+ All Categories
Home > Documents > CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour...

CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour...

Date post: 03-Jul-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
20
CHATHAM BRIDGE PROJECT Robert G. Ridgell, P.E., DBIA VDOT Fredericksburg District, Assistant District Construction Engineer May 14, 2020 City of Fredericksburg Main Street Community Meeting
Transcript
Page 1: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

CHATHAM BRIDGE PROJECT

Robert G. Ridgell, P.E., DBIA

VDOT Fredericksburg District, Assistant District Construction Engineer

May 14, 2020

City of Fredericksburg – Main Street Community Meeting

Page 2: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

“Pardon Our Dust” Meeting Agenda

2

• Project need

• Benefits and features of improved bridge

• How travelers will be affected

• Recreation on the Rappahannock River

• Construction highlights

• Your questions!

Page 3: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Chatham Bridge Today

3

• Built in 1941 (79 Years Old)

• 16,000 vehicles a day

• Travel lanes – 4 lanes, each 10 feet wide

• Narrow sidewalks (4 feet wide)

• Structurally deficient

• Asphalt in poor condition due to age

• Impacts to travelers

• High maintenance costs

• Weight Posting

Page 4: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Chatham Bridge Rehabilitation: Project Design

4

Page 5: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

5

Example of future shared use path on bridge: Photo from Dr. Martin Luther King, Jr., Memorial Bridge in Danville, Virginia

Chatham Bridge outer railing will be concrete-only

Page 6: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

6

Rendering of future Chatham Bridge

Page 7: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

7

Rendering of future Chatham Bridge

Page 8: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

8

Rendering of future Chatham Bridge

Page 9: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

9

Project Schedule

Phase Date

Dixon Street ramp improvements

Install detour signs (covered until needed)Complete!

Utility relocation Completion by June 15

Construction activity begins May 28, 2020

Bridge closes to all traffic

Demolition work begins

June 2020*

(*exact date to be announced two weeks ahead)

Bridge reopens to traffic 16.5 months after closure

(incentivized completion schedule)

Page 10: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Detour Route

10

• Route 3 Business

• Blue & Gray Parkway

• Dixon Street

• Charles Street

Remember:

No change for traffic

approaching downtown from

Route 1 at Falmouth Bridge, or

Route 3 from Interstate 95

Page 11: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Detour: Vehicles taller than 13 feet, 6 inches

Virginia Department of Transportation 11

• Route 3 Business

• Blue & Gray Parkway

• William Street

Remember:

No change for traffic

approaching downtown from

Route 1 at Falmouth Bridge, or

Route 3 from Interstate 95

Page 12: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Dixon Street Ramp Improvements: Complete

Virginia Department of Transportation 12

Page 13: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Hanson Avenue and Route 1 Traffic Pattern Changes

13

Page 14: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Impacts to River Users

Virginia Department of Transportation

June 2020 through December 2020

14

Page 15: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Impacts to River Users

Virginia Department of Transportation

December 2020

15

Page 16: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

River User Rules of Road

Virginia Department of Transportation

• Follow warning buoys

• Do not approach pipes

• Do not enter the workzone

• Use caution during high flows

• Intermittent short term closures (<24 hours) will be required

for beam demolition and setting and deck forming.

• Communication will be made to:

• Virginia Outdoors Center

• River Rock Outfitters

• Friends of the Rappahannock

• Fredericksburg Trails Alliance

16

Page 17: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

17

Construction Sequence Highlights

Construction Activity Approximate Timeframe

Access road and causeway construction

Traffic signal modifications at Route 1, Hanson Avenue

Detour sign

Late May and Early June 2020

Causeway construction continuing into July

Bridge Deck Demolition June – July 2020 (estimated 3 weeks)

Steel Beam Demolition Early August 2020

Top of river pier demolition and widening

Shore foundations and supports

Foundation protection in river

Late August 2020

Page 18: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

18

Construction Sequence Highlights

Construction Activity Approximate Timeframe

Placement of new structural steel December 2020

Bridge deck forming and placement Spring 2021

Bridge rail forming and placement Summer 2021

Bridge deck finishing, traffic elements and new signs

BRIDGE OPENS! Early October 2021

Page 19: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

Coordination with private online mapping:

• Google

• Waze

• Apple

• TomTom

• Here.com

• Others … list is always growing!

Online Mapping Providers

Virginia Department of Transportation 19

Page 20: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15

www.VirginiaDOT.org/chathambridge

Live construction camera to be added once work begins!

Follow us on …

Facebook: VDOT Fredericksburg District Group

Twitter: @VaDOTFRED

Nextdoor

Need a Chatham Bridge project speaker, or have a question?

Contact us!

Kelly Hannon, VDOT Fredericksburg District

Communications Manager

(540) 374-3344 office

(540) 656-0321 cell

(540) 899-4288 VDOT Fredericksburg District Office

[email protected]

Stay informed!

20


Recommended