+ All Categories
Home > Documents > Chapter 1

Chapter 1

Date post: 31-Jan-2016
Category:
Upload: abdullah-simpson
View: 214 times
Download: 0 times
Share this document with a friend
Description:
lkmlvmdv
38
Basic Concept of Prestressing
Transcript
Page 1: Chapter 1

Basic Concept of Prestressing

Page 2: Chapter 1

Historical Background

1872, Jackson, P.H (USA)

Used a tie Rod to construct beams and arches from individual blocks.

1888, Doehring, CEW. (Germany)

Used Metal Wires for Prestressing beams and Slabs.

Page 3: Chapter 1

Historical Background

These attempts were not successful because of loss of prestress with time.

Unavailability of high strength steel to overcome prestress losses due to shrinkage and creep.

1908, stainer, C.R. (USA) Recognized losses due to shrinkage and creep and suggested retightening the rods to overcome lost prestress.

Page 4: Chapter 1

Historical Background

1924, Hewett, W.H. (USA)

Introduced Hoop-stressed horizontal reinforcement around walls of concrete tanks.

1925, Dill, R.H. (USA)

Used High strength unbonded steel rods.

1926, Eugene Freyssinet (France)

Proposed the use of High strength steel wires to overcome prestress losses.

(Father of Prestressed Concrete)

Page 5: Chapter 1

Historical Background

During the seond world war, application of prestress and precast concrete increased rapidly.

T.y. Lin contributed a lot to the art of science of prestressed concrete.

Page 6: Chapter 1

Prestressing Structures

Page 7: Chapter 1

Prestressing Structures

Page 8: Chapter 1

Early attempts

Page 9: Chapter 1

Early attempts

Original Tensile strain = s/ E = 0.5 Fy / E

= 140/ 200,000= 0.0007

Total Loss in strain = Compressive strain due to transfer of prestress + compressive strain due to (creep & shrinkage)

≈ 0.0007

Residual strain is negligible

Solution is to use high strength steel

Page 10: Chapter 1

Advantages of prestressing

1- Considerable reduction in depth of section

Relative to RC Less S.W. (Self Weight)

Longer Spas.

More aesthetic Appeal.

Span/ Depth For Slabs

- Prestressed Slab 45:1

- RC Slab 28:1

Page 11: Chapter 1

Advantages of prestressing 2- Uncracked Concrete under service loads

- Reduction of steel corrosion

- Uncracked Section Higher Moment of Inertia

Less Deformation

3- Suitable for Precast construction

- Rapid Construction. - Better Quality Control.

- Reduced Maintenance. - Suitable for repetitive construction.

- Multiple Use of formwork. - Availability of standard sections

Page 12: Chapter 1

Shapes of Prestressed Elements

Page 13: Chapter 1

Concerns of Prestressing

Need for skilled personnel.

Higher Unit Cost of stronger Materials.

Need for Expensive accessories.

Necessity for close inspection and quality control.

In the case of pretension, a higher initial investment in plant.

Page 14: Chapter 1

Forms of Prestressing Steel

Wires (Single Unit made of steel)

Strands (Two, Three, or Seven wires are wound to form a prestressing strand)

Tendon (A group of strands or wires- Normal Method for applying prestress Force).

Cable ( A group of Tendons)

High Strength Bars.

Page 15: Chapter 1

Forms of Prestressing Steel

Page 16: Chapter 1

Methods of Prestressing

I. Pre-Tension

II. Post-Tension

Pre-Tension:

- Tendons are tensioned before the concrete is placed.

- Usually performed in a casting yard in the following steps:

1. Tendons are placed in a prescribed pattern between two anchorage abutment, Tendons are then tensioned to the required force.

Page 17: Chapter 1

Pretension

Page 18: Chapter 1

Pretension

Page 19: Chapter 1

Pretension

Page 20: Chapter 1

Pretension

Concerns:

- Expensive molds.

- Prepared Plants Anchorage Abutments

Curing

Post-Tension

Page 21: Chapter 1

Post-Tension

Page 22: Chapter 1

Post-Tension

Page 23: Chapter 1

Post-Tension

5- The space in the ducts around the strands may be grouted using:

Pumped Grout Bonded Post-Tensioned

Otherwise Un-bonded Post Tensioned

Post-Tension

Post-Tension

Page 24: Chapter 1

Post-Tension

Advantages of Post-Tension: - Suitable for big cast-in place members.

Concerns:

- Requirement for anchorage devices.

- Stresses are transferred via anchorage devices.

Why Un-bonded?

1) Grouting is eliminated.

2) Ability to de-stress the strands

3) Replaceable.

Page 25: Chapter 1

Post-Tension

Why Bonded?

1) Tendons are less likely to de-stress.

2) Higher Ultimate strength due to bond generated between the strand and the concrete.

3) No Maintenance is needed due to:

Corrosion

Anchorage Ends

Post-Tension

Post-Tension

Page 26: Chapter 1

Duct

Page 27: Chapter 1

Anchorages

Page 28: Chapter 1

Anchorages

Page 29: Chapter 1

Jacking

Page 30: Chapter 1

Jacking

Page 31: Chapter 1

Grouting

Page 32: Chapter 1

Post-Tension

Page 33: Chapter 1

Post-Tension

Page 34: Chapter 1

Post-Tension

Page 35: Chapter 1

Source of Prestressing Force

1) Hydraulic Prestressing (Most Popular).

2) Thermal Prestressing by application of Electric Heat (The wires are anchored before placing the concrete in the molds).

3) Chemical prestressing by means of expansive cement which expands chemically after setting and curing hardening.

Page 36: Chapter 1

Types of Prestressing

Based on Location of Tendons:

1- External Prestressing:

- Tendons Lie outside the member or inside the hollow space or box girder.

- This technique is adopted for bridges and strengthening of existing structures.

2- Internal Prestressing:

- Tendons Lie inside the concrete member ( Concrete of the member is casted around the ducts.

Page 37: Chapter 1

Types of Prestressing

Based on amount of prestressing Force:

1. Full Prestressing: No tensile stress under service loads.

2. Partial Prestressing: Crack width is within allowable limits.

3. Limited Prestressing: Tensile stresses are within cracking strength of the concrete.

Page 38: Chapter 1

Types of Prestressing

Based on the direction of prestressing:

1. Uniaxial: Parallel to one axis. – Example: Beams.

2. Biaxial: Parallel to two axis. Example: Slabs.

3. Multiaxial: Parallel to more than two axis. Example: Domes.

Based on the shape of the member:

1. Linear: Beams & Slabs.

2. Circular: Tanks & Silos.


Recommended