Date post: | 08-Mar-2016 |
Category: |
Documents |
Upload: | fatin-nabila |
View: | 3 times |
Download: | 0 times |
of 15
A STUDY OF RAINWATER HARVESTING SYSTEM
CHAPTER 4DATA ANALYSIS AND RESULTS4.0IntroductionIn this chapter the analysis were as described in Chapter 3. This analysis was carried out to identify the most used reduce, reuse, recycle and recovery technique at construction site and the differences among reduce, reuse, recycle and recovery technique on residential projects, commercial project, industrial project and government projects. To achieve this, a study was conducted on 20 construction sites that have been randomly selected in the district of Jasin, Melaka.Data collected through the questionnaire to 30 respondents and interviews with responsible officials at the 20 construction site is selected. Interviews carried out in order to gain insight into the contractor on the rate of total construction waste and techniques that have been used.
To obtain data and information required, a questionnaire has been prepared to facilitate the respondents to cooperate in providing information related to the purpose of this study. Data and information obtained through this method and then analyzed using appropriate statistic that conclusion can be made and give the extent of recycling of construction waste materials can be carried out at a construction site. Questionnaire form is shown in Appendix B.4.1General Information Project and the RespondentGeneral information on the respondents' construction projects were displayed in Table 4.1.1. This table reflects the project's location, status of the contractor, project type and number of respondents for this study.Table 4.1.1: General information of respondentsLocation of projectJasin, Melaka
Types of sitesResidentialIndustrialCommercialGovernment
Total of sites9254
Total of forms distributed27060150120
Total of respondents23149124108
Table 4.1.2: Percentage of Respondents Number of responsesTypes of sitesTotal of respondentsPercentage of the returned (%)
No. of distributedNo. of the returned
Residential27023186
Industrial604982
Commercial15012483
Government12010890
( = 600( = 512
Figure 4.1.1: The bar chart reflects the experience of the respondents in the construction by year.4.2Identify common materials of construction waste disposed of at a construction site.
Figure 4.2.1: The bar chart shows the mean of the types of construction waste disposed of regularlyTable 4.2.1: The average index for construction waste removed5= Highest4=High3= Intermediate2=Low
1=LowestTypes of construction wasteFrequency analysisThe average indexStatus
12345
Bricks/concrete-119132255-3.23Intermediate
Timbers---1054074.79Highest
Steels/metals68308136--2.13Low
Gravel and aggregate-221187104-2.77Intermediate
Glass (un-tempered)44270---1.14Lowest
There are five common types of waste materials removed from the research literature are identified and listed in the questionnaires. There were 512 respondents to give feedback on construction waste material most often thrown at a construction site. Construction waste materials can be identified in Table 4.3. Data obtained from 20 construction sites of the point (1-5) are given based on the frequency of each type of construction waste being dumped at a construction site.Average points obtained will be used to determine the frequency of each type of construction waste being dumped at a construction site classification based on the following points:Highest
4.50 point average < 5.00
High
3.50 point average < 4.50
Intermediate 2.50 point average < 3.50
Low
1.50 point average < 2.50
Lowest
0.00 < point average < 1.50
Based on the average index value was analyzed, type of construction waste is often disposable a timber with an average index of 4.79. This decision is based on the average index value of the highest in five different types of construction waste.
While the construction waste material intermediate in disposed is a bricks/concretes and gravel and aggregate products. Two of the index recorded an average value of 3.23 and 2.77.
Next is the low frequent construction waste materials disposed of steel. The mean value for steel is 2.13, followed by the glass (un-tempered) where the average value of 1.14 recorded the lowest average value in the material being studied.4.3Reduce, reuse, recycle and recovery technique usage analysisThis data is obtained through interviews. Three officers from each of 20 selected sites were interviewed. The interview can be concluded as follows:
4.3.1Reducing of sources
NoWaste Reduction
(conceptual planning)Material
Bricks / concreteTimbersSteels/metalsGravel and aggregate productsGlass (un-tempered)
Waste minimization techniques are consider during:
1planning stage2716934
2design phase121721818
3tender and contract stage82-52
4construction phase2843443219
5procurement-1-3-
6setting up site layout1215511-
7Storage and material handling71712020
8Collection procedures4----
9site personnel job description3--12-
10the execution of waste management system1456-7
Figure 4.3.1.1: The graph above showed the reducing of sources.4.3.2Reuse technique
NoWaste Reuse
(continuous used of material)Material
Bricks / concreteTimbersSteels/metalsGravel and aggregate productsGlass (un-tempered)
Waste are being use for :
1Repeated purpose32471429100
2Backfilling5--31-
3sub base for pavement---18-
4sub base for apron slab26--13-
5Embankment37--9-
6reinforcement in the apron slab--58--
7support work-5328--
Figure 4.3.2.1: Reuse technique4.3.3Recycle technique
NoWaste Recycle
( waste to material )Material
Bricks / concreteTimbersSteels/metalsGravel and aggregate productsGlass (un-tempered)
Waste are :
1sold to recycle centre-6371-68
2use as crusher run97--74-
3produce into other material to be used again337292632
Figure 4.3.3.1: The graph above shown a recycle technique4.3.4Recovery technique
NoWaste Recover
( waste to energy)Material
Bricks / concreteTimbersSteels/metalsGravel and aggregate productsGlass (un-tempered)
Waste are sent for / to :
1Gasification (to extract carbon)
2pyrolysis(chemically process)
3power plant as a form of fuel
4biodigestion (for future fossil energy)
xiii
_1394984023.xlsChart1
251
137
124
Total of respondent
The experienceof the respondentsin the constructionby year.
Sheet1
YearsTotal of respondent
1 years - 5 years251
5 years - 10 years137
10 years - 20 years124
To resize chart data range, drag lower right corner of range.
_1394998000.xlsChart1
3250263700
470000053
1400005828
29311813900
100000000
Repeated purpose
Backfilling
Sub base for pavement
Sub base for apron
Embakment
Reinforcement in the apron slab
Support work
construction waste materials
works
Reuse technique
Sheet1
Repeated purposeBackfillingSub base for pavementSub base for apronEmbakmentReinforcement in the apron slabSupport work
Bricks/concrete3250263700
Timbers470000053
Steels/metals1400005828
Gravel and aggregates products29311813900
Glass (un-tempered)100000000
To resize chart data range, drag lower right corner of range.
_1394998261.xlsChart1
0973
63037
0029
297426
10000
Sold to recycle centre
use as crusher run
produce unto other material to be used again
construction waste materials
actions
Recycle technique
Sheet1
Sold to recycle centreuse as crusher runproduce unto other material to be used againSub base for apronEmbakmentReinforcement in the apron slabSupport work
Bricks/concrete0973263700
Timbers6303700053
Steels/metals0029005828
Gravel and aggregates products29742613900
Glass (un-tempered)100000000
To resize chart data range, drag lower right corner of range.
_1394997156.xlsChart1
21282801274314
71724311517005
1621044051006
98532311200120
34182190020007
Planning
Design
Tender and contract
Construction
Procurement
Setting up site layout
storage and material handling
collection procedures
site personnel job description
the execution of waste management system
construction waste materials
stages
Reducing of sources
Sheet1
PlanningDesignTender and contractConstructionProcurementSetting up site layoutstorage and material handlingcollection proceduressite personnel job descriptionthe execution of waste management system
Bricks/concrete21282801274314
Timbers71724311517005
Steels/metals1621044051006
Gravel and aggregates products98532311200120
Glass (un-tempered)34182190020007
To resize chart data range, drag lower right corner of range.
_1394982364.xlsChart1
1.14
2.77
2.13
4.79
3.23
Series 1
Construction waste
The average index
construction waste disposed of at a construction site.
Sheet1
Series 1
Glass (un-tempered)1.142.42
Gravel and aggregate products2.774.42
Steels/metals2.131.83
Timbers4.792.8
Bricks/concrete3.23
To resize chart data range, drag lower right corner of range.