+ All Categories
Home > Documents > CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design...

CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design...

Date post: 28-Jul-2018
Category:
Upload: trinhngoc
View: 214 times
Download: 0 times
Share this document with a friend
32
Challenges in Planning and Design of Cable Transmission System of Pugalur North Trichur HVDC System- Users Perspective R. K. CHAUHAN , M.M. GOSWAMI, B.B. MUKHERJEE, S. BHATTACHARYA PUNEET TYAGI ,P. CHAKRABORTY Power Grid Corporation of India India CIGRE SC B1 Colloquium on H.V. Insulated Cables New Delhi (India) on 13-14 Oct. 2017
Transcript
Page 1: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Challenges in Planning and Design of Cable Transmission System of Pugalur North

Trichur HVDC System- Users Perspective

R. K. CHAUHAN , M.M. GOSWAMI, B.B. MUKHERJEE, S. BHATTACHARYA,

PUNEET TYAGI ,P. CHAKRABORTY

Power Grid Corporation of India

India

CIGRE SC B1 Colloquium on H.V. Insulated Cables

New Delhi (India) on 13-14 Oct. 2017

Page 2: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

About 6000 MW power from the new IPP generation in

Raigarh(Kotra), Champa, Raigarh(Tamnar) and Raipur area is

earmarked for transfer to Southern region (SR) as the target

region and balance power is to be transferred to the Western/

Northern regions.

Out of this 6000 MW power, Kerala has a share of 2000 MW.

This Transmission system is realized by—

• ± 800kV, 6000MW HVDC Bipole between Raigarh

(Near kotra) Pooling Station and Pugalur

• ±320 kV ,2 x 1000 MW Voltage Source Converters

(VSC) symmetrical monopoles HVDC systems from

Pugalur to North Trichur

Introduction

Page 3: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The two symmetrical monopoles converter stations

will be connected by a combination of HVDC OH

line and 320 kV DC XLPE underground cables.

The length of the OHL is approximately 143 ± 15

Km and the length of the XLPE cable is

approximately 32 ± 05 Km.

A transition station is planned to connect HVDC

overhead line with HVDC underground cable

Introduction

Page 4: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Key Challenges in the Câble Route-

Contraints of the Utility Corridor Along NH 544:

ROW is a major contraint in Kerala

After exploration of varions options, utility corridor of

National highway 544 from Wadaakanchary to North

Trichur was finalised for the Cable Corridor.

The Utility corridor was having a width of 2 meters

For crossings of culverts, rivers /streams and other impediments in the given ROW, HDD or other

suitable method as required may be adopted for laying the cables.

Page 5: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The Extension of NH544

At the time of finalisation of the corridor for the Cable, the National Highway 544 was under

expansion from four lane highway to 6 lane highways.

The cable corridor was allotted considering the adjacency to 6 lane high way and during the

bidding stage due to on-going construction work of national Highway, the clear corridor of the

Cable route was not available for detailed route survey and soil investigation.

The same was a key challenge in finalising the bill of quantity of the cable supply , laying and

installation of the same.

Key Challenges in the Câble Route-

Page 6: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Cable Laying /crossing of the existing CCK pipeline.

During preliminary cable route survey a petroleum product pipeline was found to be under operation

from Kochi to Karur for transporting petroleum product.

The pipeline is under high pressure and is catholically protected against corrosion.

The pipe line was crossing the NH 544 from Vellanikkara(km 260.00) to Vadakkenchery (km 237) at

the following locations-

• Before the Kuthiran Hills ( near Hotel Mekattil)

• Just before Kuthiran Temple

• Immediately after the Kuthiran temple

• Below the Irimpupalam

• At Kombazha after Peechi Catchment Area

Key Challenges in the Câble Route-

Page 7: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Future LPG Pipeline

During the preliminary route survey it was found a new LPG pipeline between Cochin to Palakkad is

also likely to be in close proximity with the cable route.

The pipeline is of 12 "diameter along and the length of this parallel section is approximately 1.2 km.

Top of pipe is at a depth of 1.2 m (approx.) from ground level.

The pipeline will be catholically protected against corrosion.

It is required to provide adequate mitigation measures for example an appropriate polarization cell or

any other suitable method to prevent corrosion of the existing pipeline.

Key Challenges in the Câble Route-

Page 8: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Key Challenges in the Câble Route-

Cable Bridge for Canal Crossing

Another major impediment in the Cable route is a canal in the wild life area

Required study of various options for Cable Crossing of the Canal including options like HDD,Cable

Bridge etc.

It was decided after careful consideration of all the factors that the optimum solution for the Canal

Crossing was a Cable Bridge with Cable encapsulated in Concrete duct.

Page 9: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Voltage Stresses

Cable system thermal design

Cable Screen Current Stresses

Environmental Aspects Analysis for HVDC Cable Route

Key Design Consideration of Cable

Page 10: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Voltage stress which govern the insulation thickness of cable are the steady state, transient & dynamic

stresses.

Transient and dynamic stresses imposed on the DC cable system are caused by faults within the HVDC

system and overvoltage emanating from lightning strikes to the overhead lines which propagate into the

cables.

Voltage Stresses:

Three different fault scenarios are seen as relevant for the cable design in this project because

they lead to maximum transient voltage stresses for the cable system

DC side, single pole-to-ground

DC side, pole-to-pole fault with ground contact

Transformer AC secondary side, phase-to-ground fault

Page 11: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

DC side, single pole-to-ground

DC side, pole-to-pole fault with ground contact

Transformer AC secondary side, phase-to-ground fault

Voltage Stresses:

Courtesy: Siemens

Page 12: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

DC side, pole-to-pole fault with ground contact

Current Stresses:

DC side, pole-to-pole fault with ground contact

results in highest DC side Current.

After the ac breaker is opened fault current will

decay depending on resistance of converter,

converter reactor and DC line.

Courtesy: Siemens

Page 13: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The continuous current carrying capacity of the cable has been calculated according to the method given in

IEC 60287 "ELECTRIC CABLES - CALCULATION OF THE CURRENT RATING ".

However, thermal resistance of surrounding medium (T4) in IEC does not cover the plural soil condition

(mixture of native soil, thermal backfill and concrete duct),

In order to provide optimum design Finite Element Method (FEM) analysis, which shows conductor

temperature at the given heat loss and soil thermal resistivity.

The design cases based on initial survey and soil investigation are based on different ROW which is available

for the cable route.

The following aspects are investigated.

Standard trench at a depth of 2 m

Narrow trench at a depth of 2 m.

Narrow trench at a depth of 1m.

Cable system thermal design

Page 14: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Courtesy – Geotherm Inc13-10-2017 14

Factors Affecting Thermal resistivity

Heat flows through a soil mainly by conduction along mineral particles, and by conduction and convection through the moisture or air that occupies the pore space between solid particles.

Thermal resistivity depends on : 1 Moisture content

2 Dry Density

3 Structural Composition

4 Soil particle shape/texture

Page 15: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Courtesy – Geotherm Inc13-10-2017 15

Variation of soil thermal resistivity with moisture content

In a dry state the pore spaces are filled with air (~4500°Ccm/W). As water (~165°C-cm/W) replaces air, the soil resistivity is substantially lowered (as much as 3 to 7 times) as the good heat conduction paths are expanded (‘thermal bridges’).

Page 16: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

13-10-2017 16

Variation of soil thermal resistivity with Dry density

Soil densification (or compaction) increases mineral grain contacts and displaces air (ie. lowers porosity), therefore reducing the soil resistivity, most notably at low moisture contents.

Well-graded soils are potentially more dense because smaller grains can efficiently fill the spaces between the larger particles.

Dry density is expressed as the ratio of the dry weight of the soil solids to the total volume. The total volume is taken as the initial volume of the undisturbed moist soil in a sample tube.

Page 17: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

13-10-2017 17

Variation of soil thermal resistivity with Soil Composition

Soil is a composite consisting of solid mineral grains, typically only making point-to-point contact, and pore space filled with water and air.

The thermal resistivity of a given soil mass is a function of the intrinsic resistivities of its components.

Page 18: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

13-10-2017 18

Variation of soil thermal resistivity with Texture

This refers to soil grain size, shape, and particle size gradation.

Since most of the heat is conducted through the solid particles and their contacts, the resistivity is minimized for soils that maximize these contacts.

Hence thermal resistivity varies for gravel, sand, silt, clay etc.

Page 19: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Standard trench at a depth of 2 m

Courtesy: SEI

Page 20: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Narrow trench at a depth of 2 m.

Courtesy: SEI

Page 21: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Narrow trench at a depth of 1m

Courtesy: SEI

Page 22: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Equivalent circuit for the DC cable

Cable Screen Current Stresses

Another key design study for the cable design is the

Cable screen Current Stress.

This also becomes important in the subject project

which is having a mix of overhead line and the

HVDC XLPE Cable as there may be a contribution

to these stresses from the Converter Side.

Courtesy: SEI

Page 23: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Cable Screen Current Stresses

Contribution of Converter- L G Fault

Contribution of Converter- L L Fault

Courtesy: SEI

Page 24: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The effects of the cables upon the environment are studies with respect to electromagnetic fields, and

chemical impact and the observations are as per below-

a) Electro magnetic Fields

The magnetic fields surrounding electrical conductors are produced by, and dependent on, the DC current

flowing in them.

For the subject project the cables operate as a positive and negative pole system, the current in each positive

and negative cable runs in opposite directions, leading to a significant cancellation of the external magnetic

field.

Environmental Aspects Analysis for HVDC Cable Route

Page 25: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

DC power transmission in the underground cables generates

static magnetic fields in the range of

~28 micro-Tesla (μT) at 1.0 m above ground and

~54 micro-Tesla at the ground surface with both symmetrical

monopoles operating at full load

These levels are in the same order of magnitude as the earth’s

natural static magnetic field.

Environmental Aspects Analysis for HVDC Cable Route

Courtesy: SEI

Page 26: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The electrostatic fields surrounding conductors are produced by, and dependent on, the voltage

applied to the conductor.

However, the DC cable conductors are surrounded by XLPE insulation and a metallic screen (or

shield), of which the metallic screen is grounded at earth potential.

Thus, the metallic screen confines the electric field to the cable insulation, and there is virtually no

electrostatic field outside the cable surface. This is valid for any shielded power cable, regardless of

whether the voltage is AC or DC.

Electrostatic Fields

Page 27: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Under normal operation conditions, land power cables do not release chemicals, consumables,

or other agents into the environment. I

n case of damage or rupture, cables with solid insulation, such as the XLPE used for this

project, do not contain fluids that can leak into the environment

Chemical Impact

Page 28: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Nominal Rated Power at

Receiving End

1000MW

Nominal voltage at cable

terminations, Uo:

± 320 kV

Maximum continuous voltage at

cable terminations, Um:

Uo + 5 % kV

Maximum total continuous AC

ripple superimposed on Um:

0.03 Um

(peak)

Surge withstand voltage(SIWV)

(approximately) :

740 kV

peak

Lightning Impulse withstand

voltage LIWV( approximately)

770 kV

Copper conductor size 2500 mm2 is considered for the cable rating capacity for required transmission of

1000MW under the maximum allowable conductor temperature at 90oC.

All the calculations shall be rechecked after right of way handover, detailed route survey, thermal

resistivity measurements in situ and laboratory.

Page 29: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

9,500

Earth rod

Coffin box

"a"

Typical Joint Bay for HVDC XLPE Cable

Page 30: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The cable system is defined as being comprised of the HVDC land cables, land cable joints,

land/OHL transition station joints and all auxiliary equipment.

The cables supplied in this project are already covered by range of approval of completed

pre-qualification test of another size according to CIGRE TB 496.

Since this is a critical item of this project also a first time usage in our country all the type

tests shall be performed on the cable system being supplied in this project as per CIGRE

Technical Brochure496, IEC62067 ( as applicable) .

Since HVDC cable systems are exposed are interface a to overhead lines, the superimposed lightning

impulses may be of the same and opposite polarities. Hence as a suppliment to the tests already a part

of CIGRE Technical Brochure496, lightning impulse tests shall be done with superimposed lightning

impulses may be of the same and opposite polarities.

Routine and sample tests shall be performed the routine tests described in CIGRE Technical

Brochure496 and IEC62067

Tests On HVDC Cable system

Page 31: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

The first VSC HVDC interconnection in India offers a technology driven option for power transfer

between two load centers in Southern parts of India.

The HVDC cable and transmission line mix and a cable route through a city offers challenges in

design and execution.

The detailed engineering of the subject project is under progress and the successful execution of the

project will be a bench mark for some more HVDC project utilising the Cable Technology to

mitigate the ROW issues for city infeeds and in submarine applications involving off shore wind

farms and cross border transmission system .

Way Forward….

Page 32: CIGRE SC B1 Colloquium on H.V. Insulated Cables Challenges in Planning and Design …cigreindia.org/VIVANTAFEB2017/Data/13-10-17/S3.1.pdf · 2017-10-17 · Key Design Consideration

Thank You


Recommended