+ All Categories
Home > Documents > Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 ·...

Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 ·...

Date post: 16-Apr-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
28
Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M. Sotomil Sr. Dept. Manager & Head Metering Services Group National Transmission Corporation Renato B. Afurong Metering Unit Head Philippine Electricity Market Corporation (PEMC)
Transcript
Page 1: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Challenges & Experiences in AMR Application to Support the

Philippine WESM

Emmanuel M. SotomilSr. Dept. Manager & HeadMetering Services Group

National Transmission Corporation

Renato B. AfurongMetering Unit HeadPhilippine Electricity MarketCorporation (PEMC)

Page 2: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Presentation Outline

� Overview of the Philippine WESM� Market Structure and Coverage� Supply – Demand Balancing� Metering Requirements� Meter Data Processing for Trading Settlements

� Challenges to TRANSCO as WESM MSP� The TRANSCO WESM Metering Project

� Project Milestones� Present State of TRANSCO’s Metering/AMR System� “Birth Pains” of the Metering/AMR System

� Other Valuable Experiences

Page 3: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Philippine Wholesale Electricity Spot Market (WESM)

� Established by the Philippine Department of Energy (DOE) in accordance with the Electric Power Industry Reform Act of 2001

� Philippine Electricity Market Corporation (PEMC) was created to develop and operate the WESM.

Page 4: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Philippine Wholesale Electricity Spot Market (WESM)

� WESM is the venue for buyers and sellers engage in the trading of electricity as a commodity.

� PEMC shall establish, maintain and govern an efficient, competitive, transparent and reliable market for the wholesale trade of electricity.

Page 5: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

MARKET STRUCTUREOF PHILIPPINE WESM

� PEMC is the Market Operator (MO)� Regulator : Energy Regulatory Commission (ERC)� TRANSCO is Transmission Provider , System Operator ,

& default Metering Service Provider (MSP)� Sellers : Generation Companies (NPC, others)

Suppliers/Supply AggregatorsIPP Administrators

� Buyers : Distribution UtilitiesElectricity End-users/Load CustomersSuppliers/Supply Aggregators

� Other entities authorized by ERC according to Law.

Page 6: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

WESM COVERAGE

Luzon – Commercial Operation June 2006

Visayas – Commercial Operation is set to start January 2008Trial Operation is on-going

Mindanao – Will follow after Visayas Commercial Operation

Initially, only entities connected to the Grids and with a capacity of 1MW and higher are admitted in the WESM.

Page 7: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

DEMAND – SUPPLYBALANCING

Generation Companies

(GenCo’s)

Customers(DU’s, EC’s,

LC’s, Suppliers

and/or Aggregators)

OffersOffers BidsBids

Supply SideSupply Side Demand SideDemand Side

Price

P= /MWH

0.8

0.7

0.9

1.00

P

Page 8: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

WESM METERING REQUIREMENTS

� Meters and Instrument Transformers Accuracy Class.

� Blondel’s Theorem Compliance of metering circuit.

� Meter Functionalities:� Load Profile Meter Data Memory

� Data Communication Ports for On-site & Remote Data Access using an AMR System or proprietary meter data retrieval software

� Connectivity to MSP’s AMR System for daily meter data retrieval and delivery to the MO

� Metering Facility Integrity Certification by the MSP

� Metering Facility Registration with the MO

Page 9: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

DAILY METER DATA PROCESSINGT

radi

ng P

artic

ipan

ts MSP’s AMR System

1. Daily retrieval of previous day meter data by AMR: 12AM to 4AM

2. Meter Data Validation

3. Transmit meter data to M.O.: 6 - 8 AM

MO’s MDCSMARKET

MANAGEMENT SYSTEM

15-minute MDEF

MO’s Settlement System

Settlement Ready Data

MTRMTR

1. Receiving of Meter Data from MSP’s AMR System

2. Meter Data undergoes Validation, Estimation & Editing (VEE)

3. SSLA: Translation of Metered Energy to Market Trading Node

4. Posting of Settlement-Ready Meter Data in the Settlement System

Page 10: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

VALIDATION, ESTIMATION & EDITING

ESTIMATION & EDITINGUse data from alternate meters or SCADA dataWhere no alternate meter or SCADA data is available:� Estimation based on interpolation between values

for short-duration cases of missing data� Use historical value for the same hour of the

previous day (weekdays)� Use historical value for the same day of previous

last week (weekends)

Missing meter data

If value is invalid, a Meter Trouble Report (MTR) is issued to the MSP.

Values Outside Min/Max Limits

For defective Main Meter, the Check or Alternate meter data is substituted.

Check or Alternate Meter

CORRECTIVE MEASURECHECK FOR:

Page 11: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

METER TROUBLE REPORTING & RESOLUTION

� MO issues an MTR to the MSP for meters that failed the validation process

� MSP performs the following upon issuance of the MTR :

• Investigate the problem

• Perform repairs as required

• Provide substitute meter data

� MO estimates remain in place until MSP provides met er data acceptable to MO.

Page 12: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

SITE-SPECIFIC LOSS ADJUSTMENT (SSLA)

� Load Customer’s Metering Points are required to be at the Market Trading Node (MTN)

� For Metering Points not located at the Market Trading Node: customer meter data measured at the metering point is translated to the MTN.

� The Adjusted Meter Data is inclusive of Line and Transformer Losses between the MTN and Metering Point.

M1

M2

MTN

Metering Point 1

Metering Point 2

Power Transformer

Page 13: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Outside the limit

Outside the limit

Manually Approved

Manually Approved

Within the limit (automatically

approved)

Within the limit (automatically

approved)

Validation

Estimation

& Editing

Page 14: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Validation, Estimation, & Editing

Page 15: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

SETTLEMENT

CONVERT CD XLS(DEL & REC)

TO SQL

CALCULATE RTUFACTOR THEN

CONVERT TO SQL

SOURCE DATAPREPARATION

FOR SSLA

Y

Monthly Meter Data Process Flow

OK

COMPARISONOF MDW,

MDCS & CD

OK

COMPARISON GEN RTU AND

GEN CD

OK

M

T

R

EVALUATEMSP CD

DAILY MQFROM MDCS

DAILY MQFROM MDW

DAILY AVESNAPSHOT(GEN RTU)

N

Y

N

MSP RECONCILED CD

START

N

Y

N

OKCOMPARISON OF

SQL AND XLS(QC/SUMMARY)

SSLACALCULATION

CONVERT SSLA XLS TO SQL

OKCOMPARISON OF

RAW SSLA AND CD(QC/SUMMARY)

COMPARISON OF SQL AND XLS

(QC/SUMMARY)

UPLOAD

TO

MDW

N

N

Y

Y

Y

COMPARISON OF SQL AND XLS

(QC/SUMMARY)

OK

N

Y

OK

N

AGGREGATED MQ(FOR MARKET

FEES)

COMPARISON OF GEN DEL AND CD DEL

(QC/SUMMARY)

OK

AGGREGATED MQ(NODAL)

COMPARISON OF NODAL AND CD(QC/SUMMARY)

OKY

N

APPROVED

FOR

SETTLEMENT

ENERGY BALANCE

Y

N

Page 16: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

METERING & AMR CHALLENGES OF PHILIPPINE WESM

In 2003, TRANSCO organized the Metering Services Groupto perform TRANSCO’s role as default WESM Metering Service Provider.

� No AMR System was in place.

� TRANSCO had NO AMR EXPERIENCE, but had SCADA experience since the mid-80’s.

� The NPC Plants, accounting for roughly 60% of total generation capacity, had no revenue metering facilities.

� Metering facilities of Grid-connected Load Customers and IPP’s were equipped with meters with Load Profile Data storage capability but less than 20% were AMR-ready.

Page 17: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

METERING & AMR CHALLENGESOF PHILIPPINE WESM

TRANSCO undertook a WESM Metering Project that started in 2004, with the following components:1. Automated Meter Data Retrieval (AMR) System for all Grid-

connected metering points.2. Upgrading of revenue metering facilities of Customers:

� New, AMR-ready electronic meters� Meter communication links to the AMR System.

3. Revenue metering equipment for NPC power plants:

� Instrument transformers� AMR-ready electronic meters� Meter communication links to the AMR System

Page 18: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

METERING POINTS BEFORE WESM METERING PROJECT

� Most of NPC and IPP Power Plants were served by TRANSCO’s PSTN Digital Telephone System.

� Customers’metering points are in receiving substations that are not served by TRANSCO’s phone system.

� GSM service reaches almost all sites.

REMARKS

0133. IPP Plants

0

145

0

166

160

376

AMR-Ready

Meters

METERING

POINTS

A. LUZON 1. Customers

C. MINDANAO 1. Customers

0252. NPC Plants

145886PHILIPPINES

0202. NPC Plants

0203. IPP Plants

0733. IPP Plants

0332. NPC Plants

B. VISAYAS 1. Customers

AREAS

Page 19: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

TRANSCO WESM METERING PROJECT MILESTONES

� Decision on AMR Strategy was made in mid-2003, to use an industry-tested System designed for a multi-meter vendor situation and dial-up connection via PSTN & GSM links.

� Tenders for the AMR System and the first batch of AMR-ready electronic meters were issued in November 2003.

� The AMR System:

� November 2004: Hardware and software components were delivered.

� June 2005: Vendor completed the Luzon AMR Stationinstallation and testing, and training of AMR Station operating staff.

� April 2006: Luzon AMR Station was ready for service.

Page 20: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

TRANSCO WESM METERING PROJECT MILESTONES

� AMR-Ready Electronic Meters:

� February 2005: First Batch of 582 Meters delivered.

� April 2005: Installation of AMR-Ready Meters on the 476 metering points in Luzon completed.

� April 2007: Second batch of 225 Meters delivered, to complete all the requirements for AMR-ready meters.

� Telephone Links:

� June 2006: Connectivity of Luzon metering facilities to the AMR System was achieved using PSTN and GSM links (80 PSTN + 394 GSM).

� September 2007: A batch of 325 GPRS-capable GSM Modems have been delivered.

Page 21: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

THE TRANSCO AMR SYSTEM

Workstations Server

Switch

Firewall

RouterCentral AMR Station

WAN

Router

Firewall

WorkstationsServer

Switch

VisMin AMR Station

Workstations ServerSwitch

Firewall

RouterBackup AMR Station

Remote Metering Points

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

Workstations Serve

r

Switc

h

Firewal

l

Rout

er

PEMCMarket Operator

Luzon Visayas/Mindanao

Via dial-up

TransCo Billing System

NPC TOU Billing

Via E-mail

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

•GSMGSMGSMGSM•DTSDTSDTSDTS

•TELCOTELCOTELCOTELCO

Page 22: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

Present State of the TRANSCO AMR System

March 2008

� Tested and ready for installation.

� Installation to commence after construction of AMR Station Building.

3. National Back-up AMR Station

N/AAlready tested and in service since April 2007.

2. Vis/Min AMR StationTransCo-VisayasRegional Office, Cebu

N/A

ECD

In service to the WESM since April 2006.

Status/On-going Work

1. Luzon AMR StationTransCo Head Office

AMR Station

Page 23: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

PRESENT STATE OF WESM METERING POINTS

Read by

AMRW/Tel. Link

w/AMR-Ready

Meters

METERING

POINTS

A. LUZON

C. MINDANAO

44501661. Customers

001252. NPC Plants

004133. IPP Plants

8816202. NPC Plants

8818203. IPP Plants

737373733. IPP Plants

3743743763761. Customers

333333332. NPC Plants

4949155

B. VISAYAS

1601. Customers

AREAS

Page 24: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

“BIRTH PAINS” OF TRANSCO’sWESM METERING PROJECT

� High Failure Rate of AMR-ready Electronic Meters.

� Meters would fail within a few days from installation.

� A recall program that lasted at least 9 months was done by the meter manufacturer to change meters/modify meter electronics.

� AMR System – Meter Compatibility Issues

� Significant Meter Data Drop-out cases were initially experienced.

� Proprietary meter software was temporarily used for remote meter data retrieval until a new AMR Driver was developed by the AMR Supplier for the meter.

Page 25: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

OTHER VALUABLE EXPERIENCES

Comparison of Telephone Connection between AMR System and Meters – Availability, Reliability and Cost

Approx. 8c/min.

$35 Fixed Subscription + Approx. 15c/min.

Not quantified

OPEXCAPEX

$350-400 per Meter

VERY GOODPractically

everywhere

GSM Cell Phone Service

BETTER THAN TRANSCO’s

Service limited to urban areas

PRIVATE PSTN

LOWGOODServes NPC Power Plants & most IPP’s

TRANSCO PSTN

COSTRELIABILITYAVAILABILITY

Page 26: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

OTHER VALUABLE EXPERIENCES

� Duration for retrieving 4 – Channels of Meter Data: KWH Delivered, KWH Received, KVARH Delivered & KVARH Received at 15-Minute Interval:

� For first-time retrieval, the operation can take as long as 30 minutes and even longer for some meters.

� Succeeding retrieves last 2 – 6 minutes for 24-hour’s meter data depending on meter make.

� AMR Workstation Loading : For a 5-hour meter data retrieval window, 80 Meters/Workstation, with a 25% allowance for “retries”.

� Data Reject & Retrieval Failure Rate is down to <5%from 20-25% when the System was deployed in 2006.

Page 27: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

CONCLUSIONS

� AMR System – Meter Compatibility is critical to avoid surprises in getting the system to work.

� Go with tried and tested meters whose bugs with an AMR System have been corrected.

� The meter’s load profile data log set-up can greatly affect duration and cost of meter data retrieval .

� Doing the work in-house preserves knowledge.

� With knowledge gained, TRANSCO and PEMC are better prepared to handle the metering and AMR challenges of the next phases of the WESM.

Page 28: Challenges & Experiences in AMR Application to Support the Philippine … · 2019-09-02 · Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M.

End of Presentation.Thank you!


Recommended