Pg 1 Aurangabad Municipal Corporation JNNURM (CDP) CONTENTS Preamble – The need for City Development Plan Executive summary City Introduction and Assessment A. General B. Economic Profile C. Poverty Profile D. Utilities and Infrastructure E. Environmental Profile F. Land Use and Development Profile G. Tourism and History Profile H. Financial Profile City Development Plan 1. Process 2. Vision/ Objectives/ Projects Reforms 1. Mandatory Reforms 2. Optional Reforms 3. State level Reforms Implementation and Budgeting The Calendar Budgeting Monitoring and Revision of CDP Resolve and MOU Epilogue Appendices A) Map B) Subject Committees C) Declared / undeclared sulms and illegeal localities D) List of Projects E) List of Priority Projects
Transcript
Page 1: CDP

Pg 1Aurangabad Municipal Corporation JNNURM (CDP)

CONTENTS

Preamble – The need for City DevelopmentPlan

Executive summary

City Introduction and AssessmentA. GeneralB. Economic ProfileC. Poverty ProfileD. Utilities and InfrastructureE. Environmental ProfileF. Land Use and Development ProfileG. Tourism and History ProfileH. Financial Profile

City Development Plan1. Process2. Vision/ Objectives/ Projects

Reforms1. Mandatory Reforms2. Optional Reforms3. State level Reforms

Implementation and BudgetingThe CalendarBudgetingMonitoring and Revision of CDP

Resolve and MOU

Epilogue

AppendicesA) MapB) Subject CommitteesC) Declared / undeclared sulms and illegeal localitiesD) List of ProjectsE) List of Priority Projects

Page 2: CDP

Pg 2Aurangabad Municipal Corporation JNNURM (CDP)

DETAIL CONTENTSPreambleThe need for City Development Plan

Executive summaryVision StatementObjectivesStrategiesProjects and Expected OutcomesReforms

City Introduction and AssessmentA. General1. Historical Background2. Regional setting, linkages and accessibility3. Demographic Profile4. Administration & Urban Governance5. Institutional Setup6. At a glance

B. Economic Profile1. Employment2. Predominant Sectors’ contribution to Economy & Industrial Development

C. Poverty Profile1. General Characteristics of slums2. Population below Poverty Line3. Social set up4. Employment5. Average household size6. Housing type7. Health8. Education9. Location of slums10. Urban basic services in slums11. Slum Improvement and Poverty Alleviation Programs

D. Utilities and Infrastructure1. Water supply2. Solid Waste Management3. Sewerage and sanitation4. Traffic and Transportation5. Health6. Education7. Art, Sports and Culture8. Fire Service9. Zoo and Animal Husbandry

DETAIL CONTENTS

E. Environmental Profile1. Climate2. Air3. Influence of activity sectors on Air4. Topography and natural drainage5. Geology6. Soil Characteristics and Land use7. Influence of activity sectors8. Surface water9. Influence of activity sectors on surface water10. Ground Water11. Influence of activity sectors on ground water12. Forest and Vegetation13. Wild life14. Noise Levels15. Environmental Resource Sensitivity and EPM guidelines16. What AMC is doing

F. Land Use and Development Profile1. Statutory Provisions for Plan preparation 1.1 Preparation of the Development Plan2. Landuse in the city 2.1 Landuse Analysis3. Housing4. Gunthewari

G. Tourism and History Profile

H. Financial Profile

I. City Development Plan1.Process2.Vision/ Objectives/ Projects

a. Development Plani.Visionii.Objectivesiii.Strategiesiv.Projectsv.Key Parameters

b.Water supplyi.Visionii.Objectivesiii.Strategiesiv.Projectsv.Key Parameters

Page 3: CDP

Pg 3Aurangabad Municipal Corporation JNNURM (CDP)

c.Sewerage and Sanitationi.Visionii.Objectivesiii.Strategiesiv.Projectsv.Key Parameters

d.Solid waste management including Bio- Medical waste

i.Visionii.Objectivesiii.Strategiesiv.Projects

e.Healthi.Visionii.Objectivesiii.Strategiesiv.Projects

f.Road Infrastructurei.Visionii.Objectivesiii.Strategiesiv.Projects

g.Urban Transporti.Visionii.Objectivesiii.Strategiesiv.Project

h.Heritage Buildings/ Tourismi.Visionii.Objectivesiii.Strategiesiv.Projects

i.Slums and Urban Povertyi.Visionii.Objectivesiii.Strategies

j.Street Lightingi.Visionii.Objectivesiii.Strategiesiv.Projects

DETAIL CONTENTS

k.Educationi.Visionii.Objectivesiii.Strategiesiv.Projects

l.Governance and City Financei.Visionii.Objectivesiii.Strategiesiv.Projects

Reforms

1. Mandatory Reforms1.1 Adoption of modern accrual based double entry system of accounting

1.1.1 Current Status1.1.2 Vision and Process1.1.3 Schedule

1.2 Introduction of a system of e-governance us ing IT applications, such as GIS and MIS for various services

1.2.1 Current Status1.2.2 Vision and Process1.2.3 Schedule

1.3 Reform of Property Tax with GIS1.3.1 Current Status1.3.2 Vision and Process1.3.3 Schedule

1.4 Levy of reasonable user charges with theobjective that the full cost of O&M or recur ringcost is collected within next seven years1.4.1 Current Status1.4.2 Vision and Process1.4.3 Schedule

1.5 Internal earmarking in the budget for basicservices to the urban poor1.5.1 Current Status1.5.2 Vision and Process1.5.3 Schedule

1.6 Provision of basic services to the urban poorincluding security of tenure at affordable prices,improved housing, water supply and sanitation.Delivery of other existing universal services ofthe government for education, health and so-

Page 4: CDP

Pg 4Aurangabad Municipal Corporation JNNURM (CDP)

cial security is ensured1.6.1 Current Status1.6.2 Vision and Process1.6.3 Schedule

2. Optional Reforms2.1 Revision of bye laws for building construction etc.

2.1.1 Current Status2.1.2 Vision and Process2.1.3 Schedule

2.2 Earmarking of at least 20-25% of developedland in all housing projects for EWS/LIG cat-egory with a system of cross subsidization.2.2.1 Current Status2.2.2 Vision and Process2.2.3 Schedule

2.3 Revision of byelaws to make rain waterharvesting mandatory in all b u i l d i n g s a n dadoptions of water conservation measures.2.3.1 Current Status2.3.2 Vision and Process2.3.3 Schedule

2.4 Bylaws for reuse of recycled water2.4.1 Current Status2.4.2 Vision and Process2.4.3 Schedule

2.5 Administrative reforms2.5.1 Current Status2.5.2 Vision and Process2.5.3 Schedule

2.6 Structural reforms.2.6.1 Current Status2.6.2 Vision and Process2.6.3 Schedule

2.7 Encouraging Public Private Partnership.2.6.1 Current Status2.6.2 Vision and Process2.6.3 Schedule

3. Reforms at State Government level.Implementation and BudgetingThe CalendarBudgetingMonitoring and Revision of CDPResolve and MOUEpilogueAppendices

DETAIL CONTENTS

Page 5: CDP

Pg 5Aurangabad Municipal Corporation JNNURM (CDP)

PREAMBLE

Preamble

Page 6: CDP

Pg 6Aurangabad Municipal Corporation JNNURM (CDP)

The need for City DevelopmentPlan

Due to rapid industrialization in and aroundAurangabad corporation as also due to explosionof tourist traffic for the city, Aurangabad city is grow-ing at phenomenal pace for last two decades. Dur-ing first half of 1990s the city was touted as fastestgrowing city in the country. Population has in-creased from 150483 in 1971 to 873311 in 2001.The city, in absence of a long term planning hasbeen tackling the issues arising out of this explo-sion on an ad-hoc basis. In fact till an issue be-comes something of an urgency it does get ad-dressed as city government is already grapplingwith other issues that have acquired urgent pro-portions. This has led to sub-optimum uses of re-sources and also less than desirable effects of re-source spending. Again discontent in the popula-tion also gets risen as problems are tackled lateand in an unsatisfactory way. Also important issuesgets a back seat as urgent issues take over.

This has led to a realization that city must assessits current situation, understand the opportunity thatexist as well as competition it faces, project its vi-sion, focus on priority issues that otherwise maycreate bottlenecks in the developmental goals, al-locate its resources in an optimum way and planan investment raising routes, with evaluation of al-ternate strategies for implementation of the vision.

JNNURM, the Jawaharlal Nehru Urban RenewalMission, launched by Hon. Prime Minister of Indiaon 3rd of December, 2005 also makes this need acorner stone of the initiative. The mission whichaims at ‘creating economically productive, efficient,equitable and responsive cities in an integratedframework with focus on economic and social in-frastructure, basic services to poor and urban sec-tor reforms’, makes it mandatory to make a me-

dium term ‘City Development Plan’ to avail any kindof assistance under the mission. Even the Gov-ernment of Maharashtra has made it clear that anykind of financial assistance that a corporation orany civic body desire will follow only if the city makesthis medium term plan and utilizes the assistancein a manner that is consistent with the plan.

This insistence of both the state and central gov-ernments, amidst the growing realization as statedin the paragraph preceding the last one, has led tocrystallization of idea of need of making a mediumterm CDP. Thus Aurangabad Municipal Corpora-tion started in right earnest the preparation of CDPand this document is the result. However, one as-pect of CDP that needs to be stressed here is its‘dynamism’. Even if this plan is medium term, itmust be realized that this plan will be needed to bereturned to, at periodical intervals, not only to as-sess the level of its implementation and its effecton the measurable key parameters but also tomodify it as per the changes in internal and exter-nal environments, including financial, legal as wellas natural environments.

nnn

Preamble – The need for City Development Plan

Page 7: CDP

Pg 7Aurangabad Municipal Corporation JNNURM (CDP)

EXECUTIVE SUMMARY

Executive summary

Page 8: CDP

Pg 8Aurangabad Municipal Corporation JNNURM (CDP)

Vision StatementAurangabad Municipal Corporation desires theAurangabad City to acquire a status by 2025 of acity that is –l economically efficient and capable of taking up

new projects necessary for keeping pace with thedevelopments inside and outside the country

l at the forefront of the tourist destinations in thecountry

l having well developed and adequate physicaland social infrastructure capable of expansionto take care of increasing population due to ex-pected inflow as well as natural growth of popu-lation and a city that affords to all its citizens –

l equitable and minimum level of access to basicservices offered by the city

l responsive and transparent governancel economic opportunities of personal growthl security of minimum economic well being

ObjectivesVision statement leads to following objectives forthe city to attain in medium term:

1. Upgrade the physical and social infrastructure in stages to the requirement of 2025.

2. Fix the user charges for the different serviceskeeping in view both the requirements, one ofensuring that charges compensate for the run-ning and maintenance expenditure and subsidyon the capital investment returns is sustainablethrough other sources of income and secondof ensuring that charges for the basic civic ser-vices remain within the capacity of urban lowerincome groups.

3. Urban lower income groups have access to reasonable housing.

4. City creates conducive procedural, legal andtax environment for private investments in dif-ferent sectors including industrial and trading

sectors that lead to universally affordable ser-vices that are not directly provided by the city(like higher end medical, educational services)and that create increasing income opportuni-ties for the citizens.

5. Create world class infrastructure needed for thetourists by creating some itself and for other bycreating right environment for the service pro-viders.

6. Use modern governance methods and systemsthat ensure responsiveness, transparency andinvolvement of and maximum information to thecitizens.

7. Minimize the governance directly by outsourcingsome of its functions without affecting the so-cial face of the services.

8. Keep system in place that warns and ensurestimely policy response to changes in nationaland international scenario in various fields, thatkeep tracks of the threats, warns of the weak-nesses, spots opportunities and builds onstrengths.

9. Embrace the reforms in all the aspects of internal and external workings of city governance.

Strategies

For the achievement of the objectives delineatedabove in pursuance of the vision developed for thecity following strategies may be adopted:

1.Raise the income of the corporation:a. by adding new sourcesb. by expanding the scope of existing sourcesc. by increasing the efficiency of collection of existing sourcesd. by rationalizing the rates for different services offerede. by rationalizing the taxation levied by the

corporation for better compliance and better tar-geting

Executive summary

Page 9: CDP

Pg 9Aurangabad Municipal Corporation JNNURM (CDP)

f. by better utilization of land resources at the disposal of corporation

2.Reduce the expenditure:a. by outsourcing some of the activities of the corporationb. by more efficient utilization of the human and material resourcesc. by ceasing to do some unnecessary activities altogether and concentrating on the core activi tiesd. by changing the legal structure for periodic

requirements of a duty ( like renewing of licensesevery year which can be changed to every fiveyear or longer)

e. by outright privatization of some servicesf. by involvement of social groups/ community

groups in management and or performance ofsome of the services.

3. Prioritization of expenditure into developmentof basic infrastructure, provision of basic ameni-ties to urban poor and infrastructural require-ments of tourists.

4. Rationalization of the user charges for directservices.

5. Modifications of procedural and legal rules andadministrative framework for expediting thefunctioning of the city governance, including sim-plification of methods, comprehensive comput-erization of the systems, e-governance and useof MIS in decision making.

6. Creating right tax environment for the new investments.

7. Embracing the reforms in all fields includingdouble accounting in finance.

8. Minimizing the governance by focusing on thecore and shrugging off unnecessary activities.

9. Ensuring that all new projects taken up areeconomically sustainable and provide for ser-vice charges in tune with operational and main-tenance charges as well as the depreciation.

10.Periodical rating of financial condition by

approved agencies.11. Establishing the system to periodically review

the external and internal situation including newopportunities arising and any bottlenecks for de-velopment inside.

12. Creation of social infrastructure like education and health to make available a satisfied andcompetitive human resource for the city to grow.

13. Encouraging Public Private Partnership. PPPcan reduce the cost burden on Corporation whileensuring better services for its citizens. Experi-ence of corporation in this regard has beenencouraging.

Projects and Expected Outcomes

The vision enshrined above, objectives that flowout of it and the strategies decided to achieve thoseobjectives lead to no of projects which are listed inAppendix – D. Out of this following projects imme-diately need to be taken up:1. Project: New parallel water supply line with

stage wise augmentation of source to take careof the drinking water needs of the city till 2025.Outcome: Per head water availability to the ex-tent of 150 liters per day till 2025.

2. Project: Setting up of new Sewerage Treatment Plant(s) of capacity 100 MLD and to bringexisting system into use.Outcome: Treatment of sewerage water toirrigable quality before discharging it into natu-ral streams.

3. Project: Development of slums through integrated approach, including infrastructure cre-ation.Outcome: Better living conditions for the Ur-ban Poor.

4. Project: Integrated Road Development Plan forthe city.Outcome: A dependable road infrastructure thatis safe as well as convenient.

5. Project: Comprehensive computerization of the

Executive summary

Page 10: CDP

Pg 10Aurangabad Municipal Corporation JNNURM (CDP)

different systems,especially accounting branchwith shift to double accounting system, usingstandard ERP package.Outcome: Optimum utilization and tracking andmaintenance of all the resources including landother assets leading to better financialmanagement.

6. Project: Start of Municipal Transport systemand upgrading it to the necessary requirementof the city.Outcome: Convenient, safe and affordabletransport system for the city p a s s e n g e r s ,leading to less stress on road infrastructure asmore and more people go for public transportinstead of private transport.

7. Project: Conservation project for the heritagemonuments present in the city, especially 300years old Town Hall and different Gates, about13 in number.Outcome: Preservation and packaging of his-tory for the purpose of promotion of tourism aswell as self-esteem and identity for the city.

8. Project: Completion of the survey and computerization project of Property Tax and its linkageto GIS system, developed on basic data layerprepared by MRSAC.Outcome: Better realization of the property taxwith minimum leakages, as well as rational-ization of the same and streamlining the growthof property tax with natural growth of the city.

9. Project: Fulfillment of additional manpowerrequirement in services like sanitation throughprivatization.Outcome: Better standard of services providedto the citizens in vital areas of sanitation etc.with minimal expenditure,leading to better healthenvironment.

10. Project: Privatization of maintenance workespecially for street lights and gardens.Outcome: Better standard of services with ex-penditure in check, more responsive services.

11.Project: Implementation of Development planespecially in view of reservations required for

better services to citizens particularly for urbanpoor.Outcome: Planned and futuristic developmentof the city with all aspects of a good urban lifeand all amenities getting appropriate attentionwhile embarking on the development, ensuringno bottlenecks crop up in any of the services oramenities leading to hampering of the growth.

12. Project: Transport Nagar13. Project: Tourism development and heritage

conservationOther projects mentioned in the Appendix – Dwill be taken up in priority.

Reforms

Representatives of the citizens, office-bearersamong them, administration and citizens as a wholehave recognized the need for time bound reformsfor the sustainable development of the city. Someof the reforms which need increase or rationaliza-tion of the taxes or the charges for different ser-vices have also found favor with these stake hold-ers. Even though JNNURM mandates some re-forms, city government has anyway decided to em-brace these reforms due to felt need rather thandue to directives.Vide resolution dated 20-01-2006, and bearingnumber 156 / 02, city government has decided toimplement all the reforms mandated by the centralgovernment in a time bound manner, as delineatedbelow:

1. Adoption of modern accrual based double entry system of accounting:

a.Time limit: Corporation intends to implementdouble entry system in financial year, 2006-07.

b.Current Stage: Under process for tenderingfor making of ‘assets’ and ‘liabilities’ registers, andvaluation of each oh these entries. Also under pro-cess is the tender for ERP implementation with em-phasis on double entry accounting system. It is ex-

Executive summary

Page 11: CDP

Pg 11Aurangabad Municipal Corporation JNNURM (CDP)

pected that a trial run, when both single entry anddouble entry systems will run parallel for a year,should start from January, 2007.

2. Introduction of a system of e-governance using IT applications, such asGIS and MIS for various services:

a.Time Limit: Corporation intends to implementfull ERP system in next two financial years i.e. 2006-07 and 2007-08.

b.Current stage: Under tender process for ERPimplementation. Tender forms have been dis-cussed, presentations of different ERP productcompanies like SAP, Oracle and Microsoft repre-sentatives over, and are in final stages for publica-tion of the tender.

3. Reform of Property Tax with GIS:

a.Time Limit: Linking of GIS with property tax tobe done in next financial year, i.e. 2006-07.

b.Current Stage: Full survey of properties in thecorporation area complete which led to jumping ofproperties no from 90000 to 143000. Computer-ization of basic data complete. Notices on for final-ization of the property tax. Basic layer of propertiesas per satellite data from MRSAC ready. Proposalfor linking the two under consideration.

4. Levy of reasonable user charges withthe objective that the full cost of O&M orrecurring cost is collected within nextseven years:

a.Time limit: Seven years.

b.Current stage: Corporation subsidizes watersupply and drainage services to the tune of almost50% through other taxations. New water supplyproject for augmentation of water source and par-allel water supply line will have charges to be lev-ied related to the O&M cost. Capital expenditure of

that will however come from the other taxations.Municipal Transport service launched by the cor-poration is without any subsidy and through BOTroute it has ensured that not only are the rates oftickets very affordable to everyone, it earns a loy-alty of about 40 lakhs a year.

5. Internal earmarking in the budget forbasic services to the urban poor:

a.Time limit: Next financial year i.e. 2006-07.

b.Current stage: Currently some budget heads arespecifically for the urban poor especially those re-siding in slums. Schemes of central governmentfor urban poor like SJSRY etc. are implemented inletter and spirit. Corporation’s internal schemes likefree uniforms, books to all etc. are targeted towardsurban poor who take education in corporation’s pri-mary schools. All internal health schemes have ser-vice prices very affordable. However more specificinternal earmarking will be done in the budget fromnext financial year.

6. Provision of basic services to the urbanpoor including security of tenure at af-fordable prices, improved housing, wa-ter supply and sanitation. Delivery ofother existing universal services of thegovernment for education, health andsocial security is ensured:

a.Time limit: Seven years.

b.Current Stage: Security of tenure is a state sub-ject, but a massive drive has been taken to regu-larize unauthorized structures owned by urban poorwho could not afford housing otherwise, underGunthewari Act, so that each one of them has ac-cess to basic services like roads, water and sani-tation. Out of expected 40000 households like this,20000 have already been survey and notices toabout 6000 have already been issued, in responseto which about 2000 have applied for the regular-

Executive summary

Page 12: CDP

Pg 12Aurangabad Municipal Corporation JNNURM (CDP)

ization. It is expected that this procedure will leadto regularization of at least 20000 households outof expected households in next six months. Oncethis goal is realized, corporation can give these poorall the services which is otherwise not possible le-gally. Education, health and other universal servicesare targeted more for urban poor, but will now bespecifically and focused targeted. Though socialsecurity is not guaranteed but corporation hasimplemented a novel scheme under which all thecitizens who pay property tax regularly are ensuredby the corporation for 25000 accidental benefits.No other social security is implemented.

Other than these mandatory reforms,following optional reforms are being takenup the corporation:

Revision of bye lawsFor building construction etc. Administration hasundertaken serious measures to streamline theprocess of grant of building permission etc. Ad-ministration has officially moved from the sys-tem of ‘betterment charges’ to ‘self develop-ment’; also system of approval of estimates hasbeen simplified by giving model estimates; eventax incentives for builders going for ‘group hous-ing schemes’ has been approved by GeneralBody of corporation.

Housing Project For EWS / LIG

Earmarking of at least 20-25% of developedland in all housing projects for EWS/LIG cat-egory with a system of cross subsidization. Thisreform will require change in the act and therules. This may be taken up under guidance ofstate government.

Rain Water Harvesting

Revision of byelaws to make rain water harvesting mandatory in all buildings and adoptionsof water conservation measures. This reformhas already been implemented with rain water

harvesting compulsory.

Reuse of Recycled Water

Proposal for tax incentive for reuse of recycledwater is under consideration.

Administrative reforms:

Corporation has its administrative expenditure un-

der 40% of its budget. However, while taking over

CIDCO area in corporation limits, corporation in-

tends to increase its staff by bare minimum and

reduce this percentage below 30%. Again when

corporation started its municipal transport system,

it did by BOT route and did not add even a single

person on its establishment while running a fleet

of 150 buses finally. Corporation also intends to

outsource most of its activities to reduce admin-

istrative expenditure.

Structural Reforms

Corporation will take up structural reforms inphases.

Encouraging Public Private Partnership

Corporation has started municipal transport with

PPP. About 14 projects have been given admin-

istrative approval for BOT implementation. Even

in Gunthewari regularization project, help of 7

agencies have been taken in a novel and com-

prehensive way that precludes need of individual

citizen to come to corporation and which en-

sures that a massive project of its dimensions,

regularizing 40000 houses, can be completed

in 6 months rather than 2 to 3 years. Corpora-

tion intends to explore all the fields in which

better services can be offered at lower cost,

without increasing its expenditure by going viaPPP route. Experience of corporation in thisregard has been encouraging.

nnn

Executive summary

Page 13: CDP

Pg 13Aurangabad Municipal Corporation JNNURM (CDP)

CITY INTRODUCTION AND ASSESSMENT

City Introduction and Assessment

Page 14: CDP

Pg 14Aurangabad Municipal Corporation JNNURM (CDP)

A General

1. Historical Background

Aurangabad is the headquarters of Aurangabaddistrict and also the divisional head quarters of theAurangabad Region. It is an ancient and historicalcity of the Marathwada Region.There was a village named Kirki (Khadki) wherethe city stands today. According to some histori-ans, the city was founded in 1610 by Malik Ambar.Malik Ambar was the Prime Minister of MurtazaNizam Shah II of Ahmednagar, the then ruler ofthe Deccan (central parts of Southern India). It iswidely believed that city took shape between 1604and 1610 under Malik Ambar’s rule. Initially, it wasnamed Fatehabad (city of Victory), probably afterMalik’s son Fateh Khan. A mint was built in the city.In 1634, Aurangzeb was sent to Kirki, and namedas Governor of Deccan. In 1644, He moved to Agrato play an active role in Mughal politics. In 1681,the city again became the residence of Aurangzeb,who had now become Mughal Emperor. He usedthe city as base for his campaigns to conquer thelast remaining Deccan sultanates. He lived thereuntil his death in 1707. The modern name of thecity was probably taken after his death. Aurangzeb’stomb is situated at Khultabad, a small town near

the city.There are no direct references to the present daycity in the ancient history. However the region onthe north of the Godavari, now included in theAurangabad district, was known by the name ofMulaka. This country together with its capitalPratishthana (modern Paithan) is mentioned in thePali literature. Pratishthana later became the capi-tal of the Satavahanas. The Yadava rulers had theircapital at Devgiri (present day Daulatabad) nearAurangabad. This city was famous for its 52 gates,its fortress walls and its Rajwada known by thename of Subhedari. Malik Amber had designed awater supply system for the city through a canalthat still exists. The city has world famous ‘Bibi kaMakbara’ (a replica of TajMahal ) , Panchakki (asystem of water supply that also run a Chakki togrind), Saneri (golden) Palace and very old Bud-dhist caves along with Navkhanda Palace, Kileark,Gulshan Palace etc. It also has Jama Masjid, KaliMasjid, Shahganj Masjid etc. Around Aurangabadare Daulatabad which has Devgiri Fort, Paithan andworld heritage sites of Ajantha and Ellora. This richhistory has put Aurangabad’s name on the touristmap of the world with prominence.It was a part of Hyderabad State and was ruled byNizam in British period. Aurangabad was head-quarter of the Subha (region) comprising of fivedistricts known as Marathwada in Nizam period. Itbecame a part of Indian in 1949. Aurangabadformed part of the Hyderabad State until 1956 af-ter which it was transferred to the Bombay State.In 1960 when Maharashtra State was formed itbecame an integral part of the state and the divi-sional headquarter of the Aurangabad Region., oneof the six divisional head quarters. The importance of the city increased with passageof time. City became an educational centre forbackward Marathwada region after establishmentof Marathwada University in 1958, which later re-named as Dr. Babasaheb Ambedkar University.During 1971-81 decade High Court was established

City Introduction and Assessment A General

Page 15: CDP

Pg 15Aurangabad Municipal Corporation JNNURM (CDP)

in Aurangabad. Thereafter city has commandedmore and more area under its influence. Large ef-forts were taken by state to promote Industrializa-tion from 1961. As a result of which MIDC Estateof Chikalthana was established in 1961-1971. Cityhas two industrial estates within Municipal Corpo-ration area and third large industrial estate WalujMIDC Area, 7 Km away from City in AurangabadUrban Agglomeration. Another Industrial Estate isup coming at Shendra MIDC Area, few Km awayfrom Aurangabad. These Industrial areas playedan important role in development of the Aurangabadcity.Beside these industries, tourism is a major eco-nomic activity of the city as places of significanthistorical importance like great fort of Daulatabad,Grave of Aurangzeb; caves of Ajanata and Elloraare located within few Km from the city. Monumentslike Bibi Ka Maqbara, replica of Taj Mahal of Agra,Panchakki and caves of Sonehri Mahal are situ-ated inside the city. So city is also developing as atourist centre.

2. Regional setting, linkages and accessibility

Aurangabad city is a head quarter of district andMarathwada region and is situated at the bank ofthe river Kham, a tributary of Godavari. City is situ-ated at the latitude of 19053’50" north and longi-tude of 75022’46" east. Aurangabad sits in a stra-tegic position on the Decaan Plateau. The city issurrounded by hills of the Vindhya Ranges and theRiver Kham passes through it. The city stands inthe Dudhana valley between Lakenvara range onthe north and Satara hills on the south. The valleyhas a general breadth of about 10 miles is opentowards the east, but on the west, the northernrange deflects and curves in towards the city send-ing a spur close upon its suburbs. Along the centreit deepens. Thus city occupies very uneven ground.Aurangabad is well connected with Mumbai, thestate capital, Delhi, the national capital and otherimportant places by air, rail and road. The city islocated on Hyderabad-Manmad-Mumbai railwayline. Mumbai to Aurangabad distance is 233 milesby railway. Conversion of meter gauge into broadgauge brings well links with the major cities inIndia.

City Introduction and Assessment A General

Page 16: CDP

Pg 16Aurangabad Municipal Corporation JNNURM (CDP)

Aurangabad also has an airport with direct flightsto Mumbai. It connects to Pune, New Delhi andother cities of the country, via Mumbai.

3. Demographic Profile

Aurangabad was Asia’s one of the fastest growingcity during the decade of 80s and 90s due to de-velopment of industrialarea.The population of Aurangabad as per the 2001census is 8,73,311 persons the same for the year

City Introduction and Assessment A General

1991 was 4,87,025 persons, thus there was agrowth of 3,86,286 persons. The table 1.1 belowshows that the population of the city has grownrapidly from 1961 to 1981. The growth rate washighest in 1981 at 89%. This could be due to theindustrial development at Waluj which attract dotof people for employment. It was in 1982 whenAurangabad was converted from an ‘A’ Class Mu-nicipal Council to a Municipal Corporation Thegrowth rate decreased from 1981 to 1991 and hasagain increased in the last decade.

Table 1.1 Population Growth of Aurangabad

Year Population Increase/ Decrease Decadal Growth Rate

1931 292881941 41644 12356 42.191951 57949 16305 39.151961 87579 29630 51.131971 150483 62904 71.831981 284807 134324 89.261991 487025 202218 71.002001 873311 386286 79.32

Population Growth of Aurangabad

0

100000

200000

300000

400000

500000

600000

700000

800000

900000

1000000

1931 1941 1951 1961 1971 1981 1991 2001

Year

Po

pu

lati

on

Source: Census of India 2001 and DP Report, Aurangabad

Page 17: CDP

Pg 17Aurangabad Municipal Corporation JNNURM (CDP)

City Introduction and Assessment A General

The Aurangabad Municipal Council was formed in1936 when the geographical area of the town was54.40 sq. km. In 1982 the council was convertedinto a Municipal Corporation and 18 nearby villageswere included in the city. The area of the MunicipalCorporation at present is 138.5 sq. km. The den-sity of the city as per the 2001 census population is6300 persons/ sq.km.

The city has 83 census wards and ward no. 16 isthe most populated with 42,791 persons and 9007households. However the household size in thisward is 4.7, just below the average for the city at5.0 persons per household. The ward no.17 hasthe largest household size at 7.5.

Table2.1: Socio economic Indicators of Aurangabad City

Socio- economic Indicators National State District AurangabadCity

Population 2001 1,027,015,247 96878627 2897013 873311Urbanization Rate (%) 27.8 42.42 37.50 100Area (sq. km.) 32,87,263 308000 138.5Density (persons / Sq Km) 324 315 6300No. of households 193,579,954 19,576,736 549898 167081Average Household Size 5.3 4.9 5.0 5.0Sex Ratio - Females 933 922 924 901per 1000 malesSex Ratio – females 927 913 890 887

per 1000 males (Below 6 years)SC Population as proportion to 16.2 10.2 13.0 17.1

total population (%)ST Population as proportion to 8.2 8.9 3.2 1.0total population (%)Literacy Rate (%)      65.38 76.9 72.90 83.7Female Literacy Rate (%) 54.16 67.0 60.10 75.8Work Participation Rate 39.25 42.5 40.60 28.6(Main and Marginal in %)Female Work Participation Rate 25.67 30.8 31.1 9.70

(Main and Marginal in %)

Density

The gross density of Municipal Corporation Areain 2001 is 6301 persons per Km2, which was4139 persons per Km2 in 1991. Density of the

area under development plan was 15181 personsper Km2, which was already developed area (CityCentre) in 1991.

Page 18: CDP

Pg 18Aurangabad Municipal Corporation JNNURM (CDP)

Census Year Area in Gross Density Net Area in Km2 Net Density per Km2

Population Km2 Per Km2

1951 57949 —— ——1961 87579 40.87 2143 2.47 354571971 150483 40.79 3689 2.46 610001981 284607 40.79 6977 2.43 1168001991 573272 138.5 4139 9.41 609002001 872667 138.5 6301 9.41 92738

The city has a good literacy rate at 84 % which wellabove the state and national average. The literacyamongst women is also good at 76 % and is wellabove the district average. The Scheduled Tribespopulation in the city is very less and forms only

Table . Literacy

Year 1971 1981 1981 2001 Person % Person % Person % Person % Literate s Literate s Literate s Literate s

Total 150483 54.46 284607 59.58 573272 61.06 872667 71.74Male 82252 65.43 151953 69.11 305257 69.45 458869 77.67Female 68231 41.23 132653 48.67 268015 51.52 413798 65.17e

Table. Sex Ratio

Year 1971 1981 1991 2001

Sex Ratio number of females per 1000 males 870 873 878 902

4. Administration and Urban governance

Physical Growth of the City:

Aurangabad, as mentioned earlier was originally asmall town called Khirki, later on the walled citycame up which was 5.35 Ha. in area. Then thecantonment area was established towards the endof 19th century, which was developed on the west-ern bank of the south-west walled city. Till the be-ginning of this century the development of the citywas limited within the walled city, Begampura and

Cantonment. As population started growing areaoutside the walled city started developing. The de-velopment was not possible on the northern partof the city due to the hilly land, which acts as amajor physical constraint. Hence city started de-veloping towards south and areas like Usmanpura,Padmpura, Kranti Chowk etc started developing.CIDCO was established during 1972 as a specialplanning authority and New Aurangabad Townshipwas developed towards east side of the city during1971-81. Eastern and north-eastern areas likeChikalthana and Harsool near city started devel-

Table. Population Density

1.0% of the total population. The sex ratio for thecity is not so good and is even below the state av-erage. The female work participation ratio is verylow compared to the high literacy among thewomen.

City Introduction and Assessment A General

Page 19: CDP

Pg 19Aurangabad Municipal Corporation JNNURM (CDP)

oping due to establishment of CIDCO. The MIDC,industrial area just on the east of the Municipal lim-its have given a great inputs for development alongJalana Road, the proximity of the area to the north-ern Delhi Gate with the Himayat Bagh, the Gov-ernment Office Complex, the Shahaganj area (citycentre). Areas like Jyotinagar, Jawahar Colony andGarkheda etc started developing in 1980s with largeno of apartments and are still developing today. Onthe south-west, city started developing towardsPaithan road in the areas like Kanchanwadi,nakshtrawadi etc.City is developing in three main directions, which arel South of Railway Stationl Along the Jalana Road towards the eastl Towards north along Jalagaon Road and north-west side beyond Dr. Babasaheb AmbedkarMarathwada University.Now city is developing beyond Garkheda towardsSatara near Bid Bypass Road on the Southern side.This area is outside the Aurangabad Municipal cor-poration limit. Also due to establishment of new FiveStar Industrial Estate at Shendra towards east, cityis expected to grow in that direction.

Administration

The Aurangabad Municipal Corporation is the gov-erning body of the city. The Corporation was formedon 3rd December 1982. At present there are 98electoral wards in city. The Corporation has 98elected representatives (councilors) and 5 nomi-nated representatives thus having a total of 103councilors in the corporation. The Corporation isheaded by a Mayor who is the elected representa-tive. The AMC carries out the governance throughthe General body meeting, standing committee andsix wards committees (as per the 74th amendmentto the constitution on decentralizing governance)and five committees on different subjects. The ChiefAdministrator is appointed by the Government fromIAS (Indian Administrative Services) cadre as com-missioner. In order to decentralize the governance

the AMC is trying to address all the issues and prob-lems of the citizens at the ward level. AMC hasalso taken over the area of CIDCO since first April,2006, for providing the services. This has facilitatedintegration of services with rest of the city. Munici-pal corporation had general elections in February2005. With 5 co-opted members, total strength ofthe body goes to 103. All the representatives dis-charge their duties through General Body which isthe apex body for policy decision and is chaired byMayor and in his absence by Deputy Mayor, astanding committee that meets every week andtake financial decisions especially as required bythe budget passed by General Body, five SubjectCommittees for different subjects like health, edu-cation, women and child welfare, urban develop-ment, and six Ward Committees that take admin-istrative decisions for works upto five lakhs for sixdivisions of the city. Corporation derives its exist-ence as well as most of its powers and dutiesthrough Bombay Provincial Municipal CorporationsAct and is responsible for almost all the facets ofan urban life, like roads, drainage, water supply,primary education, health including preventive aswell as curative care, gardens etc. Corporationderives its financial resources by levying PropertyTax, Water charges, Development Charges, Oc-troi etc.

5. Institutional Setup

The Aurangabad city today comprises of three dis-tinct physical entities – the old Aurangabad city in-cluding Aurangabad Industrial area, Chitalthana in-dustrial area and the township of New Aurangabad.Each area which was till recently managed by a spe-cific agency. There are three institutions, which areinvolved in planning and provision of infrastructuralservices to Aurangabad City as well as AurangabadUrban Agglomeration. They arel Aurangabad Municipal Corporation (AMC)l City and Industrial Development Corporation (CIDCO)

City Introduction and Assessment A General

Page 20: CDP

Pg 20Aurangabad Municipal Corporation JNNURM (CDP)

l Maharashtra Industrial Development Corpora tion (MIDC)CIDCO however has ceased to be a Special Plan-ning Authority as AMC has taken over all the func-tions of CIDCO on first of April, 2006.Each institution had prescribed territorial jurisdic-tion for provision of infrastructure. However, therewere some functions performed by AMC withinCIDCO and MIDC jurisdiction.

6. At a Glance

Education Management :There are 240 Primary schools, 32 High schools and30 colleges including one University in the city. Thereare Medical Colleges, Engineering Colleges, LowColleges, Pharmacy Colleges, Architecture Collegeand other Colleges of Technical & other Higher Edu-cation in the city. Aurangabad Municipal Corpora-tion also manages 53 Marathi medium, 16 Urdumedium, 12 Bi-lingual medium thus a total of 81 pri-mary schools. There are also 152 Balwadis run byAurangabad Municipal Corporation. Out of theseschools, 65 school buildings are owned byAurangabad Municipal Corporation. Rests of theschools are run in the rented buildings.

Public Health Services:There is a govt. Medical college and Hospital anda govt. Civil Hospital located in the city. In additionto this there are 5 big hospitals. The AurangabadMunicipal Corporation also runs three 20-beddedhospitals and 23 health centers in various parts ofthe city. Apart from these, private specialistmedicos also run their own hospitals.

Gardens and Zoo:

The Aurangabad Municipal Corporation has devel-oped a garden by name Siddharth Garden in thevicinity of Central Bus Stand. A Municipal Zoo isalso established adjacent to Siddharth Garden. Inthis Zoo, there is a Mini Theatre, an Aquarium anda Snake Park. In Siddharth Garden there is a

Musical Fountain, a Mini Train, a Traffic Gardenfor the amusement of Children and public.The municipal Zoo is known as one of the bestZoos not only in Maharashtra but in India also.The Aurangabad Municipal Corporation has alsodeveloped Swami Vivekanand Garden in Majbu Hillarea of the city. In this garden also a Mini Train isavailable.In the Northern side of the city a “Smruti Van” hasbeen developed adjacent to Harsul Tank. In HarsulTank boating facility is made available.In addition to above, with a view to have a pollu-tion-free atmosphere 52 gardens have been de-veloped by Aurangabad Municipal Corporation inthe different parts of the city.

Other facilities :

The Aurangabad Municipal Corporation has con-structed 20 shopping complexes, 28 CommunityCenters, 24 Libraries, 26 Multipurpose Halls, 01Hostel, 65 school buildings, 03 hospital buildings,23 Health Centers, 01 Veterinary Hospital, 01 Swim-ming Pool, 14 Gymnasium Halls, 02 SlaughterHouses, 52 gardens etc. for the benefit of the pub-lic.Similarly keeping in view the security aspect firebrigade facilities are also made available. Effortsare being made to upgrade this facility at a regionallevel.

Some important attractions :

Historical Bibi ka Maqbara, Panchakki, SonehriMahal, Siddharth Garden, Municipal Zoo,Acquarium, Snake Park, Musical Fountain, SmrutiVan, Swami Vivekanand Garden, ChhatrapatiShivaji Maharaj Museum, Dr. BabasahebAmbedkar Research Centre, Maulana Abul KalamAzad Research Centre, Aurangabad Caves, Swim-ming Pool, Nehru Bal Udyan, Dr.ShyamaprasadMukharji Udyan etc. are some of the places of at-tractions located in the city of Aurangabad.

nnn

City Introduction and Assessment A General

Page 21: CDP

Pg 21Aurangabad Municipal Corporation JNNURM (CDP)

B Economic Profile

1. Employment

Aurangabad City today is an important urban cen-tre in the state having a multiplicity of roles such asan administrative centre, industrial centre and cen-tre for trade & commerce. The employment pat-tern from the 1991 and 2001 census shows thatemployment in the primary sector has reducedconsiderably which is a common trend in almostall urban areas of the state. The employment inthe household industries has also decreased in thelast decade. The 2001 census shows that majority

of the population is engaged in the tertiary sector.Though the total number of workers in the tertiarysector has increased in the last decade the sharetertiary sector in employment generation has de-creased from 54% to 49 %.

The total workers in the last decade have increasedby 200 %. The main workers have increased by 57% whereas marginal workers have grown at veryhigh rate and their number has increased by 8000times. The decrease in the employment in tertiarysector could be due to the considerable increasein the number of marginal workers.

City Introduction and Assessment B Economic Profile

Table: Employment Pattern in Aurangabad

Sector Workers

1991 2001Nos. % Nos. %

Primary Sector 13392 8.27 5170 1.06Cultivators 4162 2.57 2622 0.54Agricultural Labour 5671 3.50 2548 0.52Livestock, Forestry, Fishing, & Plantation 3474 2.14 - -Mining & Quarrying 85 0.05 - -Secondary Sector 58000 35.80 3679 0.76Manufacturing and Processing in 1922 1.19 3679 0.76Household IndustriesManufacturing & Processing in Other than 41193 25.42 - -Household IndustriesConstruction 14885 9.19 - -Tertiary Sector 87837 54.21 240898 49.54Trade and Commerce 28844 17.80 240898 -Transport, Storage & Communication 12780 7.89 - -Other Services 46213 28.52 - 49.54Total Workers 162032 - 486306 - Main Workers 159229 - 249747 - Marginal Workers 2803 - 236559 - Non Workers 411240 - 623564 -Grand Total Population

Page 22: CDP

Pg 22Aurangabad Municipal Corporation JNNURM (CDP)

2. Predominant sectors contribut ing to the economy & Industrial Development

As seen from the employment pattern in section3.1 the tertiary sector provides maximum employ-ment. This section describes the sectors which

The industrial development around Aurangabad ishas taken place in Chikalthana and Waluj (10 kmtowards Pune). Some industrial growth is also hap-pening along the Paithan Road and Beed Road.These developments have significantly contributedto growth of the city. There are quite a few smallscale units with in the city limits also and in the last20 years or so, Aurangabad has emerged as amajor industrial centre for automobile, pharmaceu-tical, breweries, distilleries and engineering sec-tors.

Waluj industrial area is a prime industrial area de-

2.1 Industries

veloped by MIDC spread over an area of 1,518.47hectares. It was started in 1982-83 when MIDCacquired the land. Today, it has attracted renownedcompanies such as Bajaj Auto, Colgate-Palmolive,Ceat Tyres, Wipro, Kenstar, Garware, Wockhardt,Foster, Sterlite Industries Ltd., Franke, Johnson &Johnson and others who have set up their manu-facturing units.

The Chikalthana industrial area developed by MIDChas a total area of 719.68 hectares. The land wasacquired by MIDC in 1965. Today this estate hasthe largest concentration of Foreign Direct Invest-

City Introduction and Assessment B Economic Profile

form the backbone of the local economy. The na-ture of development, present situation and futuregrowth prospects are mentioned here to give a pic-ture of the economic profile.

Page 23: CDP

Pg 23Aurangabad Municipal Corporation JNNURM (CDP)

ment with renowned companies includingWockhardt, Maharashtra Distilleries Ltd., Lupin,Indo German Tool Room, Greeves, Cosmo Films,Hindustan Lever Ltd., HMT, Dagerfost, NRB whichhave their manufacturing units based there.

Table: Industries in Aurangabad and Employment Generated

Sr. No. Type of Industry No. of units in Total employment Annual Turn over the city generated (Rs.)

1 Engineering

2 Oil extraction

3 Dal Mills

4 Sugar Industries

5 Stone Crushing

2.2 Trade and Commerce

Aurangabad is an important centre for trade andcommerce. There is a whole sale vegetable mar-ket at Shahganj and smaller markets at Shahganj,Aurangpura, Osmanpura and Railway Station.There are two mutton markets, five beef marketsand eight shopping centers in the city. Besides theabove there are few shopping streets and informalshopping areas in the city.

Table: Industries in Aurangabad MIDC

Sr. No. Type of Industry No. of units

1 Chemical 12 Engineering 50

3 Cloth 8

4 Pharmaceutical 15 Other 200

Shendre is the third industrial estate nearAurangabad having a area of 927 hectares. It islocated on the Aurangabad – Jalna – Nagpur Statehighway. It is 8 km away from the Aurangabadairport and 19 kms from the Aurangabad RailwayStation.

The weekly market near Jafar gate is held everySunday and the other weekly market at Pir Bazaarsouth of Osmanpura is held every Monday. In ad-dition to the beef and mutton shops mentionedbelow the AMC has issued licenses for 130 muttonshops, 225 beef shops, 10 for pork shops, 13 forchicken and 6 for fish shops.

City Introduction and Assessment B Economic Profile

Page 24: CDP

Pg 24Aurangabad Municipal Corporation JNNURM (CDP)

Table: Shops and Markets in Aurangabad City

Name of the Market Area No. of Shops owned by AMC Privately owned

Shopping Centers1 Shahgunj 1562 Nizamuddin Darga Road 173 Jafar Gate 234 Aurangpura 34

5 Pir Bazaar, Osmanpura 116 Sabzi Mandi 377 Railway Station 318 Nath Super Market 31

Mutton Market

1 Lota Karanja 152 Raja Bazaar 6

Beef Market1 Lota Karanja 112 Barudghar Nala 2

3 Shah Bazaar 44 Moti Karanja 45 Sillekhana 4

Besides the above construction activity and is alsoan important activity providing employment to thepeople. Construction activity gives rise to otheractivities such as brick kilns, stone quarrying andmurum (soil) quarrying.

2.3 Agriculture and allied activities

The city has very little agriculture land within themunicipal limits. As described in Table 000The employment in the primary sector is very less.The surrounding rural area however has agricul-ture land and the chief crop grown is cotton andsugarcane. Besides this other crops such asWheat, millets, gram, and banana are grown. FromAurangabad the goods are transported to othermarkets in the state and country and in few casesproducts are also sent to foreign countries.Aurangabad thus serves as a market place andtransportation centre for these agriculture produce.

Aurangabad has an APMC established in 1934. Themarket trades mainly in Cotton, Wheat, Jowar,Maize, Green gram, Black gram and Pigeon pea.The market has 10 godowns having a total capac-ity of 3080 tons. The APMC does not have any ad-ditional facilities such as ripening units or cold stor-ages. The average daily dispatch during the peakseason is 1500 quintals and during other times itis1000 quintals. The produce is mainly sent to theneighboring states of Gujarat and Madhya Pradeshand important cities within the state. The APMChas about 199 commission agents, 1195 proces-sors, 870 coolies. In all directly and indirectly theAPMC provides employment to 3099 persons.The APMC has five sub markets under itsjurisdiction at Karmad, Pimpriraja, Phulbri,Khultabad and Bazar Savangi

City Introduction and Assessment B Economic Profile

Page 25: CDP

Pg 25Aurangabad Municipal Corporation JNNURM (CDP)

Table : APMC Income & Expenditure (value in Rs.)

Year Income Expenditure Surplus/ Deficit

2001-2002 12060534 12642417 -581883

2002-2003 12243942 49522211 -37278269

2003-2004 13228420 40691308 -27462888

The detail of arrivals of different commodities and their value is given below

Table : Yearly Arrivals and value of commodities

Year Arrivals (Quintals) Value in Rs

2001-2002 161608 230628365

2002-2003 484621 426178106

2003-2004 356369 411454909

Table : Details of Arrivals of Commodities in Aurangabad APMC

Sn. Name of the commodity Total annual arrivals in tons

2001-2002  2002-2003  2003-2004 

1 wheat  7900  5032  5630 

2 Maize  6315  9400  7164 3 Moog  558  503  47 

4 Safflower  90  37  48 

5 Toor  5827  4348  2070 

6 Bajra  7447  4244  5413 

7 Mustard  25  9  5 8 Jawar  2926  1698  3163 

9 Gram  635  320  677 

10 Sunflower  28  84  124 

2.4 Education and allied services

In the past few decades Aurangabad has emergedimportant educational centre in the region and the

state. The Babasaheb Ambedkar Marathwada Uni-versity is head quartered at Aurangabad. The cityhas 240 primary schools, 32 secondary schoolsand 30 degree colleges. Besides these there are

City Introduction and Assessment B Economic Profile

Page 26: CDP

Pg 26Aurangabad Municipal Corporation JNNURM (CDP)

37 different types of colleges in the city including 6engineering colleges, 2 medical colleges, 3 homeo-pathic colleges and 3 ayurvedic colleges.The increasing number of colleges in the city hasgiven rise to services catering to the needs of thestudents such as stationery shops, telephonebooths, hostels for accommodation, tiffin messservices etc. However the exact number of peopleengaged in these activities in not known. Thereabout six hostels for girls run privately by individu-als and community organizations.

2.5 Informal sector

Informal sector has become an integral part of mostdeveloping economies and its definitions and con-cepts vary according to the geo cultural and socioeconomic setting. In Asia the informal sector is saidto comprise of small scale enterprises and unitswhich are usually the main source of livelihood andremain at that level. In many cases they contributeto almost one fourth of the urban economy.

In the city of Aurangabad the activities under thissector include petty shops, hawkers, rag pickersetc. There is no data available on the exact num-ber of people employed in this sector and its sharein the city’s economy. The hawkers are seen alongthe MSRTC Bus stand, Ganjgolai, Railway Line andGandhi Market.

Key Issues

Aurangabad city functions as an administrative cityas well as a centre for trade and commerce. In therecent years it has emerged as an educational cen-tre. The availability of skilled manpower has alsogiven impetus to industrial development includingthe IT industry.

nnn

City Introduction and Assessment B Economic Profile

Page 27: CDP

Pg 27Aurangabad Municipal Corporation JNNURM (CDP)

Slum Population in

5627 5136

15333

19654

29266

0

5000

10000

15000

20000

25000

30000

I II III IV V VI Administrative Zones

Government

Private

CIDCO/MIDC

C. Poverty Profile

1 General Characteristics of Slums

In the year 1991 the AMC carried out a survey tonotify slum areas in the city. According to the sur-vey there are 63 notified slum colonies. The totalpopulation of the slum colonies is 299985 personswhich forms about 81.35 %of the total populationof Aurangabad.

As slums are defined as settlements having noaccess to basic services and infrastructure (evenif they have pucca house) and finance for improve-ment programmes, parts of old Gaothans weredeclared as “Slums” by the AMC.

Out of the total slum population, about 60.23 per-cent resides on Government lands in 26 settle-ments and 30.37 percent on private lands in 14settlements. Remaining 9.40 percent slum popu-lation has been squatting on land owned by CIDCO/MIDC or other semi- public bodies. It is seen thatthe maximum slum population of about 47.18 per-cent is in Zone IV, followed by Zone I and Zone V,slum population being 24.58 percent and 24.23

percent respectively.

As per the 1991 census, almost 22 percent of thecity’s population (about 1,24,558) resides in 53slum settlements. This figure is observed to in-crease in the last few years (although precise in-formation is not available, it is estimated that about30 percent of the population is residing in slumsettlements at present). The total population inundeclared slums is 94,240. The details are givenbelow in table

2. Population Below Poverty Line

The survey of population below poverty line wasdone in 1998 and the according to the survey thereare 15703 BPL households having a population of84653 persons. This forms about 28% of the totalpopulation (as per 2001 census) of the city. All theBPL families stay in the different slum areas.

3. Social set-up

The social composition in majority of slums com-prises of general caste, Scheduled caste, and otherbackward castes. Most of the slums have mixedcastes living in them except slum no. which con-sists of only general caste. Some wards, namely,etc. have predominantly Muslim slum populationwhereas some other wards like 000, etc have pre-dominantly Hindu slum population.

City Introduction and Assessment C. Poverty Profile

Page 28: CDP

Pg 28Aurangabad Municipal Corporation JNNURM (CDP)

4. Employment

Almost all of the slum dwellers are employed in theinformal sector. Most of the people are hawkers,construction labourers and some are employed inthe small industries such as oil extraction. A few ofthem have small shops such as pan stalls, cob-blers, food stalls near medical college etc. Quite afew ladies are employed as housemaids in the sur-rounding residential areas. Most of the work forcecomprises of skilled and semi skilled labourers.

5. Average household size

The average household size is about 5.8 personsper household

6. Housing type

Most of the housing is of Kutcha type except inward 0000 where some pucca and semi puccastructures are seen. The slums along the railwayline and railway yard are all of kutcha type. Around10% of the housing is of pucca type.The slums occupy 300 hectares of landing the citywhich is about 9.2 % of the total area of the city.

7. Health

The Aurangabad Municipal Council runs two OPD’sfor the slum population and there is a mobile dis-pensary that makes frequent rounds to all the slumareas. The mobile dispensary runs in two sessionswith fixed weekly programmes. The OPD treats 50patients daily approximately.

8. Education

The municipal schools provide primary and sec-ondary education to the slum dwellers. There arethree municipal schools in the city which cater tothe needs of the slum dwellers.

9. Location of slums

The slum localities are more towards the northernand eastern part of the city along the main trans-port routes to Nagpur and Amravati. However thereis no distinct pattern in the distribution of the slums.A few slums are located along the railway tracks.The fringe area around the Municipal Border hasalso given rise to slum like colonies. But these aremainly unplanned & uncontrolled developmentshappening around the city.

City Introduction and Assessment C. Poverty Profile

Page 29: CDP

Pg 29Aurangabad Municipal Corporation JNNURM (CDP)

Table: INFORMATION REGARDING SLUMS IN PLANNING AREA

Sr. No. Name of slum and locations Land Ownership Population 1 2 3 4

** Declared Slums

1 Ghati Govt. 6433

2 Ramanagar Private 4438

3 Hamalwada Govt. 3107

4 Gautam Nagar Private 2664

5 Noor Colony Govt. 1051

6 Shahnoorwadi Private 1238

7 Geeta Nagar NA 178

8 Sanjay Nagar Private 2444

9 Indira Nagar Private 7144

10 Phule Nagar Osmanpura Govt. 2631

11 Kirad Pura NA 7351

12 Chausar Nagar Osmanpura Gaothan 282

13 Pahadsingh Pura Private 610

14 Ajabnagar Private 154

15 Harsh Nagar Govt. 5000

16 Garkhenda Govt. 1500

17 Priyadarshini Indira Nagar Govt. 5000

18 Garam Pani Private WAKF. Board 598

19 Prdnya Nagar Private 510

20 Bhavsingpura Village S. No. 131 Govt. 808

21 Prabudhnagar NA 400

22 Mogal Pura WAKF Board 414

23 Sansar Nagar Private 526

24 Mochi Mohalla Govt. 1691

25 Shah Bazar NA NA

26 Bhawasingpura Gaothan NA NA

27 Nagsen Nagar NA NA

28 Khokad Pura NA NA

29 Roje Bagh CIDCO 748

30 Bouthwadi Chiklthana GOVT. 934

31 Naregon GOVT. and MIDC 2665

City Introduction and Assessment C. Poverty Profile

Page 30: CDP

Pg 30Aurangabad Municipal Corporation JNNURM (CDP)

Sr. No. Name of slum and locations Land Ownership Population1 2 3 4

** Declared Slums

32 Brijwadi GOVT. 190933 Masnatpur (Ashok Nagar, MIDC) NA 205134 Fulenagar (Harsool) GOVT. 36435 Sanjaynagar (Mukundwadi) Private and CIDCO 163536 Kanchanwadi A GOVT. 28437 Kanchanwadi B GOVT. 19438 Kanchanwadigaon GOVT. 72239 Nakshatrawadi GOVT. 43040 Nakshatrawadigoan GOVT. 107041 Mitmitagaon GOVT. 100042 Padhegaon GOVT. 250043 Banewadi GOVT. 100044 Itkhedagaon GOVT. 80045 Mukundwadi GOVT. 260046 Harsoolgaon GOVT. 513647 Chikalthanagaon GOVT. 773348 Rahulnagar Private 241249 Sadatnagar Private 76350 Shaha Shaukta Colony Private 23751 Takshashil nagar Private 116152 Ambedkarnagar GOVT. 326853 Damadinagar, Sidharthnagar CIDCO 1881

Table : INFORMATION REGARDING SLUMS IN PLANNING AREA

Sr. No. Name of slum and locations Land Ownership Population 1 2 3 4

** Undeclared Slums

1 Fazil Pura NA 19502 Murlidhar Nagar NA 19653 Kabir Nagar Govt. 19744 Kille Arc NA NA5 Bhimpura Nagar Private 19606 Dimbar Galli Private 19627 Vishnu Nagar NA NA8 Bhanudas Nagar Private 19849 Panchasheel Nagar Private 197510 Jameel Pura Private 196011 Prakash Nagar Private 1984

City Introduction and Assessment C. Poverty Profile

Page 31: CDP

Pg 31Aurangabad Municipal Corporation JNNURM (CDP)

Sr. No. Name of slum and locations Land Ownership Population 1 2 3 4

** Undeclared Slums

12 Shivshankar Colony NA NA13 Nathnagar Private 198014 Budha Nagar Private 197215 Uttam Nagar Private 197216 Kranti Nagar NA NA17 Bhoi Wada NA NA18 Balaji Nagar Private 198019 Gajanan Nagar NA NA20 Pundalik Nagar NA NA21 Vithal Nagar NA NA22 Thakardas Girni NA NA23 Misorwadi NA NA24 Mogal Pura Private 1960

10. Urban Basic Services in Slums

The AMC has provided basic urban services suchas water supply, sanitation, solid waste collectionand internal roads in most of the slum colonies.

Water supply – 10 slums are not provided withwater supply. In the rest of the localities there are330 public stand posts for providing water. Duringperiods of shortage water is also supplied usingtankers.

Solid waste management – There is no organizedfacility for solid waste collection in almost all slums.The waste is dumped in the community bins and inmany cases there are unauthorized dumps fromwhere the council collects the waste for disposal.

Sewerage and Sanitation – 10 slum colonies donot have proper toilet facilities, in most other slumsthey either have individual private toilets or the AMChas constructed community toilets.

There 8 slum colonies which do not have properinternal roads, where as the balance settlementshave paved roads and the total length is 12.66 km.

The entire slum population of 1,24,588 (1991 cen-sus) is served by 98 common toilets. There are1174 seats, of which, 627 are for gents and 547 forladies. Moreover, these are not maintained and theirquality has deteriorated. There are 4 pay and usetoilets, maintained as Sulabh Sauchalayas but nourinals. Almost all the small settlements are pro-vided with open drain gutters.

Table: Details of Sulabh sauchayalaya

Sr.No. Location1. Jafar gate2. Near Siddharth Garden3. Near Aurangapura4. Near Hospital

City Introduction and Assessment C. Poverty Profile

Page 32: CDP

Pg 32Aurangabad Municipal Corporation JNNURM (CDP)

Access to all the slums is provided in the form oftar roads, WBM roads and pathways. About 90percent of the slums have tar roads (apx.12 m wide)for main access covering a length of 4.81 kms,while 80 percent of the settlements have WBMroads (9 m wide) of length 9.18 kms. About 60 per-cent of the slums have 5 m wide pathway accessand their total length is 5.07 kms.

It is seen that access is not a major problems inthe slums, but lack of basic sanitation and surfacewater disposal is a matter of concern.

Table: Targets achieved by the SJSRY

Year Target for No. SHG No. of No. of groups Total amountNo. of SHG formed people provided with sanctioned

Revolving grant Rs.

2000 – 01 39 39 517

2001 – 02 7 14 156 10 95000

2002 – 03 25 25 263

2003 – 04 14 14 158 20 198975

2004 – 05 70 91 910 21 225000

2004 – 06 70 49 502 14 277000

Total 225 232 2586 75 822975

The AMC has set up a separate poverty alleviationcell to look after the above activities. Out of theabove SHG’s 122 groups are of BPL category and1492 families are benefited from it.

DWCUA (Development of Womenand Child in Urban Areas)

Under this program, a group loan (subject to maxi-mum grant of Rs. 1.25 lakh or 50% of the total in-vestment whichever is less) is provided to a group

11. Slum Improvement and Poverty Alleviation Programs

a. SJSRY (Swarana Jayanti Shaheri Rozgaar Yojana)

The AMC has formed self help groups under theSJSRY, in all 232 SHG’s have been formed till date,of these 75 groups have received a revolving grantof 8.31 lakh rupees. In the year 2005-2006 twentyfour SHG’s have been given 2.77 lakh rupees. Thedetails of targets given and SHG’s formed are givenbelow.

of women having a minimum of 10 members. Outof the total investment, 5% is to be provided by thebeneficiaries themselves. The maximum limit of theloan is not fixed. Group finance is provided with50% subsidy, 45 % bank loan and 5% group con-tribution.In the year 2004 - 05 thirteen SHG’s have beengiven loans for starting different types of economicactivities. Loans have been sanctioned to theseSHG’s and a total grant of 11.50 lakhs has beendisbursed. In the coming year a target of forming32 SHG’s has been set.

City Introduction and Assessment C. Poverty Profile

Page 33: CDP

Pg 33Aurangabad Municipal Corporation JNNURM (CDP)

Table : Targets achieved by the DWCUA

Year No. DWCUA No.Proposals No. of proposals Loan in Grant in Group formed sent to bank accepted Lakh Rs. Lakh Rs.

1998 – 99 1 1 1 0.50 0.501999 – 00 3 3 2 1.45 1.452000 – 01 2 2 - - -2002 – 03 3 3 1 0.50 0.502003 – 04 6 6 3 1.75 1.752004 – 05 6 6 1 0.50 0.50

Total 21 21 8 4.70 4.70The groups are running various enterprises suchas brick kiln, tent supplier, ready made garments,fishing, goat rearing, catering and grain stores. Allthe above groups are women SHG’s. Two of theabove groups have repaid their loan and othergroups are also doing well and paying the install-ments regularly.

b. VAMBAY (Valmiki Ambedkar Malin Basti Aawas Yojana)VAMBAY is a centrally sponsored scheme aimingat shelter delivery to the poor. The main objectiveof the scheme is to provide or upgrade shelter forthe people living below poverty line in urban slums.The ministry of urban development and povertyalleviation provides guidelines for the implementa-tion of VAMBAY. The target group for VAMBAY isall the slum dwellers in urban areas that are belowpoverty line or E.W.S. without adequate shelter. Inthis scheme the state government contributes 50%of the cost of the tenement and 40 % is given bycentral government. The beneficiary needs to con-

tribute 10%. In Maharahstra MHADA is the nodalagency for constructing the houses under theVAMBAY.Under the VAMBY scheme a total of 85 slum settle-ments have been identified for rehabilitation in threephases. Construction of tenements under thephase I with 125 beneficiaries is completed. A listof 2085 beneficiaries in Phase II has been approvedby MHADA and identification of beneficiaries inPhase III is under progress. A proposal for con-structing 2151 tenements is being prepared.Key Issues1 Absence of appropriate and adequate informa-tion on slums and levels of services in slums2 Infrastructure and service requirements of slumsare inadequate; most slums seem to be depen-dent on ground water for their daily needs.3 Very few voluntary community-based organiza-tions working in the slum areas; Most of the slumsare on encroached land, and land tenure is a ma-jor problem, as a result of which slum dwellers donot invest adequately in housing, fearing eviction.

Table Targets achieved by Poverty Alleviation SchemesSl. Program No. of Beneficiaries Achievements (no.)No. Targeted

1 Urban Self Employment 521 2992 DWCUA 51 Groups 023 VAMBAY 103 1034 Family Welfare Scheme 450 450 SHG’s5 Savtribai Phule Dattak Palak Yojana 14250 Per Year 14250 Per Year6 Dr.Ambedkar Uniform Scheme 22363 Per Year 22363 Per Year

City Introduction and Assessment C. Poverty Profile

Page 34: CDP

Pg 34Aurangabad Municipal Corporation JNNURM (CDP)

D. Utilities and Infrastructure

1. Water supply

Water Planning

Presently the Aurangabad Municipal Corporationis supplying water @ about 100 liters per capitaper day. It is essential to supply 150 liters per capitaper day. For this it is essential to improve waterdistribution system taking into account the popula-tion of city during 2025 A.D. The existing watersupply system is highly insufficient and cannot bearthe burden of increasing population. Therefore theAurangabad Municipal Corporation has startedplanning a new water supply project.

There has been rapid progress in the development ofthe city during last three decades. Similarly some prob-lem cropped up. One of such problems is drinking wa-ter and its use for different purposes.It is expected thatthere should be a clear concept of Aurangabad Vision2025. Water is life. It has been tried to paint a picture inthis note about increase in population and industrializa-tion and water supply system for the same by givingintegrated though to it.

Some time back through a concept of “AurangabadCity Vision- 2021” the Chief Minister of MaharashtraState has formed a committee under the chairman-ship of divisional commissioner to prepare a planfor 2021 with respect to drinking water, electrifica-tion, drainage, road etc. The committee comprisedof experts like shri Madhav Chitale, Prof.Morwanchikar,Dr.Warade,Chief Engineer ofMaharashtra Jeevan Pradhikaran ShriDumkondwar,retired Chief Engineer Shri Narsapuretc. The committee held several meetings and dis-cussed following issues.

Nandur Madhmeshwar & Tembapur Dam etc. maybe considered as an alternative to Jayakwadi Dam.However, an on spot study of these Dams revealedthat they cannot be treated as alternative to watersupply source of Jayakwadi Dam.

The Committee suggested good maintenance ofNahar-e-Ambari & Nahare-e-Malik Ambar whichare not only serving as important source of waterto the city but they also city’s cultural heritage. Thisnahar supplies 2 MLD water per day for 7 to 8months in a year. Therefore a package treatmentplant of 2 MLD capacity should be prepared forwhich an amount of Rs.30 Lakh would be required.A special provision should be made for this pur-pose in the annual budget.

There are in all 588 well in the different parts of thecity. These wells require strengthening. It was dis-cussed water of these wells should be used forgardening and other purpose.

The Committee also received suggestions fromexperts that in future Jayakwadi Dam should beused as main source of drinking water to the city.Therefore planning should done keeping in viewthe need of water in the year 2031by lay a parallelwater supply line. This parallel project should in-clude pumping machinery, filternation plant andother components in the first phase 2021. Accord-ingly a line estimate has been prepared and actionhas been proposed on point no.1,2 & 7 of report.About point no.9 the Aurangabad Municipal Cor-poration has launched a compaign for regulariza-tion of unauthorised water connection under thename of “Abhay Yojana”. This scheme will beimplemented in future also. The Aurangabad Mu-nicipal Corporation has starated water every auditin the year 2004-05 and this is going to give ac-count of quantity of lift and use of water.

Existing water supply and its capacity

Old water supply pipe line of 700 mm dia 42 MLDNew water supply pipe line of 1200/1400 mm dia 88 MLD

Total 130 MLD

City Introduction and Assessment D. Utilities and Infrastructure

Page 35: CDP

Pg 35Aurangabad Municipal Corporation JNNURM (CDP)

Requirement of Water

There are several elements in water supply. Inwater supply system following basis componentsare involved:l Drinking waterl Livestockl Water for industriesl Gardens & Forestsl Constructionl Water for amusement

At the same thoughts have also been given to vari-ous problems. It was also necessary to think ofdrainage system in urban water use. There is dif-ference between water draining out from drinkingwater use and the water draining out from indus-trial use of water. And there fore there are differentmethods of treatment of these waters.

Requirements of Drinking WaterThe following statement the progress in city popu-lation during last three decades and also expectedincrease in it in future decades

Year Population Ratio of Growth Remarks

1971 1,75,000 — —

1981 4,25,000 2.4 Industrial growth

1991 6,25,000 1.5 Extention of Cidco

2001 9,65,000 1.4 -

2011 13,72,000 1.4 -

2021 16,50,000 1.3 -

2031 25,00,000 1.3 -

The expected population of the city in the next25years is 2 more than 20 lakh. As to the planning ofwater supply scheme it is a criteria than the palnningshould be for next 15 years period. It is necessaryto do planning of 2031 in the year 2001. In thisproject the main pipe lines should be designed tak-ing into account the needs of 2031 and other equip-ment as per needs of 2021 as a phase I project.Accordingly the city would need following quantityof water for 2021 x 2031.

l City population (2021) - 20,00,000

l Daily need in 2021 - 295 MLD

l City population (2031) - 25,00,000

l Daily need in 2031 - 375 MLD

l Quantity available today - 75 MLD

Water requirement for live stock :

Some villages have been included in municipal lim-

its of AMC. These villages have a sizeable number

of livestock such as cows, bulls, buffalos, pigs,

hens, goats etc. Even pet dogs are also there. All

these Livestock require water. A quantity of 5 litres

per capita is added in drinking water, but facts are

otherwise. Buffalos and cows require 80 litre water

per capita. The correct number of livestock is not

available. The Irrigation commission has fixed the

quantity of water required for animals. Consider-

ing this criteria, the city is short of one MLD water.

The city would require one more annually in 2021.

City Introduction and Assessment D. Utilities and Infrastructure

Page 36: CDP

Pg 36Aurangabad Municipal Corporation JNNURM (CDP)

Water requirement for Industries :

As per 1996 figures 5.2 % of total population ofMaharashtra state was engagaed in Industries. If

Water Requirement for Construction :

The City is noticing increase in construction activi-ties in the fields of roads, bridges, houses, colleges,hospitals, schools and housing projects. A quantityof 20% of drinking water is used for these construc-tion activities. It means generally 21 MLD water isused for civil works from different sources.

Requirement of water in 2021 :A) Drinking water - 110.0 MLDB) Livestock - 001.0 MLDC) Industies - 005.5 MLDD) Parks & Gardens- 002.0 MLDE) Civil works - 021.0 MLD

Total - 139.5 MLD

i.e. - 140.0 MLD

Thus out of above 110 MLD will be required fordrinking purpose and 30 MLD for other purposes.110 MLD can be derived from main source andremaining quantity of 30 MLD from other sourcesviz. wells, borewells and other old existing &sources.

As such the city would require 110 MLD of waterper year. A report is given below about the existingsources and planning for additional and alternatesources of water. It is specifically mentioned herethat a planning is essential for existing parks &Gardens. By strengthening th existing sources otherthan main source i.e. wells, borewells etc. includ-ing water which will be available through efluentplant we may get water for this purpose. Thus tak-ing into account this quantity the requirement ofwater in the year 2021 will be 100 MLD. For this aparallel scheme should be prepared. For thisscheme and for inprovement is existing water sup-ply scheme, provisin of funds will have to be made.

Alternative Sources :

As far as main source of water supply is concernedthe Jayakwadi Dam is under consideration. As analternative source, the Nandur Madhmeshwar Damand Tembapuri Dam (as a support source) are alsounder consideration. The Nandur MadhmeshwarDam is constucted on Godavari River as a pick upware. It is located in Vinchor Taluka of Nashik dis-

City Introduction and Assessment D. Utilities and Infrastructure

this figure is applied to Aurangabad city the popu-lation figure working in Industries comes as follows:

Year Population Per capita water Total M.L.D.2001 50,700 150 2.77

2021 1,04,000 150 5.55

Water Requirement for Parks and Gardens :

Aurangabad Municipal Corporation has developedparks and Gardens in an area of about 100 hect-

Year Area (10%) Garden Area Requirement of water M.L.D.

2001 1400 hect. 100 1.0

2021 1540 200 2.0

are. Taking into account the open lands, the re-quirement of water for parks & Gardens would beas follows:

Page 37: CDP

Pg 37Aurangabad Municipal Corporation JNNURM (CDP)

trict. It is located at a distance of 185 Km fromAurangabad. Its level is 530 m and capacity is 7.00DLM (220 DLM). This Dam is dependent of otherDams such as Darna, Bham, Mukne x BhavliDams. the lifting capacity form this Dam is less by74 m. However, as compared to Jayakwadi source(45 Km distance from others) and NandurMadhmeshwar source (185 Km. away from city)have a difference of more than 140 Km.

Threrefore if it is decided to lift water from thissource as per standard of 2.40 m/km the lift is willbe more than 325 m. This can save electricity con-sumption to some extent. However, feasibility ofthe proposal will be to be properly checked. There-fore proper decision will have to be taken whetherNandur Madhmeshwar source is to be used or oth-erwise. For undertaking above works an expendi-ture of Rs.100 crore is expected. Moreover, watercan be lifted through gravity which can result issaving of electricity to some extent.

On the northern side of the city there is anothersource of water viz. Savangi Tank adjoining JalgaonRoad. Possibility of increasing its capacity can beexamined. Presently an intake well is constructedin this tank. This well can be improved for morewater supply.

For these works an amount of Rs.100 crore will berequired.

Jayakwadi Source :

Jayakwadi Dam which is known as “Nath Sagar”was commissioned in the year 1975. It is situatedat a distance of 45 Km from the city. It has got asource of 2909 MLD with dead level of 738 MLD.City can depend on this source for supply of 140MLD in the year 2021. A study shows that since,beginnig the Dam was filled upto 25-30% Capacity

only. The reason for this is that there are 8 to 9dams constructed on Pravara x Godavari rivers onthe areas. Which are located before rivers reachesJayakwadi Dam which stop flow of water uptoJayakwadi Dam. This also results in minimising thewater level in Dam every summer which goes upto455.52 M. During the same season water is re-leased to low lying areas of Jalna, Beed, Parli etc.This also adds to further difficulties. Because ofthese problems Aurangabad city faces difficultiesof water supply during summer. During May 2004the water supply was distupted for city for entire 24hours. To avoid this situation it is necessary thatIrrigation Dept. should not release water after mini-mum water level of 455.52 M. Similarly there is dif-ference between sea level of Dam which is 455.52M and that of city which is 611 SML. This requireslifting of water through pumping which results inexhorbitant billing of electiricity. If electricity ischarged at agriculture rate, this will give some fi-nancial relief to AMC. Efforts are required to bemade or higher level to solve this problem. If boththe above problems are solved then JFayakwadiDam is a reliable source of water supply to the city.

An amount of Rs.100 crore will be required in fu-ture for the improvement of above source.

Additional distributory pipe line for Pundlik Nagar,and Shivaji Nagar have been sanctioned forRs.9.93 crore out of which an amount of Rs.3.20crore has been spent on this work. Works amount-ing to 4.675 Crore are in progress.

Revision of Water Charges :

Presently the water supply scheme of AMC is run-ning into losses. Even effort to run this scheme on“No profit No loss” basis did not succeed. It isthrerefore necessary to increase water charges tominimise the losses. This can be done in phases.The water charges are fixex on the basis of dia of

City Introduction and Assessment D. Utilities and Infrastructure

Page 38: CDP

Pg 38Aurangabad Municipal Corporation JNNURM (CDP)

water connection. If meter system is commissionedthese charges would be for actual consumption ofwater and thus theft of water can be avoided.

Rain water Harvesting System :

The ground water level increases due to drainagewater and reharvesting of rain water into ground.This will result in availability of water in borewellsin urban areas. This water can be used for dailyuse for puposes other than drinking water purpose.This will also minimise the burden AMC to someextent. During rainy season the pressure onsewevage treatment plan will also minimise.

It is suggested that while preparing soak pits, bedconcreting should not be done. This will allow wa-ter, to merge in the ground thereby raising theground water level.

For educationg the builders, developers,architechts, plumbers, peoples, representatives,engineers, Govt. and Semi Govt. Employees aTraining workshop should be conducted on thesubject of rain water harvesting system.

Drainage water can be used for gardening etc. af-ter its treatment. This will also ease the distributionof drinking water of AMC.

A proposal has been initiated to make Rain waterharvesting system mandatory while giving com-mencement certificate for constuction and to in-clude it appendix V of development Control Rulesby starting proceedings under section 37 ofMaharashtra regional Town planning act 1966.

Electricity charges for the water system

Seven Electric Pumps of different horse powershave been installed at pumping station for purpose

of lifting water from Jayakwadi Dam source. Theseelectric pumps function 24 hours a day The AMChas to pay an exhorbitant amount of Rs.146 lakhper month to MSEB towards electricity charges sumremedical action can help in redusing thisexhorbitant billing .

Concssion is available if the power factor is keptas 0.96 or more. presentaly The A.M.C is gettingconcssion of Rs.0.60 lakh per month in respect ofsome of the pumps. If the power factor is kept at0.96 more concssion can be obtained .

The existing pumping machinery has become veryold sinceS it was installed in the year 1975. This isalso resulting in more billing. These should be re-placed with new pumping machinery action in thisdirection has been statred.

By installing Solar system at pump station premisesexpanditure on electircty consumption can becurtailed. This will required an amount of Rs.50 lakhfor providing Solar system.

Electricity can be saved by using 80 HPSV lamp isinsted of 125. HPSV lamp . Action is benig takenis this regard.

Charging Agricultural use rate for con-sumption energy by A.M.C

As per existing system the electrictiy connectionshave been done on HTP-ITI basis. AccordinglyMSEB levy charges. The pumping stations are lo-cated in rulel areas. Therefore MSEB authoritieshave been requested to charge at the rate agricul-tural use of energy.If the energy consumption charged at the rate ofagricultural use then the billing amount will comeRs 200 Crores.

City Introduction and Assessment D. Utilities and Infrastructure

Page 39: CDP

Pg 39Aurangabad Municipal Corporation JNNURM (CDP)

Transportation of Garbage:

Types of Number of Capacity Total trips Total K.M. Balance vehicle vehicle

Compacter 01 7 M.T. 3 35 K.M. 5 M.T.Truck 13 3 to 4 M.T. 2-3 20-40 K.M. 4 M.T.Truck-Tipper 18 2 to 3 M.T. 2-3 20-40 K.M. 3 M.T.Tracter teller 10 2 M.T. 1-2 10-20 K.M. 2 M.T.Auto Riksha 06 350 K.G. 6-8 60-70 K.M. 300 K.G.

As on today 300 M.T. garbage is collected per day.With increase inpopulation the quantity of garbage

will also increase. Presently the sanitation vechilesare insufficient to lift the garbage. They have be-come old also.

Disposal of Garbage:

l Name of Place Mandki 70 acres outside Municipal lilmitsl Distance from city 10 K.M. from central Bus Stand

The General Body of Aurangabad Municipal Cor-poration has accorded approval in 2003 to the re-vised Urban Solid Waste Management & Disposal

Rules 2000. As per these rules the garbage hasbeen categorized. Also improvement was donein stacking, transport and disposal of garbage.

Improvement in collection & Disposal of Gurbage:

l Effortrs to produce fertilizers out of garbage at ward levell Starting a project at Siddhart Garden Samarth nagar for vermin compost.l Transportation of 1 Ton wet garbage of Aurangabad vegetable market to Siddharth Garden for vermin compost.l Construction of compost pits for producing of fertilizer at 16 places (2 places in each ward)l Proposal of vermin compost units near each weekly marketl Efforts to make 100% use of vechilesl Covering all garbage vechiles by tar panlinl Use of Sweeping Sticks with long handle, masks, Gum bootsl Sweeping of roads on all 365 days of the year

City Introduction and Assessment D. Utilities and Infrastructure

2. Solid Waste Management

Implementation of Solid Waste Management Act2000. A piece of land admeasuring 25 acres out ofGat No.165 of village Naregaon has been madeavailable by the Collector Aurangabad for disposalof solid waste. A separate solid waste manage-ment unit has been established with a medical of-ficer as its head. For developing this land viz: con-struction of boundary wall, interal roads, pits, land

scaping outside wall, approach road etc. an amountof Rs.15 crore is required.

Collection of Waste and Stacking

A Quantity of garbage 300 TonnesB No.of Sanitory Workers 1522C No.of RCC Kachra Kundis 1635D No.of Community Dust Bins 246E No.of Spot not fixed for garbage 155F No.of Hand carts 500

Page 40: CDP

Pg 40Aurangabad Municipal Corporation JNNURM (CDP)

Alternate land for disposal of solid waste

Following are the efforts made by Aurangabad

Municipal Corporation to find out suitable land for

disposal of solid waste. Presently municipal

Trenching Ground is situated at Mandki which 2.6

km away from Airport. A PIL was filed by Dr.Shaik

Shafeeq in the High Court. Since the Aurangabad

Municipal Corporation had not taken No Objection

certificate from Airport for Mandki Trenching

Ground, the Hon’ble High Court has given direc-

tions on 6-2-2003 to shift the Trenching Ground

from Mandki. Therefore the Aurangabad Munici-

pal Corporation had started to find out suitable land

at various places.

A piece of land out of Gat No.135 of Karodi Village

is selected by Aurangabad Municipal Corporation

for which No Objection Certificate has been issued

by Sr.Manager, Airport Aurangabad, Regional of-

ficer, Pollution Control Board, Dy.Conservator of

Forests, Asstt.Director of Town Planning, CIDCO

Administration, Sr. Geiologist, Superiondending

Archeaologist & C.E.O. Zilla Parishad, Aurangabad.

A proposal for transfer of this Govt. land has been

sent to collectorate on 21-3-2003.

The hon’ble High Court after taking into consider-

ation the oppistion on of Village Panchayat has in-

structed Maharashtra Govt. to transfer the land

within 6 months.

On 25-11-2003 the Divisional Commissioner and

collector Aurangabad were instructed to make spot

inspection of the land and to submit a report and

also see that the villagers do not oppose the pro-

posal.

The villages of Karodi submitted a representation

on 25-12-2003 to the collector, Municipal Commis-

sioner, C.E.O. Zilla Parishad and B.D.O.

Aurangabad opposing the solid waste project at

Karodi. In respect of this land at Karodi, a request

has been made to member secretary, Maharshtra

State Pollution Control Board vide letter no.279/

2004 dt.24-2-2004 for issue of Authorisation Cer-

tificate. The same is pending. Even after making

all out efforts on war footing by Aurangabad Mu-

nicipal Corporation the said land has not been trans-

ferred to Aurangabad Municipal Corporation for

solid waste management Project. Therefore the

Aurangabad Municipal Corporation has again

started efforts to find out some suitable alternate

land and Govt. help is also sought vide letter ad-

dressed to shri.B.C.Khatua, Principal Secretary,

Water supply & Sanitation Depaertment,

Mantralaya, Mumbai.

Pre-monsoon Zero Garbage Campaign

Special sanitation campaign have been com-

menced through ward officers. Zero Garbage cam-

paign is being implemented. Similarly as a pre-

ventive measure blood samples are collected by

health centres, halogen tablets are distributed,

leacking of pipeline is controlled, antimosquito

medicines are spreayed.

For medicines required at hospital, health centres,

laboratories, medical equipments, and medicines

for preventive measures etc. during next 20 years

an amount of Rs.65 Crore is needed.

City Introduction and Assessment D. Utilities and Infrastructure

Page 41: CDP

Pg 41Aurangabad Municipal Corporation JNNURM (CDP)

Action Completed

1. Prohibition on garbage on road 10%2. Awareness among public to separate 2 bins are compulsory 63% public wet garbage from dry garbage has been approached.3. 100% cleaning of roads Main road 100%4. Ban on garbage on open space This has been banned on 38 places5. Coverage of garbage Truck 100%6. Lifting of garbage before kundis are overflown 68%

Public Participation in Solid Waste Management

It is necessary to implement a scheme of public-private partnership for Solid Waste Management.This include;

1. Adoption of Slums2. Use of Modern technology for housing management3. Participation of NGOs in sanitation works

Public Awareness:

l Hoardings containing sanitation awareness at different placesl Advertisement on local T.V.channelsl Posters, Pamphletsl Publilc Participation

City Introduction and Assessment D. Utilities and Infrastructure

Administrative Reforms

l Establilshment of separate solid waste management unit on 17-12-2003l Zero Garbage compaign deployment of more workers in the words having more quantity of garbage –100% lifting of garbage – cleaning of nallahs – spraying of anti- masque to medicines.l Plastic Ban Unit formationl Check up of sanitary workers.

Page 42: CDP

Pg 42Aurangabad Municipal Corporation JNNURM (CDP)

Year Propose/Estimated Disposal Total Capacity Population Per-head

2001 8,73,000 120 102.00 M.L.D.2011 13,72,000 120 165.00 M.L.D.2021 16,50,000 120 198.00 M.L.D.2031 25,00,000 120 300.00 M.L.D.

Present About 11,00,000Population

The AMC has prepared a water supply scheme forthe needs of populated estimated in 2031. In thisscheme the need of water is taken @ 150 litre percapita. As per criteria in drainage system this isfixed 80% i.e. 120 liter per capita. As such for theyear 2031 the system will have to be prepared for300 MLD and for 2021 this will be for 200 MLD.

Planning of Scheme :

The pipe lines under the water supply system workon the method of pressure whereas under drain-age system the pipes work on the basis of gravity.Therefore it is necessary to take into considerationthe geographical status of the city. A study of re-

port prepared by M/s. Shah Consultants it is re-vealed that city has been divided in two parts con-sidering the land slope, rain water flow, river flow,catchment area, geographical slope etc.

Catchment Area :

Kham River Catchment Area - Zone (A) :

In this Zone A, the old part of city, Municipal limits,additional municipal area including Padegaon,Mitmita, Bahvsinghpura, Garkheda, Shahnoorwadi,Part of Harsul, Kanchanwadi, Nakashatrawadi etc.has been included. This Zone A has further beendivided into seven parts and considering natural

3. Sewerage and sanitation

For disposing off drainage water of the city a pump-ing station has been set up at Banewadi from wherethe drainage water is flown to Oxidation Pond atKanchanwadi. Presently the functioning of both thepumping station and Oxidation Pond is out of order.Efforts are being made to put this system withmamimum capacity so that the Nallah water may beclean and there should be less pollution is the city.

The work of construction of 5.26 MLD S.T.P. inJhalta area for Zone B is in progress. Civil work isnearing completion. Pumps have been supplied forengineering work. After remaining machinery isreceived the work will be completed and the plantwill be commissioned.

Present condition of drainage system :

At present there are two treatment palnts of 5.26and 5.38 capacity. It is necessary to make plan-ning future drainage system taking into account thepollution condition of the city. While doing so it isalso necessary to fix up the boundaries and limitsof the Nallahs flowing through the city limits.

Population Vision

Previously while preparing drainage system the citypopulation estimated in 2001 was taken as 2.00lakh. Similarly the Govt. Engineering College hadsuggested to prepare scheme for 100 MLD cost-ing Rs.700 Crore. However, considering the groundrealities the following picture emerges.

City Introduction and Assessment D. Utilities and Infrastructure

Page 43: CDP

Pg 43Aurangabad Municipal Corporation JNNURM (CDP)

slope, Nallah flow, water flow etc. main sewer lineshave been designed. These lines are as follows :

Main Sewer A : Western part of Bibi Ka Maqbara

Main Sewer B : Part of Kham River flowing throughHimayat Bagh Nallah flowing through.

Main Sewer C : Majnu Hill to Siddharth Garden,Barudgar Nala- Saraswat Bank-Nageshwarwadi.

Main Sewer D : Nallah flowing through Hotel RamaInternational to Samarth Nagar-S.B. Colony-Nageshwarwadi.

Main Sewer E : Forest Office - Kranti chowk-KhamRiver.

Main Sewer F : Nallah flowing through St.FrancisHigh School-Paithan Gate.

Main Sewer K : Kanchanwadi-Nakshatrawadi -Wadagaon cart.

Catchment Area of Sukhna River - Zone (B)

In this Zone B, the areas of Naregaon, Brijwadi,Masnatpur, Chikalthana, MIDC, Mukundwadi,Cidco, Harsul, Jadhavwadi etc. For these areas twomain sewer lines have been designed which areaas follows.

Main Sewer L : Nallah flowing through N-2, Cidco-Sukhna River.

Main Sewer M : Chikalthana Gaothan-ChikalthanaMIDC - Sukhna River.

Survey of Nallahs & Removal of Encroachments

A majority of Nallahs have not been entered intoeither revenue reord of city survey record. There-

fore a survey of all these nallahs has become nec-essary. After survey boundaries and limits of thenallahs will be fixed and encroachments will be re-moved. For this purpose an amount of Rs. OneCrore will be required.

Aurangabad is the capital city of Marathwada Divi-sion and is its Divisional Headquarter’s. The city ishaving historical and archaeological importance.In view of this planning of infrastructure viz: roads,electricity, gardens, schools, hospitals and waterhave been done. In fact underground drainagesystem is also as important as water supply water.But unfortunately this has been neglected. It wasnecessary to consider underground drainage sys-tem at per with water supply system. As on today120 MLD drainage water is disposed off throughincomplete drainage pipe lines and on the mercyof natural flow of river & nallahs. This water is usedfor agriculture without any treatment. Which is re-sulting in harm to agril. land and underground wa-ter is also being polluted. Due to this it has alsobecome difficult to use borewell waters. This isalso adverserly affecting implementation of Envi-ronment Report.

In the year 1972 a drainage system was preparedby the erstwhile municipal council for the use ofpopulation of 2 lakhs expected in 2001. It was ascheme of 15 MLD capacity.

The estimated figures of city population haveproved completely wrong due to 4-5 times increasein population. Accordingly all schemes have beenproved to insufficient.

Recently a join survey was conducted alongwithofficers of Govt. Engineering College. The collegevide letter no.ENV/2002/12 has submitted its re-port. This is a very preliminary report and does notthrough any light on the details of the project.Therefore it is necessary to prepare an exhaustivereport on this subject. The govt. Engg. College

City Introduction and Assessment D. Utilities and Infrastructure

Page 44: CDP

Pg 44Aurangabad Municipal Corporation JNNURM (CDP)

has also suggested to prepare the scheme forRs.170 Crore. However, this will need funds andat the same time there is urgency to prepare thisscheme other there is apprehension that environ-ment and health of the city will collapse.

The work of de-silting the nallahs, channelising andconstruction of security walls will cost an amountof Rs.125 crore.

Measures for managements of Nallahs,Drainage Lines etc.

Crores of rupees are required for de-silting of ex-isting Nallahs. After the funds are made availablea comprehensive planning can be done. Howeverit is fact that flow of drainage water through opennallahs makes the environment of the city polluted.Proper timely action in respect of drainage systemwill help in controlling the flow of drainage water &the condition of environment will also improve.There are encroachments on several nallahs flow-ing through the city. Therefore it is the need of thetime to conduct survey of all the nallahs, to removethe encroachments and to fix up boundaries as perdevelopment plan by initiating action under sec-tion 37 of Maharashtra Regional Town Planning ofAct 1966. Therefore action is being proposed toconduct a total station survey for which an amountof Rs.10 crore is expected.

Construction of Sulabh Shruchalayas

It is necessary to constructed sulabh shouchalayasat thickly populated areas and at govt. offices. TheAurangabad Municipal Corporation has alreadyconstructed sulabh shouchalayas near SiddharthGarden (Central Bus Stand) and centrally locatedAurangpura. More shouchalayas will be con-structed on BOT basis or by its own funds byAurangabad Municipal Corporation.

4. Traffic and Transportation

Nashik-Nirmal High way passes through the cen-tral part of Aurangabad city. Due to traffic of heavyvehicles on this road Beed by Pass Road has beenconstructed as a parallel road to Jalna Road.Flyover bridges have been constructed at RailwayStation and seven Hill areas.

In the development plan of Aurangabad city roadsof 45 to 60 metre width have been proposed in dif-ferent areas of the city. The details of land acquisi-tion and estimated expenditure for these road arementioned in statement no.2.13.

To connect various road to Beed by Pass Road itis necessary to construct Flyover Bridges at ShivajiNagar, Sangram Nagar, & Shahanoor Miya Dargah.Similarly Flyover Bridges and Footover Bridges arealso necessary to cross Railway Line to approachSilk Mill Colony & Hamalwada areas which areaadjacent to Railway Station. Subways area alsonecessary at places of heavy traffic viz: RailwayStation, Bus Station, Collect orate etc.

Maharashtra State Road Development Corporationhas proposed Flyover Bridges at following places:

A) Kranti ChowkB) Mahavir ChowkC) Malik Ambar Chowk GhatiD) Mondha Naka

An estimated cost of Rs.167 Crore is expected tocomplete these works.

The Govt. of Maharashtra has sanctioned follow-ing road works under Aurangabad city IntegratedRoad Development Programme:1. Railway Station to Harsul Road (Repairing on Nagpur Pattern)2. Mahavir Chowk to Chikalthana Road (construction of Nagpur Pattern)3. Seven Hill to Shivaji Nagar 100' Development

City Introduction and Assessment D. Utilities and Infrastructure

Page 45: CDP

Pg 45Aurangabad Municipal Corporation JNNURM (CDP)

City Introduction and Assessment D. Utilities and Infrastructure

plan Road4. Old High Court to Aurangpura via Tapdia Ter race 80' Development plan Road5. Savarkar Chowk to Jawahar nagar Police Station 80' Development plan Road6. Aurangpura to Mill Corner 80' Development plan Road7. Gajanan Maharaj Mandir to Pundlik nagar Road (upto CIDCO boundary)8. Kranti chowk to Railway Station 100' Develop ment plan Road

9. Konkanwadi Chowk to Hotel Panchavati 80' De velopment plan Road10.Soot Girni To Peer Bazar 80' Development plan Road

The Aurangabad Municipal Corporation has takenup the work of beautification of 33 traffic islands.These are mentioned below:Efforts will be made to develop the traffic islandsthrough NGos by allowing them to fix up their hoard-ings to minimize the burden on Aurangabad Mu-nicipal Corporation finances.

01 Repairing and colouring of Kamgar Chowk in front of Aurangabad Municipal Corporation Head Office02 Beautification of Paramveer Chakra Abdul Hameed Chowk in front of Central Octroi Naka03 Development & Beautification of Bhausaheb More Chowk in Laxmi Colony04 Beautification of Vivekanand Chowk in Ward No.2905 Beautification of road divider between Baba Petrol Pump and Hotel Kartiki06 Repairing and Beautification of Dr.Babasaheb Ambedkar Statue Chowk, Bhadkar Gate07 Beautification and fixing railing to waterfall adjacent to pump house at Jubilee Park08 Repairing and Beautification of Samrat Ashok Chowk at Kirana Chawadi.09 Repairing and Beautification of Raj Hans Bird Chowk at Maheshnagar10 Re-planning and Beautification of Chowk at Gajanan Maharaj Mandir in Ward No.1811 Designing & Development of Transparent Artificial Flowers model opposite employment office.12 Development of chowk at Seven Hills13 Repairing and development of Champa Chowk14 Re-designing and beautification of island in front of Lucky Juice Centre at Painthan Gate15 Refunctioning of water fall near Delhi Gate and tree plantation16 Colouring of 14 traffic islands in ward No.1417 Providing Gun and Beautification of traffic island in from of collect orate18 Fixing fountains and Beautification of Chhatrapati Shivaji Maharaj Museum19 Repairing & Beautification of traffic island in front of civil hospital near City Club20 Development of Anand Gade Chowk at Peer Bazar in word No.2721 Beautification of sign Boards in Rama Nagar, Chetna Nagar, & Sindhi Colony etc. areas22 Development Beautification of island in Milind Chowk near Little Flower School23 Repairing, Beautification and providing railing to island near Rangeen Gate24 Repairing of Chatrapati Shahu Maharaj Statue island, footpath and traffic channeliser25 Repairing of Kranti Chowk island26 Beautification of Mahavir Chowk island27 Development of small traffic island adjacent to kranti chowk28 Repairing & Beautification of four traffic island located on road between Satish Motors and Aurangpura29 Beautification of road dividers between Divisional Commissionerate and Annabhau Sathe Statue Chowk30 Repairing & Beautification of traffic island infront of Kartiki Hotel31 Beautification of road divider in front of Sales Tax Office near Railway Station32 Beautification of road dividers between Kranti Chowk and Mahavir Chowk33 Construction and Beautification of road dividers between Little Flower School and Laxmi Colony

An estimated amount of Rs.3 crore is required for all these works.

Page 46: CDP

Pg 46Aurangabad Municipal Corporation JNNURM (CDP)

City Bus Transport

Providing City Bus Transport facility to citizens fallunder the category of “optional duties” ofAurangabad Municipal Corporation as per provi-sions of section 66(20) of Bombay Provincial Mu-nicipal Corporations Act 1949. The MaharashtraState Road Transport Corporation was providingthis facility. However, due to losses the said cor-poration has stopped this services. Keeping in viewthe inconveniences caused by common public theAurangabad Municipal Corporation has decided totake over this city transport services and to run thesame on B.O.T. basis.

Presently the ratio of air pollution in the city is com-paratively less. In future if the city faces problemof air pollution, pollution-free buses will be neces-sary. Therefore it will be better if permission is givenfor CNG buses on the basis of Delhi TransportService.

For the first time it is proposed to run 150 city buseson 25 city routes on BOT basis through a privateagency. This service will start from Januray,2006.The General Body and Standing Committee videresolution no.89/1 dt.19-10-2005 and no.81 dt.18-10-2005 respectively have accorded sanction toagreement between Aurangabad Municipal Corpo-ration & Private Agency.

The above mentioned City Bus Transport Serviceswill be run by a private agency for a period of 10years for which the Aurangabad Municipal Corpo-ration will get royalty @ Rs.0.80 per k.m. More-over, one side space of bus will be available forAurangabad Municipal Corporation for displayingits advertisements. This service will be run as pernorms and conditions of R.T.O.

5. Health

Existing Health Services / Management

It is estimated that the population of AurangabadMunicipal Corporation has crossed 10 lakh in theyear 2005-2006. As per Govt. standard theAurangabad Municipal Corporation has established24 Health Centres and One Hospital to providehealth facilities to the publilc. At these health cen-ters & hospital inpatient services, OPD, and sixnational programmes including family planning,child & women welfare, students health are beingprovided.

In 24 health center of Aurangabad Municipal Cor-poration 64 employees are working in 7 urbanhealth centres as per govt. standard. These cen-tres are funded by govt. through additional direc-tor, health services, pune.The Malaria Eradication Project is also run byAurangabad Municipal Corporation. Regular medi-cine spreading is done in the city t eradicated mos-quito menace through senior health workers andfield employees. Blood samples are collected bymultipurpose health workers and patients aretreated whenever necessary. Under this projectgovt. gives 100% funds for employees and alsosupplies medicines as per requirement ofAurangabad Municipal Corporation.

Under revised T.B.Control Programme twoT.B.Units, 10 Centres and 49 treatment centreshave been opened from govt. funds for these cen-tres, 2 medical officers, 2 S.T.S., 2 S.T.L.S., 1 DataEntry Operator, 2 Lab. Technicians, 5 T.B.HealthVisitors and 1 Driver have been appointed on con-tract basis. The state govt. has provided 10binaculars, microscopes, 2 motor cycles, and 1 Tatasumo jeep for this programme. Govt. also sup-plies medicines as per requirement. Thisprogramme is cent percent funded by Government.

City Introduction and Assessment D. Utilities and Infrastructure

Page 47: CDP

Pg 47Aurangabad Municipal Corporation JNNURM (CDP)

V.C.T.C

The Aurangabad Municipal Corporation has startedthis project with the help Maharashtra State Aidscontrol committee in march 2004. There are facili-ties for HIV counseling, blood testing, testing of HIVaffected, T.B. affected patients, seriously ailing per-sons at 24 health centres & 1 Hospital ofAurangabad Municipal Corporation. Under thisprogramme 2 counsellors. (1 male, 1 female), 1Lab.Technician have been appointed on contractbasis. However, one medical officer from the es-tablishment of Aurangabad Municipal Corporationhas been appointed. All medicines under thisprogramme are purchased from the Govt. funds.The programme is 100 per cent funded by Gov-ernment.

Under R.C.H., four health centres have beengraded where 24 hour services are provided fordeliveries, family planning operation, MTP, etc. TheAdditional Director, H.S.Pune provides funds forthese activities. Out of these funds medicines andsurgical equipments are purchased. Under thisproject 8 medical officers, 4 child specialists(Peadiatricts), 2 Anaesthesists, 1 Statistics Assis-tant, 1 clerk-cum-Accountant, 14 staff nurses, 4laboratory trchinicials, 13 sevkas are appointed oncontract basis.

Under public health department of AurangabadMunicipal Corporation in all 24 health centres and1 hospital are working in hospital 24 hour serviceis provided. The department also runs a FamilyPlanning & Child & Mother Centre, school healthprogramme and also 6 national health programesincluding OPD/ Inpatient services and also providehealth services in field.

Medical OfficersPermanent 16Fixed Pay 04Total 20

Para Medical Employees

Permanent 106Daily wages 57Total 163

The head office of public health department ad-ministers its activities as follows:

Food & Drug Control

Licences are granted to hotels, eating houses, Gro-cery shops etc. under Food & Drug Control Act1954. A zone-wise survey was conducted througha private agency in respect of hotels, grocery shops,eating houses, shops selling food items. Thereare 12500 such units located in the city. Out ofthese 2905 holders have granted licences. No-tices have been issued to other shop holders whodo not hold licences under the provisions of Food& Drug Control Act 1954. Licence fees is beingcollected.

Nursing Home Registration:

As per provisions of nursing home registration act309 hospitals have been registered in the city.

Birth & Death Registration:

A 24 hour open window has been established inhead office of Aurangabad Municipal Corporationwhere licence is issued for cremation in samshanbhoomi consolidated periodical reports are submit-ted about birth and death figures.

Epidemics

Daily figures of patients of epidemic desieases arecollected from Govt. Medical College and Hospi-tal. Nomes of such patients are communicated tomedical officers of health centres and these pa-tients are given contract treatment by visiting theirhanses. Halogen tablets are provided. Sanitationtraining is also given.

City Introduction and Assessment D. Utilities and Infrastructure

Page 48: CDP

Pg 48Aurangabad Municipal Corporation JNNURM (CDP)

P.N.D.T.As per provisions of PNDT Act 1952 registration ofsonography centres is done. Under this Act caseshave been filed against two hospitals.

Bio-medical waste Management:

A Bio-medical waste project has been started whichis 15 km away from the city. Bio-medical waste ofcity hospitals is collected through M/s Wateraceproducts for its disposal. In all 419 hospitals havebecome members and 21% royalty is credited intomunicipal funds.

The above Govt. programmes are implementedby public health department of Aurangabad Mu-nicipal Corporation in addition to followingprogrammes: as per instructions of Government.National Programmes1. Family planning programme2. school health3. pulse polio4. blindness eradication5. leprosy eradication6. AIDS

Special health project

Revised T.B. control programme (RNTCP)Under revised T.B.control programme 2 T.B.Units,10 Microscopic centres, & 49 Treatment Centreshave been established in the city. Out of govt. fundsavailable for this programme, medical officer, S.T.S,S.T.L.S., Data entry operator, Lab. Technician,T.B.Health Visitor, Driver- all these posts have beenfilled up on contract basis. Govt. has provided 10bincular microscopes, 2 motor cycles and 1 Tatasumo Jeep. This programme is 100 percent fundedby Government. Medical officer, padiatricts,Anaesthesist, Statistics Assistant, Clerk-cum-Ac-countant, Staff Nurses, Lab. Technician and wardserikas are also working on contract basis.V.C.T.CThe Aurangabad Municipal Corporation has startedthis project under Maharashtra State Aids Control

Programme in march 2004. there are facilities forHIV counseling, blood testing,. Test of HIV offectedpersons, T.B.affected persons, seriously ill personat 24 health centre and the Hospital of AurangabadMunicipal Corporation. Under this programme, twocounselors (1 Male + 1 Female), one Lab. Techni-cian, have been appointed on contract basis. Onemedical officer is given from the establishment ofAurangabad Municipal Corporation Medicines arepurchased out of govt. grants.

Three tier system :

The Aurangabad Municipal Corporation hasplanned to provide health facilities through threetier system. In First tier there are six wards. Thiswill work as first-phase. This will include participa-tion of Balwadis, Anganwadis, Mahila Mandals,Social Organisations etc. through urban healthwelfare centre. There will be an advisory commit-tee comprising of ward chairman, corporators,NGOs and prominent citizens.The Second tier will comprise of a modern hospitaland,The Third tier will comprise of ICU facilities.

Preventive Measures:Adopting preventive measures is one of the im-portant functions of Aurangabad Municipal Corpo-ration. This include health services through in-crease in health posts and increase in man poweretc.This also include establishment of machinery forsocial awareness.During next 20 years Polio, Leprosy etc. be com-pletely eradicated. But there may be increase incancer, diabetics and hypertension cases. To con-trol these diseases the Aurangabad Municipal Cor-poration will have to establish multi speciality / Su-per speciality 500 bed hospital. For this participa-tion of NGOs will have to be sought. An amount ofRs.50 crore is required for this.

City Introduction and Assessment D. Utilities and Infrastructure

Page 49: CDP

Pg 49Aurangabad Municipal Corporation JNNURM (CDP)

6. Education

To provide Primary education to city children is the

primary duty of AMC as per sub section 15 of sec-

tion 63 of Bombay Provisions Municipal Corpora-

tions Act 1949.

There are 240 Primary schools, 32 High Schools,

30 colleges and one University in the City run by

Government and Private Education societies. There

are Engineering Colleges of Architecture. AMC runs

53 Marathi Medium, 16 Urdu Medium and 12 Bi

Medium Primary Schools thus a total of 81 primary

schools in the city in addition to this 152 Balwadis

are also run by AMC. In these schools 441 Marathi

Medium Teachers and 168 Urdu Medium Teach-

ers Working on the establishment of AMC. Draw-

ing Teachers and Physical Teachers are also ap-

pointed in these schools. 65 schools are run in the

rented buildings.

Pre-Primary (Balwadi) and Primary Education (1

to 7) is imparted in these Schools. These are 3009

students in Balwadis and Anganwadis whereas in

Primary School the Strenth of student is 19, 179.

Reservations are kept for primary schools and play

Grounds. The AMC is the Planning and Develop-

ment Authority for these sites. The details of Pri-

mary schools, play Grounds and Open Spaces

have been shown in statement 2.

Hostel for Students

The AMC has constructed hostels in AamkhasMaidan which is named after Lokshahi AnnabhauSathe. This hostel is meant for the use of Back-ward Student of Schools and Colleges of the city.There are Government Hostels also in the city.

School Uniform and Books Scheme

In the Municipal Schools children of very poor andEconomically weaker families take admissions.Most of these student / parents are unable to pur-chase school uniforms and books. Therefore theAMC has started a Programme for giving two uni-forms and books free to the students.

School Nutrition Scheme

As per Government directions mid-day meal isgiven to students of Municipal Schools.

Sarva Shiksha Abhiyan

Under Government Sarva Shiksh Abhiyan devel-opment of schools, construction of additional classrooms and other amenities are provided by AMC.

Night Education.

The State Govt. has provided Night School andNight College for working class intending to geteducation. There are Law Colleges also which areopen prior to 10.00 A.M. in the morning and after6.00 P.M. in the evening for the benefit of Govt. /Semi Govt. employees to equip themselves withthe knowledge of Law.

Education Concept of AMC

Universalization of Primary Education is donethrough the medium of Municipal Corporation. Forthis the AMC has to open schools in the extendedareas of the Corporation limits. There are 123 and96 reservation sites in Development Plan for Pri-mary School and Play Grounds respectively. TheAMC is the Planning & Development Authority forall there sites. There is no Bal Bhavan and Sci-ence Udyan in the city. In all six Bal Bhavan &Science Udyan will be developed in different partsof the city.

City Introduction and Assessment D. Utilities and Infrastructure

Page 50: CDP

Pg 50Aurangabad Municipal Corporation JNNURM (CDP)

7. Art, Sports and Culture

For the first time the AMC has Constructed NehruBhavan in the central place of the city. Taking in toconsideration growing needs a modern auditoriumSant Eknath Rang Mandir was constructed inOsmanpura area. Recently the State Govt. havesanctioned an amount of Rs. 5 crore for construc-tion of a Natyagruha [Drama Theatre] in CIDCOarea. The construction of this Theatre will be doneby CIDCO. Apart from these a private auditoriumhas been constructed by name Tapadia NatyaGruha. There are Natya Gruha constructed byDr.Babasaheb Ambedkar Marathwada Universityand Saraswati Bhawan College. Another culturalhall is under construction by Padmashri Wajd Me-morial Trust.An annual cultural programme in the name ofAurangabad-Ellora Festival is held comprising ofvarious cultural, musical, lok kala and otherprogrammes which is arranged by State Govt. &MIDC. A Committee undre the chairmanship ofDivisional Commissioner for this Festival.The AMC has also constructed some cultural hallswhich can be used for cultural activities after addi-tions and alterations.

Development of Aurangabad Hut on DelhiHut Lines

The Delhi Tourism and Transportation corporationLtd arranges an Exhibition ‘’Delhi Hut’’ at Delhiwhere Indian traditions, urban and rural, culture,traditional ornaments, dresses, living standard ofthe country and various States etc. are displayedHere in Aurangabad sneh Exhibition ‘’AurangabadHut’’ can be arranged on a piece of 6 acre land inAMC-Garware Stadium, on the lines of Delhi Hut.For this purpose plans have been prepared. TheAMC is considering to develop this ‘’AurangabadHut’’ on BOT basis.

Establishment of permant Art Gallery /Exhibition Gallery

A beautifull and archecturally designed buildingknown as Town Hall was built some 400 years ago.Looking to its design, architecture and style of con-struction this building can very well be used as anArt & Exhibition Gallery. AMC is making efforts inthis direction, paintings can be kept for exhibitionas well as sale purpose in this Gallery. The AMChas proposal to start permanent gallery for paint-ing exhibition, handicrafts, cultural exhibitions ofdifferent states, murals etc.This Will help in promotion of Literature, Dance,Drawing, Hand craft, Handlooms etc. CulturalProgrammes can also be held on regular basissimilary ancient Satvanana art and Culture can bepromoted. This will create opportunities for localartists and artists from other areas. This will alsohelp to create interest in the minds of new genera-tion about our ancient heritage and culture.For establishment of this permanent Art and Cul-ture Centre an amount of Rs. 1 crore will be re-quired.

Light and Sound show can be arranged at theplaces like Bibi Ka Maqbara, Panchakki, DaultabadFort, Chatrapati Shivaji Maharaj Museum and otherplaces

It is proposed to establish a Kala Garam (Art Vil-lage) for city and adjoining areas, Municipal Landavailable at different places can also be used asExibition Ground as per needs.

Mayor Trophy Dance andSong Competitons

Mayor Trophy Dance and Song Competitions areheld for school children of Government and Pri-vate Schools to create interest among them. Meri-torious Students in this field are awarded prizesand certificates.

City Introduction and Assessment D. Utilities and Infrastructure

Page 51: CDP

Pg 51Aurangabad Municipal Corporation JNNURM (CDP)

The AMC also holds Mayor Trophy State LevelOpen Drama Competitions. The Winners are fe-licitated by awarding prizes and certificates.

Felicitation Of Prominent Citizens

As a social binding the AMC has felicitated promi-nent persons of different fields by civic receptionand by presenting momentous and Samman Patrasto them. Some of such examples are as below.1. Public felicitation of all Freedom Fighters2. Felicitations of all artists of drama “Acanak” on winning first prize. All Artists of this Drama be long to Aurangabad.3. Felicitation of Senior Citizens of the city.4. Felicitations and Financial assistance given to Film “Shwas” on the selection for Oscar Film Awards.5. Felicitation of World Record Holder Drama artist Laxman Deshpande.6. Felicitation of Loksabha Speaker, Central Ministers, Chief Minsters of the State, Member of State Cabinet etc.

Presentation of Historical and CulturalAspect of City

Hoardings, Showing Historical and Cultural Factsand Figures of the City on Various Chowks andmain Roads leading to the city will help in commu-nication of these facts to the general public. Mor-als can also be painted on walls of Government/Semi Government Offices premises.

Open Spaces, Play Grounds and SportsComplex

In the city the Municipal Garware Stadium and theland meant for Sports Complex at Aam KhasMaidan are in the possession of AMC. The Gov-ernment land reserved for sports complex in silkmill colony is also in the possessions of AMC. Sports

Complex at Aam Khas Maidan has been Partiallydeveloped. The AMC has developed fully theGarware stadium. The Divisional Sports Complexis being developed in S.No 55 which is a Govern-ment land in Soot Girni premises in Garkheda area,by state Government. Final plans and Estimatesof this complex have approved by state Govern-ment. Apart from these there are sports Complexin Dr. Babasaheb Ambedkar Marathwada Univer-sity, Milind College, Marathwada SanskrutikMandal, Maulana Azad College and CIDCO N-4Cricket Ground, Jhalani Tools Cricket Ground etc.A mini sports complex is being developed in AamKhas Maidan considering above facts it seemsnecessary to have a co ordination between AMCand State Government to Chalk out a policy in re-spect of all these Sports Complexes.Similarly the AMC will develops play groundsadajacent to Municipal Schools.The AMC has constructed a swimming Pool nearSiddharth Garden. Badminton Halls have been con-structed in AMC Garware stadium and in BansilalNagar, Jyoti Nagar, Vedant Nagar Wards. TableTennis facility is available in the hall adjacent toMTDC office, Garware Stadium etc. A Modern Skat-ing field is constructed in Vedant Nagar and N-4CIDCO.Two new swimming pools are proposed to be con-structed in AMC Garware Stadium and in JyotiNagar.The AMC also makes arrangement for stay of theplayers. A Hostel has been constructed in AMCGarware Stadium in future also such hostels willbe constructed as per needs at various places.

Mayor Trophy Tournaments andBal Ananad Melava

Every Year the AMC conducts Mayor Trophy Tour-naments at Local, State and National Level. Tour-naments also held for Deaf and Dumb and otherphysically challenged players. These tournaments

City Introduction and Assessment D. Utilities and Infrastructure

Page 52: CDP

Pg 52Aurangabad Municipal Corporation JNNURM (CDP)

are held for cricket, Atheletes, Kabadi, Kho Kho,Skating, punja, Wrestking, Swimming Badminton,Football, Hockey, Kung FU, Karate, Taikwandu etc.Both for boys and girls winners are awarded prizesstay and boarding arrangements are made for play-ers by AMC.The AMC also hold Children Festival every year topromote education, sports and qualities amongthem.

Library & promotion of reading Habit :

In all 24 Libraries are run by AMC in the city out ofthem Municipal Library located at Khadkeshwar isone of the big Libraries of the city. This Library ishaving all types of books viz, educational, social,economic, vocational, etc. All types of magazines,periodicals, weeklies, be-weeklies, fortnightlies,monthlies, annual numbers dairy newspapers arealso subscribed for the use of public. In Dr.Babasaheb Ambedkar Research Center also somereference books have been made available. Onemore reference Library is being opened shortly atMaulana Abul Kalam Azad Research Center whichis nearing completion. There are several Librariesin the city.Books of all prevalent languages are available inMunicipal Libraries. This will help to create read-ing habits among the general public in general andamong the student community in particular.It is expected that the AMC will purchase booksworth Rs. 3 crore, till the year 2025. The StateGovt. also has constructed a modern Library build-ing in the central part of the city.

Research Centers.

a. Dr. Babasaheb Ambedkar Research Center.

Dr. B.R. Ambedkar, Mahatma Jyotiba Phule Ma-hatma Gandhi, Shahu Maharaj, Sant GadgeMaharaj, Annabhau Sathe, Ramswami Periyar,

Bhaurao Patil are social reformers. Books of allthere personalities have been made available un-der roof in this Research Center. There are rarephotographs of Dr. Babasaheb Ambedkar, Medita-tion hall and a meeting hall in this Center.

With coordination with various Universities for col-lection of information, holding State Level Debat-ing, Essay, Drawing, speech and arranging lectureseries are some of the proposals. This center hasbeen constructed with a cost of Rs. 1 Crore whichis having books worth Rs. 7 Lakhs.

Anybody can become a monthly, annual or lifemember of this Research Center. Very useful booksfor research purpose are available here.

b. Maulana Abul Kalam Azad Research Centre

The AMC has constructed a beautiful building inMajnu Hill area on the main road leading to CIDCO.This Center is named after Maulana Abul KalamAzad the first Education Minister of free India anda great Freedom Fighter. This Research Centerwill works as a center for new India vision andthoughts of Maulana Azad. The civil work of thebuilding has been completed with a cost of Rs. 3crore. Very soon this Research will be inaugurated.For other works an amount of Rs. 1 Crore is re-quired.

There are Library, Meeting Hall, guest House etc.in this Center. Creation of best literature, culture,publication of books, are going to be awarded prizes& mementos at National & International Level bythis Center.

This Center will encourage the local writers.Marathi, Hindi, Urdu Kavi Sammelan-Mushairas etcwill be held.

City Introduction and Assessment D. Utilities and Infrastructure

Page 53: CDP

Pg 53Aurangabad Municipal Corporation JNNURM (CDP)

8. Fire Brigade

There are three Fire Stations in the city. All thesethree Fire Station provide their services toAurangabad city, Waluj and Chikalthana . As perGovt’s Disaster Management Policy a DisasterManagement Center is being established atAurangabad at divisional level. The Municipal FireBrigade will work with this Disaster ManagementCenter.

The Fire Brigade has done an excellent job duringheavy rains in July 2005 in the city and preventedpossible human loss. The Search & RescueScheme is very useful scheme during natural ca-lamities such as earth quake, flood, fire, riots, roadaccidents, chemical leakage etc. This preventspossible loss of properties and also human loss.For equipping Fire Brigade with modern equipmentpurchase of new fire tender & fire equipment’s inindispensable.

Emergency Cell.

Under Govt’s Disaster Management Policy a Di-saster Management Center is going to be openedin the city. For this the General Body of AMC has

passed a Resolution No. 186/6 dt. 20.11.2003 anda proposal to that effect has been submitted to theGovernment. The AMC Fir Brigade will have workwith this Center. After approval of Govt. necessarystaff will be appointed.

With the increase in population, area andindustrialisation there is likelihood of increase inaccidents also there are following buildings whichhave been declared dangerous.

l High Rise Buildings 49

l Hotels 1310

l Cinema Houses 12

l Paint Shops & Stores 150

l Petrol Pumps 17

l Gas Agencies 12

l Function Halls 70

l Saw Mills 45

l Kerosene Agencies 42

In future the number of such buildings will increaseresulting in fire accidents/ rescue cases. Accidentof various kinds, natural calamities, vists etc. There-fore well equipped & modern fire machinery isnecessary. Considering future population it is nec-essary to have zone- wise arrangements for firefighting for this following expenditure is expected.

01 Fire Tenders 30 7.50 Crore

02 T.T.L. Snorkel 12 15.00 Crore

03 RescueVan 03 9.00 Crore

04 Workshop Tools/Materials 1.00 Crore

05 Offices for Fire Station 10.00 Crore

06 Fire Fighting Material 1.00 Crore

07 TrainingCentre

construction & running 4.00 Crore

08 Laying Hydrant Line 3.00 Crore

Total 50.50 Crore

City Introduction and Assessment D. Utilities and Infrastructure

Page 54: CDP

Pg 54Aurangabad Municipal Corporation JNNURM (CDP)

Increase in Fire Fighting Centres

For providing Fire Fighting Services in the

Chikalthana area it is necessary to restart the Fire

Station of Chikalthana . Similarly in future more

Fire Station will have to be established in view of

increasing population for which monetary provisions

will have to be made.

Education & Training

Considering the emergency during natural calami-

ties shortage of manpower should not be felt. For

this purpose workers of NGOS MCC and NSS stu-

dents are required to be given training similary re-

freshing training employees of Fire Brigade . Com-

puter training is also necessary

Disaster Management Cell

To face natural calamities and other emergency

situations it is necessary to form a central Disaster

Management cell and also to provide video

conferencing facility to connect with sub centers.

Setting up of wireless machinery, telephone etc. is

also essential

Fire N.O.C.

Fire NOC is necessary for various industries. The

procedure of NOC should be made easy for which

action is being taken by AMC.

9 Zoo & Animal Husbandry

Present condition of Municipal Zoo.A Municipal Zoo is established on a piece of 17 acresin sidharth Garden by AMC in the year 1985. This isonly Zoo being run by AMC in Marathwada Region.Peoples are educated about wild life through this Zoo.The Animals are very well kept. The Central ZooAuthority of India Delhi has accorded their approvalto this Zoo.There are 22 spices of wild animals including whitetigers, leapords, crocodiles, elephants, monkeys,sambar, NeelGai, Cheetah,Chinkara, Sayal, Waterbirds and Thoom birds etc. Snakes of various kindsare also kept in snake Park. Efforts are being madeto make this Zoo more attractive so that number ofvisitors may increase.The number of visitors during last three years is asfollows.

Sr.No. Year No.of Visitors

1 2002-2003 4,96,9002 2003-2004 4,11,6003 2004-2005 4,72,200

Various Projects of Zoo

Vasundhara Mini Theatre

Vasundhara Wild Animal Mini Theatre has beenstarted since 5.9.1995 in the premises of Zoo with acapacity of 100 to 200 persons. A 30 Minute film isexhibited on wild animals to educate the visitors.If is proposed to construct a theatre on the lines ofScience Park of Kolkata where feature films on na-ture and wild animals can be exhibited to educate thegereral public and toruists. An estimated expendi-ture of Rs.6.50 core will be required for this.

Snake Park

The Aurangabad Municipal Corporation has con-structed a Snake Park on the lines of Nehru National

City Introduction and Assessment D. Utilities and Infrastructure

Page 55: CDP

Pg 55Aurangabad Municipal Corporation JNNURM (CDP)

Park Hyderababd. 90 Snake of different kinds arekept in this Snake Park.Water BirdsVarious kinds of water Birds have been broughtfrom Veer Mata Jeejabai Bhosle Udyan Mumbaifor Aurangabad Municipal Corporation Zoo. Lastyear 4 Thoom Birds were brought .This has addedattraction to the Zoo .

Bird Sanctuary

Foreign birds come to Dr.Salim Ali Lake. Takingbenefit of this bird migration a Bird Sanctuary canbe developed through BOT method. This will in-crease number of tourists and bird watchers. Thiswill also help eduate the general public about birds.

Present Animals in Zoo (Dt.01/01/2006)

City Introduction and Assessment D. Utilities and Infrastructure

Sr. Name of Male Female Total RecieptsNo. Animals

1 Lion 02 02 04 Sanjay Ghandhi national Park, Boriwali

2 Tiger 02 02 04 Chatbeer Zoo, Chandigadh3 White Tiger 03 07 10 Nandankanan national Park, Bhuvneshwar

Orisa

4 Panther 03 04 07 Forest office, Bhandara, Gondiya,

Navegaon5 Hyena 01 03 04 Local Forest office, Aurangabad

6 Jackal 01 03 04 Local Forest office, Aurangabad

7 Wolf 01 00 01 Local Forest office, Aurangabad8 Civet cat 02 02 04 Local Forest office, Aurangabad

9 Elephant 00 02 02 Forest office, Maysur Karnataka

10 Samber 11 07 18 Veer Mata Jijabai Bhonsle Uddyan, Mumbai11 Nil-Gai 02 04 06 Nanded Marathwada Division

12 Chikara 00 02 02 Local Forest office, Aurangabad

13 Spotted Deer 02 04 06 Veer Mata Jijabai Bhonsle Uddyan, Mumbai

14 Black Buck 28 21 49 Local Forest office, Aurangabad

15 Monkey 04 06 10 Local Forest office, Aurangabad

16 Porcupine 03 03 06 Nandankanan national Park, Bhuvneshwar

Orisa17 Guniapig 05 05 10 Nandankanan national Park, Bhuvneshwar

Orisa

18 Emu 01 01 02 Mumbai

19 Crocodile 01 00 01 Mumbai, Tadoba Uddyan20 Tortoise 02 02 04 Local Forest office, Aurangabad

21 Water Birds — — 33 Veer Mata Jijabai Bhonsle Uddyan, Mumbai

22 Snake — — 90 Local Forest office, Aurangabad23 Bear 01 01 02 Local Forest office, Aurangabad

Page 56: CDP

Pg 56Aurangabad Municipal Corporation JNNURM (CDP)

Aquarium

An aquarium has been opened in Municipal Zoo inJanuary 1997 . Fishes of various kinds are kept inthis acquarium.Proposed Underground Aquarium.An underground aquarium can be constructed inSalim Ali Lake on the lines of other cities on BOTmethod In this acquarium fishes from variouscontries of the world can be kept. This Project willrequire Rs. 5 Crore.

Shifting of Municiapl Zoo

The present area of Zoo is insufficient .Thereforeit is being proposed that the Zoo may be shifted toa larger area either in Himayat Bagh or in the areaadjacent to Harsul Tank. Alternatively the area ofZoo can be extended by acquiring land on thesouth-west side. For this purpose an amount of Rs.25 Crore will be required.

Bird Sanctuary

For developing a bird sanctuary at the existing tank anamount of Rs. 2 Core is required. Publicity of Zoo

With a view to give information to the public visit-ing the city about Zoo putting up hoardings at vari-ous prominent places in the city, painting photo-graphs of wild animals of City Buses, giving infor-mation through AMC information Boards, givinginformation about wild animals in educational insti-tutions will result in increase in number of visitingpublic in the Zoo.

Slaughter House

There are two slaughter Houses of AMC function-ing in the City- one at Padegaon for large animalsand the other at Shah Bazar for small animals.

Modernisation of Slaughter House.

In future the number animals brought for slaugh-tering will increase with a view to supply clean meat

and in view of public health it is necessary tomodernise the slaughter house on the lines ofDeonar slaughter House of Mumbai in Padegaonarea in AMC limits.For the purpose of modernisation of MunicipalSlaughter House at Padegaon on amount of Rs. 4Crore is required. During the year 1999-2000 anamount of Rs. 10 Lakh was received from Govt. ofIndia. Tenders have been called at State Level formodernisation of slaughter House. The work willbe started after finalisation of the tenders.With a view to complete modernisation work early,this can be done by appointing a consultant to avoidun authorised slaughtering a animals in the city.

Developmental work related withslaughter House.

Cold Storage : For stocking of meat a modern coldstorage will be constructed. There will be sepa-rate cold storage for the large and small animals. -one at Padegaon and one at Shah Bazar. Anamount of Rs. 1 Crore is estimated and efforts willbe made to complete this on Bot basis.

Godown for Skin & Bones : The AMC has shiftedskin & bone godown alongwith staughter housefrom the city. While constructing modern slaugh-ter House, godowns for skin and bones will alsohave to be constructed for which an amount of Rs.1Crore will be required.

Tannery : The AMC has allotted a price of landnear Mandki Trenching ground for tanning pur-poses which help is sanitation and public health.

Preventive Measures :Squad for unauthorised slaughtering and sale.The AMC has formed a squad with the help of Po-lice to keep a watch on unauthoritised slaughterand illegal sale of meat in the city. Police casesare filed in Police stations and the meat seized isdestroyed in Trenching Ground.In view of increasing population it is necessary to

City Introduction and Assessment D. Utilities and Infrastructure

Page 57: CDP

Pg 57Aurangabad Municipal Corporation JNNURM (CDP)

have four such squads to curb unauthorised slaugh-tering and sale of meat.Presently there are several private meat shops inthe city. It is proposed to construct mutton marketat various places in the city to have a control overmeat sale and also to curb the illegal meat sale.

Cattle PondA central Cattle Pond has been constructed in 1995in Garam Pani area where stray animals are keptwhich are caught by a squad appointed for thispurpose.It is necessary to construct one more Ponds inChikalthana area for CIDCO Action is being pro-posed in this regard.

Veterinary Hospital :Ailing animals are treated in Municipal VeterinaryHospital. Every Friday the hens are immunised.For pet dogs licences are issued and they are alsogiven immunisation.

Dog UnitA Govt. Dog Unit is working since 1984-85 to catchthe stray dogs. After they are caught they are keptin the Dog House and are immunised. It is neces-sary to construct more Dog House in the city.

Dog House & Dog HostelTo minimise the number of stray dogs in the city itis necessary to give them immunisation treatment.This keeps a control over the population of straydogs. For this purpose a modern Dog House anda veterinary Hospital with surgery facilities are es-sential. There are many dog lovers in the city. How-ever then face difficulties in summer and Diwalivacation to keep their pets. In view of this a DogHospital in necessary where these pets can be keptand taken care of temporarily on some chargesfrom owners for this project an amount of Rs. 35lakh will be required. This can also be done on Botbasis.

Other proposed works

Bengal Tiger

Recently two pairs of Royal Bengal Tigers havebeen brought from Chatbir Zoo Chendigadh theyhave been dedicated to public on the occasion ofAnnuarsery of AMC on 08.10.2005As per discussion with the authorities of ChatbirZoo Chandigadh they are prepared to give hippo-potamus. Therefore arrangements are being madeto bring this animals for which an amount of 15.00lakh is expected on its transportation and for con-struction of its house.

Dugdh NagriThe AMC has decided to construct a Dugdh Nagrifor shifting of all cattle stables existing in the city.The reservation has been kept in Chikalthan andnear Padegaon slaughter House. A proposal hassent to collector for transfer of these Govt. landswork will be started soon after transfer of land toAMC.The construction of Dugdh Nagri will comprise ofcivil work, water supply, approach roads, electricityetc. This will cost about Rs. 2 Core. This does notinclude cost of land acquisition since Govt. landcan be obtained free of cost from Govt.

Modern Laboratory

In Dudgh Nagri arrangements will have to be madefor testing of milk and animal feeds. For which amodern Laboratory is necessary. An amount of Rs.1 Crore is required for this work.

Shifting of PiggeriesThe AMC has earmarked a piece of land atNaregaon Trenching Ground for piggeries. It isnecessary to shift all pigs from city to this place toavoid public complaints. In Future wheneverTrenching Ground will be made available, piggerieswill also have to be shifted in the adjoining area ofthis ground. For this purpose an amount of Rs. 1Crore will be required.

City Introduction and Assessment D. Utilities and Infrastructure

Page 58: CDP

Pg 58Aurangabad Municipal Corporation JNNURM (CDP)

E. Environmental Profile

Environmental resources namely constitute air,water, land (soil) and vegetation. This section givesan outline of these resources of the city which arebeing used or likely to be used to support the ur-ban life. The resources include both the living aswell as non-living things. The interface of theseresources with the developmental activities andissues arising out of the same are also describedin this section.

1.Climate

a.Topography

Aurangabad city is surrounded by the hilly rangesfrom north, south and west sides at the attitude of611 Mt. above mean sea level. Northern side Mu-nicipal limits are flanked by Jathwada hill rangesand on south locally named Satara hills are located.General topography of the city is undulating. Atti-tude of the city increases towards north side.

b. Geology and Soil Condition

Aurangabad falls in semi-arid area with indicatingtopography, poor soil, and low productive of land.The soil is mostly formed from igneous rocks andis black, medium black, shallow and calcarioustypes having different depths and profiles.

c.Seasons :

The climate is characterized by hot summer andgeneral dryness throughout the year except dur-ing southwest monsoon season. The year may bedivided into four seasons. The cold season is fromDecember to February and hot season from Marchto May. June to September is southwest monsoonperiod whereas October to November is post mon-soon period.

d. Rainfall

In Aurangabad City the average rainfall is 725.8mm and about 83% of the annual rainfall falls dur-ing June to September. Maximum rain is experi-enced in the month of July, some amount of rain-fall occurs during May while the months of Octo-ber and November are mainly in the form of thun-dershowers. On an average there are 46 rainy daysand there is large variation in the annual rainfallfrom year to year.

e. Temperature

May is the hottest month. With the mean dailymaximum temperature 39.8 0C and mean dailyminimum temperature 24.4 0C. During the hot sea-son the day temperature may rise to about 45 0C.With the advance of the south-west monsoon inthe district by the second week of June, there isappreciable drop in both the day and night tem-perature and the weather becomes pleasant. Withthe withdrawal of the monsoon by about the end ofSeptember the day temperatures increases a littleand secondary maximum, day temperature is re-corded in October but night temperature decreasesprogressively. After October both, the day and nighttemperatures decrease steadily.Cold weather commences by the end of Novem-ber and temperatures begin to fall rapidly. Decem-ber is the coldest month with the mean daily maxi-mum temperature of 28.7 0C. And the mean dailyminimum of 13 0C.In the cold season the city issometimes affected by cold waves, when the mini-mum temperature may drop to about 2 0C.

f. Humidity

The air is generally dry except during the monsoonwhen the relative humidity is high. The summermonths are the driest when the relative humidity isgenerally between 20 and 25 percent in the after-noons.

City Introduction and Assessment E. Environmental Profile

Page 59: CDP

Pg 59Aurangabad Municipal Corporation JNNURM (CDP)

g. Winds

Winds are generally light to moderate with an in-crease in speeds during the latter half of the hotseason and in the monsoon season. The windsblow predominantly from the directions between theWest and North during the hot season. They aremostly from the direction between South-West andNorth -West during the monsoon season. Theyblow mostly from the directions between North-Eastand South -East during the rest of the year.

h. General

The climate of Aurangabad is temperate with mod-erate winters in the months of November - Febru-ary and hot summers from April through to June.This southwestern monsoon arrives here by endJune - September and the city receives a moder-ate amount of rainfall.The climate of the city is generally dry except forthe monsoon season. It receives an average an-nual rainfall of 170 mm. bulk of rainfall is receivedfrom the southwest monsoon, from the months ofJune to September. The average annual rainfall ofthe district ranges between 800 to 750 mm. Thedistrict often experiences drought with rainfall re-cording as low as 400 to 450 mm. The monsoonseason starts from June and continues up Sep-tember.The rainy season is followed by winter, which lastsup to February, during which the minimum tem-perature ranges from 110 C to 130 C. The winter isfollowed by hot summer, which continues up toJune. The maximum day temperature ranges be-tween 390 C & 42 0 C during summer. December isthe coldest month of the year and May is the hot-test month

2 AirAurangabad has a weather monitoring location.The meteorological data for Aurangabad shows thatthe relative humidity in the area is 76% to 87 %during rainy season (June to September), 52 % to64 % during the winter season (October to Janu-ary) and 41% to 47 % during the summer season(February to May). The predominant wind direc-tion during monsoon and summer is from the west,during winter it is from the east. If the whole year isconsidered the predominant wind direction is fromthe west.

3. Influence of Activity Sectors on AirThe activities in the city which are most likely tohave adverse impact on the air quality are the in-dustrial development and the vehicular traffic.

Industrial activityThe industrial activities in Aurangabad consistmainly of dal mills, foundries, sugar industry andoil extraction units. Out of this oil extraction unitsand sugar industries are likely to have maximumadverse impact from the fumes and dust if ad-equate abatement measures are not taken. Thedal mills and seed production units are classifiedas green industries and do not have major impactsexcept dust and fine particles given out while pol-ishing the pulses in the dal mills.There are a few cotton ginning and pressing millsin and around the city, the cotton fluff given out fromthese mills remains in the air and is carried all overthe city.The various activities such as husking, cleaning,crushing, and conditioning of oil seeds in extrac-tion units affect the air quality due to generation ofdust. The emissions from the fuels used for me-chanical oil expellers, pressing units and otherequipments add to the air pollution. Other signifi-cant impact includes the odour nuisance from theextraction units.

City Introduction and Assessment E. Environmental Profile

Page 60: CDP

Pg 60Aurangabad Municipal Corporation JNNURM (CDP)

Traffic and transportThe city has a high concentration of 2 wheelersand 3 wheelers and 4wheelers. The city does nothave a public transport system and is dependenton auto rickshaws for the same. Most of the rick-shaws are old and run on diesel adding to the airpollution. The town also attracts heavy goods traf-fic whose diesel engines are responsible for car-bon particles emission. The roads and streets inthe city are narrow and encroached hence the traf-fic is not free flowing, the continuous changing ofgear and idling of engines affects the air quality.The climate of the city is dry and arid hence asvehicles pass on the roads lot of dust is generatedand there is very little vegetation along the road toabsorb the dust.

Construction activityConstruction activity gives of lot of dust while mix-ing the cement concrete, breaking of old structures,digging, drilling etc. The operation of diesel mixersfor concrete also pollutes the air. Construction ac-tivity also adds to the noise pollution. The debrisand construction material when left un attendedalong the road causes inconvenience to motoristsas well as pedestrians and increases the possibil-ity of road accidents.The bricks kilns, stone quarries, stone crushers andsoil quarries adversely the affect the environment.The key impacts include air pollution (increasedlevels of SPM & RSPM), land degradation, loss offorest/ vegetation, noise pollution and surface &

ground water pollution. Abandoned stone quar-ries need to be rehabilitated and rejuvenated sothat they prevented from being misused as unau-thorized dumping grounds.

Informal sectorThe only activity impacting air is the weekly hidemarket that gives out strong odour. The other ac-tivities such as petty shops, pan stalls, small ga-rages do not have a wide scale impact on the airquality. In most cases the air pollution caused islocalized and the mixed land use of the city withresidential areas close by affects the health of thepeople. In many cases the workshops are exten-sion of the owner’s house and they themselves areignorant about the dangers of the pollution.

Air quality monitoringThe above facts are strengthened in some aspectsfrom the past air quality data available with theAurangabad Municipal Council. The air qualityshows very high levels of SPM near Cenral BusStand and Railway Station which are busy trafficjunctions. SPM levels are also high in the areas ofTown Hall, Jalna Road and City Chowk comparedto the permissible standards. The SPM levels inthe MIDC Chikhalthana area are low compared tothe permissible standards. The sulphur dioxide andnitrogen dioxide levels are within the permissiblelimits in The main reason for high SPM levels isthe increasing vehicular traffic and absence ofgreenery along the roads to absorb the particles.

Table 1: Air Quality in AurangabadStandards SPM (µg/m3) SO2 (µg/m3)

NAAQ Stds Residential 140 0NAAQ Stds Industrial 360 0NAAQ Stds Sensitive 75 0Locations 24 hours average 24 hours averageTown Hall 309 7Central Bus Stand 1037 2City Chowk 648 2MIDC Chikhalthana 175Jalna Road 611 4Railway Station 712 6

Source: 2000 – 2001 ESR Report Aurangabad

City Introduction and Assessment E. Environmental Profile

Page 61: CDP

Pg 61Aurangabad Municipal Corporation JNNURM (CDP)

4 Topography and natural drainage

Aurangabad is situated on an altitude of 663 mabove mean sea level. It has developed on the highlevel plateau which runs along the Nanded- Barshiand Ausa Road. The surrounding area is some whatlow level having good agriculture productivity. TheManjar River flows through the City and it is alsodrained by other nalas (streams).

5 Geology

This entire Aurangabad district is covered by theDeccan Trap lava flows of upper cretaceous toeocene age.  The traps are overlain by thin alluvialdeposits along the major rivers. The basaltic lavaflows belonging to the Deccan Trap is the only majorgeological formation occurring in the district.  Thelava flows are horizontal and each flow has distincttwo units.  The upper layers consist of vesicularand amygdular zeolitic basalt while the bottom layerconsists of massive basalt.  The flow thicknessranges between 15-20 mts. And in all 10 flows havebeen demarcated which are lying between 510-740

m msl.  The flows are generally separated by a redclay bed commonly called as ‘Red bole’.

The thickness of alluvium ranges between 10-15mtrs.  The extension of alluvial belt is confined to0.5-1 km. across the rivers.

A number of lineaments which are fracture zoneshave been identified on the satellite imagery dueto linear pattern, exhibited by darker tone andstraight drainage course.

These lineaments are favourable for occurrenceof groundwater. The major lineament trends in thedistrict are NW-SE, NE-SW and E-W.

6 Soil Characteristics and Land use

The predominant soil cover in the district is me-dium black to deep black calcareous formed withvarying depth and texture. The soil in Aurangabadhas coarse texture and is suitable for growing cropssuch as Jawar, Bajra, Wheat, Pulses and Sugar-cane. The land use classification according to theDP is given below in Table 2 below.

Table 2: Existing land use in Aurangabad

No. Land use type % to % to Total area Developed included in DP

1 Residential 55.04 24.522 Commercial 4.46 1.993 Industrial 19.44 8.664 Public & Semipublic 7.12 3.175 Public Utility 1.05 0.476 Transport & Communication 12.22 5.457 Gardens & Playgrounds 0.67 0.30

Total Developed Area 100.00 -

8 Agricultural - 37.439 Water bodies - 0.3310 Vacant & Barren - 17.69

Total Area in Municipal Limits. 100.00

City Introduction and Assessment E. Environmental Profile

Page 62: CDP

Pg 62Aurangabad Municipal Corporation JNNURM (CDP)

7 Influence of Activity Sectors

The land use in the Aurangabad City shows thatmaximum area is under residential use as far asthe developed area is concerned. The next majorcategory is the industrial land use. Most of the in-dustries in the city are located in the MIDC Estateon the Aurangabad – Barshi Road to the south ofthe city. A significant portion of the city is undevel-oped and is under agricultural use. This forms about37 % of the total area of the city. The area for openspaces and recreation is very less and is 0.67 % ofthe developed area.

The unauthorized disposal of industrial waste andmunicipal solid waste affects the soil quality therebymaking it vulnerable for putting to effective publicuse in future.

The brick kilns and stone quarries in the surround-ing areas adversely affect the soil quality and land-form in the near vicinity.

8 Surface water

The Manjra River flows through Aurangabad city.The length of the rivers within the municipal limitsis 00 km and 00 km respectively. There is no docu-mented evidence of fishing activity in the river.

There is a fresh water lake opposite the MunicipalOffice in Aurangabad. Add on use of water

9 Influence of Activity Sectors on Surface Water

Industrial activity

Amongst the industries in Aurangabad the wastefrom the oil extraction units is most likely to affectthe surface water quality. The waste water containshigh organic content and chemicals used duringthe extraction and refining of the oil. The waste

water is also likely to contain fat residues, ash resi-dues and organic nitrogen. The city does not havean underground drainage system and generally allthe waste water flows in to the Manjra River througha network of open drains. The industrial waste wa-ter will also find its way to the Manjra River andadversely affect its water quality.

Informal sector

The precise contribution of this sector in water pol-lution is difficult to determine. However the natureof activities is not likely to cause major water pollu-tion, except in cases of garages and small work-shops where the waste water contains lubricantsand chemicals. The magnitude of this is small.

Housing and urbanization

As described in the Chapter 5 the City does nothave an under ground drainage system and thesewage generated to the tune of 4.2 MLD is letinto the Manjra River and other open drains with-out any treatment. Open drains passing throughthe city carrying waste water present an ugly sightand pose health hazard for the people. The ab-sence of toilet facilities in slum areas forces thepeople to defecate in the open, they generally squatalong the river or along the road side drains add-ing to the surface water pollution.Waste water recycling and rain water harvestingare not practiced in the city and there are no meansof water auditing in the water supply system.

10 Ground water

The major part of the district forms the moderatelydissected basaltic plateau, which has moderate togood groundwater potential. The northern partforms the highly dissected basaltic plateau; thegroundwater potential is expected to be poor. Goodpotential pockets for groundwater exploitation are

City Introduction and Assessment E. Environmental Profile

Page 63: CDP

Pg 63Aurangabad Municipal Corporation JNNURM (CDP)

expected along the lineaments. The narrow allu-vial deposits along the major river also form poten-tial zones for groundwater exploitation. Jalna cityfalls in the central portion of the district and hencehas good ground water potential. Add details ofGSDA.

11 Influence of Activity Sectors on Ground water

Industrial activity

The waste water generated from the different in-dustries gets absorbed in the ground water when itis disposed without treatment into the open drainsand even in cases where it is disposed off in aban-

doned wells and pits the ground water gets con-taminated when these pits are not lined properly.

Housing and urbanization

The ground water in Aurangabad district is knownfor its high nitrate content and the Central PollutionControl Board has declared it as one of the criticalareas in the country. However its impact for thecity as such is not known.

Water Quality Monitoring

The water quality monitored by the Municipal coun-cil shows that surface water quality is very poorwhere as the drinking water quality is fairly good.

Source: 2000 – 01 ESR Report Aurangabad

12 Forest and vegetationThere are no forest areas in the city of Aurangabad.The gardens and play grounds have some vegeta-tion in the form trees and shrubs. Roadside planta-tion is absent along most of the internal roads, it isseen on the roads in the outskirts and consists oftrees such as gulmohur, copper pod, Bhendi etc. Thevegetation along the river needs to be studied topresent a detailed account of the riverside habitat.The absence of vegetation along roads adds to theproblem of dust flying due to vehicular movementon the roads. The MIDC has certain amount of treeswhich helps in arresting the pollution.

13 WildlifeThere is no significant wildlife in the city such asrare and endangered species of fauna. Howeverall the activity sectors if continued in an unplannedan unorganized manner may adversely affect thelocal flora and fauna in the long run.

14 Noise levelsThe noise levels in the town were monitored at 10locations spread across the town. The noise levelsare particularly high in residential zone and the com-mercial areas.

Table : Water Samples

Parameters Raw Water Treated Water Accepted Norms

(Potable Water) For Treated Water

(Potable Water)

pH 8.0 8.0 7.0028.50Turbidity 1.18 1.00 1.00 NTUAlkalinity 105 98 200 mg/lTotal Hardness 130 116 200 mg/lSulphate 200 200 200 mg/lNitrates 4.87 4.43 45 mg/l

City Introduction and Assessment E. Environmental Profile

Page 64: CDP

Pg 64Aurangabad Municipal Corporation JNNURM (CDP)

Table 5: Noise levels in Aurangabad

No. CPCB Standards Day Night6:00 AM – 10:00 10:00 PM TO 6:00 PM in dB AM in dB

A Industrial 75 75

B Commercial 65 55C Residential 55 45D Silent 50 40

No. Monitoring Locations Type

1 Central Bus Stand Commercial 80.5 -2 Town Hall Commercial 72.6 -3 Bibi ka Makbara Tourist 64.4 -4 Chikhalthana MIDC Industrial 62.6 -5 City Chowk 76.3 -

6 Railway Station 89.2 -7 Kanti Chowk 82.3 -8 Jalna Road 84.3 -9 Gulmandi 81.2 -10 Waluj MIDC 60.1 -

15. Environmental Resource Sensitivity and EPM guidelines

Based on the above discussions the threats to theenvironmental resources and their status are sum-marized below. The matrix also summarizes thestatus of the urban utilities and priority issues per-

Sr. Environmental Threat and status SensitivityNo. Resource &

Description

1 Air l1 Pollution due to Industriesl2 Increasing vehicular emissions Medium

2 Surface water l3 Untreated disposal of sewage & waste waterl4 Disposal of solid wastel5 Untreated industrial waste & effluent High

3 Ground water l6 Over extraction for secondary purposesl7 Possible pollution due to non maintenance of septic tanks & soak pits Medium

4 Soil/ Land l8 Unscientific disposal of solid waste

City Introduction and Assessment E. Environmental Profile

taining to utilities provision and management. To-gether the matrix serves as a guideline for the En-vironment Planning and Management interventionsrequired for the city. These would be further delib-erated and refined in the city consultations and fi-nally working groups shall be constituted on thepriority issues.

Page 65: CDP

Pg 65Aurangabad Municipal Corporation JNNURM (CDP)

l9 Mixed land use in gaothan & unplanned High fringe development

5 Noise l10 Increasing vehicular traffic creating high Medium noise levels

6 Forest/ vegetation l11 No significant forests within the cityl12 Absence of urban forestry and Low development of regional parks

Urban Utilities and Infrastructure

Sn. Sector Status / issues Priority

1 Water supply l13 Inadequate supply of potable waterl14 Absence of adequate water conservation measuresl15 Heavy dependence on ground water Medium

2 Sewerage & l16 Untreated disposal of untreated sewage in tosanitation water bodies

l17 Inadequate sanitation facilities in 2 slum colonies High3 Solid waste l18 No segregation of waste at source

management l19 Absence of decentralized disposal techniques of wet waste such as vermin composting, High biomethanation etc.

4 Traffic & l20 Heavy through traffic passing through the citytransportation

l21 Absence of adequate parking area for local traffic & goods vehicles Medium

5 Power supply l22 Extreme shortage of power leading to frequent power cutsl23 Absence of use & awareness on non-conventional energy resources High

The issue of provision and management of the ur-ban utilities in the slums and poorer areas of thecity is critical as the unsanitary conditions directlyaffect the health of the people living there.

16. What AMC is doing ?

As per provisions of section 67 of Bombay provin-cial Municipal Corporation Act 1949 it is manda-tory for AMC to publish annual Environmental re-port of the city Accordingly the AMC publishes suchreport every year. Environment comprises of air,

water, land all living dead animals. Biological andnon-biological elements are two main element en-vironment of a place depends upon condition ofadjacent areas of that place. Apart from urbaniza-tion and industrialization population is the main el-ement for environment increasing urbanization,increase in population to improve economic condi-tion cutting of trees, in crease in number of slums,increase in solid waste and bio-medical waste,drainage system public toilets, increase in vehicles,traffic accidents, air and sound pollution etc aresome of the several problems improvement in en-

City Introduction and Assessment E. Environmental Profile

Page 66: CDP

Pg 66Aurangabad Municipal Corporation JNNURM (CDP)

vironment means improvement in public health,providing facilities improving living stand and pro-viding civic amenities, control over pollution andincreasing population good etc. There is alterna-tive except environmental condition for a better liv-ing for living beings.

The AMC is conducting periodical tests to checkair sound and water pollution level in different partsof the city with different timings. As per air pollu-tion tests conducted by AMC the level of air pollu-tion is below the standard set forth by the centralPollution Control Board. The drainage water andthe effluent of industries are allowed directly to flowthrough river or nearest nallahs. This adverselyaffects the health condition of resident living in thevicinity. This also affects the fertility of agricultureland. Similarly a sound with 100 decibels causesdumbness. This also affects the working efficiencyof man power. There is every possibility of follow-ing deficiencies.

1.Exhaustion, boredom2.Temporary dumbness3.Permanent dumbness4.Mental depression5.Effects on efficiency

The causes of air pollution

1.Traffic hindrance2.Increasing number of vehicles3.Narrow Roads4.Traffic Jam on Roads5.Horns with harsh sound

Natural sources of environment in the city

1.Tree plantation and its preservation2.Developmental works of Gardens3.Zoological parkThe environment report is required to be publishedannually as per section 67 of BPMC Act 1949 for

which an amount of Rs.5 Lakh is spent As such fornext 25 years an amount of Rs.1.25 Crore will beregaired for this work.

Tree plantation, Preservation andDevelopment of Gardens

There are reservations for gardens, parks and openspaces etc in the development plan of the city.Details of there reservations are mentioned in state-ment No.1 Apart from these there are open spacesin sanctioned lay out and also there are some Mu-nicipal open lands. All these lands are proposedto be developed by doing tree plantation its preser-vation and by developing gardens and parks. Simi-larly tree plantation is done on Govt. lands hillocksetc.Following works are proposed in these develop-mental works.

1.Botanical park2.Zoological park3.Small gardens4.Medium gardens5.Big gardens6.Green belts7.Play grounds8.Medicinal Plant garden

In addition to existing gardens some 200 small-biggardens will have to be developed in next 25 yearsCIDCO area is also going to be transferred to AMC.Similarly there are large area of Municipal lands atoxidation pond Kanchavwadi where Ayurvedic gar-den con be developed gat No.9 of Nakshatrawadi,Gat Nos.214&215 adjacent to Harsul tank and alsoGat No.235&236 As also land near AurangabadCaves in S.No.237 Slaughter House premises inpadeguon, S.No.31 of Bhavsinghpura,S.No.306&307 of mitmita premises of oxidationpond at kanchanwadi, S.No.17 of Pahadsinghpuraand hanuman tekdi premises are such placeswhere tree plantation and its preservation is nec-

City Introduction and Assessment E. Environmental Profile

Page 67: CDP

Pg 67Aurangabad Municipal Corporation JNNURM (CDP)

essary.Similarly to remind our history, ancient treasure andmonuments, such models can be developed. Themodels of nahar-e-Ambari and satvahan pillar canbe prepared and installed in such gardens.The beautification of city roads is necessary fortaking up tree plantation and its preservation. Thefollowing roads are included in this programme.This include tree plantation, providing road divid-ers. Traffic islands, developing lawns, electrifica-tion and foot paths.1. Ajanta Naka to Delhi Gate2. Airport to Mukundwadi3. Sharnapur to Mahawir Chowk4. Paithan Naka to Railway Station5. Beed by pass Road6. 50Km long roads in MIDC Chikalthana premises7. 40 Roads pf 40 Km long the city area8. Developing land beneath several fly over bridges9. Tree plantation in kabrastans samsham bhoomi

is open places, schools, Hospitals, Govt. Of-fices Octroi Nakas, College premises etc.

10.Tree plantation at historical places & Memorials etc.

11.Developing 25-50 M. Long strip at outsideboundary of trenching ground.

12.Implementation of “Beautiful clean and greenAurangabad project”

Developments of Tanks, water park lake view pointrope way and beautiful & green Aurangabad project.There are three Tanks/lakes in the city viz. lakenear Delhi gate, Harsul Tank and Kham Gate. Thelake neat Delhi Gate is named after renowned Birdexpert Dr.Salim Ali Boating facility is available. It isnecessary that drainage water of CIDCO area isnot allowed to mix with the clean water of this lake.The water depth can be increased by de-silting thelake. The capacity of water will increase and boat-ing can be done throughout the year which is nowrestricted to certain period of the year. It is pro-posed to develop a jogging track foot paths and todevelop a garden. Amusement items can be pro-

vided in existing garden adjacent to the lake.

In Harsul Tank also Boating is done for a certainperiod to the year. A smruti van has been devel-oped adjacent to tank. However, this requires fur-ther development with play items of children andproper electrification. A small island is existed inthe middle of the Tank. This island can be devel-oped by providing a rope way and can be thrownopen to the public as a picnic centre.

Adjacent to Harsul tank there is smruti van. Thereis lot of space available for garden and water parkboth at one place. The AMC has decided to de-velop a water park on an area of 5 acres on BOTbasis. This will be a new attraction for tourists.

A rope way can be provided upto island in themiddle of the tank similarly there can be anotherrope way between Nipat Niranjan Hillock or GogaBaba Hillock. This possibility is being examinedby the AMC.

Birds from various parts of India and several otherforeign countries migrate to Dr.Salim Ali Lake dur-ing a specific period of the year. Thousands ofbird lovers visit this lake for bird watching as sucha watching point can be developed here. Similarly,earthen dam at Harsul Tank, development of areaof tank, water park near smruti van view points etcadd more attraction and can result is increase innumber of local and foreign tourists.

By developing gardens, tree plantation & its pres-ervation, development of lake and tank premises,green lawns etc. The city will become beautifuland clean. Hoarding having these slogans can alsobe put up at different places of the city.

For all the above works an amount of Rs.32.37Crore is estimated. Also for planting 2 Lakh treesand its preservation a further amount of Rs.10.88Crore is required. Thus a total amount of Rs. 43.15Crore is required for maintaining environmental

City Introduction and Assessment E. Environmental Profile

Page 68: CDP

Pg 68Aurangabad Municipal Corporation JNNURM (CDP)

balance and for providing Air pollution watch, oxy-gen booths and other measures a sum of Rs. 10Crore is required similarly including other works allthese items will require a sum of Rs. 60 Crore.

Maintenance & preservation ofEnvironment Tree plantation :

1.Development of green belts2.Development of Swamp3.Development of gardens & greeneries4.Tree plantation at chowks and road dividers5.Development of Ayurvedic Park6.Development of Heritage Park

Participation of Public

1.Formation of nature studies circles2.Formation of study groups/organizations for pres-ervation of environment

Measures for pollution control.

It is necessary to make arrangements for manage-ment of drainage water, garbage, traffic, drain wa-ter of garages etc. etc.

Training of city nallahsMeasures for re-use of water preparation of Bio-route zone

Control over dust pollutionbeautification and developing lawns and flowergardens in the buildings which are located on bothsides of the roads.Treatment plants for effluent of industriesTo avoid under ground water pollution inclusion ofa project as the basic amenity in the facilities pro-vided by MIDC of State Govt. supply of pure waterto city and adjoining villages.Controlling on liquor plants and pharmaceutical unitsfor providing effluent plant for drainage water.

Awareness through public education1.Awareness among school/College students.

2.Lectures, Slide Shows, Nature camps, NatureDindi, etc for public awareness. Education & train-ing of Govt./Semi Govt./Public representatives,

Hoardings at different places.

Tree plantation & its preservation

1.Tree plantation on both sides of roads2.Dense tree plantation on open spaces in the city3.Tree plantation in the premises of Schools/Col leges/Govt./Semi Govt. offices4.Tree plantation in Housing colonies, river, nallah

& trenching ground premises. Developing Nurs-eries implementation of compost and vermi fertil-izer projects.

nnn

City Introduction and Assessment E. Environmental Profile

Page 69: CDP

Pg 69Aurangabad Municipal Corporation JNNURM (CDP)

F. Land Use and Development Profile

1. Statutory Provisions for Plan preparation

The statutory powers regarding Planning were em-bodied under the Bombay Town Planning Act- 1915,which was in force till it was replaced by the TownPlanning Act of 1954. The act of 1954 incorporatedthe provisions of the Bombay Town Planning Act,1915 and in addition, made it obligatory for everylocal authority to prepare a development plan forthe entire area within its jurisdiction. The BombayTown Planning Act, 1954 applied to lands withinthe municipal limits only and therefore there wereno provisions for exercising proper and effectivecontrol over the planning and developments oflands in peripheral areas lying just outside themunicipal limits and were growing in a haphazardand irregular manner. There was no statutory powerunder the Act of 1954 for the preparation of regionalplans which, was therefore repealed and replacedby the Maharashtra Regional and Town PlanningAct, 1966. This act came in effect from January11, 1967. This act provided for the establishmentof regions and constitutions of the Regional Plan-ning Board for preparation of Regional Plans, des-ignation of sites for new towns, establishment ofdevelopment authorities to create new towns,preparation of development plans for municipalareas and Town Planning Schemes for executionof the sanctioned Development Plans.

1.1 Preparation of the Development Plan

The present Aurangabad Municipal Corporationwith an area of 138.5 sq. kms under its jurisdictioncame into existence from December 8, 1998 videGovt. Resolution No. AMC/1082/207/CP-12/82UD-21 dated December 3, 1982, after 18 villages wereadded to erstwhile “A” Class municipal council of

Aurangabad. The Bombay Town Planning Act, 1954was applicable to the Marathwada Region underthe provisions of the Bombay Town Planning (Ex-tension and Amendment) Act, 1964 and it cameinto force with effect from May 1, 1965. The provi-sions of this act made it obligatory for every localauthority to prepare a Development Plan for thearea under its jurisdiction within a period of fouryears from the date the act came into force.

Accordingly, Aurangabad Municipal Council pre-pared and published a Draft Development Planfor its limits of 54 sqkm which was sanctioned fora part of the area comprising of 8 planning unitsvide Govt. Notification No. TPS/3067/22693-Wdated April 24, 1969. After following the stipulatedprovisions, the council, submitted the DevelopmentPlan prepared afresh for the remaining areas, whichwas also sanctioned by Govt. vide Notification No.TPS-3073-4259-W-2 dated January 6, 1975.

After formation of the municipal corporation, a needfor controlling and regulating the development inthe extended area (18 villages) was felt. With thisconcern, a Development Plan for the extended areaalong with the area designated as “No Develop-ment Zone” in the earlier sanctioned DevelopmentPlan was prepared by AMC which was sanctionedby the Govt. in UD vide Notification No. TPS/3088/454-CR-59-88UD-12 dated October 15, 1991andit came into force with effect on November 19, 1991.

In 1995, the municipal corporation undertook therevision of the remaining old sanctioned Develop-ment Plan of 1975. The municipal corporation de-clared its intention under section 23(1) [read withsection 38] of the Maharashtra Regional and TownPlanning Act, 1966 to revise the sanctioned Devel-opment Plan of 1975 for the area excluding thearea of “No Development Zone” and including thearea denotified by CIDCO. This planning area un-der revision is almost developed and includes thecongested CBD areas of the city.

City Introduction and Assessment F. Land Use and Development Profile

Page 70: CDP

Pg 70Aurangabad Municipal Corporation JNNURM (CDP)

2 Landuse in the city

The land development as per the development planin Aurangabad city has been under constant revi-sions owing to the presence of different planning

authorities like CIDCO and MIDC and the exten-sions of the municipal limits in 1969 and 1982. Thedetails regarding the landuse under different plansare given in the table 3.1.

Almost all the area under consideration is developed and includes the CBD and congested parts of the city.

1. Development Plan for the municipal council was first prepared in 1969 and was approvedin 1975. According to this plan

a. Total area of municipal council 54.39 sqkms

b. No Development Zone (NDZ) 18.96 sqkms

c. Part of CIDCO in the council area 6.52 sqkms

Net area under plan proposal {a- (b+c)} 28.91 sqkms

________________________________________________________________________

2. After addition of 18 villages to the council and establishment of the corporation in 1982,a Development Plan for the additional area including the NDZ of old council area was pre-pared in 1991. According to this plan,

a. Additional area 70.70 sqkms

b. NDZ of the 1975 plan 18.96 sqkms

c. Area under CIDCO and MIDC (6.52+6.1+7.25) 19.87 sqkms

d. Overlap of 3.92 sqkms 3.92 sqkms

Net area under plan proposal 93.58 sqkms*

Note*: 1. The overlapping area (behind Bibi- ka- Maqbara) was shown in 1975 planas residential area and in 1991, was retained as residential area.

2. The overlapping area was not considered in calculations hence the D.P. Report gives areaunder plan as 89.66 sqkms.

________________________________________________________________________

3. In 1995, the old plan of 1975 of council area was revised which excluded the overlappingarea. According to this Development Plan,

a. Area under 1975 plan 28.91 sqkms

b. The overlapping area 3.92 sqkms

c. Denotifed area of CIDCO 0.30 sqkms

Net area under plan proposal (1-2+3) 25.29 sqkms

City Introduction and Assessment F. Land Use and Development Profile

Page 71: CDP

Pg 71Aurangabad Municipal Corporation JNNURM (CDP)

Table: Development plan Aurangabad (revised)Existing Landuse Analysis 1969 and 1991 - Comparative Statement

Sr.No. Landuse As per standard D.P. of 1969 As per 1991 Survey

Area in Has % Area %

1. Residential 270.87 6.12 942.40 37.262. Commercial 21.25 0.41 80.26 3.173. Public Semi public 490.55 9.27 595.67 23.554. Industrial 94.59 1.79 64.20 2.575. Public utility 7.87 0.15 26.54 1.046. O.S., P.A., Park 63.00 1.19 71.86 2.82

and garden7. Transport and 101.57 1.91 212.51 8.40

communicationTotal developed 1050.57 19.84 1993.44 78.81area

8. Agriculture 2116.14 39.99 74.88 2.979. Water bodies 92.52 1.75 68.87 2.7310. Vacant Land 3082.68 38.42 391.66 15.49

Total Planning Area 5291.34* 100 2528.85 100

Note: * In 1969, the planning area was the entire municipal limit, while in 1991, the planning area was excluding thearea of no development zone of the sanctioned D.P. and area of CIDCO. Therefore an area difference is seen.

As per the revised DP (25.29 sq. Kms), the resi-dential area has been increased to 51 percent andthe area under transportation is increased to about12.50 percent. Another feature is that the recre-

EXISTING LANDUSE AS PER D.P. OF 1969

6% 0%9%

2%0%1%2%

40%2%

38%

residentialCommercialPublic&SemiIndustrialPublic utilityPark&gar.Trans&com.AgriW.bodiesVacant land

2.1 Landuse AnalysisAs already stated there had been three differentDP’s prepared for the present AMC area. The de-tails regarding the different landuse for differentDP’s are given in table 3.1.As per the ELU of 1969 for the council area (52.91

sqkms), only 19.84 percent of the total area wasdeveloped and residential area amounted to 5.12percent. The ELU of 1991 for the revised area(25.29sqkms) shows that this residential area in-creased to 37.26 percent and the entire council areawas developed.

City Introduction and Assessment F. Land Use and Development Profile

ational area is increased to 6.0 percent (as per ELUof 1991), which is necessary for the densely popu-lated areas in the old city.

EXISTING LANDUSE ANALYSIS AS PER D.P. OF 1991

37%

3%24%

3%1%3%

8%

3%3%

15%

Page 72: CDP

Pg 72Aurangabad Municipal Corporation JNNURM (CDP)

Table: Proposed Landuse Analysis (revised) Sanctioned D.P. 2001

Sr.No. Proposed landuse Area in ha. % of developable % of Total area area

1. Residential 1291 53 512. Industrial 45 2 23. Commercial 22 1 14. Public and semi public 596 24 235. Public Utility 29 1 16. Recreational (Parks, P.G.S.,Gardens etc) 137 6 67. Transport and Communication 323 13 12.50

Total Developed area 2443 100 96.5

8. Water Bodies 72 - 39. Agriculture 7 - 0.2510. Cantonment (Vacant land) 8 - 0.25 Total non developed area 87 - 3.50

Total area 2530 - 100

PROPOSED LANDUSE ANALYSIS AS PER D.P. 2001-%0F DEVELOPABLE

LAND

51%

2%1%

23%

1%6%

13%3%0%0%

residentialindustrialcommercialpub&semipublicPublic utilityrecreationalTrans&com.W.bodiesagriVacant land

3. Housing

The building and construction activity is controlledand regulated by the Town Planning Departmentof the corporation. However, there has been a lotof unauthorized construction in the city, owing tothe discrepancies in land titles, as most of the areain the old city was donated by the Nizam ofHyderabad as Bakshis to his citizens.

City Introduction and Assessment F. Land Use and Development Profile

Another peculiar characteristic of housing devel-opment is that the area in CIDCO is developed in asystematic way whereas the development in theold city is haphazard with no regards to rules andregulations. Most of these are termed as slumseven though they have good pucca houses.

Page 73: CDP

Pg 73Aurangabad Municipal Corporation JNNURM (CDP)

Table: Details of Development charges and other charges in BuildingPermission Dept. in Aurangabad Municipal Corporation

Particulars Year 2000-2001 Year 2001-2002 Year 2002 - 2003 Year 2003-2004

Proposal Submitted 862 824 758 753Approved proposals 539 624 557 631Application for 205 214 155 119completionApproval for 98 101 50 51completionLand Development 52,55,360.00 69,10,965.00 85,70,725.00 1,04,86,018.00charges in Rs.Expenses for 43,21,780.00 54,96,125.00 1,22,17,041.00 1,32,26,078.00Development (Rs.)City Development 1,20,25,920.00 85,59,897.00 73,29,509.00 83,03,689.00Charges (Rs.)

Particulars Year 2000-2001 Year 2001-2002 Year 2002 - 2003 Year 2003-2004

Penalties (Rs.) 7,77,377.00 7,95,542.00 2,94,705.00 3,98,448.00Building 49,57,361.00 41,90,479.00 46,87,409.00 44,45,808.00PermissionDeposit (Rs.)

Total (Rs.) 2,83,32,772.00 2,68,51,959.00 3,46,66,666.00 3,90,03,559.00

4. Gunthewari

In the year 2002-2003 the Gunthewari Schemecame into existence under the Aurangabad Munici-pal Corporation. Till date 600 projects have beenproposed, out of which 60 projects are completed.From the completion of these 60 projects Rs.30,00,000 was obtained as the developmentcharges, administrative charges and other charges.

In areas like Srikrishnanagar, Uttamnagar,Bhanusnagar, Balajinagar, Mahunagar, etc. regis-tration of the houses was done. The houses in thisarea do not have any proof of their existence andownership. Therefore, the Gunthewari Scheme isnot applied in such areas. In some areas of the citythere are houses, 20’x 30’ in size. The open spacesin front these houses and in some cases, some

area inside the houses was used for widening ofthe roads. The cooperation of the people was ob-tained but was not as expected. People’s partici-pation is required for the promotion of theGunthewari Scheme. To increase the participationof the local people in the Gunthewari Scheme,some advertisements need to be done.

Certain papers are required for the enrollment inthe Gunthewari Scheme. These are:l Applicationl Sales deedl Tax Clearance Certificatel 7/12, abstract, index- 2l A promising letter of Rs200 on the stamp paper.l 6 prints of the map of the house.

City Introduction and Assessment F. Land Use and Development Profile

Page 74: CDP

Pg 74Aurangabad Municipal Corporation JNNURM (CDP)

For permission to be enrolled in the GunthewariScheme, the following charges are required.

1. Area development charges-Rs.120/sq.metre.2. Administrative charges Rs.12.50/sq.metre.3. Irregular administrative charges Rs.25/sq.metre.

By special order in 2005, Government ofMaharashtra has allowed a proof of lawful posses-sion as enough document for the regularization andno more a proof of lawful ownership is required.Due to lack of knowledge and unscrupulous ele-ments, many poor and lower middle class peoplehad got into a trap of buying a low cost land in ille-gal areas, where it was not allowed to transact forhousing purposes, and thereafter remaining devoidof any civic amenities in unhygienic and very un-comfortable and compromising situations. Due togovernment’s interference now civic body has beenable to embark a massive program of Gunthewaridevelopment and regularization. It is expected thatabout 25000 houses will get regularized in comingmonths.

nnn

City Introduction and Assessment F. Land Use and Development Profile

Page 75: CDP

Pg 75Aurangabad Municipal Corporation JNNURM (CDP)

G. Tourism and History Profile

Aurangabad, a dream destination of Mughal Em-peror Aurangzeb, founded in 1610, is known to-day, as one of the four important cities inMaharashtra. The city is heading towards rapid in-dustrial growth, but retains its past glory andcharms, heritage and traditions. Conspicuouslyseen on the Deccan plateau, it has a rich cultureand a plethora of magnificent arts on display.

The gateway to theWorld Heritage Sitesof Ajanta and Ellora,Aurangabad isnamed after the lastgreat Mughal em

peror, Aurangzeb. Aurangabad district has a longhistory of art and culture – to which several Bud-dhist, Hindu, and Jain Muslim communities havecontributed over the years.

Aurangabad, the district headquarters, is today amodern city, which offers visitors all the comfortsand amenities. It has several luxury and budgethotels, shopping centers, hospitals and banks. Inthe city are three museums housing art treasuresof the region- the Sunheri Mahal Museum, the Uni-versity Museum and the Chhatrapati Shivaji Mu-seum. The numerous city gates of Aurangabad arethe most prominent remnants of an era that estab

lished as a centerof power in theDeccan region.The city wasAurangzeb’s mili-tary base and hemade sure of its

protection walls to resist any attacks. The city oncehas five fortifications and 52 gates, out of which 13

remain today. These gates at the cardinal pointsare named after the cities that lie far beyond. Inthat direction i.e. The Delhi Gate to the North, thePaithan Gate to the South, the mecca (Makkai)Gate to the West and the Jalna Gate to East.Tourism still remains one of the important factorsin working of the city of Aurangabad. Thousandsof tourists, including foreign tourists from variouscountries, visit the city throughout the year. Thedevelopment of Aurangabad has been predomi-nantly due to the importance of tourism industry.The tourists globally for its proximity to the worldfamous know Aurangabad heritage caves ofAjanta and Ellora.Bibi-Ka –Maqbara

Designed as a rep-lica of the famousTaj Mahal, the Bibi-Ka-Maqbara is one ifthe finest examplesif Mughal architec-ture in the Deccan.Aurangzeb’s son, inmemory of his mother Begum Rabis Durani, built itin 1678

PanchakkiAn engineeringfeat of the time isthe panchakki, orthe water mill builtin 1695 by MallikAmbar. The wa-ter, channeledfrom a spring ona distant hill, wasused to power theflourmill and grind

grain for pilgrims. The gardens, with several foun-tains, are a memorial to a Sufi Sant.

City Introduction and Assessment G. Tourism and History Profile

Page 76: CDP

Pg 76Aurangabad Municipal Corporation JNNURM (CDP)

Aurangabad Caves

Situated 3kms. fromAurangabadcity, thesecaves wereexcavated be-tween the 1st

and 6th centuryAD. Though predominantly Buddhist in dedication,they reflect tartaric influences in their iconography.These nine caves comprise mainly Viharas. Thesculptures and paintings inside the caves consistof Buddha images, the Jataka tales and variousBuddhist divinities

nnn

City Introduction and Assessment G. Tourism and History Profile

Page 77: CDP

Pg 77Aurangabad Municipal Corporation JNNURM (CDP)

H. Financial Profile

Since beginning octroi and property tax is the mainsource of income. Generally octroi duty is the back-bone of income of Municipal Corporation.With a view of city development income is mostimportant. The pace of development of the city,similarly industries, business and communicationare responsible for the development. The flow oflocal and foreign tourists also adds to the incomeof the city.Because of Chikalthana and Railway Station Indus-trial Areas, Aurangabad City has rapidly developed.

The development of Waluj and Paithan IndustrialAreas also had important effects on the develop-ment of the Aurangabad city.There is Agricultural produce market committee.The Committee had shifted business activities to anew and spacious place where truck terminal fa-cilities have also been made available. Whole saleand retail business of vagetables, fruits and cere-als are carried out there.The details of Annual Budgets with revised annualbudgets, receipts and expenditures for the last 8financial years have been mentioned in the follow-ing statement.

Actual Receipts (in thousand)

Sr. Year Opening Original Revised Actual ActualNo. Balance Budget Budget Reciepts expenditure

Provisions Provisions

01 1997-98 44646 784842 695548 701392 63542002 1998-99 110618 934784 823952 768899 79255403 1999-2000 86963 1036972 883060 858427 79357804 2000-2001 151812 1155840 1014845 879334 92185005 2001-2002 109296 1355640 970135 942916 97117306 2002-2003 81039 1286620 1079270 992512 89062007 2003-2004 182931 1492615 1185100 1154794 110333508 2004-2005 234390 1727935 1383545 1223093 1340144

nnn

City Introduction and Assessment H. Financial Profile

Page 78: CDP

Pg 78Aurangabad Municipal Corporation JNNURM (CDP)

CITY DEVELOPMENT PLAN

City Development Plan

Page 79: CDP

Pg 79Aurangabad Municipal Corporation JNNURM (CDP)

made for different subjects who had four membersof the corporation including minimum one ladymember, subject experts residing in Aurangabad,concerned HOD and officials of corporation, andtwo journalists who write about the concerned sub-jects in the media, as members.On 20th December, representatives of All India In-stitute of Local Self Government were invited andthey gave guidance to all the HODs for the makingof CDP. After more meetings with office-bearers ofthe corporation, a rough structure was decidedupon and basic data and concept were improvedupon. These data and concept were circulated toall the members of the subject committee, after theyhad sufficient time to through these, a one dayworkshop was held on 13th of January, 2006, inwhich after introductory remarks and guidance, allthe subject committees sat for the whole day indifferent sections of the building and did brain-storming on the subject allotted and gave recom-mendations at the end of the day. All the MPs,MLAs, ex-MP, retired high ranking bureaucrats,professors of professional colleges and other ex-perts also attended the workshop. The suggestionsthat had come from the general public and othereminent personalities as a response to corpora-tions request to participate were also discussed andconsidered. To have a well-defined focus of thediscussion and to have output in a systematic for-mat, all the subject committees were requested tosubmit their conclusions in a three page note:

First Page: Vision statement and the goals/ projects for the subject allotted.

Second Page: Strategy to achieve the goals/ projects.

Third Page: Schedule for implementation.

1.Process

City Development Plan, by the virtue of being adocument that is comprehensive, futuristic and fun-damental from the perspective of a ‘commondream’ for the city, requires a procedure of prepa-ration that must ensure, foremost of all discussionsand participation of all sections of society and notonly elected representatives and the bureaucrats.Elected representatives though represent the popu-lation and bureaucrats though have rich experiencein civic administration and handling of all sorts ofsituations that arise from time to time, can not beexpected to produce a document that takes careof all aspects of civic life and all expectations ofthe general population. It was decided on the be-ginning only that a method will be devised to elicitand incorporate suggestions from a wide strata ofpeople.First meeting in which requirement of CDP wascommunicated took place on 15th of July, 2005 inMantralaya which led immediately to a meeting withall the office bearers in Aurangabad, on 19th of July,in which the concept was discussed and it wasdecided that city must prepare CDP as a basicdocument of development. The decision was an-nounced in the press conference and suggestionsfrom the general population as well as experts wereelicited. All the head of the departments were in-formed and educated about the concept of CDP indetails and the work of basic data preparationstarted immediately. Nagar-sachiv, one of the HODwas entrusted with the work of compilation and fu-ture coordination. All the corporators and publicrepresentatives were requested to give their sug-gestions and ideas and to participate in the pro-cess. About a year back a similar exercise was doneby divisional commissioner’s office for the city andinvaluable suggestions were obtained from theiroutput document. All the experts and other resourcepersons were also involved. To give a formal struc-ture to the whole process, eight committees were

City Development Plan - 1. Process

Page 80: CDP

Pg 80Aurangabad Municipal Corporation JNNURM (CDP)

Details of the subject committees are delineated in

Appendix – B.

All the suggestions of the subject committees werecompiled and put before the General Body Meet-ing of the corporation and discussed and passedas CDP for the Aurangabad city. One point to em-phasize here is that, a CDP, being a long term docu-ment, has to be a dynamic document and has tobe revisited periodically not only to monitor its imple-mentation but also to make suitable amendmentseither to the goals or to strategies that need beadopted to achieve those. CDP, thus, which hasbeen prepared after long drawn and comprehen-sive discussion, may need to be fine tuned furtherlater. City plans to do it while taking the current blueprint to make the first steps towards planned andwell-focused development of itself. It is expectedto not only reduce incidences of issues acquiringurgent proportions before they are handled but alsoto optimize and prioritize the use of scare resources.No knee-jerk or ad-hoc projects or their implemen-tations.

City Development Plan - 1. Process

Page 81: CDP

Pg 81Aurangabad Municipal Corporation JNNURM (CDP)

2 Vision/ Objectives/ Projectsa. Development Plani. Vision

City should implement at least 75% of its develop-ment plan which has been made after so much ofdeliberations and thoughts. Also city should reviseits development plan every 10 years to ensure thatit represents changing needs of the city, and alsoensures that rights of individual citizens owninglands under reservations do not get infringed indi-rectly, by reserving those lands without develop-ing.Also obtaining the building permissions should besmooth, transparent and time bound to ensurethere is no dis-incentive to go for unauthorized con-struction.Also illegal structures that have been constructedbefore 2001 should be regularized as per Govern-ment act while having a strict watch over furtherunauthorized constructions.ii. Objectives

1. To develop at least 75% of reservations as out lined in the plan.2. To keep revisiting the plan periodically to revise the plan to incorporate changing needs.3. To simplify building permission procedures.4. To strengthen encroachment removal and un authorized construction demolition squad.5. To protect open spaces and develop them.

iii. Strategies

It is not possible for the corporation to develop thereservations outlined in development plan all by it-self as the cost required for the land acquisition aswell as its development is huge, as outlined in thecity assessment chapter. This means that corpo-ration must devise new strategies to develop thesereservations. Some of the strategies may be:a. Develop the lands in possession with reserva

tions that are commercially exploitable on a BOTbasis, generating premiums that must be ear-

marked for purchase of further lands under res-ervations or for development of commerciallyunexploitable reservations.

b. To allow the owners to develop the reservationsthrough ‘accommodation reservation’ route,wherein owner develops the reservation to theextent of 1.25 FSI, giving 0.25 FSI to corpora-tion while commercially using the rest 1 FSI.

c. To hand over the rights of development of reservations that are commercially exploitable toagencies like MSRDC etc. which will developthese reservations, as they have resources, andploughing back the premiums into the infrastruc-ture projects implemented through them only.

d. Open spaces can be handed over to the societies to protect after development and also tomaintain them.

e. To promote ‘Group Housing Schemes’ .

iv. Projects1. To digitize the whole development plan and de

velop a ‘layer’ over the basic satellite data.Currently corporation has already paid MRSACmoney to obtain digitized satellite maps.

2. To earmark all the nallas and natural drains onthe development plan.Discussions are on with District Collector officeto obtain village maps and old maps showingall the nallas. Consideration is on to privatizesurvey of these nallas.

3. To get all the open spaces on the names of corporation.Currently a list of all the open spaces as perpermissions given in last decade has been sub-mitted to the city survey office for puttingcorporation’s name on property card.

4.To computerize the checking system of buildingplans as well digitizing plans on a BOT basis.A test study has been done. Shortly tenders onBOT basis will be out.

5. To enlist all the commercially viable reservationswhere lands are not in possession of corpora-

City Development Plan - 2 Vision/ Objectives/ Projects

Page 82: CDP

Pg 82Aurangabad Municipal Corporation JNNURM (CDP)

tion and check feasibility of handing over de-velopment rights to agencies like MSRDC thathave enough resources.

6. To enlist all commercially viable reservationswhere lands are in possession of corporationand develop them on a BOT basis.Currently tenders have been finalized for foursuch reservations and work is expected to com-mence in month of July 2006.

7. To simplify building byelaws.8. To modify building byelaws to make them in line

with byelaws of other corporations and devel-opment agencies.Currently corporation has done resolution toimplement TDR, make staircase free of FSI etc.and proposal has been sent to state government.

9. To ensure that historic heritage of the city remains untouched and conserved.Currently changes in the development rules, list-ing all the heritage buildings has been approvedby the corporation and has been sent to stategovernment for final approval.

v. Key Parameters

Key parameter for this percentage of reservationsdeveloped as per development plan and numberof new building permissions granted vis a vis in-crease in properties as per satellite survey.

b. Water supplyi. VisionCity should have a water supply system that Pro-vides very good potable water,Provides minimum150 liters per capita per day,Ensures up gradationof availability along with the growth of population,Isself sustaining i.e. works on no-profit, no-loss ba-sis at least as for as running and annual mainte-nance charges are concerned,Ensures optimal useof scarce natural resource water, by use of meter-ing and penalizing in terms of charges for morethan optimal use of water,Incentivises use of re-cycle water,Takes into account in most appropri-ate way underground water and ensures rechargeequal to at least the consumption,And promotesseparation of different qualities of water for differ-ent uses like potable, non potable, irrigable, indus-trial etc.

ii. ObjectivesAbove stated vision leads to following objectives:Up gradation of water system in terms of quantityand quality,Design of system with future requirement in viewespecially in terms of pipes laid, while pumping canbe added as per demands,Rationalization of water tariffs, with these depend-ing upon the quantity used, use water is put to, withinbuilt incentives for use of recycled water and dis-incentives for more than optimal use of water, ulti-mately adding up to balancing of annual expendi-ture and recovery, And Move towards use of metersfor quantifying the water used.

iii. Strategies

To achieve the above stated objectives, Corpora-tion should adopt following strategies:a. Implementation of Parallel Water Supply Scheme

on a BOT basis. Corporation should appoint aprivate contractor to lift water from the JaikwadiDam where water has been reserved for thecity and to bring it to the MBR after treatment.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 83: CDP

Pg 83Aurangabad Municipal Corporation JNNURM (CDP)

Strategy should be to find a single private part-ner for this project so that all the three aspectsof the project i.e. intake system, filtration sys-tem and transportation system are implementedby a single agency leadingto minimizing themargin of profit for the agency instead of add-ing up three margins for three agencies andensuring that there is a single agency that isaccountable.

b. Saving cost of running the existing scheme byimplementing energy saving methods like mak-ing pumps energy efficient, on a PPP basis, ap-pointing agencies on a saving-sharing basis,thereby not making corporation invest upfront.This is most important as almost 75% of run-ning cost is due to energy consumption.

c. Reducing need of intake of water from the damby incentivising and promoting use of recycledwater at least for non-potable uses. This is alsocritical as city needs to lift water from the damto the height of almost 80 meters.

d. Raising the water charges to a level where thesystem can become self sustaining at least tothe extent of running and maintenance cost. Thedepreciation and capital cost must continue tobe cross subsidized from other taxes like octroior property tax.

e. To check the viability of captive power generation through unconventional means like wind,to ensure that energy bills of future remain incontrol.

f. To move towards formation of a separate WaterBoard for the city to ensure more professionalmanagement, least political interference,greater ability to raise funds and clear cut de-marcation of exact subsidy that keeps the sys-tem running.

iv. Projects1) Parallel Water Supply Line on a BOT basis.

Status:Tenders called, Pre-bid meetings held. In the laststage of final financial bids.

Outcome:The project has been designed to take care of thewater supply needs of the city till 2031. Due to partimplementation of a scheme by MJP for water sup-ply system augmentation, distribution system hasbeen slightly geared up but intake of water has notbeen improved. And hence the scheme has beendesigned to lift the water from the Dam and to trans-port after filtration to MBR. From MBR, corporationwill take over as the distribution system starts. Theproject has been designed to add water in phasesas population increases. Filtration and offtake hasbeen designed to increase in phases while thetransportation system has been designed to carrywater as per the need of 2031, to minimize totalcapital outlay.2)Making pumps energy efficient on a saving –sharing basis.

Status:Pending with General Body for approval in principle.Outcome:Private party will implement the energy saving de-sign and will save around 15 to 20% energy for thecity. Out of the savings, a percentage will be sharedwith the party for initial three years. This will en-sure that claims of the party are genuine and cor-poration needs not put any money upfront. Alsopumps are maintained to this extent for next threeyears free of cost.3) Isolating pumping machinery from load shading.

Status:1.08 crores have been paid to Maharashtra Elec-tricity Distribution Company, for implementation. Ithas been implemented. This project saved citizensof the city from the vagaries of power cuts leadingto disturbance of water supply schedule.Outcome: As city pumps its water almost at 5stages, load shading really disturbs the distribu-tion system and throws it out of gear, inviting pub-lic inconvenience and thus outcry. Hence City Cor-poration has paid 1.08 cr to DisCom for connect-ing its pumping stations to two different grids. This

City Development Plan - 2 Vision/ Objectives/ Projects

Page 84: CDP

Pg 84Aurangabad Municipal Corporation JNNURM (CDP)

has effectively isolated water supply system fromload shading.

4) Water Audit.Status:Underway. A professional agency has been ap-pointed which has already given an interim reportand is expected to submit the final report along withsuggestions by December 06. Some of the sug-gestions that came along with the interim reportshave already been implemented with 50% grantscoming from the government of Maharashtra forthe same.Outcome:This project should not only point out the quantityof water that is unaccounted for in the bills there bycontributing directly to the loss to City Corporationbut also will suggest changes in the system to savewater and manage this scarce resource better.While pointing out the physical leakages it will alsoresult in detection of illegal connections in the city.This will lead to better revenue realization vis-à-visthe water supplied. Also this is expected to reducethe public grievance that people who have legalconnections have to take on the burden of all theraises in the charges that are effected to reducethe financial loss, thereby effectively subsidizing theillegal connections. This will lead to greater loyalty

S.No. Parameter Current Value Expected Value Year of Achievement

1 Per Capita per 125 150 2010 day availability2 Availability – Alternate Days Daily 2010 (daily/ alternately)3 Operative (including 20 cr 0 2010 Maintenance) losses4 % of Samples coming 5 <1 2010 red

of the citizens towards payment and recoveryshould get a boost.

5) Captive power generation.

Status:Under active consideration by the corporation.Detail discussions have been held withMaharashtra Distribution Company in this regard.The company has shown a positive response. Un-der publication is invitation for expression of inter-ests from private parties for implementation.Outcome:It will have following outcomes:a. It will ensure that energy bill remains in control in future, as cost will be only maintenance cost.b. It will ensure that all the liability of DisCom on

Corporation gets over as power generation willalso generate units for supplying to DisCom inlieu of liability.

c. It will make the corporation a ‘green’ corporationwherein the entire energy requirement will comefrom environmentally clean energy.

Other projects are detailed in Appendix – D.

v. Key ParametersKey parameters to ensure that vision and objec-tives are being achieved and their expected val-ues are:

City Development Plan - 2 Vision/ Objectives/ Projects

Page 85: CDP

Pg 85Aurangabad Municipal Corporation JNNURM (CDP)

c Sewerage and Sanitationi. Vision

City should have a underground sewerage system thatCovers 100% of the city,Collects and treats sewerage quantity that equalsaround 80% of water that is consumed in the city,Recovers its running and maintenance cost throughSewerage tax and not more than 20% of propertytax collections,Upgrades its collection and treatment capacityalong with increase in population and creation,Converts most of its intake into irrigable standardsfit for reuse for non-potable use,Is environment friendly and ensures that no un-treated sewerage goes into any natural NALA ordrain, thereby creating any chances of ground wa-ter contamination or any environmental hazards.

ii. Objectives

Above stated adopted vision for sewerage systemleads to following objectives:Augmenting the capacity of Sewerage TreatmentPlants to around 100 mld in first phase and thenraising it to 80% of water intake of city, instages,Providing underground sewerage lines to all thehouseholds,Ensuring that no sewerage goes untreated into thenatural nalas or drains,Lowering the cost through energy saving methodsand raising the resources by upgrading the chargesto meet the annual operation and maintenance costs.

iii. Strategies

It is expected that a BOT model or a PPP modelmay not be readily applicable to Sewerage system,strategy Aurangabad city wishes to implement isimplement the system by its own by raising financesfrom Government of India and Government ofMaharashtra and some financial institutions. An-other strategy that may be undertaken to ensureprofessional management of the system is to con-vert the sewerage department into a board or at-taching it to water board as when it comes to exist-ence. Pumping costs can be lowered by taking ona partner on a saving-sharing basis.Another strategy is to check viability of BOT basisdevelopment of treatment plant where treated wa-ter is sold by the operator to nearby industry or otherusers on a charge basis and if needed the viabilitygap funding is done by corporation.

iv Projects1. Design and implementation of comprehensive

Sewerage system for the city.2. Addition of 5 MLD treatment facility.3. Renewal and restarting the oxidation pond in

Nakshatrawadi.4. New sewerage main line connecting the sewer

age system to oxidation plant.5. Other projects are detailed in Appendix – D.

v.Key ParametersKey parameters to ensure that vision and objec-tives are being achieved and their expected val-ues are:

S.No Parameter Current Value Expected Value Year of Achievement

1 Percentage of households 70 >95 2011 connected to underground sewerage system2 Treatment facility as 5% 80% 2015 percentage of intake of water3 Operative (including 20 cr 0 2015 Maintenance) losses4 % of Sewerage that is 95% 0 2015 discharged untreated

City Development Plan - 2 Vision/ Objectives/ Projects

Page 86: CDP

Pg 86Aurangabad Municipal Corporation JNNURM (CDP)

d. Solid waste management including Bio-Medical waste

i. VisionCity intends to become cleanest city in the state.City wishes to provide its citizens garbage free so-cial spaces, at the same time treating its garbagein a most environmentally sensitive way.

ii.ObjectivesTo minimize the garbage that is generated and fi-nally taken to dumping ground.To segregate garbage at source so that differentmeans of disposal may be adopted for differentkinds of garbage.To incentivise local use of bio-degradable garbagefor creation of fertilizer that can be used in localopen spaces, gardens, private lawns etc.To have a scientifically managed Land Filling Sitethat complies with all the guidelines of SupremeCourt.To have night sweeping so that transportation ofthe garbage does not hamper traffic and citizensfind their city clean when they get out of their housesin the morning.

iii.StrategiesTo outsource processing of garbage in a scientificand environmentally sensitive way.To privatize some part of the city for garbage lift-ing, as creation of new posts of scavengers is noteconomically sustainable for the city.To outsource transportation of the garbage to bringdown the cost of transportation while improving theoutput.To incentivise the cleaning of internal roads of alayout by association of residents by decreasingtheir Property Tax.

iv.ProjectsFollowing projects are needed to be taken up toachieve above stated vision and objectives:a. Scientific closure of current Dumping Site at

Naregaon. Current site has to be closed downscientifically as it is close to airport.

b. Development of new Land Fill Site. It is proposedthat a new Land Fill site be developed throughprivatization which will be suffice for next thirtyyears. It is expected that if city succeeds in mini-mizing its garbage than a much lesser area willbe required. Thus firstly the project is to go for aland enough for ten years, given current volumesof garbage, so that if city is successful in reduc-ing the volume of garbage to be disposed off,same land will be useful for next thirty years.

c. Processing of garbage. Tenders have been published for appointing an agency that will acceptthe garbage of the city, process it, convert it intofertilizer and sell it. This should lead to significantreduction in total garbage to dispose off finally.

d. Collection and Transportation of garbage. As cityis short of about 30% of required labor strengthto collect the garbage daily, it is proposed thatarea under Ward Office i.e. Ward – D – be priva-tized for collection and sweeping. Tenders forthis project are out. At present CIDCO area thathas been recently taken over by corporation hasprivatized cleaning, sweeping and transportationof garbage and the system is running success-fully.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 87: CDP

Pg 87Aurangabad Municipal Corporation JNNURM (CDP)

e. Health

i. Vision

To ensure ‘Health for all’. City envisions that a mini-mum level of health services must be available toeveryone, especially urban poor. City also envisionsthat for life threatening diseases which may causeuntimely deaths leading to devastations of the fami-lies not only psychologically but also financially, tobe ensured. City also envisions that no epidemicshould be allowed to break. Again all social dis-eases like malaria etc. should be under strict con-trol. Social hygiene which is the responsibility ofthe city corporation is to be given top priority.

ii. ObjectivesTo run primary treatment centers efficiently and ata very subsidized rates so that it is easily afford-able to every urban poor.To incentivise hospitals that provides secondary andtertiary treatments.To strengthen position of Aurangabad as MedicalCenter for the Marathwada, and to move ahead tohelp create all the facilities that are available innearby cities like Pune.To have very effective biological, physical andchemical methods implementation for control ofmosquitoes.To educate citizens value of personal and socialhygiene.

iii. Strategies1. Upgrade the hospital run by corporations to provide quality primary health services.2. To approach urban poor by positioning hospitals near their abodes.3. To target expectant and neo mothers and small children for a healthy delivery and life.4. To develop an effective MIS system that can fore warn increase of incidence of any disease.5. To rope in private doctors not only for better and

dependable and wholesome data collection onprevalence of different diseases but also for sec-ondary and tertiary treatments.

6. Though it is not financially possible for corporation to go for high spatiality secondary and ter-tiary treatment centers, corporation can adoptthe strategy of entering into agreements withprivate and other hospitals to provide these ser-vices to urban poor at concessional rates.

7. Insurance for urban poor against accidents andlife threatening disease is also a strategy thatcity government is willing to explore.

iv. ProjectsUnder SIP project sponsored by EU, corporationhas made a project for computerizing all the dataof Mothers and Children. This involves givingSimputers to all the lady workers that are entrustedwith the responsibility of following up individualcases of expectant and neo mothers, and infants.Insurance for the whole city has been taken up foraccidents and it is applicable to every one who haspaid 100% property tax.

Corporation is upgrading its machinery to tacklemosquito breeding grounds. First physical solutionsand then biological and finally chemical methodslike fogging is used for Malaria control program.Educational programs for teaching value of per-sonal and social hygiene are underway under SIP.City must take up all the projects necessary toachieve above stated vision and objectives.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 88: CDP

Pg 88Aurangabad Municipal Corporation JNNURM (CDP)

f. Road Infrastructure

i.VisionCity must provide its citizens a road infrastructurethat is:a. Safeb. Convenientc. Smoothd. Faste. Of least mental and physical stress.

ii. Objectivesa. To develop the roads to DP widthb. To implement IRDP sanctioned by state govern ment with the help of MSRDC.c. To plan services along with the roads to ensure

that roads need not be disturbed now and thenfor repair or replacement of services.

d. To develop all the junctions technically.e. To minimize traffic control lights by segregating the traffic through flyovers, grade-separators etc.

iii. StrategiesMain strategy is to develop road infrastructurethrough IRDP road wherein toll is collected at theentrance of the city and this is securitized to raisemoney for the roads. Another strategy that city in-tends to experiment is to hand over developmentrights over some commercially exploitable reserva-tions to agencies like MSRDC to develop them andto plough back the profits for the infrastructure.For land acquisition required to widen the roads,strategy is to grant additional FSI or TDR. Proposalfor TDR is pending with the state government forthe approval.

iv ProjectsIRDP of an outlay of 167 cr. is under implementa-tion by MSRDC, it must be taken to full execution.Special grant received by state government in 2005-06 has been converted into a mini IRDP to be imple-mented through the corporation. Roads worth 20crores are planned under defer payment system.Projects are outlined more in Appendix-D.

g.Urban Transport

i. VisionTo provide a city transport that is:a. Affordableb. Convenientc. Safed. Punctuale. Economically viable.

ii. StrategiesCorporation has decided to go through BOT routefor the city transport.

iii. ProjectAfter state transport asked corporation to take overthe city transport, corporation chose BOT route toimplement this project. After tenders, one agencywas selected to run city buses for the corporation.The agency runs the buses on the routes decidedby corporation, charges what is finalized by Re-gional Transport Authority (within the limits decidedby state government), and gives corporation a loy-alty of 80 paisa for each kilometer of running. Thisservice was started on 26th of January, 2006 andcurrently 56 buses are running, generating a dailyvolume of 1.5 lakhs and taking minimum of 50000passengers. Corporation intends to expand its fleetto 150 buses in a year’s time, generating about 3lakhs of monthly loyalty. Currently corporation isgetting about 1 lakh monthly royalty.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 89: CDP

Pg 89Aurangabad Municipal Corporation JNNURM (CDP)

h. Heritage Buildings/ Tourism

i. VisionCity should hand over its heritage in a strongercondition, without changing basic character to itsnext generation.City should offer best of facilities to incoming tour-ists to make his or her stay unforgettable. It shouldmake it easy and convenient to access places andshould provide enough activities to be done.

ii. ObjectivesTo preserve the cultural heritage.To develop the cultural heritage sites in and aroundin such a way that it becomes a economically sus-tainable activity.

iii. StrategiesTo conserve old gates, by strengthening their struc-ture and by stopping through traffic that harms itsstrength due to vibrations.To regulate the building activities near and aroundheritage sites.To declare old sites as heritage sites so that theycan be looked after in a legal way.To levy 2% cess on all developmental charges forconservation of heritage buildings.To conserve old Town Hall, which is about 400 yearsold, and to have regular functions there directedtowards tourists to showcase local art form, culi-nary heritage and culture.To create facilitation centers and information cen-ters.To create places of interest like ‘Aurangabad Haat’,international standard ‘Zoo’ with night safari, na-tional level amusement park etc.

iv Projectsa. Conservation of Gates: Already under process

of tendering. Five gates out of 13 surviving havebeen selected for first phase of project. Total re-quirement is 50 lakhs which corporation is go-

ing to bear.b. Conservation and development of Town Hall:

This has been cleared by General Body, with anexpenditure of 50 lakhs. This project includesconservation as well as its development andpackaging as a tourist center where it is plannedthat daily functions will be held with different art-ists, to show case our dance forms, folk songs,local culture etc. along with servings of local food.The project is expected to start by 15th of Au-gust.

c. Development of Aurangabad Haat. A proposalto develop Aurangabad Haat on the lines of DelhiHaat has already been submitted to GOI throughMTDC for sanction. Corporation has earmarkeda five acre well connected land for the project.

d. Shifting and development of Zoo. Currently corporation has a zoo that is over a spread of 17acres. About 150 acre land has been identifiedwhich belongs to state government and proposalsubmitted to state government for the same. Ithas been decided to shift the zoo in the new lo-cation with a new principle. New zoo will seeanimals moving freely while visitors will have tomove in covered spaces. It is also planned tohave a night safari therein.

e. Amusement Park. Corporation has already earmarked a 23 acre land in the center of the cityfor this purpose and has finalized the developerthrough BOT route. Work on this amusementpark is expected to begin in July, 2006.

f. For convenience of tourists, corporation has created a tourist cell as well as started an AMC-online facility wherein all the information is avail-able over telephone. Again a Map of the city hasbeen prepared with PPP, to be sold at 5 rupees,with all the information and important telephonenumbers.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 90: CDP

Pg 90Aurangabad Municipal Corporation JNNURM (CDP)

i. Slums and Urban Poverty

i. VisionCity should ensure minimum standard of

living in slums and for urban poor, ensure accessto civic facilities, to make available health and edu-cational facilities for the urban poor and to ensurehygienic and humane surroundings. The city shouldstrive for making economic opportunities availableto its urban poor by implanting schemes to upgradetheir skills, by outsourcing some of its requirementsfrom their groups. Next generation of urban poormust have equal opportunity to come up in lifethrough competition in educational field.

ii. ObjectivesTo subsidize health and educational facilities forthe urban poor.To develop existing slums in an integrated way, in-tegrating their dwellings and civic infrastructure.To regularize the dwellings of urban poor where hehas constructed unauthorisedly in Gunthewari area,before 2001.To grant him land title wherever possible.To run schemes to upgrade urban poor’s skill.

iii.ProjectsIHSDP: Corporation has decided to take part wholeheartedly in this scheme. It has been decided todevelop slums in a comprehensive way. Corpora-tion has conducted cadastral survey of four slums,to earmark current ground situation. Then agen-cies have been appointed to impose a good layoutover this. These agencies have not only preparedfull plans of their dwellings to be constructed un-der IHSDP but also have estimated the infrastruc-ture requirements so that wholesome developmentworks can be started simultaneously.

j. Street Lighting

i.VisionA city wide street lighting system, that is energyefficient, and has a minimum response system forcorrections.

ii.Objectivesa. To cover whole of the city under street lighting system.b. To use energy efficient fittings, and other energy saving measures, without affecting the illumination.c. To have a maintenance system in place that is very quick in responding to requirements.

iii. Strategiesa. To replace the electric fittings with energy effi cient ones, through PPP by sharing energy saving.b. To privatize maintenance of street lights, with

strict conditionality and penalty for delays in cor-rections.

c. Establishment of regular system of putting upstreet lights, along with new additions to roadsystem, in an integrated way.

iv.Projectsa. Solar operated Traffic Signal system:

Currently this project is under tender for fewplaces with the grant of GOI.

b. Replacement of normal fittings with energy efficient fittings on a BOT basis.

Currently 5000 fittings have been given on a BOTbasis to an operator who is replacing all the fittingswith energy efficient ones on his own cost and hasensured at least 40% savings in electricity con-sumption. BOT operator is going to maintain thefittings for next seven years and is going to shareenergy savings with corporations, keeping 77% ofsaving to himself and giving 23% to corporation.Other projects are enumerated in Appendix – D.

City Development Plan - 2 Vision/ Objectives/ Projects

Page 91: CDP

Pg 91Aurangabad Municipal Corporation JNNURM (CDP)

k. Educationi. VisionTo make available all the children in the corpora-tion limits, basic minimum primary education.To help develop educational institutions in the cor-poration limits.To strengthen City’s position as an educationalcenter for whole of Marathwada.ii. ObjectivesTo ensure 100% enrollment of children below theage of 14.To make drop out rates zero percentage.To provide quality education through its schools.To provide the facilities to poor children that makestheir education convenient and easy.iii. StrategiesTo train teachers regularly not only to upgrade theirskills but also to instill enthusiasm and dedication.To provide free uniforms and books that otherwiseis beyond the financial capability of many poorchildren.To implement Mid-day Meal scheme inmost effective way.iv. Projectsa. Free Uniforms to Corporation school children:

This scheme is under implementation and hasbeen upgraded this year to give two sets of uni-forms, along with shoes, tie, socks and onesports dress. Till last year only one uniform wasgiven which did not allow children to be alwaysdressed in uniforms.

b. Free Mid-Day Meal: This project is going on sat isfactorily.c. Training of teachers. A set of 21 teachers have

been sent for English Language course to a pro-fessional college, to upgrade their skills. Corpo-ration is encouraged by teachers’ enthusiasticresponse.

i. Samayojan of teachers. A full week’s exercisewas taken for ensuring the requirement of eachand every of 81 corporation schools in terms ofteachers and transfers were done of teachersto ensure optimum availability of teachers in allthe schools. These transfers were done aftertaking into account choices of teachers as wellas their tenure in a particular school.

i. Governance and City Finance

i. VisionCity must have a governance that is transparent,responsive, dynamic, people-centric, accountableand capable of handling present as well as futureneeds of the city. Its finance must be sound, havea system that correctly depicts its status, its usedor hidden resources, so balanced that total outlayfor capital works is at least 50% of its total rev-enue, outlay for establishment expenditure is lessthan 25% of its total revenue, revenue expendituremaking for the rest. Accounting system must bedouble accounting system and dynamic to evolvein to any modern new system as and when it comes.

ii. ObjectivesAbove vision leads to following objectives:Making the governance transparent, responsiveand accountable,Involving the community in decision making sys-tem to make the system people centric,Involving NGOs in implementation, feedback andevaluation systems,Implementing Double Accounting system after fullevaluation of assets and liabilities of the corporation,Reducing the liabilities by taking part in Abhay andother schemes of Government of Maharashtra,Reducing the expenditure on establishment andreducing the revenue expenditure.

iii. StrategiesTo go for the citizen facilitation center,To establish a Call Center,To produce Outcome and Calendar budget,To decentralize citizen centric functions to Wardcommittees and to strengthen these committees,To increase the periods of validity of different li-censes, NOCs etc granted by the corporation,To involve private participation in carrying out rev-enue expenditure to minimize these expenditures andto make system more responsive and accountable,

City Development Plan - 2 Vision/ Objectives/ Projects

Page 92: CDP

Pg 92Aurangabad Municipal Corporation JNNURM (CDP)

To disseminate and make available all the infor-mation about the corporation to all the citizens,To implement Information Act in letter and spirit,To implement Double Accounting System,To implement ERP systems for better control, plan-ning and efficiency,To reduce liabilities that are long standing and un-necessarily piling up by going for one time settle-ments and by swapping loans,

iv. Projects

a. Implementing Double accounting.A team of employees has been constituted in theaccounts department for this. All the HODs havebeen asked to train two of their employees on thismethod of accounting. Tenders for making of li-ability and asset ledgers is currently under process.It is expected that within 1 year corporation wouldbe running a test system where both the account-ing methods will be done parallely.

b. AMC @ Home.This project is already under implementation on aPPP basis and is running very well. Under thisproject, all the licenses, NOCs, permissions etc.are given to the citizen at their homes at a nominalcharge. This has ensured that citizen does not haveto spend his or her valuable time in coming to thecorporation.

c. AMC Online.This project is also under implementation throughPPP route, wherein all the information required byany citizen is given on phone. This is the conceptof call center applied to government.

d. E-tenderingThis project is also under implementation fromJune 1st, 2006, wherein all the tender forms arenow on electronic format and are sold through aPPP route to the prospective bidders. Tenders are

also published on internet.

e. ERP.This project envisions ERP solution to be imple-mented comprehensively for the whole of corpora-tions spanning all departments and all activities.Tender for the project is under consideration andis expected to be out in June 2006. This will notonly enhance accountability and financial consis-tency and checks and balances, but also will in-crease administrative efficiency tremendously.

Other than above projects, corporation has alsoembarked on novel ways. For the current year i.e.2006-07, corporation for the first time presentedan ‘OUTCOME BUDGET’, that was appreciated byeveryone. Also administration presented a‘CALANDER BUDGET’ which earmarks deadlinesfor all the projects undertaken in the budget.

For financial soundness, corporation took part in“ABHAY YOJNA’ of state government and got wholeliability of about 150 cr. waived off, by entering onetime settlement with MJP, and paying about 34 cr.upfront and agreeing to pay about 7 cr. by the endof September.

Corporation is also implementing Right to Informa-tion Act, in letter and spirit to instill transparencyand accountability in the system.

Corporation is also in active dialogue stage withMaharashtra Electricity Distribution Company, tosettle long standing dues of almost 217 cr. Corpo-ration has decided to check the feasibility of a novelscheme of captive power generation to waive offthis liability and to isolate itself from any increasein the cost of electricity in future.

nnn

City Development Plan - 2 Vision/ Objectives/ Projects

Page 93: CDP

Pg 93Aurangabad Municipal Corporation JNNURM (CDP)

REFORMS

Reforms

Page 94: CDP

Pg 94Aurangabad Municipal Corporation JNNURM (CDP)

Reforms

Representatives of the citizens, office-bearersamong them, administration and citizens as a wholehave recognized the need for time bound reformsfor the sustainable development of the city. Someof the reforms which need increase or rationaliza-tion of the taxes or the charges for different ser-vices have also found favor with these stake hold-ers. Even though JNNURM mandates some re-forms, city government has anyway decided to em-brace these reforms due to felt need rather thandue to directives.

Vide resolution dated 20/01/2006, and bearingnumber 156/02, city government has decided toimplement all the reforms mandated by the centralgovernment in a time bound manner, as delineatedbelow:

1. Mandatory Reforms

1.1 Adoption of modern accrual based

double entry system of accounting:

1.1.1 Current Stage: AMC currently runs single entry system of accounting.

1.1.2 Vision and Process:AMC wishes to move to Double Entry systemby the end of current financial year. Under pro-cess for tendering for making of ‘assets’ and‘liabilities’ registers, and valuation of each ofthese entries. Also under process is the ten-der for ERP implementation with emphasis ondouble entry accounting system. It is expectedthat a trial run, when both single entry anddouble entry systems will run parallel for a year,should start from January, 2007. Officers andstaff of Accounts Department are being givennecessary training to adopt this new system.Commerce graduate employees are posted inAccounts Department and the new system isbeing implemented from the year 2006.

1.1.2 Schedule:Corporation intends to implement doubleentry system in financial year, 2006-07.

1.2 Introduction of a system of e-governance using

IT applications, such as GIS and MIS for vari-ous services:

1.2.1 Current stage:The Aurangabad Municipal Corporation hasstarted a website “aurangabad. Mahapalika.org.” Through this website all the details andprocedures of all departments of AurangabadMunicipal Corporation have been made avail-able for the used of citizens. The websitealso gives information about municipal es-tates, tourist places, important buildings, of-fices, officers, non-officials etc. This also

Reforms - 1. Mandatory Reforms

Page 95: CDP

Pg 95Aurangabad Municipal Corporation JNNURM (CDP)

Category of Expected monthly rent

Building Residential per sq.m. Non- Residential per sq.m.

A 9.50 22.60B 7.20 18.50C 6.30 13.00D 3.10 09.60

provides specimen of licenses, certificatesand the procedure to obtain them.A separatecomplaint redressed centre has been estab-lished which provides all requiredinformation’s to complainants. Tender formsare also made available on this website.Computerization has been done in respectof Accounts Department, Meeting Depart-ment, and Municipal Property Departmentetc. etc. The monthly pay slips, GPF slips etc.are being given to the employees throughcomputerization. The bills of demand in re-spect of property tax and water charges havealso been computerized.

1.2.2 Vision and Process:Vision is to implement full ERP package forthe city government. Necessary budget allo-cations have been made in the current finan-cial year and already passed by the GeneralBody. Under tender process for ERP imple-mentation. Tender forms have been dis-cussed, presentations of different ERP prod-uct companies like SAP, Oracle and Microsoftrepresentatives over, and are in final stagesfor publication of the tender.

1.2.3 Schedule:Corporation intends to implement full ERPsystem in next two financial years i.e. 2006-07 and 2007-08.

1.3 Reform of Property Tax with GIS:

1.3.1 Current Stage:There are 1,46,062 properties entered in theAssessment Registers maintained by

Aurangabad Municipal Corporation out ofthese 1,44,207 properties have been as-sessed for property tax purposes. There is ademand of Rs.48 corers including arrearsfrom these properties. To have assessmentof all properties located in municipal limits asurvey is being carried out through a privateagency. While assessing a property NRV,certain percentage of General Tax, Sanita-tion Tax, State Education cess, Tree cess,Fire Tax, Water cess, Drainage Tax, Munici-pal Education cess, Road Tax and Employ-ment Guarantee cess is levied. Out of thisthe amount collected towards state educa-tion cess, and Employment Guarantee cessis credited into state treasury. Similarly, 10%of P.T. levied on large premises is also cred-ited into Govt. Treasury.

The information of Assessment of Property Taxand recovery is given below:

Total number of Properties : 1,46,062Number of Properties assessed : 1,44,207For the purposes of assessment the propertieshave been divided into two categories viz: proper-ties meant for residential purpose. For assess-ment of non-residential properties the NRV isdoubled and on this NRV various taxes/cesses arelevied and a consolidated Bill of Demand is issuedto property holder.While making assessment the properties are cat-egorized as A,B,C,D depending upon nature ofconstruction and the assessment is made accord-ingly.

Reforms - 1. Mandatory Reforms

Page 96: CDP

Pg 96Aurangabad Municipal Corporation JNNURM (CDP)

1.3.2 Vision and Process:Vision is to have full survey of the propertiesin the city area, link it with GIS, have a regu-lar system of updation by both physical sur-veys and by satellite images that may bebought from MRSAC. Access to one’s prop-erty tax details through internet, paymentthrough e-commerce as well as banks, ac-ceptance of requests for the changes throughnet is also a part of future vision.Full survey of properties in the corporationarea has been completed which led to jump-ing of properties no from 90000 to 143000.Computerization of basic data is complete.Notices are on for finalization of the propertytax. Basic layer of properties as per satellitedata from MRSAC is ready, has been paidfor by the corporation. Proposal for linkingthe two is under consideration. Corporationis also seriously considering a proposal totender out the annual process of obtainingdata from MRSAC, its linking with the prop-erties, completion of all procedures for lav-ing of taxes for newly found properties thisway and to share a percentage of the in-crease.

1.3.3. Schedule:Linking of GIS with property tax to be done innext financial year, i.e. 2006-07.

1.4 Levy of reasonable user charges with the objective

that the full cost of O & M or recurring cost is

collected within next seven years:1.4.1 Current stage:

Corporation subsidizes water supply anddrainage services to the tune of almost 50%through other taxations. New water supplyproject for augmentation of water source andparallel water supply line will have chargesto be levied related to the O&M cost. Capitalexpenditure of that will however come fromthe other taxations. Municipal Transport ser-vice launched by the corporation is withoutany subsidy and through BOT route it hasensured that not only are the rates of ticketsvery affordable to everyone, it earns a loyaltyof about 40 lakhs a year. AMC charges forentries to some of its gardens as well its zoo,and these services are mostly recovering itsrunning costs. Capital expenditure is howeverdone from other tax collections.

1.4.2 Vision and Process:All the recurring costs be recovered from theservice itself. However in case of servicesthat are universally utilized like water supply,cross subsidy from other taxes that are lev-ied universally too, like octroi or property taxmay have to be continued for some time infuture.

1.4.3 Schedule : Seven Years.

While fixing annual N.R.V. the monthly rent is fixedtaking into account the above mentioned rates.Thismonthly rent is converted into annual rent and a10% is deducted from this amount of annual rent

and thus annual N.R.V. is decided.On this NRV various taxes/cesses are levied per-centage-wise.

l Demand of Property Tax for 2003-2004 Rs. 40 Crorel Demand of Property Tax for 2004-2005 Rs. 47 Crorel Demand of Property Tax for 2005-2006 Rs. 48 Crorel Recovery of Property Tax for 2003-2004 Rs. 12 Crorel Recovery of Property Tax for 2004-2005 Rs. 11.40 Crorel Recovery of Property Tax for 2005-2006 Rs. 17.50 Crore

Information about Property Tax Demand and Recovery.

Reforms - 1. Mandatory Reforms

Page 97: CDP

Pg 97Aurangabad Municipal Corporation JNNURM (CDP)

1.5 Internal earmarking in the budget for basic

services to the urban poor:1.5.1 Current stage:

Currently some budget heads are specificallyfor the urban poor especially those residingin slums. Schemes of central government forurban poor like SJSRY etc. are implementedin letter and spirit. Corporation’s internalschemes like free uniforms, books to all etc.are targeted towards urban poor who takeeducation in corporation’s primary schools.All internal health schemes have serviceprices very affordable. However more spe-cific internal earmarking will be done in thebudget from next financial year.

Percentage of persons living in unauthorized/temporaryPersons living in unauthorized/ tempo-rary structures without any facilities.l Water supply by A.M.C. 5%l Toilets & other Sanitation 25%l Primary education 0%l Primary health 0%Procedure to reach out the poors A Poverty alle-viation Cell has been established with Project Di-rector as its head and six community organizers,three sewing class teachers and other staff work-ing in this cell for implementation of variousschemes for the benefits of poors.For civil works there is the independent by. Engi-neer (slum), Jr.Engineers, Sub Overseers, RoadKarkun etc. for carrying out various developmentalcivil works in slum areas.Budgetary provision for welfare schemes forweaker sections under slum development pro-grammed.A budgetary provision of 5% of annual budget ofAurangabad Municipal Corporation is kept reservesfor weaker section welfare schemes for develop-ment of slum areas and for providing other ameni-ties. For 2005-06 a provision of Rs. 3.96 corer hasbeen made.

A provision of 50 lakh has been made for Women& Child Welfare Committee and for urban povertyalleviation project under UBSP there is provisionof Rs.7 lakh. Similarly Aurangabad Municipal Cor-poration has also provided an amount of Rs.65 lakhfor financial assistance to poor students of munici-pal schools under Savitribai Phule Vidyarthi SahaiYojana & Dr. Babasaheb Ambedkar UniformYojana, Shaleya Poshan Ahar etc.

From the above mentioned provisions vicic ameni-ties like water supply, Drainage, Sanitation, Health,Open Gutters, Construction of boundary walls, etc.are under taken. This also includes other welfareschemes such as repairs, WBM road, Tar road,etc. Similarly, out of capital expenditure electrifi-cation, lights, health facilities are also provided.Aurangabad Municipal Corporation has also devel-oped some slums as model slums.1.5.2 Vision and Process:

To develop slums of the city in an integratedway and through cluster approach. AMC hastaken an initiative in this area and has ap-pointed agencies to carry out cadastral sur-vey of the slums to record the ground situa-tion. Already surveys of four slums is over.Agencies have also been asked to superim-pose model layout on this survey, carry outcalculations like requirement of shifting orwidening of roads etc., do the estimates forall the services that are required to be givenand to submit DPR for each slums. Socialsurvey of all these four slums have also beencarried out to enlist the social composition ofthe slum population. These surveys, bothphysical cadastral as well as social surveyfor remaining slums has been planned andis under implementation.

1.5.3 Schedule:Next financial year i.e. 2006-07, all the sur-veys must get done, DPRs prepared.

Reforms - 1. Mandatory Reforms

Page 98: CDP

Pg 98Aurangabad Municipal Corporation JNNURM (CDP)

1.6 Provision of basic services to the urban poor

including security of tenure at affordable prices,

improved housing, water supply and sanitation.Delivery of other existing universal services of

the government for education, health and social

security is ensured:1.6.1 Current Stage:

Security of tenure is a state subject, but amassive drive has been taken to regularizeunauthorized structures owned by urban poorwho could not afford housing otherwise, un-der Gunthewari Act, so that each one of themhas access to basic services like roads, wa-ter and sanitation. Out of expected 40000households like this, 20000 have alreadybeen survey and notices to about 6000 havealready been issued, in response to whichabout 2000 have applied for the regulariza-tion. It is expected that this procedure will leadto regularization of at least 20000 householdsout of expected households in next sixmonths. Once this goal is realized, corpora-tion can give these poor all the services whichis otherwise not possible legally. Education,health and other universal services are tar-geted more for urban poor, but will now bespecifically and focused targeted. Thoughsocial security is not guaranteed but corpo-ration has implemented a novel scheme un-der which all the citizens who pay propertytax regularly are ensured by the corporationfor 25000 accidental benefits. No other so-cial security is implemented.

1.6.2 Vision and Process:To regularize and develop Gunthewari areasin totality as well as slum areas, leading toproposals for the conferment of land titles bythe state government. Process for both,Gunthewari as well as Slum development isin full swing, as delineated above.

1.6.3 Schedule: Seven Years.

2. Optional Reforms:Other than these mandatory reforms, followingoptional reforms are being taken up the corpo-ration:

2.1 Revision of bye laws for building c onstruction etc.

2.1.1 Current Status:Administration has undertaken serious mea-sures to streamline the process of grant ofbuilding permission etc. Administration hasofficially moved from the system of ‘better-ment charges’ to ‘self development’; also sys-tem of approval of estimates has been sim-plified by giving model estimates; even taxincentives for builders going for ‘group hous-ing schemes’ has been approved by Gen-eral Body of corporation.

2.1.2 Vision and Process:To simplify rules and byelaws for granting andregulating building permissions. It is also aconscious effort on part of AMC to give thrustto Group-Housing schemes. AMC is the onlycorporation that has started giving 50% prop-erty tax concessions for the people livingGroup-Housing schemes. Regular meetingswith the Architects and Builders associationsfor feed backs and for improvement sugges-tions is taken.

2.1.3 Schedule : Two years.

2.2 Earmarking of at least 20-25% of developed land

in all housing projects for EWS/LIG category witha system of cross subsidization.

2.2.1 Current Status:This reform will require change in the act andthe rules.

2.2.2 Vision and Process:This may be taken up under guidance of stategovernment.

Reforms - 2. Optional Reforms:

Page 99: CDP

Pg 99Aurangabad Municipal Corporation JNNURM (CDP)

2.2.3 Schedule:This may be taken up under guidance of stategovernment.

2.3 Revision of byelaws to make rain waterharvesting mandatory in all buildings and adop-

tions of water conservation measures.

2.3.1 Current Status :This reform has already been implementedwith rain water harvesting compulsory.

2.3.2 Vision and Process:This reform has already been implementedwith rain water harvesting compulsory.

2.3.3 Schedule:This reform has already been implementedwith rain water harvesting compulsory.

2.4 Bylaws for reuse of recycled water:

2.4.1 Current Status:Proposal for tax incentive for reuse of re-cycled water is under consideration.

2.4.2 Vision and Process:To incentivise use of recycled water by de-creasing the tax leviable. Process is to put toGeneral Body after due consideration, andseek approval.

2.4.3 Schedule: Current Financial Year.

2.5 Administrative reforms:

2.5.1 Current Status:Corporation has its administrative expendi-ture under 40% of its budget. However, whiletaking over CIDCO area in corporation lim-its, corporation intends to increase its staffby bare minimum and reduce this percent-age below 30%. Again when corporationstarted its municipal transport system, it didby BOT route and did not add even a singleperson on its establishment while running afleet of 150 buses finally. Corporation also

intends to outsource most of its activities toreduce administrative expenditure.

2.5.2 Vision and Process:To make administration lean and efficient. Toreduce the layers for a decision making pro-cess.

2.5.3 Schedule: Two years.

2.6 Structural reforms.

2.6.1 Current Status:Corporation will take up structural reforms inphases. However PPP route has beenadopted for reforms at public interface level.Novel schemes like AMC@home, and AMC-online has already been implemented alongwith single window system. Efforts are on forminimization of work at corporation level andworks that need not be carried out are beingeliminated.

2.6.2 Vision and Process:Vision is to have delivery mechanism andstructure streamlined, administrative struc-ture of the corporation lean and efficient.

2.6.3 Schedule: Two years.

2.7 Encouraging Public Private Partnership.

2.7.1 Current Status:Corporation has started municipal transportwith PPP. About 14 projects have been givenadministrative approval for BOT implemen-tation. Even in Gunthewari regularizationproject, help of 7 agencies have been takenin a novel and comprehensive way that pre-cludes need of individual citizen to come tocorporation and which ensures that a mas-sive project of its dimensions, regularizing40000 houses, can be completed in 6 monthsrather than 2 to 3 years. Corporation intendsto explore all the fields in which better ser-

Reforms - 2. Optional Reforms:

Page 100: CDP

Pg 100Aurangabad Municipal Corporation JNNURM (CDP)

vices can be offered at lower cost, withoutincreasing its expenditure by going via PPProute. Experience of corporation in this re-gard has been encouraging.

2.7.2.Vision and Process:To embrace PPP way for all the process thatare amenable for this route. It is also envi-sioned that most of the non-core functionscan be better performed through this route,though enough safeguards must be put inthe system to ensure no monopolistic situa-tion is created leading to any kind of exploi-tation of citizens.

2.7.3 Schedule: Two years.

3. Reforms at State Level

Implementation of 74th AmendmentAct 1992

The provisions of 74th Amendment Act 1992 arebeing implemented in Maharashtra State. In pur-suance to these Amendments, the State Act gov-erning Municipal Corporation, Municipal Councilsetc. have also been amended. Prominently suchamendments have been incorporated in BombayProvincial Municipal Corporation Act 1949 andMaharashtra Regional Town Planning Act 1966 andother similar Acts.Details of these amendments are shown in the fol-lowing statement

Sr No Article No. Details of 74th Provision Remarks Constitutional Under B.P.M.C. Amendment Act 1949

01 243 Q Constitution of Municipal Section 5 Council/ Municipal Corporation

02 243 S Constitution of Ward Section 29-A Committees

03 243 T Reservation of Seats Section 5-A04 243 U Duration of Council/ Section 6

Corporation05 243 V Disqualification of Section- 8,9,

Councilors 10,1106 243 Z A State Election Commission Section 14 The State

Election Commissioner (Qualifications & Appointment) Act 1994

07 243 I State Finance Commission - The Maharashtra Finance Commission

(Miscellaneous Provi sions) Act 1994

Reforms - 3. Reforms at State Level

Page 101: CDP

Pg 101Aurangabad Municipal Corporation JNNURM (CDP)

As per 74th constitutional Amendment MaharashtraState Election Commission has been formed. Simi-larly reservations have been made for S.C., S.T.,O.B.C., Women, and Municipal Councils and alsofor the seats of Mayor. For this purpose theMaharashtra Municipal Corporations (Reservationof office of Mayor) rules 1994 have been madeapplicable in entire state of Maharashtra.Provisions of 74th constitutional Amendment have

Sr. Details of Provisions Under Provisions Under RemarkNo. 12th Schedule B.P.M.C. 1949 M.R.& T.P.

Act 1966

01 Urban Planning including 21 Town, Planning02 Regulation of Land-use and 217 to 222 44,45,46 construction of Buildings 253 to 263 47,48,4903 Planning for economic and 63(1-A) social development04 Road and Bridges 63(18) 63(19), 22 (D)

205, 206 22 (E)05 Water supply for domestic, 63(20), 66(7), 128 industrial and commercial purposes06 Public health, sanitation conservancy 63(3), 66(2), 66(42) 22 (B) and solid waste management 290 to 294,31907 Fire services 63(5), 193 285 to 28908 Urban forestry, protection of the 63(1-B) 67(A) 22 (H) environment and promotion of ecological aspects09 Safeguarding the interests of 66(1) weaker sections of society, including the handicapped and mentally retarded10 Slum improvement and up gradation 66(1-A)11 Urban poverty alleviation 66(1-B)12 Provisions of urban amenities and 66 (10) 22 (C) facilities such as park, gardens, playgrounds13 Promotion of cultural, educational 63(15) 66(21) 22 (B) and aesthetic aspects 66(22) 66(42)

been made available completely in Municipal Actsand Town Planning Acts.Schedules 12 include various 18 functions inBombay Provincial Municipal Corporations Act 1949and Maharashtra Regional Town Planning Act 1966which have been entrusted with the Local SelfGovernments.Details of amendments in local Acts listed in sched-ule 12th

Provisions of 12th Schedule of constitution in State Acts

Reforms - 3. Reforms at State Level

Page 102: CDP

Pg 102Aurangabad Municipal Corporation JNNURM (CDP)

14 Burials and burial grounds : 320 to 324 22 (F) cremations, cremation grounds and electric crematoriums15 Cattle ponds : prevention of cruelty to animals16 Vital statistics including registration 63(7), 363 to 371 of births and deaths17 Public amenities including street 36(7) 66(8-A) lighting, parking lots, bus stops and public conveniences18 Regulation of slaughter houses and 63(12), 328, 331 tanneries

As per schedule 12 in all 18 functions have beenentrusted with the Local Self Government, How-ever, such transfer of functions has not been ac-companied by transfer of staff.

Selection Committee

There is already a provision of constitution of se-lection committee for creation of posts, and appoint-ments to these posts after seeking sanction of stategovt. as per provisions of section 45 of BombayProvincial Municipal Corporation Act 1949.

Stamp Duty Rationalization, 2005

As per Registration of Properties Act there is provi-sion of levy of 40% cess on all registration of sale& purchase of properties in Aurangabad city as wellas in entire state of Maharashtra.

Public Disclosure Law

The Government of Maharashtra has notified rightto information ordinance 2002 for entire state witheffect from 23-09-2002. This has been publishedin Maharashtra Govt. Gazette Extra Ordinary Part

IV dt.23-09-2002. The Aurangabad Municipal Cor-poration has also appointed all heads of depart-ments as information officers for their respectivedepartments in the corporation.

Community Participation Law:

There is provision in sections 66(A) of BombayProvincial Municipal Corporations Act 1949 regard-ing the involvement of civil society, while implement-ing the policies/works of Aurangabad MunicipalCorporation. As per provisions contained in section 73, 74 andchapter V of Bombay Provincial Municipal Corpo-rations Act 1949, all works are executed by invitingpublic tenders and by entering into agreementsenvisaging various terms & conditions.There is provision of a Planning Committee as perSection 82(3) of Maharashtra Regional Town Plan-ning Act 1966. This committee comprises of 3-5members of standing committee and experts ofvarious subjects such as Architects, Engineers,Planners, etc.As per provisions of Section 26(1) of MaharashtraRegional Town Planning Act 1966 a draft Develop-ment plan of the city is prepared and notified invit-ing suggestions/ objections from the general pub-lic. The Planning Committee takes decision of

Reforms - 3. Reforms at State Level

Page 103: CDP

Pg 103Aurangabad Municipal Corporation JNNURM (CDP)

these suggestion/ objections. As such the partici-pation of Civil Society, Industry and Business is in-volved in the development of the city.For implementation of development plan the StateGovt. has issued certain instructions vide circulardt.10.04.94 as per section 154 of MaharashtraRegional Town Planning Act 1966. As per theseinstructions the scheme of Accommodation Res-ervation is adopted. Under this scheme the ownerof land which is reserved for a particular purposeis allowed to develop his land for that specific pur-pose and after the site is developed 25% of suchdeveloped site is handed over to Aurangabad Mu-nicipal Corporation free of cost.The Govt. of Maharashtra has formulated a schemefor development of slums. As per this scheme theentire area of slum is got vacated and is given todeveloper with increased FSI. After developmentof the area the slum dwellers are allotted flats inthe building and thus they are rehabilitated.As per provision of rule N-3 of Development Con-trol Rules extra FSI is given in lieu of compensa-tion of land acquired for widening of the roads.Various gardens/traffic islands etc. are given tosponsor NGOs/individual developers for develop-ment of these gardens/ traffic islands and thenNGOs/ developers are allowed to put up their ad-vertisement hoardings free of charges.

City Planning Function

Section 2(21) of Maharashtra Regional Town Plan-ning Act 1966 states that the Local Authority will bethe Planning Authority. As such the AurangabadMunicipal Corporation, Aurangabad is the PlanningAuthority and in this capacity it is responsible prepa-ration of development plan for the municipal limitsof the city an Aurangabad.In the municipal limits of Aurangabad there are in-dependent planning Authorities notified by Govt.These are CIDCO and MIDC. As far as CIDCO is

concerned this authority has completed almost allits developmental activities. Now they are prepar-ing development plan for the adjoining area ofWaluj. As such the entire notified area of CIDCOlocated within the limits of Aurangabad MunicipalCorporation has now been transferred toAurangabad Municipal Corporation.

nnn

Reforms - 3. Reforms at State Level

Page 104: CDP

Pg 104Aurangabad Municipal Corporation JNNURM (CDP)

IMPLEMENTATION AND BUDGETING

Implementation and Budgeting

Page 105: CDP

Pg 105Aurangabad Municipal Corporation JNNURM (CDP)

The Calendar

Year Achievements expected

2006 –October

Reforms

Physical – Projects

Mandatory :1. Double accounting - work on assets and liability ledger started. Tenders finalized.2. ERP tenders finalized, work started.3. Computerization of property tax completed.4. Most of illegal water connections either regularized or disconnected.5. Proposals for at least 4 slums submitted under IHSDP.Optional:1. Completion of rounds of discussion with

interested groups for simplifying and improvingbuilding byelaws.

2. Putting up to GB for discussion on incentivising use of recycled water.3. Start of procedure for decreasing layers of decision making, at least in few departments.4. To sanction at least four BOT development proposals

1. Tender for BOT parallel water supply scheme finalized.2. Fixation of PMC for drainage improvement scheme.3. Completion of replacement of 5000 fittings by energy saving fittings.4. Submission of DPR to central government for different proposals under JNNURM.5. Submission of a new IRDP to MSRDC for con sideration.6. Progress in captive power generation project.

Whole discussion above with the time limits thrownup by the discussions lead to following ‘calendar’that must be adhered to at every step to ensurethat CDP keeps its rendezvous with final 25 years

for which it has been planned. Offcourse CDP be-ing dynamic, some of these milestones may getshifted, or better brought forward, mostly it shouldbe endeavor of the city to stick to these dead lines.

Implementation and Budgeting - The Calendar

Page 106: CDP

Pg 106Aurangabad Municipal Corporation JNNURM (CDP)

7. Start of work on upgradation of Historic system of water supply.8. Floating of expression of interest for recycling of drainage on a BOT basis.9. Cleaning of natural nallas done.10.Traffic signals using solar energy as approved by GOI installed.

Mandatory :1. Double accounting - work on assets and liability ledger started. Tenders finalized.2. ERP tenders finalized, work started.3. Computerization of property tax completed.4. Most of illegal water connections either regularized or disconnected.5. Proposals for at least 4 slums submitted under IHSDP.Optional:1. Completion of rounds of discussion with interested

groups for simplifying and improving building bye-laws.

2. Putting up to GB for discussion on incentivising use of recycled water.3. Start of procedure for decreasing layers of decision making, at least in few departments.4. To sanction at least four BOT development proposals.

1. Work on BOT parallel water supply scheme started.2. DPR for drainage improvement scheme submitted.3. Completion of replacement of another 5000 fittings by energy saving fittings.4. Work on proposals submitted to central government for different proposals under JNNURM started.5. Sanction for new IRDP by state government through MSRDC for consideration.6. Work started on captive power generation project.7. Completion of work on upgradation of Historic

Reforms

Physical – Projects

2007January

Implementation and Budgeting - The Calendar

Page 107: CDP

Pg 107Aurangabad Municipal Corporation JNNURM (CDP)

system of water supply.8. At least one project on recycling of drainage on a BOT basis started.

Mandatory:1. Double accounting – Move completely to Double Accounting.2. ERP full flegdedly in operation.3. Regular system for upgradation of Property tax registers with regular satellite imagery established.4. Percentage of unaccounted water under check, at least 80% of running cost recoverd.5. Integrated development of few slums under IHSDP.Optional:1. Simplified byelaws for building permission comes to force.2. Minimum layers of decision making in all departments established.

1. First phase of parallel water supply system commissioned.2. Work on upgradation of sewerage system started.3. Some works completed under new IRDP, all works under current IRDP completed.4. Almost all poles have energy efficient fittings.5. All traffic junctions to have traffic lights.6. First phase of captive power generation project finalized.7. Completion and recommissioning of upgradation

of Historic system of water supply.8. Start of recycling of drainage on a BOT basis.

Mandatory:1. Double accounting – Move completely to Double Accounting.2. ERP full flegdedly in operation.3. Regular system for upgradation of Property tax registers with regular satellite imagery estab lished.

2007July

2008July

Reforms

Physical – Projects

Reforms

Implementation and Budgeting - The Calendar

Page 108: CDP

Pg 108Aurangabad Municipal Corporation JNNURM (CDP)

4. Percentage of unaccounted water under check, at least 80% of running cost recoverd.5.Integrated development of few slums under IHSDP.Optional: 1.Simplified byelaws for building permission comes to force.2. Minimum layers of decision making in all departments established.

1. First phase of parallel water supply system commissioned.2. Work on upgradation of sewerage system started.3. Some works completed under new IRDP, all works under current IRDP completed.4. Almost all poles have energy efficient fittings.5. All traffic junctions to have traffic lights.6. First phase of captive power generation project finalized.7. Completion and recommissioning of upgradation of Historic system of water supply.8. Start of recycling of drainage on a BOT basis.

Mandatory:1. Percentage of unaccounted water under check, at least 80% of running cost recovered.2. Integrated development of slums under IHSDP.Optional:1. Structural and administrative reforms on progress

1. Parallel water supply system fully commissioned.2. Work on upgradation of sewerage system mostly completed.3. Most of the works completed under new IRDP.4. Captive power generation project commissioned.5. Newer projects submitted under JNNURM.

Physical – Projects

Reforms

Physical – Projects

2009July

CDP is revisited, modified, new projects as per current needs get identified and

implemented. Financial and administrative discipline sets in. City marches towards

achievement of vision set in CDP. Reforms get acceptance as a dynamic feature.

City government becomes responsive, transparent and accountable.

20102011201520212031

Implementation and Budgeting - The Calendar

Page 109: CDP

Pg 109Aurangabad Municipal Corporation JNNURM (CDP)

Budgeting

Annual budget, that the corporation prepares ev-ery year, plans for that year the receipts as well asthe expenditure. However its effect should be seenin the change in the key parameters of urban life,and thus more than the financial budget, the out-come budget becomes more important for know-ing its contribution towards the vision that has beenenumerated in this document. It is thus plannedthat from 2006-07 onwards, every year, the city willnot only prepare the financial budget but also itsoutcome budget. This has been started in rightearnest and the budget that has been prepared for2006-07 and presented to the General Body foracceptance has ‘outcome’ budget too. This will helpkeep an eye on whether after the annual expendi-ture has been made, city has progressed in theright direction or not. Another issue to be addressedis that this document talks about different key pa-rameters for different aspects of city governanceto be achieved in a particular timely way (as de-tailed in the ‘calendar’ section preceding currentsection), and every budgeting exercise should takeinto account this fact while planning its revenue andexpenditure. Financial projections for the differentprojects enumerated in this document must getaligned with the budgets of successive years. Againthe strategies that have been suggested in thisdocument, should get reflected in the budgets. It isthe budget that is implemented in any given year.Thus while preparing the budget of any year, CDPmust be used as a guiding tool. This has beenstarted in right earnest by the administration. Andthus budget that has been submitted to GeneralBody has new heads like premiums from BOT pro-posals like Bus Transport, Amusement park, com-mercial complexes etc. on the revenue side andhas new heads like expenditure on ERP solution,payment to private agency for maintenance andupgradation to energy saving in street lights etc. inthe expenditure side. Next year, once the BOOT

project on water supply rolls out, heads in revenueand expenditure sides will also get added corre-spondingly. New revenue sources enumerated inthis document as well as new ways of expenditure(through PPP) must get reflected.Annual Budgets will also serve as important yard-sticks to know whether implementation of CDP ison track. The composition of the revenue receiptsfrom different taxes and sources should get modi-fied to that expected after realization of vision.Thus city must links its successive budgets to CDPand use budgets to keep track of its implementa-tion also.

Monitoring and Revision of CDP

It is proposed that a committee at the city level, bythe name of City Management Committee beformed with Hon. Mayor as the chairman and draw-ing its members from the elected representativesas well as eminent personalities and experts fromthe citizens to meet at least twice a year to over-see the implementation and the progress madeunder CDP. There will be another executive com-mittee under chairmanship of Commissioner toimplement the CDP, under the overall guidance ofCity Management Committee. It would be the re-sponsibilities of these committees to monitor theimplementation of CDP and also to take up neces-sary discussion steps with all concern if any needis felt to revise the CDP, or to revise its targets.Without such periodic monitoring and necessaryrevision, CDP may soon loose its relevance withtime.

Implementation and Budgeting - Budgeting - Monitoring and Revision of CDP

Page 110: CDP

Pg 110Aurangabad Municipal Corporation JNNURM (CDP)

RESOLVE AND MOU

Resolve and MOU

Page 111: CDP

Pg 111Aurangabad Municipal Corporation JNNURM (CDP)

Resolve and MOU

Aurangabad Municipal Corporation Aurangabad.

Extracts of proceedings of General Body Meeting held on 20.01.2006

Subject No. 156/02Proposal is submitted that Jawaharlal Nehru National Urban Renewal Mission is a scheme of Gov-ernment of India, superseding all existing schemes of financial assistance. This scheme was de-clared by Central Govt. on 03-12-2005. To take part in J.N.N.U.R.M the Municipal Corporation hasto prepare a Development Plan for city upto 2025. As per instructions of Central Govt. a commitmentfor mandatory Reforms and a Time Table is necessary to be given. After Completion of above for-malities a Project Report will be prepared in consonance with Development Plan and the same willbe sent for grant of financial assistance under the above scheme. For this purpose the Administra-tion after consultation with mayor, office Bearers, and by calling suggestions Municipal Corporatorsinclusive of Lady Corporators, Experts in various fields in the city, Journalists and other persons, hasprepared a Draft Development Project which is submitted for approval.After approval the same would be incorporated in prescribed form expected by Central Governmentand will be finalized with necessary revision and changes with the approval of Mayor and then will besubmitted to Government. Similarly a proposal of Mandatory Reforms is also submitted here with forapproval. After approval, a Memorandum of Understanding (MOU) will be finalized with the Govern-ment of India with the prior approval of Mayor and Office Bearers. It is also proposed that followingprojects may be approved for submission to Central Government for grant of financial assistance.These Projects are in consonance with development plan and priorities mentioned therein.01. Water Supply-Laying of parallel water supply Line, improving and strengthening distribution system.02. Drainage Project. 03. Solid Waste Management.04. City Bus Transport. 05. Construction of 1000 houses under slum development.Similarly, approval is also sought for submitting other proposals which will be eligible for financialassistance as per Development Plan. Such proposals will be submitted with the approval of Mayor.Submitted for approval.Resolution :-As mentioned in the proposal, approval is accorded unanimously to the Project for Aurangabad City2025 under Jawaharlal Nehru National Urban Renewal Mission. Similarly, approval is given forpreparing the Project in Prescribed form with the necessary approval of Mayor with necessary revi-sion and changes and submitting the same to Central Government through State Government andalso to mandatory reforms and to sign a Memorandum of Understanding with a approval of Mayorand Office Bearers. Unanimous approval is also given to projects mentioned at sr. no. 1 to 5 forobtaining financial assistance from Government by submitting the same from time to time.Action may be taken.

Sd/- Sd/- Secretary Mayor Municipal Corporation Municipal Corporation

Resolve and MOU

Page 112: CDP

Pg 112Aurangabad Municipal Corporation JNNURM (CDP)

MEMORANDUM OF AGREEMENT [MOA]

THIS AGREEMENT is made on this ——-————day of —————,200———— between theGovernment of India, through the Ministry of Ur-ban Development or the Ministry of Urban Employ-ment and Poverty Alleviation, of the Part I

AND

The State Government of Maharashtra State,through its Governor , of the Part II

AND

The Municipal Corporation of Aurangabad throughits authorised person, of the Part III

WHEREAS the part III, seeks financial assiswtancefrom the Part I under the Jawaharlal Nehru Na-tional Urban Renewal Mission (JNNURM);

WHEREAS the part III, in pursuasnce of the require-ments for assistance has developed a city Develop-ment Plan (CDP), Fully detailed in Annexure I;

AND WHEREAS the part III has formulated a de-tailed project report in respect of ———————————————, with details on its feasibility, fullydetailed in Annexure II;

AND WHEREAS the part II and part III have un-dertaken to implement the reform agenda, as perthe timeline indicated therein, fully detailed in An-nexure III and IV;

AND WHEREAS the part I has considered thedocuments mentioned in Annexure I,II,III, and IVand found them consistent with the goasl and ob-jectives of JNNURM;

AND WHEREAS the part I agrees to release a

grant of Rs. ———/- over a period of —————years, in accordance with the trerms and condi-tions specified in the agreement.

NOW THE PARTIES WITNESSED as follows:

1.That the part I shall release the first installmentof Rs.—————- /- upon signing of theMemorandum of Agreement (MOA) and submis-sion of the above mentioned documentsi.e.,Annexure I,II,III,and IV;

2.That the Part I may release the second install-ment of Rs . ——————/- upon submissionof a statisfactory Progress Report indicating—

a) —————————————-

b) —————————————

c) ————————————-

3.That the Part I may release the third installmentof Rs.————————/-upon submission of asatisfactory Progress Report indicating-a) —————————————-

b) —————————————

c) ————————————-

4.That the Part I may release the final installmentof Rs.————————/- upon submission of asatisfactory Progress Report indicating-a) ——-———————————

b) —————————————

c) ————————————-5.The Part I or an Institution nominated by it, mayundertake a sitevisit to ascertain the progress ofthe ongoing projects and also the reforms agenda

Resolve and MOU

Page 113: CDP

Pg 113Aurangabad Municipal Corporation JNNURM (CDP)

through designated representatives periodically;

6.That apart from the Progress Report, the Part IIIshall submit a Quarterly Report of the spendingsof the grant to the Part I. In casePart III fai ls tosubmit such a report further installment of grantmay be withheld until such submission;

7.Similarly, the Part II shall submit a Half-yearlyReport of the progress in respect of the implemen-tation of the reform agenda as detailed out in An-nexure III.

8.That Part II and Part III shall submit a completereport regarding the outcome of the JNNURM onthe completion of the project;

9.That the Parties to the agreement further cov-enant that in case of adispute between the par-ties the matter will be resoved to arbitration withinthe provisions of the Arbitration and ConciliationAct, 1996 and the rules framed thereunder andamended from time to time. The matter in disputeshall be referred to ————————( Insert aname of an arbitrator) as arbitrator,however, in case such person refuses to act asarbitrator, or is rendered, unable because of sick-ness or otherwise, or dies, ———————(nameof the second person for arbitrator) shall act asarbitrator between the parties and the dispute shallbe referred to such person and still in case thissecond person is not available for any reason toact as arbitrator between trhe parties, both partiesshall name one person of their choice as arbitratorand decision of such arbitration shall be final andbinding on the parties.

10.That in case there is any delay in the i m p l e -mentation of thereforms agenda or submission ofany periodic reports, etc. at the State level by thePart II or Urban Local Body or Parastatal level bythe Part III, due to the circumstances beyond the

control of Part II or Part III i.e.,Force Majeure orany othe reason, the decision on the matter of ex-tension of time for the implementation of the goalsand objectives of the JNNURM shall be at the dis-cretion of Part I.

11.That in case of any breach regarding the termsand conditions of the JNNURM, the Part I shall beentitled to withhold subsequent installments ofthe grant on giving 30 days notice to the part II orthe Part III. However, in this regard decision takenby the Part I shall be final and binding on the Part IIor the Part III, though, before making such orders,opportunity of hearing shall be given to the Part IIor the Part III.

IN WITNESS HERE OF all the parties have puttheir hands on these presents of Memorandum ofAgreement in the presence of witnesses.

WITTNESES:

1. ———————— Ministry of Urban De-velopment

or2.—————Ministry of Urban Employment andPoverty Alleviation(Government of India) (Part I )The Government of ———(Part II)

Municipal Corporation of —————or

Parastatal Agency —————(Part III)

Resolve and MOU

Page 114: CDP

Pg 114Aurangabad Municipal Corporation JNNURM (CDP)

EPILOGUE

Epilogue

Page 115: CDP

Pg 115Aurangabad Municipal Corporation JNNURM (CDP)

Epilogue

The city government, after much internal and ex-ternal debate and discussions, has given itself thisCity Development Plan, formally vide the resolu-tion stated in the last chapter and has also com-mitted itself to implement it through the MOU pro-posed therein. The success of the plan, and thusof the city itself in giving its citizens every aspect ofurban life enumerated in its vision, will depend uponthe continuance of this earnestness. This earnest-ness can be demonstrated every year by linkingthis document with its budgetary process and bymaking sure that each successive budget takescity further on the path shown in this document. Asalso stated in prologue and the chapter on imple-mentation and monitoring of CDP, this documentis a dynamic one, requiring frequent revisits andmodifications, to take care of changes in internalas well external environments. This dynamism andearnestness will surely take city on the path toachieving its vision for its citizens. How close thecity gets to achieving this vision will be the test ofsuccess of this exercise of making CDP and of theambitious program JNURM, launched by Govern-ment of India, in respect of Aurangabad City.