Date post: | 30-Oct-2014 |
Category: |
Documents |
Upload: | mohammad-bilal |
View: | 17 times |
Download: | 3 times |
�Outline
• The context
• The challenges
– Photovoltaics (PV)
– Solar Thermal Electric (STE)
• The potential impacts on GHG emissions
�Photovoltaics (PV)
• Photons in sunlight hit the solar panel and are absorbed by semiconducting materials, such as silicon.
• Electrons (negatively charged) are knocked loose from their atoms, allowing them to flow through the material to produce electricity.
• The complementary positive charges that are also created are called holesand flow in the direction opposite of the electrons in a silicon solar panel.
• An array of solar cells converts solar energy into a usable amount of DC electricity.
�PV - Technologies
Amorphous silicon
Cadmium telluride (CdTe)
Module inverterCopper indium diselenide (CIS)
Dual axis tracking system
String inverterPolycrystallineSingle-axis tracking system
Central inverter for entire system
Mono-crystallineFixed
InvertersModulesStructure
�PV – Technical Challenges
Resource Availability
– Silicon:
• Pure Silicon
– High quality
– Used to be a problem
– New plants built (2004)
– Higher efficiency
• Metallurgical Silicon
– Silicon reclaiming
– Cheaper
– Less energy
– Efficiency compromised (?)
�PV – Technical Challenges
Resource Availability (continuation)
– Tellurium (CdTe)
– Indium
– Selenium (CuInSe2)
– Cadmium (environmental issues)
– Cooper
– Glass
Thin Film
�PV – Technical Challenges
Efficiency
– Monocrystalline-Silicon
• Efficiency: 10 - 18%
– Polycrystalline-Silicon
• Efficiency: 9 - 13%
– Amorphous-Silicon
• Efficiency: 6 - 8%
– CdTe
• Efficiency: 7 - 10%
– CIS
• Efficiency: 9 - 12%
Space requirement
�PV – Technical Challenges
Dispachability
– The sun is an intermittent source of energy
Storage
– Batteries
– Fuel Cells
– “Grid”
�PV – Technical Challenges
Data Availability
Energy Yield Calculation
• Weather data
• Irradiation data
• Topographic data
Cleaning
– Water
– Vibration
�PV - commercial challenges - cost
• Cost, cost, cost, cost, cost,
• Today
– Euro 4.5 – 8 /Wp installed
– USD 5.5 – 10 /Wp installed
�PV - commercial challenges - cost
• High cost = Gov support
– Investment subsidies
– Feed-in-tariffs (Spain: Royal Decree 1578/2008)
– Green certificates (UK - ROCs)
�PV - commercial challenges - cost
• Future cost reductions
– Prices have fallen by 20% every
doubling of output - LR
– Technical challenges to keep prices
falling at historic rates
• When will we get grid parity ?
�PV - commercial challenges - other
• Revenue certainty – political uncertainty
– Japanese, Spanish examples
• Financing
– Large capital investments – credit crunch
– Low but constant paybacks
• Securing supply – less of an issue now
• Emerging technology problems – increase risks/costs
• Good people, experience, etc…. hampering
development
�What is possible - Germany
• Stable feed-in tariff
• 50% global demand
• Now >5GW installed (ish)
• Bavaria 2% total supply
• Small nuclear plant
�PV projects - buildings
• CIS Tower Manchester
– The UK's largest solar power project
to date,
– 400 KWp which will generate
200,000 kWh per year
– £5.5 million
�PV projects – utility v big
• Spain - Parque Fotovoltaico Olmedilla de Alarcon
• 60 MW
• 85 GWh/yr
• Bigger to come –
– 3 GWs India ?
�Solar Thermal Electrical (STE)
Parabolic trough
Central receiver system - power tower
Parabolic dish engine
Linear Fresnel collector
�Solar Thermal – Technical Challenges
• Cleaning
– Water
• Storage
– Sensible Heat Storage – Change of temperature occurs
– Latent Heat Storage – Change of phase occurs
– Thermochemical Storage – reversible chemical reaction occurs
• Land Requirement for collectors
• Location constrains
�Solar Thermal – Technical Challenges
• Data Availability
Energy Yield Calculation
• Weather data
• Irradiation data
• Topographic data
• More environmental impact Higher foot print
• New technologies Less bankable
• Qualified personnel
�STE - commercial challenges - cost
• Learning effect –costs expected to fall as capacity
increases
• But what about transmission costs?
�STE - commercial challenges - others
• Suitable locations far from demand centres –transmission
• Lead times?
• Expertise
• Contractually complicated – EPC wrap / O&M
• Getting project finance complicated - bankability
�STE Project examples
• 9 SEGS plants California
• Troughs
• 1984 - 1991
• 354MW
• 936,384 mirrors
• > 6.5 km2.
�STE Project examples
• Andasol 1 – Spain
• First troughs in Europe
• 2008
• 50MWe
• Thermal storage
• 510, 000 m2 collectors
• Andasol 2 & 3 to follow
�STE Project examples
• PS10 – Spain
• Solar power tower
• 2007
• 11MWe
• 624 heliostats
• 115 m tower
�STE Project examples
• Kimberlina
• Fresnel reflectors
• 2008
• 5MWe – demonstration
• 177MWe plant in development - California
�GHG emissions – beyond 2020
• IPCC estimates CO2 emissions to reduce by >80% to carrying capacity
• Solar to play vital part in meeting that target