Date post: | 28-Dec-2015 |
Category: |
Documents |
Upload: | myron-french |
View: | 215 times |
Download: | 0 times |
Chapter 20
Process Costing andProcess Costing andActivity-Based CostingActivity-Based Costing
© 2009 The McGraw-Hill Companies, Inc.
McGraw-Hill/Irwin Slide 2
Job Order versus Process Costing
Job Order Costing Process Costing
Type of Product
Unique Products and services such as a customer built ship
Homogeneous products and services such as cans of soda
Manufacturing Approach
Customized to meet the needs of the customer or client
Mass produced in a series of standardized processes
Cost Accumulation
Costs Accumulated by jobs or by customer
Costs accumulated by process
Major cost report
Job cost sheet for each unique unit, customer, or job
Production report for each major production process
Job Order Costing Process Costing
Type of Product
Unique Products and services such as a customer built ship
Homogeneous products and services such as cans of soda
Manufacturing Approach
Customized to meet the needs of the customer or client
Mass produced in a series of standardized processes
Cost Accumulation
Costs Accumulated by jobs or by customer
Costs accumulated by process
Major cost report
Job cost sheet for each unique unit, customer, or job
Production report for each major production process
McGraw-Hill/Irwin Slide 3
ProductionReport
The Process Costing Production Report
Step 4: Reconcilethe total cost ofwork in process.
Step 2: Translate thephysical units intoequivalent units.
Step 1: Reconcile thenumber of physical
units worked onduring the period.
Step 3: Calculatethe cost per
equivalent unit.
McGraw-Hill/Irwin Slide 4
Beginning Barrels in Process 200 Barrels Started 1,800 Total Barrels to Account For 2,000
Barrels Completed ?Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Beginning Barrels in Process 200 Barrels Started 1,800 Total Barrels to Account For 2,000
Barrels Completed ?Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Beginning Barrels in Process 200 Barrels Started 1,800 Total Barrels to Account For 2,000
Barrels Completed 1,600 Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Beginning Barrels in Process 200 Barrels Started 1,800 Total Barrels to Account For 2,000
Barrels Completed 1,600 Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Step 1: Reconcile the Physical Units
Barrels Completed = 2,000 ‒ 400 = 1,600
McGraw-Hill/Irwin Slide 5
Beginning Barrels in Process 200 Barrels Started and Completed ?Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Beginning Barrels in Process 200 Barrels Started and Completed ?Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Barrels Started and Completed = 2,000 ‒ 200 ‒ 400 = 1,400
ORBarrels Startedand Completed
=Barrels
CompletedBeginning
Barrels ‒ = 1,600 – 200 = 1,400
ORBarrels Startedand Completed
=Barrels Started
EndingBarrels
‒ = 1,800 – 400 = 1,400
Step 1: Reconcile the Physical Units
Beginning Barrels in Process 200 Barrels Started and Completed 1,400 Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
Beginning Barrels in Process 200 Barrels Started and Completed 1,400 Ending Barrels in Process 400 Total Barrels Accounted For 2,000
Mondavi CFA Process Physical Flow
McGraw-Hill/Irwin Slide 6
Equivalent units are the product of the number of partially completed units times the percentage of
completion for those units.
We need to calculate equivalent units because a process usually has some partially completed units
in its beginning and ending inventory.
Step 2: Translate Physical Units into Equivalent Units
+ = 1
Two half completed units are equivalent to one completed unit, so 10,000 units 70% complete
are equivalent to 7,000 complete units.
Two half completed units are equivalent to one completed unit, so 10,000 units 70% complete
are equivalent to 7,000 complete units.
McGraw-Hill/Irwin Slide 7
Exh. 20-21
Step 2: Translate Physical Units into Equivalent Units
• Direct materials are added at the beginning of the process, so, once a unit is started, it will have 100% of the required direct materials. • Conversion costs are incurred uniformly in the process. The 200 units in beginning inventory were 70% of the way through the process, and the 400 units in ending inventory were 60% of the way through the process. • The 1,400 units that were started and completed during the period are 100% complete for material and conversion.
McGraw-Hill/Irwin Slide 8
Exh. 20-22
Step 2: Translate Physical Units into Equivalent Units
1,400 units × 100% = 1,400200 units × (100% ‒ 70%) = 60
400 units × 60% = 240
McGraw-Hill/Irwin Slide 9
Step 3: Calculate Cost per Equivalent UnitCost per
EquivalentUnit
Current Period CostsEquivalent Units=
McGraw-Hill/Irwin Slide 10
Step 4: Reconcile the Total Cost of Work in Process
Materials Conversion TotalEquivalent units in Ending Inventory 400 240 Cost per Equivalent Unit × 450$ × 540$ Cost of Ending Inventory = 180,000$ = 129,600$ 309,600$
Mondavi CFA ProcessCost of Ending Inventory
McGraw-Hill/Irwin Slide 11
Step 4: Reconcile the Total Cost of Work in Process
Materials Conversion Total
Beginning Inventory Cost (From Prior Period) 165,600$ Cost to Complete Beginning Inventory: Equivalent Units to Complete - 60 Cost per equivalent unit × 540$ Cost to Complete Beginning Inventory -$ = 32,400$ 32,400$ Cost of Units Started and Completed: Units Started and Completed 1,400 1,400 Cost per Equivalent Unit × 450$ × 540$ Cost of Units Started and Completed = 630,000$ = 756,000$ 1,386,000$ Cost of Goods Completed 1,584,000$
Mondavi CFA ProcessCost of Goods Completed
McGraw-Hill/Irwin Slide 12
Activity Based Costing
Four BasicSteps in ABC
Step 4: Assign coststo products or
services based ontheir activity demands.
Step 2: Form activitypools and assignindirect costs to
each pool.
Step 1: Identify andclassify activities
Step 3: Select a costdriver for each pool
and calculatethe activity rate.
McGraw-Hill/Irwin Slide 13
Step 1. Identify and Classify ActivitiesLevel Activities Sample Activities Facility Performed for the company to Installing and maintaining
level support all customers and equipment. Paying forproducts/services. insurance, utilities, and taxes.
Customer Performed for specific Designing a special customerlevel customers. label. Negotiating prices for a
large customer.
Product Performed to support individual Research and development forlevel product lines. a new wine. Special tools
used only for certain wines.
Batch Performed for a group of units Aging wine in barrels or vats.level or customers all at once. Quality-testing each barrel
or vat.
Unit Performed for each unit or Pouring wine into bottles.level customer (one at a time). Labeling bottles and inserting
corks.
Level Activities Sample Activities Facility Performed for the company to Installing and maintaining
level support all customers and equipment. Paying forproducts/services. insurance, utilities, and taxes.
Customer Performed for specific Designing a special customerlevel customers. label. Negotiating prices for a
large customer.
Product Performed to support individual Research and development forlevel product lines. a new wine. Special tools
used only for certain wines.
Batch Performed for a group of units Aging wine in barrels or vats.level or customers all at once. Quality-testing each barrel
or vat.
Unit Performed for each unit or Pouring wine into bottles.level customer (one at a time). Labeling bottles and inserting
corks.
McGraw-Hill/Irwin Slide 14
Step 2: Form Activity Pools and Assign Indirect Costs to Each Pool
$90,000$90,000Purchasing/Purchasing/Receiving/Receiving/CrushingCrushing
$300,000$300,000Setting up andSetting up and
MaintainingMaintaining Equipment Equipment
$216,000$216,000Fermenting/Fermenting/
Aging inAging inBarrelsBarrels
$99,000$99,000Bottling/Bottling/LabelingLabeling
$175,000$175,000QualityQualityControlControl
$880,000 of Manufacturing Overhead Costs$880,000 of Manufacturing Overhead Costs
Mondavi has a total of $880,000 in manufacturing overheadcost that can be divided among five activity cost pools.
McGraw-Hill/Irwin Slide 15
Activity Cost Pools
Total Indirect
CostPurchasing 90,000$ ÷ 450,000 Pounds = 0.20$ per poundMachine setups 300,000 ÷ 500 Setups = 600.00 per setupFermenting 216,000 ÷ 270,000 Days = 0.80 per dayQuality Control 175,000 ÷ 10,000 Inspectons = 17.50 per insp.Bottling 99,000 ÷ 330,000 Bottles = 0.30 per bottle
880,000$
Activity RateActivity Cost Driver
Step 3: Select an Activity Cost Driver for Each Pool and Calculate an Activity Rate
Activity Cost Pools Activity Cost Driver Activity MeasurePurchasing/Receiving/Crushing Pounds of Grapes 450,000 PoundsSetting up and Maintaining Equipment Setups 500 SetupsFermenting/Aging in Barrels Fermentation/Aging Days 270,000 DaysQuality Control Quality Inspectons 10,000 InspectionsBottling/Labeling Bottles Processed 330,000 bottles
McGraw-Hill/Irwin Slide 16
Step 4: Assign costs to Products or Services Based on Activity Demands
Activity Requirements Standard Chardonnay Vintage CabernetPounds of Grapes 1250 Pounds per Batch 375 Pounds per BatchNumber of Setups 1 Setup per Batch 1 Setup per BatchFermentation/Aging Days 150 Days per Batch 900 Days per BatchQuality Inspections 10 per Batch 90 per BatchNumber of Bottles 1,000 Bottles per Batch 150 Bottles per Batch
Mondavi produces two types of wine, Standard Chardonnay and Vintage Cabernet with the following Activity requirements.
McGraw-Hill/Irwin Slide 17
Step 4: Assign costs to Products or Services Based on Activity DemandsCost Pools ABC Cost
Purchasing 0.20$ per pound × 1,250 Pounds = 250$ Machine setups 600.00 per setup × 1 Setups = 600 Fermenting 0.80 per day × 150 Days = 120 Quality Control 17.50 per insp. × 10 Inspectons= 175 Bottling 0.30 per bottle × 1,000 Bottles = 300
Manufacturing Overhead Cost Per Batch 1,445$ Number of Bottles per Batch ÷ 1,000 Manufacturing Overhead Cost Per Bottle = 1.45$
ActivityActivity Rate
Cost Pools ABC CostPurchasing 0.20$ per pound × 375 Pounds = 75$ Machine setups 600.00 per setup × 1 Setups = 600 Fermenting 0.80 per day × 900 Days = 720 Quality Control 17.50 per insp. × 90 Inspectons= 1,575 Bottling 0.30 per bottle × 150 Bottles = 45
Manufacturing Overhead Cost Per Batch 3,015$ Number of Bottles per Batch ÷ 150 Manufacturing Overhead Cost Per Bottle = 20.10$
ActivityActivity Rate
Cha
rdon
nay
Cab
erne
t
End of Chapter 20
© 2009 The McGraw-Hill Companies, Inc.