CITY COUNCIL CONSENT CALENDAR SEPTEMBER 23, 2019 SUBJECT: NOTICE OF COMPLETION: CITY HALL LOBBY IMPROVEMENT PROJECT - C.I.P #55-17/18-01 INITIATED BY: FACILITIES AND RECR~ON SERVICES DEPARTMENT (Steve Campbell , Directo~ (Helen Collins, Facilities and Recreation Services Manager) fal:--- STATEMENT ON THE SUBJECT: The City Council will consider approving the Notice of Completion for the City Hall Lobby Improvement. RECOMMENDATIONS: Accept the work for the City Hall Lobby Improvement Project and authorize the following : a. File the Notice of Completion (NOC) with the Los Angeles County Recorder's Office; b. Issue the final payment to the Contractor at the end of the 35-day lien period ; and c. Release the Payment Bond 35-days after the NOC date of recordation, pend ing no receipt of a Stop Notice or other actions. BACKGROUND / ANALYSIS: On November 6, 2017, the City Council approved an Agreement to complete improvements in the amount of $749,000 and authorized the Facilities and Field Services Division to manage Change Orders to the agreement in an amount not-to- exceed $187,250 (25%) for a total not-to-exceed contract amount of $936,250 for the City Hall Lobby Improvement Project. The Agreement was awarded to Optima RPM, Inc. through a competitive bidding process. The project included the installation of the staircase, reception improvements and other security upgrades. Substantial completion and beneficial use of the project was accepted by the Design Team and the Facilities and Field Services Division on August 14, 2019. To date, there are twenty-one (21) approved change orders totaling $141,855.78 associated with the project. The final project cost is: $890,855.78. All work under the agreement has been satisfactorily completed in accordance with the project plans and specifications. The City took over possession and control of the completed work on August 14, 2019 initiating the one (1) year contractors warranty period. The Performance Bond shall remain in effect until the end of all warranty periods P age 1 of 3 AGENDA ITEM 2.AA.
Transcript

CITY COUNCIL CONSENT CALENDAR

SEPTEMBER 23, 2019

SUBJECT: NOTICE OF COMPLETION: CITY HALL LOBBY IMPROVEMENT PROJECT - C.I.P #55-17/18-01

INITIATED BY: FACILITIES AND RECR~ON SERVICES DEPARTMENT (Steve Campbell , Directo~ (Helen Collins, Facilities and Recreation Services Manager)fal:---

STATEMENT ON THE SUBJECT:

The City Council will consider approving the Notice of Completion for the City Hall Lobby Improvement.

RECOMMENDATIONS:

Accept the work for the City Hall Lobby Improvement Project and authorize the following :

a. File the Notice of Completion (NOC) with the Los Angeles County Recorder's Office;

b. Issue the final payment to the Contractor at the end of the 35-day lien period ; and

c. Release the Payment Bond 35-days after the NOC date of recordation , pending no receipt of a Stop Notice or other actions.

BACKGROUND / ANALYSIS:

On November 6, 2017, the City Council approved an Agreement to complete improvements in the amount of $749,000 and authorized the Facilities and Field Services Division to manage Change Orders to the agreement in an amount not-to­exceed $187,250 (25%) for a total not-to-exceed contract amount of $936,250 for the City Hall Lobby Improvement Project. The Agreement was awarded to Optima RPM, Inc. through a competitive bidding process.

The project included the installation of the staircase, reception improvements and other security upgrades. Substantial completion and beneficial use of the project was accepted by the Design Team and the Facilities and Field Services Division on August 14, 2019. To date, there are twenty-one (21) approved change orders totaling $141,855.78 associated with the project. The final project cost is: $890,855.78.

All work under the agreement has been satisfactorily completed in accordance with the project plans and specifications. The City took over possession and control of the completed work on August 14, 2019 initiating the one (1) year contractors warranty period . The Performance Bond shall remain in effect until the end of all warranty periods

Page 1 of 3

AGENDA ITEM 2.AA.

set forth in the Contract Documents. Upon recordation of the Notice of Completion with the County Recorder, the subcontractors and material suppliers have a 35-day lien period to file a claim.

CONFORMANCE WITH VISION 2020 AND THE GOALS OF THE WEST HOLLYWOOD GENERAL PLAN:

This item is consistent with the Primary Strategic Goal(s) (PSG) and/or Ongoing Strategic Program(s) (OSP) of:

• OSP-9: Upgrade Existing Buildings & Infrastructure.

In addition, this item is compliant with the following goal(s) of the West Hollywood General Plan:

• IRC-11: Provide high quality, safe, well-maintained and sustainable facilities for City operations.

EVALUATION PROCESSES:

1) The Contractor was required to obtain final approval of all relevant building permits issued as part of this project.

2) The Contractor was required to obtain final approval of all relevant deliverables from the engineer of record employed by the design team of LPA Inc.

3 The Contractor was required to provide all warranty and user manuals for all equipment, materials and work as outlined in the contract documents.

ENVIRONMENTAL SUSTAINABILITY AND HEALTH:

The Contractor was required abide by the City's requirements that 80% of all demolition and construction material must be recycled .

COMMUNITY ENGAGEMENT:

N/A.

OFFICE OF PRIMARY RESPONSIBILITY:

FACILITIES AND RECREATION SERVICES DEPARTMENT/ FACILITIES & FIELD SERVICES DIVISION

FISCAL IMPACT:

There is no impact: The project was included in the fiscal year 2017-2018 budget as

Page 2 of 3

part of the Capital Improvement Work Plan. The approved project budget was $749,000.00 plus a contingency of $187,250 for a not-to-exceed amount of $936,250. There were twenty-one (21) approved change orders, totaling $141,855.78. The change orders included security upgrades. The final project cost was under budget at $890,855.78.

AMOUNT DESCRIPTION $890,855.78 100-4-08-55-702010 City Hall Purchase & Improvements

ATTACHMENT:

Attachment A - NOTICE OF COMPLETION: CITY HALL LOBBY IMPROVEMENT PROJECT - C.I.P #55-17/18-01 IN THE CITY OF WEST HOLLYWOOD.

Page 3 of 3

RECORDING REQUESTED BY:

OFFICE OF THE CITY CLERK CITY OF WEST HOLLYWOOD

WHEN RECORDED MAIL ro:

Office of the City Clerk City of West Hollywood 8300 Santa Monica Blvd. West Hollywood, CA 90069

SPACE ABOVE THIS LINE RESERVED FOR RECORDER'S USE

Attachment A

NOTICE OF COMPLETION: CITY HALL LOBBY IMPROVEMENT PROJECT - C.I.P #55-17/18-01 IN THE CITY OF WEST HOLLYWOOD.

NOTICE OF COMPLETION

Notice is hereby given that:

1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described:

2. The full name of the owner is the City of West Hollywood.

3. The full address of the owner is 8300 Santa Monica Blvd., West Hollywood, CA 90069.

4. The nature of the interest or estate of the owner is In Fee.

5. A work of improvement on the property hereinafter described was completed on August 14, 2019, the work consisted of the following:

Furnishing all labor, materials, tools, and equipment necessary for the installation a staircase to the 2nd floor, new tile and modifications to the customer service counters and receptions areas in accordance with the plans and specifications.

6. The contractor for the work was: Optima RPM, Inc. 17945 Sky Park Circle, Suite D

Irvine, CA, 92614

7. The name of the contract for such work of improvement was:

City Hall Lobby Project - C.I.P #55-17/18-01.

8. The property on which said work of improvement was completed is in the City of West Hollywood, County of Los Angeles, State of California, and the general locations and limits of work are as follows:

City Hall : 8300 Santa Monica Blvd., West Hollywood, CA. 90069

9. Detailed plans and specifications of said project are on file in the Department of Facilities and Recreations Services at the West Hollywood City Hall.

VERIFICATION

I, Steve Campbell , Director, Department of Facilities and Recreation Services for the City of West Hollywood, hereby certify under penalty of perjury that the foregoing Notice of Completion is true and correct to the best of my knowledge.

Witness my hand this 19th day of August 2019 at West Hollywood, California.

Steve Campbell , Director Department of Facilities and Recreation Services City of West Hollywood

Paul Arevalo , City Manager, Cityof West Hollywood

STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss CITY OF WEST HOLLYWOOD )

On _________ , before me, YVONNE QUARKER, CITY CLERK OF THE CITY OF WEST HOLLYWOOD, personally appeared PAUL AREVALO, known to me to be the CITY MANAGER and STEVE CAMPBELL, known to me to be the DIRECTOR OF THE DEPARTMENT OF FACILITIES AND RECREATION SERVICES, of the CITY OF WEST HOLLYWOOD, A MUNICIPAL CORPORATION, and acknowledged to me that the Municipal Corporation executed the same.

Witness my hand and official seal


Recommended