+ All Categories
Home > Documents > CCFC Regional Workshops Community College … · CCFC Regional Workshops . Community College...

CCFC Regional Workshops Community College … · CCFC Regional Workshops . Community College...

Date post: 20-Aug-2018
Category:
Upload: trantram
View: 216 times
Download: 0 times
Share this document with a friend
46
CCFC Regional Workshops Community College Construction Delivery Methods: Options, Obligations, and Opportunities BAY AREA Friday, May 12, 2017 9:00 am to 2:30 pm XL Construction Office – Training Room 851 Buckeye Court Milpitas, CA 95035 AGENDA 9:00 am Welcome and Opening Remarks 9:15 am CCFC Update: 2017-18 State Capital Outlay Funding Rebekah Cearley, Community College Facility Coalition 9:30 am Delivery Methods Primer The Legal Perspective: Delivery Method Authorization and Legal Issues Mark W. Kelley, Dannis Woliver Kelley The Construction Manager’s Perspective: Delivery Method Benefits and Considerations Steve Winslow, XL Construction Monet Crowley, XL Construction Jack Herbert, Swinerton Management and Consulting The District Perspective: Selecting the Right Delivery Method Leigh Sata, Santa Rosa Junior College The Architect’s Perspective: Encouraging Collaborative Project Delivery Karen Kuklin, Gensler 10:15 am Break 10:30 am Delivery Methods Primer, Continued 11:30 am The Chancellor’s Office Perspective: State Funding and Delivery Methods Harold Flood, California Community Colleges Chancellor’s Office 12:00 pm Lunch 1:00 pm The Evolution Toward Progressive Design-Build at San Mateo County CCD: The Skyline Environmental Services Building Project Case Study Chris Strugar-Fritsch, San Mateo County Community College District Erin Allred, XL Construction Craig Ivancovich, DES Architects + Engineers Tay Othman, DES Architects + Engineers 2:15 pm Q&A 2:30 pm Evaluations & Adjourn
Transcript

CCFC Regional Workshops

Community College Construction Delivery Methods: Options, Obligations, and Opportunities

BAY AREA

Friday, May 12, 2017 9:00 am to 2:30 pm

XL Construction Office – Training Room 851 Buckeye Court Milpitas, CA 95035

AGENDA

9:00 am Welcome and Opening Remarks 9:15 am CCFC Update: 2017-18 State Capital Outlay Funding Rebekah Cearley, Community College Facility Coalition 9:30 am Delivery Methods Primer

• The Legal Perspective: Delivery Method Authorization and Legal Issues Mark W. Kelley, Dannis Woliver Kelley

• The Construction Manager’s Perspective: Delivery Method Benefits and Considerations Steve Winslow, XL Construction Monet Crowley, XL Construction Jack Herbert, Swinerton Management and Consulting

• The District Perspective: Selecting the Right Delivery Method Leigh Sata, Santa Rosa Junior College

• The Architect’s Perspective: Encouraging Collaborative Project Delivery Karen Kuklin, Gensler

10:15 am Break 10:30 am Delivery Methods Primer, Continued 11:30 am The Chancellor’s Office Perspective: State Funding and Delivery Methods Harold Flood, California Community Colleges Chancellor’s Office 12:00 pm Lunch 1:00 pm The Evolution Toward Progressive Design-Build at San Mateo County CCD: The Skyline Environmental Services Building Project Case Study

Chris Strugar-Fritsch, San Mateo County Community College District Erin Allred, XL Construction Craig Ivancovich, DES Architects + Engineers Tay Othman, DES Architects + Engineers

2:15 pm Q&A 2:30 pm Evaluations & Adjourn

CCFC Regional Workshop

Community College Construction Delivery Methods:

Options, Obligations and Opportunities

Friday, May 12, 2017 9:00 a.m. – 2:30 p.m.

Bay Area

COMMUNITY COLLEGE FACILITY COALITION

1303 J Street, Suite 520 ♦ Sacramento, CA 95814 ♦ Phone (916) 446-3042 ♦ Fax (916) 441-3893 ♦ www.caccfc.org

CCFC Update: 2017-18 State Capital Outlay Funding

Rebekah Cearley Community College Facility Coalition

5/12/2017

1

Rebekah CearleyCommunity College Facility Coalition

Passed with 55.2% of the vote – 7.5 million “yes” votes

$10 million Yes on 51 campaign◦ Direct voter contact made a difference – mailers, social

media, television Provides:◦ $2 billion for community college facilities◦ $7 billion for K-12 facilities

Vast, bipartisan support◦ Both California Democratic & Republican parties

endorsed◦ Governor says he will “respect the will of the people” in

implementing Prop 51

5/12/2017

2

Community college capital outlay projects funded annually in state budget

For 2017-18 – Governor proposes to fund five new projects◦ Pasadena City College – Armen Sarafain Building Seismic

Replacement◦ San Francisco CCD – Alemany Center Seismic Upgrade◦ San Francisco CCD – Ocean Campus Utility Replacement◦ North Orange CCD – Fullerton College – Business and

Humanities Buildings Modernization◦ El Camino CCD – Compton Center – Instructional Building 2

Replacement All are Health & Safety – 3 Category A, 2 Category C Worth $7.4 million in 2017-18 – preliminary plans

only◦ Total funding $182 million

Contrast budget proposal to Board of Governor’s action

2017-18 Spending Plan – Approved by BOG May 2016

Spending Plan prioritization:◦ “Least Cost to State”◦ Health & Safety projects – up to 50% available funds

The need is great◦ $28 billion (state + local) – 2017-18 Five-Year

Capital Outlay Plan $10.6 B – new facilities $17.4 B – modernization

5/12/2017

3

No changes proposed by Administration for community college capital outlay program

Legislative Analyst’s Office agrees that the proposal is insufficient to meet need◦ Would take 11 years to administer funds

Chancellor’s Office asking to fund all 29 projects◦ Will defer unfunded projects to 2018-19◦ Not currently accepting FPPs for 2019-20

CCFC legislative advocacy◦ Budget subcommittee process

Department of Finance accepted additional justification for “health and safety” projects◦ Information submitted for 11 projects

Four projects added for 17-18 by April Letter:◦ Allan Hancock Fine Arts Complex◦ Long Beach Liberal Arts Campus Multi-Disciplinary

Facility Replacement◦ Santa Monica College Math/Science Addition◦ Orange Coast College Language Arts/Social

Sciences Building Worth $4.3 m planning◦ Total funding $121.4 m

5/12/2017

4

CCFC is urging funding for all 29 projects in 2017-18 budget◦ Proposal does not honor BOG process and creates

planning challenges Negotiations occurring through budget process If your district has an “unfunded project”:◦ Contact your state Senator and Assembly Member to

request funding in the 2017-18 budget Initial signaling from Legislative members is

positive but we need to build pressure! Deferral of Prop 51 implementation does not

meet the will of voters

DIR proposal to increase compliance with the public works prevailing wage monitoring program (SB 854, 2014)

SB 854 created new contractor registration and awarding body noticing requirements (PWC-100)

New budget proposal via trailer bill language ◦ Goal of increasing contractor registrations to address

program’s structural imbalance◦ Uses “carrot and stick” approach

Budget requests additional positions:◦ 6 positions to educate awarding bodies ◦ 1 attorney to pursue debarments

5/12/2017

5

Carrot (Relief):◦ Small project exemption: raise threshold of applicability

from $1,000 to $15,000 for maintenance, $25,000 for construction

◦ Notice to DIR within 30 days of award (not 5) Stick (Compliance):◦ Creates new penalty for awarding bodies $100/day, up to $10,000

◦ Increases penalties for contractors and subs◦ An awarding agency with two violations in 12 months

loses state facility funding for one year Would be effective for work performed on/after

January 1, 2018

Proposal subject to review in budget process Stakeholders concerned penalties are overly

punitive (contractors, awarding agencies) Chair of Assembly Budget Subcommittee on

State Administration asked DIR and DOF to work with stakeholders over the next few months to address concerns

5/12/2017

6

Rebekah CearleyLegislative Advocate

Community College Facility [email protected]

(916) 446-3042

CCFC Regional Workshop

Community College Construction Delivery Methods:

Options, Obligations and Opportunities

Friday, May 12, 2017 9:00 a.m. – 2:30 p.m.

Bay Area

COMMUNITY COLLEGE FACILITY COALITION

1303 J Street, Suite 520 ♦ Sacramento, CA 95814 ♦ Phone (916) 446-3042 ♦ Fax (916) 441-3893 ♦ www.caccfc.org

Delivery Methods Primer

Mark W. Kelley

Dannis Woliver Kelley

Steve Winslow XL Construction

Monet Crowley XL Construction

Jack Herbert Swinerton Management &

Consulting

Leigh Sata Sonoma CCD

Karen Kuklin

Genlser

5/12/2017

1

Mark Kelley, Dannis Woliver KelleySteve Winslow, XL ConstructionMonet Crowley, XL ConstructionJack Herbert, Swinerton Management and ConsultingLeigh Sata, Santa Rosa Junior CollegeKaren Kuklin, Gensler

1

Legal Perspective: ◦ Mark Kelley, Dannis Woliver Kelley

The Industry GC/CM/Architect:◦ Steve Winslow, XL Construction◦ Monet Crowley, XL Construction◦ Jack Herbert, Swinerton◦ Karen Kuklin, Gensler

The District Perspective:◦ Leigh Sata, Santa Rosa Junior College

2

5/12/2017

2

District 2016Nov.Measure

Amount

LosAngelesCCD CC $3,300,000,000SanJose‐EvergreenCCD X $748,000,000DesertCCD CC $577,860,000KernCCD J $502,821,000MiraCosta CCD MM $455,000,000SouthwesternCCD Z $400,000,000AntelopeValleyCCD AV $350,000,000SantaMonicaCCD V $345,000,000GlendaleCCD GC $325,000,000Butte‐GlennCCD J $190,000,000Hartnell CCD T $167,000,000YubaCCD Q $33,565,000

TOTAL $7,394,246,000

3

4

Source: US Census Bureau 9/16, Saylor Consulting Group, Market Trends 2017 (dated March 2017)

5/12/2017

3

5

Continued low interest rates Wages up 3% two years in a row State funds and spending up State construction bond issuance up Office rents up 7.6% yoy Real estate market up 5.2% yoy Multi-year transportation bill passed in 2015 Promises of infrastructure spending boost Industry confidence

Source: Saylor Consulting Group, Market Trends 2017 (dated March 2017)

6

Source: EDD, California Labor Market Review, Saylor Consulting Group, Market Trends 2017 (dated March 2017)

5/12/2017

4

7

Source: SF Business Times Crane Watch, Saylor Consulting Group, Market Trends 2017 (dated March 2017)

8

In Design:◦ SFPUC Sewer System Improvement Program

Central Bayside--$500-800 MM BioSolids Digester--$1.2 Billion

◦ Ca. High Speed Rail--$4 Billion In Construction:◦ Bart Warm Springs/Berryessa--$2 B◦ Transbay Transit Center--$2 B◦ Folsom Dam--$500 MM◦ eBART & Highway 4 widening--$1 B◦ SF Muni Central Subway--$2.25 B

Source: Saylor Consulting Group, Market Trends 2017 (dated March 2017)

5/12/2017

5

9

Source: EDD, Saylor Consulting Group, Market Trends 2017 (dated March 2017)

10

It may be advisable to carry a 10% market factor for all projects bid in the Bay Area in 2017 to address the likely lack of competition.

BAY AREA 2017 – 5%2018 – 5%2019 – 4%

Source: Saylor Consulting Group, Market Trends 2017 (dated March 2017)

5/12/2017

6

CCD PROJECT DELIVERY OPTIONS

11

Publicly Bid:◦ Design-Bid-Build◦ Multiple-Prime Contracting

Negotiated, Non-Bid:◦ Lease-Leaseback◦ Design-Build

Hybrid:◦ Construction Management At Risk

12

5/12/2017

7

13

14

=Owner Team

District

Architect General Contractor

Subcontractors

ConstructionManager (Opt.)

14

5/12/2017

8

Advantages Disadvantages

Advantages DisadvantagesFamiliar and established way of delivering a project.

No early contractor involvement.

A/E of record works for District and represents owner.

Potential conflicts between general contractor and architect after construction begins.

Suitable for competitive bidding w/ lowest initial price.

Bids over budget are challenging to adjust to obtain cost reductions.

Could be adversarial.

Legal perspective Industry – GC / CM / Architect perspective District perspective

16

5/12/2017

9

=Owner Team

17

District

ConstructionManagerArchitect Trade Contractors

Disadvantages Construction

Advantages DisadvantagesTrade contractors are procured through competitive lowest responsible bidders.

Potential conflicts between contractor and architect after construction begins.

Avoids general contractor mark-up. Bids over budget are challenging to adjust to obtain cost reductions.

Potential overlaps or gaps in scopes of work.

Higher risks due to multiple contractors.

Difficult to coordinate and control schedule.

Additional work and risk for District.

5/12/2017

10

19

Legal perspective Industry – GC / CM / Architect perspective District perspective

20

5/12/2017

11

21

=Owner Team

District

ArchitectLLB Builder

Trade Contractors

ConstructionManager (Opt.)

21

22

Architect BuilderOwner

Owner lease to Builder

Owner makes tenant improvement payments

Lease expires (grey area)

Construction completion and lease payments begin

Construction startTime

Design

Input From LLB EntityConstruction

22

5/12/2017

12

K-12 (Ed. Code 17406):◦ 17406. (a) (1) Notwithstanding Section 17417, the

governing board of a school district, without advertising for bids, may let, for a minimum rental of one dollar ($1) a year…

CCDs (Ed. Code 81335):◦ 81335. The governing board of a community

college district may let, at a minimum rental of one dollar ($1) a year…

24

5/12/2017

13

Authorized by education code § 81335 Provides owners with flexibility and benefits that may not be possible with some of the other delivery methods.

LLB allows an owner to select a GC during the design/preconstruction phase through a “defined” qualification and fee based selection process.

All requirements for construction and/or public works are still applicable; i.e. prevailing wage, bonds, insurance, indemnification, field act compliance (seismic), and skilled workforce requirements.

25

CM

Advantages DisadvantagesA District may use Lease-Lease-Back to satisfy its need for financing the project.

Uncertainty for employing revised methodology (post Davis v. Fresno environment).

The District has flexibility on who controls the Architect.

Higher learning curve for delivery method.

The District may participate in selecting Developer-Contractor, and all the trade contractors and suppliers.

Solicitation of savings/cost can create costs savings.

5/12/2017

14

27

Legal perspective Industry – GC / CM / Architect perspective District perspective

=Owner Team

28

DistrictProgram Architect

Design-Build Entity(Architect + Contractor)

Trade contractors

5/12/2017

15

Advantages DisadvantagesMultiple packages provide greater opportunity for participation by local trade contractors.

No common standards for methodology.

Teamwork is promoted because general contractor and architect are on the same team.

Higher learning curve for delivery method.

Earlier knowledge of construction costs guaranteed during design.

Design risk shift to the Design-Build Entity (DBE).

Potential for faster delivery systems.

30

Legal perspective Industry – GC / CM / Architect perspective District perspective

5/12/2017

16

31

=Owner Team

32

ConstructionManagerArchitect Trade Contractors

District

5/12/2017

17

ConstructionManagerArchitect Trade Contractors

=Owner Team

33

District

SUB

DesignAdvantages Disadvantages

Advantages DisadvantagesPotential for faster delivery systems.

No common standards for methodology.

Mitigate material shortages and price escalation issues.

Higher learning curve for delivery method.

May bring construction input into design.

Confirm legal authorization to use this method.

May facilitate Value Engineering.

5/12/2017

18

35

Legal perspective Industry – GC / CM / Architect perspective District perspective

• Design-Bid-Build• Multi-Prime

Contracting• CM at-Risk

• Lease-Leaseback • Design-Build

36

5/12/2017

19

6

10

8

6

7

9

150 150

200

144

90

84

90

758

LLB

37

Q & A

CCFC Regional Workshop

Community College Construction Delivery Methods:

Options, Obligations and Opportunities

Friday, May 12, 2017 9:00 a.m. – 2:30 p.m.

Bay Area

COMMUNITY COLLEGE FACILITY COALITION

1303 J Street, Suite 520 ♦ Sacramento, CA 95814 ♦ Phone (916) 446-3042 ♦ Fax (916) 441-3893 ♦ www.caccfc.org

The Chancellor’s Office Perspective: State Funding and Delivery Methods

Harold Flood

California Community Colleges Chancellor’s Office

5/12/2017

1

Project Delivery MethodsProposition 51 and Beyond

Statewide Facility Need• Growth

• Modernization

Facilities Needs (2017/18 Five Year Plan) ASF COSTS New Facilities 8,501,000 $8,826,477,000Modernization 23,366,000 $11,279,991,000

Total 31,867,000 $20,106,468,000

5/12/2017

2

Proposition 51• November 2016 - Voters approve a $2 Billion bond to handle this

$20 Billion need

Proposed Governor’s Budget2017/18 Governor’s Budget

• $11.7 Million for 9 new start projects– Total state funding: $304 Million

2018/19 Governor’s Budget

• $ 61.9 Million (not submitted - preliminary estimate for 9 continuing and 20 new start projects)– Total state funding: $703 Million

5/12/2017

3

Delivery MethodsThe primary public sector construction delivery methods:

• Design-Bid-Build – Single prime– Multi-prime

• Design-Buildhttp://www.lao.ca.gov/2005/design_build/design_build_020305.pdfhttp://extranet.cccco.edu/Portals/1/CFFP/Facilities/Reference_Materials/Guidelines/C C_DB_Guidelines.dochttp://extranet.cccco.edu/Divisions/FinanceFacilities/FacilitiesPlanning/ReferenceMaterials.aspx

• Lease-Leaseback

Design-Bid-BuildDesign-Bid-Build (DBB) is the most frequently used construction delivery method

• State-funded DBB– Preliminary Plans (Year 1)

– PWB Approval

– Working drawings (Year 2)– Contracting/ Construction (Year 3)

5/12/2017

4

Design-BuildThe 2017-18 Governor’s Budget contains the first state-funded Community College DB project.

• State-funded Design-Build (DB)– Performance Criteria (Year 1)

– PWB Approval

– Design Build (Year 2)

Lease-Leaseback (LLB)The Department of Finance posits that the state cannot fund LLB with bond funds (includes Proposition 51)

• DOF considers LLB payments as lease payments not construction payments – lease payments are not covered in bond language

5/12/2017

5

State Funding Options• State still prefers DBB

• The first state-funded Community College DB project – Future proposed DB projects:

– CCCO only considering typical DB at this time (PC/DB)

– District must show prior successful use of DB (local funds)

– DOF has requested comparison of anticipated costs DBB vs DB

– DB must be requested and approved at IPP

• Department of Finance will not fund LLB with bond– DOF says payments are lease payments not construction funds (not

covered by bonds)

Questions?

CCFC Regional Workshop

Community College Construction Delivery Methods:

Options, Obligations and Opportunities

Friday, May 12, 2017 9:00 a.m. – 2:30 p.m.

Bay Area

COMMUNITY COLLEGE FACILITY COALITION

1303 J Street, Suite 520 ♦ Sacramento, CA 95814 ♦ Phone (916) 446-3042 ♦ Fax (916) 441-3893 ♦ www.caccfc.org

The Evolution Toward Progressive Design-Build at San Mateo County CCD: The Skyline Environmental

Services Building Project Case Study

Chris Strugar-Fritsch San Mateo County Community College District

Erin Allred

XL Construction

Craig Ivancovich DES Architects + Engineers

Tay Othman DES Architects + Engineers

5/12/2017

1

Chris Strugar‐Fritsch, San Mateo County Community College District

SMCCCD History with Design Build

• SMCCD first California CCD to use Design‐Build

• AB 1000: Enacted in September 2002.  Allowed Design‐Build to be used by five CCDs as pilot programs until December 2007

• José Nuñez, SMCCD Vice Chancellor for Facilities and Jeff Gee, Swinerton Management Consultants lobbied legislature to approve AB 1000

• Current California Education Code 81700 – 81708 allows CCDs to use Design‐Build for project > $2.5M through 2020

• SMCCD two previous Bond Measure Programs has constructed ~$400M of capital projects using Design‐Build

• Current Bond Measure Program using Design‐Build ~$250M

5/12/2017

2

SMCCCD Practices• Past District Two Step Practice

• Architect Develops Bridging Documents

• RFSOQ and RFP Process to Select Design‐Build‐Entity

• Design Competition

• Guaranteed Maximum Price (GMP) Established at Contract Award

• Current District Practice Migrating to Progressive Design‐Build

• RFP Qualifications/Best Value Selection Process

• No Bridging Documents

• No Design Competition – Design Completed with College/District Input

• GMP Established After Design is Fully Developed, Agencies Permit Processes and Buyout Completed

Design Build Procurement Process

• Three highest ranked Design‐Build Entities are invited to participate• Employs objective evaluation criteria as required per Education Code 

81700; price, technical expertise, life cycle costs, skilled labor force availability, and acceptable safety record

• Allows for price or costs to be considered with qualifications

• Employs evaluation criteria traditionally used for qualifications‐based selection along with a prequalification questionnaire based on the Department of Industrial Relations’ guidelines

• Allows for a larger pool of qualified firms to participate

“Best Value”Qualifications + Cost 

Request for Statement of Qualifications

Request for Proposals

5/12/2017

3

Reasons for Implementing Current Practice

• District Has More Influence on Design After Contract Award

• District Can Hire DBE Team that is Best Fit for College

• Improved Integrated Design Process 

• Leverage IPD and Lean Construction Practices

• Improved Speed to Market

• Open Book/Transparent Cost Management

• Improved Competition

Proposal Renderings

Cañada College Building 1N Kinesiology and Wellness

Skyline College Building 12N Environmental Science

5/12/2017

4

Q & A

5/12/2017

1

Erin Allred, XL ConstructionCraig Ivancovich, DES+EngineersTay Othman, DES+Engineers

1

Team Participants◦ Erin Allred, XL Construction◦ Craig Ivancovich, DES Architects + Engineers◦ Tay Othman, DES Architects + Engineers

2

5/12/2017

2

RFP & Teaming Methodology 

Project Schedule Overview

Target Value Design

Alignment Session

Project Delivery

Lessons Learned

3

4

5/12/2017

3

5

Program Validation & SD Phase

DD Increment 1

Increment 2

CD’s

DSA

DSA

1/27

3/1

3/17CD’s

4/28

6

Initial Estimate 15% Higher than Construction Budget.

5/12/2017

4

7

8

5/12/2017

5

9

Behavioral Alignment Values Alignment Milestone Planning and Risks

10

Meetings with District in program validation

SD phase and beyond Design Pull Planning

Session

5/12/2017

6

11

District/Swinerton early involvement in coordinating meetings

Schedule alignment session earlier

COMMUNITY COLLEGE FACILITY COALITION 1303 J Street, Suite 520 ♦ Sacramento, CA 95814 ♦ Phone (916) 446-3042 ♦ Fax (916) 441-3893 ♦ www.caccfc.org

Community College Construction Delivery Methods: Options, Obligations and Opportunities

Friday, May 12, 2017

Bay Area

THANK YOU SPEAKERS

Erin Allred XL Construction [email protected] (408) 240-6392 Rebekah Cearley Murdoch Walrath & Holmes [email protected] (916) 441-3300 Monet Crowley XL Construction [email protected] (916) 895-1650 Jack Herbert Swinerton Management & Consulting [email protected] (415) 984-1345 Harold Flood California Community Colleges Chancellor's Office [email protected] (916) 327-5364 Craig Ivancovich DES Architects + Engineers [email protected] (650) 364-6453

Mark Kelley Dannis Woliver Kelley [email protected] (415) 543-4111

Karen Kuklin Gensler [email protected] (213) 327-3600 Tay Othman DES Architects + Engineers [email protected]

Leigh Sata Sonoma CCD [email protected] (707) 527-4011

Chris Strugar-Fritsch San Mateo CCD [email protected] (650) 378-7342

Steve Winslow XL Construction [email protected] (408) 240-6306


Recommended