CCTV Survey Report
Client: Chrome Services Limited
Date: 31st, July, 2017
Weather Condition at time of Survey: Dry
Prepared by Andrew Barlow
Site: Chapel Hill, Longridge, Preston, PR3 3JY
2
Date: 31/07/2017
Report Summary:
Following our receipt of your order and as requested our engineers attended site to carry out a
CCTV survey of the drainage lines from the manholes of interest (see plan) to check their
condition, location and connectivity.
Once on site our engineers carried out a CCTV survey from Manhole-1(SWMH-1 marked on
plan) downstream to Manhole-2 (SWMH-2 marked on plan). The CCTV survey established a
number of large displaced joints, large cracks, fine roots and encrustation at some of the joints.
We recommend to undertake an excavation over the defective section of pipework and replace
with new pipework, we also recommend High Pressure Water Flailing/ Root Cutting in order to
clear the drainage line of any roots, encrustation and debris. we also recommend to install 5 x
225mm patch liners within the defective section of pipework to ensure the maximum flow of
water can be discharged downstream and also to eliminate any future root growth at certain
joints.
Our engineers then carried out a CCTV survey from Manhole-1Branch Line-1 Upstream to
Head of Line. Unfortunately the survey was abandoned at 4.0 meters due to what we believe to
be a work boot blocking the drainage line which we believe to be leading into a buried manhole.
The CCTV survey also established a number of large displaced joints within the drainage line.
We recommend to undertake an excavation to a maximum depth of 1.5 meters from manhole-1
Branch Line-1 the over the defective section of pipework to the buried manhole and replace
with new 225mm pipework. We also recommend to undertake an excavation over the buried
manhole in order to expose its cover and gain access. Once access has been gained we
recommend to clear the manhole of all debris and provide a manhole condition report, once the
manhole condition has been established a quotation will be provided to raise the frame and cov-
er to ground level.
Our engineers then carried out a CCTV survey From Manhole-1 Branch line-2 Upstream to
Head of Line. Unfortunately this CCTV survey had to be abandoned at 3.2 meters as our
engineers were unable to continue to push the gully camera due to it snagging on something.
We recommend to undertake an excavation from Manhole-1 Branch Line-2 over the defective
section of pipe work and replace with new pipework, whilst the excavation is open a resurvey
will be required in order to establish the drainage lines full condition.
Our engineers then carried out a CCTV survey from Manhole-3 Branch Line-1 upstream to head
of Line. This CCTV survey established a change in pipe diameter at 3.5 meters in which our
Micro Gully camera was unable to pass. Due to the nature of the drain we do not recommend
any further work at this present time.
Our engineers then proceeded with a CCTV survey to Manhole-3 Downstream to Discharge,
This CCTV survey established a number of large displaced joints, fractures at joints,
encrustation at joints and a large amount of silt/debris build up. We recommend High Pressure
Water Flailing in order to clear the drainage line of any encrustation and silt/debris build up, and
to install 3 x 150mm patch liners within the defective section of pipework in order to ensure full
flow as water is being discharged.
3
Date: 31/07/2017
Report Summary:
The following report highlights our findings on site, and where necessary we have put forward
recommendations for repairs to be carried out on the drainage system. We have colour coded
the proposed repairs within this report according to the severity of the defect identified/urgency
of the repair. Green=No Defects Yellow = Caution, Red = Urgent.
Please find below our summary of the survey, along with the detailed survey log sheets,
indicative plan of the drains and a manhole condition report.
4
Legend of Drawing:
5
Manhole Condition Report
Manhole No.
Depth
Cover sizeManhole Status
Duty
Cover Shape
Surface Re-Instatment
Other Info
PIPE DETIALS
BranchCover
Depth from
Ref
Downstream MH
Upstream /
ShapeSize (mm)
Height WiidthPipe Mat
(Y/N)
Drop Shaft
Depth (mm)
Drop ShaftRemark
1
2
3
4
5
6
X
X
X
X
X
X
Incoming Details
Outgoing Pipes
X
Y X
X
Cover Opening at Narrowest
Shaft Size (mm)
mm
mm
Chamber Size (mm) mm
mmShaft Depth (from CL)
Evidence of Surcharge
atmosphere
OX/H2S/METH Toxic
MANHOLE CONSTRUCTION DETIALS
Pre Cast Concrete
Reducing Slab
No. Of Regulation Brick Courses
In Situ Concrete
Segments
Brick PVCu
No. of Landings
Arch Corbel Taper Side Entry
No. of Ladders No. of Step Irons
CONDITION INFOMATION (specific in remarks)
OK
Needs attention
Urgent attention
Cover Shaft Irons/ladder Chamber Benching Channel
Depth of Flow mm Depth of Silt Height of Surcharge from CL mmmm
Remarks
1.17m Circular 225
1.15m Circular 150
Medium
Private
Unmade
SW
500mm
1.19m
SWMH-1
Vitrified Clay
Vitrified Clay 150
225
225 Vitrified Clay 1.19m Circular 225
450
450
600x600
0.16
Cover Duty
Circular
Site Chapel Hill, Longridge, Preston, PR3 3JY
6
Manhole Condition Report
Manhole No.
Depth
Cover sizeManhole Status
Duty
Cover Shape
Surface Re-Instatment
Other Info
PIPE DETIALS
BranchCover
Depth from
Ref
Downstream MH
Upstream /
ShapeSize (mm)
Height WiidthPipe Mat
(Y/N)
Drop Shaft
Depth (mm)
Drop ShaftRemark
1
2
3
4
5
6
X
X
X
X
X
X
Incoming Details
Outgoing Pipes
X
Y X
X
Cover Opening at Narrowest
Shaft Size (mm)
mm
mm
Chamber Size (mm) mm
mmShaft Depth (from CL)
Evidence of Surcharge
atmosphere
OX/H2S/METH Toxic
MANHOLE CONSTRUCTION DETIALS
Pre Cast Concrete
Reducing Slab
No. Of Regulation Brick Courses
In Situ Concrete
Segments
Brick PVCu
No. of Landings
Arch Corbel Taper Side Entry
No. of Ladders No. of Step Irons
CONDITION INFOMATION (specific in remarks)
OK
Needs attention
Urgent attention
Cover Shaft Irons/ladder Chamber Benching Channel
Depth of Flow mm Depth of Silt Height of Surcharge from CL mmmm
Remarks
2.31m Circular 350
Heavy
Public
Tarmac
Foul
600x600mm
2.33m
MHF-1
Concrete 350
350 Concrete 2.33m Circular 350
600
600x600
1400
600
4
Cover Duty
Square
Site Chapel Hill, Longridge, Preston, PR3 3JY
4
7
Manhole Condition Report
Manhole No.
Depth
Cover sizeManhole Status
Duty
Cover Shape
Surface Re-Instatment
Other Info
PIPE DETIALS
BranchCover
Depth from
Ref
Downstream MH
Upstream /
ShapeSize (mm)
Height WiidthPipe Mat
(Y/N)
Drop Shaft
Depth (mm)
Drop ShaftRemark
1
2
3
4
5
6
X
X
X
X
X
X
Incoming Details
Outgoing Pipes
X
Y X
X
Cover Opening at Narrowest
Shaft Size (mm)
mm
mm
Chamber Size (mm) mm
mmShaft Depth (from CL)
Evidence of Surcharge
atmosphere
OX/H2S/METH Toxic
MANHOLE CONSTRUCTION DETIALS
Pre Cast Concrete
Reducing Slab
No. Of Regulation Brick Courses
In Situ Concrete
Segments
Brick PVCu
No. of Landings
Arch Corbel Taper Side Entry
No. of Ladders No. of Step Irons
CONDITION INFOMATION (specific in remarks)
OK
Needs attention
Urgent attention
Cover Shaft Irons/ladder Chamber Benching Channel
Depth of Flow mm Depth of Silt Height of Surcharge from CL mmmm
Remarks
1.97 Upstream Circular 225
Light
Private
Unmade
SW
500
1.99m
SWMH-3
Vitrified Clay 225
225 Vitrified Clay 1.99 Downstream Circular 225
450
450
870x870
0.12
2
Concrete Biscute Snapped.
Cover Duty
Circular
Site Chapel Hill, Longridge, Preston, PR3 3JY
8
The drain surveyed is a circular 225mm diameter vitrified clay pipe transporting surface water.
The below observations have been made:
0.0m - Water level, 0-5%
0.5m - Encrustation, from 9 to 3 o’clock, poor vision to 80.0 meters
1.2m - Encrustation, from 5 to 8 o’clock 5%
2.0m - Longitudinal crack at joint, at 8 o’clock
2.5m - Large displaced joint, encrustation at joint
57.0m - Fine roots at joint
60.4m - Fine roots at joint, fracture at joint
65.0m - Fine roots at joint,
73.5m - Multiple fractures at joint, to 75 meters
80.0m - Large multiple cracks, large open joint.
82.0m The survey finished at Manhole-2.
We recommend the below work:
Undertake an excavation to a maximum depth of 2.0 meters from Manhole-2 over the defective
section of pipework to 3.0 meters and replace with new 225mm pipework (allowing up to
3.0 meters of pipework to be replaced). Whilst the excavation is open High Pressure Water Flailing/
root cutting will be required in order to clear the drainage line of any encrustations, debris or root
growth. Backfill the excavation and reinstate to match the existing surface finish (unmade)
We recommend to install 5 x 225mm Patch Liners within the defective sections of
pipework from Manhole-1at 1.8 to 2.8 meters, 57.0 meters, 60.4 meters, 65.0 meters and 2 at 73.0 to
75.0 meters.
The cost for The excavation is £2480.00 Plus VAT.
The cost for 5 x 225mm x 1.0m Patch Liners is £3200.00 Plus VAT.
The cost for High Pressure Water Flailing/Root cutting is £150.00Plus VAT.
Manhole-1
Manhole-1 Downstream to Manhole-2
9
Large crack at joint Large displaced joint with longitudinal crack,
encrustation at joint
Scale build up at joint Encrustations at joint, with fine roots
Fine roots at joint Fine roots at large displaced joint
10
Multiple fracturs at joint Large crack with open joint
11
The drain surveyed is a circular 225mm diameter vitrified clay pipe transporting surface water.
The below observations have been made:
0.0m - Water level, 10%
0.2m - Line deviates right 45°
0.5m - Large displaced joint, on deviation
0.9m - Line deviates left 45°
0.9m - Large displaced joint
1.4m - Large displaced joint
3.2m - Large displaced joint
4.0m - The survey was abandoned, buried manhole with possible collapse, work boot blocking
entrance to it.
We recommend the below work:
Trace and locate the buried manhole (at 4.0 meters fromManhole-1). Undertake an excavation to a
maximum depth of 1.5 meters over the buried manhole in order to expose the cover and gain access.
Once access has been gained we recommend to remove all debris and provide a full report on our
findings (ie contents, condition, usage, connectivity, depth, shaft size and pipework diameter size) ,
once established a quotation will be provided to raise the frame and cover back to ground level.
The cost for the excavation is £920.00 Plus VAT.
We recommend to undertake an excavation to a maximum depth of 1.5 meters over the defective
section of pipework from 0.0 meters at Manhole-1 Branch Line-1 to 4.0 and replace with new
225mm pipework (allowing up to 4.0 meters of pipework to be replaced). Backfill the excavation
and reinstate to match existing surface finish (Unmade).
The cost for the excavation is £995.00 Plus VAT.
Manhole-1 Branch-1 Upstream to Head of Line.
Manhole-1 Branch Line-1
12
Large displaced joint on deviation Large displaced joint
Large displaced joint on deviation Large displaced joint on deviation
Boot blocking drain line into buried manhole,
possible collapse
13
The drain surveyed is a circular 150mm diameter vitrified clay pipe transporting surface water.
The below observations have been made:
0.0m - Water level, 25%
1.0m - Encrustation and scale, from 7 to 1 o’clock
1.1m - Loss of vision, camera under water to 1.6 meters
1.6m - Large displaced joint, encrustation at joint
1.6m - Loss of vision, camera under water to 3.2 meters
3.2m - The survey was abandoned, unable to continue pushing camera.
We recommend the below work:
Undertake an excavation to a maximum depth of 1.5 meters over the defective section of pipework
at 0.0 meters from Manhole-1 Branch line-2 to 3.2 meters an replace with new 150mm pipework
(allowing up to 4.0 meters of pipework to be replaced). Whilst the excavation is open a resurvey
will be required in order to establish the drainage lines full condition. Backfill the excavation and
reinstate to match the existing surface finish (unmade).
The cost for the excavation is £995.00 Plus VAT.
The cost for the resurvey is £150.00 Plus VAT.
Manhole-1 Branch-2 Upstream to Head of Line
Manhole-1 Branch Line-2
14
Large displaced joint Large displaced joint
15
The drain surveyed is a circular 225mm diameter vitrified clay pipe transporting surface water.
The below observations have been made:
0.0m - Water level, 0-5%
0.2m - Medium displaced joint
0.5m - Debris/silt build up, 10%
1.6m - Line deviates up, slight
2.65m - Line deviates left slight
2.66m - Line deviates down slight
3.0m - Water level, 10%
3.5m - Diameter change , 100mm
3.5m - The survey was abandoned, unable to pass diameter change.
We do not recommend any further work at this present time.
Manhole-3 Branch-1 Upstream to Head of Line
Manhole-3
16
Medium displaced joint Pipe diameter change, 100mm
17
The drain surveyed is a circular 150mm diameter vitrified clay pipe transporting surface water.
The below observations have been made:
0.0m - Water level, 0-5%
0.5m - Large displaced joint, fracture at joint
2.0m - Water level, 10%
4.5m - Water level, 25%
4.7m - Debris/silt build up, 25%
5.6m - Large displaced joint, with large fracture
7.0m - Large displaced joint, encrustation at joint
7.3m - Encrustation at joint, from 12 to 12 o’clock, 10%
9.2m - The survey finished at discharge
We recommend the below work:
Undertake High Pressure Water Jetting/Flailing in order to clear the drainage line of any encrusta-
tion and debris/ silt build up. Supply and install 3 x 150mm Patch Liners within the defective sec-
tion of
pipework at 0.5m, 5.6m, and 7.0m.
The cost for 3 x 150mm Patch Liners is £1170.00 Plus VAT.
The Cost for High Pressure Water Jetting/Flailing is £150.00 Plus VAT.
Manhole-3 Downstream to Discharge
Manhole-3
18
Large displaced joint, fracture at joint Large displaced joint, encrustation at joint
Large displaced joint, fracture at joint Silt/debris build up, under water line
Large displaced joint, encrustation around joint
19
Our engineer has reported the concrete biscuit has
snapped
Our engineer has reported the manhole cover needs replacing with a new manhole cover and frame.
Our engineer has reported the shaft brickwork is deteriorating and crumbling into the drainage line.
Our engineer has reported the step irons are in poor condition and need replacing.
Further work required To Manhole-3