of 26
8/2/2019 Chapter 3 Project Life Cycle
1/26
PROJECT LIFE CYCLE
1
8/2/2019 Chapter 3 Project Life Cycle
2/26
Projects also follow a progression of phases from
beginning to end called theproject life cycle.
The project life cycle consists of four phases as shown inFigure.1
2
PROJECT LIFE CYCLE
Figure.1
8/2/2019 Chapter 3 Project Life Cycle
3/26
"The first phase of a project is the initiation phase.
During this phase , a business problem or opportunity is
identified and a business case providing various solution
options is defined.
Next, a feasibility study is conducted to investigate whether
each option addresses the business problem and a finalrecommended solution is then put forward.
Once the recommended solution is approved, a project is
initiated to deliver the approved solution. Terms of reference
are completed outlining the objectives, scope and structureof the new project, and a project manager is appointed.
The project manager begins recruiting a project team and
establishes a project office environment. Approval is then
sought to move into the detailed planning phase. 3
Project Initiation
8/2/2019 Chapter 3 Project Life Cycle
4/26
"Within the initiation phase, the business problem or
opportunity is identified, a solution is defined, a project is
formed and a project team is appointed to build and deliverthe solution to the customer.
Figure shows the activities undertaken during the initiation
phase:
4
Project Initiation
8/2/2019 Chapter 3 Project Life Cycle
5/26
5
Develop a business case:
The trigger to initiating a project is identifying a business
problem or opportunity to be addressed.
A business case is created to define the problem or opportunity
in detail and identify a preferred solution for implementation.
8/2/2019 Chapter 3 Project Life Cycle
6/26
6
Develop a business case:
The business case includes:
A detailed description of the problem or opportunity;
A list of the alternative solutions available;
An analysis of the business benefits, costs, risks and issues;
A description of the preferred solution;
A summarized plan for implementation.
8/2/2019 Chapter 3 Project Life Cycle
7/26
7
Establish the terms of reference:
After the business case and feasibility study have been
approved, a new project is formed.
At this point, terms of reference are created. The terms of
reference define the vision, objectives, scope anddeliverables for the new project.
They also describe the organization structure; and activities,
resources and funding required to undertake the project. Any
risks, issues, planning assumptions and constraints are also
identified.
8/2/2019 Chapter 3 Project Life Cycle
8/26
8/2/2019 Chapter 3 Project Life Cycle
9/26
9
Set up a project office:
The project office is the physical environment within which
the team is based.
Although it is usual to have one central project office, it is
possible to have a virtual project office with project team
members located around the world.
8/2/2019 Chapter 3 Project Life Cycle
10/26
10
Set up a project office:
A project office environment should include:
Equipment, such as office furniture, computer equipment,
stationery and materials;
Communications infrastructure, such as telephones,computer network, e mail, Internet access, file storage,
database storage and backup facilities;
Documentation, such as a project methodology, standards,
processes, forms and registers;
Tools, such as accounting, project planning and risk
modeling software.
8/2/2019 Chapter 3 Project Life Cycle
11/26
11
Perform a phase review:
At the end of the initiation phase, perform a phase review.
This is basically a checkpoint to ensure that the project has
achieved its objectives as planned.
8/2/2019 Chapter 3 Project Life Cycle
12/26
12
Project Planning
"Once the scope of the project has been defined in the terms
of reference, the project enters the planning phase.
This involves creating a:
Project plan outlining the activities, tasks, dependencies and
timeframes;
Resource plan listing the labour, equipment and materials
required;
Financial plan identifying the labour, equipment and
materials costs; Quality plan providing quality targets, assurance and
control measures;
Risk plan highlighting potential risks and actions to be
taken to mitigate those risks;
8/2/2019 Chapter 3 Project Life Cycle
13/26
13
Project Planning
Acceptance plan listing the criteria to be met to gain
customer acceptance;
Communications plan describing the information needed to
inform stakeholders;
Procurement plan identifying products to be sourced fromexternal suppliers.
8/2/2019 Chapter 3 Project Life Cycle
14/26
14
Create a project plan:
The first step in the project planning phase is to document
the project plan.
A 'work breakdown structure' (WBS) is identified which
includes a hierarchical set of phases, activities and tasks to
be undertaken to complete the project.
After the WBS has been agreed, an assessment of the levelof effort required to undertake each activity and task is
made.
The activities and tasks are then sequenced, resources are
allocated and a detailed project schedule is formed.
This project plan is the key tool used by the project manager
to assess the progress of the project throughout the project
life cycle.
8/2/2019 Chapter 3 Project Life Cycle
15/26
15
Create a resource plan:
Immediately after the project plan is formed, the level of
resource required to undertake each of the activities andtasks listed within the project plan will need to be allocated.
Although generic resource may have already been allocated
in the project plan, a detailed resource plan is required to
identify the:
Type of resource required, such as labor, equipment and
materials;
Quantity of each type of resource required;
Roles, responsibilities and skill sets of all human resource
required;
Specifications of all equipment resource required;
Items and quantities of material resource required.
8/2/2019 Chapter 3 Project Life Cycle
16/26
16
Create a financial plan :
A financial plan is created to identify the total quantity of
money required to undertake each phase in the project (inother words, the budget).
The total cost of labour, equipment and materials is
calculated and an expense schedule is defined which
enables the project manager to measure the forecast spendversus the actual spend throughout the project.
Detailed financial planning is an extremely important
activity within the project, as the customer will expect thefinal solution to have been delivered within the allocated
budget.
8/2/2019 Chapter 3 Project Life Cycle
17/26
17
Create a quality plan :
Meeting the quality expectations of the customer can be a
challenging task.
To ensure that the quality expectations are clearly defined
and can reasonably be achieved, a quality plan is
documented.
The quality plan:
Defines the term 'quality' for the project.
Lists clear and unambiguous quality targets for eachdeliverable. Each quality target provides a set of criteria and
standards to be achieved to meet the expectations of the
customer.
Provides a plan of activities to assure the customer that thequality targets will be met (in other words, a quality
assurance plan).
Identifies the techniques used to control the actual quality
level of each deliverable as it is built (in other words, a
quality control plan).
C
8/2/2019 Chapter 3 Project Life Cycle
18/26
18
Create a risk plan :
The next step is to document all foreseeable project risks
within a risk plan.
This plan also identifies the actions required to prevent each
risk from occurring, as well as reduce the impact of the risk
should it eventuate.
Developing a clear risk plan is an important activity withinthe planning phase, as it is necessary to mitigate all critical
project risks prior to entering the execution phase of the
project.
C l
8/2/2019 Chapter 3 Project Life Cycle
19/26
19
Create an acceptance plan:To deliver the project successfully, you will need to gain
full acceptance from the customer that the deliverables
produced by the project meet or exceed requirements.
An acceptance plan is created to help achieve this, by
clarifying the completion criteria for each deliverable
and providing a schedule of acceptance reviews.
Create a communications plan:Prior to the execution phase, it is also necessary to identify
how each of the stakeholders will be kept informed of the
progress of the project.The communications plan identifies the types of
information to be distributed to stakeholders, the methods of
distributing the information, the frequency of distribution,
and responsibilities of each person in the project team for
distributing the information.
C l
8/2/2019 Chapter 3 Project Life Cycle
20/26
20
Create a procurement plan:The last planning activity within the planning phase is to
identify the elements of the project to be acquired from
external suppliers.
The procurement plan provides a detailed description of the
products (that is, goods and services) to be acquired from
suppliers, the justification for acquiring each product
externally as opposed to from within the business, and the
schedule for product delivery.It also describes the process for the selection of a preferred
supplier (the tender process), and the ordering and delivery
of the products (the procurement process).
Contract the suppliers: Although externalsuppliers may be appointed at any stage of the project, it is
usual to appoint suppliers after the project plans have been
documented but prior to the execution phase of the project
P j t E ti
8/2/2019 Chapter 3 Project Life Cycle
21/26
21
Project Execution
"This phase involves implementing the plans created during
the project planning phase. While each plan is beingexecuted, a series of management processes are undertaken
to monitor and control the deliverables being output by the
project.
This includes identifying change, risks and issues,reviewing deliverable quality and measuring each
deliverable produced against the acceptance criteria. Once
all of the deliverables have been produced and the customer
has accepted the final solution, the project is ready forclosure. The activities of this phase are shown in Figure
P j t Cl
8/2/2019 Chapter 3 Project Life Cycle
22/26
22
Project Closure
"Project closure involves releasing the final deliverables to
the customer, handing over project documentation to the
business, terminating supplier contracts, releasing project
resources and communicating the closure of the project to all
stakeholders.
The last remaining step is to undertake a postimplementation review to quantify the level of project
success and identify any lessons learnt for future projects
P j t E ti
8/2/2019 Chapter 3 Project Life Cycle
23/26
23
Project Execution
Project management executionactivities
P f j t l
8/2/2019 Chapter 3 Project Life Cycle
24/26
24
Perform project closure:
"Project closure, or 'close out', essentially involves windingup the project.
This includes:
Determining whether all of the project completion criteriahave been met;
Identifying any outstanding project activities, risks or
issues;
Handing over all project deliverables and documentation tothe customer;
Cancelling supplier contracts and releasing project
resources to the business;
Communicating the closure of the project to all
stakeholders and interested parties.
R i j t l ti
8/2/2019 Chapter 3 Project Life Cycle
25/26
25
Review project completion:
" The final activity within a project is the review of itssuccess by an independent party. Success is determined by
how well it performed against the defined objectives and
conformed to the management processes outlined in theplanning phase. To determine how well it performed, the
following types of questions are answered:
Did it result in the benefits defined in the business case?
Did it achieve the objectives outlined in the terms ofreference?
Did it operate within the scope of the terms of reference? 0
Did the deliverables meet the criteria
defined in the quality plan?
Was it delivered within the schedule outlined in the project
Review project completion
8/2/2019 Chapter 3 Project Life Cycle
26/26
26
Review project completion:
To determine how well it performed, the following types of
questions are answered:
Did it result in the benefits defined in the business case?
Did it achieve the objectives outlined in the terms ofreference?
Did it operate within the scope of the terms of reference? 0
Did the deliverables meet the criteria
defined in the quality plan? Was it delivered within the schedule outlined in the project
plan?
Was it delivered within the budget outlined in the financial
plan?