+ All Categories
Home > Business > Ceca adjudication the process - january 2013

Ceca adjudication the process - january 2013

Date post: 30-Nov-2014
Category:
Upload: watsonburton
View: 291 times
Download: 2 times
Share this document with a friend
Description:
 
19
clear practical advice Adjudication: The Process Stephen McLellan January 2013
Transcript
Page 1: Ceca   adjudication  the process - january 2013

clear practical advice

Adjudication: The Process

Stephen McLellanJanuary 2013

Page 2: Ceca   adjudication  the process - january 2013

Stephen McLellan

Solicitor

Construction and Engineering

Watson Burton LLP

Telephone: 0845 901 0936

Email: [email protected]

Page 3: Ceca   adjudication  the process - january 2013

Adjudication

1. Background to adjudication

2. The process

2.1 starting the process

2.2 submissions

2.3 decision / enforcement

3. The future of adjudication

Page 4: Ceca   adjudication  the process - january 2013

1 Background to Adjudication

What is adjudication?• 3rd party adjudicator• 28 day process (up to 42 days)• Interim decision

• Costs not recoverable

Page 5: Ceca   adjudication  the process - january 2013

1 Background to Adjudication

- Housing Grants, Construction and Regeneration Act 1996

“The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decision of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement….”

Page 6: Ceca   adjudication  the process - january 2013

“…The timetable for adjudications is very tight…many would say unreasonably tight, and likely to result in injustice. Parliament must be taken to have been aware of this. So far as procedure is concerned, the adjudicator is given a fairly free hand”.

(Macob Civil Engineering Ltd -v- Morrison Construction Ltd

[1999])

1 Background to Adjudication

Page 7: Ceca   adjudication  the process - january 2013

1 Background to Adjudication

- Local Democracy, Economic Development and Construction Act 2009• came into force October 2011• requirement for construction contracts to be “in writing”

removed• parties cannot agree who will pay the costs of the process

before the Notice of Adjudication is issued

Page 8: Ceca   adjudication  the process - january 2013

2 The Process

- When can you use adjudication?

• there must be a dispute• qualifying contract – the following are excluded:

– sale of goods contracts– extraction of oil, gas, materials– work associated with nuclear processing, power generation,

water or effluent treatment, production and processing of chemicals etc.

– contracts with residential occupants

Page 9: Ceca   adjudication  the process - january 2013

2 The Process

2.1 Starting the process

• the Notice of Adjudication– identifies intention to adjudicate – defines the adjudicator’s jurisdiction

• can be deliberately narrow or wide

Page 10: Ceca   adjudication  the process - january 2013

2 The Process

2.1 Starting the process

• appointment of an adjudicator– named in contract? – agreed between parties– nomination

7 days after Notice of Adjudication

Page 11: Ceca   adjudication  the process - january 2013

2 The Process

2.2 Submissions

- Referral Notice• re-statement of the dispute • complete explanation of the claim:

- identify the parties- contract documents and relevant terms- what obligations have been breached?

• relevant supporting documentation: - witness statements?

Page 12: Ceca   adjudication  the process - january 2013

2 The Process

2.2 Submissions

- Referral Notice (continued…)• points of law• request for a meeting or hearing?

Page 13: Ceca   adjudication  the process - january 2013

2 The Process

2.2 Submissions- Response• be prepared • understand the extent of the dispute

- is clarification required? • are there any jurisdictional issues? • extension of time?

7 days from the Referral Notice

Page 14: Ceca   adjudication  the process - january 2013

2 The Process

2.2 Submissions

- written questions- meeting- further submissions

Page 15: Ceca   adjudication  the process - january 2013

2 The Process

2.3 Decision / enforcement

- Decision• reasons to be provided? • 28 to 42 days from referral• effect of decision• payment • other, e.g. construing contract• temporarily binding

Page 16: Ceca   adjudication  the process - january 2013

2 The Process

2.3 Decision / enforcement

- Enforcement• binding

- must comply, cannot appeal- if a party disagrees with a decision, can challenge by

litigation / arbitration• courts will enforce the decision, in the first instance• shortened process – summary judgement

Page 17: Ceca   adjudication  the process - january 2013

3 The Future for Adjudication

• verbal contracts – disputes over oral terms?

• costs– “Tolent” clauses banned

Page 18: Ceca   adjudication  the process - january 2013

Further information

- Useful websites

www.rics.org/drs

www.adjudication.org

www.adjudication.co.uk

www.watsonburton.com

Page 19: Ceca   adjudication  the process - january 2013

clear practical advice

Adjudication: The Process

Stephen McLellanJanuary 2013


Recommended