CHERRY HUFFMAN ARCHITECTS, PAWake County PSC Skylight & PSC
& L Bldg. Fall Protection ADDENDUM NO. 2 Raleigh, North
Carolina Page 1 April 8, 2021 HUFFMAN ARCHITECTS, PA 632 PERSHING
ROAD RALEIGH, NORTH CAROLINA 27608 PHONE (919) 740-5669 TO: ALL
PRIME BIDDERS OF RECORD This Addendum forms a part of the Contract
Documents and modifies the original Project Manual and Construction
Documents dated March 15, 2021. Acknowledge receipt of this
Addendum in the space provided on the Bid Form. Failure to do so
may subject the Bidder to disqualification. This addendum consists
of three (3) pages, fourteen (14) 8 ½” x 11” attachments, and one
(1) 24x36 attachment. All documents are distributed digitally.
SPECIFICATIONS: Item No. Description 1. Add the following
specification Section “08 3950 BULLET RESISTANT ALUMINUM DOOR
AND
STOREFRONT FRAME SYSTEM.”
2. Add the following specification section “11 0140 ROOFTOP FALL
PROTECTION ANCHORAGE SYSTEMS. 3. Section 01 3100 – PROJECT
MANAGEMENT AND COORDINATION – Make the following revisions.
a. Change 1.6.D To read “Progress Meetings: Conduct progress
meetings at two-week intervals. Coordinate dates of meetings with
preparation of payment requests.”
4. Section 01 3300 – SUBMITTAL PROCEDURES – Make the following
revisions.
a. Change 1.4.B.A.1 To read “Shop drawing and product data
submittals shall be transmitted to Architect in electronic (PDF)
format.”
b. Delete section 1.4.B.B.3.
5. Section 07 4243 – COMPOSITE WALL PANELS – Make the following
revisions. a. Delete section 2.2 WEATHER BARRIER.
6. Section 07 8100 – APPLIED FIREPROOFING – Make the following
revisions.
a. Change 3.4.A To read “Special Inspections: A third party special
inspector shall be hired by the Owner to perform the following
special inspections:”
7. Section 08 4115 – ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS –
Make the following
revisions: a. 1.2 SUMMARY A.1 change to read “Interior manual-swing
entrance doors.”
b. 1.2 SUMMARY B add line 3. “Section 08 3950 Bullet Resistant
Aluminum Door and Storefront Frame
System.:
c. Remove paragraph 2.1 MANUFACTURERES A. Drawings: Item No.
Description 1. Drawing Sheet S001 – Make the following
revisions:
a. Replace the entire sheet with the attached sheet S001 Revision 1
Special Inspections Revision dated 4/8/2021.
b. Add the attached “Statement of Special Inspections.”
Wake County PSC Skylight & PSC & L Bldg. Fall Protection
ADDENDUM NO. 2 Raleigh, North Carolina Page 2 April 8, 2021
CLARIFICATIONS: Item No. Description 1. OBE standard Reliance is
the Basis-of-Design, but the specs also call for an OITC of 33
minimum & Bullet-
resistant glazing in both the system & in the doors. OBE does
not have Bullet-resistant doors or curtain wall to offer. Do the
doors and frames need to be Bullet-resistant or just the glazing?
Also, the Bullet-resistant glazing is 1-1/4” thick. We cannot
accommodate this thickness in our doors (1” Max). The thickness
will not be a problem in the curtain wall. Also, none of our
systems meet an OITC of 33 minimum. Response: The basis-of-design
shall be Oldcastle Reliance HTC. It is understood that Oldcastle
does not have bullet resistant doors or curtain wall frames. ¼”
steel plate shall be added to the curtain wall frames, per the
drawings, to provide bullet-resistance. The basis-of-design for the
exterior bullet resistant doors shall be the Aluminum Bullet
Resistant Door ABRD Series, as manufactured by C.R. Laurence, Co.,
Inc (see attached specification section 08 3950). The minimum OTIC
of 33 shall not be required.
2. “The spec doesn’t say that the Curtainwall framing has to be
bullet resistant, but the doors and glazing must
be. I was hoping you could clarify if the framing has to be bullet
resistant or not. Our security glazing vendor is seeing if they can
do that glass in a thinner size so that we would be able to fit it
into a standard curtainwall frame. If the framing doesn’t have to
be bullet resistance it opens up our options quite a bit and will
be much less expensive. If the entire assembly - framing, glazing,
and doors must have steel inserts to be bullet resistance it
narrows the vendors quite a bit and inflates the price.” Response:
See response to CLARIFICATIONS Item No. 1 Above. The curtainwall
framing must be able to accept 1” insulated glass and bullet
resistant glass, an air space, and ¼” glass for a total thickness
of 1 ¾ inches.
3. We were reviewing the RFQ package for the Wake County Fall
Protection scope on Planhub. We didn't see any specifications for
the fall protection equipment, however the plans did defer to a
particular player in the market. We can offer the full package -
anchors, lifelines, guardrail, davits, testing, etc. However, I
believe a substitution request may be required. Can you confirm
Tractel may be able to provide equipment? Response: See attached
specification section 11 0140 ROOFTOP FALL PROTECTION ANCHORAGE
SYSTEMS”.
4. Section 01 3100; 1.6.D requires weekly progress meetings. Please
confirm weekly meetings are required. Response: Weekly progress
meetings are not required. Progress meetings will be scheduled
every two weeks.
5. Does the permit fee allowance cover lane and sidewalk closures
that may be required to perform the work? Response: No, the permit
fee allowance, Allowance No. 1, only covers the actual cost of the
building permit fee. The cost of all inspection fees, lane, and
sidewalk closures, etc. are not covered by the allowance and are
the responsibility of the general contractor.
6. Section 01 3300 requires the use of Submittal Exchange for shop
drawing transmission. Is this required? Response: No, Submittal
Exchange is not required.
7. Spec section 07 2726 is requiring a fluid applied air barrier
however spec section 07 4243 (2.2.A) mentions the installation of
house wrap style air barrier. Please clarify. Response: Provide the
fluid applied air barrier per specification section 07 2726.
Wake County PSC Skylight & PSC & L Bldg. Fall Protection
ADDENDUM NO. 2 Raleigh, North Carolina Page 3 April 8, 2021
8. Please confirm that the contractor is responsible for special
inspection of fire proofing (per section 07 8100; 3.4.A).
Response: A special inspector shall be hired by Wake County. The
General Contractor is not responsible to hire a special inspector.
See attached revised Sheet S001 and the Statement of Special
Inspections.
END OF ADDENDUM NUMBER TWO
04/08/2021
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME SYSTEM 08 3950
- 1
SECTION 08 3950 BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME
SYSTEM
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including
General and Supplementary Conditions and Division 01 Specification
Sections, apply to this Section.
1.2 SUMMARY
B. Related Sections:
1. Section 08 3950 "Bullet Resistant Aluminum Door and Storefront
Frame System” 2. Section 08 4413 “Glazed Aluminum Curtain Walls.”
3. Section 08 7110 "Door Hardware.”
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product indicated. Include
construction details, material descriptions, dimensions of
individual components and profiles, and finishes for aluminum-
framed systems. 1. Certification: Provide printed data in
sufficient detail to indicate compliance with the
contract.
B. Shop Drawings: For swinging doors. Include plans, elevations,
sections, details, and attachments to other work.
1. For entrance doors, include hardware schedule and indicate
operating hardware types, functions, quantities, and
locations.
C. Samples for Verification: For each type of exposed finish
required, in manufacturer's standard sizes.
D. Other Action Submittals:
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME SYSTEM 08 3950
- 2
1. Entrance Door Hardware Schedule: Prepared by or under the
supervision of supplier, detailing fabrication and assembly of
entrance door hardware, as well as procedures and diagrams.
Coordinate final entrance door hardware schedule with doors,
frames, and related work to ensure proper size, thickness, hand,
function, and finish of entrance door hardware.
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: For swinging doors to include in maintenance
manuals.
1.7 QUALITY ASSURANCE
B. Accessible Entrances: Comply with applicable provisions in the
U.S. Architectural & Transportation Barriers Compliance Board's
ADA-ABA Accessibility Guidelines.
C. Preinstallation Conference: Conduct conference at Project
site.
1.8 PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of structural
supports for aluminum-framed systems by field measurements before
fabrication and indicate measurements on Shop Drawings.
1.9 WARRANTY
A. Special Warranty: Manufacturer's standard form in which
manufacturer agrees to repair or replace components of
aluminum-framed systems that do not comply with requirements or
that fail in materials or workmanship within specified warranty
period.
1. Failures include, but are not limited to, the following:
a. Structural failures including, but not limited to, excessive
deflection. b. Noise or vibration caused by thermal movements. c.
Deterioration of metals, metal finishes and other materials beyond
normal
weathering. d. Failure of operating components.
2. Warranty Period: Five years from date of Substantial
Completion.
B. Special Finish Warranty: Manufacturer's standard form in which
manufacturer agrees to repair or replace components on which
finishes do not comply with requirements or that fail in materials
or workmanship within specified warranty period. Warranty does not
include normal weathering.
1. Warranty Period: 20 years from date of Substantial
Completion.
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME SYSTEM 08 3950
- 3
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: The basis-of-design shall be based on Aluminum
Bullet Resistant Door and Storefront Frame ABRD Series, as
manufactured by C.R. Laurence Co. Inc.
2.2 MATERIALS
A. Aluminum: Extrusions shall be 6063-T5 alloy and temper (ASTM
B221 alloy T5 temper). Fasteners, where exposed, shall be aluminum,
stainless steel or zinc plated steel in accordance with ASTM A 164.
Perimeter anchors shall be aluminum or steel, providing the steel
is properly isolated from the aluminum. Framing must utilize
testing recognized under the standards established by u.l. 752 for
bullet resistant components.
B. Finish: Aluminum extrusions shall be given a caustic etch
followed by an anodic oxide treatment to obtain Fluoropolymer paint
coating conforming with the requirements of AAMA 2605. Color shall
be a custom color to match the curtain wall finish.
C. Glazing: The glazing must be in accordance with U.L. 752 testing
standards (Level 3) and as specified in Section 08 800
Glazing.
2.3 ENTRANCE DOOR SYSTEMS
1. Door Construction: 2-3/16 inches overall thickness,
2. Door Design: As indicated.
a. Accessible Doors: Smooth surfaced for width of door in area
within 10 inches (255 mm) above floor or ground plane.
3. Glazing Stops and Gaskets: Manufacturer’s standard.
a. Provide nonremovable glazing stops on outside of door.
B. Entrance Door Hardware: As specified in Section 08 7110 "Door
Hardware."
C. Bullet Resistance: Install bullet resistant Level 3 fiberglass
per manufacturer’s requirements.
2.4 FABRICATION
A. Form or extrude aluminum shapes before finishing.
B. Weld in concealed locations to greatest extent possible to
minimize distortion or discoloration of finish. Remove weld spatter
and welding oxides from exposed surfaces by descaling or
grinding.
C. Entrance Doors: Reinforce doors as required for installing
entrance door hardware.
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME SYSTEM 08 3950
- 4
1. At exterior doors, provide weather sweeps applied to door
bottoms.
D. Entrance Door Hardware Installation: Factory install entrance
door hardware to the greatest extent possible. Cut, drill, and tap
for factory-installed entrance door hardware before applying
finishes.
E. After fabrication, clearly mark components to identify their
locations in Project according to Shop Drawings.
2.5 ALUMINUM FINISHES
A. High-Performance Organic Finish: 3-coat fluoropolymer finish
complying with AAMA 2605 and containing not less than 70 percent
PVDF resin by weight in both color coat and clear topcoat. Prepare,
pretreat, and apply coating to exposed metal surfaces to comply
with coating and resin manufacturers' written instructions.
1. Color and Gloss: Provide a custom finish to match the finish of
the existing curtain wall system.
PART 3 - EXECUTION
A. Examine areas and conditions, with Installer present, for
compliance with requirements for installation tolerances and other
conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions
have been corrected.
3.2 INSTALLATION
A. General:
1. Comply with manufacturer's written instructions. 2. Do not
install damaged components. 3. Fit joints to produce hairline
joints free of burrs and distortion. 4. Rigidly secure nonmovement
joints. 5. Install anchors with separators and isolators to prevent
metal corrosion and electrolytic
deterioration. 6. Seal joints watertight unless otherwise
indicated.
B. Install components plumb and true in alignment with established
lines and grades, and without warp or rack.
C. Install glazing as specified in Section 08 8000 "Glazing."
D. Entrance Doors: Install doors to produce smooth operation and
tight fit at contact points.
1. Exterior Doors: Install to produce weathertight enclosure and
tight fit at weather stripping.
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME SYSTEM 08 3950
- 5
2. Field-Installed Entrance Door Hardware: Install surface-mounted
entrance door hardware according to entrance door hardware
manufacturers' written instructions using concealed fasteners to
greatest extent possible.
3.3 ADJUSTING
A. Adjust operating entrance door hardware to function smoothly as
recommended by manufacturer.
1. For entrance doors accessible to people with disabilities,
adjust closers to provide a 3- second closer sweep period for doors
to move from a 70-degree open position to 3 inches (75 mm) from the
latch, measured to the leading door edge.
END OF SECTION 09 3950
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-1
SECTION 11 0140 - ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Personal Fall Arrest Anchorage Systems:
1. System design and certification. 2. Fall protection roof
anchors. 3. Horizontal lifelines. 4. Training.
1.2 RELATED SECTIONS
1.3 REFERENCES
A Occupational Safety and Health Administration (OSHA):
5. OSHA 1910, Subpart D - Walking and Working Surfaces. 6. OSHA
1910.66, Appendix C - Personal Fall Arrest Systems. 7. OSHA
Procedures and Precautions for Employees Using Decent Control
Equipment.
B. American National Standards Institute: ANSI Z 359 - Fall
Protection Code.
C. American Institute of Steel Construction (AISC): Load and
Resistance Factor Design.
B. American Welding Society: AWS D1.1 - Structural Welding
Code.
1.4 SUBMITTALS
A Submit under provisions of Section 01 3300 “Submittal
Procedures.”
B. Product Data: Manufacturer's data sheets and detail drawings for
each product to be used, including:
1. Preparation instructions and recommendations. 2. Storage and
handling requirements and recommendations. 3. Product literature,
material specifications. 4. Installation details and methods. 5.
Dimensions of product components. 6. Finishes of anchor
components.
C. Shop Drawings
1. Shall be to scale and clearly show dimensioned layout of system
components. 2. Include details for each specified product to
indicate materials, dimensions,
accessories, rated load, and ultimate load. Details shall clearly
indicate attachment to building structure and welds shall be
indicated by AWS welding symbols, distinguishing between shop and
field welds, and show size, length and type of each weld.
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-2
3. Include notes to indicate proper use of system. 4. Shall bear
the seal of the supervising registered professional engineer.
Professional engineer shall be licensed in the state of North
Carolina.
D. Close-out Submittals:
1. Provide a Fall Protection Anchorage System Log Book to
include:
a. Requirements for inspection and re-certification. b. Statement
by supervising qualified fall protection engineer that system
was
designed and installed in accordance with ANSI Z359.6 and is
certified for use. It is the requirement of the General Contractor
to hire a fall protection engineer to provide this statement and
certification.
c. As-built Drawings to indicate as-installed anchorage locations,
details, and user notes.
1) The As-Built drawings shall provide a fall protection device
labeling and numbering system such that each fall protection device
is specifically identified. Each anchor shall be assigned a unique
number which shall include the building number, flooring, and
anchor. The contractor shall coordinate the labeling and numbering
system with the architect and Owner.
d. Manufacturer's 1 year standard warranty document commencing on
date of Substantial Completion. Manufacturer's warranty is in
addition to any warranties as required by project contract
documents.
1.5 QUALITY ASSURANCE
A Manufacturer Qualifications:
1. Specializes in the design, fabrication, and installation of fall
protection anchorage systems with a minimum of five years of
documented experience.
2. Manufacturer shall carry specific liability insurance (products
and completed operations) in an amount not less than $5,000,000 to
protect against product failure.
3. Manufacturer shall provide samples of product for inspection or
outside agency testing at the request of the owner. Manufacturer
shall be compensated for additional product.
B. Installer Qualifications:
1. Installation contractor shall be trained or qualified by the
manufacturer. 2. The fall protection installer shall maintain
appropriate insurance as applicable for
the installation of fall protection systems. 3. Welding methods
shall comply with AWS D1.1 and welding personnel shall be
certified in accordance with AWS requirements.
1.6 DELIVERY, STORAGE, AND HANDLING
A Deliver, store and handle materials and products in strict
compliance with manufacturer's instructions and recommendations and
industry standards.
B. Inspect products prior to installation and replace damage
products.
C. Store products indoors in manufacturer's or fabricator's
original containers and packaging, with labels clearly identifying
product name and manufacturer. Protect from damage.
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-3
1.7 SEQUENCING AND COORDINATION
A Coordinate installation of products that connect to the work of
other trades. Furnish setting drawings and directions for
installing products that are to be embedded in concrete or masonry.
Deliver such items to the project site in time for
installation.
B. Contractor shall be immediately made aware of any site
conditions that may interfere with proper installation and intended
use of anchorage system.
1.8 PROJECT CONDITIONS
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A Basis of Design: Fall protection systems are based on products
manufactured by Peak Fall Protection, Inc. Subject to compliance
with requirements, provide the named products or comparable
products by one of the following:
1. Fall Protection Systems. 2. Miller Fall Protection, by Honeywell
International, Inc.
3. Tractel LTD.,
2.2 DESIGN REQUIREMENTS
A. System Design Requirements:
1. System shall comply with current OSHA, ANSI and applicable state
regulatory requirements.
2. System shall be designed by a qualified fall protection engineer
with experience in the design of horizontal lifeline systems.
3. Provide rooftop edge access to designated roof areas where
parapet height does not meet OSHA/ANSI requirements for fall
prevention. Refer to the Drawings for extent of fall protection
system.
B. Fall Protection Anchorage Design Requirements:
1. Fall Protection Roof Anchors: Capable of sustaining a minimum
ultimate load of 5000 lbs (2268 kg) in any direction the load may
be applied without fracture or failure.
2. Fall Protection Roof Anchors: Capable of sustaining a minimum
proof load of 2500 lbs (1134 kg) in any direction the load may be
applied without damage or permanent deformation.
C. Horizontal Lifeline Design Requirements:
1. The horizontal lifeline shall be designed for a minimum of two
users, each using an energy absorbing lanyard which limits the
force applied to the horizontal lifeline to 900 lbs (or as
designated by the Qualified Fall Protection Engineer, not to exceed
1,800 lbs).
2. Termination anchors, intermediate anchors, and cable components
shall maintain
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-4
a minimum safety factor of 2:1 as required by OSHA, specifically
1926.502(d)(8). 3 Permanently installed horizontal lifelines shall
be designed for fall arrest in
accordance with ANSI Z359.6 section 6.2.2.2. 4. Horizontal lifeline
required clearance shall be less than or equal to the
available
clearance for the system. Clearance safety margin shall comply with
ANSI Z359.6.
2.3 MATERIALS
A. Steel: Minimum strengths.
1. Structural Steel W-Shapes: ÅSTM A 572, Grade 50, Fy= 50 ksi. 2.
HSS (Tube): ÅSTM A 500, Grade B, Fy = 46 ksi. 3. Angles, Channels,
and Plates: ASTM A 36, Fy = 36 ksi. 4. Stainless Steel Shapes: ASTM
A 276, Type 304. 5. Stainless Steel Wire Rope: ÅSTM A 492, Type
316, 5/16 inch (8 mm) minimum diameter.
B. Aluminum: 6061-T6 alloy.
C. Fasteners: Provide stainless steel Type 304 for exterior
fasteners exposed to weather. Diameter of bolt sizes per
designer/engineer.
D. Non Stainless Steel Materials: Hot dipped galvanized.
2.4 MANUFACTURED UNITS
A. Fall Protection Roof Anchors:
1. U-Bars: Minimum 0.75 inch (19 mm) diameter type 304 stainless
steel with 1.5 inch (39 mm) eye opening.
2. Anchor Posts: Hot dipped galvanized HSS with minimum height as
designated by General Contractor to provide not less than 8 inches
(203 mm) above finished roof or as necessary to allow proper
flashing per roof manufacturer requirements.
3. Baseplates: Minimum 5/8 inch (8 mm) or as designed by
manufacturer. Hot dipped galvanized.
4. Fasteners: As designed and provided by manufacturer for proper
attachment to substrate. Exposed fasteners are to be Type 304
SS.
B. Horizontal Lifelines:
1. Horizontal Lifeline system shall be composed of galvanized steel
fall protection anchors and stainless steel wire rope. Extent of
system is as noted on contract Drawings.
2. Wire rope shall be minimum 5/16 inch (8 mm) diameter. Wire rope
and wire rope termination components shall be stainless
steel.
3. Shall allow user to bypass intermediate anchors without
detachment or reattachment to the system.
4. Provide two stainless steel cable runner devices capable of
attachment and removal at any point along the system.
C. Personal User Equipment
1. OSHA/ANSI Z359 Compliant Full Body Harnesses. QTY = 2
Units.
2.5 FABRlCATlON
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-5
A. Product manufacturing shall be constructed without defects in
appearance or defects damaging to the performance of the
product.
B. Anchors shall be checked for any material (including but not
limited to welding material build-ups) and are free of sharp edges
or abrasions that can cause damage to workers ropes.
C. Painting: Rooftop anchors shall be primed and painted to match
the metal roofing color.
PART 3 - EXECUTION
3.1 EXAMINATION AND PREPARATION
A Inspect and prepare substrates for compliance with anchorage
requirements using the methods recommended by the manufacturer for
achieving best result for the substrates under project
conditions.
B. Do not proceed with installation until substrates have been
prepared using the methods recommended by the manufacturer and
deviations from manufacturer's recommended tolerances and
conditions that will be detrimental to the anchorage system are
corrected. Commencement of installation constitutes acceptance of
conditions.
C. If preparation is the responsibility of another installer,
notify Architect in writing of deviations from manufacturer's
recommended installation tolerances and conditions.
3.2 INSTALLATION
A Install products in accordance to manufacturer's instructions and
approved shop drawings.
B. Coordinate installation with Contractor to ensure an approved
water-tight roofing and flashing method will be used.
C. Clean mounting surfaces to insure direct and even bearing of
base plates.
E. Torque fasteners to manufacturer's required rating.
F. All fasteners threads shall be deformed by mechanical, chemical
or welding methods to prevent accidental removal or
vandalism.
G. All welders shall be certified to applicable American Welding
Society (AWS) standards.
H. After installation, clean and paint as necessary any field welds
with cold galvanizing compound to prevent corrosion.
3.3 FIELD QUALITY CONTROL
A Anchors utilizing adhesive studs shall be tested using a load
cell test apparatus in accordance with manufacturer's written
instructions.
B. Equipment shall be tested and inspected on site in accordance
with manufacturer's recommendations and under the supervision of a
professional engineer. Testing should be conducted in accordance
with applicable OSHA/ANSI standards. Testing data shall be recorded
and submitted with system log book. Testing data shall be sent to
the Engineer of Record.
3.4 PROTECTION
Wake County PSC Skylight & PSC & L Bldg Fall Protection
Huffman Architects, PA
ROOFTOP FALL PROTECTION ANCHORAGE SYSTEMS 11 0140-6
A Protect installed products until completion of project.
B. Touch-up, repair or replace damaged products before Substantial
Completion.
3.5 ADJUSTMENT
A Verify that products have been installed in accordance with
manufacturer's instructions. Adjust as necessary to ensure
compliance.
B. Correct component deficiencies to assure compliance prior to
substantial completion.
3.6 TRAINING
A Provide on-site instruction by manufacturer's certified
technician for owner's designated operators in proper use of
personal fall arrest anchorage system. Provide training session and
one bound copy of training materials.
END OF SECTION 11 0140
Revised on 01/05/18
Statement of Special Inspections
Project: Location: Owner’s Representative: Owner’s Address:
Architect of Record: Structural Engineer of Record: This Statement
of Special Inspections is submitted as a condition for permit
issuance in accordance with the Special Inspection requirements
(Chapter 17) of the North Carolina State Building Code. The
Statement includes a Schedule of Special Inspections applicable to
this project as well as the required qualifications for the Special
Inspector and Agents of the Special Inspector to perform on this
project. The Special Inspector shall keep records of all
inspections, furnish inspection reports, and identify discrepancies
as required by Section 1704.1.3 of the North Carolina State
Building Code. A final report of Special Inspections, documenting
the completion of all required Special Inspections and confirming
the correction of any discrepancies, will be submitted prior to
issuance of a Certificate of Use and Occupancy. The Special
Inspections program does not relieve the Contractor of his or her
responsibilities. Job Site safety and means and methods of
construction are solely the responsibility of the Contractor.
Schedule of Special Inspections The following sheets comprise the
required schedule of special inspections for this project. The
construction divisions which require special inspections for this
project are as follows:
Soils Site Retaining Walls Special Foundations Cast-in-Place
Concrete Structural Load Bearing Precast Concrete Wall Panels and
Veneers Post Tensioned Concrete Sprayed Fire-Resistant Materials
Structural Masonry – Level 1
Exterior Insulation & Finish System (EIFS) Wood Shear Walls
Smoke Control Structural Steel: Connections, welds, bolts, &
anchors Quality Assurance for Seismic Resistance Mastic &
Intumescent Fire-Resistant Coating Quality Assurance for Wind
Requirements Modular Construction Alternate Methods
Cold-Formed Steel Framed “X” Bracing/Seismic Resisting Systems
Seismic Design Category: Basic Wind Speed: Wind Exposure Category:
Statement of Special Inspections Prepared by (Structural Engineer
of Record):
________________________________________________________________
Signature Date Owner’s Authorization Accepted for the Building
Official by: _____________________________________________
_____________________________________________ Signature Date
Signature Date
WC PSC Skylight Replacement & PSC & L Bldg Fall Protection
330 S Salisbury St., Raleigh, NC 27601
Wake County / Eric Sowers
Eric Sowers, Huffman Architects
Chuck Lysaght, Lysaght & Associates
Item Qualifications Scope
SI
• Collect certificate of compliance from fabricator at completion
of fabrication
2. Welding SI • Continuous inspection of complete and partial joint
penetration welds, multipass fillet welds, plug and slot welds, and
single-pass fillet welds > 5/16” in accordance with NCSBC Table
1704.3
• Periodic inspection of single-pass fillet welds ≤ 5/16”
• Collect certificate of compliance for weld filler material
• Identify use of approved filler material and in accordance with
AWS D1.1
3. Metal Deck SI
• Collect material data sheets for decking and connectors or
fasteners
• Periodic inspection of welds and / or mechanical fasteners
4. Structural Details SER / SI • Periodic inspection of steel
framing and joint details
5. Bolting SI
SI SER / SI
• Collect certificate of compliance from bolt supplier
• Periodic inspection of snug-tight, pretensioned, and slip
critical joints in accordance with NCSBC Table 1704.3
• Continuous inspection of pretensioned and slip- critical joints
using turn-of-nut without matchmarking or calibrated wrench methods
of installation
6. Material Certification
2 of 2
Schedule of Special Inspection Services Sprayed On Fire Resistant
Materials
Item Qualification Scope
1. Preparation SI / ITL • Periodically inspect preparation of
substrate prior to installation in accordance with approved fire
resistance design and approved manufacturer’s written
instructions
2. Application SI / ITL • Periodically inspect that substrate has
minimum
ambient temperature before and after application as specified by
the fire resistance design and approved manufacturer’s written
instructions
• Test thickness of sprayed on material per the instruction of
Section 1704.12.4, the fire resistance design, and the approved
manufacturer’s written instructions
• Periodically test Density of sprayed on material per fire
resistance design and approved manufacturer’s written
instructions
• Periodically test bond Strength to ensure a value greater than
150 pounds per square foot.
GENERAL STRUCTURAL NOTES
THESE DRAWINGS, AS INSTRUMENTS OF PROFESSIONAL SERVICE, ARE THE
PROPERTY
OF LYSAGHT & ASSOCIATES, P.A., FOR USE SOLELY WITH THIS PROJECT
AND
SHALL NOT BE REPRODUCED FOR OTHER PURPOSES.
THE PROFESSIONAL ENGINEER WHOSE SEAL APPEARS ON THESE DRAWINGS IS
THE
PROJECT STRUCTURAL ENGINEER-OF-RECORD (SER) WHO BEARS LEGAL
RESPONSIBILITY FOR THE PERFORMANCE OF THE STRUCTURAL FRAMING
RELATING TO
PUBLIC HEALTH, SAFETY, AND WELFARE. NO OTHER PARTY, WHETHER OR NOT
A
PROFESSIONAL ENGINEER, MAY COMPLETE, CORRECT, REVISE, DELETE, OR
ADD TO
THESE CONSTRUCTION DOCUMENTS OR PERFORM INSPECTIONS OF THE WORK
WITHOUT
THE WRITTEN PERMISSION OF THE SER.
USE STRUCTURAL DRAWINGS IN CONJUNCTION WITH JOB SPECIFICATIONS,
AND
OTHER DRAWINGS.
SECTIONS AND DETAILS SHOWN SHALL BE CONSIDERED TYPICAL FOR ALL
SIMILAR
CONDITIONS.
BEEN SHOWN IN GENERAL RELATIONSHIP TO THE STRUCTURAL ELEMENTS.
THEY
SHALL NOT BE ASSUMED TO BE ACCURATE AND REFERENCE MUST BE MADE TO
THE
APPROPRIATE CONSULTANT(S) PLANS AND SPECIFICATIONS.
CONTRACTOR SHALL VERIFY ALL CONDITIONS IN THE FIELD AND TAKE
ALL
NECESSARY FIELD MEASUREMENTS.
CONTRACTOR SHALL TAKE SUCH ACTION AS NECESSARY TO PREVENT MOVEMENT
OF OR
DAMAGE TO THE ADJACENT STRUCTURE DURING CONSTRUCTION.
THE STRUCTURE SHOWN ON THESE DRAWINGS IS STRUCTURALLY SOUND ONLY IN
ITS
COMPLETED FORM. THE CONTRACTOR SHALL PROVIDE ALL NECESSARY BRACING
TO
STABILIZE THE BUILDING DURING CONSTRUCTION.
WHENEVER EXISTING CONSTRUCTION IS RENOVATED, THERE IS LIKELY
SOME
COSMETIC DEFECTS DUE TO THE AGE OF THE BUILDING THAT WILL NOT
BE
CORRECTED DURING THE RENOVATION. THESE DEFECTS INCLUDE SAGGING
FLOORS,
MINOR CRACKS IN MASONRY WALLS, CRACKS IN SHEETROCK OR PLASTER THAT
IS
LEFT IN PLACE, ETC. THIS IS TO BE EXPECTED BY THE OWNER, UNLESS
NOTED
OTHERWISE ON THE DRAWINGS.
METAL DECK
DESIGN, FABRICATION AND ERECTION OF METAL DECK SHALL CONFORM TO
THE
STEEL DECK INSTITUTE "DESIGN MANUAL FOR COMPOSITE DECKS, FORM DECKS
AND
ROOF DECKS".
METAL ROOF DECK SHALL BE 22 GAGE, TYPE "B" BY NEW MILLENNIUM, WIDE
RIB
STEEL WITH 1 1/2" NOMINAL CORRUGATION DEPTH (1.5B22), OR APPROVED
EQUAL.
THE MINIMUM YIELD STRESS SHALL BE 33 KSI.
METAL ROOF DECK SHALL BE INSTALLED IN 2 SPAN CONDITION,
MINIMUM.
FASTEN METAL ROOF DECK TO SUPPORTING STEEL WITH #12 SCREWS IN A
36/4
PATTERN WITH (2) #10 TEK SCREW SIDELAP FASTENER AT EQUAL SPACING
WITHIN
DECK SPANS.
SUSPENDED CEILINGS, LIGHT FIXTURES, DUCTS, AND OTHER UTILITIES
OR
FINISHES SHALL NOT BE SUPPORTED BY THE METAL DECK.
ALL ROOF DECK SHALL RECEIVE A SHOP-COAT OF HIGH QUALITY RUST
INHIBITIVE
PRIMER, IN ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS.
ALL
FLOOR DECK SHALL BE GALVANIZED IN CONFORMANCE WITH ASTM A653-94,
G60
MINIMUM.
SUBMIT ERECTION DRAWINGS TO THE STRUCTURAL ENGINEER FOR REVIEW
PRIOR TO
FABRICATION.
EXCEPT WHERE INDICATED ON THE DRAWINGS, POST-INSTALLED ANCHORS
SHALL
CONSIST OF THE FOLLOWING ANCHOR TYPES AS PROVIDED BY HILTI, INC.,
OR
APPROVED EQUAL. THE GENERAL CONTRACTOR SHALL CONTACT HILTI AT
(800)-879-8000 FOR PRODUCT RELATED QUESTIONS.
A. ANCHORAGE TO CONCRETE - USE "KH-EZ" UNLESS NOTED OTHERWISE
ON
PLANS, OR REQUIRED BY HILTI PER APPLICATION.
1. ADHESIVE ANCHORS FOR CRACKED AND UNCRACKED CONCRETE USE:
a. HILTI "HIT-RE 500 V3" EPOXY ADHESIVE ANCHORING SYSTEM
PER ICC ESR-2322 FOR SLOW CURE APPLICATIONS.
b. STEEL ANCHOR ELEMENT SHALL BE HILTI "HIS-N" INTERNALLY
THREADED INSERTS (USED WITH "RE 500-SD" AND "HY 200"
ONLY), HILTI "HAS-E" CONTINUOUSLY THREADED ROD, OR
CONTINUOUSLY DEFORMED STEEL REBAR.
CONCRETE USE:
a. HILTI "KWIK HUS EZ" SCREW ANCHORS PER ICC ESR-3027
ANCHOR CAPACITY USED IN DESIGN SHALL BE BASED ON THE TECHNICAL
DATA
PUBLISHED BY HILTI (OR SUCH OTHER METHOD AS APPROVED BY THE
STRUCTURAL
ENGINEER OF RECORD). SUBSTITUTION REQUESTS FOR ALTERNATIVE
PRODUCTS
MUST BE APPROVED IN WRITING BY THE STRUCTURAL ENGINEER OF RECORD
PRIOR
TO USE. CONTRACTOR SHALL PROVIDE CALCULATIONS DEMONSTRATING THAT
THE
SUBSTITUTED PRODUCT IS CAPABLE OF ACHIEVING THE PERFORMANCE VALUES
OF
THE SPECIFIED PRODUCT. SUBSTITUTIONS WILL BE EVALUATED BY THEIR
HAVING
AN ICC ESR SHOWING COMPLIANCE WITH THE RELEVANT BUILDING CODE
FOR
SEISMIC USES, LOAD RESISTANCE, INSTALLATION CATEGORY, AND
AVAILABILITY
OF COMPREHENSIVE CREEP, IN-SERVICE TEMPERATURE AND
INSTALLATION
TEMPERATURE.
INSTALL ANCHORS PER THE MANUFACTURER INSTRUCTIONS, AS INCLUDED IN
THE
ANCHOR PACKAGE.
ANCHOR CAPACITY IS DEPENDENT UPON SPACING BETWEEN ADJACENT ANCHORS
AND
PROXIMITY OF ANCHORS TO EDGE OF CONCRETE. INSTALL ANCHORS IN
ACCORDANCE
WITH SPACING AND EDGE CLEARANCES INDICATED ON THE DRAWINGS.
EXISTING REINFORCING BARS IN THE CONCRETE STRUCTURE MAY CONFLICT
WITH
SPECIFIC ANCHOR LOCATIONS. UNLESS NOTED ON THE DRAWINGS THAT THE
BARS
CAN BE CUT, THE CONTRACTOR SHALL REVIEW THE EXISTING STRUCTURAL
DRAWINGS
AND SHALL UNDERTAKE TO LOCATE THE POSITION OF THE REINFORCING BARS
AT
THE LOCATIONS OF THE CONCRETE ANCHORS. G.C. SHALL CONTACT S.E.R.
WITH
CONFLICTS IN THE FIELD, PRIOR TO CONSTRUCTION.
SCOPE OF STRUCTURAL ENGINEERING SERVICES
LYSAGHT & ASSOCIATES, P.A. HAS PERFORMED THE STRUCTURAL DESIGN
AND
PREPARED THE STRUCTURAL WORKING DRAWINGS FOR THIS PROJECT.
"CONSTRUCTION REVIEW" SERVICES ARE ALSO A PART OF OUR CONTRACT.
THE
CONTRACTOR MUST NOTIFY THE STRUCTURAL ENGINEER AT THE FOLLOWING
STAGES
OF CONSTRUCTION FOR A FIELD REVIEW OF THE WORK:
1. AFTER PLACEMENT OF COLUMN ANCHORAGE.
2. AFTER ERECTION OF THE STRUCTURAL STEEL.
3. AFTER COMPLETION OF THE STRUCTURAL SYSTEM, BEFORE INTERIOR
FINISHES ARE INSTALLED.
4. AT ANY STAGE OF CONSTRUCTION WHEN DESIGN OR CONSTRUCTION
PROBLEMS
ARE ENCOUNTERED.
A "CONSTRUCTION REVIEW REPORT" WILL BE SENT TO THE CONTRACTOR
FOLLOWING
EACH FIELD TRIP.
THE STRUCTURAL ENGINEER IS RESPONSIBLE FOR THE DESIGN OF THE
PRIMARY
STRUCTURAL SYSTEM, EXCEPT FOR THE COMPONENTS NOTED ABOVE.
RESPONSIBILITY FOR ANY SECONDARY STRUCTURAL AND NON-STRUCTURAL
SYSTEMS
NOT SHOWN ON THE STRUCTURAL PLANS RESTS WITH SOMEONE OTHER THAN
THE
STRUCTURAL ENGINEER.
THE STRUCTURAL ENGINEER IS NOT RESPONSIBLE FOR, AND WILL NOT
HAVE
CONTROL OF, CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES
OR
PROCEDURES, OR FOR SAFETY PRECAUTIONS AND PROGRAMS IN CONNECTION
WITH
THE CONSTRUCTION WORK; NOR WILL HE BE RESPONSIBLE FOR THE
CONTRACTOR'S
FAILURE TO CARRY OUT THE CONSTRUCTION WORK IN ACCORDANCE WITH
THE
CONTRACT DOCUMENTS.
FIELD MEASUREMENTS AND THE VERIFICATION OF FIELD DIMENSIONS ARE
NOT
PART OF THE STRUCTURAL ENGINEER'S RESPONSIBILITY. THE CONTRACTOR
MUST
CHECK ALL (ASSUMED) EXISTING CONDITIONS SHOWN ON THESE DRAWINGS
FOR
ACCURACY AND NOTIFY THE STRUCTURAL ENGINEER OF ANY
DISCREPANCIES.
CODE
BUILDING OCCUPANCY CATEGORY II
SNOW LOAD DATA :
SNOW EXPOSURE FACTOR 1.0
THERMAL FACTOR 1.0
ROOF SLOPE FACTOR 1.0
WIND LOAD DATA :
NOMINAL WIND SPEED, Vasd 89 MPH
WIND IMPORTANCE FACTOR 1.0
ULTIMATE WIND BASE SHEAR (x-x DIRECTION) 7.3 KIPS
ULTIMATE WIND BASE SHEAR (y-y DIRECTION) 17.0 KIPS
WIND PRESSURE FOR COMPONENTS / CLADDING PER ASCE 7-10
SEISMIC LOAD DATA :
MAPPED SPECTRAL RESPONSE ACCELERATION, Ss 0.154
MAPPED SPECTRAL RESPONSE ACCELERATION, S1 0.077
SITE CLASS D
SEISMIC DESIGN CATEGORY B
SPECIFICALLY DETAIL FOR
LATERAL DESIGN CONTROL WIND
THE 2015 NORTH CAROLINA EXISTING BUILDING CODE CLARIFIES ALL
REQUIREMENTS FOR "EXISTING BUILDINGS AND STRUCTURES." THESE
REQUIREMENTS INCLUDE, BUT ARE NOT LIMITED TO, ADDITIONS,
ALTERATIONS,
AND REPAIRS OF EXISTING STRUCTURES.
THESE CODE PROVISIONS HAVE BEEN INTERPRETED AS FOLLOWS:
1. THE EXISTING BUILDING IS EXEMPT FROM A WIND OR SEISMIC
ANALYSIS
BECAUSE THE MAIN WIND (AND SEISMIC) FORCE RESISTING SYSTEM WILL NOT
BE
ALTERED DURING THIS RENOVATION.
2. ALL EXISTING GRAVITY ELEMENTS THAT ARE AFFECTED BY THE
RENOVATION
MUST BE CHECKED FOR DESIGN LOADS SHOWN ABOVE, AND REINFORCED
AS
NECESSARY.
3. ALL DEFECTIVE STRUCTURAL ELEMENTS MUST BE REPAIRED OR
REPLACED.
THE SCOPE OF STRUCTURAL DESIGN IS ONLY AS NOTED IN THE DRAWINGS. IT
IS
THE RESPONSIBILITY OF THE GENERAL CONTRACTOR TO NOTIFY THE S.E.R.
IF ANY
DEFECTIVE, DETERIORATED, OR DAMAGED MEMBERS ARE FOUND, THAT ARE
NOT
SPECIFICALLY NOTED ON THE DRAWINGS.
ASSUMPTIONS
FOR PURPOSES OF THESE NOTES, ASSUMPTION SHALL BE DEFINED AS "TO
BELIEVE,
THINK, OR SUPPOSE A CONDITION TO BE TRUE." AN ASSUMPTION CAN NOT
BE
CONFIRMED BY THE STRUCTURAL ENGINEER BECAUSE IT IS BEYOND HIS SCOPE
OF
SERVICES AND/OR EXPERTISE. IF THE CLIENT REQUIRES CONFIRMATION OF
AN
ASSUMPTION, THEN ANOTHER EXPERT SHALL DO THE NECESSARY CALCULATIONS
AND
TESTING.
THE FOLLOWING ASSUMPTIONS HAVE BEEN MADE REGARDING THE STRENGTHS OF
THE
VARIOUS EXISTING STRUCTURAL COMPONENTS:
B. EXISTING CONCRETE, f'c 4,000 PSI
C. EXISTING REBAR, fy 60,000 PSI
D. STRUCTURAL STEEL, fy 33,000 PSI
STRUCTURAL STEEL
FABRICATE AND ERECT ALL STRUCTURAL STEEL IN ACCORDANCE WITH THE
AMERICAN
INSTITUTE OF STEEL CONSTRUCTION "SPECIFICATION FOR STRUCTURAL
STEEL
BUILDINGS (ANSI/AISC 360-14)".
STRUCTURAL STEEL SHALL RECEIVE ONE SHOP COAT OF RUST-INHIBITIVE
PAINT.
STEEL COLUMNS BELOW GRADE THAT ARE NOT ENCASED IN CONCRETE SHALL
BE
FIELD PAINTED WITH A WATERPROOF MASTIC COMPOUND TO PREVENT
CORROSION.
THE STEEL USED SHALL HAVE THE FOLLOWING MINIMUM YIELD STRESS:
WIDE FLANGE SHAPES ('W' SHAPES) 50 KSI (A992)
CHANNELS, ANGLES, PLATES, MISC. SHAPES 36 KSI (A36)
HSS TUBE SHAPES 46 KSI (A500, B)
USE 3/4" DIAMETER A-325N BOLTS FOR ALL STEEL TO STEEL CONNECTIONS
U.N.O.
BOLTS SHALL BE TIGHTENED TO THE SNUG TIGHT CONDITION UNLESS
NOTED
OTHERWISE. THE SNUG TIGHT CONDITION IS DEFINED AS THE TIGHTNESS
THAT
EXISTS WHEN ALL PLIES IN A JOINT ARE IN FIRM CONTACT.
USE F1554 (GRADE 36) BOLTS FOR ALL ANCHOR BOLTS U.N.O. HEADED WELD
STUDS
SHALL BE MADE OF MATERIAL CONFORMING TO ASTM A108. USE E-70
ELECTRODES
FOR ALL SHOP AND FIELD WELDING.
THE STEEL FABRICATOR SHALL DESIGN ALL STEEL TO STEEL CONNECTIONS
FOR THE
SERVICE LOAD REACTIONS SHOWN ON THE DRAWINGS (USE 6.0k MINIMUM
WHERE NOT
SHOWN). WHERE SINGLE SHEAR PLATES ARE USED, CONNECTIONS FOR WIDE
FLANGE
BEAMS SHALL HAVE THE FOLLOWING MINIMUM ROWS OF BOLTS:
W8, W10, W12 BEAMS (2) ROWS OF BOLTS
W14, W16 BEAMS (3) ROWS OF BOLTS
W18 BEAMS (4) ROWS OF BOLTS
W21 BEAMS (5) ROWS OF BOLTS
W24 BEAMS (6) ROWS OF BOLTS
FOR MISCELLANEOUS STEEL NOT SHOWN ON THESE DRAWINGS, SEE
ARCHITECTURAL
AND OTHER ENGINEERING DRAWINGS.
CONNECTIONS BETWEEN STRUCTURAL STEEL MEMBERS SHALL BE AS SHOWN
ON
STRUCTURAL DRAWING DETAILS. ALTERNATE CONNECTION DETAILS MUST
BE
APPROVED IN WRITING, BY THE STRUCTURAL ENGINEER OF RECORD, PRIOR TO
THE
SUBMITTAL OF SHOP DRAWINGS.
SUBMIT ERECTION AND SHOP DRAWINGS TO THE STRUCTURAL ENGINEER FOR
REVIEW
PRIOR TO FABRICATION.
LIGHT GAGE STRUCTURAL STEEL FRAMING
LIGHT GAGE STRUCTURAL STEEL INCLUDES ALL AXIALLY OR WIND LOADED
LIGHT
GAGE STEEL STUDS, TRACK, JOISTS, TRUSSES, BRIDGING AND
RELATED
ACCESSORIES AS INDICATED ON THE DRAWINGS.
DESIGN, FABRICATION AND ERECTION OF LIGHT GAGE STRUCTURAL STEEL
FRAMING
SHALL BE IN ACCORDANCE WITH THE AMERICAN IRON AND STEEL
INSTITUTE
"SPECIFICATION FOR THE DESIGN OF COLD-FORMED STEEL STRUCTURAL
MEMBERS".
THE STEEL USED SHALL HAVE THE FOLLOWING MINIMUM YIELD STRESS:
LIGHT GAGE STEEL STUDS 33 KSI
TRACKS FOR STEEL STUDS 33 KSI
LIGHT GAGE STEEL JOISTS & HEADERS 33 KSI
THE MEMBER DESIGNATIONS AND DETAILS SHOWN ON THESE DRAWINGS ARE
FROM THE
STEEL STUD MANUFACTURERS ASSOCIATION "PRODUCT TECHNICAL
INFORMATION".
THE CONTRACTOR MAY USE ANY LIGHT GAGE STEEL FRAMING THAT
MATCHES
MATERIAL AND PHYSICAL PROPERTIES INDICATED IN THIS
PUBLICATION.
ALL LIGHT GAGE STRUCTURAL STEEL FRAMING SHALL BE GALVANIZED,
IN
ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS.
SPLICES IN STEEL STUDS, JOISTS, AND HEADERS SHALL NOT BE
PERMITTED
EXCEPT WHERE SPECIFICALLY SHOWN ON THE DRAWINGS.
FASTENING OF COMPONENTS SHALL BE WITH SELF TAPPING SCREWS OR
WELDS.
WELDING SHALL BE IN ACCORDANCE WITH SECTION 6.0 OF THE AMERICAN
WELDING
SOCIETY'S "STRUCTURAL WELDING CODE - SHEET METAL" (AWS D1.3-8).
ALL
WELDS SHALL BE TOUCHED UP WITH A ZINC RICH PAINT.
SUBMIT ERECTION DRAWINGS TO THE ARCHITECT AND STRUCTURAL ENGINEER
FOR
REVIEW PRIOR TO FABRICATION. ERECTION DRAWINGS SHALL INCLUDE
SECTIONS,
PLANS OR ELEVATIONS DEPICTING COMPONENT LOCATION AND CONNECTION
DETAILS
SHOWING SCREW TYPES AND LOCATIONS, WELD LENGTHS AND LOCATIONS, OR
OTHER
RELATED FASTENER REQUIREMENTS.
SPECIAL INSPECTIONS (GENERAL)
SPECIAL INSPECTORS SHALL BE EMPLOYED BY THE OWNER AND SHALL
DEMONSTRATE
COMPETENCE/QUALIFICATION TO THE SATISFACTION OF THE BUILDING
OFFICIAL.
SPECIAL INSPECTORS SHALL KEEP RECORDS OF ALL INSPECTIONS. REPORTS
SHALL
BE FURNISHED TO THE BUILDING INSPECTOR, ARCHITECT, AND
STRUCTURAL
ENGINEER OF RECORD WITHIN TEN WORKING DAYS OF THE SITE VISIT.
SPECIAL INSPECTIONS ACTIVITIES REQUIRED FOR THIS PROJECT ARE
INDICATED
IN THE STATEMENT OF SPECIAL INSPECTIONS PROVIDED WITH THE
CONSTRUCTION
DOCUMENTS. INSPECTIONS FREQUENCY AND TYPE OF INSPECTION SHALL BE
PER THE
SCHEDULES INCLUDED WITH THE STATEMENT OF SPECIAL INSPECTIONS.
>500 sq ft0-10 sq ftZONE
0-10 sq ftZONE >100 sq ft
COMPONENTS AND CLADDING WIND LOADS (psf)
Q
h
a
a
a
a
4
5
55
5
4
AREA.
AWAY FROM THE SURFACES, RESPECTIVELY.
3. WIND PRESSURES MAY BE INTERPOLATED FOR EFFECTIVE
WIND AREAS BETWEEN THE SPECIFIED RANGES.
+16.0, -31.3
+19.8, -22.0
CONSTRUCTION
AR ANCHOR ROD
B/ BOTTOM OF
CG CENTER OF GRAVITY
CIP CAST IN PLACE
CJP COMPLETE JOINT PENETRATION
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
L PT LOW POINT
LSH LONG SIDE HORIZONTAL
LSV LONG SIDE VERTICAL
MAS MASONRY
NTS NOT TO SCALE
ASSOCIATION
PCA PORTLAND CEMENT ASSOCIATION
PCI PRECAST/PRESTRESSED CONCRETE INSTITUTE
PLYWD PLYWOOD
PRCST PRECAST
PROJ PROJECTION
PT POINT
SOG SLAB ON GRADE
SPA SPACES OR SPACING
THK THICK
GENERAL NOTES
03.15.2021
1925
NLH
CAL
BID / PERMIT SET
121 FAYETTEVILLE STREET RALEIGH, NC 27601
919.719.1800 T
919.833.0495 T
1
04/08/2021
08 3950 BULLET RESISTANT ALUMINUM DOOR AND STOREFRONT FRAME
SYSTEM.pdf
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including
General and Supplementary Conditions and Division 01 Specification
Sections, apply to this Section.
1.2 SUMMARY
B. Related Sections:
1. Section 08 3950 "Bullet Resistant Aluminum Door and Storefront
Frame System”
2. Section 08 4413 “Glazed Aluminum Curtain Walls.”
3. Section 08 7110 "Door Hardware.”
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product indicated. Include
construction details, material descriptions, dimensions of
individual components and profiles, and finishes for
aluminum-framed systems.
1. Certification: Provide printed data in sufficient detail to
indicate compliance with the contract.
B. Shop Drawings: For swinging doors. Include plans, elevations,
sections, details, and attachments to other work.
1. For entrance doors, include hardware schedule and indicate
operating hardware types, functions, quantities, and
locations.
C. Samples for Verification: For each type of exposed finish
required, in manufacturer's standard sizes.
D. Other Action Submittals:
1. Entrance Door Hardware Schedule: Prepared by or under the
supervision of supplier, detailing fabrication and assembly of
entrance door hardware, as well as procedures and diagrams.
Coordinate final entrance door hardware schedule with doors,
fram...
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: For swinging doors to include in maintenance
manuals.
1.7 QUALITY ASSURANCE
B. Accessible Entrances: Comply with applicable provisions in the
U.S. Architectural & Transportation Barriers Compliance Board's
ADA-ABA Accessibility Guidelines.
C. Preinstallation Conference: Conduct conference at Project
site.
1.8 PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of structural
supports for aluminum-framed systems by field measurements before
fabrication and indicate measurements on Shop Drawings.
1.9 WARRANTY
A. Special Warranty: Manufacturer's standard form in which
manufacturer agrees to repair or replace components of
aluminum-framed systems that do not comply with requirements or
that fail in materials or workmanship within specified warranty
period.
1. Failures include, but are not limited to, the following:
a. Structural failures including, but not limited to, excessive
deflection.
b. Noise or vibration caused by thermal movements.
c. Deterioration of metals, metal finishes and other materials
beyond normal weathering.
d. Failure of operating components.
2. Warranty Period: Five years from date of Substantial
Completion.
B. Special Finish Warranty: Manufacturer's standard form in which
manufacturer agrees to repair or replace components on which
finishes do not comply with requirements or that fail in materials
or workmanship within specified warranty period. Warran...
1. Warranty Period: 20 years from date of Substantial
Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: The basis-of-design shall be based on Aluminum
Bullet Resistant Door and Storefront Frame ABRD Series, as
manufactured by C.R. Laurence Co. Inc.
2.2 MATERIALS
A. Aluminum: Extrusions shall be 6063-T5 alloy and temper (ASTM
B221 alloy T5 temper). Fasteners, where exposed, shall be aluminum,
stainless steel or zinc plated steel in accordance with ASTM A 164.
Perimeter anchors shall be aluminum or steel, pro...
B. Finish: Aluminum extrusions shall be given a caustic etch
followed by an anodic oxide treatment to obtain Fluoropolymer paint
coating conforming with the requirements of AAMA 2605. Color shall
be a custom color to match the curtain wall finish.
C. Glazing: The glazing must be in accordance with U.L. 752 testing
standards (Level 3) and as specified in Section 08 800
Glazing.
2.3 ENTRANCE DOOR SYSTEMS
1. Door Construction: 2-3/16 inches overall thickness,
2. Door Design: As indicated.
a. Accessible Doors: Smooth surfaced for width of door in area
within 10 inches (255 mm) above floor or ground plane.
3. Glazing Stops and Gaskets: Manufacturer’s standard.
a. Provide nonremovable glazing stops on outside of door.
B. Entrance Door Hardware: As specified in Section 08 7110 "Door
Hardware."
C. Bullet Resistance: Install bullet resistant Level 3 fiberglass
per manufacturer’s requirements.
2.4 FABRICATION
A. Form or extrude aluminum shapes before finishing.
B. Weld in concealed locations to greatest extent possible to
minimize distortion or discoloration of finish. Remove weld spatter
and welding oxides from exposed surfaces by descaling or
grinding.
C. Entrance Doors: Reinforce doors as required for installing
entrance door hardware.
1. At exterior doors, provide weather sweeps applied to door
bottoms.
D. Entrance Door Hardware Installation: Factory install entrance
door hardware to the greatest extent possible. Cut, drill, and tap
for factory-installed entrance door hardware before applying
finishes.
E. After fabrication, clearly mark components to identify their
locations in Project according to Shop Drawings.
2.5 ALUMINUM FINISHES
A. High-Performance Organic Finish: 3-coat fluoropolymer finish
complying with AAMA 2605 and containing not less than 70 percent
PVDF resin by weight in both color coat and clear topcoat. Prepare,
pretreat, and apply coating to exposed metal surface...
1. Color and Gloss: Provide a custom finish to match the finish of
the existing curtain wall system.
PART 3 - EXECUTION
A. Examine areas and conditions, with Installer present, for
compliance with requirements for installation tolerances and other
conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions
have been corrected.
3.2 INSTALLATION
A. General:
1. Comply with manufacturer's written instructions.
2. Do not install damaged components.
3. Fit joints to produce hairline joints free of burrs and
distortion.
4. Rigidly secure nonmovement joints.
5. Install anchors with separators and isolators to prevent metal
corrosion and electrolytic deterioration.
6. Seal joints watertight unless otherwise indicated.
B. Install components plumb and true in alignment with established
lines and grades, and without warp or rack.
C. Install glazing as specified in Section 08 8000 "Glazing."
D. Entrance Doors: Install doors to produce smooth operation and
tight fit at contact points.
1. Exterior Doors: Install to produce weathertight enclosure and
tight fit at weather stripping.
2. Field-Installed Entrance Door Hardware: Install surface-mounted
entrance door hardware according to entrance door hardware
manufacturers' written instructions using concealed fasteners to
greatest extent possible.
3.3 ADJUSTING
A. Adjust operating entrance door hardware to function smoothly as
recommended by manufacturer.
1. For entrance doors accessible to people with disabilities,
adjust closers to provide a 3-second closer sweep period for doors
to move from a 70-degree open position to 3 inches (75 mm) from the
latch, measured to the leading door edge.
210408 WC PSC Skylight Struct REV 1.pdf
Sheets