+ All Categories
Home > Documents > Cec 103.- Workshop Technology 1

Cec 103.- Workshop Technology 1

Date post: 03-Jun-2018
Category:
Upload: viethungcao
View: 1,093 times
Download: 764 times
Share this document with a friend

of 128

Transcript
  • 8/12/2019 Cec 103.- Workshop Technology 1

    1/128

    &

  • 8/12/2019 Cec 103.- Workshop Technology 1

    2/128

    TABLE OF CONTENT

    Title page

    Content

    WEEK ONE

    1. Sketch of site layout showing how to set out a simple residential building foundation

    and superstructure

    1.1 Site plan

    1.2 Example:practical to set out site

    FIG: 1.1: Site plan showing boundaries and adjacent roads

    FIG: 1.2: Site plan with landscaping

    WEEK TWO

    2. Execution of foundation trench and casting concrete

    2.1 Trench excavation

    2.2 Timbering of trench excavation

    2.3 Trench preparation for concrete foundation

    FIG: 2.1: Timbering in trench excavation

    WEEK THREE

    3. Mixing of concrete

    3.1 Batching

    3.2 Mixing

    3.3Handling

  • 8/12/2019 Cec 103.- Workshop Technology 1

    3/128

    3.4 Placing

    3.5 Specifying concrete

    3.6 Example:

    FIG: 3.1. concrete mixer

    FIG: 3.2. placing of concrete

    FIG: 3.3. a model mobile concrete mixer

    FIG: 3.4. a wheelbarrow

    WEEK FOUR

    4. Setting out of a simple resdential building block wall super structure

    FIG: 4.1. Setting out of block wall superstructure

    WEEK FIVE

    5. Plumbing of pipes for waste water as drainage

    5.1 System of drainage

    5.2 Choice of pipes

    5.3 Setting out of drainage system

    5.4 Laying of pipes

    5.5 Jointing of pipes

    5.6 Drainage test

    FIG: 5.1. Couplings and vents

    FIG: 5.2. Drainage system

  • 8/12/2019 Cec 103.- Workshop Technology 1

    4/128

    WEEK SIX

    6. Laying of blocks/bricks in different bonds

    6.1 Purpose of bonding

    6.2 Choice of brick bond

    6.3 Choice of mortar.

    6.4 Principles of bonding of brickwork

    6.5Types of bond

    6.6 Setting out bonds

    FIG: 6.1. Stretcher bond

    FIG: 6.2. English bond

    FIG: 6.3. Flemish bond

    FIG: 6.4. Header bond

    FIG: 6.5. Brick bonds

    FIG: 6.5. A brick wall

    WEEK SEVEN

    7. Identification of construction wood types and their sizes

    7.1 Construction wood types:

    7.2 common sizes of timber

    FIG: 7.1. Internal structure of wood

    FIG: 7.2. Sawn wood

    WEEK EIGHT

    8. Preparation of piece of wood by hand and machine

    8.1 Hand preparation of member

  • 8/12/2019 Cec 103.- Workshop Technology 1

    5/128

    8.2 Machine preparation

    WEEK NINE

    9. LAYOUT OF A STANDARD CARPENTRY AND JOINERY WORKSHOP

    9.1 standard carpentry and joinery workshop

    9.2 example: 1

    FIG: 9.1: Standard carpentry and joinery workshop

    FIG: 9.2: Standard carpentry and joinery workshop

    FIG: 9.3: Standard carpentry and joinery workshop

    FIG: 9.4: Standard carpentry and joinery workshop

    WEEK TEN

    10. Preparation for joints in wood work

    10.1 Types of joints

    10.2 Example: 1

    FIG: 10.1.Halved joint

    FIG: 10.2.Halved joints

    FIG: 10.3. Bridle joint

    FIG:10.4. Mortice and tenon joint

    FIG: 14.5. Dowelled mortice and tenon joints

    FIG: 14.6. The secret haunch mortice and tenon

    FIG: 14.6. The secret haunch mortice and tenon

    FIG: 14.7. Wedged mortice and tenon

  • 8/12/2019 Cec 103.- Workshop Technology 1

    6/128

    WEEK ELEVEN

    11. Making use of metal dogs/fastening and gusset plate

    11.1 Gusset plate

    Fig: 11.1. 25mm gusset plate

    Fig: 11.2. Timber girder truss with gusset plate

    Fig: 11.3. Gusset plate in truss roof

    Fig: 11.4. Timber king post trusses with gusset

    Fig: 11.5. Gusset plate

    Fig: 11.6. Gusset plate

    Fig: 11.7. Gusset assembly for trusses

    11.1.0 Metal dogs

    FIG: 11.8. Iron dogs

    WEEK TWELVE

    12. Construction of wooden floor

    12.1 Types of wooden floor

    12.2 Method of construction:

    12.3 Floor joists suitable for domestic floor loadings

    FIG: 12.1: Double floor

    FIG: 12.2: Framed floor

    WEEK THIRTEEN

    13.0.0 Nails, screws and bolts

    13.0.1Nnails

  • 8/12/2019 Cec 103.- Workshop Technology 1

    7/128

    13.0.2 Screws

    13.0.3 Raw bolt

    FIG: 13.1. Different types of nails

    13.1.0 Construction of wooden sills

    13.1.1 Window sills

    FIG: 13. 2. Construction of window sill

    WEEK FOURTEEN

    14.0.0 construction of centres for arches

    14.0.1 construction

    figure: 14.1. segmental arch centre

    FIG: 14.2.Costruction of semicircular arch centre

    FIG: 14.3. Construction of turning piece

    14.1.0 Construction of timber shores

    14.1.1 Method of construction

    FIG: 14.5. Raking shore

    FIG: 14.6. Dead

    14.2.0 construction of panel doors

    14.2.1 Manufacture of paneled doors

    FIG: 14.7. Four panel door

    FIG: 14.8. Three panel door

    FIG: 14.9. Panel doors

    FIG: 14.10. Panel doors

    14.4.0 Construction of door and window frame

  • 8/12/2019 Cec 103.- Workshop Technology 1

    8/128

    14.4.1 Door frames

    14.4.2 Window frames.

    WEEK FIFTEEN

    15.0.0 Construction of simple and built-up roofs

    15.0.1 Design of roof

    15.0.2 Construction method

    FIG: 15.1. Untrussed roofs

    FIG: 15.2. Trussed roof

    15.1.0 Construction of straight flight of stairs

    15.1.1 Setting out one paper

    15.1.2 Setting out and construction in workshop

    15.1.3 Assembling the parts of stair

    FIG: 15.4. Straight flight stair plan

    FIG: 15.5. Wooden straight flight stair

    FIG: 15.6. Wooden straight flight stair

    15.2.0 Construction of door casing

    15.2.1 Door casing or lining

    15.2.2 Example: assembling and installation of door casing

    FIG: 15.7-15.15: Construction of window sill

  • 8/12/2019 Cec 103.- Workshop Technology 1

    9/128

    WEEK ONE

    1. A SKETCH OF SITE LAYOUT SHOWING HOW TO SET OUT A

    SIMPLE RESIDENTIAL BUILDING FOUNDATION AND

    SUPERSTRUCTURE

    1.1SITE PLAN

    A site plan is a drawing of your property showing the property lines and any structures that

    currently exist on that land (house, garage, fence, etc) and where your proposed addition,

    deck, porch, garage, fence, etc is to be located.

    Contents of a site plan

    A site plan should include:

    An arrow indicating north

    The scale of the drawing

    Draw the site plan to the most appropriate scale, for example, 1 = 10, 1 = 20,

    1/4 1.

    Property lines For most additions, property lines will need to be physically

    located. Additionally, a certificate of survey, signed by a licensed surveyor, will

    be required in some cases.

    Adjacent streets and any easements.

    The distance between buildings and between buildings and property lines.

    The dimensions of the existing buildings.

    A clear indication of the proposed addition or alteration.

    Other appropriate items for your project.

    For additions, two copies of the site plan must be submitted. An architectural plan and/or

    a structural plan may also be required.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    10/128

    Site plan review

    A site plan review determines compliance with local ordinances and applicable state

    building and mechanical codes. This review is done by a city planner. When the planner

    gives approval, the next step is to apply for permits.

    Projects that usually do not require a site plan review:

    Siding, roofs, window replacement, and miscellaneous repairs do not require a site plan

    review. Most electrical, plumbing, and mechanical permits also do not require a site plan

    review.

    Changes to the site plan

    After your site plan has been approved, any changes to it must also be approved.

    A SITE PLAN is a map of your site. It is drawn "to scale" which means that all of the

    real life dimensions are reduced to the same degree. Scales can vary, depending on the

    size of your site and the size of your paper. A typical scale for a small site might be 1

    inch equals 1 foot. The larger the site, the smaller the scale you would use, such as 1/4

    inch equals 1 foot

    Why draw a site plan?

    A SITE PLAN is a very helpful planning tool. When you are able to see the dimensions

    and layout of your site on paper it is much easier to calculate the materials you will need

    and to see where different activities can occur. The site plan makes your project portable;

    you can carry it in your pocket or mail it. You can make copies. Your planning group can

    sit around a table and discuss the project over a copy of the plan.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    11/128

    1.2 EXAMPLE:Practical to set out site

    Tools:

    To measure the site:

    Tape measure, or measuring "wheel" and a compass to find north.

    To draw the plan:

    Graph paper, pencils or pens, ruler (or scale.)

    HINT: If you don't have a tape measure you can "pace off" the site. This means that you

    walk the places you want to measure with even strides, counting how many strides you

    took. Then you measure your stride. If your stride is 3 feet long, and you paced twenty

    strides along the front of a building, the building is 60 feet long. You can also use your

    feet and hands as measuring tools. For example, if you know your feet are ten inches long

    you can measure the width of a sidewalk by placing one foot after the other, counting and

    multiplying.

    When you go out to a site to take measurements and notes, do a "rough draft." You don't

    need to draw straight lines or make it neat, just get the information you need.

    Measuring

    Measure the length and width of the lot, or the portion of the lot you want to work

    on.

    Locate important built features such as buildings, sidewalks, streets, fences, etc.

    and mark them on your plan.

    Locate natural features, such as trees, large rocks and water and mark them on

    your plan.

    Find north. Knowing where north is will be helpful when you want to know how

    much sun your site gets. Make a "north arrow" on your plan.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    12/128

    Drawing

    Later sit down with your notes and graph paper and draw your site plan. First draw the

    outside edges, or boundaries, of the site. Then put in the other features you noticed, such

    as buildings, sidewalks, trees and fences. This is a site plan.

    Copying

    Make some Xerox copies of your plan so you can draw directly on it and try out a few

    different ideas. Pass copies around to get feedback on your ideas and to let others

  • 8/12/2019 Cec 103.- Workshop Technology 1

    13/128

    FIG.1.1: SITE PLAN SHOWING BOUNDARIES AND ADJACENT

    ROADS

  • 8/12/2019 Cec 103.- Workshop Technology 1

    14/128

    FIG.1.2 : SITE PLAN WITH LANDSCAPING

  • 8/12/2019 Cec 103.- Workshop Technology 1

    15/128

    WEEK TWO

    2. EXECUTION OF FOUNDATION TRENCH AND CASTING

    CONCRETE

    2.1 TRENCH EXCAVATION

    After setting out of building and fixing the profile board, the next operation will be to

    excavate the foundations of the building.

    For large scale excavation mechanical means are used for digging trenches. Trenches are

    the holes dug to receive concrete foundation of building.

    When the building is medium size, manual method is employed and the common tools

    required here will be diggers and shovels. Excavation should always start from the lowest

    side of a site to enable steps be formed incase the site is sloping. Steps enable any volume

    of earth removed from a high point of site to be greatly reduced.

    Minimum depth of trench should be about 750mm. All earth removed must be packed to

    the side. Ensure profile boards are not fully covered up.

    The level of the bottom of the trench can be easily checked using spirit level and straight

    edge. Ensure that the trench is truly level. Compact hard to ensure that no loose soil is at

    the bottom.

    Excavation takes various forms depending upon the type of foundation to be laid.

    Strip foundation requires the excavation of strip trenches. Pad or isolated foundations

    requires holes to be dug where the foundation are to come only, unless connected by

    ground beams, while raft and basements needs the excavation of the whole area of the

    building, referred to as bulk excavation.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    16/128

    Excavation in clay, soft chalk or other soils likely to be affected by exposure to the

    atmosphere should, whenever practicable, be concreted as soon as they are dug. When

    this is not possible, it is advisable to protect the bottom of the excavation with a 75mm

    layer of lean concrete blinding, or to leave the last 50 to 75mm of excavation until the

    commencement of concreting.

    2.2 TIMBERING OF TRENCH EXCAVATION

    When trenches are being excavated to a depth likely to cause the caving in of the sides,

    they must either be given some form of temporary support or the sides sloped to provide

    self support. The support given to the sides of the trench depends upon the depth of the

    trench and the soil conditions. Vibration and loads from traffic or other causes, position

    of water table, and climatic conditions and the time for which the excavation is to remain

    open also affect the decision.

    Weak soil requires more elaborate temporary supports. Most temporary support takes the

    form of timbering the sides. As timbering is only meant to support the sides of the trench

    until all foundation work is complete. Over timbering should always be avoided so that

    progress of the work is not hampered in any way

    In relatively shallow trenches in firm soil it may be possible to dispense with timbering

    or, as it is sometimes termed, planking and strutting. The most that would be required, are

    pairs of 17538mm poling boards, spaced at about 1.8m centres, and strutting with a

    single 100100mm strut. Alternatively adjustable steel strut may be used.

    Most of the timber used for timbering is soft wood, often red or yellow. The various

    members required are.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    17/128

    Poling boards. These are boards 1.00 to 1.50m in length (depending on the depth of

    excavation) and they vary in cross-section from 17538 to22550mm.The boards are

    placed vertically and abut the soil at the sides of the excavation.

    Walings.These are longitudinal members running the length of trench other excavation

    and they support poling boards. They vary in size from 17550 to 22575mm.

    Struts. These are usually square timbers, either 100100 or 150150mm in size. They

    are generally used to support the waling which, in turn, hold the poling boards in

    position. Struts are usually spaced at about 1.8m centres to allow adequate working space

    between them.

    Sheeting.This consists of horizontal boards abutting one another to provide a continuous

    barrier when excavating in loose soils. A common size for the sheeting is

    17550mm.

    FIGURE.2.1. TMBERING IN TRENCH EXCAVATION

  • 8/12/2019 Cec 103.- Workshop Technology 1

    18/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    19/128

    used to set all other pegs in the trench. Pegs are best set along the centre line of the

    trench.

    Iron pegs are best used but wooden pegs can also be used. Wooden pegs must however

    be removed after placing the concrete and before the concrete has hardened to prevent

    wood material rotting in the concrete and creating weak points.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    20/128

    WEEK THREE

    3. MIXING OF CONCRETE

    3.1 BATCHING

    Concrete can be batched by volume or weight.

    Batching by volume. This method is usually carried out using an open bottom box called

    a gauge box. A 25-kg bag of cement has a volume of approximately 0.02m3.For a 1:2:4

    mix a gauge box is filled once with cement, twice with fine aggregate and four times with

    coarse aggregate, the top of the gauge box being struck off level each time.

    If the fine aggregate is damp or wet its volume will increase by up to 25% and therefore

    the amount of fine aggregate should be increased by this amount. This increase in volume

    is called bulking.

    Batching by weight. This method involves the use of a balance which is linked to a dial

    giving an exact mass of the materials as they are placed in the scales. This is best method

    since it has a greater accuracy and the balance can be attached to the mixing machine.

    Tools required are gauge box, head pan/wheel barrow and shovel/mixer.

    3.2 MIXING

    Hand Mixing. This should be carried out on a clean hard surface. The materials should

    be thoroughly mixed in the dry state twice before the water is added. The water should be

    added slowly and mixed at least three times.

    Machine mixing. The mix should be turned over in the mixer for at least two minutes

    after adding the water. The first batch from the mixer tends to be harsh since some of the

    mix will adhere to the sides of the drum. This batch should be used for some less

    important work such as filling in weak pockets in the bottom of the excavation.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    21/128

    FIGURE: 3.1. CONCRETE MIXER FIGURE: 3.2. PLACING OF

    CONCRETE

    Ready mixed. This is used for large batches with lorry transporters up to 6m3capacity.

    It has the advantage of eliminating site storage of materials mixing plant, with the

    guarantee of concrete manufactured to quality controlled standards. Placement is

    usually direct from the lorry, therefore site- handling facilities must be co-odinated with

    deliveries.

    FIGURE: 3.3. A MODEL MOBILE CONCRETE MIXER

    3.3HANDLING

    If concrete is to be transported for some distance over rough ground, the runs should be

    kept as short as possible since vibration of this nature can cause segregation of the

    materials in the mix. For the same reason concrete should not be dropped from a height

    of more than 1m. If this is unavoidable a chute should be used.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    22/128

    FIGURE: 3.4. A WHEELBARROW

    3.4 PLACING

    If the concrete is to be placed in a foundation trench, it will be levelled from peg to peg or

    if it is to be used as an oversite bed, the external walls could act as a levelling guide. The

    levelling is carried out by tamping with a straight edge board. This tamping serves the

    dual purpose of compacting and bringing the excess water to the so that it can evaporate.Concrete must not be over-tamped as this will not only bring the water to the surface but

    also the cement past which is required to act as matrix. Concrete should be placed as soon

    as possible after mixing to ensure that the setting action has not commenced. Concrete

    which dries out too quickly will not develop its full strength; therefore new concrete

    should be protected from the drying winds and sun by being covered with canvas, straw,

    polythene sheeting or damp sawdust. This protection should be continued for at least

    three days since concrete takes about twenty-eight days to obtain its working strength.

    3.5 SPECIFYING CONCRETE

    Concrete can be specified by any of the four following methods.

    Designed mix. The mix is specified by a grade corresponding to required characteristic

    compressive strength at 28days.There are 12 grades from C7.5 to C60, the C indicates the

    compressive strength in N/mm2or MPa. Flexural (F) strength grades may also be

    specified as F3, F4 or F5 i.e. 3, 4 or 5 N/mm2. Also the requirement must specify the

    cement and aggregate content and maximum free water/ cement ratio.

    Prescribed mix. This is a recipe of constituents with their properties and quantities used

    to manufacture the concrete. The specification must be made for.

    The type of cement

  • 8/12/2019 Cec 103.- Workshop Technology 1

    23/128

    Type of aggregates and their maximum size

    Mix proportions by weight

    Degree of workability

    Prescribed are based on established data indicating conformity to strength, durability and

    other characteristics.

    Example.

    1:3:6/40mm aggregate.

    1:2:4/20mm aggregate.

    Standard mix. Mixes are produced from one of five grades, ranging from ST1 to ST5,

    with corresponding 28 days strength characteristics of 7.5 to a limit of only 25N/mm2.

    Mix compositions are specified as in prescribed mix.

    These mixes are most suited to site production, where the scale of operations is

    relatively small. Alternatively, they may be used where mix design procedures would be

    too time consuming, inappropriate uneconomical.

    Design mix. This mixes are selected relative to particular applications and site

    conditions, in place of generalizations or use of alternative design criteria that may not be

    entirely appropriate. Grading and strength characteristics are extensive and vary with

    application.

    General (GEN), grade 0-4, ranging from 7.5 to 25N/mm2characteristic strength. For

    foundations, floors and external works.

    Foundations (FND), graded 2, 3, 4A and 4B with characteristic strength of 35N/mm2.

    These are particularly appropriate for resisting the effects of sulphates in the ground.

    Paving (PAV), graded 1 or 2 in 35 or 45N/mm2strengths, respectively. A strong

    concrete for use in driveways and heavy duty pavings.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    24/128

    Reinforced (RC) and prestressed concrete grade 30, 35, 40 and 50 corresponding with

    characteristic strength and exposures ranging from mild to most severe.

    Quality control is of paramount importance in this mix. Therefore, producers are

    required to have quality assurance product conforming to BS EN ISO 9001.

    3.6 EXAMPLE:

    Prepare mixing bay by mixing and spreading weak concrete to form mixing slab on

    which the materials are mixed. Before this, the materials i.e river sand called fine

    aggregate and gravels called coarse aggregates are stored on clean surface.

    The mixing slab is then set out and the concrete mixed, placed, properly compacted and

    leveled. The materials are then carefully measured using gauge box, head pan or any

    suitable container are placed on the slab. The cement is then mixed with the material

    before adding water.

    Suitable mixes for different jobs are:-

    1: 3:6 - Mass concrete

    1:2:4 - Reinforced concrete

    Reinforced concrete is any concrete with reinforcement for additional strength.

    For manual mixing, first measure the fine aggregate and mix dry with the cement

    thoroughly according to the job. Spread the material and spread coarse aggregate all over.

    Mix about two times dry. Then add water and start mixing thoroughly, at three times.

    For mechanical mixing, first measure and poor the fine aggregate into the mixer, add the

    cement required and mix for about two minutes. Ensure thorough mixing. Add coarse

    aggregate and thoroughly mix before adding water. Finally mix and serve. Clean all tools

    and equipment at the end of work.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    25/128

    PLACING AND COMPACTING OF CONCRETE FOUNDATION

    Concrete shall be thoroughly mixed on clean hard surface or using mechanical method

    before placing.

    The tools required when placing include shovels, trowels, wooden or iron rammer or

    mechanical rammer, straight edge, wheel barrows, head-pans or mechanical dumpers.

    Concrete must be carefully transported from the mixing point to the trench to prevent

    separation of the coarse aggregate, fine aggregate from the cement which is known as

    segregation. Using two men for mixing, six labourers with head pans and either one or

    two with wheel barrows, the foundation project for a simple building can be completed

    within a short time.

    Place and spread the concrete. When it has reached or covered the required depth, the

    rammer or poky vibrator is used to compact the concrete. The straight edge can also be

    used to ensure true surface. After twenty-four hours, the member should be cured by

    wetting it with water to Ensure strength development.

    Students are required to write a report on concrete mix, handling, placing and

    compacting.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    26/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    27/128

    WEEK FOUR

    4. SETTING OUT OF A SIMPLE RESDENTIAL BUILDING BLOCK

    WALL SUPER STRUCTURE

    After laying the foundation concrete, wall construction commences according to the

    setting out plans. The common tools required for wall construction include:

    - Trowel - Tape

    - Spirit level - Straight edge

    - Line - Head pan

    - Batten - Shovels

    - Steel square- Cutting axe

    The types of blocks used for wall construction are:-

    - 225 x 225 x 450 = for erecting external walls

    - 150 x 225 x 450 = For erecting external walls and partitions

    - 100 x 225 x 450 = For erecting partition walls only

    - 102.521560 brick = For erecting external and partition walls

    - Other decorative blocks are required for fancy work only.

    The most important aspect of block-laying are:-

    - Lining = straightness of wall

    - Level = true horizontal surface

    - Plumbing = true vertical surface

    To set out the corner walls,

    - Set up lines, along the wall lines from the profile boards either from the internal

    or external part.

    - Spread mortar (mixture of cement and sand only) at the corner points.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    28/128

    - Use straight edge and spirit level to plumb down the line and mark on the mortar.

    - Place the block and check against the line using same tools.

    - After ensuring proper setting of the blocks at the corners, level them and erect two

    or three layers at each corner and partitions. Fill the joints properly.

    - Stretch line in-between the corner blocks and set the straight line blocks to fill the

    spaces. Ensure the blocks are truly straight and level. Lines can be used both at

    the top and sides of the wall during the block-laying to ensure true level and

    plumb of the block wall, The spirit level bubble must always be in the centre of

    the glass and likewise bubble must also be at the centre for true plumb line. i.e

    true vertical alignment of the blocks

    - The walls should be properly set up and erected in the trench; this is erected up

    until the building is out of the trench.

    - The blocks should be taken out of the ground at least 150mm above the ground

    level. This level represents the ground floor level.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    29/128

    FIGURE: 4.1. SETTING OUT OF BLOCK WALL SUPERSTRUTURE

    Students are required to write a report on how to set out a block wall

    superstructure.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    30/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    31/128

    WEEK FIVE

    5.PLUMBING OF PIPES FOR WASTE WATER AS DRAINAGE

    5.1 SYSTEM OF DRAINAGE

    SEPARATE SYSTEM:

    In these systems, the rainwater is kept separate from the foul water from the house. The

    rainwater is collected and either discharged into water tanks to be used later or discharged

    into water course. The system can be of great benefits In areas where rainfall is scanty.

    COMBINED SYSTEM

    This is an alternative system whereby water from roofs and paved areas together with the

    effluent of sanitary fittings are collected together and discharged into a sewer. The

    advantage of this system is that, the storms water gives an effective flushing to the drain.

    5.2 CHOICE OF PIPES

    All the pipes are suitable for use below ground, but the strength of a pipeline may

    become a limiting factor under loading conditions. In these situations ri.gid pipes with

    flexible joints should be used, and short lengths pipe in ground subject to severe

    settlement. Where pipes are laid above ground, special attention should be paid to

    structural support and protection against mechanical damage, frost and corrosion.

    Rigid pipes.Vitrified clay pipes. Manufactured to Bs65 and 540 with nominal bores of 75

    to 900mm and lengths of 300mm to 1.50m. Clay pipes are resistant to attack by wide

    range of substances, both acid and alkaline. It is very popular although the traditional

    joint made of two rings of tarred yarn and with socket and spigot filled with cement

    mortar is increasingly displaced by mechanical or flexible joints. This is liable to damage

    by settlement. Further more the short pipe lengths produce a larger number of joints.

    Concrete pipes. These are suitable for use with normal effluents but may be attack acid

    or sulphate in the effluent, or in the surrounding soil. Concrete pipes are used mainly for

    large pipes of 225mm diameter and upwards, and with these sizes external wrappings of

    glass-fibre laminate are available which reinforce the pipe and protect them from external

  • 8/12/2019 Cec 103.- Workshop Technology 1

    32/128

    attack. Concrete pipes to BS 556 are supplied either reinforced or unreinforced in lengths

    of 900mm to 5m. Prestressed concrete pipes are also available complying with BS 5178.

    Asbestos cement pipes.These are made to BS 3656. They are used for drainage

    purposes and have the same shortcoming as concrete pipes.

    Cast iron pipes.These can be supplied with spigot and socket joints to BS 437 for

    caulking with lead or a proprietary material, or as pressure pipes with flexible joints to

    BS1211, which are more much more satisfactory for use in difficult or waterlogged

    conditions or ground subject to large movement. The coating on these pipes gives good

    protection against corrosion and a reasonable life with average ground conditions and

    normal effluents. They can be laid at any depth on account of their great strength. Cast

    iron pipes are made in varying lengths, but the most commonly used length is around

    3.6m. Ductile iron pipes are covered by BS 4772.

    Flexible pipes. Pitch-impregnated fibre pipes. Made to BS 2760, they are becoming

    increasingly popular due to their suitability for use with normal domestic and most trade

    wastes.

    They are manufactured in nominal bores of 50 to 225mm and standard lengths are 1.7,

    2.5 and 3m. They are more economical than clay pipes where long lengths are involved

    and in bad ground conditions.

    Unplasticised PVC pipes. Manufactured to BS 4660, they are 110 and 160mm nominal

    sizes and are golden brown in colour. They are suitable for domestic installations and

    surface drainage. UPVC pipes are available in 1, 3, and 6m lengths. They should not be

    use for effluent at high temperatures and they become brittle at low temperatures and

    therefore handling with care. They are light in weight.

    Reinforced plastic pipes. These are made of thermosetting resin and have advantages of

    light weight and resistance to corrosion and effluents with high temperature.

    5.3 SETTING OUT OF DRAINAGE SYSTEM

  • 8/12/2019 Cec 103.- Workshop Technology 1

    33/128

    The setting out of the trench is much simpler than setting out for building foundation,

    because the drain line follows a straight course as much as possible. Sight rails pegs and

    travelers are needed for the setting out operation. Travelers are T-shaped wooden tools

    used in a similar way to boning rods.

    The centre line of the drain pipe is marked out by wooden pegs driven into the ground

    starting from the building outlet. A rail, which is a horizontal piece nailed to two vertical

    member, is erected across the trench at the position of the first manhole or inspection

    chamber near the building. The height of the rail is fixed at a suitable known level above

    the invert level of the pipe. The positions of inspection chambers are then marked out

    along the line by driving four pegs into the ground.

    Excavation can commence after the setting out. Shallow trenches in firm soils up to 1.3m

    deep do not need supports. The trench is excavated to constant fall from the building. To

    ensure that this is done, a series of traveler are placed at the bottom of trench and the top

    sighted to the sight rail. The length of the vertical piece of the traveler is the same as the

    height of the sight rail measured from the invert level of the pipe.

    The rails are erected at the inspection chamber positions or at changes of direction. This

    gives an acceptable gradient. The sighting of the travelers is done from the lower rail

    through to the upper one. The pipes are kept in a straight line by means of a line stretched

    from one inspection chamber to the next.

    5.4 LAYING OF PIPES

    Rigid pipes must have an even bed laid to the required slope, this bed is usually 150mm

    thick concrete. The bed is to prevent the pipes fracturing when the trench is backfilledand compacted.

    In less important jobs, a concrete bed may not be necessary, especially if the ground is

    firm and stable. A well consolidated earth bed is all that is required, but the back filling

    and compacting should be done with a lot of care.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    34/128

    A concrete bed is not required by the regulations for cast iron pipes and where its

    provided, a 100mm thick is sufficient.

    5.5 JOINTING OF PIPES

    The jointing of pipes made with sockets and spigots is achieved by inserting the spigots

    into the socket caulking with tarred hemp or yarn and then making the joint with 1:1

    cement and sand mortar.

    Where this type of joint is used, the drain must not be tested until the cement has gained

    sufficient strength. This period should be at least twelve hours after jointing. The purpose

    of caulking the joint with yarn is to centre the spigot in the socket and to prevent mortar

    falling into the bore of the pipe during the process of jointing.

    Cast iron pipes are jointed by inserting a ring of yarn or lead wool into the jointing space

    and then running in molten lead and caulking. A flexible joint can be obtained by using a

    rubber ring.

    PVC jointing methods use pre-formed socket or loose couplings, and this is made by a

    rubber ring or using a solvent and adhesive. Pitch fibres pipes are jointed by means of

    external couplings in polypropylene. Asbestos cement pipes also have tapered ends which

    are joined using coupling and rubber rings.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    35/128

    FIGURE: 5.1. COUPLINGS AND VENTS

    5.6 DRAINAGE TEST

    Drains can be tested in three ways. These include:

    Hydraulic Test

    This is the most reliable method of testing drains. The test is performed by blocking

    the lower end of the section of drain to be tested by inserting an expanding plug or

    air flatted bag and then filling the portion of the system with water up to the level of

    the gullies which should also be plugged or stopped with one of the devices made

    specially for this purpose. The filling of water is carried out by attaching one end of a

    length of rubber tubing to the nipple of the drain stopper or plug at the upper end and

    connecting the other end to a container holding water at the required head. 600mm

    head of water should be removed when applying this test.

    A leakage is indicated by a drop in the leveled water in the container, and the drain

    pipes are covered. The points of leakage are easily noticeable.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    36/128

    Fifteen minutes should elapse before the water level is observed to allow for any

    absorption that might take place.

    Smoke Test

    This test is performed by forcing air- laden smoke into the section of the system

    under test from a special smoke box, the smoke is produced by burning oily waste in

    the smoke box. The smoke is forced through the lower end of the drain and vent

    pipes. Soil pipes as well as traps should be left unsealed until the smoke emerged

    from them, this ensured that the drain under examination is full of air laden smoke.

    A few strokes of the bellows of the smoke machines will set up a slight pressure in

    the system and the dome over-the smoke box should rise and remain in the position

    if there are no leakages

    The advantage in this system is that any smoke escaping through a leakage is easily

    visible.

    Air test

    This test is particularly suitable for soil pipes. Plug all soil and vent pipes and

    gullies. The air is then pumped into the drain through a T-piece air pipe and one arm

    is attached to one of the stoppers as in water test. The other arm is connected to u-

    gauge containing water. The rubber tubing may be made to pass under a water seal

    instead of connecting to a stopper.

    When the pressure is applied, the water in one arm of the gauge will be depressed

    and the other elevated. The difference in level of the water will register the head

    pressure and if the water in the gauge remains still, the drain is satisfactory. A fall

    indicates leakage. The disadvantage of the air test is that the point of leakage is not

    easily detected as in the two previous tests

  • 8/12/2019 Cec 103.- Workshop Technology 1

    37/128

    FIGURE: 5.2. DRAINAGE SYSTEM

  • 8/12/2019 Cec 103.- Workshop Technology 1

    38/128

    WEEK SIX

    6. LAYING OF BLOCKS/BRICKS IN DIFFERENT BONDS

    To build or construct a wall of brick or blocks, it usually follows the pattern of laying

    the bricks or blocks In some regulation arrangement. The brick /blocks courses or rows in

    a wall are arranged to ensure that each brick/block overlaps or bear upon two or more

    bricks / immediately below it. The process of laying the bricks across each other and

    binding them together is called bonding. The amount of overlap and the part of the brick

    used determine the pattern or bond of brick work.

    6.1 PURPOSE OF BONDING

    The main purpose of bonding is to provide maximum strength, lateral stability and

    resistance to side thrust, and it distributes vertical and horizontal load over a large area of

    the wall. A secondary purpose of bonding is to provide appearance (decoration).

    6.2 CHOICE OF BRICK BOND

    The choice of any brick bond defends on the following factors.

    1. Prevailing environmental or site conditions.

    2. Thickness of the wall.

    3. The purpose for the wall construction i.e either strength or decoration

    6.3 CHOICE OF MORTAR.1. Cement and sand mortar (1:4). This is use for load bearing wall and water works

    2. Lime, cement and sand mortar (1:1:4, 1:1:6). This use for building construction

    work.

    6.4 PRINCIPLES OF BONDING OF BRICKWORK

    1. The correct lap should be set out and maintained by introduction of:

    (a)A closer next to the quoin header.

    (b)A three-quarter bat starting the stretcher course.

    2. There should be no straight joints in a wall.

    3. The perpends or cross-joints in alter courses should be kept vertical.

    4. Closer should never be built in the face of the wall except next to the quoin

    header.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    39/128

    5. The tie bricks at junctions or quoins should be well-bonded to secure the walls

    together.

    6. The bricks which are laid in the interior of thick walls should be laid header wise

    as far as possible.

    7. Sectional bond should be maintained across the wall, that is, the bond on the back

    should be in line with the bond on the face side of the wall.

    8. To achieve the maximum strength in a wall, all the joints in the interior of the

    wall should be kept filled or flushed in with mortar in every course. This can be

    done by mixing a quantity of mortar to a grout or slurry and running it into the

    joints between the bricks which have been laid in the wall.

    6.5TYPES OF BOND

    STRETCHER BOND: This consists of all bricks laid as stretchers on every

    course with the courses laid half-bond to each other; this is affected in a plain wall

    with stopped ends by introducing a half-bat as the starting brick to alternate

    courses. Usually only used in walls of a half-brick in thickness.

    FIGURE: 6.I. STRETCHER BOND

    ENGLISH BOND:This consists of alternate courses of headers and stretchers

    with a closer placed next to the quoin header to form the lap. There is, however, a

    variation where a closer is not used in the header course, and the lap is formedby

  • 8/12/2019 Cec 103.- Workshop Technology 1

    40/128

    starting each stretcher course with a three-quarter bat. Such variation is not very

    common. It is considered one of the strongest bonds. It is suitable for the

    construction of load-baring walls and for places where strength is of utmost

    importance.

    FLEMISH BOND: This consists of alternate headers and stretchers, with the

    headers in one course being placed centrally over the stretcher in the course

    below. A closer is placed next to the quoin header to form the lap. Flemish bond

    is said to give a more attractive face appearance than English bond as it appears

    less monotonous. It affords a saving in facing bricks because of the header.

    English bond requires approximately eighty-nine facing bricks per square metre,

    while Flemish bond requires only seventy eight facings. The header face of

    many bricks is dark, and they are separated in this bond as against the English

    where they are continuous.

    FIGURE: 6.2. ENGLISH BOND

  • 8/12/2019 Cec 103.- Workshop Technology 1

    41/128

    FIGURE: 6.3. FLEMISH BOND

    HEADER BOND:In this bond the arrangement shows the header face of every brick,

    with 215 mm thickness. The bond is formed by three-quarter bats at the quoin. It is rarely

    in use, because it has now attractive finish (too many joints). It is used in footing courses

    or walling curved on plan.

    FIGURE: 6.4. HEADER BOND

    Garden Wall Bond: This is designed to reduce the number of header faces to facilitate

    a fair finish both sides in walls where appearance is important. There is one course of

    header bricks to every three courses of stretchers in English garden wall bond, and one

    header to every three stretchers in each course of Flemish garden wall bond.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    42/128

    FIGURE: 6.5. BRICK BONDS

    6.6 SETTING OUT BONDS

    In some cases it may be difficult to apply the standard patterns to the quoin, junction

    walls and stopped ends. The reason is that consistency of bonding is impossible to

    maintain. For example when setting out English and Dutch bonds for walls of 1 and 2

    bricks in thickness, the pattern is the same on both faces, whereas on one 1 1/2 and 21/2

    brick walls the pattern is different. That is headers on one face and stretchers on the other.

    Any rules concerning bonding can be applied as far as practicable. A general rule for

    quoins, stopped ends and junction walls in English and Dutch bonds is that where a wall

    changes direction, so the bond will also change, that is if there are stretchers on one face

    then the adjoining face will be headers. This is however , cannot be applied in every case,

    as in a 11/2

    -brick junction wall adjoining a 2-brick such as 1 and 2 bricks in thickness. There must

    be two adjoining faces having similar bonds.

    One rule, however, should always be applied. When setting out quoins or junction walls,

    care should be taking to ensure correct trying in the walls at the internal angles to achieve

    the maximum resistance against cracking due to shrinkage or uneven settlement.

    Quoins

  • 8/12/2019 Cec 103.- Workshop Technology 1

    43/128

    The bonding arrangements to quoin vary according to the bonds which are used and the

    sizes of the walls comprising the corners.

    FIGURE: 6.5. A BRICK WALL

  • 8/12/2019 Cec 103.- Workshop Technology 1

    44/128

    WEEK SEVEN

    7. IDENTIFICATION OF CONSTRUCTION WOOD TYPES AND

    THEIR SIZES

    7.1 CONSTRUCTION WOOD TYPES:

    Timber is divided into two classes: The coniferous trees, known as softwoods, and the

    deciduous trees, known as hardwoods. A tree consists of three main parts: the stem, and

    the crown. The root fixes the tree in the ground and takes in moisture form the soil. The

    stem or trunk stores food-stuffs, conducts these to the leaves and provides strength and

    rigidly to the tree. Te timber which man has used since the earliest ages is, of curse, cut

    form the trunk. The crown consists of branches, twigs and leaves in which the chemical

    process essential t growth takes place.

    Softwoods: These are usually evergreen with needle-pointed leaves and are cone-bearing.

    Hardness trees have board leaves, which in most cases are shed at the end of the growing

    seasons. There are certain exceptions, one example being the holly tree which is

    evergreen throughout the year.

    A tree consists of three main parts: the stem, and the crown. The root fixes the tree in the

    ground and takes in moisture form the soil. The stem or trunk stores food-stuffs, conducts

    these to the leaves and provides strength and rigidly to the tree. Te timber which man has

    used since the earliest ages is, of curse, cut form the trunk. The crown consists of

    branches, twigs and leaves in which the chemical process essential t growth takes place.

    Hardwoods: These bear fruit in which the seeds are to be found, the chestnut of the

    horse-chestnut, the acorn of the oak, and the berries of the holly tree are examples.

    The terms softwood and hardwood are by no means accurate in every case; they are

    however, generally descriptive and established terms in the trade. Some hardwoods are as

  • 8/12/2019 Cec 103.- Workshop Technology 1

    45/128

    soft as, or even softer than, the nominally softwood, whilst some softwoods are harder

    than many hardwoods.

    Most of the timber used by the carpenters and joiners in the construction of building is

    softwood. This is mainly of the pine and fir class, and through they are to be found in

    many parts of the world, the chief sources of pine are the forest of Canada, North

    America, Scandinavia, and Russia. The forest belts providing the hardwoods are to be

    found in the tropical zones, namely: central and south America, West Africa, regions of

    India, Burma, and Malaya and Eastern Australia.

    Advantage of Wood

    Wood has the following advantage:

    i. Very high strength compared to its weight

    ii. Easily worked and shaped

    iii. Easily erected, dismantled, and modified to suit changing conditions

    iv. Warmth to the touch and richness and variety in natural colour an texture

    v. Wide variety of species to suit differing requirements

    vi. Good thermal insulation

    vii. High fire endurance-does not suddenly lose its strength, distort, or expand and

    thus increases the time for escape, salvage, and fire-fighting.

    The timber expert has to know many more than those given, and he h as to be able to

    identify the family, group, species, and variety. General appearance, texture, colour,

    smell, weight, etc, are useful I distinguishing different kinds of timber, but identification

    is more reliable if it is based on the structural features of the timber. For this purpose a

    hand magnifying glass or microscope is necessary to examine samples of the timber,

    specially cut with a sharp knife as shown in or by a machine called a microtome.

    Structure

    Softwood timber is composed of many tubular cells cemented together called tracheids,

    these have wall of wood substance and the rising sap passed from one tracheid to anther

  • 8/12/2019 Cec 103.- Workshop Technology 1

    46/128

    thought the softer texture within the cell walls, known as pits, A parts from transporting

    the moisture drawn up from the roots, the trachelds in the structure of softwoods give

    strength to the tree.

    A further series of cells, termed parenchyma rays, pass from the outside of the tree

    towards the pith and are formed of a pity substance. These cells, which are shorter than

    the tracheids store reserves of food which can be passed to any part of the tree which

    requires them. The rays are often used as a means of identifying timbers. Resin canals

    sometimes occur in softwoods. These are placed in a horizontal ad vertical direction.

    The structure of hardwoods is more complicated than that of softwoods. The main feature

    of the structure is the presence of large cells or vessels which pass the moisture up the

    tree from the roots to the leaves. Along with the large vessels are rays parenchyma cells

    and fibres. The latter serve to give strength to the tree.

    There are two types of hardwoods: Ring-porous, and diffuse-porous, In ring-porous

    timbers large cells are produced during the early part of the growth ring and these

    become smaller in size as the season progresses. In diffuse-porous timbers the cells are

    generally the same size within the growth ring.

    Annual or growth rings

    These are formed by the early spring-wood and are arranged in roughly concentric

    formation round the pith, as each growing season an additional sheath of tissue is

    produced around the tree, increasing the diameter and pushing the bark outwards. In

    softwoods which have been grown slowly, the timber will have more growth rings than

    one which as been grown quickly, resulting in much stronger timber, the age of a tree can

    be determined by counting these rings of annual growth.

    There are many more large cells and fewer fibres in a slow-grown ring-porous hardwood.This means that a weaker timber is produced than is the case with hardwood which is

    fast-grown.

    Medullary raysThese exist in all woods. They are seen as lines or the transverse section,

    radiating form the pith to the bark and running with the grain of the tree. Generally, these

  • 8/12/2019 Cec 103.- Workshop Technology 1

    47/128

    rays are not easy to see without the use of a lens or microscope, except in certain

    hardwoods, particularly oak. It is these rays which give many hardwoods their rich

    decorative figuring.

    Sapwood and heartwood

    New wood formed on the outside, next to the bark, is called sapwood. Every part of

    wood in any tree has, therefore, been sapwood at some time. As this contains all the

    food-stuffs, it is liable to

    attack from fungi or insect for this reason. Sapwood, properly treated, can be made

    immune from such attack, and should not be discarded on this account

    .

    Heartwood, is the growth of earlier years and is the inner portion of the tree trunk. It is

    darker in colour and the more mature wood. It serves mainly to give strength to the tree

    trunk.

    FIGURE: 7.1. INTRENAL STRUCTURE OF WOOD

  • 8/12/2019 Cec 103.- Workshop Technology 1

    48/128

    Pitch

    This is centre of the tree and represents the fist growth Bark

    This outer covering of corky tissue serves to protect tree against external injury and

    extremes of temperature. The outside of the bark is termed the cortex and that betweenthe cambium layer and the cortex, the bast.

    It is not proposed to consider the chemical component of tree in detail here. It may be

    sufficient to indicate that cellulose is the chef structural component contained in the cell

    walls, while resins, colouring matter, alkaloids, tannins, etc. are other substance to be

    found.

    Grain

    This term is very loosely when applied to timber and should not be confused with its

    texture. Grain refers to the direction of the fibres and other woody elements, while texture

    refers to the arrangement, fineness or coarseness, and distribution of these elements.

    Thus, fine textured timber has element which are small and close together. When they are

    larger an spaced wider apart the term coarse in applied.

    Straight grain refers in timber where the fibres are parallel with the surface; such timber

    is relatively strong and easy to work. Cross grain is a deviation of the fibres of ht timberfrom a line parallel to the edges of the wood. Diagonal-grained timber is a result of

    improper conversion so that fibres are inclining to the edges of the timber; this reduces

    strength and is sometimes referred to as oblique grain. Spiral-grained timber has fibres

    which take a more or less spiral course in a particular direction. Interlocking grains as

    fibres partly-spiraling which are in-clined in opposite directions and are often known as

    wild grain. Curly grain and wavy grain indicates wave-like stripes on the surface of the

    timber due to the fibres changing direction, and is valued because of it highly decorative

    appearance. Short grain indicates that the timber may fracture due to fibres lying in a

    certain direction. End grain refers to the section of a cross-cut surface, showing the

    arrangement of the exposed fibres.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    49/128

    Figure is the pattern on the surface of the timber and is due entirely to the structure of the

    wood. Straight-grained timber has only a plain figure whereas wavy or interlocked-

    grained timber produces a finely marked and attractive figure.

    The method of conversion affects the nature of the figure. Quarter sawing in the case of

    oak used for such purpose as paneling and furniture, where appearance is most important,

    discloses on the surface the medullary rays which gives the silver grain or rich figure.

    A compete list of commercially used timbers is outsider the scope this book, but the

    following short descriptions are of varieties in extensive use. The standard name of the

    timber is given first, followed by alternatives.

    FIGURE: 7.2. SAWN WOOD

    Softwoods

    Douglas fir (British Columbian pine, Oregon pine) average weight 528.66kg/m3.

    available I logon lengths and large sections; straight-grained and resilient: easy to work

    by hand or machine. Reddish brown to pinkish brown in colour. Being one of the hardest

    softwood it can take heavy, continuous wear. The strongest, for its weight, of any

    softwood in the world, with a high resistance to acids and decay, has good gluing an high

  • 8/12/2019 Cec 103.- Workshop Technology 1

    50/128

    insulation qualities. Used of first-class joinery. Large quantities of plywood are made

    from Douglas fir.

    Hemlock, western

    (pacific hemlock, British Columbian hemlock) average weight 480-60kg. It ranks high in

    strength and durability and has a fine uniform texture. Straight-grained, stiff yet easily

    worked, and light brown in colour. Easy to work by hand or machine and good for

    gluing. Its smooth clear surface takes stain, paint, and varnish without difficulty used for

    interior journey work, built-in furniture, agricultural and timber buildings.

    Larch, Europeanaverage weight 592.74kg/m3. one of the most valuable and most used

    home grown timber reddish brown in colour, very strong and durable; resinous; straight-

    grained. The larch grown to a height of 30-48m or more, with a girth of 4-570m in some

    trees. Used for all kinds of carpentry work, fencing gates, posts, garden furniture,

    flooring, and railway sleepers.

    Parana pine average weight 544-68kg/3. This South America softwood had an even

    texture and is straight-grained. It is unsuitable for exterior work, being brittle and mot

    durable. The colour is from light to darkish brown with some reddishness. Suitable for all

    classes of interior joinery but is inclined to split on nailing. Takes screw, glue, and paint

    well.

    Hardwoods

    Afrormosia (kokrodua) average weight 688-86kg/m3 . This wood resembles teak in

    appearance, but has a finer grain. It is very durable and well. it is suitable for high-class

    joinery, ship and carriage work. Care should be taken when use on outside work in direct

    contact with ironwork to avoid staining.

    Agba (Nigeria cedor, pink mahogany) average weight 480-60kg/m3. this West African

    timber grow up to 60-960m in height.

    American whitewood (canary whitewood, yellow poplar) average weight 528-66kg/m3.

    Essentially a wood for interior work to be painted. It takes glue, nails an screws well and

    is easy to work. Ther tree grow to a height of 45.700-60.960m and up to 3.048m in

  • 8/12/2019 Cec 103.- Workshop Technology 1

    51/128

    diameter. The colour varies according to the age of the wood, between quite yellow and

    grey, it is not particularly strong and will deteriorate quickly in damp situations.

    Botanically whitewood is a hardwood, but in workability it is to all intents and purpose a

    softwood.

    Beech, European average weight 720-kg/m3. This is one of the most used hardwood in

    this country, large quantities being imported form central and southern Europe. The

    timber is hard, close-grained and durable, with a fine texture. It is used extensively for

    furniture. Particularly chair-making wooden planes, handles of the woodworker saw other

    tools, block and parquets flooring. It shows silver grain and is used for veneers on this

    account. Colour reddish yellow or light brown.

    Birch average weighty 672-90kg/m3. From Europe generally, also Canada and other

    regions of North America. European birch is used principally of plywood. Large

    quantities form Finland and Sweden are imported into this country. Colour white to light

    brown. Straight-grained and medium texture. Similar to beech in many ways but is more

    inclined to warp.

    Black bean average weight 720-90kg/m3. chocolate brown with greyish brown streaks

    giving an attractive rich appearance to the wood. Similar to French walnut in colour, hard

    to work. For new south Wales and queensland, the timber is excellent for veneers high-

    class joinery, paneling and furniture.

    7.2 COMMON SIZES OF TIMBER

    253003600

    503003600

    50503600

    50753600

    501503600

    1001003600

  • 8/12/2019 Cec 103.- Workshop Technology 1

    52/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    53/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    54/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    55/128

    10. Drilling machine (Table and pillar).

    11. Sanding machine.

    12. Spraying machines.

    13. Grinding machine.

    14. Router machine.

    15. The lathe machine

    16. Blower.

    17. Bracing machine

    18. Presser.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    56/128

    It is very difficult is get a perfect layout for the machines and benches in a workshop

    because of the varying nature of the work they are used for. It is a good plan, however, to

    arrange the machine in the following groups: first, the cutting-off machines (cross-cut

    and rip saws), next the planning machines (surface planers, thickeners, and four sides),

    then the jointing and finishing machines (mortising, tenoning, and moulding machines,

    belt, drum and disc sanders). The joiners shop should be near the finishing machines so

    that there is no unnecessary waste of time when work is carried operations.

    Small workshop layout

    Two typical layouts for a small workshop employing about eight men are given. The first

    example show the machines shop equipped with one general woodworking machine, one

    mortise machine, and one band saw. The joiners shop contains three double benches,

    with assembly and storage space provided at the end of each bench. The foreman the

    bench nearest to the office.

    It the second example the machine shop contains six machines a cross-cut saw, a rip saw,

    a planer and thicknesser, a mortise machine, a spindle moulder, and a band saw. The

    joiners shop has two double benches and a single setting-out bench which is placed near

    the office. The single bench would again probably be occupied by the foremen.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    57/128

    FIGURE: 9.1: STARNDARD CAPENTRY AND JOINERY WORKSHOP

  • 8/12/2019 Cec 103.- Workshop Technology 1

    58/128

    FIGURE: 9.2: STARNDARD CAPENTRY AND JOINERY WORKSHOP

  • 8/12/2019 Cec 103.- Workshop Technology 1

    59/128

    9.2 EXAMPLE: 1

    An example is the layout of medium-sized joinery workshop employing about thirty-six

    men and housing sixteen woodworking machines and eight double benches.

    FIGURE: 9.3: STANDARD CAPENTRY AND JOINERY WORKSHOP

  • 8/12/2019 Cec 103.- Workshop Technology 1

    60/128

    FIGURE: 9.4: STANDARD CAPENTRY AND JOINERY WORKSHOP

  • 8/12/2019 Cec 103.- Workshop Technology 1

    61/128

    WEEK TEN

    10. PREPARATION FOR JOINTS IN WOOD WORK

    There are many different joints that the carpenter and joiner may use. Joints generally fall

    into three categories and carry out the following functions:

    CATEGORY JOINT FUNCTION

    Lengthening End To increase the effective length

    of timber

    Widening Edge To increase the width of wood

    or

    Manufactured boards

    Framing Angle To terminate or to change

    direction

    10.1 TYPES OF JOINTS

    An example of timber Joints are; Halved joints, bridle joints, mortice and tenon,

    dowelled and wedged mortice and tenon joints.

    Halved Joints: In this type of joint one piece crosses over the other.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    62/128

    FIGURE: 10.1.HALVED JOINT

    FIGURE: 10.2.HALVED JOINTS

  • 8/12/2019 Cec 103.- Workshop Technology 1

    63/128

    BRIDLE:

    These two bridle joints are used when a light frame is needed. for example, a

    picture frame. One part of the joint fits into the other part and is glued

    permanently in position.

    FIGURE: 10.3. BRIDLE JOINT

    MORTICE AND TENON JOINTS:

    Below are two examples of mortice and tenon joints: These are used when making tables

    or cabinets and they are very strong when glued together. There are many different types

    and a larger feature on this type of joint appears below.

    FIGURE:10.4. MORTICE AND TENON JOINT

  • 8/12/2019 Cec 103.- Workshop Technology 1

    64/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    65/128

    when it is under great pressure. This is used as a joint on chairs and other pieces of

    furniture so that the joints do not break apart when extra weight is applied.

    This is another way in which dowels can be used to form a joint. Modern pieces of

    furniture are often jointed in this way. It is a permanent method but it is not the strongest

    joint as the parts can eventually pull apart, especially as the joint becomes old. Modern

    glues that are very strong have meant that this joint is often used to quickly fix parts

    together.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    66/128

    FIGURE: 14.6. THE SECRET HAUNCH MORTICE AND TENON

    THE SECRET HAUNCH MORTICE AND TENON:

    If the mortice and tenon joint is to used as part of a frame, a secret or sloping haunch is

    used. The tenon does not show on the outer side of the joint and it gives greater gluing

    area, adding to the overall strength of the joint.

    FIGURE: 14.7. WEDGED MORTICE AND TENON

    WEDGED MORTICE AND TENON:

  • 8/12/2019 Cec 103.- Workshop Technology 1

    67/128

    This is a very strong and attractive joint. The tenon has two slots and when it is pushed

    into the mortice wedges are tapped into position. The wedges hold the joint together

    firmly and they also give the joint an interesting look.

    10.2 EXAMPLE: 1

    MAKING A MORTICE AND TENON JOINT - THE MORTICE

    The construction of a plain mortice and tenon joint is shown. This type of joint has a wide

    range of uses and is particularly useful when manufacturing furniture. Several types of

    mortice and tenon joint exist. The marking out and cutting of all the mortice and tenon

  • 8/12/2019 Cec 103.- Workshop Technology 1

    68/128

    joints are based in this simple joint. Below is a stage by stage account of the marking and

    cutting of the mortice part of the joint.

    The mortice gauge is a special type of marking gauge and it is used to mark wood so that

    a mortice can be cut into it. The diagram to the above represents a typical mortice and

    tenon joint. The mortice is marked out using the mortice gauge although it must be set to

    the correct size of mortice chisel very carefully. A mortice chisel is then used to remove

    the waste wood.

    The mortice gauge is normally made from a hardwood such as rose wood with brass

    being used for the parts that slide along the stem.

    Animated Mortice Gauge

    MARKING OUT A MORTICE

    STEP ONE: 1

    The distance between the fixed spur and the adjustable spur is set

    so that it matches the width of the mortice chisel. The width of the

    mortice chisel should match the width of the mortice to be cut in thewood.

    STEP TWO:

  • 8/12/2019 Cec 103.- Workshop Technology 1

    69/128

    A try square and a marking knife are used mark the lines at the top and bottom of the

    mortice.

    STEP THREE:

    The stock of the mortice gauge is pressed against the side of the

    wood. It is then pushed along the wood until the mortice is

    marked out correctly.

    STEP FOUR:

    The mortice chisel is then used to

    break the surface of the waste wood

    by gently tapping the handle with a

    mallet.

    STEP FIVE:

    The waste wood is then slowly removed,

    this time, by applying more force to the

    handle of the chisel with the mallet. The

    waste is removed until the entire mortice

    hole has been cut.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    70/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    71/128

    Remove waste wood with a chisel

    Level the bottom of the trench with router.

    Test for fitness by putting the pieces together and removed.

    Prepare final fixing and dress up using slicing or smoothing tools.

    Students are required to write a report on joints in woodwork.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    72/128

    WEEK ELEVEN

    11. MAKING USE OF METAL DOGS/FASTENING AND GUSSET

    PLATE

    11.1 GUSSET PLATE

    FIGURE: 11.1. 25MM GUSSET PLATE

    FIGURE: 11.2. TIMBER GIRDER TRUSSWITH GUSSET PLATE

    FIGURE: 11.3. GUSSET PLATE IN TRUSS ROOF

  • 8/12/2019 Cec 103.- Workshop Technology 1

    73/128

    FIGURE: 11.4. TIMBER KING POST TRUSSES WITH GUSSET

  • 8/12/2019 Cec 103.- Workshop Technology 1

    74/128

    FIGURE: 11.5. GUSSET

    PLATE

    FIGURE: 11.6. GUSSET PLATE

  • 8/12/2019 Cec 103.- Workshop Technology 1

    75/128

    FIGURE: 11.7. GUSSET ASSEMBLY FOR TRUSSES

  • 8/12/2019 Cec 103.- Workshop Technology 1

    76/128

  • 8/12/2019 Cec 103.- Workshop Technology 1

    77/128

    WEEK TWELVE

    12. CONSTRUCTION OF WOODEN FLOOR

    12.1 TYPES OF WOODEN FLOOR

    SINGLE FLOOR: When bridging joists are used to support floor board and the joist in

    one continuous length that span from wall to wall is known as single floors. These types

    of floors are generally use in domestic buildings and offices of supervisors in

    manufacturing companies. The maximum economic span should be about 4.5m long.

    Two members are used in constructing the floor:

    I. Joist 150mm by 50mm thick or 75mm thick

    ii. Floor board 25mm thick

    DOUBLE FLOORS: Double floors are rarely used in modern building practice.

    The maximum clear span for softwood bridging joists can be considered as 4.8m, and

    when the smallest plan dimension of a room exceeds this length it is necessary to

    construct a double floor. Here relatively large members, called binders, are introduced to

    given intermediate support to the joists.

    Frame floors. When the shortest span of the room exceeds 7.2m it is necessary to

    constructs a framed floor. This consists of bridging joists, binders, and girders. It is now

    common practice to use rolled-steel joist sections for both girders, but in older buildings

    the main supporting units were of solid timber or flitched timber members. The bridging

    joists are placed the short way of the room that is, parallel to the main girders. The

    binders which give support to the bridging joist are themselves supported by the main

    girders.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    78/128

    12.2 METHOD OF CONSTRUCTION:

    The floor is divided into three bays by two 375x175mm solid timber binders. These

    support 150x50 mm bridging joists spaced at 375mm centres. The binders may be solid

    timber beams, flitched beams, or rolled=steel joists put in position at 2.4 to 3.6m centres

    across the shortest way of the room. They are supported at each end on 225 x 162x600

    mm stone pads, with an allowance for a free passage of air round the ends of each binder.

    Where the ceiling below needs an unbroken surface, ceiling joists are also needed. For

    the outer bays, these joists may be supported at one end by fillets nailed firmly to the

    sides of the binders, and at the other end by fillets securely fixed to the wall. The joists

    for the middle bay are supported on fillets nailed to the binders.

    The method of supporting the bridging joists and the ceiling joists are also shown. The

    method of supporting the binder, the free passage of air round the beam, and a section

    view of the stone pad are also shown here.

    At the top are the plan and section of a floor 5.4m wide and 9m long, set out in three 3m

    bays.

    The details show a section through the floor with the bridging joist notched up to and

    over the steel binders, and supported by steel angles. Also shown is a second method

    where wood bearers are fixed to the steel binder by bolts, to receive the ends of the joist

    which are notched up to the binder.

    The bridging joists are lathed and plastered.

    Cradling for the steel binder consists of firings which are halved at the joints to form

    frames, fixed to the side of each bridging joists, and arranged around the binder to receive

    the lath and plaster.

    A side view of the steel binder and the cradling are also illustrated.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    79/128

    FIGURE: 12.I: DOUBLE FLOOR FIGURE: 12.2: FRAMED FLOOR

  • 8/12/2019 Cec 103.- Workshop Technology 1

    80/128

    The plan and sectional view of a traditional framed floor is given. This example has

    150x75 mm bridging joists, 275x 150mm binders, The sectional views of the flitched

    girder and the bridging joists. Also shown is a sectional view of the binder and the

    method of supporting the flitched girder.

    The framed floor illustrated has a 375 x 125 mm steel girder, 275 x 150 mm solid wood

    binders, 150 x 75mm bridging joists, and 100 x 50 mm ceiling joist.

    The details show the method of supporting the binders and the fixing of the casing.

    Control BCG006

    Guidance Note Issued 01/01/2001 Rev B Page 1 of 2

    The following table gives details of allowable spans and spacing between joists for the

    most commontimber sizes used in floor construction. All the figures are based on normal

    floor loadings in dwellings

    where the floor construction is typically 18-25mm floor boards/sheets with up to 12.5mm

    thick plasterboardand skim underneath. For any other situation these tables may not be

    appropriate and you should refer to theApproved Document to Part A of the Building

    Regulations or ask your Building Control Officer for advice.

    When choosing a joist spacing you should also check that your floorboards (or sheets) are

    themselves strong enough to span over the width chosen.

    12.3 FLOOR JOISTS SUITABLE FOR DOMESTIC FLOOR LOADINGS

    Size of joists Maximum clear span in metres for joist spacing of in mm400mm

    450mm 600mm

    97 x 50 1.98 1.87 1.54

    122 x 50 2.60 2.50 2.19

    147 x 50 3.13 3.01 2.69

    170 x 50 3.61 3.47 3.08

    195 x 50 4.13 3.97 3.50

    220 x 50 4.64 4.47 3.91

    147 x 75 3.56 3.43 3.13

    170 x 75 4.15 3.96 3.61

  • 8/12/2019 Cec 103.- Workshop Technology 1

    81/128

    195 x 75 4.68 4.52 4.13

    220 x 75 5.11 4.97 4.64

    Timber sizes and construction details

    Building Control BCG006

    Guidance Note Issued 01/01/2001 Revision B Page 2 of 2

    When constructing timber floors, you should also bear in mind the following

    points:-

    1/ Floors are used to give lateral restraint to walls, and where the joists run parallel to the

    wall, straps need to be installed as shown in the details below. Normally these straps need

    to be positioned every 2m along the wall, but up to 3m is acceptable where this is to

    allow the formation of a stairwell or similar opening in the floor. The galvanized mild

    steel straps must have a minimum cross sectional area of 30 x 5mm

    2/ Around stairwells and similar openings it is often necessary to use trimmer beams to

    support the ends of joists. These details are dealt with separately on guidance note

    number 009.

    3/ Where joists support a partition wall or under baths they usually need to be 'doubled

    up' to

    support the increased localised loading.

    4/ On joist spans over 2.5m, strutting is required to prevent joists twisting when loaded.

    For spans of between 2.5 and 4.5 m only one row of strutting is needed, at the mid span

    position. For spans over 4.5 m two rows of strutting will be required, positioned at the

    one third and two third span positions. Solid strutting should be at least 38 mm thick

    timber extending to at least three

    quarters the depth of the joist. For example, 200 x 50mm joists would need at least 150 x

    38mm

    timber used as strutting. Herringbone strutting should be at least 38 x 38mm timber but

    can only

    be used where the spacing between the joists is less than three times the depth of the joist.

    Hence

  • 8/12/2019 Cec 103.- Workshop Technology 1

    82/128

    for a 150 x 50 joist, herring bone strutting can only be used up to a spacing of 450mm but

    for a

    200 x 50 joist, a spacing of up to 600mm would be satisfactory.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    83/128

    WEEK THIRTEEN

    13.0.0 NAILS, SCREWS AND BOLTS

    The commonest fixing carried out by the carpenter and and joiner in building is nailing.

    This type of connection may give a joint efficiency as low as 15 percent as a joint

    efficiency of the order of 100 percent in the case of adhesives. This is due to the difficulty

    of placing A sufficient number of units in the contact area of the member to be joined.

    The main reasons for the low efficiency of the rigid bar type of connection, such as the

    nailed or bolted joint, are:

    The low shear strength of timber parallel to the grain.

    The non- uniform distribution of bearing stress along the shank of the nail or bolt, e.t.c.

    In steel work it is assumed that the bearing stress is uniformly distributed over an area

    equal to the plate thickness multiplied by the bolt diameter.

    Members joined by together using screws provide a more scientifically designed joint

    fastening than that of nailing, but it is more costly. Screws may be position more

    accurately, and have a much higher resistance to withdrawal, than nails, and serve as a

    much better clamping device. In jointing, where nails or screws would not provide

    sufficient strength bolts are employed. These serve mainly as a clamping device.

    13.0.1 NAILS

    Oval wire nails are used for carpentry and joinery work, and have less tendency to split

    the timber because of their section when driven with the widest dimension in the same

    direction as the grain of timber. Their sizes vary from 1-6 (25mm-150mm).

    Circular nails are used for temporary work.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    84/128

    Cut clasp nails are used for general purpose.

    Floor brands are used for nailing floor boards and the length varies from 1.5to 3 (35-

    75mm).

    Spikes are wire nails used for securing large members, their length exceed 6 (150mm).

    Joiners brands or springs are used by joiners and their length varies from 1to 2 (25-

    50mm).

    Panel pins are used generally for fine work, the fixing of mouldings, thin panel and

    hardboard. Ring shank nails are used for heavy work (carpentry work).

    Clout nails are used in fixing the ceiling board and laths to the joist.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    85/128

    FIGURE: 13.1. DIFFERENT TYPES OF NAILS

    Holding power of nails

    A useful guide in obtaining the maximum holding power of nails in use is that the nail

    should penetrate the timber into which it is driven by the distance equal to the thickness

    of timber it is driven through.

    13.0.2 SCREWS

    Like nails, screws are made in variety of metals. The mild steel type is the most common;

    copper, brass, stainless steel, and aluminium are others. They have also a number of

    different finishes, such as galvanized, sheradized, nickel-plate, brassed, chromed, and

    black japanned.

    The sizes of wood screws vary between gauge NO. 0, having a shank diameter of

    1.56mm, and gauge NO. 32 with a diameter of 12mm. And the length vary from 3.17mm

    for the smaller gauges length to 152mm for the thicker screws.

    Iron screws are the strongest and cheapest screws and used for ordinary purposes. But

    they corrode easily especially in hard wood particularly oak.

    Screws are available in various sizes from 1to 6 (25mm-150mm).

    Flat or countersunk head screws

    Round head screws used for fixing metal to wood.

    Raised head screws also used for fixing metal to wood.

    Coach screws with square or hexagonal head, used for heavy

    construction job.

    Holding power of screws

  • 8/12/2019 Cec 103.- Workshop Technology 1

    86/128

    Screws develop a greater resistance to withdrawal during the seasoning process of the

    timber. This is the case with screws used in doors and windows which have been fixed in

    position on the site for some time.

    13.0.3 RAW BOLT

    These are metal bolt-fixings designed for use in masonry. There are two types to meet

    different method of fixing. The bolt and shell and the loose bolt type.

    13.1.0 CONSTRUCTION OF WOODEN SILLS

    13.1.1 WINDOW SILLS

    A window frame is usually less thick than the wall in which it is built, unless the frame is

    set flush with the outside face of the wall. Most of the area of a window is glass which

    does absorb water and rain runs off it on to the external surface below. To prevent this

    rain saturating the brickwork below the window, a sill is constructed. The sill may be of

    wood, stone, tiles, brick, sheet metal, e.t.c. which will not absorb moisture. Internal

    surfaceat

    the bottom of a window will collect dust and may become damp from moisture which

    condenses on the inside face of the glass and runs down.

    It is usually to construct an internal sill of some materials which is hard and that can becleaned. A timber board, called a window board, is commonly used. Clay or concrete

    tiles may also be used.

    INTERNAL SILLS OF WOOD WINDOW BOARD: The usual way of finishing the

    internal sill of windows is to fix a timber a timber window board. A softwood board is

  • 8/12/2019 Cec 103.- Workshop Technology 1

    87/128

    prepared with one edge rounded and it is fixed to grounds, plugs or fixing blocks in the

    brickwork below the window.

    It is not generally possible to drive nails through timber and in to brickwork. Most bricks

    are too hard to be penetrated by nails, hence the use of grounds, plugs or blocks.

    Timber grounds consist of lengths of small section sawn softwood. These grounds are

    either nailed to wood plugs driven into brickwork joint or directly into mortar joints, to

    provide a level surface to which the window board can be nailed.

    Plugs are wedge shaped piece of timber driven into joints between bricks and to which

    the window board is nailed.

    Fixing blocks offcuts of lightweight aggregate concrete blocks which are built at

    intervals into brickwork and into which nails can readily be driven.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    88/128

    FIGURE: 13. 2. CONSTRUCTION OF WINDOW SILL

  • 8/12/2019 Cec 103.- Workshop Technology 1

    89/128

    WEEK FOURTEEN

    14.0.0 CONSTRUCTION OF CENTRES FOR ARCHES

    Centres are wood structures which are used as temporary supports for arches during

    construction. Arches are constructed mainly of brick work masonry or concrete and they

    may be flat, sequential or semi-circular in shape.

    Centers consist of one or more rib which supports laggings. Laggings are cast to length

    equal to the thickness of the wall. They are battens or plywood, nailed on the ribs to form

    a platform for the walling.

    Two types of lagging are common i.e. open lagging. The centers are supported or

    vertical props.

    Folding wedges are necessary to permit a slight vertical adjustment of levels. The wedge

    also allows the center to be ease or lowered and then revolved (easing and striking).

    Ribs form the profile of the arch and are made from sheet materials (plywood) or solid

    section joined with metal plates or are built- up of two thicknesses of timber with their

    joint s lapping. Ribs provide support and fixing for lagging.

    Struts stabilise the framework by helping to redistribute some of the load placed on the

    ribs.

    Ties prevent built-up ribs from spreading and provide affixing for bearers.Bearers tie the base of the centre and provide a sole, under which the centre is wedge

    and propped.

    14.0.1 CONSTRUCTION

    Start by drawing a full-size outline of half the centre. Remember to deduct the thickness

    of the lagging (except for centres for segmental arches)

    Segmental arch of 50mm rise may need only a turning piece but most will requires a

    centre consisting of two curved ribs to span the width of the opening and to which

    laggings are nailed.

  • 8/12/2019 Cec 103.- Workshop Technology 1

    90/128

    Semi-circular arch is supported on a centre consisting of two built-up ribs which are

    prevented from spreading by the introduction of a tie. The laggings are 25x25 or

    plywood. The centre is supported on 50x175 props.

    FIGURE: 14.1. SEGMENTAL ARCH CENTRE

  • 8/12/2019 Cec 103.- Workshop Technology 1

    91/128

    FIGURE: 14.2. COSTRUCTION OF SEMICIRCULARARCH CENTRE

    FIGURE: 14.3. COSTRUCTION OF TURNING

    PIECE

  • 8/12/2019 Cec 103.- Workshop Technology 1

    92/128

    Centres for large arches: Regulations provide that for arches greater them 1.2m span,

    braced or trussed centers should be used.

    The centring systems described were mainly for supporting arches in buildings. Arches

    which have a span more than 3m are required mainly in large structures as religious

    buildings and arched bridges over rivers or roads.

    Large centring systems are generally constructed by much the same methods as are used

    for smaller units. Two way of forming large centers are:-

    (a)Built-up from two, three or more laminations.

    (b)Solid timber framed together with mortise and tenon joints which are secured with

    metal fasteners (straps or bolts).

    It is important that large span centring systems should be adequately supported, either by

    stout timber shores or by a sufficient number of steel props

  • 8/12/2019 Cec 103.- Workshop Technology 1

    93/128

    FIGURE: 14.4. SEMICIRCULAR ARCH

    CENTRE FOR DOMES

    Domes constructed of concrete are usually hemispherical in shape. The centering for

    those with span of 6m and over would be supported on a platform of steel scaffolding, or

    some other steel props systems,

    and it is general practice for such structures to be properly supported during

    construction. Centre for small domes may be built in two ways i.e. they may either

    consist of vertical ribs radiating from the centre of the dome with the curved surface

    covered by horizontal boarding or it may be built on circular ribs. The circular ribs would

    vary in sizes and would be placed horizontally and covered with vertical boarding.

    14.1.0 CONSTRUCTION OF TIMBER SHORES

    A shore is a member, generally of timber used temporarily to prop a wall which is either.

    (a)Defective and likely to collapse

    (b)Liable to collapse when alterations are made to adjacent property.

    (c)Liable to collapse when being altered by the removal of its lower portion for

    reconstruction.

    Shores are the supports or props used in shoring.

    14.1.1 METHOD OF CONSTRUCTION

    Raking shores:- This is an inclined struts used to support a wall which shows signs of

    failure such as cracks or bulge. The defects may be due to thrusts from one or more

    upper floors, or from the roof or because of unequal settlement of its foundation. In its

    simplest form the shore consist of struts, together with a suitable support at the foot and

    fixing at the head. It consist of an inclined member supported at ground level on a piece

    of wood called sole plate and secured at the top by wood needle inserted in the wall. The

  • 8/12/2019 Cec 103.- Workshop Technology 1

    94/128

    angle between the shore and the sole plate must be slightly less than 90oor 87

    o. The wall

    pieces provide a suitable abutment for the shore and fixing for the lower end of the strut

    or brace. The wall piece is hold for the needle. The wall pieces are attach to the wall by

    metal wall hooks wh


Recommended