7 1CONSTRAINT MANAGEMENT
Constraint ManagementConstraint Management
7
8/3/2019 Chap 7 Constraint Management
2/28
7 2
CONSTRAINTCONSTRAINT
Any factor that limits the performance of asystem and restricts its output.
Constraints can occur up or down the supplychain, with either the firms suppliers or
customers, or within one of firmsprocesses like service/productdevelopment or order fulfillment.
CONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
3/28
7 3
KINDS OF CONSTRAINTSKINDS OF CONSTRAINTS
Three kinds of constraints can generally beidentified:
Physical (usually machine, labor orworkstation capacity or material shortages)
Market ( demand is less than capacity)
Managerial ( policy, metrics, or mind-setsthat create constraints which impede workflow)
CONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
4/28
7 4
BOTTLENECKBOTTLENECK
A bottleneck is a special type of constraintthat relates to:
The capacity shortage of a process, & isdefined as
Any resource whose available capacitylimits the organizations ability to meet theservice or product volume, product mix, orfluctuating requirements demanded by the
market place
CONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
5/28
7 5
MANAGING CONSTRAINT ACROSS THEMANAGING CONSTRAINT ACROSS THEORGANIZATIONORGANIZATION
Firms must manage their constraints andmake appropriate capacity choices at theindividual-process level, as well as at theorganization level.
Hence this process involves inter-functionalcooperation
A bottleneck could be the sales departmentnot getting enough sales or the loan
department not processing loans fastenough as in many banks.
The constraint could be a lack of capital orequipment or it could be planning or
schedulingCONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
6/28
7 6
THEORY OF CONSTRAINTTHEORY OF CONSTRAINT
A systematic management approach thatfocuses on actively managing thoseconstraints that impede a firms progresstoward its goals
TOC methods increase the firms profitsmore effectively by focusing on makingmaterials flow rapidly through the entiresystem
They help firms look at the big picturehowprocesses can be improved to increaseoverall work flows, & how inventory andworkforce levels can be reduced while still
effectively utilizing critical resources.CONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
7/28
7 7CONSTRAINT MANAGEMENT
Theory of ConstraintsTheory of Constraints
Bottlenecks can both be internal or external to thefirm and are typically a process or step with thelowest capacity
Throughput time is the total elapsed time from thestart to the finish of a job or a customer being
processed at one or more work centers
A bottleneck can be identified in several differentways
1. If it has the highest total time per unit processed
2. If it has the highest average utilization and total workload3. If a reduction of processing time would reduce the
average throughput time for the entire process
8/3/2019 Chap 7 Constraint Management
8/28
7 8CONSTRAINT MANAGEMENT
Identifying the BottleneckIdentifying the Bottleneck
EXAMPLE 7.1
Managers at the First Community Bank are attempting to shorten
the time it takes customers with approved loan applications to
get their paperwork processed. The flowchart for this process,
consisting of several different activities, each performed by a
different bank employee, is shown in Figure.
Approved loan applications first arrive at activity or step 1, where
they are checked for completeness and put in order.
8/3/2019 Chap 7 Constraint Management
9/28
7 9
At step 2, the loans are categorized into different classes
according to the loan amount and whether they are being
requested forpersonalorcommercial reasons.
While credit checking commences at step 3, loan application
data are entered in parallel into the information system for
record-keeping purposes at step 4.
Finally, all paperwork for setting up the new loan is finished at
step 5. The time taken in minutes is given in parentheses.
CONSTRAINT MANAGEMENT
8/3/2019 Chap 7 Constraint Management
10/28
7 10CONSTRAINT MANAGEMENT
Complete paperworkfor new loan
(10 min)
Identifying the BottleneckIdentifying the Bottleneck
Check for credit rating(15 min)
Enter loan applicationinto the system
(12 min)
Categorize loans(20 min)
Check loan documentsand put them in order
(15 min)
Figure: Processing Credit Loan Applications at First Community Bank
Which single step is the bottleneck? The management is alsointerested in knowing the maximum number of approved loansthis system can process in a 5-hour work day.
8/3/2019 Chap 7 Constraint Management
11/28
7 11CONSTRAINT MANAGEMENT
Identifying the BottleneckIdentifying the Bottleneck
SOLU
TION
We define the bottleneck as step 2, where a single-minutereduction in its time reduces the average throughput time of theentire loan approval process. The throughput time to complete anapproved loan application is 15 + 20 + max(15, 12) + 10 = 60minutes. Although we assume no waiting time in front of any
step, in practice such a smooth process flow is not always thecase. So the actual time taken for completing an approved loanwill be longer than 60 minutes due to non uniform arrival ofapplications, variations in actual processing times, and therelated factors.
The capacity for loan completions is derived by translating theminutes per customer at the bottleneck step to customer perhour. At First Community Bank, it is 3 customers per hourbecause the bottleneck step 2 can process only 1 customer every20 minutes (60/3).
8/3/2019 Chap 7 Constraint Management
12/28
7 12CONSTRAINT MANAGEMENT
A Line ProcessA Line Process
Line Balancing Assignment of work to stations in a line so as to
achieve the desired output rate with the smallestnumber of workstations
Achieving the goal is similar to the theory ofconstraints but it differs in how it addressesbottlenecks
Precedence diagram AON network
8/3/2019 Chap 7 Constraint Management
13/28
7 13CONSTRAINT MANAGEMENT
Precedence DiagramPrecedence Diagram
EXAMPLE
Green Grass, Inc., a manufacturer of lawn and gardenequipment, is designing an assembly line to produce a newfertilizer spreader, the Big Broadcaster. Using the followinginformation on the production process, construct a precedence
diagram for theBig Broadcaster.
WorkElement
Description Time(sec)
ImmediatePredecessor(s)
A Bolt leg frame to hopper 40 None
B Insert impeller shaft 30 A
C Attach axle 50 A
D Attach agitator 40 B
E Attach drive wheel 6 B
F Attach free wheel 25 C
G Mount lower post 15 C
H Attach controls 20 D, E
I Mount nameplate 18 F, G
Total=244
8/3/2019 Chap 7 Constraint Management
14/28
7 14CONSTRAINT MANAGEMENT
Precedence DiagramPrecedence Diagram
SOLU
TION
Figure shows the complete diagram. We begin with work elementA, which has no immediate predecessors. Next, we add elementsB and C, for which element A is the only immediate predecessor.After entering time standards and arrows showing precedence,we add elements D and E,
and so on. The diagram simplifiesinterpretation. Work element F,for example, can be doneanywhere on the line afterelement C is completed.However, element I must
await completion ofelements F and G.
D
40
I
18
H
20
F
25
G
15
C
50
E
6
B
30
A
40
Figure: Precedence Diagram for
Assembling the Big Broadcaster
8/3/2019 Chap 7 Constraint Management
15/28
7 15CONSTRAINT MANAGEMENT
CYCLE TIMECYCLE TIME
Cycle time is the maximum time allowed forwork on a unit at each station.
c =1
r
wherec = cycle time in hours
r = desired output rate
8/3/2019 Chap 7 Constraint Management
16/28
7 16CONSTRAINT MANAGEMENT
THEORETICAL MINIMUMTHEORETICAL MINIMUM
A benchmark or goal for the smallestnumber of stations possible, where the totaltime required to assemble each unit isdivided by the cycle time.
TM =7t
c
where
7t= total time required to assembleeach unit
8/3/2019 Chap 7 Constraint Management
17/28
7 17CONSTRAINT MANAGEMENT
Idle time, efficiency, and balance delay
Idle time = nc 7t
where
n = number of stations
Efficiency (%) = (100)7t
nc
Balance delay (%) = 100 Efficiency
8/3/2019 Chap 7 Constraint Management
18/28
7 18CONSTRAINT MANAGEMENT
Calculating Cycle Time, TM, EfficiencyCalculating Cycle Time, TM, Efficiency
EXAMPLE
Green Grasss plant manager just received marketings latestforecasts ofBig Broadcaster sales for the next year. She wantsits production line to be designed to make 2,400 spreaders perweek for at least the next 3 months. The plant will operate 40
hours per week.
a. What should be the lines cycle time?
b. What is the smallest number of workstations that she couldhope for in designing the line for this cycle time?
c.S
uppose that she finds a solution that requires only fivestations. What would be the lines efficiency?
8/3/2019 Chap 7 Constraint Management
19/28
7 19CONSTRAINT MANAGEMENT
Calculating Cycle Time, TM, EfficiencyCalculating Cycle Time, TM, Efficiency
SOLUTION
a. First convert the desired output rate (2,400 units per week) toan hourly rate by dividing the weekly output rate by 40 hoursper week to get units per hour. Then the cycle time is
c = 1/r =
b. Now calculate the theoretical minimum for the number ofstations by dividing the total time, 7t, by the cycle time,c = 60 seconds. Assuming perfect balance, we have
TM =7t
c
244 seconds
60 seconds= = 4.067 or 5 stations
1/60 (hr/unit) = 1 minute/unit = 60 seconds/unit
8/3/2019 Chap 7 Constraint Management
20/28
7 20CONSTRAINT MANAGEMENT
Calculating Cycle Time, TM, EfficiencyCalculating Cycle Time, TM, Efficiency
c. Now calculate the efficiency of a five-station solution,assuming for now that one can be found:
Efficiency = (100) =7t
nc244
5(60)= 81.3%
8/3/2019 Chap 7 Constraint Management
21/28
7 21CONSTRAINT MANAGEMENT
The theoretical minimum number of workstationsis 5 and the cycle time is 60 seconds, so Figure7.5 represents an optimal solution to the problem
Figure 7.5 Big Broadcaster Precedence Diagram Solution
D40
I
18
H
20
F
25
C
50
E
6
B
30
A
40
G
15
8/3/2019 Chap 7 Constraint Management
22/28
7 22CONSTRAINT MANAGEMENT
Solved ProblemSolved Problem
A company is setting up an assembly line to produce 192 unitsper 8-hour shift. The following table identifies the workelements, times, and immediate predecessors:
Work Element Time (sec) Immediate Predecessor(s)
A 40 NoneB 80 A
C 30 D, E, F
D 25 B
E 20 B
F 15 B
G 120 AH 145 G
I 130 H
J 115 C, I
Total 720
8/3/2019 Chap 7 Constraint Management
23/28
7 23CONSTRAINT MANAGEMENT
a. What is the desired cycle time (in seconds)?
b. What is the theoretical minimum number of stations?
c. Use trial and error to work out a solution, and show yoursolution on a precedence diagram.
d. What are the efficiency and balance delay of the solutionfound?
SOLUTION
a. Substituting in the cycle-time formula, we get
c = =1
r
8 hours
192 units(3,600 sec/hr) = 150 sec/unit
8/3/2019 Chap 7 Constraint Management
24/28
7 24CONSTRAINT MANAGEMENT
b. The sum of the work-element times is 720 seconds, so
TM =7t
c
= = 4.8 or 5 stations720 sec/unit
150 sec/unit-station
8/3/2019 Chap 7 Constraint Management
25/28
7 25CONSTRAINT MANAGEMENT
c. The precedence diagram is shown in Figure. Each row in thefollowing table shows work elements assigned to each of thefive workstations in the proposed solution.
J
115
C
30
D
25
E
20
F
15
I
130
H
145
B
80
G
120
A
40
Figure Precedence Diagram
WorkElement
ImmediatePredecessor(s)
A None
BA
C D, E, F
D B
E B
F B
G A
H G
I H
J C, I
8/3/2019 Chap 7 Constraint Management
26/28
7 26CONSTRAINT MANAGEMENT
Station Candidate(s) ChoiceWork-Element
Time (sec)
Cumulative
Time (sec)
Idle Time
(c= 150 sec)
S1
S2
S3
S4
S5
J
115
C
30
D
25
E
20
F
15 I
130H
145
B
80
G
120
A
40
8/3/2019 Chap 7 Constraint Management
27/28
7 27CONSTRAINT MANAGEMENT
J
115
C
30
D
25
E
20
F
15 I
130H
145
B
80
G
120
A
40
A A 40 40 110
B B 80 120 30
D, E, F D 25 145 5
E, F, G G 120 120 30
E, F E 20 140 10
F, H H 145 145 5
F, I I 130 130 20
F F 15 145 5
C C 30 30 120
J J 115 145 5
Station Candidate(s) ChoiceWork-Element
Time (sec)
Cumulative
Time (sec)
Idle Time
(c= 150 sec)
S1
S2
S3
S4
S5
8/3/2019 Chap 7 Constraint Management
28/28
7 28CONSTRAINT MANAGEMENT
Solved ProblemSolved Problem
d. Calculating the efficiency, we get
Thus, the balance delay is only 4 percent (10096).
Efficiency (%) = (100)7t
nc
=720 sec/unit
5(150 sec/unit)
= 96%