Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | sheila-dorcas-newman |
View: | 215 times |
Download: | 0 times |
C.Hauviller/TS-IC27 avril 2007 1
24-25 April 2007
Summary
C. Hauviller
Review of the inner triplet
C.Hauviller/TS-IC
Inner Triplet Review
The mandate as stated by Lyn Evans, LHC project leader, is:"A review of the mechanical design of the inner triplet to be
sure that there are no further hidden defects.A review of the proposed in-situ repair once the design is
complete."Following discussions with US and CERN colleagues,- the mechanical design is interpreted as all engineering
related to stresses and displacements and therefore also the alignment
- the inner triplet will include all the assembled systems: DFBX, Q1, Q2, Q3 and , when relevant, D1.
27 avril 2007 2
C.Hauviller/TS-IC
LHC low- triplet – warm assembly
27 avril 2007 3
C.Hauviller/TS-IC
LHC low- triplet – DFBX
27 avril 2007 4
C.Hauviller/TS-IC
Inner Triplet Review
• Review panel:
Claude Hauviller/CERN - Chairman
Vittorio Parma/CERN – Scientific Secretary
Alain Poncet/CERN
Jean-Michel Rifflet/ CEA
John Herbert Sondericker/BNL
27 avril 2007 5
C.Hauviller/TS-IC
Inner Triplet Review
• All presentations are accessible on the CDS at the address http://indico.cern.ch/conferenceDisplay.py?confId=15267
• Treat only the points related to the mechanics. Electrical integrity, magnetic performances,… are not part of the review, neither the organizational issues.
27 avril 2007 6
C.Hauviller/TS-IC
Inner Triplet ReviewOverview (Ranko Ostojic CERN)Generalities (Jim Kerby FNAL Q1/Q2/Q3 Thermo-Mechanics (Tom Nicol FNAL)DFBX Thermo-Mechanics (Tom Peterson FNAL , Joseph Rasson LBNL D1 Thermo-Mechanics (Erich Willen BNL Integrated systems (Jim Kerby FNAL Activities on the triplets at CERN (Herve Prin CERN)Interconnections including modifications (Cedric Garion CERN) Jacks (Sonia Bartolome Jimenez CERN)Ground (John Osborne CERN)Alignment / Positioning (Dominique Missiaen CERN
Fixes (Jim Kerby FNAL
27 avril 2007 7
C.Hauviller/TS-IC
Inner Triplet Review
• No guarantee to be full proof. – Complex assemblies– Time too short to be thorough and to
swallow all the information
• The incident during the pressure test of L5 has generated a lot of work/analysis in the labs
27 avril 2007 8
C.Hauviller/TS-IC
Q1 supports at IP 5L
27 avril 2007 9
C.Hauviller/TS-IC
Path of forces
Forces originate at the magnet interconnect from bellows spring forces and pressure induced axial forces…
…they act on the internal piping and are transmitted to the cold mass through the pipe anchors…
…then are transferred to the support structure through the anchor and slide mechanisms…
…then to the vacuum vessel through the external support lugs…
…and finally to the floor through the external jacks.
27 avril 2007 10
C.Hauviller/TS-IC
Fix Points
MQXA MQXB MQXAMQXB
Q3 Q2A Q1
DFBX
Q2B
38490
MQXBLBX
D1
External heat exchanger (HX)
Fixed Point HX-Cold Mass
FP Cold Mass-Vacuum Vessel
Fixed Point Triplet-Tunnel Floor
Tie Rods Linking Vacuum Vessels
Jacks (longitudinal)
Internal heat exchanger
27 avril 2007 11
C.Hauviller/TS-IC
Inner Triplet Review
Main subjects– General– Internal piping and anchoring to cold
masses (helium vessels)– Connection of cold masses to vacuum
vessels– Forces on vacuum vessels transferred to
ground
27 avril 2007 12
C.Hauviller/TS-IC
Inner Triplet Review
– General• Documentation exists but incomplete
• Design standards not uniform– Safety factors
• ASME codes for ductile materials typically 3 – 3.5 to ultimate or 1.5 to yield strength (in 1998 Div I was 4 to ultimate)
– Welds further derated depending on geometry and inspection
• Spider support transverse SF 2 to ultimate
– Welding coefficientZ=0.55
27 avril 2007 13
C.Hauviller/TS-IC
Inner Triplet Review
– Internal piping and anchoring to cold masses (helium vessels)
Unbalanced forces, elbows
Extreme cases of loading: – pressure test (traction)– vacuum (compression)
Systematic verifications launched (FEM analysis)
27 avril 2007 14
C.Hauviller/TS-IC
Inner Triplet Review
Internal piping and anchoring to cold masses (helium vessels)
– Weak points located in the anchoring to cold masses. To be reinforced on Q1, Q3 and DFBX. Can be done in-situ
27 avril 2007 15
C.Hauviller/TS-IC
Completed cold mass and piping on spider supports
27 avril 2007 16
C.Hauviller/TS-IC17
Q1 pipe support weldment (Q3 similar)
27 avril 2007 17
C.Hauviller/TS-IC
Q1 pipe support weldment proposed modification
As designed pipe anchor stresses
Bracket to cold mass weld stress: 41797 psi (288 MPa)
Elbow to end dome weld stress: 17383 psi (120 MPa)
Modified pipe anchor stresses
Bracket to cold mass weld stress: 9121 psi (63 MPa)
Elbow to end dome weld stress: 9430 psi (65 MPa)
See Q1 Pipe Anchor Stress Analysis – T. Page, April 19, 2007
27 avril 2007 18
C.Hauviller/TS-IC
Q3 End
D1 End
DFBX Piping Layout
27 avril 2007 19
C.Hauviller/TS-IC20
DFBX Summary
• Cold shocks, pressure tests and vacuum leak checks were performed at the component level at the manufacturer and CERN
• Analysis confirmed that the LHe vessel structure is robust• During the last month the DFBX mechanical structure was
reviewed and much of it was analyzed• The analysis confirmed that the bus duct thrust support is
marginal– “Weld Clamp” was not welded– Support bracket is too thin
27 avril 2007 20
C.Hauviller/TS-IC
Bus Duct Thrust Support Analysis (weld clamp)
Weld Clamp Stress Calculation DetailsMaterial: 304L stainless steelPeak thrust load: 20.1 kN (4510 lb) Weld size: 1.59 mm (1/16”) 2 sides of clampWeld diameter: 48.3 mm (1.90”)Shear stress: 61.5 MPa (8.92 ksi)Equivalent stress: 107 MPa (15.4 ksi)
Allowable stress: 115 MPa (16.7 ksi)Weld efficiency factor: 0.55Net allowable stress: 63.3 MPa (9.19 ksi)
Weld stress exceeds allowable stress dictated by PV code but is still within material strength limits
Thrustsupport
Weldclamp
27 avril 2007 21
C.Hauviller/TS-IC
Inner Triplet Review
Internal piping and anchoring to cold masses (helium vessels)
– Weak points located in the anchoring to cold masses. To be reinforced on Q1, Q3 and DFBX. Can be done in-situ
– Too low safety factor for the global stability of the piping. Recommended to add extra supports. Note that the H pieces have been modified to increase stability of the cold mass
lines and reliability of the heat exchanger inner copper tube. Can be done in or near the interconnections
27 avril 2007 22
C.Hauviller/TS-IC
Q1/Q2, Q2/Q3 interconnectionsStability issue - Global stability (at the IC scale)
Cold mass and heat exchangerModifications
First global mode: 49.5 bars (Q1/Q2) 1 mode suppressed
First mode with limited displacement
Critical pressure of ~49.5 bars for Q1/Q2 and ~49 bars for Q2/Q3 (rescaling)
Assembly of H pieces done by welded sleeves minimum of shear pres-stress in the bellows
Stiff restrain on M4 bellows
27 avril 2007 23
C.Hauviller/TS-IC
Q1/Q2, Q2/Q3 interconnectionsStability issue - Global stability
Pcr ~30bars
Pcr ~60bars
Guiding device to be installed on the end plate
LD
Q1
Aluminium plate
Interconnection support
EE, FF
bellows
bellows
Pcr ~50bars
Thermal shield extremity
Thermal shield: “Soft” boundary conditions
Pcr ~39.5bars
27 avril 2007 24
C.Hauviller/TS-IC
Inner Triplet Review
Connection of cold masses to vacuum vesselsComposite parts inside the magnets. Bars in the DFBX.
Integrity of all the composite parts not guaranteed. Movements not properly controlled during transports. No specific action proposed. Limit the load where possible.
27 avril 2007 25
C.Hauviller/TS-IC
Handling and TransportMean(s) Container Restraints Data Recorder
US to CERN Truck / Boat / (Plane)
Q1/Q3 Fixation on transport Frame inside a metallic container 1 per side
ShockwatchAcceleration Recorders
Q2 Fixation on transport Frame inside a wooden box 1 per side
D1 Fixation on transport Frame inside a metallic container 1 per side
DFBX Fixation on transport Frame inside a wooden box Springs
181 ↔ storage
↔ Smi2Truck
Q1/Q3
1 per side
SchocklogsQ2 1 per side
D1 1 per side
DFBX covered truck
Smi2 ↔ 181 ↔ storage
Truck
Q1/Q3
1 per side
SchocklogsQ2 1 per side
D1 1 per side
DFBX covered truck
Installation Truck
Q1/Q3
1 on the non IP side
SchocklogsQ2
1 on the non IP side
D11 on the non IP side
DFBX covered truck
27 avril 2007 26
C.Hauviller/TS-IC
Inner Triplet Review
Connection of cold masses to vacuum vessels
• Inside the DFBX, eliminate LHe vessel vertical rods linkage dependence on friction generated by bolt tightness. Check load case when rods are in compression
• Safety factor to ultimate too low for composite parts in Q1/Q2/Q3. Repaired part not acceptable. To be replaced.
27 avril 2007 27
C.Hauviller/TS-IC
Repaired spider
27 avril 2007 28
C.Hauviller/TS-IC
Inner Triplet Review
Connection of cold masses to vacuum vessels
• Inside the DFBX, eliminate LHe vessel vertical rods linkage dependence on friction generated by bolt tightness. Check load case when rods are in compression
• Safety factor to ultimate too low for composite parts in Q1/Q2/Q3. Repaired part not acceptable. To be replaced.
• Fixes in Q1 and Q3 to be finalized and qualified: cartouche proposal. Unload the spiders from longitudinal loads
27 avril 2007 29
C.Hauviller/TS-IC
Requirements for a Fix
• In Situ
• Does not move fix point of the assemblies
• React loads with sufficient stiffness to limit deflection – 150kN design load (slide 4)
• Acts at any temperature 300K to 2K
• Focus on implementation in Q1—Q3 solution tuned for length will then accommodate
27 avril 2007 30
C.Hauviller/TS-IC
Cartouche / Cartridge
• Affixed at Q1 non-IP end; Q3 IP end
• Transfer load at all temperatures
• Limits support deflections
27 avril 2007 31
C.Hauviller/TS-IC
Pieces….
Cold Mass Bracket,
mechanically and thermally
attaches AL cylinder to cold
mass volume
Vacuum vessel bracket, transfers Invar load to Vacuum Vessel
Cartridge, Invar rod centered in Al tube
27 avril 2007 32
C.Hauviller/TS-IC
Q1 Cartridge Modeling
• Cartridge applied to Q1 model including bellows for:– Warm 25 bar
pressure test load– Cold– Cold, 20 bar
quench load
Figure 1. Finite Element Model of Q1 with Cartridge
27 avril 2007 33
C.Hauviller/TS-IC
Cartridge Initial Analysis
Cartridge looks very promising, and is the proposed solution• Worst case Q1 spider support longitudinal deflection < 2mm limit• Worst case Q1 spider load < ¼ load that caused failure during recent pressure
test• Does not move magnet fix point
– In fact fixes Q1 / Q3 better than currently• Magnetic effect negligible• Design is ongoing to look at:
– Length; diameter of rod (not 10% effect in various models)– Steady state thermalization BC’s– Thermal performance under upset / transient conditions– Attachment details to cold mass (corrector containment volume shell)– Attachment details to vacuum vessel, including effect on O ring groove due to
• Cartridge bracket / tie rod ear deflections• Cooling of the Vacuum Vessel due to additional heat leak
– Q3 attachment– Consolidation of design variants and anlayses
27 avril 2007 34
C.Hauviller/TS-IC
Spider and tie bar assembly
• Define the worst case loading of the spider, including tie rods contractions, and pre-stress. Validate by testing that the SF on longitudinal load is at least 4.
27 avril 2007 35
C.Hauviller/TS-IC
Connection of cold masses to vacuum vessels
• Define the worst case loading of the spider, including tie rods contractions, and pre-stress. Validate by testing that the SF on longitudinal load is at least 4.
• Validate the cartridge solution fix:– Complete the thermo-mechanical analysis including a sensitivity
analysis on T profiles, in particular including cool-down/warm-up transients, accidental loss of insulation vacuum
– Encourages the components and assembly tests proposals, possibly including a LN2 cold test.
– Understand the mechanics of the overall support system (component and integrated assembly). Experimental validation recommended.
• Check the thermo-mechanical transverse stability/reproducibility of the magnets inside the vessels.
27 avril 2007 36
C.Hauviller/TS-IC
Inner Triplet Review
Forces on vacuum vessels transferred to ground
Overall approach unclear.
Not clearly specified/ understood.
Two extreme cases:
Case 1: - loads transmitted to the DFBX and then to ground through the tie bars (initial specification)
Case 2: -loads transmitted to the ground through the jacks
27 avril 2007 37
C.Hauviller/TS-IC
Load Transfer
• Alignment Requirements for the LHC Low-Beta Triplets (LHC-G-ES-0016, 2002). Main points concerning supports:– CERN supplies jacks, cups and other equipment for installation to the
tunnel floor.– Lateral load specified as 1 ton– No reference to vacuum load (assumed taken up by the tie-rods).
• Decision to use PMPS jacks for the inner triplets (2004?)– Jacks designed to take loads up to 8 tons
• Specification for the motorization of the PMPS jacks (IT3200, 2004)– Lateral load specified as 1.3 tons
• Anchor specification (date?)– Lateral load specified as 5 tons
• All cases referred to assumed vacuum loading
27 avril 2007 38
C.Hauviller/TS-IC
Inner Triplet Review
– Forces on vacuum vessels transferred to ground
Case 1: - loads transmitted to the DFBX and then to ground through the tie bars
Resistance of tie bars and tie bars supports not adequate. Can be modified in-situ.
Free the jacks
Global (in)stability to be assessed
27 avril 2007 39
C.Hauviller/TS-IC
Tie rod assembly at warm fit-up
27 avril 2007
40
C.Hauviller/TS-ICC. Garion
Q1/Q2, Q2/Q3 interconnectionsVacuum vessel closure
Vacuum longitudinal force:
Max 8000daN
Buckling force (per rod): 5770daN
Buckling force (per rod):1440daN
Is the guide length sufficient to avoid rotation?
Stiff guidance has probably to be implemented
Bellows buckling pressure: 3.7 bars4.8 mm thick
27 avril 2007 41
C.Hauviller/TS-IC
Inner Triplet Review
– Forces on vacuum vessels transferred to ground
Case 2: -loads transmitted to the ground through the jacks
Longitudinal forces on jacks limited to 4 tons due to anchoring and local floor conditions
27 avril 2007 42
C.Hauviller/TS-IC
External jack stands in warm fit-up
27 avril 2007 43
C.Hauviller/TS-IC
Inner Triplets Supports:fixation to the ground
– Different tunnel ground conditions:
Point 2 (RB24): platform made of concrete blocks and reinforced concrete slabs to continue the tunnel
slope
Point 1: Two holes of ~400mm diameter to fix the supports to the concrete underneath
Point 8 (RB86): reinforced concrete beam
27 avril 2007 44
C.Hauviller/TS-IC
Inner Triplet Review.
• Forces on vacuum vessels transferred to ground– Clarify the situation and decide on the option.– Reinforce tie bars and tie bars supports. Can be
modified in-situ.– Study carefully the load sharing (use the overall FEM
model prepared by FNAL)– Take into account the transverse adjustment
requirements for alignment
27 avril 2007 45
C.Hauviller/TS-IC
Inner Triplet reviewMain Recommendations
• Internal piping and anchoring to cold masses (helium vessels)– Weak points located in the anchoring to cold masses. To be reinforced on Q1, Q3
and DFBX. Can be done in-situ– Too low safety factor for the global stability of the piping. Recommended to add
extra supports. Can be done in or near the interconnections • Connection of cold masses to vacuum vessels
– Safety factor to ultimate too low for composite parts in Q1/Q2/Q3 (spiders). • Integrity of these parts not guaranteed. Limit the load where possible.• Repaired part not acceptable. To be replaced.
– Fixes in Q1 and Q3 to be finalized and qualified (including transients, accidental loss of insulation vacuum, a LN2 cold test): cartouche proposal. Unload the spiders from longitudinal loads.
• Forces on vacuum vessels transferred to ground– Clarify the situation and decide on the option.– Reinforce tie bars and tie bars supports. Can be modified in-situ.– Study carefully the load sharing – Take into account the transverse adjustment requirements for alignment
27 avril 2007 46