+ All Categories
Home > Documents > Chapter - V EGS AND SGRY IN NASHIK DISTRICT - Shodhganga

Chapter - V EGS AND SGRY IN NASHIK DISTRICT - Shodhganga

Date post: 09-Feb-2022
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
111
177 177 Chapter - V EGS AND SGRY IN NASHIK DISTRICT: GRASSROOTS LEVEL IMPLEMENTATION AND PERFORMANCE IN COMPARATIVE PERSPECTIVE 5.0 Introduction: The second objective of this study was to understand the salient features of administration and implementation mechanisms of EGS and SGRY on the basis of empirical data. The third objective of this study was to empirically evaluate the performance of EGS and SGRY in a comparative perspective. This fifth chapter is designed to analyse the data in the context of both the second and the third objective of the present research. As noted in the chapter on methodology, 12 villages from Nashik district were selected as a sample and an attempt to understand the salient features of administration and implementation mechanisms of both EGS and SGRY works was made. To guide the inquiry for fulfilling both the above mentioned objectives of this research, the following questions were kept in mind: a) What are the salient features of administration and implementation mechanisms of EGS and SGRY? Which PEP is more effective in its implementation at the grassroots level? b) What are the conditions that resulted in good or bad implementation of both the PEPs at the grassroots level? c) How the implementation of the two PEPs is different in terms of the level of development in three areas in the district? This chapter is mainly based on the empirical observations, evidences and data related to implementation and performance of EGS and SGRY. The Sarpanch, Deputy Sarpanch, Gram Sevak,
Transcript

177

177

Chapter - V

EGS AND SGRY IN NASHIK DISTRICT: GRASSROOTS

LEVEL IMPLEMENTATION AND PERFORMANCE IN

COMPARATIVE PERSPECTIVE

5.0 Introduction:

The second objective of this study was to understand the

salient features of administration and implementation mechanisms

of EGS and SGRY on the basis of empirical data. The third objective

of this study was to empirically evaluate the performance of EGS

and SGRY in a comparative perspective. This fifth chapter is

designed to analyse the data in the context of both the second and

the third objective of the present research. As noted in the chapter

on methodology, 12 villages from Nashik district were selected as a

sample and an attempt to understand the salient features of

administration and implementation mechanisms of both EGS and

SGRY works was made. To guide the inquiry for fulfilling both the

above mentioned objectives of this research, the following questions

were kept in mind:

a) What are the salient features of administration and

implementation mechanisms of EGS and SGRY? Which

PEP is more effective in its implementation at the

grassroots level?

b) What are the conditions that resulted in good or bad

implementation of both the PEPs at the grassroots level?

c) How the implementation of the two PEPs is different in

terms of the level of development in three areas in the

district?

This chapter is mainly based on the empirical observations,

evidences and data related to implementation and performance of

EGS and SGRY. The Sarpanch, Deputy Sarpanch, Gram Sevak,

178

178

Talathi, Mukadam and the workers, were the six main categories of

the respondents. Informal interviews with the political leaders,

higher level implementing officers, scholars and members of civil

society organisations were also conducted to seek detailed and

comprehensive understanding of the scheme implementation and

performance.

The data collected from the six main categories of respondents

enable us to compare the 12 EGS projects and 12 SGRY projects

according to a range of variables selected to compare EGS projects

with SGRY. The inferences are drawn on the basis of the responses

gathered from these respondents.

The chapter has been divided into four sections as under:

Section One- Profiles of different categories of

respondents selected as sample

Section Two- A Comparison of Implementation of EGS

with SGRY in Nasik District

Section Three- A Comparison of Performance of EGS

with SGRY in Nasik District

Section Four- Implementation and Performance of EGS

and SGRY: A Critical Evaluation

Now, let us see the three sections one by one.

SECTION –I

5.1 Section One- Profiles of different categories of

respondents selected as samples

As noted in the chapter II the researcher selected six main

categories of respondents. Those include- EGS and SGRY workers

(85), Mukadams (24), Sarpanchs (12), Deputy Sarpanchs (12), Gram

Sevaks (12) and Talathis (12). The profile of the each these

categories of the respondents are given below:

179

179

5.1.1 Profile of the workers

The workers working on the worksites selected as a sampled

respondents were 85. 51 of them were EGS workers and 34 were

SGRY workers. The data are presented in Table 5.1 the proportion of

young workers (25 to 35) years was high (40%) by those who were in

the age group off 18 to 34 were (28.2%). Others belonging to different

age categories were less than 20% each. Number of female workers

under sample was very low (18.8%) against male workers (81.2%).

Among the sampled workers, majority of them were from ST

category (81.2%). The workers belonging to Mahadev Koli, tribal

group were highest in number in the sampled workers (41.2%).

Following this were the Koknas (28.2%) and Warli (5.9%). Nav

Baudhha workers were very low in number (3.5%). Higher caste

groups like Vanjari and Marathas were 4.7% and 1.7% respectively.

Socio-economic backwardness of the workers thus remains the major

factor that pushes them to seek work under the EGS and SGRY.

Among the tribals, the Mahadev Kolis relatively have less access to

land and that is why their number was high among the workers.

Looking at the educational background of the sample workers,

it can be seen that 32.9% of the workers were illiterate. Those

educated up to 5th and 10th standard were 22.4 and 34.1%

respectively. It was striking that about 10% of the workers were

college going youths. Helping parents during the vacations for

earning bread might have been the main cause.

The livelihood means of the workers were not very diverse.

40% of them were wage labourers and 23.5% were small farmers and

simultaneously also were wage labourers. Workers relied on

agriculture for their livelihoods were 34.1% and 2.4% and involved

were involved in part time service and part time agriculture. 35.3%

workers had no access to land at all. Those who had land were either

180

180

small land holder or dry land holder. Among the sample workers

3.6% were having some irrigated land.

More than 54% of the workers were living in nuclear type

family. The tribal workers were leading among them. Rest of the

45.9% workers hailed from joint type of family. 44.7% of the workers

had family size ranging 6 to 9 members followed by another 40%

having family size of 2 to 5 members. The average family size was

just above 5 members per family.

About 50% of the workers had two earning members in their

family. No. of families of the workers with three earning members

was 22.4% and more than three members was 23.3%.

To assess family income of the workers is rather a difficult job.

The workers were not able to tell about their earnings. I simply

asked them to calculate their earnings from different sources of the

all family members roughly. There has been the tendency among the

workers to disclose less total family earnings. More than 78% of the

workers reported that they had family average earnings less than

Rs. 30 000 a year. Workers with earnings more than Rs. 70 000/- a

year were just 1.2%.

There has been cycles and flows of migration from less

developed areas to developed areas of Nashik district. The tribal belt

of Nashik district, being less developed belt has remained the core

area of out migration. 16.5% said they only migrated when there

were conditions of droughts. More than 68% of the workers were

regular migrants to developed belts of the district. That is either

towards Nashik city for any casual unskilled works or towards

agriculturally richer zone like Niphad, Pimpalgaon Baswant. The

tribals (popularly known here as Koknis) were among the leading

migrants to other developed areas.

181

181

Table 5.1

SAMPLE WORKER’S PROFILE Sr.

No. Variable Category Frequency Percentage

1) EGS

2) SGRY

51

34

60.0

40.0

1 Scheme Name

and No. of

workers Total 85 100.0

18 to 24 Years 24 28.2

25 to 35 Years 34 40.0

36 to 45 Years 13 15.3

46 to 55 Years 8 9.4

56 to 60 Years 2 2.4

60 Plus Years 2 2.4

Below 18 Years 2 2.4

2 Age

Total 85 100.0

Male 69 81.2

Female 16 18.8

3 Sex

Total 85 100.0

Maratha 1 1.2

Vanjari 4 4.7

Dhor 1 1.2

Nav Baudhha 3 3.5

Kokana 24 28.2

Mahadev Koli 35 41.2

Warli 5 5.9

Thakar 2 2.4

Vadar 2 2.4

Bhill 2 2.4

Mang 1 1.2

Lonari 2 2.4

Dawar 2 2.4

Muslim 1 1.2

4 Caste/Tribe/

Community

Total 85 100.0

Non Reserved

Caste Category

1 1.2

SC 3 3.5

ST 69 81.2

NT/DT/VJ 7 8.2

OBC 4 4.7

Muslim Monority 1 1.2

5 Caste Category/

Religion

Total 85 100.0

Illiterate 28 32.9

Up to 5th 19 22.4

5th to 10th 29 34.1

11th to 12th 6 7.1

FY to Graduate 3 3.5

6 Education

Total 85 100.0

182

182

Service +

Agriculture

2 2.4

Agriculture 29 34.1

Agriculture +Wage

Labourer

20 23.5

Wage Labourer 34 40.0

7 Means of

Livelihood

Total 85 100.0

No land 30 35.3

Below 2 acres dry 12 14.1

2-5 dry 30 35.3

6-10 dry 4 4.7

11 and above dry 6 7.1

Below 2 Irrigated 2 2.4

Irrigated + Dry 11

acres and above

1 1.2

8 Family Land

Holding

Total 85 100.0

Joint 39 45.9

Nuclear 46 54.1

9 Family Type

Total 85 100.0

2-5 34 40.0

6-9 38 44.7

10-15 9 10.6

More than 15 4 4.7

10 Family

Members

Total 85 100.0

1 5 5.9

2 42 49.4

3 19 22.4

4 11 12.9

5 and more 8 9.4

11 Earning

members

of the family

Total 85 100.0

Less than 10 000 25 29.4

10 000 - 20 000 42 49.4

21 000- 30 000 12 14.1

31 000 - 40 000 2 2.4

41 000 - 50 000 2 2.4

More than 70 000 1 1.2

Cannot say 1 1.2

15 Yearly Family

income

Total 85 100.0

Never 13 15.3

Only in conditions

of drought

14 16.5

1 month a year 12 14.1

2-3 months in a

year

25 29.4

12 Trends of

Migration

To city

4 months in a year 12 14.1

183

183

More than 4

months in a year

3 3.5

Frequent

interaction with

city

6 7.1

Total 85 100.0

5.1.2 Profile of the Mukadams

The Mukadam is the lowest level on site manager of the

works. The data relating to the sample Mukadams are presented in

the table 5.2. From 24 worksites all 24 Mukadams were selected as a

sample. Mukadams were relatively younger in age. 62.5% of the

Mukadams belonged to 25 to 35 years age category followed by

another 20.83% of them who belonged to 36 to 45 years age category.

All of them were male. More than 54% of the Mukadams working on

EGS- SGRY sites were tribals. However as compared to the workers

the percentage of non tribal Mukadams was on higher side. 33.3% of

the Mukadams were Marathas. 20.83% of the Mukadams were

Kokana, Warli and Mahadev Koli 16.66% each and 4.2% belonged to

Nomadic Tribes. Marathas or higher caste Mukadams were 21.16%,

predominantly from the developed and semi developed areas where

as tribal Mukadams (54.16%) were dominant in less developed belt.

Mukadams were supposed to be educated enough to handle

accounts work but 62.5% of the Mukadams were illiterate. Another

25% were educated up to 5th standard and only 4.16% were educated

up to college level. Here skill and qualification was not important

but the reliability and ability to handle the human, non human

resources and especially the outsiders was considered more

important.

Mukadams had diverse livelihood avenues. 25% of them were

government serviceman or lowest agency men and another 25% were

wage labourers. 20.8% of the Mukadams were contractors

184

184

themselves and 12.5% were businessman. So the Mukadams were

not representatives of the workers in general.

As far as the land holding and its nature is concerned,

Mukadam or lowest level site managers were not quite distinct from

the workers. This may be because of the involvement of the

contractors and businessmen in the category of Mukadams.

As far as the family type was concerned 50% of the Mukadams

had joint families.

Table-5.2

SAMPLE MUKADAM’S PROFILE

Sr.

No.

Variable Category Frequency Percentage

1) EGS

2) SGRY

12

12

50.00

50.00

Total 24 100.00

1 Scheme

Name

Total 24 100.00

25 to 35 Years 15 62.50

36 to 45 Years 5 20.83

46 to 55 Years 3 12.50

56 + Years 1 4.16

2 Age

Total 24 100.00

3 Sex All 24 Mukada-

ms were Male

24 100.00

Maratha 8 33.33

Vanjari 2 8.33

Kokana 5 20.83

Mahadev Koli 4 16.66

Warli 4 16.66

Bhatka 1 4.16

4 Caste/ Tribe/

Minority

Total 24 100.00

Non Reserved

Caste Category

7 21.16

SC 2 8.33

ST 13 54.16

NT/DT/VJ 2 8.33

5 Category

Total 24 100.00

Illiterate 15 62.50

Up to 5th 6 25.00

FY to Graduate 2 8.33

Any Other 1 4.16

6 Education

Total 24 100.00

185

185

Service 6 25.00

Service +

Agriculture

2 8.33

Agriculture+

Wage Labourer

2 8.33

Wage labourer 6 25.00

Contractor 5 20.83

Business 3 12.50

7 Means of

livelihood

Total 24 100.00

No land 7 21.16

Below 2 acres

dry

2 8.33

2-5 dry 8 33.33

11 and above

dry

4 16.66

6-10 Irrigated 2 8.33

11 and above

Irrigated

1 4.16

8 Family Land

Holding

Total 24 100.00

Joint 12 50.00

Nuclear 12 50.00

9 Family

nature

Total 24 100.00

5.1.3 Profile of the Sarpanchs

All the 12 Sarpanchs from the sampled villages were selected

as a sample. The data relating to the socio-economic background of

the Sarpanchs are presented in the table 5.3. Majority (58.33%) of

the Sarpanchs were from age group of 25 to 35 years. Again, 58.3 of

them were male and 41.7% of them were female. Reservation for

women in Panchayati Raj is the only reason there to see why these

women could reach there to become Sarpanch. The percentage of

young Sarpanches seems to be increasing in recent years.

Out of 12 Sarpanchs, 6 (50%) were tribals, and 4 (33.3%) were

Dalit. Ramoshi and Vanjari were 8.33% each. This shows that all

the Sarpanches were from SC, ST and OBC category. Nav Baudhha

and Koakanas were dominant among these (33.33% each). Caste

reservations played dominant role here.

All the Sarpanchs in the sample were having moderate

educational level; SSC passed. 16.66% of the Sarpanchs and 8.33% of

186

186

the Deputy Sarpanchs had completed their graduation. Their

background in terms of land holding revealed that, 25% of the

Sarpanchs were landless labourers (two of them told that they have

land access but they do not get any benefit from the family land) and

one was contractor/businessman. All the remaining 8 (66.7%) were

dependent on agriculture.

Only 8.3% of the Sarpanches were without land holding. All

the others were farmers. 41.6% of them had some irrigated land.

This indicates that, those who had better economic position could

reach to acquire position of Sarpanch. Half of the Sarpanches had

joint family background.

Table- 5.3

BACKGROUND PROFILE OF THE SAMPLE SARPANCHS

Sr.

No.

Variable Category Frequency Percentage

1 Scheme Name EGS and SGRY 12 100

Below 25 Years 2 16.7

25 to 35 Years 7 58.3

36 to 45 Years 2 16.7

56 to 60 Years 1 8.3

2 Age

Total 12 100.0

Male 7 58.3

Female 5 41.7

3 Sex

Total 12 100.0

Vanjari 1 8.3

Nav Baudhha 4 33.3

Kokana 4 33.3

Mahadev Koli 2 16.7

Ramoshi 1 8.3

4 Caste/ Tribe/

Minority

Total 12 100.0

SC 4 33.3

ST 6 50.0

NT/DT/VJ 2 16.7

5 Category

Total 12 100.0

SSC to HSC 2 16.7

SSC +Diploma 8 66.7

Graduate 2 16.7

6 Education

Total 12 100.0

187

187

Agriculture 8 66.7

Landless Labour 3 25.0

Business

+Contractor 1 8.3

7 Means of

livelihood

Total 12 100.0

No land 1 8.3

Below 2 acres dry 1 8.3

2-5 dry acres dry 2 16.7

6-10 acres dry 3 25.0

Below 2 Irrigated 1 8.3

Irrigated +Dry

up to 5 acres 2 16.7

Irrigated +Dry 6-

10 acres 1 8.3

Irrigated + Dry

11 acres and

above

1 8.3

8 Family Land

Holding

Total 12 100.0

Joint 6 50.0

Nuclear 6 50.0

9 Family Type

Total 12 100.0

5.1.4 Profile of the Deputy Sarpanchs

The 12 Deputy Sarpanchs belonging to the 12 sample were

selected as sample respondents. Among the Deputy Sarpanchs, an

overwhelming majority (i.e. 75%) belonged to young age group i.e.

they were below 35 years of age. All the Deputy Sarpanchs were

male. 50% of the Deputy Sarpanchs were belonging to tribal

category. Vanjari and Mali constituted 25% and 8.3% respectively;

they were relatively better positioned. In terms of their educational

level, 83.2% of the Deputy Sarpanchs had matriculation and post

matriculation education to their credit whereas 8.33% of them had

completed their graduation. Deputy Sarpanchs were found relatively

better off economically than the Sarpanchs. 83.3 were engaged in

agriculture, 8.3 in services and 8.3 were doing agriculture with

supportive earnings from wage labour. No one of them was landless.

66.7% of the Deputy Sarpanchs were having joint type of family

background.

188

188

Table: 5.4

PROFILE OF THE DEPUTY SARPANCHS

Sr.

No. Variable Category Frequency Percentage

1 Scheme

Name and

Number

EGS and SGRY 12 100

Below 25 Years 1 8.3

25 to 35 Years 8 66.7

36 to 45 Years 2 16.7

46 to 55 Years 1 8.3

2 Age

Total 12 100.0

3 Gender Male 12 100.0

Vanjari 3 25.0

Mali 1 8.3

Nav Baudhha 1 8.3

Kokana 1 8.3

Mahadev Koli 5 41.7

Ramoshi 1 8.3

4 Caste/ Tribe/

Minority

Total 12 100.0

SC 1 8.3

ST 6 50.0

NT/DT/VJ 4 33.3

Minority 1 8.3

5 Category

Total 12 100.0

Up to SSC 2 16.7

SSC to HSC 3 25.0

SSC + Diploma 4 33.3

HSC + Diploma 1 8.3

Graduate 1 8.3

Post Graduate 1 8.3

6 Education

Total 12 100.0

Service 1 8.3

Agriculture 10 83.3

Agri+ Labour 1 8.3

7 Means of

livelihood

Total 12 100.0

No land 1 8.3

Below 2 acres

dry 1 8.3

2-5 dry 3 25.0

6-10 dry 1 8.3

11 and above dry 1 8.3

8 Family Land

Holding

11 and above

Irrigated 2 16.7

189

189

Irrigated + Dry

11 acres and

above

3 25.0

Total 12 100.0

Joint 8 66.7

Nuclear 4 33.3

9 Family

Type

Total 12 100.0

5.1.5 Profile of the Gram Sevaks

The 12 Gram Sevaks were selected as sample who belonged to

the sampled villages. The data regarding their socio-economic

background are presented in table 5.5. Majority of them (53.3%)

belonged to higher age group of 25 to 35 followed by those belonging

to year’s age group 36 to 45 years age group (41.7%). Only one Gram

Sevak hailing from semi developed belt was female. Majority of the

Gram Sevaks were from the castes like Marathas (58.3%), Lingayat

(8.3%) and Dhangar (8.3%). Only 16.6% were tribals representing

relatively better of tribal groups in the regions like Kokna and

Warli.

The Gram Sevaks are expected to complete SSC or HSC with

agriculture diploma. Gram Sevaks in this category of education were

relatively few in number and 41.66% of them were graduates. All the

Gram Sevaks were involved in service. Besides, 58% of them were

having agricultural income as means of livelihood. Nearly 50% of

them had owned irrigated land. Most of them (75%) were having

nuclear type of family background.

190

190

Table: 5.5

PROFILE OF THE SAMPLE GRAM SEVAKS

Sr.

No.

Variable Category Frequency %

1 Scheme

Name

EGS and SGRY 12 100

25 to 35 Years 7 58.3

36 to 45 Years 5 41.7

2 Age

Total 12 100.0

Male 11 91.7

Female 1 8.3

3 Sex

Total 12 100.0

Maratha 7 58.3

Dhangar 1 8.3

Kokana 1 8.3

Warli 1 8.3

Lingayat 1 8.3

Chambhar 1 8.3

4 Caste/ Tribe/

Minority

Total 12 100.0

Non Reserved Caste

Category 8 66.7

SC 1 8.3

ST 2 16.7

NT/DT/VJ 1 8.3

5 Category

Total 12 100.0

Education SSC to HSC 1 8.3

SSC +Diploma 2 16.7

HSC + Diploma 4 33.3

Post Graduate 5 41.7

6

Total 12 100.0

Service 5 41.7

Service + Agriculture 6 50.0

Agriculture 1 8.3

7 Means of

livelihood

Total 12 100.0

No land 5 41.7

2-5 dry land 1 8.3

6-10 Irrigated 3 25.0

11 and above Irrigated 2 16.7

Irrigated +Dry up to 5

acres 1 8.3

8 Family Land

Holding

Total 12 100.0

Joint 3 25.0

Nuclear 9 75.0

9 Family Type

Total 12 100.0

191

191

5.1.5 Profile of the Talathis

The Talathi is lowest ranked official from the revenue

department. The 12 Talathis selected as a sample were relatively

older than the Gram Sevaks (66.7%) belonged to age group of 36 to

45 years and 25% to the age category of 46 to 55). Except one female

Talathi (8.3%) all were male. Like Gram Sevaks, majority of them

were from the Maratha Castes (50%) and the rest half of them were

from the backward caste/tribe; SCs (16.7%) and STs (33.3%).

In terms of education 8.33% were graduates and 16.66% had

education less than SSC. All the remaining Talathis had education

up to SSC and HSC (16.7% respectively). New generation Talathis

and Gram Sevaks were better educated. The newly recruited female

Talathis and Gram Sevaks were visible although not welcomed for

these hitherto male dominated jobs.

66.66% of the Talathis were having agriculture as a side

business. 25% of them had irrigated land. The other 33.33% relied

only on their service as a source of livelihood.

25.0% of the Talathis did not have access to land as owners.

Those having land were supported by some irrigational facilities.

They said their land and agriculture was managed by the family

members since they were very busy in their service. Half of the

Talathis were hailing from joint type of families.

Table: 5.6

PROFILE OF THE TALATHIS

Sr.

No.

Variable Category Frequency %

1 Scheme Name

and No. of

Talathis

EGS and SGRY 12 100

25 to 35 Years 1 8.3

36 to 45 Years 8 66.7

46 to 55 Years 3 25.0

2 Age

Total 12 100.0

192

192

Male 11 91.7

Female 1 8.3

3 Sex

Total 12 100.0

Maratha 6 50.0

Nav Baudhha 2 16.7

Kokana 2 16.7

Mahadev Koli 1 8.3

Bhill 1 8.3

4 Caste/

Tribe/Minority

Total 12 100.0

Non Reserved

Caste Category 6 50.0

SC 2 16.7

ST 4 33.3

5 Caste Category

Total 12 100.0

Up to SSC 2 16.7

SSC to HSC 4 33.3

SSC+Diploma 2 16.7

HSC + Diploma 2 16.7

Graduate 1 8.3

Post Graduate 1 8.3

6 Education

Total 12 100.0

Service 4 33.3

Service +

Agriculture 8 66.7

7 Means of

livelihood

Total 12 100.0

No land 3 25.0

2-5 dry 5 41.7

6-10 dry 1 8.3

3-5 Irrigated 2 16.7

6-10 Irrigated 1 8.3

8 Family Land

Holding

Total 12 100.0

Joint 6 50.0

Nuclear 6 50.0

9 Family Type

Total 12 100.0

5.2 Section Two- A Comparison of Implementation of EGS

with SGRY in Nashik District

Section two analyses aspects of implementation of EGS and

SGRY in Nashik District, with dimension of variation observed in

Developed, Semi Developed and Less Developed areas of Nashik

District.

193

193

Implementation is a process of achieving the goals of the

scheme through a chain of organized human resources plus

administrative machinery of the governing body. Scheme design of

framework, planning, administration, institutional bases, execution

of the scheme activities and the way of running work sites, role of

the implementing agencies, distribution of wages and amenities to

actual beneficiaries etc. are the aspects of the implementing

processes.

The main variables relating to the process of implementation

aspects that have been considered here for analysis include: a)

Demand patterns and decision making in bringing EGS-SGRY

works; b) Decision making in selection of works; c) Means of

communication to the concerned people in the village about the

starting of work; d) Nature of work and Agency of implementation;

e) Nature of Monitoring and supervision- who did it, visits,

frequency; f) Number of days workers worked on the sample sites; g)

Selection of workers: Social Inclusion and Social exclusion-bases,

reasons and implications, h) Sufficiency of EGS/SGRY workers,

alternatives; i) Wages and Income gains to workers, j) Amenities

provided on work sites, k) Gaps in the work and its reasons, l)

Measurement- who did, when, how; m) Observance of the procedures

or norms laid down: cards, contractor, local and outsiders, 60:40

ratio; o) Unofficial Involvement of Political leaders and stakeholders,

p) Which scheme is better implemented, q) Role of Agency, agency

officers and the Implementers and r) The Level of Political

Involvement.

Instead of analyzing them separately, let us evaluate them by

clubbing the interrelated variables. An overall attempt was made to

seek answer to the questions: How the works were began, planned

and executed at the grassroots level?

194

194

How the EGS and SGRY works began and were planned in the

villages? This was the initial important aspect to understand their

implementation. This can be understood in the context of the

regulations and guidelines of the schemes and what practices

actually were followed at the village level.

The researcher attempted to collect the data relating to the

following: Wheather workers and some of the implementers had

adequate knowledge of the schemes or not? Did the EGS workers

demanded the work by following procedure laid down?

1) How the EGS and SGRY works were brought to the villages?

How decision making took place while selecting the works? How

workers were communicated about the starting of the works?

2) How the worker beneficiaries were included or excluded? What

could be the implications of this inclusion and exclusion? What

was the nature of the works? Which were started? How the works

were supervised, monitored and measured? What was the nature

of onsite problems? In what way the workers were benefitted?

(Wages, foodgrains, amenities, employment opportunities)

3) How there was an involvement of intermediaries, machine and

elite stakeholders?

4) What was the role of agency officers and implementers? What

about the quality of implementation?

5.2.1 Knowledge about the Scheme and Pattern of

Demanding the work:

As a scheme EGS is a very complex scheme in its

implementation. The workers, Talathis, and others associated with

the scheme, must have basic knowledge of various procedures

involved in its implementation.

195

195

During the field-work visits, the researcher found that many

such procedures that were important to avail the benefits of the

scheme were not known to the workers and even to some of the

Sarpanchs, Gram Sevaks and the Talathis. 64.7% workers working

on the EGS sites did not know the scheme-name under which they

were working.

EGS is a demand driven scheme. The article 3 of the

Employment Guarantee Act of 1988, says that every adult person in

the rural areas in Maharashtra shall have the right to get a

guaranteed employment for doing unskilled manual work and to

receive wages thereof weekly, or in any case, not later than a

fortnight. Unless and until the workers from the villages demand for

the work under EGS in writing, EGS will not be allotted or started

in the village concerned. Each worker has to demand for EGS work

by filling up form No. 4. Then, Talathis are expected to register the

names of the potential workers on the basis of such demands and he

is also expected to distribute EGS identity cards to the workers.

It was revealed during the field visits that, workers did not

take initiative in registering their name as potential workers

because 91.8% of them did not know the demand driven nature of

the EGS works. No worker had registered the demand by filling in

form No. 4. Though 13.72% of the EGS workers had made demands

for the works, the correct procedure was, however, not followed by

them. They had put the oral demands through mediators and other

stakeholders. In some instances, the demands were also initiated by

the implementing officers who wanted to start particular EGS works

in certain villages. Not all the workers were issued the identity cards

by the Talathis. Only 23.5% of the workers from the sample were

having EGS cards.

196

196

Then, the question arises as to how most of the workers could

get EGS works without demanding on their own. The information

elicited through the personal interviews revealed that, the local

political leaders, Sarpanches, Gram Sevaks, Talathis, Gram

Panchayat members made demands on behalf of the workers. In

doing so, the procedures were not followed in most of the cases.

Thus, the verbal request, collective general demands made by the

Gram Panchayat could bring the EGS works to the villages. 3.92% of

the EGS workers did not know how or by whose efforts they got the

work. Making collective demands through representatives or by

Gram Panchayats is not illegal but it showed the inability of the

workers to follow the procedures to get EGS works.

Demand making in EGS is also shaped and influenced by the

stake-holders’ interests. Contractors, Agency Officer’s intervention

and elite stakeholder’s demands also played role in bringing EGS

work to particular villages. One Sarpanch from the developed belt

said, “you need good interactions and connections to bring EGS

works to your village. Just demand making is not enough. Constant

follow-up at Tehsil office or agency level is also required.”

All the 12 Sarpanchs reported that they did make serious

efforts to bring EGS to their respective villages. Eleven Assistant

Sarpanchs also told that they made some efforts to bring EGS and

that too with the help of Gram Panchayat decisions. But workers, on

the other hand, hold the view that nobody from the villages was

serious to bring EGS works to them and to their villages.

Talathi is the lowest ranked EGS officer placed at the

grassroot level to collect the demands and forward these to Tehsildar

office of the Taluka. The data showed that half of the Talathis were

not sufficiently aware of their role in EGS.

197

197

Table 5.7

Answer of the Talathis about their Role in EGS

Implementation

Responses of Talathis Frequency Percent

Know very well 1 8.3

Fairly good 5 41.7

Confused about the role 4 33.3

Do not know the role 2 16.7

Total 12 100.0

Although the Gram Sevaks did not have direct concern with

EGS they are expected to deliver information of all policies and

programmes in Gram Sabhas and in Gram Panchayats. This has not

been done by most of them; 4 of the 12 Gram Sevaks claimed that

they did made efforts to aware people and encouraged them to make

EGS demands. The rest 8 (66.7%) of them said they did not do

anything to bring EGS in their villages.

SGRY: SGRY is basically not a demand driven scheme. The specific

work under the first stream is given to specific village on the basis of

selection of the village done either by Panchayat Samiti member or

by ZP member. Under second stream, specific funds are allotted to

each Panchayat on certain fixed criterion. The villagers cannot

further demand the extra work besides the one which happens to be

based on the given funds despite they are in more vulnerable

condition. For successful implementation of the scheme, knowledge

about the SGRY scheme is essential.

During the field visits, it was revealed that most of the

workers and even some Sarpanchs did not know even the name of

SGRY. Some of them still called it by its earlier name ‘Jawahar

Yojana’. 91.8% of the workers did not know that their respective

198

198

villages get SGRY funds annually to plan and complete the works for

generating employment for the poor.

Thus, it was noticed that was lack of awareness about both the

EGS and SGRY schemes among most of the workers, Sarpanchs,

Talathis and Gram Sevaks who are the key persons in the process of

implementation at the grassroots level.

Regional Variation: It is interesting to note that 71.42% of the

EGS workers, who had made demands for the work were from the

less developed areas. This may be due to several reasons like-high

incidences of poverty, vulnerability and less alternative employment

opportunities, earlier experience of working under EGS, need to

avoid migration and relatively better knowledge of the scheme. Some

efforts of the civil society organizations also influenced the demand

making (its details would be covered in the next sections and

chapter).The tribals from the less developed areas were not just

better awared of making demands but also one step ahead in making

collective demands in order to put higher some pressure on the

implementing body to open the work in their respective villages.

The tribal took collective decisions regarding the works. This

might not be done through the Gram Sabha every time but some sort

of collective interest has been taken by the tribal poor.

199

199

Case No. 5.1: “Innovative Experiments in Making EGS

Demand collectively”

This is the case of one of the tribal villages. The villagers were

worried about possible leaking of percolation tank that was build

for more than 10 years back. The village was entirely dependent

on the tank for water (both for drinking and agriculture). There

was shortage of water in the village and strength of the

percolation tank was declining due to the leakage. The villagers

made several applications to the concerned departments but did

not get any response from them. They collectively decided to

repair the tank by making use of EGS. Some agency men, when

they were convinced about the issue, helped them. The whole

village made an effort to get the work sanctioned under EGS.

They took labour contract and the whole village was working for

the tank repair work. The poor from the tribal village said, we

were desperate to save the tank and were ready to do anything

for it. Finally they did it by collective efforts.

5.2.2 Decision making in selection of works

EGS: As per the guidelines under EGS workers do not have much

say in decision making about the selection of the works. This mainly

applies to SGRY scheme. SGRY: Who decided the nature of the

works is an issue related to the SGRY. SGRY provides the

opportunity to take decision about the work by the Gram Sabha in

participatory, democratic manner. 26.47% of the SGRY workers said

that the Gram Sabha was conducted for deciding, planning and

managing the works. 29.49% said since they did not attend the

Gram Sabhas regularly, therefore, they did not know about it.

200

200

Table 5.8

Was Gram Sabha conducted to discuss and decide about

SGRY work?

Development Category

Developed Semi Developed Less Developed

Total

Yes 1 4 4 9

No 4 2 9 15

Do not

know 5 3 2 10

10 9 15 34

Table 5.9

Did workers participate in discussion in G.S.

about SGRY Works?

Development Category

Developed

Semi

Developed

Less

Developed

Total

Yes 1 1 2

No 4 7 13 24

Not

Applicable 5 2 1 8

Total 10 9 15 34

During informal discussions, most of the villagers and

members from Gram Panchayat said that they did not know about

the collective-democratic decision making and planning incorporated

in SGRY. The Gram Sevak did not explain the basics of SGRY in the

meetings. A question was asked to the workers was ‘who took final

decision about the SGRY work?’ The responses are presented in

table 5.10.

201

201

Table 5.10

Who took final decision about the SGRY work?

Responses Developed Semi

Developed

Less

Developed Total

Gram Sabha

Collectively 0 0 1 1

Gram

Panchayat

Collectively

0 0 2 2

Sarpanch 1 1 2 4

Gram Sevak 2 5 4 11

Sarpanch +

Gram Sevak 2 5 4 11

Contractor 2 2

Do not know 5 3 5 13

12 14 18 34

The data presented in the table 5.10 clearly reveal that, the

decision about the selection of the works is not being taken in

according to the procedure laid down.

Regional Variation: Discussions in Gram Sabha and participation

of the workers in the deciding and planning of the SGRY works was

little higher in semi developed and less developed areas. The

principle of participatory-democratic decision making in the Gram

Sabhas about the SGRY works largely remains on paper. Instead of

decision making in Gram Sabhas, the final decision in most of the

cases is taken by other stakeholders having their extraneous vested

interests. The Sarpanch and Gram Sevaks were leading decision

makers in semi and less developed areas whereas, such elites had

upper hand in developed areas as well.

202

202

5.2.3 Means of communication to village about the starting

of work

Sargrantha, the bible of EGS, says that, each and every

worker from the village should be communicated before

commencement of work at EGS worksite. Drum beating and

announcing is the usual method used for such communication. This

provides maximum opportunity to rural poor to participate in the

work project and selection bias is removed. SGRY procedures also

expect the same thing. The village authorities and the agency

officers undertaking the work in the village under EGS or SGRY

work projects were expected to communicate the information about

the commencement of the works by drum beating in the village, by

holding separate gram Sabha or at least putting the notice about

commencement of the works on the Gram Panchayat notice board.

Against this backdrop, let us look at the empirical realities at the

grassroots level.

EGS: Drum beating method for communication was used in only one

case EGS work. Notice on Gram Panchayat board was another

method used by another one village. In case of still another village

special Gram Sabha meeting was held to convey the message of

opening of the EGS work. In all other cases no such method of

communicating the commencement of the work project was used.

SGRY: The guidelines regarding communicating information about

the commencement of work were not followed seriously in most of

the SGRY works too. In 91.6% SGRY cases the workers were not

communicated about the commencement of SGRY works before. One

Gram Sevak put the notice of the work on the Gram Panchayat

notice board. A general apathy, ignorance about the guidelines and

sometimes deliberate intentions of hiding the information could be

203

203

some of the main reasons for this. In some cases, the message was

given to some of the potential workers.

Regional Variation: There was no much regional variation

observed with regard to the issue of prior communication to workers

about the commencement of works. Less developed/Tribal areas too

did not pay much attention to communicate the commencement

information to the village poor. One Sarpanch reported that since,

the tribal poor are generally more desperate in seeking work

opportunities, no such method was required.

5.2.4 Aspects of Work Implementation

The specific aspects of the work implementation examined and

discussed below include: (a) place of worksite, (b) nature of work and

implementing agency, (c) allocation of funds, (d) supervision,

monitoring and managerial issues, (e) gaps in the work, (f) schedule

of measurement of work, (g) who took the measurement of the work,

(h) sufficient availability of workers. Let us look at these aspects one

by one.

(a) Place of worksite:

After decision making, the process of works implementation

starts at the location of the site. Variation with regard to place of

worksites of EGS and SGRY works was also observed.

EGS: According to 31.37% of the EGS workers, the sites were

located within the respective villages, 54.90 said those were close to

the villages and 13.7% were noted that the site located in radious of

more than 3 kms i.e. far from the villages concerned.

SGRY: In case of SGRY sites, according to 73.52% workers, the

worksites were located within the villages and 26.47% told that they

were close to the villages. No SGRY worksite was away from the

villages concerned. (See table 5.11)

204

204

Some EGS sites were far from the villages. This may be

because of the nature of the EGS sites. Generally, water

conservation works tend to be relatively bigger and need particular

catchment areas which may away from the village concerned.

Table 5.11

Place of the worksite: Respondent Workers Responses

Place of the worksite

Scheme Inside the

village

Close to

village

Far away

from the

village

Total

EGS 16 28 7 51

SGRY 25 9 0 34

Total 41 37 7 85

The other dimensions of site implementation can be analysed

as under-

(b) Nature of work and Agency of implementation

The PEPs like EGS and SGRY have an important objective of

creating rural infrastructure that would boost the development of

the village. The government emphasized Water conservation and

Soil conservation works. These two work -types were considered

central for development of village economy and agriculture. What

kinds of works were undertaken under EGS and SGRY? who

selected those works? with what intensions? were the main issues of

our concern here.

There are many agencies and their officers involved in the

programme implementation. They are supposed to be onsite

implementers. Minor Irrigation (MI), Building and Construction (B

and C), Agriculture, Public Works Department (PWD), Forest and

others were the leading agencies or departments involved both in

EGS and SGRY. Only 10.6% of the workers were unaware of the

205

205

implementing agency of the work where they were engaged. About

43% of the workers from the sample did work under Minor Irrigation

agency or department that showed that they were engaged in water

conservation works.

EGS: EGS policy regulations say that workers can only demand

EGS works and they do not have ultimate choice to select the nature

of the work. EGS being the centralized, bureaucratic oriented

scheme, the policy implementers and especially the agency officials

are supposed to decide the nature of EGS work.

The nature of the EGS works implemented in the 12 sample

villages were as under: 3 Soil Bandhara, 1 Aforestration+ Mazgi, 1

Afforestation, 2 Plants Development, 1 Cement Bandhara, 1

Bandhara reaping work, 1 Village tank works, 1 Road construction+

Aforestration, 1 CCT.

Minor Irrigation (6), Agriculture (02), Forest department (02)

and Social Forestry (03), PWD (01) were the agencies by which the

EGS works in the 12 villages were going on. In two villages more

than one EGS works were undertaken.

SGRY: The SGRY works were undertaken in 12 villages include: 1

Soil Bandhara, 4 Stone Bandhara, 1 Cement Bandhara, 1 Gutters /

Raw (Kaccha) road, 1 Land leveling for play ground, 1 Kitchen shed,

1 Gram Panchayat office building, 2 Funeral shed, 2 Well

construction, 1 Waste soil lifting, 1 Wall compound to Gram

Panchayat office with 2 Urinary around. Some villages did more

than one work at a time.

58.2% of the SGRY works were water or soil conservation

works and the remaining 49.8% of the works were of buildings and

construction works.

Minor Irrigation, Agriculture, Forest department were the

prominent agencies in SGRY. PWD and B and C are the least

206

206

engaged agencies. They are more involved in SGRY works in

comparison with the EGS. Some building construction works like

construction of Gram Panchayat building, kitchen shed for schools

are allowed in SGRY.

So the nature and government agencies associated with the

works under EGS and SGRY were different. EGS was specialized in

forest development and plantation and thus given scope to agencies

like forest and social forestry while as SGRY did also emphasized

construction works and invited agencies like Building and

Construction.

Regional Variation: It can be seen from the data presented in the

table 5.12 that majority of the works in tribal areas were water and

soil conservation works. In the developed and semi developed areas

on the other hand, roads construction and other infrastructural

works were predominant.

Table: 5.12

Nature of the work projects

EGS SGRY

Development

Category

Worksite

No. Nature of work Nature of work

1 Aforestration +

Plant

Development

4 Stone Bandharas

2 Plants

Development

Gutters / Kaccha

road

3 Cement Bandhara Construction of

latrines

4 Soil Bandhara Funeral shed

Developed

5 Aforestration/

Mazgi

Kitchen shed Semi

Developed

6 Plants

Development

Land leveling for

play ground

207

207

7 Road construction

(Raw) and

Afforestation

Wall compound /

Urinaries

8 Soil Bandhara Waste soil lifting

9 Soil Bandhara Gram Panchayat

office building

10 CCT Stone Bandhara

11 Bandhara reaping

work

Well construction

Less

Developed

12 Village tank Well construction

(c) Funds allocation to the schemes –

Quality and size of the assets generated and the employment

generation heavily rests on the funds. The size and the funds

definitely affect the performance of EGS and SGRY as well.

EGS: EGS is a demand driven scheme and it is difficult to set out a

budget for particular village. We can judge the fund allocation from

the total expenditure at District and Taluka level (see Section II in

chapter III for details). It was observed that the funds allocated

under EGS were obviously larger than SGRY.

All of the EGS works undertaken in the sample villages were

having funds or budget more than Rs. 1 lack. The data collected from

the field shows that EGS works were relatively big works.

SGRY: SGRY works in comparison with EGS works were having

lower budget. Only 16.6% of the SGRY works were having funds

higher than Rs. 1 lac. Fund allocation for SGRY works, especially

from the second stream was smaller in size. The funds are given for

the whole year, mostly in installments and no one can get more

funds beyond the limit for the same year.

In case of SGRY works, the fund allocation under Ist Stream

works were close to EGS funds but these works were very few in

number. Only one village out of 12 could get SGRY Ist stream work

208

208

during the study period. The second stream fund allocation under

SGRY was so meager that only those two villages out of the 12,

received funds more than one lac.

Regional Variation: SGRY funds are largely dependent on the

population of the village. Smaller villages with low population

reduce the funds. The villages from the less developed regions full of

people from S.C. – S.T. categories received higher per head funds

than the other categories but those were the typical villages with

lower population and thus got lower funds under SGRY.

(d) Supervision, Monitoring and Managerial Issues on the

site Problems

The supervision and monitoring mechanisms of the two

schemes are distict from each other.

EGS: EGS sites are required to be managed by the agency officials.

But in practice Mukadams, owners of the land where water

conservation works were going on, contractors also kept records and

supervised the works.

SGRY: Under SGRY, the responsibility to manage, supervise and

monitor the works goes to the respected Gram Sevaks, Sarpanches

and the members of the Gram Panchayats and sometimes to the

agency officers. Special committees are appointed from National

level to Taluka level for vigilance and monitoring. Their visits on

sites were rare. At the empirical level it was found that, 33.33%

(four) of these works were also recorded and managed by the

contractors, one from the workers themselves, one from Gram

Panchayat Peon and in one case no supervision or recording man

was visible.

Technical monitoring and supervision for the EGS works was

better than the SGRY projects.

209

209

Regional Variation: It was observed during the fieldwork that, the

Works from the developed areas were more likely to be recorded and

supervised by the agency officers and contractors and works in semi

and less developed areas were recorded and managed by the

Mukadams, land owners in association with the agency men.

As far as SGRY works were concerned, the Sarpanch and

Gram Sevaks from the semi and less developed areas were more

serious about their duties than in the developed areas. Agencies

were more or less seemed negligent.

(e) Gaps in the work and its reasons

After the starting of the work on the sites, gaps in work are

frequently observed and most of the time they are inevitable. They

also reflect lacunae in the scheme implementation. In all, 44.7 % of

workers experienced gaps in the works they were working.

EGS: 25.9% of the workers reported that they experienced shorter

and occasional gaps in works and 20% of them experienced huge

gaps mostly observed on EGS sites. EGS projects are not ruled by

the annual budgetary cycle. They are larger and technically more

complex than SGRY projects, and therefore intrinsically more likely

to fall victim to logistical or organisational delays.

SGRY: The gaps were small and rare in the case of SGRY projects.

SGRY projects are relatively small, and supposed to be completed

within one year, and there is considerable organisational pressure to

complete work quickly.

Regional Variation: There was no much variation in case of gaps

in ongoing work on the basis of level of development area.

It is interesting to find out the reasons for such gaps in the

work. Workers were asked about the gaps. 2.4 % of the workers said

that the delays were due to lapses from implementing authority.

While as 1.2% of them said that it was due to natural obstructions.

210

210

Another 1.2% reported that it was due to funding problems. 14.1%

workers said that non availability of workers as the reason. The

remaining workers did not know the reasons.

(f) Frequency of Measurement of the work done by the

workers:

Measurement of the work done by the workers is one of the

important factors relating to the implementation.

EGS: EGS works are expected to be measured every fortnight.

Measurement of the work was considered a responsibility of agency

officer. Measurements should be taken in front of workers so that

the workers could realize and relate the proportion of work they did

and the amount of payment they received. The data of the present

study reveal that, all such regulations were rarely followed on EGS

sites. At the time of visit, the researcher could not see sample pit,

brass measuring sample, onsite guiding board showing links

between amount of wages to the nature and amount of work were

absent in all of the 12 EGS sites under sample. On 8.33% EGS

worksites measurement was being taken as per schedule, sincere as

well as frequent. Measurements after every 15 days were present on

50% of the EGS sites but there were still some amount of

irregularities at times. On 41.66% EGS sites measurement was very

irregular.

SGRY: The SGRY norms are not directly saying anything about the

frequency of measurements but norm no. 3.4 from its guidelines say

that the wages should shall be made on a fixed day in every week.

That means measurement should be taken on every week. In case of

only 16.66% of SGRY worksites, measurements were being taken

after every week. In 16.66% it was taken after every 15 days. That

means measurement was fairly regular there. On 66.66% of the

SGRY works measurements were very irregular.

211

211

Regional Variation: The measurement was relatively regular in

less developed regions rather than in the case of developed and semi

developed regions. (see Table 5.13)

Table 5.13

Frequency of measurement of the Works

Development Category Frequency of

measurement

Scheme

Name Developed Semi

Developed

Less

Developed

Total

EGS 0 1 0 1 Very Frequent

Total 0 1 0 1

SGRY 0 1 1 2 Weekly

Total 0 1 1 2

EGS 3 3 0 6

SGRY 1 1 0 2

After 15 days

Total 4 4 0 8

EGS 1 1 0 2

SGRY 0 2 0 2

After a month

Total 1 3 4

EGS 0 1 2 3

SGRY 3 2 1 6

After the work /

very late

Total 3 3 3 9

f ) Who took measurements?

68.2% of the EGS and SGRY workers said the measurements

were done by the agency officer; 28.2% said the lowest level Agency

men took measurements and 2.4% said the Mukadams on the site

took the measurements. (See table 5.14)

212

212

Table 5.14

Who took measurements?

Who took

measurements Frequency Percent

1 Agency Officer 58 68.2

2 Lowest Level

Agency men 24 28.2

3 Mukadam 2 2.4

4 Do not Know 1 1.2

Total 85 100.0

Taking measurement is ultimately a responsibility of the

concerned agency officer but on occasions Mukadam, Gram Sevaks

too took measurements. Measurement by genuine Agency officer

was more common in EGS rather than the SGRY. Semi developed

areas were better in this regard. (see table 5.15)

Table 5.15

Who took measurements of the works done

Development Category Who took

measurements

Scheme

Name Developed Semi

Developed

Less

Developed

Total

EGS 1 5 2 8

SGRY 0 1 0 1

Agency Officer

Total 1 6 2 9

EGS 3 1 0 4

SGRY 1 1 0 2

Lowest Level

Agency men

Total 4 2 0 6

SGRY 0 2 0 2 Mukadam

Total 0 2 0 2

SGRY 1 1 2 4 Gram Sevak

Total 1 1 2 4

SGRY 2 1 0 3 Don’t know

Total 2 1 0 3

EGS: Some workers, especially the workers in EGS land leveling

work from the tribal belt complained that the measurement work

did not executed seriously. Measuring the work done in land leveling

213

213

work is already very ambiguous work. The lapses from the

measurement really affect badly to the wages the workers earn

under the scheme and encourages malpractices and manipulations

of different kinds. These lapses, more specifically on EGS worksites,

were also responsible to the delayed payments.

The data collected from the Mukadams have presented in the

table 5.15. The data from the table reveal that in case of all the 12

EGS worksites, the measurements were taken by either agency

officer or lowest level agency men.

SGRY: In case of SGRY worksites, 50% of the measurements were

either done by the Mukadams or Gram Sevaks. These

measurements were relatively more irregular. Since SGRY II stream

works were shorter in time and budget, the some implementers tend

to measure the work after completion. Technical support and

measurement exercise was not prompt. Measurement was not

significantly done by the agencies associated with the DRDA or ZP.

This was not expected by the regulations.

EGS was little better than the SGRY in measurement

concerns.

Regional Variation:

The measurement of the EGS and SGRY works from

developed and semi developed regions were observed better the

works from the less developed areas because comparatively more of

them were conducted either by agency officer or lowest level agency

men.

g) Sufficiency of EGS/SGRY workers

75% of the Mukadam respondents said that the number of

workers were sufficient on their respective EGS and SGRY projects.

EGS: From Mukadam’s point of view on 50% of the EGS works

number of workers was sufficient and on 16.66% of the EGS projects

214

214

workers were more than sufficient. On remaining 33.33% EGS

projects workers were short or insufficient.

SGRY: The Mukadam from all of the 12 SGRY projects said that the

number of workers working there was sufficient. 2 Sarpanch, 3

Gram Sevaks however, said there was problem of insufficient

workers for SGRY projects.

Regional Variation

EGS projects from the developed region clearly showed

shortage of workers. Out of 25 % of the total EGS works (all from

developed belt) and 8.33% of total EGS works (all from semi

developed belt) workers were short. (see table 5.16)

Table 5.16

Sufficiency of EGS workers

Development Category Sufficiency of

EGS workers

Scheme

Name Developed Semi

Developed

Less

Developed

Total

EGS 1 4 1 6

SGRY 4 6 2 12

Yes

Total 5 10 3 18

EGS 3 1 4 No

Total 3 1 4

EGS 1 1 2 More than

sufficient Total 1 1 2

Source- Data collected from Mukadams

On two SGRY worksites (one from semi and one from less

developed area worksite) the response of the workers was so high

that they had many workers did not get chance to work on those

sites.

For both SGRY and EGS, most of the respondents from

developed and semi developed belt believe that inviting contractors

and contract labour from outside is wise because workers were

insufficient severally.

215

215

5.2.5 Following of the procedures or norms of Scheme

Implementation

The scheme implementation at various levels is expected to

follow certain procedures and norms. Did the implementers of EGS

and SGRY were keen to follow the procedural norms of the scheme

implementation? Giving preference to the local workers, adhering to

wage-material ratio of 60:40, controlled use of machines and

contractors were few of such norms considered while collecting data

to study the implementation process.

a) Were the local workers given preference in employment?

EGS: According to the norms local workers should have been

preferred and they were entitled to get work on EGS and SGRY. The

researcher found that around 10% of the workers from both the

schemes were brought from far outside. Needless to say that these

workers were brought by the professional, big contractor involved in

the schemes.

SGRY: SGRY scheme too gives preference to the local workers. But

the involvement of outsider workers, mostly linked with the big

outsider contractor was not uncommon on the SGRY sites, the

researcher noticed.

Regional Variation: The workers and villagers of less developed

tribal regions did know better about the entitlements to be given to

the locals. They were more aware of the rights of the local people

over the employment generated under the PEPs in and around of

that particular village.

The number of insider or local workers was relatively highest

in less developed areas. Workers from long distance (beyond 10 kms)

were higher in one EGS and three SGRY projects from the developed

and semi developed areas. EGS did slightly better in providing

employment to the local workers.

216

216

b) Wage and Material components (60:40 ratio)

The norms of both the schemes clarify that more expenditure

(60%) should be made on the wages for labour and not beyond 40%

of the expenses should go for the material component that include-

machine, contracts, raw material etc.

EGS: The data obtained from the Talathis and Mukadams reveal

that, in 33.3% of the EGS cases the 60:40 ratios was not followed.

EGS regulations do provide some exceptions to the rule. On road

projects or big water conservation projects this limit was extended

up to 51:49. But still proportion of expenditure on machines and

material was higher. Two Talathis were of the view that following

60:40 ratio of expenditure was rather very difficult in recent years.

SGRY: The data from the Gram Sevaks reveal that, the ratio of

60:40 related to the expenditure on wages and material was not

followed in case of 66.6% of the SGRY cases. As the employment of

contractors, machine and material component increases the benefits

to the poor worker decreases.

Not following wage material/machine (60:40) ratio was higher

in SGRY than EGS and therefore, EGS was better in this concern.

Regional Variation: There was no prominent regional variation as

far as following the 60:40 ratio of expenditure on workers and

machine/material respectively in case of EGS worksites. On SGRY

projects, however, such variation was observed. The data obtained

from the Sarpanchs reveal that, in semi-developed areas overriding

the 60:40 ratio was as much as the double than what was observed

in case of the SGRY projects from the developed and less developed

areas.

217

217

Case No. 5.2: Why 60:40 norm get overruled?

One EGS officer explained that non-observance of 60:40 rules

might be inevitable for several times. The unexpected hard stone

found while digging the holes, increased cost of material, machine

charges and several other practical on site problems make it

impossible to follow the 60: 40 ratio. But many times due to

illegal use of machinery, illegal entry of big contractor and such

other reasons also results in violation of 60:40 labour –material

ratio.

c) Involvement of Intermediaries, contractors in the

implementation

EGS: The guidelines of both EGS and SGRY schemes reject the idea

of existence of intermediary between the implementers and the

beneficiaries. Contractors, middle men are not allowed. Task-work

system is normal in EGS implementation but unofficial contracts are

not allowed in EGS. If the budget is higher, the contracts can be

given to Labour Cooperative Societies and if the work is still bigger

the tenders from Government contractors (up to 10% of the total

expenditure) are invited and passed by certain procedures.

As per the information given by Mukadams, there were 8.3%

cases of EGS where there was 100% involvement of big outside

contractors was observed. In two EGS works (16.66%) cases of EGS

not complete but higher involvement of around 75 to 99% of the big

outside contractors was found.

SGRY: Works under SGRY on the other hand, are expected to be

planed, manage and implemented by the locals. They can take

technical help from the agency departments but here too contractors,

middle men are not allowed. Under SGRY, Contractors are not

permitted to be engaged for execution of any of the works under the

218

218

programme (SGRY Guidelines: 5.16.1:19). But still the involvement

of middleman or and other intermediate agency was observed while

executing the works under the programme. The data from the

Mukadams reveal that, 33.3% of SGRY works, there was 100%

involvement of big outside contractors (see Table 5.18). The use of

machines causing exclusion of the human labour was obviously

highest on those sites. In 8.3% SGRY cases, there was higher

involvement (approximate 75 to 99%) of the big outside contractors.

However, the involvement of small/part-time outside contractors was

observed in higher proportion in EGS than SGRY works.

As a result of this the employment generation ability of the

schemes was negatively affected.

The norms of both the schemes clarify that 60% of the

expenses should go to the labour component of the schemes and not

beyond 40% of the expenses should go for the material component of

expenses that include- use of machine, contracts, raw material etc.

This 60:40 ratio of wage-material expenditure was not followed in

66.6% of the SGRY cases (Gram Sevak data) against 33.3% of the

EGS cases. This was evident from the data collected from Talathis

and Mukadams. As the employment of contractors, machine and

material component increases, the benefits and transfers to the poor

workers decreases. This was higher in SGRY.

In case of both the EGS and SGRY sites illegal involvement of

big contractors was observed. However, the general trend is that the

EGS works were more accessible to the rural poor than SGRY. In

33.33% SGRY cases, due to the involvement of the contractor

middlemen, there was almost no room for the poor sections to get the

employment.

Regional Variation: Involvement of contractors and middleman

was observed and middleman in all the three regions. However, the

219

219

involvement of big outsider contractors was highest (20.83%) in

developed regions, followed by semi developed regions (8.33%) and

less developed regions (4.16%). Involvement of small contractors

with less participation in the work was observed more in less

developed regions. As reported by the Mukadams point of view the

number of no contract works were 3 in developed region, 4 in semi

developed region and 3 in lees developed region. On 50% of the EGS

projects and 33.33% of the SGRY projects any kind of contractor was

not involved. (See Table 5.17)

Table 5.17

Percentage of the work given to big outsider contractor

Development Category Total Percentage

of the work

on big

outsider

contract

Developed Semi

Developed

Less

Developed

1 0 0 1

1 0 0 1

0 1 0 1

0 1 0 1

0 0 1 1

100%

Total 2 2 1 5

1 0 0 1

1 0 0 1

1 0 0 1

75-99

Total 3 0 0 3

0 1 0 1

0 0 1 1

50-74

Total 0 1 1 2

0 0 1 1

0 0 1 1

25-49

Total 0 0 2 2

0 1 0 1

0 0 1 1

1-24

Total 0 1 1 2

1 0 0 1

1 0 0 1

0%

1 0 0 1

220

220

0 1 0 1

0 1 0 1

0 1 0 1

0 1 0 1

0 0 1 1

0 0 1 1

0 0 1 1

Total 3 4 3 10 Source: The primary data obtained from Mukadams.

On EGS and SGRY worksites 100% use of contractor was

observed by Mukadam in all regions; developed (16.66%

worksites), semi developed (16.66% worksites) and less developed

(8.33% worksites).High involvement of contractor (i.e. about 75 to

99%) was more visible in developed region only (25.00%

worksites). Low participation of the contractors (i.e. below 25%)

was observed in semi and less developed regions (8.33% each).

(See table 5.18)

5.2.6 Selection of Worker Beneficiaries

a) Selection of workers: Social Inclusion and Social

exclusion:

Measuring social exclusion is difficult task. However, Arjan de

Haan (1997) believes that it is possible to measure social

exclusion and to develop multi dimensional aspects of

deprivation. Arjan de Haan (1999:5) clarifies that, “the central

definition of the notion of exclusion stresses the processes

through which people are being deprived, taking the debate

beyond descriptions of merely the situation in which people are.”

Thus, to identify areas of social exclusion one has to look at the

hurdles, gaps, forces and inabilities in the process of inclusion in

social networks in general and particularly in the

implementation of PEPs.

221

221

Let us see how caste, class, gender, region and other socio-

economic parameters played their role in social inclusion and

exclusion of the workers and the beneficiaries.

i) Female Participation in EGS and SGRY:

Averages of female participation from the data collected for

the study reveal that female workers were very less in number in

both EGS and SGRY schemes.

EGS: There were two data sets regarding the percentage of

female participation among the EGS. The sampled data revealed

that among the sampled workers the 15% participation of women

workers.

However, when the rates of female participation was

calculated on the basis of total female workers working on all the

12 EGS worksites, the percentage of female participation was

found to be around 74.9%. Why it is that female participation was

low at some specific worksites?

The use of contract labour and involvement of big contractors

with their own hired labour, were the main reasons for decreased

participation of female workers on EGS worksites.

SGRY: In general terms, considering the total number of workers

working on the SGRY worksites (not only from the sampled sites)

female participation in the labour force of SGRY works was

26.25%. Average female participation on EGS sites was 47.91%

against 26.25% on SGRY projects.

In case of five sampled villages women were totally excluded from

the SGRY works. There were several case specific reasons for

that. SGRY works in four villages were given to outsider big

contractors. These contractors used their own men for the EGS

works. Women were totally excluded from the works. SGRY

works of well construction were undertaken in two of the villages

222

222

where only men were employed who were professional well

construction contractor workers. They thought women were not

required in this work. Low participation of women in SGRY was

clearly found contradictory to the guidelines that specifically

favourable for female participation by reserving their quota i.e.

30%.

Regional Variation: Average female participation in case of

developed and semi developed belt was surprisingly higher on the

EGS sites (25% and 15.38% respectively). But Female

participation in semi developed and less developed areas was

higher in SGRY works (22.22% and 33.33% respectively). (See

table 5.18)

Table 5.18

Averages of female participation data

Development

category

Total

Workers

Female

workers

Female

participation

on EGS in %

Total

Workers

Female

workers

Female

participation

on SGRY in %

Developed 20 05 25.00

10 01 10.00

Semi

Developed

13 2 15.38 09 02 22.22

Less

Developed

18 1 5.55 15 05 33.33

Total 51 8 15.68

34 8 23.52

There were some noteworthy case stories about this from the field.

Two of them are given as below-

Case No. 5.3: Contracts and women: A women worker from a

village complained that under both EGS and SGRY women

worker and older workers have declining employment protection

since the gang of workers dealing the contract / task work, avoid

women and elders to maximum the work and in turn maximum

the returns.

223

223

Case No. 5.4: Skilled works and women: SGRY have tendency

to generate more skilled work than EGS and thus without such

specified skills women workers are kept aside. For example-

SGRY works in few villages and many other works like well

construction and building construction works hardly provided the

working opportunity to women workers.

ii) Caste System, worker’s inclusion and their

participation in PEPs.

EGS: The caste system in India and economic inequality has

clear association with each other. This is especially true in rural

sections of India. Significant number of the workers (both on EGS

and SGRY worksites) belong mainly to the backward castes. The

backward castes and tribes had almost no problem in inclusion in

the workforce of EGS and SGRY.

There have been very negligible cases of fighting among the

members of different castes in getting EGS works. The castes like

Maratha, Vanjari, Mali, Dhangar were very rarely observed on

EGS sites. There were several reasons for that. First, they had

better land access. Second, they were power holders in Developed

and Semi developed areas. Third, they are better off people and

least interested in manual works outside their farms. The

sample comprises of only three workers from these castes.

SGRY: Generally, the local workers belonging to lower castes and

tribes were present on PEPs. Caste composition of the SGRY

workers was little different. Higher rate of outsider workers did

change the caste composition of workers on SGRY sites. Two

workers belonging to Dawar caste were working on SGRY work

in the developed region. (See the case no. 5.5)

224

224

Case No. 5.5: Outsider Workers brought from Labour

Market

The two Dawar workers, migrated from Madhya Pradesh were

working on a SGRY work project in one village from developed

region. They did not know about SGRY. They readily accepted the

job which was giving assurance of work for more than a month

and above Rs. 150/- wages per person per day.

The labour contractor cum Mukadam admitted that the workers

were brought from labour market and said that, bringing outside

workers was inevitable since local labourers were not willing to

work there.

Regional Variation: More than 80 percent of the total EGS and

SGRY workers in the sample were tribal. Around 5 percent of

them were from dalit castes and the other constitute from the

middle castes and nomadic tribes. Among tribals, Mahadev Kolis

(42.68%) and Koknas (28.2%) were the prominent tribals mostly

situated in less developed region. Their higher level of inclusion

was obvious for the reason that they have poor land access in the

Nashik region. Koknas, Thakurs and Warlis were the tribes with

relatively better land access. (See Table 5.19).

225

225

Table 5.19

Caste/Tribe/Minority composition and participation of

Workers

Scheme

No.

Caste/Tribe/

Minority Development Category Total

Developed

Semi

Developed

Less

Developed

Maratha 0 0 1 1

Vanjari 2 0 0 2

Dhor 1 0 0 1

Kokna 4 1 5 10

Mahadev Koli 7 9 7 23

Warli 1 0 4 5

Thakar 1 1 0 2

Vadar 0 2 0 2

Bhill 1 0 1 2

Mang 1 0 0 1

Lonari 2 0 0 2

EGS

Total 20 13 18 51

Vanjari 2 0 0 2

Nav Baudhha 1 2 0 3

Kokna 0 1 13 14

Mahadev Koli 4 6 2 12

Dawar 2 0 0 2

Muslim 0 1 0 1

SGRY

Total 10 9 15 34

Regional Variation: The tribal workers were mostly

representing the semi developed and the less developed areas.

While as most of the other castes were representing the

developed and semi developed areas.

b) Wages and Foodgrain gains to workers

EGS: Wages to the workers on EGS and SGRY are paid partly in

cash and partly in the form of food grains. On an average, EGS

workers were comparatively better paid.

On an average, the EGS workers got wages per day at the rate of

Rs. 56.35 (including the amount of foodgrain). It was better than

the scheduled rates under minimum wages which was Rs. 47/- for

226

226

the Nashik region during the period of this research. The highest

wage rate the worker under EGS received was Rs. 150/- per day

and the minimum was Rs. 28/-. The machine drivers and skilled

workers usually get highest returns. The lowest paid workers

received fewer wage because they were working in gangs and

sometimes the labour contract fails to yield the desired wage rate.

Agency officers hold that, those who work less receivedless

amount as wage. EGS wages were generally based on the task

work wage system and not daily wage system. It is important to

note that a large number of the workers (86.2%) working on the

sites did not receive payments in the form of foodgrains.

Table 5.20

Daily average wages to workers including foodgrain

Sex Total Daily average wages

including FG Scheme

Male Female

SGRY 00 01 01 No payment in Cash

Total 00 01 01

EGS 01 01 02

SGRY 01 00 01

20-30

Total 02 01 03

EGS 05 00 05

SGRY 01 01 02

31-40

Total 06 01 07

EGS 17 06 23

SGRY 06 03 09

41-50

Total 23 09 32

EGS 06 01 07

SGRY 07 03 10

51-60

Total 13 04 17

EGS 05 00 05

SGRY 04 00 04

61-70

Total 09 00 00

EGS 04 00 04

SGRY 01 00 01

71-80

Total 05 00 00

EGS 02 00 02 81-90

Total 02 00 00

227

227

EGS 01 00 01

SGRY 02 00 02

91-100

Total 03 00 00

EGS 01 00 01 101-120

Total 01 00 00

SGRY 04 00 04 121-150

Total 04 00 00

EGS 01 00 01 Not Applicable/

Salaried worker Total 01 00 01

SGRY: Average wages to workers, including the amount of

foodgrain, under SGRY were at the rate of Rs. 70.70 per day. The

highest wages paid under SGRY were at the rate of Rs. 150/- and

the lowest was at the rate of Rs. 32/-. On this issue of wages

SGRY was better paid.

This is because the higher number of skilled and contract

works under SGRY increased the rate of wages in case of SGRY

workers.

The four skilled workers, who worked on SGRY works received

highest wages (i.e. between Rs. 121/- to Rs. 150/-). 86% of the

workers from EGS and 64.7% from SGRY reported that they did

not receive food grains as a part of their wages and received

wages only in terms of cash. The maximum foodgrain they

received was 5kg and the minimum 2 kg. One of the responsible

respondents informally told the researcher that in his SGRY

project the workers did not receive wages or food grain, but

instead, rather forcefully they were given the material required

for toilet construction.

Regional Variation: The workers from the developed region

received average wages under EGS (including the amount of food

grain) at the rate of Rs. 58.68 as against SGRY at the rate of Rs.

73.55. The workers from the semi developed regions received

228

228

average EGS wages at the rate of Rs. 61.57 as against SGRY at

the rate of Rs. 96.0. In the less developed region workers received

EGS wages of Rs. 58.35 against SGRY wages of Rs. 52.13.

The highest wage earners were the SGRY workers from the

semi developed areas. This was mostly due to the higher

involvement of big outsider contractors and due to the higher

machine use there. Involvement of contractors increases

involvement of skilled workers and thus those workers generally

receive higher wages. Higher level unofficial contracts on the

sites, however, decreases the work opportunity or mandays

generation under the schemes. Workers of both EGS and SGRY

from less developed areas received lowest wages. (see table Table

5.21)

Table 5.21

Averages wages to workers

EGS wages in

Rs.

EGS wages

in Rs.

Developed areas 58.68 73.55

Semi Developed

areas

61.57 96.00

Less Developed

areas

58.35 52.13

Many studies and the World Bank Report published in 1998

hold that wage employment programmes based on PEPs have

most effective potential to reach the benefits to the poor, both

directly and indirectly. Direct benefits to the poor go in the form

of wages and food grains. Both of these two factors indicate direct

income gain. The workers from the sample villages selected under

present study (EGS and SGRY sites) did receive wages that

helped to generate income but the picture is rather ambiguous.

The calculations of the wages and food grain they received are

229

229

difficult to measure. The wages were paid on irregular basis, on

the criterion of work the workers did and the measurements

made by the implementing officials. The calculations made on the

basis of work days they worked on and the amount of Rupees and

the valuation of the amount of Food grain they received in Kgs.

Thus, the averages of the amount of wages plus value of Food

grain was roughly used for the assessment and analysis of the

income gains.

c) Difference observed in the delivery of wages and

foodgrains:

EGS and SGRY: There was no age bias as such while delivering

wages and Food grain. But gender and skill bias was observed

while delivering wages.

Minimum and Equal wages to male and female workers, is the

norm firstly incorporated in EGS and later on also become a

routine in PEPs. At least at the rate of Rs. 47/- per worker per

day should be given to by these norms. Against this norm,

however, 13.72% workers from EGS and 8.82% SGRY workers

reported that they received wages less than at the rate of Rs. 40/-.

Clearly, in these cases the norm of minimum wages was not

followed. All the 16 female workers from the sample from both

EGS and SGRY received wages including the amount of the food

grain not exceeding Rs. 60/-. However 24 male workers mostly

engaged in relatively better skilled jobs, and contracted skilled

workers received wages between Rs. 60/- to Rs. 150/-. SGRY

workers, since they were engaged more in skilled and contract

works, earned more than that of EGS workers. But as far as

unskilled work is concerned, EGS workers got better wages.

230

230

d) Promptness or Delays in wage distribution

EGS: Delays in paying wages and food grains to workers on PEPs

have been considered as negative side from the worker’s point of

view.

Nobody from EGS workers received wages in stipulated 15

days time. 27.1% of the EGS workers from the sample received

much delayed payments and 17.64% had to wait for more than a

month for the wages.

SGRY: More than 50% of the workers from SGRY sites said that

they received wages in stipulated 7 days time. 17.6% SGRY

workers from the sample received very delayed payment of wages

and waited for more than a month. Delays in payments are

comparatively less in cases of SGRY for relatively faster

availability of funds. Nine EGS workers and 12 SGRY workers

had to wait for more than a month to get food grains funds in

hand but waiting for the food grain is specialty of SGRY. The

Sarpanch, Gram Sevaks said the government machinery to make

available food grain to the workers is seriously faulty and time

taking. Delays in payments and food grains are coupled with the

delayed workers’ work reports and measurements.

Regional Variation: Under EGS relatively prompt payment of

wages were observed in semi developed areas. 11.76 % of the

workers who received timely wages were from the semi developed

areas as against 2.35% from the developed areas and 5.88% from

less developed areas. There was no significant regional difference

in delays in delivering foodgrains to workers as a part of

payments.

231

231

Table 5.22

Delays in payment of wages to workers

Development Category Total Whether

delays in

wages

Scheme No. Developed

Semi

Developed

Less

Developed

EGS 00 02 00 02 1-8 Days

Total 00 02 00 02

EGS 01 04 00 05

SGRY 01 06 05 12

9-15

Total 02 10 05 17

EGS 11 07 11 29

SGRY 01 00 04 05

16-30

Total 12 07 15 34

EGS 08 00 06 14

SGRY 00 00 03 03

31-60

Total 08 00 09 17

SGRY 00 00 03 03 More

than 60 Total 00 00 03 03

SGRY 08 03 00 11

EGS 00 00 01 01

No

delays

Total 08 03 01 12

EGS guidelines expect that Sarpanch, Gram Sevak, Talathis

must be present while distributing wages. Actually only one

Sarpanch (out of 12) and 2 Gram Sevak (out of 12) were remained

present regularly while distributing wages. Only one Sarpanch

and one Gram Sevak did regularly remain present while

distributing foodgrains to EGS workers.

On SGRY sites workers from semi developed areas received

relatively prompt wages.

e) Amenities provided on work sites

EGS act of 1979 prescribed that amenities to its workers must

be provided almost equal to the factory workers. Potable water,

crèches for the children coming with working mothers, sheds,

temporary accommodations for the outsider workers, free first aid

and medical facilities and half the daily wage rate for injuries; in

232

232

case of death at the work-site, Rs. 50000/- to the next of kin of the

deceased; in case of disablement, an ex-gratia payment,

maternity leave for female worker were the basic amenities that

were supposed to be provided at work sites. Expenditure involved

for providing these facilities should be made out of the non-wage

component under the programme. EGS was applauded for

providing such amenities that were close to factory act provisions

for the oragnised factory workers. Most of these amenities were

also needed to be provided to SGRY workers.

EGS: However, there has been very serious apathy and sheer

negligence by the agencies and the implementers involved in EGS

and SGRY in providing these amenities to the workers. 30 EGS

workers out of 51 (58.82%) said that they did not receive any kind

of amenities on working site, not even potable water.

Ten of 12 Gram Sevaks (83.3%) did not even know about the

amenities to be provided on EGS worksites. One of the remaining

two Gram Sevaks said that, there were no amenities at all

provided to EGS workers and one said only water was provided.

SGRY: 76.47% of the SGRY workers said that they did not

receive any of the amenities on working site including potable

water. These works were closer to the village houses and the

implementers thought that water would be easily available there

around. (see table 5.23)

233

233

Table: 5.23

Specification of amenities to onsite workers

Nature of Amenities Frequency Percent

No Amenities 59 69.4

Only Water 17 20.0

Water + Shelter 6 7.1

Water + Medicine+Shelter

+Tools 1 1.2

Crushes + Water 2 2.4

Total 85

100.

0

Regional Variation: Baring few exceptions with regard to some

amenities which were provided on some sites, no significant

variation in this regard was observed in terms of level of

development.

Table: 5.24

Regional variation in amenities to workers on sites

Development Category Specification

of Amenities Scheme No.

Developed Semi

Developed

Less

Developed

Total

EGS 13 6 11 30

SGRY 7 9 13 29

No Amenities

Total 20 15 24 59

EGS 5 7 0 12

SGRY 3 0 2 5

Only Water

Total 8 7 2 17

EGS 0 0 6 6 Water +

Shelter Total 0 0 6 6

EGS 1 0 0 1 Water +

Medicine+

Shelter+Tools Total 1 0 0 1

EGS 1 0 1 2 Crushes +

Water Total 1 0 1 2

In general terms, we can say, amenities at work were almost

absent except drinking water. Water, the basic amenity, was not

234

234

even made available in few cases. Shelter for shed was observed

only in 6 workers. In general, EGS is relatively better in

providing amenities to the workers. EGS implementers at least

knew about the provision of such amenities but SGRY

implementers generally did not know much about it.

5.2.7 Intervention of Political leaders and stakeholders:

Involvement is nothing but the undue intervention of political

leaders and stake holders in demanding, sanctioning and

implementing the worksites. For example; -1) giving priority to

one’s own village or region or caste while demanding, allotting

the EGS or SGRY (first stream) works, 2) Influencing the

worksites and its implementation to facilitate or satisfy the

interest of one’s own party men, kins or class-castes etc.

Implementing officers from Minor Irrigation, Agriculture did

often complain about such undue interventions. They believed

that this was the most unpleasant part of their duty.

EGS: Political representatives at various levels are directly or

indirectly associated with EGS implementation. EGS being a

State Government Scheme, politicians got some responsibilities

and rights regarding framing, planning and implementing EGS.

They are--1) Each and every MLA, MLC and MP gets some

authority and control over the governmental programme carried

out in his electorate. 2) Some political leaders like MLA and MLC

could get opportunity to be the members of State and District

EGS Councils and they can play role in policy decisions and state

level planning as well as supervising of EGS activities. 3)

Political representatives from various levels for example MLA,

M.P., members of Z.P. and Panchayat Samiti are part of EGS

committees at District and taluka level. 4) Political leaders

including Sarpanch from the villages can put demands for EGS

235

235

works on behalf of their voters. 5) Political leaders can start or

demand enquiry of EGS officers by charging allegations of

malpractices and corruption.

The cases studied in this research revealed that when EGS

demand makers were weak, unorganized and experienced

difficulties in putting their demands, they often used to go to the

politicians. Political interventions in EGS projects were observed.

Fair political involvement was also observed in both of the

schemes. Establishing patron client relationship with the village

masses benefits them so that they could get electoral footage.

Political leaders, leaders of labour organizations, Panchayat

Samiti and ZP members, MLAs do play such role in both EGS

and SGRY.

However, in recent times there has been change in this regard.

The political will regarding EGS or SGRY implementation has

been declining sharply. Interventions (both positively and

negatively directed) by the politicians are declining remarkably.

Case No. 5.6: Connections to tehsil office and towns works

The local elites from one tribal village were planned to grab

benefits of Jawahar well scheme under EGS. The real poor, their

preferences were kept aside and they brought sanctions for the

two Jawahar wells on their name. Local leaders and their

connections with the MLA, ZP and Panchayat Samiti members

are interested in seeking the benefits of the schemes. The local

villagers said four to five times a week, these so called leaders

visit the Taluka Panchayat Samiti or Tahsil office and pass their

time in maintaining the connections.

236

236

SGRY: Political interventions in SGRY were more at local levels.

In SGRY first stream works, ZP and Panchayat Samiti members

do have any role to play and intervene.

Case No. 5.7: Dilemma between need and democratic

choice

One of the Shramajivi activists got elected as Panchayat Samiti

member. He said he did not know that SGRY I stream works

were allotted to certain villages of Panchayat Samiti member’s

choice. In allotting such works to certain villages, the members

see their personal stakes and the whole selection process were

thus politically biased.

Regional Variation: Political interventions did not have

significant regional variation. Such interventions were found

everywhere. In developed and semi developed regions their extent

might have been little higher.

Case No. 5.8: Double Game

The political leader from a village who also happened to be the

member of Taluka Panchayat Samiti opted for the nearing village

for big SGRY work under the first stream. When asked as to why

he selected the other village instead of his own village or the

village that would provide political mileage, his answer was

interesting. He said, the nearing village that he selected for water

conservation project was on the higher lands and the percolated

water would provide the benefits to his own village. He played

double game. On one hand, he posed himself free of bias in

selecting the village and on the other; he managed to benefit his

own village interests.

237

237

Case No. 5.9: Political power and exclusion

One tribal village from semi developed area from one of the

sampled talukas was full of mixed caste-tribe categories. The

political leaders of Kokana tribe who had good contacts at

Panchayat Samiti office managed to earn EGS work on labour

contract. All the workers selected for the contract were Kokanas.

The Mahadev Kolis, the real poor from the village were excluded

from the work despite the Sarpanch women from there was

Mahadev Koli.

It is pertinent to note that, practically intermediaries have

emerged in between people and government for the reason that

the workers cannot get EGS work on their own strength as per

their demand easily. Thus, they have either go to the

intermediary like political leaders or they have to keep constant

follow up for getting the EGS work.

It is very difficult for the poor, tribals and women to go to the

Taluka place every now and then and keep follow up with agency

officer or with Tahsil office. They cannot afford spending time and

money for that. They even do not know how to keep follow up and

how to meet the officers. As a result, intermediaries get

opportunity to exploit the conditions in their favour.

5.2.8 Role of Agency, agency officers and the Implementers

General strengths and weaknesses as well as specific actions of

the implementing agencies do influence the performance of the

schemes. Extra ordinary contribution by the implementing actor

or agency, which would be unexpected in normal circumstances

need to be focused.

EGS and SGRY: To understand the dynamics of

implementation of PEPs one must study the interactions among

238

238

the village leaders, officers and agency men. Gram Sevak,

Talathis, Sarpanch and Asst. Sarpanch were having better

liaison with the agency men. They admitted that they frequently

try to maintain good relations with the agency men. Village

elites and especially those having better land access too take keen

interest in maintaining relations with the agency men. These

relations help them to bring the works under either of the

schemes and see that they benefit most from it. One such

benefitted elite from the developed belt remarked that, the

agency men too were in search of safety pockets and safety

supporter from the villages under their area. PEPs and especially

EGS is very complicated scheme where anybody with little

knowledge of scheme regulations could catch the implementers.

‘Safe pockets’ technique of the agencies has been observed and

reported by some of the researchers who did field work on EGS

sites.

The stakeholder elites from the villages who sought works

especially promoting their agricultural benefits found to be the

unofficial supervisor. (Sony Pellissery called them unofficial

owners of the sites) These stakeholder elites thus acted handily

for the agency men who kept them engaged in multiple works at

a time and also did work in short of muster clerks of lowest

agency men.

The implementing agencies (e.g., line Ministries of the

government, private contractors, nongovernmental agencies or a

combination of the above) and the main office bearers involved in

the onsite implementation also influence how much benefits the

program transfers to the poor.

239

239

Case No. 5.10: Role of Agency officer is important

Agency officers do influence the work positively or negatively. In

some pockets, some agency officers have good reputation and

workers join those works without hesitation. Some Agriculture

Officers have good reputation among the workers from their

respective belts. In case of a village from one Taluka, when the

researcher visited the just started EGS worksite, he observed

many workers working there did not know about the payment

details. The researcher found it strange. The workers said, “its so

and so Tatya’s work. We do not bother about the rates because he

will pay us what we deserve and we trust him”.

S. Liberman’s onsite observations based on the interviews of

EGS implementing officers from Pune and Ahmednagar are

worth to quote here. Liberman has noted, “ In fact, apart from the

general principles set out in the (EGS) Compendium, the field

staff appear to have been left largely to their own devices in

handling everyday matters and in coping with the crisis that

arise in EGS operation. It would seem that the success in

implementing EGS projects depends on how field officers respond

to circumstances in which they enjoy some discretionary powers

but are at the same time susceptible to various administrative

and political pressures.” The EGS implementing officers in

Nashik district experienced such crisis conditions of pressures

and onsite problems. The most threatening part of their job was

the complexity of EGS regulations of implementation. They said,

despite taking all the precautions and abiding the regulations of

implementation, some lacuna, errors are bound to happen. Many

of lacunas on the site for example delayed payments are part of

broader bureaucratic mechanisms. Any authority, journalists,

240

240

politicians can catch them there. EGS and SGRY to some extent

seemed to make the implementing officers vulnerable for

blaming, for pressures and action against them.

5.2.9 Which is better implemented PEP?

EGS: Among the respondent’s categories, only Talathis and

workers thought that EGS was better implemented than the

SGRY. They think EGS has comprehensive mechanisms and

structure to help the rural poor and to strengthen the rural

infrastructure. Workers were not happy due to the delayed

payments and mistimed works under EGS but they said EGS,

provided them handful employment assurance, especially in

adverse conditions.

SGRY: Sarpanchs and Deputy Sarpanchs from the 12 villages

did think that SGRY was better implemented than EGS. This

may be due to their involvement in the scheme. SGRY received

58.3% votes from Sarpanchs and Deputy Sarpanchs and EGS got

33.3% of the votes from Sarpanches. 8.3% that is, one Sarpanch

could not judge which was better.

The most important reasons they advanced for their

judgments were varied. Some said ‘SGRY was better accessible to

the villagers’. Some others said, ‘it was locally managed’ so that

they could decide the nature of the work as per their needs. Those

who opted for EGS said, ‘it was better funded and thus provided

bigger works’. It was better in generating employment on larger

scales. Still some others said, ‘there was less politics in it and

thus it could reach to the commons’.

Regional Variation:

On scales of implementation, Sarpanches and Deputy

Sarpanchs in general and from semi developed and less developed

241

241

areas in particular, preferred SGRY than EGS. Gram Sevaks

from all the regions said SGRY was better implemented.

Table: 5.25

Which is better implemented Scheme?

Which is better

implemented Type of Respondent

EGS SGRY Cannot

say

Total

Sarpanch 4 7 1 12

Deputy Sarpanch 4 7 1 12

Gram Sevak 2 10 0 12

Talathi 10 1 1 12

Total 20 25 3 48

The workers from semi and less developed areas prefer

EGS for longer and better employment opportunities.

A General Observation of EGS-SGRY Implementation

General strengths and weaknesses of the schemes, as well as

specific actions of the implementing agencies do influence the

implementation of the schemes.

Ground level contextual issues like social, economic, cultural,

political interests of the stakeholders do influence the

performance of the schemes. The state of developmental levels of

the regions and politics and economics associated with that also

influenced the scheme performance.

Historical factors that shaped the ground level contextual

factors also shaped the performance. The villages where EGS and

SGRY works were frequently undertaken did well in

implementing the scheme. The capabilities and experiences of the

implementers and the workers also raised the quality of

implementation.

242

242

EGS projects have been observed to be relatively superior to

SGRY projects. In a number of ways, the EGS better meets the

needs of poor rural people for manual wage work and especially

for work at times when no other employment is available. The

most noteworthy reasons include a) SGRY work is driven by the

limited annual budget cycle rather than employment needs and

thus produced meager employment opportunities; b) SGRY

funding is spread almost evenly across all areas on population

and backwardness basis and they cannot satisfy the local

employment needs as well as the size and quality of

infrastructure it produces. c) First Stream SGRY funds are

concentrated very heavily on politicized Panchayati Raj

interventions. Their funds reached to less than 5% of the villages.

d) Politics around EGS was on the higher levels. However, it did

not influence much in the inclusion and exclusion of the workers

on the worksites. e) Involvement of contractors and machines was

relatively less in EGS despite the works under EGS were bigger

in size.

SGRY on the other hand did well in several aspects such as

better wages, timely wages, fewer gaps, better quantity of

foodgrain distribution. The villagers think that diverse local

needs like Gram Panchayat office building, kitchen cabinet for

the school (useful for Mid Day Meal preparations) and latrines

could be met under the SGRY projects. Implementation of the

SGRY however, found a difficult responsibility to some of the

Sarpanch and Gram Panchayat members. Without training and

sufficient information to them SGRY implementation could not be

systematic and fruitful.

243

243

5.3 Section Three- A Comparison of Performance of EGS

with SGRY in Nasik District

We already defined in the first chapter that ‘Performance of

the scheme’ is a qualitative and quantitative output of a

particular scheme associated with its results towards achieving

the intended objectives. The performance indicators of the

qualitative aspects of the scheme that include- targeting,

implementations, quality, quality of assets, benefits, leakages,

distortions, diversions, capabilities and relative deprivations.

It is not easy to come to the generalised conclusions about the

performance of the two schemes from the limited study of 12

sample villages. Performance assessment is more than the cost

benefit analysis, on which the economists would rely. While

evaluating the performance of the two schemes in comparative

perspective, we have raised some questions and asked them to

the respondents who were workers and some of others who

involved as implementers.

The set of questions which the researcher asked while

assessing the performance of the schemes include following

questions:

1) How did the institutional framework, design of the scheme

pertaining to the administrative mechanisms, financial

provisions etc. worked in favour of the poor and for their

inclusion? Scheme design determines institutional capability

of the scheme.

2) What institutional arrangements generate employment

opportunities and transfer them to poor? For example in case

of SGRY, its design of democratic decentralization, local

management certainly influences levels of participation of the

244

244

poor and in case of EGS the right to work was the main

outstanding feature. Did these schemes benefit the rural poor?

3) What was the quality of assets created under these schemes?

How far these assets have ability to generate the chain of

employment through development?

4) What are the direct and indirect benefits to the village

community in tackling poverty, unemployment and seasonal

adversities/vulnerabilities and migration?

To answer these questions, the data from the field was

analysed on the basis of following parameters:

Objectives and Design of the schemes, Funds allocation to the

schemes, Income gains through wages and foodgarin, Punctuality

of wages distribution, Amount of machine use replacing the

labour participation, Leakages and malpractices, Number of

mandays generated, Nature of monitoring and vigilance and its

impact, Completion of the work in time and delays-reasons for

delays, Quality of works, Level of Utility of works, Who benefitted

from the assets, Relevance of the scheme in need satisfaction,

Future profits of the work/asset, Outputs for the village.

5.3.1 Objectives and Design of the schemes

The program features (especially the level of the wage rate

and the timing of the program) and the design features

(implementing agencies and the institutional framework)

together determine the program’s efficacy as an anti-poverty

intervention and its cost- effectiveness. Legislative Provisions

and rights involved in the schemes also do influence the scheme

implementation and performance.

245

245

A) Objectives of the schemes:

As far as the objectives of the two PRPs are concerned they are

not much different. But the provisions and characteristic features

of the two schemes were different.

EGS: EGS is more comprehensive for having wider objectives of

employment generation that must provide gainful results to the

workers and productive assets to the economy of the state. A

guarantee aspect of the EGS assuring to provide manual work is

another important aspect that empowers the workers targeted

under it. Targets like mitigation to drought, floods and conditions

of scarcity were also emphasized. (for more details see

Sargrantha 1989:2)

SGRY: The SGRY has two sets of objectives- First, the primary

one is to provide additional wage employment in all rural areas

and thereby provide food security and improve nutritional levels

and secondary one is the creation of durable community, social

and economic assets and infrastructural development in rural

areas (SGRY Guidelines:2001:2).

Regional Variation: There no regional dimension in their

objective and provisions but both of the schemes intended to focus

more on the areas of less developed, backward sections. SGRY

stood better here since 22.5% of the annual allocation under first

stream of the SGRY both at District and Block levels were

embarked for the individual beneficiaries of the SC and ST

families living below poverty lines and 30% employment

opportunities were reserved for women (SGRY

Guidelines:2001:3).

B) Nature of works and developments:

Not much difference is observed in the nature of works in EGS

and SGRY. Antecedents of SGRY were more focused on building

246

246

construction works. However, SGRY although insisted on the

water and soil conservation works it undertook more building

construction works.

The institutional framework says EGS can go for big works

but SGRY cannot take big works like watershed development.

EGS did well in constructing soil and water conservation works.

Plantation and forest development works done by EGS is its

specialty. The nature of works under SGRY is required to be such

that they could be completed in one or two years, thus watershed

development projects require a large period to get such projects

completed.

Plantation and forest development works under EGS were

taken up in developed and semi developed areas. EGS and SGRY

projects from less developed belt were more concentrated on soil

and water conservation.

EGS has performed better in producing assets that would

benefit the villages in the long run.

5.3.2 Funds allocation to the schemes –

The size and the funds definitely affect the performance of

these PEPs. Quality and size of the assets generated and the

employment generation heavily rests on the funds.

EGS: EGS is demand driven for it is difficult to set out a budget

for particular village. We can judge the fund allocation from the

total expenditure at District and Taluka level (see Section II of

chapter III for details). But Funds under EGS were obviously

larger than SGRY. All of the EGS works under the sample were

having funds or budget more than Rs. 1 lacks. The data collected

from the field shows that EGS works were relatively big works.

SGRY: SGRY in comparison with EGS were having allocation of

meager funds. Only 16.6% of the SGRY works were having funds

247

247

higher than Rs. 1 lac. Fund allocation for SGRY works, especially

from the second stream was smaller in size. The funds are given

for the whole year, mostly in installments and no one can get

more funds beyond the limit for the same year. SGRY- I st stream

works were close to EGS funds but these works were very rare to

get opened. Only one village out of 12 could get SGRY – I st

stream work during the study period.

The nature of work required under SGRY should to be such

that it could be completed in one or two years, thus on non

economic terms too, big projects like watershed development were

not possible. So on these line EGS has better performing abilities.

Regional Variation: The availability of SGRY funds were

largely depend on the population of the village. Smaller villages

with low population reduce the funds still further. The villages

from the less developed regions full of people belonging to SC-ST

categories, were having lower population and thus could get

lower funds under SGRY in Nashik district. The performance of

the SGEY in these small villages was hampered due to less

availability of funds. No village from the less developed areas

received SGRY funds more than one lac.

5.3.3 Income gains through wages and foodgarin

PEPs are generally criticized for wages paid to the workers

which are lower than the wage rate, or minimum wage decided

per person per day ( Rs. 47/- in the Nashik region).

What did the workers get while working on these sites? What

was the level of earnings? Did the earnings help the poor in

getting rid of their adversity? Let us see the findings of the

present study.

248

248

Wages to the workers

EGS and SGRY: The minimum wages rule is applied to both

the schemes but still in some cases wages were paid to the

workers which were below the level of minimum wages for

agricultural work (for Nasik it is Rs. 47/- per day). Around 30% of

the workers received wages blow the standard line of Rs. 47/-.

The implementing officers reacted to this fact saying “in piece

rate type work, we cannot guarantee the wages. Workers did get

what they deserved for. Their wages were bound to the

measurements of their work.”

There were 3.92% of the workers from EGS and 2.94% of the

worker from SGRY who received wages below Rs. 30/-. Again,

9.80% workers from EGS and 5.88% from SGRY received wages

in the range of Rs. 31/- to Rs. 40/-. Another 40.09% from EGS and

26.47% from SGRY received wages in the range of Rs. 41/- to Rs.

50/-. There was not much difference between the earnings of EGS

and SGRY workers between the range of Rs. 51 to Rs. 120/- . But

11.76% of SGRY workers earned more than Rs. 120/-. This was

striking. The picture of the earnings of EGS and SGRY workers is

rather confusing. Still, it apparently showed that the skilled

contract work under SGRY could deliver better wages than EGS.

So, on an average SGRY workers were paid better wages than

EGS and performed well in this regard.

Average Wages to workers, including the amount of foodgrain,

under SGRY workers were Rs. 70.70 per day. This is because the

higher number of skilled and contract works under SGRY

increased the wage averages.

249

249

Table 5.26

Wage Earnings in comparison: Workers

Daily average

wages including

FG

EGS

(workers

in

numbers)

EGS

(Workers

in %)

SGRY(workers

in numbers)

SGRY

(Workers

in %)

No payment in

Cash 00 00 01 2.94

20-30 2 3.92 01 2.94

31-40 5 9.80 02 5.88

41-50 23 40.09 09 26.47

51-60 07 13.72 10 29.41

61-70 05 9.80 04 11.76

71-80 04 7.84 01 2.94

81-90 02 3.92 00 00

91-100 01 1.96 02 5.88

101-120 01 1.96 00 00

121-150 00 00 04 11.76

Not Applicable

/Salaried worker

01 00

Total 51 34

Regional Variation: Regional variation was also observed in

the earnings. The workers from the developed and especially semi

developed regions earned more wages than the workers from the

less developed regions. The workers from the semi developed

regions received higher average wages. EGS wages they earned

Rs. 61.57 as against SGRY Rs. 96.0.

Table 5.27

Amount of daily average wages including foodgrain

Development. Category Total Daily average

wages

including FG

Scheme

Name Developed Semi

Developed

Less

Developed

SGRY 00 00 01 01 No payment

in Cash Total 00 00 01 01

EGS 01 00 01 02

SGRY 00 00 01 01

20-30

Total 01 00 2 03

250

250

EGS 04 01 00 05

SGRY 00 00 02 02

31-40

Total 04 01 02 07

EGS 09 05 9 23

SGRY 02 01 6 09

41-50

Total 11 06 15 32

EGS 02 02 03 07

SGRY 03 04 03 10

51-60

Total 05 06 06 17

EGS 01 03 01 05

SGRY 02 00 02 04

61-70

Total 03 03 03 09

EGS 00 02 02 04

SGRY 00 01 00 01

71-80

Total 00 03 02 05

EGS 02 00 00 02 81-90

Total 02 00 00 02

EGS 01 00 00 01

SGRY 02 00 00 02

91-100

Total 03 00 00 03

EGS 00 00 01 01 101-120

Total 00 00 01 01

EGS 00 00 00 00

SGRY 01 03 00 04

121-150

Total 01 03 00 04

EGS 00 00 01 01 Not

Applicable /

Salaried

worker

Total 00 00 01 1

5.3.4 The Punctuality in wage distribution:

Did the workers receive wages as per the guidelines of the

schemes? Were they paid promptly?

The workers and most of the implementers did not know the

standard guidelines and amount of standard minimum wages

and foodgrains to be given to the workers. The implementers,

however, instructed to pay the piece rate wages to the workers for

the type and quantity of the works completed.

251

251

EGS and SGRY: EGS norms say that the workers should be

paid their wages with 15 days of the work. (Ro. Ha. Yo.

Sargrantha: 8.3.8:89) SGRY norms say that they should be paid

within a week. (SGRY Guidelines: 3.4:8). The payment of wages

and food grain under EGS were relatively more delayed. The data

from the workers show that only 13.74% of the EGS workers and

majority i.e. 67.64% of the SGRY workers could get timely wages.

The statistical analysis shows that, 27.45% of the EGS workers

and 8.82% of the SGRY workers received payments very late (i.e.

is within 30 to 60 days) after the work. 8.82% of SGRY workers

complained for getting very late payment (i.e. after 60 days) after

the work.

Irregular and delayed measurements, red-tapism,

distributional blunders, were the typical reasons given by the

workers. The implementers on the other hand blamed the

complicated systems and procedure of releasing funds under

EGS.

SGRY had the same problems but relatively, it was better in

payments and delivering food grains for, having the funds and

food grains availability with the implementing agency. However,

SGRY Ist stream works were similar to the EGS works. (see table

5.2.30)

Regional Variation: Regional variation in late payments was

considerable. The data in the table shows that, 37.25% of the

EGS workers from developed region received late payments

against 13.72% from semi developed region and 33.33 from less

developed region.

Late payments in SGRY were very low proportion in case of

developed (3.94%) and semi developed regions (0.0%). But in less

developed region SGRY payments were late (29.41%). This was

252

252

striking. The ignorance of the Sarpanch and miss coordination

between Sarpanch and Gram Sevak were the major reasons for

this.

Table 5.28

Delays in wage Distribution to workers on EGS and SGRY

Development Category Whether

delays in

wages

Scheme

Name Developed Semi

Developed

Less

Developed

Total

EGS 0 2 0 2 1-8 Days

Total 0 2 0 2

EGS 1 4 0 5

SGRY 1 6 5 12

9-15

Total 2 10 5 17

EGS 11 7 11 29

SGRY 1 0 4 5

16-30

Total 12 7 15 34

EGS 8 0 6 14

SGRY 0 0 3 3

31-60

Total 8 0 9 17

SGRY 0 0 3 3 More than

60 Total 0 0 3 3

SGRY 8 3 0 11 No delays

Total 8 3 0 11

EGS 0 0 1 1 Not

Applicable /

Salaried

worker

Total

0 0 1 1

It can be said from the data that SGRY performed relatively

better with respect to the timely payment of wages and

foodgrains to workers.

5.3.5 Use of Machine and involvement of Contractors:

A) Use of machines

Use of machines and contractors has been considered as the

dark side of the PEPs. It not only encourages leakages but also

negatively influences the share of workers working under the

253

253

scheme. EGS and SGRY guidelines and objectives consider this

as a serious and most objectionable matter against worker’s

interests and their employment opportunities.

52.9% of the workers from the sample reported about the use

of machine. 20% of the workers did see JCB machines on the

worksites. Another 32.9% workers said they observed heavy legal

(like concrete mixer, road roller machines) and small machines

like simple Crain machine, tractors on the sites. Remaining

41.7% of the workers said there were no machines on the site.

(see Table 5.29)

Table 5.29

Workers observations regarding the use of machines

Level of Machine use Frequency Percent

JCB Machine 17 20.0

Legal Heavy Machine 6 7.1

Tractors and Trolleys 15 17.6

Crain, Fire-Blasting

machine 7 8.2

No Machine 40 47.1

Total 85 100.0

The general impression was that the use of machines was

relatively higher in SGRY worksites.

EGS: Machines are permitted under EGS. For example- Road

roller, water tankers are essential in road construction works.

Special permission can be taken for use of some machines in some

specific working condition. Data from Mukadam did reveal that

in 16.66% of the EGS works, occasional JCB machine was used.

In 16.66% EGS works, small machines were frequently used in

254

254

16.66% cases; occasional, small machines were used. EGS works

with no machines were 41.66%.

SGRY: There was more widespread use of illegal heavy

machinery, especially JCB earthmovers, to substitute for labour

in SGRY projects than the EGS. The data from the Mukadams

also showed that on 8.33% of the SGRY works frequently JCB

machine was used. JCB machine was occasionally used in case of

16.66% SGRY works. Frequent small machines (8.33%) and

occasional small machines (50.00%) were used in SGRY

worksites. EGS works with no machines were 16.66%.

Regional Variation: The data obtained from Mukadam did

depict that, the less developed tribal region was better in case of

machine use. There were no JCB machines used at all. Use of

small machines was also very low (16.66% cases). In semi

developed belt, however, use of JCB machines was highest

(33.33% worksites) and use of small machines was observed in

case of 83.33% worksites. Developed region did show moderate

use of machines, big JCB machines (8.33% worksites) and small

machines (33.33% worksites). Table 5.30 reveals the data from

the Mukadams.

Table 5.30

Amount of machine used

Development Category Amount of

machine

used

Name of

the

Scheme Developed Semi

Developed

Less

Developed

Total

SGRY 0 1 0 1 Frequent

JCB

Machine Total

0 1 0 1

EGS 0 2 0 2

SGRY 1 1 0 2

Occasiona

l JCB

Machine Total 1 3 0 4

255

255

EGS 2 0 0 2

SGRY 1 0 0 1

Frequent

Small

Machines Total 3 0 0 3

EGS 0 2 1 3

SGRY 1 4 1 6

Occasional

Small

Machines Total 1 6 2 9

EGS 2 2 1 5

SGRY 1 0 1 2

No

Machines

allocated Total 3 2 2 7 Source- the data provided by the Mukadams

Frequent and occasional use of JCB like big machines and

small legal machine was little higher in semi developed areas

than the developed and less developed belts.

Thus it can be said that there was not much difference in

machine-use in both of the schemes. But considering the size,

nature and funds available for the works, use of machine under

SGRY was higher despite strict regulations of banning all sorts of

machine. EGS however, permits some kind of machines (not

JCBs) that are required for specific works. Taking these points

into consideration, it can be inferred that EGS did better in terms

of relatively less use of machines on the worksites.

B) Involvement of Contractor-middleman

EGS: Task-work system is normal in EGS implementation but

unofficial contracts are not allowed in EGS. If the budget is

higher, the contracts can be given to Labour Cooperative

Societies and if the work is still bigger the tenders from

Government contractors (up to 10% of the total expenditure) are

invited and passed by following certain procedures. The

responses from the Mukadams revealed that, there were 8.3%

cases of EGS where 100% involvement of big outside contractors

was observed. In case of two EGS works (16.66%), higher

involvement (75 to 99%) of the big outside contractors was found.

256

256

SGRY: Under SGRY, contractors are not permitted to be

engaged for execution of any of the works under the programme

(SGRY Guidelines: 5.16.1:19). But still the involvement of

middleman or any other intermediate agency was more in

executing the works under the programme. There were 33.33%

cases of SGRY where very few from poor sections had chance to

get the employment.

The data from the Mukadams revealed that there were 33.3%

of SGRY cases of 100% involvement of big outside contractors (see

Table 5.31).

Table 5.31

Percentage of the work given on big contract

Percentage of the work on big outsider contract Name of

the

scheme 100% 75-

99

50-

74

25-

49

1-

24

0%

EGS 01 02 01 01 01 06

SGRY 04 01 01 01 01 04

Total 05 03 02 02 02 10

Source: Data obtained from the Mukadam respondents

The machines causing exclusion of the human labour was

obviously highest on those sites. In 8.3% SGRY cases, higher

involvement (75 to 99% involvement) of the big outside

contractors was found. However, small/part-time outsider

contractors were observed higher in EGS than SGRY.

As a result of this, the employment generation ability of the

schemes was curtailed. General trend is that EGS works are

more accessible to the rural poor than SGRY and thus EGS

performed slightly better than SGRY.

Regional Variation: Involvement of contractors and middlemen

was observed in all the three regions. Involvement of big outsider

257

257

contractors was highest (20.83%) in developed region. It was

followed by semi developed regions (8.33%) and less developed

region (4.16%). Involvement of small contractors with less

participation in the work was observed more in less developed

regions. Mukadams reported that the number of works where

there was given no contract were 3 in developed region, 4 in semi

developed region and 3 in lees developed region. (See Table 5.32)

Table 5.32

Percentage of the works on big outsider contract

Development Category Percentage of

the work on big

outsider contract

Developed

Semi

Developed

Less

Developed

Total

1 0 0 1

1 0 0 1

0 1 0 1

0 1 0 1

0 0 1 1

100%

Total 2 2 1 5

1 0 0 1

1 0 0 1

1 0 0 1

75-99

Total 3 0 0 3

0 1 0 1

0 0 1 1

50-74

Total 0 1 1 2

0 0 1 1

0 0 1 1

25-49

Total 0 0 2 2

0 1 0 1

0 0 1 1

1-24

Total 0 1 1 2

1 0 0 1

1 0 0 1

1 0 0 1

0 1 0 1

0 1 0 1

0%

0 1 0 1

258

258

0 1 0 1

0 0 1 1

0 0 1 1

0 0 1 1

Total 3 4 3 10 Source: Data obtained from the Mukadam respondents

5.3.6 Leakages and malpractices:

It is hard to collect data and find out proof of leakages and

malpractices precisely. An attempt was made to see how some of

these things happen.

High amount of leakages and malpractices were reported in

case of some of the sites. Both the schemes were to be blamed for

rampant corruptions and irregularities. EGS has better

mechanisms to control the malpractices. However, these were not

effective in reality for variety of reasons. Role of agency men,

their irregular follow up, their nexus with local politicians and

contractors, use of unofficial machine, involvement of unofficial

contractors, rural elites turned out to be unofficial implementers

of the works, forging of the muster records and the allied

manipulations were routine malpractices both in case of EGS and

SGRY sites.

Leakages in PEPs were generally the results of multiple

factors. Use of illegal machine, bogus muster records,

substandard work, no or less provision of amenities, use of

contractors or labour contractors, inviting and allowing outside

workers, fraud at measuring the works etc. can be some of them.

There was very little difference, but the level of leakages was

comparatively higher in the SGRY cases than EGS cases.

EGS: Keeping Muster duly filled at the EGS worksite is

necessary. Actually, it is a Junior Engineer’s or agency

personnel’s responsibility. Generally, however, the Mukadam

259

259

appointed by the agency officer, keeps the muster. The official

data from Mukadam, however, did show that in 83.33% of the

EGS cases, the agency officer kept the record and in 8.33% of the

cases Mukadam and in 8.33% cases owner of the land where the

work was going on kept the attendance record.

Fudging the record, incorporating bogus enlarged number of

workers, recording the false attendance, keeping the record blank

in order to do further manipulations are some of such types of

malpractices have been observed by the grievances committee’s

reports and PEO studies. Off the record information tells the

stories of it but no such precise data could be gathered from the

field in this study. It was difficult to collect realistic data about it.

However, cases of grievances from the government record took

account of such manipulations. (A report for EGS Legislative

Council Committee, Vidhi Mandal Samiti Ahawal 2008)

Manipulation in distributing food grains, in providing

amenities, deliberate, unrecorded but actual gaps in the work

were the common discrepancies between ideal and actual was

unofficially admitted by some of the Mukadams.

SGRY: In case of SGRY, muster keeping is the responsibility of

the Gram Sevak. 75.0% of the Gram Sevak reported that they did

this job on their own. Sarpanch-Gram Sevak combo, contractor,

peon and one of the workers (8.3% each) also did keep the

musters. 66.7% of the Gram Sevak informally said that they did

not follow 60:40 ratios as per the rule. Amenities were not

provided as per the guidelines. Discrepancy in the number of

workers reported and actually observed on the site was there.

Regional Variation: Contractor from semi developed region and

one of the workers from less developed region handled

260

260

supervising and muster recording responsibility on behalf of the

Gram Sevaks.

The data from the Collector office, Nashik district created for the

EGS Legislative Council Committee meeting in February 2008

showed the nature extent of cases of vigilance. The data referred

to above shows the nature of malpractices and leakages on the

EGS worksites-bogus muster records, lacunas in distribution of

wages, expenditure more than the estimates, corruption, use of

JCB machine on sites, irregularities in implementation, poor

quality of work, implementing the works on another place than

the sanctioned one, over payments to the workers, discrepancies

in the measurements, technical faults in construction of assets

and so on. (A report for EGS Legislative Council Committee

meeting in February 2008, pp-360 to 444).

If the implementing agencies and the institutional framework

are supported by supervision, vigilance and grievances redressal

mechanisms are strongly followed, the amount of leakages might

certainly reduce the leakages and thus might help the poor who

participate in the program. But there were hardly any serious

attempts to control the malpractices and improve their

performance.

5.3.7 Number of Mandays Work Generated

How much mandays of work was generated under EGS and

SGRY? It can be said that the more the employment generation

better the performance. The general observation can be noted

here that the EGS workers got better employment than SGRY

workers. The analysis of the data on the mandays generated has

been studied here on two levels.

a) At one level, the data are based on the information collected

from the Mukadams. To calculate the mandays generated on the

261

261

12 EGS and 12 SGRY worksites was very difficult. Senior officers

on site too were not sure about this data. The best the researcher

could do was just to calculate the total workdays and multiply

them with the number of total workers worked on. The

researcher took help of Mukadams in this matter. 87 per cent of

the Mukadams said they could tell about the total employment

generation on that particular work project. Mukadams could not

assess the mandays on the 3 EGS worksites for, their long

duration of work and employing multiple Mukadams in between.

b) The second set of data on mandays generated was based on

the information collected from the individual worker respondents

from the EGS and SGRY worksites. The number of days they

worked on the site was calculated. Their averages are calculated

to have an idea of how much of mandays the workers earn while

working on these sites at individual level.

EGS: Data from the Mukadams did reveal us that, total 12,445

mandays and average 1382.77 mandays from each of the nine

villages were generated under EGS. Here the average has been

calculated by excluding three EGS villages from which the data

was not available. The average mandays generated under the

EGS for each workers under sample comes to 24.43 days.

SGRY: The mandays generated under SGRY are given as

follows-

a) When we look at the averages, we can notice, as compared to

the EGS, SGRY created less employment generation and less

number of mandays for each village.

b) The average mandays generated under the SGRY for each

worker under sample was 17.54 mandays.

262

262

Regional Variation:

Developed Region

a) Data obtained from Mukadams did reveal that the actual EGS

worksite from developed region created 3520 mandays of

employment generation with average of 1760 for each village. On

the other hand SGRY works could generate 4,995 mandays of

employment with average of 1248.75 days for each village.

Table: 5.33

Mandays generated from EGS and SGRY worksites from

developed areas

EGS SGRY

Worksite 1 2520 527

Worksite 2 Data not Available 136

Worksite 3 1000 4200

Worksite 4 Data not Available 132

Total 3520 4995

Averages 1760 1248.75

Source: Data obtained from the Mukadam respondents

b) Data obtained from Workers did reveal that, the actual

mandays created for the EGS workers under the sample averaged

28.05 for the each EGS worker under the sample from the region.

On the other hand, SGRY works could produce average of 38.5

mandays for each village and 17.11 mandays for the each worker

in the village.

i) Semi Developed areas

a) In semi developed region the mandays employment created

under EGS was 2065 with average of 688.33 and SGRY generated

3238 mandays with average of 809.5. Here SGRY exceeded in

relation to EGS in this matter. One work from this region had

263

263

created 2310 mandays, did make the difference. They used two

years funds for SGRY work and thus had better funds to spend

on.

b) In semi developed region the average mandays created for

EGS workers under the sample were average of 25.78 mandays

for the each EGS sampled workers under the region. SGRY

generated average of 19.8 mandays for the each sampled worker

under the region.

Table: 5.34

Mandays Work Generated for Worksites:

Semi developed areas

EGS SGRY

Worksite 1 460 720

Worksite 2 Data not Available 2310

Worksite 3 900 196

Worksite 4 705 12

Total 2065 3238

Averages 688.33 809.5

Source: Data obtained from the Mukadam respondents

a) Total 6860 mandays were generated in less developed regions

under EGS with average of 1715 in contrast with 4220 mandays

and average of 1055 under SGRY.

b) In less developed region, the average number of mandays created

for EGS workers under the sample was 20.22 for each of the EGS

sampled worker under the region. SGRY generated average of

15.73 mandays for the each sampled worker under the region.

264

264

Table: 5.35

Mandays work generated for worksites:

less developed areas

EGS SGRY

Worksite 1 5700 768

Worksite 2 4800 2320

Worksite 3 2530 828

Worksite 4 6860 304

Total 6860 4220

Averages 1715 1055

Source: Data obtained from the Mukadam respondents

Table: 5.36

Mandays generated under EGS and SGRY

Development

Regions

Average

Mandays

EGS

Average

Mandays

SGRY

Developed 28.05 17.11

Semi Developed 25.78 19.8

Less Developed 20.22 15.73

Average 24.68 17.54

Source: Data obtained from the worker respondents

SGRY works do generate less number of working days/

mandays. In some cases, work opportunities/mandays generated

were so meager that it almost excluded the poor from getting

employment opportunities in real sense of the term. For

instance, in one SGRY case just 12 mandays were created and big

machine and contractor was employed. The number of workers

involved in SGRY works is again less in comparison with EGS in

general. This is for the two reasons- 1) Funds are short 2) Use of

machine and involvement of contractor is higher.

265

265

The EGS on the other hand was more effective at meeting the

employment need of the village poor. Reasons include: better

planning of the local administration to maintain a 'shelf or

reserve’ of EGS projects implementable at short notice in case of

drought, many are designed, at least in outline, long before they

reach the construction stage), better implementing organization,

better monitoring and some deterrence of vigilance. By contrast,

SGRY projects are designed once the money becomes available.

5.3.8 Nature of Monitoring:

Monitoring and supervision includes the record keeping,

supervising, quality checking, addressing irregularities and also

social auditing.

EGS: In general, the EGS sites were better supervised and

monitored than that of SGRY. But still, this supervision was not

up to the expectations of the scheme. Talathi, the lowest level

responsible person of EGS administrative line did not visit the

EGS sites regularly. 41.67% Talathis did not visit the site at all.

EGS works were supervised commonly by the Mukadams or

agency men. Agency officers and Muster clerks visit the site for

monitoring maximum for once or twice a day.

SGRY: At grassroot level Gram Sevak, the responsible supervisor

under second stream SGRY works. He is generally very busy

person. He is given the charge of at least two to three Gram

Panchayats. It is quite hectic for him. Therefore, generally, he

prefers to share his responsibility with some of the workers or

professional contractors to avoid supervision. Without proper

supervision and day-to-day technical informational support, the

quality of assets generated decreases. Most of the Gram Sevak

claimed that they visited SGRY sites regularly. Only 1 out of 12

Gram Sevaks told that he visited EGS worksite of the village

266

266

frequently. More than 58% admitted that they did not visit the

EGS sites at all. In SGRY Higher level monitoring mechanism

was found almost non working.

The consolidated data from the EGS and SGRY workers reveal

that, 29.4% of them were recorded and supervised by the Agency

officials. 15.3% said they were recorded and supervised by the

Sarpanch and Gram Sevak. Thus, more than 50% of the workers

said they were recorded and supervised by the unofficial

supervisors like - One of the workers (4.7%), Owner of the land

(7.1%), Contractor (9.4%) and in one case even the Gram

Panchayat Peon (5.9%). Surprisingly 10.6% workers said they

were neither recorded nor supervised by any specialized person.

The workers did their job for themselves.

Monitoring and supervision by the implementers and the

village level officers and leaders are regarded as key aspects in

performance of PEPs. Both EGS and SGRY have made many

provisions of monitoring and supervision of the works under the

schemes. However, ground reality reveals the fact that

monitoring and supervision was very poor on the projects in the

sample.

Regional Variation: Most of the SGRY works were supervised

and recorded by the Gram Sevaks. In less developed regions some

assistance by the Sarpanch and one of the workers was taken. In

semi developed region on one SGRY (8.66%) worksite was

recorded as well as supervised by the contractor engaged on the

worksite. Higher level monitoring was nonexistent in all the

regions.

5.3.9 Quality of Vigilance and Grievance Redressal:

Vigilance and grievances redressal mechanisms are the two

distinguished features of quality control and management of

267

267

human resources. Vigilance committees at Taluka level were

almost inactive during the study period. Local committees at

worksite where more than 100 workers were working were too

absent. This finding seems consistent with observations of the

other studies on EGS, like PRAYAS, a Pune based NGO. (Rohayo

kadun Magrarohayokade (2008).

EGS: Under EGS these duties were assigned at the divisional

level to the commissioner with assistance of the officer on Special

duty in each division. In addition to this, Collectors, CEOs of Zilla

Parishads, Deputy Collectors, Tahsildars and Supervisory

Officers of the implementing agencies have given responsibilities

to inspect the EGS works as per the norms prescribed.

Legislative Council/State level EGS Committee, Divisional level

EGS Committees, Taluka level EGS Committees are formed to

monitor the EGS work operations. Vigilance squads have also

formed at Secretary, Divisional and District level to control

corruption. EGS is planned in such a manner so that checks and

balances are neatly created at every stage of the implementation.

Data obtained from Talathis reveal that, on three (25%) EGS

work projects they observed vigilance visit by the Tahsildar and

upper level agency officers.

Table: 5.37

Data from Talathi about No. of vigilance visits to EGS site:

Development Category No. of vigilance

visits to EGS site Developed Semi

Developed

Less

Developed

Total

One visit 2 1 0 3

No visit 0 1 4 5

Don't know 2 2 0 4

Total 4 4 4 12

268

268

The field data showed that inspection of the EGS works was

done by the Tahsildar / BDO and Upper Level Agency Officers.

EGS committees at Taluka level and district level were on visible

on grounds. Nobody directly approached the workers and asked

them about their difficulties out there on the sites. When asked

did they see somebody on vigilance visit during the work on EGS

or SGRY, 22.4% of the workers replied that they observed some

kind of vigilance on working site.

A detailed record of vigilance and cases of grievances has

made available from the Collector office, Nashik district. This

record was specially created for the EGS Legislative Council

Committee meeting in February 2008. This record shows that

there have been 107 cases of grievances in Nashik district during

last two decades. The highest cases of grievances registered were

from Minor Irrigation department (Sthanik Staar-Local Level)

(22 cases) and the lowest were from Agriculture Department,

Nashik (2 cases).

The data from the report reveal the following facts:

• Various irregularities in implementation were reported many

a times from the political leaders, social workers, actionists and

from the committees of vigilance from state level to district level,

monitoring and quality control committees at agency level.

• Very few cases were explored by these committees

• Very few of the implementers involved in the grievances were

actually punished

• The court cases, and inquiries took long time to produce

results

• The whole process of grievances redressal is very complex

• Non-governmental committees were highly inactive and

complaisant

269

269

(See Rohayo kadun Magrarohayokade (2008: 83-93), a Study

based book by the Prayas, Pune for the details)

SGRY: Vigilance & Monitoring Committees at the State, District

& Panchayat Samiti level constituted for overseeing the various

programmes of the Ministry of Rural Development are held

responsible to monitor the implementation of the works under the

first & second streams of the SGRY. According to the Gram

Sevaks vigilance committee visited on only 4 SGRY projects

(33.33%) under the second stream. On one site the committee

visited for more than three times, on the remaining three sites, it

visited for one time.

From the cases it is record observed that monitoring under

SGRY is less effective than EGS.

Regional Variation: The data obtained from Talathis reveal

that, frequent vigilance visits were observed in 2 villages from

developed region (16.66%) and in 1 village from semi developed

region (8.33%). One EGS work from the village under semi

developed belt and all the four villages from less developed areas

were reported for no vigilance visit at all. They were not sure

about the visits in two cases of developed and two cases from the

semi developed regions.

Workers, however, could not distinguish the vigilance officer

from any agency officer or politician, however observed that

vigilance visitors were higher in number in developed belt than

semi and less developed belt and on EGS sites than SGRY sites.

270

270

Case No. 5.11: Just keep it

A woman from the tribal belt was active in the village

development activities initiated by a social worker from the

Nashik. One journalist working in the area recommended her

name for the Taluka EGS committee. She became the member of

this committee but received no training and no knowledge

support from the EGS office there. She said, “I just went on to

attend the occasional meetings of the committee and did not

realize my role and responsibilities.” For few times she received

amount ranging Rs. 500 to 2000 from some agency men. When

she asked, “what for this money?” The answer was “just keep it”.

Later on she came to know that the money was for not visiting

the sites and for not raising problematic issues pertaining to the

sites.

5.3.10 Completion of the work in time and Reasons for the

Delays-

EGS: EGS works are generally long lasted and big works. It is,

not lacuna on the part of the implementation agency. Most of the

time, local conditions, technical factors, workers’ problems, and

land acquisition problems have been responsible for delays in

completing the EGS works. When asked Gram Sevaks about the

problems occurred at EGS worksites, all the 12 Gram Sevaks said

they did not know the problems there. There was almost no

coordination among the Talathis, Sarpanchs and the Gram

Sevaks from all of the sampled villages. When the question was

asked to the Gram Sevaks about the timeliness in completing

works, their responses revealed that 50% of the EGS works were

completed in time. Another 17.6% works were completed but

little late, 8.3% works were completed very late. Some works

271

271

(8.3%) did not get completed or were left unfinished. Plantation

and nursery works, the two EGS works, (16.7%) were continuous

works.

It has been a major issue in criticizing EGS that these works

are not getting completed in time. The delays in completing

works have been quite common thing. The official statistics about

EGS reported that 32 works have been remained incomplete for a

period of 5 to 10 years while 80 works were still incomplete even

after 10 years. (Vidhi Mandal Samiti Ahawal 2008:245-316)

The general reasons reported in the report 2008 are:

1. Objections by the owner of the land

2. Objections by the forest department regarding the forest land

3. Local objections

4. Local problems on the sites

5. Pending cases of inquiries of the implementers on the site etc.

SGRY: One Sarpanch from semi developed region said that his

village got SGRY fund very late. He said the funds were received

funs in March and the target to complete the SGRY work was 31st

March. Under such conditions late completion of works was

bound to happen. But this experience was very rare in case of

SGRY. The Sarpanch and Gram Sevaks of particular village

generally receive SGRY funds twice in a year. They have to spend

that amount for SGRY works before that official year ending

before 31st of March. They can plan out a bigger work by adding

the two years funds together but two-year period was the

maximum limit. SGRY works in two villages (16.66%) which did

not follow two-year limit were very late to complete the works.

Importantly there were no significant reason for delayed

completion of planning and executing the works.

272

272

Regional Variation: The information given by the Gram Sevak

and the villagers reveals that one EGS work from the semi

developed region did not get completed as per the norms. The

villagers had some objections about the quality of work. Still they

did not follow any official procedure to register their complaint.

Villages from developed regions took longer time to manage and

implement EGS works. The involvement of middleman, apathy

might be the reasons for that. However, one SGRY work from the

tribal-less developed region, also took long time to get it

completed. The lack of coordination was observed between the

groups of Gram Panchayat members, especially between the

Sarpanch and Panchayat members from another village where

the work was proposed.

Case No. 5.12: Power matters

The lady Sarpanch from one village was unaware about the

SGRY procedures. She said her husband, manages everything.

When asked to the husband, who was acting as if he himself was

Sarpanch, about the delays for completing SGRY works, he

replied, “the political patriarch (godfather) from that village did

not yet ordered to think about SGRY works. He also said, “we

discussed this issue in Gram Panchayat meeting and decided to

wait for the order from the leader. We were not aware of the two-

year limit either.”

When asked, what he would do if the funds were called back by

the government for not completing the work in the scheduled

time, he laughed and said, “this will not happen especially about

this particular village because the so called leader had good chair

and also connections with the concerned authorities.” Later on,

after six months they did this work from outsider professional

contractor.

273

273

5.3.11 Quality of work and assets

A good and useful quality of assets generation is obviously

expected under both EGS and SGRY.

EGS: The workers from the two PEPs under the sample said

22.4% of the EGS works were ‘very good’ in quality, 49.4% were

‘good’ in quality and another 20.0% were ‘fair enough’. 7.1%

workers said, the EGS works generated were ‘bad’ in quality and

1.2% said those were ‘very bad’ in quality.

The reality observed from the data provided by the Sarpanch

was not much different.

The Sarpanchs under the study said, 16.7% of the EGS works

were of ‘very good’ quality, 50% were of ‘good’ quality and 16.7%

of ‘fair quality’. The percentage of very poor quality assets

generated under EGS was just 8.3%.

SGRY: Gram Sevaks’ data reveal that 25.0% of SGRY works

were ‘very good’ in quality. 41.66% were ‘good’ and another

16.66% were of ‘fair’ quality. The per cent of ‘poor’ and ‘very poor’

quality was 16.66%. The Sarpanch rated the quality of SGRY

works as having ‘better quality’.

The one of the Gram Sevaks said, most of the stone

bandharas, small bandharas (bunding) were generally useless for

their technical limitations. The quality of such works under

SGRY was so bad that the purpose of such scheme to generate

sustained employment through assets, did not get satisfied.

Ordinary quality of assets has been a major point for which

the PEPs are undermined. Good quality of the assets ensures

targeted all round development of the villages. The quality of the

assets generated under the EGS and SGRY was found not very

bad, although, it was not good enough either.

One of the agency officers said, in general the EGS works were

274

274

‘better in quality’ than the SGRY. He put some reasons for the

comparatively poor quality of the works under SGRY like - a)

Meager funds, b) Poor monitoring and supervision, c) Higher

amount of works done by the contractors, d) lack of experience of

the Gram Sevaks and Talathis in managing such kind of works.

Regional Variation:

EGS: Following table based on the data obtained from the

Talathi reveal that, the EGS works in less developed areas were

of better quality.

Table: 5.38

Level of quality of EGS Assets

Development Category Level of quality

of EGS/SGRY

assets Developed Semi

Developed Less Developed

Total

Don’t know 0 1 0 1

Very Good 0 1 1 2

Good 3 1 3 7

Poor 1 1 0 2

Total 4 4 4 12

Source: Data obtained from the Talathi respondents

SGRY: According to the Gram Sevaks, 25% of the works in semi

developed and 50% of the SGRY works from the less developed

regions were very good in quality. 50% from the developed, 25%

from the semi-developed and 25% works from the less developed

region were of good quality and 25% of the SGRY works from

semi and less developed region were of fair quality. The Gram

Sevaks observed that the 50% works from the developed region

were bad in quality. It reveals the fact that the developed region

where more contractors for building the assets were employed,

did not maintain the minimal quality.

275

275

Table: 5.39

Quality of SGRY work done

Quality of SGRY work done

Development

Category Very

Good Good Fair Poor Total

Developed 0 2 0 2 4

Semi Developed 1 2 1 0 4

Less Developed 2 1 1 0 4

Total 3 5 2 2 12

Source: Data obtained from the Gram Sevak respondents

Using substandard material, stakeholders’ nexus, negligence

in technical supervision, poor monitoring, inexperienced local

management and absence of vigilance were some of the general

reasons for the poor quality of asset generation.

Case No. 5.13: Beneficiaries suffered due to poor quality:

One EGS work from the developed region took more than three

years to complete the percolation tank there. The muster clerk

who was given charge of the work was very busy in many other

projects. He visited this site very rarely. Professional contracts,

substandard material, irregular workers, poor technical

supervision and low participation of the villagers, lack of

monitoring and vested interests of the neighboring farmer

stakeholder made this work of very bad quality. The neighboring

farmer did suffer and lost some crop and cultivable soil when the

percolation tank broke up in the first heavy rain after its faulty

construction.

But there are success stories too. See Case No. 5.14.

276

276

Case No. 5.14: A lady Sarpanch could make it a success

story

A lady Sarpanch from a tribal village was very keen in

managing SGRY work. She took consent of the Gram Sabha.

They collectively decided to build well for drinking water and

tried to avoid undue interventions by the local elites. She

personally devoted attention for supervision of the site. The local

workers having interest in getting drinking water from the

proposed well did perform their role in better manner. Now the

well is full of water. Due to her differences with the Gram Sevak

there, however, could not complete the tap water scheme in the

village.

5.3.12 Level of Utility

The level of utility of assets generated under the scheme is

very hard to judge. Asking the respondents about the usability of

the works was the only way to judge this.

EGS: The data from the Sarpanchs (as given in the table) reveal

the fact that only 8.3% of works were useful for all. 16.7% of the

EGS assets were useful for majority, 8.3% of the works were

useful for the poor and 66.7% of the works were either useful for

very few or were of least use. The Sarpanchs told that the

affroestation works near the village, and works of farm tanks,

stone bandharas and plant development works close the village

were of least use.

28.2% worker believed that the EGS assets were useful for all,

24.7% said the works were useful for majority. 7.1% workers felt

that they will benefit the poor. 10% of the workers told the assets

277

277

will benefit local elites. 1.2% workers have marked the EGS

works, as works not useful for anybody.

Table: 5.40

Level of utility of Assets generated under EGS

Level of utility of EGS assets

Development

Category Useful

for all

Useful

for

majority

Useful

for

poor

Useful for

very

few/least

useful

Total

Developed 0 0 0 4 4

Semi Developed 0 1 1 2 4

Less Developed 1 1 0 2 4

Total 1 2 1 8 12

Source: Data obtained from the Sarpanch respondents

SGRY: Surprisingly, 25.0% of the Sarpanchs said that they could

not tell whether the SGRY assets generated in their respective

villages were useful or not. 41.7 % said those works were useful

for all and 25.0% of them said they were useful for poor. Only

8.3% works were useful only for the local elites.

Table: 5.41

Level of utility of Assets generated under SGRY

Level of utility of SGRY asset

Devt. Category Do not

know

useful

for all

Useful

for

poor

Useful

for local

elites

Total

Developed 2 0 1 1 4

Semi Developed 0 3 1 0 4

Less Developed 1 2 1 0 4

Total 3 5 3 1 12

Source: Data obtained from the worker respondents

278

278

Regional Variation:

EGS: There was no considerable deviation when the data for

assessing regional variation was analysed. But still, it can be

said that the tribal-less developed region created assets under

both EGS and SGRY which were more useful for the community.

The data from the Talathis (given in the table) reveal that, the

number of assets useful for few and useful for elite was on little

higher side in semi developed area and assets from the less

developed areas were more useful for the village community. (See

table 5.42)

Table: 5.42

Regional variation in the level of utility of assets

generated

Development Category Level of utility of

EGS/SGRY assets Developed Semi

Developed

Less

Developed

Total

Do not know 0 1 0 1

Useful for all 1 0 3 4

Useful for majority 1 1 0 2

Useful for local

elites/farmers 1 0 0 1

Useful for very few/least

useful 1 1 1 3

For local elites+ For very

few 0 1 0 1

Total 4 4 4 12

Source: Data obtained from the Talathi respondents

279

279

Case No. 5.15: Land leveling enhanced livelihood levels

The villagers from a tribal belt approached the agriculture officer

and requested him to start land leveling (mazgi) works on their

agricultural land. Lands in this belt are uneven and thus less

productive. The EGS work completed in this village benefitted

more than 20 tribal farmers. The beneficiaries got almost doubled

production of Nagali, and rice on their improved farm lands.

Table: 5.43

Level of utility of EGS assets: A combined view

Type of Respondent Level of utility of

EGS/SGRY assets Sarpanch Deputy

Sarpanch

Gram

Sevak Talathi

Total

Do not know 0 0 0 1 1

Useful for all 1 1 1 4 7

Useful for majority 2 2 6 2 12

Useful for poor 1 3 1 0 5

Useful for local

elites/farmers 0 3 3 1 7

Useful for very

few/least useful 8 3 1 3 15

11.00 0 0 0 1 1

Total 12 12 12 12 48

Source: Data obtained from the Sarpanch, Deputy Sarpanch, Gram

Sevak and Talathi respondents

EGS works were expected to be more beneficial for the village

poor for, 1) Assets generated are big 2) They are demand driven

3) Those seem technically more sound, durable with proper

supervision, vigilance and technical support.

280

280

SGRY: The data collected from Sarpanchs tells us that SGRY

works from semi developed and less developed region were more

useful than the works from the developed region.

Table: 5.44

Level of utility of SGRY assets: Sarpanch view

Development Category Level of utility of

SGRY asset Developed Semi

Developed

Less

Developed

Total

Do not know 2 0 1 3

useful for all 0 3 2 5

Useful for poor 1 1 1 3

Useful for local

elites 1 0 0 1

Total 4 4 4 12

Source: Data obtained from the Sarpanch respondents

The data collected from the Sarpanchs reveals that the assets

generated under SGRY were more useful than the EGS. SGRY

works, because they were since planned and managed at local

level and had distinct potentials in generating useful assets.

5.3.13 Who were benefitted the most?

EGS: 33.33% of the Sarpanch said, the EGS worksite from their

village would benefit the elites. 25% of them said it would help

the farmers, 41.7% of them said it would help to backward

sections. When asked the workers that did they personally

benefited from the EGS assets directly or indirectly, only 20%

said yes.

SGRY: Sarpanchs believed that the EGS works would more

benefit to the local elites than SGRY. 25% of them said that the

works provided benefit to the farmers, 50.0% said it benefited the

villagers in general, 16.7% thought that the works would benefit

to the backward sections and 8.3% said the SGRY work from

281

281

their village would benefit the school children. 8.88% of the

Talathis and 16.66% of the Gram sevak however believed that the

SGRY assets have benefited to the local elites. 8.88% of the

Talathis said elites and backward section both were benefited

from the SGRY work.

The responses from different categories of respondents were

confusing. However, a general impression among the

respondents was that, the SGRY scheme was superior in

delivering benefits to the villagers than the elites.

Regional Variation:

EGS: According to 8.33% of the Gram Sevaks, the EGS work

from the less developed region benefitted the local elites. The

Gram Sevaks in one village said that the local tribal political

leader by using all his connections at the taluka level authorities

constructed village tank close to his house and he was the

unofficial owner-user of the tank.

In general terms one can say that, the backward sections or

the semi and less developed areas were benefitted slightly more

from the EGS assets than the developed areas.

SGRY: The data obtained from the Gram Sevaks (given in the

table) reveal that, the SGRY assts have comparatively more

benefitted the elites from developed and semi developed areas.

Villagers from backward section have also been benefitted more

than the ones from the developed and semi developed areas.

282

282

Table: 5.45

Who benefited by the assets under SGRY

Who Benefited Development

Category

Elites Villagers Backward

Sections

School

Children

Elites+ Backward

Sections

Total

Developed 1 2 1 0 0 4

Semi

Developed 1 2 0 1 0 4

Less

Developed 0 3 0 0 1 4

Total 2 7 1 1 1 12

Source: Data obtained from the Gram Sevak respondents

5.3.14 Relevance of the scheme

Which of the two programmes tends to satisfy the needs of the

respondents by the assets it created? How far does it meet urgent

local needs?

EGS: When asked the question that ‘did they find EGS relevant

today’? the answers reveal that for 16.66% of the Talathis EGS

was very relevant today. The 75% of the Gram Sevaks on the

other hand reported EGS was of very much of relevance today.

The Sarpanch (75.0%) and more than 50% of the Talathis said

EGS was relevant today.

Table 5.50 indicates that 8.88% of the Sarpanchs and Talathis

each did say that EGS was of very little relevance today.

70.83% of the Sarpanches, Deputy Sarpanches, Gram Sevaks

and Talathis together did reveal that EGS was relevant for

supportive employment in lean agricultural season and in

adverse conditions. 14.71% of them believed that EGS is relevant

for poverty alleviation, 8.47% for distress management, 4.44% for

stopping migration to cities, 14.85% for development, 10.55% for

asset generation, 6.38% for comprehensive reasons and 4.44%

since having doubts about relevance of EGS any more. So in

283

283

general it can be said that EGS was believed to be relevant for

generating supportive employment only during the lean

agricultural season or during the adverse conditions like drought.

They did not believe that it would eradicate their poverty or it

would develop the villages.

58.82% workers also said that EGS and SGRY were relevant

because they provided them additional employment.

SGRY: SGRY on the other hand was felt relevant by the Gram

Sevaks, Sarpanch and the Deputy Sarpanch for the development

of the village. The workers relatively in more percentage believe

that SGRY did better job in satisfying their local, village level

needs.

Responses of the workers revealed that when they were in

urgent and desperate need of employment EGS was better option

for them. EGS projects come out on average as markedly superior

to SGRY projects here in producing employment.

Regional Variation: Both EGS and SGRY were felt of desperate

relevance in the less developed regions. There was no significant

difference between the three regions showing the relevance of

EGS verses SGRY. However, most of the workers working on the

EGS sites from the developed area said EGS was of little

relevance now.

5.3.15 Future profits or outputs of the work assets

The workers working under the schemes categorized the works

concerning the arenas of future profits. Almost half of them said

that, the works on which they worked on would help to conserve

water. 3.5% said that it would enrich the agriculture there. Some

of them could not categories the profits but replied that the work

or asset would help any way for village development.

16.5% of the workers said the work or asset would

284

284

development of plantation and forestry and add to the future

profits. Rest of the workers said the assets would generate other

future profits like sanitation of the village (2.4% workers),

performing religious ceremonies (7.1% workers), and drinking

water supply (7.1% workers). One worker (1.2%) could not tell

what kind of profit the work will generate.

EGS and SGRY: Most of the EGS and SGRY workers from the

less developed areas said that the assets would help them in

reducing water problems. The workers from developed and semi

developed areas thought that the assets would benefit them in

future in satisfying their civil needs directly. EGS was also

considered outstanding for generating forestry and plantation

assets that would benefit the villagers in comprehensive but

indirect way.

PEPs were meant to generate employment. The assets

generated under these programmes were expected to help in

creating new employment opportunities and a chain of works

through works will go on. This chain was considered to be the

essence of the poverty reduction potentialities of wage based

PEPs. Assets generated under SGRY rarely found to have such

potential. EGS relatively did better in this regard.

Regional Variation: The data based on the workers perceptions

reveals that there was no significant difference on the basis of

areas of development. Only exception was that the workers from

the semi and less developed region believe that the EGS works

from their village would help to agriculture and solve water

problems. They also felt that SGRY works would also help in the

village development even better than the EGS works.

285

285

5.3.16 Outputs for the village

What exactly were the developmental benefits delivered to the

village by means of assets generated under these two PEPs?

EGS: EGS did slightly better in producing water and soil

conservation works. The water and soil conservation works under

EGS works relatively more sustainable and useful. Village tank

construction under EGS in the tribal area was not profitable for

the villagers there but old bandhara repairing work was very

important for the tribal village from the less developed region.

The villagers said, in the absence of repairy work, they would

have spoiled the main water source of the village. It was huge

work and might not be produced under SGRY second stream.

EGS stood outstanding in creating six assets of plant

development and forest conservation and on the other side SGRY

did not do any of such works. Soil conservation and Mazgi

(agricultural land leveling) works under EGS were very useful

and different from SGRY.

Road constructed in semi developed area under EGS was of

better quality and of better use than the two roads under SGRY.

SGRY: SGRY works produced different outputs. Those works

were more of building construction type works. Gram Panchayat

building, toilet, kitchen shed, death ceremony sheds and Latrine

were the construction works under SGRY. Well construction

works under SGRY in the two less developed villages did

outstanding work in generating future profits for its villagers.

Some useless works were also taken under the SGRY. Waste soil

lifting from the bandhara, kachha road for the inclination

towards protection of two developed villages did prove futile. The

SGRY works reflect the interests of the villagers and the local

elites. The needs satisfied from the SGRY works were not so

286

286

urgent but to some extent those were of interest of local

aspirations.

Regional Variation: There was no remarkable difference

between EGS works on the regional grounds. Plant and Forest

development works were slightly more in number in less

developed region.

Outputs produced by the SGRY assets however show

remarkable variation. The works from less developed villagers

were more focused on strengthening sources of potable water.

Villages from developed and semi developed region produced

building construction, road and sanitation type works. The

interests of the local elites were reflected in those works.

To sum up it can be said that, no conclusive evidence was

found to assert that one scheme was superior to other. There

were different areas where both of these schemes performed

better than the other.

287

287

References:

Lieberman, Samuel. S. 1985. Field-level perspectives on

Maharashtra’s Employment Guarantee Scheme, Public,

Administration and Development, Vol. 5( No.2), Edited

by Brian Smith,Vol.-5,Number-2, John Wiley and Sons

Publication, pp. 109–127.

De Haan, Arjan. 1997. ‘Poverty and Social Exclusion: Comparison

of Debates’, PRUS working Paper No. 2, University of

Sussex, Brighton, UK

-----. 1999. Social Exclusion: Towards an Holistic Understanding

of Deprivation, a mimeo

A report for EGS Legislative Council Committee (Vidhi Mandal

Samiti Ahawal prepared for meeting in February 2008,

pp-360 to 444

“Rohayo kadun Magrarohayokade (MREGS)… :

Magrarohayochya Sandharbhat Rohayochi Chikitsa”

(2008:83-93), a Study based book by the Prayas, Pune.

Reports:

Government of India, SGRY Guidelines: 2001


Recommended