VICTOR PARANHOS
CEO OF ENERGIA SUSTENTÁVEL DO BRASIL
ESBR: General Framework
ESBR
Financing(BNDES)
Other Companies
Interfaces(Concremat)
Civil Project(Themag)
Civil Works(CCCC and JMalucelli)
Jirau HPP
Turbines and Generators
(DongFang and Alstom/Voith/Andritz)
Owner’s Engineering(LEME)
BS Construtora
Works Around the Reservoir
Owner’s Engineering(INTT)
Concession Agreement(ANEEL/MME)
Environmental Licensing(IBAMA)
Assembly and Mounting
(ENESA)
Mitsui(20%)
GDF Suez (40%)
Eletrosul (20%)
Chesf(20%)
Jirau HPP: Basic Characteristics
Part of PAC -Growth
Acceleration Program
Located at Ilha do Padre, 120 km far from Porto Velho, State of Rondônia,
in the North of Brazil
3,750 MW installed capacity - enough
to supply more than 10 millions of
families
Connected to the National
Interconnecd Grid System through
three 500 kV transmission lines
• Energy:
Power houses: 2, one at each riverbank
Installed capacity: 3,750 MW
Quantity of turbines: 50
Turbine type: Bulb
Individual turbine capacity: 75 MW
• Reservoir:
Variable water level: 82.5 m – 90.0 m
Reservoir area: 361.6 km2
Reservoir area increase due to the project: 21.0 to 207.7 km2
Life expectancy: more than 50 years
• Spillway:
Design flow: 82,600 m3/s
18 gates, each 22.7 m high by 20 m wide
Jirau HPP: Location
Power HouseRight Bank
SpillwayLog-Boom
Logs Discharger
Power HouseLeft Bank – 1ª Phase
Power HouseLeft Bank – 2ª Phase
Jirau HPP: Overview
• 13 units in operation (975 MW);
• 8 additional units already being commissioned (600 MW);
• Jirau units have already operated successfully at full power and with aperformance above auction requirements;
• 95,5% overall project progress;
• Work force and night shift increased in order to speed upcommissioning.
Jirau HPP: Project Update
Spillway
Power HouseLeft Bank – 2ª Phase
Largest HPP in the World
HPPInstalledCapacity
1 Three Gorges Dam – China 22,500 MW
2 Itaipu Dam – Brazil/Paraguay 14,000 MW
3 Xiluodu – China 13,860 MW
4 Guri – Venezuela 8,850 MW
5 Tucuruí – Brazil 8,370 MW
6 Xiangjiaba – China 7,750 MW
7 Grand Coulle – United States 6,809 MW
8 Longtan Dam – China 6,426 MW
9 Krasnoyarsk – Russia 6,000 MW
10 Nuozhadu – China 5,850 MW
HPPInstalledCapacity
11 Churchill Falls – Canada 5,828 MW
12 Robert-Bourassa – Canada 5,616 MW
13 Jinping-II – China 4,800 MW
14 Bratsk – Russia 4,500 MW
15 Laxiwa Dam – China 4,200 MW
16 Xiaowan Dam – China 4,200 MW
17 Sayano-Shushenskaya – Russia 3,840 MW
18 Ust Ilimskaya – Russia 3,840 MW
19 Jirau – Brazil 3,750 MW
*HPP under construction are not included. Some HPP mayhave additional units under construction, but only currentinstalled capacity is listed.
A True Challenge
INSTALL ONE OF THE LARGEST HYDROELECTRIC PLANTS IN THE AMAZON
REGION
MEET THE PROJECT DEADLINES
INCREASE THE POWER-GENERATING CAPACITY (6 MORE TURBINES)
TECHNOLOGICAL CHALLENGES – TURBINES, LOG-BOOMS, SEDIMENTS
LOGISTICAL CHALLENGES FOR TRANSPORTING OF EQUIPMENT AND MATERIALS
CIVIL WORKS
ENVIRONMENTAL LICENSING PROCESS
Challenge: Jirau HPP’s Schedule
50%55% 61%
68%75%
KEY SUCESS FACTORS
Best suppliers;
Responsabilities cleary allocated;
Owners-engineer arrangements forevery aspect of the project
– Civil works: LEME Engenharia
– Transmissions lines: LEME Engenharia
– Nova Mutum Paraná and worksaround the reservoir: INTERTECHNE
Interface Management:
– CONCREMAT is a contractor focussedspecifically on interface issues withrespect to technical aspects of theconstruction activities, focussing onlogistics control, storage, transport,and others.
Mix of national and foreigncompanies.
Contractors and Interfaces:
Pursuit of Excellence
Civil Project
THEMAG
Civil Works
CCCC
Civil Works
JMalucelli
Turbines and Generators
DONG FANG
Turbines and Generators
ALSTOM / VOITH / ANDRITZ
Electro-mechanical Equipament
SIEMENS/CNEC
Hydro-mechanical Equipament
BARDELLA
Assembly and Mounting
ENESA
Transmission Lines
TOSHIBA
Logistics
BERTILING
International Supervision
COYNE ET BELLIER
Nova Mutum Paraná
BS Construtora
MAJOR CONTRACTORS:
Difficulties and Risks
Jirau HPP is being built in a remote area;
There are a lot of construction risks: geological, hydrological, topographyand others;
There is a concentration of players in charge of the civil constructionindustry:
Great difficulty in replacing companies that do not perform in accordance tocontracts.
Low productivity;
High labor turnover;
Constructions claims (very common in the construction industrynowadays);
Large projects as Jirau HPP tend to suffer adjustments duringimplementation;
Consume precious time, money and resources for both parties.
Delays and disruptions (caused by criminal acts);
Risks of tax changes.
EPC
• There is only a basicdesign of the projectwhen the contract issigned.
• The size of theseprojects is such thatno one contractor iswilling to take theoverall risk.
• There are so manytecnhological risksinvolved.
Contractual Structures
Unit Price
• Higher risk for owner.
• The exact final priceof the project is notknow until thecompletos of theproject.
Open Book
• Require more workfor the owner tomanage.
• Require auditingcontractor’s invoices.
• Difficulties to predictthe final cost of theproject.
• Contractors pay lessattention to costcontrol andproductivity.
Final Considerations
Local and regional governments should provide health and education services andpublic safety to ensure that the projects benefits delivered by the project are sustainedinto the long term.
Non-insurable risks (vandalism and others events) cannot be imputed to the owners ofthe project because they do not have the police power.
Risks need to be shared between the owner and the contractors.
– Types of contracts;
– Long-term relationship.
It is important to have stable and fixed rules from the beginning of the project and toavoid changing existing measures which causes significant increases in a project’s cost.
Environmental licensing should be simplified.
Investors must have a clear vision of what will be their future costs.