China Creek Hydroelectric Project Water Shrew Survey
Toth and Associates
Environmental Services
China Creek Hydroelectric Project Water Shrew Survey
Prepared for:
Upnit Power Limited Partnership
5500 Ahahswinis Drive
Box 211
Port Alberni, B.C. V9Y 7M7
Prepared by:
Steve Toth, AScT, R.P.Bio.
Toth and Associates Environmental Services 6821 Harwood Drive
Lantzville, B.C. V0R 2H0
November, 2005
Toth and Associates
Environmental Services
TABLE OF CONTENTS
1.0 INTRODUCTION ...................................................................................................4
2.0 BACKGROUND .....................................................................................................4
2.1 Study Area 5
2.2 Water Shrew Ecology 5
3.0 METHODS ..............................................................................................................7
4.0 RESULTS ..............................................................................................................10
4.1 Sample Site Descriptions 10
5.0 DISCUSSION........................................................................................................18
6.0 RECOMMENDATIONS.......................................................................................22
7.0 REFERENCES ......................................................................................................23
LIST OF TABLES
Table 1. Pitfall trapping results .........................................................................................10
LIST OF FIGURES
Figure 1. Study Area ...........................................................................................................7
Figure 2. Sample Site Locations .......................................................................................16
LIST OF APPENDICES
Appendix A: Field Forms .................................................................................................25
Toth and Associates 4
1.0 Introduction
Toth and Associates Environmental Services completed the Vancouver Island water shrew
(Sorex palustris brooksi) pitfall trapping surveys of the China Creek run-of-the-river
Hydroelectric Project south of Port Alberni, B.C. during August 2 – 6, 2005. A total of 40
pitfall traps were installed within the study area. One Vancouver Island water shrew was
captured approximately 200m downstream of the intake weir location on August 6, 2005. Two
vagrant shrews, three dusky shrews and one deer or Keen’s mouse were also captured. Trap
mortalities included one vagrant shrew, one dusky shrew and unfortunately, the water shrew.
2.0 Background
The initial environmental impact studies conducted on China Creek during October –
November 2003 and March 2004 by Cordillera Environmental Services did not include
sampling for water shrews. However, Cordillera did recognize the potential for Vancouver
Island water shrews on China Creek (Cordillera Environmental Services, 2004). The Ministry
of Water, Land and Air Protection (MWLAP) and the Canadian Wildlife Service (CWS) also
identified the potential for water shrews. Water shrews were not observed during any of the
wildlife surveys conducted on the China Creek by Cordillera, during any of the fisheries studies
conducted by Ecofish Research Ltd. and CBR and Associates, or during riverine bird surveys
conducted in May and July 2005 by Toth and Associates.
As the wildlife surveys conducted by Cordillera did not include riparian pitfall trapping, it was
recommended by Public Works and Government Services Canada (PWGSC) in their Canadian
Environmental Assessment Act (CEAA) Screening Report of the China Creek Hydropower
Project that directed pitfall trapping surveys should be conducted for water shrews
(Environmental Assessment Screening Report, October 2004). The PWGSC indicated in the
CEAA report that appropriate agency(s) (MWLAP) must be contacted prior to the initiation of
the surveys so the surveyor may receive the most recent Best Management Practices
Guidelines. All field investigations would follow the most recent sampling guidelines
(Recovery Team/Resource Information Standards Committee) to evaluate the extent and
suitability of Vancouver Island Water Shrew habitat and their presence.
In June 2005 Toth and Associates Environmental Services provided an outline for water shrew
surveys for the China Creek Run-of-the-river Hydroelectric Project. The survey was designed
China Creek Water Shrew Survey Report
Toth and Associates 5
at the Presence / Not Detected level. Toth and Associates has conducted over 43 environmental
assessments of land developments, including 9 environmental impact assessments of run-of-
the-river hydroelectric projects on Vancouver Island, 6 of which have included a riparian pitfall
trapping component.
2.1 Study Area
The China Creek Hydropower Project is located approximately 11 km southeast of Port
Alberni, B.C. The proposed Study Area for the water shrew pitfall trapping surveys was from
the proposed powerhouse / tailrace location to the intake weir location, providing an overall
study area length of approximately 4.9 km (Figure 1). In addition, an effort would be made to
include at least one sampling area upstream of the intake location, that according to the
available literature, had habitat with a higher capability / probability of supporting a water
shrew population.
2.2 Water Shrew Ecology
The Provincially red-listed Vancouver Island sub-species of common water shrew (Sorex
palustris brooksi) is restricted to Vancouver Island. The water shrew is a riparian dependent
species reliant upon intact functional riparian areas and is strongly associated with the land /
water interface. Most of the approximately 20 recorded occurrences are from swampy low
gradient productive watercourses such as Robertson Creek, tributaries to Lowry Lake, Black
Creek and tributaries to French Creek near Coombs. The common water shrew feeds primarily
on aquatic invertebrates but will also take terrestrial invertebrates, small fish and amphibians.
The Vancouver Island water shrew is not included on Schedule 1 of the Federal Species at Risk
Act.
The Vancouver Island Water Shrew is a subspecies of the common water shrew, identified as
occurring only on Vancouver Island, British Columbia. It is a Provincially red-listed species,
indicating that it is a candidate for endangered status. Only 9 specimens had been collected
from 7 localities on Vancouver Island during the period of 1897 to 1984 (Hartman, 2002).
Water shrew inventories completed by Lisa Hartman in 1997 (Results of 1997 Inventory of
Vancouver Island Water Shrew, 2002) yielded an additional 14 water shrew captures. Most of
the available literature concerning water shrews is based on the mainland subspecies; little in
the way of detailed habitat information was available for the Vancouver Island subspecies prior
to the work conducted by L. Hartman.
China Creek Water Shrew Survey Report
Toth and Associates 6
Two subspecies of common water shrew are recognized within British Columbia: S. p. brooksi,
on Vancouver Island, and S. p. navigator, occurring throughout the mainland of the province. A
second species of water shrew (Sorex bendirii) occupying the lowland areas of the Lower
Mainland and Fraser Valley is also red-listed (Nagorsen 1996). Only two other shrew species
occur on Vancouver Island; the vagrant shrew (S. vagrans) and the dusky shrew (S.
monticolus), both are terrestrial species.
The Vancouver Island water shrew is identifiable by its large size (in comparison to vagrant
and dusky shrews), charcoal grey dorsal fur, silver-grey ventral fur and bicoloured tail with
dark above and white-silver below. A key identifying characteristic is that the hind feet are
large and have a thick fringe of short, stiff hairs around the outer margin. They also emit a
fairly strong, musky odour that is somewhat similar to that of a skunk.
The water shrew can be active at all hours, but has two peak times of activity; within one hour
of dawn and one hour after dusk. The water shrew dives readily into water and can remain
submerged for periods of up to 30 seconds. The stiff hairs on the water shrew’s feet allow this
species to actually run on the water’s surface for short distances. The water shrew’s senses are
not well understood, but their sense of smell is well developed and it is thought that they may
use high frequency sounds for echolocation, as captive shrews continuously emitted a series of
rapid squeaks (Nagorsen1996). We have also heard this same “clicking squeak” emitted from
terrestrial shrews while foraging.
The water shrew feeds primarily on aquatic insects such as caddisflies, craneflies, stoneflies,
and mayflies, but will feed opportunistically on terrestrial prey including, slugs, spiders,
beetles, snails, crickets and have also been documented eating salmonid fry in fish hatcheries.
Water shrews hoard food in caches for later consumption.
The breeding season extends from December to September with pregnant females documented
from May to September. Two – three litters can be produced in a breeding season with 3 – 10
young in a litter. The maximum lifespan is approximately 18 months. Predators of Vancouver
Island water shrews likely include mink, herons, owls and snakes.
Shrews in general are difficult to study in the field because their small body size and high
metabolism render them vulnerable to trap mortality.
China Creek Water Shrew Survey Report
Toth and Associates 7
Figure 1. Study Area
3.0 Methods
The surveys were conducted according to Resources Inventory Standards Committee’s (RISC)
Standards for Components of British Columbia’s Biodiversity No. 31: Inventory Methods for
Small Mammals: Shrews, Voles, Mice and Rats (Version 2.0, May 1998) with methodologies
modified to include a longer trap check frequency and different pitfall trap lay-out. It was
determined early within the water shrew survey logistics and design phase that the RISC
recommended trap check frequency (every 1.5 – 2.0 hours) and pitfall transect lay-out would be
extremely difficult to achieve due to the limited access, rough topography and large size of the
study area. Trudy Chatwin (Rare and Endangered Species Biologist) at the Ministry of
Environment (MOE) in Nanaimo was contacted regarding modifying the water shrew inventory
methodologies. Trudy Chatwin asked us to contact Vanessa Craig, Ph.D., R.P. Bio. (Ecologic
Research) for detailed methods and practical advice. Vanessa Craig provided us with good
practical information regarding trap check frequency as it related to shrew pitfall trapping
mortality rates and a draft copy of the Vancouver Island water shrew inventory conducted by
Lisa Hartman in 1997 (Hartman 2002). Ross Vennesland (Species at Risk Recovery Biologist)
at MWLAP in Surrey was also contacted regarding the China Creek water shrew survey. Mr.
Vennesland is the Chairperson of the Provincial Pacific Water Shrew Recovery Team. Mr.
China Creek Water Shrew Survey Report
Toth and Associates 8
Vennesland provided us with a draft copy of the Best Management Practices Guidelines for
Pacific Water Shrew in Urban and Rural Areas (Craig and Vennesland, April 2005). The trap
check frequency recommended by V. Craig and L. Hartman was every 3 – 4 hours, and by R.
Vennesland was every 6 – 8 hours. The information provided by the persons contacted, and
within the reports and BMPs indicated that shrew trap mortalities are high regardless of trap
check frequency and that during L. Hartman’s 1997 inventory only one water shrew survived
capture.
A B.C. Ministry of Environment Wildlife Permit (Permit # NA05 – 14343) was issued to Toth
and Associates for this project.
Riparian area / river shoreline pitfall trapping surveys are the preferred method for surveying
common water shrews. Pit-fall index trapping lines were stratified according to accessibility
and to provide appropriate coverage of the diversion reach of the China Creek hydroelectric
project. Sample sites were biased towards covering those locations identified during the
background information review as having the most suitable water shrew habitat within the
diversion reach, and therefore the highest probability of success. Sample sites included the two
areas previously identified by Cordillera Environmental Services (2004) as having potential
water shrew habitat; namely the intake weir and the small tributary located approximately 200
m downstream from the weir location.
The RISC recommended protocol for water shrew surveys is to set an index line (transect) of
20 pitfalls at 15-m intervals, for a minimum of 300 m along the edge of the waterway being
sampled. However, as the goal was to determine presence and to appropriately cover the
diversion reach, we proposed pitfall sets at variable intervals over a transect length to be
determined by the habitat suitability at each sampling site. The diversion reach consists of
steep bedrock influenced channel morphology with only small areas of potential water shrew
habitat between bedrock chutes and cascades. Adherence to the 300 m transect length and 15
m interval would mean that much of the trapping effort on any transect would be expended in
areas with little potential of success, and would not be possible as pitfall trapping requires loose
substrates.
Pitfall traps were located within 5 - 15 cm of the wetted edge of China Creek and within 5 cm
of the water surface elevation. As water shrew pitfall trapping success is reliant on stable
stream flows, all reasonable attempts were made to conduct surveys during appropriate low
flow and fair weather conditions.
The RISC guidelines recommend that index traplines (transects) should be active up to a
maximum of 6 days to allow resident individuals sufficient time to encounter the trap line.
China Creek Water Shrew Survey Report
Toth and Associates 9
Longer periods may be required for rare species with long latency of detection periods;
however these latency of detection parameters had not yet been determined for water shrews.
Field gear included chest waders, cruiser vests, safety equipment, RISC field forms and field
notebooks, detailed maps of the study area, handheld GPS, headlamps, and waterproof 35 mm
camera. Trapping gear included:
• Pitfall traps
• Vapour barrier plastic (medium weight) for fencing
• Fencing tie wire
• Bait for traps
• Bedding and Floats for traps
• Cotton gloves
• Flagging tape
• Plastic sample bags
• A small vial of 10% sugar in water
• RBCM Handbook: Opossums, Shrews and Moles of British Columbia (Nagorsen1996)
• Pack board
Two sizes of Pitfall containers were used: 34 plastic buckets measuring 23.5 cm wide x 24 cm
deep, and 6 buckets measuring 20 cm wide x 24 cm deep. Drift fences were constructed out of
2 – 4 m long sections of 35 cm high vapour barrier plastic, staked in place with fencing wire.
Pitfall traps were also placed against naturally occurring structures such as logs and large
boulders. Pitfalls were dried, weighted down with cobble sized rocks to prevent floating,
supplied with bedding material (dry moss), bait (tuna cat food), and a cover (pieces of tree bark
or skunk cabbage leaves) raised approximately 5 – 8 cm above the lip of the bucket.
As the objective of the study was to determine the presence of water shrews within the study
area, pitfall traps were active 24 hours a day to maximize trapping effort. Traps were checked
every 6 - 8 hours during daylight hours. It was anticipated that to achieve this trap check
frequency, a more or less continuous circuit of the trap sets would be required during daylight
hours. The locations of the sample sites are indicated on figure 2.
Basic stream and riparian habitat conditions were recorded at each sampling unit on standard
stream survey Site Cards. The sites and trap sets were photographed and geo-referenced with a
handheld GPS.
All animals captured at each trap station were identified to species and photographed. The
water shrew trap mortality was placed in an individual labelled plastic bag and frozen as soon
as possible.
China Creek Water Shrew Survey Report
Toth and Associates 10
Observations of other fish, wildlife, and listed vegetation encountered during these surveys
were also recorded in field notes. The field surveys were conducted by Steve Toth and
Cameron Tatoosh.
4.0 Results
The results of the field surveys are provided in Table 1, below and in Field Forms (Appendix
A). The surveys performed covered approximately 756 m of the 4.9 km diversion reach, as
well as approximately 375 m of stream channel upstream of the diversion reach.
Approximately 3,152 hours of trap effort was applied.
Table 1. Pitfall trapping results
Trap
Site
# of
traps
Site
Length
(m)
Duration
(hours)
Total Effort
(hours)
Catch
1 6 172 103 618 0
2 5 198 96 480 2 vagrant shrews
3 5 136 76 380 0
4 8 133 68 544 1 dusky shrew, 1 mouse
5 6 117 70 420 1 water shrew
6 10 375 71 710 2 dusky shrews
The China Creek CEAA Screening Report produced by the PWGSC (2004) states in Appendix
D that “if SAR (Species at Risk) are identified to be present within the project area or identified
as being impacted due to project activities either prior to or during the construction activities, or
throughout the operation of the project, the appropriate agencies must be notified prior to the
commencement of any further activities”. Trudy Chatwin, Ministry of Environment Rare and
Endangered Species Biologist in Nanaimo was contacted on August 17, 2005 and informed of
the capture of a water shrew on China Creek.
4.1 Sample Site Descriptions
Site 1 was located upstream from the lower bridge crossing, located approximately 30 m
upstream of the powerhouse location (Photograph 1). Six pitfall traps were installed over
approximately 172 m on the south side of the creek. The site was primarily comprised of an
expansive gravel bar with some bedrock morphology near the upstream end of the site. Forest
China Creek Water Shrew Survey Report
Toth and Associates 11
cover on both sides of the stream at site 1 was comprised of a leave strip of young forest aged
second growth western hemlock, Douglas fir and red alder. The leave strip width varied
between 10 – 30 m. Stream banks were stable, but with little large woody debris or
complexity. Five of the pitfall traps were placed along the wetted edge of China Creek, while
one trap was placed at the wetted edge of an isolated off channel pool next to the south bank.
There were no captures at Site 1.
Photograph 1. View downstream through Site 1.
Site 2 was located approximately 1.5 km upstream of the powerhouse location. The site
consisted of 5 pitfall traps placed over approximately 198 m on the north side of the stream
(Photograph 2). Stable streambanks were located in close proximity to the water’s edge for
most of the site. Substrates consisted of cobble and small – medium sized boulders for most of
the site. Forest cover on both sides of the stream was comprised of mature forest cover,
dominated by western hemlock, western redcedar and Douglas fir with bigleaf maple and red
alder. Large woody debris was rare at this site. Two vagrant shrews were captured at Site 2
(Photograph 3).
China Creek Water Shrew Survey Report
Toth and Associates 12
Photograph 2. View upstream through Site 2.
Photograph 3. Vagrant shrew in pitfall trap at Site 2.
Site 3 was located approximately 150 m downstream of the City of Port Alberni intake dam
(Photograph 4). Five pitfall traps were installed over 156 m of stream with 4 traps on the south
side of the stream and 1 trap on the north side. Stream substrates were dominated by boulder
China Creek Water Shrew Survey Report
Toth and Associates 13
blocks and sorted gravels. The south bank was composed of fines and bedrock blocks while
the north side consisted of large diameter rip-rap. Forest cover consisted of mature coniferous
western hemlock dominated forest cover on the south side of the stream and a thin strip (5 – 10
m) of young red alder dominated tree cover below the intake dam access road on the south side
of China Creek. The resident at the house located at the city intake dam mentioned that the
water shrew we captured was the same animal that his dog was observed to capture (and eat)
below the intake dam on occasion. High numbers of large sized crickets were captured in
pitfalls at Site 3. Small mammals were not captured at this location.
Photograph 4. View upstream through Site 3.
Site 4 was located on a groundwater fed fish bearing tributary watercourse located on the north
side of China Creek approximately 200 m downstream of the intake weir location (Photograph
5). This site appeared to represent the best potential habitat for water shrews, with stable
stream flows and stream banks and abundant functional large woody debris. Eight pitfall traps
were placed along 133 m on the south side of the tributary. The steep, woody debris lined
banks and lack of bedload aggradation made this a difficult site for placement of pitfall traps.
Forest cover consisted of young western hemlock dominated tree cover with lush herb and
shrub layer development in the vicinity of the tributary. Although this site likely represented
the habitat with the highest capability of supporting water shrews, it was noted that aquatic
insects on stream substrates were rare in this tributary. One dusky shrew and one mouse (cover
photo) were captured at Site 4.
China Creek Water Shrew Survey Report
Toth and Associates 14
Photograph 5. View downstream through Site 4.
Site 5 was located immediately upstream of the confluence with the Site 4 tributary on China
Creek (Photograph 6). Six pitfall traps were installed over 117 m with five traps on the north
side and 1 trap on the south side of China Creek. Substrates consisted of boulders, bedrock
blocks and small amounts of sorted gravels. Forest cover consisted of young western hemlock
dominated coniferous tree cover. Stream banks were stable and had significant amounts of
China Creek Water Shrew Survey Report
Toth and Associates 15
stable large woody debris and tree roots. The pitfall trap placed at the upstream end (UTMs
10.376469.5447608) of Site 5 captured one water shrew (Photograph 7).
Photograph 6. View downstream through Site 5.
Photograph 7. View of Vancouver Island water shrew captured at Site 5.
China Creek Water Shrew Survey Report
Toth and Associates 16
Figure 2. Sample Site Locations
China Creek Water Shrew Survey Report
Toth and Associates 17
Site 6 consisted of 10 pitfall traps installed over 375 m of stream upstream and downstream of
the upper bridge crossing on China Creek (Photograph 8). This site had good potential for
water shrews due to the lower gradient and more meanderous channel morphology. Forest
cover consisted largely of mature red alder, bigleaf maple, western redcedar and western
hemlock with a well developed shrub and herb layer. Streambanks and bedload were stable,
with the wetted edge of the river in close proximity to the stream banks in most locations. Two
dusky shrews were captured at Site 6. Both captures occurred at one pitfall site, but did not
appear to be the same shrew (Photograph 9).
Photograph 8. View upstream through Site 6.
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 18
Photograph 9. View of dusky shrew captured at Site 6.
5.0 Discussion
One water shrew was captured during 3,152 hours of trapping effort. The fact that a water
shrew was captured on China Creek likely indicates that low numbers of water shrews are
present throughout the watershed in suitable habitats. The population may be limited by habitat
suitability and availability of prey.
Water diversion and operation of the facility may result in alienation of the Vancouver Island
Water Shrew from China Creek and fragmentation and/or disruption of their habitat (PWGSC
2004). However, activities associated with the City water intake, logging and mining may
cumulatively have had similar effects.
With the proposed release flows, there will be a reduction in wetted perimeter, water depth,
water velocity and frequency of flushing flows, thus reducing the area for fish habitat and
possibly affecting the aquatic ecosystem (PWGSC 2004). Although the project will reduce
flows and instream aquatic habitat in the diversion reach, DFO has required that a minimum
conservation flow of 15% MAD (0.51 cms at the intake) be maintained and that post-
construction flow monitoring must be undertaken directly downstream of the intake to ensure
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 19
that the minimum conservation flow is maintained at all times. DFO has also required the
development and submission of a ramping strategy to protect fish and aquatic habitat during the
shut down and start up of operations and a detailed monitoring plan for construction and post-
construction of the project. A detailed Environmental Management Plan, which provided
specific information on construction mitigation measures to be implemented during all phases
of this project was prepared and submitted to DFO prior to commencement of project
construction.
The operation of the China Creek Hydroelectric Project has the potential to impact metal
concentrations in China Creek (Public Works and Government Services 2004). Naturally
occurring zinc levels in China Creek already exceed the limits required for the protection of
aquatic life. These elevated metals may be a limiting factor to aquatic production and therefore
could also have an influence on water shrew populations. Monitoring recommendations
provided in the ECOfish report (2004), included monitoring for zinc, nickel, silver, total
phosphate and titanium. Environment Canada has recommended that if analysis or monitoring
indicates a change in levels of zinc or nickel that are above recommended concentrations for
aquatic life, mitigation measures are to be developed and implemented.
Based on the limited habitat information provided by the single capture of a water shrew during
this study, it would appear that suitable habitats might include those areas where the wetted
edge of China Creek is in close proximity to a stable stream bank. Functional, stable large
woody debris, overhanging vegetation and tree roots may also be an important factor.
However, Hartman (2002) did not find any clear association between water shrew occurrences
and the habitat variables measured. Water shrews were found in young and old forest sites
from 10m to 320m in elevation and were found in streams characterized by a range of widths,
depths, flows and bed materials. More quantitative data is needed to identify site-specific water
shrew habitat characteristics / requirements that would not be achievable using the current
RISC recommended sampling protocols.
All of the water shrew trapping reference material reviewed suggested that placement of pitfall
traps in close proximity to the water’s edge was crucial to water shrew capture success.
However, we would contend that the water shrew must navigate from its burrow site to the
water to forage and therefore should be subject to interception by pitfalls or other trap types
placed in this area. While the current pitfall trapping method does provide information
regarding shrew presence and foraging habitat, it does not provide precise information on water
shrew shelter / burrow habitat, as it is not possible to tell with any certainty where the captured
water shrew came from. A possible alternate trapping method could involve extending a
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 20
measured section of drift fence from the stream bank in a shallow V shape, with placement of a
pitfall in the notch of the V fence. This set-up could be moved every 24 – 48 hours to sample
the next section of stream bank. This method would be entirely quantitative, allowing
estimation of area sampled, habitat used / not used, likely reduce mortality rates and would be
less subject to flooding / floating, as it would not be necessary to place pitfalls in close
proximity to the water’s edge. Most importantly it would allow accurate evaluation of what
constitutes good water shrew shelter / burrow habitat. This information potentially could be
applied to similar habitats elsewhere, and could eventually provide estimates of habitat
capability / relative abundance. Captured shrews could be marked with hair dye and the stream
bank within the capture site could be monitored for water shrew activity (essentially recaptures)
using remote cameras. The effective range on most of the commercially available remote
cameras is approximately 10 - 20 m, but due to the small size and heat signature of a shrew it
would be necessary to use one camera approximately every 5 m. Remote camera sites could be
baited to draw small mammals within close range of the camera. The use of remote cameras
would also provide valuable information on water shrew activity (i.e. peak periods, duration,
frequency).
Water shrews are noted for their strong musky odour, produced by numerous scent glands on
the body; most predominantly the flank glands on male shrews. A potential method for water
shrew detection of which we have not found any mention in the literature, but may be highly
effective, would be to use dogs that have been trained to detect the “skunky” odour of water
shrews.
Although the recorded number of captures and locations of water shrews on Vancouver Island
are low, it is not unheard of for this species to be captured in minnow traps during fisheries
surveys or observed by others who work in the bush, but is generally not reported or is
mistaken for another species. We are aware of several instances of multiple water shrews being
captured in minnow traps and have made attempts to provide this information to the B.C. CDC.
Possible areas that are not utilised by water shrews may include those areas on China Creek
with wide gravel / cobble bars, unstable banks with little habitat complexity and areas of
bedload aggradation. However, until further site specific data is collected regarding water
shrew habitat utilisation and life requisite requirements, all the riparian and stream channel
habitat on China Creek should be considered as potential critical habitat for the China Creek
water shrew population. Unfortunately, blasting and construction of the intake weir site had
already commenced prior to this study; it is not possible to tell if construction activities resulted
in any water shrew mortalities.
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 21
The construction of the penstock has primarily occurred outside of the riparian area and the
likely zone of water shrew utilization. Two footprint impacts have been realised at the
powerhouse and intake weir location, resulting in the alienation of approximately 2,600 m2 of
streamside habitats.
Considerable loss of primarily terrestrial vegetation and wildlife habitat has resulted from the
construction of the intake, penstock, and access roads. Some vegetation clearing did occur
during the breeding bird season. It is not known if a breeding bird survey was undertaken of the
penstock route prior to construction.
During this study adult red-legged frogs were observed frequently along China Creek.
Previous information indicated that it was unlikely the hydro project would have an impact on
the blue-listed red-legged frog population. However, from what was observed during this
study, reduced flows as a result of hydro project operations may have an impact on red-legged
frogs within the diversion reach through reduction of aquatic habitat. It is important that
restoration of the penstock and access road areas include reinstatement of coarse woody debris
in these areas.
It is difficult to assess the potential impacts on China Creek’s water shrew population posed by
the operation of the China Creek Hydroelectric Project. China Creek is typical of previously
logged Vancouver Island streams, with high peak flows and quick response times. The valley
is narrow and steep sided with little in the way of side channel or off channel fish habitats.
Reduced average flows may have an initial impact by increasing the distance between the
stream bank and the wetted edge of the creek. However, it is unlikely that this area will be
significantly reduced from current conditions during the peak period of water shrew activity of
approximately May – September, due to the requirements for maintaining instream flows for
resident fish populations during that same period. Likewise, the project will not have a
significant effect on reducing peak flood flows.
Flow control through the diversion reach resulting from hydro operations may actually result in
a net increase in riparian habitats as the land / water interface is colonized by plants, effectively
reducing the distance between the riparian edge and the edge of the water in some locations
(i.e. large gravel bars). Reduced flows may also result in a net increase in aquatic insect
populations by creating a more stable environment, reducing bedload movement, allowing
increased periphyton growth, and allowing nutrients to remain in the system for longer periods.
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 22
6.0 Recommendations
It is imperative that the China Creek project includes continued post-construction monitoring of
the China Creek water shrew population. Given the very short life-span of this species of 12 –
18 months, two or three years of poor recruitment / survivorship as a result of hydroelectric
operations could result in loss of this red-listed species from the diversion reach of China
Creek. Therefore, it is important to determine whether or not the hydroelectric project’s
operation is having a negative impact on the China Creek water shrew population.
We recommend that there be continued inventory of water shrews on China Creek in 2006 with
follow-up monitoring in 2007 and potentially 2008, depending upon initial results from 2006,
2007. The objectives of the inventory should be to ascertain extent of occurrence (using RISC
standards), habitat utilisation (capability / suitability) and relative abundance (using methods
discussed in Section 5.0), possible limiting factors and habitat mitigation / compensation
strategies. The inventory should include detailed surveys of aquatic and terrestrial insect
production. The objectives of follow-up surveys should be to monitor / evaluate the effects of
the China Creek Hydropower Project’s operations on the water shrew population. All water
shrew surveys undertaken will require increased trap check frequencies / field effort to ensure
that surveys result in minimal water shrew trap mortalities.
Sincerely,
Steve Toth, AScT, R.P.Bio.
Toth and Associates Environmental Services
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 23
7.0 References
B.C. Ministry of Environment, Lands and Parks, B.C. Ministry of Forests. 1998. Field Manual
for Describing Terrestrial Ecosystems, Land Management Handbook No. 25. 214 pp.
B.C. Ministry of Environment, Lands and Parks, Resources Inventory Branch. 1998. Species
Inventory Fundamentals. Standards for Components of British Columbia’s Biodiversity
No. 1, Version 2.0. 119 pp.
B.C. Ministry of Environment, Lands and Parks, Resources Inventory Branch. 1998. Inventory
Methods for Small Mammals: Shrews,Voles, Mice & Rats. Standards for Components
of British Columbia’s Biodiversity, No. 31, Version 2.0. 131 pp.
Cordillera Environmental Services 2004. China Creek Power Project Wildlife Impact
Assessment and Penstock Stream Crossing Inventory.
Craig, V. and R. Vennesland. April 2005. Best Management Practices Guidelines for Pacific
Water Shrew in Urban and Rural Areas, Working Draft. 38 pp.
Demarchi, D. 1996. An introduction to the ecoregions of British Columbia. MELP, Wildlife
Branch. Victoria, B.C. 46 pp + appendices.
ECOfish, March 2004. China Creek Hydroelectric Project – Assessment of Fish Habitat
Impacts and Mitigation / Compensation.
Green, R.N. and K. Klinka. 1994. A field guide for site identification and interpretation for the
Vancouver Forest Region. Land Management Handbook Number 28. BC Ministry of
Forests. Victoria, B.C. 285 pp.
Hartman, L. 2002. Results of 1997 Inventory of Vancouver Island Water Shrew.
Luttmerding, H.A., D.A. Demarchi, E.C. Lea, D.V. Meidinger and T. Vold. 1990. Describing
Ecosystems in the Field, Second Edition. BC Ministry of Environment, Lands and
Parks, BC Ministry of Forests. Victoria, B.C. 213 pp.
Meidinger, D. and J. Pojar. 1991. Ecosystems of British Columbia. BC Ministry of Forests.
Victoria, B.C. 330 pp.
Nagorsen, D. 1996. Opossums, Shrews and Moles of British Columbia. Volume 2: The
Mammals of British Columbia. Royal British Columbia Museum Handbook. Victoria,
B.C. 169 pp.
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 24
Nagorsen, D. 1990. The Mammals of British Columbia: A Taxonomic Catalogue. Royal British
Columbia Museum, Memoir No. 4. Victoria, B.C. 140 pp.
Nuzdorfer, F.C., N.L. Nuzdorfer, A.M. Scagel, K. Klinka, T. Lewis, P. Courtin and R.N.
Green. 1994. Biogeoclimatic Units of the Vancouver Forest Region, Map Sheet 5 of 6.
Southern Vancouver Island and Sunshine Coast. B.C. Ministry of Forests. Prepared by:
Hugh Hamilton Ltd. Vancouver, B.C.
Public Works and Government Services Canada, Environmental Services – Pacific Region,
October 2004. Environmental Assessment Screening Report of the China Creek Hydro
Power Project.
China Creek Water Shrew Survey Report
Toth and Associates 25
Appendix A: Field Forms
Project Name China Creek Hydroelectric Project Water Shrew Survey Surveyors: Steve Toth, Cameron Tatoosh
Dates: August 2 – 6, 2005
# of Transects 6 Transect Lengths 1 = 172 m, 2 = 198 m, 3 = 136 m, 4 = 133 m, 5 = 117 m, 6 =
375 m
UTMs of d/s end 1 = 10.373272.5449500
2 = 10.373660.5449138
3 = 10.374338.5448658
4 = 10.376460.5447643
5 = 10.376511.5447620
6 = 10.378865.5446869
UTMs of u/s end 1 = 10.373341.5449416
2 = 10.373695.5448954
3 = 10.374387.5448585
4 = 10.376479.5447581
5 = 10.376602.5447595
6 = 10.379118.5446974
Transect Effort 1 = 618 hrs, 2 = 480 hrs, 3 = 380 hrs, 4 = 544 hrs, 5 = 420 hrs, 6 = 710 hrs
Weather: Clear, warm and sunny, no precipitation, winds calm.
Survey Type Riparian Pitfall Trapping Site # Trap # Date Set
Time
Date Check
Time
Captures
Comment
Date Check
Time
Captures
Comment
Date Check
Time
Captures
Comment
1 1 Aug. 2 09:00 Aug. 4 08:40 0 Aug. 5 15:20 0 Aug. 6 15:25 0
1 2 Aug. 2 10:00 Aug. 4 08:42 0, floated Aug. 5 15:25 0 Aug. 6 15:30 0
1 3 Aug. 2 10:10 Aug. 4 08:53 0 Aug. 5 15:35 0 Aug. 6 15:35 0
1 4 Aug. 2 10:25 Aug. 4 09:00 0 Aug. 5 15:45 0 Aug. 6 15:45 0
1 5 Aug. 2 10:40 Aug. 4 09:05 0 Aug. 5 15:55 0 Aug. 6 15:50 0
1 6 Aug. 2 11:00 Aug. 4 09:10 0, floated Aug. 5 16:00 0 Aug. 6 16:00 0
2 1 Aug. 2 14:00 Aug. 4 10:13 0, floated Aug. 5 09:35 0 Aug. 6 13:45 0
2 2 Aug. 2 14:15 Aug. 4 10:15 0 Aug. 5 09:45 0 Aug. 6 13:55 1 vagrant, mort.
2 3 Aug. 2 14:25 Aug. 4 10:20 crickets Aug. 5 09:55 0 Aug. 6 14:15 0
2 4 Aug. 2 14:45 Aug. 4 10:24 1 vagrant, mort Aug. 5 10:00 0, wrecked by bear, pulled Aug. 6 14:20 0
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 26
2 5 Aug. 2 15:10 Aug. 4 10:30 0 Aug. 5 10:20 0, wrecked by bear Aug. 6 14:30 0
3 1 Aug. 3 08:35 Aug. 4 11:00 0 Aug. 5 11:45 0 Aug. 6 12:45 0
3 2 Aug. 3 08:45 Aug. 4 11:05 0 Aug. 5 11:50 crickets Aug. 6 12:50 crickets
3 3 Aug. 3 08:55 Aug. 4 11:10 crickets Aug. 5 11:55 crickets Aug. 6 12:55 crickets
3 4 Aug. 3 09:10 Aug. 4 11:15 crickets Aug. 5 11:58 crickets Aug. 6 13:00 crickets
3 5 Aug. 3 09:30 Aug. 4 11:20 0 Aug. 5 12:25 0 Aug. 6 13:05 0
4 1 Aug. 3 14:45 Aug. 4 12:10 0 Aug. 5 13:30 0 Aug. 6 10:00 0
4 2 Aug. 3 14:55 Aug. 4 12:15 0 Aug. 5 13:35 0 Aug. 6 10:05 0
4 3 Aug. 3 15:10 Aug. 4 12:20 0 Aug. 5 13:40 0 Aug. 6 10:10 0
4 4 Aug. 3 15:25 Aug. 4 12:25 0 Aug. 5 13:45 1 mouse, released Aug. 6 10:15 0
4 5 Aug. 3 15:30 Aug. 4 12:28 0 Aug. 5 13:50 0 Aug. 6 10:20 0
4 6 Aug. 3 15:45 Aug. 4 12:32 1 dusky, mort Aug. 5 13:55 1 vagrant, mort Aug. 6 10:25 0
4 7 Aug. 3 15:55 Aug. 4 12:40 0 Aug. 5 13:57 0 Aug. 6 10:30 0
4 8 Aug. 3 16:05 Aug. 4 12:45 0 Aug. 5 14:10 0 Aug. 6 10:35 0
5 1 Aug. 3 13:10 Aug. 4 12:55 0 Aug. 5 14:22 0 Aug. 6 10:45 0
5 2 Aug. 3 13:25 Aug. 4 13:00 0 Aug. 5 14:25 0 Aug. 6 10:50 0
5 3 Aug. 3 13:40 Aug. 4 13:05 0 Aug. 5 14:30 0 Aug. 6 10:53 0
5 4 Aug. 3 13:55 Aug. 4 13:08 0 Aug. 5 14:35 0 Aug. 6 10:57 0
5 5 Aug. 3 14:05 Aug. 4 13:10 0 Aug. 5 14:35 0 Aug. 6 10:58 0
5 6 Aug. 3 14:15 Aug. 4 13:12 0 Aug. 5 14:40 0 Aug. 6 11:00 1 water shrew, mort
6 1 Aug. 3 10:20 Aug. 4 14:10 0 Aug. 5 08:20 0 Aug. 6 08:15 0
6 2 Aug. 3 10:35 Aug. 4 14:20 0 Aug. 5 08:25 0 Aug. 6 08:20 0
6 3 Aug. 3 10:55 Aug. 4 14:25 0 Aug. 5 08:30 0 Aug. 6 08:25 0
6 4 Aug. 3 11:15 Aug. 4 14:30 0 Aug. 5 08:35 0 Aug. 6 08:35 0
6 5 Aug. 3 11:30 Aug. 4 14:40 0 Aug. 5 08:40 0 Aug. 6 08:40 0
6 6 Aug. 3 11:45 Aug. 4 14:45 0 Aug. 5 08:42 0 Aug. 6 08:45 0
China Creek Water Shrew Survey Report
Toth and Associates Environmental Services 27
6 7 Aug. 3 11:55 Aug. 4 14:50 0 Aug. 5 08:45 0 Aug. 6 08:55 0
6 8 Aug. 3 12:10 Aug. 4 14:55 0 Aug. 5 08:50 1 dusky, released Aug. 6 09:05 1 dusky, released
6 9 Aug. 3 12:20 Aug. 4 15:10 0 Aug. 5 08:55 0 Aug. 6 09:20 0
6 10 Aug. 3 12:40 Aug. 4 15:15 0 Aug. 5 08:55 0 Aug. 6 09:25 0
Other
Wildlife
Sign:
August 2: Common merganser female with 6 young and 1 American dipper observed at site 1.
August 4: 1 red-legged frog at site 2, 1 barred owl at site 6.
August 5: 2 red-legged frogs at site 2, 1 red-legged frog at site 1.
August 6: 2 red-legged frogs and elk tracks at site 6.