+ All Categories
Home > Documents > CBS IG Battery Storage Process Roadmap 950px RGB line diagram entailing connections of system...

CBS IG Battery Storage Process Roadmap 950px RGB line diagram entailing connections of system...

Date post: 18-Mar-2018
Category:
Upload: donhi
View: 218 times
Download: 2 times
Share this document with a friend
1
2. Initial site visit If this is required, it will be for a viability sense check. 1. Data gathering Desktop analysis, half hourly energy data modelling, identifying potential opportunities. 4. Top level proposal Build and offer a high level proposal outlining the site/customer specific developed project with the expected revenues. 6. G83/G59 application The system requires approval from DNO to enable grid connection, to do so a formal application process is followed beginning with an ENA application form detailing the system specifications. 8. Detailed electrical design proposal Single line diagram entailing connections of system electrical components, calculations required to ensure correct cable and electrical protection sizes. 7. Site survey Site restrictions, obstructions and general terrain issues are identified. Physical site measurements are taken for use in detailed design stage, electrical point of connection is verified. 8. Detailed mechanical & structural design proposal Site Layout detailing plan view of equipment i.e. transformer substation, battery, inverter, etc. showing connection points, cable routes and trenches if required. 5. Planning application An assessment to determine the suitability of the potential site for the battery storage system. In general, the systems footprint, height, noise emission and proximity to nearby residential areas are taken into consideration. 3. Options assessment Analyse energy consumption, perform walkthrough site survey (if required) and develop the best fit DE project around the site requirements and limitations. PROCESS ROAD MAP Battery Storage Scoping Solution design & development Implementation Optimisation & Management Bidding – revenue back to customer Dispatch Bid assets into the market Iterate & revise run strategy 10. Design modifications To reflect new measurements taken from the additional site survey. Final construction drawings are issued. 12. Electrical installation LV and HV cables laid, connected and buried if required, all relevant protection installed, interposing transformer oſten necessary to match AC inverter output to relevant connection voltage. 11. Civil works Clearing of site, erecting safety fences, set up access and welfare facilities. Foundations are prepared, cable trenches dug out (if required) and permanent site security measures are installed. 9. Additional site survey Undertaken when access restrictions occur during the initial survey. Further measurements are taken and available capacity at point of connection is confirmed. 14. Electrical inspections & EESS commissioning tests Commissioning process includes, testing system to BS7671 requirements, inspection and tests to comply with DNO G83/G59 Engineering recommendations, commissioning tests to conform with manufacturers requirements. 13. Site acceptance tests Performance tests to measure energy capacity, power, round trip efficiency and basic equipment function tests involving start stop tests and operating cycle tests. © 2017 Centrica plc. Registered office: Millstream, Maidenhead Road, Windsor, Berkshire. SL4 5GD. Registered in England & Wales No 3033654 IG-2017-1 1 2 5 10 13 3 4 8 9 11 12 14 7 6 Contract NDA PDA To discover more, visit centricabusinesssolutions.com
Transcript

2. Initial site visitIf this is required, it will be for a viability sense check.

1. Data gatheringDesktop analysis, half hourly energy data modelling, identifying potential opportunities.

4. Top level proposalBuild and o�er a high level proposal outlining the site/customer specific developed project with the expected revenues.

6. G83/G59 applicationThe system requires approval from DNO to enable grid connection, to do so a formal application process is followed beginning with an ENA application form detailing the system specifications.

8. Detailed electricaldesign proposalSingle line diagram entailing connections of system electrical components, calculations required to ensure correct cable and electrical protection sizes.

7. Site surveySite restrictions, obstructions and general terrain issues are identified. Physical site measurements are taken for use in detailed design stage, electrical point of connection is verified.

8. Detailed mechanical& structuraldesign proposalSite Layout detailing plan view of equipment i.e. transformer substation, battery, inverter, etc. showing connection points, cable routes and trenches if required.

5. Planning applicationAn assessment to determine the suitability of the potential site for the battery storage system. In general, the systems footprint, height, noise emission and proximity to nearby residential areas are taken into consideration.

3. Options assessmentAnalyse energy consumption, perform walkthrough site survey (if required) and develop the best fit DE project around the site requirements and limitations.

PROCESS ROAD MAP

Battery Storage

Scoping

Solution design & development

Implementation

Optimisation& Management Bidding – revenue

back to customer

Dispatch

Bid assets into the marketIterate & revise

run strategy

10. Design modificationsTo reflect new measurements taken from the additional site survey. Final construction drawings are issued.

12. Electrical installationLV and HV cables laid, connected and buried if required, all relevant protection installed, interposing transformer o�en necessary to match AC inverter output to relevant connection voltage.

11. Civil worksClearing of site, erecting safety fences, set up access and welfare facilities. Foundations are prepared, cable trenches dug out (if required) and permanent site security measures are installed.

9. Additional site surveyUndertaken when access restrictions occur during the initial survey. Further measurements are taken and available capacity at point of connection is confirmed.

14. Electrical inspections& EESS commissioning testsCommissioning process includes, testing system to BS7671 requirements, inspection and tests to comply with DNO G83/G59 Engineering recommendations, commissioning tests to conform with manufacturers requirements.

13. Site acceptance testsPerformance tests to measure energy capacity, power, round trip e�ciency and basic equipment function tests involving start stop tests and operating cycle tests.

© 2017 Centrica plc. Registered o�ce: Millstream, Maidenhead Road, Windsor, Berkshire. SL4 5GD. Registered in England & Wales No 3033654 IG-2017-1

1

2

5

10

13

3

4

8

9

11

12

14

7

6

Contract

NDA

PDA

To discover more, visitcentricabusinesssolutions.com

Recommended