CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 1
FINDINGS FOR THE
GRIFFIN PARK MASTER PLAN PROJECT REQUIRED UNDER THE CALIFORNIA ENVIRONMENTAL QUALITY ACT
(Public Resources Code, Section 21000 et seq)
I. INTRODUCTION
The California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.) requires
the City of Manteca (City), as the CEQA lead agency, to: 1) make written findings when it approves
a project for which an environmental impact report (EIR) was certified, and 2) identify overriding
considerations for significant and unavoidable impacts identified in the EIR.
This document explains the City’s findings regarding the significant and potentially significant
impacts identified in the environmental impact report (EIR) prepared for the Griffin Park Master
Plan Project (Project). The statement of overriding considerations in section VII, below, identifies
economic, social, technical, and other benefits of the Project that override any significant
environmental impacts that would result from the Project.
As required under CEQA, the Final EIR describes the Project, adverse environmental impacts of the
Project, and mitigation measures and alternatives that would substantially reduce or avoid those
impacts. The information and conclusions contained in the EIR reflect the City’s independent
judgment.
The Final EIR (which includes the Draft EIR, comments, responses to comments, and revisions to
the Draft EIR) for the Project, examined the proposed Project and several alternatives to the
Project including: (1) No Project (No Build) Alternative; (2) Increased Density Alternative; and (3)
Agriculture Protection Alternative.
The Findings and Statement of Overriding Considerations are presented for adoption by the City
Council, as the City’s findings under CEQA and the CEQA Guidelines (Cal. Code Regs., title 14, §
15000 et seq.) relating to the Project. The Findings provide the written analysis and conclusions of
this City Council regarding the Project’s environmental impacts, mitigation measures, alternatives
to the Project, and the overriding considerations, which in this City Council’s view, justify approval
of the Project, despite its environmental effects.
II. GENERAL FINDINGS AND OVERVIEW
Project Overview
The Project site comprises approximately 343.94 acres of land, only 333.94 of which would be
developed as part of the Project. The Project site is bounded on the north by West Atherton Drive,
on the east by Manteca Road, on the south by Sedan Avenue, and on the west by South Union
Road.
CEQA FINDINGS
2 CEQA Findings – Griffin Park Master Plan
The Conceptual Land Use Plan for the proposed Project includes designations for large lot,
standard lot, and small lot residential uses that will provide for cluster housing to large estate lots.
At full build-out, the Project site will accommodate up to 1,592 residential units and up to 65,340
square feet of neighborhood-serving commercial uses. The proposed Project includes a Central
Park, neighborhood parks, linear parks, streetscapes, gateway entries, and community walls and
fences totaling 26.46 acres. The Project also includes expansion of the existing vehicular and non-
vehicular circulation system and utility improvements. The proposed Project does not include a
detailed site plan for the Commercial Mixed Use area. The Commercial Mixed Use land would
ultimately require a design review approval by the City prior to any development on this portion of
the Project site.
The proposed Project is proposed by a private sector developer who is proposing to design and
build the subdivision. The quantifiable objectives of the proposed Project include annexation of
343.94 acres of land into the Manteca city limits, and the subsequent development of land, which
will include: Commercial Mixed-Use, Low Density Residential, and Open Space Parkland.
PROPOSED LAND USE CHANGES AND PRE-ZONING
The proposed Project would require a General Plan amendment to change land uses on the Project
site. As shown in Figure 2.0-8b in Section 2.0 of the Draft EIR, changes to the Land Use Element
would include changing approximately 0.28 acres of General Commercial (GC) to Low Density
Residential (LDR) uses; changing approximately 31.63 acres of Urban Reserve-Very Low Density
Residential (UR-VLDR) to LDR uses; changing approximately 5.0 acres of UR-VLDR to Commercial
Mixed Use (CMU) uses; eliminating all 15.16 acres of Park (P) uses; and maintaining the remainder
of the site as LDR.
The Project site is currently within the jurisdiction of San Joaquin County. The San Joaquin County
Local Agency Formation Commission (LAFCo) will require the Project site to be pre-zoned by the
City of Manteca in conjunction with the proposed annexation.
As shown in Figure 2.0-8c in Section 2.0 of the Draft EIR, the City’s pre-zoning will include the
following zoning designations: One-Family Dwelling Zoning District (R-1), and Mixed Use
Commercial Zoning District (CMU). The pre-zoning would go into effect upon annexation into the
City of Manteca.
RESIDENTIAL DISTRICTS
The Griffin Park Master Plan will provide a variety of housing types and lot sizes, referred to as
residential districts, that will accommodate a range of housing objectives and buyer needs with a
goal to ensure housing for a variety of families and lifestyles. The three proposed residential
districts are designated as GP-Large Lot, GP-Standard Lot, and GP-Small Lot. The aforementioned
residential zoning districts correspond to the Manteca R-1 zoning district. The land use and
development standards for the residential districts of the Griffin Park Master Plan shall comply
with all requirements that apply to the corresponding zoning in the Manteca Municipal Code,
except as modified within the Master Plan.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 3
COMMERCIAL DEVELOPMENT AREAS
The proposed Griffin Park Commercial District (GP-Commercial) provides a neighborhood-oriented
commercial area that may include a mix of retail and services, and multi-family residential. The GP-
Commercial site provides an opportunity to locate retail and services scaled to serve the proposed
Project and surrounding neighborhoods to enhance the overall walkability within the Project site
and to further minimize reliance on vehicles. The Project includes a 5-acre commercial site that it is
situated in order to minimize conflicts with adjacent residential neighborhoods while also
remaining accessible by all neighborhoods within the Project site by short walk or by bicycle. At full
build-out, the 5-acre commercial site will provide an estimated 65,340 square feet of
neighborhood-serving commercial uses.
PARKS, RECREATION, AND OPEN SPACE
Approximately 26.46 acres of active and passive park and recreation facilities will be provided
within the Project site in a variety of forms, consistent with the City’s General Plan. After
dedication to the City, the parks, parkways, and recreation facilities will be under the jurisdiction
of the City, and will be operated and maintained by the City for the enjoyment of the residents of
Manteca. Maintenance will be funded through a services community facilities district. Parks may
include community or neighborhood parks with active and passive components as approved by the
City. Park acreage and facilities shall occur within the Project site in a variety of forms as
determined by the City during the mapping and improvement plan process. Parks may feature play
fields, children play areas, picnic areas, ball courts, open lawn areas, or other amenities. Park areas
will be designed in conjunction with storm water basins and interconnected by trails and bikeways.
Open space shall be integrated throughout the Project site to provide recreational opportunities,
aesthetic value, protection of non-vehicular pathways, and offer locations for non-vehicular
pathways. The open space areas will be landscaped with regionally-appropriate plantings grouped
towards similar water needs.
PROCEDURAL BACKGROUND
Notice of Preparation Public Circulation: The City of Manteca circulated a Notice of Preparation
(NOP) of an EIR for the proposed Project on June 13, 2016 to State Clearinghouse, State
Responsible Agencies, State Trustee Agencies, Other Public Agencies, Organizations and Interested
Persons. A public scoping meeting was held on June 28, 2016 to present the Project description to
the public and interested agencies, and to receive comments from the public and interested
agencies regarding the scope of the environmental analysis to be included in the Draft EIR. The City
received five NOP comments from the following agencies: California Department of
Transportation, Central Valley Regional Water Quality Control Board, San Joaquin Council of
Governments, Inc., San Joaquin County Environmental Health Department, and San Joaquin
County Public Works Department. Concerns raised in response to the NOP were considered during
preparation of the Draft EIR. The NOP and comments received on the NOP by interested parties
are presented in Appendix A of the Draft EIR.
CEQA FINDINGS
4 CEQA Findings – Griffin Park Master Plan
Notice of Availability and Draft EIR: The City of Manteca published a public Notice of Availability
(NOA) for the Draft EIR on March 7, 2017, inviting comment from the general public, agencies,
organizations, and other interested parties. The NOA was filed with the State Clearinghouse (SCH #
2016062029) and the County Clerk, a newspaper of regional circulation pursuant to the public
noticing requirements of CEQA. The Draft EIR was released for a 45-day public review and
comment on March 7, 2017. The Draft EIR was then recirculated on April 6, 2017 and the public
review period was extended for another 45 days. The Recirculated Draft EIR comment period
ended on May 20, 2017.
The Draft EIR contains a description of the Project, description of the environmental setting,
identification of Project impacts, and mitigation measures for impacts found to be significant, as
well as an analysis of Project alternatives, identification of significant irreversible environmental
changes, growth-inducing impacts, and cumulative impacts. The Draft EIR identifies issues
determined to have no impact or a less than significant impact, and provides detailed analysis of
potentially significant and significant impacts. Comments received in response to the NOP were
considered in preparing the analysis in the Draft EIR.
Final EIR: The City of Manteca received eight (8) comment letters on the Draft EIR during the
public review period. In accordance with CEQA Guidelines Section 15088, this Final EIR responds to
the comments received during the public review period. This Final EIR also responds to all
comments received after the public review period had ended. The Final EIR also contains minor
edits to the Draft EIR, which are included in Section 3.0, Errata. This document and the Draft EIR,
as amended herein, constitute the Final EIR.
Responses to comments do not involve any new significant impacts or “significant new
information” that would require recirculation of the Draft EIR pursuant to CEQA Guidelines Section
15088.5. Each response is provided in the Final EIR.
RECORD OF PROCEEDINGS AND CUSTODIAN OF RECORD
For purposes of CEQA and the findings set forth herein, the record of proceedings for the City’s
findings and determinations consists of the following documents and testimony, at a minimum:
The NOP, comments received on the NOP, and all other public notices issued by the City in
relation to the Project (e.g., Notice of Availability).
The Draft EIR and Final EIR, including comment letters, and technical materials cited in the
documents.
All non-draft and/or non-confidential reports and memoranda prepared by the City and
consultants in relation to the EIR.
Minutes and transcripts of the discussions regarding the Project and/or Project
components at public hearings held by the City.
Staff reports associated with City Council meetings on the Project.
Those categories of materials identified in Public Resources Code Section 21167.6.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 5
The City Clerk is the custodian of the administrative record. The documents and materials that
constitute the administrative record are available for review at the City of Manteca at 1001 West
Center Street, Manteca, CA 95337.
FINDINGS REQUIRED UNDER CEQA
Public Resources Code section 21002 provides that “public agencies should not approve projects
as proposed if there are feasible alternatives or feasible mitigation measures available which
would substantially lessen the significant environmental effects of such projects[.]” Further, the
procedures required by CEQA “are intended to assist public agencies in systematically identifying
both the significant effects of proposed projects and the feasible alternatives or feasible mitigation
measures which will avoid or substantially lessen such significant effects.” (Id.) Section 21002 also
provides that “in the event specific economic, social, or other conditions make infeasible such
project alternatives or such mitigation measures, individual projects may be approved in spite of
one or more significant effects thereof.”
The mandate and principles established by the Legislature in Public Resources Code section 21002
are implemented, in part, through the requirement in Public Resources Code section 21081 that
agencies must adopt findings before approving projects for which an EIR is required.
CEQA Guidelines section 15091 provides the following direction regarding findings:
(a) No public agency shall approve or carry out a project for which an EIR has been
certified which identifies one or more significant environmental effects of the project
unless the public agency makes one or more written findings for each of those significant
effects, accompanied by a brief explanation of the rationale for each finding. The possible
findings are:
(1) Changes or alterations have been required in, or incorporated into, the project
which avoid or substantially lessen the significant environmental effect as
identified in the final EIR.
(2) Such changes or alterations are within the responsibility and jurisdiction of
another public agency and not the agency making the finding. Such changes have
been adopted by such other agency or can and should be adopted by such other
agency.
(3) Specific economic, legal, social, technological, or other considerations,
including provision of employment opportunities for highly trained workers, make
infeasible the mitigation measures or project alternatives identified in the final
EIR.
(See also Pub. Resources Code, § 21081, subd. (a)(1)-(3).)
As defined by CEQA, “feasible” means capable of being accomplished in a successful manner
within a reasonable period of time, taking into account economic, environmental, social, legal, and
technological factors. (Pub. Resources Code, § 21061.1; see also CEQA Guidelines, § 15126.6(f)(1)
CEQA FINDINGS
6 CEQA Findings – Griffin Park Master Plan
[determining the feasibility of alternatives].) The concept of “feasibility” also encompasses the
question of whether a particular alternative or mitigation measure promotes the underlying goals
and objectives of a project. (See Association of Irritated Residents v. County of Madera (2003) 107
Cal.App.4th 1383, 1400 [court upholds findings rejecting a “reduced herd” alternative to a
proposed dairy as infeasible because the alternative failed to meet the “fundamental objective” of
the project to produce milk]; Sierra Club v. County of Napa (2004) 121 Cal.App.4th 1490, 1506-
1508 [agency decision-makers, in rejecting alternatives as infeasible, appropriately relied on
project objective articulated by project applicant].) Moreover, “‘feasibility’ under CEQA
encompasses ‘desirability’ to the extent that desirability is based on a reasonable balancing of the
relevant economic, environmental, social, legal, and technological factors.” (City of Del Mar v. City
of San Diego (1982) 133 Cal.App.3d 410, 417; see also California Native Plant Society v. City of
Santa Cruz (2009) 177 Cal.App.4th 957, 1001-1002.
With respect to a project for which significant impacts cannot be feasibly avoided or substantially
lessened, a public agency may nevertheless approve the project if the agency first adopts a
statement of overriding considerations setting forth the specific reasons that the project’s benefits
outweigh its significant unavoidable adverse environmental effects. (Pub. Resources Code, §§
21001, 21002.1(c), 21081(b).)
CEQA Guidelines section 15093 provides the following direction regarding a statement of
overriding considerations:
(a) CEQA requires the decision-making agency to balance, as applicable, the economic,
legal, social, technological, or other benefits, including region-wide or statewide
environmental benefits, of a proposed project against its unavoidable environmental risks
when determining whether to approve the project. If the specific economic, legal, social,
technological, or other benefits, including region-wide or statewide environmental
benefits, of a proposed project outweigh the unavoidable adverse environmental effects,
the adverse environmental effects may be considered “acceptable.”
(b) When the lead agency approves a project which will result in the occurrence of
significant effects which are identified in the final EIR but are not avoided or substantially
lessened, the agency shall state in writing the specific reasons to support its action based
on the final EIR and/or other information in the record. The statement of overriding
considerations shall be supported by substantial evidence in the record.
(c) If an agency makes a statement of overriding considerations, the statement should be
included in the record of the project approval and should be mentioned in the notice of
determination. This statement does not substitute for, and shall be in addition to, findings
required pursuant to Section 15091.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 7
MITIGATION MONITORING PROGRAM
A Mitigation Monitoring Program has been prepared for the Project and has been adopted
concurrently with these Findings. (See Pub. Resources Code, § 21081.6, subd. (a)(1).) The City will
use the Mitigation Monitoring Program to track compliance with Project mitigation measures.
CONSIDERATION OF THE ENVIRONMENTAL IMPACT REPORT
In adopting these Findings, this City Council finds that the Final EIR was presented to this City
Council, the decision-making body of the lead agency, which reviewed and considered the
information in the Final EIR prior to approving the Project. By these findings, this City Council
ratifies, adopts, and incorporates the analysis, explanation, findings, responses to comments, and
conclusions of the Final EIR. The City Council finds that the Final EIR was completed in compliance
with CEQA. The Final EIR represents the independent judgment of the City.
SEVERABILITY
If any term, provision, or portion of these Findings or the application of these Findings to a
particular situation is held by a court to be invalid, void, or unenforceable, the remaining
provisions of these Findings, or their application to other actions related to the Project, shall
continue in full force and effect unless amended or modified by the City.
III. FINDINGS AND RECOMMENDATIONS REGARDING SIGNIFICANT
AND UNAVOIDABLE IMPACTS
A. AESTHETICS AND VISUAL RESOURCES
1. IMPACT 3.1-1: PROJECT IMPLEMENTATION MAY RESULT IN SUBSTANTIAL ADVERSE EFFECTS
ON SCENIC VISTAS AND RESOURCES OR SUBSTANTIAL DEGRADATION OF VISUAL CHARACTER.
(a) Potential Impact. The potential for the Project to result in impacts to the visual
character of the region is discussed on pages 3.1-6 through 3.1-7 of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. The Project would result in the
conversion of the land from agricultural uses, which would contribute to changes
in the regional landscape and visual character of the area. In order to reduce visual
impacts, development within the Project site is required to be consistent with the
General Plan and the Manteca Zoning Ordnance which includes design standards
in order to ensure quality and cohesive design of the Project site. These standards
include specifications for building height, massing, and orientation; exterior
lighting standards and specifications; and landscaping standards. Implementation
CEQA FINDINGS
8 CEQA Findings – Griffin Park Master Plan
of the design standards would ensure quality design throughout the Project site,
and result in a Project that would be internally cohesive while maintaining
aesthetics similar to surrounding uses. However, regardless of the quality of design
implemented on the Project site, Project implementation would permanently
remove the existing agricultural land on the Project site, and convert the site to
urbanized uses. This is considered a significant and unavoidable impact. There is
no additional feasible mitigation available that would reduce this impact to a less
than significant level.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with impacts to the visual character of the region, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
2. IMPACT 4.2: CUMULATIVE DEGRADATION OF THE EXISTING VISUAL CHARACTER OF THE
REGION
(a) Potential Impact. The potential for the Project to result in impacts to the visual
character of the region is discussed on pages 4.0-5 through 4.0-6 of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Implementation of the proposed
Project would convert the Project site from its existing agricultural character to a
developed residential, commercial and business park with various buildings,
landscaping, parking areas, and recreational amenities. In order to reduce visual
impacts, development within the Project site is required to be consistent with the
General Plan and the Manteca Zoning Ordnance which includes design standards
in order to ensure quality and cohesive design of the Project site. These standards
include specifications for building height, massing, and orientation; exterior
lighting standards and specifications; and landscaping standards. Implementation
of the design standards would ensure quality design throughout the Project site,
and result in a Project that would be internally cohesive while maintaining
aesthetics similar to surrounding uses to ensure consistent development that is in
line with the City’s vision for the community’s identity. However, Project
implementation would alter the existing visual character of the Project site.
Under cumulative conditions, buildout of the General Plan for Manteca and the
surrounding jurisdictions could result in changes to the visual character and quality
of the City of Manteca through development of undeveloped areas and/or
changes to the character of existing communities. Development of the proposed
Project, in addition to other future projects in the area, would change the existing
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 9
visual and scenic qualities of the City. There are no mitigation measures that could
reduce this impact except a ceasing of all future development, which is not a
feasible option. As such, this is a cumulatively considerable contribution and a
significant and unavoidable impact.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with impacts to the visual character of the region, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
B. AGRICULTURAL RESOURCES
1. IMPACT 3.2-1: THE PROPOSED PROJECT HAS THE POTENTIAL TO RESULT IN THE CONVERSION
OF FARMLANDS, INCLUDING PRIME FARMLAND AND FARMLAND OF STATEWIDE IMPORTANCE,
AS SHOWN ON THE MAPS PREPARED PURSUANT TO THE FARMLAND MAPPING AND
MONITORING PROGRAM OF THE CALIFORNIA RESOURCES AGENCY, TO NON-AGRICULTURAL
USES.
(a) Potential Impact. The potential for the Project to result in the conversion of farmlands,
including important farmlands, to nonagricultural uses is discussed on pages 3.2-12
and 3.2-13 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.2-1.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Development of the proposed
Project as a whole would result in the permanent conversion of 290.56 acres of
Prime Farmland and Farmland of Statewide Importance, to nonagricultural use.
The loss of Important Farmland is considered a potentially significant
environmental impact.
The City‘s agricultural mitigation fee program requires that future development
pay the agricultural mitigation fee, currently $2,584.51 per acre but subject to
annual increases, to mitigate the conversion of agricultural land to urban use. The
City then uses these funds to purchase conservation easements or deed
restrictions on agricultural land to ensure that the land remains in agricultural use
in perpetuity. While the proposed Project will contribute fees toward the purchase
of conservation easements on agricultural lands through the City’s agricultural
mitigation fee program and the SJMSCP (as required by Mitigation Measure 3.2-1),
those fees and conservation easements would not result in the creation of new
farmland to offset the loss that would occur with Project implementation. As such,
CEQA FINDINGS
10 CEQA Findings – Griffin Park Master Plan
the loss of Important Farmland would be a significant and unavoidable impact
relative to this topic.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with impacts to farmlands, as more fully stated in the Statement of
Overriding Considerations in Section VII, below.
2. IMPACT 4.4: CUMULATIVE IMPACT ON AGRICULTURAL AND FOREST RESOURCES
(a) Potential Impact. The potential for the Project to result in a cumulative impact on
agricultural and forest is discussed on pages 4.0-6 and 4.0-7 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.2-1.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Development of the proposed Project
as a whole would result in the permanent conversion of 290.56 acres of Prime
Farmland and Farmland of Statewide Importance, to nonagricultural use. The loss
of Important Farmland is considered a potentially significant environmental
impact.
The City‘s agricultural mitigation fee program requires that future development
pay the agricultural mitigation fee, currently $2,584.51 per acre but subject to
annual increases, to mitigate the conversion of agricultural land to urban use. The
City then uses these funds to purchase conservation easements or deed
restrictions on agricultural land to ensure that the land remains in agricultural use
in perpetuity.
While the proposed Project will contribute fees toward the purchase of
conservation easements on agricultural lands through the City’s agricultural
mitigation fee program and the SJMSCP mitigation program, as required by
Mitigation Measure 3.2-1, those fees and conservation easements would not
result in the creation of new farmland to offset the loss that would occur with
Project implementation. As such, the loss of Important Farmland would be a
cumulatively considerable contribution and a significant and unavoidable impact.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with cumulative impacts on agricultural land and uses, as more fully
stated in the Statement of Overriding Considerations in Section VII, below.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 11
C. AIR QUALITY
1. IMPACT 3.3-1: PROJECT OPERATION HAS THE POTENTIAL TO CAUSE A VIOLATION OF AN AIR
QUALITY STANDARD OR CONTRIBUTE SUBSTANTIALLY TO AN EXISTING OR PROJECTED AIR
QUALITY VIOLATION.
(a) Potential Impact. The potential for the Project to result in cause a violation of an air
quality standard or contribute substantially to an existing or projected air quality
violation is discussed on pages 3.3-19 and 3.3-23 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.3-1, 3.3-2, and 3.3-3.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. The proposed Project would be a
direct and indirect source of air pollution, in that it would generate and attract
vehicle trips in the region (mobile source emissions) and it would increase area
source emissions and energy consumption. The mobile source emissions would be
entirely from vehicles, while the area source emissions would be primarily from
the use of natural gas fuel combustion, landscape fuel combustion, consumer
products, and architectural coatings.
The proposed Project would exceed the San Joaquin Valley Air Pollution Control
District (SJVAPCD) thresholds of significance for operations even with mitigation
measures. The proposed Project is subject to the SJVAPCD Rule 9510 (Indirect
Source Rule), which could result in substantial mitigation of emissions. The
reductions are accomplished by the incorporation of mitigation measures into
projects and/or by the payment of an Indirect Source Rule fee for any required
reductions that have not been accomplished through project mitigation
commitments. The current fees are $9,350 per ton of NOx, although these are
subject to adjustments by the SJVAPCD. The actual calculations will be
accomplished by the SJVAPCD and Project applicants as the Project (i.e. or portions
of the Project) are brought forward for approval under Rule 9510. However, even
with the application of the ISR and the mitigation measures described above,
emissions levels may remain above the defined thresholds of significance for the
Project as a whole. As such, operation of the proposed Project would have a
significant and unavoidable impact relative to operational air emissions.
A Mitigation Measure is included in this EIR that requires the Project proponent to
consider the potential use of a VERA as a method to achieve emissions reductions
in excess of District Rule 9510 (Indirect Source Review) requirements. The
mitigation measure also requires consideration of the benefits of improved air
CEQA FINDINGS
12 CEQA Findings – Griffin Park Master Plan
quality with the costs of implementation in the decision-making process. Because
a VERA is a voluntary contractual agreement that is negotiated, it cannot be
certain that both parties will agree to acceptable terms. The inclusion of this
mitigation does not guarantee that the impact would be reduced to a less than
significant level. As such, the impact would be significant and unavoidable impact
relative to operational air emissions.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with impacts to air quality, as more fully stated in the Statement of
Overriding Considerations in Section VII, below.
2. IMPACT 4.5: CUMULATIVE IMPACT ON THE REGION'S AIR QUALITY
(a) Potential Impact. The potential for the Project to have a cumulative impact on the
region’s air quality is discussed on pages 4.0-7 and 4.0-8 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.3-1 through and 3.3-8.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Under buildout conditions in the San
Joaquin County, the SJVAB would continue to experience increases in criteria
pollutants and efforts to improve air quality throughout the basin would be
hindered. San Joaquin County has a state designation of nonattainment for Ozone,
PM10, and PM2.5 and is either unclassified or attainment for all other criteria
pollutants. The County has a national designation of nonattainment for ozone and
PM2.5.
The proposed Project would result in increased emissions primarily from vehicle
miles travelled associated with Project implementation. The SJVAPCD has
established operations related emissions thresholds of significance and it was
determined that annual emissions of ROG, NOx, and PM10 exceed the SJVAPCD
thresholds of significance.
The proposed Project is subject to the SJVAPCD Rule 9510 (Indirect Source Rule),
which could result in substantial mitigation of NOx and associated ROG emissions.
The reductions are accomplished by the incorporation of mitigation measures into
projects and/or by the payment of an Indirect Source Rule fee for any required
reductions that have not been accomplished through Project mitigation
commitments. The current fees are $9,350 per ton of NOx. The actual calculations
will be determined and finalized by the SJVAPCD and Project applicants as
individual projects are brought forward for approval under Rule 9510.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 13
The substantial reductions in NOx (and associated ROG) and PM10 emissions
accomplished by the application of the ISR represent the best achievable
mitigation for indirect sources. However, even with the application of these
measures, emissions levels would remain above the defined thresholds of
significance. As such, implementation of the proposed Project would have a
cumulatively considerable contribution and significant and unavoidable impact
from air emissions.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with cumulative impacts to the region’s air quality, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
D. GREENHOUSE GASES AND CLIMATE CHANGE
1. IMPACT 3.7-1: POTENTIAL TO GENERATE GREENHOUSE GAS EMISSIONS, EITHER DIRECTLY OR
INDIRECTLY, THAT MAY HAVE A SIGNIFICANT IMPACT ON THE ENVIRONMENT OR POTENTIAL
TO CONFLICT WITH AN APPLICABLE PLAN, POLICY, OR REGULATION ADOPTED FOR THE
PURPOSE OF REDUCING THE EMISSIONS OF GREENHOUSE GASES.
(a) Potential Impact. The potential for the Project to generate greenhouse gas (GHG)
emissions, either directly or indirectly, that may have a significant impact on the
environment or potential to conflict with an applicable plan, policy, or regulation
adopted for the purpose of reducing the emissions of GHGs is discussed on pages 3.7-
18 through 3.7-25 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.7-1.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Short-term construction GHG
emissions are a one-time release of GHGs and are not expected to significantly
contribute to global climate change over the lifetime of the proposed Project. With
the implementation of mitigation measures, the overall annual GHG emissions
associated with the proposed Project would be reduced by 15.8 percent by the
year 2020. The mitigation measures include mobile source, area source, energy,
and water measures.
Additionally, the Project would be generally consistent with the goals, policies, and
measures of the Regional Transportation Plan (RTP)/Sustainable Communities
Strategy (SCS) and the Manteca Climate Action Plan. The Project is currently
served by the San Joaquin Regional Transit District (RTD) and would incorporate
bus turnouts and transit improvements where requested by the San Joaquin RTD,
CEQA FINDINGS
14 CEQA Findings – Griffin Park Master Plan
continuous public sidewalks and/or multi-use trails adjacent to all proposed public
streets, and paving and striping for bike lanes/paths. The Project site is assumed
for low density residential development in Appendix M of the RTP/SCS. The Project
would also comply with Strategies ENB-1, BI-1 through BI-3, and MUD-1 of the
Climate Action Plan by complying with the CALGreen requirements and providing
transit amenities on-site.
The proposed Project demonstrates that it has included feasible Best Performance
Standards (BPS) that will collectively reduce GHG emissions by 15.8 percent.
Nevertheless, the proposed Project will result in a net increase in emissions that
will contribute to global climate change. While the 15.8 percent reduction is a
reflection of the proposed Project’s intent to comply with the SJVAPCD’s efforts to
ensure that land development projects reduce GHG compared to business-as-
usual approaches, there will be an overall net increase in GHG emissions. As such,
implementation of the proposed Project would have a cumulatively considerable
contribution and significant and unavoidable impact from GHG emissions.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with cumulative impacts related to GHG emissions, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
2. IMPACT 3.7-2: CUMULATIVE IMPACT ON CLIMATE CHANGE FROM INCREASED PROJECT-
RELATED GREENHOUSE GAS EMISSIONS.
(b) Potential Impact. The potential for the Project to result in a cumulative impact on
climate change from increased Project-related greenhouse gas emissions is discussed
on pages 3.7-25 and 3.7-26 of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. Implementation of the proposed
Project will still generate GHG emissions that wouldn’t otherwise exist without the
proposed Project. Given the length of construction activities for a Project of this
size, the maximum short-term annual construction emissions of GHG associated
with development of the Project are estimated to be 3,082.1391 metric tons of
carbon dioxide equivalents (MTCO2e) (2019) with a low of 58.4330 MTCO2e (2023)
emitted. The operational emissions would be a long-term release totaling
approximately 35,772.2514 MTCO2e.
The City of Manteca must weigh the economic and social benefits of development
against the environmental impacts associated with development. The City of
Manteca’s planning efforts included targeted growth that accommodates the
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 15
economic and social needs of the community, while recognizing and seeking to
mitigate environmental impacts when growth occurs. The proposed Project has
incorporated mitigation measures that are intended to reduce emissions to the
extent feasible. The State continues to implement measures that are intended to
reduce emissions on a State-wide scale (i.e. vehicle fuel efficiency standards in
fleets, low carbon fuels, etc.) that are consistent with AB 32. These types of State-
wide measures will benefit the proposed Project (and City as a whole) in the long-
term as they come into effect; however, the City does not have the jurisdiction to
create far reaching (i.e. State-wide) measures to reduce GHG emissions.
Additionally, the proposed Project would be generally consistent with the goals
and strategies of the RTP/SCS and the Manteca Climate Action Plan. The proposed
Project would be located in an area that is currently served by the San Joaquin
RTD. The Project would incorporate bus turnouts and transit improvements where
requested by the San Joaquin RTD, continuous public sidewalks and/or multi-use
trails adjacent to all proposed public streets, and paving and striping for bike
lanes/paths. Furthermore, the Project is required to prepare and implement a
TDM plan for the non-residential portion of the Project. The TDM plan is required
to be coordinated with SCJOG’s Commute Connection Program.
On a project-by-project case, the City of Manteca evaluates a project and the
potential to impose project-specific mitigation, which has been done through this
GHG analysis. However, the Project would result in a net increase in CO2e
emissions even with mitigation measures incorporated into the Project. As such,
implementation of the proposed Project would have a cumulatively considerable
contribution and significant and unavoidable impact from GHG emissions.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with cumulative impacts related to GHG emissions, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
3. IMPACT 4.9: CUMULATIVE IMPACT ON CLIMATE CHANGE FROM INCREASED PROJECT-
RELATED GREENHOUSE GAS EMISSIONS
(b) Potential Impact. The potential for the Project to have a cumulative impact on climate
change from increased Project-related GHG emissions is discussed on pages 4.0-11 and
4.0-12 of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Effects of Mitigation and Remaining Impacts. In August 2008, the SJVAPCD
adopted its Climate Change Action Plan. The Climate Change Action Plan directed
CEQA FINDINGS
16 CEQA Findings – Griffin Park Master Plan
the SJVAPCD's Air Pollution Control Officer to develop guidance to assist APCD
staff, Valley businesses, land use agencies, and other permitting agencies in
addressing GHG emissions as part of the CEQA process. Regarding CEQA guidance,
some of the goals of the Climate Change Action Plan are to assist local land use
agencies, developers, and the public by identifying and quantifying GHG emission
reduction measures for development projects and by providing tools to streamline
evaluation of Project-specific GHG effects, and to assist Valley businesses in
complying with State law related to GHG emissions. A product of this direction to
provide CEQA guidance is the Final Staff Report – Climate Change Action Plan:
Addressing GHG Emissions Impacts, presented to the APCD Board in December
2009. A central component of the Final Staff Report is the establishment of Best
Performance Standards, which are specifications or Project design elements that
identify effective, feasible GHG emission reduction measures. Emission reductions
achieved through Best Performance Standards implementation would be pre-
quantified, thus negating the need for Project-specific quantification of GHG
emissions. For projects not implementing Best Performance Standards,
demonstration of a 29% reduction in GHG emissions from business-as-usual
conditions is required to determine that a Project would have a less than
cumulatively significant impact.
With the implementation of Mitigation Measure 3.7-1, the overall annual GHG
emissions associated with the proposed Project would be reduced by
approximately 15.8 percent by the year 2020, when compared to the business as
usual scenario. This is not consistent with applicable standards and threshold of a
29 percent reduction established by the SJVAPCD. The percentage reduction is not
consistent with the GHG reduction percentage sought by the State’s Scoping Plan.
The proposed Project would not be consistent with the reduction target set in the
Climate Change Action Plan and consistent with the Scoping Plan. As such,
implementation of the proposed Project would have a cumulatively considerable
contribution and significant and unavoidable impact from GHG emissions.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with cumulative impacts related to GHG emissions, as more fully stated
in the Statement of Overriding Considerations in Section VII, below.
E. TRANSPORTATION AND CIRCULATION
1. IMPACT 3.13-1: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE MAIN STREET / SR 120 EB RAMPS INTERSECTION.
(a) Potential Impact. The potential for the Project to have a significant impact at the Main
Street / SR 120 EB Ramps intersection is discussed on pages 3.13-22 and 3.13-23 of the
Draft EIR.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 17
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-1.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / SR 120 EB Ramps intersection
currently operates at LOS C with 21 seconds of delay in the AM peak hour and 22
seconds of delay in the PM peak hour. The addition of Project generated traffic
would cause the intersection’s operations to decline to LOS F with 82 seconds of
delay in the AM peak hour and to LOS E with 62 seconds of delay in the PM peak
hour. The following improvement would improve the delay from LOS F to LOS D in
the AM peak hour and from LOS E to LOS D in the PM peak hour: Retime and
optimize the intersection.
Caltrans would be responsible for the intersection improvement; therefore, based
on the significance criteria, this impact is considered significant and unavoidable in
the short-term until the planned improvements are completed. The Project
applicant would be required to pay their fair share fee towards the intersection
improvement, as required by Mitigation Measure 3.13-1. It is noted that this
impact would be reduced to less than significant once these improvements are in
place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with the Project impacts to the Main Street / SR 120 EB Ramps
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
2. IMPACT 3.13-2: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE MAIN STREET / ATHERTON DRIVE INTERSECTION.
(a) Potential Impact. The potential for the Project to impact the Main Street / Atherton
Drive intersection is discussed on pages 3.13-23 and 3.13-24 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-2.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Atherton Drive intersection
currently operates at LOS B with 13 seconds of delay in the AM peak hour and 17
seconds of delay in the PM peak hour. The addition of Project generated traffic
CEQA FINDINGS
18 CEQA Findings – Griffin Park Master Plan
would result in the intersection’s operations to decline to LOS E with 58 seconds of
delay in the AM peak hour and 62 seconds of delay in the PM peak hour. This
study intersection is under City of Manteca jurisdiction and the following
improvements, identified in their Public Facilities Implementation Plan (PFIP),
improve the delay from LOS E to LOS C during the AM and PM peak hours: Retime
and optimize the intersection.
The City of Manteca would be responsible for the intersection improvement;
therefore, based on the significance criteria, this impact is considered significant
and unavoidable in the short-term until the planned improvements are complete.
The Project applicant would be required to pay their fair share fee towards the
intersection improvements, as required by Mitigation Measure 3.13-2. It is noted
that this impact would be reduced to less than significant once these
improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with impacts to impacts to the Main Street / Atherton Drive
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
3. IMPACT 3.13-3: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE MAIN STREET / WOODWARD AVENUE INTERSECTION.
(a) Potential Impact. The potential for the Project to impact the Main Street / Woodward
Avenue intersection is discussed on pages 3.13-24 and 3.13-25 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-3.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Woodward Avenue
intersection currently operates at LOS C with 22 seconds of delay during the AM
peak hour and 23 seconds of delay in the PM peak hour. The addition of Project
traffic would result in the intersection’s operations to decline to LOS F with 62
seconds of delay in the AM peak hour and 60 seconds of delay in the PM peak
hour.
This study intersection is under City of Manteca jurisdiction and the following
improvements, identified in their PFIP, would improve intersection operations
from LOS F to LOS D conditions in the AM peak hour and from LOS F to LOS B
conditions in the PM peak hour: Signalize intersection; and construct one
southbound thru lane.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 19
The City of Manteca would be responsible for the intersection improvement,
acquisition of right-of-way, and construction of the southbound thru lane;
therefore, based on the significance criteria, this impact is considered significant
and unavoidable in the short-term until the planned improvements are complete.
The Project applicant would be required to pay their fair share fee towards the
intersection improvements, as required by Mitigation Measure 3.13-3. It is noted
that this impact would be reduced to less than significant once these
improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact to the Main Street
/ Woodward Avenue intersection, as more fully stated in the Statement of
Overriding Considerations in Section VII, below.
4. IMPACT 3.13-4: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE MAIN STREET / TANNEHILL DRIVE INTERSECTION.
(a) Potential Impact. The potential for the Project to cause impacts to the Main Street /
Tannehill Drive intersection is discussed on page 3.13-25 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-4.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Tannehill Drive intersection
currently operates at LOS A with seven seconds of delay in the AM peak hour and
four seconds of delay in the PM peak hour. The addition of Project generated
traffic would result in the intersection’s operations to decline to LOS F with 217
seconds of delay in the AM peak hour and 107 seconds of delay in the PM peak
hour. This study intersection is under City of Manteca jurisdiction and the
following improvement would improve intersection operations from LOS F to LOS
B conditions during the AM peak hour and from LOS F to LOS C during the PM peak
hour: Signalize the intersection.
The intersection of Main Street / Tannehill Drive is currently not included in the
City of Manteca’s PFIP; therefore, based on the significance criteria, this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
CEQA FINDINGS
20 CEQA Findings – Griffin Park Master Plan
associated the impacts at the Main Street / Tannehill Drive intersection, as more
fully stated in the Statement of Overriding Considerations in Section VII, below.
5. IMPACT 3.13-5: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE WOODWARD AVENUE / UNION ROAD INTERSECTION.
(a) Potential Impact. The potential for the Project to impact the Woodward Avenue /
Union Road intersection is discussed on page 3.13-26 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-5.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Woodward Avenue / Union Road
intersection currently operates at LOS B with 12 seconds of delay in the AM peak
hour and at LOS C with 20 seconds of delay in the PM peak hour. The addition of
Project generated traffic would result in the intersection’s operations to decline to
LOS E with 39 seconds of delay in the AM peak hour and 47 seconds of delay in the
PM peak hour. This study intersection is under City of Manteca jurisdiction and the
following improvements, identified in their PFIP, would improve intersection
operations from LOS E to LOS C conditions during both the AM peak hour and PM
peak hours: Signalize the intersection; and restripe the southbound approach to
one shared right-turn / thru lane and one left-turn lane.
The City of Manteca would be responsible for the intersection improvement;
therefore, based on the significance criteria, this impact is considered significant
and unavoidable in the short-term until the planned improvements are completed.
The Project applicant would be required to pay their fair share fee towards the
intersection improvements, as required by Mitigation Measure 3.13-5. It is noted
that this impact would be reduced to less than significant once these
improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated the impacts at the Woodward Avenue / Union Road intersection, as
more fully stated in the Statement of Overriding Considerations in Section VII,
below.
6. IMPACT 3.13-6: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT AT THE UNION ROAD / SR 120 EB RAMPS INTERSECTION.
(a) Potential Impact. The potential for the Project to impact the Union Road / SR 120 EB
Ramps intersection is discussed on pages 3.13-26 and 3.13-27 of the Draft EIR.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 21
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-6.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Union Road / SR 120 EB Ramps
intersection currently operates at LOS B with 13 seconds of delay in the AM peak
hour and at LOS C with 20 seconds of delay in the PM peak hour. The addition of
Project generated traffic would result in the intersection’s operations to decline to
LOS E with 59 seconds of delay in the AM peak hour and 65 seconds of delay in the
PM peak hour. The following mitigation measure will improve the delay from LOS
E to LOS D in both the AM and PM peak hours: Retime and optimize the
intersection.
Because this terminal intersection is retimed, the Union Road / SR 120 WB Ramps
intersection will be retimed as well. Retiming and optimization of the Union Road /
SR 120 WB Ramps intersection is consistent with plans coordinated by Caltrans
and the City of Manteca.
Caltrans would be responsible for the intersection improvement; therefore, based
on the significance criteria, this impact is considered significant and unavoidable in
the short-term until the planned improvements are completed. The Project
applicant would be required to pay their fair share fee towards the intersection
improvement, as required by Mitigation Measure 3.13-6. It is noted that this
impact would be reduced to less than significant once these improvements are in
place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts at the Union Road / SR 120 EB Ramps intersection,
as more fully stated in the Statement of Overriding Considerations in Section VII,
below.
7. IMPACT 3.13-7: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN A
SIGNIFICANT IMPACT TO FREEWAY FACILITIES.
(a) Potential Impact. The potential for the Project buildout to impact the freeway facilities
is discussed on pages 3.13-27 and 3.13-28 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-7.
CEQA FINDINGS
22 CEQA Findings – Griffin Park Master Plan
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The addition of Project generated traffic would
result in unacceptable (i.e., LOS E) AM peak hour or PM peak hour operations on
the following freeway facilities: EB SR 120 off-ramp to Main Street (PM Peak
Hour); EB SR 120 off-ramp to SR 99 (PM Peak Hour); and WB SR 120 off-ramp to
Union Road (AM Peak Hour).
Project traffic would cause in excess of a 100 vehicle-per-day increase on the
impacted SR 120 mainline, and in excess of a 1 percent increase in off-ramp
volumes at these locations. This is a potentially significant impact. The SR 120
interchange at Union Road is undergoing redesign and reconstruction by the City
of Manteca and Caltrans District 10 (Stockton, CA). This project is included in the
list of Tier 1 (Funded) projects in the adopted 2014 – 2040 SJCOG RTP / SCS.
The Tier 1 Project list also includes widening SR 120 from four to six lanes. The
effectiveness of the planned improvements was analyzed under Existing Plus
Project conditions. With this widening, all study segments would improve from
unacceptable LOS E or F to acceptable LOS D conditions or better. Due to the
uncertainty of the construction of this improvement, this impact is considered
significant and unavoidable in the short-term until the planned improvements are
completed and less than significant once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to freeway facilities, as more fully stated in the
Statement of Overriding Considerations in Section VII, below.
8. IMPACT 3.13-10: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / SR 120 RAMP TERMINAL
INTERSECTIONS.
(a) Potential Impact. The potential for the Project buildout to impact the Main Street / SR
120 ramp terminal intersections is discussed on pages 3.13-37 and 3.13-38 of the Draft
EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-1.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / SR 120 EB Ramps
intersection would operate at LOS F during both peak hours in the Cumulative No
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 23
Project scenario, while the Main Street / SR 120 WB Ramps would operate at LOS
D or better during both AM and PM peak hours. The addition of Project traffic
would exacerbate already unacceptable operations at the EB ramp terminal, while
increasing the average control delay by more than three seconds. Project traffic
would also cause the LOS at the Main Street / SR 120 WB ramp terminal
intersection to worsen to LOS E during both peak hours. These impacts are
considered potentially significant.
The following improvements, identified in the City’s PFIP, would be necessary for
acceptable operations at the SR 120 / Main Street ramp-terminal intersections
under Cumulative Plus Project conditions:
At the Main Street / SR 120 EB Ramps intersection:
o Widen Main Street to two northbound and southbound approach
lanes. Restripe the northbound approach as one thru lane and one
shared right-turn / thru lane. Restripe the southbound approach as
two thru lanes, and one left-turn lane;
o Widen EB approach and restripe as one left-turn lane, one shared left-
turn/ thru lane, and two right-turn lanes; and
o Retime the signal and optimize splits.
At the Main Street / SR 120 WB Ramps intersection:
o Widen northbound approach and restripe as two thru lanes and one
left-turn lane;
o Widen southbound approach and restripe as one right-turn lane and
two thru lanes;
o Widen the west leg to have two receiving lanes; and
o Convert the WB right-turn to a signalized right-turn.
The improvements outlined above would reduce the proposed Project’s impact to
less than significant. The improvements are identified in the City’s PFIP with
coordination and approval from Caltrans. However, the ramp terminal
intersections at this interchange are under Caltrans jurisdiction and funding for a
future Main Street interchange Project has not been secured. If full funding is not
secured, then the intersections would continue to operate at an unacceptable LOS
under Cumulative Plus Project conditions, and the Project’s contribution to this
impact would be considered significant. Nevertheless, the proposed Project would
be responsible for payment of the appropriate San Joaquin RTIF to cover their
proportionate cost of the improvements at the SR 120 / Main Street ramp-
terminal intersections.
Because implementation of these measures is beyond the control of the City of
Manteca and the Project applicant, and full improvement funding has not been
secured, the impact is considered significant and unavoidable.
CEQA FINDINGS
24 CEQA Findings – Griffin Park Master Plan
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / SR 120 ramp terminal
intersections, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
9. IMPACT 3.13-12: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / WOODWARD AVENUE
INTERSECTION.
(a) Potential Impact. The potential for the Project buildout to impact the Main Street /
Woodward Avenue intersection is discussed on pages 3.13-39 and 3.13-40 of the Draft
EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-10.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Woodward Avenue
intersection would operate at LOS F during both the AM and PM peak hours under
Cumulative No Project conditions. The addition of Project traffic would exacerbate
unacceptable operations and would increase average control delay at the
intersection by more than three seconds.
In order to achieve acceptable operations under Cumulative Plus Project
conditions, the following mitigation measures would be required:
Widen the northbound approach and restripe as one left-turn lane, one thru
lane, and one shared right-turn / thru lane;
Widen the southbound approach and restripe as two left-turn lanes, two left
lanes, and one left-turn lane;
Widen the south leg to have two receiving lanes;
Widen and restripe the EB approach as two left-turn lanes, one thru lane, and
one left-turn lane; and
Signalize intersection.
Implementation of the improvements outlined above would reduce the impact to
a less than significant level. The Woodward Avenue / Main Street intersection
would operate at LOS D during the AM and PM peak hours. However, the City of
Manteca would be responsible for the intersection improvements; therefore,
based on the significance criteria, this impact is considered significant and
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 25
unavoidable in the short-term until the planned improvements are completed, and
less than significant once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / Woodward Avenue
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
10. IMPACT 3.13-13: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
RESULT IN A SIGNIFICANT IMPACT AT THE MAIN STREET / TANNEHILL DRIVE / PROJECT
DRIVEWAY 3 INTERSECTION.
(a) Potential Impact. The potential for the Project to impact the Main Street / Tannehill
Drive / Project Driveway 3 intersection is discussed on pages 3.13-40 through 3.13-42
of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-11.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would impact the Main Street /
Tannehill Drive / Project Driveway 3 intersection, which is currently a side-street
stop controlled intersection under City of Manteca jurisdiction. The Main Street /
Tannehill Drive / Project Driveway 3 intersection is projected to operate at LOS A
during both the AM and PM peak hours with 7 seconds and 3 seconds of average
delay, respectively, for the Cumulative No Project scenario. Under Cumulative Plus
Project conditions, the Project would add a west leg that serves as Project
Driveway 3. The addition of Project traffic to this intersection would worsen its
operations to LOS F with >120 seconds of delay during both the AM and PM peak
hours. The worst movement during both peak hours would experience vastly
greater delay.
The following improvements would be necessary to provide acceptable operations
under Cumulative Plus Project conditions:
Widen the southbound approach and restripe as one left-turn lane, one thru
lane, and one shared right-turn / thru lane;
Widen the northbound approach and restripe as one left-turn lane and one
shared right-turn / thru lane; and
Signalize intersection. The EB and WB left-turn movements should be
permitted, while the northbound and southbound left-turn movements should
be protected.
CEQA FINDINGS
26 CEQA Findings – Griffin Park Master Plan
Implementation of the improvements outlined above would reduce the impact to
a less than significant level. The Main Street / Tannehill Drive / Project Driveway 3
intersection would operate at LOS B during the AM peak hour and LOS C during
the PM peak hour.
It should be noted that the intersection of Main Street / Tannehill Drive / Project
Driveway 3 is currently not included in the City of Manteca’s PFIP; therefore, based
on the significance criteria, this impact is considered significant and unavoidable in
the short-term until the planned improvements are completed, and less than
significant once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / Tannehill Drive / Project
Driveway 3 intersection, as more fully stated in the Statement of Overriding
Considerations in Section VII, below.
11. IMPACT 3.13-14: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE WOODWARD AVENUE / UNION ROAD
INTERSECTION.
(a) Potential Impact. The potential for the Project to result in a significant impact at the
Woodward Avenue / Union Road intersection is discussed on pages 3.13-42 and 3.13-
43 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-5.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The all-way stop controlled Woodward Avenue
/ Union Road intersection would operate at LOS E during the AM peak hour and
LOS F during the PM peak hour under Cumulative No Project conditions. The
addition of Project traffic would exacerbate unacceptable operations and would
meet the peak hour signal warrant during both peak hours.
The following improvements would be necessary to provide acceptable operations
under Cumulative Plus Project conditions:
Widen the southbound approach and restripe as one left-turn lane, one thru
lane, and one right-turn lane;
Restripe the WB approach as one left-turn lane and one shared left-turn / thru
lane;
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 27
Widen the northbound approach and restripe as a one left-turn lane and one
shared right-turn / thru lane;
Widen the east leg to have two receiving lanes;
Restripe the EB approach as one shared left-turn / thru lane and one shared
right-turn / thru lane; and
Signalize the intersection. Use all-way split phasing and make the WB right-
turn movement a permitted-plus-overlap movement.
Although the PFIP calls for a roundabout, implementation of the roundabout, as
designed in the PFIP, would not lower LOS to acceptable levels. Additionally, the
Cumulative Plus Project volumes would meet a signal warrant. Implementation of
the improvements outlined above would reduce the impact to a less than
significant level. The Project applicant would be required to pay their fair share fee
towards the intersection improvements, as required by Mitigation Measure 3.13-
5.
The Woodward Avenue / Union Road intersection would operate at LOS C during
the AM peak hour and LOS D during the PM peak hour. The City of Manteca would
be responsible for the intersection improvement, acquisition of right-of-way, and
construction; therefore, based on the significance criteria, this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts at the Woodward Avenue / Union Road
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
12. IMPACT 3.13-15: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE UNION ROAD / ATHERTON DRIVE INTERSECTION.
(a) Potential Impact. The potential for the Project to result in a significant impact at the
Union Road / Atherton Drive intersection is discussed on pages 3.13-43 and 3.13-44 of
the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-12.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Union Road / Atherton Drive intersection
would operate at LOS F during the AM and PM peak hours under Cumulative No
CEQA FINDINGS
28 CEQA Findings – Griffin Park Master Plan
Project conditions. The addition of Project traffic would exacerbate unacceptable
operations and would increase average control delay for intersection by more than
three seconds.
A detailed study and design of the Union Road / SR 120 interchange is currently
underway by the City of Manteca in coordination with Caltrans. Union Road /
Atherton Drive is a part of this study. The required interchange design to serve
projected Design Year AM and PM peak hour volumes is currently being
determined. With a projected construction year of 2020, Caltrans required a 20
years of acceptable level of service D conditions or better for design Year 2040 AM
and PM peak hour conditions. The current adopted improvement at the SR 120 /
Union Road interchange is a partial cloverleaf interchange. A new option being
studied is a Diverging Diamond Interchange (DDI).
With implementation of the interchange project’s partial cloverleaf alternative and
changing the signal timing to actuated-uncoordinated, the Union Road / Atherton
Road intersection would operate at LOS B during the AM peak hour and LOS C
during the PM peak hour under Cumulative Plus Project conditions. The Project
applicant would be required to pay their fair share fee towards the improvement,
as required by Mitigation Measure 3.13-12. However, the City of Manteca would
be responsible for the intersection improvement; therefore, based on the
significance criteria, this impact is considered significant and unavoidable in the
short-term until the planned improvements are completed, and less than
significant once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts at the Union Road / Atherton Drive intersection,
as more fully stated in the Statement of Overriding Considerations in Section VII,
below.
13. IMPACT 3.13-16: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE UNION ROAD / SR 120 RAMP TERMINAL
INTERSECTIONS.
(a) Potential Impact. The potential for the Project to result in significant impacts to the SR
120 / Union Road ramp-terminal intersections is discussed on page 3.13-44 of the
Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-12.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 29
(1) Mitigation and Remaining Impacts. The signalized SR 120 / Union Road ramp-
terminal intersections are projected to operate at unacceptable LOS F conditions
during the PM peak hour under Cumulative No Project conditions. The Union Road
/ SR 120 EB ramps intersection would also operate at unacceptable LOS F during
the AM peak hour. The addition of Project traffic would exacerbate both terminal
intersections of the Union Road / SR 120 interchange to LOS F during both AM and
PM peak hours, and would increase the average control delay of this signalized
intersection by more than three seconds.
A detailed study and design of the Union Road / SR 120 interchange is currently
underway. With implementation of the interchange project’s partial cloverleaf
alternative, the Union Road ramp terminal intersections would operate at LOS B or
better under Cumulative Plus Project conditions. The Project applicant would be
required to pay their fair share fee towards the improvement, as required by
Mitigation Measure 3.13-12. The Union Road ramp terminal intersections would
also operate at LOS B or better under Cumulative Plus Project conditions with the
construction of a DDI. However, Caltrans would be responsible for the intersection
improvement; therefore, based on the significance criteria, this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the SR 120 / Union Road ramp-terminal
intersections, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
14. IMPACT 3.13-17: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / MISSION RIDGE DRIVE /
INDUSTRIAL PARK DRIVE INTERSECTION.
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Main Street / Mission Ridge Drive / Industrial Park Drive signalized intersections is
discussed on pages 3.13-44 3.13-45 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-13.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Mission Ridge Drive /
Industrial Park Drive signalized intersection would operate at unacceptable LOS E
CEQA FINDINGS
30 CEQA Findings – Griffin Park Master Plan
during the PM peak hour under Cumulative No Project conditions. The addition of
Project traffic would further exacerbate operations under the Cumulative Plus
Project scenario and would increase the average control delay at the intersection
by more than three seconds.
The following improvements would be necessary to mitigate the Project’s impact
at this intersection: Add a WB left-turn lane; and optimize splits.
Implementation of the improvements outlined above would reduce the impact to
a less than significant level. The Main Street / Mission Ridge Drive / Industrial Park
Drive intersection would operate at LOS C during the AM peak hour and LOS D
during the PM peak hour. The City of Manteca would be responsible for the
intersection improvement and construction.
It should be noted that the improvements to the intersection of Main Street /
Mission Ridge Drive / Industrial Park Drive is currently not included in the City of
Manteca’s PFIP; therefore, based on the significance criteria, this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / Mission Ridge Drive /
Industrial Park Drive signalized intersection, as more fully stated in the Statement
of Overriding Considerations in Section VII, below.
15. IMPACT 3.13-18: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MANTECA ROAD / RAYMUS EXPRESSWAY
INTERSECTION.
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Raymus Expressway side-street stop intersection is discussed on
pages 3.13-46 and 3.13-47 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-14.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Manteca Road / Raymus Expressway side-
street stop intersection would operate at an acceptable LOS under Cumulative No
Project conditions. The addition of Project traffic would cause the critical
movement to worsen to LOS F for the Cumulative Plus Project scenario.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 31
The following improvement would make the impact less than significant under
Cumulative Plus Project conditions: Construct a roundabout at Manteca Road /
Raymus Expressway.
The Project proposes to build two southbound lanes on Main Street between
Tannehill Drive and Sedan Avenue. With these improvements in place, the Project
applicant would only have to pay toward the fair share cost of building a
roundabout. With the above improvement implemented, the Manteca Road /
Raymus Expressway intersection would operate at LOS A during the AM peak hour
and LOS B during the PM peak hour.
It should be noted that the intersection of Manteca Road / Raymus Expressway is
currently not included in the City of Manteca’s PFIP; therefore, based on the
significance criteria, this impact is considered significant and unavoidable in the
short-term until the planned improvements are completed, and less than
significant once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Manteca Road / Raymus Expressway side-
street stop intersection, as more fully stated in the Statement of Overriding
Considerations in Section VII, below.
16. IMPACT 3.13-19: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
RESULT IN A SIGNIFICANT IMPACT AT THE MANTECA ROAD / PROJECT DRIVEWAY 4
INTERSECTION.
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Project Driveway 4 intersection is discussed on pages 3.13-47 and
3.13-48 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-15.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would impact the Manteca Road /
Project Driveway 4 intersection, which is currently controlled by a side-street stop
and is under City of Manteca jurisdiction. The Manteca Road / Project Driveway 4
intersection would not exist under Cumulative No Project conditions. Under
Cumulative Plus Project conditions, the Project would add a west leg that serves as
Project Driveway 4. The critical movement at this intersection would operate at
LOS F with 91 seconds of delay during the PM peak hour. The following
CEQA FINDINGS
32 CEQA Findings – Griffin Park Master Plan
improvements would be necessary to provide acceptable operations under
Cumulative Plus Project conditions:
Widen the southbound approach and restripe as one left-turn lane, one thru
lane, and one shared right-turn / thru lane;
Widen the northbound approach and restripe as one left-turn lane, one thru
lane, and one shared right-turn / thru lane; and
Signalize intersection. The EB and WB left-turn movements should be
permitted, while the northbound and southbound left-turn movements should
be protected.
Implementation of these improvements would reduce the impact to a less than
significant level. The Manteca Road / Project Driveway 4 intersection would
operate at LOS D during the PM peak hour. It should be noted that the intersection
of Manteca Road / Project Driveway 4 is currently not included in the City of
Manteca’s PFIP; therefore, based on the significance criteria this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Manteca Road / Project Driveway 4
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
17. IMPACT 3.13-20: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
RESULT IN A SIGNIFICANT IMPACT AT THE MANTECA ROAD / PROJECT DRIVEWAY 5
INTERSECTION.
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Project Driveway 5 intersection is discussed on pages 3.13-48 and
3.13-49 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-16.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would cause significant impacts to
the Manteca Road / Project Driveway 5 intersection, which is currently controlled
by a side-street stop and is under City of Manteca jurisdiction. The Manteca Road /
Project Driveway 5 intersection would not exist under Cumulative No Project
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 33
conditions. Under Cumulative Plus Project conditions, the Project would add a
west leg that serves as Project Driveway 5. The critical movement at this
intersection would operate at LOS F with 54 seconds of delay during the PM peak
hour. The following improvement would be necessary to provide acceptable
operations under Cumulative Plus Project conditions:
Widen the northbound approach and restripe as one left-turn lane and one
thru lane; and
Construct a two-way left-turn lane on the north and south legs so that EB left-
turn vehicles exiting the Project site can turn into the center two-way left-turn
lane.
Implementation of these improvements would reduce the impact to a less than
significant level. The Manteca Road / Project Driveway 5 intersection would
operate at LOS D during the PM peak hour. It should be noted that the intersection
of Manteca Road / Project Driveway 5 is currently not included in the City of
Manteca’s PFIP; therefore, based on the significance criteria this impact is
considered significant and unavoidable in the short-term until the planned
improvements are completed, and less than significant once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Manteca Road / Project Driveway 5
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
18. IMPACT 3.13-21: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
RESULT IN A SIGNIFICANT IMPACT TO FREEWAY FACILITIES.
(a) Potential Impact. The potential for the Project to result in significant impacts to
freeway facilities is discussed on pages 3.13-49 and 3.13-50 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-7.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The addition of Project-generated traffic would
exacerbate unacceptable (i.e. LOS E or LOS F) peak hour operations at the
following study freeway facilities and peak hours by adding 100 vehicles per day or
more:
CEQA FINDINGS
34 CEQA Findings – Griffin Park Master Plan
WB SR 120 off-ramp at Main Street during both the AM and PM peak hours;
and
WB SR 120 on-ramp at SR 99 during both the AM and PM peak hours.
In addition, Project traffic would cause in excess of a 1 percent increase in ramp
volumes at these locations, which already operate unacceptably under Cumulative
No Project conditions. Lastly, off-ramp queueing would affect freeway operations
at the following segments:
EB SR 120 off-ramp at Union Road during the PM peak hour;
EB SR 120 off-ramp at Main Street during the PM peak hour; and
WB SR 120 off-ramp at Main Street during the PM peak hour.
The SR 120 interchange at Union Road is undergoing redesign and reconstruction
by the City of Manteca and Caltrans District 10 (Stockton, CA). This project is
included in the list of Tier 1 (Funded) projects in the adopted 2014 – 2040 SJCOG
RTP / SCS. The SR 120 interchange at Main Street has not yet secured funding,
although it is identified in the PFIP as an interchange that should receive future
improvements.
Through implementation of the SR 120 / Union Road interchange project’s partial
cloverleaf design, the EB SR 120 off-ramp queuing at Union Road would be
reduced and this impact would become less-than-significant, provided the
following: The off-ramp turn pockets have 845 feet of storage length.
Similarly, through mitigation measures involving the EB off-ramp that are
identified in Impact 3.13-10, the impact at the EB SR 120 off-ramp at Main Street
would be less than significant, provided the following:
The off-ramp turn pockets have approximately 900 feet of storage length. A
more precise estimate would be developed when the Main Street interchange
improvements and design study is undertaken.
Furthermore, mitigation measures identified in Impact 3.13-10 would not be
sufficient to prevent off-ramp queuing at the WB SR 120 off-ramps at Main Street.
The following improvement would be required to mitigate off-ramp queuing at
this intersection:
Add a left-turn pocket and restripe as one left-turn lane, one shared left-turn /
thru lane, and one right-turn lane.
In addition to this improvement, other mitigations would need to be implemented
in order to reduce the impact at the WB SR 120 off-ramp at Main Street during
both the AM and PM peak hours and at the WB SR 120 on-ramp at SR 99 during
both the AM and PM peak hours. Because freeway facilities are under Caltrans
jurisdiction, the impacts are considered significant and unavoidable.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 35
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to freeway facilities, as more fully stated in the
Statement of Overriding Considerations in Section VII, below.
19. IMPACT 4.19: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / SR 120 RAMP TERMINAL
INTERSECTIONS
(a) Potential Impact. The potential for the Project to exacerbate Levels of Service at the SR
Main Street / SR 120 EB Ramps intersection is discussed on pages 4.0-19 and 4.0-20 of
the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / SR 120 EB Ramps
intersection would operate at LOS F during both peak hours in the Cumulative No
Project scenario, while the Main Street / SR 120 WB Ramps would operate at LOS
D or better during both AM and PM peak hours. The addition of Project traffic
would exacerbate already unacceptable operations at the EB ramp terminal, while
increasing the average control delay by more than three seconds. Project traffic
would also cause the LOS at the Main Street / SR 120 WB ramp terminal
intersection to worsen to LOS E during both peak hours. These impacts are
considered potentially significant.
The improvements outlined in Section 3.13 would reduce the proposed Project’s
impact to less than significant. The improvements are identified in the City’s PFIP
with coordination and approval from Caltrans. However, the ramp terminal
intersections at this interchange are under Caltrans jurisdiction and funding for a
future Main Street interchange Project has not been secured. If full funding is not
secured, then the intersections would continue to operate at an unacceptable LOS
under Cumulative Plus Project conditions, and the Project’s contribution to this
impact would be considered significant. Nevertheless, the proposed Project would
be responsible for payment of the appropriate San Joaquin RTIF to cover their
proportionate cost of the improvements at the SR 120 / Main Street ramp-
terminal intersections.
Because implementation of these measures is beyond the control of the City of
Manteca and the Project applicant, and full improvement funding has not been
secured, the impact is considered significant and unavoidable and cumulatively
considerable.
CEQA FINDINGS
36 CEQA Findings – Griffin Park Master Plan
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts at the Main Street / SR 120 EB Ramps intersection,
as more fully stated in the Statement of Overriding Considerations in Section VII,
below.
20. IMPACT 4.21: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / WOODWARD AVENUE
INTERSECTION
(a) Potential Impact. The potential for the Project buildout to impact the Main Street /
Woodward Avenue intersection is discussed on page 4.0-20 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-10.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. PM peak hours under Cumulative No Project
conditions. The addition of Project traffic would exacerbate unacceptable
operations and would increase average control delay at the intersection by more
than three seconds.
Implementation of the improvements outlined in Section 3.13 would reduce the
impact to a less than significant level. The Woodward Avenue / Main Street
intersection would operate at LOS D during the AM and PM peak hours. However,
the City of Manteca would be responsible for the intersection improvements;
therefore, based on the significance criteria this impact is considered significant
and unavoidable and cumulatively considerable in the short-term until the
planned improvements are completed, and less than significant and less than
cumulatively considerable once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / Woodward Avenue
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 37
21. IMPACT 4.22: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN
A SIGNIFICANT IMPACT AT THE MAIN STREET / TANNEHILL DRIVE / PROJECT DRIVEWAY 3
INTERSECTION
(a) Potential Impact. The potential for the Project buildout to impact the Main Street /
Tannehill Drive / Project Driveway 3 intersection is discussed on page 4.0-21 of the
Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-11.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would impact the Main Street /
Tannehill Drive / Project Driveway 3 intersection, which is currently a side-street
stop controlled intersection under City of Manteca jurisdiction. The Main Street /
Tannehill Drive / Project Driveway 3 intersection is projected to operate at LOS A
during both the AM and PM peak hours with 7 seconds and 3 seconds of average
delay, respectively, for the Cumulative No Project scenario. Under Cumulative Plus
Project conditions, the Project would add a west leg that serves as Project
Driveway 3. The addition of Project traffic to this intersection would worsen its
operations to LOS F with >120 seconds of delay during both the AM and PM peak
hours. The worst movement during both peak hours would experience vastly
greater delay.
Implementation of the improvements outlined in Section 3.13 would reduce the
impact to a less than significant level. The Main Street / Tannehill Drive / Project
Driveway 3 intersection would operate at LOS B during the AM peak hour and LOS
C during the PM peak hour.
It should be noted that the intersection of Main Street / Tannehill Drive / Project
Driveway 3 is currently not included in the City of Manteca’s PFIP; therefore, based
on the significance criteria this impact is considered significant and unavoidable
and cumulatively considerable in the short-term until the planned improvements
are completed, and less than significant and less than cumulatively considerable
once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Main Street / Tannehill Drive / Project
Driveway 3 intersection, as more fully stated in the Statement of Overriding
Considerations in Section VII, below.
CEQA FINDINGS
38 CEQA Findings – Griffin Park Master Plan
22. IMPACT 4.23: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE WOODWARD AVENUE / UNION ROAD INTERSECTION
(a) Potential Impact. The potential for the Project buildout to impact the Woodward
Avenue / Union Road intersection is discussed on pages 4.0-21 and 4.0-22 of the Draft
EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The all-way stop controlled Woodward Avenue
/ Union Road intersection would operate at LOS E during the AM peak hour and
LOS F during the PM peak hour under Cumulative No Project conditions. The
addition of Project traffic would exacerbate unacceptable operations and would
meet the peak hour signal warrant during both peak hours.
Although the PFIP calls for a roundabout, implementation of the roundabout, as
designed in the PFIP, would not lower LOS to acceptable levels. Additionally, the
Cumulative Plus Project volumes would meet a signal warrant. Implementation of
the improvements outlined in Section 3.13 would reduce the impact to a less than
significant level. The Project applicant would be required to pay their fair share fee
towards the intersection improvements, as required by Mitigation Measure 3.13-
5.
The Woodward Avenue / Union Road intersection would operate at LOS C during
the AM peak hour and LOS D during the PM peak hour. The City of Manteca would
be responsible for the intersection improvement, acquisition of right-of-way, and
construction; therefore, based on the significance criteria this impact is considered
significant and unavoidable and cumulatively considerable in the short-term until
the planned improvements are completed, and less than significant and less than
cumulatively considerable once the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Woodward Avenue / Union Road
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
23. IMPACT 4.24: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE UNION ROAD / ATHERTON DRIVE INTERSECTION
(a) Potential Impact. The potential for the Project to exacerbate cumulatively
unacceptable levels of service at the Under Cumulative conditions, the proposed
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 39
Project would exacerbate levels of service at the Union Road / Atherton Drive
intersection is discussed on page 4.0-22 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-12.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Union Road / Atherton Drive intersection
would operate at LOS F during the AM and PM peak hours under Cumulative No
Project conditions. The addition of Project traffic would exacerbate unacceptable
operations and would increase average control delay for intersection by more than
three seconds.
A detailed study and design of the Union Road / SR 120 interchange is currently
underway. Union Road / Atherton Drive is a part of this study. With
implementation of the interchange project’s partial cloverleaf alternative and
changing the signal timing to actuated-uncoordinated, the Union Road / Atherton
Road intersection would operate at LOS B during the AM peak hour and LOS C
during the PM peak hour under Cumulative Plus Project conditions. The Project
applicant would be required to pay their fair share fee towards the improvement,
as required by Mitigation Measure 3.13-8. However, the City of Manteca would be
responsible for the intersection improvement; therefore, based on the significance
criteria this impact is considered significant and unavoidable and cumulatively
considerable in the short-term until the planned improvements are completed,
and less than significant and less than cumulatively considerable once the
improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Union Road / Atherton Drive intersection,
as more fully stated in the Statement of Overriding Considerations in Section VII,
below.
24. IMPACT 4.25: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE UNION ROAD / SR 120 RAMP TERMINAL
INTERSECTIONS
(a) Potential Impact. The potential for the Project to result in a significant impact at the SR
120 / Union Road ramp-terminal intersections is discussed on pages 4.0-22 and 4.0-23
of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
CEQA FINDINGS
40 CEQA Findings – Griffin Park Master Plan
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that: The signalized SR 120 / Union Road ramp-terminal intersections are
projected to operate at unacceptable LOS F conditions during the PM peak hour under
Cumulative No Project conditions. The Union Road / SR 120 EB ramps intersection
would also operate at unacceptable LOS F during the AM peak hour. The addition of
Project traffic would exacerbate both terminal intersections of the Union Road / SR
120 interchange to LOS F during both AM and PM peak hours, and would increase the
average control delay of this signalized intersection by more than three seconds.
A detailed study and design of the Union Road / SR 120 interchange is currently
underway. With implementation of the interchange project’s partial cloverleaf
alternative, the Union Road ramp terminal intersections would operate at LOS B or
better under Cumulative Plus Project conditions. It should be noted that the Union
Road / SR 120 interchange may be constructed as a DDI. The Union Road ramp
terminal intersections would also operate at LOS B or better under Cumulative Plus
Project conditions with the construction of a DDI. However, Caltrans would be
responsible for the intersection improvement; therefore, based on the significance
criteria this impact is considered significant and unavoidable and cumulatively
considerable in the short-term until the planned improvements are completed, and
less than significant and less than cumulatively considerable once the improvements
are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits of
the Project override any remaining significant adverse impact of the Project associated
with Project impacts at the SR 120 / Union Road ramp-terminal intersections, as more
fully stated in the Statement of Overriding Considerations in Section VII, below.
25. IMPACT 4.26: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / MISSION RIDGE DRIVE /
INDUSTRIAL PARK DRIVE
(a) Potential Impact. The potential for the Project to result in a significant impact at the
Main Street / Mission Ridge Drive / Industrial Park Drive signalized intersection is
discussed on page 4.0-23 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-13.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Main Street / Mission Ridge Drive /
Industrial Park Drive signalized intersection would operate at unacceptable LOS E
during the PM peak hour under Cumulative No Project conditions. The addition of
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 41
Project traffic would further exacerbate operations under the Cumulative Plus
Project scenario and would increase the average control delay at the intersection
by more than three seconds.
Implementation of the improvements outlined in Section 3.13 would reduce the
impact to a less than significant level. The Main Street / Mission Ridge Drive /
Industrial Park Drive intersection would operate at LOS C during the AM peak hour
and LOS D during the PM peak hour. The City of Manteca would be responsible for
the intersection improvement and construction.
It should be noted that the improvements to the intersection of Main Street /
Mission Ridge Drive / Industrial Park Drive is currently not included in the City of
Manteca’s PFIP; therefore, based on the significance criteria this impact is
considered significant and unavoidable and cumulatively considerable in the short-
term until the planned improvements are completed, and less than significant and
less than cumulatively considerable once the improvements are in place
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts at the Main Street / Mission Ridge Drive /
Industrial Park Drive signalized intersection, as more fully stated in the Statement
of Overriding Considerations in Section VII, below.
26. IMPACT 4.27: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MANTECA ROAD / RAYMUS EXPRESSWAY
INTERSECTION
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Raymus Expressway side-street stop intersection is discussed on page
4.0-24 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-14.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Manteca Road / Raymus Expressway side-
street stop intersection would operate at an acceptable LOS under Cumulative No
Project conditions. The addition of Project traffic would cause the critical
movement to worsen to LOS F for the Cumulative Plus Project scenario.
The Project proposes to build two southbound lanes on Main Street between
Tannehill Drive and Sedan Avenue. With these improvements in place, the Project
applicant would only have to pay toward the fair share cost of building a
CEQA FINDINGS
42 CEQA Findings – Griffin Park Master Plan
roundabout. With implementation of the improvement outlined in Section 3.13,
the Manteca Road / Raymus Expressway intersection would operate at LOS A
during the AM peak hour and LOS B during the PM peak hour.
It should be noted that the intersection of Manteca Road / Raymus Expressway is
currently not included in the City of Manteca’s PFIP; therefore, based on the
significance criteria this impact is considered significant and unavoidable and
cumulatively considerable in the short-term until the planned improvements are
completed, and less than significant and less than cumulatively considerable once
the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Manteca Road / Raymus Expressway side-
street stop intersection, as more fully stated in the Statement of Overriding
Considerations in Section VII, below.
27. IMPACT 4.28: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN
A SIGNIFICANT IMPACT AT THE MANTECA ROAD / PROJECT DRIVEWAY 4 INTERSECTION
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Project Driveway 4 intersection is discussed on page 4.0-24 of the
Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-15.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would impact the Manteca Road /
Project Driveway 4 intersection, which is currently controlled by a side-street stop
and is under City of Manteca jurisdiction. The Manteca Road / Project Driveway 4
intersection would not exist under Cumulative No Project conditions. Under
Cumulative Plus Project conditions, the Project would add a west leg that serves as
Project Driveway 4. The critical movement at this intersection would operate at
LOS F with 91 seconds of delay during the PM peak hour.
Implementation of the improvements outlined in Section 3.13 would reduce the
impact to a less than significant level. The Manteca Road / Project Driveway 4
intersection would operate at LOS D during the PM peak hour.
It should be noted that the intersection of Manteca Road / Project Driveway 4 is
currently not included in the City of Manteca’s PFIP; therefore, based on the
significance criteria this impact is considered significant and unavoidable and
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 43
cumulatively considerable in the short-term until the planned improvements are
completed, and less than significant and less than cumulatively considerable once
the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to the Manteca Road / Project Driveway 4
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
28. IMPACT 4.29: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN
A SIGNIFICANT IMPACT AT THE MANTECA ROAD / PROJECT DRIVEWAY 5 INTERSECTION
(a) Potential Impact. The potential for the Project to result in significant impacts to the
Manteca Road / Project Driveway 5 intersection is discussed on page 4.0-25 of the
Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-16.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. The Project would cause significant impacts to
the Manteca Road / Project Driveway 5 intersection, which is currently controlled
by a side-street stop and is under City of Manteca jurisdiction. The Manteca Road /
Project Driveway 5 intersection would not exist under Cumulative No Project
conditions. Under Cumulative Plus Project conditions, the Project would add a
west leg that serves as Project Driveway 5. The critical movement at this
intersection would operate at LOS F with 54 seconds of delay during the PM peak
hour.
Implementation of the improvements outlined in Section 3.13 would reduce the
impact to a less than significant level. The Manteca Road / Project Driveway 5
intersection would operate at LOS D during the PM peak hour.
It should be noted that the intersection of Manteca Road / Project Driveway 5 is
currently not included in the City of Manteca’s PFIP; therefore, based on the
significance criteria this impact is considered significant and unavoidable and
cumulatively considerable in the short-term until the planned improvements are
completed, and less than significant and less than cumulatively considerable once
the improvements are in place.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
CEQA FINDINGS
44 CEQA Findings – Griffin Park Master Plan
associated with Project impacts to the Manteca Road / Project Driveway 5
intersection, as more fully stated in the Statement of Overriding Considerations in
Section VII, below.
29. IMPACT 4.30: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD RESULT IN
A SIGNIFICANT IMPACT TO FREEWAY FACILITIES
(a) Potential Impact. The potential for the Project to result in significant impacts to
freeway facilities is discussed on pages 4.0-25 and 4.0-26 of the Draft EIR.
(b) Mitigation Measures. No feasible mitigation measures were identified.
(c) Findings. Based upon the EIR and the entire record before this City Council, this City
Council finds that:
(1) Mitigation and Remaining Impacts. Implementation of the proposed Project would
result in adverse impacts to freeway operations. The significance criteria specify
four instances in which the proposed Project would create significant impacts. This
section describes the impacts caused by the Project to the freeway based on the
significance criteria they satisfy.
Table 3.13-15 in Section 3.13 shows that the addition of Project traffic would not
worsen operations from LOS D or better to LOS E or F at any study segment. The
addition of Project-generated traffic would exacerbate unacceptable (i.e. LOS E or
LOS F) peak hour operations at the following study freeway facilities and peak
hours by adding 100 vehicles per day or more:
WB SR 120 off-ramp at Main Street during both the AM and PM peak hours;
and
WB SR 120 on-ramp at SR 99 during both the AM and PM peak hours.
In addition, Project traffic would cause in excess of a 1 percent increase in ramp
volumes at these locations, which already operate unacceptably under Cumulative
No Project conditions. Lastly, off-ramp queueing would affect freeway operations
at the following segments:
EB SR 120 off-ramp at Union Road during the PM peak hour;
EB SR 120 off-ramp at Main Street during the PM peak hour; and
WB SR 120 off-ramp at Main Street during the PM peak hour.
As seen in Table 3.13-15, several other freeway segments are forecast to operate
at unacceptable LOS. However, the Project will not add traffic to these sections
and would, therefore, not cause a significant impact on those sections.
As noted previously, the SR 120 interchange at Union Road is undergoing redesign
and reconstruction by the City of Manteca and Caltrans District 10 (Stockton, CA).
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 45
This project is included in the list of Tier 1 (Funded) projects in the adopted 2014 –
2040 SJCOG RTP / SCS. The SR 120 interchange at Main Street has not yet secured
funding, although it is identified in the PFIP as an interchange that should receive
future improvements.
Through implementation of the SR 120 / Union Road interchange project’s partial
cloverleaf design, the EB SR 120 off-ramp queuing at Union Road would be
reduced and this impact would become less-than-significant, provided the
following:
The off-ramp turn pockets have 845 feet of storage length.
Similarly, through mitigation measures involving the EB off-ramp that are
identified in Impact 3.13-10, the impact at the EB SR 120 off-ramp at Main Street
would be less than significant, provided the following:
The off-ramp turn pockets have approximately 900 feet of storage length. A
more precise estimate would be developed when the Main Street interchange
improvements and design study is undertaken.
Furthermore, mitigation measures identified in Impact 3.13-10 would not be
sufficient to prevent off-ramp queuing at the WB SR 120 off-ramps at Main Street.
The following improvement would be required to mitigate off-ramp queuing at
this intersection:
Add a left-turn pocket and restripe as one left-turn lane, one shared left-turn /
thru lane, and one right-turn lane.
In addition to this improvement, other mitigations would need to be implemented
in order to reduce the impact at the WB SR 120 off-ramp at Main Street during
both the AM and PM peak hours and at the WB SR 120 on-ramp at SR 99 during
both the AM and PM peak hours. Because freeway facilities are under Caltrans
jurisdiction, the impacts are considered significant and unavoidable and
cumulatively considerable.
(2) Overriding Considerations. The environmental, economic, social and other benefits
of the Project override any remaining significant adverse impact of the Project
associated with Project impacts to freeway facilities, as more fully stated in the
Statement of Overriding Considerations in Section VII, below.
CEQA FINDINGS
46 CEQA Findings – Griffin Park Master Plan
IV. FINDINGS AND RECOMMENDATIONS REGARDING SIGNIFICANT
IMPACTS WHICH ARE MITIGATED TO A LESS THAN SIGNIFICANT
LEVEL
A. AESTHETICS
1. IMPACT 3.1-3: PROJECT IMPLEMENTATION MAY RESULT IN LIGHT AND GLARE IMPACTS.
(a) Potential Impact. The potential for the Project to result in light and glare impacts is
discussed on pages 3.1-8 through 3.1-9 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.1-1.
(c) Findings. Implementation of the proposed Project would introduce new sources of
light and glare into the Project site. New sources of glare would occur primarily from
the windshields of vehicles travelling to and from the Project site and from vehicles
parked at the site. There is also the potential for reflective building materials and
windows to result in increases in daytime glare.
A detailed lighting plan has not been prepared for the proposed Project, but for the
purposes of this analysis, it has been conservatively assumed that nighttime street
lighting, outdoor recreational, and safety lighting will be installed throughout areas of
the Project site. It is assumed that security lighting will be installed within the various
parking areas throughout the commercial areas.
The Manteca Municipal Code Chapter 17 (Zoning Code) states that direct glare shall
not be permitted, and provides standards for nuisance prevention and shielding
requirements. Chapter 17.48 of the Manteca Zoning Ordinance also includes
requirements for the installation of parking lot landscaping which further limit glare
impacts.
Chapter 17.50, Lighting, of the City Zoning Ordinance contains standards and
provisions related to exterior lighting. The primary purpose of this chapter is to
regulate lighting to balance the safety and security needs for lighting with the City’s
desire to preserve dark skies and to ensure that light trespass and glare have negligible
impacts on surrounding property (especially residential) and roadways. Section
17.50.070 requires the preparation of an outdoor lighting plan as part of each Site Plan
and Design Review application for commercial and industrial properties. At a
minimum, the outdoor lighting plan shall include the following:
1. Manufacturer specifications sheets, cut sheets, and other manufacturer-provided
information for all proposed outdoor light fixtures to show fixture diagrams and
outdoor light output levels.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 47
2. The proposed location, mounting height, and aiming point of all outdoor lighting
fixtures.
3. If building elevations are proposed for illumination, drawings of all relevant
building elevations showing the fixtures, the portions of the elevations to be
illuminated, the illumination level of the elevations, and the aiming point for any
remote light fixture.
4. Photometric data including a computer-generated photometric grid showing foot-
candle readings every 10 feet within the property or site and 10 feet beyond the
property lines.
The Manteca General Plan EIR determined the impact of new sources of light and glare
can be minimized by incorporating design features and operating requirements into
new developments that limit light and glare. Policy CD-P-44 requires the use of
minimal street lighting to meet safety standards and provide direction. Policy CD-P-45
requires the use of directionally shielded lighting for all exterior lighting. Policy CD-P-
46 requires automatic shut-off or motion sensors for lighting features in newly
developed areas. The City of Manteca Zoning Ordinance has requirements for lighting
and glare to reduce the impacts of glare and light trespass.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.1-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for adverse effects from light or glare will be
mitigated to a less than significant level.
B. AGRICULTURAL RESOURCES
1. IMPACT 3.2-3: THE PROPOSED PROJECT HAS THE POTENTIAL TO RESULT IN CONFLICTS WITH
ADJACENT AGRICULTURAL LANDS OR INDIRECTLY CAUSE CONVERSION OF AGRICULTURAL
LANDS.
(a) Potential Impact. The potential for the Project to result in conflicts with adjacent
agricultural lands or indirectly cause conversion of agricultural lands is discussed on
pages 3.2-13 through 3.2-15 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.2-2.
(c) Findings. Neighboring agricultural land, including Prime Farmland and Farmland of
Statewide Importance, are located to the east, south, and west of the Project site. A
variety of residential and commercial uses would be developed on the Project site with
implementation of the proposed Project.
CEQA FINDINGS
48 CEQA Findings – Griffin Park Master Plan
The City’s General Plan anticipates that agricultural lands to the east, south, and west
of the Project site would develop with urban uses. Existing agricultural lands that are
located adjacent the Project site south of Sedan Avenue and to the west of the site
may be impacted by the increased human presence on the Project site. The City’s
Right-to-Farm Ordinance reduces the potential for conflict between existing
agricultural lands and adjacent uses. The notification procedures in the ordinance
serves to inform landowners and developers of non-agricultural uses of what the
expectations are in the area with regard to agricultural activities and to reduce
complaints.
The General Plan 2023 EIR identifies that the location or nature of the General Plan
could result in the conversion of farmland to non-agricultural use and identified
Mitigation Measure AG-3.1, which included General Plan Policies RC-P-20, RC-P-23, RC-
P-24, RC-P-25, and RC-P-27 and Implementation Measure RC-I-30. It is noted that
some of these policies are re-numbered in the General Plan as adopted. The General
Plan 2023 EIR determined that the impact would be less than significant if the
mitigation was implemented to maintain agricultural use adjacent to non-agricultural
uses (General Plan 2023 Draft EIR, pp. 4-18 and 4-19).
General Plan Policy RC-P-24 requires buffers at the interface of urban development
and farmland in order to minimize conflicts between the uses. Policy RC-P-25 requires
that the City, in approving urban development near existing agricultural lands, ensures
that such development will not constrain nearby agricultural practices.
Implementation measure RC-I-30 requires urban development next to farmland to
provide notifications in keeping with the Right-to-Farm Ordinance and include
adequate and secure fencing at the interface of urban and agricultural uses.
Most of the proposed development would be buffered from existing agricultural
operations by existing roadways including, Manteca Road on the eastern side of the
Project site and by Sedan Avenue on the southern side of the Project site. Additionally,
land opposite Manteca Road to the east of the Project site has been approved for a
residential subdivision. Further, S. Tinnin Road would provide a buffer from existing
agricultural operations west of the Project site. However, the portion of the Project
located west of S. Tinnin Road would not be buffered from nearby agricultural
operations. Similarly, the portion of the Project site located north of E. Woodward
Avenue is not currently buffered from the agricultural operations to the north of the
Project site. As discussed previously, the City’s Right to Farm Ordinance is intended to
reduce the occurrence of such conflicts between nonagricultural and agricultural land
uses within the City through requiring the transferor of any property in the City to
provide a disclosure statement describing that the City permits agricultural operations,
including those that utilize chemical fertilizers and pesticides. Compliance with the
City’s Right to Farm Ordinance would be ensured through Mitigation Measures 3.2-2.
Implementation of Mitigation Measure 3.2-2 would ensure that the Project includes
adequate measures to buffer Project uses from adjacent agricultural uses and would
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 49
reduce adverse effects on neighboring agricultural uses. Consistent with the General
Plan 2023 EIR, implementation of Mitigation Measure 3.2-2 would reduce potential
impacts to less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.2-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to result in conflicts with
adjacent agricultural lands or indirectly cause conversion of agricultural lands will be
mitigated to a less than significant level.
C. AIR QUALITY
1. IMPACT 3.3-2: PROJECT CONSTRUCTION HAS THE POTENTIAL TO CAUSE A VIOLATION OF AN
AIR QUALITY STANDARD OR CONTRIBUTE SUBSTANTIALLY TO AN EXISTING OR PROJECTED AIR
QUALITY VIOLATION.
(a) Potential Impact. The potential for the Project to cause a violation of an air quality
standard or contribute substantially to an existing or projected air quality violation is
discussed on pages 3.3-23 through 3.3-27 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.3-4 through 3.3-8.
(c) Findings. The SJVAPCD has established construction related emissions thresholds of
significance as follows: 10 tons per year of ROG, 10 tons per year of NOx, or 15 tons
per year of PM10 or P2.5. If the proposed Project’s emissions will exceed the SJVAPCD’s
threshold of significance for construction-generated emissions, the proposed Project
will have a significant impact on air quality and all feasible mitigation are required to
be implemented to reduce emissions. Annual emissions of ROG, PM10, and PM2.5 will
not exceed the SJVAPCD thresholds of significance in any given year. However, annual
emissions of NOx will exceed the thresholds of significance in three of the seven
construction years. Nevertheless, regardless of emission quantities, the SJVAPCD
requires construction related mitigation in accordance with their rules and regulations.
Implementation of Mitigation Measures 3.3-4 through 3.3-8 of the Draft EIR will
ensure that the proposed Project would reduce construction related emissions to the
extent possible. Mitigation Measure 3.3-4 requires preparation and submittal of a Dust
Control Plan, Mitigation Measure 3.3-5 requires implementation of dust control
measures, Mitigation Measure 3.3-6 requires implementation of dust control practices
(per SJVAPCD’s Guide for Assessing and Mitigating Air Quality Impacts (GAMAQI),
Mitigation Measure 3.3-7 requires the use of low volatile organic compound (VOC)
architectural coatings, and Mitigation Measure 3.3-8 requires compliance with
SJVAPCD Rule 4641.
CEQA FINDINGS
50 CEQA Findings – Griffin Park Master Plan
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.3-4
through 3.3-8 are appropriate changes or alterations that have been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
before this City Council, this City Council finds that the potential for the Project to
cause a violation of an air quality standard or contribute substantially to an existing or
projected air quality violation will be mitigated to a less than significant level.
D. BIOLOGICAL RESOURCES
1. IMPACT 3.4-1: THE PROPOSED PROJECT HAS THE POTENTIAL TO HAVE A DIRECT OR INDIRECT
EFFECT ON SPECIAL-STATUS INVERTEBRATE SPECIES.
(a) Potential Impact. The potential for the Project to have a direct or indirect effect on
special-status invertebrate species is discussed on pages 3.4-18 through 3.4-19 of the
Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.4-1.
(c) Findings. There are three special-status invertebrates that are documented within a
10-mile radius of the Project site, including: Molestan blister beetle (Lytta molesta),
Sacramento anthicid beetle (Anthicus sacramento), and valley elderberry longhorn
beetle (Desmocerus californicus dimorphus). The valley elderberry longhorn beetle,
vernal pool fairy shrimp, and vernal pool tadpole shrimp are covered species under the
SJMCP. Field surveys and habitat evaluations for the entire Project site were
performed on March 4, May 10, and June 28, 2016.
Essential habitat for Molestan blister beetle and Sacramento anthicid beetle is not
present on the Project site.
Valley elderberry longhorn beetle (VELB) is a federal threatened insect, proposed for
delisting. Elderberry (Sambucus sp.), which is a primary host species for valley
elderberry longhorn beetle (VELB), is not present within the Project site. VELB is not
anticipated to be directly affected by any individual phase or component of the
proposed Project because there are no blue elderberry shrubs in the Project site.
Nevertheless, VELB is a covered species under the SJMSCP.
Vernal pool fairy shrimp (VPFS) is a federal threatened invertebrate found in the
Central Valley, central and south Coast Ranges from Tehama County to Santa Barbara
County. They are commonly found in vernal pools and in sandstone rock outcrop
pools. VPFS is not anticipated to be directly affected by any individual phase or
component of the proposed Project because there in not appropriate vernal pool
habitat on the Project site.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 51
Vernal pool tadpole shrimp (VPTS) is a federal endangered invertebrate found in
vernal pools and stock ponds from Shasta county south to Merced county. VPTS is not
anticipated to be directly affected by any individual phase or component of the
proposed Project because there in not appropriate vernal pool habitat on the Project
site.
No special-status invertebrates were observed within the Project site or offsite
improvement corridors during field surveys and none are expected to be affected by
the proposed Project. Therefore, the proposed Project would have a less than
significant impact on special-status invertebrate species. While there are no special
status invertebrate species that are anticipated to be affected by the proposed
Project, participation in the SJMSCP will provide the coverage for the incidental take of
a species if it were to occur. Mitigation measure 3.4-1 will ensure coverage under the
SJMSCP.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.4-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to have a direct or indirect
effect on special-status invertebrate species will be mitigated to a less than significant
level.
2. IMPACT 3.4-3: THE PROPOSED PROJECT HAS THE POTENTIAL TO HAVE A DIRECT OR INDIRECT
EFFECT ON SPECIAL-STATUS BIRD SPECIES.
(a) Potential Impact. The potential for the Project to have a direct or indirect effect on
special-status bird species is discussed on pages 3.4-20 through 3.4-21 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.4-1.
(c) Findings. Special-status birds that are documented in the CNDDB within a ten-mile
radius of the Project site include: Aleutian goose (Branta canadensis leucopareia),
Yellow-headed blackbird (Xanthocephalus xanthocephalus), Swainson’s hawk (Buteo
swainsoni), song sparrow (Modesto population) (Melospiza melodia), Merlin (Falco
columbarius), western yellow-billed cuckoo (Coccyzus americanus occidentalis),
burrowing owl (Athene cunicularia), Tricolored blackbird (Agelaius tricolor). In
addition, the bald eagle (Haliaeetus leucocephalus), black rail (Laterallus jamaicensis),
fox sparrow (Passerella iliaca), least bittern (Ixobrychus exilis), lesser yellowlegs (Tringa
flavipes), Lewis’s woodpecker (Melanerpes lewis), loggerhead shrike (Lanius
ludovicianus), long-billed curlew (Numenius americanus), marbeled godwit (Limosa
fedoa), mountain plover (Charadrius montanus), Nuttalls woodpecker (Picoides
nuttallii), oak titmouse (Baeolophus inornatus), peregrine falcon (Falco peregrinus),
CEQA FINDINGS
52 CEQA Findings – Griffin Park Master Plan
short-eared owl (Asio flammeus), western grebe (Aechmophorus occidentalis),
Williamson’s sapsucker (Sphyrapicus thyroideus), and yellow-billed magpie (Pica
nuttalli) are documented in the USFWS IPAC database as potentially occurring within
the region. The Project site may provide suitable foraging habitat for a variety of
potentially occurring special-status birds, including those listed above. Potential
nesting habitat is present in a variety of trees located within the Project site and in the
vicinity. There is also the potential for other special-status birds that do not nest in this
region and represent migrants or winter visitants to forage on the Project site.
Year-round birds: Special-status birds that can be present in the region throughout the
year include: bald eagle (Haliaeetus leucocephalus), black rail (Laterallus jamaicensis),
burrowing owl (Athene cunicularia), loggerhead shrike (Lanius ludovicianus), Nuttalls
woodpecker (Picoides nuttallii), oak titmouse (Baeolophus inornatus), song sparrow
(Modesto population) (Melospiza melodia), tricolored blackbird (Agelaius tricolor),
Williamson’s sapsucker (Sphyrapicus thyroideus), yellow-billed magpie (Pica nuttalli),
among others. Some of these species are migratory, but also reside year-round in
California.
Summering Birds: Special-status birds that are only present in the region in the spring
and summer months include: Aleutian goose (Branta canadensis leucopareia), least
bittern (Ixobrychus exilis), Swainson’s hawk (Buteo swainsoni), western yellow-billed
cuckoo (Coccyzus americanus occidentalis), and yellow-billed magpie (Pica nuttalli).
Overwintering Birds: Special-status birds that are only present in the region in the fall
and winter months include: fox sparrow (Passerella iliaca), lesser yellowlegs (Tringa
flavipes), Lewis’s woodpecker (Melanerpes lewis), long-billed curlew (Numenius
americanus), marbeled godwit (Limosa fedoa), merlin (Falco columbarius), mountain
plover (Charadrius montanus), peregrine falcon (Falco peregrinus), short-eared owl
(Asio flammeus), and western grebe (Aechmophorus occidentalis).
Nesting Raptors (Birds of Prey): All raptors (owls, hawks, eagles, falcons), including
species and their nests, are protected from take pursuant to the Fish and Game Code
of California Section 3503.5, and the federal Migratory Bird Treaty Act, among other
federal and State regulations. Special-status raptors that are known to occur in the
region include: bald eagle (Haliaeetus leucocephalus), burrowing owl (Athene
cunicularia), Cooper's hawk (Accipiter cooperii), ferruginous hawk (Buteo rega), golden
eagle (Aquila chrysaetos), great horned owl (Bubo virginianus), prairie falcon (Falco
mexicanus), red-tailed hawk (Buteo jamaicensis), short-eared owl (Asio flammeus),
Swainson's hawk (Buteo swainsoni), and white-tailed kite (Elanus leucurus), among
others.
Analysis: Powerlines and trees located in the region represent potentially suitable
nesting habitat for a variety of special-status birds. Additionally, the agricultural land
represents potentially suitable nesting habitat for the ground-nesting birds. In general,
most nesting occurs from late February and early March through late July and early
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 53
August, depending on various environmental conditions. The CNDDB currently
contains nesting records for Swainson's hawk and burrowing owl in the vicinity of the
Project site. In addition to the species described above, common raptors such as
among others, may nest in or adjacent to the Project site.
New sources of noise and light during the construction and operational phases of the
Project could adversely affect nesters if they located adjacent to the Project site in any
given year. Additionally, the proposed Project would eliminate the agricultural areas
on the Project site, which serve as potential foraging habitat for birds throughout the
year. Mitigation Measure 3.4-1 requires participation in the SJMSCP. As part of the
SJMSCP, SJCOG requires preconstruction surveys for projects that occur during the
avian breeding season (March 1 – August 31). When active nests are identified, the
biologists develop buffer zones around the active nests as deemed appropriate until
the young have fledged. SJCOG also uses the fees to purchase habitat as compensation
for the loss of foraging habitat. Implementation of the proposed Project, with
Mitigation Measure 3.4-1, would ensure that potential impacts to special status birds
are reduced to a less than significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.4-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to have a direct or indirect
effect on special-status bird species will be mitigated to a less than significant level.
3. IMPACT 3.4-10: THE PROPOSED PROJECT HAS THE POTENTIAL TO CONFLICT WITH LOCAL
POLICIES OR ORDINANCES PROTECTING BIOLOGICAL RESOURCES, SUCH AS A TREE
PRESERVATION POLICY OR ORDINANCE.
(a) Potential Impact. The potential for the Project to conflict with any local policies or
ordinances protecting biological resources, such as a tree preservation policy or
ordinance is discussed on pages 3.4-24 through 3.4-26 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.4-2.
(c) Findings. The Resource Conservation Element of the General Plan establishes
numerous policies and implementation measures related to biological resources as
listed below:
Conservation Element Policies
RC-P-31. Minimize impact of new development on native vegetation and wildlife.
CEQA FINDINGS
54 CEQA Findings – Griffin Park Master Plan
Consistent: This EIR includes an in depth analysis of impacts for sensitive plants and
wildlife, as well as habitat. Where impacts are identified, mitigation measures are
presented to minimize, avoid, or compensate to the extent practicable.
RC-P-33. Discourage the premature removal of orchard trees in advance of
development, and discourage the removal of other existing healthy mature trees, both
native and introduced.
Consistent: The proposed Project will require the removal of orchard trees in order to
develop the Project site. Neither the City, nor the applicants have any intention on
removing these orchard trees in advance of development. Additionally, the Project site
contains numerous ornamental landscaping and shade trees in association with the
existing residences, farm structures, and roadways. The proposed Project is a Master
Plan and detailed tentative maps and site plans are not yet available. It may be
possible for specific trees to be incorporated into the final design of the development
once the more detailed engineering effort begins. Neither the City, nor the applicants
have any intention on removing these trees in advance of development. Nevertheless,
the City would review Project improvement plans, grading plans, and building plans
and apply the Manteca Municipal Code (17.19.060) as applicable once these Project
details are known.
RC-P-34. Protect special status species and other species that are sensitive to human
activities.
Consistent: This EIR includes an in depth analysis of impacts for sensitive plants
and wildlife, as well as habitat. Where impacts are identified, mitigation measures
are presented to minimize, avoid, or compensate to the extent practicable.
RC-P-35. Allow contiguous habitat areas.
Consistent: Habitat areas in the vicinity of the Project site include largely
agricultural plant communities which provide habitat for a variety of biological
resources in the region. Agricultural areas occur throughout the region and are
generally flat and well drained, and as a result are well suited for many crops.
Alfalfa fields, hay, row crops, orchards, dominate the agricultural areas in the
vicinity. The proposed Project does not require contiguous habitat areas to change
or convert to another use.
RC-P-36. Consider the development of new drainage channels planted with native
vegetation, which would provide habitat as well as drainage.
Consistent: The Project does not include new drainage channels.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 55
Municipal Code
The Manteca Municipal Code calls for the avoidance of heritage trees as defined under
section 17.61.030. Heritage trees are any natural woody plant rooted in the ground
and having a diameter of 30 inches or more when measured two feet above the
ground. There are no heritage trees on the Project site.
Section 17.19.060 calls for the protection of all existing trees having a diameter of six
inches or more when measured 4½ feet above the ground. The City planning
department must be notified of planned construction or grade changes within the
proximity of existing mature trees. Existing trees must be protected from construction
equipment, machinery, grade changes, and excavation for utilities, paving, and
footers. Replacement of existing trees is subject to approval from the planning director
and must be with a minimum 24-inch box tree of compatible species for the
development site and be consistent with Section 17.19.030.
Section 12.08.070 of the municipal code prohibits cutting, pruning, removing, injuring,
or interference with any tree, shrub, or plant upon or in any street tree area or other
public place in the City without prior approval from the superintendent. The City is
authorized to grant such permission at their discretion and where necessary. Except
for utility companies, as provided in Section 12.08.080, no such permission shall be
valid for a longer period than 30 days after its issuance.
The Project site contains numerous ornamental landscaping and shade trees in
association with the existing residences, farm structures, and roadways. The proposed
Project is a Master Plan and detailed tentative maps and site plans are not yet
available. It may be possible for specific trees to be incorporated into the final design
of the development once the more detailed engineering effort begins. Nevertheless,
any trees that cannot remain in the final design must be replaced in accordance with
the Manteca Municipal Code (17.19.060) if deemed applicable at the time of removal.
Mitigation Measure 3.4-2 would require compliance with the Manteca Municipal Code
for removal and replacement of trees. With the implementation of this mitigation
measure, the proposed Project would have a less than significant impact relative to
this topic.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.4-2 is an
appropriate changes or alterations that have been required in, or incorporated into,
the Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to conflict with any local policies or ordinances
protecting biological resources, such as a tree preservation policy or ordinance will be
mitigated to a less than significant level.
CEQA FINDINGS
56 CEQA Findings – Griffin Park Master Plan
E. CULTURAL RESOURCES
1. IMPACT 3.5-1: PROJECT IMPLEMENTATION HAS THE POTENTIAL TO CAUSE A SUBSTANTIAL
ADVERSE CHANGE TO A SIGNIFICANT HISTORICAL RESOURCE, AS DEFINED IN CEQA
GUIDELINES §15064.5, OR A SIGNIFICANT TRIBAL CULTURAL RESOURCE, AS DEFINED IN
PUBLIC RESOURCES CODE §21074.
(a) Potential Impact. The potential for the Project to have an impact on significant
historical resources or significant tribal cultural resources is discussed on pages 3.5-9
and 3.5-10 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.5-1.
(c) Findings. The Project site is located in an area known to have historical resources. The
field surveys revealed three building complexes that are more than 50 years in age.
These were recorded, but were not deemed to be significant. However, as with most
projects in the region that involve ground-disturbing activities, there is the potential
for discovery of a previously unknown historical resource or tribal cultural resource.
Mitigation Measure 3.5-1 requires specific standards in the event of the discovery of a
previously unknown resource and would ensure that this potential impact is less than
significant.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.5-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to cause an adverse impact on historical
resources or tribal cultural resources will be mitigated to a less than significant level.
2. IMPACT 3.5-2: PROJECT IMPLEMENTATION HAS THE POTENTIAL TO CAUSE A SUBSTANTIAL
ADVERSE CHANGE TO A SIGNIFICANT ARCHAEOLOGICAL RESOURCE, AS DEFINED IN CEQA
GUIDELINES §15064.5
(a) Potential Impact. The potential for the Project to have an impact on significant
archaeological resources is discussed on page 3.5-10 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.5-1.
(c) Findings. The Project site is located in an area known to have cultural resources.
Although three building complexes are more than 50 years in age have been recorded
along S. Main Street / Manteca Road, the field surveys did not reveal a significant
archeological resource or site on the Project site. However, as with most projects in
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 57
the region that involve ground-disturbing activities, there is the potential for discovery
of a previously unknown cultural resource or human remains. Implementation of the
previously described Mitigation Measure 3.5-1 requires specific standards in the event
of the discovery of a previously unknown resource and would ensure that this
potential impact is less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.5-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to cause an adverse impact on archaeological
resources will be mitigated to a less than significant level.
3. IMPACT 3.5-3: PROJECT IMPLEMENTATION HAS THE POTENTIAL TO DIRECTLY OR INDIRECTLY
DESTROY A UNIQUE PALEONTOLOGICAL RESOURCE.
(a) Potential Impact. The potential for the Project to have an impact on significant
paleontological resources is discussed on page 3.5-9 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation measure
3.5-2.
(c) Findings. The field surveys by did not reveal any surface evidence of paleontological
resources on the Project site. The Project site is not expected to contain subsurface
paleontological resources, although it is possible.
Damage to or destruction of a paleontological resource would be considered a
potentially significant impact under local, state, or federal criteria. Implementation of
the Mitigation Measure 3.5-2 would ensure steps would be taken to reduce impacts to
paleontological resources in the event that they are discovered during construction.
This mitigation measure would reduce this impact to a less than significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.5-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to cause an adverse impact on paleontological
resources will be mitigated to a less than significant level.
4. IMPACT 3.5-4: PROJECT IMPLEMENTATION HAS THE POTENTIAL TO DISTURB HUMAN
REMAINS, INCLUDING THOSE INTERRED OUTSIDE OF FORMAL CEMETERIES
(a) Potential Impact. The potential for the Project to have an impact on human remains is
discussed on page 3.5-11 of the Draft EIR.
CEQA FINDINGS
58 CEQA Findings – Griffin Park Master Plan
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.5-3.
(c) Findings. Indications are that humans have occupied San Joaquin County for over
10,000 years and it is not always possible to predict where human remains may occur
outside of formal burials. Therefore, excavation and construction activities, regardless
of depth, may yield human remains that may not be interred in marked, formal
burials.
Under CEQA, human remains are protected under the definition of archaeological
materials as being “any evidence of human activity.” Additionally, Public Resources
Code Section 5097 has specific stop-work and notification procedures to follow in the
event that human remains are inadvertently discovered during Project
implementation.
While no human remains were found during field surveys, implementation of the
Mitigation Measure 3.5-3 would ensure that all construction activities that
inadvertently discover human remains implement state required consultation
methods to determine the disposition and historical significance of any discovered
human remains. This mitigation measure would reduce this impact to a less than
significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.5-3 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to cause an adverse impact on human remains
will be mitigated to a less than significant level.
F. GEOLOGY AND SOILS
1. IMPACT 3.6-2: IMPLEMENTATION AND CONSTRUCTION OF THE PROPOSED PROJECT MAY
RESULT IN SUBSTANTIAL SOIL EROSION OR THE LOSS OF TOPSOIL
(a) Potential Impact. The potential for the Project to result in substantial soil erosion or
the loss of topsoil is discussed on pages 3.6-13 through 3.4-15 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.6-1.
(c) Findings. According to the United States Environmental Protection Agency, polluted
stormwater runoff is a leading cause of impairment to the nearly 40 percent of
surveyed U.S. water bodies which do not meet water quality standards. Over land or
via storm sewer systems, polluted runoff is discharged, often untreated, directly into
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 59
local water bodies. Soil erosion and the loss of topsoil is one of the most common
sources of polluted stormwater runoff during construction activities. When left
uncontrolled, storm water runoff can erode soil and cause sedimentation in
waterways, which collectively result in the destruction of fish, wildlife, and aquatic life
habitats; a loss in aesthetic value; and threats to public health due to contaminated
food, drinking water supplies, and recreational waterways.
Mandated by Congress under the Clean Water Act, the NPDES Stormwater Program is
a comprehensive two-phased national program for addressing the non-agricultural
sources of stormwater discharges which adversely affect the quality of our nation's
waters. The program uses the National Pollutant Discharge Elimination System
(NPDES) permitting mechanism to require the implementation of controls designed to
prevent harmful pollutants, including soil erosion, from being washed by stormwater
runoff into local water bodies. The construction activities for the proposed Project
would be governed by the General Permit 2009-0009-DWQ (amended by 2010-0014-
DWQ & 2012-0006-DWQ), which states:
“…Particular attention must be paid to large, mass graded sites where the
potential for soil exposure to the erosive effects of rainfall and wind is great and
where there is potential for significant sediment discharge from the site to surface
waters. Until permanent vegetation is established, soil cover is the most cost-
effective and expeditious method to protect soil particles from detachment and
transport by rainfall. Temporary soil stabilization can be the single most important
factor in reducing erosion at construction sites. The discharger is required to
consider measures such as: covering disturbed areas with mulch, temporary
seeding, soil stabilizers, binders, fiber rolls or blankets, temporary vegetation, and
permanent seeding. These erosion control measures are only examples of what
should be considered and should not preclude new or innovative approaches
currently available or being developed. Erosion control BMPs should be the primary
means of preventing storm water contamination, and sediment control techniques
should be used to capture any soil that becomes eroded…”
General Permit 2009-0009-DWQ (amended by 2010-0014-DWQ & 2012-0006-DWQ)
further states that:
“Sediment control BMPs should be the secondary means of preventing storm water
contamination. When erosion control techniques are ineffective, sediment control
techniques should be used to capture any soil that becomes eroded. The discharger
is required to consider perimeter control measures such as: installing silt fences or
placing straw wattles below slopes. These sediment control measures are only
examples of what should be considered and should not preclude new or innovative
approaches currently available or being developed…Inappropriate management of
run-on and runoff can result in excessive physical impacts to receiving waters from
sediment and increased flows. The discharger is required to manage all run-on and
runoff from a project site. Examples include: installing berms and other temporary
CEQA FINDINGS
60 CEQA Findings – Griffin Park Master Plan
run-on and runoff diversions…All measures must be periodically inspected,
maintained and repaired to ensure that receiving water quality is protected.
Frequent inspections coupled with thorough documentation and timely repair is
necessary to ensure that all measures are functioning as intended…”
To ensure that construction activities are covered under General Permit 2009-0009-
DWQ (amended by 2010-0014-DWQ & 2012-0006-DWQ), projects in California must
prepare a Stormwater Pollution Prevention Plan (SWPPP) containing Best
Management Practices (BMPs) to reduce erosion and sediments to meet water quality
standards. Such BMPs may include: temporary erosion control measures such as silt
fences, staked straw bales/wattles, silt/sediment basins and traps, check dams,
geofabric, sandbag dikes, and temporary revegetation or other ground cover. The
BMPs and overall SWPPP is reviewed by the Regional Water Quality Control Board as
part of the permitting process. The SWPPP, once approved, is kept on site and
implemented during construction activities and must be made available upon request
to representatives of the RWQCB and/or the lead agency.
The Custom Soils Report identified the erosion potential for the soils in the Project
site. This report summarizes those soil attributes used by the Revised Universal Soil
Loss Equation Version 2 (RUSLE2) for the map units in the selected area. Soil property
data for each map unit component includes the hydrologic soil group, erosion factors
Kf for the surface horizon, erosion factor T, and the representative percentage of sand,
silt, and clay in the surface horizon.
Erosion factor K indicates the susceptibility of a soil to sheet and rill erosion by water.
Values of K range from 0.02 to 0.69. Other factors being equal, the higher the value,
the more susceptible the soil is to sheet and rill erosion by water. Within the Project
site, the erosion factor Kf varies from 0.02 to 0.28, which is considered a low to
moderate potential for erosion. Furthermore, because the Project site is essentially
flat, the erosion potential is considered slight. Regardless of the potential for erosion,
there is always the potential for human caused erosion associated with construction
activities or through the operational phase of a project. Grading, excavation, removal
of vegetation cover, and loading activities associated with construction activities
temporarily expose soils and increase the potential for soil erosion and sedimentation
during rail events. Construction activities can also result in soil compaction and wind
erosion effects that can adversely affect soils and reduce the revegetation potential at
construction sites and staging areas.
In accordance with the NPDES Stormwater Program, Mitigation Measure 3.6-1
requires an approved SWPPP designed to control erosion and the loss of topsoil to the
extent practicable using BMPs that the RWQCB has deemed effective in controlling
erosion, sedimentation, runoff during construction activities. The RWQCB has stated
that these erosion control measures are only examples of what should be considered
and should not preclude new or innovative approaches currently available or being
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 61
developed. The specific controls are subject to the review and approval by the RWQCB
and are existing regulatory requirements. Implementation of the proposed Project
would have a less than significant impact relative to this topic.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.6-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to result in substantial soil erosion or the loss
of topsoil will be mitigated to a less than significant level.
2. IMPACT 3.6-3: THE PROPOSED PROJECT HAS THE POTENTIAL TO BE LOCATED ON A GEOLOGIC
UNIT OR SOIL THAT IS UNSTABLE, OR THAT WOULD BECOME UNSTABLE AS A RESULT OF
PROJECT IMPLEMENTATION, AND POTENTIALLY RESULT IN LANDSLIDE, LATERAL SPREADING,
SUBSIDENCE, LIQUEFACTION OR COLLAPSE.
(a) Potential Impact. The potential to be located on a geologic unit or soil that is unstable,
or that would become unstable as a result of Project implementation, and potentially
result in landslide, lateral spreading, subsidence, liquefaction or collapse is discussed
on pages 3.6-15 through 3.6-17 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.6-2.
(c) Findings. Soil liquefaction results from loss of strength during cyclic loading, such as
imposed by earthquakes. Soils most susceptible to liquefaction are clean, loose,
saturated, and uniformly graded, fine-grained sands. Soil data from the NRCS Web Soil
Survey (NRCS 2015) suggests that the potential for liquefaction is moderate given that
the soils are high in sand and the water table is moderately high.
The City of Manteca General Plan Draft EIR has indicated that “Given that there is a
relatively high water table, liquefaction could be a significant impact within the Study
Area.” The General Plan Draft EIR indicates that with the implementation of goals,
policies, and implementation measures from the 2023 General Plan Safety Element
the potentially significant impact would be reduced to a less than significant impact.
Lateral Spreading
Lateral spreading typically results when ground shaking moves soil toward an area
where the soil integrity is weak or unsupported, and it typically occurs on the surface
of a slope, although it does not occur strictly on steep slopes. Oftentimes, lateral
spreading is also directly associated with areas of liquefaction. Since the potential for
liquefaction is moderate to high, the potential for lateral spreading is present. The
General Plan Draft EIR indicates that with the implementation of goals, policies, and
CEQA FINDINGS
62 CEQA Findings – Griffin Park Master Plan
implementation measures from the 2023 General Plan Safety Element the potentially
significant impact would be reduced to a less than significant impact.
Landslides
Landslides include rockfalls, deep slope failure, and shallow slope failure. Factors such
as the geological conditions, drainage, slope, vegetation, and others directly affect the
potential for landslides. One of the most common causes of landslides is construction
activity that is associated with road building (i.e. cut and fill). The Project site is
essentially flat; therefore, the potential for a landslide in the Project site is non-
existent.
Collapsible Soils
Collapsible soils undergo a rearrangement of their grains and a loss of cementation,
resulting in substantial and rapid settlement under relatively low loads. Collapsible
soils occur predominantly at the base of mountain ranges, where Holocene-age
alluvial fan and wash sediments have been deposited during rapid run-off events.
Differential settlement of structures typically occurs when heavily irrigated landscape
areas are near a building foundation. Examples of common problems associated with
collapsible soils include tilting floors, cracking or separation in structures, sagging
floors, and nonfunctional windows and doors. Collapsible soils have not been
identified in the Manteca General Plan as an issue in the Manteca area. However, in
areas subject to potential liquefaction, the potential for liquefaction induced
settlement is present. The General Plan Draft EIR indicates that with the
implementation of goals, policies, and implementation measures from the 2023
General Plan Safety Element the potentially significant impacts relating to liquefaction
would be reduced to a less than significant impact.
Subsidence
Land subsidence is the gradual settling or sinking of an area with little or no horizontal
motion due to changes taking place underground. It is a natural process, although it
can also occur (and is greatly accelerated) as a result of human activities. Common
causes of land subsidence from human activity include: pumping water, oil, and gas
from underground reservoirs; dissolution of limestone aquifers (sinkholes); collapse of
underground mines; drainage of organic soils; and initial wetting of dry soils.
Subsidence has not been identified in the Manteca General Plan.
Conclusion
The Project site does not have a significant risk of becoming unstable as a result
landslide, subsidence, or soil collapse. There is a potential for liquefaction, liquefaction
induced settlement, and lateral spreading. However, through the implementation of
Mitigation Measure 3.6-2, which requires a final geotechnical evaluation of the soils,
the proposed Project would have a less than significant impact relative to this topic.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 63
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.6-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to be located on a geologic unit or soil that is
unstable, or that would become unstable as a result of Project implementation, and
potentially result in landslide, lateral spreading, subsidence, liquefaction or collapse
will be mitigated to a less than significant level.
3. IMPACT 3.6-4: POTENTIAL FOR EXPANSIVE SOILS TO CREATE SUBSTANTIAL RISKS TO LIFE OR
PROPERTY.
(a) Potential Impact. The potential for expansive soils to create substantial risks to life or
property is discussed on pages 3.6-17 and 3.6-18 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: implementation of
Mitigation Measure 3.6-2.
(c) Findings. Expansive soils are those that undergo volume changes as moisture content
fluctuates; swelling substantially when wet or shrinking when dry. Soil expansion can
damage structures by cracking foundations, causing settlement and distorting
structural elements. Expansion is a typical characteristic of certain varieties of clay-
type soils. Expansive soils shrink and swell in volume during changes in moisture
content, such as a result of seasonal rain events, and can cause damage to
foundations, concrete slabs, roadway improvements, and pavement sections.
According to the NRCS Web Soil Survey, the soils in the Project site have a low shrink-
swell potential. The NRCS Web Soil Survey indicated that near surface soils within the
Project site have low plasticity, and the expansion potential of the soils would respond
to fluctuations in moisture content. Figure 3.6-2 provides a map of the shrink-swell
potential of the soils at the Project site and in the vicinity.
The California Building Code Title 24, Part 2, Chapter 18, Section 1803.1.1.2 requires
specific geotechnical evaluation when a preliminary geotechnical evaluation
determines that expansive or other special soil conditions are present, which, if not
corrected, would lead to structural defects. The City of Manteca also requires a final
geotechnical evaluation to be performed at a design-level to ensure that the
foundations, structures, roadway sections, sidewalks, and other improvements can
accommodate the specific soils, including expansive soils, at those locations.
Mitigation Measure 3.6-2, presented above, provides the requirement for a final
geotechnical evaluation in accordance with the standards and requirements outlined
in the California Building Code, Title 24, Part 2, Chapter 16, Chapter 17, and Chapter
18, which addresses structural design, tests and inspections, and soils and foundation
standards. The final geotechnical evaluation would include design recommendations
CEQA FINDINGS
64 CEQA Findings – Griffin Park Master Plan
to ensure that soil conditions do not pose a threat to the health and safety of people
or structures. The grading and improvement plans, as well as the storm drainage
outfall and building plans, are required to be designed in accordance with the
recommendations provided in the final geotechnical evaluation. With the
implementation of Mitigation Measure 3.6-2 (requiring a final Geotechnical
Evaluation, and site recommendations) the proposed Project would have a less than
significant impact relative to this topic.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.6-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential to result in impacts from expansive soils will
be mitigated to a less than significant level.
G. HAZARDS AND HAZARDOUS MATERIALS
1. IMPACT 3.8-1: POTENTIAL TO CREATE A SIGNIFICANT HAZARD THROUGH THE ROUTINE
TRANSPORT, USE, OR DISPOSAL OF HAZARDOUS MATERIALS OR THROUGH THE REASONABLY
FORESEEABLE UPSET AND ACCIDENT CONDITIONS INVOLVING THE RELEASE OF HAZARDOUS
MATERIALS INTO THE ENVIRONMENT.
(a) Potential Impact. The potential for the Project to create a significant hazard through
the routine transport, use, or disposal of hazardous materials or through the
reasonably foreseeable upset and accident conditions involving the release of
hazardous materials into the environment is discussed on pages 3.8-12 through 3.7-14
of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measures
3.8-1, 3.8-2, 3.8-3, and 3.8-4.
(c) Findings. Construction activities would occur in phases through the development of
the proposed Project. Construction equipment and materials would likely require the
use of petroleum based products (oil, gasoline, diesel fuel), and a variety of chemicals
including paints, cleaners, and solvents. The use of these materials at a construction
site will pose a reasonable risk of release into the environment if not properly handled,
stored, and transported. A release into the environment could pose significant impacts
to the health and welfare of people and/or wildlife, and could result in contamination
of water (groundwater or surface water), habitat, and countless important resources.
Like most agricultural and farming operations in the Central Valley, agricultural
practices in the area have used agricultural chemicals including pesticides and
herbicides as a standard practice. Although no contaminated soils have been identified
on the Project site or the vicinity above applicable levels, residual concentrations of
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 65
pesticides may be present in soil as a result of historic agricultural application and
storage. Continuous spraying of crops over many years can potentially result in a
residual buildup of pesticides, in farm soils. Of highest concern relative to
agrichemicals are chlorinated herbicides, organophosphate pesticides, and
organochlorine pesticides, such as such as Mecoprop (MCPP), Dinoseb, chlordane,
dichloro-diphenyltrichloroethane (DDT), and dichloro-diphenyl-dichloroethylene
(DDE). There are no records of soil contamination on the Project site. Mitigation
Measure 3.8-1 require a Soils Management Plan (SMP) to be submitted and approved
by the San Joaquin County Department of Environmental Health prior to the issuance
of a grading permit. The SMP will establish management practices for handling
hazardous materials, including fuels, paints, cleaners, solvents, etc., during
construction. Implementation of the following mitigation measures will ensure that
these potential impacts are reduced to a less than significant level.
There are 18 single-family residences with associated sheds and garage structures, as
well as areas that are used for farm equipment storage. As noted previously, the farm
equipment storage area in the southeastern portion of the Project site currently
contains inoperable automobiles, tractors and other farm machinery, as well as above
ground storage tanks. The homes and adjoining structures, as well as the farm
equipment storage areas, will require removal prior to any construction. If the homes
and structures are demolished, they will require evaluation for asbestos and lead
containing materials. If such materials are present in the demolition of the structures,
special demolition and disposal practices are required in accordance with state
regulations to ensure their safe handling. Additionally, existing areas containing above
ground storage tanks and storage of farm equipment would require soil sampling to
assess the soils in these areas. Further, groundwater wells may be located within the
vicinity of the on-site residences. Should groundwater wells be present on-site, the
proper well abandonment permit would be obtained. Mitigation Measure 3.8-2
requires additional testing in areas that have been deemed to have potential
hazardous conditions present. Mitigation Measure 3.8-4 requires a well abandonment
permit from the San Joaquin County Environmental Health Division prior to any
ground disturbing activities within 50 feet of a well.
Operational Phase Impacts
The operational phase of the Project will occur after construction is completed and
business operators/employees, and residents move in to occupy the structures and
facilities on a day-to-day basis.
The proposed Project includes commercial mixed use facilities and residential
structures. Each of these uses will likely use a variety of hazardous materials
commonly found in urban areas including: paints, cleaners, and cleaning solvents. If
handled appropriately, these materials do not pose a significant risk. These facilities
will store and use these materials. There will be a risk of release of these materials into
the environment if they are not stored and handled in accordance with best
CEQA FINDINGS
66 CEQA Findings – Griffin Park Master Plan
management practices approved by San Joaquin County Environmental Health Division
and the Manteca Fire Department. Implementation of the Mitigation Measure 3.8-3
requires the applicant to submit a Hazardous Materials Business Plan (HMBP) to San
Joaquin County Environmental Health Division (CUPA) for review and approval, which
will ensure that the proposed Project would have a less than significant impact relative
to this issue.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.8-1, 3.8-2,
3.8-3, and 3.8-4 are appropriate changes or alterations that have been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
before this City Council, this City Council finds that the potential to create a significant
hazard through the routine transport, use, or disposal of hazardous materials or
through the reasonably foreseeable upset and accident conditions involving the
release of hazardous materials into the environment will be mitigated to a less than
significant level.
H. HYDROLOGY AND WATER QUALITY
1. IMPACT 3.9-1: THE PROPOSED PROJECT HAS THE POTENTIAL TO VIOLATE WATER QUALITY
STANDARDS OR WASTE DISCHARGE REQUIREMENTS DURING CONSTRUCTION.
(a) Potential Impact. The potential for the Project to violate water quality standards or
waste discharge requirements during construction is discussed on pages 3.9-18
through 3.9-20 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.6-1.
(c) Findings. According to the United States Environmental Protection Agency, polluted
stormwater runoff is a leading cause of impairment to the nearly 40 percent of
surveyed U.S. water bodies which do not meet water quality standards. Over land or
via storm sewer systems, polluted runoff is discharged, often untreated, directly into
local water bodies. Soil erosion is one of the most common sources of polluted
stormwater runoff during construction activities. When left uncontrolled, storm water
runoff can erode soil and cause sedimentation in waterways, which collectively result
in the destruction of fish, wildlife, and aquatic life habitats; a loss in aesthetic value;
and threats to public health due to contaminated food, drinking water supplies, and
recreational waterways.
Mandated by Congress under the Clean Water Act, the NPDES Stormwater Program is
a comprehensive two-phased national program for addressing the non-agricultural
sources of stormwater discharges which adversely affect the quality of our nation's
waters. The program uses the National Pollutant Discharge Elimination System
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 67
(NPDES) permitting mechanism to require the implementation of controls designed to
prevent harmful pollutants, including soil erosion, from being washed by stormwater
runoff into local water bodies. The construction activities for the proposed project
would be governed by the General Permit 2009-0009-DWQ (amended by 2010-0014-
DWQ & 2012-0006-DWQ), which states:
“…Particular attention must be paid to large, mass graded sites where the
potential for soil exposure to the erosive effects of rainfall and wind is great and
where there is potential for significant sediment discharge from the site to surface
waters. Until permanent vegetation is established, soil cover is the most cost-
effective and expeditious method to protect soil particles from detachment and
transport by rainfall. Temporary soil stabilization can be the single most important
factor in reducing erosion at construction sites. The discharger is required to
consider measures such as: covering disturbed areas with mulch, temporary
seeding, soil stabilizers, binders, fiber rolls or blankets, temporary vegetation, and
permanent seeding. These erosion control measures are only examples of what
should be considered and should not preclude new or innovative approaches
currently available or being developed. Erosion control BMPs should be the primary
means of preventing storm water contamination, and sediment control techniques
should be used to capture any soil that becomes eroded…”
General Permit 2009-0009-DWQ (amended by 2010-0014-DWQ & 2012-0006-DWQ)
further states that:
“Sediment control BMPs should be the secondary means of preventing storm water
contamination. When erosion control techniques are ineffective, sediment control
techniques should be used to capture any soil that becomes eroded. The discharger
is required to consider perimeter control measures such as: installing silt fences or
placing straw wattles below slopes. These sediment control measures are only
examples of what should be considered and should not preclude new or innovative
approaches currently available or being developed…Inappropriate management of
run-on and runoff can result in excessive physical impacts to receiving waters from
sediment and increased flows. The discharger is required to manage all run-on and
runoff from a project site. Examples include: installing berms and other temporary
run-on and runoff diversions…All measures must be periodically inspected,
maintained and repaired to ensure that receiving water quality is protected.
Frequent inspections coupled with thorough documentation and timely repair is
necessary to ensure that all measures are functioning as intended…”
Grading, excavation, removal of vegetation cover, and loading activities associated
with construction activities could temporarily increase runoff, erosion, and
sedimentation. Construction activities also could result in soil compaction and wind
erosion effects that could adversely affect soils and reduce the revegetation potential
at construction sites and staging areas. To ensure that construction activities are
covered under General Permit 2009-0009-DWQ (amended by 2010-0014-DWQ &
CEQA FINDINGS
68 CEQA Findings – Griffin Park Master Plan
2012-0006-DWQ), projects in California must prepare a Stormwater Pollution
Prevention Plan (SWPPP) containing Best Management Practices (BMPs) to reduce
erosion and sediments to meet water quality standards. Such BMPs may include:
temporary erosion control measures such as silt fences, staked straw bales/wattles,
silt/sediment basins and traps, check dams, geofabric, sandbag dikes, and temporary
revegetation or other ground cover. The BMPs and overall SWPPP is reviewed by the
Regional Water Quality Control Board as part of the permitting process. The SWPPP,
once approved, is kept on site and implemented during construction activities and
must be made available upon request to representatives of the RWQCB and/or the
lead agency.
In accordance with the NPDES Stormwater Program, Mitigation Measure 3.6-1
contained in Section 3.6, Geology and Soils, ensures compliance with existing
regulatory requirements to prepare a SWPPP designed to control erosion and the loss
of topsoil to the extent practicable using BMPs that the RWQCB has deemed effective
in controlling erosion, sedimentation, runoff during construction activities. The
RWQCB has stated that these erosion control measures are only examples of what
should be considered and should not preclude new or innovative approaches currently
available or being developed. The specific controls are subject to the review and
approval by the RWQCB and are an existing regulatory requirement. Implementation
of the proposed Project would have a less than significant impact relative to this topic.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.6-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to violate water quality
standards or waste discharge requirements during construction will be mitigated to a
less than significant level.
2. IMPACT 3.9-2: THE PROPOSED PROJECT HAS THE POTENTIAL TO VIOLATE WATER QUALITY
STANDARDS OR WASTE DISCHARGE REQUIREMENTS DURING OPERATION.
(a) Potential Impact. The potential for the Project to violate water quality standards or
waste discharge requirements during operation is discussed on pages 3.9-20 through
3.9-23 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.9-1 and 3.9-2.
(c) Findings. The long-term operations of the proposed Project (all phases) could result in
long-term impacts to surface water quality from urban stormwater runoff. The
proposed Project would result in new impervious areas associated with roadways,
driveways, parking lots, buildings, and landscape areas. Normal activities in these
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 69
developed areas include the use of various automotive petroleum products (i.e. oil,
grease, and fuel), common household hazardous materials, heavy metals, pesticides,
herbicides, fertilizers, and sediment. Within urban areas, these pollutants are generally
called nonpoint source pollutants. The pollutants pollutant levels vary based on factors
such as time between storm events, volume of storm event, type of uses, and density
of people.
The drainage collection system within the City of Manteca consists of gravity pipes,
retention/detention/surge basins, pump station, force mains, outfalls, and irrigation
canals/ditches. The collection system for the proposed Project will be designed to
contain the 10-year storm event within the pipe system and basins while maintaining
one foot of freeboard. The streets will be designed in combination with the pipe
system to convey the 100-year storm event to the basins and pump station in
accordance with City standards. Early phases of development may to rely on
temporary basins in order to delay the construction of the overall storm drainage
system. The final design of all onsite and offsite storm drain infrastructure
improvements is subject to the review and approval of the City of Manteca.
The ongoing operational phase of the proposed Project requires the final discharge of
stormwater into the on-site detention basins. The discharge of stormwater must be
treated through BMPs prior to its discharge. The City of Manteca implements best
management practices to the extent they are technologically achievable to prevent
and reduce pollutants. Under the City’s standard practices, the owner or operator of a
commercial establishment shall provide reasonable protection from accidental
discharge of prohibited materials or other wastes into the municipal storm drain
system or watercourses. Facilities to prevent accidental discharge of prohibited
materials or other wastes shall be provided and maintained at the owner or operator’s
expense.
Additionally, there are various non-structural and structural stormwater BMPs that can
be implemented to reduce water pollution. Non-structural BMPs are typically aimed at
prevention of pollution through public education and outreach. Non-structural BMPs
include: school educational programs, newsletters, website information, commercial,
billboards/advertisements, river cleanups, and storm drain stenciling. Structural BMPS
are aimed at the physical collection, filtering, and detaining of stormwater. Structural
BMPs include items such as drop inlet filters, vault filters, hydrodynamic separators,
surface detention basins, and underground detention facilities.
Mitigation Measures 3.9-1 and 3.9-2 would ensure that BMPs are implemented to
reduce the amount of pollution in stormwater discharged from the Project site into
the Delta during the operational phase of the Project. The management of water
quality through obtaining a General Industrial Stormwater Permit and implementing
BMPs is intended to ensure that water quality does not degrade to levels that would
violate water quality standards. These are existing regulatory requirements.
CEQA FINDINGS
70 CEQA Findings – Griffin Park Master Plan
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.9-1 and
3.9-2 are appropriate changes or alterations that have been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
before this City Council, this City Council finds that the potential for the Project to
violate water quality standards or waste discharge requirements during operation will
be mitigated to a less than significant level.
3. IMPACT 3.9.5 THE PROPOSED PROJECT HAS THE POTENTIAL TO OTHERWISE SUBSTANTIALLY
DEGRADE WATER QUALITY.
(a) Potential Impact. The potential for the Project to otherwise substantially degrade
water quality is discussed on pages 3.9-26 and 3.9-27 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measure 3.6-1, 3.9-1, 3.9-2.
(c) Findings. Water Quality Impacts from Discharges to 303(d) Listed Water Bodies:
Section 303(d) of the federal Clean Water Act (CWA) requires States to identify waters
that do not meet water quality standards or objectives and thus, are considered
"impaired." Once listed, Section 303(d) mandates prioritization and development of a
Total Maximum Daily Load (TMDL). The TMDL is a tool that establishes the allowable
loadings or other quantifiable parameters for a waterbody and thereby the basis for
the States to establish water quality-based controls. The purpose of TMDLs is to
ensure that beneficial uses are restored and that water quality objectives are
achieved.
According to the California Water Quality Control Monitoring Council, which is part of
California Environmental Protection Agency, Natural Resources, there are many areas
within the San Joaquin County which are considered Section 303(d) impaired
waterbodies. Those areas in the regional vicinity of the Project site that are impaired
are referred as Delta Waterways (Southern Portion) by the Water Quality Control
Monitoring Council. This includes 3,125 acres listed as early as 1996 for Chlorpyrifos
(Agriculture, Urban Runoff/Storm Sewers), DDT (Agriculture), Diazinon (Agriculture,
Urban Runoff/Storm Sewers), Electrical Conductivity (Agriculture), Group A Pesticides
(Agriculture), Invasive Species (Source Unknown), Mercury (Resource Extraction), and
Unknown Toxicity (Source Unknown).
The San Joaquin River is specifically listed by the Central Valley Regional Water Quality
Control Board (CVRWQCB) as an impaired water body due to mercury under the Clean
Water Act. Mercury is a sediment-based pollutant that can be released into the water
column during various in-water construction activities (e.g., construction of the storm
drain outfall) that may disturb the sediment and cause turbidity. As a result, such
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 71
activities may increase the likelihood of mercury exposure to the public and wildlife
that utilize the San Joaquin River.
In accordance with the NPDES Stormwater Program, Mitigation Measure 3.6-1
contained in Section 3.6, Geology and Soils, requires an approved SWPPP designed to
control erosion and the loss of topsoil to the extent practicable using BMPs that the
RWQCB has deemed effective in controlling erosion, sedimentation, runoff during
construction activities. Such BMPs may include: temporary erosion control measures
such as silt fences, staked straw bales/wattles, silt/sediment basins and traps, check
dams, geofabric, sandbag dikes, and temporary revegetation or other ground cover.
The BMPs and overall SWPPP is reviewed by the Regional Water Quality Control Board
as part of the permitting process. The SWPPP, once approved, is kept on site and
implemented during construction activities and must be made available upon request
to representatives of the RWQCB and/or the lead agency. The RWQCB has stated that
these erosion control measures are only examples of what should be considered and
should not preclude new or innovative approaches currently available or being
developed. The specific controls are subject to the review and approval by the
RWQCB.
The ongoing operational phase of the proposed Project (all phases) requires discharge
of stormwater into the on-site detention basins, which would ultimately flow into
SSJID system and exit into the Delta. The discharge of stormwater must be treated
through BMPs prior to its discharge. Mitigation Measures contained in Section 3.4
Biological Resources would ensure that BMPs are implemented to reduce the amount
of pollution in stormwater discharged from the Project site into the on-site detention
basins, which would ultimately flow into the Delta during the operational phase of the
Project. There are various non-structural and structural stormwater BMPs that can be
implemented to reduce water pollution. Non-structural BMPs are typically aimed at
prevention of pollution through public education and outreach. Non-structural BMPs
include: school educational programs, newsletters, website information, commercial,
billboards/advertisements, river cleanups, and storm drain stenciling. Structural BMPS
are aimed at the physical collection, filtering, and detaining of stormwater. Structural
BMPs include items such as drop inlet filters, vault filters, hydrodynamic separators,
surface detention basins, and underground detention facilities. The management of
water quality through obtaining a General Industrial Stormwater Permit and
implementing BMPs is intended to ensure that water quality does not degrade to
levels that would violate water quality standards.
The use of BMPs are intended to treat runoff close to the source during the
construction and long term operational phase of the Project (all phases) to reduce
stormwater quality impacts. Mitigation Measures 3.6-1, 3.9-1, and 3.9-2 listed are
existing regulatory requirements that through implementation the proposed Project
would have a less-than-significant impact relative to this topic.
CEQA FINDINGS
72 CEQA Findings – Griffin Park Master Plan
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.6-1, 3.9-1,
and 3.9-2 are appropriate changes or alterations that have been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
before this City Council, this City Council finds that the potential for the Project to
otherwise substantially degrade water quality will be mitigated to a less than
significant level.
I. NOISE
1. IMPACT 3.11-2: THE PROPOSED PROJECT HAS THE POTENTIAL TO INCREASE NOISE LEVELS
ASSOCIATED WITH CONSTRUCTION ACTIVITIES.
(a) Potential Impact. The potential for the Project to increase noise levels associated with
construction activities is discussed on pages 3.11-14 and 3.12-15 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.11-1 and 3.11-2.
(c) Findings. During the construction of the Project including roads, water, and sewer lines
and related infrastructure, noise from construction activities would add to the noise
environment in the Project vicinity. Activities involved in construction would generate
maximum noise levels ranging from 76 to 90 dB at a distance of 50 feet. Construction
activities would be temporary in nature and are anticipated to occur during normal
daytime working hours.
Noise would also be generated during the construction phase by increased truck traffic
on area roadways. A significant Project-generated noise source would be truck traffic
associated with transport of heavy materials and equipment to and from construction
sites. This noise increase would be of short duration, and would likely occur primarily
during daytime hours.
Construction activities would be temporary in nature and are exempt from noise
regulation during the hours of 7:00 a.m. to 7:00 p.m. as outlined in the City’s Municipal
Code:
17.58.050 D Exempt Activities
8. Construction activities when conducted as part of an approved Building
Permit, except as prohibited in Subsection 17.58.050(E)(1) (Prohibited
Activities) below.
17.58.050 E. Prohibited Activities
1. Construction Noise. Operating or causing the operation of tools or
equipment on private property used in alteration, construction,
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 73
demolition, drilling, or repair work daily between the hours of 7:00 p.m.
and 7:00 a.m., so that the sound creates a noise disturbance across a
residential property line, except for emergency work of public service
utilities.
Mitigation Measures 3.11-1 and 3.11-2 requires Project construction activities to
adhere to the requirements of the City of Manteca Municipal Code with respect to
hours of operation. And requires all equipment to be fitted with factory equipped
mufflers, and in good working order. Which reduces impacts related to construction
noise to a less than significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.11-1 and
3.11-2 are appropriate changes or alterations that has been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
before this City Council, this City Council finds that the potential for the Project to
increase noise levels associated with construction activities will be mitigated to a less
than significant level.
2. IMPACT 3.11-4: THE PROPOSED PROJECT HAS THE POTENTIAL TO EXPOSE NEW SENSITIVE
RECEPTORS TO EXCESSIVE TRANSPORTATION NOISE.
(a) Potential Impact. The potential for the Project to expose people to expose new
sensitive receptors to excessive transportation noise is discussed on pages 3.11-16
through 3.11-18 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measures are hereby adopted and will
be implemented as provided by the Mitigation Monitoring Program: Mitigation
Measures 3.11-3, 3.11-4, and 3.11-5.
(c) Findings. The FHWA traffic noise prediction model was used to predict Cumulative +
Project traffic noise levels at the proposed residential land uses associated with the
Project. Table 3.11-10 of the Draft EIR shows the predicted traffic noise levels at the
proposed residential uses adjacent to the major Project-area arterial roadways. Table
3.11-10 also indicates the property line noise barrier heights required to achieve
compliance with an exterior noise level standard of 60 dB Ldn.
Appendix C of the Noise Study provides the complete inputs and results to the FHWA
traffic noise prediction model and barrier calculations. The modeled noise barriers
assume flat site conditions where roadway elevations, base of wall elevations, and
building pad elevations are approximately equivalent.
To describe future noise levels due to traffic, FHWA Highway Traffic Noise Prediction
Model (FHWA RD-77-108) was used. Direct inputs to the model included traffic
volumes provided by Fehr & Peers. The FHWA model is based upon the Calveno
reference noise factors for automobiles, medium trucks and heavy trucks, with
CEQA FINDINGS
74 CEQA Findings – Griffin Park Master Plan
consideration given to vehicle volume, speed, roadway configuration, distance to the
receiver, and the acoustical characteristics of the site. The FHWA model was
developed to predict hourly Leq values for free-flowing traffic conditions. To predict
Ldn/CNEL values, it is necessary to determine the day/night distribution of traffic and
adjust the traffic volume input data to yield an equivalent hourly traffic volume.
Table 3.11-10 of the Draft EIR indicate that noise barriers 6- to 8-feet in height would
be sufficient to achieve compliance with the City of Manteca 60 dB Ldn exterior noise
level standard for the proposed residential uses. This conclusion assumes the setback
distances shown in Table 3.11-10.
Interior Noise Impacts
Modern construction typically provides a 25 dB exterior-to-interior noise level
reduction with windows closed. Therefore, sensitive receptors exposed to exterior
noise of 70 dB Ldn, or less, will typically comply with the City of Manteca 45 dB Ldn
interior noise level standard. Additional noise reduction measures, such as
acoustically-rated windows, are generally required for exterior noise levels exceeding
70 dB Ldn.
It should be noted that exterior noise levels are typically 2 to 3 dB higher at second
floor locations. Additionally, noise barriers do not reduce exterior noise levels at
second floor locations. The proposed residential uses are predicted to be exposed to
unmitigated first floor exterior transportation noise levels ranging between 59 to 69
dB Ldn. Therefore, second floor facades are predicted to be exposed to exterior noise
levels of up to 62 to 72 dB Ldn.
Based upon a 25 dB exterior-to-interior noise level reduction, interior noise levels are
predicted to range between 34 to 47 dB Ldn. Predicted interior noise levels would
exceed the City’s 45 dB Ldn interior noise level standard at the first row of residential
uses located along Main Street / Manteca Road. Therefore, additional interior noise
control measures would be required for these residential uses. In order to reduce
interior noise levels to 45 dB Ldn, or less, second floor facades shall include windows
having a Sound Transmission Class (STC) 32, or higher, rating. This would specifically
apply to the first row of homes adjacent to Main Street / Manteca Road and does not
apply to facades facing away from the roadway.
With implementation of the interior and exterior measures contained in Mitigation
Measures 3.11-3, 3.11-4, and 3.11-5, the proposed Project would have a less than
significant impact relative to this environmental topic
In accordance with Public Resources Code, § 21081, Mitigation Measures 3.11-3, 3.11-
4, and 3.11-5 are appropriate changes or alterations that has been required in, or
incorporated into, the Project which avoid or substantially lessen the significant
environmental effect as identified in the EIR. Based upon the EIR and the entire record
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 75
before this City Council, this City Council finds that the potential for the Project to
expose new sensitive receptors to excessive transportation noise will be mitigated to a
less than significant level.
J. TRANSPORTATION AND CIRCULATION
1. IMPACT 3.13-8: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT MAY ADVERSELY
AFFECT PEDESTRIAN AND BICYCLE FACILITIES.
(a) Potential Impact. The potential for proposed Project to adversely affect pedestrian and
bicycle facilities is discussed on pages 3.13-28 and 3.13-29 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-8.
(c) Findings. Figure ES-1, Existing and Proposed Bicycle Route System, of the City of
Manteca Bicycle Master Plan (2003) indicates that future Class II bike lanes are
proposed along Main Street north of Tannehill Drive and along the proposed Project’s
Driveway 3 from Manteca Road to Tinnin Road.
One of the proposed Project’s objectives is to “tie into and expand the City’s bikeway
and pedestrian paths to offer additional bicycling and walking facilities for all of
Manteca’s residents.” In order to serve all travel modes, the Project proposes to
construct a multi-use Class II bike / pedestrian path on one side of Anton Raymus
Expressway and a standard pedestrian sidewalk on the other. Additionally, the Project
includes a north / south multi-use Class II bike / pedestrian path along with the
construction of the southbound lane on Main Street and Manteca Road, as well as
sidewalks along Tinnin Road and other residential collectors.
Therefore, the proposed Project is consistent with the City’s Bicycle Master Plan by
providing the following:
A multi-use Class II bike / pedestrian path is to be constructed along the Project
frontage (west side of Main Street from Woodward Avenue to Tannehill Road);
and
An 8-foot Class II bike lane is to be constructed at Project Driveway 3 / Tannehill
Drive, east of Main Street.
However, the proposed Project is not consistent with the City’s Bicycle Master Plan by
not providing the following:
An 8-foot Class II bike lane is to be constructed on both sides of the street from
Project Driveway 3 / Tannehill Drive / Main Street to the western boundary of the
Project site (and eventually connecting to Tinnin Road).
CEQA FINDINGS
76 CEQA Findings – Griffin Park Master Plan
Although the proposed bike lanes will add continuity to the proposed bicycle network
in the City of Manteca Bicycle Master Plan, the proposed Project is not consistent with
the bike facilities in the City of Manteca Bicycle Master Plan. Mitigation Measure 3.13-
8 requires the Project applicant to provide bike and pedestrian paths consistent with
the City’s Bicycle Master Plan. Consequently, this impact would be reduced to a less
than significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.13-8 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for proposed Project to adversely affect
pedestrian and bicycle facilities will be mitigated to a less than significant level.
2. IMPACT 3.13-9: UNDER EXISTING CONDITIONS, THE PROPOSED PROJECT MAY ADVERSELY
AFFECT TRANSIT SERVICES OR FACILITIES.
(a) Potential Impact. The potential for the proposed Project to adversely affect transit
services or facilities is discussed on pages 3.13-29 and 3.13-30 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.13-9.
(c) Findings. The Project includes up to 1,592 residential dwelling units, 5.0 acres of
commercial mixed-use area, and 26.46 acres of parks and open space. The Project is
located near Manteca Transit Routes 2 and 3, both of which have a stop on Atherton
Drive approximately 0.5 miles away from the northwest corner of the Project site. The
Project would not disrupt or interfere with existing or planned public transit services
or facilities. However, if the Project creates an inconsistency with policies concerning
transit systems set forth in a General Plan or another adopted policy document, a
potentially significant impact would result. The Manteca Transit Short Range Transit
Plan (2014) does not contain policies concerning transit systems; however, the Plan
contains proposed system routing changes for Routes 2 and 3, which both currently
serve the Project site. The proposed changes would not disrupt service to the Project.
Additionally, implementation of Mitigation Measure 3.13-9 would ensure that the
Project applicant(s) work with Manteca Transit to ensure that future service to the
Project is available.
The SJCOG RTP/SCS contains policies and supportive strategies related to transit
services or facilities. Specifically, Strategy #6 aims to “facilitate transit-oriented
development to maximize existing transit investments.” While the proposed Project is
not a transit-oriented development, the proposed Project includes a mixture of uses
located near SR 120 in the City’s southern future growth area. Mitigation Measure
3.13-9 requires the Project applicant to work with Manteca Transit in order to provide
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 77
service to the Project and ensure that existing and future transit investments in the
southern portion of the City are consistent with future growth in the area. Therefore,
this impact is considered less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.13-9 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the proposed Project to adversely affect
transit services or facilities will be mitigated to a less than significant level.
3. IMPACT 3.13-11: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
EXACERBATE LEVELS OF SERVICE AT THE MAIN STREET / ATHERTON DRIVE INTERSECTION.
(a) Potential Impact. The potential for proposed Project to exacerbate levels of service at
the Main Street / Atherton Drive intersection under cumulative conditions is discussed
on pages 3.13-38 and 3.13-39 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-2.
(c) Findings. The Main Street / Atherton Drive intersection would operate at LOS F during
both peak hours under Cumulative No Project conditions. The addition of Project
traffic would exacerbate unacceptable operations at this City of Manteca intersection
and would increase average control delay at this intersection by more than three
seconds.
This study intersection is under City of Manteca jurisdiction and the following
improvements, identified in their PFIP, would mitigate the impact to less than
significant under Cumulative Plus Project conditions:
Restripe the southbound approach as one left-turn, one thru lane, and one shared
right-turn / thru lane;
Widen the northbound approach and restripe as one left-turn, one thru lane, and
one shared right-turn / thru lane;
Widen the south leg to have two receiving lanes; and
Retime signal and optimize splits.
Through these improvements, the Atherton Drive / Main Street intersection would
operate at LOS C during the AM peak hour and LOS D during the PM peak hour.
Calculations for this analysis are in Appendix E.8. The City of Manteca would be
responsible for the aforementioned intersection improvements, which are included in
the PFIP. The Project applicant would be required to pay their fair share fee towards
the intersection improvements, as required by Mitigation Measure 3.13-2.
CEQA FINDINGS
78 CEQA Findings – Griffin Park Master Plan
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.13-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for proposed Project under cumulative
conditions to exacerbate levels of service at the Main Street / Atherton Drive
intersection will be mitigated to a less than significant level.
4. IMPACT 3.13-22: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD
ADVERSELY AFFECT PEDESTRIAN AND BICYCLE FACILITIES.
(d) Potential Impact. The potential for proposed Project to adversely affect pedestrian and
bicycle facilities under cumulative conditions is discussed on pages 3.13-50 and 3.13-
51 of the Draft EIR.
(e) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-8.
(f) Findings. The proposed Project includes construction of a multi-use Class II bicycle /
pedestrian path on one side of Anton Raymus Expressway and a standard pedestrian
sidewalk on the other. Additionally, the Project includes construction of a north /
south multi-use Class II bicycle / pedestrian path along with the construction of the
southbound lane on Main Street and Manteca Road, as well as sidewalks along Tinnin
Road and other residential collectors.
The City of Manteca Bicycle Master Plan (2003) indicates that future Class II bike lanes
are proposed along Main Street north of Tannehill Drive and along the proposed
Project’s Driveway 3. The Project indicates that 8-foot bike lanes are to be constructed
at entry streets off Main Street. Consequently, this impact would be reduced to a less
than significant level.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.13-8 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for proposed Project under cumulative
conditions to adversely affect pedestrian and bicycle facilities will be mitigated to a
less than significant level.
5. IMPACT 3.13-23: UNDER CUMULATIVE CONDITIONS, THE PROPOSED PROJECT WOULD NOT
ADVERSELY AFFECT TRANSIT SERVICES OR FACILITIES.
(a) Potential Impact. The potential for the proposed Project to adversely affect transit
services or facilities under cumulative conditions is discussed on page 33.13-51 of the
Draft EIR.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 79
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Implementation of
Mitigation Measure 3.13-9.
(c) Findings. The Project includes up to 1,592 residential dwelling units, 5.0 acres of
commercial mixed-use area, and 26.46 acres of parks and open space. As noted
previously, the Project is located near Manteca Transit Routes 2 and 3, both of which
have a stop on Atherton Drive approximately 0.5 miles away from the northwest
corner of the Project site.
The Project would not disrupt or interfere with existing or planned public transit
services or facilities. However, if the Project creates an inconsistency with policies
concerning transit systems set forth in a General Plan or another adopted policy
document, a potentially significant impact would result. Mitigation Measure 3.13-9
requires the Project applicant to work with Manteca Transit in order to provide service
to the Project. Therefore, this impact is considered less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.13-9 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the proposed Project under cumulative
conditions to adversely affect transit services or facilities will be mitigated to a less
than significant level.
K. UTILITIES
1. IMPACT 3.14-6: THE PROPOSED PROJECT HAS THE POTENTIAL TO REQUIRE OR RESULT IN THE
CONSTRUCTION OF NEW STORM WATER DRAINAGE FACILITIES OR EXPANSION OF EXISTING
FACILITIES, THE CONSTRUCTION OF WHICH COULD CAUSE SIGNIFICANT ENVIRONMENTAL
EFFECTS.
(a) Potential Impact. The potential for the Project to require or result in the construction
of new storm water drainage facilities or expansion of existing facilities is discussed on
pages 3.14-51 through 3.14-53 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.14-1.
(a) Findings. Flooding events can result in damage to structures, injury or loss of human
and animal life, exposure of waterborne diseases, and damage to infrastructure. In
addition, standing floodwater can destroy agricultural crops, undermine infrastructure
and structural foundations, and contaminate groundwater. The RD-17 levee system is
designed to a 100-year protection standard. The Project site is currently located in
CEQA FINDINGS
80 CEQA Findings – Griffin Park Master Plan
Zone X, protected by levee, which by definition indicates an area protected by levees
from the 1% annual chance flood. The Project site is not located within the 200-year
floodplain as delineated on the most recent 200-year flood plain maps for Manteca.
Onsite storm drainage would be installed to serve the proposed Project. As shown in
Figure 2.0-15, development of the proposed Project would include construction of a
new storm drainage system, including a drainage collection system, and detention
basins. All on-site storm drainage runoff will be collected through drain inlets in the
landscaped areas and catch basins along the streets and within properties, and
conveyed via surface swales and underground trunk lines to four detention and water
quality basins. The storm water drainage detention basins will be constructed to meet
the City of Manteca Standards. Discharge from the basins will be conveyed through
controlled flow pumping facilities to existing City of Manteca and SSJID dual use main
storm drain laterals.
The proposed public storm drainage and water quality system is planned to function
independently from surrounding developments. An internal layout of stormwater
collection pipes with various sizes, as necessary, will be installed within the Project
site. A system of drainage swales may be included to treat and convey collected
stormwater. Four on-site drainage sheds are included within the Project site. All on-
site storm drainage runoff will be collected through drain inlets in the landscaped
areas and catch basins along the streets and within properties, and conveyed via
surface swales and underground trunk lines to four detention and water quality
basins. The conveyance systems and detention basins may include facilities designed
to address water quality standards and requirements. Discharge from the basins will
be conveyed through controlled flow pumping facilities to existing City of Manteca and
SSJID dual use main storm drain laterals. The duration of the discharge will comply
with City of Manteca standards. The water quality detention basins will be designed to
comply with SWRCB and City of Manteca specifications and standards.
Because the Project site could increase runoff significantly, and create downstream
drainage problems; Project impacts to stormwater are considered potentially
significant. Mitigation Measure 3.14-1 requires the Project applicant to install a
drainage system that meets this performance standard and, prior to issuance of
grading permits, provide a drainage plan and report to the City of Manteca for review
and approval. With the implementation of Mitigation Measure 3.14-1, drainage
impacts would be reduced to less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.14-1 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to require or result in the
construction of new storm water drainage facilities or expansion of existing facilities,
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 81
the construction of which could cause significant environmental effects will be
mitigated to a less than significant level.
2. IMPACT 3.14-7: THE PROPOSED PROJECT HAS THE POTENTIAL TO BE SERVED BY A LANDFILL
WITH SUFFICIENT PERMITTED CAPACITY TO ACCOMMODATE THE PROJECT’S SOLID WASTE
DISPOSAL NEEDS AND COMPLY WITH FEDERAL, STATE, AND LOCAL STATUTES AND
REGULATIONS RELATED TO SOLID WASTE.
(a) Potential Impact. The potential for the Project to be served by a landfill with sufficient
permitted capacity to accommodate the Project’s solid waste disposal needs and
comply with federal, state, and local statutes and regulations related to solid waste is
discussed on pages 3.14-57 and 3.15-58 of the Draft EIR.
(b) Mitigation Measures. The following mitigation measure is hereby adopted and will be
implemented as provided by the Mitigation Monitoring Program: Mitigation Measure
3.14-2.
(c) Findings. Permitted maximum disposal at the Forward Landfill is 8,668 tons per day.
The total permitted capacity of the landfill is 51.04 million cubic yards, which is
expected to accommodate an operational life until January 1, 2020. The remaining
capacity is 23,700,000 cubic yards. Solid waste generated by the proposed Project was
estimated based on CalRecycle generation rate estimates by use (discussed below).
The Commercial Mixed Use area is estimated to generate roughly five pounds per day
per 1,000 square feet. It is estimated that the 65,340 square feet of commercial space
would generate 327 pounds per day of solid waste. Note, this estimate of the square
footage for the commercial space is considered a worst-case scenario and may very
well prove to be an overestimate.
The Residential portion of the Project site is estimated to generate roughly 10 pounds
per day per household. It is estimated that the proposed 1,592 residential units would
generate 15,920 pounds per day of solid waste.
The total solid waste generated by the proposed Project is estimated to be 8.12 tons
per day. As previously described, solid waste generated in the City is disposed at the
Forward Landfill. This landfill is projected to close in the year 2020. At that time the
City can utilize the Foothill Landfill as a location for solid waste disposal. The City’s
solid waste per capita generation has decreased since 2007 due to the waste diversion
efforts of the City. The permitted maximum disposal at the Forward Landfill is 8,668
tons per day. Currently, the average daily disposal is 620 tons per day. The total
permitted capacity of the landfill is 51.04 million cubic yards. The addition of solid
waste associated with the proposed Project, approximately 8.12 tons per day at total
buildout, to the Forward Landfill would not exceed the landfill’s remaining capacity.
The City will need to secure a new location of disposal of all solid waste generated in
the City when the Forward landfill is ultimately closed. There are several options that
CEQA FINDINGS
82 CEQA Findings – Griffin Park Master Plan
the City will have to consider for solid waste disposal at that time which is estimated
to be 2020. Because the Project would increase the local waste stream, and require
the city to invest in additional resources for the collection and disposal of solid waste;
local impacts to solid waste are considered potentially significant. Mitigation Measure
3.14-2 requires the payment of a solid waste connection fee prior to issuance of
grading permits. With the implementation of Mitigation Measure 314-2, solid waste
impacts would be reduced to less than significant.
In accordance with Public Resources Code, § 21081, Mitigation Measure 3.14-2 is an
appropriate change or alteration that has been required in, or incorporated into, the
Project which avoid or substantially lessen the significant environmental effect as
identified in the EIR. Based upon the EIR and the entire record before this City Council,
this City Council finds that the potential for the Project to result in impacts to solid
waste including, solid waste disposal needs and compliance with federal, State, and
local statutes and regulations related to solid waste will be mitigated to a less than
significant level.
V. FINDINGS AND RECOMMENDATIONS REGARDING THOSE IMPACTS
WHICH ARE LESS THAN SIGNIFICANT OR LESS THAN
CUMULATIVELY CONSIDERABLE
Specific impacts within the following categories of environmental effects were found to be less
than significant as set forth in more detail in the Draft EIR.
Aesthetics: The following specific impacts were found to be less than significant: 3.1-2.
Agricultural Resources: The following specific impact was found to be less than significant:
3.2-2.
Air Quality: The following specific impacts were found to be less than significant: 3.3-3,
3.3-4, and 3.3-5
Biological Resources: The following specific impacts were found to be less than significant:
3.4-2, 3.4-4, 3.4-5, 3.4-7, 3.4-8, and 3.4-9.
Geology and Soils: The following specific impact was found to be less than significant: 3.6-
1.
Greenhouse Gases and Climate Change: The following specific impact was found to be
less than significant: 3.7-3.
Hazards and Hazardous Materials: The following specific impacts were found to be less
than significant: 3.8-2, 3.8-3, 3.8-4, 3.8-5, 3.8-6, and 3.8-7.
Hydrology and Water Quality: The following specific impacts were found to be less than
significant: 3.9-3, 3.9-4, 3.9-5, 3.9-6, and 3.9-7.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 83
Land Use and Population: The following specific impacts were found to be less than
significant: 3.10-1, 3.10-2, 3.10-3, 3.10-4, and 3.10-5.
Noise: The following specific impacts were found to be less than significant: 3.11-1 and
3.11-3.
Public Services and Recreation: The following specific impacts were found to be less than
significant: 3.12-1, 3.12-2, 3.12-3, 3.12-4, 3.12-5, and 3.12-6.
Utilities: The following specific impacts were found to be less than significant: 3.14-1, 3.14-
2, 3.14-3, 3.14-4, and 3.14-5.
The Project was found to have a less than cumulatively considerable contribution to specific
impacts within the following categories of environmental effects as set forth in more detail in the
Draft EIR.
Aesthetics: The following specific impacts were found to be less than cumulatively
considerable: Impact 4.1 and 4.3
Biological Resources: The following specific impact was found to be less than cumulatively
considerable: 4.6.
Cultural Resources: The following specific impact was found to be less than cumulatively
considerable: 4.7.
Geology and Soils: The following specific impact was found to be less than cumulatively
considerable: 4.8.
Hazards and Hazardous Materials: The following specific impact was found to be less than
cumulatively considerable: 4.10.
Hydrology and Water Quality: The following specific impact was found to be less than
cumulatively considerable: 4.11, 4.12, 4.13, and 4.14.
Land Use and Population: The following specific impact was found to be less than
cumulatively considerable: 4.15 and 4.16.
Noise: The following specific impact was found to be less than cumulatively considerable:
4.17.
Public Services and Recreation: The following specific impact was found to be less than
cumulatively considerable: 4.18.
Transportation and Circulation: The following specific impacts were found to be less than
cumulatively considerable: 4.20, 4.31, and 4.32.
Utilities: The following specific impact was found to be less than cumulatively
considerable: 4.33, 4.34, 4.35, and 4.36.
CEQA FINDINGS
84 CEQA Findings – Griffin Park Master Plan
The above impacts are less than significant or less than cumulatively considerable for one of the
following reasons:
The EIR determined that the impact is less than significant for the Project.
The EIR determined that the Project would have a less than cumulatively considerable
contribution to the cumulative impact.
The EIR determined that the impact is beneficial (would be reduced) for the Project.
VI. PROJECT ALTERNATIVES
A. IDENTIFICATION OF PROJECT OBJECTIVES
An EIR is required to identify a range of reasonable alternatives to the project. The “range of
potential alternatives to the project shall include those that could feasibly accomplish most of the
basic purposes of the project and could avoid or substantially lessen one of more of the significant
effects.” (CEQA Guidelines Section 15126.6(c).) “Among the factors that may be taken into account
when addressing the feasibility of alternatives are site suitability, economic viability, availability of
infrastructure, general plan consistency, other plans or regulatory limitations, jurisdictional
boundaries (projects with a regionally significant impact should consider the regional context), and
whether the proponent can reasonably acquire, control or otherwise have access to the
alternative site (or the site is already owned by the proponent).” (CEQA Guidelines Section
15126.6(f)(1).)
The quantifiable objectives of the proposed Project include annexation of 333.94 acres of land into
the Manteca city limits (with 10 acres of the Project site remaining undeveloped in the
unincorporated County), and the subsequent development of land, which will include: Commercial
Mixed-Use, Low Density Residential, and Open Space Parkland.
The Griffin Park Master Plan Project identifies the following objectives:
Complete neighborhoods, rather than monolithic subdivisions. Neighborhood designs
should foster a mixture of compatibly scaled housing types on urban lots.
Provision for public transit and other alternatives to the private automobile (i.e. bicycling
and walking) will be encouraged to create an active, thriving lifestyle.
Street patterns will be carefully configured to allow for multiple outlets from
neighborhoods, and to provide for connections between neighborhoods, without
encouraging through traffic to create convenience and access without a private
automobile.
A network of planned walkways, bikeways and greenways will be implemented as an
integral part of development. This will make getting outside convenient, easy and
enjoyable.
Provide for street, driveway and sidewalk design to minimize impervious improvements.
Regularly spaced street trees selected and planted in accordance with the City of Manteca
street tree master plan.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 85
Each neighborhood will have adequate open space areas designed into the development,
if possible. These spaces will serve as meeting spaces and may have fitness equipment or
recreational activities.
Residential architecture will respect the value of the street upon which it faces, and
contribute to the sense of community featuring human scaled architecture with its
associated details. This generally means houses pulled up to the street, porches in front, a
front walk connecting to the sidewalk, and garages to the rear or at least set back from the
front face of the home. Front porches inviting neighborly visits will be encouraged.
To employ additional conservation measures through thoughtful consideration of street
and driveway design; the siting of buildings; and the availability of solar.
Durable construction materials and designs suited to local conditions to contribute to the
ongoing costs of the housing will be encouraged.
Provide a range of housing opportunities to support a diverse population, lifestyles, and
family groups.
Establish a planning/zoning concept that is responsive to the market.
Implement the Circulation Element of the City’s General Plan.
Implement City’s Infrastructure Master Plans.
B. ALTERNATIVES NOT SELECTED FOR FURTHER CONSIDERATION
1. ALTERNATIVE LOCATION CONSIDERED:
An Alternative Location is discussed on pages 5.0-2 and 5.0-3 of the Draft EIR.
Findings: The City of Manteca considered alternative locations early in the public scoping process.
The City’s key considerations in identifying an alternative location were as follows:
Is there an alternative location where significant effects of the project would be avoided or
substantially lessened?
Is there a site available within the City’s Sphere of Influence with the appropriate size and
characteristics such that it would meet the basic project objectives?
The City’s consideration of alternative locations for the Project included a review of previous land
use planning and environmental documents in Manteca including the General Plan. The search
included a review of lands in the south part of Manteca that is located within the Sphere of
Influence and is otherwise suitable for development. It was found that there are numerous
approved projects and proposed projects that are currently under review in South Manteca. These
approved and proposed projects are not available for acquisition by the Project applicant, and are
not considered a feasible alternative for the Project applicant. Additionally, much of the
undeveloped land located to the west of the Project site is located within a 200-year flood plain.
These areas within the 200-year flood plain are severely constrained and are not developable until
the City of Manteca is able to design, fund, and construct a solution to protect this area from the
200-year flood plain. The City has found that there are no feasible alternative locations that exist
within the City’s Sphere of Influence with the appropriate size and characteristics that would meet
CEQA FINDINGS
86 CEQA Findings – Griffin Park Master Plan
the basic Project objectives and avoid or substantially lessen a significant effect. The City has
determined that alternative locations outside the Sphere of Influence would not be feasible
because an expansion of the Sphere of Influence would induce unplanned growth and cause
impacts greater than development on the Project site. For these reasons, the City of Manteca
determined that there are no feasible alternative locations.
In addition, as discussed in Citizens of Goleta Valley v. Board of Supervisors (1990) 52 Cal.3d 553
(Goleta II), where a project is consistent with an approved general plan, no off-site alternative
need be analyzed in the EIR. The EIR “is not ordinarily an occasion for the reconsideration or
overhaul of fundamental land-use policy.” (Goleta II, supra, 52 Cal.3d at p. 573.) In approving a
general plan, the local agency has already identified and analyzed suitable alternative sites for
particular types of development and has selected a feasible land use plan. “Informed and
enlightened regional planning does not demand a project EIR dedicated to defining alternative
sites without regard to feasibility. Such ad hoc reconsideration of basic planning policy is not only
unnecessary, but would be in contravention of the legislative goal of long-term, comprehensive
planning.” (Goleta II, supra, 52 Cal.3d at pp. 572-573.) Here, the proposed Project is generally
consistent with the types of uses considered in the Manteca General Plan and associated EIR, and
thus, in addition to the reasons discussed above, an off-site alternative need not be further
discussed in the Draft EIR.
2. OTHER ALTERNATIVES CONSIDERED:
A Notice of Preparation was circulated to the public to solicit recommendations for a reasonable
range of alternatives to the proposed Project. Additionally, a public scoping meeting was held
during the public review period to solicit recommendations for a reasonable range of alternatives
to the proposed Project. No specific alternatives were recommended by commenting agencies or
the general public during the NOP public review process.
The Draft EIR was also circulated for public review and comment. No specific alternatives were
recommended by commenting agencies or the general public during the Draft EIR public review
process that were not previously considered by the City.
C. ALTERNATIVES ANALYSIS IN EIR
1. NO PROJECT (NO BUILD) ALTERNATIVE:
The No Build Alternative is discussed on pages 5.0-3, and 2.5-4 through 5.0-9 of the Draft EIR. This
alternative assumes development of the Project site would not occur, and the Project site would
remain in its current condition.
Findings: Environmental benefits of this alternative over the proposed Project include the
reduction of impacts to aesthetics and visual resources, agricultural resources, air
quality, biological resources, cultural resources, geology and soils, greenhouse gases
and climate change, hazards and hazardous materials, hydrology and water quality,
land use, population, and housing, noise, transportation and circulation, and utilities.
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 87
While the City recognizes the environmental benefits of the No Build Alternative, this
alternative would not achieve all of the Project objectives, and would not provide new
residential and commercial opportunities, local jobs, or tax revenue generation for the
City of Manteca. For these reasons, this alternative is rejected.
2. INCREASED DENSITY ALTERNATIVE:
The Increased Density Alternative is discussed on pages 5.0-3, 5.0-4, and 5.0-9 through 5.0-15 of
the Draft EIR. Under this alternative, the proposed Project would be developed with the same
components as described in the Project Description, but density of the residential uses would be
increased. Under the Increased Density Alternative, the same number of residential units as the
proposed Project (1,592 units) would be constructed. The residential areas would be clustered
throughout the Project site at increased densities to allow for an increase in park/open space
areas. Additionally, all of the residences would have equal lot sizes. The residential density under
the Increased Density Alternative would fall within the allowed density for the City’s Low Density
Residential land use designation (2.1 to 8.0 dwelling units per acre [du/ac]). The 26.46-acres of
park/open space uses would be increased to 40.0 acres. Additionally, the 5-acre Commercial
Mixed Use area would provide an estimated 65,340 square feet of neighborhood-serving
commercial uses, identical to the proposed Project.
Findings: Environmental benefits of this alternative over the proposed Project include the
reduction of impacts to aesthetics and visual resources, biological resources, hydrology
and water quality, and public services and recreation.
While the City recognizes the environmental benefits of this alternative, this
alternative would not fully achieve all of the Project objectives, and would decrease
Project impacts in only four resources areas. For these reasons, this alternative is
rejected.
3. AGRICULTURE PROTECTION ALTERNATIVE:
The Agricultural Protection Alternative is discussed on pages 5.0-4, and 5.0-15 through 5.0-22 of
the Draft EIR. The reasoning behind this alternative is to present an alternative to protect some of
the farmland on the Project site. Development of the proposed Project would result in the
permanent conversion of roughly 290.56 acres of Prime Farmland and Farmland of Statewide
Importance. Under this alternative, the proposed Project would be developed with the same
components as described in the Project Description, but the size of the buildings and residential
areas would be reduced resulting in an increase of undeveloped land beyond the Increased
Density Alternative. The 5.0-acre Commercial Mixed Use area would be reduced from 65,340
square feet to 32,670 square feet. Residential units would be reduced from 1,592 to 796. The total
acreage dedicated to proposed Project would be reduced by approximately 1/2. The total acreage
developed would be 166.98 acres, with 166.96 acres remaining in its current state. The 166.96
acres that would remain undeveloped would include the agricultural land only.
CEQA FINDINGS
88 CEQA Findings – Griffin Park Master Plan
Findings: Environmental benefits of this alternative over the proposed Project include the
reduction of impacts to aesthetics and visual resources, agricultural resources, air
quality, biological resources, cultural resources, geology and soils, greenhouse gases
and climate change, hazards and hazardous materials, hydrology and water quality,
land use, population, and housing, noise, transportation and circulation, and utilities.
While the City recognizes the environmental benefits of this alternative, this
alternative would not fully achieve all of the Project objectives, and would not provide
the number of new residential and commercial opportunities, local jobs, or tax
revenue generation for the City of Manteca (reduced by one-half). For these reasons,
this alternative is rejected.
4. ENVIRONMENTALLY SUPERIOR ALTERNATIVE:
CEQA requires that an environmentally superior alternative be identified among the alternatives
that are analyzed in the EIR. If the No Project Alternative is the environmentally superior
alternative, an EIR must also identify an environmentally superior alternative among the other
alternatives (CEQA Guidelines Section 15126.6(e)(2)). The environmentally superior alternative is
that alternative with the least adverse environmental impacts when compared to the proposed
Project.
As discussed in Section 5.0, and shown on Table 5.0-1 of the Draft EIR (page 5.0-23) a comparison
of alternatives is presented. The No Project Alternative is the environmentally superior alternative.
However, as required by CEQA, when the No Project Alternative is the environmentally superior
alternative, the environmentally superior alternative among the others must be identified.
Therefore, the Increased Density and Agricultural Protection Alternatives both rank higher than
the proposed Project. Comparatively, the Agricultural Protection Alternative would result in less
impact then the Increased Density Alternative because it provides the greatest reduction of
potential impacts in comparison to the proposed Project. However, neither the Agricultural
Protection Alternative nor the Increased Density Alternative fully meet all of the Project objectives.
While the City recognizes the environmental benefits of the Increased Density and Agricultural
Protection Alternatives, these alternatives would not provide as many opportunities for new local
job generating uses, or the amount of residential uses and park-space that is identified in the
Project objectives under full buildout of the Project site. Thus, does not achieve all of the Project
objectives.
The Increased Density Alternative does not meet, or only partially meets, the Project objectives.
This alternative would not provide a range of housing opportunities to support a diverse
population, lifestyles, and family groups. All of the residences would have equal lot sizes.
Additionally, this alternative would decrease Project impacts in only four resources areas. For the
reasons provided above, this alternative is rejected.
This Agricultural Protection Alternative does not meet, or only partially meets, the Project
objectives. This alternative would reduce the number of new jobs generated, additional park-
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 89
space, and residential opportunities within the City of Manteca by approximately one-half when
compared to the full Project buildout. For the reasons provided above, this alternative is rejected.
VII. STATEMENTS OF OVERRIDING CONSIDERATIONS RELATED TO THE
MANTECA GRIFFIN PARK MASTER PLAN FINDINGS As described in detail in Section III of these Findings, the following significant and unavoidable
impacts could occur with implementation of the Project:
vistas and resources or substantial degradation of visual character
Impact 3.2-1: The proposed Project has the potential to result in the conversion of
Farmlands, including Prime Farmland and Farmland of Statewide Importance, as shown on
the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the
California Resources Agency, to non-agricultural uses
Impact 3.3-1: Project operation has the potential to cause a violation of an air quality
standard or contribute substantially to an existing or projected air quality violation.
Impact 3.7-1: Potential to generate greenhouse gas emissions, either directly or indirectly,
that may have a significant impact on the environment or potential to conflict with an
applicable plan, policy, or regulation adopted for the purpose of reducing the emissions of
greenhouse gases.
Impact 3.7-2: Cumulative impact on climate change from increased Project-related
greenhouse gas emissions.
Impact 3.13-1: Under Existing conditions, the proposed Project would result in a significant
impact at the Main Street / SR 120 EB Ramps intersection.
Impact 3.13-2: Under Existing conditions, the proposed Project would result in a significant
impact at the Main Street / Atherton Drive intersection.
Impact 3.13-3: Under Existing conditions, the proposed Project would result in a significant
impact at the Main Street / Woodward Avenue intersection.
Impact 3.13-4: Under Existing conditions, the proposed Project would result in a significant
impact at the Main Street / Tannehill Drive intersection.
Impact 3.13-5: Under Existing conditions, the proposed Project would result in a significant
impact at the Woodward Avenue / Union Road intersection.
Impact 3.13-6: Under Existing conditions, the proposed Project would result in a significant
impact at the Union Road / SR 120 EB Ramps intersection.
Impact 3.13-7: Under Existing conditions, the proposed Project would result in a significant
impact to freeway facilities.
Impact 3.13-10: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Main Street / SR 120 ramp terminal intersections.
Impact 3.13-12: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Main Street / Woodward Avenue intersection.
Impact 3.13-13: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Main Street / Tannehill Drive / Project Driveway 3 intersection.
CEQA FINDINGS
90 CEQA Findings – Griffin Park Master Plan
Impact 3.13-14: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Woodward Avenue / Union Road intersection.
Impact 3.13-15: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Union Road / Atherton Drive intersection.
Impact 3.13-16: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Union Road / SR 120 ramp terminal intersections.
Impact 3.13-17: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Main Street / Mission Ridge Drive / Industrial Park Drive.
Impact 3.13-18: Under Cumulative conditions, the proposed Project would exacerbate
levels of service at the Manteca Road / Raymus Expressway intersection.
Impact 3.13-19: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Manteca Road / Project Driveway 4 intersection.
Impact 3.13-20: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Manteca Road / Project Driveway 5 intersection.
Impact 3.13-21: Under Cumulative conditions, the proposed Project would result in a
significant impact to freeway facilities.
Impact 4.2: Cumulative Degradation of the Existing Visual Character of the Region
Impact 4.4: Cumulative Impact on Agricultural Resources
Impact 4.5: Cumulative Impact on the Region's Air Quality
Impact 4.9: Cumulative Impact on Climate Change from Increased Project-Related
Greenhouse Gas Emissions
Impact 4.19: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Main Street / SR 120 ramp terminal intersections
Impact 4.21: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Main Street / Woodward Avenue intersection
Impact 4.22: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Main Street / Tannehill Drive / Project Driveway 3 intersection
Impact 4.23: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Woodward Avenue / Union Road intersection
Impact 4.24: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Union Road / Atherton Drive intersection
Impact 4.25: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Union Road / SR 120 ramp terminal intersections
Impact 4.26: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Main Street / Mission Ridge Drive / Industrial Park Drive
Impact 4.27: Under Cumulative conditions, the proposed Project would exacerbate levels
of service at the Manteca Road / Raymus Expressway intersection
Impact 4.28: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Manteca Road / Project Driveway 4 intersection
Impact 4.29: Under Cumulative conditions, the proposed Project would result in a
significant impact at the Manteca Road / Project Driveway 5 intersection
CEQA FINDINGS
CEQA Findings – Griffin Park Master Plan 91
Impact 4.30: Under Cumulative conditions, the proposed Project would result in a
significant impact to freeway facilities
The adverse effects listed above, and described in detail in Section III, are substantive issues of
concern to the City. However, the City of Manteca has a General Plan that provides for an array of
land uses throughout the City that are intended to accommodate the City’s needs for growth over
the foreseeable future. The proposed Project has been designated with land uses that are
intended to generate jobs and tax revenue for the City, while providing recreational and housing
opportunities. The proposed Project would provide an increase in local jobs that could be served
by the citizens of Manteca, reducing the number of citizens commuting, while providing nearby
housing opportunities for current and future residents. The actual number of jobs would vary by
the exact business that locates within the Plan Area. Additionally, the proposed Project would
generate tax revenue that the City would not otherwise benefit from if the Project was not
developed. The job creating uses, additional housing opportunities, and tax benefits discussed
above would ultimately improve the overall quality of life in the City of Manteca.
Based on the entire record and the EIR, the economic and social benefits of the Project in Manteca
outweigh and override any significant unavoidable environmental effects that would result from
future Project implementation as more fully described in Section III Findings and
Recommendations Regarding Significant and Unavoidable Impacts. The City Council has determined
that any environmental detriment caused by the proposed Project has been minimized to the extent
feasible through the mitigation measures identified herein, and, where mitigation is not feasible, has
been outweighed and counterbalanced by the significant social, environmental, and land use benefits
to be generated to the region.
CEQA FINDINGS
92 CEQA Findings – Griffin Park Master Plan
This page left intentionally blank.