CHAPTER
6 Net Present Value and Other
Investment Rules
Slide 2
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
Chapter Outline
6.1 Why Use Net Present Value?6.2 The Payback Period Method6.3 The Discounted Payback Period Method6.4 The Average Accounting Return Method6.5 The Internal Rate of Return6.6 Problems with the IRR Approach6.7 The Profitability Index6.8 The Practice of Capital Budgeting
Slide 3
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.1 Why Use Net Present Value?
• Accepting positive NPV projects benefits shareholders.
Forgoing the project today, the value of the firm today is $V + $100
Accepting the project today, the value of the firm today is $V + $100.94 (107/1.06)
The difference is $0.94.• The value of the firm rises by the NPV of the
project.
Slide 4
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
• The discount rate on a risky project is the return that one can expect to earn on a financial asset of comparable risk.
• This discount rate is often referred to as an opportunity cost.
Slide 5
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Net Present Value (NPV) Rule
• Net Present Value (NPV) = -Initial Investment +Total PV of future CF’s
• Estimating NPV:– 1. Estimate future cash flows: how much? and when?– 2. Estimate discount rate– 3. Estimate initial costs
• Minimum Acceptance Criteria: Accept if NPV > 0• Ranking Criteria: Choose the highest NPV
Slide 6
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
Good Attributes of the NPV Rule
• 1. Uses cash flows• 2. Uses ALL cash flows of the project• 3. Discounts ALL cash flows properly
• Reinvestment assumption: the NPV rule assumes that all cash flows can be reinvested at the discount rate.
Slide 7
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.2 The Payback Period Method
• How long does it take the project to “pay back” its initial investment?
• Payback Period = number of years to recover initial costs
• Minimum Acceptance Criteria: – Set by management
• Ranking Criteria: – Set by management
Slide 8
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Payback Period Method• Disadvantages:
– Ignores the time value of money– Ignores cash flows after the payback
period– Biased against long-term projects– Requires an arbitrary acceptance criteria– A project accepted based on the payback
criteria may not have a positive NPV
• Advantages:– Easy to understand– Biased toward liquidity
Slide 9
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
• The payback rule is often used by: large and sophisticated companies when making relatively small decisions, or firms with very good investment opportunities but no available cash (small, privately held firms with good growth prospects but limited access to the capital markets).
Slide 10
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.3 The Discounted Payback Period
• How long does it take the project to “pay back” its initial investment, taking the time value of money into account?
• Decision rule: Accept the project if it pays back on a discounted basis within the specified time.
• By the time you have discounted the cash flows, you might as well calculate the NPV.
Slide 11
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.4 Average Accounting Return
• Another attractive, but fatally flawed, approach
• Ranking Criteria and Minimum Acceptance Criteria set by management
Investment of ValueBook Average
IncomeNet AverageAAR
12
Slide 13
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
Average Accounting Return
• Disadvantages:– Ignores the time value of money– Uses an arbitrary benchmark cutoff rate– Based on book values, not cash flows and
market values
• Advantages:– The accounting information is usually
available– Easy to calculate
Slide 14
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.5 The Internal Rate of Return
• IRR: the discount rate that sets NPV to zero • Minimum Acceptance Criteria:
– Accept if the IRR exceeds the required return• Ranking Criteria:
– Select alternative with the highest IRR• Reinvestment assumption:
– All future cash flows assumed reinvested at the IRR
Slide 15
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
Internal Rate of Return (IRR)
• Disadvantages:– Does not distinguish between investing and
borrowing– IRR may not exist, or there may be multiple
IRRs – Problems with mutually exclusive investments
• Advantages:– Easy to understand and communicate
Slide 16
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
IRR: Example
Consider the following project:
0 1 2 3
$50 $100 $150
-$200
The internal rate of return for this project is 19.44%
32 )1(
150$
)1(
100$
)1(
50$2000
IRRIRRIRRNPV
Slide 17
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
NPV Payoff Profile
0% $100.004% $73.888% $51.11
12% $31.1316% $13.5220% ($2.08)24% ($15.97)28% ($28.38)32% ($39.51)36% ($49.54)40% ($58.60)44% ($66.82)
If we graph NPV versus the discount rate, we can see the IRR as the x-axis intercept.
IRR = 19.44%
($80.00)($60.00)($40.00)($20.00)
$0.00$20.00$40.00$60.00$80.00
$100.00$120.00
-1% 9% 19% 29% 39%
Discount rate
NP
V
Slide 18
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.6 Problems with IRR
Multiple IRRs
Are We Borrowing or Lending
The Scale Problem
The Timing Problem
Slide 19
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
Mutually Exclusive vs. Independent
• Mutually Exclusive Projects: only ONE of several potential projects can be chosen, e.g., acquiring an accounting system. – RANK all alternatives, and select the best one.
• Independent Projects: accepting or rejecting one project does not affect the decision of the other projects.– Must exceed a MINIMUM acceptance criteria
Slide 20
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Scale Problem (P.175)
Slide 21
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Timing Problem
0 1 2 3
$10,000 $1,000$1,000
-$10,000
Project A
0 1 2 3
$1,000 $1,000 $12,000
-$10,000
Project B
Slide 22
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Timing Problem
($5,000.00)
($4,000.00)
($3,000.00)
($2,000.00)
($1,000.00)
$0.00
$1,000.00
$2,000.00
$3,000.00
$4,000.00
$5,000.00
0% 10% 20% 30% 40%
Discount rate
NP
V
Project A
Project B
10.55% = crossover rate
16.04% = IRRA12.94% = IRRB
Slide 23
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
NPV versus IRR
• NPV and IRR will generally give the same decision.
• Exceptions:– Non-conventional cash flows – cash flow
signs change more than once– Mutually exclusive projects
• Initial investments are substantially different• Timing of cash flows is substantially different
Slide 24
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.7 The Profitability Index (PI)
• Minimum Acceptance Criteria: – Accept if PI > 1
• Ranking Criteria: – Select alternative with highest PI
Investent Initial
FlowsCash Future of PV TotalPI
Slide 25
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Profitability Index
• Disadvantages:– Problems with mutually exclusive investments
• Advantages:– May be useful when available investment
funds are limited– Easy to understand and communicate– Correct decision when evaluating
independent projects
Slide 26
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
6.8 The Practice of Capital Budgeting
• Varies by industry:
• The most frequently used technique for large corporations is IRR or NPV.
27
87
28
Slide 29
Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved
McGraw-Hill/Irwin
The Internal Rate of Return: Example
Consider the following project:
0 1 2 3
$50 $100 $150
-$200
The internal rate of return for this project is 19.44%
32 )1(
150$
)1(
100$
)1(
50$200$0
IRRIRRIRRNPV