Page 1: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Chapter 10

Page 2: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Activity-on-Node Network Fundamentals

X

Y

Z

Y and Z are preceded by X

Y and Z can begin at thesame time, if you wish

(B)

A B C

A is preceded by nothingB is preceded by AC is preceded by B

(A)

J

K

L

M

J, K, & L can all begin atthe same time, if you wish(they need not occursimultaneously)

All (J, K, L) must becompleted before M canbegin

but

X Z

AAY

(C)

(D)

Z is preceded by X and Y

AA is preceded by X and Y

Page 3: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Network-Planning Models• A project is made up of a sequence of activities

that form a network representing a project.

• The path taking longest time through this network of activities is called the “critical path.”

• The critical path provides a wide range of scheduling information useful in managing a project.

• Critical Path Method (CPM) helps to identify the critical path(s) in the project networks.

Page 4: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Prerequisites for Critical Path Methodology

A project must have:

well-defined jobs or tasks whose completion marks the end of the project;

independent jobs or tasks;

and tasks that follow a given sequence.

Page 5: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Types of Critical Path Methods

• CPM with a Single Time Estimate– Used when activity times are known with certainty.– Used to determine timing estimates for the project, each

activity in the project, and slack time for activities.

• CPM with Three Activity Time Estimates– Used when activity times are uncertain. – Used to obtain the same information as the Single Time

Estimate model and probability information.

• Time-Cost Models– Used when cost trade-off information is a major consideration

in planning.– Used to determine the least cost in reducing total project time.

Page 6: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Steps in the CPM with Single Time Estimate

• 1. Activity Identification.

• 2. Activity Sequencing and Network Construction.

• 3. Determine the critical path.– From the critical path all of the project and

activity timing information can be obtained.

Page 7: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1. CPM with Single Time Estimate

Consider the following consulting project:

Develop a critical path diagram and determine the duration of the critical path and slack times for all activities

Activity Designation Immed. Pred. Time (Weeks)Assess customer's needs A None 2Write and submit proposal B A 1Obtain approval C B 1Develop service vision and goals D C 2Train employees E C 5Quality improvement pilot groups F D, E 5Write assessment report G F 1

Page 8: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: First draw the network

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

A None 2

B A 1

C B 1

D C 2

E C 5

F D,E 5

G F 1

Act. Imed. Pred. Time

Page 9: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine early starts and early finish times

ES = ? EF = ?

ES=0EF=2

ES=2EF=3

ES=3EF=4

ES=4EF=9

ES=4EF=6

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

Page 10: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine early starts and early finish times

ES=9EF=14

ES=14EF=15

ES=0EF=2

ES=2EF=3

ES=3EF=4

ES=4EF=9

ES=4EF=6

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

WHAT IS EF OF THE PROJECT?

Page 11: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine late starts and late finish

times

ES=14EF=15

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LF=15

Duration = 15 weeks

Page 12: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine late starts and late finish

times

ES=14EF=15

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LF=15

Duration = 15 weeks

Page 13: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine late starts and late finish

times

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LF=15

LS=9LF=14

LS=4LF=9

LS=7LF=9

LS = ?LF = ?

Page 14: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Determine late starts and late finish

times

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LF=15

LS=9LF=14

LS=4LF=9

LS=7LF=9

LS=3LF=4

LS=2LF=3

LS=0LF=2

Page 15: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: DON’T WRITE DOWN, JUST TO SHOW ALL NUMBERS

ES=9EF=14

ES=14EF=15

ES=0EF=2

ES=2EF=3

ES=3EF=4

ES=4EF=9

ES=4EF=6

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LF=15

LS=9LF=14

LS=4LF=9

LS=7LF=9

LS=3LF=4

LS=2LF=3

LS=0LF=2

Page 16: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

NOW:::

• FOR CRITICAL PATH

Page 17: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Critical Path & Slack

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

ALL THAT IS NEEDED ES & LS or EF & LF

I PREFER ES & LS

Page 18: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Critical Path & Slack

ES=9 ES=14ES=0 ES=2 ES=3

ES=4

ES=4

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LS=9

LS=4

LS=7

LS=3LS=2LS=0

Duration = 15 weeks

Page 19: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 1: Critical Path & Slack

ES=9 ES=14ES=0 ES=2 ES=3

ES=4

ES=4

A(2) B(1) C(1)

D(2)

E(5)

F(5) G(1)

LS=14LS=9

LS=4

LS=7

LS=3LS=2LS=0

Slack=(7-4 = 3 Wks

A CHECKTASK LS - ES CPA 0 - 0 YESB 2 - 2 YESC 3 - 3 YESD 7 - 4 NOE 4 - 4 YESF 9 - 9 YESG 14 - 14 YES

THEREFORE CP = A-B-C-E-F-G

Page 20: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. CPM with Three Activity Time Estimates

TaskImmediate

Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28

6

4

6

Time Pess. + Time)Likely 4(Most + Time Opt. = Time Expected

bmaET

OR

a m b

Page 21: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Expected Time Calculations

TaskImmediate

PredecesorsExpected

TimeA None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18

ET(A)= 3+4(6)+15

6

ET(A)=42/6=7

6

4 bmaET

Page 22: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Network

A(7)

B(5.333)

C(14)

D(5)

E(11)

F(7)

H(4)

G(11)

I(18)

Duration = 54 Days

Page 23: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Network

A(7)

B(5.333)

C(14)

D(5)

E(11)

F(7)

H(4)

G(11)

I(18)

Duration = 54 Days

ES=0

ES=7

ES=7

ES=21

ES=32

ES=12

ES=36

ES=0 ES=5.333

LS=36

LS=32

LS=21LS=7

LS=0

LS=25LS=20

LS=25LS=19.667

Page 24: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

THEREFORE:

• CRITICAL PATH IS:

A-C-E-H-I

Page 25: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Probability ExerciseWhat is the probability of finishing this project in less than 53 days?

p(t < D)

TE = 54

Z = D - TE

cp2

tD=53

Page 26: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

22

6

a-b = ariance,Activity v

Task Optimistic Most Likely Pessimistic VarianceA 3 6 15 4B 2 4 14C 6 12 30 16D 2 5 8E 5 11 17 4F 3 6 15G 3 9 27H 1 4 7 1I 4 19 28 16

(Sum the variance along the critical path.)

41=2 cp

Page 27: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

There is a 43.6% probability that this project will be completed in less than 53 weeks.

p(Z < -.16) = .5 - .0636 = .436, or 43.6 % (Appendix D)

Z = D - T

=53- 54

41= -.156E

cp2

TE = 54

p(t < D)

t

D=53

or - .16

Std Normal Dist.

Page 28: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Additional Probability Exercise

• What is the probability that the project duration will exceed 56 weeks?

Page 29: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Example 2. Additional Exercise Solution

tTE = 54

p(t > D)

D=56

Z = D - T

=56 - 54

41= .312E

cp2

p(Z >.31) = .5 - .1217 = .378, or 37.8 % (Appendix D)

or .31

Std Normal Dist.

Page 30: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

Time-Cost Models• Basic Assumption: Relationship between

activity completion time and project cost.

• Time Cost Models: Determine the optimum point in time-cost tradeoffs.– Activity direct costs.– Project indirect costs.– Activity completion times.

Page 31: Chapter 10. Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) ABC A is preceded.

CPM Assumptions/Limitations • Project activities can be identified as entities.

(There is a clear beginning and ending point for each activity.)

• Project activity sequence relationships can be specified and networked.

• Project control should focus on the critical path.• The activity times follow the beta distribution,

with the variance of the project assumed to equal the sum of the variances along the critical path. Project control should focus on the critical path.