Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
36
CHAPTER-2: DISASTER MANAGEMENT BY GOVT AGENCIES –
SELECTED CASE STUDIES
In the recent times some of the crises like urban floods, earthquake and drought have
been causing considerable losses and creating the distress hotspots in the country. The
Mumbai floods 2005 along with the ONGC, Mumbai High disaster caused a loss of Rs
30,000 crore. Similarly, the recurrent droughts have been indirectly driving the small and
marginal farmers into extremely distress situation falling in the trap of local money
lenders. The disaster management strategies by Government agencies have been analysed
in the case studies described in this chapter.
In the government approach, there is a visible and subtle transitions leading from disaster
response to disaster risk reduction.2.1
The key points, listed below, reflects how a holistic
disaster risk reduction strategy is evolving in India:
i) Till Killari earthquake in 1993, India had been responding to natural disasters with a
relief centric approach. Very limited efforts were taken on mitigation and preparedness
and those were not connected with sustainable development efforts in the country. India
learnt from Killari earthquake experiences and started placing more focus on mitigation,
economic recovery and community participation;
ii) Following Andhra Pradesh cyclone in 1997 and Orissa super-cyclone in 1999, disaster
risk management concepts further developed; initiatives were led by affected states in
association with central government and multi-lateral agencies but have not been very
successful. However, the need was felt having proper institutional and legal framework
in disaster risk management;
iii) Bhujearthquake in 2001 prompted major institutional and legal framework; disaster
management shifted from Ministry of Agriculture to Ministry of Home Affairs;
mitigation and preparedness formally recognised at various levels; link between
disaster management and sustainable development recognized; disaster management
recognised also as a “political agenda”;
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
37
iv) Since then, India has taken rapid strides such as:
� Gujarat disaster management strategy widely acclaimed – Honourable mention for
Sasakawa Award;
� Disaster Risk Management (DRM) Program initiated – Helped develop a cadre of
motivated and trained disaster management practitioners;
� Disaster Management Act passed by Indian Parliament;
� National Disaster Management Policy and Guidelines issued by the National
Disaster Management Authority (NDMA).
v) The major challenges/lessons listed out include:
� Inadequate review of past disasters – poor ability to learn from the past;
� Unable to evaluate future disaster risks;
� Inability to fully engage various stakeholders;
� Many programs based on empirical knowledge;
� Mismatch in scale of problem and programs under implementation
vi) These challenges could be addressed by putting into practices the learning from the
disasters of the past while preparing to mitigate the future disasters. Knowledge
management aspects, as listed below, have been highlighted as the key to effective
disaster management in future:
� Knowledge of contributory factors,
� Knowledge of consequences of disaster,
� Knowledge of mitigation measures,
� Knowledge of preparedness measures,
� Multi-disciplinary knowledge is required – technical, administrative, social,
political, financial, etc.
vii) Knowledge management cycle in disaster management covering assessment of lacunae,
empirical and academic knowledge, and specifications to state of the art practices was
advocated to form the basis of regulatory, social and policy inputs.
viii) Focusing on knowledge management as a key input for disaster risk reduction, it could
be concluded that:
� Lessons from the past provide important (but not total) knowledge,
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
38
� Future strategies should be based on realistic understanding of disasters and the role
of all stakeholders – KNOWLEDGE IS THE KEY,
� Strategies should aim to support sustainable development,
� Disaster Risk Management should be embedded in various regular programs of all
stakeholders.
The Government response to some of the specific disasters in the recent times is
summarized below:2.2
2.1 Case Study 1: Mumbai Floods 2005
Mumbai city, having an area of 437 sqkm with a population of 12 million, came to a
complete halt owing to the unprecedented rainfall of 994 mm during the 24 hours on 26 July
2005. At least 419 people (and 16 000 cattle) were killed as a result of the flash floods and
landslides in Mumbai municipal area, and another 216 as a result of flood-related illnesses.
Over 100,000 residential and commercial establishments and 30, 000 vehicles were
damaged.This was the highest rain fall (for one day) ever recorded in India from past 100
years. The previous highest was atCherrapunji - 985 mm in 1974.
On 26th July2006, Mumbai received a record- breaking rain of 94 cm. Thousands of
Mumbaikars were stranded. Streets turned rivers and transport networks came to a complete
halt. Mumbai’s suburban rail and Bus system both lurched to a dead stop. Air services were
also affected. Massive water logging and congestion paralyzed telephone lines and cell phone
systems. Electricity was shut off in many places for several days, prompting the Government
to order electricity supply companies to resume operations forthwith. The Bombay Stock
Exchange suspended trading. The armed forces were called in for rescue and food
distribution work. Government authorities urged people to remain indoors.
The rain fall started early in the morning at 8:30 and it gradually started to pour down heavily
by around 3:30 PM to 4:30 PM. During this duration there was a heavy rainfall of around
190.3 mm. This was the highest rainfall recorded throughout the day. This heavy rainfall was
accompanied with high tides at around 3:50 pm. Due to these high tides the sea level
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
39
increased by 4.48 m which made the sea water to come in to the drain which led to increase
in water level in the drainage system. There was no way for the rain water to drain. This led
to the flood.
One more reason for the flood was that the sewage pumps shutdown. To prevent damage to
the pumps at the sewage pumping stations, pumps were switched off. This led to the back
flow of the sewage water.
An assessment of strength and weakness of Governmental systems in handling Mumbai
floods 2005 has been highlighted below:
Strength
� Response of various agencies of Government was quick. Army was deployed within 12
hours of the first day of incessant rainfall of 27th
July 2006. Indian Army deployed 16
columns and 15 medical teams, Indian Navy put 16 relief teams and Indian Air Force
deployed 2 helicopters for rescue and relief operations in the affected areas. 3 teams of
Disaster Management Battalions provided by the CRPF were placed with DG Police for
rescue and relief operations. These helped rescue operations and helped to restore
normalcy soon.
� Declaration of 27th and 28th July as state holidays, closure of all schools and advisory to
all residents to stay indoors were real smart moves, which helped to ease the situations,
particularly considering the fact that 150,000 commuters and 15,000 school children were
stranded on the road on the first day of the disaster.
� Civil society responded in a big way. Shelter and food was provided to school children
and not a single case of arson or looting was reported despite the preoccupation of
thepolicein rescue operations. This was in sharp contrast to the situation in New Orleans
hurricane a month later.
� Massive immunization programme and effective mobilization of health infrastructure
prevented any major epidemics although as many as 170 persons lost their lives due to
leptospirosis. This could be much worse considering the magnitude and extent of
inundation of low-lying slum areas.
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
40
Weakness
� Unprecedented rainfall completely exposed the weather prediction and early warning
system.
� Both the Indian Meteorological Department, in its 24-hour forecast and the National
Centre for MRWF in its 48-hour forecast predicted only 8cm to 16 cm of rain over
Mumbai on 26th
-27th
July but actual rainfall recorded was 94.4 cm. Thus the margin of
error was nearly 600%.
� There were significant intra-regional differences in rainfall due to cloudbursts in some
areas. For example Colaba had a rainfall of 7.3 cm while Santacruz experienced rainfall
of 96 cm. Neither IMD nor NCMRWF could forecast these huge intra city differences in
rainfall.
� While unprecedented rainfall was the main reason of Mumbai flood, other contributing
factors were unplanned urban development in complete disregard of delicate environment
and ecology of the area.
Other contributing factors for the flood were an antiquated storm-water drainage system
of MumbaiCity which is nearly 100 years old and is capable of draining 25 mm of water
per hour against actual rainfall of 96 cm. The drainage system is also clogged due to
heavy ingress of solid waste. Only 3 'outfalls' out of 115 are equipped with floodgates
and there is no way to stop seawater from rushing into the drainage system during high
tide. Rs. 600 crore project for overhauling the drainage system was prepared, but the
project had to be shelved by Bombay Municipal Corporation on cost consideration.
MumbaiCityDisaster Management Plan (DMP) was prepared in 2000 under World Bank
funded earthquake reconstruction project, but the plan was not updated during last five
years. The worst scenario not anticipated in worst affected wards. The process of bottom
up approach not followed in preparation on DMP. Community not involved with
preparation and implementation of disaster management plan. Concerns expressed by
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
41
environmentalists not given any consideration. The city development authorities took no
meaningful flood mitigation project.
Sometimes unplanned development projects without due consideration of the hazards,
risks and vulnerabilities may themselves create or precipitate disasters. For example - a
study on the recent floods in Mumbai has shown that various city development projects in
the recent past had contributed to the crisis such: as (a) Bandra-Kurla complex over 730
acres of mangrove wetland in Mahim creek destroyed the natural drainage system and
cushion against tidal surge, (b) expansion of airport runway diverted the course of Mithi river,
(c) widening of the western expressway seriously compromised the drainage system and (d)
indiscriminate Transferable Development Right (TDR) without consideration of carrying
capacity of the area. Such examples would galore in every State.
2.2 Case Study 2 : Kosi Floods 2008
The response from Government of India to natural disasters has now been overall well
structured. Relief and rehabilitation were followed by long term mitigation and risk reduction
in the major disasters. For example, the floods which affected largely India in 2008 were
responded better. The response to Kosi flood 2008 is worth mentioning as a success story.
On Aug 18, 2008 an embankment of river Kosi in South Nepal breached, leading to change
of the river course completely and finally resulted in one of the worst flood disasters in
Bihar, India. The flood inundated large areas of Nepal and the state of Bihar in India,
affected nearly 4 million people (Nepal and India put together) and caused immeasurable
sufferings to poor people in one of the most backward areas of the region. As per the latest
damage assessment figure released by Govt. of Bihar in Feb 2009, inBihar alone, 3.32
million were affected, while 527 people lost their lives. Close to one million affected
population were evacuated and enabled to take shelters in relief camps for more than 3-4
months. On the mission mode, efforts were made to carry relief materials to remote areas by
helicopter, making the boat available in large numbers, providing the health facilities in the
affected areas and in the camps. The specialized Natural Disaster Response Force, which has
been set up recently by National Disaster Management Authority along with armed and
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
42
paramilitary forces, took part in massive response operations. All these efforts helped in
enhancing the quality of response and keeping the loss of lives to the bare minimum.2.3
Strength: What made Kosi flood response effective?
Considering the nature of disasters, the people in Bihar calls ‘Kosi catastrophe’ not the floods.
Several new and innovative methods were adopted to enhance the quality of response, which
worked well on the ground. An effective management practice followed up by the Govt of
Bihar include the followings: 2.4
i) Control Room setup added efficiency as well as effectiveness
The Control room set-up was comprised of:
� State & District Level- Telephone Nos. adequately publicized through Radio, News
Papers, TV Channels
� 24 x 7 Operational
� Adequate Human Resources Support
� Data Bank concept (Near real time satellite maps showing the inundation dynamics) –
Regular Follow up
� Decision making –Quick Response
ii) Effective use of Technology
� Extensive use of mobile phones by all stakeholders
� Restoration of Tele-communication network
� Satellite Map – Flood Management Information System (FMIS) of Govt. of Bihar &
National Remote Sensing Centre (NRSC) portal of Govt. of India
� Satellite Phone setup in affected districts.
� Mobile Inspector
� Departmental website – Daily updation
iii) Monitoring Response & Relief Activities
� Minister in charge for each affected districts
� Deputation of Senior Officers -Districts/ Sub divisions/ Blocks
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
43
� Inter Departmental Coordination - Daily Review
iv) Rescue & Evacuation Operation
� Identification of inundated areas
� Analysis through Satellite images
� Streamlining of Evacuation Plan
� Massive mobilization of boats from all over the state
� Proper deployment of early responders
� (Extensive deployment and more effective and strategic use of Army/ Navy/ National
Disaster Response Force (NDRF)/State Forces)
� Coordination between Civil &Defence Authorities
� Frequent Aerial Survey
� 24 x 7 Help Line Service at Control Rooms-important telephone numbers publicized.
� Special Appeal to affected populace (Media/Radio/Pamphlets)
v) Relief CampManagement
� Affected & evacuated persons sheltered in camps.
� Concept of mini township-Mega Camps
� People’s participation in camp management
� Utility services to camp inmates
� Special health care for women & children
� Entertainment & skill development initiatives
� Effective policing - special thrust on law & order
� GR & Cash Dole – in two phases
vi) Effective Handling of Media
� Separate Media Room established
� Updated Information on website
� Daily Press Release, Press conference
� Quick response on received information
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
44
Weakness: Regional Cooperation – A Missing Link
With the backdrop of lessons emanating from Kosi flood 2008, the bilateral mechanisms
between India and Nepal gained momentum with the formation of Ministerial and high
level official committees to look into better ways to manage embankments and create more
accountable mechanisms to evolve trans-boundary solutions to problems of Kosi floods in
the future. Further, these committees are likely to examine various ways and means including
building the cluster of high dams, upstream embankments, benefit and resource sharing in the
forms of flood control, irrigation, power etc.
In the unique geographical settings of the region, unquestionably, solution to floods and
water security in South Asia lies in enhanced regional cooperation. It is important to
recognize that floods are the cumulative outcome of rainfall in the catchment areas, siltation
loads on rivers, settlement pattern on the plains and standards of maintenance of flood
protection works. Long term measures for flood risk mitigation include conservation of the
catchments, efficient system of early warning of floods, protection measures at vulnerable
locations and increased awareness about the measures to be taken to live with the
flood.Despite all the structural and non-structural measures, there would be still a residual
risks of flood which cannot be prevented and which we have to learn to live with. The
countries of the region would stand to gain immensely if a sound mechanism of regional
cooperation on flood risk mitigation in South Asia is developed. The specific issues on which
regional cooperation can play significant role in mitigating the risks of flood are as under: 2.3
� Set up an institutional mechanism for regional cooperation on flood risk mitigation in
South Asia on the pattern of Mekong River Commission which has immensely benefited
the countries of South East Asia;
� Develop a regional early warning system on flood whereby upstream countries share
information on rainfall and river discharge etc. with the downstream countries on a
regular basis;
� Develop a data base on regional drainage system, topography, settlement pattern etc. on
the basis of which flood modeling can be carried out at regional and local scales for better
understanding and planning for reducing the risks of flood;
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
45
� Identify the cross country flood protection measures that can be taken up jointly at sub-
regional level;
� Study the short, medium and long term impacts of climate change on the flood situation
in South Asia and develop a long term strategy and planning for adapting to such
impacts;
� Share good practices on flood management adopted by the countries and the
communities;
� Promote greater exchange of ideas through field visits, training programmes etc.
2.3 Case Study 3 : Recent Droughts
While many definitions of drought exist, the importance of drought lies in its overall social,
economic and environmental impacts. With non-structural nature and greater spatial extend,
drought hits the largest number people. The agrarian economies of the developing nations are
therefore more vulnerable. In fact, drought has been one of the primary reasons for
widespread poverty and environmental degradation. Further the climate model predictions
indicate that global change is like to increase the vulnerability of tropical countries to drought,
more in south Asia, where India is likely to get hard hit (IPPC 1996 and 2001).
Droughts refer to a serious shortfall in availability of water, mainly but not exclusively due to
deficiency of rains, affecting agriculture, drinking water supply and industry. Droughts can
occur anywhere in the world bringing misery particularly to most of Africa and large parts of
West and South Asia due to heavy dependence of populations on agriculture and the
generally degraded status of land in these areas- the causative factors being both natural and
man-made. The impact of droughts on societies widely varies depending on `coping
capabilities' and the general health of the national economies concerned.
India is amongst the most vulnerable drought-prone countries of the world; a drought is
reported atleast once in every 3 years in the last 5 decades. What is of more concern is its
increasing frequency. Since the mid-nineties, prolonged and widespread droughts have
occurred in consecutive years while the frequency of droughts has also increased in the
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
46
recent times (FAO, 2002, World Bank, 2003). The impact of droughts is more severe on the
food and agriculture sector. The loss of crop and livelihood and its effect on the agrarian
economy have severe consequences to the overall well-being of the rural poor. Continued
decline of productivity leads to diminished assets and reduced investments.
Within this generalization, droughts in India have their own `peculiarities', brief reference to
which is essential to understand what needs to be done to deal with emergencies more
efficiently. Such `peculiarities' require appreciation of some basic facts.2.5,2.6,2.7
These are:
♦ India has an average annual rainfall of around 1150 mm; no other country has such a
high annual average;
♦ However, more than 80% of rainfall is received in less than 100 days during the South-
west monsoon;
♦ Adequacy of rains coupled with adverse `land-man ratio' compels the farmers to
practice "rain-fed" agriculture in large parts of the country;
♦ Despite the overall liberal precipitation, 21% area receives less than 700 mm rains
annually making such areas the `hot spots' of droughts;
♦ Irrigation, supposedly the perfect answer to drought, itself aggravates the situation in
the long run as Ground-water withdrawal exceeds its replenishment; in the peninsular
region availability of surface water itself becomes restricted whenever there is severe
rainfall insufficiency;
♦ Per capita water availability in the country is steadily declining;
♦ Changing life-styles occasioned by a buoyant economy have immensely escalated
demand for water leading to a situation where even minor setbacks in supply produce
major problems;
These factors demonstrate the complexity of Indian droughts and the constraints which rule
out `perfect solutions'. Further, it is of utmost importance to understand a major corollary of
the Indian `peculiarities'; causes of droughts will be increasingly traceableto the mismatch
between supply and demand, particularly the demand for non-agriculturalpurposes. In other
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
47
words, it is not as if, a pre-existing problem is awaiting better remedies, the 'problem itself is
becoming more complex.
Finally, it needs to be underscored that like anywhere else in the world, agriculture is
affected by weather in all its phases- from tillage and sowing to post harvest disposal. Thus
while adequate availability of water is crucial to the well-being of agriculture, it will continue
to be affected by other variables like temperature, humidity, solar radiation and wind patterns
etc.
2.4 Drought Management – Institutional Framework
The country has institutionalized drought monitoring system, declaration and mitigation at
different levels. The India Meteorological Department carries out drought monitoring and the
forecasting function. It has over time evolved complex parametric models to forecast the
probable arrival and intensity of the monsoon on broad regional scales. To internalize this
mechanism there is an Inter-Ministerial Crop Weather Watch Group within the Ministry of
Agriculture. Whereas drought declaration is the primary responsibility of the concerned State,
post-declaration, the Central Government assists and facilitates finance and institutional
assistance and processes. Financing Relief Expenditure is in accordance with the awards of
the Finance Commission appointed every five years. Under the award, two Funds have been
set up - constituting the Calamity Relief Fund (CRF) and Natural Calamity Contingency
Fund (NCCF). The CRF has been in operation for each State with an amount prescribed by
the Commission and is maintained outside the government account, receiving contributions
from Central and State Government in the ratio of 3: 1 in two half yearly instalments. The
declaration of drought sets into motion several response mechanisms at various levels of
management, including constitution of several Special Task Force, High Level Committee
and Control Rooms. In almost all cases, the drought situation is moderated by
commencement of employment generation through relief works, cattle conservation camps,
medical and health arrangements and creation of new water sources.
For a long term solution and mitigation of drought relief problems, Government of India has
put in place several innovative and people centric programmes like the National Watershed
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
48
Development Programme, Drought Prone Area Programme, Desert Development Programme
and very recently the Dry-land Farming Programme.2.8,2.9
2.5 Changing Patterns
It is not mere chance that the description of the situation resulting from failed or erratic
Monsoon has undergone changes over the last century or so. Till the 1920s, it was "famine",
indicating acute dearth of food supply; from the 30s to well into 60s of that century the
phenomenon was "scarcity" connoting inadequacy of agricultural production i.e. a situation
where it is the agriculture dependant who is distressed and not the rest of the population. The
current formulation is "drought" viz. inadequacy of water. There is more than changing
preference for words in this linguistic passage. Credit for this metamorphosis can be given to
the increasing efficacy with which Indian Public Administration has managed to deal with
the aftermath of disappointing monsoon rains in the above time span. Broadly speaking, the
transition from "famine" to "scarcity" owed itself to rational policies governing food grain
trade and the ability of the Government to speedily move goods; the graduation from
"scarcity" to "drought" is the gift of the Green Revolution.
There is no gainsaying the fact that this shift necessarily makes a difference to crisis
management. Improvement in resource base, and rising expectations of the affected
population, require that ameliorative measures commence much earlier. Improvements in
technology and widening of scientific knowledge enable early detection of emerging
problems and the awesome outreach of media now facilitates dissemination of such
information with a speed not conceivable even in mid 1990s. Larger resources now need to
be deployed to mitigate hardship than ever before- resources not only in terms of money but
also in the form of areas of `relief interventions'. A simple illustration will explain the point;
for the period, 1985-90 the total expenditure on drought relief was no more than Rs 2500
crores, this rose to almost Rs 40000 crores for 2000-05. Similarly, in 1985 there were around
20 identified `action points' for Central Government agencies and Departments to supplement
`relief efforts' of States, there are 41 such points now. 2.10,2.11, 2.12
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
49
Such increases are clearly on account of more activities qualifying for relief, an even more
liberal scale of funding and increasingly early triggering of responses. Such factors have,
however, given rise to problems e.g. increasing the scope for coordination and strengthening
the existing administrative machinery to shoulder 'additional' responsibilities etc.
For all natural calamities, prevention and mitigation are closely linked,the linkage is
particularly strong in case of droughts. Added to this is the rather ambitious and considerably
unrealistic perception in the public domain-a view which experts have done little to put in
perspective- that if enough efforts are made droughts can be altogether eradicated. This
makes it imperative that measures to improve crisis management may not be considered in
isolation from strategies to reduce vulnerability.
2.6 Key Learning
2.6.1 Bringing "Water" at the Centre Stage of Policy Domain
Management of the crisis as also long term solutions would be sub-optimal unless they take
into account the larger issue of a National Water Budget and a policy regime that takes
holistic cognizance of the mismatch between supply and demand. A major impediment in
making progress in this direction is the `segmented policy attention' receives from a number
of ministries/Departments. Without being exhaustive, attention may be invited to the
following different policy platforms:2.13,2.14,2.15
• Ministry of Water Resources; Irrigation and Flood Control; Inter-Basin transfer etc.;
• Department of Drinking Water Supply; Accelerated Rural Water Supply Programme;
• Ministry of Urban Development; Urban Water Supply; Ministry of
Environment and Forests; Lakes; control of Desertification/Aridity;
• Ministry of Agriculture; Watershed Development;
• Ministry of Rural Development; Water conservation in rural areas;
• Ministry of Science and Technology; Hydrology, Hydrogeology etc.
This is only an illustrative list and can be easily multiplied. The long term interests of the
country, including drought related concerns, will be better addressed if all the policy aspects
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
50
and schemes with objectives like water, water conservation and improving water availability
as primary concerns are brought on a single policy platform. This aspect needs to be
considered along with other issues relating to `machinery of the central government'. It may
be added here that while a National Water Policy encompassing diverse policy concerns was
framed in 2001 with the Ministry of Water Resources as the `nodal point', recognition of
`policy diversities' has not resulted in emergence of an integrated Road Map, integration of
responsibilities under one roof is clearly indicated.
2.6.2 Crisis Preparedness- Limitations of `Drought Proofing'
Rhetoric about making the country "drought proof' has inadvertently contributed to a degree
of neglect of `acute' drought management. In 2002, for instance, some of the worst affected
pockets had some groundwater `irrigation cover'. Local communities and administrations
alike were complacent in the belief that `exploitation of groundwater' had brought about
"drought proofing"; there was no adjustment in cropping pattern even with an unprecedented
break in July rains. The degree of distress in such areas was often more severe than in
adjoining ‘rain-fed’ pockets. Understandably, there was poor preparedness for relief
operations. The reason is obvious where droughts are `unexpected', preparedness is poor.
Preparedness and recognition go hand in hand.
Such recognition should preferably inform a policy document on managing acute droughts to
be brought out by the nodal Department. Such document should facilitate putting general
formulations like, `making the country drought free' in perspective. It is imperative that
without discounting the essential role of long-term measures for reducing vulnerability,
inevitability of `acute events' occurring somewhere or the other is acknowledged. This will
contribute to maintaining a high level of preparedness and harmonize the `long' and `short'
term measures.
2.6.3 Long and Short-Term Measures - Policy Integration
While a number of centrally sponsored Schemes have objectives connected, directly or
indirectly, with drought avoidance, the two pre-eminent interventions in this sphere are the
Drought Prone Area Programme (DPAP) and the Desert Development Programme
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
51
(DDP). The thrust of these schemes is to `treat' land and vegetation in selected areas,ina
manner that the `treated areas' become less vulnerable to ill effects associated with high
drought vulnerability and aridity. These schemes are handled by the Department of Land
Resources (DoLR) in the Ministry of Rural Development. DoLR is also entrusted with
another issue of crucial significance to agriculture, namely, Land Reforms. As already
mentioned, for droughts, management of the acute crisis and the chronic malady are best
dealt with in a holistic manner. It is, therefore, imperative that management of the acute crisis
and chronic problems in case of droughts is handled in the same Ministry.2.14, 2.15
2.6.4 Diagnosis andPrognosis of Drought Situations
Satellite imagery and similar techniques are powerful tools in anticipating occurrence and
assessment of the effect of `extreme weather events' generally. Its efficacy and value has
been repeatedly demonstrated in pilot mode, both during droughts and normal periods. Such
successful demonstrations have, however, not always lived up to the `pilot' promise in field
situations.
The problem is not with technology, hardware or expertise; it lies in evolving a paradigm that
enables the `exotic' to go `native'. Putting it simply, `remote sensing' has not yet been
dovetailed in the routine institutional framework, as for instance, is the case with
communication technologies. Given the tortuous course of droughts, remote sensing cannot
be used on `stand-alone' basis- there is no alternative to the `mainstreaming' taking place at
the cutting edge level in the States. The process calls for innovative solutions, which, apart
from being cost effective leave room for technological and professional innovation. A
workable, indicative, model would involve positioning of technical personnel of the
Department of Space (DOS), National Remote Sensing Centre (NRSC) at the District level
on the analogy of similar arrangements by the NationalInformaticsCentre (NIC). NRSC
personnel will function in close association with the revenue functionaries of the District to
generate information that is constantly buttressed by `ground truth verification'.2.15,2.16,2.17
A
State level cell of the NRSC will have the responsibility of collating District-wise
information on as near `real time' basis as possible.
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
52
2.6.5 Rationalization of Drought Declarations
Requirements of Revenue laws or executive instructions of Famine/Scarcity codes entail a -
formal declaration of droughts. In many States relief works can commence only after such a
declaration. Such declaration has the effect of wholly or partly extinguishing the liability of
the land-holder to pay land revenue. In the days when land revenue constituted a major
resource for the State, issue of such declarations had major fiscal consequences unconnected
with the management of disaster per se. 2.18,2.19
Not surprisingly, therefore, issue of declarations has become a rather cumbersome process
preceded by `crop cutting' experiments variously called `Paisewari, `Anawari', `Relief
Khatauni' or 'Kharaba' etc. For 'Kharif droughts the earliest declarations have not been
possible before October i.e. at least three months into a severe drought. Some States do have
an enabling provision about `eye estimations' in case of a very severe drought. This involves
an assessment of area that is left unsown due to severe moisture distress or withering of
plants soon after germination.
The method and mechanism of declaration of droughts can do with some rationalization. The
following broad guiding principles need to be kept in view:
a) Where twenty per cent of area normally cultivated remains unsown till the end of July or
December for Khalif and Rabi respectively the affected Tehsil/Taluka/Mandal could be
declared drought affected by the Government.
b) Declaration of drought be not insisted upon for meeting expenditure on Drinking Water
Supply from the CRF (and not the NCCF) if at least 20% of the villages in a District
Report deficient water availability attributable to failure of rains.
2.6.6 Financial Assistance for Droughts
A very significant difference between droughts and almost all other natural calamities is its
long course before the situation stabilizes. This difference has important implications for
relief operations. For floods and cyclones immediate relief measures are initiated which
involve incurring expenditure from the Calamity Relief Fund (CRF). This process is
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
53
accompanied by projection of detailed additional requirements of funds from the National
Calamity Contingency Fund (NCCF). The exigencies of the situation in such cases leave
little scope for inaction. Experience in case of droughts, however, shows that inMost of the
cases initiation of relief operations is delayed as long as possible.This approach has serious
implications for Crisis Management - the very concept of CRF as a source of readily
available funds to meet the exigencies of a calamity without any delay is defeated. The
present arrangement of financing relief expenditure has no incentive or disincentive for early
provision of relief to victims of droughts. There is a strong case for introducing this element
in financing relief expenditure and accordingly, it is recommended that:2.20
a) A condition should be laid down that a State can seek assistance from the NCCF only
after it spends at least half the balances in its CRF on drought relief; and
b) The assistance sanctioned from the NCCF in case of droughts should be without
adjusting any balance in the CRF.
2.6.7 Relief Employment
Even in the mid-19th
Century a keen observer of the Indian scene (Baird-Smith) could remark
that (the)"Indian Famine is not a famine of food but a famine of work". It is not surprising,
therefore, that provision of relief employment has always accounted for bulk of relief
expenditure ever since Famine/Drought Relief operations were first undertaken
systematically from 1870s.
The enactment of the National Rural Employment Guarantee Act-2005 (NREGA) has
important implications for relief employment although its impact may be felt only after some
time after the scheme spans the whole country and gathers momentum.
Relief employment sees the Victim through the period of crisis- typically, provision of
employment for 10-15 days a month ordinarily for 3-4 months and for 6 months in the worst
of droughts suffice. The new legislation, on the other hand assures 100 days employment
during crisis. With regard to the working of the Maharashtra Employment Guarantee Scheme
which has operated for close to-three decades, it can be assumed that once the REG stabilizes
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
54
a certain pattern of "predictable demand" will emerge for each District or other
administrative unit during `peace time'. Such averages will escalate during period of crisis
and distress, notably serious droughts. During such phases there will be added pressure on
the REG funds and it stands to logic that if REG receives more work-seekers on account of
drought related distress, relief funds must be deployed to meet such additional ties. It can be
argued that as the norms of relief employment differ considerably from the REG in that it
seeks to provide work for periods much less than the guaranteedl00 days, it should be a
`stand-alone' arrangement during periods of calamity related distress. It must be admitted that
till the late 1990s this approach was indeed adopted in Maharashtra where relief works were
kept apart from EGS work particularly during the severe drought of 1987. It is only in the
recent years that the EGS funds have been supplemented by subventions from the CRF and
the NCCF to off-set the additional costs.
From an objective stand-point there are negative aspects in both the scenarios; `loading' relief
works on the REG tends to encourage the beneficiary to go in for 100 days' employment
when exigencies of a typical drought can be met by a much shorter span of livelihood support ;
on the contrary, a few years down the line when REG is fully operational, ad hoc
arrangements to cobble together relief works will be a Herculean task and will often because
of much friction on executive and judicial fronts.
2.6.8 Livelihood Management in 'Extremely Drought Prone Areas'
Areas suffering repeated droughts over the millennia have highly degraded land resources
such areas are found in pockets in many parts of the country and the subsistence agriculture
in such areas fall an easy prey to even a modest drought. Human populations in many such
degraded spots have adapted their life-styles to deal with the vagaries of nature through a
predominantly pastoral mode of existence. There are a number of studies which show that
such well-adapted populations have developed greater resilience and coping capabilities.
There are, however, areas where deep attachment to agriculture tends to dissuade frequently
drought affected communities from looking for a more ecologically compatible livelihood.
Programmes like the DDP have contributed significantly to promoting alternative, more
sustainable non-agricultural livelihoods. The issue of concretizing a strategy of facilitating
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
55
pursuing of livelihoods appropriate to an ecosystem is beyond the remit of the Commission,
there are, however, some aspects, which need to be addressed urgently to mitigate frequent
crises which result from unsustainable agriculture. These are:
a) A multi-disciplinary team needs to be immediately constituted by the Ministry of
Environment and Forests to specifically identify villages where drought related
degradation of landmakes`conventional agriculture' incompatible with sustainable
development.
b) "Land" being a subject assigned to the States, the relevant Governments must decide
whether introduction of suitable incentives will be sufficient to achieve the goal of
sustainable development or whether, in the interest of the communities concerned,
exercise of legislative power would be necessary to ensure .an ecologically appropriate
livelihood regimen.
c) Areas not amenable to conventional agriculture, lend themselves very well to cultivation
of fodder-grasses. Considering the overall fodder deficit in the country, it is unfortunate
that adequate policy initiatives have not been taken to encourage fodder cultivation. An
indicative scheme for cultivation of suitable fodder crops need to be also drawn up by
the ICAR and funded through the DDP.
d) Villages identified as at (i) above, where it is decided to restrict practice of agriculture
may qualify for special `livelihood support' under the DDP for a specified time. This
will serve as a safety net to enable the local communities to adapt to major changes in
their relations with land.
2.6.9 Revisiting Long Term Interventions
There is strong circumstantial evidence, however, that many schemes like DPAP, DDP and
many of the Watershed Development Programmes have not lived up to their full or promised
potential. Thus an analysis of Districts where drought was declared between 2000 and 2004
reveals that as many as 136 Districts with DPAP Blocks and 36 Districts with DDP Blocks
found mention in one or more drought. declaration during the period. Even assuming that all
the declarations may not pass muster on strict, technical grounds, it is clear that these figures
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
56
strongly suggest that long term measures did not yield optimal results at least in these
Districts. 2.15
Similarly, while the net irrigated area which was 20.85 million hectares in 1950-51 rose to
53.07 million hectares in 2002-03 representing an increase of more than 150%, the
corresponding decline in areas vulnerable to repeated droughts has been no more than 20%.
A major constraint in developing this theme "further is absence of an over-all Impact
Evaluation of these enterprises. So far only specific projects have been assessed and positive
`local' findings like improvement in vegetative cover, and water table and improved
productivity etc. have been arrived at such local levels. There has been no assessment, for
instance, of DPAP making any difference to frequency and intensity of droughts. Similarly,
no study of "drought proofing" actually achieved, by extension of irrigation coverage in the
peninsular region is as yet available; even more important, the impact of use of Ground-water
for irrigation on increasing frequency of droughts in certain areas has also not so far been
systematically looked into. The point that emerges, therefore, is that much work remains to
be done to ascertain the reasons why droughts continue to occur even in areas where
irrigation has been introduced or other major ameliorative interventions have taken place.2.21
Another aspect which needs to be seriously studied is the long-term impact of water
harvesting on the local ecosystems as such measures, though of great immediate utility, alter
to some extent the natural `pathways' of water flow; changes in such pathways and their
possible impact on acute droughts deserve to be studied in detail unfettered by presumptions
and conjectures
A long-term impediment in understanding the causes (and remedies) for occurrence of
droughts is the absence of integrated expertise in water. There are institutions of excellence
in Hydrology, concerning scientific and engineering aspects of water and those concerned
with ground-water and water requirements of crops etc. Availability of integrated expertise
on water under one roof and utilization of talent from Social Sciences to understand socio-
economic factors that influence water resource management is a keenly felt need. It is only
with the availability of a multi-disciplinary platform that "Droughts" could be contextualized
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
57
in their entity, and strategies of preparing societies to sustainable use of water and live within
the inherent constraints of their habitats, can be evolved. These aspects need to be considered
carefully and setting 'up an institution devoted to "water" in its multi-disciplined totality
needs to be seriously explored.
2.7 Technology – an Enabler
Role of technology in disaster management lies in its criticality to produce as well as
disseminate the information – on real/near real time basis. Earth Observation (EO) satellites
are used for observing the disaster related phenomena, their impacts and associated
vulnerability; the observation provides appropriate information and information is converted
to knowledge through comprehensive value addition. After value addition, user-friendly EO
based knowledge products trigger decision-making processes for the action on the ground by
the stakeholders at the various levels. It is important to recognize that space enabled
knowledge inputs are scientific; help in resolving the complex issues pertaining to the
people’s vulnerability; address information needs covering all the phases of disaster
management (Fig 2.1). Science & Technology driven knowledge-based information
infrastructure is required to provide balanced support to each phase of these activities in the
Disaster Management cycle.
In the recent years, the focus of disaster management community is increasingly moving on
to the more effective utilizations of the technologies, including remote sensing, Geographic
Information Systems (GIS), and satellite communications enabling communities at risk to
prepare for, and to mitigate the potential damages likely to be caused due to the natural
disasters. Role of space technology, in terms of information gathering and their real time
dissemination leading to effective risk reduction at the national and local level, could be
visualized in terms of early warning, risk information, impact/damage assessment,
preparedness and communication sub-systems.
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
58
Use of high-end technology plays an important role in disaster management. India has well
established space systems, which are used strategically in case of disaster management.
Investments in building space assets do help in reducing the losses due to natural disasters.
Indian Space Research Organisation (ISRO), Department of Space, Govt. of India has built
unique constellation of Satellites to support Communication/Broadcasting, Meteorology and
Remote Sensing. Geo-stationary meteorological satellites, INSAT and METSAT have
distinct advantages with their capability to image on a continuous basis, which is essential for
tracking cyclones and deriving atmospheric wind vectors over large oceanic areas. Indian
Remote Sensing Satellite (IRS) constellation of satellites captures disaster events and has
been helpful providing valuable data for risk management related applications. Aerial
systems with laser terrain mapper and Synthetic Aperture Radar (SAR) do fill the
observational gaps. Thus, multitier space infrastructure with INSAT, IRS and Aerial
platforms forms combination for disaster management. 2.24,2.25,2.26
Fig 2.1 Space technology enabled knowledge products towards disaster management
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
59
INSAT Data Relay Transponder (DRT) has capability to collect data from platforms located
in remote, not easily accessible areas and over the oceans. Space enabled ground systems like
Automated Weather Station (AWS), Cyclone Warning and Dissemination System (CWDS)
and Doppler Weather Radar (DWR) are also augmented to dandify the observational
networks.
To deliver the services emanating from space applications for supporting disaster
management, ISRO has set up the Decision Support Centre (DSC) at National Remote
Sensing Centre (NRSC), Hyderabad, as a single window service provider. The related
centres/ units of ISRO, have been positioned to work in synergy; so that the DSC, with the
required institutional back-up will efficiently generate and deliver the variety of services to
meet the needs of the disaster management functionaries of knowledge institutions [IMD,
Central Water Commission (CWC), Geological Survey of India (GSI), Ministry of Earth
Sciences (MoES), Department of Ocean Development (DOD), Dept. of Science and
Technology (DST) and Forest Survey of India (FSI)] andend users [Ministry of Home
Affairs (MHA), National Disaster Management Authority (NDMA), Ministry of Agriculture
(MoA) for drought, PMO, CabSectt (Cabinet Secretary), Crisis Management Group (CMG)
and State Agencies].
Further, the DSC has already been linked through satellite based secure Virtual Private
Network (VPN) to the National Emergency Operations Centre (NEOC) at MHA and PMO
(Fig 2.2).
2.7.1 Disaster Risk Management and Space
The different activities associated with disaster management can be broadly divided into
three phases, viz., pre-disaster planning, disaster response, and post disaster recovery and
management (Table 2.1).
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
60
Table 2.1: Main Phases of Disaster management
Phase of Disaster
management
Main Elements
Disaster Preparedness � Hazard mapping
� Vulnerability assessment
� Forecasting of events (intensity, impact potential}
Disaster Response � Warning of affected areas
� Evacuation of the affected to safer locations
� Rapid assessment of impact
� Detailed evaluation of damage
Recovery � Evaluation of needs of the affected
� Prioritization of reconstruction activities and
implementation
Satellite, Aerial & Ground
SystemsMet/ Ocean
ObservationsEmergencycommunication
High-Res. Imaging
Laser
Terrain Mapper
All weather mappingReal TimeMapping LEO
AerialGround basedAWS DWR
Geo.
Products & Services –
Damage Assessment,
Monitoring, .. NDEM, Hazard Zonation, Risk
Assessment, …
Networking, Early Warning
[CWDS, IOTWS, INFRAS, ..]
MHA, NDMA, MoA, PMO,
CabSectt [CMG], State
Agencies
Decision
Support Centre
(DSC)
CWC, IMD, GSI, MOES/
DOD, DST, FSI, ..
Delivery Mechanisms
Emergency Communication Network - VPN;
Support - MSS Type-D, WLL VSAT, …
Technology Development & Research - ASAR,
Forecasting/ Simulation Models, ..
Disaster Management Support (DMS) System
Fig 2.2: Indian Space Systems for Disaster Management
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
61
The role of space technology, in terms of information gathering, creation of value added
products/services and real time dissemination of information, leading to effective risk
reduction at the national and local levels, could be visualized in terms of early warning, risk
information, impact/ damage assessment, preparedness and communication sub-
systems.Thevalue added information/data provided by space systemshelps in decision
making and initiating required action on ground during all the phases of risk management
cycle.2.27,2.28
2.7.2 Use of Space Applications for managing Cyclone
The intense tropical storms are known in different part of the world by different names. In
the Pacific Ocean, they are called 'typhoons', in the Indian ocean they are called 'cyclones'
and over North Atlantic, they are called 'hurricane'. Among various natural calamities,
tropical cyclones are known to claim a higher share of deaths and destruction world over.
Records show that about 80 tropical cyclones form over the globe every year. India has a vast
coast line which is frequently affected by tropical cyclones causing heavy loss of human lives
and property. Cyclones occur usually between April and May (called pre-monsoon cyclonic
storms) and between October and December (called post-monsoon cyclonic storms). While
cyclonic storms can't be prevented, the loss of lives and damage to the properties can be
mitigated if prompt action is taken after receiving timely warnings.2.29
2.7.3 Cyclone Warning
Meteorologists have been using satellite images for monitoring storms for about thirty years.
One of the most important applications in this endeavor is to determine the strength and
intensity of a storm. In the late 1960's, meteorologists began observing tropical cyclones at
more frequent intervals. The infrared sensors aboard polar orbiting satellites began providing
day-and-night observations while geo-stationary satellite provided the continuous coverage
during daytime. There exists a very efficient cyclone warning system in India, which is
comparable to the best known in the world. The approach essentially involves the prediction
of the track and intensity of the cyclone using conventional as well as satellite and radar-
based techniques. 2.30,2.31
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
62
2.7.4 Cyclone Management - Orissa Super Cyclone
The most striking advantage of the earth observation satellite data has been demonstrated
during Orissa super-cyclone event. A severe cyclonic storm with a wind speed about 260
kmph hit the Orissa coast at Paradip on 29-oct-99 causing extensive damage to human life,
property, livestock and public utilities. The National Remote Sensing Centre acted promptly
and provided spatial extent of inundated areas using pre-cyclone IRS LISS-III data collected
on 11th
October, 1999 and Radarsat Synthetic Aperture Radar(SAR) data of 2nd
November,
1999 since cloud -free optical sensor data over the cyclone-hit area were not available. The
map showing inundated area as on 2nd
Nov, 1999 was draped over topographical map, and
was delivered to the Orissa Government on 3rd
Nov, 1999. Information, thus generated, was
effectively used by various departments of Orissa Government involved in relief operations.
Subsequently, the recession of inundated areas was also studied using Radarsat and IRS data
of 5th
, 8th
, 11th
, 13th
and 14th
November 1999. An estimated 3.75 lakh ha in Jagatsinghpur,
Kendrapara, Bhadrak, Balasore, Jajpur, besides Cuttack, Khurda and Puri districts had been
found to be inundated. In addition, the crop damage assessment was also made and maps
along with block-wise statistics derived using pre-and post-cyclone images. 2.32
2.7.5 Tsunami Response
Immediately after 2004 Indian Ocean Tsunami which caused massive devastations, space
infrastructure was put to use while responding this major disaster. 1 VSAT Terminal, 10
INMARSAT telephones and 4 INSAT Mobile Satellite Phones were airlifted to Port Blair;
and the telecommunications link between the Andaman & Nicobar Islands and the mainland
was augmented. The VSAT based video conferencing facilities, set up in the Islands earlier
were used for videoconferencing between the Islands for uniting the scattered families and
coordinating relief operations. The telemedicine facilities set up earlier at 3 Hospitals in the
Andaman & Nicobar Islands were also put to extensive use.
Simultaneously, survey of the tsunami-affected areas of the country was carried out using
data from both Indian Remote Sensing (IRS) satellites and aerial surveys conducted
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
63
specifically using NRSC’s aircraft. This survey data was used in damage assessment, and
subsequently planning rehabilitation.
Government has since decided to set up a National Centre for Tsunami Warning and Storm
Surge Modeling. The Space Department is going to provide satellite connectivity to network
the Seismic Stations, Ocean Data Buoys measuring tidal variations; and the Data Buoys of
the DART system. Also, Space Department carried out aerial surveys, and provide spatial
data on Coastal Inundation and Storm Surge Modeling.2.33
2.7.6 Gujarat Earthquake: Reconstruction of Bhuj
Following the devastating earthquake in Kachchh, ISRO/DOS as desired by the Prime
Minister’s Office, New Delhi and also based on the request from the Government of Gujarat,
has taken up the responsibility for preparing land and water resources development plans for
the entire Kachchh district in a time-bound manner.
The project provided action plans to the Government of Gujarat for rebuilding of Bhuj with
cadastral level information with GIS queries; development planning for Kachchh region on
watershed basis on 1:25,000 scale; Seismotectonic studies of Kachchh/Gujarat and
rehabilitation sites for Bhuj earthquake affected villages.
The study area is covered by ~ 150 Survey of India topographic maps of 1:25, 000 scale.
Using satellite data land use map, ground water prospect map and soil maps have been
prepared. These maps were integrated to generate land and water resources action plans.
Digital database for the thematic maps and action plan maps have been created. Thematic
maps (~ 150) like land use, soil, hydro-geomorphology, drainage and watershed, transport
and settlement and action plan maps have been prepared and submitted to the Gujarat Govt.
in support of rebuilding Bhuj.2.29
2.7.7 GlacierLand Slides – The PereechuLake
The PereechuLake in the Tibet region (across the Indian border – 35 km away from India
boarder in inaccessible terrain of China, formed during end-July 2004 due to blockade by
Chapter-2: Disaster Management by Govt.Agencies – Selected Case Studies
64
landslide) was regularly monitored till end-June 2005, when the blockade was seen to have
breached (Fig 2.3). The information was provided to MHA and CWC, all through the life of
the lake, in a timely manner, so that adequate precaution to prevent loss to lives and property
downstream in Himachal Pradesh could be taken by the concerned.
Within 12 hours after receiving the alert, the newly formed lake on Pareechu river was
identified and information on its geographical location, lake dimensions and water spread
were computed and furnished to Ministry of Home Affairs. At the request of Cabinet
Secretary, monitored the lake on daily basis during Aug/Sept 04 and information was
provided on day-to-day basis. Monitoring of PareechuLake was continued from its frozen
state. During last week of June 2005, heavy discharges were reported in SutlejRiver in
Himachal Pradesh. IRS-P6 data of 27 June 2005 was analysed and observed that the
blockade was breached and free flow of water from the lake was noticed. 2.34
Lake
Observations:• No significant change in the water spread area as compared to
14th & 16th August 2004• The blockade is seen clearly
• Flow of water downstream of the blockade is also seen clearly
Water spread Area: 193 ha[including downstream and upstream reaches]
Lake Length [E-W]: Total 5.0 km
Upstream reach: 2.6 km
Lake proper: 1.9 km
Downstream reach: 0.5 km
Lake Width [N-S]: 1.1 kmAvg. upstream width:
0.16 km
Part of Sutlej BasinSatellite Image of 17th August 2004 showing the Lake
Downstream
water flow
Fig 2.3