Smith Blvd & Paulann Blvd Improvements Robert Schneeman, Interim Director of Economic Development
Transcript

Smith Blvd & Paulann Blvd Improvements

Robert Schneeman, Interim Director of Economic Development

Paulann & Smith Blvd. Extension

Paulann & Smith Blvd. Extension

Paulann Blvd. Proposed Full Width 64’

Paulann & Smith Blvd. Extension

Paulann Blvd. Proposed Half Width 32’

Paulann & Smith Blvd. Extension

Paulann Blvd. Proposed Full Width 64’

Paulann & Smith Blvd. Extension

Paulann Blvd. Proposed Half Width 32’

Paulann & Smith Blvd. Extension

Cost Estimates Original Estimate $350,000

Council Meeting July 2012

Option 2Paulann Blvd. Half Width (32’)

& Smith Blvd.(26’)

$443,030.23

Option 1Paulann Blvd. Full Width (64’)

& Smith Blvd.(26’)

$512,867.58


Recommended