEQUATE VENTING UP TO AN UNLOADING RATE OF 80,000 BPH (2000MT/HR). IF SUBSTANTIALLY HIGHER RATES ARE NEEDED, PLEASE CONTACTCHIEF INDUSTRIES FOR A RECOMMENDED VENT REQUIREMENT.

    Sidedraw baffle systems may be installed in the bin sizes specified in Chief catalog. Also,the Chief Industries, Inc., sidedraw unit is the only approved type of sidedraw system thatcan be installed in a Chief grain bin.

    IMPORTANT: ANY SIDEDRAW UNIT IMPROPERLY INSTALLED IN A CHIEF BINWITHOUT CHIEF INDUSTRIES' APPROVAL, OR SIDEDRAW UNITSMANUFACTURED BY OTHER THAN CHIEF INDUSTRIES, INC., COULD RESULT INSTRUCTURAL DAMAGE TO THE BIN AND WILL VOID THE BIN WARRANTY.

    d) Temperature Cables

    Temperature cables can be installed in all standard Chief bins; the number and location of temperature cables for each bin size are listed in the temperature cable installation sectionof the erection manual.

    Temperature cable support kits supplied by Chief Industries, Inc., are available and mustbe used whenever temperature cables are installed. Be sure to allow adequate clearancefor sweep augers or other internal equipment. Follow temperature cable manufacturer'srecommendations for shortening temperature cables if necessary, provide adequatesealant where temperature cable lead wire exits the bins.

    IMPORTANT: SUPPORT OF TEMPERATURE CABLES BY ANY MEANS OTHERTHAN CHIEF INDUSTRIES' RECOMMENDED SUPPORT KITS MAY CAUSESTRUCTURAL DAMAGE TO THE BIN ROOF AND WILL NULLIFY THE CHIEF GRAINBIN WARRANTY.

    IMPORTANT: All TEMPERATURE CABLES SHOULD BE SECURED TO FLOOR TOPREVENT CABLE FROM DRIFTING TOWARD BIN WALL DURING FILLING. THEUSE OF LIGHT TWINE OR MONOFILAMENT LINE SECURED TO A RECESSEDANCHOR IS RECOMMENDED.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    12/83

    Page 11 MANUAL CHIEF42 CB24 TITAN

    e) Fans and Transitions

    Aeration fans should be sized in accordance with Chief's specifications for the particular bin being considered.

    All fans must be installed per Chief's recommendations and leveled prior to operation. Aqualified electrician should be contracted to complete all electrical wiring and servicing.

    The transition through the bin wall must be thoroughly sealed around the outside of thetransition entrance collar to prevent airflow leakage. Use of strip caulking in combinationwith flashing provided by the transition manufacturer is recommended. If the transitioninterrupts a stiffener line, the special transition stiffener available from Chief Industries,Inc., must be installed as described in the erection manual. Also, if the transition entersthrough the bin's bottom sidewall sheet (full floor aeration and tube aeration), adequatereinforcing of the bottom sidewall sheet must be added. Contact Chief Industries, Inc., for recommendations. Standard drying bins do not require reinforcing of bottom sidewallsheet as long as transition enters below the false floor level.

    f) Heaters

    The heater unit must be properly matched with the fan size to be used. Heater unit andfan must be compatible, and it is recommended that both units be supplied by the samemanufacturer to insure compatibility and safety. Heater unit installation and servicingshould only be completed by personnel properly trained by the manufacturer of productsbeing used. The fan and heater need to be located on the bin to assure uniform airflow tothe bin. The units should be located at a position 180 0 from the outlet of the withdrawaltube.

    DANGER: Fuel tanks, lines and all valves must be compatible with the type of fuel to beused. Failure to use certified fuel tanks, lines or valves can result in death or severepersonal injury.

    DANGER: Never use anhydrous ammonia tanks or improperly modified fuel tanks for L.P. gas storage.

    DANGER: L.P. fuel flow control regulators must be installed as recommended by heater unit manufacturer.

    DANGER: Natural gas flow regulators at the service entrance must be installed by naturalgas supplier and must not be modified.

    The drying temperature should be established based on the type of grain to be dried.Contact Chief for optimum drying temperature. Excessive heat can result in graindamage, overdrying and potential grain fires.

    CAUTION: When drying sunflower seeds, the drying temperature should not exceed 105 o Fahrenheit (41 0Celcius). Higher temperatures can result in sunflower oil combustion.

    g) Aeration Floors

    Chief recommends the use of channellock floors with steel supports for full floor applications. Commercial applications, (floors loaded and unloaded more than once per year) and bins with a total grain depth of 60' (18.3 m) or greater require an 18 gauge (1.3mm) floor. The floor layout support spacing must be followed for the particular bin beingconstructed. Floor supports, fan locations and auger tube should be oriented as shown inthe manufacturer's floor plan to insure optimum airflow movement.

    Corrugated perforated floors require a concrete block and lumber support system.Concrete block and lumber floor supports are not recommended in bins larger than the#13 or bins taller than eight rings. Airflow restrictions when using concrete block andlumber can significantly reduce the air flow efficiency.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    13/83

    MANUAL CHIEF42 CB24 TITAN Page 12

    h) Roof Ventilation

    Any grain bins using forced air for aeration or drying must be provided with sufficientexhaust or intake vents to prevent excessive internal pressures, either positive or negative. The vent supplier should be consulted for ventilation requirements on eachproject, with the specific bin size, grain type and depth, fan size and floor type taken intoconsideration. Chief Industries, Inc., does not recommend the use of negative aerationsystems. In the event that negative aeration is to be used, the intake vent requirementshould be sized for the bin in the empty condition.

    IMPORTANT: ROOF VENT MUST BE FREE OF DEBRIS OR OTHER OBSTRUCTIONSPRIOR TO OPERATION OF FANS.

    POWER FANS SHOULD NOT BE OPERATED WHEN AMBIENT TEMPERATURE ISBELOW 35 o FAHRENHEIT (2 o Celsius) DUE TO POTENTIAL OF VENT ICING.

    OBSTRUCTED OR ICED VENTS CAN SIGNIFICANTLY INCREASE INTERNAL TOEXTERNAL PRESSURE DIFFERENTIAL AND COULD RESULT IN STRUCTURALDAMAGE TO BIN ROOF, WALL OR BOTH.

    i) Stirring Device Stirring devices can be installed in any drying bin, with the limitations discussed in Section3. The bins storage capacity will be reduced when installing a stirring device. Drying binstorage capacities listed in the Chief catalog should be used with the additional capacityreduction for down auger drive unit clearance. Inside ladders may require short bracketsfor wall attachment to provide clearance for the stirring device.

    CAUTION: The grain level must not be filled above the stirring device. Grainpressure on the stirring device could cause roof or stirring device damage.

    Down augers may require shortening in order to provide minimum floor clearance of 3"-5"(76mm -127 mm) or additional clearance for sweep augers. Manufacturers down auger shortening procedure should be followed.

    j) Recirculators or Continuous Flow

    Recirculators can only be installed in CB bins. These devices should be installed asinstructed by the manufacturer and with the following additional considerations:

    a. Consult floor manufacturer for recommended floor reinforcing measures at baseof recirculator.

    b. If transfer auger exits through roof panels, provide sealant around auger tube toprevent water leakage.

    c. The weight of the transfer auger must not be supported by the roof panels. Thetransfer auger should be supported by the recirculator boot and an adjacent binor independent support.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    14/83

    Page 13 MANUAL CHIEF42 CB24 TITAN

    Section 2 Bin Erection

    Chief Industries, Inc. will not assume any responsibility for parts damaged due to faulty orimproper erection procedures.

    Chief Industries, Inc. recommends that Bin Jacks be used for all bins taller than 8 ringsand all bins larger than 30 in diameter.

    WARNING:The allowable lifting capacity of the BIN JACKS must never be exceeded. Always check Binweight to insure a safe and trouble free erection.

    Grain Bin Color Codes

    Chief Grain Bins are color coded based on bin diameter. Components such as Roof Rafters,

    Wind Rings, and Base Angle will be marked with the following Color Codes to help identifythem.

    Bin Size Color Code Bin Size Color Code#12 Yellow/Black #22 Blue#13 Green/Black #24 Brown#14 Orange/Black #26 Yellow#16 Red #30 Green#18 Black #34 Orange#20 Pink

    A. Suggested Erection Equipment

    Impact Wrench & Sockets Wrenches Crescent WrenchVise Grips Alignment Punches Rubber MalletLevel Drill and Drill Bits Extension CordsLadders Bin Jacks Screw Gun

    7/16 bin bolts use 5/8 on the head of the bolt and 11/16 on the nut.5/16 bin bolts use 1/2 on the head of the bolt and nut.

    1/2 bolts in the roof structure use 3/4 on the head of the bolt and nut.

    Bolt Buckets are Color Coded with a Dot as Shown Below.

    Bolt Size Color Code5/16 Blue7/16 Red1/2 Green5/8 Yellow

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    15/83

    MANUAL CHIEF42 CB24 TITAN Page 14

    B. Checking Shipment

    Check your shipment at the time of pickup and delivery against the packing list furnishedwith the shipment. If a shortage exists or if any damaged material is evident, note suchshortage or damage on the freight bill before you sign for the shipment.

    Claims of shortages will not be honored after thirty days from receipt of shipment.Parts that are short or damaged are the responsibility of the delivering carrier, not themanufacturer or dealer.

    It is advisable to reorder damaged or missing parts immediately so that there will be nodelay in erecting the bin. After receiving the invoice for the reordered material, file aclaim with the delivering carrier at once.

    The galvanized panels leave our plant in prime condition; store off the floor in a heatedroom if possible. If stored outside, place panels down, off the ground. Upon arrival of shipment if you are not certain whether or not moisture is present, store panels on edge or on end allowing 1/4 air space between panels until dry. Exposure to trapped moisturecan cause white rust, which will void the warranty.

    C. Stop and Study

    Before beginning erection of the bin, take the time to thoroughly study the constructionmethods in this manual. It will save you both time and money .

    Important: The peak load capacities listed under Auxiliary Roof Loads must not be exceeded. If your

    application will exceed the listed values, contact Chief Industries for recommendations.

    Chief Industries makes no warranty concerning parts, accessories or equipment notmanufactured by Chief Industries.

    D. Sight Selection

    Choose a site that has good drainage away from the bin so that water will not stand around

    the bin. The soil should be firm and preferably without fill. If fill is required, water andcompact the fill material to avoid uneven settlement. A field investigation of the soil

    bearing conditions is recommended especially for larger grain bins where the foundationloads and floor pressure become large. A licensed engineering firm should be employed totake soil borings, determine the maximum allowable soil pressure and design the binfoundations and floor slab accordingly.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    16/83

    Page 15 MANUAL CHIEF42 CB24 TITAN

    E. Bin Jack Erection

    Position the structure you provided to hold the Inner Ring at its approximate height,centering the Inner Ring on the center of the Bin.

    Use at least one Bin Jack per Sidewall Sheet. (For example, on the #18 Bin, use 18 BinJacks, etc.)

    The application of one bin jack per sidewall sheet will minimize sidewall distortion duringerection. Failure to use the proper quantity of jacks may result in inward-outward lay of the binsidewall or even permanent distortion of the bin sidewall sheets.

    The recommendation of at least one Bin Jack per sidewall sheet is based on keeping the binround, refer to the warning below, and make sure the lifting capacity of the jack issufficient for the weight of the bin. Note that all jacks may not shift equally, Thereforemake sure the lifting capacity rating by the jack manufacturing is met.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    17/83

    MANUAL CHIEF42 CB24 TITAN Page 16

    F. Assembling Sidewall Sheets

    All bolts are washer head bolts with sealing washers S.A.E. Grade 8, with whiz flangenuts. Grade 8 bolts are marked with six radial lines on the bolt head as shown. If these

    descriptions do not correspond with the bolts shipped with the bin, please contact thecustomer service department immediately. Do not substitute any other Bolts.

    Bin bolts must be TIGHT . The following table contains recommended minimum andmaximum torque values.

    BOLT DIA. TORQUE FT. LBS(INCHES) MINIMUM MAXIMUM

    5/16" 22 287/16" 60 75

    Tighten the bin bolts from the inside of the bin (nut end of the bolt) to eliminate spinoff of the sealing washer.

    USE ONLY THOSE BOLTS SUPPLIED BY CHIEF INDUSTRIES.THE SUBSTITUTION OF BOLTS FROM OTHER SOURCES IS NOT PERMITTED.

    The top 2 rings of the bin and the roof should be assembled on the concrete bin floor.Attach the lifting brackets to the bolts at the endlaps of the sidewall sheets. The lifting

    brackets must be attached to the endlap by at least 8 standard bin bolts.

    NOTE: Proper bolting sequence MUST be followed at all times.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    18/83

    Page 17 MANUAL CHIEF42 CB24 TITAN

    The Titan Sign Sheet must be installed in the second ring as shown in figures below.

    (Shown installed on a 2 stiffened bin)

    (Shown installed on a 3 stiffened bin)

    Install the Titan Sign Sheet by field drilling (6) six holes in the Titan Sign Sheet andstiffeners as shown above. Bolt the Titan Sign Sheet to the stiffeners with (6) six 7/16 bolts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    19/83

    MANUAL CHIEF42 CB24 TITAN Page 18

    Assembling top ring

    Locate the proper gauge of sidewall sheets needed for the top ring from the gauge chart. Lap andcaulk sheets as shown below. Locate top stiffeners and install on top ring.

    Note: Top Sheets have special punching on the top of the sheet at the stiffener holes for therafter to attach to. Leave bolts out of top (4) stiffener holes until eave brackets areattached.

    Wipe off the outside ends of all the Sidewall Sheets to remove excess oil so that the StripCaulking will adhere to the metal. Place the Strip Caulking as near to the vertical inside edge of sheet at every vertical seam.

    On Bins 12 gauge or heavier a horizontal strip of caulking is needed on the inside at the center bottom of the Sidewall sheet located on the hill near to the bottom holes. This strip of caulkingshould fit where the endlap of the next ring Sidewall Sheets bolts up to this location.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    20/83

    Page 19 MANUAL CHIEF42 CB24 TITAN

    G. Roof Panel Location

    The rafters need to be bolted directly behind a top 2 ring stiffener, the roof panel rib will line updirectly above the rafter from the peak to the eave. (There is 1 Rafter and 4 roof panels per sidewall sheet.)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    21/83

    MANUAL CHIEF42 CB24 TITAN Page 20

    H. Crane and Jack Capacities

    Crane Capacity:

    The total roof dead load for each of the respective bin roof sizes is shown in the table below.

    This weight includes the roof panels and all structural members (roof beams, compression rings, bolts, ect.)

    When determining the crane capacity necessary to erect the roof structure, the booming distancemust be considered. If the cane sizes available will not lift the roof structure (using one crane),two cranes may be used, utilizing a spreader bar. The spreader bar must be adequately designedto carry the entire roof dead weight.

    Peak Heights

    All peak heights listed below are to the bottom of the peak ring from the ground with (2) Titansidewall sheet rings installed. Deduct 42 1/2 from the peak heights when only one ring of sidewall sheets are installed.

    Model Peak HeightCB18 20 - 8 7/8CB20 22 6 5/16CB22 24 3 3/4CB24 26 1 1/8CB26 27 10 9/16

    CB30 31 5 7/16CB34 35 0 5/16

    WARNING!! OVERLOADING CRANE CAPCITY CAN RESULT INSUBSTANCIAL PROPERTY DAMAGE OR SEVERE PERSONAL INJURY.ALWAYS CHECK CRANE CAPACITY PRIOR TO LIFTING ROOFSTRUCUTRE

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    22/83

    Page 21 MANUAL CHIEF42 CB24 TITAN

    #34 #30 #26 #24 #22 #20 #18Single Rafter 660 550 400 300 250 230 2002 Rafter 1,450 1,200 850 700 600 550 4503 Rafters 2,300 1,825 1,350 1,075 950 850 675Total Roof w/o Roof Panels 31,250 23,650 15,350 11,925 9,900 8,525 5,750Total Roof w/ Roof Panels 50,000 38,400 26,600 21,000 17,500 15,000 11,000

    Weight in Pounds (lbs .)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    23/83

    MANUAL CHIEF42 CB24 TITAN Page 22

    Section 3 - #24 Bin Roof

    A. Part Identification

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    24/83

    Page 23 MANUAL CHIEF42 CB24 TITAN

    B. Pre-Assembly

    After the top two rings of the bin are built and stiffeners are added, brackets need attached to thesidewall and rafters, pre-assemble these brackets on the ground before raising the roof will speedup erection time.

    Top Angle

    Attach top angle to inside of top ring as shown with 5/16 x 3/4 Bin Bolts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    25/83

    MANUAL CHIEF42 CB24 TITAN Page 24

    Roof Ring Brackets

    Attach Roof Ring brackets to the inside of the top sidewall sheet behind the stiffener with 7/16x 1-1/2 bin bolts. There is one Roof Ring Bracket per sidewall sheet on 2 stiffened bins. On 3stiffened bins there is two Roof Ring Brackets per sidewall sheet.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    26/83

    Page 25 MANUAL CHIEF42 CB24 TITAN

    C. Roof Assembly

    Raise the peak ring to the correct height as shown and begin attaching rafter to the peak ring andeave brackets with 1/2 x 1-1/2 bolt with washers on the brackets. Attach 4 sets of raftersequally spaced around the bin and check to insure peak ring is level, and then install all other

    beams. Leave all bolts loose in the structure until all rafters and cross members and struts areinstalled.

    Refer to the drawing below for sequence of beams.Refer to the part identification page at the beginning of this section to determine proper rafters.

    All Rafter to rafter connections are 1/2 x 1-1/2 bolts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    27/83

    MANUAL CHIEF42 CB24 TITAN Page 26

    Ring Segment Clips

    Attach the ring segment clip to every rafter as shown; using 1/2 x 1-1/2 bolts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    28/83

    Page 27 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    29/83

    MANUAL CHIEF42 CB24 TITAN Page 28

    Detail at Eave

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    30/83

    Page 29 MANUAL CHIEF42 CB24 TITAN

    Ring Segments

    After all rafters are installed, begin installing ring segments to the clips that are bolted to therafters as shown. Install ring segments with 1/2 x 1-1/2 bolts with washers against the ringsegment.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    31/83

    MANUAL CHIEF42 CB24 TITAN Page 30

    Roof Struts

    Attach upper Roof Strut with 1/2 x 1-1/2 bolts between center set of holes on Rafters B asshown. An Upper Roof Strut is placed between every rafter as shown below.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    32/83

    Page 31 MANUAL CHIEF42 CB24 TITAN

    Attach Middle Roof Strut with 1/2 x 1-1/2 bolts to back side of upper ring segment and center set of holes on Rafter B as shown. A middle Roof Strut is placed on every upper ring segmentas shown below.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    33/83

    MANUAL CHIEF42 CB24 TITAN Page 32

    Attach Lower Roof Strut with 1/2 x 1-1/2 bolts to inside of the lower ring segment and center set of holes on Rafters A and B as shown. A lower roof strut is placed on every lower ringsegment as shown below.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    34/83

    Page 33 MANUAL CHIEF42 CB24 TITAN

    Eave Brackets

    Attach Left Hand and Right Hand Eave Brackets to the inside of the top sidewall sheet behindthe 2 ring top stiffener, with 7/16 x 1-1/2 bin bolts with bolt head inside the bin, as shown.(Note: one L.H. and one R.H. Eave Bracket per sidewall sheet equally spaced around the bin)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    35/83

    MANUAL CHIEF42 CB24 TITAN Page 34

    Roof Ring

    After all the structure is assembled, place the segments of roof ring pipe thru the eave bracketsand roof ring brackets as shown, there are 2 roof ring connectors are used to connect every roof ring segment. Leave roof rings approx. 5 apart until all connectors are installed. Attach the

    connectors to the pipe with 5/8 x 4 bolts. When all roof ring segments and connectors areinstalled, begin tightening the connectors by turning the nut on the connector to draw the pipetogether at every connector, as much as possible until rafters start to arc slightly, check to makesure the pipe is not bound up against the brackets.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    36/83

    Page 35 MANUAL CHIEF42 CB24 TITAN

    D. Roof Panel Assembly

    Lower Roof Panel Assembly

    Install bottom standoff angle centered on top side of ring segment as shown. Place row or strip

    caulking on standoff angle where the lower roof sheets will be attached. Use 5/16 x 1-1/4 bin bolts (heads on outside of bin) to attach upper end of lower sheets to bottom standoff angle andring segment. Align roof sheet so that rib is inline with rafter. Bolt wide end of lower roof panelto top angle

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    37/83

    MANUAL CHIEF42 CB24 TITAN Page 36

    Always working to the right around the bin, place strip caulking on right rib of the previouslyinstalled roof panel (top only). Placing roof panel in a vertical position, lock the left rib of the

    panel being installed over the right rib of the previously installed panel. Tip the roof panel down.As each roof panel is set into place, insert a lining punch through the hole in the rib at the bottomof each roof panel. Temporarily clamp the two roof panels together with vise grips so that the

    punch can be removed and a 5/16 x 3/4 bolt inserted and hand tightened. Continuedinstallation of roof panels as described in preceding steps.

    All bins are equipped with one manhole and a roof ladder as standard. Extra manholes should bespaced evenly around the bin.

    When the last roof panel is placed, it will have to be interlocked by using a rubber mallet.Starting at the top and working down, tap the vertical rib until it is sealed to the other panel.Align roof panel holes and insert 5/16 x 3/4 bolts in the same manner as previously described.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    38/83

    Page 37 MANUAL CHIEF42 CB24 TITAN

    Attach the roof panels to the roof joist using two #12 x 1 self-drilling screws per panel asshown.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    39/83

    MANUAL CHIEF42 CB24 TITAN Page 38

    Upper Roof Panel Installation

    Roof Panel flashing extensions

    The extensions come in 8 equal pieces install clockwise around the peak and attach with 7/16 x

    1 bin bolts. (Note: Flashing Extensions must be started as shown to properly align roof panels,align first extension on hole that is aligned with rafter and flashing hole in peak ring.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    40/83

    Page 39 MANUAL CHIEF42 CB24 TITAN

    Roof Panel Installation

    1. Install strip caulking between top end of roof panels and roof panel flashing. Use 5/16 x3/4 bolts at top end of panel. Bolt roof panels standoff ring with 5/16 x 1-1/4 bin bolts.Align upper roof panel so the rib is inline with the rafter.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    41/83

    MANUAL CHIEF42 CB24 TITAN Page 40

    Install top standoff angle to inside of bottom standoff angle and attach angles together with 5/16x bin bolts as shown. Place strip caulking on top side of top standoff angle where upper sheets will to attached to top standoff angle.

    Place strip caulking around standoff splice and install to inside of top and bottom standoff anglesas shown. Attach to standoff with 5/16 x bin bolts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    42/83

    Page 41 MANUAL CHIEF42 CB24 TITAN

    Proceed by installing additional roof panels in the following manner: Always working to theright around the bin, place strip caulking on right rib of the previously installed roof panel(top only). Placing roof panel in a vertical position, lock the left rib of the panel beinginstalled over the right rib of the previously installed panel. Tip the roof panel down. As eachroof panel is set into place, insert a lining punch through the hole in the rib at the bottom of

    each roof panel. Temporarily clamp the two roof panels together with vise grips so that the punch can be removed and a 5/16 x 3/4 bolt inserted and hand tightened. Continuedinstallation of roof panels as described in preceding steps.

    When the last roof panel is placed, it will have to be interlocked by using a rubber mallet.Starting at the top and working down, tap the vertical rib until it is sealed to the other panel.Align roof panel holes and insert 5/16 x 3/4 bolts in the same manner as previouslydescribed.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    43/83

    MANUAL CHIEF42 CB24 TITAN Page 42

    Special Note:Bins 25 rings and taller will have roof panels with additional holes in the roof sheet ribs. Fielddrill hole in ribs using pre-punched hole on adjacent rib as template, Attached roof panels ribstogether with 5/16 x 3/4 bin bolts and washer as shown.

    Roof Panels installation for bins 25 rings and taller

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    44/83

    Page 43 MANUAL CHIEF42 CB24 TITAN

    E. Cap Flashing

    The cap flashing comes in 8 equal pieces; install the cap flashing to the peak ring with the 7/16x 1 bin bolts. After cap flashing pieces are attached to the peak ring attach the cap flashing tothe top of the roof panel ribs with #12 x 1-1/4 self-drilling screws.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    45/83

    MANUAL CHIEF42 CB24 TITAN Page 44

    Section 4 Typical Roof Accessories

    A. Top Lid

    (1) Apply strip caulking around the top of the peak ring.

    (2) Install top lid using twenty 7/16 x 1 bolts (bolt heads on top). Securely tighten bolts.

    B. Manhole Lid

    (1) Install manhole lid as shown below. Note that manhole hinge should be installed towardtop of bin.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    46/83

    Page 45 MANUAL CHIEF42 CB24 TITAN

    NOTE: Leaf to lid and hinge to roof panel bolts are to be installed with heads inside.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    47/83

    MANUAL CHIEF42 CB24 TITAN Page 46

    C. Working Ring

    Field locate and Install the working ring to the roof panels as shown, with 5/16 x 3/4 Bin bolts.The working ring clips are to be evenly spaces around the ring. Connect the working ringsegments together with the connectors as shown below. Expand the connector as needed.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    48/83

    Page 47 MANUAL CHIEF42 CB24 TITAN

    D. Roof Ladder

    Two Piece Roof LaddersOn bins #22 through #34

    1. Bins supplied with standard two piece roof ladder. The roof ladder should be located adjacentto the manhole and centered on a roof beam.

    2. Install the lower roof ladder first. Bolt wide end of roof ladder to roof panel, using same boltsthat connect roof panel to top sidewall sheet.

    Detail A

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    49/83

    MANUAL CHIEF42 CB24 TITAN Page 48

    3. Bolt the top part of the lower roof ladder to the lower roof panel with same bolts used to boltthe lower roof panel to the standoff ring.

    Detail B

    4. Install the upper roof ladder by bolting the wide end to roof panel using same holes that boltupper roof panel to the standoff ring.

    Detail C

    5. At the top of the upper roof ladder, field drill 3/8 holes in roof panel rib and bolt ladder toroof panel, using 5/16 x 1-1/4 bolts.

    Detail D

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    50/83

    Page 49 MANUAL CHIEF42 CB24 TITAN

    E. Roof Vents

    A. Goose Neck Vent Installation

    1. Refer to the bulletin that comes with the vent for installation procedures

    2. Locate Goose Neck Vent on the desired roof sheet. Typically slide Goose Neck Vent up theroof sheet (Toward the small end) until the corners of the base intersect the roof sheet ribs.

    3. Using the base as a template, mark and drill the 11/32 diameter mounting holes.

    4. Apply (2) two beads of butyl sealant or mastic sealant as shown, between the Goose Neck Vent base and roof sheet. Leave a 1 gap at the lower side of the outside bead.

    5. Assemble Goose Neck Vent to roof sheet using 5/16 x 3/4 hex bin bolts and nuts. Tightenall bolts and check sealant along upper end of Goose Neck vent base for any gaps or pockets.Apply extra sealant as required.

    6. Peen up edge on inside of Goose Neck Vent to make a water tight seal. The lip should beapproximately 1 all the way around.

    7. Do Not Weld Goose neck vent to roof as rusting will result.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    51/83

    MANUAL CHIEF42 CB24 TITAN Page 50

    B. Low Profile Roof Vents

    1. Install the Screen and clips on the roof vent body using 5/16 x 3/4 bin bolts, nuts and flatwashers as shown below. The bolt heads should be on the outside of the vent with thewashers and nuts on the inside (against the screen).

    2. Locate the roof vent assembly on the roof panel (over the manhole) by aligning the holes inthe clips with the corresponding holes in the lower end of the roof panel.

    3. Mark the outline of the roof vent with a marking pencil so that the vent can be returned to thesame position after the caulking is applied.

    4. Remove the vent from the roof panel, turn upside down, and apply caulking to the mounting

    surface of the sides and top.

    5. At this time, install and tighten three 5/16 x 3/4 bin bolts and nuts in the holes directlyabove and below the manhole (in the roof panel to prevent leakage).

    6. Locate the roof vent on the roof panel in its original position and attach with the #14 x 3/4self-drilling screws provided. If a screw gun is not available, use the holes in the vent as aguide and drill 3/8 holes through the vent and roof panel, and attach with 5/16 x 3/4 bin

    bolts and nuts.

    7. Install 5/16 x 3/4 bin bolts and nuts in the clips and bottom of screen as shown in detail on

    previous page.

    8. Tighten all bolts securely.

    NOTE: Roofs with structural beams may require field installation of angles between beams at both top and bottom of manhole opening if 20 PSF or 30 PSF live loading is required.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    52/83

    Page 51 MANUAL CHIEF42 CB24 TITAN

    Section 5 Temperature Cables

    A. General Considerations

    Follow temperature cable manufacturers recommendations for installation of temperaturecables. Be sure to allow adequate clearance for sweep augers or other internal equipment.

    All temperature cables should be stabilized at floor level, to prevent cables from drifting outtowards the sidewall as bin is being filled. The use of light twine or monofilament linedouble wrapped and secured to a recessed anchor, is a common practice.

    Provide adequate sealant where temperature cable leads exit the bin.

    Support of temperature cables by any means other than Chief Industries recommended brackets may cause structural damage to the bin roof and will nullify the Chief Grain Bin

    Warranty.

    CB24 Temperature Cable

    BinSize

    Total #Temp.Cables

    Temp.Cables

    #/Radius

    #24 14 5/11'-2"

    9/28'-10"

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    53/83

    MANUAL CHIEF42 CB24 TITAN Page 52

    B. Temperature Cable Brackets

    (1) Install temperature cable bracket as shown below. Do not install more than onetemperature cable per roof beam. Temperature cable brackets for rafters are provided

    with all commercial bins, Chief recommends that they are installed on rafters if temperature cables are being install at time of erection or not.

    (2) Attach temperature cables to rafters per temperature cable manufactures instructions

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    54/83

    Page 53 MANUAL CHIEF42 CB24 TITAN

    #24 Temperature Cable Layout

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    55/83

    MANUAL CHIEF42 CB24 TITAN Page 54

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 148 11 12 12 8 11 12 8 11 129 10 9 10 12 12 9 10 12

    10 10 12 12 10 10 10 10 12 1211 9 10 10 11 9

    12 9 10 10

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 148 11 12 8 11 12 8 11 129 10 12 9 10 12 9 10 12

    10 10 12 10 10 12 10 10 1211 9 10 10 11 9 10 11 9 1012 9 12 9 10 10 12 9 1013 8 8 8 13 8 13 8 8 8

    14 8 8 8 14 815 1313 1010 1010

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 148 11 12 8 11 12 8 11 12

    9 10 12 9 10 12 9 10 1210 10 12 10 10 12 10 10 1211 9 10 11 9 10 11 9 1012 9 10 12 9 10 12 9 1013 8 8 13 8 8 13 8 814 8 8 8 14 8 8 14 8 815 1313 15 1313 1010 1010 15 1313 101016 1313 1010 1010 16 1313 16 1313 1010 1010

    17 1313 1010 1010 17 131318 1313 1010 1010

    CB24-12Stiffeners

    CB24-13 CB24-14 CB24-15

    Stiffeners StiffenersCB24-11CB24-10

    Stiffeners Stiffeners Stiffeners

    CB24-16 CB24-17 CB24-18Stiffeners Stiffeners Stiffeners

    Section 6 Sidewall Sheet and Stiffener Gauge Chart

    Note: All Sidewall and Stiffener gauges in the charts below are for standard 2 stiffened bins(Unless noted). If bins are designed for High Load/Unload rates, concrete pits or SeismicConditions, Contact Chief Industries, Inc. for gauge chart needed.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    56/83

    Page 55 MANUAL CHIEF42 CB24 TITAN

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 148 11 12 8 11 12 8 11 129 10 12 9 10 12 9 10 12

    10 10 12 10 10 12 10 10 1211 9 10 11 9 10 11 9 1012 9 10 12 9 10 12 9 1013 8 8 13 8 8 13 8 814 8 8 14 8 8 14 8 815 1313 1010 15 1313 1010 15 1313 101016 1313 1010 16 1313 1010 16 1313 101017 1313 1010 1010 17 1313 1010 17 1313 1010

    18 1313 18 1313 1010 1010 18 1313 101019 1212 1010 1010 19 1212 19 1212 1010 1010

    20 1212 88 88 20 121221 1212 88 88

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 148 11 12 8 11 12 8 11 129 10 12 9 10 12 9 10 12

    10 10 12 10 10 12 10 10 1211 9 10 11 9 10 11 9 1012 9 10 12 9 10 12 9 1013 8 8 13 8 8 13 8 814 8 8 14 8 8 14 8 815 1313 1010 15 1313 1010 15 1313 101016 1313 1010 16 1313 1010 16 1313 1010

    17 1313 1010 17 1313 1010 17 1313 101018 1313 1010 18 1313 1010 18 1313 101019 1212 1010 19 1212 1010 19 1212 101020 1212 88 88 20 1212 88 20 1212 8821 1212 21 1212 88 88 21 1212 8822 1212 101010 101010 22 1212 22 1212 101010 101010

    23 1212 101010 101010 23 121224 1212 101010 101010

    CB24-19 CB24-20 CB24-21Stiffeners Stiffeners Stiffeners

    CB24-22 CB24-23 CB24-24Stiffeners Stiffeners Stiffeners

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    57/83

    MANUAL CHIEF42 CB24 TITAN Page 56

    Ring SWS Ring SWS Ring SWS1 14 18 1 14 18 1 14 182 14 18 2 14 18 2 14 183 14 18 3 14 18 3 14 184 13 18 4 13 18 4 13 185 13 16 5 13 16 5 13 166 12 14 6 12 14 6 12 147 11 14 7 11 14 7 11 14

    8 11 12 8 11 12 8 11 129 10 12 9 10 12 9 10 12

    10 10 12 10 10 12 10 10 1211 9 10 11 9 10 11 9 1012 9 10 12 9 10 12 9 1013 8 8 13 8 8 13 8 814 8 8 14 8 8 14 8 815 1313 1010 15 1313 1010 15 1313 101016 1313 1010 16 1313 1010 16 1313 101017 1313 1010 17 1313 1010 17 1313 101018 1313 1010 18 1313 1010 18 1313 101019 1212 1010 19 1212 1010 19 1212 101020 1212 88 20 1212 88 20 1212 8821 1212 88 21 1212 88 21 1212 8822 1212 101010 22 1212 101010 22 1212 10101023 1212 101010 101010 23 1212 101010 23 1212 10101024 1212 24 1212 101010 101010 24 1212 10101025 1212 888 888 25 1212 25 1212 888 888

    26 1212 888 888 26 121227 1111 888 888

    Ring SWS1 14 182 14 183 14 184 13 185 13 166 12 14

    7 11 148 11 129 10 12

    10 10 1211 9 1012 9 1013 8 814 8 815 1313 101016 1313 101017 1313 101018 1313 101019 1212 101020 1212 8821 1212 8822 1212 10101023 1212 10101024 1212 10101025 1212 88826 1212 888 88827 111128 1111 888 888

    StiffenersCB24-25 CB24-26 CB24-27

    CB24-28Stiffeners

    Stiffeners Stiffeners

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    58/83

    Page 57 MANUAL CHIEF42 CB24 TITAN

    Sidewall Sheet Gauge Color 20 White18 Orange17 Light Blue16 Green14 Yellow

    14 Transition Yellow/Black13 Brown12 Dark Blue11 Pink10 Black9 Light Green8 Red

    Note: Sidewall Sheets for Top Ring are alsocolor coded with GOLD

    Section 7 Sidewall Erection

    A. Sidewall Sheets and Stiffeners

    NOTE: All sheets must be installed with color code right side down as shown below. Check theedges of the sheet for traces of the shop color code. The shop color code is always located on the

    bottom edge of the sheet. The color codes and their corresponding gauges are listed in the table below.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    59/83

    MANUAL CHIEF42 CB24 TITAN Page 58

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    60/83

    Page 59 MANUAL CHIEF42 CB24 TITAN

    NOTE: Proper Bolting Sequence Must Be Followed At All Times.

    (1) Tighten bolts in top 2 rings and top stiffeners.

    (2) Select sheets of the proper gauge for the 3rd ring of the bin. Select proper gauge and

    length of stiffeners.

    (3) Install stiffener splice plates, to both ends of stiffeners with (2) 7/16 x 1-1/4 BinBolts and whiz flange nuts per splice before securing the stiffener to the bin. Note: Ontop stiffeners, splice plate is only required on the bottom end of the stiffener.

    (3) Wipe excess oil from ends of the sheets and apply caulking as shown below

    (4) Loosely assemble 3 rd ring

    (5) Loosely install stiffeners of the proper gauge to the exterior of the bin with 7/16 bin bolts. Stiffener bolts are always placed with heads inside the bin. Using largealignment punch, force stiffener up so that splices are tightly compressed. Tighten (4)four bolts in 3 rd ring to keep stiffeners compressed. Loosely install the (2) 7/16 x 1-1/4 bolts connecting the stiffener splices to the stiffener splice plate above.

    Note:Blocks may be used to place under the stiffener splices to compress the stiffener splices.

    Note:Install bolts on sidewall sheets seam that are in the center of stiffener holes before installingnext stiffener.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    61/83

    MANUAL CHIEF42 CB24 TITAN Page 60

    (6) Lower the bin on to the foundation. This will force the 2 ring stiffeners in 2 nd and 3 rd ring up to splices.

    (7) Tighten stiffeners to sheets and stiffener splice to stiffener splice bolts.

    (8) Tighten bolts in vertical seams in 3 nd ring.

    (9) Tighten bolts in horizontal seams between 2 nd and 3 rd ring beginning at center of sheetand working both ways.

    (10) Add ladder sections as required (See separate Ladder Manual)

    (11) Repeat steps 1 thru 10 to add 4 th ring and each additional ring. Proper boltingsequence must be followed at all times to assure proper assembly.

    NOTE: Use 7/16x1 1/4 bin bolts at bottom sidelap of transition sheets. Use 5/16x3/4 bin bolts at the top sidelap at vertical seams of transition sheet.

    NOTE: All bins have all 2 ring bottom stiffeners at the bottom, a 1 ring stiffener must beplaced at every other stiffener line in the 3 rd ring.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    62/83

    Page 61 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    63/83

    MANUAL CHIEF42 CB24 TITAN Page 62

    B. Laminated Sheet Installation

    (1). All rings, which require laminated sheets (indicated in the sheet and stiffener charts)must be installed with the endlaps lapped as shown in the endlap detail below.

    (2). Select the proper sheet gauge for each ring of the bin as indicated in the stiffener andgauge chart.

    Laminated Sheet Endlap

    (3). Lap the bin sheets so that the outside ring of sheets follow this sequence: The right end of each sheet is always on the outside of the bin and the left end is always on the inside(looking from the outside). Refer to the endlap detail.

    NOTE : This sequence is the same as the single sheet sequence.

    (4). Lap the inner ring of the bin sheet so that they follow the same lapping sequence as theoutside ring of sheets. Refer to the endlap detail for lapping sequence.

    (5). Follow the bolt installation procedure for bin sheet endlaps and sidelaps.

    (6). Install stiffeners as outlined.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    64/83

    Page 63 MANUAL CHIEF42 CB24 TITAN

    C. Base Angle Detail

    (1) Bolt the base angle to the bottom of the bottom sheet as shown, with either 5/16 x 3/4 witha 3/8 flat washer between the whiz nut and the base angle or 7/16 bin bolts.

    (2) Seal base angle to concrete, using plastic cement or tar sealant. ( NOTE : Sealant not supplied

    by Chief Industries, Inc.)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    65/83

    MANUAL CHIEF42 CB24 TITAN Page 64

    D. Titan One Ring Door

    1. Place expandable foam around edges of frames as shown below.

    2. Bolt the inner and outer frame to the bin sidewall with 7/16 x 3 bin bolts, making sure toonly place bolts in the holes shown in the detail below. The top eyebrow on the outer frame is to

    be placed behind the sheet above the door. The bottom eyebrow is to be placed on the outside of the sheet below the door. Bolt the inner and outer frames together with (10) 7/16 x 2 bin boltswith whiz flange nuts.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    66/83

    Page 65 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    67/83

    MANUAL CHIEF42 CB24 TITAN Page 66

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    68/83

    Page 67 MANUAL CHIEF42 CB24 TITAN

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    69/83

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    70/83

    Page 69 MANUAL CHIEF42 CB24 TITAN

    Bin Stiffener anchors allow up to 3 anchor bolts to be used at each anchor location. There are (2)1 diameter and (1) 1-1/2 diameter holes in each Bin Stiffener Anchor.

    There are several different combinations that Chief Industries Recommends to anchor the bin tothe foundation.

    1. One 1-1/4 x 12 anchor bolt may be used in the 1-1/2 diameter hole, if this is done theanchor bolt must be pre set in the concrete

    2. Two 3/4 x 12 anchor bolts may be used in the two 1 diameter holes. If this is done, at leastone of the two anchor bolts must be pre set in the concrete the second may be drilled in. (It isrecommended that both anchor bolts are pre-set.)

    If anchor bolts are not pre set as stated above, and the anchor bolt radius is not held, the binswarranty may be nullified .

    Larger anchor bolts or the use of all three anchor bolts may be required if seismic conditions or high wind loads exist. Chief Industries should be consulted for proper anchor bolts to be used.

    All anchor bolts must project a minimum of 2 above the concrete floor.

    All anchor bolts, nuts and washers shall conform to ASTM A307 (specification for carbon steelthreaded standard fasteners) unless otherwise noted. Anchor bolts, nuts and washers are not

    provided by Chief Industries, Inc.

    IMPORTANT: If expansion type anchor bolts are used to replace damaged anchor bolts, the bolt radius circle must be checked at replacement locations so that the bin isround when anchored. Chief Industries recommends using wedge anchors that meet10,000 LB Pull-Out and 7,500 LB shear criteria.

    Anchor Bolt Anchor Bolt Typical Chord Typical ChordRadius Diameter (2 Stiffened Bins) (3 Stiffened Bins)

    CB12 18'-10 1/2" 37'-8 15/16" 4'-11 1/8" 3'-3 1/2"CB13 20'-5" 40'-10 1/16" 4'-11 1/16" 3'-3 7/16"CB14 21'-11 9/16" 43'-11 3/16" 4'-11" 3'-3 3/8"CB16 25'-0 11/16" 50'-1 7/16" 4'-10 15/16" 3'-3 5/16"CB18 28'-2 1/8" 56'-4 3/16" 4'-10 15/16" 3'-3 5/16"CB20 31'-3 1/4" 62'-6 1/2" 4'-10 7/8" 3'-3 1/4"

    CB22 34'-4 7/16" 68'-8 13/16" 4'-10 13/16" 3'-3 1/4"CB24 37'-5 9/16" 74'-11 1/8" 4'-10 13/16" 3'-3 1/4"CB26 40'-6 11/16" 81'-1 7/16" 4'-10 3/4" 3'-3 3/16"CB30 46'-9" 93'-6 1/16" 4'-10 3/4" 3'-3 3/16"CB34 52'-11 5/16" 105'-10 5/8" 4'-10 11/16" 3'-3 1/8"

    Note: All dimensions are to center anchor bolt. All dimensions are for standard NON-Seismic Bins

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    71/83

    MANUAL CHIEF42 CB24 TITAN Page 70

    F. Transition Stiffeners

    Aeration Trough Transition Stiffener Installations (for flush-floor aeration systems with two or more fans)

    (1) The formed concrete dimensions and the anchor bolt placement are important for the correctinstallation of the transition stiffeners. When forming the concrete, the aeration troughsshould be located as specified in Chiefs aeration layout. The anchor bolt locations for the binneed to be oriented to make sure that the number of anchors over the aeration trough isminimized. When installing the anchor bolts, the bolt radius and bolt chord must be correctand they must also be placed according to the details below.

    IMPORTANT NOTE: Do NOT install the anchor bolts inside the aeration trench at thistime.

    2 Stiffener/Sheet Bins 3 Stiffener/Sheet Bins

    (2) When the bin is erected and located correctly (as illustrated above), insert the transition in theaeration trough. Using the hole in the anchor bracket as a guide, drill a 3/4 hole through thetop of the transition. Slide the transition stiffener inside the transition and line it up with the

    previously drilled hole. Loosely install the 5/8 x 1-1/2 A325 bolt. Rotate the transitionstiffener body so that it is centered under the bin wall anchor. See installation detail thatfollows.

    (3) The transition stiffener must be attached to the foundation with two (2) 5/8 x 6 expansion-type anchor bolts. The holes for these anchor bolts should now be located. With an acetylenetorch, cut two holes in the bottom of the transition using the holes in the transition stiffener

    base plate as guides. (This would mark the location of the anchor bolts in the concrete aswell.)

    (4) Remove the transition stiffener and the transition.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    72/83

    Page 71 MANUAL CHIEF42 CB24 TITAN

    Aeration Trough Transition Stiffener Installation Detail

    (5) Locate the two anchor bolt locations (from cutting the holes in the bottom of the transition).Set the transition stiffener over the locations to insure that the holes line up. Also, check toinsure that the transition stiffener is directly under and in line with the anchor. Makeadjustments if necessary. Drill the two holes for the 5/8 x 6 anchor bolts.

    IMPORTANT NOTE: Do NOT install anchor bolts at this time.

    (6) Enlarge the two holes in the bottom of the transition to 1 diameter.

    (7) Reinstall the transition and slide the transition stiffener into position Loosely install the 5/8x 1-1/2 A325 bolt and rectangular washers at the anchor bracket location. The two 5/8 x 6expansion-type anchor bolts should now be installed and securely tightened the 5/8 bolts atthe anchor bracket. Caulking should be applied to seal the transition.

    IMPORTANT NOTE: Transition stiffeners support the bin anchors. The transition must also be supported inside the bin. See Chiefs aeration layout for supporting the transition.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    73/83

    MANUAL CHIEF42 CB24 TITAN Page 72

    G. Stiffener Upgrades for Goal Post (Optional)

    When a goal post is being attached to bin, an extra layer of stiffeners are laminated over standardstiffeners at goal post location from eave to base, as been is being erected.

    Chief recommends that goal post be uniformly attached to at least the top 2 rings of tank at thestiffeners from bottom of 2 nd ring to top of 1 st ring.

    Note: Listed below are the maximum loads that can be applied to upgraded stiffener columns.16GA stiffener upgrade = 5,000 lbs. per column14GA stiffener upgrade = 6,000 lbs. per column

    2 stiffeners per sidewall

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    74/83

    Page 73 MANUAL CHIEF42 CB24 TITAN

    2 stiffeners per sidewall sheet

    3 stiffeners per sidewall sheet

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    75/83

    MANUAL CHIEF42 CB24 TITAN Page 74

    Section 8 Wind Rings

    A. Wind Rings

    Consult the Chief catalog for the quantity of wind rings required for your bin. The quantity of wind rings depends on the size of the bin and the application of any accessories (such as asidedraw system). For quantities and placement of wind rings required when a Sidedraw Systemis installed on the bin, refer to the charts in this manual. The wind rings will be attached to thesidewall using one bracket per stiffener spaced 58-5/16 apart (38-7/8 on 3 stiffened bins). The

    brackets are specially formed and prepunched to bolt directly to the sidewall stiffener holes. Thewind ring segments will be joined together using a bolted coupler.

    NOTE: All wind ring segments are 248 long, and may need field cut to keep couplers in between brackets. Always cut segments on end opposite end with pre-punched hole.

    (1) Working from outside the bin, determine the proper location for installation of the first windring.

    (2) Bolt the first wind ring bracket to the sidewall stiffener holes as shown in Detail below using(2) of the stiffener attachment bolts and nuts with bolt heads on the inside. (Note: Wind ring

    brackets may be installed below the endcaps if desired to allow for clearance of ladders and platforms.)

    ASSEMBLYDETAIL OFWIND RINGBRACKET

    (3) Move right to the next stiffener and repeat step 2.

    (4) When 4 wind ring brackets have been installed, slide the first ring segment through the four brackets leaving approximately 29 inches of the segment projection past the last bracket.Insert coupler over end of wind ring segment, and attach with 5/8 x 4 bolt.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    76/83

    Page 75 MANUAL CHIEF42 CB24 TITAN

    (5) Repeat step 2 through 3 until four more brackets have been installed.

    (6) Slide another connector into the end of the previously installed ring segment. Slide the nextring segment through the four brackets and butt it firmly against the previous segment.

    (7) Repeat steps 5 and 6 until only one ring segment remains to be installed. Installing thefinal ring segment requires special procedures.

    (8) Attach coupler to end of last wind ring segment.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    77/83

    MANUAL CHIEF42 CB24 TITAN Page 76

    (9) Slide coupler attach to segment over end of 1 st segment so segments are bolted together.

    (10) Field cut other end of segment so segments are flush.

    (11) Slide last coupler and brackets over segments.

    (12) Hold segments flush and slide coupler over joint and attach with 5/8 x 4 bolts. Attach brackets to stiffeners

    (15) Check to see that all bolts in the complete wind ring are tight

    (16) Repeat steps 1 through 13 for the remaining wind rings.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    78/83

    Page 77 MANUAL CHIEF42 CB24 TITAN

    Titan Commercial Bins 5 thru 15 Rings Tall

    Drawing is for illustrative purpose only. The quantity and location of wind rings required

    depends on the application of any accessories (EX: sidedraw system). On Standard Bins placewind rings as shown in figure above. Refer to chart on following page for qty. of wind ringsrequired on standard tanks. (Ex. If only one wind ring is required place on 2 nd ring from eave, if 2 reqd place on 2 nd and 5 th ring, if 3 reqd place on 2 nd, 5h, and 8 th and so on)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    79/83

    MANUAL CHIEF42 CB24 TITAN Page 78

    Titan Commercial Bins 16 thru 30 Rings Tall

    Drawing is for illustrative purpose only. The quantity and location of wind rings requireddepends on the application of any accessories (EX: sidedraw system). On Standard Bins placewind rings as shown in figure above. Refer to chart on following page for qty. of wind rings onstandard tanks. (Ex. If only one wind ring is required place on 3 rd ring from eave, if 2 reqd placeon 3 rd and 6 th ring, if 3 reqd place on 3 rd, 6 th, and 9 th, and so on)

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    80/83

    Page 79 MANUAL CHIEF42 CB24 TITAN

    BINHEIGHT 18 20 22 24 26 30 34

    8 0 1 1 1 1 1 19 0 1 1 1 2 2 210 1 1 1 1 2 2 211 1 1 2 2 2 2 212 1 1 2 2 2 2 213 1 1 2 2 2 2 214 1 1 2 2 2 2 315 1 1 2 2 2 2 316 1 1 2 2 2 2 317 1 2 2 2 2 2 318 2 2 2 2 2 2 319 2 2 2 2 2 2 320 2 2 2 2 3 3 321 2 2 2 3 3 3 322 2 2 2 3 3 3 423 2 2 2 3 3 3 424 2 2 2 3 3 3 425 2 2 3 3 3 4 426 2 2 3 3 3 4 527 2 3 3 3 3 5 528 3 3 3 3 3 5 NA29 3 3 3 4 3 5 NA30 3 3 3 4 3 5 NA

    BIN SERIES

    Wind rings required on standard Commercial Titan Bins

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    81/83

    MANUAL CHIEF42 CB24 TITAN Page 80

    Section 9 Miscellaneous

    A. Maintenance Instructions

    ROOF: Annual inspection of the roof structure should be made to be sure there isno holes in the roof panels and all connections are water tight. If leaksshould occur apply weatherproof caulk in the area of concern.

    SIDEWALL: Sidewall inspection must also be conducted at least annually. Should leaksoccur apply caulk to area of concern.

    Should spoilage occur, thoroughly clean surfaces. If oxidation is present,remove oxidation and apply corrosive resistance paint.

    BASE: Inspect base as often as possible for spoilage, as this is a direct indicationof excess moisture. If spoilage is present, thoroughly clean surface. If oxidation is present, remove oxidation and apply corrosive resistance

    paint. After paint has dried, apply base sealer to effected area.

    DOORS: Inspect doors and manholes as often as possible to be sure proper seal ismaintained.

    DECALS: Be sure all warning decals are installed in proper locations. Replace alldamaged or unreadable warning decals.

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    82/83

    Page 81 MANUAL CHIEF42 CB24 TITAN

    B. Comment Sheet

    Dear Erector:

    In an effort to better serve and please you, list below any problems you may have encountered

    with your product or the erection procedures in this manual. Also list any suggestions you mayhave for improvements.

    Erection Manual Problems: ____________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ __________________________________________________

    Recommended Solutions: ____________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ __________________________________________________

    Product Problems: ____________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ __________________________________________________

    Product Improvements Suggestions: ____________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ _____________________________________________________________________________________ __________________________________________________

    Thank you for your time and reason. All responses will be reviewed by our engineering staff.

    Please detach this page and send to: Agri Engineering DepartmentChief Industries, Inc.P.O. Box 848Kearney, NE 68848-0848

  • 7/28/2019 CB24_-_30_Degree_J-Rib_Manual_-_347862

    83/83