+ All Categories
Home > Documents > CESC - Karnataka(hereinafter referred to as CESC) is a Distribution Licensee under the provisions of...

CESC - Karnataka(hereinafter referred to as CESC) is a Distribution Licensee under the provisions of...

Date post: 28-Jan-2021
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
279
KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2016 OF CESC ANNUAL PERFORMANCE REVIEW FOR FY15 & ANNUAL REVENUE REQUIREMENT FOR FY17-19 & REVISION OF RETAIL SUPPLY TARIFF FOR FY17 30 th March 2016 6 th and 7 th Floor, Mahalaxmi Chambers 9/2, M.G. Road, Bengaluru-560 001 Phone: 080-25320213 / 25320214 Fax : 080-25320338 Website: www.karnataka.gov.in/kerc - E-mail: [email protected]
Transcript
  • KARNATAKA ELECTRICITY REGULATORY COMMISSION

    TARIFF ORDER 2016

    OF

    CESC

    ANNUAL PERFORMANCE REVIEW FOR FY15

    &

    ANNUAL REVENUE REQUIREMENT FOR FY17-19

    &

    REVISION OF RETAIL SUPPLY

    TARIFF FOR FY17

    30th

    March 2016

    6th and 7th Floor, Mahalaxmi Chambers

    9/2, M.G. Road, Bengaluru-560 001

    Phone: 080-25320213 / 25320214

    Fax : 080-25320338

    Website: www.karnataka.gov.in/kerc - E-mail: [email protected]

    http://www.karnataka.gov.in/kerc

  • ii

    C O N T E N T S

    CHAPTER

    Page No.

    1.0 Chamundeshwari Electricity Supply Corporation

    Ltd.,

    3

    1.1 The CESC at a glance 5

    1.2 Number of Consumers, Sales in MU to various

    categories of consumers and details of Revenue

    for FY15

    5

    2 Summary of Filing and Tariff Determination

    Process

    7

    2.0 Background for current filing 7

    2.1 Preliminary Observations of the Commission 7

    2.2 Public Hearing Process 8

    2.3 Consultation with the Advisory Committee of the

    Commission

    9

    3.0 Public consultation – Suggestions / Objections

    and Replies

    10

    3.1 List of persons who filed written objections 10

    4 Annual Performance Review for FY15 12

    4.0 CESC’s Application for APR for FY15 12

    4.1 CESC’s Submission 12

    4.2 CESC’s Financial Performance as per Audited

    Accounts for FY15

    14

    4.2.1 Sales for FY15 15

    4.2.2 Distribution Losses for FY15 19

    4.2.3 Power Purchase for FY15 20

    4.2.4 RPO Compliance by CESC for FY15 23

    4.2.5 Operation and Maintenance Expenses 25

    4.2.6 Depreciation 28

    4.2.7 Capital Expenditure for FY15 30

    4.2.8 Prudence check of FY15 32

    4.2.9 Interest and Finance Charges 36

    4.2.10 Interest on Working Capital 37

    4.2.11 Interest on Consumer Deposit 38

    4.2.12 Other Interest and Finance Charges 39

    4.2.13 Interest o belated payment of power purchase

    cost

    39

    4.2.14 Capitalisation of Interest 39

    4.2.15 Other Debits 40

    4.2.16 Net Prior Period Charges 41

    4.2.17 Return on Equity 41

    4.2.18 Income Tax 42

    4.2.19 Other Income 42

    4.3 Abstract of Approved revised ARR for FY15 43

    4.3.1 Gap in Revenue for FY15 44

    5.0 Annual Revenue Requirement for FY17-19 –

    CESC’s filing

    45

  • iii

    5.1 Annual Performance Review for FY15 & FY16 46

    5.2 Annual Revenue Requirement for FY17-19 46

    5.2.1 Capital Investments for FY17-19 46

    5.2.2 Sales forecast for FY17-19 51

    5.2.3 Distribution Losses for FY17-19 63

    5.2.4 Power Purchase for FY17-19 65

    5.2.5 Sources of Power 66

    5.2.6 CESC’s Power Purchase Cost and Transmission

    Charges

    69

    5.2.7 RPO Target for FY17 72

    5.2.8 O & M Expenses for FY17-19 73

    5.2.9 Depreciation 76

    5.2.10 Interest on Capital Loan 77

    5.2.11 Interest on Working Capital 80

    5.2.12 Interest on Consumer Deposit 81

    5.2.13 Interest and other Expenses Capitalised 82

    5.2.14 Other Debits 83

    5.2.15 Net Prior Period Credit / Charges 83

    5.2.16 Return on Equity 73

    5.2.17 Other Income 85

    5.2.18 Fund towards Consumer Relations / Consumer

    Education

    86

    5.3 Treatment of Regulatory Asset 86

    5.4 Abstract of ARR for FY17-19 87

    5.5 Segregation of ARR into ARR for Distribution

    Business and ARR for Retail Supply Business

    88

    5.6 Gap in Revenue for FY17 90

    5.7 Application for Additional Revenue Requirement

    for FY17

    91

    6 Determination of Tariff for FY17 94

    6.0 CESC’s Proposal and Commission’s Analysis for

    FY17

    94

    6.1 Tariff Application 94

    6.2 Statutory Provisions Guiding Determination of

    Tariff

    94

    6.3 Consideration for Tariff Setting 95

    6.4 New Tariff Proposals by CESC 96

    6.5 Revenue at Existing Tariff and Deficit for FY16 99

    6.6 Other Issues 131

    6.6.1 Tariff for Green Power 131

    6.6.2 Determination of Wheeling Charges 132

    6.6.3 Wheeling within CESC area 132

    6.6.4 Wheeling of Energy using Transmission Network

    or network of more than one licensee

    134

    6.6.5 Charges for Wheeling of Energy by RE sources

    (non REC route) to consumer in the State

    135

    6.6.6 Charges for Wheeling Energy by RE sources

    wheeling energy from the State to a consumer /

    others outside the State and for those opting for

    renewable energy

    135

  • iv

    6.7 Other Tariff related issues 135

    6.8 Cross Subsidy Levels for FY17 140

    6.9 Effect of Revised Tariff 140

    6.10 Summary of Tariff Order 141

    6.11 Commission’s Order 142

    Appendix 143

    Appendix - I 183

  • v

    LIST OF TABLES

    Table

    No.

    Content Page

    No.

    4.1 Revised ARR for FY15 – CESC’s Submission 13

    4.2 CESC’s Financial Performance as per Audited

    Accounts for FY15

    14

    4.3 CESC’s Accumulated Profits / Losses 15

    4.4 Approved Sales as per APR for FY15 18

    4.5 Incentives for loss reduction in FY15 20

    4.6 CESC’s Power Purchase for FY15 21

    4.7 RPO Compliance as submitted by CESC for FY15 23

    4.8 Normative O & M Expenses – CESC’s Submission 25

    4.9 Approved O & M Expenses as per Tariff Order dated

    12.05.2014

    25

    4.10 O & M Expenses of CESC as per Annual Audited

    Accounts for FY15

    26

    4.11 Allowable O & M Expenses for FY15 28

    4.12 Depreciation for FY15 – CESC’s Submission 29

    4.13 Actual Capital Expenditure incurred by CESC for FY15 30

    4.14 Approved Vs Actual Capital Investment 32

    4.15 Gist of Prudence Check findings for FY15 33

    4.16 Allowable Interest on Loans – FY15 36

    4.17 Allowable Interest on Working Capital for FY15 38

    4.18 Allowable Interest and Finance Charges 39

    4.19 Other Debits CESC’s Submission 40

    4.20 Allowable other Debits 40

    4.21 Net Prior Period Charges – CESC’s Submission 41

    4.22 Allowable Return on Equity 42

    4.23 Approved Revised ARR for as per APR 43

    5.1 Proposed ARR for FY17-19 45

    5.2 Proposed Capital Investment by CESC for FY17 to

    FY19

    48

    5.3 Category wise approved number of installations 62

    5.4 Category wise approved energy sales 62

    5.5 Projected Distribution Losses FY17-19 – CESC’s

    Submission

    63

    5.6 Approved & Actual Distribution Losses – FY11 to FY16 64

    5.7 Approved Distribution Losses for FY17-19 65

    5.8 Consolidated requirement of electricity as filed by

    ESCOMs

    65

    5.9 Source wise Power Purchase of ESCOMs for the

    Control Period FY17 to FY19

    68

    5.10 Power Purchase Cost of CESC for FY17 70

    5.11 Power Purchase Cost of CESC for FY18 71

    5.12 Power Purchase Cost of CESC for FY19 71

    5.13 O & M Expenses – CESC’s Proposal 74

  • vi

    5.14 Computation of Inflation Index for FY17 74

    5.15 Approved O & M Expenses for FY17-19 75

    5.16 Depreciation – FY17-19 – CESC’s proposal 76

    5.17 Approved Depreciation for FY17-19 77

    5.18 Interest on Capital Loans – CESC’s Proposal 78

    5.19 Approved Interest on Capital Loans for FY17-19 79

    5.20 Interest on Working Capital – CESC’s Submission 80

    5.21 Approved Interest on Working Capital for FY17-19 81

    5.22 Interest on Consumer Security Deposits for FY17-19 –

    CESC’s Proposal

    81

    5.23 Approved Interest on Consumer Security Deposits for

    FY17-19

    82

    5.24 Approved Interest and Finance Charges for FY17-19 82

    5.25 Status of Debt Equity Ratio for FY17-19 84

    5.26 Return on Equity for FY17-19 85

    5.27 Other Income – CESC’s Proposal 85

    5.28 Approved Other Income for FY17-19 86

    5.29 Approved ARR for FY17-19 88

    5.30 Approved Segregation of ARR – FY17-19 – CESC’s

    Proposal

    89

    5.31 Approved Segregation of ARR FY17-19 89

    5.32 Approved Revised ARR for Distribution Business – FY17-

    19

    90

    5.33 Approved ARR for Retail Supply Business FY17-19 90

    5.34 Revenue Gap for FY17 91

    6.1 Revenue Deficit for FY17 99

    6.2 Wheeling Charges 133

  • vii

    LIST OF ANNEXURES

    SL.NO. DETAILS OF ANNEXURES Page

    No.

    I Total Approved Power Purchase Quantum and Cost

    of all ESCOMs for FY17

    210

    II Approved Power Purchase quantum and cost of

    CESC for FY17

    216

    III Proposed and approved Revenue for FY17 222

    IV Electricity Tariff – 2017 223

  • viii

    ABBREVIATIONS

    AAD Advance Against Depreciation

    AEH All Electric Home

    ABT Availability Based Tariff

    A & G Administrative & General Expenses

    ARR Annual Revenue Requirement

    ATE Appellate Tribunal for Electricity

    BBMP Bruhut Bangalore Mahanagara Palike

    BDA Bangalore Development Authority

    BESCOM Bangalore Electricity Supply Company

    BMP Bangalore Mahanagara Palike

    BST Bulk Supply Tariff

    BWSSB Bangalore Water Supply & Sewerage Board

    CAPEX Capital Expenditure

    CCS Consumer Care Society

    CERC Central Electricity Regulatory Commission

    CEA Central Electricity Authority

    CESC Chamundeshwari Electricity Supply Corporation

    CPI Consumer Price Index

    CWIP Capital Work in Progress

    DA Dearness Allowance

    DCB Demand Collection & Balance

    DPR Detailed Project Report

    EA Electricity Act

    EC Energy Charges

    ERC Expected Revenue From Charges

    ESAAR Electricity Supply Annual Accounting Rules

    ESCOMs Electricity Supply Companies

    FA Financial Adviser

    FKCCI Federation of Karnataka Chamber of Commerce & Industry

    FR Feasibility Report

    FoR Forum of Regulators

    FY Financial Year

    GESCOM Gulbarga Electricity Supply Company

    GFA Gross Fixed Assets

    GoI Government Of India

    GoK Government Of Karnataka

    GRIDCO Grid Corporation

    HESCOM Hubli Electricity Supply Company

    HP Horse Power

    HRIS Human Resource Information System

    ICAI Institute of Chartered Accountants of India

    IFC Interest and Finance Charges

    IW Industrial Worker

  • ix

    IP SETS Irrigation Pump Sets

    KASSIA Karnataka Small Scale Industries Association

    KEB Karnataka Electricity Board

    KER Act Karnataka Electricity Reform Act

    KERC Karnataka Electricity Regulatory Commission

    KM/Km Kilometre

    KPCL Karnataka Power Corporation Limited

    KPTCL Karnataka Power Transmission Corporation Limited

    KV Kilo Volts

    KVA Kilo Volt Ampere

    KW Kilo Watt

    KWH Kilo Watt Hour

    LDC Load Despatch Centre

    MAT Minimum Alternate Tax

    MD Managing Director

    MESCOM Mangalore Electricity Supply Company

    MFA Miscellaneous First Appeal

    MIS Management Information System

    MoP Ministry of Power

    MU Million Units

    MVA Mega Volt Ampere

    MW Mega Watt

    MYT Multi Year Tariff

    NFA Net Fixed Assets

    NLC Neyveli Lignite Corporation

    NCP Non Coincident Peak

    NTP National Tariff Policy

    O&M Operation & Maintenance

    P & L Profit & Loss Account

    PLR Prime Lending Rate

    PPA Power Purchase Agreement

    PRDC Power Research & Development Consultants

    REL Reliance Energy Limited

    R & M Repairs and Maintenance

    ROE Return on Equity

    ROR Rate of Return

    ROW Right of Way

    RPO Renewable Purchase Obligation

    SBI State Bank of India

    SCADA Supervisory Control and Data Acquisition System

    SERCs State Electricity Regulatory Commissions

    SLDC State Load Despatch Centre

    SRLDC Southern Regional Load Dispatch Centre

    STU State Transmission Utility

    TAC Technical Advisory Committee

    TCC Total Contracted Capacity

  • x

    T&D Transmission & Distribution

    TCs Transformer Centres

    TR Transmission Rate

    VVNL Visvesvaraya Vidyuth Nigama Limited

    WPI Wholesale Price Index

    WC Working Capital

  • xi

    KARNATAKA ELECTRICITY REGULATORY COMMISSION,

    BANGALORE - 560 001

    Dated this 30th day of March, 2016

    Order on CESC’s Annual Performance Review for FY15 & Annual Revenue

    Requirement for FY17-19 & Revision of

    Retail Supply Tariff for FY17

    In the matter of:

    Application of CESC in respect of the Annual Performance Review for FY15,

    Annual Revenue Requirement for FY17-19 and Revision of Retail Supply Tariff

    for FY17, under Multi Year Tariff framework.

    Present: Shri M.K.Shankaralinge Gowda Chairman

    Shri H.D.Arun Kumar Member

    Shri D.B.Manival Raju Member

    O R D E R

    The Chamundeshwari Electricity Supply Corporation Ltd.,

    (hereinafter referred to as CESC) is a Distribution Licensee under

    the provisions of the Electricity Act, 2003, and has, on 30.11.2015

    & 15.12.2015, filed the following applications for consideration

    and orders:

    a) Review of Annual Performance for FY15 and approval of

    revised ARR thereon.

    b) Approval of ARR for FY17-19

  • xii

    c) Approval for revision of Retail Supply Tariff, for the financial

    year 2016-17 (FY17)

    In exercise of the powers conferred under Sections 62, 64 and other

    provisions of the Electricity Act, 2003, read with KERC (Terms and

    conditions for Determination of Tariff for Distribution and Retail Sale of

    Electricity) Regulations 2006, and other enabling Regulations, the

    Commission has considered the applications and the views and

    objections submitted by the consumers and other stakeholders. The

    Commission’s decisions are given in this order, Chapter wise.

  • xiii

    CHAPTER – 1

    INTRODUCTION

    1.0 Chamundeshwari Electricity Supply Corporation Ltd.:

    The Chamundeshwari Electricity Supply Corporation Ltd., (CESC) is a

    Distribution Licensee under Section 14 of the Electricity Act, 2003

    (hereinafter referred to as the Act). The CESC is responsible for

    purchase of power, distribution and retail supply of electricity to its

    consumers and also providing infrastructure for open access, Wheeling

    and Banking in its area of operation which includes five Districts of the

    State as indicated below:

    1. Mysuru

    2. Hassan

    3. Mandya

    4. Chamarajnagara

    5. Kodagu

    The CESC is a registered company under the Companies Act, 1956,

    incorporated on 19th August, 2004. The CESC commenced its

    operations on 1st April, 2005, with four districts in its area of operation.

    Further, the Madikeri Division (Kodagu District) which was earlier under

    the MESCOM, was transferred to the CESC with effect from 1st April,

    2006.

    At present the CESC’s area of operations is structured as follows:

    CESC, Mysore

    HASSAN

    MANDYA

    KODAGU MYSORE

    CH NAGAR

  • xiv

    O&M Zones O&M Circles O&M Divisions

    Mysore zone

    Mysore Works Circle

    VV Mohalla

    NR Mohalla

    Nanjangud

    Hunsur

    Mysore O&M Circle

    Chamarajnagar

    Kolegala

    Madikeri

    Hassan Circle

    Hassan

    CR patna

    Arasikere

    HN Pura

    Mandya Circle

    Mandya

    Pandavapura

    Nagamangala

    Maddur

    These O & M divisions of the CESC are further divided into sixty one

    O&M sub-divisions with accounting / non accounting sections.

    The section offices are the base level offices looking into operation

    and maintenance of the distribution system in order to provide reliable

    and quality power supply to the CESC’s consumers.

  • xv

    1.1 The CESC at a glance:

    The profile of the CESC is as indicated below:

    1.2

    Number of Consumers, Sales in MU to various

    categories of consumers and details of Revenue for FY15

    are as follows:

    CATEGORY

    CESC

    No. of

    Installation

    Sales in

    MU

    Revenue in

    Rs.Crs.

    Domestic 2121040 937.94 391.04

    Commercial 197847 354.35 287.57

    Industrial 35276 883.01 568.45

    Agriculture 305791 2355.47 940.02

    Others 75848 709.3 442.16

    Total 2735802 5240.07 2629.24

    The CESC has filed its application for Annual Performance Review for FY15,

    Annual Revenue Requirement (ARR) for FY17-19 and revision of Retail Supply

    Tariff for FY17.

    The CESC’s application, the objections / views of stakeholders thereon and the

    Commission’s decisions on the Annual Performance Review for FY15, ARR for

    Sl.

    No. Particulars (As on 31.03.2015) Statistics

    1. Area Sq. km. 27772.82

    2. Districts Nos. 5

    3. Taluks Nos. 29

    4. Population lakhs 81.55

    5. Consumers Lakhs 27.36

    6. Energy Sales MU 5240.07

    7. Zone Nos. 1

    8. DTCs Nos. 84086

    9. Assets (including current assets) Rs. in Crores 4806.40

    10. HT lines Ckt. kms 42658

    11. LT lines Ckt. kms 75117

    12. Total employees strength:

    A Sanctioned Nos. 10411

    B Working Nos. 5048

    13. Revenue Demand in FY15 Rs. in Crores 2629.24

    14. Revenue Collection in FY15 Rs. in Crores 2483.34

  • xvi

    FY17-19 and Revision of Retail Supply Tariff for FY17 are discussed in detail in

    the subsequent Chapters of this Order.

  • xvii

    CHAPTER – 2

    SUMMARY OF FILING & TARIFF DETERMINATION PROCESS

    2.0 Background for Current Filing:

    The Commission in its Tariff Order dated 6th May, 2013 had approved

    the ERC for FY14 to FY16 and the Retail Supply Tariff of CESC for FY14

    under MYT principles for the control period of FY14 to FY16. CESC in its

    present application filed on 15th December, 2015 has sought for

    Annual Performance Review (APR) for FY15 based on the audited

    accounts, ARR for the fourth control period i.e. FY17-19 and revision of

    Retail Supply Tariff for FY17.

    2.1 Preliminary Observations of the Commission

    After a preliminary scrutiny of applications the Commission had

    communicated its observations to CESC on 1st January, 2016 which

    were mainly on the following points:

    Capital Expenditure

    Sales Forecast

    Assessment of IP set consumption

    Power Purchase

    Issues pertaining to items of revenue and expenditure

    Other new proposals

    Compliance to Directives

    The CESC has furnished its replies on 11th January, 2016. The replies

    furnished by CESC are considered in the respective Chapters of this Order.

    Further, the Commission also held a validation meeting to discuss the

    proposals of CESC on 10th February, 2016.

  • xviii

    2.2 Public Hearing Process:

    As per the Karnataka Electricity Regulatory Commission (Terms and

    Conditions for Determination of Tariff for Distribution and Retail Sale of

    Electricity) Regulations, 2006, read with the KERC Tariff Regulations,

    2000, and KERC (General and Conduct of Proceedings) Regulations,

    2000, the Commission vide its letter dated 14th January, 2016 treated

    the application of CESC as petition and directed CESC to publish the

    summary of ARR and Tariff proposals in the newspapers calling for

    objections, if any, from interested persons.

    Accordingly, CESC has published the same in the following newspapers:

    Name of the News Paper Language Date of Publication

    Deccan Herald English 18/1/2016

    &

    19/1/2016

    The Hindu

    Udayavani Kannada

    Kannada Prabha

    The CESC’s applications on APR of FY15, ARR for FY17-19 and revision of

    retail supply tariff for FY17 were also hosted on the web sites of CESC and

    the Commission for the ready reference and information of the general public.

    In response to the application of CESC, the Commission has received thirty

    seven statements / letters of objections. CESC has furnished its replies to all

    these objections. The Commission has held a Public Hearing on 27th

    February, 2016 at Mysore. The details of the written / oral submissions made

    by various stake holders and the response from CESC thereon have been

    discussed in Chapter - 3 / Appendix to this Order.

    2.3 Consultation with the Advisory Committee of the Commission:

    The Commission has also discussed the proposals of KPTCL and all

    ESCOMs in the State Advisory Committee meeting held on 10th March, 2016.

    During the meeting the following important issues were also discussed:

  • xix

    Performance of KPTCL / ESCOMs during FY15

    Major items of expenditure of KPTCL / ESCOMs for FY17-19

    Members of the Committee have offered valuable suggestions on the

    proposals. The Commission has taken note of these suggestions while

    passing the order.

  • xx

    CHAPTER – 3

    PUBLIC CONSULTATION

    SUGGESTIONS / OBJECTIONS & REPLIES

    3.1 In pursuance of section 64 of the Electricity Act, 2003, the Commission

    undertook the process of public consultation, to obtain

    suggestions/views/objections from the interested stake-holders, on the

    application filed by CESC, for Annual Performance Review for FY15,

    approval of ERC, and ARR for FY17, FY18 and FY19 and approval of

    revised retail supply tariff for FY17, under the MYT Principle. In the

    written submissions as well as during the public hearing, the Stake-

    holders and the public have raised several objections/ made

    suggestions, on the Tariff Application. The names of the persons who

    have filed written objections and made oral submissions are given

    below:

    List of persons who filed written objections:-

    Sl.

    No

    Application

    No. Name & Address of Objectors

    1 CB-01 Sri Yagnanarayana M.N, General Secretary, Laghu Udyog

    Bharati – Karnataka, Bengaluru.

    2 CB-02 Sri Chetan Jain, AM- Business Development, Indian Energy

    Exchange Limited, New Delhi.

    3 CA-01 Sri N. Ravidranath & others, Madhuvanahalli, Kollegala.

    4 CA-02 Sri R. Ramanna, Financial Advisor & Chief Accounts Officer,

    BWSSB, Bengaluru.

    5 CA-03 Sri K.B. Arasappa, Hon. Gen. Secretary, KASSIA, Bengaluru.

    6 CA-04 Sri Anil Savur D, Secretary, The Karnataka Planters Association,

    Chikmagaluru

    7 CA-05 Sri M.M. Suryanarayana, General Secretary, Akhila Bharatiya

    Grahak Panchayat ( R). Mysuru.

    8

    CA-06

    Sri K. Ravindra Prabhu, Vice President, KIADB Industrial Area

    Manufactures Association, Mysuru.

    9 CA-07 Sri P.B. Chengappa, Chairman, Kodagu Planters Association,

    Kodagu.

    10 CA-08 Sri C.A. Subbaiah, Vice President, Kodagu District Small Growers

    Association, Kodagu.

    11 CA-09 Sri Lokaraj, Secretary, Federation of Karnataka Chambers of

    Commerce and Industry Bengaluru.

    12 CA-10 Sri K. Ravindra Prabhu, Chairman, Energy Subcommittee,

    Hebbal Industrial Estate Manufacturers Association, Mysuru.

    13 CA-11 to

    CA-35

    Sri S.B. Kempegowda & others, Mandya, Maddur,

    Nagamangala, Pandavapura, T. Narasipura and Mysuru.

    14 AE-01 Sri P.N. Karanth, Kundapura.

    15 AE-02 Sri Praveen Sood, IPS, Additional Director General of Police,

    Administration, Bengaluru

  • xxi

    3.2 List of the persons, who made oral submissions during the Public

    Hearing, held on 27.02.2016.

    SL.No. Names & Addresses of Objectors

    1 Sri K. Ravindra Prabhu, Vice President, KIADB Industrial Area Manufacturers

    Association & Hebbal Industrial Estate Manufacturers Association.

    2 Sri Suresh Kumar Jain, Mysuru Industries Association

    3 Sri Mallappa Gowda & Manjunath, KASSIA.

    4 Sri Savitha Ranganath, The Call, Secretary General, CVO.

    5 Sri Rajesh Kadi, Anti-Corruption Committee, Mysuru.

    6 Sri N. Nataraj, Chamarajanagar Kissan Sangha.

    7 Sri Y.M. Raju, Hassan District Kissan Sangha.

    8 Sri Anil Savur, Secretary, Karnataka Planters Association.

    9 Sri Mohd. Arif Khan, Advocte, BWSSB.

    10 Sri Vasanth. S. Karnataka State Electrical Contractors Association.

    11 Sri Anselm Nazareth, Consumer, Mysuru.

    12 Sri Rajendra, Bharatiya Kissan Sangha, Chamarajanagar.

    13 Sri K.V. Siddappa, Hanuru Kissan Sangha.

    14 Sri Chethan Jain, IEx.

    15 Sri Capt. M.A. Hussain, Mysuru.

    16 Sri Biddappa M.C, Orange County.

    3.3 The gist of the objections, replies by CESC and the Commission’s views

    in Appendix-1 of this order.

  • xxii

    CHAPTER – 4

    ANNUAL PERFORMANCE REVIEW FOR FY15

    4.0 CESC’s Application for APR for FY15:

    The CESC, in its application dated 30th November, 2015, has sought for

    review of its Annual Performance (APR) for FY15 and approval of a

    revised ARR thereon, based on the Audited Accounts.

    The Commission in its letter dated 1st January, 2016 had communicated

    its preliminary observations on the application of CESC. The CESC, in its

    letter dated 11th January, 2016 has furnished its replies to the

    preliminary observations of the Commission.

    The Commission in its Multi Year Tariff (MYT) Order dated 6th May, 2013

    had approved the CESC’s Annual Revenue Requirement (ARR) for

    FY14 – FY16. Further, in its Tariff Order dated 12th May, 2014, the

    Commission had approved the APR for FY13 and had revised the ARR

    for FY15 along with Retail Supply Tariff for FY15.

    The Annual Performance Review for FY15 based on the CESC’s Audited

    Accounts is discussed in this Chapter.

    4.1 CESC’s Submission:

    The CESC has submitted its proposals for revision of ARR for FY15 based

    on the Audited Accounts as follows:

  • xxiii

    TABLE – 4.1

    Revised ARR for FY15 – CESC’s Submission Amount in Rs. Crores

    Sl.

    No Particulars As Filed

    1 Energy @ Gen Bus in MU 6299.35

    2 Energy @ Interface in MU 6084.89

    3 Distribution Losses in % 13.88

    Sales in MU

    4 Sales to other than IP & BJ/KJ installations 2911.20

    5 Sales to IP & BJ/KJ installations 2328.87

    Total Sales 5240.07

    Revenue in Rs Crs

    6 Revenue from tariff and Misc. Charges 1671.36

    7 RE Subsidy 957.87

    Total Revenue 2629.23

    Expenditure in Rs Crs

    8 Power Purchase Cost 1894.39

    9 Transmission charges of KPTCL 265.50

    10 SLDC Charges 3.42

    Power Purchase Cost including cost of

    transmission 2163.31

    11 Employee Cost 294.33

    12 Repairs & Maintenance 37.56

    13 Admin & General Expenses 39.55

    Total O&M Expenses 371.44

    14 Depreciation 46.08

    Interest & Finance charges

    15 Interest on Loans 78.85

    16 Interest on Working capital 1.41

    17 Interest on belated payment of power purchase 1.54

    18 Interest on consumer deposits 37.09

    19 Other Interest & Finance charges 2.44

    20 Less interest & other expenses capitalised 27.71

    Total Interest & Finance charges 93.62

    21 Other Debits 4.94

    22 Net Prior Period Debit/Credit (72.44)

    23 Return on Equity 0.00

    24 Tax 15.78

    25 Other Income 33.77

    Net ARR 2588.96

    Considering a revenue of Rs.2629.23 Crores against a net ARR of

    Rs.2588.96 Crores, the CESC has reported surplus in revenue of Rs.40.27

    Crores for FY15.

  • xxiv

    4.2 CESC’s Financial Performance as per Audited Accounts for FY15:

    An overview of the financial performance of the CESC for FY15 as per

    their Audited Accounts is given below:

    TABLE – 4.2

    Financial Performance of CESC for FY15

    Amount in Rs. Crores

    Sl.

    No. Particulars FY15

    Receipts

    1 Revenue from Tariff and misc. charges 1671.36

    2 Tariff Subsidy 957.87

    Total Revenue 2629.23

    Expenditure

    3 Power Purchase Cost 1894.39

    4 Transmission charges of KPTCL 265.50

    5 SLDC Charges 3.42

    Power Purchase Cost including cost of transmission 2163.31

    6 O&M Expenses 371.45

    7 Depreciation 46.08

    Interest & Finance charges

    8 Interest on Loans 55.39

    9 Interest on Working capital 24.88

    10 Interest on consumer deposits 37.08

    11 Interest on belated payment of power purchase

    cost 1.54

    12 Other Interest & Finance charges 2.44

    13 Less interest and other expenses capitalized 27.71

    Total Interest & Finance charges 93.62

    14 Other Debits 4.94

    15 Net Prior Period Debit/Credit (72.44)

    16 Other income 32.77

    17 Income tax 15.77

    Net ARR 2588.96

    As per the Audited Accounts, the CESC has earned a profit of Rs.40.27

    Crores for FY15. The profits / losses reported by the CESC in its audited

    accounts in the previous years are as follows:

  • xxv

    TABLE – 4.3

    CESC’s Accumulated Profits / Losses

    Particulars

    Amount in

    Rs. Crs

    Accumulated losses as at the end of FY10 (285.15)

    Profit earned in FY11 11.38

    Loss incurred in FY12 (123.45)

    Loss incurred in FY13 (269.63)

    Loss incurred in FY14 (15.61)

    Profits earned in FY15 40.27

    Accumulated losses as at the end of FY15 (642.19)

    As seen from the above table, the accumulated losses are Rs.642.19

    Crores.

    Commission’s analysis and decisions:

    The Annual Performance Review for FY15 has been taken up duly

    considering the actual expenditure as per the Audited Accounts

    against the expenditure approved by the Commission in its Tariff Order

    dated 12th May, 2014. The item wise review of expenditure and the

    decisions of the Commission thereon are as discussed in the following

    paragraphs:

    4.2.1 Sales for FY15:

    a) Sales-Other than IP sets

    The Commission in its Tariff order dated 12.05.2014 had approved for

    FY15 total sales to various consumer categories at 5448.45 MU as

    against the CESC proposal of 5596.11 MU. The Actual sales of CESC as

    per the current APR filing [FORMAT D-2] is 5240.09 MU, indicating a short

  • xxvi

    fall in sales to an extent of 208.36 MU vis-à-vis the approved sales. The

    shortfall in sales is 104.21 MU in LT-categories and104.15 MU in HT-

    categories.

    The Commission notes that, as against approved sales of 2997.80 MUs

    to categories other than BJ/KJ and IP sets, the actual sales achieved

    by CESC is 2911.22 MU, resulting in shortfall of sales to these categories

    by 86.58 MU. Further, the CESC has sold 2328.87 MU to BJ/KJ and IP

    categories against approved sales of 2450.65 MU resulting in lower

    sales to these categories by 121.78 MU.

    The actual share of sales to categories other than BJ/KJ and IP sets is

    55.56% as against the estimated share of 55.02% resulting in marginal

    increase in share of sales to these categories, while the actual share of

    sales to BJ/KJ and IP sets has taken short by the same percentage

    point. The Commission notes that the major categories contributing to

    the lower sales are HT Industries (134.79 MU), HT Commercial (27.23 MU)

    and IP sets (121.46 MU).

    b) Sales to IP sets

    In its Tariff Order dated 6th May, 2013, the Commission had approved

    specific consumption of IP sets at 8,195 units/installation/annum for the

    entire control period of FY14 to FY16, whereas, as per the IP set

    consumption reported by the CESC in its filing, the specific

    consumption works out to 7,843 units /installation/annum for the FY15,

    which indicates a decrease in the specific consumption of 352

    units/installation/annum. The total IP set consumption reported by the

    CESC for the FY15 is 2,294.33 MU as against 2,415.79 MU sales quantum

    approved by the Commission. Thus, the specific consumption has

    decreased by 352 units /installation/annum with the corresponding

    decrease in sales by 121.46 MU when compared to those approved by

    the Commission for the FY15.

  • xxvii

    Further, the Commission had approved 3,16,336 as number of

    installations likely to be serviced in the FY 15; whereas the actual

    number of installations serviced as reported by the CESC is 3,00,070.

    The difference in number of installations is 16,266. This indicates

    decrease of around 5 per cent in number of installations serviced, as

    compared to the approved number of installations by the Commission

    for the FY15. Further, it is noted that the shortfall in the sales can be

    attributed to lower number of installations serviced than the projected

    numbers.

    The Commission in its Tariff Order dated 12th May, 2014 had directed

    the CESC to furnish feeder wise IP set consumption based on the

    feeder energy meter data, every month to the Commission, in respect

    of agricultural feeders segregated under NJY. The CESC in its tariff

    application has submitted the data of IP sets from April 14, to March 15,

    without indicating as to how much loss in 11 kV lines, distribution

    transformers and LT system has been deducted from the gross

    consumption obtained from the agricultural feeders, to arrive at the

    net IP set consumption.

    The Commission in its preliminary observations had directed the CESC

    to justify its claims of IP consumption of 2,294.33 MU declared for the

    FY15 with necessary data in support of the same and the methodology

    adopted to arrive at the energy loss figures in the 11 kV System. The

    CESC was also directed to explain whether the total IP set

    consumption for the FY15 has been worked out by considering the

    specific consumption of agricultural feeders segregated under NJY or

    on the basis of readings obtained from the meters fixed to sample

    DTCs feeding predominantly IP set loads, with the necessary data to

    justify its claims in support of IP sales declared for the FY15.

    The CESC, in its reply to the preliminary observations made by the

    Commission, has stated that it has submitted the IP set details based on

    the energy meters data in respect of the segregated agricultural

  • xxviii

    feeders as desired by the Commission and the distribution system loss

    figures at 15 per cent has been considered to arrive at the net IP set

    consumption from April, 2014 to March 2015.

    Further, the CESC during the validation meeting held on 10.02.2016 in

    the Commission has also submitted the necessary data in respect of IP

    set consumption for the FY15 on the basis of energy meter readings of

    11 kV agricultural feeders which have been segregated under NJY.

    The Commission notes that the decrease in IP set sales for the FY15 can

    be attributed to the fact that the CESC has serviced less number of IP

    sets than it has projected. However, it is also noted that the specific

    consumption as well as the sales have significantly decreased vis-à-vis

    the approved quantities by the Commission for the FY15 perhaps due

    to restricted hours of power supply made to agricultural feeders which

    are segregated under NJY. The Commission also notes that the CESC

    has declared overall 11 kV distribution system losses at 15 per cent,

    whereas, the same could have been directly calculated for each

    feeder considering the 11 kV and LT sketches in respect of all the

    agricultural feeders to arrive at accurate IP set consumption.

    The CESC is directed to report henceforth the total IP set consumption

    on the basis of data from energy meters in respect of agricultural

    feeders segregated under NJY to the Commission every month

    regularly duly calculating the distribution system losses in 11 KV lines,

    distribution transformers and LT lines, as discussed above.

    For the present, the Commission decides to accept the sales to IP sets

    for the FY15 as 2,294.33 MU as submitted by the CESC.

    The category wise sales approved by Commission and the actuals for

    FY 15 are indicated in the table below:

    TABLE – 4.4

    Approved Sales as per APR for FY15

    Figures in MU

    Category Approved Actuals Actuals - Approved

  • xxix

    LT-2a* 889.51 903.40 13.89

    LT-2b 6.65 7.21 0.56

    LT-3 249.02 245.89 -3.13

    LT-4b 0.71 0.89 0.18

    LT-4c 8.55 9.77 1.22

    LT-5 133.93 138.74 4.81

    LT-6 147.85 140.98 -6.87

    LT-6 83.16 90.40 7.24

    LT-7 11.92 11.59 -0.33

    HT-1 392.45 413.98 21.53

    HT-2a 879.06 744.27 -134.79

    HT-2b 135.69 108.46 -27.23

    HT-2c 7.80 36.63 28.83

    HT-3a & b 40.90 50.48 9.58

    HT-4 9.06 5.82 -3.24

    HT-5 1.54 2.71 1.17

    Sub total 2997.80 2911.22 -86.58

    BJ/KJ 34.86 34.54 -0.32

    IP 2415.79 2294.33 -121.46

    Sub total 2450.65 2328.87 -121.78

    Grand total 5448.45 5240.09 -208.36

    *Including BJ/KJ installations consuming more than 18 units/month

    Thus the Commission approves the energy sales for FY15 at 5240.09 MU.

    4.2.2 Distribution Losses for FY15:

    CESC’s Submission:

    The Commission had approved distribution losses for FY15 as

    shown in the table below:

    Range FY15

    Upper limit 15.50%

    Average 15.00%

    Lower Limit 14.50%

    CESC has reported a loss level of 13.88% for FY15 as detailed

    below:

  • xxx

    1 Energy at Interface Points in MU 6084.89

    2 Total sales in MU 5240.07

    3 Distribution losses as a percentage of

    input energy at IF points 13.88%

    Commission’s analysis and decisions:

    The distribution losses of 13.88% reported by CESC is based on the sales

    of 5240.09 MU as against the energy of 6084.89 MU at interface points.

    Considering the approved range of losses for FY15, CESC has achieved

    distribution loss reduction of 0.62% as compared to the lower limit of

    allowable losses. As per the provisions of the MYT Regulations,

    incentives for loss reduction is allowed to CESC as follows:

    TABLE – 4.5

    Incentives for loss reduction in FY15

    Particulars FY15

    Actual input at IF points as per audited accounts in

    MU 6084.89

    Retail sales as per audited accounts in MU 5240.07

    Percentage distribution losses 13.88%

    Target of lower limit of distribution loss 14.50%

    Reduction in loss in percentage point 0.62%

    Input at target loss for actual sales in MU 6128.74

    Decrease in input due to reduction in distribution

    losses in MU 43.85

    Average cost of power purchase @ IF points in

    Rs./unit 3.43

    Reduction in power purchase cost due to lower

    distribution losses in Rs. Crores 15.06

    Incentives allowed in APR 15 (Sharing gains with

    consumers in the ratio of 50:50) in Rs.Crs. 7.53

    Accordingly, the Commission decides to add an amount of Rs.7.53

    Crores as incentive towards loss reduction in the revised ARR for FY15.

    4.2.3 Power Purchase for FY15:

    CESC’s Submission:

  • xxxi

    1. The Commission in its Tariff order dated 12th May, 2014 had

    approved source-wise quantum and cost of power purchase for

    FY15. The CESC, in its application has submitted the details of actual

    power purchase for FY15 for its Annual Performance Review. The

    details of power purchase are detailed as under:

  • xxxii

    TABLE – 4.6

    CESC’s POWER PURCHASE FOR FY15

    Particulars

    Actuals for FY15 Approved for FY15

    Difference of Actuals

    over the Approved-for

    FY15

    % increase /decrease

    over approved figures

    Energy

    in MUs

    Cost in

    Rs Crs.

    Rate

    in Rs

    per

    Unit

    Energy

    in MUs

    Cost in

    Rs Crs.

    Rate

    in Rs

    per

    Unit

    Energy

    in MUs

    Cost

    in Rs

    Crs.

    Rate

    in Rs

    per

    Unit

    Energy Cost Rate

    KPCL Hydel

    Stations

    1808.49 105.07 0.58 1793.84 101.74 0.57 14.65 3.33 0.01 0.82 3.27 2.44

    KPCL-Thermal

    Stations

    1627.55 627.25 3.85 1694.06 645.15 3.81 -66.51 -17.90 0.05 -3.93 -2.77 1.20

    Total 3436.04 732.32 2.13 3487.9 746.89 2.14 -51.86 -14.57 -0.01 -1.49 -1.95 -0.47

    CGS 1451.01 439.02 3.03 1578.31 503.76 3.19 -127.30 -64.74 -0.17 -8.07 -12.85 -5.21

    Major IPPs 38.90 16.76 4.31 0.78 0.36 4.62 38.12 16.40 -0.31 4887.18 4555.56 -6.65

    IPPs -Minor

    (NCE

    Projects)

    615.03 220.92 3.59 895.83 318.51 3.56 -280.80 -97.59 0.04 -31.35 -30.64 1.03

    Other States

    Projects

    15.86 4.74 2.99 21.7 6.91 3.18 -5.84 -2.17 -0.20 -26.91 -31.40 -6.15

    Short

    /Medium

    term

    including U I

    & Sce-11

    910.78 476.02 5.23 679.31 354.33 5.22 231.47 121.69 0.01 34.07 34.34 0.20

    Transmission

    Charges

    (KPTCL &

    PGCIL)

    318.47 309.9 0.00 8.57 0.00 2.77

    LDC Charges

    (POSOO &

    SLDC)

    3.77 3.56 0.00 0.21 0.00 5.90

    Energy

    Balancing

    -168.23 -53.27 3.17 -168.23 -53.27 3.17

    Others

    Charges

    4.52 0.00 4.52 0.00

    TOTAL 6299.39 2163.31 3.43 6663.83 2244.22 3.37 -364.44 -80.95 0.07 -5.47 -3.61 1.97

    Commission’s analysis and decisions;

    1. The actual power purchase for FY15 as filed by the CESC for

    approval of Annual Performance Review is 6299.39 MU at a cost of

    Rs.2163.97 Crores, as against the approved quantum of 6663.83 MU,

    amounting to Rs.2244.22 Crores. Thus there is reduction in quantum

    of power purchased to an extent of 364.44 MU and in cost by

    Rs.80.95 Crores.

  • xxxiii

    2. On an analysis of the source-wise approved and actual power

    purchases, the following deviations in quantum of energy and its

    cost of purchase are found:

    i. As against the approved quantum of 6663.83 MU the actual

    power purchased by the CESC is 6299.39 MU for FY15, which is

    around 5.47% of the approved quantum. Such decrease during

    FY14 was 3.39%. This has reflected in reduction in power

    purchase.

    ii. On a verification of the source-wise power purchase, it is found

    that, there is lesser energy supply from KPCL thermal, CGS, NCE

    and outside the State projects to an extent of 480.45 MU at a cost

    of Rs.182.40 Crores. Consequently, CESC has purchased

    additional power from KPCL hydel, major IPPs and Short-term

    supplies, over and above the approved power purchase against

    these sources, to a tune of 284.24 MU, incurring an expenditure of

    Rs.141.42 Crores. However, there is an overall reduction in power

    purchase to a tune of Rs.80.95 Crores. Consequent to reduced

    supply of energy from KPCL thermal, CGS, NCE etc., the power

    purchase cost per unit, has increased by 7 paise.

    iii. All these factors including the change in the source-wise mix of

    supply and reconciliation of energy and its cost among ESCOMs

    have resulted in higher average power purchase cost of CESC at

    Rs.3.43 per KWh as against the approved rate of Rs.3.37 per KWh

    leading to an overall increase by Rs.0.07 per unit. During FY 14 the

    increase in per unit cost was Rs.0.29 per unit which worked out to

    9.66 %. Now, for FY15, the increase in per unit cost is 1.97 %.

    iv. D1 format of CESC indicates energy balancing among other

    ESCOMs to an extent of 168.23 MU amounting to Rs.53.27 Crores,

    which has been reconciled with Energy Balancing Statement of

    SLDC.

    3. The Commission notes that, the SLDC is yet to implement the intra-

    state ABT scheme. The Commission therefore directs SLDC to take

  • xxxiv

    appropriate action immediately to expedite the implementation of

    intra-state ABT and to host such details on its website.

    4. The Commission in its Tariff order dated 2nd March, 2015 had

    directed CESC to move the Government to effect necessary

    adjustments in the tariff subsidy payable to ESCOMs and ensure

    that there are no inter ESCOM payments outstanding in their

    accounts. Further, CESC was also directed to reconcile the inter

    ESCOM exchanges and its costs duly making necessary

    adjustments to ensure proper accounting of energy and its cost.

    5. CESC is directed to reconcile the inter ESCOM energy exchanges

    and its costs every month and the difference amounts shall be

    collected/paid out of the tariff subsidy received from the

    Government of Karnataka, to ensure proper accounting of energy

    and its cost.

    6. The Commission reiterates that, for the prior period

    receivables/payables, CESC should move the Government to

    effect necessary adjustments out of the tariff subsidy, to be

    received from the Government of Karnataka.

    In terms of the MYT Regulations, the Commission taking note of the

    above facts, decides to consider 6299.39 MU at a cost of Rs.

    2163.30 Crores (as per audited Accounts), towards power purchase

    for approving the Annual Performance Review of CESC for FY15.

    4.2.4 Renewable Purchase Obligation (RPO) compliance by CESC for FY15:

    CESC has submitted that its achievement of non-solar RPO and solar

    RPO are at 11.51% and 0.23% respectively as against target of 10% and

    0.25% respectively, as indicated below:

    TABLE – 4.7

    RPO compliance as submitted by CESC for FY15

  • xxxv

    Company

    Name

    Total

    Input

    Energy

    (MU)

    Non-Solar RPO Solar RPO

    Target Achieved Target Achieved

    (MU) (%) (MU) (%) (MU) (%) (MU) (%)

    CESC 6299.35 629.94 10 725.23 11.51 15.74 0.25 14.50 0.23

    The Commission has perused the source-wise renewable energy

    purchased, as submitted by CESC under D1 format of the Petition vis-à-

    vis the RPO compliance data submitted by CESC in its reply to the

    Commission’s preliminary observations.

    The Commission has observed that, CESC has accounted 7.49 MU of

    non-solar renewable energy purchased under APPC for the purpose of

    non-solar RPO compliance. Since, renewable energy purchased under

    APPC cannot be considered for the RPO calculation, the Commission

    has not considered the same. Thus, the non-solar RE reckoned by the

    Commission for non-solar RPO compliance is 717.74 MU as against

    725.23 MU declared by CESC.

    The Commission has approved total power purchase quantum of

    6299.3MU for FY15 in its APR. Thus, CESC was required to purchase

    629.93 MU of Non-solar energy to meet its RPO target. Based on the

    information furnished, the Commission notes that CESC has purchased

    717.74 MU of non-solar RE power for FY15 complying with the non-solar

    target for FY15.

    Regarding solar RPO target, it is noted that CESC has been able to

    achieve solar RPO target of 0.23% as against a specified target of

    0.25%, resulting in shortfall of 0.02% in meeting the solar RPO target.

    Further, in replies to the observations made by the Commission in the

    validation meeting, CESC has stated that the shortfall is due to

    inordinate delay in commissioning of 10MW capacity M/s Sai Sudhir

    Energy Pvt. Ltd. It is further, stated that if the project had been

    commissioned, CESC would have been able to meet the solar RPO

    from the anticipated generation of 15 MU. Further, CESC has requested

    the Commission to allow them to carry forward unfulfilled FY-15 solar

  • xxxvi

    RPO to FY16 as two solar projects of M/s Madhav Solar of 5 MW

    capacity each have been commissioned during July, 2015 and in the

    event of non-fulfillment of solar RPO in FY-16, it would consider

    purchase of RECs to achieve the solar RPO.

    The Commission notes that when the State as a whole is taken for the

    purpose of assessment of achievement of solar RPO, in aggregate all

    the State owned ESCOMs have achieved the total solar RPO target set

    for the State. The Commission therefore decides not to recognize the

    individual achievement of CESC and to treat the matter as closed.

    4.2.5 Operation and Maintenance Expenses:

    CESC’s Submission:

    CESC has sought approval of O&M expenditure of Rs.371.44

    Crores for FY15. CESC has claimed this O&M expenses as follows:

    TABLE – 4.8

    Normative O & M Expenses – CESC’s submission

    Amount in Rs. Crores

    Particulars FY15

    Repairs & Maintenance 37.56

    Employee Expenses 294.33

    A&G expenses 39.55

    O&M expenses 371.44

    Commission’s analysis and decisions:

    The Commission had approved O&M expenses for FY15 as detailed

    below:

    TABLE – 4.9

    Approved O&M Expenses for FY15 Amount in Rs. Crores

    Particulars FY15

    No. of installations as per actuals as per Audited Accts 2888721

    Weighted Inflation Index 6.89%

    CGI based on 3 Year CAGR 5.54%

  • xxxvii

    Actual O&M expenses for FY13 326.07

    Approved O&M Expenses for FY15 393.51

    As per the Annual Audited Accounts of the CESC for FY15, the actual

    O&M expenditure is as follows:

  • xxxviii

    TABLE – 4.10

    O&M Expenses of CESC for FY15 as per actuals

    Amount in Rs. Crores Repairs & Maintenance 37.56

    Employee Expenses 294.33

    A&G expenses 39.55

    O&M expenses 371.44

    The Commission in its preliminary observations made on the O & M

    expenses had sought the details of the items of expenditure incurred

    by the CESC during FY15 under A & G expenses. The CESC in its replies

    has stated that it has incurred expenses of Rs.14.70 Crores towards

    professional charges, Rs.8.52 Crores towards conveyance, travel and

    vehicles expenses besides other A&G expenses. On detailed review of

    the expenses, it is observed that CESC is incurring substantial expenses

    on vehicle hire charges and professional charges.

    Also, the R&M expenses are increasing year on year without proper

    justification. One of the major items noticed under R & M is expenses

    incurred on repairs of distribution transformers. The CESC needs to

    institutionalize a mechanism for minimizing such expenses.

    These expenses are abnormally increasing as compared to the

    previous years. Since the O & M expenses are controllable expenses,

    the CESC has to initiate necessary measures to ensure prudence in

    incurring these expenses. The Commission is of the view that the CESC

    should continue control its O & M expenses as per the approved O & M

    expenses.

    However, for the present, based on the provisions of the MYT

    Regulations, the Commission has proceeded with determining the

    normative O & M expenses.

    Considering the Wholesale Price Index (WPI) as per the data available

    from the Ministry of Commerce & Industry, Government of India and

    Consumer Price Index (CPI) as per the data available from the Labour

  • xxxix

    Bureau, Government of India and adopting the methodology followed

    by the CERC with CPI and WPI in a ratio of 80 : 20, the allowable

    inflation for FY15 is computed as follows:

    Year WPI CPI Composite

    Series Yt/Y1=Rt Ln Rt

    Year

    (t-1)

    Product [(t-

    1)* (LnRt)]

    2003 92.6 107 104.12

    2004 98.72 111.1 108.624 1.04 0.04 1 0.04

    2005 103.37 115.8 113.314 1.09 0.08 2 0.17

    2006 109.59 122.9 120.238 1.15 0.14 3 0.43

    2007 114.94 130.8 127.628 1.23 0.20 4 0.81

    2008 124.92 141.7 138.344 1.33 0.28 5 1.42

    2009 127.86 157.1 151.252 1.45 0.37 6 2.24

    2010 140.08 175.9 168.736 1.62 0.48 7 3.38

    2011 153.35 191.5 183.87 1.77 0.57 8 4.55

    2012 164.93 209.3 200.426 1.92 0.65 9 5.89

    2013 175.35 232.2 220.83 2.12 0.75 10 7.52

    2014 182 246.9 233.92 2.25 0.81 11 8.90

    A= Sum of the product column 35.36

    B= 6 Times of A 212.19

    C= (n-1)*n*(2n-1) where n= No of years of data=12 3036.00

    D=B/C 0.07

    g(Exponential factor)= Exponential (D)-1 0.0724

    e=Annual Escalation Rate (%)=g*100

    7.24

    For the purpose of determining the normative O & M expenses for FY15,

    the Commission has considered the following:

    a) The actual O & M expenses allowed for FY13 excluding contribution

    to Pension and Gratuity Trust.

    b) The three year compounded annual growth rate (CAGR) of the

    number of installations considering the actual number of

    installations as per audited accounts up to FY15.

    c) The weighted inflation index (WII) at 7.24% as computed above.

    d) Efficiency factor at 2% as considered in the earlier two control

    periods.

    Thus, the normative O & M expenses for FY15 will be as follows:

    Particulars FY15

    No. of Installations as per actuals as per Audited Accts 2735802

    Weighted Inflation Index 7.24%

    Consumer Growth Index (CGI) based on 3 Year CAGR 3.65%

    Normative O & M expenses for FY13 excluding P&G 270.60

  • xl

    contribution - Rs. Crs.

    O&M Index= 0&M (t-1)*(1+WII+CGI-X)- Rs. Crores 318.60

    The above normative O & M expenses have been computed without

    considering the contribution to Pension and Gratuity Trust.

    The Commission has treated certain employee costs on account of

    contribution to P&G Trust as uncontrollable O&M expenses. This

    component has been allowed beyond the normative O&M expenses

    to enable ESCOMs to meet their actual employee costs.

    The CESC in its audited accounts for FY15 has indicated an amount of

    Rs.48.70 Crores towards contribution to Pension and Gratuity trust.

    Considering the request of the CESC to treat gratuity contribution as

    uncontrollable O & M expenses, the Commission has computed the

    allowable O & M expenses for FY15 as follows:

    TABLE – 4.11

    Allowable O & M Expenses for FY15

    Amount in Rs. Crores Sl.

    No. Particulars FY15

    1 Normative O & M expenses 318.60

    2 Additional employee cost (uncontrollable

    O & M expenses)

    48.70

    3 Allowable O & M expenses 367.30

    The Commission decides to allow an amount of Rs.367.30 Crores as

    O&M expenses for FY15.

    4.2.6 Depreciation:

    CESC’s Submission:

    CESC in its application has claimed an amount of Rs.46.08 Crores as

    depreciation computed after deducting an amount of Rs.35.87 Crores

    towards depreciation withdrawn on account of contributions /

    subsidies as per Accounting Standards (AS) – 12.

    As per the audited accounts, the asset wise depreciation is as follows:

  • xli

    TABLE – 4.12

    Depreciation for FY15 – CESC’s Submission

    Amount in Rs. Crores

    Particulars

    Opening

    Balance of

    Asset as on

    01.04.2014

    Closing

    Balance of

    Asset as on

    31.03.2015

    Depreciation

    for FY15

    Buildings 52.62 58.81 1.84

    Civil 1.72 1.79 0.09

    Other Civil 0.69 0.72 0.02

    Plant & M/c 327.77 432.87 20.64

    Line, Cable Network 1244.80 1505.59 58.85

    Vehicles 3.80 4.38 0.05

    Furniture 3.95 3.90 0.18

    Office Equipment 6.93 5.18 0.28

    Total 1642.28 2013.24 81.95

    Intangible assets 2.17 2.17

    Net Depreciation 1644.45 2015.41 81.95

    Commission’s analysis and decisions:

    The depreciation is determined by the Commission in accordance

    with the provisions of the KERC (Terms and Conditions for

    Determination of Tariff) Regulations, 2006 as amended on 1st February,

    2012. Considering the opening and closing balance of gross blocks of

    fixed assets for FY15 and the depreciation as per annual accounts, the

    weighted average rate of depreciation works out to 4.46%.

    As per the audited accounts for FY15, an amount of Rs.35.87 Crores on

    account of depreciation on assets created out of grants and

    contribution on actual basis, is considered for computation of

    allowable depreciation for FY15.

    Based on the above, the Commission decides to allow the actual

    depreciation of Rs.46.08 Crores for FY15.

  • xlii

    4.2.7 Capital Expenditure for FY15

    CESC has reported a capital expenditure of Rs.368.12 Crores against

    the approved capex of Rs.455 Crores (CESC had approached the

    Commission for approval of additional capex for FY15 duly furnishing

    the reasons for its increased capex requirement from Rs.378 Crores and

    the Commission had approved an additional capex of Rs.77 Crores for

    FY15 totalling to a capex of Rs.455 Crores for FY15). The actual

    expenditure incurred by CESC for different category of works is as

    shown in the table below:

    TABLE- 4.13

    The actual capital expenditure incurred by CESC for FY15

    Amount in Rs.

    Crores

    Sl.

    No. Schemes Approved

    Actual

    expenditure

    1 Extension & Improvement

    a) HVDS+LTD Box + E&I works 70 65.95

    b) NJY 125 85.77

    2 R-APDRP 45 16.83

    3 RGGVY(Restructured )+DDG 25 0.04

    4 Replacement of failed

    Transformers 50 62.57

    5 Service Connections 35 31.52

    6 Rural Electrification(General)

    A Electrification of

    Hamlets/HB/JC/KJ under RGGVY 38 79.97

    B

    Providing infrastructure to

    Irrigation Pump sets & Energization

    of IPSETS

    C Kutir Jyothi(RGGVY)

    7 Tribal plan

    A Electrification of

    HB/JC/AC(RGGVY) 3 4

    B Energization of IP sets

    C Kutir Jyothi (RGGVY)

    8 Special Component Plan

    A Electrification of

    HB/JC/AC(RGGVY) 8 11

    B Energization of IP sets

    C Kutir Jyothi (RGGVY)

    9 Tools & Plants (Other works) 4 2.23

    10 Civil Engineering Works 10 8.20

  • xliii

    Sl.

    No. Schemes Approved

    Actual

    expenditure

    11 Providing Meters to DTC, IP Set. 42 0.04

    Total 455 368.12

    Commission’s Analysis and decision:

    From the above table it is to be noted that, in the category of RGGVY

    (Restructured) +DDG works, the CESC has incurred very meager capex

    of only Rs.0.04 Crores against the approved capex of Rs.25 Crores.

    In case of replacement of failed Transformers, the CESC has indicated

    capital expenditure of Rs.62.57 Crores, which is 25% more than the

    approved capex of Rs.50 Crores. It is to be noted that, the failed

    transformers should be replaced by repaired good transformers only

    and it should be charged to revenue expenditure. In case, the failed

    transformer is scrapped then only it can be replaced by a new

    transformer which can be booked under capex. However, in the reply

    to the preliminary observations, the CESC has admitted that, there is a

    discrepancy in accounting system/booking of expenditure pertaining

    to replacement of failed transformers. The CESC has indicated that,

    1397 numbers of new transformers (100kVA, 63kVA and 25kVA) are

    used for replacing failed transformers amounting to a total of Rs.13.28

    Crores only. But, the amount indicated in capital expenditure for

    replacement of failed transformer is at Rs.62.57 Crores. The CESC has

    agreed to streamline its accounting system to reflect only the capital

    expenditure actually incurred for replacement of failed transformers by

    new transformers. Further, when the capex incurred for replacement of

    failed transformers by new transformers, is considered as Rs.13.25

    Crores only, the capital expenditure of FY15 will be Rs.318.83 Crores

    instead of Rs.368.12 Crores.

    The CESC had ambitiously sought additional capex approval from the

    Commission for FY15 from Rs.373 Crores to Rs.455 Crores, but, it could

    achieve only Rs.368.12 Crores which is very well within the original

    approval of Rs.378 Crores. The CESC should have strived to complete

  • xliv

    more number of works and achieve a higher capex nearer to the

    additionally approved capex figures.

    The year-wise expenditure incurred by the CESC against the approved

    Capex during the last four years is shown in the following Table:

    TABLE – 4.14

    Approved Vs Actual capital investment

    Amount in Rs.Crores

    Particulars FY12 FY13 FY14 FY15

    Capital Investment Proposed

    & Approved

    485.00 560.00 575.50 455

    Capital Investment actually

    incurred

    183.27 195.87 321.75 318.83

    Short fall 301.73 364.13 253.75 136.17

    % Achievement 37.79% 34.98% 55.91% 70.07%

    From the above table, it can be observed that, though the CESC has

    improved its spending on capital investments over the years, it has not

    achieved more than 70% of its approved capex in any year from FY12.

    Considering the above points, the Commission considers the capital

    expenditure incurred by the CESC at Rs.318.83 Crores subject to

    prudence check of capital investment of FY15 as discussed in the

    following paras.

    4.2.8 Prudence check of FY15:

    The prudence check of capex of CESC was taken in two parts:

    a) Prudence check of execution of the capital works of FY15:

    b) Prudence check of material procurement process of FY15:

    a) Prudence check of execution of the capital works of FY15

    The Commission had taken up prudence check of the capital

    expenditure incurred by the CESC for the period FY15 by engaging the

    services of M/s. Power Research Development Consultants Private

  • xlv

    Limited, (M/s PRDC) as consultants to evaluate the capital expenditure

    incurred during FY15, in respect of completed and categorized works.

    The Consultant has taken a list of division wise and cost wise total

    Capex works carried out, completed and categorized in the CESC

    during FY-15 from KERC. It has classified the works cost wise in three

    groups as per the Scope of work mentioned in bid document, namely,

    works costing above 6 lakhs, works costing between Rs.6 lakh and 3

    lakh and works costing between 3 lakh and 1 lakh respectively. The

    works were taken up under various schemes like RAPDRP, UNIP and

    Niranthara Jyothi Schemes apart from General capital works like

    service connection, Extension & Improvement works, Civil engineering

    works, metering, etc. A representative sample in each category was

    selected covering the geographical area of the Company as per the

    Scope of work and submitted the report of the prudence check.

    As per the prudence check report submitted by the consultants, the

    following are the salient features:

    TABLE – 4.15

    Gist of Prudence check findings for FY15

    Particulars Numbers Amount

    in Rs. Crs

    Works costing Rs.6 Lakhs and above considered as

    samples for validation 119 95.79

    Works costing between than Rs.6 Lakhs and Rs.3

    Lakhs considered as samples 50 2.53

    Works costing below Rs.3 Lakhs considered as

    samples 24 0.69

    Works not meeting the

    norms of prudence

    Rs.6 Lakhs and above Nil

    Rs.6 Lakhs and Rs.3 Lakhs Nil

    below Rs.3 Lakhs Nil

    Total works not meeting the norms of prudence as

    stipulated in the guidelines issued by this

    Commission

    Nil

    A summary of the other findings in the prudence check are given in

    following Table:

    Summary of Works having cost overrun

  • xlvi

    Particulars Within 10% 10-25% Above 25%

    Rs.6 Lakhs and above 04 09 07

    Rs.6 Lakhs and Rs.3 Lakhs 03 01 00

    below Rs.3 Lakhs 01 01 00

  • xlvii

    Summary of Works having Time overrun

    Particulars Within one

    Year

    Between one

    and two Years above 2 Years

    Rs.6 Lakhs and above 22 16 08

    Rs.6 Lakhs and Rs.3 Lakhs 11 03 03

    below Rs.3 Lakhs 04 02 02

    The Commission has forwarded the copy of the Report on the Prudence

    check to the CESC for its information.

    b) Prudence check of material procurement process of FY15:

    The Consultant has stated that, the CESC has considered all the

    aspects related to procurement prudently and procured the materials

    as per the requirement after due process of “e-tendering” dully

    following the transparency act. However the Government of

    Karnataka has exempted the ESCOMs from the KTPP act in respect of

    purchase of materials directly from a few firms without calling for

    tenders. Some materials are also purchased through rate contract

    basis from firms after necessary bidding processes.

    The following are the observations made by the Consultant on the

    procurement of materials:

    a) The CESC has considered the actual requirement of materials

    based on work in progress and the annual program of works

    planned.

    b) The materials are procured through the process of e-tendering

    duly following the regulations as per the KTPP Act and from the

    firms which are exempted from KTTP.

    c) There has been a downward trend in the materials stocked at

    the end of the year (Closing Balance) as compared to the

    beginning (Opening Balance). Only in respect of conductors,

    insulators, Group Operating Switch (GOS), HG fuse and PSC

  • xlviii

    poles there was a small percentage of increase (15 to 20%)

    which may be of necessity considering the large consumer

    base, huge quantity of infrastructure to be maintained and

    developmental needs. Only in respect of weasel and rabbit

    ACSR conductors there has been a huge pile up of stock to an

    extent of 774 kms and 815 kms respectively.

    d) Major materials like 250 kVA transformers, UG cables, aerial

    bunched cables, RMU’s have not been procured during the

    year.

    e) Some of the materials like energy meters are under Rate

    Contract agreement with leading and reputed Firms, these

    meters are ordered by sub-division or divisional levels as and

    when required.

    c) Prudence check of execution of the capital works of FY13 &

    FY14:

    The Commission had disallowed interest and depreciation charges on

    the two works pertaining to FY13& FY14, which were termed as not

    meeting the norms of prudence in the Tariff Order dated: 02-03-2015.

    The CESC in its reply to the preliminary observation has submitted that,

    the short comings of the two works have been rectified and requested

    the Commission to consider them as meeting the norms of prudence.

    Based on the reply of the CESC, the Commission desired to revalidate

    the two works of the CESC, by the consultant conducting prudence

    check of capital works of the CESC for FY15 and submit a separate

    report.

    The consultant, M/s PRDC (P) Ltd. has verified the two projects and

    furnished a separate report and stated that, CESC has rectified the

    system of metering of DTCs and started energy audit. In view of the

    rectification and utilisation of the assets for the benefit of the

  • xlix

    Company, M/s PRDC (P) Ltd, has stated that, the projects can be

    treated as meeting the norms of prudence.

    Hence, the Commission, having taken note of the findings has decided

    to consider the two projects as meeting norms of prudence and

    discontinue the disallowance.

  • l

    4.2.9 Interest and Finance Charges

    a) Interest on loan:

    CESC’s Submission:

    The CESC has claimed an amount of Rs.39.19 Crores towards

    interest on long term loans drawn from banks / financial

    institutions during FY15.

    Commission’s analysis and decisions:

    The Commission has noted the status of opening and closing balances

    of loans as per the audited accounts and format D9 of the filings as

    shown below:

    TABLE – 4.16

    Allowable Interest on Loans – FY15

    Amount in Rs. Crores

    Particulars FY15

    Opening Balance Secured Loans 394.74

    Opening Balance Un-secured Loans 36.30

    Total opening balance of loans 431.04

    Less Short term loans/ Over draft 0.00

    Less Interest accrued & dues 0.00

    Total Long term secured & unsecured loans 431.04

    Add new Loans 286.67

    Less Repayments 46.47

    Total loan at the end of the year 671.24

    Average Loan 551.14

    Interest on long term loans as per audited accounts for FY15 56.56

    Considering the average loan of Rs.551.14 Crores and an amount of

    Rs.56.56 Crores incurred towards interest on long term loans, the

    weighted average of interest works out to 10.26%. The actual

    weighted average rate of interest is comparable with the prevailing

    rate of interest for long term loans.

  • li

    Thus, the Commission decides to allow an amount of Rs.56.56 Crores

    towards interest on long term loans for FY15.

    4.2.10 Interest on Working Capital:

    CESC’s Submission:

    The CESC in its application has stated that it has borrowed short

    term loans and overdrafts during the year to meet day to day

    expenditure during FY15. The interest on these loans is

    indicated at Rs.1.41 Crores. However, as per the replies to the

    preliminary observations, The CESC has informed that the interest

    on short term loan and overdraft for FY15 is Rs.23.71 Crores.

    Commission’s analysis and decisions:

    As per its audited accounts the CESC has incurred an interest of

    Rs.23.71 Crores on short term borrowings and overdrafts during FY15.

    The present interest rates by commercial banks and financial

    institutions are charged mainly on the basis of base rate of interest

    declared by RBI from time to time. Hence, the Commission would

    consider base rate plus certain basis points depending upon the

    tenure of the loan. Considering the base rate of interest of 9.30% with

    a spread of 250 basis points and noting the downward trend in the

    interest rate, the Commission decides to allow the normative interest

    on short term loans of 11.75% for FY15.

    As per the KERC (Terms and Conditions for Determination of Tariff)

    Regulations, 2006 as amended on 1st February, 2012, the Commission

  • lii

    has computed the allowable interest on working capital for FY15 as

    follows:

  • liii

    TABLE – 4.17

    Allowable Interest on Working Capital for FY15

    Amount in Rs.

    Crores Particulars FY15

    One-twelfth of the amount of O&M Expenses 30.61

    Opening GFA 1644.73

    Stores, materials and supplies 1% of Opening balance of GFA 16.45

    One-sixth of the Revenue 438.21

    Total Working Capital 485.26

    Rate of Interest (% p.a.) 11.75%

    Normative Interest on Working Capital 57.02

    Actual interest on WC as per audited accounts for FY15 23.71

    Allowable Interest on Working Capital 40.36

    The Commission decides to allow an amount of Rs.40.36 Crores

    towards interest on working capital for FY15.

    4.2.11 Interest on Consumer Deposits:

    CESC’s Submission:

    The CESC in its application has claimed an amount of Rs.37.09

    Crores towards payment of interest on security deposits for FY15.

    Commission’s analysis and decisions:

    The Commission notes that, the interest on consumer deposits

    amounting to Rs.37.09 Crores claimed by the CESC works out to a

    weighted average rate of interest of 8.91%. As per the KERC (Interest

    on Security Deposit) Regulations, 2005 the interest on consumer

    deposits is to be allowed as per the bank rate prevailing on the 1st of

    April of the relevant year. The bank rate as on 1st April, 2013 was 9%.

    The weighted average rate of interest as per actuals is within the

    applicable bank rate.

    Thus, the Commission decides to allow an amount of Rs.37.09 Crores

    claimed towards interest on consumer deposits for FY15.

  • liv

    4.2.12 Other Interest and Finance charges:

    The CESC has claimed an amount of Rs.2.44 Crores towards other

    interest and finance charges for FY15 which includes charges payable

    to banks / financial institutions and guarantee commission payable to

    GoK. The Commission notes that the claims are as per audited

    accounts and hence decides to allow the same for FY15.

    4.2.13 Interest on belated payment of power purchase cost:

    The CESC in its application has claimed an amount of Rs.1.54 Crores

    towards interest on belated payment of power purchase cost during

    FY15. Since the Commission is allowing interest on working capital on

    normative basis, the Commission decides to disallow any claims on

    interest on belated payment of power purchase cost separately.

    4.2.14 Capitalization of Interest:

    The CESC has capitalized interest of Rs.27.71 Crores during FY15. The

    same has been considered for computation of APR for FY15.

    Thus the allowable interest and finance charges for FY15 are as follows:

    TABLE – 4.18

    Allowable Interest and Finance Charges

    Amount in Rs. Crores

    Sl.

    No. Particulars FY15

    1. Interest on Loan capital 56.56

    2. Interest on working capital 40.36

    3. Interest on consumer deposits 37.09

    4. Other interest and finance charges 2.44

    5. Capitalisation of interest (27.71)

    6. Total interest and finance charges 108.74

  • lv

    4.2.15 Other Debits:

    CESC’s Submission:

    CESC, in its application has claimed an amount of Rs.4.94 Crores

    towards other debits as detailed below:

    TABLE – 4.19

    Other Debits-CESC’s Submission

    Amount in Rs. Crores

    Sl

    No Particulars FY15

    1 Small and Low value items written off 0.08

    2 Losses/gains relating to Fixed assets 0.70

    3 Assets decommissioning cost (0.07)

    4 Bad debts written off 0.18

    5 Miscellaneous losses and write offs 1.71

    6 Provision for bad and doubtful debts 2.34

    Total 4.94

    Commission’s analysis and decisions:

    The Commission notes that the claims of the CESC include an amount

    of Rs.2.34 Crores towards provision for bad and doubtful debts which

    are not actual expenses incurred. Considering the claims as per the

    audited accounts, the allowable other debits for FY15 is as detailed

    below:

    TABLE – 4.20

    Allowable Other Debits

    Amount in Rs. Crs.

    Sl

    No Particulars FY15

    1 Small and Low value items written off 0.08

    2 Losses/gains relating to Fixed assets 0.70

    3 Assets decommissioning cost (0.07)

    4 Bad debts written off 0.18

    5 Miscellaneous losses and write offs 1.71

    Total 2.60

    Thus, the Commission decides to consider an amount of Rs.2.60 Crores

    as other debits for FY15.

  • lvi

    4.2.16 Net Prior Period Charges:

    CESC’s Submission:

    The CESC in its application as per audited accounts has claimed a

    net credit balance of Rs.72.44 Crores towards Net Prior Period

    Credits as detailed below:

    TABLE – 4.21

    Net Prior Period Charges-CESC’s Submission

    Amount in Rs. Crs.

    Particulars FY15

    Prior period expenses / losses 110.94

    Prior period income (183.38)

    Net prior period credits 72.44

    Commission’s analysis and decisions:

    As per the Audited Accounts for FY15, the prior period debit is Rs.110.94

    Crores on account of employee costs, A&G expenses and under

    provided depreciation of earlier years. Further the prior period credit

    of Rs.183.38 Crores is on account of excess depreciation, finance

    charges and other expenses. Hence the Commission decides to allow

    net prior period credit of Rs.72.44 Crores for FY15.

    4.2.17 Return on Equity:

    CESC’s Submission:

    CESC in its application has not claimed Return on Equity for FY15.

    Commission’s analysis and decisions:

    As per the KERC (Terms and Conditions for Determination of Tariff)

    Regulations, 2006 as amended on 1st February, 2012, the Commission

    has computed the allowable Return on Equity at 15.5% on equity plus

    reserves and surplus as at the beginning of the year besides allowing

  • lvii

    taxes as per actuals. The allowable RoE for FY15 is determined as

    follows:

    TABLE – 4.22

    Allowable Return on Equity

    Amount in Rs. Crores

    Particulars FY15

    Paid Up Share Capital 325.52

    Share deposit 23.20

    Reserves and Surplus (682.46)

    Less recapitalized security deposit (23.00)

    Total Equity (356.74)

    Considering accumulated losses of Rs.682.46 Crores and total equity of

    Rs.348.72 Crores as at the beginning of the year and recapitalization of

    security deposit of Rs.23.20 Crores, CESC has negative net worth of

    Rs.356.74 Crores.

    Thus, the Commission decides not to allow any Return on Equity for

    FY15.

    4.2.18 Income tax :

    As per the audited accounts, CESC has incurred an expenditure of Rs.15.78

    Crores towards payment of Income Tax for FY15. The Commission decides

    to allow the actual Income Tax payment of Rs.15.78 Crores for FY15


Recommended