+ All Categories
Home > Documents > City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local...

City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local...

Date post: 02-Oct-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
119
City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding. August 3, 2018 Agency Name County Project Type Title Description Location Est. Project Start Est. Project Completion Est Useful Life Min Est Useful Life Max Assembly Districts Senate Districts Alameda Alameda Road Maintenance & Rehabilitation Pavement Management Resurfacing and repair of street pavement, and restoration of flowlines of associated curb and gutter, in order to extend the life of the street and improve its ridability for cyclists and motorists. The Pavement Management program that is funded in FY 18-19 is spread throughout the City of Alameda. Streets identified for resurfacing include sections of Alameda Avenue, Fernside Boulevard, Harbor Bay Parkway, Park Street and Versailles Avenue. 05/2018 11/2018 30 40 18 9 Alameda Alameda Road Maintenance & Rehabilitation Sidewalks Street tree root pruning and sidewalk repair to maintain pedestrian circulation and safety, and minimize future damage to the street and sidewalk. Throughout the City of Alameda - the backlog of repairs includes about 5,000 locations, of which several clusters will be chosen that address the oldest requests, and maximize economy by aggregating sites in close location to each other. 07/2018 06/2019 10 70 18 9 Albany Alameda Road Maintenance & Rehabilitation 17/18 Carryover This project consists of asphalt overlay of Evelyn Street from Garfield Avenue to Portland Avenue, for a distance of approximately 600 feet. It will also include base repair, traffic striping and upgrade of existing curb ramp to meet ADA requirements. Evelyn Street from Garfield Avenue to Portland Avenue, in the City of Albany 05/2018 09/2018 20 30 15 9 Albany Alameda Road Maintenance & Rehabilitation 2019 Annual Street Rehabilitation Project The 2019 Annual Street Rehabilitation Project includes the repair and rehabilitation of local streets and roads within the City of Albany. Street Saver software and a pavement condition index provided through a Pavement Management Technical Assistance Program provided priority streets for rehabilitation. Jackson Street, Pierce Street, and Garfield Avenue along with other priority streets were identified treatment based on function, pavement condition, and coordination with other projects. Various streets including portions of Pierce Street, Garfield, and Jackson Street in the City of Albany. 06/2018 05/2019 20 30 15 9 Berkeley Alameda Road Maintenance & Rehabilitation FY 2019 Street Rehabilitation FY 2019 Street Rehabilitation Project to overlay and reconstruct up to 1.01 miles of Berkeley streets. Planned segments for SB1 funds include: 6th Street from Allston Way to Dwight Way, Catalina Avenue from Colusa Avenue to The Alameda, Derby Street from San Pablo Avenue to Mabel Street, Dwight Crescent from 6th Street to 7th Street, Highland Place from Ridge Road to Hearst Avenue, Ridge Road from La Loma Avenue to Highland Place, Station Place from Catalina Avenue to the south end of Station Place 6th Street from Allston Way to Dwight Way, Catalina Avenue from Colusa Avenue to The Alameda, Derby Street from San Pablo Avenue to Mabel Street, Dwight Crescent from 6th Street to 7th Street, Highland Place from Ridge Road to Hearst Avenue, Ridge Road from La Loma Avenue to Highland Place, Station Place from Catalina Avenue to the south end of Station Place 05/2019 10/2019 10 30 15 9 Berkeley Alameda Complete Streets Components Shattuck Avenue Reconfiguration Reconfiguration of a three-block segment of Shattuck Avenue from Allston Way to University Avenue to improve pedestrian and bicycle safety, northbound circulation for motorists and transit vehicles, and the quality of public spaces in the Downtown core. Shattuck Avenue from Allston Way to University Avenue 09/2018 03/2020 20 30 15 9 Berkeley Alameda Road Maintenance & Rehabilitation FY 2018 Street Rehabilitation The FY 2018 Street Rehabilitation Project to reconstruct up to 0.81 miles of Berkeley Streets is continuing from its original FY 2018 submission due to construction timing that will occur in FY 2019. Segments planned for pavement reconstruction funded from SB1 include: *Prospect Street - Pavement Reconstruction of 0.13 miles of Prospect Street from the UC Berkeley Campus to Hillside Avenue; *Panoramic Way - Pavement Reconstruction of 0.68 miles of Canyon Road to east city limit Segments planned for pavement reconstruction funded from SB1 include: *Prospect Street - Pavement Reconstruction of 0.13 miles of Prospect Street from the UC Berkeley Campus to Hillside Avenue *Panoramic Way - Pavement Reconstruction of 0.68 miles of Canyon Road to east city limit 08/2018 04/2019 20 30 15 9 Dublin Alameda Other Dublin Boulevard Extension Design and construction of a 1.5-mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. This is a new proposed project for FY 18/19 report. Between Fallon Road in the City of Dublin and North Canyons Parkway in City of Livermore 07/2023 12/2025 30 50 16 7 Dublin Alameda Other Tassajara Road Realignment and Widening Planning, design, and construction of Tassajara Road from North Dublin Ranch Drive to city limit. The funding from FY 17/18 was carried forward as planned to FY 18/19 report. Between North Dublin Ranch Drive and the City Limit along Tassajara Road. 01/2016 06/2020 30 50 16 7 Dublin Alameda Road Maintenance & Rehabilitation Annual Street Resurfacing Pavement surface treatments and repairs to existing City streets. The City is proposing to resurface three streets this summer. These streets include; San Ramon Road, Dublin Blvd and Amador Valley Blvd. FY 17/18 SB1 funding was carried over to the FY 18/19 funding. These streets include; San Ramon Road, Dublin Blvd and Amador Valley Blvd. 07/2018 03/2019 7 25 16 7 Dublin Alameda Other Dublin Boulevard Improvements - Sierra Court to Dublin Court Design and construction of Dublin Boulevard from Sierra Court to Dublin Court. This is a new proposed project for FY 18/19 report. Between Sierra Court and Dublin Court on Dublin Blvd. 07/2018 06/2019 30 50 16 7 Dublin Alameda Safety Iron Horse Trail Bridge at Dublin Boulevard Design and environmental review of an Iron Horse Trail bridge for bicycles and pedestrians over Dublin Boulevard. Funding from FY 17/18 was carried forward as planned to FY 18/19 report. At Scarlet Drive on Dublin Blvd 07/2018 06/2019 30 50 16 7 Emeryville Alameda Safety San Pablo Avenue Mid-Block Cross Walk (17/18 Carryover) The Public Works Committee and BPAC have identified a new potential project in the City of Emeryville to install a mid-block crosswalk on San Pablo Avenue between 40th Street and Adeline Street in Caltrans State right-of-way. The work will include the new construction of ADA pedestrian ramps, large pedestrian refuge area in the median, and highly-visible pedestrian/vehicular traffic control devices. San Pablo Avenue between 40th Street and MacArthur Boulevard 09/2018 04/2019 10 20 15 9 *All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).
Transcript
Page 1: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Alameda Alameda Road Maintenance & Rehabilitation Pavement Management

Resurfacing and repair of street pavement, and restoration of flowlines of associated curb and gutter, in order to extend the life of the street and improve its ridability for cyclists and motorists.

The Pavement Management program that is funded in FY 18-19 is spread throughout the City of Alameda. Streets identified for resurfacing include sections of Alameda Avenue, Fernside Boulevard, Harbor Bay Parkway, Park Street and Versailles Avenue.

05/2018 11/2018 30 40 18 9

Alameda Alameda Road Maintenance & Rehabilitation Sidewalks Street tree root pruning and sidewalk repair to maintain pedestrian circulation and

safety, and minimize future damage to the street and sidewalk.

Throughout the City of Alameda - the backlog of repairs includes about 5,000 locations, of which several clusters will be chosen that address the oldest requests, and maximize economy by aggregating sites in close location to each other.

07/2018 06/2019 10 70 18 9

Albany Alameda Road Maintenance & Rehabilitation 17/18 Carryover

This project consists of asphalt overlay of Evelyn Street from Garfield Avenue to Portland Avenue, for a distance of approximately 600 feet. It will also include base repair, traffic striping and upgrade of existing curb ramp to meet ADA requirements.

Evelyn Street from Garfield Avenue to Portland Avenue, in the City of Albany 05/2018 09/2018 20 30 15 9

Albany Alameda Road Maintenance & Rehabilitation

2019 Annual Street Rehabilitation Project

The 2019 Annual Street Rehabilitation Project includes the repair and rehabilitation of local streets and roads within the City of Albany. Street Saver software and a pavement condition index provided through a Pavement Management Technical Assistance Program provided priority streets for rehabilitation. Jackson Street, Pierce Street, and Garfield Avenue along with other priority streets were identified treatment based on function, pavement condition, and coordination with other projects.

Various streets including portions of Pierce Street, Garfield, and Jackson Street in the City of Albany. 06/2018 05/2019 20 30 15 9

Berkeley Alameda Road Maintenance & Rehabilitation FY 2019 Street Rehabilitation

FY 2019 Street Rehabilitation Project to overlay and reconstruct up to 1.01 miles of Berkeley streets. Planned segments for SB1 funds include: 6th Street from Allston Way to Dwight Way, Catalina Avenue from Colusa Avenue to The Alameda, Derby Street from San Pablo Avenue to Mabel Street, Dwight Crescent from 6th Street to 7th Street, Highland Place from Ridge Road to Hearst Avenue, Ridge Road from La Loma Avenue to Highland Place, Station Place from Catalina Avenue to the south end of Station Place

6th Street from Allston Way to Dwight Way, Catalina Avenue from Colusa Avenue to The Alameda, Derby Street from San Pablo Avenue to Mabel Street, Dwight Crescent from 6th Street to 7th Street, Highland Place from Ridge Road to Hearst Avenue, Ridge Road from La Loma Avenue to Highland Place, Station Place from Catalina Avenue to the south end of Station Place

05/2019 10/2019 10 30 15 9

Berkeley Alameda Complete Streets Components Shattuck Avenue Reconfiguration

Reconfiguration of a three-block segment of Shattuck Avenue from Allston Way to University Avenue to improve pedestrian and bicycle safety, northbound circulation for motorists and transit vehicles, and the quality of public spaces in the Downtown core.

Shattuck Avenue from Allston Way to University Avenue 09/2018 03/2020 20 30 15 9

Berkeley Alameda Road Maintenance & Rehabilitation FY 2018 Street Rehabilitation

The FY 2018 Street Rehabilitation Project to reconstruct up to 0.81 miles of Berkeley Streets is continuing from its original FY 2018 submission due to construction timing that will occur in FY 2019. Segments planned for pavement reconstruction funded from SB1 include: *Prospect Street - Pavement Reconstruction of 0.13 miles of Prospect Street from the UC Berkeley Campus to Hillside Avenue; *Panoramic Way - Pavement Reconstruction of 0.68 miles of Canyon Road to east city limit

Segments planned for pavement reconstruction funded from SB1 include:*Prospect Street - Pavement Reconstruction of 0.13 miles of Prospect Street from the UC Berkeley Campus to Hillside Avenue*Panoramic Way - Pavement Reconstruction of 0.68 miles of Canyon Road to east city limit

08/2018 04/2019 20 30 15 9

Dublin Alameda Other Dublin Boulevard Extension

Design and construction of a 1.5-mile extension of Dublin Boulevard from Fallon Road to North Canyons Parkway in Livermore. This is a new proposed project for FY 18/19 report.

Between Fallon Road in the City of Dublin and North Canyons Parkway in City of Livermore 07/2023 12/2025 30 50 16 7

Dublin Alameda Other Tassajara Road Realignment and Widening

Planning, design, and construction of Tassajara Road from North Dublin Ranch Drive to city limit. The funding from FY 17/18 was carried forward as planned to FY 18/19 report.

Between North Dublin Ranch Drive and the City Limit along Tassajara Road. 01/2016 06/2020 30 50 16 7

Dublin Alameda Road Maintenance & Rehabilitation Annual Street Resurfacing

Pavement surface treatments and repairs to existing City streets. The City is proposing to resurface three streets this summer. These streets include; San Ramon Road, Dublin Blvd and Amador Valley Blvd. FY 17/18 SB1 funding was carried over to the FY 18/19 funding.

These streets include; San Ramon Road, Dublin Blvd and Amador Valley Blvd. 07/2018 03/2019 7 25 16 7

Dublin Alameda Other Dublin Boulevard Improvements - Sierra Court to Dublin Court

Design and construction of Dublin Boulevard from Sierra Court to Dublin Court. This is a new proposed project for FY 18/19 report. Between Sierra Court and Dublin Court on Dublin Blvd. 07/2018 06/2019 30 50 16 7

Dublin Alameda Safety Iron Horse Trail Bridge at Dublin Boulevard

Design and environmental review of an Iron Horse Trail bridge for bicycles and pedestrians over Dublin Boulevard. Funding from FY 17/18 was carried forward as planned to FY 18/19 report.

At Scarlet Drive on Dublin Blvd 07/2018 06/2019 30 50 16 7

Emeryville Alameda Safety San Pablo Avenue Mid-Block Cross Walk (17/18 Carryover)

The Public Works Committee and BPAC have identified a new potential project in the City of Emeryville to install a mid-block crosswalk on San Pablo Avenue between 40th Street and Adeline Street in Caltrans State right-of-way. The work will include the new construction of ADA pedestrian ramps, large pedestrian refuge area in the median, and highly-visible pedestrian/vehicular traffic control devices.

San Pablo Avenue between 40th Street and MacArthur Boulevard 09/2018 04/2019 10 20 15 9

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 2: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Fremont Alameda Road Maintenance & Rehabilitation Pavement Rehabilitation Project Pavement rehabilitation of asphalt roadways.

1. Central Ave: Blacow Rd to Fremont Blvd 2. Mowry Ave (East Bound): I-880 to Farwell Ave 3. South Grimmer Blvd (South Bound): Auto Mall Pkwy to Technology Dr 4. Washington Blvd: Palm Ave to Mission Blvd 5. Paseo Padre Parkway (South Bound): Mission Blvd to Curtner Rd 6. East Warren Ave: Curtner Rd to Yakima Dr. 7. Lake Oneida St 8. Lake Pyramid St 9. Chaucer Dr 10. Cornwallis Pl & Ct 11. Torrington Ct & Pl 12. Atteridge Pl & Ct 13. Barnfield Pl 14. Milton St 15. Ardo St 16. Gustavo Ct 17. Aquado Ct 18. Cano Ct 19. Tampico Rd 20. Cadiz Dr & Ct 21. Lexington St 22. Argonaut Way: Garland Dr to Mowry Ave 23. Blacow Rd Frtg (West Side): Eggers Dr to Brophy Dr 24. Blacow Rd Frtg (East Side): Eggers Dr to South End 25. Wheeler Dr: Sundale Dr to Logan Dr 26. Margery Dr: Davis St to Fremont Blvd 27. Baylis St 28. Coco Palm Dr: Whitecap St to Royal Palm Dr 29. Curtis St: Omar St to Peony Court 30. Fremont Blvd Frtg (West Side): Delaware Dr to Doane St 31. Montrose Ave: Fremont Blvd to Jamestown Rd 32. Duarte Ave 33. Mission Creek Dr 34. Anza St: Ellsworth St to Mission Blvd 35. Mohican Ct 36. Sentinel Pl: Raindance Rd to Owhanee Ct 37. Lippert Ave: to Hoyt St

06/2018 11/2018 10 15 10 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 3: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Fremont Alameda Road Maintenance & Rehabilitation Cape and Slurry Seal Project Pavement maintenance project to apply cape and slurry seals to existing asphalt

roadways

1. Abaca Way 2. Agnes Ct 3. Alder Ave: 625' E/O Fremont Blvd To Fremont Blvd 4. Alder Ave: 625' E/O Fremont Blvd To Hereford St 5. Alder Ave: Hereford St To Nicolet Ave 6. Alvaniece Ct 7. Ambar Pl North End 8. Ambar Pl South End 9. Andrews Ct 10. Arkwood St: Doane St To Cedarwood St 11. Athy Ct 12. Audubon Park Ct 13. Barry Way: Tyson Ln To Athy Ct 14. Benavente Ave: Canyon Heights Dr To Almeria Ave 15. Benavente Pl 16. Blacow Rd: Roberts Ave To East End 17. Blair Pl 18. Bogalusa Ct 19. Bruce Dr: Meredith Dr To Middlefield Ave 20. Cadencia St: Mission Blvd To Morada Ct 21. Canto Pl 22. Carnation Way: Niles Blvd To N/O Ilima Ct 23. Casals Way 24. Cassio Cir: Othello Dr To Othello Dr 25. Castillejo Ct 26. Castillejo Way: Castillejo Rd To East End 27. Castillejo Way: Castillejo Rd To West End 28. Chapman Ct 29. Chateau Park Ct 30. Chatterton Ct 31. Claremont Park Ct 32. Clarendon Park Ct 33. Collin Ct 34. Covina Way: Cholla St To Towhee St 35. Curtis St: 110' E/O Farina Ln To Butano Park Dr 36. Dortha Ct 37. Durillo Ct 38. Eden Ct 39. El Portal Av: Niles Blvd To Plumeria Way 40. Emerson Ct

06/2018 11/2018 5 10 10 25

Fremont Alameda Road Grade SeparationI-880 Bicycle and Pedestrian Bridge and Trail Project (East Bay Greenway Trail Reach 6)

Bridge project to provide safe crossing over an existing freeway for pedestrians and cyclists. Over Interstate 880 near Mission Boulevard 10/2020 12/2022 40 60 10 25

Fremont Alameda Complete Streets Components

Multi-Modal Improvements-BART Way and Gateway Plaza

Roadways improvements to improve safety and accessibility. Includes installation of raised bike lanes, intersection modifications, and guide signs for pedestrian navigation. BART Way and Gateway Plaza 06/2018 11/2018 20 30 10 20

Fremont Alameda Traffic Control Devices Traffic Signal at Grimmer Blvd. and Seneca Park Ave. Installation of new traffic signals Intersection of Grimmer Boulevard and Seneca Park Avenue 06/2018 11/2018 20 30 10 25

Fremont Alameda Traffic Control Devices Traffic Signal at Blacow Rd. and Gatewood St. Installation of new traffic signal Intersection of Blacow Road and Gatewood Street 06/2018 11/2018 20 30 10 25

Fremont Alameda Traffic Control Devices Pedestrian Crossing Enhancement Phase 2 Installation of HAWK beacon signal and RRFB

Fremont Boulevard and Norris Road: Installation of HAWK beacon signal, Driscoll Road and Chiltern Drive: Installation of RRFB, Fremont Boulevard and Margery Drive: Installation of RRFB, Paseo Padre Parkway and Surry Place: Installation of RRFB, Driscoll Road (mid block) between Amapola Drive and Chiltern Drive: Installation of RRFB

05/2018 12/2018 20 30 10 25

Fremont Alameda Traffic Control Devices Pedestrian Crossing Enhancement Phase 1

Installation of High Intensity Activated Crosswalk (HAWK) beacon signal and Installation of Rapid Rectangular Flashing Beacon (RRFB)

1. Mowry Avenue and Waterside Circle/Vancouver Common: Installation of High Intensity Activated Crosswalk (HAWK) beacon signal. 2. East Warren Avenue at Bradley Street: Installation of Rapid Rectangular Flashing Beacon (RRFB)

06/2018 11/2018 20 30 10 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 4: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Fremont Alameda Complete Streets Components Intersection Ramps Installation of curb ramps at street intersections to improve accessibility

Intersections of: 1. Alder and Coronado 2. Alder and Laredo 3. Altura and Tothero 4. Alvarado and Lake Arrowhead 5. Alvarado and Merganser 6. Ambar and Casa Marcia 7. Ambar and Quintana 8. Athy and Barry 9. Benavente and Canyon Heights 10. Benavente and Platero 11. Benavente and Benavente Pl 12. Benavente and Estrella 13. Benavente and Orden 14. Benavente and Obispo 15. Benavente and Almeria 16. Blanchard and Hawkins 17. Cadencia and Charlita 18. Cadencia and Danzon 19. Calaveras and Mariposa 20. Calaveras and Drake 21. Calaveras and Sutter 22. Camero and Canto 23. Canyon Heights and Fisalia 24. Canyon Heights and Hidalgo 25. Carnation and Niles 26. Carnation and Ilima 27. Cassio and Cassio Ct 28. Cassio and Othello (South Intersection) 29. Castillejo Way and Castillejo Ct. 30. Castillejo Way and Castillejo Rd. 31. Castillejo Way and Caldas 32. Chiltern and Casals 33. Chiltern and Kensington 34. Covina and Mantis 35. Dauphine and Blue Ridge 36. Deep Creek and Amberwood 37. Durillo and Durillo Ct 38. Essanay and Essanay Pl. 39. Everglades Park and Clarendon Park

06/2018 03/2019 20 30 10 25

Hayward Alameda Road Maintenance & Rehabilitation

FY 2019 Pavement Rehabilitation and Preventative Maintenance Project

The project consists of pavement rehabilitation treatment including overlay, cold-in-place recycling, and full depth reclamation.

Breakwater Av: from Breakwater Ct to Whitesell St, Fairway St: from Mission Blvd to Faircliff St, Lester Av: from Hesperian Blvd to Thelma St, Miami Av: from Melbourne Av to Calaroga Av, Mohr Dr: from West St to Occidental Rd, Oakes Dr: from Chatham Ct to Durham Wy, Pontiac St: from Dale St to Jackson St, San Antonio St: from San Luis Obispo Av to Zephyr Av, San Luis Obispo Av: from Medallion Dr to San Antonio St, San Luis Obispo Av: from Huntwood Av to Medallion Dr, Vanderbilt St: from Briergate Wy to Garin Av

11/2018 07/2019 10 15 20 10

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 5: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Livermore Alameda Road Maintenance & Rehabilitation

Street Resurfacing 2018 (17/18 Carryover)

Asphalt resurfacing and base repairs of various residential, collector and arterial roadways including repairing curb and gutter, sidewalk, video detection at traffic signals, signing and striping and handicap ramp installation. The priorities for selecting streets to be resurfaced are established by the Pavement Managment System (PMS) and a risk level analysis, traffic volumes and staff field inspections.

P ST (PINE ST to CHESTNUT ST) SCENIC AV (ARROWHEAD AV to 125' E/O MT DIABLO WY) SEVENTH ST (S I ST to S LIVERMORE AV) SILVER OAKS WY (FOURTH ST to SCHOOL ST) WISTERIA WY (BLUEBELL DR to 125' E/O ARROWHEAD AVE) AIRWAY BLVD (220' S/O KITTYHAWK RD to 880' W/O ISABEL) CONCANNON BLVD (WB LANES) (MURDELL LN to ALTAIR AV) (3) EAST AV (XAVIER WY to 160' E/O MADISON AV) HILLCREST AV (EAST AV to YALE WY) POMONA WY (HILLCREST AV to END) JACKSON AV (POMONA WY to LOYOLA WY) SCHOOL ST (MADERIA WY to END) HOLMES ST (MURRIETA BLVD to 200' S/O AARON ST) FOURTH ST (P STREET to 550' W/O Q ST) LAS POSITAS RD (PULLMAN ST to 585' E/O PRESTON AV) N CANYONS PKWY (INDEPENDENCE RD to COLLIER CANYON RD) (2) S. GREENVILLE RD (265' S/O NATIONAL DRIVE to 450' S/O LAS POSITAS RD) PORTOLA AV (N L ST to N LIVERMORE AV) ENOS WY (JUNCTION AV to PORTOLA AV) E STANLEY BLVD (MURRIETA BLVD to FENTON ST) N. VASCO RD (SCENIC AV to CRESTMONT AV) S VASCO RD (NB LANES) (EMILY WY to PATTERSON PASS RD) S VASCO RD (BRISA ST to 60' N/O NAYLOR AVE) WALL ST (EL CAMINITO to E STANLEY BLVD) LEAHY WAY (JENSEN ST to END) GARNET DR (RUBY RD to 310' W/O ZIRCON WY) PEARL DR (MURDELL LN to AMBER WY) QUARTZ CIRCLE (MURDELL LN to END) (2) S. Greenville Rd. Bid Alternate #2 (3) East Ave. Bid Alternate #3

05/2018 12/2018 20 30 16 7

Livermore Alameda Road Maintenance & Rehabilitation Slurry Seal 2018 (17/18 Carryover)

Slurry seal treatment and microsurfacing of residential, collector and arterial roadways, including base repairs, installation of ramps, and signing and striping. The priorities for selecting streets to be slurried are established by the Pavement Management System (PMS) and a risk level analysis, traffic volumes and staff field inspections.

E JACK LONDON BLVD (CURLEW RD to N MURRIETA BLVD) BARBER STREET (DUKE WY to FORDHAM WY) CLARKE AV (CALLAGHAN ST to KENNEDY ST) COVELLITE LN (PEARL DR to END) DUKE WY (MADEIRA WY to FORDHAM WY) EAST AV (CHARLOTTE WY to 1025 FT E/O CHARLOTTE WY) FLINT ST (COVELLITE LN to PEARL DR) FORDHAM WY (DUKE WY to HILLCREST AV) FOURTH ST (60 FT W/O S P ST to S N ST) GARDELLA PLAZA (RR CROSSING to SCOTT ST) HILLCREST AV (YALE WY to FORDHAM WY) JEFFERSON AV (EAST AV to POMONA WY) JUNCTION AV (N LIVERMORE AV to OLD FIRST ST) KELLY ST (ENOS WY to LEE AV) KENNEDY ST (KELLY ST to MARTIN AV) LADD AV (JUNCTION AV to LEE AV) LEE AV (LADD AV to PORTOLA AV) MADEIRA WY (SCHOOL ST to JENSEN ST) MICHELL CT (MICHELL ST to END) MURPHY ST (SCOTT ST to END) OLD FIRST ST (JUNCTION AV to END) OREGON WY (ROSE ST to JENSEN ST) PORTOLA AV (100 FT W/O WOODHAVEN COMM to N L ST) S VASCO RD (PATTERSON PASS RD to RR OVERPASS) S VASCO RD (RR OVERPASS to BRISA ST) SCHERMAN WY (MURDELL LN to ALBERT WY) SCOTT ST (MICHELL ST to FIRST ST) STANFORD CT (STANFORD WY to END) STANFORD WY (E/O JENSEN ST to W/O ESTATES ST) VERN AV (KELLY ST to KENNEDY ST) VISTA ST (PESTANA WY to MADEIRA WY)

05/2018 09/2018 7 10 16 7

Livermore Alameda Road Maintenance & Rehabilitation Street Resurfacing 2019

Asphalt resurfacing and base repairs of various residential, collector and arterial roadways including repairing curb and gutter, sidewalk, video detection at traffic signals, signing and striping and handicap ramp installation. The priorities for selecting streets to be resurfaced are established by the Pavement Managment System (PMS) and a risk level analysis, traffic volumes and staff field inspections.

The following list of preliminary street locations are subject to change and will be selected based on priority need and resources throughout the year.Fourth Street (South Livermore Avenue to Maple Street), Las Positas Road (South Vasco Road to Pullman Street), First Street (South Q Street to South M Street), First Street (South M Street to South L Street), East Avenue (South Livermore Avenue to Sixth Street), East Avenue (Sixth Street to Jensen Street)

05/2019 12/2019 20 30 16 7

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 6: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Livermore Alameda Road Maintenance & Rehabilitation Slurry Seal Project 2019

Slurry seal treatment and microsurfacing of residential, collector and arterial roadways, including base repairs, installation of ramps, and signing and striping. The priorities for selecting streets to be slurried are established by the Pavement Management System (PMS) and a risk level analysis, traffic volumes and staff field inspections.

All preliminary street locations are subject to change and will be selected based on priority need and resources throughout the year. E Stanley Blvd (Murdell And El Caminito) El Caminito (Wall Street And El Padro Street) Farnsworth Dr (Harewood Dr And Lambeth Rd) Felicia Av (Jessica Dr And Nina Wy) Rhododendron Dr (Daffodil Wy And Springtown Blvd) College Av (Cross Creek Pl And S L St) Tamalpais Av (Logan St And Hagemann Dr) Catalina Dr (Orchard Wy And Wagoner Dr) Ventura Av (Rincon Av And Western Av) Sixth St (S N St And S L St) First St (Las Positas Rd And 956' N/O Las Positas Rd) Findlay Wy (Madison Av And Hillcrest Av) Capriconus Av (Bluebell Dr And Aquarius St) Murrieta Blvd (Fenton St And Holmes St) Industrial Wy (Vasco Rd And Preston Av) Florida Ct (Linclon Av And End) Joyce St (Patterson Pass Rd And Theresa Wy) Skylinks Wy (Pasatiempo St And Spyglass Hills Rd) Portola Av (Rincon Av And Alviso Pl) Covington Wy (Wilton Rd And Hanover St) Yosemite Dr (Cascade Av And Yellowstone Wy) Fifth St (Mc Leod St And Maple St) Sunflower Ct (E/O Bluebell Dr And 830' S/O Bluebell Dr) Mc Leod St (First St And Fourth St) Lincoln Av (Stanford Wy And Pomona Wy) Bianca Wy (Shelley St And Felicia Av) Bristlecone Wy (Monterey Dr And End) Farnsworth Dr (Lambeth Rd And Wellingham Dr) Southfront Rd (Mc Graw Av And Franklin Ln (Pave Chg)) N Murrieta Blvd (Del Norte Dr And Portola Av)

05/2019 08/2019 7 10 16 7

Newark Alameda Traffic Control Devices Citywide Street Signs Installation or replacement of street signs at various locations throughout the City

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific street signs on those roadways will be prioritized and selected for maintenance during development of construction plans based on identified needs.

08/2019 12/2019 15 25 25 10

Newark Alameda Traffic Control Devices Thermoplastic Street Striping Installation or replacement of traffic striping and pavement markings at various locations throughout the City

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific locations and limits of thermoplastic pavement striping on those roadways will be prioritized and selected for maintenance during development of construction plans based on identified needs.

08/2019 09/2019 5 10 25 10

Newark Alameda Road Maintenance & Rehabilitation 2019 Street Slurry Seal Program

Roadway pavement preventative maintenance on various streets located throughout the City. Preventative maintenance typically involves application of a slurry seal to the existing roadway pavement

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific sections and limits of roadways on which slurry seal will be applied will be prioritized and selected during development of construction plans based on identified needs.

05/2019 07/2019 5 7 25 10

Newark Alameda Complete Streets Components

Citywide Accessible Pedestrian Ramps

Installation, repair or replacement of accessible pedestrian ramps at various locations throughout the City

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific curb ramp locations on those roadways will be prioritized and selected during development of construction plans based on identified needs.

02/2019 04/2019 20 30 25 10

Newark Alameda Complete Streets Components

2019 Sidewalk, Curb and Gutter Replacement

Repair of damaged concrete curb, gutter and sidewalk at various locations throughout the City.

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific locations and limits of curb, gutter and sidewalk replacement on those roadways will be prioritized and selected for maintenance during development of construction plans based on identified needs.

02/2019 04/2019 15 30 25 10

Newark Alameda Road Maintenance & Rehabilitation 2019 Street Patch Paving Program Removal and replacement of failed roadway pavement sections on various streets

located throughout the City

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific locations and limits of patch paving on those roadways will be prioritized and selected during development of construction plans based on identified needs.

04/2019 06/2019 15 20 25 10

Newark Alameda Road Maintenance & Rehabilitation

2019 Asphalt Concrete Overlay Program

Roadway pavement rehabilitation on various streets located throughout the City. Pavement rehabilitation typically involves removal of 2" of existing pavement and replacement with an asphalt concrete pavement overlay.

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific sections and limits of roadways on which asphalt concrete overlay will be performed will be prioritized and selected during development of construction plans based on identified needs.

04/2019 06/2019 15 20 25 10

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 7: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Newark Alameda Complete Streets Components Traffic Calming Measures Installation of traffic calming measures such as speed bumps on various streets located

throughout the City.

The City of Newark is bounded to the north by State Route 84, to the east by Interstate 880, to the south by Stevenson Blvd and to the west by the SF Bay. In total, the City is responsible for maintaining 106 centerline miles of roadways. Specific roadways and locations on which traffic calming measures will be installed will be prioritized and selected for maintenance during development of construction plans based on identified needs.

04/2019 06/2019 15 20 25 10

Oakland Alameda Road Maintenance & Rehabilitation

Dwight Way Resurfacing (17/18 Carryover) Repave .28 miles of roadway City Limit to Dwight Place 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Panoramic Place Resurfacing (17/18 Carryover) Repave .92 miles of roadway Panoramic Way to West End, and Dwight Way to City Limit (two sections) 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Chatham Road Resurfacing (17/18 Carryover) Repave .65 miles of roadway Beaumont Ave to Park Blvd. South End to 29th Ave (2 segments) 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Bridge Ave Resurfacing (17/18 Carryover) Repave .2 miles of roadway Foothill Boulevard to E. 16th Street 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

E. 16th Street Resurfacing (17/18 Carryover) Repave .29 miles of roadway 34th Ave to 37th Ave 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Mason Street Resurfacing (17/18 Carryover) Repave .08 miles of roadway Foothill Boulevard to Walnut Street 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Shone Ave Resurfacing(17/18 carryover) Repave .23 miles of roadway Sterling Drive to Fontaine Street 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Old Redwood Road Resurfacing (17/18 Carryover) Repave .28 miles of roadway Redwoood Road to North End 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation

Lowell Street Resurfacing (17/18 Carryover) Repave .67 miles of roadway Adeline Street to Market Street 08/2018 01/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation 14th Street Resurfacing Repave 0.40 miles of roadway Wood Street to Mandela Pkwy 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation 29th Avenue Resurfacing Repave 0.22 miles of roadway East 17th St to International Blvd 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation 4th Avenue Resurfacing Repave 0.34 miles of roadway East 12th Street to E 18th Street 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation 82nd Avenue Resurfacing Repave 0.26 miles of Roadway Utah Street to MacArthur Blvd 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Brush Street Resurfacing Repave 0.16 feet of Roadway 3rd Street to 6th Street 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Carson Street Resurfacing No. 1 Repave 0.05 miles of roadway Tompkins Avenue to Fair Avenue 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Carson Street Resurfacing No. 2 Repave 0.19 miles of roadway Reinhardt Drive to Mountain Blvd 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Claremont Avenue Resurfacing Repave 1.05 miles of roadway Alvarado road to Grizzly Peak Blvd 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Enterprise Way Repave 0.24 miles of roadway 85th Avenue to Edes Avenue 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Hillmont Drive Resurfacing Repave 0.10 miles of roadway Sunkist Drive to Edgemoor Pl 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Kingland Avenue Resurfacing Repave 0.15 miles of roadway Birdsall Avenue to Redding Street 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Peterson Street Resurfacing Repave 0.17 miles of roadway East End to Glasscock Street 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Tompkins Avenue Resurfacing Repave 0.13 miles of roadway Carson St to High St 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Webster Street Resurfaing Repave 0.21 miles of roadway Broadway to Grand Avenue 09/2018 04/2019 10 20 18 9

Oakland Alameda Road Maintenance & Rehabilitation Yerba Buena Avenue Resurfacing Repave 0.13 miles of roadway 40th Street to City Limits 09/2018 04/2019 10 20 15 9

Oakland Alameda Road Maintenance & Rehabilitation Local Road Maintenance Citywide Street maintenance activities including potholing and spot repairs to city

streets and sidewalks with city asphalt and concrete crews.

Citywide - Bancroft Avenue, 98th Avenue, Telegraph Avenue, and Foothill Boulevard. Oakland’s street inventory consists of 806 miles of arterial, collector and residential streets. Minor street repair activity is determined by the location of problems, as reported by the general public and noted by city crews. All locations have yet to be finalized and are subject to change throughout the year. Each location will be selected based on priority need and resources.

09/2018 04/2019 5 10 15, 18 9

Piedmont Alameda Road Maintenance & Rehabilitation 2018 Pavement Restoration Project Pavement restoration of Magnolia Avenue Magnolia Avenue between Hillside Avenue and Nova Drive 11/2018 06/2019 20 30 15 9

Pleasanton Alameda Road Maintenance & Rehabilitation One Bay Area Grant Cycle II

The project will resurface various streets throughout Hacienda Business Park in the summer of 2019, including but not limited to: Stoneridge Drive between Gibraltar and Owens, Chabot Drive between Owens and Inglewood and Hacienda Drive between Gibraltar and I-580.

The project will resurface various streets throughout Hacienda Business Park in the summer of 2019, including but not limited to: Stoneridge Drive between Gibraltar and Owens, Chabot Drive between Owens and Inglewood and Hacienda Drive between Gibraltar and I-580.

10/2018 04/2019 10 15 16 7

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 8: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pleasanton Alameda Road Maintenance & Rehabilitation

Annual Resurfacing and Reconstruction of Various Streets

The project will resurface various streets throughout the City in the summer of 2019, including but not limited to: various streets in County Fair Estates off of Paseo Santa Cruz (north); various streets in Rheem tract, Santa Rita road frontage; and various streets in Val Vista, off of Single Tree, Payne, Alvord, and Inglewood. The resurfacing treatments will extend the useful life of the roadway an additional 10 to 15 years.

The project will resurface various streets throughout the City in the summer of 2019, including but not limited to: various streets in County Fair Estates off of Paseo Santa Cruz (north); various streets in Rheem tract, Santa Rita road frontage; and various streets in Val Vista, off of Single Tree, Payne, Alvord, and Inglewood. The resurfacing treatments will extend the useful life of the roadway an additional 10 to 15 years.

02/2019 06/2019 10 15 16 7

San Leandro Alameda Road Maintenance & Rehabilitation Adason Drive Placement of thin overlay of travel lane and crack-seal surface. Adason Drive, between Halcyon Dr. to Hesperian Blvd. 07/2018 08/2018 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Coburn Court Remove and replace all distressed pavement and crack seal surface Coburn Court, between parking lot to end of cul-de-sac 08/2018 08/2018 15 20 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Sherry Court Remove and replace all distressed pavement and crack seal surface Sherry Court between Benedict Dr. to end of cul-de-sac 08/2018 08/2018 15 20 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Hillside Drive Remove and replace all distressed pavement and crack seal surface Hillside Drive between Daily Drive to Montrose Drive 09/2018 09/2018 15 20 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Sylvia Way Crack seal surface from end to end. Sylvia Way between Diletta Ave. to Sidney Ave. 09/2018 09/2018 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Fairway Drive Crack seal surface from end to end. Fairway Drive between Doolittle Drive to 880 Overpass 10/2018 10/2018 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Andover Street Crack seal surface from end to end. Andover Street between Lewelling Blvd. to Burkhart Ave. 10/2018 10/2018 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Duzmal Avenue Crack seal surface from end to end. Duzmal Avenue from Faris Street to cul-de-sac of Kramer Street 04/2019 04/2019 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Foothill Blvd. Crack seal surface from end to end. Foothill Blvd. between Durant Avenue to Macarthur Blvd. 04/2019 04/2019 4 5 18 9

San Leandro Alameda Road Maintenance & Rehabilitation Bigge Street Crack seal surface from end to end. Bigge Street between Adams Ave. to end of cul-de-sac 05/2019 05/2019 4 5 18 9

Union City Alameda Road Maintenance & Rehabilitation Pavement Repair Project

Road maintenance of 1) Decoto Road from Union Square to south City Limits (Fremont); 2) Alvarado-Niles Road from I-880 interchange to Fredi Street; 3) Union City Boulevard from north City Limit (Hayward) to Smith Street and 4)Tamarack Drive from Mission Boulevard to Ithaca Street 5) and various streets.

Decoto Road, Alvarado-Niles Road, Union City Boulevard, Tamarack Drive, and other various streets in Union City, CA. 05/2019 06/2019 10 15 20 10

Amador City Amador Road Maintenance & Rehabilitation Road Maintenance New pavement striping on all City roadways. Main Street; Old Highway 49; O'Neil Alley; God's Hill; Church St.; Keystone Alley 09/2018 12/2018 10 20 5 8

Amador City Amador Road Maintenance & Rehabilitation Road Maintenance Repainting Crosswalks (17/18 Carryover) Old Highway 49; Water St.; Keystone Alley 12/2018 03/2019 10 10 5 8

Ione Amador Road Maintenance & Rehabilitation

2018/19 Pavement Rehabilitation project

Placement of micro-paving on various streets within the City as identified in the City's Pavement Management Programe

BIRCHWOOD COURT, GLENBROOK DRIVE, GLENBROOK DRIVE, QUAIL HOLLOW, RAYMOND CIRCLE, RAYMOND DRIVE, CASTLE OAKS DRIVE, CASTLE OLKS DRIVE, BRIERWOOD, EDGEBROOK, EDGEBROOK, COTTONWOOD COURT

12/2018 06/2019 10 20 5 14

Jackson Amador Road Maintenance & Rehabilitation Citywide Street Drainage Repair Repair and/or replacement of street drainage improvements. China Graveyard Road, Broadway, Jackson Gate/North Main Street 04/2019 05/2019 15 75 5 8

Plymouth Amador Complete Streets Components

Plymouth ATP (Safe Routes to School Project) Shared Path and Bike Lanes Plymouth Elementary School to Shenandoah School Main Street/Shenandoah Rd Plymouth, CA 06/2018 10/2018 20 40 5 8

Sutter Creek Amador Road Maintenance & Rehabilitation Main St. Bridge (17/18 Ongoing) Reconstruction and Rehab Main St. 10/2017 10/2018 10 20 5 8

Biggs Butte Road Maintenance & Rehabilitation Aleut Street 2" grind and overlay with Road Fabric. About 4695 square yards in Area. Between 3rd Street and 7th street. Does not include intersection of crossing streets. 07/2018 12/2018 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation F Street 2" grind and overlay with Road Fabric. About 2108 square yards in Area. Between 2nd street to 4th street. Does not include intersections at 3rd street. 07/2018 12/2018 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation C Street 2" grind and overlay with Road Fabric. About 2191 square yards in Area. From 2nd street to 4th street. Includes 5th and 6th street intersection. 07/2019 08/2019 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation C Street 2" grind and overlay with Road Fabric. About 2463 square yards in Area. From 4th street to 7th street. Includes 5th and 5th street intersections. 07/2019 08/2019 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation West Biggs-Gridley Road 2" grind and overlay with Road Fabric. About 1216 square yards in Area. From Bannock Street south to City Limits. 07/2019 08/2019 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation H street 2" grind and overlay with Road Fabric. From 4th to 7th street. 07/2020 08/2021 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation 6th Street 2" grind and overlay with Road Fabric. From Hamiltion Slough to Chatfield. 07/2020 08/2021 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation 10th Street 2" grind and overlay with Road Fabric. From B treet to Bannock. 07/2021 08/2022 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation 3rd Street 2" grind and overlay with Road Fabric. From Trent to F street. 07/2021 08/2022 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation 7th Street 2" grind and overlay with Road Fabric. From H to C street. 07/2022 08/2023 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation 2nd Street 2" grind and overlay with Road Fabric. From B to F street. 07/2022 08/2023 5 10 3 4

Biggs Butte Road Maintenance & Rehabilitation D street 2" grind and overlay with Road Fabric. From 2nd to 7th Street. 07/2022 08/2023 5 10 3 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 9: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Chico Butte Road Maintenance & Rehabilitation

Street Improvements and Maintenance (2018) Cohasset Road (Carryover Project FY17/18)

The project involves reconstruction of Cohasset Road between East Avenue and Eaton Road. Roadway rehabilitation will include a 4-inch grind and inlay of approximately 5,207 linear feet (LF) of the existing roadway. Construction of new sidewalks and upgrading existing curb ramps to be ADA compliant will occur along the corridor. Class 2 bike lanes will be included in the new striping plan to promote safe bike travel through the corridor and continue the city’s efforts to expand Chico’s bike lane infrastructure.

On Cohasset Road, from approximately 500' north of East Avenue to just south of Eaton Road. 04/2018 07/2018 18 25 3 4

Chico Butte Road Maintenance & Rehabilitation

Street Improvements and Maintenance (2019) Esplanade from Lindo Channel to East Ave

Preform a Cold in-Place Recycle (CIR) of approximately 0.70 miles of existing pavement surface, including upgrades to ADA curb ramps (19), installation of Class II bike lanes, and restriping.

On Esplanade, from the Lindo Channel bridge to East Ave 03/2019 06/2019 18 30 3 4

Gridley Butte Road Maintenance & Rehabilitation Spruce Street Rehab Repair structural failures and Grind and Overlay, 5284 L.F. full Width. Oregon Street to Virginia Street 06/2019 12/2019 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Magnolia Street Rehab Repair structural failures and Grind and Overlay, 2575 L.F. full Width. Oregon Street to Virginia Street 06/2019 12/2019 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Nevada Street Rehab Repair structural failures and Grind and Overlay, 400 L.F. full Width. Cedar Street to Laurel Street 06/2020 12/2020 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Indiana Street Rehab Repair structural failures and Grind and Overlay, 450 L.F. full Width. Peach Street to Pecan Street 06/2020 12/2020 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Peach Street Rehab Repair structural failures and Grind and Overlay, 330 L.F. full Width. Indiana Street to Vermont Street 06/2021 12/2021 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Bridgeford Street Rehab Repair structural failures and Grind and Overlay, 427 L.F. full Width. Ohio Street to Virginia Street 06/2021 12/2021 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Ohio Street Rehab Repair structural failures and Grind and Overlay, 800 L.F. full Width. Spruce Street to Sycamore Street 06/2022 12/2022 5 10 3 4

Gridley Butte Road Maintenance & Rehabilitation Kentucky Street Rehab Repair structural failures and Grind and Overlay, 800 L.F. full Width. Spruce Street to Sycamore Street 06/2022 12/2022 5 10 3 4

Oroville Butte Road Maintenance & Rehabilitation Orange Avenue Repave/Resurface Along Montgomery Street to Long Bar Rd 01/2020 06/2020 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation FEATHER RIVER BL Repave/Resurface ORO DAM BLVD. E TO SAFFORD ST. 01/2020 06/2020 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation NELSON AV Repave/Resurface 4TH ST TO END OF SCHOOL 01/2020 06/2020 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation 6TH STREET Repave/Resurface NELSON AVE TO END OF SCHOOL 01/2020 06/2020 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation ORO BANGOR HWY Repave/Resurface LINCOLN ST TO BURLINGTON AVE 01/2019 06/2019 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation GREENVILLE ST Repave/Resurface LINCOLN ST TO BURLINGTON AVE 01/2019 06/2019 10 20 3 4

Oroville Butte Road Maintenance & Rehabilitation MYERS ST Repave/Resurface LINCOLN ST TO WYANDOTTE AVE 01/2019 06/2019 10 20 3 4

Paradise Butte Complete Streets Components Paradise Gap Closure Complex

Project exemplifies the meaning of 'complete streets' effort as work will include road rehabilitation, installation of new sidewalks, bike lanes, bike paths, lighting, and drainage.

Almond Street (Pearson to Elliott), Birch Street (Skyway to Black Olive), Fir Street (Skyway to Black Olive), Elliott Road (Skyway to Almond), Black Olive (Pearson to Fir), Foster Road (Pearson to Birch) 08/2018 08/2020 10 50 3 4

Angels Camp Calaveras Road Maintenance & Rehabilitation 2018 Road Improvment Project Repave or Reconstruct Acorn Drive Acorn Drive 07/2018 08/2018 30 40 5 8

Colusa Colusa Road Maintenance & Rehabilitation 5th Street Reconstruction 5th Street Structural Reconstruction: Levee Rd - Market; Oak - Webster; Lafayette - South City Limits 05/2019 06/2019 20 30 3 4

Colusa Colusa Road Maintenance & Rehabilitation 3rd Street Reconstruction 3rd Street Structural Reconstruction Jay Street - Webster 05/2019 06/2019 20 30 3 4

Colusa Colusa Road Maintenance & Rehabilitation Alley Ways (Various) Structural Reconstruction of Various Alley Ways Alley Between Carson and Sioc; 7th - 5th, 10th - 9th., Alley Between Fremont and Carson; 13th - 12th,

Alley Between Market and Jay; 12th - 10th 05/2019 06/2019 20 30 3 4

Colusa Colusa Road Maintenance & Rehabilitation City Wide Cape Seal Cape Seal of Various City Streets

Clay Street Between 12th - 11th, Main Street Between 8th - 6th, Fremont Street Between 5th - 3rd; 10th - 9th, and B st. - Bridge St. , 11th Street Between Oak and Parkhill, Lafayette Street Between 7th - 6th.

05/2019 06/2019 5 10 3 4

Williams Colusa Road Maintenance & Rehabilitation

Husted Rd South Pavement Rehab Project (17/18 carryover) Husted Road (South) Pavement Repair & Overlay Husted Road (South) from I-5 to Abel Road 06/2019 12/2019 7 10 4 4

Williams Colusa Road Maintenance & Rehabilitation 7th Street Rehab Project Pavement Repair & Overlay 7th Street/ Frontage Road from Theater Road to Husted Road 06/2020 12/2020 7 10 4 4

Williams Colusa Road Maintenance & Rehabilitation

Husted Rd North Pavement Rehab Project Pavement Repair & Overlay Husted Road (North), from E street to State Route 20 06/2021 12/2021 7 10 4 4

Williams Colusa Road Maintenance & Rehabilitation E Street Rehab Project Pavement Repair & Overlay E street from Husted Road to 6th Street 06/2022 12/2022 7 10 4 4

Williams Colusa Road Maintenance & Rehabilitation Intersection Improvements Pavement repairs, sidewalk improvements, and traffic control devices at various Street

Intersection Locations

Pavement overlay on E Street from the Vann Street intersection east to approximately 400 feet. Sidewalk repairs & ADA ramps on E Street at I-5 Off-ramp intersection and at 8th Street intersection. Traffic control improvements on E Street at Vann Street intersection and at 8th Street intersection.

06/2018 11/2018 7 10 4 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 10: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Antioch Contra Costa Road Maintenance & Rehabilitation 2019 Ruberized Cape Seal Project Leveling Course (where needed) and rubberized cape seal

various locations: (109 locations)Acorn Road, Milner Road, Matssqui Road, Longview Court, Kalama Road, Langley Court, Chrisse Court, Nanimo Court, Shasta Court, Terranova Drive, Clearbrook Drive, Echo Cir, Clayburn Road, Fairside Way, Primrose Court, Morning Vale Court, Pembroke Court, Sandrose Court, Washington Way, Jefferson Way, Garfield Place, Regan Ct, Johnson Drive, Hayes Way, Carter Way, Harding Way, Harding Court, Van Buren Drive, S. Apple Court, Cherry Street

02/2019 09/2019 10 15 11 7

Brentwood Contra Costa Road Maintenance & Rehabilitation

Pavement Management Program - 2019

This project will consist of pavement condition surveying of roadways every two years and then reconstructing, overlaying, surface sealing and crack sealing various roads each year as needed. The City's pavement management software selects those streets on which it is the most cost effective to perform preventative maintenance with field verification by staff. Constructing roadways is a significant investment for the City. Preventative maintenance is the best means for keeping this large investment in good, operable condition and avoids costly reconstruction.

The City of Brentwood currently maintains:192 Miles of Streets, 5,957 Street Lights, 65 Traffic Signals, 9,416 Traffic Signs, 150 acres of weed abatement 05/2019 08/2019 7 15 11 7

Brentwood Contra Costa Road Maintenance & Rehabilitation

Pavement Management Program - 2018 (17/18 Ongoing)

This project will consist of pavement condition surveying of roadways every two years and then reconstructing, overlaying, surface sealing and crack sealing various roads each year as needed. The City's pavement management software selects those streets on which it is the most cost effective to perform preventative maintenance with field verification by staff. Constructing roadways is a significant investment for the City. Preventative maintenance is the best means for keeping this large investment in good, operable condition and avoids costly reconstruction.

Armstrong Road, Elkins Way, Sycamore Avenue, and the residential neighborhood south of Balfour Road between Fairview Avenue and Walnut Avenue. 05/2018 08/2018 7 15 11 7

Brentwood Contra Costa Road Grade Separation Lone Tree Way - Union Pacific Undercrossing

This project will construct a grade separation underpass consisting of four travel lanes crossing under the Union Pacific Railroad. This project entails: constructing a bridge structure; relocation of numerous existing wet and dry utilities; high pressure gas lines; storm water pump station; retaining walls and landscaped parkway. This project will increase public safety by creating a grade separation crossing of the Union Pacific Railroad, instead of the present at-grade crossing.

Lone Tree Way and Union Pacific Railroad at-grade crossing 07/2021 07/2023 25 30 11 7

Brentwood Contra Costa Complete Streets Components

Brentwood Boulevard Widening North - Phase I

This project will continue the widening of Brentwood Boulevard with two lanes in each direction and will include: two bike lanes; curbs; gutters; medians; sidewalk on east side; street lights and landscaping on each side of the roadway. This project will also include a new parallel bridge over Marsh Creek, traffic signal modification at Brentwood Boulevard and Grant Street and moving the overhead power lines, telephone lines and cable lines underground. This project will improve safety, traffic flow and facilitate adjacent development.

Brentwood Boulevard from Havenwood Avenue to Homecoming Way 07/2020 07/2021 25 30 11 7

Brentwood Contra Costa Safety John Muir Parkway Extension - Phase II (17/18 Carryover)

Construct approximately 1,600' of road including a 16' median; two 12' lanes; 12" water main; median landscaping; street lights; 24" storm drain and 8" non-potable water main. This section of roadway will replace existing Concord Avenue to ensure continued traffic circulation in the area.

John Muir Parkway from the future Foothill Drive intersection with Concord Avenue to Briones Valley Road 05/2019 11/2019 25 30 11 7

Brentwood Contra Costa Road Maintenance & Rehabilitation

Brentwood Various Streets and Road Preservation

This project will provide pavement rehabilitation and preventative maintenance on arterial roadway segments in the City. Treatments will include grind and overlay, spot repairs, and slurry seals/crack seals. These pavement rehabilitation activities will require removal and replacement of ADA ramps to ensure compliance with current accessibility requirements. New traffic signal detection and striping will also be required where the existing assets are removed.

Balfour Road from Minnesota Avenue to Fairview Avenue and from East Country Club Drive to the Western City Limits; Lone Tree Way from Brentwood Boulevard to Medallion Drive, excluding portion located in unincorporated Contra Costa County

05/2021 09/2021 15 20 11 7

Brentwood Contra Costa Road Maintenance & Rehabilitation

Downtown Alley Rehabilitation (17/18 Carryover)

This project includes the installation of new water and sewer facilities, the rehabilitation of existing facilities, including streetlights and either the removal or replacement of existing infrastructure, to correct existing operations and maintenance constraints due to the age of the facilities. This project will allow the City to accommodate the anticipated development of the Downtown area and, where feasible, bring the aging facilities up to current standards.

Diablo Way and Midway Alleys, bounded by Brentwood Boulevard, Pine Street, Second Street, and Chestnut Avenue 06/2019 07/2022 25 30 11 7

Clayton Contra Costa Road Maintenance & Rehabilitation

Pine Hollow Road Improvement Project

Street rehabilitation and complete streets components for Pine Hollow Road between Mt Zion/Tiffin Drives and the Western City Limit line opposite from Quiet Circle. Pine Hollow Road, Clayton, CA 04/2019 04/2020 7 50 14 11

Clayton Contra Costa Road Maintenance & Rehabilitation

2018 Neighborhood Streets Project (2017-18 Ongoing) Annual Street maintenace of various local neighborhood streets within Clayton, CA

City of Clayton: Frank Place - Yolanda Circle to Cul-de-Sac, Bettencourt Drive - Yolanda Circle East to Yolanda Circle West, Southbrook Drive - 250' west of Marquette Ct. to 100' east of Eastwood Ct, Westbrook Ct. - Southbrook Dr. to Cul-de-Sac, El Camino Dr. - Clayton Rd. to Pine Hollow Rd, Coronado Ct. - El Camino Dr. to Cul-de-Sac, Yosemite Ct. - El Camino Dr. to Cul-de-Sac, Yosemite Cir. - El Camino Dr. South to El Camino Dr. North.

06/2018 12/2018 7 10 14 7

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 11: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Concord Contra Costa Road Maintenance & Rehabilitation

Oak Grove Road Pavement Rehabilitation

This project will extend the recently completed pavement rehabilitation work on Oak Grove Road from Whitman Road to Treat Boulevard, likely using cold-in-place recycling, similar to the previous phase, whereby a portion of the existing roadway asphalt is removed, treated with an asphalt recycling agent, compacted in place and then covered with a new asphalt surface layer. Work will also include the installation/upgrade of curb ramps at intersections, minor concrete repairs, replacement of traffic signal loops, adjustment of pedestrian push buttons to meet accessibility standards, and restriping the roadway.

Oak Grove Road from Whitman Road to Treat Boulevard 01/2019 12/2019 15 20 14 7

Concord Contra Costa Road Maintenance & Rehabilitation

Diamond Boulevard Pavement Rehabilitation (17/18 Carryover) (17/18 Ongoing)

This project will include base repairs and resurfacing of Diamond Boulevard from Willow Pass Road to the bridge over Walnut Creek and include the upgrade/replacement of accessible ramps on the north side of the intersection and at driveways, minor curb and gutter repairs, traffic signal loop replacement, and restriping the roadway.

Diamond Boulevard from Willow Pass Road to the bridge over Walnut Creek 01/2019 12/2019 10 12 14 7

Danville Contra Costa Road Maintenance & Rehabilitation Pavement Management Program

The work generally includes, but is not limited to, preparatory tree trimming, removal and replacement of existing Portland Cement Concrete curb, sidewalk, curb ramp, and valley gutter, installing PCC swale, subdrain installation, removal and replacement of existing asphalt concrete pavement (dig-outs), pavement cold planning, installation of paving mat, installation of asphalt concrete overlay, removal and replacement of asphalt concrete speed lumps/bumps, removal and replacement of new traffic signal loop detectors, adjusting to grade of survey monument castings, water valve castings, storm drain and sanitary sewer manhole covers, and other utility lids, removal and replacement of existing pavement striping and markers, traffic control, and other items as required.

Various streets in Danville including El Capitan Drive, El Cerro Boulevard, Brookside Drive, Freitas Road. 06/2018 09/2018 20 25 16 7

El Cerrito Contra Costa Traffic Control Devices Street Light, Traffic Signal & Street Sign Replacement and Upgrades

Replacement, repair and upgrades of street light equipment, traffic signal equipment and street signs

Citywide on arterial and collector streets. These include Principal Arterials: Carlson Blvd, Central Ave, Fairmount Ave, San Pablo Ave; Minor Arterials: Ashbury Ave, Arlington Blvd, Barrett Ave, Colusa Ave, Cutting Blvd, Elm Street, Hill St, Key Blvd, Moeser Ln, Potrero Ave, Richmond St; and Major Collectors: Alta Punta, Ashbury Ave, Avis Dr, Buckingham Dr, Colusa Ave, Edwards Ave, Eureka Ave, Fairview Dr, Ganges Ave, Jordan Ave, King Dr, Macdonald Ave, Manila Ave, Navellier St, San Mateo St, Sea View Dr, Shevlin Dr, South 55th St, Terrace Dr, and Tulare Ave. All locations have yet to be finalized and will be selected based on safety need, condition of existing asset, and traffic volumes.

10/2018 09/2019 10 25 15 9

El Cerrito Contra Costa Safety Central Ave & San Diego St Pedestrian Crossing Improvements

Pedestrian Crossing Improvements including flashing beacons and median modifications Carlson Boulevard at San Diego St 12/2018 12/2019 10 25 15 9

El Cerrito Contra Costa Safety Central Ave & Carlson Blvd Street Improvements

Pedestrian Crossing Improvements including high-visibility crosswalk pavement markings and signs and median modification Carlson Boulevard at El Dorado St 09/2018 09/2020 7 25 15 9

El Cerrito Contra Costa Complete Streets Components

Active Transportation Program (17/18 Ongoing)

Implement the Active Transportation Plan, adopted by the City Council in April 2016, includes access, safety and other enhancements to pedestrian and bicycle infrastructure.

Locations are on major Pedestrian and Bicycle Routes as identified in the City's Active Transportation Plan (available for review at www.el-cerrito.org/ATP) including San Pablo Avenue, BART to Bay Trail connection along Fairmount Avenue-Carlson Blvd-Cerrito Creek path-Lassen St-San Diego Street-Belmont Ave-Central Ave, Richmond St, Fairmount Ave, Key Blvd and Arlington Blvd. Locations have yet to be finalized and will be selected based on leveraging of other funding opportunities and grant prioritization criteria and prioritization criteria in the Active Transportation Plan.

12/2020 12/2030 7 25 15 9

El Cerrito Contra Costa Complete Streets Components

Korematsu Safe Routes to School Improvements, Phase 1 (17/18 Carryover)

Implement enhanced crosswalk signing & striping and portions of the East Side Bicycle Boulevard per the City's Active Transportation Plan in the vicinity of the school

Bicycle boulevard striping and speed humps on Norvell St and Schmidt Ln between Potrero Ave and Richmond St and enhanced crosswalks on Richmond St, Norvell St and Lawrence St at Gladys and Donal Aves, on Navellier St at Gladys Ave, on Potrero Ave at Navellier St

07/2018 12/2018 7 10 15 9

El Cerrito Contra Costa Safety Sidewalk & Street Sign Maintenance (17/18 Ongoing) Sidewalk repair and sign replacement

Locations on Richmond St, San Pablo Ave, Arlington Blvd and Moeser Ln for signs and other prioritized locations throughout the City to address citizen requests for sidewalk repairs including Elm St, Douglas Dr, Kearney St, Edith St, Cutting Blvd, Potrero Ave, Roberta Dr, Richmond St, Fairmount Ave, Coronado St, Moeser Lane, and San Pablo Ave .

06/2018 12/2018 10 25 15 9

El Cerrito Contra Costa Safety Sidewalk Infrastructure Maintenance Repair sidewalk areas uplifted by street tree roots, including tree root pruning or tree removal.

Locations are on major Pedestrian Routes including: San Pablo Ave., Richmond St., Central Ave., Potrero Ave., and Cutting Blvd. Locations have yet to be finalized and will be selected based on a methodology that prioritizes locations on major Pedestrian Routes (designated in the City’s Active Transportation Plan), and based on their proximity to schools, the severity of the sidewalk damage and repair method, and other factors (e.g. number of requests received).

12/2018 06/2019 20 25 15 9

El Cerrito Contra Costa Traffic Control Devices Street Light & Traffic Signal Maintenance Street light and traffic signal on-going maintenance Citywide for on-going maintenance of 12 traffic signalized intersections, 1728 City-owned street light

locations, and 17 flashing beacons/ in-roadway lights/ radar speed feedback signs locations. 08/2018 06/2019 10 20 15 9

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 12: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

El Cerrito Contra Costa Safety Access Modifications - Streets & Sidewalks

Implement the City's American with Disabilities Act (ADA) Transition Plan, adopted by City Council in 2009 to remove physical barriers along the street right-of-way including mid-block sections of sidewalks, intersections and pedestrian signals

Locations are on major Pedestrian Routes and serving City facilities, which include: Moeser Lane and Pomona Ave adjacent to the Civic Theater and connecting to Community Center/Swim Center. Additional locations are on other major Pedestrian Routes including Arlington Blvd, Ashbury Ave, Barrett Ave, Central Ave, Colusa Ave, Cutting Blvd, Fairmount Ave, Hill St, Navellier St, Moeser Ln, Potrero Ave, Richmond St, San Pablo Ave, Schmidt Ln, Stockton Ave. Locations have yet to be finalized and will be selected based on methodology contained in the City's ADA Transition Plan (available for review at http://www.el-cerrito.org/522/ADA-Transition-Plan). These are locations along Pedestrian Routes (designated in the City’s Active Transportation Plan), locations requested by a person with disabilities, locations serving state and local government office and facilities, locations serving important transportation including pathways to schools, and locations serving commercial zones and other Title III entities.

12/2018 06/2019 10 25 15 9

Hercules Contra Costa Road Maintenance & Rehabilitation

2018 Pavement Maintenance Project Work includes pavement dig-outs, crack filling, slurry seal and reinstall striping.

Coronado Street ( Refugio Valley Road to Carson Street), Carson Street (Refugio Valley Road to Coronado Street), Falcon Way (Sparrow Drive to Wren Court), Bobolink Way (Partridge Drive to Sparrow Drive), Brighton Street (Dartford Way to Edinburgh Court), Canterbury (Newbury Court to Dartford Way), Village Parkway (Hercules Avenue to Hercules Avenue), Goldenrod Drive (Violet Road to Columbine Drive)

08/2018 09/2018 7 10 15 9

Lafayette Contra Costa Road Maintenance & Rehabilitation 2019 Road Reconstruction Project

Fully reconstruct six residential streets. Existing streets will be pulverized in-place to a depth of approximately 16 inches to create a new road base and reclaim existing asphalt concrete, base rock, and sub-base materials. New base may be cement-treated based on actual field and testing conditions. following re-grading, the new base will receive two layers of hot mix asphalt concrete to provide a strong and smooth road surface.

Barrot Road - Stanley Boulevard to the end Clover Court - Stanley Boulevard to the end of court Grondine Road - South Silver Springs to the end of road Linda Vista Lane - Old Tunnel road to the end of lane Rohrer Drive - Silvrado Drive to Dead Horse Canyon Rossi Street - Reliez Valley Road to the end of the street

04/2019 10/2019 25 30 16 7

Lafayette Contra Costa Road Maintenance & Rehabilitation

2018 Road & Drain Rehabilitation Project

Reconstruct failed pavement by rebuilding the roadway structural section. Replace failed storm drain crossing coincident with road reconstruction. This is a carryover project that Lafayette submitted last year.

Crescent Dr, Del Arroyo Ct, Hillview Ln, Moon Ct, Via Baja, Via Media 04/2018 10/2018 25 30 16 7

Martinez Contra Costa Road Maintenance & Rehabilitation

2019 Downtown Arterial Paving Project Base failure repair and AC overlay, ADA ramps Alhambra Ave from Jones St to Marina Vista; Pine/Court Street from Susana St to Marina Vista 06/2019 06/2020 12 25 14 3

Moraga Contra Costa Road Maintenance & Rehabilitation

2018 Joint Moraga-Orinda Full Depth Reclamation

The type of rehabilitation chosen for this year’s pavement rehabilitation project will be Full Depth Reclamation (FDR), a technique that pulverizes the existing asphalt pavement and underlying base material and blends it with cement to create a reconstructed roadway base with superior strength. This eco-friendly method efficiently utilizes existing materials, with lessened needs for virgin materials and off haul/delivery trucking. The roadway will receive a top overlay of Rubberized Hot Mix Asphalt (RHMA) as a wearing surface, a product that incorporates recycled rubber from tires, and thereby provides the environmental benefit of diverting tires from landfills. The streets selected --with the length and area to be rehabilitated -- are listed under “Project Location”.

On April 11th, 2018, The Moraga Town Council approved Resolution 19-2018, appropriating $278,728 of RMRA funds to the Town’s annual Pavement Management Program for this summer’s pavement rehabilitation project. This total is in addition to the $93,300 appropriated in October 2017 for the same project, which will span two fiscal years (2017/2018 and 2018/2019), with the specific portions of the project funded, by year, as follows:Tharp Drive (Redfield Place to Springfield Place), 430 linear feet / 14,190 Square feet, FY 2018/19Tharp Drive (Springfield Place to Deerfield Drive), 635 linear feet / 20,955 Square feet, FY 2018/19 Tharp Drive (Deerfield Drive to Butterfield Place), 355 linear feet / 11,715 Square feet, FY 2017/18

04/2018 10/2018 20 20 16 7

Oakley Contra Costa Complete Streets Components

Laurel Road Widening Project (Rose Avenue to Mellowood Drive)

The scope of CIP 196 is to complete the roadway and median improvements on Laurel Road between Rose Avenue and Mellowood Drive. This work includes design and construction of pavement widening, bike lanes, new curbs, gutters, sidewalks, medians, street, landscaping with new street trees and lights.

Laurel Road between Rose Avenue and Mellowood Drive 07/2018 01/2019 20 25 11 7

Oakley Contra Costa Road Maintenance & Rehabilitation

FY 2018-19 Street Repair and Resurfacing Project

The project streets all have different degrees of failures due to their age and varying pavement condition. The project will repair identified streets and place a Thin Maintenance Overlay (TMO) over those streets. The TMO provides a minor structural benefit that will have a longer useful life. Other streets identified in the project and are not as severely worn will get slurry seal treatment that will extend the life of the roadways.

The Repair and Resurfacing Project consists of the following streets: Walnut Meadows Drive, Merlot Lane, Merlot Court, Chappalet Place, Walnut Meadows Court, Fetzer Court, Fetzer Lane, Jordan Lane, Forbes Court, Jomanet Court, Soda Rock Place, Deerpark Road, Deerpark Way, Deerpark Court, Northgate Place, Lakespring Drive, Cotati Court, Beaulieu Lane, Lakespring Place, Lakespring Court, W. Summerfield Ct., E. Summerfield Ct., Fairhaven Way, Fairhaven Ct.

08/2018 10/2018 5 10 11 7

Orinda Contra Costa Road Maintenance & Rehabilitation

Miner Road Pavement Rehabilitation & Shoulder Widening Project

Rehabilitate existing pavement and include width to selective should pavement areas where feasible. A portion of Miner Road from Camino Pablo to Lombardy Lane. 05/2018 07/2018 10 15 16 7

Pinole Contra Costa Road Maintenance & Rehabilitation

Annual Residential Slurry Seal Project RO1807-SB1 (P1) Crack seal, repair isolated base failures, slurry seal, and reinstall existing striping

Valley Ave, San Pablo Avenue to Charles Avenue;Lopes Lane, All; Clark Court, All; Danny Court, All; Collins Ave, All; Clark Court, All, Flamingo Court, All;, Blue Jay Circle, All; Whippoorwill Court, All, Park Street, Quinan to Tennant; Rafaela Street, Pinole Valley Road to John Street; Sunnyview Drive, San Pablo Avenue to Woy Circle; Wilde Court, All

07/2018 07/2019 3 5 15 9

Pinole Contra Costa Road Maintenance & Rehabilitation

Annual Residential Rehabilitation Project RO1807-SB1 (P2) Thin AC Overlay Delores Court 01/2019 07/2019 6 10 15 9

Pinole Contra Costa Road Maintenance & Rehabilitation

Annual Residential Rehabilitation Project RO1807-SB1 (P3) Localized patch paving to correct base failures Tennent Avenue, from Pinole Valley Road to WPCP 07/2018 07/2019 6 10 15 9

Pinole Contra Costa Road Maintenance & Rehabilitation

Annual Residential Slurry Seal Project RO1701-A (17/18 Ongoing) Crack seal, repair isolated base failures, slurry seal, and reinstall existing striping Crestview Dr (all), Major Vista Ct (all), Nob Hill Ave (Meadow Ave to Sunnyview Dr), Fifth Ave (San

Pablo Avenue to Nob Hill Ave), O’Conner Dr. (City Limits to Bantry Rd). 01/2018 09/2018 3 5 15 9

Pittsburg Contra Costa Traffic Control Devices Traffic Signal Modification Modifications to traffic signal timing and modernization of traffic control equipment Loveridge Road and West Leland Road 07/2018 08/2018 1 10 14 7

Pittsburg Contra Costa Road Maintenance & Rehabilitation Citywide Pavement Striping Installation or replacement of striping on streets as determined by Staff Loveridge Road from Pittsburg-Antioch Highway to Buchanan Road 07/2018 08/2018 1 5 14 7

Pittsburg Contra Costa Road Maintenance & Rehabilitation

W. Leland Road Pavement Management Pavement rehabilitation of W. Leland Road W. Leland Road from Railroad Avenue to Woodhill Drive 06/2018 07/2019 10 20 14 7

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 13: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pittsburg Contra Costa Traffic Control Devices 2018 Traffic Signal Modification (17/18 Ongoing) Modifications to traffic signal timing and modernization of traffic control equipment Citywide, with emphasis on the Leland Road corridor 07/2017 08/2018 1 10 14 7

Pleasant Hill Contra Costa Complete Streets Components

Pleasant Hill Road Improvement Project (Taylor Boulevard to Gregory Lane)

Project elements include new street lighting, intersection geometry modification, lane reconfiguration, new signals at PHR/Westover Drive and PHR/Gregory Lane intersections, pavement rehabilitation, new bike lanes, and landscaping.

Pleasant Hill Road, Between Gregory Lane and Taylor Boulevard, Pleasant Hill, CA 07/2019 08/2019 12 22 14 3

Richmond Contra Costa Road Maintenance & Rehabilitation Pavement Rehabilitation Project

Concrete sidewalk, curb and gutter repairs, ADA curb ramps; localized asphalt base repairs, asphalt milling and hot mix asphalt/rubberized hot mix asphalt overlay; pavement striping and markings; traffic calming elements and regulatory signs; installation of bicycle facilities; and traffic signal modifications for vehicular, pedestrian, and bicycle safety.

Portions of 7th Street, Castro Ranch Road, Cutting Boulevard, Giant Highway, Marina Way, and South 55th Street. 12/2018 12/2019 15 20 15 9

San Pablo Contra Costa Road Maintenance & Rehabilitation

Market Street Pavement Rehabilitation Project

The Market Street Resurfacing Project includes annual pavement rehabilitation and preventative maintenance. The Pavement Condition Index (PCI) for this arterial section of pavement is 51. Pavement in this area is significantly distressed due to high traffic volumes and transit use. The work to be performed will include, but is not limited to, base failure repairs, slurry sealing, crack sealing, cold planing of existing asphalt concrete, overlaying or reconstructing the existing asphalt concrete pavement with conventional asphalt concrete, constructing concrete curb ramps, placement of striping and installing valley gutters.

The project section is located between Church Lane and 23rd Street along Market Street. 09/2018 01/2019 15 20 15 9

San Ramon Contra Costa Road Maintenance & Rehabilitation

2019 Pavement Management Project

This project provides street rehabilitation work in accordance with the City Pavement Management Program. Based on long-range projections, each street is programmed for necessary rehabilitation. Street rehabilitation work will include slurry seal, microsurfacing , asphalt overlays, street reconstruction, etc.

ADELAIDE HILLS CT(ARROWFIELD WAY to END),ALBION RD(HARCOURT WAY to WATERMILL RD),ALKANTE CT(ASTERBELL DR to END),ALLANMERE CT(ALLANMERE DR to END),ALLANMERE DR(ARROWFIELD WAY to ANDREAS WAY),ANDREAS CT(ANDREAS WAY to END),ANDREAS WAY(ARROWFIELD WAY to END),ANGSLEY CT(N BELLINGHAM WAY to END),ANGSLEY LN(ARROWFIELD WAY to N BELLINGHAM WAY),APPLEWOOD DR(S MONARCH RD to GOLDENBAY AVE) - Not Limited To These Locations TBD

05/2019 12/2019 3 20 16 7

San Ramon Contra Costa Road Maintenance & Rehabilitation

Crow Canyon Road Pavement Rehabilitation

This project will provide pavement repair on Crow Canyon Road, including slurry seal/microsurfacing, localized repairs, reconstruction and striping on the entire project limits.

Along Crow Canyon Road, from St. George Road to Dougherty Road. 03/2019 11/2019 7 15 16 7

Walnut Creek Contra Costa Road Maintenance & Rehabilitation Oak Grove Road Rehabilitation

"The 2018 Oak Grove Rehabilitation project will repave Oak Grove Road from Ygancio Valley Road to Cedro Lane, and Oak Grove Road from Mitchell Drive to the City Limits. These sections were last repaved between 1982 and 1990 and has a PCI average rating of 59. The project will perform required ADA upgrades and traffic signal upgrades as needed. The roadway area to be repaved is estimated to be 275,000 S.F. This project will be funded by Measure J/ Gas Tax Funding."

The 2018 Oak Grove Rehabilitation project will repave Oak Grove Road from Cedro Lane to Ygnacio Valley Road, and Oak Grove Road from Ygnacio Valley Road to the City Limits. 04/2018 05/2018 10 20 14 7

Walnut Creek Contra Costa Road Maintenance & Rehabilitation North Main Street Rehabilitation

The 2019 OBAG North Main Street project will repave North Main Street from Interstate 680 to California Boulevard. This section of North Main Street was last repaved in 1982 and has a PCI rating of 69. The project will perform required ADA upgrades and traffic signal upgrades as needed. The roadway area to be repaved is estimated to be 127,000 S.F. for a project cost of $900,000.

North Main Street between Interstate 680 & California Blvd 01/2019 08/2019 10 20 14 7

Walnut Creek Contra Costa Road Maintenance & Rehabilitation Ygnacio Valley Road Rehabilitation

Ygnacio Valley Road Rehabilitation Project will repave Ygnacio Valley Road from Civic Drive to San Carlos Drive. This section of Ygnacio Valley Road was last repaved in 1989 and has a PCI rating of 70. The project will perform required ADA upgrades and traffic signal upgrades as needed. The roadway area to be repaved on Ygnacio Valley Road is estimated to be 630,000 S.F.

Ygnacio Valley Road between Civic Drive and San Carlos Drive 01/2020 08/2020 10 20 14 7

Walnut Creek Contra Costa Road Maintenance & Rehabilitation

Broadway and Parkside Drive Rehabilitation

The 2020 Roadway Rehabilitation project will repave Broadway from Parkside Drive to Ygnacio Valley Road and Parkside Drive from Civic Drive to San Juan Avenue. Broadway and Parkside Drive were last repaved between 1986 and 1993 and has a PCI average rating of 71. The project will perform required ADA upgrades and traffic signal upgrades as needed. The roadway area to be repaved is estimated to be 191,000 S.F.

Broadway between Parkside to Ygnacio Valley Road Parkside Drive between San Juan to Civic Dr 01/2020 08/2020 10 20 14 7

Crescent City Del Norte Road Maintenance & Rehabilitation

K Street Drainage Improvement and Roadway Rehabilitation Project (17/18 Ongoing)

Install new drainage improvements, repave/resurface a minimum of 300 LF of Roadway, install new ADA compliant access ramps and pedestrian improvements K Street between Front Street and 2nd Street 03/2020 06/2020 20 30 2 2

Crescent City Del Norte Road Maintenance & Rehabilitation

Crescent City Storm Drainage Improvement and Roadway Rehabilitation Project (17/18 Ongoing)

Install new drainage improvements, repave/resurface a minimum of 1200 LF of Roadway, install new ADA compliant access ramps and pedestrian improvements Front Street between F Street and B Street, C Street between Howe Drive and 5th Street 06/2018 06/2019 20 30 2 2

Placerville El Dorado Safety Safety Retro-Reflective Signage Replace old traffic signs and street signs with new standard safety retro-reflective signs throughout the city

Street signs and Stop signs throughout the city.All locations subject to change and will be selected based on priority need and resources throughout the year. Barrett, Dr. Bartlett Ave., Bedford Ct., Benson Ct, Chapel St. Cottage St., Corker St. Cresent St. Debra Ct. Deena Ct, Dimity Lane, Garden Loop, Gerle Ave, Hazzard St., Letitita Ave.

03/2019 04/2019 15 20 5 1

Placerville El Dorado Road Maintenance & Rehabilitation

Country Dr. Crack Sealing - 2017 / 2018 Carry Over

Crack sealing the road section as described in the project locations using hot crack sealing machine. Country Club Dr. from top of Country Club Dr. near Airport at city county line to Cedar Ravine Road. 02/2019 05/2019 5 10 5 1

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 14: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Placerville El Dorado Road Maintenance & Rehabilitation Crack Sealing Perform crack sealing on various streets throughout the city using hot pour crack filling

processSections of lower Main Street, Upper Main Street, Lower Broadway, Cedar Ravine Road, Washington Street, Pacific Street, Benham Street, Armory Street and other streets throughout the City. 09/2018 06/2019 5 10 5 1

Placerville El Dorado Road Maintenance & Rehabilitation Utility Patch Paving

Utility patch pavement repairs throughout the city - Remove temporary patch and replace with permanent Asphalt Concrete (AC). These location are all from the repair of water and sewer repairs.

There are 23 locations identified throughout the city.All locations subject to change and will be selected based on priority needs and resources throughout the year. 2 on Main Street, 2 on Broadway, 2 on Country Club, Bedford, Bee Street, Washington Street, Pine Street, Bartlet Street, Chappel Street, Manor Drive, Baker Road, David Cir, Goldner, Goyan, Fowler, Accia, Duden, Sean, Darlinton

09/2018 06/2019 5 10 5 1

Placerville El Dorado Road Maintenance & Rehabilitation Patch Paving and or Slurry Sealing Patch and/or slurry various streets throughout the city using the cities Dura-Patch

machine and or slurry pot.

All locations subject to change and will be selected based on priority needs and resources throughout the year. The scope includes small areas of work on over 15 streets in the city. Big Cut Road, Benham St, Fowler Way, Bedford, Lewis Ave, Stout Ct, Goyan Ave, Fiske St, Clark St, Coon Hollow Rd, Bear Rock, Armory Dr., Spanish Ravine, Elm St, Washington St.

02/2019 06/2019 5 10 5 1

Placerville El Dorado Road Maintenance & Rehabilitation

Country Dr. Remove and Replace Asphalt Cracks - 2017 / 2018 On-Going

Remove large cracks in pavement and replace with AC as described in the project location. Country Club Dr. from top of Country Club Dr. near Airport at city county line to Cedar Ravine Road. 12/2017 06/2019 5 10 5 1

Placerville El Dorado Road Maintenance & Rehabilitation

Placerville Dr. Crack Sealing - 2017 / 2018 Carry Over

Crack seal road section as described in the project location using a hot crack sealing machine. On Placerville Dr. from near US Hwy 50 Bridge to lower Main Street. 02/2019 06/2019 5 10 5 1

South Lake Tahoe El Dorado Road Maintenance & Rehabilitation

3rd Street SB-1 Pavement Rehabilitation Project

The City proposes to rehabilitate approximately 2,000 l.f. of collector class roadway serving access to the City's hospital corridor. The project proposes to dig out and repair several failing structural sections, cold mill existing asphalt, re-use millings for base structure in failed sections (eliminates 30% of off-haul), re-pave using PG64-28 Polymer Modified asphalt with recycled asphalt product. Strip and paint all lines and crosswalks with water based paint.

3rd Street - South Lake Tahoe, Ca. Limits of US Hwy 50 to the limits of South Avenue 06/2019 10/2019 15 20 5 1

Clovis Fresno Road Maintenance & Rehabilitation

Fowler Street Improvements - Barstow to Shaw

Grind and overlay existing pavement, some reconstruction. Traffic loop replacement. Minor concrete work. Stripping. Fowler Avenue from Barstow Avenue to Shaw Avenue 05/2020 10/2020 7 20 23 8

Clovis Fresno Road Maintenance & Rehabilitation

Minnewawa Street Improvements - Shepherd to Teague

Grind and overlay existing pavement, some reconstruction. Traffic loop replacement. Minor concrete work. Stripping. Minnewawa Avenue from Shepherd Avenue to Teague Avenue 05/2020 10/2020 7 20 23 8

Clovis Fresno Road Maintenance & Rehabilitation

Villa Street Improvements - Barstow to Shaw

Grind and overlay existing pavement, some reconstruction. Traffic loop replacement. Minor concrete work. Stripping. Villa Avenue from Barstow Avenue to Shaw Avenue 05/2020 10/2020 7 20 23 8

Coalinga Fresno Road Maintenance & Rehabilitation

Sunset Street Rehabilitation Project (Phase 1)

Installation of curb and gutter, sidewalks, curb ramps to comply with Americans with Disabilities Act requirements, driveway approaches, alley approaches, valley gutters, A.C. pavement, aggregate base, storm drain laterals, storm drain inlets, LED street lights, electrical conduit, electrical wire, pull boxes, crosswalks, traffic striping and markings, traffic signage, bike lane striping, existing utility lid adjustment, street tree removal or trimming and construction surveying

Sunset Street from Polk Street to Washington Street 08/2018 05/2019 15 25 31 12

Firebaugh Fresno Road Maintenance & Rehabilitation

Helm Canal Road Rehabilitation (north side) Roadway rehabilitation In the City of Firebaugh between Poplar and Birch Drive 07/2018 07/2019 10 20 31 12

Firebaugh Fresno Road Maintenance & Rehabilitation Roadway Sealing Project Roadway crack sealing and slurry sealing

At various locations in the City of Firebaugh: Birch Dr from Helm Canal to cul-de-sac, Dogwood Wy from Maple to cul-de-sac, Cypress Wy from Helm Canal to Maple, Alder Wy from Elm St to cul-de-sac, Poplar Wy from Helm Canal to Elm St, Willow Wy from Spruce to Elm St, Spruce St from Willow Wy to cul-de-sac, Maple Ct from Poplar to Dogwood Wy, Elm Street from Willow to Birch Drive, Ash Street from Alder to Dogwood Wy, Oak Street from Alder to Dogwood Wy

07/2018 07/2019 5 10 31 12

Fowler Fresno Road Maintenance & Rehabilitation Main St. / 9th St. Slurry Seals Apply crack and slurry seals on city streets. Main Street between 10th St. and 8th St. & 9th St. from Fresno St. to Merced St. 09/2018 12/2018 5 7 31 12

Fowler Fresno Road Maintenance & Rehabilitation

Adams Avenue Reconstruction (17/18 Carryover) Reconstruction pavement, curb, gutter and sidewalks. Adams Avenue - Golden State to 5th Street 02/2018 07/2018 15 20 31 12

Fresno Fresno Other BPMP Bride Deck Rehab Phase 2 (17/18 Carryover) Bridge Deck Rehabilitation Also Senate District 14 - State Assembly District 31 - Multiple bridge deck repairs throughout the City

of Fresno 11/2018 01/2019 20 40 23 8

Fresno Fresno Road Maintenance & Rehabilitation Emerson, West to Marks (S) Pavement slurry seal Emerson - West to Marks 07/2018 10/2018 7 10 23 8

Fresno Fresno Road Maintenance & Rehabilitation Hughes, Shields to Dakota (S) Pavement slurry seal Hughes - Shields to Dakota 07/2018 10/2018 7 10 23 8

Fresno Fresno Road Maintenance & Rehabilitation Barstow, First to Millbrook (S) Pavement slurry seal Barstow - First to Millbrook 07/2018 10/2018 7 10 23 8

Fresno Fresno Road Maintenance & Rehabilitation Olive, Fresno to Clovis (S) Pavement slurry seal Olive - Fresno to Clovis 07/2018 10/2018 7 10 31 14

Fresno Fresno Road Maintenance & Rehabilitation

Cedar-Jackson-Jensen-Church Neighborhood (S) Pavement slurry seal Cedar-Jackson-Jensen-Church Neighborhood 07/2018 10/2018 7 10 31 14

Fresno Fresno Traffic Control Devices Harrison and Shields Traffic Signal (D) New Traffic Signal Harrison Ave & Shields Ave 09/2019 11/2019 15 30 23 8

Fresno Fresno Traffic Control Devices Barstow and Palm Traffic Signal Left Turn Phasing Traffic Signal Modification Barstow Ave & Palm Ave 06/2019 08/2019 15 30 23 8

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 15: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Fresno Fresno Traffic Control Devices California and Walnut Traffic Signal New Traffic Signal California Ave & Walnut Ave 06/2019 08/2019 15 30 31 14

Fresno Fresno Traffic Control Devices Armstrong and Lane Traffic Signal (D) New Traffic Signal Armstrong Ave & Lane Ave 09/2019 11/2019 15 30 23 8

Fresno Fresno Traffic Control Devices Clinton and Fresno Traffic Signal Left Turn Phasing (D) Traffic Signal Modification Clinton Ave & Fresno Street 09/2019 11/2019 15 30 31 8

Fresno Fresno Road Maintenance & Rehabilitation

Marks Ave Overlay, Ashlan to Dakota (D) Pavement overlay Marks Ave - Ashlan to Dakota 08/2019 09/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Sierra Overlay, Blackstone to Maroa (partial County) (D) Pavement overlay Sierra Ave - Blackstone to Maroa 08/2019 09/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Nees Overlay, Fresno to Millbrook (D) Pavement overlay Nees Ave - Fresno to Millbrook 08/2019 09/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Chestnut Overlay, Bullard to Herndon (D) Pavement overlay Chestnut Ave - Bullard to Herndon 08/2019 09/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

North & Fig Pavement Reconstruction (17/18 Carryover)

Reconstruction of North Avenue from Fig to Walnut; and Fig Avenue from North to 0.25 miles south, including pavement reconstruction and drainage facilities. North Avenue and Fig Avenue 06/2019 06/2020 15 20 31 14

Fresno Fresno Road Maintenance & Rehabilitation

North Ave Overlay Elm to Fig (17/18 Carryover) Asphalt overlay on North Avenue from Elm Avenue to Fig Avenue North Avenue from Elm Avenue to Fig Avenue 08/2018 12/2018 15 25 31 14

Fresno Fresno Road Maintenance & Rehabilitation

Blackstone Overlay, Shaw to Ashlan (17/18 Carryover)

Curb ramp replacement, traffic signal loop replacement, curb and gutter repair, signing and pavement markings. Blackstone Avenue from Shaw Avenue to Ashlan Avenue 08/2018 10/2018 10 20 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Clinton Overlay, Blackstone to Maroa (17/18 Carryover)

Rehabilitiation of Clinton Avenue consisting of an asphalt concrete overlay, replacing damaged traffic detector loops, restriping and upgrading non-standard curb ramps to meet ADA standards

Clinton Avenue from Blackstone Avenue to Maroa Avenue 08/2018 10/2018 20 25 31 8

Fresno Fresno Road Maintenance & Rehabilitation

Shields Overlay, Sunnyside to Folwer (17/18 Carryover)

Rehabilitiation of Shields Avenue consisting of an asphalt concrete overlay, replacing damaged traffic detector loops, restriping and upgrading non-standard curb ramps to meet ADA standards

Shields Avenue from Sunnyside Avenue to Fowler Avenue 10/2018 12/2018 20 25 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Marks Ave Overlay, Barstow to BNSF (17/18 Carryover) Pavement overlay Marks Avenue from Barstow Ave to BNSF railroad crossing 03/2019 04/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

FY18-19 Annual Street Maintenance Program

Operational program to replace damaged concrete and street repaving. Located in State Senate Districts 8 and 14; State Assembly Districts 23 and 31.

Lane-Kings Canyon-Maple Neighborhood concrete and slurry; West Ave (east side) south of Clinton concrete repair; West Ave (west side) Ashlan to Griffith concrete repair; Shields Ave east of Valentine concrete repair; Bullard/Brawley/Calimyrna/Marty Neighborhood concrete repair; Bullard/Sierra/Millbrook/Cedar Neighborhood concrete repair; Helm, Belmont to Harvey (partial County) paving; Hughes Ave Overlay, Ashlan to Emerson; Bluff Overlay, Van Ness to easterly limit; Second St./Jensen Ave Frontage Rd/Fourth St/Date paving; Channing Overlay, West Ave to Kearney; Hazelwood Overlay, Ventura to Butler; Dakota/Hampton/Millbrook/Ninth Neighborhood paving; Clay Overlay, Peach Ave to City/County limit; Winery Overlay, Butler to Hamilton; Hamilton Overlay, Winery to Chestnut; El Paso-Angus Overlay, Fresno to Nees connector; Maroa Overlay, Dakota to Ashlan (partial County); Maple Ave Overlay, Olive to Belmont.

08/2018 05/2019 7 20 31 14

Fresno Fresno Road Maintenance & Rehabilitation

Cedar Ave Overlay, Barstow to Bullard Pavement overlay Cedar Ave - Barstow to Bullard 05/2019 06/2019 10 15 23 8

Fresno Fresno Road Maintenance & Rehabilitation

Bullard, First to Cedar (partial grant match) Pavement overlay Bullard Ave - First to Cedar 05/2019 06/2019 10 15 23 8

Huron Fresno Complete Streets Components

Palmer Ave Class II Bike Lane From Lassen Ave to Siskiyou Ave Install 0.9 mi of Class II bike lane Palmer Ave from Lassen Ave to Siskiyou Ave 09/2018 10/2019 10 20 31 12

Huron Fresno Complete Streets Components

M St Class II Bike Lanes From 4th St to 7th St Install two (2) 900 ft Class II bike lanes M St from 4th St to 7th St 10/2018 12/2019 10 20 31 12

Huron Fresno Complete Streets Components

M St Class IV Bike Lanes from 7th St to Palmer Ave Install two (2) 0.63 Class IV bike lanes M St from 7th St to Palmer Ave 03/2019 09/2020 10 20 31 12

Huron Fresno Complete Streets Components

Lassen Ave Sidewalks from Placita to 12th St Improve sidewalks and install landscaping to improve pedestrian experience Lassen Ave from Placita (9th St) to 12th St 12/2018 12/2020 25 35 31 12

Huron Fresno Complete Streets Components

Lassen Ave Sidewalks & Greening from 12th St to Post Office Improve sidewalks and install landscaping to improve pedestrian experience Lassen Ave from 12th St to US Post Office 06/2019 06/2021 25 35 31 12

Kerman Fresno Complete Streets Components Del Norte Avenue Reconstruction Complete reconstruction including removal and replacement of full depth pavement

section. On Del Norte 200' South of C Street to Kearney Blvd in Kerman, CA 07/2018 09/2018 20 35 31 12

Kingsburg Fresno Road Maintenance & Rehabilitation 21st Avenue Reconstruction Pavement, curb, gutter, sidewalk, and curb ramp reconstruction. 21st Avenue between Sierra Street and Mariposa Street 05/2018 12/2018 15 20 31 12

Mendota Fresno Road Maintenance & Rehabilitation

5th Street and Quince Street Reconstruction

In general, the project consists of reconstruction of 5th Street from Oller Street (State Route 180) to Derrick Avenue (State Route 33) and Quince Street from 5th Street to 6th Street, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, driveway and alley approaches, and traffic striping and markings to add two way left turn lanes, parking/bike lanes and high visibility school zone cross walks.

5th Street from Oller Street (SR 180) to Derrick Avenue (SR 33), and Quince Street from 5th Street to 6th Street 03/2019 08/2019 15 30 31 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 16: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Mendota Fresno Road Maintenance & Rehabilitation

Black, Fleming, McCabe Avenue Reconstruction

In general, the project consists of reconstruction of the three streets between Rowe Avenue and Sorensen Avenue, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, driveway approaches, and traffic striping and markings to add center lane lines, parking/bike lanes and high visibility school zone cross walks.

Black Avenue from Rowe Avenue to Sorensen Avenue, Flemming Avenue from Rowe Avenue to Sorensen Avenue, and McCabe Avenue from Rowe Avenue to Sorensen Avenue 03/2020 11/2020 15 30 31 12

Mendota Fresno Road Maintenance & Rehabilitation Kate Street Reconstruction

In general, the project consists of reconstruction of North Kate Street between Divisadero Street and I Street, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, and traffic striping and markings to add center lane line and parking/bike lanes.

North Kate Street between Divisadero Street and I Street 03/2020 11/2020 15 30 31 12

Mendota Fresno Road Maintenance & Rehabilitation Rio Frio Street Reconstruction

In general, the project consists of reconstruction of Rio Frio Street between 7th Street and 8th Street, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, and traffic striping and markings to add two way left turn lanes and parking/bike lanes.

Rio Frio Street from 7th Street to 8th Street 03/2021 09/2021 15 30 31 12

Mendota Fresno Road Maintenance & Rehabilitation Stamoules Street Reconstruction

In general, the project consists of reconstruction of Stamoules Street between 7th Street and 9th Street, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, and traffic striping and markings to add two way left turn lanes and parking/bike lanes.

Stamoules Street from 7th Street to 9th Street 03/2021 09/2021 15 30 31 12

Mendota Fresno Road Maintenance & Rehabilitation

Marie Street & 5th Street Reconstruction

In general, the project consists of reconstruction of Marie Street between Divisadero Street and 5th Street and 5th Street betwee Marie Street and Lolita Street, including demolition of existing asphalt and concrete pavements, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, and traffic striping and markings to add center lane line and parking/bike lanes.

Marie Street from Divisadero Street to 5th Street, and 5th Street from Marie Street to Lolita Street 03/2021 09/2021 15 30 31 12

Mendota Fresno Road Maintenance & Rehabilitation Naples Street Reconstruction

In general, the project consists of reconstruction of Naples Street between 2nd Street and 9th Street, including demolition of existing asphalt and concrete pavements, storm drain inlets, manholes and pipes, Full Depth Reclamation soil-cement treatment, new HMA pavement, curbs, gutters, ramps, and traffic striping and markings to add two way left turn lanes and parking/bike lanes.

Naples Street from 2nd Street to 9th Street 03/2022 10/2022 15 30 31 12

Orange Cove Fresno Complete Streets Components Park & Anchor Street Project Construct curb, gutters, sidewalks, street lights and asphalt paving. Northwest corner of Park Blvd. & Anchor Ave. 08/2018 04/2019 25 50 31 14

Orange Cove Fresno Complete Streets Components

Park Boulevard Sidewalks (17/18 Carryover)

Repair of Sidewalks to remove trip and fall hazards and improve accessibility for disabled persons. The North side of Park Blvd. between Center St. and Sixth Street 03/2019 05/2019 20 50 31 14

Parlier Fresno Complete Streets Components

5th Street Construction (2017/18 Carryover) Construction of 160 feet of new street, curb and gutter and sidewalk 5th Street between Academy Avenue and Sierra Avenue 10/2020 06/2021 15 30 31 14

Parlier Fresno Road Maintenance & Rehabilitation Cypress/Rodriguez Reconstruction Reconstruction of asphalt pavement and base rock, construction of compliant curb

ramps and associated infrastructure. Cypress Avenue and Rodriguez Avenue between Mendocino Avenue and Mulberry Lane. 03/2019 06/2019 25 30 31 14

Reedley Fresno Road Maintenance & Rehabilitation

Manning Avenue Phase 2 Heavy Maintenance (17/18 Ongoing)

Project will employ heavy roadway maintenance strategies in the form of digouts of distressed areas and cape seal within the limits of the project. Same project as the 18-19 Fiscal Year. SB-1 Funds from 17/18 & 18/19 required to complete the project.

City of Reedley - Manning Ave between Frankwood and Columbia Avenues 04/2018 08/2018 6 8 31 14

San Joaquin Fresno Road Maintenance & Rehabilitation

Idaho Avenue Reconstruction - 17/18 Carryover Roadway reconstruction In the City of San Joaquin between 9th Street and Main Street 08/2020 08/2021 10 20 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

Nevada Avenue Overlay - 17/18 Carryover Roadway overlay In the City of San Joaquin between 5th Street and Main Street 08/2019 08/2020 10 20 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

Roadway Sealing Project - 17/18 Carryover Roadway crack sealing and slurry sealing

Various locations in the City of San Joaquin: First St from Colorado to Annabella, Annabella from Helm to 4th Street, Helm from Colorado to California, 2nd St from Annabella to Helm, 3rd St from Annabella to Helm, 1st St Court, 2nd St Court, 4th St from Annabella to West Nevada, West Nevada from 3rd St to 5th St, White St from 3rd St to 5th St

08/2020 08/2021 5 10 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

6th Street Repairs Project - 17/18 Carryover Roadway reconstruction In the City of San Joaquin between Colorado Avenue and Nevada Avenue 08/2019 08/2020 10 20 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

11th Street Reconstruction - 17/18 Carryover Roadway reconstruction In the City of San Joaquin between Colorado Avenue and Nevada Avenue 08/2022 08/2023 10 20 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

9th Street Reconstruction - 17/18 Carryover Roadway reconstruction In the City of San Joaquin between Colorado Avenue and Nevada Avenue 08/2023 08/2024 10 20 31 12

San Joaquin Fresno Road Maintenance & Rehabilitation

Oregon Avenue Reconstruction - 17/18 Carryover Roadway reconstruction In the City of San Joaquin between 9th Street and Pine Street 08/2024 08/2025 10 20 31 12

Sanger Fresno Road Maintenance & Rehabilitation

Rawson Ave. Reconstruction - 14th Street to Hoag Ave.

Reconstruction of asphalt pavement, construction of compliant curb ramps and associated infrastructure Rawson Ave. Reconstruction - 14th Street to Hoag Ave. 07/2018 12/2018 25 30 31 8

Sanger Fresno Road Maintenance & Rehabilitation

Dewitt Ave Reconstruction - Hoag Avenue to 14th Street

Reconstruction of asphalt pavement, construction of compliant curb ramps and associated infrastructure Dewitt Ave Reconstruction - Hoag Avenue to 14th Street 07/2018 12/2018 25 30 31 8

Sanger Fresno Road Maintenance & Rehabilitation 2018/19 Street Sealing Project Biennial preventative maintenance project including crack seal, slurry seal and/or

rubberized cape seal

sealing project will be within the boundaries of the streets S. Newmark, North Ave, Church Ave and Del Ray Ave. Arterial roads within the boundaries include N. Bethel, Greenwood Ave, Jensen and Academy Ave. *All locations have yet to be finalized and are subject to change. Each location will be selected based on the assessed priority need and resources throughout the year.

07/2018 06/2019 10 15 31 8

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 17: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Selma Fresno Road Maintenance & Rehabilitation

Alphabet Streets (A & B) Reconstruction Project

Reconstruct and rehabilitate A & B street from Floral Avenue to Rose Avenue. Upgrade ramps to current ADA standards, replace/add sidewalk where missing Alphabet Streets (A through E) Floral Avenue to Rose Avenue in Selma, CA 01/2019 08/2019 20 25 31 14

Selma Fresno Complete Streets Components Nebraska Avenue (17/18 Carryover)

Located in Selma on Nebraska Avenue from Highway 43 to Mitchell Avenue, reconstruct the existing 2-lane rural roadway including widening the westbound roadway to the ultimate width, providing enhanced access in and out of downtown Selma and congestion relief at the Thompson/Highland intersection.

Nebraska Avenue from Hwy 43 to Mitchell Avenue 10/2019 10/2020 20 25 31 14

Selma Fresno Road Maintenance & Rehabilitation Arterial Street Rehabilitation

Patch longitudinal cracking with Hot Mix Asphalt (HMA) in 4’ strips along Arterials and Major Collectors using a 4’ wide paving machine (see attached photos). Crack seal all joints and cracks, place Caltrans type II slurry seal over entire road width and restripe

McCall from Floral to Dinuba, Orange from Floral to Nelson, Nelson from Highland to Thompson, Rose from McCall to Country Rose, Second from E Front to High 01/2019 05/2019 20 25 31 14

Orland Glenn Road Maintenance & Rehabilitation Tehama Street Improvements

As part of the Tehama Street Improvement Project, Tehama Street from Woodward Avenue to East Street will be rehabilitated for roadway repairs and ADA compliance to curbs, gutters, sidewalks and pedestrian ramps.

Tehama Street from Woodward Avenue to East Street. 07/2018 06/2019 15 20 3 4

Willows Glenn Complete Streets Components Sycamore Street Rehabilitation Supplement STIP funds for Sycamore Street repair/replace sidewalk, curb and gutters

where needed. Replace ramps to meet State ADA requirements. Sycamore St. from Lassen St. to Tehama St. 04/2018 10/2018 20 50 3 4

Willows Glenn Safety Birch Street/Tehama Street Sidewalk renovation

Remove and replace broken and uneven sidewalks that are trip and fall hazards or force pedestrian traffic to leave the sidewalk and travel in the street. Repair or replace curb and gutter where needed. Connect sections to encourage pedestrian travel and bring sidewalk system into ADA compliance.

South side of Birch St. from Butte St. to Tehama St. West side of Tehama St. from Birch ST. to Cedar St. 07/2018 04/2019 20 50 3 4

Willows Glenn Safety Walnut Street/Butte Street Sidewalk renovation

Remove and replace broken and uneven sidewalks that are trip and fall hazards or force pedestrian traffic to leave the sidewalk and travel in the street. Repair or replace curb and gutter where needed. Connect sections to encourage pedestrian travel and bring sidewalk system into ADA compliance.

South side of Walnut St. from Shasta St. to Butte St. West side of Butte St. from Walnut St. to Sycamore St. 08/2018 05/2019 20 50 3 4

Arcata Humboldt Safety Road Safety Improvement Installing two radar feedback signs within city limits for traffic/speed control 11th Street 07/2018 01/2019 8 10 2 2

Arcata Humboldt Road Maintenance & Rehabilitation Road Paving Project Overlaying Crescent Way and Bayside Road with a thin AC layer Crescent Way between Old Arcata Road and Bayside Road

Bayside Road between Union Street and Buttermilk Lane 02/2019 11/2019 18 20 2 2

Arcata Humboldt Road Maintenance & Rehabilitation

Street Maintenance (Fixing Potholes and AC Overlay) '17/18 Carry Over Annual Maintenance Project Westwood Court 07/2018 10/2018 15 20 2 2

Arcata Humboldt Road Maintenance & Rehabilitation

Street Maintenance (Fixing Potholes and AC Overlay) '17/18 Carry Over Annual Maintenance Project 13th Street, Bayside Road to Union Street 07/2018 10/2018 15 20 2 2

Blue Lake Humboldt Road Maintenance & Rehabilitation City of Blue Lake SB 1-2018-2019 Pothole repair Acacia Drive, South Railroad, Railroad Avenue 08/2018 09/2018 2 5 2 2

Blue Lake Humboldt Traffic Control Devices City of Blue Lake SB 1-2018-2019 Traffic Calming Railroad Avenue, Raymar Avenue 08/2018 10/2018 2 5 2 2

Eureka Humboldt Road Maintenance & Rehabilitation Maintenance Paving 2018 Remove and replace sections of Asphalt Pavement, install new bicycle sensitive traffic

signal detectors and install new thermoplastic striping and markings.

Portions of H Street between 16th and Henderson Streets. Portions of 6th Street between Myrtle Ave. and Commercial Street Portions of 7th Street between Pine Street and E Street

07/2018 09/2018 15 20 2 2

Ferndale Humboldt Road Maintenance & Rehabilitation

Washington Street paving improvement (17/18 Carryover) Street surface is severely cracked. 325 feet of re-pavement. Washington Street 08/2018 09/2018 20 30 2 2

Ferndale Humboldt Road Maintenance & Rehabilitation Shaw Street Street surface is severely cracked. 200 feet of re-pavement. Shaw Street 08/2018 09/2018 20 30 2 2

Fortuna Humboldt Road Maintenance & Rehabilitation

Annual Paving Project - Intersections

Asphalt Concrete and replacement and leveling course to repair failing asphalt, and striping

Kenmar & Fortuna Blvd Intersection, Main & 12th St. Intersection, Newburg and Fortuna Boulevard Intersection 07/2018 06/2019 10 20 2 2

Fortuna Humboldt Road Maintenance & Rehabilitation

Kenmar Road Reconstruction Project

Asphalt Concrete and replacement and leveling course to repair failing asphalt. This is a carryover project from FY17/18. Kenmar Road between Church Street and Lee Court, and Renee Ct. to Crestview Drive 07/2018 06/2019 10 15 2 2

Rio Dell Humboldt Road Maintenance & Rehabilitation General Maintenance and Repairs General streets maintenance and repairs including but not limited to potholes,

sweeping, storm drain maintenance, etc.Eeloa Ave. between Spring St. and Fern St.; 1st, 2nd, 3rd, and 4th Avenues including side streets of Dixie, Columbus, and Elko; Ogle St. 07/2018 06/2019 1 5 2 2

Trinidad Humboldt Road Maintenance & Rehabilitation

Westhaven Drive Pavement Rehabilitation (2017-18 Carryover) Resurface and restripe approximately 0.25 miles of roadway. Westhaven Drive From Main St. to City Limits 11/2018 06/2019 5 10 2 2

Trinidad Humboldt Road Maintenance & Rehabilitation

Edwards Street Pavement Rehabilitation (17/18 Carryover) Resurface and restripe approximately 0.35 miles of roadway. From Trinity Street to the pier parking lot. 01/2018 06/2019 5 10 2 2

Trinidad Humboldt Complete Streets Components

Town Hall Pedestrian and Accessible Parking Improvements (17-18 Carryover)

Construct curb ramp, accessible driveway and accessible on-street parking stall, including striping and signage. Trinity Street in front of Town Hall 01/2019 06/2019 5 10 2 2

Brawley Imperial Road Maintenance & Rehabilitation

Streets Rehabilitation Phase 11, (17/18 Ongoing) Resurface approximately 0.5 miles of road utilizing recycled materials. 16th, 17th, 18th Streets between K St. and Malan St. 08/2018 03/2019 10 15 56 40

Brawley Imperial Road Maintenance & Rehabilitation

Rehabilitation of Legion Street from Highway 86 to Evelyn Street

Rehabilitation of 0.3 miles of Asphalt Concrete with recycled material, remove and replace accessible ramps, installation of striping.

Legion Street between Highway 86 and Evelyn Avenue in the City of Brawley, County of Imperial, California 03/2019 06/2019 10 15 56 40

Calexico Imperial Road Maintenance & Rehabilitation Cesar Chavez Blvd. Improvement

The project will consist of widening and improving Cesar Chavez Blvd. to four (4) lanes from 2nd Street to Highway 98 and include surface rehab, turn lanes, traffic signal, lighting and sidewalks

Cesar Chavez Blvd. from 2nd Street to Highway 98 06/2018 07/2018 10 20 56 40

Calexico Imperial Road Maintenance & Rehabilitation De Las Flores Street Improvemet The project will consist of paving dirt road De Las Flores Street between Eady Avenue

and Kloke Avenue to include installation of curb, gutter and sidewalk. De Las Flores Street between Eady Avenue and Kloke Avenue 09/2018 10/2018 10 20 56 40

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 18: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Calexico Imperial Road Maintenance & Rehabilitation Second Street Bridge The project will consist of widening and improving Second Street bridge Second Street Bridge 11/2018 12/2018 10 20 56 40

Calipatria Imperial Road Maintenance & Rehabilitation

Freeman Street Rehabilitation Between Brown and Commerical Avenues

The City will rehabilitate at least 500 lineal feet of full width improvements on Freeman Avenue. Freeman Street Rehabilitation between Brown and Commercial Avenues. 02/2019 05/2019 10 20 56 40

El Centro Imperial Road Maintenance & Rehabilitation

2018 Streets Overlay and Rehabilitation Project

Street asphalt overlay and chip seal. Project will eliminate rough riding conditions and potholes by rehabilitating the street segments

La Brucherie Avenue between Adams Avenue and Villa Avenue Ross Avenue between Dogwood Avenue and Alder Canal (East city limit) 06/2018 12/2018 15 20 56 40

Holtville Imperial Road Maintenance & Rehabilitation

Citywide Pavement Rehabilitation Project

This project will "touch" virtually every street in the City, not rehabilitated within the past 3 years. It will refurbish a portion of them with crack sealing followed by a slurry sealcoat. Other street sections in poorer condition are to be crack sealed followed by the placement of an asphalt rubber aggregate membrane chip over the pavement surface followed by a slurry sealcoat. It would be necessary to remove and replace pavement failure areas in the existing street system by saw cutting and removing the A.C. failed pavement and re-installing new hot mix A.C. pavement prior to either of the aforementioned pavement refurbishment methods. Other minor street improvement work associated with the street refurbishment includes covering and cleaning slurry from water valves, gas valves and manhole covers and applying striping to the streets

City of Holtville citywide (Chestnut, Olive & Webb Avenues, etc.). All locations have yet to be finalized and will be selected based on priority need and resources throughout the year. 09/2018 12/2018 15 25 56 40

Imperial Imperial OtherStorm Drain Installation - Northwest Quadrant of City - Continuing (17/18 Carryover)

Project list is as follows: Continue with the installation of non previously existing storm drain system on the Northwest quadrant of the City. Much of this area gets inundated with rain water causing the asphalt to accelerate oxidation. This situation has been causing severe damage to the roadway including multiple cracks thus creating sinkholes.

Barioni Blvd. north to 15th Street, between SR 86 and La Brucherie Road. This area is the northwest quadrant of the City where there are no storm drains. 06/2019 11/2019 25 30 56 40

Westmorland Imperial Road Maintenance & Rehabilitation

Streets Rehabilitation Program Phase 2 (17/18 Carry-Over)

City of Westmorland is proceeding with a project for the design and installation of conventional asphalt with an asphaltic rubberized aggregate membrane. The selected streets have been in conjunction with the Pavement Management Study. (Design phase completed as of June 2018, and construction will begin in September 2018)

C Street from Main Street to 7th Street, D Street from 5th Street to 6th Street and J Street from 7th Street to 8th Street 09/2018 12/2018 12 15 56 40

Westmorland Imperial Road Maintenance & Rehabilitation

CMAQ Project to install new street and curb and sidewalks (17/18 Carry-Over)

Pave existing roadway without adding capacity. Excavate to place Cl.2 A.B. with A.C.; install curb, gutter, cross gutter, ADA ramps, sidewalk, and driveway entrances; raise manhole covers and water valve covers; striping and signage. (Design phase was completed in June 2018)

North H Street (from 7th to 8th St) and 8th Street (from H St. to I St.) [950'] 09/2018 12/2018 30 50 56 40

Bishop Inyo Road Maintenance & Rehabilitation Spruce Fiber Seal Place fiber seal Spruce Street between Yaney and Wye 08/2018 10/2018 10 25 26 8

Bishop Inyo Road Maintenance & Rehabilitation Home Street Fog Seal Place fog seal Home Street 08/2018 10/2018 5 15 26 8

Bishop Inyo Road Maintenance & Rehabilitation Mac Iver Street Fog Seal Place fog seal Mac Iver Street 08/2018 10/2018 5 15 26 8

Bishop Inyo Road Maintenance & Rehabilitation South Second Fog Seal Place fog seal South Second Street 08/2018 10/2018 5 15 26 8

Bishop Inyo Road Maintenance & Rehabilitation Third and South Digouts Replace failed pavement At and near the intersection of South and Third streets. 07/2018 11/2018 25 75 26 8

Bishop Inyo Road Maintenance & Rehabilitation 2018-2019 Cross Gutters Construct concrete cross gutters

West Elm, Schley; West Elm, Hammond; West Elm, Warren; East Elm, Central; East Elm, Howard; West Pine, Schley; Academy, Hammod; South, Sneden; Clarke, Third; Clarke, Sneden; Willow, Whitney; Willow, Rose; Willow, High; Willow, Second; May, Second; May, Third; May, Bush; May, High; May, Rose

12/2018 06/2019 75 100 26 8

Bishop Inyo Road Maintenance & Rehabilitation 2018-2019 Sidewalks Construct and reconstruct sidewalks. Park Street 12/2018 06/2019 75 100 26 8

Arvin Kern Road Maintenance & Rehabilitation Purchase Equipment-Hot Mix Purchase a hot mix trailer and a roller compactor for road maintenance of pot holes The City maintains Arvin approximately 4.8 square miles 12/2018 12/2018 5 20 32 21

Arvin Kern Road Maintenance & Rehabilitation Pothole Filling throughout the City Road Maintenance of potholes The City maintains Arvin approximately 4.8 square miles 06/2018 12/2019 5 20 32 21

Arvin Kern Road Maintenance & Rehabilitation

Microsurfacing various streets throughout the City Microsurfacing various streets throughout the City- Grouped Project Franklin Avenue-between A and Butte, S Hill Street-between SR 223 and Haven,

Walnut Drive-between Franklin and 223 01/2019 04/2019 5 10 32 21

Arvin Kern Road Maintenance & Rehabilitation Varsity ORad Widening

Widen Varsity Road in front of the high school to fully originally planned 60-foot width by installing an additional 10 feet of pavement atop of the current shoulder, and install new curb, gutter, sidewalk

Varsity Road between Campus Drive and Mahin Drive. 01/2019 04/2019 5 10 32 21

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Rehabilitation on Wible Road from White Lane to Planz Road

Local match requirement for FHWA funding. Existing pavement along this roadway is in disrepair. Rehabilitation of this pavement will improve the overall rideability of the road for both passenger cars and commercial trucks. This project is 88.53% federally funded with a 11.47% local match requirement.

Wible Road from White Lane to Planz Road 03/2019 09/2019 20 25 34 14

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Rehabilitation on District Blvd from Gosford Road to Stine Road

Local match requirement for FHWA funding. Existing pavement along this roadway is in disrepair. Rehabilitation of this pavement will improve the overall rideability of the road for both passenger cars and commercial trucks. This project is 88.53% federally funded with a 11.47% local match requirement.

District Blvd from Gosford Road to Stine Road 03/2019 09/2019 20 25 34 16

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 19: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Bakersfield Kern Other Bridge Improvements

Local match requirement for FHWA funding. This project will resurface the existing bridge decks using methacrylate treatment, cleaning and replacing joint seals, repairing unsound concrete with rapid setting concrete patches, cleaning bridge decks, cleaning rebars and apply epoxy coating, repairing curbs and median curb, sealing deck cracks, and remove and replace striping. This project is 88.53% federally funded with a 11.47% local match requirement.

11 locations (South Monterey Street; 0.1 mile east Coffee Road; 0.2 mile south Truxtun Avenue - Gosford Road SB; 0.2 mile south Truxtun Avenue - Gosford Road NB; 0.3 mile south Truxtun Avenue - Gosford Road SB; 0.3 mile south Truxtun Avenue - Gosford Road NB; 0.3 mile north Truxtun Avenue - Coffee Road NB; 0.1 mile north Brundage Lane; South of Terrace Way; East of H Street; South Monterey Street

03/2019 09/2019 20 25 32, 34 14, 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Resurfacing - Jewetta Avenue from Hageman Road to South of Lonon Avenue

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

Jewetta Avnue from Hageman Road to South of Lonon Avenue 08/2018 09/2018 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Resurfacing - Pin Oak Blvd from White Lane to Bear Creek

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

Pin Oak Blvd from White Lane to Bear Creek 08/2018 09/2018 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Resurfacing - Clay Patrick Farr from Granite Falls to Hageman Road

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

Clay Patrick Farr from Granite Falls to Hageman Road 08/2018 09/2018 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Rehabilitation on H Street from 4th Street to Truxtun Avenue

Existing pavement along this roadway is in disrepair. Rehabilitation of this pavement will improve the overall rideability of the road for both passenger cars and commercial trucks.

H Street from 4th Street to Truxtun Avenue 12/2018 05/2019 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Rehabilitation on Haley Street from Columbus Avenue to University Avenue

Existing pavement along this roadway is in disrepair. Rehabilitation of this pavement will improve the overall rideability of the road for both passenger cars and commercial trucks.

Haley Street from Columbus Avenue to University Avenue 12/2018 05/2019 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Resurfacing - Park View from White Lane to Campus Park

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

Park View from White Lane to Campus Park 04/2019 05/2019 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Resurfacing - Berkshire Rd from Wible Road to Santana Sun Dr.

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

Bershire Rd from Wible Road to Santana Sun Dr. 04/2019 05/2019 20 25 34 16

Bakersfield Kern Road Maintenance & Rehabilitation

Pavement Rehabilitation on H Street from Brundage Lane to 4th Street

City Staff will perform section repairs, as needed, along with doing a complete .35 feet overlay on the entire steet. This will be done by utilizing various annual contracts from material suppliers, trucking, and asphalt grinding contractors with City Streets staff doing the paving.

H Street from Brundage Lane to 4th Street 04/2019 05/2019 20 25 34 16

California City Kern Road Maintenance & Rehabilitation

Holly & Grapewood ave Rehabilitation

Grind +/- 2" of Existing Asphalt Surface and Repave with 3" of Hot Mix Asphalt an Estimated 0.60 Miles of Local Street.

Holly ave between Eucaliptus ave and Corwin st and Grapewood ave between Fir ave and Corwin st. 01/2019 02/2019 8 10 36 16

California City Kern Road Maintenance & Rehabilitation Bay & Catalpa Ave Rehabilitation Grind +/- 2" of Existing Asphalt Surface and Repave with 3" of Hot Mix Asphalt an

Estimated 0.74 Miles of Local Street.Bay av. between Catalpa ave and 94th st. and Catalpa ave. between Lask st. and 94th st. 10/2018 11/2018 8 10 36 16

California City Kern Road Maintenance & Rehabilitation Eucalyptus/Fir Ave Rehabilitation Grind +/- 2" of Existing Asphalt Surface and Repave with 3" of Hot Mix Asphalt an

Estimated 0.65 Miles of Local Street.Eucalyptus ave between S. Loop Blvd and Corwin st. and Fir ave between Holly ave and Corwin st. 11/2018 12/2018 8 10 36 16

Delano Kern Road Maintenance & Rehabilitation

2019 Pavement Resurfacing and Rehabilitation at Various Streets in Delan

Repave/Resurface 5.32 miles of road pavements with average width of 42 FT and restripe 8,000 LF of double left turn lanes, 4,000 LF of center lines and 3.0 miles of Bike Lanes and repaint pavement markings and crosswalks and replace raised pavement markers.

Albany Street between 11th Avenue and Garces Highway; Austin St between 1st Ave and Garces Hwy; Belmonth St between Diaz Stand Garces Hwy; Dover Pl between Diaz St and 1st Ave; Dover St between 1st Ave and Garces Hwy; Oleander St bet. 20th Ave and End of Rd; Oxford St bet. 20th Ave and Co. Ln. Rd; Patton St bet. 21st Ave and Co. Ln. Rd.; Quincy St bet. 18th Ave and Cecil Ave.; Randolph St bet. Co. Ln. Rd and Cecil Ave.; Rounds St bet 20th Ave and End of Rd.; Thomas Way bet Co. Ln. Rd and End of Rd.; 21st Ave bet Princeton St and Oxford St.

02/2019 09/2019 7 10 32 14

Delano Kern Road Maintenance & Rehabilitation

Pavement Resurfacing and Rehabilitation (17/18 Carryover)

Repave/Resurface 4.9 miles of of road pavements and restripe 2,950 LF of turn lane, 1,155 LF of Left turn pockets and repaint pavement markings and crosswalk.

Lexington St. between Woollomes Ave and Schuster Road; Kensington St. between Cecil Avenue and 6th Avenue; Dover Place between Garces Highway and 9th Avenue; Dover Place between 10th Avenue and 12th Avenue; Dover Place between Garces Highway and 12th Avenue; Belmont St. between 11th Avenue and 13th Avenue; Belmont St. between Garces Highway and 8th Avenue; Belmont St. between Cecil Avenue and 20th Avenue; Asti Street between 1st Avenue and Garces Highway; Austin St. between Garces Highway and 8th Avenue; Clinton St. between Cecil Avenue and 20th Avenue; 22nd Avenue between Girard Street and Oxford Street

03/2018 06/2018 5 10 32 14

Maricopa Kern Road Maintenance & Rehabilitation

Street Improvement Project FY 2018-2019

Crack Fill and Slurry Sear 8800 +/- square yards of residential streets within the city of Maricopa Union Street; Adeline St; Mary St; Broadway St; Helen St 03/2019 08/2019 5 10 34 16

McFarland Kern Complete Streets Components

City of McFarland_ATP Kern Ave Elementary SR2S Connectivity Project (17/18 Ongoing)

Complete Street Components new sidewalks, curb, gutter, class 3 bike lanes and high visibility crosswalks.

Various locations- three city blocks bounded by 5th Street from W. Kern to W. Sherwood; 4th Street from W. Harlow Ave to California Ave; 3rd and 4th Place from W. Sherwood to California Ave 05/2018 09/2018 10 20 32 14

McFarland Kern Road Maintenance & Rehabilitation

McFarland Kern Ave SB1 Road Maintenance

Repave/resurface, re-stripping of crosswalk and road on West Kern Ave from 5th Street to 6th Street. W. Kern Ave from 5th Street to 6th Street: 02/2019 05/2019 10 20 32 18

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 20: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Ridgecrest Kern Road Maintenance & Rehabilitation 2018 Road Projects Work is divided between four preventive maintenance fixes: Double Fiber, Single Fiber,

Flex and a Rubberized Double Chip

Locations TBD- SampleCalifornia Ave. (Sunland Dr. - Gateway Blvd.), California Ave. (China Lake Blvd. - Sunland Dr.), California Ave. (Alley - China Lake , vd.), Church Ave. (Gateway Blvd. - Richmond Rd.), Haloid Ave. (Warner St. - China Lake Blvd.), Lincoln St. (Upjohn Ave. - Church Ave.), Robertson Ave. (Warner St. - China Lake Blvd.), Valley St. (Church Ave. - Ridgecrest Blvd.), Valley St. (Upjohn Ave. - Church Ave.), Wilson Ave. (Warner St. - China Lake Blvd.), Gemstone St. (California Blvd. - Ridgecrest Blvd.), Gemstone St. (Church Ave. - California Ave.), American St. (Church Ave. - Commercial Ave.), American St. (Commercial St. - Ridgecrest Blvd.), Beth Ln. (Henry St. - Cul-de-Sac), Broadway St. (Commercial - Church Ave.), Broadway St. (Beth Lane - Church Ave.), Church Ave. (China Lake Blvd. - Gold Canyon Dr.), Church Ave. (Gold Canyon Dr. - Sunland St.), Debra Ln. (Holly Canyon Dr. - Sunland Dr.), Desert Candles St. (Haloid Ave. - Upjohn Ave.), Desert Candles St. (Haloid Ave. - Church Ave.), Emily St. (Yellow Astor Ave. - Wilson Ave.), Fire Opal Dr. (Church Ave. - Ridgecrest Blvd.), Forest Knoll St. (Upjohn Ave. - North to end pavement), Garnet St. (Grande Way - Gemstone St.)

09/2018 11/2018 6 15 34 16

Shafter Kern Road Maintenance & Rehabilitation Munzer St. - Road Rehabilitation Residential Road and Sidewalk Grind, Repair, & Seal - Munzer St. from Shafter Ave. to

N. Wall St. Munzer St. from Shafter Ave. to N. Wall St. 12/2018 06/2019 10 15 32 14

Shafter Kern Road Maintenance & Rehabilitation Pine St. - Road Rehabilitation Residential Road and Sidewalk Grind, Repair, & Seal - Pine St. From State Ave to

Blake Ave. Pine St. From State Ave to Blake Ave. 12/2018 06/2019 10 15 32 14

Shafter Kern Road Maintenance & Rehabilitation Polo St. - Road Rehabilitation Residential Road and Sidewalk Grind, Repair, & Seal - Polo St. from Shafter Ave to N.

Wall St. Polo St. from Shafter Ave to N. Wall St. 12/2018 06/2019 10 15 32 14

Shafter Kern Complete Streets Components

Sidewalk Rehabilitation - 345 Calloway Sidewalk Repair and Installation at 345 Calloway St. 345 Calloway St., Shafter , CA 93263 12/2018 06/2019 10 15 32 14

Taft Kern SafetyVarious pedestrian improvements 10th Street Between Kern Street and Front Street

Repair or replace broken sidewalks, curbs/ gutter, and install pedestrian ramps at various locations 10th Street between Kern Street and Front Street 02/2018 02/2019 15 25 34 16

Tehachapi Kern Road Maintenance & Rehabilitation

Valley Boulevard Rehabilitation Project Repave Valley Boulevard from Tucker Road to Curry Street. Valley Boulevard from Tucker Road to Curry Street. 06/2019 06/2020 15 20 34 16

Tehachapi Kern Road Maintenance & Rehabilitation Surface Treatment of Local Street Various surface treatments

3 different areas in City limits:Boundaries are Pinon Street south to Highline and Curry Street east to Ponderosa: 10 streets, Boundaries are Georgia Street south to E. Abajo Ave and Dennison Road east to city limit: 10 streets, Valley Blvd north to Fir Street and Curry Street east to Clearview: 10 streets

07/2019 01/2020 3 5 34 16

Tehachapi Kern Road Maintenance & Rehabilitation

Tehachapi Boulevard Rehabilitation Project Repave Tehachapi Boulevard from Curry Street to Hayes Street. Tehachapi Boulevard from Curry Street to Hayes Street. 12/2018 06/2019 15 20 34 16

Wasco Kern Road Maintenance & Rehabilitation

Streets Rehabilitation (Sunset, Maple, & Jubilee)

The Projects funded by SB 1 will consist of asphalt rehabilitation, ADA curb ramps and other Street improvements on Sunset St. between Palm Ave. and Griffith Ave., Maple Ave. between 9th Place and Poso Ave. and Jubilee Dr. between Palm Ave. and Maple Ave.

Sunset St. between Palm Ave. and Griffith Ave., Maple Ave. between 9th Place and Poso Ave. and Jubilee Dr. between Palm Ave. and Maple Ave. 01/2019 04/2019 10 15 32 14

Avenal Kings Complete Streets Components

Seventh Avenue Road Project (17/18 Carryover)

Remove and replace 4,390 square yards of road. Remove and replace 400 linear feet of concrete curb and gutter. Remove and replace 1,500 square feet of concrete sidewalk. Remove and replace 200 square feet of concrete driveway. Remove and replace 8 wheelchair ramps.

Seventh Avenue from San Joaquin St south to SR 269 (Skyline Blvd.) 10/2018 03/2019 10 20 32 14

Avenal Kings Complete Streets Components

Monterey Street Road Project (17/18 Carryover)

Remove and replace 7,480 square yards of road. Remove and replace 600 linear feet of concrete curb and gutter. Remove and replace 2,000 square feet of concrete sidewalk. Remove and replace 400 square feet of concrete driveway. Remove and replace 8 wheelchair ramps.

Monterey St. from 1st Ave east to 5th Ave. 08/2019 04/2020 10 20 32 14

Avenal Kings Complete Streets Components

Mariposa Street Road Project (17/18 Carryover)

Remove and replace 7,470 square yards of road. Remove and replace 600 linear feet of concrete curb and gutter. Remove and replace 2,000 square feet of concrete sidewalk. Remove and replace 400 square feet of concrete driveway. Remove and replace 8 wheelchair ramps.

Mariposa St. from First Ave. east to Fifth Ave. 08/2020 04/2021 10 20 32 14

Avenal Kings Complete Streets Components Avenal Cutoff Road Project

Grind, remove and install 45,000 square yards of 2 1/2" Asphaltic Concrete. Install 60,000 square yards of 2 1/2" Asphaltic Concrete. Haul, place and compact 45,000 square yards of Asphaltic Concrete Grindings on the shoulder of the road. Install roadway striping. Furnish Traffic Controls

Avenal Cutoff Road from SR 269 east to the California Aqueduct overcrossing. (17/18 Carryover) 03/2022 03/2023 15 25 32 14

Corcoran Kings Road Maintenance & Rehabilitation

2018/2019 City of Corcoran SB1 Road Maintenance Projecst (17/18 Ongoing)

Whitey Avenue: Dairy Avenue to Van Dorsten Avenue, Type II Slurry Seal, update striping and signingLetts Avenue: Sherman Avenue to Oregon Avenue, Chip Seal, update striping and signingOtis Avenue: Niles Avenue to Orange Avenue, Chip Seal, update striping and signing Niles Avenue: Dairy Avenue to Otis Avenue, Chip Seal, update striping and signing Dairy Avenue: Niles Avenue to Business Park, Chip Seal, update striping and signing (ongoing)Dairy Avenue: Bainum Avenue to Orange Avenue, Type II/Fiber Seal, update striping and signing

Whitey Avenue: Dairy Avenue to Van Dorsten Avenue Letts Avenue: Sherman Avenue to Oregon Avenue Otis Avenue: Niles Avenue to Orange Avenue Niles Avenue: Dairy Avenue to Otis Avenue Dairy Avenue: Niles Avenue to Business Park (ongoing)Dairy Avenue: Bainum Avenue to Orange Avenue

07/2018 06/2019 5 10 32 14

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 21: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Hanford Kings Traffic Control DevicesTraffic signal installation at intersection of 13th Ave. / Grangeville Blvd.

Installation of a traffic signal at the intersection of 13th Avenue and Grangeville Boulevard, and the widening / resurfacing of 13th Avenue from Grangeville Boulevard to a point approximately 1500 feet south of Grangeville (north end of Hanford Learning Center Development). The project will increase traffic flow efficiency and reduce intersection congestion by allowing more free flow traffic movements through the intersection. The project will also provide air quality benefits by reducing vehicle idling times.

Intersection of 13th Avenue / Grangeville Boulevard. 04/2019 08/2019 30 50 14 32

Hanford Kings Road Grade Separation Grangeville / BNSF - Grade Separation Feasibility Study

Preliminary engineering study report to determine feasibility of providing a grade separation structure between the BN&SF Railroad and Grangeville Boulevard. Grangeville Boulevard / BN&SF Railroad Intersection 07/2018 12/2018 50 100 32 14

Hanford Kings Road Maintenance & Rehabilitation 12th Avenue Pavement Resurfacing Resurface 0.4 miles of street. 12th Avenue, between Hanford-Armona Road and Springcrest Street. 01/2019 04/2019 15 30 32 14

Hanford Kings Road Maintenance & Rehabilitation

Tenth Avenue Resurfacing, Grangeville Boulevard to Third Street

Project will resurface Tenth Avenue, from Grangeville Boulevard to Third Street, with a double coat fiber seal treatment. The pavement preservation treatment consists of an asphalt emulsion coating with fibers added to provide structural integrity. Resurfacing of Tenth Avenue will extend the useful life of the asphalt concrete pavement surface thereby prolonging the need for more expensive roadway repairs.

Tenth Avenue, from Grangeville Boulevard to Third Street. 03/2019 06/2019 7 10 14 32

Hanford Kings Road Maintenance & Rehabilitation

Grangeville Boulevard Resurfacing, 11th Avenue to 12th Avenue.

Project will resurface Grangeville Boulevard from 11th Avenue to 12th Avenue, with a double coat fiber seal treatment. The pavement preservation treatment consists of an asphalt emulsion coating with fibers added to provide structural integrity. Resurfacing of Grangeville Boulevard will extend the useful life of the asphalt concrete pavement surface thereby prolonging the need for more expensive roadway repairs.

Grangeville Boulevard, from 11th Avenue to 12th Avenue. 03/2019 06/2019 7 10 14 32

Lemoore Kings Road Maintenance & Rehabilitation 2019 Slurry Seal Type II Slurry seal, update striping and signing Multiple Locations - Cinnamon Drive from 19 1/2 Avenue to Holly Avenue

19 1/2 Avenue from Castle Way to Cinnamon Drive 04/2019 10/2019 8 10 32 14

Lemoore Kings Road Maintenance & Rehabilitation 2020 Slurry Seal Type II Slurry seal, update striping and signing

Multiple Locations - Hanford-Armona Road from Hwy 41 to Fox Street; Hanford-Armona Road from Belinda Drive to the Canal; Silverado Drive from 19 1/2 Avenue to 19th Avenue; 19 1/2 Avenue from Silverado Drive to Bush Avenue

04/2020 10/2020 8 10 32 14

Lemoore Kings Road Maintenance & Rehabilitation 2021 Slurry Seal Type II Slurry seal, update striping and signing Multiple Locations - Cedar Lane from 19th Avenue to Vine Street

Cinnamon Drive from Balboa to Hanford-Armona Road 04/2021 10/2021 8 10 32 14

Clearlake Lake SafetyDam Road/Dam Road Extension Roundabout Project (17/18 Carryover)

Installation of a roundabout with multi-lane entries at all intersection approaches with a 10-foot shared use pathway and crosswalk. Dam Road at Dam Road Extension at the intersection near Walmart. 04/2020 11/2020 20 25 4 2

Clearlake Lake Complete Streets Components

Burns Valley/Civic Center Enhancement Project (17/18 Carryover)

Approximately 2,600 lineal feet of curb, gutter and sidewalk improvements. Olympic Drive from Pine Street to Lakeshore Drive. Lakeshore Drive from Olympic Drive to Division Avenue. 01/2020 06/2020 20 25 4 2

Clearlake Lake Safety Dam Road Extension Project (17/18 Carryover)

Extension of Dam Road Extension South Center Drive to 18th Avenue, approximately 1,000 lineal feet. Dam Road Extension Drive from Dam Road to 18th Avenue. 04/2019 07/2019 20 25 4 2

Clearlake Lake Complete Streets Components

Highlands Park Frontage Improvements (17/18 Carryover)

Frontage improvements, parking lot and pedestrian improvements totaling approximately 515 lineal feet. 14335 Lakeshore Drive, Highlands Park 08/2018 11/2018 20 25 4 2

Clearlake Lake Complete Streets Components Airport Road Improvements Regional shopping center connector road from 18th Avenue east to west. 18th Avenue at State Road 53 09/2019 11/2020 20 25 4 2

Lakeport Lake Road Maintenance & Rehabilitation Second Street Reconstruction Reconstruct existing roadway and replace curb, gutter & sidewalk to meet current ADA

standards Second Street between Main Street and Park Street 07/2018 08/2018 8 15 4 2

Lakeport Lake Road Maintenance & Rehabilitation

Miscelleneous roadway maintenance activities Mill and Fill, dig-outs, pot-hole repairs and thin lift overlays Project boundaries will be Lakeport Blvd. to 20th Street. This area has approximately 52 City

maintained Streets within it. 10/2018 04/2019 4 8 4 2

Susanville Lassen Road Maintenance & Rehabilitation 2018-2019 SEAL COATS APPLY FOG SEAL AND/OR TYPE II SLURRY w/CRACK SEALING TO NEWER

PAVED STREETS WITHIN THE CITY VARIOUS STREETS I.E. RIVERSIDE, JOHNSTONVILLE, NUMA, BUNYAN & GRAND 02/2019 05/2019 3 7 1 1

Agoura Hills Los Angeles Road Maintenance & Rehabilitation

FY 2018/19 Annual Street Resurfacing Project

Resurfacing 11 streets of pavement using rubberized asphalt concrete (RAC). The project also includes removing and replacing curb ramps in order to comply with current American with Disabilities (ADA) standards.

Capehorn Dr, Captains Pl, Dunegal Ct, Eaglebrook Dr, Forestridge Dr, Goodspring Dr, Janlor Dr, Kiva Ct, Lake Crest Dr, Passageway Pl, and Rigger Rd 07/2018 09/2018 10 20 50 27

Agoura Hills Los Angeles Traffic Control Devices Thousand Oaks Boulevard/Argos Street Traffic Signal

Installation of traffic signal at the intersection of Thousand Oaks Blvd and Argos St. Includes new crosswalks and new curb ramps in order to comply with current ADA standards.

Intersection of Thousand Oaks Boulevard and Argos Street. 07/2018 10/2018 50 60 50 27

Alhambra Los Angeles Road Maintenance & Rehabilitation

FY18/19 RMRA SB1 Street Rehabilition Project Street grind and overlay with rubberized asphalt. The southeast portion of the City. North of the San Bernardino freeway, east of Garfield (excluding

Garfield), south of Valley Blvd (excluding Valley Blvd), and west of New Avenue. 09/2018 03/2019 15 20 49 22

Alhambra Los Angeles Road Maintenance & Rehabilitation

FY 17/18 RMRA SB1 Street Rehabilitation Project Grind and overlay

The project is located in the north end of the City. Bounded by Pine Street on the north; Alhambra Road on the south; Electric Avenue on the west; and Olive Avenue to the east. Two other street segments are: Almansor Street from Main Street to Huntington Drive and Marengo Avenue from Main Street to Valley Blvd.

07/2018 12/2018 15 20 49 22

Arcadia Los Angeles Road Maintenance & Rehabilitation

FY 2018-19 Pavement Rehabilitation Program

This project will resurface approximately 2.5 miles of City roadways with rubberized asphalt. Work includes pavement rehabilitation/reconstruction to extend the roadway service life. Other repair items to be included in the scope of work are localized AC dig-out repairs and minor repairs to concrete curb and gutter, sidewalk, and cross gutters. All striping and pavement markers will be reinstalled upon completion of the paving.

Fallen Leaf Road (From Hampton Road to Glencoe Drive), Rodeo Road (From Hacienda Drive to Foothill Boulevard), Camino Real Avenue (From Santa Anita Avenue to Sixth Avenue), Las Flores Avenue (From Holly Avenue to Santa Anita Avenue)

03/2019 04/2019 15 20 49 22

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 22: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Arcadia Los Angeles Complete Streets Components

Colorado Blvd Sidewalk Gap Closure (17/18 Ongoing)

This project will include construction of new sidewalk and retaining wall along the north side of the Colorado Boulevard from San Antonio Road to Colorado Boulevard Gold Line Bridge. The project will consist of abandoning an existing sewer main, removing several mature trees, regarding and landscaping the adjacent frontage of Newcastle Park, and placing a new retaining wall where needed to construct an new 5ft wide sidewalk per City Standards.

North side of Colorado Boulevard from San Antonio Road to the Colorado Boulevard Gold Line Bridge. 02/2019 04/2019 20 20 49 22

Artesia Los Angeles Safety Norwalk Boulevard (17/18 Ongoing)

The project is the final phase that closes the gap in the City's master plan to provide safe bike and pedestrian paths for the City's lowest-income residents. The project will provide 26,400 linear feet of Class 2 bike lanes, 835 linear feet of sidewalk improvements, 3,000 linear feet of traffic-calming safety medians, and 5 ADA ramps.

The project will span the entire length of Norwalk Boulevard within the City limits, from the intersection of the Metro right-of-way to Artesia Boulevard. 01/2018 08/2018 25 30 58 32

Artesia Los Angeles Road Maintenance & Rehabilitation

Residential Street Resurfacing (17/18 Carryover)

Resurfacing pavement, and/or removal and replacement of asphalt, and/or cape sealing and striping Hibbing St., Meadow Dr., 181st St., and 188th St. 08/2018 10/2018 25 30 58 32

Avalon Los Angeles Complete Streets Components Five Corner Complete Street Project

Reconstruct a 5-way intersection utilizing complete streets concepts by installing two mini roundabouts, new sidewalks, lighting, improved transit facilities and shared bicycle facilities.

Intersection of Tremont, Avalon Canyon, Country Club and Sumner roadways 09/2019 06/2021 20 30 70 26

Azusa Los Angeles Road Maintenance & Rehabilitation

Gladstone Street Pavement Rehabilitation

This project will rehabilitate the pavement on Gladstone Street from Azusa Avenue to Heathdale Avenue and Citrus Avenue to Galanto Avenue. Gladstone Street from Azusa Avenue to Heathdale Avenue and Citrus Avenue to Galanto Avenue 06/2019 12/2019 15 25 48 22

Azusa Los Angeles Road Maintenance & Rehabilitation

Vernon Avenue Pavement Rehabilitation from Gladstone Street to 6th Street (17/18 Carryover)

Rehabilitate Pavement on Vernon Avenue from Gladstone Street to 6th Street (17/18 Carryover) Vernon Avenue from Gladstone Street to 6th Street 09/2018 12/2018 10 15 48 22

Baldwin Park Los Angeles Road Maintenance & Rehabilitation

Brooks Drive and Spring Street Reconstruction (FY17/18 Ongoing)

This project is ongoing from FY 2017-18. Design phase has commenced and is scheduled to be completed by 8/2017. Construction will begin in 10/2018. Project will consist of reconstruction of portions of the street structural section including removal of 22-inches of the existing roadway and constructing new roadway section including sub-surface preparation, sub grade and constructing aggregate base and asphalt concrete (AC) pavement sections. The project also includes upgrade/replacement of accessible ramps and major curb and gutter repairs.

Brooks Drive between Rivergrade and Road and End of Street. Spring Street between Littlejohn and End of Street. 10/2018 02/2019 20 25 48 22

Baldwin Park Los Angeles Road Maintenance & Rehabilitation Entry Street Monument Signs

Design and construction of eight (8) entry monument signs to be placed at major entry points to the city. The project includes street improvements necessary to accommodate the installation including sub-surface preparation, subgrade and AC overlay, and concrete improvements.

Proposed locations: Badillo St. (WB), Puente Ave. (NB), Ramona Blvd. (WB), Baldwin Park Blvd. (WB), Pacific Ave (NB), Los Angeles St. (WB), Francisquito Ave (NWB), Root St. (WB)

02/2018 06/2018 20 30 48 22

Baldwin Park Los Angeles Road Maintenance & Rehabilitation

Residential Street Rehabilitation Project

Work includes 2-inch cold-mill of the roadway and placing new asphalt layer. The project also includes upgrade/replacement of accessible ramps, minor curb and gutter repairs, traffic signal loop replacement, and re-striping.

Leorita St - Dalewood St to Bess Avenue, Vineland Ave – City Limit to end of street, Valona Dr - Walnut Creek Pkwy to end of street, Gardenview Ln- Siesta Ave to Dalewood St, Dundry A ve- Corak A ve to end of street, Athol St. Bess Ave to Fairgrove St, Stichman Ave- I-10 Freeway to end of street, Baldwin Park Blvd- SCL to Bess Ave

09/2018 12/2018 15 25 48 22

Baldwin Park Los Angeles Road Maintenance & Rehabilitation

Street Rehabilitaion Project (FY17-18 Carryover)

This project is being carried over from FY2017-18. The project consist of 2-inch cold-mill of existing roadway and constructing new asphalt layer. The project also includes upgrade/replacement of accessible ramps, minor curb and gutter repairs, and re-striping.

Fraizer Street - Judith and End of Street, Amar Road - Fraizer to End of Street, Phelan Avenue - Los Angeles St to Olive Street, Nolina St - Ledford St to Dalewood St, Ledford St - Fraizer St to Nolina St 09/2018 12/2018 10 15 48 22

Baldwin Park Los Angeles Road Maintenance & Rehabilitation

Maine Avenue Supplemental Paving and Street Improvements

This project will consist of reconstruction of portions of the street structural section including sub-surface preparation, subgrade and constructing aggregate base and asphalt concrete (AC) pavement sections. The project also includes upgrade/replacement of accessible ramps, relocation of water main and major curb and gutter repairs.

Maine Avenue - Between Los Angeles Street and Arrow Highway 11/2018 06/2019 15 25 48 22

Bell Los Angeles Road Maintenance & Rehabilitation

Pavemement Repaving Project Fy 18-19

Cold mill existing AC pavement, ARHM overlay, remove and replace damaged driveway approaches, sidewalks, curb and gutter, curb ramps, AC pavement, replace signing and striping, water quality improvements, and install ADA compliant ramps as needed.

Flora Avenue - Walnut St. to 350’ s/o of Walnut St., Florence Ave. Frontage Road - Florence Ave. to East End, Walnut St. - Otis Ave. to East End, Vinevale Ave. - Gage Ave. to Randolph St., Chanslor Ave. - Gage Ave. to Florence Ave., Heliotrope Ave. - Gage Ave. to Florence Ave., Fishburn Ave. - Bell Ave. to Gage Ave., Pine Ave. - Bell Ave. to Florence Ave. (Carry Over), Weik Ave. - Heliotrope Ave. to Vinevale Ave. (Carry Over)

06/2018 09/2018 15 20 63 33

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Sidewalks, Curb and Gutter Replacement, Citywide Remove and replace damage concrete improvements, Citywide

Citywide Maintenance Zones; Zone 1 bounded by NCL, WCL, Lubec St and Jaboneria; Zone 2 bounded by WCL, Lubec St, Jaboneria and Clara St; Zone 3 bounded by WCL, SCL, Clara St and Garfield; Zone 4 bounded by NCL, Jaboneria, Clara St, and Perry Rd; Zone 5 is bounded by NCL, ECL, Park Ln and Perry Rd.

10/2017 06/2019 20 30 58 33

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Street Signage Replacement, Citywide Remove and replace damaged or non-compliant street signs, Citywide

Citywide Maintenance Zones. Zone 1 bounded by NCL, WCL, Lubec St and Jaboneria Rd; Zone 2 bounded by WCL, Lubec St, Jaboneria Rd, and Clara St; Zone 3 bounded by WCL, SCL, Clara St and Garfield; Zone 4 bounded by NCL, Jaboneria, Clara St and Perry Rd; Zone 5 bounded by NCL, ECL, Park Ln and Perry Rd

10/2017 06/2019 20 30 58 33

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Annual Pavment Striping and Markings Project, Citywide Re-stripe all pavement striping, markings, legends, and curb painting, Citywide

Citywide Maintenance Zones. Zone 1 bounded by NCL, WCL, Lubec and Jaboneria; Zone 2 bounded by WCL, Lubec, Jaboneria and Clara St; Zone 3 bounded by WCL, SCL, Clara St and Garfield; Zone 4 bounded by NCL, Jaboneria, Clara St and Perry Rd; Zone 5 bounded by NCL, ECL, Park Ln and Perry Rd

10/2017 06/2019 10 15 58 33

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Pothole Repairs and AC Overlay Maintenance Project, Citywide Repair potholes and AC Overlay maintenance project on streets and alleys, Citywide

Citywide Maintenance Zones. Zone 1 bounded by NCL, WCL, Lubec St and Jaboneria; Zone 2 bounded by WCL, Lubec St, Jaboneria and Clara St; Zone 3 bounded by WCL, SCL, Clara St and Garfield; Zone 4 bounded by NCL, Jaboneria, Clara St and Perry Rd; Zone 5 bounded by NCL, ECL, Park Ln and Perry Rd.

10/2017 06/2019 10 15 58 33

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 23: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Annual Local Road Maintenance Rehabilitation - 17/18 Carry Over

Annual Local Road Maintenance Rehabilitation 1.5 - 2 grind and overlay on the following roadway segments Agra from Specht to End; Hannon St from Emil to Perry; Toler Ave from Loveland to End; Loveland from Darwell to Toler; Chalet from Hannon to Foster Bridge; Adams fro Ludell to Lubec; Ludell from Jaboneria to El Selinda; Ira from Florence to Perry; Ira from Priory to Clara; Florence Ave from Scout to Flood Control; Clara from Emil to Scout; Gotham fro Jaboneria to Gephart;

Annual Local Road Maintenance Rehabilitation 1.5 - 2 grind and overlay on the following roadway segments Agra from Specht to End; Hannon St from Emil to Perry; Toler Ave from Loveland to End; Loveland from Darwell to Toler; Chalet from Hannon to Foster Bridge; Adams fro Ludell to Lubec; Ludell from Jaboneria to El Selinda; Ira from Florence to Perry; Ira from Priory to Clara; Florence Ave from Scout to Flood Control; Clara from Emil to Scout; Gotham fro Jaboneria to Gephart;

06/2018 06/2019 10 15 58 33

Bell Gardens Los Angeles Road Maintenance & Rehabilitation

Annual Arterial Road Maintenance Rehabilitation - 17/18 Carry Over

Annual Arterial Road Maintenance Rehabilitation - 1.5 - 2 inch grind and overlay on the following arterial roadway segments; Garfield Ave from Shull to Eastern; Gage from Garfield to Perry; Gage from Emil to Chalet; Gage from Darwell to Garfield.

Annual Arterial Road Maintenance Rehabilitation - 1.5 - 2 inch grind and overlay on the following arterial roadway segments; Garfield Ave from Shull to Eastern; Gage from Garfield to Perry; Gage from Emil to Chalet; Gage from Darwell to Garfield.

06/2018 06/2019 10 15 58 33

Bellflower Los Angeles Safety SR2SL-5348 (027) Eucalyptus Avenue

Remove and replace damaged sidewalk, install pedestrian lighting, install chokers mid-block, remove and replace non ADA compliant drive aprons, and install curb bulb-outs, modify traffic signal, and install high visibility crosswalk.

Eucalyptus Avenue between Flora Vista Street and Somerset Boulevard. 06/2018 07/2018 10 15 58 32

Bellflower Los Angeles Road Maintenance & Rehabilitation

STPLH-5348 (031) Bellflower and Alondra

Cold mill and resurface with ARHM, remove and replace sidewalk, curb ramps, curb, gutter, drive aprons, and adjusting utilities to grade.

Bellflower Boulevard between Flora Vista and Somerset Boulevard and Alondra Boulevard between Bellflower Boulevard and East City Limit. 07/2018 11/2018 10 15 58 32

Beverly Hills Los Angeles Road Maintenance & Rehabilitation

Beverly Hills - Road Repair Improvements (17/18 Carryover)

To include the design and construction related rehabilitation of roadway paving for multiple locations throughout the City that will include the use of recycled rubberized asphalt, whenever feasible. All project details are an estimate and are subject to change throughout the year based on priority need and resources available to the City.

All locations are an estimate and are subject to change throughout the year based on priority need and resources available to the City. - – Burton Way (North Side) between North Rexford Drive and Oakhurst Drive, Burton Way (South Side) between North Rexford Drive and North Robertson Boulevard, Rexford Drive between Olympic Boulevard and Pico Boulevard, Crescent Drive between Sunset Boulevard and Lexington Road, Copley Place near Copley Drive and Sunset Boulevard, Linden Drive between S. Santa Monica Boulevard and Charleville Boulevard, Rexford Dr. between Olympic Boulevard and Wilshire Boulevard, and Almont Dr. between Charleville Boulevard and Olympic Boulevard.

02/2019 06/2020 15 20 50 26

Bradbury Los Angeles Road Maintenance & Rehabilitation Royal Oaks North Curb Extension Installation of new curb and gutter along the north side of Royal Oaks Drive. Royal Oaks Drive in the City of Bradbury. 07/2018 06/2019 75 100 48 25

Bradbury Los Angeles Road Maintenance & Rehabilitation

Design of Citywide Slurry Seal Project - 17/18 Carryover The total cost of design will be $15,000 so this funds the start of the design.

Local Streets (Public) (35’-40’):Bradbury Rd. (Lemon Ave to Wildrose Ave.), Braewood Dr. (Royal Oaks Drive to Col De Sac), Elda Street ( Moutn Olive Drive to Col De Sac), Fairlee Ave (Gardi Street to Col De Sac), Freeborn Dr. (Moutn Olive Drive to Col De Sac), Gardi Street (Spring Point Drive to Col De Sac – West), Gardi Street (Spring Point Drive to Mount Olive Drive), Gardi Street (Mount Olive Drive to Col De Sac – East), Mount Olive Lane (Mount Olive Drive to Col De Sac), Oak Shade Road (Spring Point Drive to Col De Sac), Spring Point Dr. (Gardi Street to Oak Shade Road), Winston Street (Royal Oaks Drive to Lemon Avenue), Woodlyn Lane (250 W. Mt Olive Dr to Mount Olive Drive)Collector Streets (35’-40’):Lemon Avenue (Winston Street to Bradbury Ave), Mount Olive Dr (Royal Oaks Drive to Bradbury City Line to the North), Royal Oaks Dr (Public Trail on Tract 18507 to Parcel 10 on 17 Acre lot in TIN R 10 Wpor SEC 30), All locations have yet to be finalized and are subject to change. Each location will be selected based on priority need and resources throughout the year.

12/2018 06/2019 5 7 48 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 24: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Burbank Los Angeles Road Maintenance & Rehabilitation Street Restoration Zones 1, 2, & 19

To resurface/reconstruct deteriorated streets, alleys, and concrete (sidewalk, driveway apron, curb, gutter, and pedestrian ramps). Sidewalk improvements include new pedestrian ramps for improved disabled access. Resurfacing/reconstructing deteriorated streets, alleys, and sidewalks reduces on-going maintenance and improves ride quality.

AVON ST from WARNER BL to RIVERSIDE DR AVON ST from ALAMEDA AV to VERDUGO AV BOB HOPE DR from END to PARKSIDE AV BRIGHTON ST from EDISON BL to VERDUGO AV CALIFORNIA ST from VALLEY HEART DR to RIVERSIDE DR CALIFORNIA ST from ALAMEDA AV to VERDUGO AV CATALINA ST from OLIVE AV to VERDUGO AV CLYBOURN AV from SARAH ST to VERDUGO AV CORDOVA ST from WARNER BL to OLIVE AV CORDOVA ST from ALAMEDA AV to OAK ST EDISON BL from ALAMEDA AV to BUENA VISTA ST EVERGREEN ST from NATIONAL AV to RIVERSIDE DR EVERGREEN ST from ALAMEDA AV to END FAIRVIEW ST from VALLEY HEART DR to END FAIRVIEW ST from OLIVE AV to OAK ST FLORENCE ST from OLIVE AV to VERDUGO AV FLORENCE ST from ALAMEDA AV to WILLOW ST FRANKLIN AV from END to ROSE ST FRANKLIN AV from ROSE to END FREDERIC ST from ALAMEDA AV to OLIVE AV FREDERIC ST from OLIVE AV to VERDUGO AV GAYLORD DR from VALLEY HEART DR to RIVERSIDE DR HEFFRON DR from PASS AV to SCREENLAND DR HOLLYWOOD WY from VALHALLA DR to 212' N/O VALHALLA DR HOLLYWOOD WY from PACIFIC AV to VALHALLA DR HOOD AV from END to ROSE ST JACARANDA AV from CLYBOURN AV to TOLUCA PAR DR JACARANDA AV from END to CALIFORNIA ST KENWOOD ST from OLIVE AV to ALAMEDA AV KEYSTONE ST from OLIVE AV to VERDUGO AV LIMA ST from OLIVE AV to OAK ST LINCOLN ST from ALAMEDA AV to VERDUGO AV MAPLE ST from MONTEREY AV to PACIFIC AV MAPLE ST from OLIVE AV to ALAMEDA AV MAPLE ST from ALAMEDA AV to END MAPLE ST from END to HEFFRON DR MYERS ST from ALAMEDA AV to VERDUGO AV NAOMI ST from OLIVE AV to VERDUGO AV NAOMI ST from ALAMEDA AV to WILLOW ST NATIONAL AV from CLYBOURN AV to ROSE ST

12/2018 07/2019 20 20 43 25

Calabasas Los Angeles Road Maintenance & Rehabilitation Annual Street Resurfacing Program

The program is to overlay the street pavement based on the Pavement Management Index ratings. Las Virgenes Rd between Thousand Oaks Bl and Parkmor Rd is one of the segment that the City will use SB 1 funding for resurfacing. This segment is on the National Highway System

Las Virgenes Rd between Thousand Oaks Bl and Parkmor Rd 03/2019 06/2019 8 15 45 27

Calabasas Los Angeles Other Mulholland Gap Closure Project

The improvements on Mulholland Hwy adjacent to the Calabasas High School include sidewalk connecting between the eastern high school driveway on Mulholland Highway and an access road to the high school on Old Topanga Canyon Road. It will also include extending the existing Class II bike facility to Old Topanga Canyon Road. The pedestrian and bicycle facilities will end on Mulholland Highway, in front of Calabasas High School, approximately 770 feet east of the intersection. On Old Topanga Canyon Road, the improvements will include reconstructing the existing dirt path on the east side of the roadway to a fully improved sidewalk and connects it to the existing sidewalk adjacent to the school service road. Additional improvements include providing Class II bicycle facilities on both sides of the roadway that will extend to Mulholland Hwy. The pedestrian and bicycle facilities currently end north of Old Topanga Canyon Road.

Mulholland Hwy and 1000 feet east of Mulholland Hwy and Old Topanga Cyn Rd and 875 ft north of Topanga Cyn Rd 02/2019 06/2019 15 25 45 27

Carson Los Angeles Complete Streets Components

ALBERTONI STREET REHABILITATION FROM FIGUEROA ST. to AVALON BLVD. -

$1.6 million project will repair and resurface 557,930 sq. ft. of the roadway surface; including A.C. grinding as required to allow for the new layer of asphalt. This Project also includes removal and replacement of pavement sections recommended for reconstruction. Then, it will be overlaid with 2.0" to 2.5" thick of asphalt to provide a good ridabillity roadway surface. Also, the project will include repair broken and damaged concrete improvements including Curb & Gutter, Cross Gutters, Sidewalks, Driveway Approaches, Access Ramps to comply with ADA requirements.

ALBERTONI ST. FROM FIGUEROA ST. to AVALON BLVD.an East -West Collector street (approx. lengh 9,815 L.F.) within Maintenance Zone #1 S/O 91 FWY at the Eastern/Northern section of the City of Carson

02/2019 09/2019 15 20 64 35

Carson Los Angeles Complete Streets Components

TURMONT ST. FROM AVALON BLVD. to CENTRAL AVE.(17/18 Carryover)

$1.6 million project will repair and resurface 185,875 sq. ft. of the roadway surface; including A.C. grinding as required to allow for the new layer of asphalt. This Project also includes removal and replacement of pavement sections recommended for reconstruction. Then, it will be overlaid with 2.0" to 2.5" thick of asphalt to provide a good ridabillity roadway surface. Also, the project will include repair broken and damaged concrete improvements including Curb & Gutter, Cross Gutters, Sidewalks, Driveway Approaches, Access Ramps to comply with ADA requirements.

TURMONT ST. FROM AVALON BLVD. to CENTRAL AVE. - an East -West Collector street (approx. lengh 5,521 L.F.) within Maintenance Zone #3 at the Central/Northern section of the City of Carson 04/2018 08/2018 15 20 64 35

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 25: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Cerritos Los Angeles Road Maintenance & Rehabilitation

Carmenita Road Rehabilitation Project

Resurface the top 3 inches of asphalt on Carmenita Road from 183rd Street to South Street. The Project will also include the replacement of deficient sidewalks, curbs, gutters and disabled accessible ramps, replacement of traffic loops, adjustment of manholes and water valves to grade, and thermoplastic striping.

Carmenita Road from South Street to 183rd Street. 07/2018 09/2018 10 12 58 32

Cerritos Los Angeles Road Maintenance & Rehabilitation

Residential Street Rehabilitation Project

Construct asphalt removals and replacements as needed, and apply an Bituminous Slurry Coat over residential streets. Project and will also include the replacement of deficient sidewalks, curbs, gutters and disabled accessible ramps, and thermoplastic striping.

The following streets will be affected: 176th Street, Ashworth Place, Bryce Circle, Carnaby Street, Carolyn Street, Casandra Avenue, Chaparral Way, Cortner Avenue, Corto Avenue, Destino Street, Elgers Street, Felson Place, Felson Street, Niagara Avenue, Reva Street, Rose Street, Semora Place, Semora Street, Stark Avenue, Sybrandy Avenue, Yosemite Street.

03/2019 05/2019 5 7 58 32

Claremont Los Angeles Road Maintenance & Rehabilitation

Citywide Annual Roadway Improvements

The Project consists of a grind & pave of the existing roadway surface with 2 inches of Rubberized Asphalt Concrete (RAC). Areas that are lifted, or sunken, will be removed and replaced with a deeper section to restore the surface to acceptable standards. Curb and gutter, sidewalk, street striping, and ADA ramps will be replaced as necessary to pave the roadways.

Towne Avenue from Harrison Avenue to Foothill Boulevard, Andrews Drive from Claremont Boulevard North to Claremont Boulevard South, Mt. Baldy Road from Mills Avenue to Grand Avenue, and Indian Hill Boulevard from Base Line Road to Armstrong Drive.

07/2018 02/2019 10 20 41 25

Commerce Los Angeles Road Maintenance & Rehabilitation

FY 18/19 Pavement Rehabilitation Project

The Project will provide for the pavement rehabilitation of selected streets throughout the City. The selected streets were based on the recommendations identified within the City's Pavement Management System (PMS).

Garfield Avenue - Telegraph Road to South City Limit; Slauson Avenue - West of Gage Avenue to Telegraph Road; and Gage Avenue - Slauson Avenue to Zindell Avenue 12/2018 02/2019 20 25 58 32

Compton Los Angeles Complete Streets Components Compton Boulevar

Installation of raised medians and Class II bicycle lanes. Remove and replace locations for ADA ramps, curb gutters, sidewalk; grind/overlay asphalt; replace all traffic markings, linework, traffic loops

Compton Boulevard from Willowbrook Avenue to eastern city limits 07/2018 03/2019 10 20 64 35

Compton Los Angeles Complete Streets Components Compton Boulevard West

Install bike lanes and lighting along the corridor; enhance pedestrian crossing at 15 intersections. Remove and replace locations for ADA ramps, curb, gutter, sidewalk; grind/overlay asphalt; replace all traffic markings, linework traffic detectors loops.

Compton Boulevard from Willowbrook Avenue to western city limits 07/2018 04/2019 10 20 64 35

Compton Los Angeles Complete Streets Components Residential Street Resurfacing crack sealing, micro surfacing, remove and replace ADA ramps , curb, gutter, sidewalk;

replace all traffic markings and other minor associated work.

Tajauta Ave. from Rosecrans Ave. to Compton Blvd.; Elva. from to 138th St. to Parmelee Ave.; Slater Ave. from 133rd St to Wilmington Ave.; Grandee Ave. from City Limit North to 138th St.; Parmelee from City limit North to 138th St.; Oris St. from Grandee Ave. to City limit East; 135th St. from Parmelee to Elva Ave.; Compton Ave. from 130th St to 134th Pl.; Tucker St. from Crane Ave. to Van Ness Ave.; Rosecrans Ave. from City limit East to Alameda St.; Palmer St. from Alameda St. to Bowen Ave.; Bullis Rd. from City limit North to Compton Blvd.; Myrrh St. from City limit East to Oleander Ave.; Walnut St. from City limit to City limit; Walnut Park Dr. from City limit to City limit; Walnut Pkwy from City limit to City limit; Greenleaf Blvd. from Central Ave. to Center St.; Greenleaf Blvd. from Harris Ave. to City limit East; Alondra Blvd. from City limit East to City limit West; Bulllis Rd. from Compton Blvd. to City limit South; Greenleaf Blvd. from City limit East to Alameda St.; Central Ave. Pkwy & center median imp. (landscaping) from City limit North to Greenleaf Blvd.; Alondra Blvd., from City limit East to Lime Ave.; Santa Fe Ave. from City limit North to City limit South; Alameda St. West from City limit North to City limit South; Alameda St. East from City limit North to City limit South; Santa Fe Ave. from City limit North to City limit South.

07/2018 09/2019 10 15 64 35

Compton Los Angeles Complete Streets Components Residential Street Rehabilitation Remove and replace locations of ADA ramps, curb, gutter, sidewalk; grind/overlay

asphalt; replace all traffic markings, and linework

Salinas Ave. from 134th St. to 132nd St.; Dern Ave from 134th St. to 132nd St.; Riddle Ave from 134th St. to 132nd St; Grandee Ave. from 127th St. to El Segundo Blvd.; 151 St, from Tajauta Ave to Dwight Ave; 152nd St, from Tajauta Ave. to Dwight Ave; Wilmington Ave. from Stockwell Ave. to 131 St.; Nord St. from Wilmington Ave. to Paulsen Ave.; Stockwell Ave. from Wilmington Ave. to Paulsen Ave.; Carlin Ave. from Alameda St. to Santa Fe Ave.; Euclid Ave. from Alameda St. to Santa Fe Ave.; Saunders St. from Essey Ave. to East end; Pixley St. from Essey Ave. to Thorson Ave.; Thorson Ave. from Bales St. to Sauders St.; Bales St. from Bradfield Ave. to Holly Ave.; Holly Ave. from San Vicente St. to Bales St.; San Mateo St. from West end to Harris Ave.; San Marcus St. form West end to Harris Ave.; San Luis St. from West end to Harris Ave.; Locust Ave. from Compton Blvd. to San Vicente St.; San Vicente St. from Holly Ave. to Harris Ave.

07/2018 09/2019 10 15 64 35

Covina Los Angeles Traffic Control DevicesTraffic Signal Modifications - Badillo St & Hollenbeck Ave (17/18 Carryover)

Upgrades to traffic signal poles, controller cabinet, signal heads, and signage with the consideration for the addition of protected left-turn phasing to be considered. Badillo Street and Hollenbeck Avenue 12/2018 12/2018 15 20 48 22

Covina Los Angeles Road Maintenance & Rehabilitation Arterial Streets Slurry Seal Program

Arterial Street Slurry Seal Program provides application of 11.36 miles of arterial and collector streets that were identified in 2016 PMS Report that are at a point of deterioration and the application of slurry seal would assist in preserving the condition of the pavement surface and extend the overall life of the pavement. Projected will be conducted in two phases (FY 2019 and FY 2020)

Zones 1,2,3,4,5,6,7,8,9 and 10 identified in the 2016 PMS Report. Project Locations include: Zone 1 Cypress St (limits Homerest to Leaf); Zone 2 Covina Blvd (Azusa to Citrus); Zone 3 San Bernardino Rd (Citrus to Hollenbeck); Zone 4 Hollenbeck (Badillo to Rowland); Zone 5 Barranca Ave (Cienega to Covina), Citrus Ave (Cypress to Arrow), and Covina Blvd (Citrus to Barranca); Zone 6 Badillo (Citrus to Barranca), Citrus Ave (San Bernardino to Cypress), San Bernardino Rd (Second to Grand), Second Ave (Badillo to San Bernardino); Zone 7 Puente St. (Barranca to Grand), Rowland Ave (Citrus to First), Rowland Ave (Barranca to E’ly City Limit), Workman Street (Citrus to Barranca); Zone 8 Cienga Ave (Grand to Bender), Cypress St (Glendora to Bonnie Cove), Glendora Ave (Covina to Cienga), Glendora (Cypress to Covina); Zone 9 Badillo St. (Glendora to Lyman), Glendora (Badilo to Cypress), Reeder Ave (Badillo to Cypress); Zone 10 Covina Hills Rd (Oak Canyon to E’ly City Limit), Glendora Ave (Badillo to Puente), Puente St (W’ly City Limit to Glendora).

03/2019 06/2019 7 7 48 22

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 26: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Cudahy Los Angeles Road Maintenance & Rehabilitation

Cudahy Citywide Street Improvement Project

Project consists of the Citywide maintenance and rehabilitation of the City's Road & Sidewalk infrastructure. It may include Grind & Cap/AC Overlay (Full Street Reclamation); Asphalt Concrete (AC) restoration (grind and cap) at identified areas; Crack sealing at existing AC and/or PCC roads; slurry seal application; repair of damaged sidewalks, driveways & curb & gutters; ADA improvements, traffic striping & signage. The City plans to rehabilitate approx. 10-15% of its road/sidewalk infrastructure this FY under SB1 Program Funds available as described above and per the 2016 City's PMS & latest CPI. Note: This is a carry-over project from FY2017/18 with an available total funding equal to the City's SB1 allocations/revenues for FY2017/18 & FY 2018/19.

Citywide Project. Includes one or more of the following potential/eligible streets: Atlantic Ave., Patata St., Ardine St., Clara St., Cecilia St., Otis Ave., River Road, Salt Lake Ave., Park Ave., Elizabeth St., Hartle Ave., Walnut St., Santa Ana St., Bear Ave., Flower St., Flora St; Wilcox Ave., Live Oak St., Olive St. Cudahy Area: 1.2 sq. mi.

03/2019 12/2019 10 20 63 33

Culver City Los Angeles Road Maintenance & Rehabilitation

Overland Avenue paving from Ballona Creek to Washington Boulevard

3 inch grind and overlay utilizing Hot mix rubberized asphalt. Culver City, Overland Avenue, from Ballona Creek to Washington Boulevard 01/2019 02/2019 25 30 54 30

Diamond Bar Los Angeles OtherGrand Ave./Golden Springs Drive Intersection Enhancement (17/18 Ongoing)

As a result of the widening of the Grand Ave./Golden Springs Drive intersection being performed as part of the SR57/60 Confluence Project (Phase IIA), pedestrian hardscape and landscape enhancements associated with crosswalks, sidewalks, and parkways are being implemented. This project consists of 0.2 centerline miles along Golden Springs Drive and 0.25 centerline miles along Grand Ave.

Intersection of Grand Ave. and Golden Springs Drive 10/2017 12/2019 10 20 55 29

Diamond Bar Los Angeles Road Maintenance & Rehabilitation

Arterial Street Rehabilitation (Diamond Bar Blvd. from Mountain Laurel to Clear Creek Canyon)

As part of the City's ongoing pavement rehabilitation program, the entire width of the major arterial roadway, Diamond Bar Blvd., will be rehabilitated. This project consists of 0.88 centerline miles.

Diamond Bar Blvd. between Mountain Laurel Way and Clear Creek Canyon 02/2019 06/2019 10 20 55 29

Downey Los Angeles Other Lakewood Blvd./Rosemead Blvd. Corridor Study

Multijurisdictional complete street study of the Lakewood Blvd.-Rosemead Blvd. corridor within the Gateway Cities sub-region. Study will analyze multiple travel modes (transit, cycling, walking, vehicles, etc.) and enhancing connectivity among said modes.

Lakewood Blvd. (Telegraph Rd. – Gardendale St.) 12/2018 06/2020 99 99 58 32

Downey Los Angeles Road Maintenance & Rehabilitation

FY 17-18 Pedestrian Improvements/New Sidewalk/Ramp Construction & ADA Improvements

Construction of new and repair of existing pedestrian facilities (i.e. sidewalk, curb ramps) to enhance pedestrian circulation and to comply with ADA requirements Southeast and northwest quadrants of the city 07/2018 06/2019 30 50 58 32

Downey Los Angeles Road Maintenance & Rehabilitation

Paramount Blvd. Median Island Project Construction of raised concrete median islands Paramount Blvd. (Imperial Hwy. - Florence Ave.) 07/2018 06/2019 25 30 58 32

Downey Los Angeles Safety South Downey Safe Routes to School Project

Construction of new sidewalk and curb ramps, signage, replacement of striping and pavement markings, installation of vehicle speed feedback signs and safety education program

Blodgett Ave., Adoree St., Airpoint Ave., Blodgett Ave., Lankin St., Quoit St., Nada St., Julius St., Pomering Rd. & Laura St. 12/2018 06/2019 25 50 58 32

Downey Los Angeles Road Maintenance & Rehabilitation

FY 18-19 Pedestrian Improvements/ New Sidewalk/Ramp Construction & ADA Improvements

Construction of new and repair of existing pedestrian facilities (i.e. sidewalk, curb ramps) to enhance pedestrian circulation and to comply with ADA requirements

Southwest quadrant (District 2): Burns Ave., Brookshire Ave., Gardendale St., Milta Ave., Stewart & Gray Rd. & Old River School Rd. All locations are subject to change and will be selected based on priority need and resources throughout the year.

10/2018 06/2019 30 50 58 32

Downey Los Angeles Road Maintenance & Rehabilitation

FY 18-19 Annual Slurry Seal Program

Slurry seal residential streets in order to help preserve the condition of the asphalt pavement on said streets for approximately 10 more years.

Northwest quadrant (District 3): Telegraph Rd., Stoakes Ave., I-5 Fwy., Orizaba Ave., Gallatin Rd., Downey Ave., Burns Ave., Old River School Rd., Stewart & Gray Rd., Milta Ave., Rio Hondo Dr., Sherry Ave., Guatemala Ave. & Rivergrove Dr. All locations are subject to change and will be selected based on priority need and resources throughout the year.

10/2018 06/2019 5 10 58 32

Downey Los Angeles Road Maintenance & Rehabilitation

FY 18-19 Residential Street Pavement Rehabilitation

Construct rubberized asphalt overlay on residential streets to extend the useful life of said streets for approximately 20 more years.

Century Blvd (City Limit - Downey Av), Cole St (Brookshire Av - Patton Rd), Dalen St (Bellflower Blvd – Ardis Ave), Donovan St (Birchdale Ave - Brookshire Ave), Imperial Blvd (Frontage Rd N Imperial Hwy - Imperial Hwy), Imperial Bl (Frontage Rd S Imperial Hwy - Imperial Hwy), Patton Rd (Stewart & Gray Rd - Fontana St), Patton Rd (Fontana St - Cleta St), Seaaca St (Pangborn Av - Cul-De-Sac), Washburn Rd (Woodruff Ave - Regentview Ave), Washburn Rd (Bellflower Blvd. - Woodruff Ave), Alameda St (Downey Ave - Brookshire Ave), Cole St (Paramount Bl - Downey Ave), Comolette St (Paramount Bl - Downey Ave), De Palma St (Horton Ave - Rives Ave.), Horley Ave (Yankey St - Loop End), Bellder Dr (Suva St - Cul-De-Sac), Brookshire Ave (Gallatin Rd - Vista Del Rio Ave), Casanes Ave (Casanes Ave - Cul-De-Sac), Chaney Ave (Appleby St - Vista Del Rio Ave), Clancey Ave (Gotham St - Baysinger St), Cleta St (Brookshire Ave - Patton Rd), Dacosta St (Brookshire Ave - Cul-De-Sac), Dolan Ave (Charloma Dr - Cul-De-Sac), Iowa St (Downey Ave - Dolan Ave), Manzanar Ave (Suva St - Lubec St), Margaret St (Lakewood Bl - Cul-De-Sac), Raviller Dr (Mattock Ave - Lesterford Ave), Santa Gertrudes (Downey Ave - Brock Ave), Suva St (Stamps Ave - Manzanar Ave), Vista Del Rio Ave (Brookshire Ave - Stoakes Ave)All locations are subject to change and will be selected based on priority need and resources throughout the year.

10/2018 06/2019 10 20 58 32

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 27: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Duarte Los Angeles Road Maintenance & Rehabilitation 2018 Street Rehabilitation Project

The 2018 Street Rehabilitation Project will consist of sections of roadways to be cold milled and resurfaced along with section of roadways that will be slurry sealed. The preliminary Engineer’s estimate for this work is $512,000. This project is partially funded with SB 1 funds while the primary funding source is local funds. The City of Duarte, will receive and estimated $365,881 in SB 1 funding in Fiscal Year 2018-19 from SB 1 but will only allocate $125,700 to this project. Construction is estimated to begin in January 2019 and be completed in May of 2019.

Locations are all within the City of Duarte's City Limits Street Overlay – Estimated useful Life 20-25 yearsHighland Avenue from Duarte Road to Central Avenue, Mountain Avenue (half of street) from Meridian to Joella Street, Santo Domingo Avenue from Central Avenue to Huntington Drive, Fairlee Avenue from Central Avenue to Maynard Drive, Bloomdale Street from Mount Olive Drive to Crestfield Drive, Francita Avenue from Royal Oaks Drive to end of cul-de-sac

Slurry Seal – Estimated useful life 15-20 years Calle Martos from Calle Andra to Las Lomas Road, Calle Adra from Huntington Drive to Calle Martos, Calle Linares from Calle Martos to end of street, Calle Malaga from Calle Martos to end of street, Calle Villada Circle from Calla Arda to Calla Arda, Bashor Street from Sino Avenue to Las Lomas Road, Bashor Street from Vineyard Avenue to Sino Avenue, Brinsey Avenue from Royal Oaks Drive to end of street, Vineyard Avenue from Royal Oaks Drive to end of street

11/2018 05/2019 15 25 48 25

El Monte Los Angeles Road Maintenance & Rehabilitation

Slurry Seal/Overlay Project Phase II - Montain View Rd, Magnolia St, Parkway Dr and Fineview St (17-18 carryover)

Roadway/street slurry seal, overlay and resurfacing project Area encompassing Montain View Rd, Magnolia St, Parkway Dr and Fineview St 03/2019 08/2019 10 20 48, 49 22

El Monte Los Angeles Complete Streets Components

Merced Ave - Garvey Ave to Rio Hondo Parkway Road Diet (Traffic Calming) (17-18 carryover)

traffic calming and road diet Merced Ave from Garvey Ave to Rio Hondo Parkway 10/2018 06/2019 5 15 48, 49 22

El Segundo Los Angeles Road Maintenance & Rehabilitation

PW 18-18, FY17/18 Pavement Rehabilitation (17/18 Carryover)

2" Grind and overlay in the more severely damaged areas and Slurry Seal in others. The construction is expected to take place from August to September 2018, with $94,000 of the SB 1 fund expenditure (combined with other funds for a total of $1.3 Million project budget).

2" Grind and overlay in the following streets: Sheldon St. – between Grand Ave. and El Segundo Blvd.; Kansas St. – between El Segundo Blvd. and Holly Ave.; Kansas St. – between Holly Ave. and Mariposa Ave.; Holly Ave. – between Kansas St. and Illinois St.; Pine Ave. – between Kansas St. and Washington St.; Washington St. – between Holly Ave. and Mariposa Ave.; Illinois St – between El Segundo Blvd. and Franklin Ave.; Illinois St – between Grand Ave. and Mariposa Ave.; Mariposa Ave. EB – between Nash St. and Douglas St.; Mariposa Ave. WB – between Nash St and Douglas St.; Nash St. – between Rosecrans Ave. and Park Pl.; Park Pl. – between Continental Way and Douglas St.; Douglas St. – between Rosecrans Ave. and Park Pl.; Douglas St. – between Coral Cir. and El Segundo Blvd.

03/2018 06/2018 5 15 62 26

Gardena Los Angeles Road Maintenance & Rehabilitation Local Road Maintenance 2018-2019 Coldmill and Overlay and spot pavement repair of 20 to 25 streets From Crenshaw Blvd. to Vermont Ave. and from El Segundo Blvd. to 182nd Street 04/2019 05/2019 5 20 62, 66 35

Glendale Los Angeles Road Maintenance & Rehabilitation

San Fernando Road Rehabilitation Project Phase 3

Selective removal and construction of deteriorated pavement; surface grinding and placement of ARHM, Asphalt Concrete Pavement (Leveling Course); selective reconstruction of concrete curb and gutters, cross gutters, driveway aprons, and sidewalks; construction of Portland Cement Concrete ADA curb ramps; adjustment of existing manholes and water meters to finished grade; installation of striping and other pavement markings; and modification of existing traffic signal systems.

San Fernando Road between Pacific Avenue and Elk Avenue 05/2019 11/2019 15 20 43 25

Glendale Los Angeles Road Maintenance & Rehabilitation

Highland Avenue Rehabilitation Project

Selective removal and construction of deteriorated pavement; surface grinding and placement of ARHM, Asphalt Concrete Pavement (Leveling Course); selective reconstruction of concrete curb and gutters, cross gutters, driveway aprons, and sidewalks; construction of Portland Cement Concrete ADA curb ramps; adjustment of existing manholes and water meters to finished grade; installation of striping and other pavement markings; and modification of existing traffic signal systems.

Highland Avenue between San Fernando Road and Kenneth Road 05/2019 11/2019 15 20 43 25

Glendale Los Angeles Road Maintenance & Rehabilitation

Doran Street Rehabilitation Project (17/18 Ongoing)

Rehabilitation of Doran Street which includes grinding and resurfacing of the pavement using rubberized asphalt, reconstruction of damaged sidewalks, curbs, gutters and reconstruction/upgrade of ADA Accessible Curb Ramps where required.

Project is Located in the County of Los Angeles, City of Glendale, on Doran Street between Brand Boulevard and Adams Street. 04/2018 08/2018 15 20 43 25

Glendora Los Angeles Road Maintenance & Rehabilitation

Laurel and Ada Avenue Street Reconstruction

The work includes asphalt concrete resurfacing, removal and replacement of curb ramps, sidewalks, curb and gutter, driveway approaches,adjusting manholes, striping, and some local repair. The project limits are from Glendora Avenue to Cullen Avenue. On the City's Pavement Management System, Ada Avenue has an average pavement condition index (PCI) of 20 out of 100. The work includes cold mill and replacement of asphalt concrete, removal and replacement of curb ramps, repair of sidewalks, curb and gutter, driveway approaches and adjusting manholes, striping, and some local repair. The project limits are from Grand Avenue to Pennsylvania Avenue. On the City's Pavement Management System, Laurel Avenue has an average pavement condition index (PCI) of 22 out of 100.

Ada Avenue from Glendora Avenue to Cullen Avenue Laurel Avenue Street Improvement from Grand Avenue to Pennsylvania Avenue. Laurel Avenue from Grand Avenue to Pennsylvania Avenue.

07/2018 06/2019 20 30 48 25

Glendora Los Angeles Road Maintenance & Rehabilitation

Leadora Avenue Street Rehabilitation

The work includes thin layer of asphalt concrete removal and resurfacing, removal and replacement of some curb ramps,adjusting manholes, striping, and some local repair. The project limits are from Grand Avenue to Pennsylvania Ave. and from Glendora Ave. to Cullen Avenue. On the City's Pavement Management System, Leadora Avenue has an average pavement condition index (PCI) of 57 out of 100.

Leadora Avenue from Grand Ave. to Pennsylvania Ave. and Glendora Ave. to Cullen Ave. 07/2018 06/2019 20 30 48 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 28: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Hawaiian Gardens Los Angeles Road Maintenance & Rehabilitation Street Overlay Project FY 18/19

Cold mill existing AC pavement, ARHM overlay, remove & replace damaged driveway approaches, sidewalks, curb & gutter, install ADA compliant ramps, replace signing & striping.

2 street segments: 211th and 213th Streets 04/2019 05/2019 15 20 63 32

Hawthorne Los Angeles Road Maintenance & Rehabilitation

Hawthorne Blvd. Improvement Project Phase 1

Repaving of asphalt, traffic signal upgrades, installation of new traffic signal, bike lane, ADA ramp improvements, sewer relocation, adjustment of utilities. Hawthorne Blvd. between 111th Street and 126th Street. 10/2018 09/2021 10 15 62 35

Hawthorne Los Angeles Road Maintenance & Rehabilitation Local Streets & Roads Maintenance Street & Pothole Repair, Sidewalk Grinding, Traffic Marking / Signage, Related

Equipment Maintenance

117th Street from Prairie Avenue to East end; 130th Street from Roselle Avenue to Cordary Avenue; Galli Street from Chadron Avenue to West End; Doty Avenue from Imperial Highway to 118th Street; Kornblum Avenue from 115th Street to 117th Street; Kornblum Avenue from 119th Street to 120th Street; 144th Place from Doty Avenue to West end; 146th Street & 147th Place from Prairie Avenue to Doty Avenue; Cordary Avenue from 144th Street to Prairie Avenue; Lemoli Avenue, Doty Avenue & Cerise Avenue from Rosecrans Avenue to 147th Street; Washington Avenue from City Limit to El Segundo Boulevard; 118th Place from Tahoe Avenue to Felton Avenue; 134th Street, 138th Place & 139th Street from Glasgow Place to Isis Avenue; 131st Street from Chadron Avenue to Crenshaw Boulevard; 132nd Street from Prairie Avenue to Yukon Avenue; Crenshaw Boulevard, Doty Avenue & Kornblum Avenue from 135th Street to Rosecrans Avenue; Bodger Avenue from Marine Avenue to North End; Fonthill Avenue from Rosecrans Avenue to North end; Lisso Avenue from Kornblum Avenue to West end; Slayton Avenue from Cerise Avenue to West end; Freeman Avenue, Menlo Avenue, Oxford Avenue & Cedar Avenue from Imperial Highway to El Segundo Boulevard; Broadway & 118th Street from Hawthorne Boulevard to Inglewood Avenue; Dalerose Avenue (Gale) from Imperial Highway to North end; 145th Street from Doty Avenue to Yukon Avenue.; Ruthbar Avenue from 148th Street to Fonthill Avenue; Kornblum Avenue from Marine Avenue to 147th Street; Sundale Avenue from 118th Street to 115th Street; 134th Place from Isis Avenue to Judah Avenue; Isis Avenue from 135th Street to Wiseburn Street; Wiseburn Street from Judah Avenue to Glasgow Place; Atkinson Avenue, Tarron Avenue & Chanera Avenue from 119th Street to 115th Street; Grevillea Avenue from Imperial Highway to Broadway; 134th Street from Hawthorne Blvd to Prairie Avenue; Chadron Avenue Simms Avenue & Yukon Avenue from El Segundo Blvd to 131st Street; Florwood Avenue from 130th Street to 132nd Street; Doty Avenue from Ruthbar Avenue to 147th Street.

07/2018 06/2020 1 3 62 35

Hawthorne Los Angeles Road Maintenance & Rehabilitation

El Segundo Boulevard Improvement Project

Intersections widening, ADA improvements, pavement reconstruction and AHRM overlay, traffic signals upgrade and reconstruction, storm drain improvement. El Segundo Boulevard from Hawthorne Boulevard to Crenshaw Boulevard. 09/2019 07/2022 10 15 62 35

Hermosa Beach Los Angeles Safety 8th Street Improvements

The project consists of improvements that will improve walkability and provide safe pedestrian access on 8th Street from Valley Drive to Hermosa Avenue. Improvements include continuous sidewalk; ADA curb access ramps on 8th Street; drainage improvements; installing crosswalks on both sides of 8th Street at intersections of: Manhattan Avenue, Monterey Blvd, Loma Drive, Cypress Avenue, Bard Street and Valley Drive.

On 8th Street between Valley Drive and Hermosa Avenue, Hermosa Beach, CA. 09/2018 09/2019 15 30 66 26

Hermosa Beach Los Angeles Road Maintenance & Rehabilitation

Street Improvements - Various Locations (FY1718 Carryover)

This project proposes pavement rehabilitation of streets at various locations. The project will also address limited quantities of deteriorated concrete sidewalk, curb and gutter, curb ramps and drainage deficiencies.

Various Locations based on Pavement Management System developed and adopted October 2017. Streets planned as part of the project at this time are:18th St, Prospect to Pacific Coast Highway; 19th St, Harper to Prospect Ave; 20th St, Harper to Prospect Ave; 20th Pl, Harper to Prospect Ave; 21 St, Harper to Pacific Coast Highway; 24 St, Valley Dr. to Park Ave; 24th Pl, Valley Dr. to Park Ave; 28th Ct, Morningside to Manhattan Ave; 29 St., Ingleside to Highland Ave; 29 Ct., Ingleside to Highland Ave.; 31 St, Ingleside to Manhattan Ave; 32 Pl., Ingleside to Manhattan Ave.; 33 St, Highland Ave to Manhattan Ave; 33 Pl., Highland Ave to Manhattan Ave; 34th Pl., Highland Ave to Palm Dr; 34th St., Highland Ave to Manhattan Ave; Francisco St., Morningside Dr to Valley Dr; Hillcrest Dr., 21st St. to 18th St.; Park Ave., 24th Pl to Loma Dr.; Prospect Ave., Artesia to 18th St.; Rhodes Ave., 21st St to 18th St; Harper Ave., Artesia to Carnegie Ln; Longfellow, Ingleside to Manhattan Ave

11/2018 06/2019 10 20 66 26

Hidden Hills Los Angeles Complete Streets Components

Long Valley Rd/Valley Circle/US-101 On-Ramp Improvements

To improve traffic congestion and pedestrian access on the Long Valley Rd on-ramp, the City of Hidden Hills proposes to install sidewalk and remove traffic that currently contributes to congestion. This would be accomplished by constructing a right turnout lane on Long Valley Rd at the Long Valley Road intersection with the stop-controlled NB U.S. 101 on-ramp, modifications to the City's security gate house, the purchase of land and construction of a parking lot and staging area for vehicles waiting to enter Hidden Hills, and the construction of sidewalk on the Long Valley Rd corridor/on-ramp and on Valley Circle Blvd.

Long Valley Road at the City of Hidden Hills, the Long Valley Road corridor/US-101 on-ramp in the City Los Angeles, and Valley Circle Blvd in the City of Los Angeles. 04/2016 10/2019 40 50 45 27

Huntington Park Los Angeles Road Maintenance & Rehabilitation Street Rehabilitation Project

Pavement reconstruction: removal and replacement of the original pavement structural capacity by the placement of the equivalent or increased pavement structure (3" to 6"). Reconstruction may include recycled materials (tires) for the reconstruction of the complete pavement structure. Preventative maintenance shall include overlay; removal and replacement of top 2" of A.C. Enhancements also include the application of slurry seal to the existing asphalt pavement surface.

53rd St - Pacific Blvd to East City Limits; 54th St - Pacific Blvd to East City Limits; 55th St - Pacific Blvd to East City Limits; 56th St - Pacific Blvd to East City Limits; 57th St - Pacific Blvd to Soto St; Seville Ave - 58th St to Slauson Ave; Benson St - Gage Ave to End of Cul-de-Sac; California Ave - Gage Ave to Randolph Pl; Arbutus Ave - Belgrave Ave to Randolph St; Carmelita Ave - Slauson Ave to Randolph St; Fishburn Ave - Slauson Ave to Randolph St; Middleton St - Gage Ave to Saturn Ave

12/2018 05/2019 10 15 53 33

Industry Los Angeles Road Maintenance & Rehabilitation

Arenth Avenue Reconstruction (17/18 Carryover)

Cold Mill Overlay, driveway approaches, improved hydrology pattern, ADA improvements, striping Fullerton Road to Nogales Street 07/2020 10/2020 15 25 48, 55, 57 22, 29

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 29: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Inglewood Los Angeles Road Maintenance & Rehabilitation

Centinela Avenue Improvements ( 17/18 Ongoing)

Design 1.5 miles of street resurfacing, curb, gutter and sidewalk repairs, ADA ramp upgrades and related activites Centinela from La Cienega to Florence 02/2018 03/2019 10 20 62 35

Inglewood Los Angeles Road Maintenance & Rehabilitation

Imperial Highway Improvement Project (17/18 Ongoing)

Construction of 1.5 Miles of street resurfacing and associated improvements including curb, gutter and sidewalk repairs and curb ramp construction as well as traffic and pedestrian safety improvements

Imperial Hwy from Van Ness to Prairie Ave 07/2018 03/2019 10 20 62 35

Inglewood Los Angeles Road Maintenance & Rehabilitation

N. La Brea Avenue Improvements (17/18 Carryover)

Construction of 1.15 Miles of Street reconstruction, curb, gutter and sidewalk repairs, ADA ramp upgrades and related activities N. La Brea from Florence Blvd to 64 St 09/2018 02/2020 10 20 62 35

Inglewood Los Angeles Road Maintenance & Rehabilitation

South Prairie Improvement Project (17/18 Carryover)

Design 1 Mile of street resurfacing and associated improvements including curb, gutter and sidewalk repairs and curb ramp construction S. Prairie Ave from Century Blvd to I-105 fwy 03/2019 02/2020 10 20 62 35

Irwindale Los Angeles Road Maintenance & Rehabilitation 2017/2018 Resurfacing Program 2" grind and overlay of AC pavement, re-striping Irwindale Ave, between Arrow Hwy and Cypress St 02/2018 07/2018 10 15 48 22

Irwindale Los Angeles Road Maintenance & Rehabilitation 2018/2019 Resurfacing Program Resurfacing: 2" grind and overlay of AC pavement, re-striping, structural repairs where

neededRivergrade Road, Stewart Avenue, Longden Avenue, Irwindale Road, and Adelante Street; City of Irwindale 03/2019 05/2019 10 15 48 22

La Canada Flintridge Los Angeles Road Maintenance & Rehabilitation

2019 Street Resurfacing Program 18/19-1

The work to be done consists of furnishing all labor, materials, equipment, tools, and incidentals. The general items of work include variable depth cold milling of existing pavement; paving with asphalt rubber hot mix (ARHM) and conventional asphalt concrete; miscellaneous curb and gutter removal and replacement; adjustment to grade of manhole and valve cover; installation of traffic striping, marking, raised pavement marker, and curb address (house number) painting; and miscellaneous appurtenant work. Clean up and leave in an operable and acceptable condition all of the work.

Location 1 Alta Canyada Rd from Fairmount Ave to the North City Limit, Location 2 Alta Park Ln from Alta Canyada Rd to East Cul-de-sac, Location 3 Caroli Ln from Green Ln to North Cul-de-sac, Location 4 Cypress Dr from Foothill Blvd to Cul-de-sac, Location 5 El Camino Corto St Foothill Blvd to Cul-de-sac, Location 6 Encinas Dr from Salisbury Rd to Flanders Rd, Location 7 Fairview Dr from Encinas Dr to Cul-de-sac, Location 8 Flanders Rd from Alta Canyada Rd to East Cul-de-sac, Location 9 Flintridge Ave from Hampstead Rd to Chevy Chase Dr, Location 10 Green Ln from 1252 Green Ln to North Cul-de-sac, Location 11 Groveland Ln from Salisbury Rd to Parkman Dr, Location 12 Indiana Ave from Foothill Blvd to Cul-de-sac, Location 13 Jarvis Ave from Earlmont Ave to Fairmount Ave, Location 14 La Porte Dr from Commonwealth Ave to Oakwood Ave., Location 15 Lasheart Dr Green Ln to North Cul-de-sac, Location 16 Leata Ln from Foothill Blvd. to Cul-de-sac, Location 17 Parkman Dr from Groveland Ln to Commonwealth Ave, Location 18 Pembury Pl from Hampstead Rd to Cul-de-sac, Location 19 Salisbury Rd from Commonwealth Ave to Groveland Ln, Location 20 Salisbury Rd from Lasheart Ln to Encinas

07/2018 12/2018 15 20 43 25

La Habra Heights Los Angeles Road Maintenance & Rehabilitation

FY 18/19 Street Improvement Project

Repair deteriorated pavement areas and resurface streets identified as priorities in the Pavement Management Program. Repair may include crack fill, slurry seal, cape seal, chip seal, asphalt concrete overlay, or remove and replace, as well as restriping and drainage facility repair and improvements.

Chota Rd. from Fullerton Rd. to 1635’ w/o Fullerton Rd., Chota Rd. from 1635’ w/o Fullerton Rd. Carrie Hills Ln., Chota Rd. from Carrie Hills Ln. to Kashlan Rd., Fullerton Rd. from Corral Mtwy. to North City Limit, Sapota Dr. from End to Sharpless Dr., Sharpless Dr. from Skyline Vista Dr. to Skyline Dr., Coban Rd. from Dorothea Rd. to East Rd., Coban Rd. from Kashlan Rd. to End, Skyline Dr. from 1250 n/o Sharpless Dr. to Sharpless Dr., Skyline Dr. from Sharpless Dr. to Airoso Rd., Kanola Rd. from Fullerton Rd. to West End

03/2016 07/2019 10 20 57 32

La Habra Heights Los Angeles Road Maintenance & Rehabilitation

CARRYOVER - FY 17/18 Street Improvement Project

Repair deteriorated pavement areas and resurface streets identified as proprieties in the Pavement Management Plan. Repair may include crack fill, slurry seal, cape seal, chip seal, AC overlay, and R&R, as well as restriping and drainage facility repair and improvements.

REPOSADO DR (AHUACATE RD TO END); PAPAYA DR (944' N/O EAST RD TO PINTO DR); REPOSADO DR (GREENVIEW DR TO CITRON RD); AHUACATE RD (1185' N/O CHURCHHILL DR TO REPOSADO DR); REPOSADO DR (CITRON RD TO HILLSIDE CT); PAPAYA DR (EAST RD TO 944' N/O EAST RD); REPOSADO DR (HACIENDA RD TO CHANDOS LN); VALLE DR (1065' N/O EAST RD TO AIROSO DR); AIROSO DR (SKYLINE DR TO VALLE RD); REPOSADO DR (CHANDOS LN TO GREENVIEW RD); AHUACATE RD (CHURCHILL RD TO 1185' N/O CHURCHILL RD); REPOSADO DR (HILLSIDE CT TO AHUACATE RD); CHURCHILL RD (AHUACATE RD TO EAST RD); VALLE DR (EAST RD TO 1065' N/O EAST RD)

07/2018 08/2018 10 20 57 32

La Mirada Los Angeles Road Maintenance & Rehabilitation

Measure I Residential Street Phase V

Street rehabilitation on local, public streets bounded by Imperial Highway, Biola Avenue, Stage Road, Valley View Avenue and Milan Creek. Project includes pavement rehabilitation, replacement of damaged curb, gutter and sidewalk, upgrades to existing and placement of new handicap curb access ramps, removal and replacement of slotted cross gutters, storm drain pipe repairs, etc.

Street rehabilitation on local, public streets bounded by Imperial Highway, Biola Avenue, Stage Road, Valley View Avenue and Milan Creek. 12/2018 06/2019 20 25 57 32

La Puente Los Angeles Road Maintenance & Rehabilitation

Repaving of Various Local Streets Fy 18-19 Grind and overlay of local residential streets

Tamar Dr. - Prichard St. to End, Prichard St. - Tamar Dr. to Sunkist Ave., Glenshaw Dr. - Prichard St. to Temple Ave., Shadydale Ave. - Prichard St. to Temple Ave., Lasselette St. - Tonopah Ave. to East End, Beckner St. - Orange Ave. to East End,Moccasin St. - Mayland Ave. to End, Homeward Ave. - Ardilla Ave. to Sunkist Ave.,

09/2018 06/2019 20 25 57 22

La Puente Los Angeles Road Maintenance & Rehabilitation

Resurfacing of Various Local Streets FY 17-18 (CARRY OVER PROJECT)

Grind and overlay of local residential streets Radway Ave. - Prichard St. to Temple Ave., Broadmoor Ave. - Prichard St. to Temple Ave., 09/2018 06/2019 20 25 57 22

La Verne Los Angeles Road Maintenance & Rehabilitation

2018/19 Pavement Rehabilitation Projetc The proposed project will include the rehabilitation of 2.4 miles of existing pavement.

Various locations - Old Wheeler Road from Wheeler Avenue to Wheeler Avenue, Sherwood Drive from Wheeler Avenue to Wheeler Avenue, Bowdoin Street from Fruit Street to Emerald Avenue et al and the rehabilitation of Roosevelt et al which includes Madison Avenue, Brandt Street and Fillmore Court.

09/2018 10/2018 12 20 41 25

Lakewood Los Angeles Road Maintenance & Rehabilitation

Alley West of Lakewood Blvd Reconstruction

Remove existing asphalt and base. Reconstruct with new base and Portland Cement Concrete (PCC) Alley west of Lakewood Blvd between Candlewood St and Hardwick Ave 08/2018 08/2019 25 30 63 32, 33

Lakewood Los Angeles Road Maintenance & Rehabilitation Pavement Rehab Phase I Overlay with ARMH Candlewood St between Fidler Ave and 400 feet west of Lakewood Blvd

Harvey Way between Bellflower and Woodruff 08/2018 06/2019 12 15 63 32, 33

Lakewood Los Angeles Road Maintenance & Rehabilitation Del Amo Blvd Rehab Overlay with ARHM Del Amo Blvd between Paramount Blvd and Cherry Ave

Del Amo Blvd between Paramount Blvd and Downey Ave 08/2018 06/2019 12 15 63 32, 33

Lakewood Los Angeles Complete Streets Components

Paramount Blvd Drainage and Landscape

Modify existing curb and gutter and side panels (medians) to receive and retain stormwater and nuisance water runoff. (Funding by SB 1 and other sources) Paramount Blvd between Del Amo Blvd and Carson St 08/2018 06/2019 20 30 63 32, 33

Lakewood Los Angeles Road Maintenance & Rehabilitation

Downey Ave Pavement Rehab (17/18 Carryover) Overlay with ARHM Downey Ave between Del Amo Blvd and Country Club Rd 08/2018 06/2019 15 25 63 32, 33

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 30: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Lancaster Los Angeles Road Maintenance & Rehabilitation Revive 25

The 2018 PMP-Revive 25 is one of a series of projects to "revive" every lane mile within City limits by the year 2025. Revive 25 will maximize the life of all Lancaster roads by preventing road issues before they occur. This project includes street resurfacing, traffic calming measures, and right sizing roadway. Some of the projects will also incorporate recycled asphalt (RAP).

(1) 10th Street West, between Avenue L & Avenue M (17/18 Ongoing) (2) Neighborhood: Avenue K-4 to Avenue K-8; 25th Street West to 30th Street West; (3) Neighborhood: Lancaster Boulevard to Avenue J; 10th Street West to 15th Street West; (3) Neighborhood: Glenhaven to Avenue J-8; Division Street to Raysack Street; (4) Neighborhood: Lancaster Boulevard to Avenue J; 2nd Street East to 3rd Street East; (5) Neighborhood: Avenue J-8 to Avenue K; 15th Street West to Rembrandt Street; (6) 4th Street East; Avenue L to Avenue M.

06/2017 09/2018 15 30 36 21

Lawndale Los Angeles Road Maintenance & Rehabilitation Various Streets Resurfacing Project Repave/Resurface a total of 0.41 miles of road. Project also includes removal and

replacement of PCC curb/gutter, sidewalk, curb ramps, and other appurtenance work.149th Street (Hawthorne Blvd to Larch Avenue); 160th Street (Hawthorne Blvd to Freeman Ave); and 167th Street (Hawthorne Blvd to Freeman Ave). 12/2018 03/2019 20 28 62 35

Lawndale Los Angeles Road Maintenance & Rehabilitation

Alley Resurfacing Project (17/18 Carryover)

Repave/Resurface a total of 0.21 miles of alleyways. Project also includes removal and reconstruction of concrete gutters. Alleys east of Hawthorne from 163rd to 166th Streets and from 167th to 168th Streets 12/2018 03/2019 20 28 62 35

Lomita Los Angeles Road Maintenance & Rehabilitation

250th Street (Pennsylvania Avenue to Eshelman Avenue) Rehabilitation Project

Street Resurfacing/Rehabilitation 250th Street between Pennsylvania Avenue and Eshelman Avenue 06/2018 10/2019 10 20 66 26

Lomita Los Angeles Road Maintenance & Rehabilitation

Zone F Street Improvement and Slurry Seal Project

Street improvements, including AC Reconstruction, AC Overlay, Cape Seal, and Slurry Seal per the City’s 2017 Pavement Management Program update.

Streets throughout the City’s street maintenance Zone F (NW corner of the City) including portions of the following streets: 240th Street, 242nd Street, 243rd Street, 245th Street, Adona Drive, Allbrook Street, Alliene Avenue, Benhill Avenue, Cadiz Drive, Carlene Lane, Dawn Street, Hendricks Avenue, Lomita Drive, Lomita Park Place, Lucille Avenue, G654Olson Lane, and Pennsylvania Avenue.

01/2019 06/2019 5 20 66 26

Long Beach Los Angeles Road Maintenance & Rehabilitation

FY19 Residential Street Repair, CD6 Maintenance/Rehabilitation of 0.2 mile of road E 15th Street between Lewis Ave and Alamitos 05/2019 07/2019 10 15 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Anaheim Street between Pacific Ave and Atlantic Ave 08/2019 10/2019 10 15 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.3 mile of road Temple Avenue between 4th St and 7th St 08/2019 10/2019 10 15 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Ximeno Avenue between Broadway and 4th St 08/2019 10/2019 7 10 70 34

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 miles of road Anaheim Street between Gardenia Ave and Temple Ave 08/2019 10/2019 7 10 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Carson Street between Clark Ave and Bellflower Blvd 08/2019 10/2019 7 10 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Anaheim Street between Alamitos Ave to Gardenia Ave 08/2019 10/2019 7 10 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.4 mile of road Long Beach Blvd between 31st St and Wardlow Rd 08/2019 10/2019 7 10 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Del Amo Blvd between Atlantic Ave and Orange Ave 08/2019 10/2019 7 10 70 33

Long Beach Los Angeles Road Maintenance & Rehabilitation Major & Secondary Streets Maintenance/Rehabilitation of 0.5 mile of road Artesia Blvd between Cherry Ave to Paramount Blvd 08/2019 10/2019 10 15 63 33

Long Beach Los Angeles Road Maintenance & Rehabilitation

FY19 Residential Street Repair, CD4 & CD6 Maintenance/Rehabilitation of 1.2 mile of road 15th Street between Orange Ave and Obispo Ave 08/2019 10/2019 10 15 70 33

Los Angeles Los Angeles Safety Glendale Blvd/Silverlake Blvd Rockfall Mitigation (17-18 Ongoing)

The project will install a wire mesh net to keep material from a failed slope from continuing to impact the public right of way. Sandstone debris up to four feet in diameter previously dosed the sidewalk and two lanes of traffic on the street. Funding is provided from: SB1 ($34,546) and Gas Tax ($531,000)

Glendale Bl. And Silverlake Bl. 08/2018 01/2019 20 30 43 24

Los Angeles Los Angeles Safety Verde Oak Drive (2252 N) Bulkhead (17-18 Ongoing)

The project will construct a bulkhead type retaining wall with new steel piles and precast concrete lagging to restore lateral support to the roadway. The roadway has settled one to two feet over an 80 linear foot area. Funding is provided from: SB1 ($140,000); Gas Tax ($330,104) and the Public Works Trust Fund ($427,896)

2252 N. Verde Oak Drive 10/2018 04/2019 20 30 43 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 31: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Angeles Los Angeles Complete Streets Components

Street Reconstruction/Vision Zero Project Construction (17-18 Ongoing)

Construction of six Complete Streets projects begun in 2017-18: Avalon: Complete Street Project involving 3.9 lane miles of street reconstruction, 5.3 lane miles of resurfacing, and safety improvements. The project will include a street reconfiguration to one lane each way with a center lane for turning, fully protected bike lanes from 56th to Manchester, speed feedback signs, leading pedestrian intervals, rectangular rapid flash beacons (RRFB), protected left turns, curb extensions, signal timing upgrades, intersection tightening, new crosswalks with RRFB, new traffic signals, and bus stop relocation. Main: Complete Street Project involving 3.1 lane miles of asphalt street reconstruction,2.3 lane miles of concrete street reconstruction, 4.9 lane miles of asphalt resurfacing, and safety improvements. The project will include speed feedback signs, leading pedestrian intervals, adding RRFBs to crosswalks, protected left turns, signal timing upgrades, new crosswalks with RRFB, new traffic signals, and bus stop relocation. Reseda: Complete Street Project Involving 6.2 lane miles of street reconstruction, 6.2 lane miles of resurfacing and safety improvements. The project will include crosswalk installation or upgrades, striping modifications, curb extensions, signal phasing and timing changes, and proposals for closing a gap in the existing bike lanes, between Valerio and Vanowen.

Roscoe: Complete Street Project involving 3.4 lane miles of street reconstruction, and safety Improvements. The project will include speed feedback signs, leading pedestrianintervals, protected left turns, traffic signals and crosswalk upgrades. Temple: Complete Street Project involving 2.9 lane miles of street reconstruction, 1.3 lane miles of resurfacing, and safety improvements. The project will include speed feedback signs, leading pedestrian intervals, protected left turns, signal timing upgrades, new crosswalks with RRFB, new traffic signals, and bus stop relocation. Venice: Complete Street Project involving 6.8 lane miles of street reconstruction, 1.6 lane miles of resurfacing, and safety Improvements. The project will include leading pedestrian intervals, adding RRFB to crosswalks, protected left turns, and new traffic signals.

These projects total $80 million in estimated costs. However, funding will be provided from multiple sources (including SB1) over multiple years (including 2017-18, 2018-19 and 2019-20). SB1 provides $6 million in 2017-18 and $23,561,000 in 2018-19.

Avalon from San Pedro to 120th (Council Districts 8, 9, 15) Main(south) from MLK to Imperial (Council Districts 8, 9) Reseda from Parthenia to Victory (Council District 3,12) Roscoe from the 405 Freeway to Woodman (Council Districts 6) Venice (east) from Arlington to Figueroa (Council Districts 1, 9, 10) Temple from Beverly to Beaudry (Council Districts 1, 13)

06/2018 06/2020 20 25 45, 46, 53, 54, 59 18, 24, 30

Los Angeles Los Angeles Complete Streets Components

Street Reconstruction/Vision Zero Design

18/19 Complete Street Projects in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet to be finalized. Locations will be selected based upon priority need and resources throughout the year.

Citywide - in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet to be finalized. Locations will be selected based upon priority need and resources throughout the year. 01/2019 01/2020 20 25 59 30

Los Angeles Los Angeles Safety Sidewalk Repair Access Request Acceleration Repair of sidewalks adjacent to streets to safely separate vehicle and pedestrian traffic Citywide - in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet

to be finalized. Locations will be selected based upon priority need and resources throughout the year. 01/2019 01/2020 20 2539, 43, 45, 46, 50, 51, 53, 54, 59, 62, 64

18, 24, 25, 26, 27, 30

Los Angeles Los Angeles Road Maintenance & Rehabilitation Concrete Streets (17-18 Ongoing) Repair of failed concrete streets Citywide - in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet

to be finalized. Locations will be selected based upon priority need and resources throughout the year. 01/2019 01/2020 35 40 59 30

Los Angeles Los Angeles Safety Silverlake Blvd Underpass Arch Project

Sidewalk and road repair: Separate motor vehicle and pedestrian traffic for public safety. Silver Lake. Council District 13: Sunset Blvd and Silver Lake St. 01/2019 07/2019 20 25 51 24

Los Angeles Los Angeles Safety Sheldon Arleta Sidewalk Improvement - Sharp Ave

Separation of pedestrian and vehicle traffic for safety: To complete sidewalk improvements around Sheldon Arleta Park. Remove and reconstruct street pavement, curb, gutter, trees, utilities poles, new concrete sidewalk, re-strip street, construct street lights, relocate fence, new fence wrought iron(tubular). Funding sources include SB1 $2,843,734 and Public Works Trust Fund $289,782.

Sheldon Arleta Park . Council District 6, Sheldon St and Sharp Ave 01/2019 01/2020 20 25 39 18

Los Angeles Los Angeles Road Maintenance & Rehabilitation

Cochran Ave (2520) Culvert at Cul-De-Sac

Repair of roadway: Re-mediate the transition structure at the culvert outlet by correcting the grade to drain to the south and replace the deficient curb and gutter along with the sidewalk that will be impacted in order to re-establish the original drainage pattern. Project funding sources include SB1 $245,000 and Public Works Trust Fund $100,000.

South LA. Council District 10, 2520 Cochron Ave 01/2019 01/2020 20 25 54 30

Los Angeles Los Angeles Road Maintenance & Rehabilitation

Dudley Drive Pavement Reconstruction Reconstruction of street to correct drainage due to long-term subsidence. Council District 14, Dudley Dr and Cato St 01/2019 01/2020 20 25 51 24

Los Angeles Los Angeles Road Maintenance & Rehabilitation Via Marisol Street Repair

Roadway reconstruction: This project will replace damaged pavement, concrete curb, and sidewalk along Via Marisol approximately 700 feet east of Monterey Road. Anticipated repair includes excavation of existing soil, installation of replacement soil, removal and replacement of damaged existing pavement, curb, and sidewalk, and re striping of the street. Project funding sources include SB1 $2,146,224 and Public Works Trust Fund $226,464.

Council District 14: Via Marisol and Monterey Rd 01/2019 01/2020 20 25 51 24

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 32: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Angeles Los Angeles Road Maintenance & Rehabilitation

Kinney Street Improvement - Crestmoore to Lavell

Street improvement, retaining wall: Retaining walls and street improvement, including regrading street, new curb and gutter for drainage control. Council District 1, Kinney Street between Crestmoore Pl and Lavell Dr 01/2019 01/2020 20 25 51 24

Los Angeles Los Angeles Safety Branford Street - Arleta Ave to Pacoima Wash

Repair roadway to reduce flooding and promote safety: This project consists of constructing 600’ of 36”storm drain in Branford Street from the outlet at the Pacoima Wash Diversion Channel, northeasterly to Arleta Avenue. Branford Street is a heavily traveled secondary highway. The intersection of Arleta and Branford becomes flooded during even minor rainfall events, seriously impeding vehicular and pedestrian traffic. This can contribute to traffic accidents, increasing the City’s liability.

San Fernando Valley. Council District 6: Branford Street - Arleta Ave to Pacoima Wash 01/2019 01/2020 20 25 39 18

Los Angeles Los Angeles Road Maintenance & Rehabilitation

Vista Del Mar 2,200 and 3,000 feet n/o Imperial Hwy Bulkheads

This safety related project constructs 2 steel beam and precast concrete lagging bulkheads along Vista Del Mar to restore lateral support to the street. West LA. Council District 11: Vista Del Mar / Imperial Hwy 01/2019 01/2020 20 25 62 26

Los Angeles Los Angeles Other Active Transportation River to Rail Corridor

This $90 million project will create a safety separation between motorists, bicyclists and pedestrians and provide linkages with two rail lines. This project will be in construction in the spring of 2018 and will be completed before the opening of the Crenshaw line in late 2019. $3 million of SB1 is to install cool pavement, plant trees and fund one of two bike hubs. The remaining funding is provided from other sources.

South LA. Council District 8 and Council District 9. 01/2019 01/2020 20 25 54 30

Los Angeles Los Angeles Complete Streets Components 7th Street Streetscape

Road repair and sidewalk and bicycle improvements: Improve pedestrian safety by installing curb extensions, widening sidewalks, improving pedestrian lighting, enhancing crosswalks, and provide pedestrian amenities including benches, street trees, landscaped buffers from traffic and bike racks. Estimated total cost of project is $10,699,534. Project funding sources include: Wilshire Grand Development $7,970,689, Housing and Community Investment Department grant $2,115,000, Affordable Housing Sustainable Communities grant $13,845 and SB1 $600,000

Downtown LA. Council District 14: 7th Street between Olive and San Pedro. 01/2019 01/2020 20 25 53 30

Los Angeles Los Angeles Safety Main Street Lighting Improvement Unit 2

Street Lighting Improvement: Replace existing high voltage series street lighting system with a low voltage system (install new poles, foundations, conduit, wires, and energy efficient LED lighting.

Council District 9: Main St. from 42nd Pl. to 57th St. and San Pedro Pl. between Main St. and 80th. 01/2019 01/2020 15 20 59 30

Los Angeles Los Angeles Safety 2nd Street Tunnel - Hill to Figueroa STM/STP

Street Lighting improvement: Replacement of tunnel lights, including conduit, wires, poles, luminaries, and lamps. Downtown LA. Council District 14 01/2019 04/2020 15 20 53 24

Los Angeles Los Angeles Safety Security Lighting Unit 20Part of the Security Lighting at Bus Stops Program. This project installs modern pedestrian lighting systems at select bus stop locations to meet lighting standards for pedestrian traffic.

Street lighting at bus stops in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet to be finalized. Locations will be selected based upon priority need and resources throughout the year.

01/2019 08/2019 15 20 59 30

Los Angeles Los Angeles Complete Streets Components

6th Street from Rampart to Beaudry (17-18 Carryover)

Complete Street Project Involving 0.9 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Council District 1: 6th Street from Rampart to Beaudry 01/2019 06/2020 20 30 53 24

Los Angeles Los Angeles Complete Streets Components

Adams from Fairfax to Crenshaw (17-18 Carryover)

Complete Street Project involving 0.9 lane miles of resurfacing, and safety Improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Adams from Fairfax to Crenshaw (Council District 10) 01/2019 06/2020 20 30 54 30

Los Angeles Los Angeles Complete Streets Components

Alvarado from 6th to 7th (17-18 Carryover)

Complete Street Project involving safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety Improvements.

Alvarado from 6th to 7th (Council District 1) 01/2019 06/2020 20 30 53 24

Los Angeles Los Angeles Complete Streets Components

Broadway from Century to MLK (17-18 Carryover)

Complete Street Project involving 3.7 lane miles of street reconstruction, 3.4 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Broadway from Century to MLK (Council Districts 8, 9) 01/2019 06/2020 20 30 59, 64 30

Los Angeles Los Angeles Complete Streets Components

Figueroa from MLK to Imperial (17-18 Carryover)

Complete Street Project involving 9.5 lane miles of street reconstruction, 3.6 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety Improvements.

Figueroa from MLK to Imperial (Council Districts 8, 9) 01/2019 06/2020 20 30 59, 64 30

Los Angeles Los Angeles Complete Streets Components

Hoover from Vernon to Manchester (17-18 Carryover)

Complete Street Project involving 1.3 lane miles of street reconstruction, 3.7 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Hoover from Vernon to Manchester (Council Districts 8, 9) 01/2019 06/2020 20 30 59, 64 30

Los Angeles Los Angeles Complete Streets Components

N Broadway from Ave 18 to Mission (17-18 Carryover)

Complete Street Project involving 1.6 lane miles of street reconstruction, 3.3 lane miles of resurfacing and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

N. Broadway from Ave 18 to Mission (Council District 1) 01/2019 06/2020 20 30 51 24

Los Angeles Los Angeles Complete Streets Components

Pico (east) from Western to Union (17-18 Carryover)

Complete Street Project involving 0.9 lane miles of street reconstruction, 0.6 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Pico (east) from Western to Union (Council Districts 1, 10) 01/2019 06/2020 20 30 53 24

Los Angeles Los Angeles Complete Streets Components

Sepulveda from Nordhoff to Rinaldi (17-18 Carryover)

Complete Street Project involving 12.4 lane miles of street reconstruction, 4.9 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Sepulveda from Nordhoff to Rinaldi (Council District 7) 01/2019 06/2020 20 30 39, 46 18

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 33: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Angeles Los Angeles Complete Streets Components

7th from Figueroa to Alameda (17-18 Carryover)

Complete Street Project involving 1.0 lane mile of street reconstruction, 0.4 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

7th from Figueroa to Alameda (Council District 14) 01/2019 06/2020 20 30 53 24, 30

Los Angeles Los Angeles Complete Streets Components

Western from Century to Washington (17-18 Carryover)

Complete Street Project involving 3.5 lane miles of street reconstruction, 4.6 lane miles of resurfacing, and safety improvements. Input from the public and affected Council Office(s) will be used to determine specific safety improvements.

Western from Century to Washington (Council Districts 8, 10) 01/2019 06/2020 20 30 53, 59, 62 24, 30

Los Angeles Los Angeles Safety Davies Way (2044) Bulkhead (17-18 Ongoing)

The project will construct a bulkhead type retaining wall with new steel piles and precast concrete lagging to restore lateral support to the roadway and provide for pedestrian safety. SB1 will provide $200,000, Measure M will provide $516,250 and the City General Fund will provide $42,000

2044 Davies Way 02/2018 08/2018 20 30 50 26

Los Angeles Los Angeles SafetyTujunga/Strathern/Fair Street/Sidewalk Project (17-18 Ongoing)

This project will repair the roadway bed and sidewalks along Tujunga, Strathern and Fair Streets. $300,000 from SB1 is provided to start the project. The actual costs of the project and remaining funding have yet to be identified.

Tujunga Ave. , Strathern St. and Fair St. 01/2020 06/2021 20 30 39 18, 25

Los Angeles Los Angeles Complete Streets Components

Re-lmagine Ventura Blvd Streetscape Improvements (17-18 Ongoing)

This project will implement streetscape improvements along Ventura Boulevard between Royer and Sale Avenue. Improvements to parking, roadway capacity, walkability, bicycle infrastructure, driveway accessibility (turn restrictions), and aesthetics are being considered. $500,000 is provided from SB1 to begin the project. Actual costs of the project and remaining funding have yet to be identified.

Ventura Bl, between Royer and Sale Ave. 01/2020 01/2021 20 30 45 27

Los Angeles Los Angeles Safety Castellammare (17434) (17-18 Ongoing)

This project will restore lateral support to public street by extending a bulkhead approximately 120 linear feet, adjacent to a 70 foot wide landslide. Construction includes street repair, extension of metal-beam guardrail and curb. The beam size for the bulkhead is W36x193 and 60-ft deep. $771,000 is provided by Measure M. $800,000 is provided by SB1.

West LA, Council District 11 04/2018 12/2018 20 30 62 26

Los Angeles Los Angeles Complete Streets Components

Western Avenue Expo Line Station Linkage Project (17-18 Ongoing)

To design and construct pedestrian and safety enhancements intended to increase the use of public transportation and create a link to the Metro Expo LRT Station at Western Ave and Exposition Blvd. This project includes: 64 street trees, 5 bus shelters, 21 bus safety lighting, 22 ADA curb rams, 8 crosswalk enhancements, replacing all parkways with full with sidewalks and bringing 45,952 sf of sidewalks and 7,477 sf of driveways up to code. Western Ave is a priority corridor in Council District 8's economic development strategy. $181,000 is provided by SB1, $751,900 is provided by Measure M, $858,071 is provided by Metro, and $1,100 is provided by the Public Works Trust Fund.

Council District 8, Western Ave between Exposition Blvd and MLK Jr. Blvd. 08/2018 12/2019 20 30 59 30

Los Angeles Los Angeles Safety Vision Zero - Phase 3 Road Safety Improvements Citywide - in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet to be finalized. Locations will be selected based upon priority need and resources throughout the year. 07/2018 06/2019 10 15

39, 43, 45, 46, 50, 51, 53, 54, 59, 62, 64

18, 24, 25, 26, 27, 30

Los Angeles Los Angeles Traffic Control Devices Vision Zero Traffic Signals (17-18 Ongoing) Traffic Signals to Promote Roadway Safety Citywide - in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet

to be finalized. Locations will be selected based upon priority need and resources throughout the year. 07/2018 06/2019 15 2039, 43, 45, 46, 50, 51, 53, 54, 59, 62, 64

18, 24, 25, 26, 27, 30

Los Angeles Los Angeles Safety Sepulveda Blvd Tunnel Cleaning and Maintenance

Tunnel and Roadway Safety: Scope of work includes ventilation fan system, uninterrupted power supply system, carbon monoxide sensor calibration, remote monitoring system, sump pump maintenance, and fire life alarm system training.

West LA, Council District 11, Sepulveda Blvd beneath and adjacent to runways at LAX between 105 Freeway and Century Blvd 01/2019 06/2019 1 2 62 26

Los Angeles Los Angeles Safety Sherman Way Tunnel Cleaning and Maintenance

Tunnel and Roadway Safety: Perform cleaning of the existing tunnel walls quarterly (remove graffiti and accumulated grime) using existing contractual services. Scope of work includes the existing water sump pumping system, ventilation system and electrical switchgear maintenance, carbon monoxide sensor calibration, and remote monitoring system maintenance.

San Fernando Valley, Council District 6, Sherman Way between Valjean Ave & Hayvenhurst Ave 01/2019 06/2019 1 2 46 18

Los Angeles Los Angeles Safety 2nd Street Tunnel Cleaning and Maintenance

Tunnel and Roadway Safety: Perform cleaning of the existing tunnel walls quarterly (remove graffiti and accumulated grime) using existing contractual services. Additional maintenance work to complement recent replacement of four ventilation fans and installation of Carbon Monoxide sensors.

Downtown LA, Council District 1, 2nd Street between Figueroa St & Beaudry Ave 01/2019 06/2019 1 2 53 24

Los Angeles Los Angeles Safety 3rd Street Tunnel Cleaning and Maintenance

Tunnel and Roadway Safety: Perform cleaning of the existing tunnel walls quarterly (remove graffiti and accumulated grime) using existing contractual services. Additional work to complement recent upgrades to ventilation system by providing regular maintenance and service to Carbon Monoxide sensors, the ventilation system, and other electrical components.

Downtown LA, Council District 1, 3rd Street between Figueroa St & Beaudry Ave 01/2019 06/2019 1 2 53 24

Los Angeles Los Angeles SafetyTunnel and Underpass lighting Improvement Program (TULIP) (17-18 Ongoing)

This project will convert existing high intensity discharge lamps to LED's at approximately 100 tunnels and underpasses within the City. The new lighting will improve visibility and safety for motorists and pedestrians while reducing energy use.

Existing tunnels and underpasses in the Valley, West LA, South LA, East LA and the Central City. Specific locations have yet to be finalized. Locations will be selected based upon priority need and resources throughout the year.

10/2017 06/2019 15 1539, 43, 45, 46, 50, 51, 53, 54, 59, 62, 64

18, 24, 25, 26, 27, 30

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 34: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Angeles Los Angeles Road Maintenance & Rehabilitation

Sunset Bl. Phase 1, Class 3 Remedial Slope (17-18 Ongoing)

This project repairs an unstable cut slope by constructing approximately 200 linear feet of shotcrete wall with soil-nail anchors. $410,000 is funded by SB1, $785,489 is funded by Measure M Local Return Fund, and $1,223,349 is funded by Gas Tax.

Council District 13: Sunset Blvd, Coronado Ter to Waterloo St 01/2018 06/2019 20 30 51 24

Los Angeles Los Angeles Safety Lower Grand Tunnel Lighting Improvement (17-18 Ongoing)

Replace existing high voltage series street lighting system with a low voltage system Approximately 170 fixtures will be replaced with new LED fixtures. This project will result in a more reliable system that will raise lighting levels to increase visibility and reduce energy use and to improve safety.

Council District 14: Grand Ave, 4th St. to General Thaddeus Kosciuzkow Way 01/2018 06/2019 15 20 53 30

Lynwood Los Angeles Road Maintenance & Rehabilitation Wright Road

Rehabilitation of street pavement. Removal and reconstruction of PCC concrete driveway, PCC sidewalk, PCC curb ramp, and 6" PCC curb and gutter. Includes traffic striping and markings, adjustment of manhole cover to grade, etc.

Wright Road from Fernwood Avenue to Duncan Avenue 09/2018 02/2019 20 30 63 33

Malibu Los Angeles Road Maintenance & Rehabilitation 17/18 Annual Street Maintenance This project consists of the reconstruction and maintenance of approximately 686,106

square feet of City Streets.

Major maintenance to be performed on the following streets: Paseo Portola Street, Rambla Orienta Street, Paseo Hidalgo Street, Calle Del Barco, and Seaboard Road. Minor maintenance to be performed in the Carbon Canyon, Las Flores and Big Rock neighborhoods.

07/2018 10/2018 10 20 50 27

Malibu Los Angeles Road Maintenance & Rehabilitation 18/19 Annual Street Maintenance This project consists of the reconstruction and maintenance of approximately 374,854

square feet of City streets.

Major maintenance to be performed on Morning View Drive, Boniface Drive, and Portshead Road. Minor maintenance to be performed on Cliffside Drive, Greenwater Road, Selfridge Drive, and Bison Court.

03/2019 06/2019 10 20 50 27

Manhattan Beach Los Angeles Road Maintenance & Rehabilitation

Marine Avenue from Sepulveda Boulevard to Aviation Blvd Street Resurfacing

Resurfacing asphalt pavement utilizing cold-in-place recycling, capping roadway with hot mix rubberized asphalt and curb ramp upgrades at street intersections. Marine Avenue between Sepulveda Boulevard and Aviation Boulevard in Manhattan Beach 11/2018 04/2019 20 25 66 26

Maywood Los Angeles Road Maintenance & Rehabilitation Slauson Avenue Improvement Grind and Overlay. Slauson Avenue from Atlantic Boulevard to the east City border. 06/2018 07/2018 10 20 63 33

Monrovia Los Angeles Traffic Control Devices Traffic Signal Master PlanThis project involves developing an inventory of current Traffic Signal Devices and determining the condition of the assets with recommended repairs and necessary upgrades.

39 Signalized Intersections that are owned and maintained by the City of Monrovia. A complete list is attached and they are primarily located along the major thoroughfares including: Duarte Road, Foothill Boulevard, Huntington Drive, Mountain Avenue, Myrtle Avenue, and Royal Oaks Drive.

07/2018 03/2019 5 5 41 25

Monrovia Los Angeles Safety Roadway Striping Improvements This project involves the replacement of Traffic Markings throughout the City as needed.

S/E Section: 26 Streets bound by: Colorado Blvd to the North, I-210 to the South, Myrtle Ave to the West and the Easterly City Limit. N/W Section: 24 Streets bound by: Colorado Blvd to the South, Hillcrest Blvd to the North, Myrtle Ave to the East, and the Westerly City Limit. Crosswalk and Legend Striping at +/- 50 Crosswalks throuhgout the City.

07/2018 09/2018 1 2 41 25

Monrovia Los Angeles Safety Foothill Blvd Traffic Sign Replacement This project involves upgrades/replacement of all traffic signs along Foothill Blvd. The project is located along Foothill Blvd., from the west City limit (5th Ave.) to Mountain Ave. 07/2017 07/2018 15 15 41 25

Monrovia Los Angeles Road Maintenance & Rehabilitation National Bridge Repairs The project involves maintenance activities to the bridges within the City, including

resurfacing and deck treating improvements.There are three bridges within this program and they include: Duarte Road over Sawpit Wash, E. Evergreen Avenue over Sawpit Wash, and Duarte Road over Santa Anita Wash 07/2018 06/2019 3 5 41 25

Monrovia Los Angeles Traffic Control Devices Huntington Drive Traffic Sign Replacement This project involves upgrades/replacement of all traffic signs along Huntington Drive. Along Huntington Drive from the west City limit (5th Ave) to Mountain Avenue. 03/2019 06/2019 5 15 41 25

Monrovia Los Angeles Road Maintenance & Rehabilitation

Cleaning of Storm Drain Trash Screens

This project involves the removal of trash from storm water catch basins that invert along City roadways. There are approximately 500 catch basins that would be cleaned as part of this project.

Approximately 500 catch basins that are owned either by the City of Monrovia or the County of Los Angeles and are located throughout the City. A complete map has been provided for review. 07/2018 06/2019 1 1 41 25

Monrovia Los Angeles Road Maintenance & Rehabilitation Huntington Drive Phase II Project

Huntington Drive Phase II is a pavement rehabilitation and traffic signal improvement project funded through STPL Funds. This specific expense is for the City's share of inspection and project management costs. Total Project Estimate is $2,000,000

The project location is Huntington Drive between Magnolia Ave. and Shamrock Ave. 02/2019 06/2019 5 15 41 25

Monrovia Los Angeles Safety HSIP Project

The Highway Safety Improvement Program (HSIP) is a project that aims at adding additional traffic signals, roadway striping, and traffic signage to enhance pedestrian safety. This specific expense is for the City's share of inspection and project management costs. Project estimate is $750,000.

The project impacts three identified intersections within the City: (1) Foothill/California; (2) Foothill/Sunset; and (3) Huntington/5th. 01/2019 06/2019 5 25 41 25

Montebello Los Angeles Road Maintenance & Rehabilitation

Beach Street (Street Improvement #1 - Pre-Construction)

Preliminary engineering/design, construction management, inspection services related to this street improvement project (street pavement, sidewalks, etc). Beach Street from 3rd Street to Vail Avenue (City of Montebello) 09/2018 11/2018 15 20 58 32

Montebello Los Angeles Complete Streets Components

Montebello Blvd ATP Project - Design (17/18 Ongoing)

The City will conduct the preliminary engineering, design, construction management and inspection services for Montebello Blvd ATP Project (Lincoln to Paramount) which will include dedicated bike lanes and pedestrian improvements (sidewalks, crosswalks and lighting), pavement repairs, new drought-tolerant landscaped median and trees that will allow for storm water capturing, bus stop improvements, and many other complete and green street features.

Montebello Blvd ATP Project (Lincoln to Paramount) 07/2018 12/2018 15 20 58 32

Montebello Los Angeles Road Maintenance & Rehabilitation

Beach Street (Street Improvement #2 - Construction)

Construction and repairs of deteriorated asphalt pavement, damaged concrete (sidewalks, driveways, ADA ramps, curb & gutter, pavement markings, signage, traffic signal improvements, parkway trees, etc.

Beach Street from 3rd Street to Vail Avenue (City of Montebello) 02/2019 05/2019 15 20 58 32

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 35: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Monterey Park Los Angeles Road Maintenance & Rehabilitation Various Street Resurfacing

Cold mill asphalt concrete pavement and construct rubberized asphalt concrete overlay on various local streets. Work includes but is not limited to grind, overlay, and replacement of curb ramps.

Chandler Ave - Newmark Ave to Graves Ave, Crest Vista Dr - Wandering St to Crest Way (17/18 Carryover), De la Fuente St - Cadiz St to Harding Ave (17/18 Carryover), Fulton Ave - Kempton Ave (N) to Kempton Ave (S) (17/18 Carryover), Keller St - Kempton Ave to Fulton Ave (17/18 Carryover), Mabel Ave - Marguerita Ave to Atlantic Ave (17/18 Carryover), Marguerita Ave - Garvey Ave to Newmark Ave (17/18 Carryover), McPherrin Ave - Hellman Ave to Emerson Ave (17/18 Carryover), McPherrin Ave - Newmark Ave to Graves Ave, Mooney Dr - Orange Ave to East City Limit (17/18 Carryover), Moore Ave - Newmark Ave to Harding Ave (17/18 Carryover), Schoolside Ave - Cesar Chavez Ave to 1st St, Vancouver Ave - Floral Dr to Cesar Chavez Ave, Wilcox Ave - El Repetto Dr to Keller St (17/18 Carryover), Wilcox Ave - Pomona Dr to Aldergate St (17/18 Carryover)

12/2018 06/2019 15 20 49 22

Norwalk Los Angeles Road Maintenance & Rehabilitation Local Streets Cycle 2 Local Street Pavement Rehabilitation

400 miles of sidewalks and curb & gutter; 187 miles of asphalt patching and pothole repair; maintenance of alleys, City owned lots, commercial sidewalks, cul-de-sacs, culverts, drain and drainage channels, dead-ends, hillsides, parkways, and slot flows

01/2019 09/2019 10 15 57, 58 32

Norwalk Los Angeles Road Maintenance & Rehabilitation Local Streets Cycle 2 rehab local streets

400 miles of sidewalks and curb & gutter; 187 miles of asphalt patching and pothole repair; maintenance of alleys, City owned lots, commercial sidewalks, cul-de-sacs, culverts, drain and drainage channels, dead-ends, hillsides, parkways, and slot flows

01/2019 09/2019 10 15 57, 58 32

Palmdale Los Angeles Road Maintenance & Rehabilitation

Avenue R Reconstruction and Overlay (5th East to Tierra Subida

Design and construction of Avenue R from 5th East to Tierra Subida, approximately 420,000 square feet of roadway Avenue R from 5th Street East to Tierra Subida Avenue 08/2018 08/2019 10 20 36 21

Palmdale Los Angeles Road Maintenance & Rehabilitation

Avenue R-8 Reconstruction and Overlay (30th East to 40th East)

Design and construction of Avenue R-8 from 30th East to 40th East to provide reconstruction and overlay, approximately, 316,000 square feet Avenue R-8 from 30th East to 40th East 09/2018 09/2019 10 20 36 21

Palmdale Los Angeles Road Maintenance & Rehabilitation

30th Street West Overlay (Rancho Vista Blvd to P-8/Highland Avenue)

Overlay of 30th Street West from Rancho Vista Blvd to Avenue P-8/Highland Avenue to 25th Street West approximately 316,000 square feet 30th Street West from Rancho Vista Blvd to 25th West 06/2019 09/2019 10 20 36 21

Palmdale Los Angeles Safety Division Street & Rancho Vista Blvd. Traffic Signal Design and construction of a traffic signal at Division Street and Rancho Vista Blvd. Intersection of Division Street and Rancho Vista Blvd. 01/2019 12/2019 15 30 36 21

Palmdale Los Angeles Road Maintenance & Rehabilitation

2018-19 Cape Seal/Slurry Resurfacing Program

2018-19 Cape Seal/Slurry Seal Resurfacing Program. A total of 2,180,000 square feet split into 8 different neighborhoods.

Neighborhood 1 - Rancho Vista Blvd to the southwest, Towncenter Dr to the northwest, and the tract boundary to the east Neighborhood 2 - bounded by tract boundaries to the west, Avenue R-4 to the north, Avenue R-8 to the south, and 25th St East to the east Neighborhood 3 - bounded by tract boundaries to the west, Avenue R-4 to the north, Avenue R-8 tothe south, and 25th St East to the east

Neighborhood 4 - bounded by Division St to the east, tract boundary to the north, south, and west Neighborhood 5 - bounded by Division St to the west & south, tract boundary n/o East Avenue R-2 to the north, 3rd St East and Kimberly Ln to the east Neighborhood 6 - Bounded by a tract boundary n/o East Avenue R-4 to the north, 5th St East to the east, 3rd St East / Kimberly Ln to the west, and East Avenue R-8 to the south Neighborhood 7 - bound by 20th St East to the west, Avenue R-4 to the north, Avenue R-8 to the south, and tract boundary to the east(possibly include Avenue R-4 cape seal from 20th St East to 25th St East Neighborhood 8 - bounded by Avenue R to the north, 45th St East to the west, 47th St East to the east, and a tract boundary s/o Avenue R-8 to the south

04/2019 10/2019 5 8 36 31

Palmdale Los Angeles Road Maintenance & Rehabilitation

2018-19 Overlay Resurfacing Program 2018-19 Overlay Resurfacing Program

25th St East, from Avenue S to Palmdale Blvd 35th St East, from Avenue S south to Desert Oak Dr (rr trax) East Avenue Q-8, from 5th St West to Wakefield Pl Bolz Ranch Rd, from Avenue N-8 to Towncenter

06/2019 10/2019 10 20 36 21

Palmdale Los Angeles Road Maintenance & Rehabilitation

2017/18 Cape Seal & Slurry Seal (Ongoing)

2017/18 Cape Seal & Slurry Seal project throughout the City of Palmdale. 3,626,000 square feet of cape seal and 900,000 square feet of slurry.

Neighborhood 1 - bounded by Peonza Lane to Towncenter/ Concina Lane to Portola Drive., Neighborhood 2 - bounded by TownCenter to Avenue O-8/Heathrow Drive to Vicker Way, Neighborhood 3 - bounded by Kimberly Lan to Larchwood Drive/Ave R-8 to Ave R-12, Neighborhood 4 - bounded by 20th East to 25th East/Ave R-8 to Ave S, Neighborhood 5 - bounded by Ave R to Ave R-8/47th East to 55th East, Neighborhood 6 - Palmdale Blvd to Monaco Lane/50th East to 55th East

04/2018 09/2018 5 8 36 21

Palos Verdes Estates Los Angeles Road Maintenance & Rehabilitation

FY 2017-2018 ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017 (SB1)

This project consists of resurfacing a portion of Palos Verdes Drive West and will include the replacement of damaged or curb, gutter, sidewalks and curb ramps. Both sides of Palos Verdes Drive West (between Via Coronel/Cloyden to the South City Limit). 08/2018 09/2018 10 20 66 26

Paramount Los Angeles Road Maintenance & Rehabilitation

Neighborhood Street Resurfacing FY19 Grind and resurface with Rubberizes Asphalt

San Juan St. - Orange Ave. to El Camino Ave. (carryover 2017-18, est. completion 9/18), San Miguel St. - (carryover 2017-18, est. completion 9/18), El Camino Ave. - San Carlos St. to Somerset Blvd. (carryover 2017-18, est. completion 9/18), San Juan St. - El Camino Ave. to Dills Pk., San Miguel St. - El Camino Ave. to Dills Pk., San Vicente St. - Orange Ave. to Dills Pk., San Mateo Ave. - San Marino St. to Dills Pk., San Marcus St. - San Marino St. to Dills Pk., San Luis St. - San Marino St. to San Vicente St. , San Antonio Ave. - San Luis St. to San Vicente St., San Jose St. - San Luis St. to San Vicente St. , Marcelle St. - Ansmith Ave. to Gundry Ave., Motz St. - Hunsaker Ave. to Gundry Ave., Ansmith Ave. - 72nd St. to Motz St., Gundry Ave. - Jackson St. to Alondra Blvd.

02/2019 06/2019 20 25 63 33

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 36: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pasadena Los Angeles Road Maintenance & Rehabilitation

Resurfacing and Slurry Seal FY 2017 - 2019

This project will resurface 1.7 miles of City of Pasadena streets utilizing rubberized asphalt. This method is a noise reducing pavement material that consists of regular asphalt concrete mixed with crumb rubber made from recycled tires. This sustainable paving practice diverts tires from the waste stream. The project has the capacity to divert over 5,800 tires from landfills, while also reducing noise, resisting cracking, lasting longer, providing better skid resistance, retaining a dark color longer, and providing contrast to pavement markings.

Cypress Avenue from Cypress Way to Blake Street; Elizabeth Street from El Molino Avenue to Catalina Avenue; Gordon Terrace from Waverly Street to Bellevue Avenue; Grandview Street from Raymond Avenue to Garfield Avenue; Las Lunas Street from Palo Verde Avenue to Sinaloa Avenue; Pine Bluff Drive from Riviera Circle to Riviera Drive; Sierra Bonita Lane from Sierra Bonita lane to East End; Sunnyslope Avenue from Paloma Street to Hermanos Street; Verde Street from Oak Avenue to Craig Avenue.

06/2018 03/2019 15 15 41 25

Pasadena Los Angeles Traffic Control Devices Traffic Signal at Garfield Avenue and Washington Boulevard

This project provides for the installation of a traffic signal at the intersection of Garfield Avenue and Washington Boulevard. Intersection of Garfield Avenue and Washington Boulevard 12/2018 05/2019 30 30 41 25

Pasadena Los Angeles Road Maintenance & Rehabilitation

Annual Citywide Street and ADA Improvement Program

This project will resurface 3.4 miles of City of Pasadena streets utilizing rubberized asphalt. This method is a noise reducing pavement material that consists of regular asphalt concrete mixed with crumb rubber made from recycled tires. This sustainable paving practice diverts tires from the waste stream. The project has the capacity to divert over 11,600 tires from landfills, while also reducing noise, resisting cracking, lasting longer, providing better skid resistance, retaining a dark color longer, and providing contrast to pavement markings.

Adler Lane from Riviera Drive to Hastings Ranch Drive; Arroyo Boulevard from California Boulevard to Grand Avenue; Brigden Road from Allen Avenue to Altadena Drive; Claremont Street from Raymond Avenue to Garfield Avenue; Cliff Drive from Greenhill Road to Rim Road; Greenhill Road from Hastings Ranch Drive to Michillinda Avenue; Oakland Avenue from Del Mar Avenue to California Boulevard; Paloma Street from Hill Avenue to Allen Avenue; and Paloma Street from Craig Avenue to Canyon Wash Drive.

03/2019 08/2019 15 15 41 25

Pico Rivera Los Angeles Road Maintenance & Rehabilitation

Telegraph Road Traffic Througthput and Safety Enhancement Project - Phase II (17/18 Carryover)

Grind and Overlay Project Telegraph Road from Passons Boulevard to East City Limit and Telegraph Road from Manzanar Avenue to West City Limit 06/2018 06/2019 10 20 58 32

Pomona Los Angeles Road Maintenance & Rehabilitation

Street Preservation - Local Citywide (FY18-19)

Street preservation of local streets Citywide , according to pavement management program, focused primarily on slurry seals, cape seals, and thin overlays.

Arroyo Avenue (Fairplex Drive to Dudley Street), Twelfth Street (Hamilton Blvd to Park Ave), Franklin Ave (Palomares St to Towne Ave), Columbia Avenue (Washington Ave to Sheridan Ave), Alvarado Street (Loranne Ave to Sheridan Ave), Grand Avenue (Butterfield Rd to Dudley St), Palmer Street (Butterfield Rd to Dudley St), Mc Comas Street (Butterfield Rd to Dudley St), Canyon Way ( Hillcrest Dr to El Paraiso Dr), Canyon Way (Hillcrest Dr to Hillcrest Dr), La Verne Avenue (Los Flores St to Mountain Ave)

04/2019 12/2019 2 20 52 20

Pomona Los Angeles Road Maintenance & Rehabilitation

Contracted Asphalt and Concrete Repair Services

On-call as-needed asphalt, and concrete repairs for streets, sidewalks, curb and gutters)

Citywide- All Streets: Citywide - All City Streets:Abbey Lane, Abbot Street, Acacia Street, Academy Avenue, Adobe Lane, Adams Street, Airshire Lane, Alameda Street, Albert Avenue, Albona Place, Alcott Avenue, Alldama Avenue, Alder Street, Alderberry Lane, Aldis Street, Alicante Street, Alicia Court, Aliso Street, Alpline Street, Alta Drive, Alta Mira Place, AltaVista Drive, Altura Court, Alvarado Street,Amer Oaks Court, Amberson Street, American Avenue, Anderwood Court, Angela Street, Ann Arbor Avenue, Annandale Way, Anne Place, Appian Way, Appleton Way, Aralia Drive, Arboleda Way, Arbor Way, Arcana Court, Archwood Drive, Armour Street, Arrow Highway, Arroyo Avenue, Arroyo Drive, Arroyo Park Drive, Artesia Street, Arthur Avenue, Aruba Court, Asbury Avenue, Ashbrook Lane, Ashfield Avenue, Ashport Street, Aspen Lane, Aston Avenue. Atlantic AStreet, Augusta Street, Auto Center Drive, Avalon Avenue, Avenidas Rancheros, Azalea Drive, Bainbridge Street, Balboa Street, Baldwin Avenue, Baldy View, Ballerina Place, Balsam Drive, Bangor Street, Barbara Lane, Barclay Court, Bardley Court, Barjud Avenue, Barhill Avenue, Barry Avenue, Battram Street, Baudin Street, Bayport Court, Baywood Avenue, Bear Valley Road, Beaver Court, Beckford Way, Beechnut Place, Belfort Avenue, Belinda Avenue, Bella Vista Way, Bellevue Avenue, Benedict Way, Berkeley Avenue, Berkshire Way, Berrian Street, Biarritz, Biscay Way, Blackbird Lane, Blacksmith Court, Black Oak Drive, Blakely Court, Bluegrass Place, Blueridge Lane, Blueridge Drive, Bluff Point Court, Bobolink Way, Bolivar Street, Bonanza Court, Bonita Avenue, Bonnie Brae Street, Boston Place, Bougainvilla Avenue, Boyd Place, Bradford Street, Brea Place, Brea Canyon Road, Brentwood Street, Breon Street, Brewster Drive, Briarwood Lane, Brookmont Lane, Brookside Lane, Brookwin Drive, Brownfield Lane, Browning Avenue, Buchanan Drive, Buena Vista Avenue, Buffington Street, Burdick Drive, Burlington Place, Burma Court, Butterfield Road, Byron Court, Cadillac Drive, Catalina Drive, California Place, Calle De Cabos, Calle De Oro, Calle De Rodeo, Calle Del Mar, Calle Del Rey, CAlle Del Sol, Calle Las Palmas, Calpine Court, Cambrin Road, Camellia Court, Cameo Court, Cameron Avenue, Camerota Avenue, Camino Del Milagro, Camphor Place, Canfield Avenue, South Campus Drive, Canoga Place, Canyon Oak Circle, Canyon Rim Road, Canyon Way, Cantara Street, Canterbury Avenue, Capper Avenue, Caprino Way, Cardiff Court, Carlton Avenue, Carmanita Avenue, Carmel Court, Carnegie Avenue, Carrione Court, Carol Drive, Carrotwood Lane, Carolann Street, Carriage Way, Carruthers Court, Carson Lane, Cary Lane, Casa Hermosa Drive, Casa Vista Drive, Caslon Court, Castera Place, Castle Place, Caswell Avenue, Caswell Street Catalpa Place Catalina Drive, Cathedral Way, Cathy Avenue, Cedarwood Drive, Celia Street, Center Street, Chadwick Court, Chanslor Street, Chaparral Drive, Charles Way, Chelsa Drive, Cherry Way, Chester Place, Chestnut place, Christina Court, Cimarron Place, Cinderella Way, Cindy Court, Citron Place, Citrus Place, Claire Place, Claremont Place, Clark Avenue, Cleveland Street, Cleveland Place, Cloverdale Drive, Clovis Court, Club Drive, Cobre Court, Colfax Court, Cobblestone Lane, College Avenue, Collingwood Drive, Colmar Street, Colony Drive, Columbia Avenue, Comanche Circle, Commercial Street, Como Drive, Concord Avenue, Copper Canyon Circle, Cordova Street, Corinthian Way, Cornelia Street, Corporate Center Drive, Cottontail Drive, Cottonwood Place, Country Mile Road, Country Ridge Road, Country Wood Drive, County Road, Cove Crest Way, Crabapple Drive, Crest Way, Cresthaven Lane, Cresthaven Way, Crest View Place, Crimson Way, Cromwell Street, Crystal Place, Culver Court, Curran Place, Currier Street, Curtis Court, Cynthia Street, Cypress Street, Dalton Court, Darby

07/2018 07/2018 2 10 52 20

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 37: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pomona Los Angeles Road Maintenance & Rehabilitation

Annual Roadway Landscape Safety Maintenance

Routine maintenance including mowing, weed control, pest control, irrigation, debris, trash removal, maintenance and trimming of trees, shrubs and ground covers within the right-of-way. This maintenance as is defined as the preservation and upkeep of a street or road construction condition, and the operation of a street or road facility and its integral services to provide safe, convenient and economical highway transportation.

1. Albona Place 2. Alvarado Park Avenue (small median in the center of the street, 3. Arrow Highway (between Fulton Road and eastern Pomona City limits), 4. Arrow Highway (between Orange Grove Avenue and Mountain Avenue, 5. Berkshire Street (Garey Avenue/Queen Anne and Berkshire), 6. Burdick Street and White Avenue (northwest corner by the off-ramp), 7. Dudley Hansen Edison (between Ninth Street and Phillips Drive), 8. Fairplex Drive and Holt Avenue (northwest section), 9. Fourth Street (between Park Avenue and Main Street), 10. Garey Avenue (between Harrison Street and Bonita Avenue), 11. Garey Avenue (between SR71 and Ninth Street), 12. Holt Avenue (between Mission Blvd and Pomona Blvd.), 13. Huntington Boulevard (between Holt Avenue and Burdick Drive), 14. Mission Boulevard (between East End Ave and Pomona City Limits), 15. Mission Boulevard (between Human Way and Dudley Street), 16. Mission Boulevard (Mission Boulevard and Curran Place), 17. Mission Boulevard (Temple Avenue to Humane Way), 18. Mission 71 (Butterfield Street to Brea Canyon Road), 19. Murchison Street (Dudley Street to dead end -westbound), 20. Producer Way, 21. San Bernardino Avenue (between Bonnie Brae Street and Baldy View Avenue), 22. Temple Avenue (between Mission Blvd. and Valley Blvd.), 23. Towne Avenue (between County Road and Riverside Drive), 24. Towne Avenue/San Antonio Street Median, 25. University Corporate Center (between 57/71 Freeway sand South Campus Drive), 26, Fairplex Drive (between Holt Ave. and McKinley), 27. Holt Avenue (between Indian Hill Blvd. and Pomona City Limits), 28. Holt Avenue Median (east and west of Fairplex Drive), 29. Rio Rancho Road/Auto Center Drive Rancho Valley Drive/Access Road/Lexington Ave, 30. Rio Rancho Road )Garey Avenue to SR71, 31. Towne Avenue(between San Bernardino Freeway and Foothill Boulevard), 32. White Avenue (between San Bernardino Freeway and La Verne City Limits, 33. Garey Avenue (Aliso to Foothill Blvd)

07/2018 07/2018 1 2 52 20

Pomona Los Angeles Traffic Control Devices Traffic Signal and Street Light - Asset Managment System

Inventory compilation of all city-owned lights, traffic signals, street signs and posts to integrate into a Geographic Information System to feed into a new work-order system.

Citywide- All Streets: Citywide - All City Streets:Abbey Lane, Abbot Street, Acacia Street, Academy Avenue, Adobe Lane, Adams Street, Airshire Lane, Alameda Street, Albert Avenue, Albona Place, Alcott Avenue, Alldama Avenue, Alder Street, Alderberry Lane, Aldis Street, Alicante Street, Alicia Court, Aliso Street, Alpline Street, Alta Drive, Alta Mira Place, AltaVista Drive, Altura Court, Alvarado Street,Amer Oaks Court, Amberson Street, American Avenue, Anderwood Court, Angela Street, Ann Arbor Avenue, Annandale Way, Anne Place, Appian Way, Appleton Way, Aralia Drive, Arboleda Way, Arbor Way, Arcana Court, Archwood Drive, Armour Street, Arrow Highway, Arroyo Avenue, Arroyo Drive, Arroyo Park Drive, Artesia Street, Arthur Avenue, Aruba Court, Asbury Avenue, Ashbrook Lane, Ashfield Avenue, Ashport Street, Aspen Lane, Aston Avenue. Atlantic AStreet, Augusta Street, Auto Center Drive, Avalon Avenue, Avenidas Rancheros, Azalea Drive, Bainbridge Street, Balboa Street, Baldwin Avenue, Baldy View, Ballerina Place, Balsam Drive, Bangor Street, Barbara Lane, Barclay Court, Bardley Court, Barjud Avenue, Barhill Avenue, Barry Avenue, Battram Street, Baudin Street, Bayport Court, Baywood Avenue, Bear Valley Road, Beaver Court, Beckford Way, Beechnut Place, Belfort Avenue, Belinda Avenue, Bella Vista Way, Bellevue Avenue, Benedict Way, Berkeley Avenue, Berkshire Way, Berrian Street, Biarritz, Biscay Way, Blackbird Lane, Blacksmith Court, Black Oak Drive, Blakely Court, Bluegrass Place, Blueridge Lane, Blueridge Drive, Bluff Point Court, Bobolink Way, Bolivar Street, Bonanza Court, Bonita Avenue, Bonnie Brae Street, Boston Place, Bougainvilla Avenue, Boyd Place, Bradford Street, Brea Place, Brea Canyon Road, Brentwood Street, Breon Street, Brewster Drive, Briarwood Lane, Brookmont Lane, Brookside Lane, Brookwin Drive, Brownfield Lane, Browning Avenue, Buchanan Drive, Buena Vista Avenue, Buffington Street, Burdick Drive, Burlington Place, Burma Court, Butterfield Road, Byron Court, Cadillac Drive, Catalina Drive, California Place, Calle De Cabos, Calle De Oro, Calle De Rodeo, Calle Del Mar, Calle Del Rey, CAlle Del Sol, Calle Las Palmas, Calpine Court, Cambrin Road, Camellia Court, Cameo Court, Cameron Avenue, Camerota Avenue, Camino Del Milagro, Camphor Place, Canfield Avenue, South Campus Drive, Canoga Place, Canyon Oak Circle, Canyon Rim Road, Canyon Way, Cantara Street, Canterbury Avenue, Capper Avenue, Caprino Way, Cardiff Court, Carlton Avenue, Carmanita Avenue, Carmel Court, Carnegie Avenue, Carrione Court, Carol Drive, Carrotwood Lane, Carolann Street, Carriage Way, Carruthers Court, Carson Lane, Cary Lane, Casa Hermosa Drive, Casa Vista Drive, Caslon Court, Castera Place, Castle Place, Caswell Avenue, Caswell Street Catalpa Place Catalina Drive, Cathedral Way, Cathy Avenue, Cedarwood Drive, Celia Street, Center Street, Chadwick Court, Chanslor Street, Chaparral Drive, Charles Way, Chelsa Drive, Cherry Way, Chester Place, Chestnut place, Christina Court, Cimarron Place, Cinderella Way, Cindy Court, Citron Place, Citrus Place, Claire Place, Claremont Place, Clark Avenue, Cleveland Street, Cleveland Place, Cloverdale Drive, Clovis Court, Club Drive, Cobre Court, Colfax Court, Cobblestone Lane, College Avenue, Collingwood Drive, Colmar Street, Colony Drive, Columbia Avenue, Comanche Circle, Commercial Street, Como Drive, Concord Avenue, Copper Canyon Circle, Cordova Street, Corinthian Way, Cornelia Street, Corporate Center Drive, Cottontail Drive, Cottonwood Place, Country Mile Road, Country Ridge Road, Country Wood Drive, County Road, Cove Crest Way, Crabapple Drive, Crest Way, Cresthaven Lane, Cresthaven Way, Crest View Place, Crimson Way, Cromwell Street, Crystal Place, Culver Court, Curran Place, Currier Street, Curtis Court, Cynthia Street, Cypress Street, Dalton Court, Darby

07/2018 07/2018 1 10 52 20

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 38: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pomona Los Angeles Complete Streets Components

SB1 Program Compliance and Project Advancement Workforce

Partial salaries to be used towards the increase of staff dedicated to perform work on the advancement of and compliance with RMRA SB-1 relation projects. Work to be performed in the following areas for RMRA SB-1 Program Funds: Engineering, Public Works Onsite Inspection, Construction Management, Project Delivery and RMRA SB-1 Program Compliance.

Citywide- All Streets: Citywide - All City Streets:Abbey Lane, Abbot Street, Acacia Street, Academy Avenue, Adobe Lane, Adams Street, Airshire Lane, Alameda Street, Albert Avenue, Albona Place, Alcott Avenue, Alldama Avenue, Alder Street, Alderberry Lane, Aldis Street, Alicante Street, Alicia Court, Aliso Street, Alpline Street, Alta Drive, Alta Mira Place, AltaVista Drive, Altura Court, Alvarado Street,Amer Oaks Court, Amberson Street, American Avenue, Anderwood Court, Angela Street, Ann Arbor Avenue, Annandale Way, Anne Place, Appian Way, Appleton Way, Aralia Drive, Arboleda Way, Arbor Way, Arcana Court, Archwood Drive, Armour Street, Arrow Highway, Arroyo Avenue, Arroyo Drive, Arroyo Park Drive, Artesia Street, Arthur Avenue, Aruba Court, Asbury Avenue, Ashbrook Lane, Ashfield Avenue, Ashport Street, Aspen Lane, Aston Avenue. Atlantic AStreet, Augusta Street, Auto Center Drive, Avalon Avenue, Avenidas Rancheros, Azalea Drive, Bainbridge Street, Balboa Street, Baldwin Avenue, Baldy View, Ballerina Place, Balsam Drive, Bangor Street, Barbara Lane, Barclay Court, Bardley Court, Barjud Avenue, Barhill Avenue, Barry Avenue, Battram Street, Baudin Street, Bayport Court, Baywood Avenue, Bear Valley Road, Beaver Court, Beckford Way, Beechnut Place, Belfort Avenue, Belinda Avenue, Bella Vista Way, Bellevue Avenue, Benedict Way, Berkeley Avenue, Berkshire Way, Berrian Street, Biarritz, Biscay Way, Blackbird Lane, Blacksmith Court, Black Oak Drive, Blakely Court, Bluegrass Place, Blueridge Lane, Blueridge Drive, Bluff Point Court, Bobolink Way, Bolivar Street, Bonanza Court, Bonita Avenue, Bonnie Brae Street, Boston Place, Bougainvilla Avenue, Boyd Place, Bradford Street, Brea Place, Brea Canyon Road, Brentwood Street, Breon Street, Brewster Drive, Briarwood Lane, Brookmont Lane, Brookside Lane, Brookwin Drive, Brownfield Lane, Browning Avenue, Buchanan Drive, Buena Vista Avenue, Buffington Street, Burdick Drive, Burlington Place, Burma Court, Butterfield Road, Byron Court, Cadillac Drive, Catalina Drive, California Place, Calle De Cabos, Calle De Oro, Calle De Rodeo, Calle Del Mar, Calle Del Rey, CAlle Del Sol, Calle Las Palmas, Calpine Court, Cambrin Road, Camellia Court, Cameo Court, Cameron Avenue, Camerota Avenue, Camino Del Milagro, Camphor Place, Canfield Avenue, South Campus Drive, Canoga Place, Canyon Oak Circle, Canyon Rim Road, Canyon Way, Cantara Street, Canterbury Avenue, Capper Avenue, Caprino Way, Cardiff Court, Carlton Avenue, Carmanita Avenue, Carmel Court, Carnegie Avenue, Carrione Court, Carol Drive, Carrotwood Lane, Carolann Street, Carriage Way, Carruthers Court, Carson Lane, Cary Lane, Casa Hermosa Drive, Casa Vista Drive, Caslon Court, Castera Place, Castle Place, Caswell Avenue, Caswell Street Catalpa Place Catalina Drive, Cathedral Way, Cathy Avenue, Cedarwood Drive, Celia Street, Center Street, Chadwick Court, Chanslor Street, Chaparral Drive, Charles Way, Chelsa Drive, Cherry Way, Chester Place, Chestnut place, Christina Court, Cimarron Place, Cinderella Way, Cindy Court, Citron Place, Citrus Place, Claire Place, Claremont Place, Clark Avenue, Cleveland Street, Cleveland Place, Cloverdale Drive, Clovis Court, Club Drive, Cobre Court, Colfax Court, Cobblestone Lane, College Avenue, Collingwood Drive, Colmar Street, Colony Drive, Columbia Avenue, Comanche Circle, Commercial Street, Como Drive, Concord Avenue, Copper Canyon Circle, Cordova Street, Corinthian Way, Cornelia Street, Corporate Center Drive, Cottontail Drive, Cottonwood Place, Country Mile Road, Country Ridge Road, Country Wood Drive, County Road, Cove Crest Way, Crabapple Drive, Crest Way, Cresthaven Lane, Cresthaven Way, Crest View Place, Crimson Way, Cromwell Street, Crystal Place, Culver Court, Curran Place, Currier Street, Curtis Court, Cynthia Street, Cypress Street, Dalton Court, Darby

07/2018 07/2018 1 10 52 20

Pomona Los Angeles Road Maintenance & Rehabilitation

Street Preservation-Local Citywide (FY17-18) Project No. 428-68558 (17/18 Ongoing)

Street Preservation of local streets Citywide, according to pavement management program, focused primary on slurry seals, cape seals, and thin overlays. Carry Over from FY 17/18.

12th Street (Garey Ave to S. Town Ave), 12th Street (Garey Ave to S. Park), 7th Street (S. Hamilton Blvd to S. Buena Vista Ave), Brookwin Drive (End to N. Currier St.), Buena Vista Ave (W. Grand Ave to W. Phillips Blvd), Butterfield Rd (End to W. Phillips Blvd), Cameron Avenue (Mariposa St to Neptune St), Canfield Ave (Mariposa St. to Neptune St.) Neptune St (Canfield Ave -Cul-De-Sac), Dalton Court (Ross St. to End), Densmore Street (Lincoln Ave to Edgehill Drive), Deveron Place (Densmore St to Caprino Way), Caprino Way (Lincoln Ave to Deveron Pl), Surrey Lane ( Glen Ave to End), and Blakely Court (Lorrane Ave to End)

10/2018 10/2019 2 12 52 20

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 39: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pomona Los Angeles OtherCentralized Public Works Maintenance Tracking Database (17/18 Carryover)

Purchase and implementation of a centralized work order tracking system for maintenance and repair requests, and completion of said work for road, lighting, traffic signals and signage, and storm drain system; provide for an overall centralized database for efficient tracking of work orders, staff time, materials,etc. (Carry Over from FY 17/18) Request for Proposals to be sent out June/July 2018 - Implementation by July 2019.

Citywide- All Streets: Citywide - All City Streets:Abbey Lane, Abbot Street, Acacia Street, Academy Avenue, Adobe Lane, Adams Street, Airshire Lane, Alameda Street, Albert Avenue, Albona Place, Alcott Avenue, Alldama Avenue, Alder Street, Alderberry Lane, Aldis Street, Alicante Street, Alicia Court, Aliso Street, Alpline Street, Alta Drive, Alta Mira Place, AltaVista Drive, Altura Court, Alvarado Street,Amer Oaks Court, Amberson Street, American Avenue, Anderwood Court, Angela Street, Ann Arbor Avenue, Annandale Way, Anne Place, Appian Way, Appleton Way, Aralia Drive, Arboleda Way, Arbor Way, Arcana Court, Archwood Drive, Armour Street, Arrow Highway, Arroyo Avenue, Arroyo Drive, Arroyo Park Drive, Artesia Street, Arthur Avenue, Aruba Court, Asbury Avenue, Ashbrook Lane, Ashfield Avenue, Ashport Street, Aspen Lane, Aston Avenue. Atlantic AStreet, Augusta Street, Auto Center Drive, Avalon Avenue, Avenidas Rancheros, Azalea Drive, Bainbridge Street, Balboa Street, Baldwin Avenue, Baldy View, Ballerina Place, Balsam Drive, Bangor Street, Barbara Lane, Barclay Court, Bardley Court, Barjud Avenue, Barhill Avenue, Barry Avenue, Battram Street, Baudin Street, Bayport Court, Baywood Avenue, Bear Valley Road, Beaver Court, Beckford Way, Beechnut Place, Belfort Avenue, Belinda Avenue, Bella Vista Way, Bellevue Avenue, Benedict Way, Berkeley Avenue, Berkshire Way, Berrian Street, Biarritz, Biscay Way, Blackbird Lane, Blacksmith Court, Black Oak Drive, Blakely Court, Bluegrass Place, Blueridge Lane, Blueridge Drive, Bluff Point Court, Bobolink Way, Bolivar Street, Bonanza Court, Bonita Avenue, Bonnie Brae Street, Boston Place, Bougainvilla Avenue, Boyd Place, Bradford Street, Brea Place, Brea Canyon Road, Brentwood Street, Breon Street, Brewster Drive, Briarwood Lane, Brookmont Lane, Brookside Lane, Brookwin Drive, Brownfield Lane, Browning Avenue, Buchanan Drive, Buena Vista Avenue, Buffington Street, Burdick Drive, Burlington Place, Burma Court, Butterfield Road, Byron Court, Cadillac Drive, Catalina Drive, California Place, Calle De Cabos, Calle De Oro, Calle De Rodeo, Calle Del Mar, Calle Del Rey, CAlle Del Sol, Calle Las Palmas, Calpine Court, Cambrin Road, Camellia Court, Cameo Court, Cameron Avenue, Camerota Avenue, Camino Del Milagro, Camphor Place, Canfield Avenue, South Campus Drive, Canoga Place, Canyon Oak Circle, Canyon Rim Road, Canyon Way, Cantara Street, Canterbury Avenue, Capper Avenue, Caprino Way, Cardiff Court, Carlton Avenue, Carmanita Avenue, Carmel Court, Carnegie Avenue, Carrione Court, Carol Drive, Carrotwood Lane, Carolann Street, Carriage Way, Carruthers Court, Carson Lane, Cary Lane, Casa Hermosa Drive, Casa Vista Drive, Caslon Court, Castera Place, Castle Place, Caswell Avenue, Caswell Street Catalpa Place Catalina Drive, Cathedral Way, Cathy Avenue, Cedarwood Drive, Celia Street, Center Street, Chadwick Court, Chanslor Street, Chaparral Drive, Charles Way, Chelsa Drive, Cherry Way, Chester Place, Chestnut place, Christina Court, Cimarron Place, Cinderella Way, Cindy Court, Citron Place, Citrus Place, Claire Place, Claremont Place, Clark Avenue, Cleveland Street, Cleveland Place, Cloverdale Drive, Clovis Court, Club Drive, Cobre Court, Colfax Court, Cobblestone Lane, College Avenue, Collingwood Drive, Colmar Street, Colony Drive, Columbia Avenue, Comanche Circle, Commercial Street, Como Drive, Concord Avenue, Copper Canyon Circle, Cordova Street, Corinthian Way, Cornelia Street, Corporate Center Drive, Cottontail Drive, Cottonwood Place, Country Mile Road, Country Ridge Road, Country Wood Drive, County Road, Cove Crest Way, Crabapple Drive, Crest Way, Cresthaven Lane, Cresthaven Way, Crest View Place, Crimson Way, Cromwell Street, Crystal Place, Culver Court, Curran Place, Currier Street, Curtis Court, Cynthia Street, Cypress Street, Dalton Court, Darby

06/2018 07/2019 10 15 52 20

Rancho Palos Verdes Los Angeles Complete Streets Components

Hawthorne Boulevard Median Beautification Project

The project will remove colored asphalt and replace median with drought-tolerant landscaping, with curb and gutter repairs Hawthorne Boulevard - From Crest Road to Crestmont Lane 11/2018 04/2019 18 22 66 26

Redondo Beach Los Angeles Road Maintenance & Rehabilitation

Residential Street Rehabilitation Project

The Residential Street Rehabilitation Project will resurface residential streets in Redondo Beach.

The project is citywide but these funds will be used to resurface the residential streets north of 190th Street in the City. 04/2019 07/2019 15 25 66 26

Redondo Beach Los Angeles Road Maintenance & Rehabilitation

North Redondo Beach Commercial Streets

The project will resurface the commercial streets in north Redondo Beach including Santa Fe, Space Park Drive, and Doolittle. Curbs and gutters will be repaired and replaced as necessary. (Adopted CIP, pg. 22)

The project will resurface the commercial streets in north Redondo Beach including Santa Fe, Space Park Drive, and Doolittle. Curbs and gutters will be repaired and replaced as necessary. (Adopted CIP, pg. 22)

06/2018 12/2018 20 30 66 26

Redondo Beach Los Angeles Road Maintenance & Rehabilitation

Manhattan Beach Boulevard Resurfacing - Aviation Boulevard to Inglewood Avenue

This section of Manhattan Beach Boulevard is approximately 1 mile long with a roadway width of 100 feet. This section is classified as a major arterial, carries approximately 38,000 vehicles daily, and includes a transit route between Aviation Boulevard and Redondo Beach Avenue.

Manhattan Beach Boulevard runs east-west and is located in north Redondo Beach. The project limits are Aviation Boulevard on the west and Inglewood Avenue on the east. 12/2018 06/2019 20 30 66 26

Rolling Hills Estates Los Angeles Road Maintenance & Rehabilitation

2018-19 Resurfacing Project on Various City Streets

Street resurfacing on various city streets, including:Bluemound Road between Willow Wood Road to Dunwood Road, Elmdale Drive between Silver Eagle Road to Kingspine Road, Kingspine Road between Silver Eagle to E. Silver Spur; Latigo Lane between Palos Verdes Drive North to Terminus, Rollingwood Drive between Silver Eagle Road to Kingspine Road, Palos Verdes Drive North Street Depression Near Lazy Creek , Hawthorne Boulevard between Palos Verdes Drive North and the south city limit

Bluemound Road between Willow Wood Road to Dunwood Road, Elmdale Drive between Silver Eagle Road to Kingspine Road, Kingspine Road between Silver Eagle to E. Silver Spur , Latigo Lane between Palos Verdes Drive North to Terminus, Rollingwood Drive between Silver Eagle Road to Kingspine Road

07/2018 10/2018 15 25 66 26

Rosemead Los Angeles Road Maintenance & Rehabilitation

Walnut Grove Resurfacing Project (17/18 Carryover)

The project consists in ARHM pavement overlay, sidewalk replacement, striping, curb ramp installation, tree planting, and appurtenances. From Northerly City Limit to Marshall Avenues 01/2019 05/2019 10 15 49 22

Rosemead Los Angeles Road Maintenance & Rehabilitation

Colored Crosswalk Installation Project

The project will install colored concreted crosswalk at four intersections. This will provide more safety to pedestrians. Mission Drive, Valley Boulevard, Marshall and Wells Street along Walnut Grove Avenue 01/2019 05/2019 10 15 49 22

San Dimas Los Angeles Road Maintenance & Rehabilitation Rennel Ave Et Al - 17/18 Carryover

Rehabilitation, resurfacing, and restoration of speed bumps. The repair work will also include upgrade/replacement of the ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping.

Rennell Avenue from Arrow Hwy to Juanita including adjacent short sul-de-sac. 04/2018 05/2018 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Covina Blvd Rehabilitation

Project will use Full Depth Reclamation technology up to 15" deep and overlay asphalt concrete . Repair and reconstruction of work will include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping. Project will require State and Railroad permits.

Covina Blvd (Arrow Hwy to 57 Fwy) 04/2020 06/2020 15 20 41 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 40: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

San Dimas Los Angeles Road Maintenance & Rehabilitation

Lone Hill Ave (Cienega to Covina Blvd)

Project will use Full Depth Reclamation technology up to 15" deep and overlay asphalt concrete . Repair and reconstruction of work will include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping.

Lone Hill Ave (Cienega to Covina Blvd) 04/2021 06/2021 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Eaton Road Et Al

Rehabilitation, resurfacing, and restoration of existing street. Repair and reconstruction will include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping.

Southwest corner of Arrow Hwy and Lone Hill Ave 04/2022 06/2022 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Bonita Avenue Corridor

Rehabilitate existing street by use of Full Depth Reclamation technology up to 15" deep and overlay asphalt concrete base and cap. Will also include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping. Project will also include grind and overlay of short adjacent cul-de-sac.

Bonita Avenue from San Dimas Avenue to eastern City Limits 04/2023 06/2023 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Arrow Highway Rehabilitation

Rehabilitation, resurfacing, and restoration of existing street. The repair work will also include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping.

Arrow Highway Western City Limits to Eastern City Limits 04/2024 06/2024 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Gladstone Street (East of Amelia)

Rehabilitation, resurfacing, and restoration of existing street. The repair work will also include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping.

Gladstone Street (East of Amelia) 04/2025 06/2025 15 20 41 25

San Dimas Los Angeles Road Maintenance & Rehabilitation Avenida Entrada Rehab

Rehabilitate existing street by using Full Depth Reclamation Technology up to 15" deep and overlay asphalt concrete base and cap. Project will also include upgrade/replacement of ADA accessible ramps, minor curb, gutter, and sidewalk panels, and striping. Project will also include grind and overlay of short adjacent cul-de-sacs.

Avenida Entrada (Via Verde to Avenida Ladera) 04/2019 06/2019 15 20 41 25

San Fernando Los Angeles Road Maintenance & Rehabilitation Annual Street Resurfacing Project

A total of four (4)streets encompass the project. The project consists of street repaving, repairs to sidewalks, drive approaches and curb and gutter, installation of access ramps and striping and pavement markings. In addition to the street improvements, water and sewer upgrades/repairs will be conducted on the aforementioned streets.

City of San Fernando:Alexander Street between Library Street and Lucas Street, N Workman Street between Glenoaks Boulevard and Seventh Street, Lazard St between Fourth Street and Glenoaks Boulevard, Lucas Street between N Workman Street and Orange Grove Avenue

10/2018 04/2019 15 20 29 17

San Gabriel Los Angeles Road Maintenance & Rehabilitation

2018 Great Street Project (17/18 Ongoing)

The scope of work includes of resurfacing local street pavement, including removing and replacing existing curb ramps in order to comply with ADA standards. Project originally listed in the 2017-18 FY Project List, with adoption of 2018-19 FY Project List the original project scope and location(s) were expanded to maximize SB1 funding.

San Marino Ave. (Longden to Las Tunas Dr.), Warner Lane (San Marino to west terminus), Oak Lane (San Marino to west terminus), Broadway (Mission Dr. to Junipero Serra), Alanmay (Broadway to Live Oak), Cresta Avenue (Las Tunas to Hermosa), Earle Street (Las Tunas to Elm), and Mission Dr. (Las Tunas to Sycamore)

05/2018 06/2018 10 15 49 22

San Marino Los Angeles Road Maintenance & Rehabilitation

Del Mar Ave Pavement Rehabilitation (17/18 Carryover) Resurface major arterial street Del Mar Ave. from city limits to Huntington Drive 01/2020 06/2020 20 20 49 25

San Marino Los Angeles Road Maintenance & Rehabilitation

Huntington Drive Pavement Rehabilitation (17/18 Carryover) Resurface major arterial street Huntington Drive WB Virginia Road to city limits 01/2021 06/2021 20 20 49 25

San Marino Los Angeles Road Maintenance & Rehabilitation

Huntington Drive Street Rehabilitation Huntington Drive Street Rehabilitation; Deep mill & fill with spot reconstruction Huntington Drive, San Marino, CA 91108 01/2019 06/2019 20 20 49 25

San Marino Los Angeles Road Maintenance & Rehabilitation Local Street Reconstruction Local Street Reconstruction: Roanoke Road, Sierra Vista Avenue, Shenandoah Road,

Canon Drive Roanoke Road, Sierra Vista Avenue, Shenandoah Road, Canon Drive 01/2019 06/2019 20 20 49 25

Santa Clarita Los Angeles Road Maintenance & Rehabilitation 2017-2018 Overlay and Slurry Seal The annual Overlay & Slurry Seal Program reflects the City's commitment to roadway

infrastructure by resurfacing streets in need of attention.

Below is a sampling of possibl locations to be improved:Soledad Canyon Road Sierra Hwy to Sand Canyon Rd; Gary Dr Megan Dr to Cop '875 S/O Megan Dr; Gary Dr Cop 875' S/O Megan Dr to Carrousel Dr; Bougainvillia Wy Rosehaven Ln to North End; Carla Ct Lillyglen Dr to East End; Flowerpark Dr Soledad Canyon Rd to Gardenia Park Dr; Flowerpark Dr Gardenia Park Dr to Lotusgarden Dr; Gladiolus Dr Nasturtium Dr to Lotus Garden Dr; Lillyglen Dr Gladiolus Dr to Poppy Meadow St; Lotusgarden Dr Nasturtium Dr to Gardenia Lane; Gina Ct End to Via Joyce Dr; Jerry Pl End to Via Joyce Dr; Leong Ct End to Santa Catarina Rd; Nicholas Cir Rodgers Dr (N) to Rodgers Dr (S); Patricia Pl End to Rodgers Dr; Ricki Ct End to Via Joyce Dr; Rhona Pl Santa Catarina Rd to end; Rodgers Dr Adriene Wy to Santa Catarina; Santa Catarina Rd Rodgers Dr to Plum Canyon; Tamara Pl End to Nicholas Cir; Werren Pl Via Joyce Rd to end; Sassoon Pl Santa catarina to end

07/2018 04/2019 3 15 38 21, 27

Santa Clarita Los Angeles Road Maintenance & Rehabilitation

2018-2019 Overlay & Slurry Seal Program

The annual Overlay & Slurry Seal Program reflects the City's commitment to roadway infrastructure by resurfacing streets in need of attention.

Copper Hill Drive from Newhall Ranch Road to Smyth Drive, McBean Parkway from 5 fwy to Singing Hills Drive, Rye Canyon Road from 5 fwy to Newhall Ranch Road, and Valencia Blvd from Magic Mountain Pkwy to Citrus Street

06/2019 04/2020 3 15 38 21, 27

Santa Fe Springs Los Angeles Road Maintenance & Rehabilitation

Santa Fe Springs Road Street Rehabilitation

Industrial street project will consist of removal of existing asphalt concrete pavement surface, reworking the underlying aggregate base and in situ soil material to provide a firm and stable platform for placing new asphalt concrete pavement. The removal and replacement of curb and gutter along with removal of sidewalk and driveways.

Between Los Nietos Road and rail road tracks (City boundary) 12/2018 06/2019 15 20 57 32

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 41: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Santa Monica Los Angeles Safety Safe Routes to School at Six Schools

Design and construction of school access and safety improvements near Edison Language Academy, SMASH, John Muir, McKinley Elementary, Grant Elementary and Franklin Elementary that were identified during Walk Audits conducted in the spring of 2017. The crossing improvements include, bulb-outs, high-visibility beacons, curb ramp improvements, signage and striping, and operational changes to these schools. The improvements also remove crossing barriers and provide improved visibility and legibility for students and parents, making active transportation more comfortable for students and their families.

Edison Language Academy-2402 Virginia Ave; SMASH-2525 5th St; John Muir-2526 6th St.; McKinley Elementary-2401 Santa Monica Blvd.; Grant Elementary-2368 Pearl St; Franklin Elementary-2400 Montana Ave

12/2018 12/2020 25 25 50 26

Santa Monica Los Angeles Road Maintenance & Rehabilitation

Citywide Annual Paving Project - Carryover FY 2017-2018

Improvements made through the Annual Paving and Sidewalk Repair Project to maintain the City's streets.

07th St, 23rd St, 26th St, Broadway, Cloverfield Bl, San Vicente Bl, 17th St, Lincoln Bl, Stanford St, Dewey St, Neilson Wy, Ocean Av, Pico Bl, Ashland Av, Pearl St. Please see attached spreadsheet for locations. All locations have yet to be finalized and are subject to change. Each location will be selected based on priority need and resources throughout the year

10/2018 10/2019 7 25 50 26

Sierra Madre Los Angeles Road Maintenance & Rehabilitation 2018-19 Street Improvement project Grind and cap, Slurry Seal, Chip Seal, Sidewalk infill and Handicap Ramps.

San Gabriel Ct. Sierra Place to Mt Trail Ave.; San Gabriel Ct. Mt Trail Ave. to Holdman Ave.; Sierra Place Sierra Madre Blvd. to Lowell Ave.; East Highland Ave. Mt. Trail Ave. to Baldwin Ave.; Merrill Ave. Laurel Ave. to Highland Ave.; Auburn Ave. Alley Montecito Ct. to end; South Mt Trail Ave. Orange Grove to Sierra Madre Blvd.; North Baldwin Ave. Sierra Madre Blvd. to end

12/2018 02/2019 7 20 41 25

Signal Hill Los Angeles Road Maintenance & Rehabilitation SB-1 RMRA 2018/19 Repair City Streets

Myrtle Avenue (1/2 Street) 33RD TO N. CITY LIMITS, LEWIS AVENUE 32ND TO N. CITY LIMITS, LEMON AVENUE S. CITY LIMITS TO NEVADA ST., CERRITOS S. CITY LIMITS TO BURNETT ST., LEMON AVENUE 32ND TO N. CITY LIMITS, BRAYTON AVENUE (1/2 STREET) 33RD TO N. CITY LIMITS, GUNDRY AVENUE 33RD TO N. CITY LIMITS, FALCON AVENUE 33RD TO N. CITY LIMITS, WALNUT AVENUE 32ND (CITY LIMIT) TO N. CITY LIMITS, 33RD ST. CALIFRONIA AVENUE TO WALNUT AVENUE, 32ND ST. CALIFORNIA AVENUE TO ORANGE AVENUE, 29TH ST. W. CITY LIMITS TO OLIVE AVENUE, COLUMBIA ST. W. CITY LIMITS TO E. LIMIT, PATERSON W. CITY LIMITS TO E. LIMIT, WALTON ST. LIME AVE TO MYRTLE ST., VERNON ST. W. CITY LIMITS TO CALIFORNIA AVENUE, 25TH ST. W. CITY LIMITS TO CALIFORNIA AVENUE, LEWIS AVENUE S. CITY LIMITS TO BURNETT ST., 23RD ST. LEMON AVENUE TO CERRITOS, DAWSON AVENUE WILLOW TO 28TH ST., 21ST ST. CHERRY TO TEMPLE, ALLIANCE ST. ALLEY TO ORANGE, BURNETT ST. ORANGE TO WALNUT, BURNETT ST. ROSE AVENUE TO CHERRY, CRESTON AVENUE WALNUT TO TERMINES, JESSE NELSON CIRCLE HILL ST. TO TERMINES, GAVIOTA AVENUE ALAMITOS AVENUE TO HILL ST. , CRESCENT ST. ROSE TO GARDENA, 20TH ST. FREEMAN TO OBISPO

01/2019 09/2019 8 12 70 33

Signal Hill Los Angeles Road Maintenance & Rehabilitation Spring Street Overlay Carryover Restore paved road surfaces to add structural capacity, riding comfort and skid

resistance which add to the road's safety. Spring Street 07/2017 06/2020 25 30 70 33

South El Monte Los Angeles Road Maintenance & Rehabilitation Alesia Street (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Alesia St. from e/s Adelia Ave. to w/s Potrero Ave. 07/2018 10/2018 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Chico Ave. (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Chico Ave. - from n/s Rush St. to s/s Fern Ave.; 03/2019 06/2019 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Elliot Ave (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Elliott Ave. – s/s from Santa Anita Ave. e/s to 460’ east. 03/2019 06/2019 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Floradale Ave. (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Floradale Ave. – 1800 blk. n/o Thienes Ave. 03/2019 06/2019 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Granada Ave. (17/18 Carryover) This project includes street seal coating over existing AC Pavement, crack sealing, and

new striping Granada Ave. – from n/s Weaver Ave. to s/s Klingerman Ave. 03/2019 06/2019 5 7 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Lashbrook Ave. (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Lashbrook Ave. – from 600ft. s/o Garvey Ave. to s/s Garvey 03/2019 06/2019 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation Klingerman Ave. (17/18 Carryover) This project includes grinding of 2” existing asphalt, install 2” A.C. overlay and install

new striping Klingerman Ave. – from 650’ w/o Potrero Ave. to w/s Potrero 03/2019 06/2019 10 15 57 22

South El Monte Los Angeles Road Maintenance & Rehabilitation

Annual Pothole Repairs (17/18 Ongoing)

This project seeks to repair potholes at the sites listed in the Project Location area. all locations are subject to change and will be selected based on priority need and resources throughout the year

Pothole repairs on the following streets:Chico between Garvey Avenue/Rust Street, Lashbrook Avenue s/o Garvey Avenue, Fawcett Avenue s/o Santa Anita Avenue, Farndon Street s/o Lidcombe Avenue, Lerma Road from Central Avenue to Strozier Avenue, Strozier Avenue to Lerma Road to Remer Street, Elliot Avenue east of Santa Anita Avenue, Santa Anita Avenue/Merced Avenue Intersection, Durfee Avenue/Thienes Intersection, Weaver Street/Mountain View Road Intersection, 2439 Loma Avenue, Farndon Street/Durfee Avenue Intersection, Klingerman Street west of Potrero Avenueall locations are subject to change and will be selected based on priority need and resources throughout the year

07/2018 06/2019 10 15 57 22

South Gate Los Angeles Complete Streets Components

Citywide Sidewalk Improvement Phase V (17/18 Ongoing)

Ongoing from FY 2017/18: The Sidewalk Improvement Project will maintain pedestrian safety a priority. Under this project, over 650 locations of damaged sidewalk, curb, gutters and access ramp around the City will be repaired to remove any potential tripping hazards.

Within the City limits: Santa Ana Street (North-side Boundary), Alameda Street (West-side Boundary), California Avenue (East-side Boundary), and Century/Martin Luther King Jr. Boulevard (South-side Boundary); approximately 40 Streets. Note: Exclude ROW from the City of Lynwood and City of Huntington Park

06/2018 05/2019 30 50 63 33

South Gate Los Angeles Complete Streets Components

Garfield Avenue and Imperial Highway Street Rehabilitaition

Rehabilitation of pavement, reconstruction of damaged curb and gutter, drive approaches, sidewalks, on Garfield Avenue from Jefferson Avenue to South City Limits. Garfield Avenue from Jefferson Avenue to South City Limits. 11/2018 10/2019 30 30 63 33

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 42: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

South Gate Los Angeles Complete Streets Components

Firestone Boulevard Regional Corridor Capacity Enhancement Project (17/18 Ongoing)

Ongoing from FY 2017/18: The Firestone Boulevard Project Boulevard contains a wide range of infrastructure improvements which includes the following: increasing the number of travel lanes from four to six, raised landscape medians, pavement rehabilitation, traffic signal and Street light modifications, traffic signal synchronization, traffic signing and striping, concrete repairs and ADA ramp improvements, storm water quality mitigation measures, pedestrian lights, bus shelters and furniture enhancements, and a signature gateway design at five major intersections. Gateway design includes public art pieces, pedestrian lighting, street furniture, and landscaping.

On Firestone Boulevard from Alameda Street to California Avenue 07/2017 06/2019 30 30 63 33

South Gate Los Angeles Complete Streets Components

Citywide Sidewalk Improvement Project Phase VI

The sidewalk Improvement Project will maintain pedestrian safety a priority. Under this project, over 600 locations of damaged sidewalk, curb, gutters and access ramp around the City will be repaired to remove any potential tripping hazards.

Within the City limits: Imperial Highway (North-side Boundary), Los Angeles River (West-side Boundary), Paramount Boulevard (East-side Boundary), and I-105 (South-side Boundary); approximately 60 Streets. Note: Exclude ROW from the City of Downey.

09/2018 06/2019 30 50 63 33

South Pasadena Los Angeles Road Maintenance & Rehabilitation Monterey Rd - Phase3

The project scope of work consists of street and highway pavement maintenance; rehabilitation, installation, construction, and reconstruction of necessary associated facilities such as drainage and traffic control devices; maintenance, rehabilitation, installation, construction, and reconstruction of facilities that expand ridership on transit systems; safety projects to reduce fatalities; or as a local match to obtain state or federal transportation funds for similar purposes.

Orange Grove Ave to Pasadena Ave 09/2018 06/2019 15 17 41 25

South Pasadena Los Angeles Road Maintenance & Rehabilitation

South Pasadena Roadway Rehabilitation Project

The project scope of work consists of street and highway pavement maintenance; rehabilitation, installation, construction, and reconstruction of necessary associated facilities such as drainage and traffic control devices; maintenance, rehabilitation, installation, construction, and reconstruction of facilities that expand ridership on transit systems; safety projects to reduce fatalities; or as a local match to obtain state or federal transportation funds for similar purposes.

Alpha Avenue, Alta Vista, Camino Del Sol, Pine Street, Monterey Rd (at City Limits), Orange Grove Avenue, Sterling Place 09/2018 06/2019 15 17 41 25

South Pasadena Los Angeles Road Maintenance & Rehabilitation

South Pasadena Streets Preventative Maintenance Program

The project scope of work consists of street and highway pavement maintenance; rehabilitation, installation, construction, and reconstruction of necessary associated facilities such as drainage and traffic control devices; maintenance, rehabilitation, installation, construction, and reconstruction of facilities that expand ridership on transit systems; safety projects to reduce fatalities; or as a local match to obtain state or federal transportation funds for similar purposes.

La France Ave, Wayne Ave, Fletcher Ave, Stratford Ave, Camden Avenue, Camden Parkway, Courte Avenue, Stratford Avenue, Hardison Lane 09/2018 06/2019 15 17 41 25

Temple City Los Angeles Road Maintenance & Rehabilitation

Rosemead Boulevard Resurfacing (17/18 Carryover) Resurfacing of about two miles of Rosemead Boulevard, a major arterial street Rosemead Boulevard from northern city limit (just north of Calita Street) to southern city limit (railroad

grade separation south of Pentland Street) 06/2018 10/2018 5 10 49 22

Temple City Los Angeles Road Maintenance & Rehabilitation Street Resurfacing Phase 5A Resurfacing of about three miles of collector and local streets with methods appropriate

for the pavement condition

Alessandro Ave. from Las Tunas Dr. to Garibaldi Ave.; Golden West Ave. from Las Tunas Dr. to Longden Ave.; Kauffman Ave. from Garibaldi Ave. to Longden Ave.; Lemon Ave. (N/S) from Longden Ave. to Northern City Limit; Lemon Ave. (E/W) from Temple City Blvd. to Eastern City Limit; Livia Ave. from Longden Ave. to Woolley St.; Longden Ave. from Oak Ave. to Eastern City Limit; Noel Dr. from Broadway to North End; Primrose Ave. from Garibaldi Ave. to Flaherty St.; Rowland Ave. from Flaherty St. to Wendon Ave.; Trelawny Ave. from South End to Lemon Ave.; Workman Ave. from Alley E/O TC Blvd. to Camellia Ave.; Workman Ave. from Oak Ave. to Cloverly Ave.

08/2018 12/2018 5 20 49 22

Torrance Los Angeles Road Maintenance & Rehabilitation

Sidewalk Repair for Handicap Accessibility - 17/18 Carryover

Localized repairs of damaged sidewalks and handicap ramps, along with associated curb and gutter repairs, driveway repairs, and tree removal and replanting. Old Torrance 06/2018 04/2019 25 50 66 26, 35

Torrance Los Angeles Road Maintenance & Rehabilitation

Sidewalk Repair for Handicap Accessibility

Localized repairs of damaged sidewalks and handicap ramps, along with associated curb and gutter repairs, driveway repairs, and tree removal and replanting.

Tentative areas of proposed sidewalk replacement include: (1) The area bounded by Sepulveda Blvd, Western Ave, south City limit and Cabrillo Ave; and (2) The area bounded by Sepulveda Blvd, Hawthorne Blvd, Lomita Blvd and Anza Ave. Specific areas and locations have yet to be finalized, but will be selected based on priority need, resources and available funding throughout the year.

09/2018 06/2019 25 50 66 26

Vernon Los Angeles Traffic Control Devices Sign Replacement Program (FY 2018-2019)

To comply with Section 2A.08 Maintaining Minimum Retroreflectivity standards required by the 2014 Edition of the California Manual on Uniform Traffic Control Devices (CAMUTCD), the City of Vernon has adopted a sign replacement program. The city has chosen to use a blanket replacement method to maintain regulatory and warning sign retroreflectivity at or above the minimum levels as directed by Table 2A-3 of the CAMUTCD.

Section 5 of the Sign Replacement Program. Northern boundary line between Soto Street and Downey Road to north side of Leonis Boulevard. West side of Downey Road to east side of Soto Street including all streets within Section 5 - 26th Street, Bandini Boulevard, Vernon Avenue, 44th Street, 45th Street, Boyle Avenue, Sierra Pine Avenue, and Alcoa Avenue.

07/2018 06/2019 10 15 53 33

Walnut Los Angeles Road Maintenance & Rehabilitation Slurry Seal Area 4 Provides for the engineering, contract administration and slurry seal of various streets

in area 4 (Westerly half of Creekside Drive). Westerly half of Creekside Drive 07/2018 06/2019 5 7 55 29

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 43: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

West Covina Los Angeles Road Maintenance & Rehabilitation Residential Street Rehabilitation Rehabilitation of pavement, replacement of damaged curb, gutter and sidewalks,

installation of catch basin insert, signing and striping.

Alicia Street from Audrey Lane to Arline Street Andrea Court from Arline Street to End of Cul-De-Sac Angela Street from Adrienne Drive to End of Cul-De-Sac Arline Street from Audrey Lane to Alicia Street Audrey Lane from Adrienne Drive to Alicia Street Betsy Street from Carmen Street to End of Cul-De-Sac Carmen Street from Cecelia Street to Cindy Street Cecelia Street from Carmen Street to Cindy Street Chance Street from Gehrig Street to Shakespeare Drive Christie Lane from Woodgate Drive to Carmen Street Cynthia Court from Amanda Street to End of Cul-De-Sac Cindy Street from Carmen Street to Cecelia Street Dee Lane from Woodgate Drive to End of Cul-De-Sac Delores Street from Elena Avenue to Dee Lane Ferntower Avenue from Hollingsworth Street to Morganfield Avenue Francesca Drive from Woodgate Drive to Nogales Street Frieda Court from Gloria Street to End of Cul-De-Sac Gabriella Street from Gloria Street to End of Cul-De-Sac Gail Court from Gabriella Street to End of Cul-De-Sac Gehrig Street from Tinker Street to Chance Street Gina Lane from Gabriella Street to Nogales Street Ginger Court from Gabriella Street to End of Cul-De-Sac Gloria Street from Gabriella Street to Beginning of Cul-De-Sac Gloria Street from Frieda Street to End of Cul-De-Sac Lindsey Court from Shakespeare Drive to End of Cul-De-Sac Maranville Court from Gehrig Street to End of Cul-De-Sac Peggy Court from Pauline Street to End of Cul-De-Sac Penny Street from Priscilla Drive to End of Cul-De-Sac Petra Court from Priscilla Drive to End of Cul-De-Sac Priscilla Drive from Shakespeare Drive to Pauline Street Tinker Street from Gehrig Street to Shakespeare Drive Thomas Place from Woodgate Drive to End of Cul-De-Sac

07/2018 08/2018 10 20 48, 55 22, 29

West Hollywood Los Angeles Road Maintenance & Rehabilitation Annual Paving Project Grind and overlay 2 inches of rubberized hot mix A.C. on 11 residential streets.

Miscellaneous work includes: Restriping, raising valve covers, ADA curb ramps, etc.

City of West Hollywood. See attached list for locations.Greenacre Ave. cul-de-sac to SMB, Spaulding between Fountain and SMB, Formosa Ave between Lexington and SMB, Vista St. between Fountain and SMB, Genesee between Fountain and SMB, Genesee between SMB and Romaine, Genesee between Romaine and Willoughby, Orange Grove between Fountain an Santa Monica, Ogden Dr between Fountain an Santa Monica, Flores St between Fountain an Santa Monica, Kings Rd. between Fountain and SMB

06/2018 07/2018 10 20 50 26

Westlake Village Los Angeles Road Maintenance & Rehabilitation Annual Street Improvement Project Overlay or Slurry of several roadways within the industrial areas of Westlake Village. Citywide Industrial Streets. RMRA funds will be used on Russel Ranch Road for full depth grind and

overlay. 07/2018 01/2019 10 25 44 27

Whittier Los Angeles Road Maintenance & Rehabilitation

Pioneer Boulevard & Vicinity Resurfacing

Resurfacing of Pioneer Boulevard from Beverly Boulevard to Orange Drive. Includes sidewalk repairs and installation of ADA wheelchair access ramps to provide safe path of travel. Includes re-striping of Class II Bike Lanes and Share the Road Sharrow Legends. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Pioneer Boulevard from Beverly Boulevard to Orange Drive. 03/2019 05/2019 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

Scott Avenue and Vicinity Resurfacing

Joint project with the County of Los Angeles County to resurface Scott Avenue from Mulberry Drive to Leffingwell Road and adjacent streets. Includes installation of ADA wheelchair access ramps and sidewalk repairs to provide safe ADA path of travel. Scott Avenue is signed as a Class III Bike Route. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Scott Avenue from Mulberry Drive to Leffingwell Road in both the City of Whittier and unincorporated Los Angeles County. 08/2018 10/2018 15 20 57 32

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 44: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Whittier Los Angeles Road Maintenance & Rehabilitation

Valley Home Avenue & Vicinity Resurfacing

Resurfacing of Valley Home Avenue from Whittier Boulevard to Janine Drive and adjacent nearby streets. This is a joint project between the City of Whittier and the City of La Habra. Project includes installation of ADA wheelchair access ramps. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Valley Home Avenue from Whittier Boulevard to Janine Drive in both the City of Whittier and the City of La Habra 08/2018 10/2018 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

Santa Fe Springs Road Resurfacing and Vicinity

Resurfacing of Santa Fe Springs Road from Mulberry Drive to Los Netos Road. Includes the installation of new Class II Bike Lanes. Joint project between the City of Whittier and the City of Santa Fe Springs. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Santa Fe Springs Road in the City of Whittier and the City of Santa Fe Springs. 08/2018 10/2018 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

College Avenue and Vicinity Resurfacing

Resurfacing of College Avenue from Penn Street to the end at the Whittier College Campus. Includes installation of ADA access ramps. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

College Avenue from Penn Street north to the end of the street at the Whittier College Campus. 04/2019 06/2019 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

Newcomb Avenue and Vicinity Resurfacing (17/18 Carryover)

Resurfacing of asphalt roadway. Carryover of project to FY 2018-19. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Newcomb Avenue from Citrustree Road to Leffingwell Road. 03/2019 06/2019 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

Lashburn Street and Vicinity Resurfacing (17/18 Carryover)

Resurfacing of asphalt roadway. Carryover of project to FY 2018-19. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Lashburn Street from First Avenue to Maybrook Avenue. 03/2019 06/2019 15 20 57 32

Whittier Los Angeles Road Maintenance & Rehabilitation

Pounds Avenue & Vicinity Resurfacing (17/18 Carryover)

Resurfacing of asphalt roadway. Carryover of project to FY 2018-19. Several of our projects encompass several streets in the vicinity of the named street limits. We may combine some of the projects listed under one contract in order to obtain more reasonable bid prices. We are trying to provide general areas were work is to be performed utilizing SB1 funds. The City of Whittier has over 220 miles of streets that it maintains and to list each and everyone that is to be worked on separately would be vary cumbersome.

Pounds Avenue from north of Lashburn Street to south of Lashburn Street. 03/2019 06/2019 15 20 57 32

Chowchilla Madera Road Maintenance & Rehabilitation 5th Street to Road 16 Project Specific improvements related to this project include the rehabilitation of pavement on

5th Street and installation of traffic striping, marking and signage to Road 16.5th Street Curve from Mariposa Ave to the Chowchilla Fairground Parking Lot on Road 16. Length of project is 631 feet. 07/2018 04/2019 20 30 5 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 45: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Madera Madera Road Maintenance & Rehabilitation

2018 Chip Seal Project (17/18 Ongoing)

Application of a chip seal (AKA Bituminous Surface Treatment) to local streets located throughout Madera.

Falcon From 817 ft N of Aviation To Yeager N. Golden State Blvd. From 329' N of Ave. 17 To City Limts (N) Berry Dr From Plumas To Maple Dessert Ranch Way From Makenna To Toschi Dessert Ranch Way From Toschi To Granada Eagle Way From Mekiana To St Tropez Maple From Berrry Dr To Toschi Maple From Mekenna To St Tropez Mekenna From Eagle Way To Oak Mekenna From Howard Rd To Eagle Way Mekenna From Maple To Dessert Ranch Way Mekenna From Plumas To Maple Oak From Mekenna To Tropez Dr Plumas From Berrry Dr To Granada Plumas From Mekenna To Tropez Dr Plumas From Tropez Dr To Berry Dr Toschi From Dessert Ranch Way To Maple Tropez Dr From Howard Rd To Eagle way Tropez Dr From Oak To Plumas Tropez Dr From Plumas To Maple Shannon Ave. From Sunset To Venturi Shannon Ave. From Venturi To Lighthouse Dr. Foster From Bruce To N. Park Dr. Foster From Sunset To Ula Foster From Ula To Bruce Pine From De Cesari To Roberts Pine From N Park To De Cesari Pine From Roberts To Roberts Crystal From Strauss To Gary Ln. Diamond Way From Strauss To Gary Lane Gary Ln. From Crystal Way To Emily Way Gary Ln. From Diamond Way To Majestic Ct. Gary Ln. From Emily Way To End Gary Ln. From Hwy 145 To Diamond Way Gary Ln. From Majestic Ct. To Crystal Way Majestic Ct. From end To Gary Ln. Maple From Santa Clara To Santa Cruz Maple From Stadium To Sata Clara Strauss From Crystal Way To end Strauss From Diamond Way To Crystal Way

06/2018 07/2018 5 8 5 12

Madera Madera Road Maintenance & Rehabilitation

2018 Asphalt Rejuvenation Treatment Project (17/18 Ongoing)

Application of an asphalt rejuvenation treatment material (AKA Reclamite) to local streets located throughout Madera.

Sample locations of possible work, exact locations TBD - Aviation Drive From Condor To Falcon Condor From Kennedy (16) To Aviation Falcon Drive From Aviation To Yeager (1/2) Granada Drive From Foxglove To Kennedy Apple Tree Ct From Peach Tree Dr To end Apple Tree Dr From Berry Dr To Toschi Dr Apple Tree Dr From Toschi Dr To S Granada Dr Berry Dr. From Pear Tree Dr To Peanut Dr Berry Dr. From Peanut Dr To Apple Tree Dr Berry Dr. From Apple Tree Dr To Orange Tree Dr Berry Dr. From Orange Tree Dr To Cherry Tree Dr Cherry Tree Dr From Berry Dr To Toschi Dr Cherry Tree Dr From Toschi Dr To S Granada Dr Toschi Dr. From Orange Tree Dr To Cherry Tree Dr Wolftrap St. From Chianti To 78' N of Merlot Bernardi Ave From Stadium Rd To Munras Ave El Monte From Fair Oak To Stadium Fair Oak From Gamay To El Monte Lighthouse Dr. From Mainberry To Harbor Dr. Lighthouse Dr. From Harbor Dr. To Shannon Mainberry Dr. From Sunset Ave. To Bay View Dr. Mainberry Dr. From Bay View Dr. To Venturi Ct. Mainberry Dr. From Venturi Ct. To Lighthouse Ct. Mainberry Dr. From Lighthouse Ct. To Lighthouse Dr. Sand Dollar Ct. From Bay View Dr. To End Venturi Ct From Mainberry To End

05/2018 08/2018 3 5 5 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 46: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Madera Madera Road Maintenance & Rehabilitation RMRA Seals/Overlays 2018-19 Road maintenance by application of surface seals and overlays

Cleveland Avenue from Raymond to Malta Street Cleveland Avenue from Malta Street to Calimyrna Avenue Cleveland Avenue from Calimyrna Avenue to Tulare Street Cleveland Avenue from Schnoor Street to Granada Drive Country Club Drive from Adell Street to Clark Street Country Club Drive from Sherwood to Cleveland Avenue Country Club Drive from Clark to Sherwood D Street North from 4th Street to 5th Street D Street North from 5th Street to Yosemite Avenue D Street South from Yosemite Avenue to 6th Street D Street South from 6th Street to 7th Street D Street South from 7th Street to Clinton D Street South from Clinton to 9th Street Gateway Drive from Cleveland to Central Pecan Avenue from Pine Street to Stadium Road Pine Street from Almond to North end of MHS Raymond Road from Cleveland to Laguna Way Raymond Road from Laguna Way to City Limits Tozer Street from Almond to Cedar Tozer Street from Trail Way to A Street Tozer Street from Sunrise to 15th Street Tozer Street a ~220' section btwn 15th Street & Clinton Yosemite Avenue from Q Street to P Street Yosemite Avenue from P Street to O Street Yosemite Avenue from O Street to N Street Yosemite Avenue from N Street to M Street Yosemite Avenue from M Street to L Street Yosemite Avenue from L Street to K Street Yosemite Avenue from K Street to J Street Yosemite Avenue from J Street to I Street Yosemite Avenue from I Street to H Street Yosemite Avenue from H Street to Gateway Drive

01/2019 06/2019 5 15 5 12

Belvedere Marin Road Maintenance & Rehabilitation 2018 Pavement Rehab Project Trench Restoration and pavement resurfacing. Corinthian Parking/Overlook and portions of Belvedere Ave, Belvedere Ave, Blanding Lane, Byaview

Ave, San Rafael Ave, and Acacia Ave. 08/2018 10/2018 15 25 10 2

Corte Madera Marin Road Maintenance & Rehabilitation

2017/18 Pavement Rehabilitation Project (17/18 Ongoing)

Grind and Overlay of Local Streets identified to be in poor condition per the 2017 Pavement Management Report and field observation

Stetson Avenue (From Buida Court to Chapman Drive), Chapman Drive (From Stetson Avenue to Tamalpais Drive), Oakdale Avenue (From Chapman Drive to Eastman Avenue), Buena Vista Avenue (From Sausalito Street to Oakdale Avenue), Council Crest Drive, Ash Avenue

10/2017 06/2018 15 20 10 2

Corte Madera Marin Complete Streets Components

Casa Buena Complete Streets Project (17/18 Ongoing)

Widen Casa Buena Drive to add bicycle lanes and new sidewalk to provide pedestrian access from neighboring multifamily housing. Pavement rehabilitation will also be a component of this project

Casa Buena Drive from Sanford Street to Meadow Valley Road 07/2017 10/2019 15 20 10 2

Corte Madera Marin Complete Streets Components

Paradise Drive Multimodal Enhancements

Assess existing conditions and multiple sidewalk widening, crosswalk enhancements, and bike lane (class I and II) improvements and construct the improvements corridor wide

Tamalpais Avenue/San Clemente intersection out Paradise Drive to Town limits at Robin Drive 08/2018 08/2019 15 20 10 2

Corte Madera Marin Traffic Control Devices Traffic Control Device Enhancements

Assess existing conditions including traffic counts, right of way constraints, roadway geometry, etc. Begin with Madera/Tamal Vista intersection and then build between 3-4 more roundabouts at Nellen/Wornum and along Paradise Drive

Maderal/Tamal Vista, Nellen/Wornum, And along Paradise Drive where it intersects with San Clemente, Harbor Drive and Sea Wolf Passage 09/2018 10/2019 20 30 10 2

Corte Madera Marin Road Maintenance & Rehabilitation Tamal Vista Complete Streets Grind and Overlay of Tamal Vista Bl and improve/consolidate pedestrian crossings, add

bike lanes, create ADA bus stops, sidewalks, curb cuts/ramps Tamal Vista Bl between Madera and Fifer Avenues 03/2019 07/2019 15 20 10 2

Fairfax Marin Road Maintenance & Rehabilitation

Scenic Rd Repavement (17/18 Carryover) repave approximately 1,700 linear ft of Scenic Rd Scenic Rd between Shapiro Lane and Bay Rd; Scenic Rd. between Tamalpais to Upper Scenic 07/2018 12/2018 10 15 10 2

Fairfax Marin Road Maintenance & Rehabilitation

Canyon Rd Stablization and Reconstruction Road stabilization project including repavement portion of road at appox. 145 Canyon 09/2018 10/2019 20 30 10 2

Fairfax Marin Safety Sidewalk replacement in downtown reconstruct sidewalks to improve pedestrian safety and ADA accessibility in downtown various locations on Bolinas Rd and Broadway in downtown 07/2018 12/2018 20 30 10 2

Fairfax Marin Safety Parkade Pedestrian Improvements Provide matching funds for ADA improvements in Parkade parking lot in downtown. Parkade parking lot between Sir Francis Drake Blvd. and Broadway in downtown 07/2018 12/2019 15 25 10 2

Larkspur Marin Road Maintenance & Rehabilitation

local streets pavement rehabilitation 2017-18

on select streets, dig out and replace sections of failed roadway with 8" of new asphalt; remove existing pavement to 2" below existing gutter and place new 2" lift of asphalt over entire street width. install new ADA compliant curb ramps where required at crosswalks

Locust Avenue from King Street to Ward Street King Street from Magnolia Avenue to Hawthorne Avenue Ward Street from Magnolia Avenue to Hawthorne Avenue Rice Lane from Cane Street to King Street

07/2018 12/2018 20 20 10 2

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 47: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Mill Valley Marin Road Maintenance & Rehabilitation

2018 Slurry Seal Project and 2018 Street and Sewer Rehabilitation Project

Slurry Seal or street and sewer rehabilitation of existing streets in City of Mill Valley

Janes Street (Molino Avenue to Montford Avenue) Cascade Drive (Throckmorton Avenue to Cornwall Street) Summit Avenue (Tamalpais Avenue to Fern Canyon Road) Buena Vista Avenue (Oakdale Avenue to Country Club Road) Montford Avenue (Janes Street to Miller Avenue) Country Club Drive (Buena Vista Drive to End) Coach Drive (Underhill Road to Benson Circle) West Blithedale (Throckmorton Avenue to Hillside Avenue) Elm Avenue (Locust Avenue to Sidney Street) LaGoma Street (Miller Avenue to Locke Lane) Valley Circle (Plymouth Avenue to east end of Sycamore Avenue) Cascade Drive (Marion Avenue to Laurel Street) Catalpa Avenue (E. Blithedale Avenue to Fern Avenue) Elma Street (Lovell Street toThrockmorton Avenue) Manor Terrace (Elm Avenue to North End) Park Avenue (Walnut Avenue to Miller Avenue) Recreation Center Parking Lot City Hall Parking Lot

07/2018 05/2019 7 30 10 13

Novato Marin Complete Streets Components ADA RoW Transition Plan

Inventory accessibility of city right-of-way, identify & document access barriers per ADA Title II, document barriers in MTC StreetSaver Program to facilitate future upgrades in conjunction with the citywide Pavement Management Program.

All public paths of travel within the city right-of-way. 04/2019 04/2019 10 30 10 2

Novato Marin Road Maintenance & Rehabilitation

MTC Pavement Management Phase IV (17/18 Ongoing)

Citywide pavement condition assessment, rehabilitation project determination, and reporting (Design Phase)

ALAMEDA DEL PRADO: IGNACIO-ALAMEDA DE LA LOMA; ATHERTON: US 101-CITY LIMITS; BALRA DRIVE@SHEVELIN RD; CENTER ROAD: WILSON AVE-RICA VISTA; COURT ROAD@BRUNO ST; DAVIDSON STREET; EAST COURT: COURT RD-BRUNO ST; ENFRENTE ROAD: US 101 OFF RAMP-ENTRADA DR; ENTRADA DRIVE: EAST END-ENFRENTE RD; ENTRADA DRIVE: EAST END-1000 FT WEST; GOLDEN GATE PLACE; IGNACIO BOULEVARD: ENFRENTE DR-ENTRADA DR; INDIAN VALLEY ROAD: CHAMBERLAIN AVE-CITY LIMITS; LA NOCHE COURT.

07/2017 06/2021 4 4 10 2

Novato Marin Road Maintenance & Rehabilitation

Sherman Ave. & Cain Lane Improvements Pavement maintenance and rehabilitation Sherman Ave. & Cain Ln. between Sherman & Reichert 08/2020 12/2021 15 30 10 2

Novato Marin Road Maintenance & Rehabilitation

2019 Annual Pavement Rehabilitation Project Pavement preservation, maintenance and rehabilitation. Exact locations TBD pending pavement condition assessment. Likely candidate streets for

resurfacing work include Center Rd., Novato Blvd., Wilson Ave., and N. Redwood Blvd. 40/2019 06/2020 15 30 10 2

Novato Marin Road Maintenance & Rehabilitation

S. Novato Blvd to US101 Preventative Mtce Pavement preservation, maintenance and rehabilitation. S. Novato between Diablo Ave. and US101 12/2021 12/2023 10 30 10 2

Novato Marin Road Maintenance & Rehabilitation

Olive Phase III (Redwood to Railroad)

Enhance safety of the RR crossing, pavement rehabilitation, replace failing drainage facilities Olive Ave. between Redwood Blvd. and Railroad Ave. 12/2018 12/2022 15 30 10 2

Novato Marin Safety Redwood & San Marin Improvements (AGP-5 & NP-1) Enhance safety, reduce traffic congestion, modify the interchange (including widening) San Marin Dr. at Redwood Blvd. and southbound US101 I/C 12/2021 12/2024 20 30 10 2

Novato Marin Complete Streets Components

Novato Blvd Improvements 7th/Tam-Diablo

Enhance safety, reduce traffic congestion, widen roadway, and add bike/pedestrian facilities Novato Blvd. between Diablo Ave. and Tamalpais Ave. 06/2022 12/2023 20 30 10 2

Novato Marin Safety SMART Access Improvements Address deficiencies in the public right-of-way (pedestrian/bike focus) near SMART stations In the vicinity of the SMART San Marin, Hamilton, and future Downtown train stations. 12/2018 12/2019 10 20 10 2

Novato Marin Complete Streets Components

Traffic, Bicycle, & Ped Improvements FY 14/15-18/19 (17/18 Ongoing)

Enhance safety, provide equal access, and reduce congestion as issues are identified Redwood Blvd. from San Marin Dr. to Wood Hollow Dr; Novato Blvd. from Diablo to Grant; Hill Rd@Indian Valley; Oak Grove Dr.-Entrada Dr.; Sutro Ave from Novato Blvd to Center Rd. 12/2018 12/2019 10 20 10 2

Novato Marin Complete Streets Components North Redwood Blvd Corridor Study Develop comprehensive streetscape plan with public input, determine constraints. Redwood Blvd. between Diablo Ave. and Wood Hollow Dr. 12/2020 12/2022 10 30 10 2

Novato Marin Complete Streets Components Lamont Avenue Bicycle Lanes Add Class 2 bike lanes to Lamont Ave., sliver widening and drainage improvements to

accommodate new bicycle facility, pavement rehab., and new striping. Lamont Ave. between Reichert Ave. and Franklin Ave. 12/2019 12/2020 10 30 10 2

Novato Marin Complete Streets Components Novato Blvd. Multiuse Path

Evaluate improvements to bike/ped access to Stafford Lake Park as a partnership with Marin County Parks. Project may rehabilitate existing asphalt pathway and/or construct new pathway on potential public access easement from O'Hare Park west to Stafford Lake Park

Novato Blvd. between Sutro Ave. and Stafford Lake 12/2020 12/2022 10 30 10 2

Novato Marin Complete Streets Components

Pedestrian Access to Transit & Crosswalk Improvements Enhance multiple crosswalks identified as being potential barriers to transit use. Novato@McClay, Redwood@Rush Cr., DeLong@Sherman, Diablo@George, Alameda Del

Prado@Posada Del Sol. 12/2017 12/2018 10 20 10 2

Novato Marin Safety Redwood Blvd. Improvements North of San Marin (NP-2)

Enhance safety, reduce traffic congestion, widen roadway, rehabilitate existing pavement. Redwood Blvd. between San Marin Dr. and Wood Hollow Dr. 12/2022 12/2024 20 30 10 2

Novato Marin Road Maintenance & Rehabilitation Grant Ave. Bridge Rehabilitation Bridge widening/rehabilitation, construct bicycle lanes, enhance crosswalks, and

pavement maintenance/rehabilitation. Grant Ave. between 8th St. and Virginia Ave. 06/2019 12/2020 20 30 10 2

Novato Marin Complete Streets Components Downtown SMART Station Phase III Plan and construct improvements to unimproved downtown depot site Grant Ave. between Scott Ct. and Railroad Ave. 12/2019 10/2021 10 30 10 2

Novato Marin Road Maintenance & Rehabilitation

Retaining Wall Assessment Group 1 Repairs

Assess condition of city retaining walls, establish inventory, implement repairs as necessary. Simmons Lane, Sunset Parkway, and Marin Valley above Clubview Drive 11/2017 11/2018 10 20 10 2

Novato Marin Road Maintenance & Rehabilitation

Citywide Bridge Assessment/Improvement (Group 1) Assess condition of city bridges, establish inventory, implement repairs as necessary. All city-owned/maintained bridges at various locations within the city limits 12/2019 12/2022 10 30 10 2

Novato Marin Safety San Marin/Simmons Intersection Signalization or Roundabout

Enhance safety, reduce traffic congestion, eliminate porkchop islands to enhance crosswalks, rehabilitate existing pavement. Intersection of San Marin Dr. and Simmons Ln. 12/2021 12/2023 20 30 10 2

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 48: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Novato Marin Traffic Control Devices Traffic Signal Upgrade Program (17/18 Carryover)

Traffic signal equipment replacement and timing/phasing modifications to improve efficiency and enhance safety for bicyclists and pedestrians.

Nave@Bolling; Nave@S. Hamilton; Redwood@Diablo-DeLong; Redwood@Lamont; Novato Blvd@Grant; Novato Blvd@Tamalpais-7th; Ignacio@Palmer; Ignacio@Alameda Del Prado; Rowland@Redwood; Rowland@ Rowland Way; Rowland@Vintage

12/2018 12/2020 5 20 10 2

Novato Marin Road Maintenance & Rehabilitation Vineyard Road Pavement Rehab Pavement maintenance and rehabilitation, close sidewalk gap, enhance crosswalks,

and add Class II bike lanes where existing width allows. Vineyard Rd. between Wilson Ave. and Sutro Ave. 05/2018 06/2019 15 30 10 2

Novato Marin Road Maintenance & Rehabilitation Measure A Group 10

Pavement preservation, maintenance and rehabilitation. Restriping work to include bicycle lane enhancements and intersection reconfiguration at Roblar Dr. to improve access.

Nave Dr. from Alameda Del Prado to Bel Marin Keys Blvd. and Bel Marin Keys Blvd. from Nave Dr. to Digital Dr. 07/2018 06/2019 15 30 10 2

Ross Marin Road Maintenance & Rehabilitation

Town of Ross FY 18/19 Pavement Rehabilitation Project 2" grind and overlay, with minor curb and gutter repair within local residential streets. Olive Ave and Walnut Ave in the Town of Ross, CA. 04/2019 11/2019 10 15 10 3

Ross Marin Road Maintenance & Rehabilitation 17/18 Carryover pavement rehabilitation and curb/gutter repair on Fallen Leaf and portions of Wellington

Ave. Winship Park in the Town of Ross, CA 07/2018 08/2018 15 25 10 2

San Anselmo Marin Road Maintenance & Rehabilitation

2018/2019 FY Street Rehabilitation Project

Street repaving, which consists of removal of the existing pavement section and replacement with new asphalt concrete. Complete Streets elements will be analyzed and included if appropriate.

San Francisco Boulevard from Sir Francis Drake Boulevard to end; Merced Ave from Fern Lane to San Anselmo Ave; Plumas Ave from Scenic Ave to Morton Lane,; Morton Lane from Plumas Ave to Elm Ave; Kensington Road from Bolinas Ave to Ross Ave; Brookside Dr from Broadmoor Ave to Cordone Dr; Meadowcroft Dr from Butterfield Rd to Morningside Dr; and Brookside Court from Brookside Dr to end.

07/2018 11/2018 20 30 10 2

San Rafael Marin Complete Streets Components

Merrydale Pathway - North Connector (Northgate Promenade) (17/18 Carryover)

This project includes the construction of a multi-use path, parking, and other road improvements along one side of the roadway from Las Gallinas Avenue to the Civic Center SMART station. The FY 2017-18 amount listed ($100,000) is to contract with an outside firm for thepreliminary engineering and design of the pathway.

FY 2017-18 Year End Update (6/4/2018): - RMRA funds being used for the design as well as construction of these projects - Design contracted out. Will be designed and constructed same year, no need toseparate out from construction

- Design estimated to be completed late fall 2019 - WIll go out for bid January 2019

Las Gallinas Avenue to Civic Center SMART station 07/2018 01/2019 10 15 10 2

San Rafael Marin Road Maintenance & Rehabilitation

Smith Ranch and Lucas Valley Road Resurfacing (17/18 Carryover)

Removing and replacing the top 4" of asphalt, installing new roadway striping and minorelectrical work at traffic signals on Lucas Valley/Smith Ranch Roads from Los Gamos Drive on the west to Redwood Highway on the east, including the area underneath the freeway. New wheelchair ramps will be installed where necessary to comply with federallaw. This project is a high priority due to the existing asphalt having exceeded its useful lifespan. While the roadway directly under Highway 101 is Caltrans jurisdiction, per the agreement in place, the City is responsible for the maintenance of Smith Ranch Road.

FY 2017-18 Year End Update (6/4/2018): - RMRA funds being used for the design as well as construction of these projects - Design contracted out. Will be designed and constructed same year, no need to separate out from construction - Design estimated to be completed late fall 2019 - WIll go out for bid January 2019

Lucas Valley/Smith Ranch Road: from Los Gamos Drive on the west to Redwood Highway on the east, and includes the roadway under Highway 101. 03/2019 05/2019 15 20 10 2

San Rafael Marin Complete Streets Components

Lincoln Avenue Curb Ramps (17/18 Carryover)

San Rafael Sanitation District (SRSD) has performed a larger sewer replacement on Lincoln Avenue. Before SRSD resurfaces the roadway, Public Works will install new wheelchair ramps to comply with federal law. As a standard practice, all curb ramps arereplaced and updated with performed street resurfacing. Minor traffic signal upgrades will also be necessary at the intersection of Lincoln Avenue and Paloma Avenue.

FY 2017-18 Year End Update (6/4/2018): - RMRA funds being used for the design as well as construction of these projects - Design contracted out. Will be designed and constructed same year, no need to separate out from construction - Design estimated to be completed late fall 2019 - WIll go out for bid January 2019

The project will install wheelchair ramps on Lincoln Avenue from the north side of Mission Avenue to Prospect Drive. 08/2019 01/2020 30 40 10 2

Sausalito Marin Road Maintenance & Rehabilitation

Bee St. and Bonita St. Improvements

Remove existing concrete pavement and replace with AC pavement. Up to five new curb ramps, sanitary sewer main and lateral and storm drain improvements and sidewalk improvements as required .

Bee St. between Bonita St. and Caledonia St. Bonita St. Between Litho St. and Bee St. 07/2018 10/2018 20 30 10 2

Sausalito Marin Road Maintenance & Rehabilitation

2019 Streets Resurfacing Project (17/18 Carryover)

Remove exiting concrete surfacing and replace with new asphalt surface. AC overlay with attendant grinding and base repair. Elimination of exposed road base material material from entering the bay during wet weather. Six new curb ramps. Elimination of potential trip hazards, drainage improvements and repair of sanitary sewer main and laterals as may be required.

Excelsior Ln, between Bulkley Ave. and Steps to Bridgeway Easterby St. between Bridgeway/Filbert and Pearl St. Locust St. between Bridgeway and the bay Girard Ave. between Johnson St. and Turney St.

10/2018 06/2019 10 30 10 2

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 49: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Tiburon Marin Road Maintenance & Rehabilitation

2018 Various Streets Overlay Las Lomas Lane Pavement overlay of Las Lomas Lane from Mar West to end Las Lomas Lane, Tiburon 01/2018 06/2018 15 30 10 2

Tiburon Marin Road Maintenance & Rehabilitation

Hawthorne Undergrounding Road Resurfacing Restoration of streets following the undergrounding of overhead utilities.

Town of Tiburon, CA, Hawthorne Drive from East End to Rock Hill, Hawthorne Drive from Wend End to Rock Hill, Rock Hill from Tiburon Blvd to Del Mar, Rock Hill from Del Mar to Cul De Sac 01/2019 06/2019 15 25 10 2

Fort Bragg Mendocino Road Maintenance & Rehabilitation

Street and Alley Pavement Maintenance

When small localized areas of pavement are found to be in poor condition they are treated with small scale pavement repair. Small scale pavement repair must be done in a timely fashion; as potholes grow and allow water intrusion which leads to more large scale deterioration of the pavement. Surface patching and crack sealing are the two primary intermediary actions taken to conserve the existing conditions of pavement. Pothole patching is the most common local technique, done by milling a portion of the pavement to a depth that removes all deteriorated material and then the pothole is filled with asphalt and compacted. The goal of this project is to prevent the local/residential streets and alleys with low PCI’s from deteriorating into an un-usable state as these street categories often go unselected for full treatment due to the algorithm used to by the Pavement Management Program.

Azalea Circle, Espey Way, Myrtle Street, Noyo Heights Drive, Olsen Lane, West Street, Willow Street, Woodward Street, and Stewart Street 07/2018 06/2019 2 10 2 2

Fort Bragg Mendocino Traffic Control Devices Crosswalk and Street Marking

Centerline, fog line, bicycle lane, and crosswalk markings provide cost-effective roadway guidance that helps reduce crashes and supplement other traffic control devices such as sign and signals. The city’s existing pavement markings need replacing in many locations; these will be replaced by thermoplastic and raised pavement markers. This year nine streets have been identified for such work. The street striping project will replace all white and yellow line markings, decals, raised markers, and word pavement markings on approximately 3.5 miles of streets. The selected streets include arterials, collectors, and safe routes to school. The standards for the application of markings and delineation are set forth in the California Manual on Uniform Traffic Control Devices (MUTCD). The unfunded balance for this project will be covered with local street sales tax dollars.

Chestnut Street, East Oak Street, East Pine Street, Redwood Avenue, Manzanita Street, North Franklin Street, South Harold Street, South Lincoln Street, and Willow Street 07/2018 06/2019 3 4 2 2

Point Arena Mendocino Road Maintenance & Rehabilitation

Mill Street & Riverside Drive Engineering Assessment

A full length condition and engineering assessment of Riverside Drive (.63 miles) and Mill Street (.2 miles) to prepare construction documents, specifications and bidding documents for the completion of Riverside Road and Mill Street reconstruction in budget years 2019-2020 and 2020-2021.

In Point Arena, all of the City Portion of Riverside Drive and all of Mill Street 10/2018 05/2019 15 25 2 2

Point Arena Mendocino Road Maintenance & Rehabilitation Port Road Rehab & Slurry Seal

Port Road Rehab & Slurry Seal ‐ O Numerous base failures require 10,000 + sq. ft. of dig outs and 5” of reconstruction and then 42,000 sq. ft. of slurry seal. We expect a life of the slurry seal to be 8 -10 years thus preserving the underlaying asphalt while we work on repairs to streets that require larger investments per square foot. We expect the Port Rd. project to be completed before the end of summer 2018.

In Point Arena, on Port Road , extending easterly from the western terminus at the Point Arena Pier ramp for 0.6 miles, ending approximately at the eastern terminus near the Iversen Road junction. 03/2018 07/2018 10 15 2 2

Ukiah Mendocino Road Maintenance & Rehabilitation North State Street AC Overlay This project will construct a 2-inch AC overlay on North State Street from 240 feet north

of Low Gap Road to the northern City limits. North State Street from 240 feet north of Low Gap Road to the northern City limits in Ukiah, California 07/2018 10/2018 20 25 2 2

Ukiah Mendocino Road Maintenance & Rehabilitation

South Orchard Avenue AC Overlay (17/18 Carryover)

This project will construct a 2-inch AC overlay on South Orchard Avenue from Gobbi Street to Marlene Street. South Orchard Avenue from Gobbi Street to Marlene Street 07/2018 10/2018 20 25 2 2

Willits Mendocino Safety Annual Striping Program FY 2018/19

Replacement of approximately 5 miles of deteriorated traffic markings, including: pedestrian crosswalks, center lines, bike lanes, etc. This is part of a program to replace a quarter of the City's traffic markings per year. The annual striping program re-stripes and refreshes traffic markings on approximately one quarter of the City's streets each year. Certain high traffic locations and most school zones are stripped each year or every other year as needed.

Various locations throughout the City. Most streets in our city of 2.8 square miles are on a four-year rotation, with approximately 20-22 miles of paved roadway total. All project locations are within 1.5 miles of Lat 39.400528, Lon -123.349698

04/2019 06/2019 2 4 2 2

Willits Mendocino Road Maintenance & Rehabilitation

Creekside Road Stabilization Project

This project will repair drainage structures, regrade the roadway, replace approximately 80' of curb, gutter, and asphalt. Creekside Street, between Boscabell and South Lenore Streets 04/2019 06/2019 10 25 2 2

Atwater Merced Traffic Control DevicesTraffic Light Installation @ Atwater Boulevard/First Street (17/18 Carryover)

The City of Atwater will install a traffic light at Atwater Boulevard and First Street to provide safe controls for drivers and pedestrians. Atwater Boulevard and First Street 07/2018 01/2019 15 30 21 12

Atwater Merced Traffic Control Devices Traffic Retrofit @ Winton Way and Juniper Avenue (17/18 Carryover)

The City of Atwater will retrofit a traffic light from a camera control to an induction coil control for better performance in inclement weather, ensuring safety and ease of commute for drivers/pedestrians.

Winton Way and Juniper Avenue 07/2018 01/2019 15 30 21 12

Atwater Merced Complete Streets Components

Winton Way Road Improvement (17/18 Carryover)

Winton Way will undergo a long-term pavement upgrade to address future needs of the City Winton Way between Broadway and Bellevue Road 07/2018 12/2028 20 30 21 12

Atwater Merced Complete Streets Components

Fruitland Avenue Road Improvements (17/18 Carryover)

Fruitland Avenue will undergo a long-term pavement upgrade with new traffic circles to encourage the flow of traffic while reducing emissions and increasing pedestrian safety. Fruitland Avenue between Orchard Park and Shaffer Road 10/2018 12/2028 20 30 21 12

Atwater Merced Other ACE Merced Extension: Atwater Station (17/18 Carryover)

Atwater Station, in conjunction with the Altamont Corridor Express, will provide an environmentally-friendly travel alternative to the Bay Area while revitalizing Atwater Boulevard with new sidewalks and improved parking.

Atwater Boulevard, between Winton Way to east of First Street 12/2020 12/2022 20 30 21 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 50: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Atwater Merced Other Active Transportation Plan (17/18 Carryover)

The Active Transportation Plan will slowly adapt current transportation infrastructure to encourage the use of public transportation, bicycle paths and walking through the development of new mass transit options, protected bicycle lanes, and improved sidewalks. All locations have yet to be finalized and are subject to change

Its for development of the Active Transportation Plan for the City. The City currently does not have an active transportation plan. Locations include Bell Dr., Olive Ave., Applegate Rd., N Winton Way., Bellevue Rd., East Bellevue Rd., Juniper Ave., East Juniper Ave., First St., Shaffer Rd., Ave One, Ave Two, N Buhach Rd., Santa Fe Dr., Green Sands Ave. and Gertrude Ave. All locations have yet to be finalized and are subject to change.

12/2019 12/2025 20 30 21 12

Atwater Merced Road Maintenance & Rehabilitation

18/19 Annual City - Wide Roadway Painting

All City roads require extensive painting maintenance for safety. Center Striping Broadway from Winton Way to Shaffer Rd. Center Striping Third St. from Atwater Blvd. to Juniper Avenue. Center Striping Linden from First Street to Bellevue Rd. All locations have yet to be finalized and are subject to change

Broadway from Winton Way to Shaffer Rd. Third St. from Atwater Blvd. to Juniper Ave. Linden St. from First St. to Bellevue Rd. All locations have yet to be finalized and are subject to change Atwater Boulevard from Winton Way West to the Freeway on ramp Current listed locations are based on an estimate and may change based on priority need and resources. All locations have yet to be finalized and will be selected based on priority need and resources throughout the year.

08/2018 06/2019 10 20 21 12

Atwater Merced Safety Curb, Gutter and sidewalk replacement (17/18 Carryover)

Atwater's current pedestrian infrastructure is aging rapidly. In addition to cracks and unsafe ledges, sidewalks are not compliant with the Americans with Disabilities Act (ADA).

Third St. from north of Palm Ave. to Mulberry Ave; Mulberry from Third St. to Fourth St; Fourth St. from Quince Ave. to Mulberry. Approximately 1,200 LF total. 07/2018 06/2019 15 30 21 12

Dos Palos Merced Road Maintenance & Rehabilitation

Center Avenue North Project - 17/18 Carryover

The complete reconstruction and replacement of storm drainage systems, streets, sidewalks, curb, and gutter, including any environmental and engineering work ad deemed necessary located on Center Avenue from Marguerite Street to Lorain Street, and Loraine Street from Center Avenue to Dos Palos Avenue

Center Avenue from Marguerite Street to Loraine Street, and Loraine Street from Center Avenue to Dos Palos Avenue 12/2018 06/2019 40 50 21 12

Gustine Merced Complete Streets Components Greenacres Project (Ongoing) Eliminate high curbs and install ADA-compliant ramps. Sidewalks and public street near the entrance of mobile-home located in the 1400 block of Meredith

Avenue. 06/2018 01/2019 15 20 21 12

Gustine Merced Complete Streets Components Hillview Sidewalk (Ongoing)

Ramp, sidewalk and gutter rehabilitation to improve safety and walkability of the area. The project will replace uneven concrete that contains tripping hazards, as well as replace ramps for handicap access for all pedestrians, including citizens attempting to access both the public High School and the sole funeral home in the City.

Block on the southwest corner of 5th Street and North avenues and Northwest corner of 5th Street and First Avenue adjacent to the public high school and funeral home. 12/2017 07/2018 15 20 21 12

Gustine Merced Complete Streets Components Main Street/GPS Project (Carryover)

Ramp, sidewalk and gutter rehabilitation to improve safety and walk-ability of the area. The project will replace uneven concrete that contains tripping hazards, as well as replace ramps for handicap access for all pedestrians, including all traffic in the downtown corridor.

Block on the northwest corner of 5th Street and 3rd Avenue, in the heart of the City business district and utilized extensively by the public. 03/2019 12/2019 15 20 21 12

Gustine Merced Traffic Control Devices Hwy 33/140 Roundabout Eliminate stop sign on State Highway 33, replacing with a Roundabout. Junction of State Highways 33 and 140. 11/2018 11/2019 10 20 21 12

Gustine Merced Traffic Control Devices Downtown Roundabout Replace two-way stop with Roundabout to correct site obscurement and ADA compliance issues. Intersection of 5th Street and 4th Avenue. 11/2021 11/2022 10 20 21 12

Gustine Merced Road Maintenance & Rehabilitation Carnation Road Rehabilitate/reconstruct dilapidated roadway Carnation Road between East Avenue and Waste Water Treatment Plant 01/2019 11/2019 10 20 21 12

Livingston Merced Other CMAQ - Construct Roundabout at Main St & B St Construct a Roundabout at Main Street & B Street In the City of Livingston at the intersection of Main Street and B Street 08/2018 08/2019 10 20 21 12

Livingston Merced Road Maintenance & Rehabilitation Stefani Avenue Rehabilitation Reconstruction of the roadway structural section In the City of Livingston between Davis Street and Campbell Boulevard 08/2018 09/2019 10 20 21 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 51: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Banos Merced Road Maintenance & Rehabilitation Fog Seal A sprayed on application of SS1H liquid asphalt emulsion with a light coating of sand

West I Street from Pacheco Blvd to 7th St Colorado Ave from H St to J St J St from Colorado Ave to Pacheco Blvd Maryland Ave from J St to Pacheco Blvd West K St from West I St to Iowa Ave Linda Vista from West J St to West I St H St from Texas Ave to Arizona Ave H St from 2nd St to 4th St H St from 7th St to Pacheco Blvd 3rd St from H St to K St Johnson Rd from Overland Ave to H St Ortigalita Rd from Pioneer Rd to Cardoza Rd K St from 3rd St to 7th St L St from Center Ave to 5th St 5th St from M St to H St 6th St from Page Ave to H St 10th St from I St to H St 7th St from H St to Willmott Rd C St from 7th St to North St North St from D St to Willmott Rd D St from North St to 3rd St 3rd St from D St to G St E St from 2nd St to 3rd St E St from 5th St to 7th St F St from 2nd St to 7th St G St from 2nd St to 5th St 4th St from H St to F St 6th St from F St to E St M St from 4th St to 6th St North Santa Anna St from East B St to Overland Ave North Santa Rita St from East B St to Santa Cruz Way Santa Maria Rd from Santa Anna St to East End Santa Inez from Santa Maria Rd to Overland Ave Santa Paula St from Santa Maria Rd to Overland Ave North Santa Rosa from East B St to Santa Cruz Way Quail St from Mercey Springs Rd to Woodbury Dr Chukar St from Skylark Ave to Meadowlark Ave Dove St from Mercey Springs to Fairmont Dr Eagle St from Skylark Ave to Meadowlark Ave Robin St form Skylark Ave to Meadowlark Ave

07/2018 09/2018 5 7 21 12

Los Banos Merced Road Maintenance & Rehabilitation Fog Seal (17/18 Ongoing) A sprayed on application of SS1H liquid asphalt emulsion with a light coating of sand Iowa Ave from Pacheco Blvd to Madrone St 07/2018 09/2018 5 7 21 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 52: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Banos Merced Road Maintenance & Rehabilitation Crack Seal A hot liquid rubberized asphalt application material, applied to the cracks on the

roadway

West I Street from Pacheco Blvd to 7th St Colorado Ave from H St to J St J St from Colorado Ave to Pacheco Blvd Maryland Ave from J St to Pacheco Blvd West K St from West I St to Iowa Ave Linda Vista from West J St to West I St H St from Texas Ave to Arizona Ave H St from 2nd St to 4th St H St from 7th St to Pacheco Blvd 3rd St from H St to K St Johnson Rd from Overland Ave to H St Ortigalita Rd from Pioneer Rd to Cardoza Rd K St from 3rd St to 7th St L St from Center Ave to 5th St 5th St from M St to H St 6th St from Page Ave to H St 10th St from I St to H St 7th St from H St to Willmott Rd C St from 7th St to North St North St from D St to Willmott Rd D St from North St to 3rd St 3rd St from D St to G St E St from 2nd St to 3rd St E St from 5th St to 7th St F St from 2nd St to 7th St G St from 2nd St to 5th St 4th St from H St to F St 6th St from F St to E St M St from 4th St to 6th St North Santa Anna St from East B St to Overland Ave North Santa Rita St from East B St to Santa Cruz Way Santa Maria Rd from Santa Anna St to East End Santa Inez from Santa Maria Rd to Overland Ave Santa Paula St from Santa Maria Rd to Overland Ave North Santa Rosa from East B St to Santa Cruz Way Quail St from Mercey Springs Rd to Woodbury Dr Chuckar St from Skylark Ave to Meadowlark Ave Dove St from Mercey Springs to Fairmont Dr Eagle St from Skylark Ave to Meadowlark Ave Robin St form Skylark Ave to Meadowlark Ave

10/2018 06/2019 5 7 21 12

Los Banos Merced Road Maintenance & Rehabilitation Cold Mix Overlay A thin layer of cold mix spread out over entire roadway section Center Ave from Cardoza Rd to City Limits South

Willmott Rd from Johnson Rd to 1st St 06/2019 06/2019 10 20 21 12

Los Banos Merced Road Maintenance & Rehabilitation Crack Seal (17/18 Carryover) A hot liquid rubberized asphalt application material, applied to the cracks on the

roadway

West I Street from Pacheco Blvd to south end Cardoza Road from Badger Flat to West I Street Bellflower Way from Woodbrush Ave to Wildrye Ave Bluegrass Ct from Woodbrush Ave to west end Woodbrush Ave from Bellflower Way to Badger Flat Rd Dewberry Ct from Woodbrush Ave to west end Oatgrass Way from Woodbrush Ave to Ortigalita Rd Cattail Ct from Oatgrass Way to south end Reed Ct from Bellflower Way to north end Watercress Ct from Bellflower Way to north end Landing Way from Bellflower Way to Cardoza Rd Wildrye Ave from Bellflower Way to Oatgrass Way Ortigalita Rd from Pacheco Blvd to Cardoza Rd Birch Ave from Ortigalita Rd to Magnolia Way Birch Ave from West I St to Eucalyptus Dr Greenwood Way from Birch Ave to Alberta St Hawthorne Dr from Birch Ave to West I Street

10/2018 06/2019 5 7 21 12

Los Banos Merced Road Maintenance & Rehabilitation Cold Mix Overlay (17/18 Carryover) A thin layer of cold mix spread out over entire roadway section Overland Avenue from Nantes Ave to Johnson Rd 06/2019 06/2019 10 20 21 12

Los Banos Merced Road Maintenance & Rehabilitation Crack Seal (17/18 Ongoing) A hot liquid rubberized asphalt application material, applied to the cracks on the

roadway Iowa Avenue from Pacheco to Madrone St 10/2018 06/2019 5 7 21 12

Merced Merced Road Maintenance & Rehabilitation

Roadway Scrub Seal (17/18 Ongoing) Scrub Seal Roadway Rehabilitation Project. Canal Street (Childs Ave to 16th St); East El Portal Avenue (G St to Joerg Ave); West 26th Street (G

St to M St); and Merced Avenue (Parsons Ave to Motel Drive) 05/2018 09/2018 7 10 21 12

Merced Merced Safety Sidewalk Replacement Project (17/18 Ongoing) Sidewalk Replacement Project.

Various locations throughout the City of Merced - see Location Map. (K, Canal, & 8th Streets; Seville Way; East Donna Drive; Q & 4th Streets; Q & 10th Streets; R & 10th Streets; Evelyn & Julie Drive; East 22nd St & Cherry Ave)

05/2018 09/2018 10 20 21 12

Merced Merced Safety Curb and Gutter Replacement Project (17/18 Ongoing) Curb and Gutter Replacement Project. Various locations throughout the City of Merced - see Location Map.

(K St; Q & 10th St; R & 10th/11th St; Evelyn Ct; East 22nd St & Cherry Ave; V & 8th St) 05/2018 09/2018 10 20 21 12

Merced Merced Other Road Improvement Project (1) Road widening and traffic signal improvements. Yosemite Avenue (St. Augustine to SR 59) 04/2019 07/2019 20 20 21 12Merced Merced Other Road Improvement Project (2) Road widening, sidewalk, curb and gutter. Childs Avenue (Parsons Avenue to Campus Parkway) 06/2019 10/2019 20 20 21 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 53: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Merced Merced Road Maintenance & Rehabilitation

Road Maintenance and Rehabilitation Programs and Material Purchase

Road Maintenance and Rehabilitation Programs and Material Purchase.

Various locations throughout the City of Merced. Area 1 generally bounded by south of Santa Fe Avenue, north of Highway 99, east of Highway 59, and west of Yosemite Parkway. Area 2 generally bounded by south of Highway 99, north of Dickenson Ferry Road, east of Thornton Road, and west of Highway 59. See "Maintenance Area" attachment for detailed information.

07/2018 06/2019 5 7 21 12

Alturas Modoc Road Maintenance & Rehabilitation East 8th Street road way repair These funds will be used to perform minor repair work on a deteriorating section of road

way. This will give this road way some additional life. 8th and Main street 06/2019 07/2019 7 12 1 1

Mammoth Lakes Mono Road Maintenance & Rehabilitation

Meridian Blvd Curb and Gutter Phase 2

Meridian Blvd Curb and Gutter replacement project Phase 2. Located along Meridian Blvd west of Minaret Rd the project will remove and replace curb and gutter that is currently failing to convey stormwater, undermining pavement and is a hazard to pedestrians. The project is expected to last at least 20 years and would be completed during the summer of 2018.

Meridian Blvd, Mammoth Lakes CA 05/2019 07/2019 10 20 25 1

Mammoth Lakes Mono Complete Streets Components

Main Street Infrastructure Improvements

Provide funding to remedy any multi -modal infrastructure deficiencies or complete any necessary safety improvements identified during the planning and/ or construction process that are not directly funded by the current STIP sidewalk projects. Improvements of this nature typically last 20 years and would be completed during the summers of 2018 or 2019.

Main Street (SR203) Mammoth Lakes CA 05/2019 07/2019 10 20 25 1

Carmel-by-the-Sea Monterey Road Maintenance & Rehabilitation Road Project (FY 18/19) Type II Slurry Seal on 26 Possible Segments and 2 inch overlay

Type II Slurry Seal 1. 2nd Avenue from Santa Fe to Lobos Street 2. 3rd Avenue from Junipero Avenue to Santa Fe Street 3. 3rd Avenue from Santa Rita Street to Guadalupe Street 4. 4th Avenue from Santa Fe Street to Santa Rita Street 5. 5th Avenue from Dolores Street to San Carlos Street 6. 6th Avenue from Mission Street to Torres Street 7. 6th Avenue from Monte Verde to Lincoln Street 8. 7th Avenue from San Carlos Street to Junipero Avenue 9. 7th Avenue from Guadalupe Street to Forest Street 10. 10th Avenue from Junipero Avenue to Torres Street 11. 11th Avenue from Junipero to East End 12. 13th Avenue from San Carlos Street to Junipero Avenue 13. Camino Del Monte from City Limits to 2nd Street 14. Del Mar from Ocean Avenue to Turn Around 15. Dolores Street from Vista to 2nd Avenue 16. Dolores Street from 4th Avenue to 5th Avenue 17. Dolores Street from Franciscan Way to City Limits 18. Escolle Way from Perry Newberry Way to Turn Around 19. Junipero Avenue from Ocean Avenue to 8th Avenue 20. Lasuen Drive from Rio Road to City Limit 21. Lincoln Street from 5th Avenue to Ocean Avenue 22. Lobos Street from 2nd Avenue to 4th Avenue 23. Mission Street from 3rd Avenue to 4th Avenue 24. Ocean Avenue from Del Mar to San Antonio Avenue 25. Santa Lucia Avenue from Camino Real to Dolores Street 26. Torres Street from City Limits to 2nd Avenue 2 Inch overlay 1. 1st Avenue from Carpenter Street to Lobos Street 2. 8th Avenue from Casanova Street to Monte Verde Street 3. 8th Avenue from San Carlos to Junipero Avenue 4. Camino Del Monte from 3rd Avenue to Junipero Avenue 5. Forest Road from Mountain View to 7th Avenue 6. Junipero Avenue from 8th Avenue to 10th Avenue 7. Junipero Avenue from Camino Del Monte to 2nd Avenue 8. Santa Fe Street from Ocean Avenue to 8th Avenue

03/2019 04/2019 10 15 29 17

Del Rey Oaks Monterey Road Maintenance & Rehabilitation

Street Reconstruction and Overlay Package

Design and construct street reconstruction and overlay package, Del Rey Oaks residential streets, estimated useful life 15-20 years. Estimated completion October 2019.

Carlton Drive and cul du sacs north of Portola and Quendale Streets. 02/2019 06/2019 15 20 29 17

Gonzales Monterey Road Maintenance & Rehabilitation

Alta Street Pavement Rehabilitation (17/18 Ongoing)

Reconstruct major arterial through the City of Gonzales. 10,000 LF of roadway will be improved. Alta Street from 10th Street (northern City limits) to on-ramp to SB101 (southern City limits) 12/2017 08/2018 12 20 28 12

Greenfield Monterey Road Maintenance & Rehabilitation

Commercial and Residential Alley Improvement Project

Improvements to public alley servicing commercial properties fronting El Camino Real and residential properties fronting 8th Street. Project includes asphalt and concrete repairs, reconstruction of alley paving, construction of concrete ribbon gutters for drainage and stormwater control, construction of ADA pedestrian crossings at affected street intersections, construction of a subterranean stormwater retention basin, and associated design, construction management, and inspection services provided by City Engineer and City staff.

Alley between El Camino Real and 8th Street, from Apple Avenue to Elm Avenue, Greenfield, CA 93927 04/2018 11/2018 15 20 30 12

Greenfield Monterey Road Maintenance & Rehabilitation Administrative Costs Related costs of Public Works employees assigned to the Streets Division and

providing local street and road maintenance and repair services. City of Greenfield 01/2018 06/2019 1 1 30 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 54: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

King City Monterey Road Maintenance & Rehabilitation

Crack seal and Slurry Seal - Royal Coach and N Vanderhurst St/Queen St Neighborhoods

Project consist of Slurry Seal treatment to the following Street.City of King City - Amherst Dr, Bedford Ave, Bedford Circle, Bluff Avenue, Brighton Ave, Cambridge Ave, Keats Ave, Leeds Ave, Nantucket Way, Ocford Ave, Sussex Circle, Sussex Way, Wellington Ave, Orchard St, Copley St, N Vanderhurst Ave (North of King St) and Queen St.

07/2018 09/2018 10 15 30 12

King City Monterey Road Maintenance & Rehabilitation

Bitterwater Rd - East of Industrial Dr to East of Airport Dr

Design, Grind and Overlay - Total cost with other revenues is $330,000. SB1 funds expected to be used is $86,917.00. Bitterwater Road - East of Industrial Drive to East of Airport Drive 07/2018 09/2018 25 30 30 12

Marina Monterey Road Maintenance & Rehabilitation

ANNUAL STREET RESURFACING, OVERLAY CRACH SEALING, DIGOUTS, 2IN OVERLAY DEL MONTE BLVD - RESERVATION RD TO SR1, RIGHT LANE 03/2019 06/2019 4 29 29 17

Marina Monterey Road Maintenance & Rehabilitation

ANNUAL STREET RESURFACING, RUBBER CAPE CRACH SEALING, DIGOUTS, RUBBER CAPE SEAL

CRESTVIEW CT - RESERVATION RD TO END; JOHNSON PL - TALLMON ST TO END; LELIA PL - CRIVELLO RD TO END; OTTO DR - HILLCREST AVE TO END; SNELL PL - MESSINGER DR TO END; VISTA DEL CAMINO - SUSAN AVE TO MELANIE RD; YOUNG CIR - VILLA CIR TO END; JORDON CT - BROSTROM DR TO END; KENNEDY CT - REINDOLLAR AVE TO SOUTH END; SHOEMAKER PL - MESSINGER DR TO END

04/2019 06/2019 10 29 29 17

Marina Monterey Road Maintenance & Rehabilitation

ANNUAL STREET RESURFACING, CAPE CHIP SEAL & SLURRY SEAL CARMEL AVE - CALIFORNIA AVE TO SALINAS AVE; FIRST AVE - DIVERTY ST TO EIGHTH ST 04/2019 06/2019 10 14 29 17

Marina Monterey Road Maintenance & Rehabilitation

ANNUAL STREET RESURFACING, SLURRY SLURRY SEAL

ALBERT WAY - LYNSCOTT DR TO END; ARNOLD CT - LANDRUM CT TO END; BAILEY CT - WITTENMYER CT TO END; BAYER DR - RIDGEVIEW AVE TO MELVILLE RD; CALIFORNIA AVE - TAMARA CT TO CARMEL AVE; CALIFORNIA AVE - REINDOLLAR AVE TO TAMARA CT; CLARKE PL - MESSINGER DR TO END; EDNA CT - LYNSCOTT DR TO END; FERRIS CIR - SUNRISE CIR TO END; HILLCREST AVE - ZANETTA DR TO VAUGHAN AVE; HORN CT - PRESTON DR TO END; JEAN ST - FERRIS AVE TO JEAN CIR; MARINA GREENS DR - PAUL DAVIS DR TO DEL MONTE BLVD; OAK CIR - DE FOREST RD TO END; REDWOOD DR - HILLCREST AVE TO CARMEL AVE; SAND DOLLAR CT - STARFISH CT TO END; STARFISH CT - MARINA DR TO END; SUNRISE AVE - KELLI CT TO BOSTICK AVE; TALCOTT AVE - GRANT ST TO REINDOLLAR AVE; TWELFTH ST - SECOND AVE TO ELEVENTH ST; VISTA DEL CAMINO - MELANIE RD TO GEORGE WAY; BEACH RD - DEL MONTE BLVD TO DE FOREST RD

05/2019 06/2019 24 29 29 17

Marina Monterey Road Maintenance & Rehabilitation

ANNUAL STREET RESURFACING, CRACK SEAL SEAL CRACKS

CONCORD CT - EDDY ST TO END COVE WAY - DOLPHIN CIR TO END CRESCENT ST - PATTON PARKWAY TO REINDOLLAR AVE DIANA PL - LYNSCOTT DR TO END ECHO ST - NEESON RD TO DELTA ST ELLIS CT - SALINAS AVE TO END FIFTH AVE - THIRD ST TO EIGHTTH ST FITZGERALD CIR - BEACH RD TO END FOREST CIR - BAYER ST TO END HEALY AVE - ABDY WAY TO MARINA DR JUNIPER CT - DOLPHIN CIR TO END KAREN CT - CALIFORNIA AVE TO END LAKE CT - SR 1 TO END LAKEWOOD DR - DREW ST TO ABDY WAY MAX CIR - REINDOLLAR AVE TO END MICHAEL DR - MICHELLE CT TO NORTH END QUEBRADA DEL MAR RD - COSTA DEL MAR RD TO SIRENA DEL MAR RD REDONDO CT - CARDOZA AVE TO END RESERVATON RD - SEASIDE CT. TO DEL MONTE BLVD RESERVATON RD - EB - DEL MONTE BLVD TO SEACREST AVE RESERVATON RD - WB - DEL MONTE BLVD TO SEACREST AVE RESERVATON RD - WB - BLANCO RD (WEST BOUND) TO IMJIN PARKWAY SANDPIPER WAY - DOLPHIN CIR TO END SUSAN AVE - VISTA DEL CAMINO TO MELANIE RD TAMARA CT - CALIFORNIA AVE TO END VISTA DEL CAMINO CIR - GEORGE WAY TO SOUTH END VISTA DEL SUR - SUSAN AVE TO END WILSON CT - ABRAMS DR TO SOUTH END

05/2019 06/2019 16 18 29 17

Monterey Monterey Road Maintenance & Rehabilitation

Reconstruction of Via Gayuba (Carryover from FY 17/18)

Construction of concrete curbs, gutters, sidewalks, sidewalk crossings (driveway approach) and curb ramps, storm drainage, signage and striping, isolated street and driveway surface repairs, pavement grinding, street reconstruction and hot mix asphalt pavement.

Via Gayuba (between Via Del Pinar and Mar Vista) 11/2018 08/2019 20 25 29 17

Monterey Monterey Road Maintenance & Rehabilitation

Reconstruction of Mar Vista and Skyline Drive

Construction of concrete curbs, gutters, sidewalks, sidewalk crossings (driveway approach) and curb ramps, storm drainage, signage and striping, isolated street and driveway surface repairs, pavement grinding, street reconstruction and hot mix asphalt pavement.

Mar Vista, from Skyline Drive to Monte Vista, and Skyline Drive, from Veterans Drive to Mar Vista 01/2019 06/2019 20 20 29 17

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 55: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pacific Grove Monterey Road Maintenance & Rehabilitation

Congress Avenue Street Rehabilitation

This will include necessary road rehabilitation on Congress Avenue between Sunset Drive and David Avenue. The project will include reconstruction of approximately 52,000 SF of roadway and concrete overlay on approximately 67,00 SF of roadway. This project will also include construction of a continuous pedestrian walkway and installation of ADA ramps. The City plans to use the entire SB1 FY18/19 allocation of $257,361 towards the road rehabilitation and maintenance portion of the Congress Avenue Road Rehabilitation Project.

Congress Avenue, from David Avenue to Sunset Drive. 03/2019 06/2019 15 20 29 17

Salinas Monterey Safety Striping and SigningUpgrade faded lane lines, crosswalks (various locations) and bike lanes (various locations). (Carryover from 17/18)

Bike lanes include Alisal Street (Work St. to Bardin Rd.); Abbot Street 06/2018 03/2019 5 7 30 12

Salinas Monterey Road Maintenance & Rehabilitation Circle Drive Improvements

Pavement repairs and asphalt concrete overlay on collector street Circle Drive, including striping. (Carryover from 17/18)

Circle Dr., between Sanborn Rd. and St. Edwards Dr. 09/2018 03/2019 25 50 30 12

Salinas Monterey Road Maintenance & Rehabilitation

San Juan Grade Road Improvements

Pavement repairs and asphalt concrete overlay on major arterial San Juan Grade Road, including striping. San Juan Grade Road, between Boronda Road and Russell Road. 09/2018 03/2019 25 50 30 12

Salinas Monterey Road Maintenance & Rehabilitation

Pavement Slurry Seal Improvements

Citywide pavement maintenance (slurry seal) and striping on major & minor arterials and local residential roads.

Constitution Blvd (E Laurel Dr to Boronda Rd); Natividad Rd (E Alvin Dr to E Boronda Rd); John St (Wood St to Alisal Rd); Freedom Pkwy (Constitution Blvd to Williams Rd); North Sanborn Rd (Del Monte Ave to Boronda Rd); East Laurel Dr (Natividad Rd to N Sanborn Rd); and residential streets citywide.

09/2018 03/2019 5 7 30 12

Salinas Monterey Traffic Control Devices Priority Traffic Signals 1-2 New traffic signals on City Priority List (1&2) (17/18 Ongoing) East Alvin Dr at Linwood Dr; Boronda Rd at Sanborn Rd 01/2018 12/2018 25 50 30 12

Sand City Monterey Road Maintenance & Rehabilitation

Contra Costa Street and Sidewalk Improvement Project

Curb, gutter, and sidewalk improvements; and adjacent street rehabilitation with new crosswalks. Contra Costa Street between Elder Avenue and Shasta Avenue 04/2022 09/2022 10 20 29 17

Seaside Monterey Road Maintenance & Rehabilitation

Fremont Boulevard Rehab (17/18 Ongoing) Remove & Replace failed storm drains & road sections South city limit to north city limit 05/2018 11/2018 1 5 29 17

Soledad Monterey Road Maintenance & Rehabilitation 2018 Streets Maintenance Project Repair of failed roadway sections (dig-out and replace with new asphalt concrete),

slurry/Cape Seal and re-striping of various roadways throughout City.

West Street, between Front and Market Front Street, between San Vicente Rd and Oak Street Benito Street, Between North

08/2018 10/2018 10 20 30 12

Soledad Monterey Complete Streets Components

Metz Road Traffic Calming Project (17/18 Ongoing)

Installation of accessible concrete bulb-outs at two intersections and one mid block crossing to create safe crossing locations for nearby elementary schools. Upgraded roadway striping will include left hand turn lanes, bike lanes, and upgraded high visibility crosswalks. The roadway will also have repairs made and an asphalt slurry seal applied for maintenance.

Metz Road between Walker and Third 04/2018 08/2018 20 30 30 12

American Canyon Napa Road Maintenance & Rehabilitation

2019 Annual Pavement Management Project Mill and overlay Arden Court, Kensington Way (E end to Chaucer), Knightsbridge Way (Elliott to Danrose), Lansford

Court, Linwood Lane, Park Lane, Regent Court and Strand Court 06/2019 07/2019 10 20 4 3

American Canyon Napa Road Maintenance & Rehabilitation

2018 Annual Pavement Management Project (17/18 Carryover8

Mill and Overlay Ascot Court, Bedford Lane, Brookshire Way, Capra Drive, Chaucer Court, Kent Way, Kingsly Lane, Knightsbridge Court, Knightsbridge Way (Danrose to Banbury) and Patricia Drive. 07/2018 08/2018 10 20 5 3

Calistoga Napa Other Design FY 19/20 Proejcts Hire consultants to design next years SB1 projects so they are shelf ready to bid Design of projects will include assessment of all City roadways and necessary improvements. 72/2018 06/2019 10 20 7 2

Calistoga Napa Complete Streets Components

North Half Sector A Sidewalk Replacement Replace damaged sidewalks in North Half of Sector A North of Washington between Lincoln Ave and Berry Street 07/2018 06/2019 10 20 7 2

Napa Napa Road Maintenance & Rehabilitation

SB 1 - Road Maintenance Project FY2018/19

The project generally includes the application of various preventative maintenance techniques on City streets. The treatments will include, but are not limited to: crack sealing, scrub sealing, rejuvenating seals and microsurfacing. Each technique is considered cost effective and will extend the life of pavements approximately 2 to 7 years by protecting the surface from the effects of aging, cracking, deterioration, and water infiltration while also enhancing the safety and appearance.

Project locations include (but are not limited to) maintenance areas and individual streets within the City of Napa: Browns Valley West, Central, Alta Heights, Westwood, Springwood Estates, Von Uhlit Ranch, Valle Verde Dr., Salvador Ave., Foster Rd. and Kaiser Rd. Area maps showing said locations are attached with the Council Resolution. All project locations listed are preliminary and may be subject to change.

07/2018 06/2019 2 7 4 3

Napa Napa Road Maintenance & Rehabilitation

SB 1 - Street Rejuvenation Project FY17/18 (FY17/18 Carryover)

The project generally includes (but is not limited to) the application of an asphalt rejuvenation sealant on more than 100 roadway segments (approximately 16 centerline miles). This process reverses the effects of aging due to environmental damage from sunlight and water. It is cost-effective and extends the life of the roadway 2-5 years.

Project locations include (but are not limited to) various neighborhoods within the City of Napa identified as: Young Ave. Area, Mac Tract, West Twin Oaks Area, Robinson Lane Area, River Park, Napa Valley Corporate Park, and ABC Streets. Area maps are attached. All project locations listed are preliminary and may be subject to change.

05/2018 06/2019 2 5 4 3

St. Helena Napa Road Maintenance & Rehabilitation 2017/18 Pavement Restoration Overlay 0.41 miles of roadway, upgrade curb ramps and striping Kennedy Court, El Bonita, and La Quinta 05/2018 08/2018 7 15 7 2

St. Helena Napa Road Maintenance & Rehabilitation

2018/19 Pavement Restoration Project Overlay 0.89 miles of roadway, upgrade curb ramps and striping Andrea Ave frm Kearney to Oak, Grove Ct frm Hunt to End, Kearney St frm Hillview to Pine, Spring St

frm Valleyview to Sylvaner, Spring St frm City limits to west of Sylvaner, Monte Vista frm Hunt to End 05/2019 08/2019 7 15 7 2

St. Helena Napa Complete Streets Components

Downtown Sidewalk and Pedestrian Project

Design downtown sidewalk and pedestrian improvements: sidewalk, curb ramps, bulb outs, landscape, furnishing, utilities. OBAG II Grant (2 year design with construction in FY20/21

Main Street (Highway 29) from Mitchell Drive to Pine Street 02/2020 10/2022 15 30 7 2

St. Helena Napa Complete Streets Components Sidewalk Gap Closure Project Complete a sidewalk gap closure project Hunt Avenue from Monte Vista Avenue to June Lane 05/2019 07/2019 15 30 7 2

Yountville Napa Road Maintenance & Rehabilitation

Annual Paving Maintenanc and Paving Program

Remove and replace - tree abatement and replace curbs, gutters, ADA Ramps, sidewalks. Yount Street (from Finnell to Mount St) 01/2019 04/2019 25 40 3 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 56: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Grass Valley Nevada Road Maintenance & Rehabilitation

2018 Annual Street Rehabilitation Project

Road Maintenance and Rehabilitation Account (RMRA) projects will resurface or repave several streets throughout the City of Grass Valley. Streets are selected and prioritized based on the City’s Pavement Management System in order to most effectively address deferred maintenance on the local street system and prioritize the delivery of basic street maintenance and rehabilitation projects

Bennett St, Brighton St, East Main St, Freeman Ln, McCourtney Rd, Mill St, and S Auburn St, Grass Valley, CA 06/2018 10/2018 15 20 1 1

Nevada City Nevada Road Maintenance & Rehabilitation Broad Street Y

This project consists of roadway rehabiliation. Sidewalk will be widened and enhanced at intersections to provide safe, convenient and efficient pedestrian access within the Downtown Historic District. Pavement improvements include replacement of deteriorated pavement and improvements to cross-slope for drainage. This project will help reduce traffic congestion and improve pedestrian safety which reduces vehicle emissions helping the State achieve its air quality and greenhouse gas emissions reductions goals.

Broad Street from Commerical Street to (and including) the intersection of West Broad Street and East Broad Street. 04/2019 11/2019 10 25 1 1

Nevada City Nevada Complete Streets Components

Commercial Street Improvements (17/18 Carryover)

This project consists of roadway rehabiliation. Sidewalk will be widened and enhanced at intersections to provide safe, convenient and efficient pedestrian access within the Downtown Historic District. Pavement improvements include replacement of deteriorated pavement and improvements to cross-slope for drainage. This project will help reduce traffic congestion and improve pedestrian safety which reduces vehicle emissions helping the State achieve its air quality and greenhouse gas emissions reductions goals.

Commercial Street from Union Street to York Street 08/2018 06/2019 10 25 1 1

Truckee Nevada Road Maintenance & Rehabilitation 2018 Slurry Seal Project C1801

The 2018 Slurry Seal Project would apply slurry seal to approximately 33 miles of local road, representing 78 roadway segments. A slurry seal is a cold-mix combination of asphalt emulsion, fine well-graded aggregate, and water. This is a versatile treatment which results in a smooth surface with adequate friction with moderate costs. Slurry seals have been used by the Town for several years and have proven to be a cost-effective preventive treatment that is well accepted by the community.

Various roads in the Town of Truckee including portions of the Tahoe Donner and Glenshire neighborhoods. 05/2018 06/2018 5 15 1 1

Truckee Nevada Road Maintenance & Rehabilitation 2019 Slurry Seal Project The 2019 Slurry Seal Project would apply slurry seal to approximately 29 miles of local

road, representing 124 roadway segments.Roads anticipated to be slurry sealed include residential roads in Tahoe Donner, Glenshire, Donner Lake, and Gray's Crossing. A map of the roads is included in the attached project description. 05/2019 10/2019 5 15 1 1

Aliso Viejo Orange Road Maintenance & Rehabilitation

Glenwood Terrace Association Public Streets Rehabilitation

Curb ramp upgrades; patching pavement cracks; grinding existing asphalt surface; installing new, fiber reinforced, asphalt rubber surface.

Glenwood Association Public Streets - Briarglen, Amber, Birchmont, Coralwind, Parkwood, Windflower, Spicewood, Lynoak, Eastwind 08/2018 12/2018 10 20 73 36

Aliso Viejo Orange Road Maintenance & Rehabilitation Alicia Parkway Rehabilitation

Sidewalk and curb ramp repairs/upgrades; patching failed pavement areas; grinding existing asphalt surface; installing new, fiber reinforced, asphalt rubber surface. Design work only in FY 18-19.

Alicia Parkway - Pacific Park Drive to City Limits 06/2019 10/2019 10 20 73 36

Aliso Viejo Orange Road Maintenance & Rehabilitation Slurry Seal Program FY 18-19 Repair of failed pavement areas; crack filling; installation of slurry seal. Association areas: Laguna Audubon II; Moulton Parkway 1, 2 and 3; California Renaissance, Altisse,

Seaway Collection 01/2019 06/2019 5 7 73 36

Anaheim Orange Road Maintenance & Rehabilitation Weir Canyon Road Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, AC berms, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 6) - Weir Canyon Road from Serrano Avenue to Parkglen Place 07/2018 01/2019 10 15 68 37

Anaheim Orange Road Maintenance & Rehabilitation

La Palma Avenue & Magnolia Avenue Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, the removal and reconstruction of ADA access ramps, curb and gutter, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 1) - La Palma Avenue from the West City Limit to Mayflower Street & Magnolia Avenue from the I-5 Freeway to La Palma Avenue 08/2018 02/2019 10 15 65 29

Anaheim Orange Road Maintenance & Rehabilitation Riverdale Avenue Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, the removal and reconstruction of ADA access ramps, curb and gutter, commercial driveway approaches, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 6) - Riverdale Avenue from the SR-91 Freeway to Lakeview Avenue 09/2018 02/2019 10 15 68 37

Anaheim Orange Road Maintenance & Rehabilitation

Blue Gum Street & Miraloma Avenue Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay and by constructing Jointed Plain Concrete Pavement (JPCP) at the intersection approaches on Miraloma Avenue and Blue Gum Street. The work also includes the removal and reconstruction of ADA access ramps, cross gutters, and the installation of new curb, gutter, sidewalk, and the replacement of traffic striping, traffic signal loops, and pavement markings.

(District 5) - Blue Gum Street from La Palma Avenue to the North City Limits Miraloma Avenue from the SR-57 Freeway bridge to Blue Gum Street, and a 527 foot segment of La Cresta Avenue starting at 264 feet east of Blue Gum Street going easterly

10/2018 03/2019 20 25 68 37

Anaheim Orange Road Maintenance & Rehabilitation Orange Avenue Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, the removal and reconstruction of ADA access ramps, curb and gutter, commercial driveway approaches, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 2) - Orange Avenue from Magnolia Avenue to Gilbert Street 11/2018 05/2019 10 15 65 29

Anaheim Orange Road Maintenance & Rehabilitation

Orangewood Avenue Rehabilitation from Harbor Boulevard to Lewis Street [APUE UD #64]

Project Partnering with APU-Electrical to cost share on the road rehabilitation of the impacted road segments due to the APU-Electrical underground conversion project currently in construction. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.

(District 4) - Orangewood Avenue from Harbor Boulevard to Lewis Street 08/2017 11/2018 10 15 69 34

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 57: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Anaheim Orange Road Maintenance & Rehabilitation

Orangethorpe Avenue & Kraemer Boulevard Rehabilitation [OCTA Bridges]

Project partnering with the City of Placentia and OCTA to cost share on the road rehabilitation of the impacted road segments due to the Kraemer Grade Separation Project and Orangethorpe Grade Separation Project constructed by OCTA. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, slurry seal, the replacement of traffic striping, traffic signal loops, pavement markings, curb and gutter, sidewalk, and an ADA access ramp.

(District 5) - Orangethorpe Avenue from the Kraemer Boulevard Intersection easterly on Orangethorpe Avenue to the end of the Orangethorpe Grade Separation project limit and southerly on Kraemer Boulevard to East La Jolla Street

07/2018 09/2018 10 15 68 37

Anaheim Orange Road Maintenance & Rehabilitation

Arterial Slurry Seal Group 2 – Various Locations Ball Road from Beach Boulevard to Dale Avenue; La Palma Avenue from Chrisden Street to Potomac Circle; Santa Ana Canyon Road from Fairmont Boulevard to Mohler Drive;

The road rehabilitation work consists of applying a crack sealant and slurry seal coat to the existing pavement. Some minor cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.

(Districts 1, 6) - Ball Road from Beach Boulevard to Dale Avenue La Palma Avenue from Chrisden Street to Potomac Circle Santa Ana Canyon Road from Fairmont Boulevard to Mohler Drive

07/2018 08/2018 5 7 65, 68 29, 37

Anaheim Orange Road Maintenance & Rehabilitation

Lincoln Avenue Rehabilitation from State College Boulevard to Sunkist Street

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, the removal and reconstruction of ADA access ramps, curb and gutter, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 5) - Lincoln Avenue from State College Boulevard to Sunkist Street 01/2018 07/2018 10 15 69 29, 34

Anaheim Orange Road Maintenance & Rehabilitation Orange Avenue Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay or applying a slurry seal, the removal and reconstruction of ADA access ramps, curb and gutter, commercial driveway approaches, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 1) - Orange Avenue from Western Avenue to Dale Avenue 01/2018 07/2018 10 15 65 29

Anaheim Orange Road Maintenance & Rehabilitation

Lincoln Avenue & Rio Vista Street Rehabilitation [APUE UD #63]

Project Partnering with APU-Electrical to cost share on the road rehabilitation of the impacted road segments due to the APU-Electrical underground conversion project currently in construction. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.

(District 5) - Lincoln Avenue from Sunkist Street to Rio Vista Street and Rio Vista Street from Lincoln Avenue to La Palma Avenue 08/2016 10/2018 10 15 68, 69 29, 34, 37

Anaheim Orange Road Maintenance & Rehabilitation

La Palma Avenue Rehabilitation from East Street to N. Acacia Street [PW Sewer]

Project partnering with PW-Sewer Section to cost share on the road rehabilitation of the impacted road segments due to the PW-Sewer improvement project currently in construction. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.

(District 5) - La Palma Avenue from East Street to N. Acacia Street 02/2018 09/2018 10 15 69 29

Anaheim Orange Road Maintenance & Rehabilitation

Central Anaheim Rehabilitation at County Limits

Project partnering with the County of Orange to cost share on the road rehabilitation of City streets. The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, the removal and reconstruction of ADA access ramps, curb and gutter, commercial driveway approaches, concrete sidewalk, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 2) - Gilbert Street from Broadway to Orange Avenue; Broadway from Greenwhich Street to Brookhust Street; Ball Road from Gilbert Street to Perdido Street

03/2018 07/2018 10 15 65 29

Anaheim Orange Road Maintenance & Rehabilitation Acacia Neighborhood Rehabilitation

The work consists of removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing pavement striping and pavement markings.

(District 5) - Acacia Neighborhood bordered by Via Burton Street to the north, State College Boulevard to the east, Lincoln Avenue to the south, and East Street to the west 10/2018 06/2019 7 20 69 29

Anaheim Orange Road Maintenance & Rehabilitation

Kings Court Neighborhood Rehabilitation

The work consists of removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing pavement striping and pavement markings.

(District 2) - Kings Court Neighborhood bordered by Ball Road to the north, Euclid Street to the east, Katella Avenue to the south, and Brookhurst Street to the west 05/2018 06/2019 7 20 65 29

Anaheim Orange Road Maintenance & Rehabilitation

Northeast Anaheim Colony (Sabina) Neighborhood Rehabilitation (Project - A)

The project will address poor drainage areas throughout the community by constructing new concrete curb and gutter. The project improvements will also include cold planing and resurfacing the road with an asphalt concrete overlay, the replacement and construction of new ADA access ramps, and the replacement of uneven and broken sidewalks.

(District 3) - Sabina Neighborhood (Project A) - bordered by La Palma Avenue to the north, Anaheim Boulevard to the east, Sycamore Street to the south, and Harbor Boulevard to the west 05/2018 06/2019 7 20 69 29

Anaheim Orange Road Maintenance & Rehabilitation

Northeast Anaheim Colony (Sabina) Neighborhood Rehabilitation (Project - C)

The project will address poor drainage areas throughout the community by constructing new concrete curb and gutter. The project improvements will also include cold planing and resurfacing the road with an asphalt concrete overlay, the replacement and construction of new ADA access ramps, and the replacement of uneven and broken sidewalks.

(District 3) - Sabina Neighborhood (Project - C) - bordered by La Palma Avenue to the north, East Street to the east, Sycamore Street to the south, and Pauline Street to the west 01/2019 06/2019 7 20 69 29

Anaheim Orange Road Maintenance & Rehabilitation

Santa Ana Canyon Road Rehabilitation

The road rehabilitation work consists of cold planing and resurfacing the road with an asphalt concrete overlay, AC berms, and replacement of traffic striping, traffic signal loops, and pavement markings.

(District 6) - Santa Ana Canyon Road from Riverview Drive to Gypsum Canyon Road 04/2019 06/2019 10 15 68 37

Anaheim Orange Road Maintenance & Rehabilitation Arterial Sidewalk Repairs - Phase III

Project conisiting of strategic arterial sidewalk repair in phases. This will be Phase III of the program. The work includes removal and reconstruction of concrete sidewalk, curb and gutter, driveway approaches and ADA access ramps. This project will improve pedestrian mobility. Scope of Phase III equates to approximately 15.12 miles of sidewalk rehabilitation.

(Districts 3, 4) - Phase III of the program will include all north, south, east, and west arterial streets from Euclid Street to Harbor Boulevard (excluding work on Harbor) and to the City limits north and south.

08/2018 06/2019 10 15 65, 69 29, 34

Brea Orange Road Maintenance & Rehabilitation

Cliffwood Industrial Park Pavement Rehabilitation Project FY 17/18 Carryover

This project will rehabilitate the pavement on Cliffwood Street, Oak Place, Thor Place and Telstar Way. City of Brea, Ca within the Cliffwood Industrial Park Subdivision 08/2018 01/2019 10 20 55 29

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 58: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Brea Orange Road Maintenance & Rehabilitation Puente Street Rehabiliation

his project will rehabilitate Puente Street from Imperial Highway to Lambert Road. Improvements consist of reconstructing existing asphalt pavement, replacing damaged sidewalk, curb, gutter and upgrading existing curb access ramps to current Americans with Disabilities Act (ADA) requirements. Coordination with Caltrans is required for permit and construction.

The Project is located within the City of Brea on Puente Street from Lambert Road to Imperial Highway (SR 90) 02/2019 06/2019 10 20 55 29

Buena Park Orange Road Maintenance & Rehabilitation Descanso Avenue Rehabilitation

1/3 mile Descanso Avenue roadway rehabilitation with AC. Includes removal and replacement of curb & gutter, sidewalk, accessible ramps, driveway approaches, signing & striping, utility adjustments, and other incidentals.

City of Buena Park - Descanso Avenue between Altura Boulevard and Caballero Boulevard 06/2018 12/2018 10 15 65 32

Buena Park Orange Road Maintenance & Rehabilitation La Palma Avenue Rehabilitation 3/4 mile AC arterial roadway rehabilitation and replacement of curb & gutter, sidewalk,

accessible ramps, driveway approaches, signing & striping, and other incidentals. City of Buena Park - La Palma Avenue from Beach Boulevard to Knott Avenue 06/2018 06/2019 10 15 65 32

Costa Mesa Orange Road Maintenance & Rehabilitation

Bear Street Improvements, from I-405 to Baker Street

This project will provide major rehabilitation to 1,900 miles of City streets which are in immediate need for improvement. The project is implemented in accordance with the Pavement Management System to meet the City Council Goal to reach and maintain an average Citywide Pavement Condition Index (PCI) of 85. These RMRA funds will be used towards rehabilitation of Bear Street, from I-405 to Baker Street.

Bear Street, from I-405 to Baker Street 12/2018 06/2019 10 10 74 37

Costa Mesa Orange Road Maintenance & Rehabilitation

Fairview Road Improvements, from I-405 to Adams Avenue

This project will provide major rehabilitation to 6,768 miles of City streets which are in immediate need for improvement. The project is implemented in accordance with the Pavement Management System to meet the City Council Goal to reach and maintain an average Citywide Pavement Condition Index (PCI) of 85. These RMRA funds will be used towards rehabilitation of Fairview Road, from I-405 to Adams Avenue.

Fairview Road, from I-405 to Adams Avenue 12/2018 06/2019 10 10 74 37

Cypress Orange Road Maintenance & Rehabilitation

FY 2018-19 Annual Street Rehabilitation Project

The scope of work consists of slurry sealing over 250,000 SF of arterial roadway and resurfacing approximately 250,000 SF of pavement using rubberized asphalt concrete (RAC). The proposed project also includes incidental items of work, such as traffic striping, traffic loops, manhole adjustments, etc.

•Holder Street (Ball Road to Orange Avenue) •Walker Street (Ball Road to Orange Avenue) •Katella Avenue (Walker Street to Valley View Street)

10/2018 01/2019 8 20 65 29

Dana Point Orange Road Maintenance & Rehabilitation

FY18-19 Annual Residential Resurfacing, Curb & Gutter Project

This resurfacing program is intended to rehabilitate non-arterial streets including, residential, residential collector and collector streets.

The project location includes Via California from Camino Capistrano to Via Lopez and Pequito Drive from La Cresta Drive to the cul-de-sac. Additional streets may be added. 09/2018 01/2019 20 25 73 36

Fountain Valley Orange Road Maintenance & Rehabilitation

Residential Roadway Rehabilitation and Resurfacing Residential Roadway Rehabilitation and Resurfacing of Quadrant H2

Quadrant H2: Mt Marcey Ct, Evans Cir, Mt. Erebus Ct, Catskills St, Mt Tahat St, Mt Olancha St, Whitecap Cir, Diamond Ct, Amethyst Ct, Jade Ct, Carnation Ct, Shasta St, Suzette River Cir, Marigold Cir, Orchid Ave, Violet Cir, San Gabriel St, Mayflower Cir, Iris Ave, Everest Cir, Rosemary Ave, San Jacinto Cir, Sierra St, Mt Mennes Ct, Ruby Ct, Mt Ackerman Ct, Mt Musala Ct, Holly Ave, Mt Pico Ct, Richardson St, San Jacinto St, Mt Lister Ct, Poppy Ave, Mt Carmel Ct, Everest St, Lilac Ave, Turquoise Cir, Mt Kenya Ct, Zircon Ct, Foothill St, Azalea Ave, Mt Robert Ct

05/2018 09/2018 10 15 72 34

Fountain Valley Orange Road Maintenance & Rehabilitation

Euclid Street Rehabilitation and Resurfacing from Slater Avenue to Warner Avenue

Euclid Street Rehabilitation and Resurfacing from Slater Avenue to Warner Avenue Euclid Street from Slater Avenue to Warner Avenue 12/2017 06/2018 10 15 72 34

Fullerton Orange Road Maintenance & Rehabilitation

Commonwealth / Raymond Avenue Rehabilitation Project

The project street is functionally classified as arterial street and mostly consists of four (4) lanes with two (2) lanes on each direction on Commonwealth Avenue and additional median lane on Raymond Avenue. Total length of the street is approximately 1.25 miles with 60 feet wide pavement. The work includes reconstruction and grind & overlay of pavement to extend the roadway service life and to reconstruct; curb, and gutter, access ramp, cross gutter, manhole and valve adjustment to grade, traffic striping, and replace traffic loop detectors all within the City right-of-way. In conjunction with the street improvements, the project will replace water and sewer mains paid by other funds. The identified estimated total project cost ($5,331,945) is including water and sewer improvements. The street improvements cost alone is estimated to be $3,270,000.

Commonwealth Avenue from Balcom Avenue to Acacia Drive and Raymond Avenue from Commonwealth Avenue to Chapman Avenue. 04/2019 02/2020 10 20 65 29

Fullerton Orange Road Maintenance & Rehabilitation

Chapman Avenue Rehabilitation Project (Carryover from FY 2017-18)

The project street is functionally classified as arterial street and mostly consists of five lanes with two (2) lanes on each direction with median lane. Total length of the street is approximately 1.2 miles with 60-70 feet wide pavement. The work includes grind and overlay of asphalt concrete to extend the roadway service life and to reconstruct; curb, and gutter, access ramp, cross gutter, manhole and valve adjustment to grade, traffic striping, and replace traffic loop detectors all within the City right-of-way.

Chapman Avenue between; Acacia Avenue to 57 Freeway/Caltrans right-of-way excluding Commonwealth Avenue to Clarke Avenue and State College Blvd to Sycamore Avenue. 08/2018 12/2018 10 20 65 29

Garden Grove Orange Road Maintenance & Rehabilitation

Euclid Street & Chapman Avenue Rehabilitation Project

The Project will rehabilitate Euclid Street from Patricia Drive to Katella Avenue and Chapman Avenue from Brookhurst Street to Nelson Street. The Project also includes rehabilitation of residential streets: Sapphire Street (Belgrave - Vanguard), Santa Rita Avenue (Lamplighter to Vanguard to Wild Goose) and Healey at Lamplighter.

For the Euclid segment of the project, the location will be on Euclid Street, from Patricia Drive to Katella Avenue . For the Chapman segment of the project, the location will be on Chapman Avenue from Brookhurst Street to Nelson Street. For the residential streets, the locations are: Sapphire Street (Belgrave - Vanguard), Santa Rita Avenue (Lamplighter to Vanguard to Wild Goose) and Healey at Lamplighter.

03/2019 04/2019 10 20 65, 69 34

Garden Grove Orange Road Maintenance & Rehabilitation

Euclid Street Rehabilitation (Hazard Avenue - Westminster Street)

The City of Santa Ana is the lead agency responsible for rehabilitating Euclid Street, from Hazard Avenue to Westminster Street. The City of Garden Grove owns the westerly 12' of pavement and will contribute funding for their portion of the project.

On Euclid Street, from Hazard Avenue to Westminster Street. 07/2018 12/2018 10 20 65, 69 34

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 59: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Garden Grove Orange OtherLa Bonita Storm Drain Project (Westminster Avenue - Anabel Avenue)

The Project will install dual 30' RCPs to facilitate water service access on La Bonita Street, from Westminster Avenue to Anabel Avenue. On La Bonita Street, from Westminster Avenue to Anabel Avenue in the City of Garden Grove. 07/2018 12/2018 10 20 65, 69 34

Garden Grove Orange Road Maintenance & Rehabilitation

Westminster Rehabilitation (Harbor-Roxey)

The project will rehabilitate Westminster Avenue, from Harbor to Roxey, including miscellaneous concrete improvements. On Westminster Avenue, from Harbor Blvd. to Roxey Drive, in the City of Garden Grove. 03/2018 07/2018 10 20 65, 69 34

Huntington Beach Orange Road Maintenance & Rehabilitation Arterial Rehabilitation Project Project will utilize RMRA funding in addition to local funding to fully rehabilitate up to 8

arterial street segments.

Edinger Avenue (Graham-Bolsa Chica), Saybrook Street (Heil-Edinger), Algonquin Street (Warner-Heil), Slater Avenue (Beach-Gothard), Newland Street (Yorktown-Garfield), Graham Street (Warner-Springdale), Delaware Street (Main-Ellis), Atlanta Avenue (Bushard-Brookhurst)

10/2018 10/2019 15 25 74 37

Huntington Beach Orange Road Maintenance & Rehabilitation

Arterial Rehabilitation Project (FY 17/18 Project)

This is the FY 17/18 Project which is being rolled over since the project will not have been completed by June 30, 2018. The RMRA funding will be utilized to maintain and/or improve on the "Good" condition of the City's street network, specifically concentrating on its arterial highway segments. The city utilizes HMRA asphalt, which contains crumb rubber from tires that would otherwise end up in landfills. Use of HRMA also extends the design life of the project.

Heil Avenue (Bolsa Chica-Graham) and Indianapolis Avenue (Beach-Newland) 05/2018 09/2018 15 25 74 37

Irvine Orange Road Maintenance & Rehabilitation

Jamboree Pavement Rehabilitation - Michelle to Railroad Tracks

Rehabilitation and replacement of deteriorated asphalt pavement, concrete curbs, gutters, access ramps, and sidewalks. Jamboree Road between Michelle Drive and the OCTA railroad overcrossing bridge. 03/2019 12/2019 20 20 68 37

Irvine Orange Road Maintenance & Rehabilitation

Alton Pavement Rehabilitation - I-5 Freeway to Technology Drive East

Rehabilitation and replacement of deteriorated asphalt pavement, concrete curbs, gutters, access ramps, and sidewalks. Alton Pavement Rehabilitation - I-5 Freeway to Technology Drive East 12/2018 09/2019 20 20 68 37

La Habra Orange Road Maintenance & Rehabilitation

Idaho Street Pavement Project (17/18 Ongoing)

The Project consists of grind and overlay the full width of the street, reconstruction of damaged curb ramps, sidewalk, and curb and gutter. Idaho Street from La Habra Boulevard to Whittier Boulevard in the City of La Habra, CA 06/2018 09/2018 15 15 55 29

La Habra Orange Road Maintenance & Rehabilitation

La Habra Boulevard Pavement from Beach Boulevard to Idaho Street

The project consists of grind and overlay the full width the street, reconstruction of damaged curb ramps, sidewalk, and curb and gutter. La Habra Boulevard from Beach Boulevard to Idaho Street in the City of La Habra, CA 04/2019 06/2019 15 15 55 29

La Palma Orange Road Maintenance & Rehabilitation Valley View Street Rehabilitation Rehabilitation including crack sealing, dig-outs, and slurry seal (PW Contract). South City Limit to Thelma Avenue 07/2018 04/2019 7 10 65 29

La Palma Orange Road Maintenance & Rehabilitation

Orangethorpe Avenue Rehabilitation (17/18 Carryover) Rehabilitation including grinding, paving, and thermal striping ( PW Contract). Moody Street to Walker Street 02/2018 08/2018 7 10 65 29

La Palma Orange Road Maintenance & Rehabilitation Orangethorpe Avenue Rehabilitation Rehabilitation including grinding, paving, and thermal striping (PW Contract). Walker Street to Valley View street 05/2018 10/2018 7 10 65 29

La Palma Orange Road Maintenance & Rehabilitation Walker Street Rehabilitation Rehabilitation including crack sealing, dig-outs, and slurry seal La Palma Avenue to 183rd Street 07/2018 06/2019 7 10 65 29

La Palma Orange Road Maintenance & Rehabilitation Arterial Street Medians (Phase 1) Rehabilitation including curb repairs, tree and landscape removal, irrigation, hard and

soft scape installation

Citywide Project - North, South, East, and West City Limits. All locations will be selected and addressed based on priority need and resources throughout the year, locations may be subject to change prior to work commencing.

12/2018 06/2019 15 20 65 29

Laguna Beach Orange Road Maintenance & Rehabilitation

Zone 1 Street Slurry Seal and Rehabilitation

patch damaged pavement; seal cracks; apply Type 1 slurry seal; refresh pavement striping and markings All City maintained streets between Montage Resort Drive and southerly City limits. 08/2019 12/2019 8 12 74 37

Laguna Beach Orange Road Maintenance & Rehabilitation

Zone 2 Street Concrete Rehabilitation

Remove and replace damaged concrete curbs, gutters, and sidewalks at various locations Citywide.

“All City maintained streets in the area bounded by Park Avenue, Wendt Terrace, and Thalia Street”. *All locations listed are an estimate and may be subject to change based on priority need and resources throughout the year.

04/2019 09/2019 25 35 74 37

Laguna Beach Orange Road Maintenance & Rehabilitation Citywide Guard Rail Repairs Replace or modify damaged guard railings at various locations Citywide.

Existing guard railing locations within the Diamond/Crestview neighborhood and along hillside collector roads including, but not limited to, Park Avenue, Alta Vista Way, Bluebird Canyon Drive, Summit Drive, Nyes Place *All locations listed are an estimate and may be subject to change based on priority need and resources throughout the year.

09/2019 12/2019 20 30 74 37

Laguna Beach Orange Other Bent Street Drainage Improvements Re-contour roadway to improve drainage and reduce flooding. Bent Street between 450 Bent Street and Park Avenue 06/2020 12/2020 20 30 74 37

Laguna Beach Orange Road Maintenance & Rehabilitation

2080 Crestview Drive Road Edge Support Reconstruct, support and protect roadway edge adjacent to steep natural slope. West edge of roadway near 2080 Crestview Drive 06/2020 12/2020 20 30 74 37

Laguna Beach Orange Road Maintenance & Rehabilitation

Fiscal Year 2017/2018 Street Slurry Seal and Rehabilitation (17/18 Carryover)

Repair damaged pavement and slurry seal the streets that were last rehabilitated in 2008.

Laguna Canyon Frontage Road, Arroyo Drive, Woodland Drive, Canyon Acres Drive, and the area between Thalia Street and Cress Street. 05/2018 11/2018 8 12 74 37

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 60: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Laguna Hills Orange Road Maintenance & Rehabilitation

Citywide Street Maintenance, CIP No. 101-K

Pavement repairs and resurfacing of various residential and collector streets within the City's PMP zones of "C" and "E".

Multiple street segments in Zones C and E as follows: STREET NAME FROM - TO Alameda Av Aliso Hills Dr-La Paz Rd Alisal Av Linda Vista Dr-Paseo De Valencia Alisal Av Sarita Dr-Linda Vista Dr Aliso Hills Dr Alameda Av-Alicia Pw Aliso Hills Dr La Paz Rd-Alameda Av Alta Loma Ct Santa Rosa Av-East End Altamira Dr Alameda Av-Buena Vista Dr Amalia St Yolanda St-Carmel St Anacapa St San Pedro Av-El Prado St Andrea St Lupita St-North End Buena Vista Dr Los Gatos Dr-North End Calero Av La Mirada St-El Conejo Ln Carmel St South End-North End Creek Dr Linda Vista Dr-South End Creekview Dr West End-Christina Ct Del Monte St Alameda Av-La Cuesta Av El Capitan Ln Creek Dr-Largo Dr El Conejo Ln Linda Vista Dr-Calero Av El Prado St Alameda Av-San Pedro Av El Segundo St Aliso Hills Dr-North End Elena Dr Los Gatos Dr-Alameda Av Encanto Ct Luna Bonita Dr-South End Ernestine Ct Linda Flora St-North End Eva St Lupita St-Yolanda ST Gordon Rd Moulton Pw-Imperial Dr La Cienega St La Cienega St-Aliso Hills Dr La Cienega St Rio Grande Av-Sierra Bonita Dr La Cuesta Av Terra Bella Av-Sausalito St La Habra Ct Sarita Dr-East End La Mirada St Alisal Ln-Linda Vista Dr La Serra St Aliso Hills Dr-North End Las Alturas Av Mandeville Dr-Monte Royale St Las Alturas Ct Las Alturas St-East End Linda Flora St East End-El Segundo St Linda Vista Dr Largo Dr-Sarita Dr Los Alamitos Monte Royals St-Mandeville Dr Los Cerros St La Cienega St-South End Los Gatos Dr Buena Vista Dr-West End

09/2019 02/2020 7 15 73 36

Laguna Niguel Orange Road Maintenance & Rehabilitation

Niguel Road Pavement Rehabilitation Project

Roadway Maintenance and repair including the repair of isolated areas of pavement, pavement grinding and removal, asphalt pavement overlay, associated concrete improvements including bus pads and access ramps, adjustment of surface utilities to final pavement grade, and roadway marking and striping.

Niguel Road from Marina Hills Road to Highlands Avenue 01/2019 04/2019 12 15 73 36

Laguna Niguel Orange Road Maintenance & Rehabilitation

Alicia Parkway Pavement Rehabilitation Project (17/18 Carryover)

Roadway maintenance and repair including the repair of isolated areas of pavement, pavement grinding and removal, asphalt pavement overlay, associated concrete improvements including bus pads and access ramps, adjustment of surface facilities to final pavement grade, and roadway marking and striping.

Alicia Parkway from Highlands Avenue to Pacific Park Drive 06/2018 08/2018 12 15 73 36

Laguna Woods Orange Road Maintenance & Rehabilitation

Pavement Management Plan Project (Eastbound El Toro Road between Avenida Sevilla and Church Intersection)

This project involves the rehabilitation of approximately 1,000 linear feet of pavement on eastbound El Toro Road between Avenida Sevilla and Church Intersection, including replacement of deteriorated pavement and a surface seal of crack sealant and rubberized slurry.

Eastbound El Toro Road between Avenida Sevilla and Church Intersection 10/2018 06/2019 5 5 74 37

Lake Forest Orange Road Maintenance & Rehabilitation Slurry Seal, Zone B Slurry Seal of Non-Arterial Streets within Zone B. The non-arterial public streets generally between Ridge Route Drive to the southerly City limit and

Jeronimo Road to the westerly City limit. 07/2018 10/2018 7 10 68 37

Lake Forest Orange Road Maintenance & Rehabilitation

Dimension Road from Bake Parkway to Lake Forest Drive Asphalt Reconstruction on Dimension Road from Bake Parkway to Lake Forest Drive. Dimension Road from Bake Parkway to Lake Forest Drive. 05/2019 08/2019 15 20 68 37

Lake Forest Orange Road Maintenance & Rehabilitation

Civic Center Drive from Commercentre Drive to dead-end approximately 1,400 feet to the South

Asphalt Reconstruction on Civic Center Drive from Commercentre Drive to dead-end approximately 1,400 feet to the South. Civic Center Drive from Commercentre Drive to dead-end approximately 1,400 feet to the South. 05/2019 08/2019 15 20 68 37

Los Alamitos Orange Road Maintenance & Rehabilitation

Portion of Greenbrook Neighborhood Street Rehabilitation Project

Design and construction of grinding and overlay of part of the Greenbrook Neighborhood on Humboldt St from Cerritos Ave to Myra Ave and San Mateo Ave from Humboldt St to end of cul-de-sac.

Humboldt St from Cerritos Ave to Myra Ave and San Mateo Ave from Humboldt St to end of cul-de-sac 08/2018 10/2018 20 30 72 34

Los Alamitos Orange Road Maintenance & Rehabilitation

Portion of Greenbrook Neighborhood Street Rehabilitation Project

This is a carryover from FY 2017-18 SB1 project. Approximately 100 feet of street grind and overlay with rubberized asphalt concrete and 200 feet of slurry seal.

Lassen Street from San Joaquin Ave to north end of cul de sac, San Joaquin Ave from Lassen St to eastern end of cul de sac and Sierra Circle from Cerritos Ave 05/2018 08/2018 20 30 72 34

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 61: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Mission Viejo Orange Road Maintenance & Rehabilitation Residential Resurfacing

The City of Mission Viejo has established seven, distinct geographic areas to conduct the resurfacing of public residential streets in the City. Each year, one of the seven areas is budgeted as a capital improvement project (CIP) for public residential streets resurfacing. The program operates on a rotating, seven-year cycle. In FY 2018-19, Residential Resurfacing Area 7 is scheduled for residential street resurfacing. This project will resurface, with overlay and slurry seal treatments, 62.63 lane miles of public residential streets in Area 7. There are 166 public residential streets in Area 7. The purpose of the City of Mission Viejo seven-year residential resurfacing program is to regularly maintain and improve the pavement condition of the City's residential public streets. The seven-year cycle achieves a maximum useful life of the pavement treatments, to prevent the streets from degrading into more expensive pavement conditions that would require more expensive resurfacing treatments.

Public residential streets in Residential Resurfacing Area 7, which is bounded by Los Alisos Boulevard to the north, La Paz Road to the south, the City of Mission Viejo jurisdictional boundary to the east, and Marguerite Parkway to the west, in the City of Mission Viejo.

07/2018 11/2018 7 20 73 36

Mission Viejo Orange Road Maintenance & Rehabilitation

Felipe Road/Olympiad Road Arterial Resurfacing

In Fiscal Year 2018-19, the arterial streets of Felipe Road and Olympiad Road in the City of Mission Viejo will be resurfaced with overlay treatment. The resurfacing project will overlay 14.54 lane miles of arterial streets, and will tackle pavement conditions on roadway segments along Felipe Road and Olympiad Road which have been classified as "fair" and "good" in a preliminary 2018 Citywide Pavement Management Program Update.

On Olympiad Road, from Alicia Parkway south to Jeronimo Road; and, on Felipe Road, from La Paz Road south to Marguerite Parkway, in the City of Mission Viejo. 06/2019 10/2019 15 20 73 36

Newport Beach Orange Road Maintenance & Rehabilitation

MacArthur Blvd and University Dr Pavement Rehab (17/18 Carryover)

This project grinds and overlays sections of MacArthur Boulevard and University Drive with rubberized asphalt concrete. Reconstruction of deteriorated concrete improvements is also included.

MacArthur Boulevard from Bonita Canyon Road to SR 73 and University Drive from Jamboree Road to State Route 73. 09/2018 02/2019 15 25 74 37

Newport Beach Orange Road Maintenance & Rehabilitation

San Joaquin Hills Road Pavement Rehabilitation

This project involves coldmilling and overlaying the existing asphalt concrete pavement with rubberized asphalt concrete. Deteriorated concrete improvements will also be reconstructed. Impacted utilities will be adjusted to grade. The new pavement will also be restriped. Final design is scheduled to be completed by Summer of 2019 and construction will be completed by Winter 2020. The estimated useful life of this project is 15 years minimum.

This project is located on San Joaquin Hills Road from Jamboree Road to MacArthur Boulevard . 08/2019 12/2020 15 20 74 37

Orange Orange Road Maintenance & Rehabilitation Pavement Rehabilitation FY 18/19

The Pavement Rehabilitation Project will maintain and rehabilitate approximately 18 Streets for a total of 25,270 linear feet for a total of 1,385,335 square feet of pavement. The construction activities will consist of slurry seal, cold planning, and overlay operations. In addition to the pavement rehabilitation the City will improve access ramps within the project limits along with other construction activities related to pavement rehab such as, adjusting valve boxes, manhole rings, crack sealant, and striping.

1. Burton Avenue From West End To Chouteau Street 2. Chouteau Street From Emerson Avenue To Burton Avenue 3. Chouteau Street From Buckeyewood Avenue To South End 4. Cleveland Street From Meats Avenue To Del Mar Avenue 5. Del Mar Avenue From Cleveland Street To Chouteau Street 6. Del Mar Avenue From Chouteau Street To Cambridge Street 7. El Sereno Drive From Santiago Boulevard To Riding Way 8. Emerson Avenue From Pine Street To Chouteau Street 9. Gates Avenue From Cleveland Street To East End 10. Genesse Street From North End To Grove Avenue 11. Genesse Street From North End To Del Mar Avenue 12. Keokuk Street From North End To Grove Avenue 13. Namuria Street From North End To Grove Avenue 14. Pine Street From Meats Avenue To Emerson Avenue 15. Ridgewood Street From Buckeyewood Avenue To South End 16. Shaffer Street From Meats Avenue To Buckeyewood Avenue 17. Shaffer Street From Buckeyewood Avenue To Taft Avenue 18. Winlock Street From Buckeyewood Avenue To South End 19. Woodside Street From Buckeyewood Avenue To South End 20. Chapman Ave From Newport Boulevard To Trails End Lane 21. Chapman Ave From Trails End Lane To Jamboree Road 22. Meats Avenue From 280' W/0 Feather Hill To Summitridge Lane 23. Meats Avenue From Summitridge Lane To Marywood Drive 24. Meats Avenue From Marywood Drive To Via Escola 25. "Meats Avenue From Via Escola To 1065' N/O Via Escola (City Limit)" 26. Newport Boulevard From White Oak Ridge To Chapman Ave 27. Newport Boulevard From Chapman Avenue To Santiago Canyon Road 28. Taft Avenue From Tustin Avenue To Sacramento Street 29. Taft Avenue From Sacramento Street To Fern Street 30. Taft Avenue From Fern Street To Santiago Boulevard 31. Tustin Street From 400' S/O Lincoln Avenue To 150' N/O Heim Avenue

05/2019 12/2019 10 15 68 37

Placentia Orange Road Maintenance & Rehabilitation

FY 2018-19 Street Resurfacing Project Phase 1

This project will rehabilitate 191,000 square feet of residential streets utilizing central plant recycling in lieu of a traditional reconstruction project. This method will allow the City to recycle the existing pavement and aggregate in order to reconstruct the roadway. This methodology will save money as well as reduce greenhouse gas emissions. If successful, the City will employ pavement recycling projects in future road rehabilitation efforts.

See attached map. Residential neighborhood at Bastanchury Road and McCormack on our border with the City of Yorba Linda. 10/2018 04/2019 15 20 55 29

Placentia Orange Road Maintenance & Rehabilitation

FY 2017-18 Residential Slurry Seal Project

Preventative maintenance slurry seal project for approximately 400,000 square feet of residential streets. NOTE: This project is replacing project LSR-2018-5269. Based on available funding, slurry seal project LSR-2018-5269 is being scaled back

Residential neighborhood northwest of the Kraemer Boulevard/Golden Avenue intersection. This project is a scaled back version of project LSR-2018-5269 to fit within available SB 1 funding. 05/2018 06/2018 5 7 55 29

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 62: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rancho Santa Margarita Orange Road Maintenance &

Rehabilitation Avenida de las Flores Slurry Seal

Avenida de Las Flores is a heavily utilized corridor within the City that is in need of a slurry seal treatment. The segment spanning from Avenida de las Banderas at the south end to Antonio Parkway to the north has a weighted PCI of 69. By applying a slurry seal this year, the pavement life can be extended for this facility. Isolated areas of full depth removals will be identified and constructed prior to the slurry seal application, along with crack sealing of the existing cracks.

Avenida de las Flores, between Avenida de las Banderas and Antonio Parkway in the City of Rancho Santa Margarita. 02/2019 03/2019 5 7 73 36

Rancho Santa Margarita Orange Road Maintenance &

Rehabilitation Antonio Parkway Slurry Seal Project

This project will slurry seal the northernmost segment of Antonio Parkway from Las Flores to Santa Margarita Parkway, with the potential to be combined with Project 7 above. This segment of Antonio Parkway has an average PCI of 68 and was identified as a candidate for slurry seal. Isolated areas of full depth removal will be identified and construction, as well as crack sealing prior to the application of the slurry seal.

Antonio Parkway, between Santa Margarita Parkway and Avenida de las Flores in the City of Rancho Santa Margarita 03/2019 04/2019 5 7 73 36

Rancho Santa Margarita Orange Road Maintenance &

RehabilitationAvenida Empresa Pavement Rehabilitation Project

This project will rehabilitate the pavement along Avenida Empresa (a major arterial) from Avenida de las Banderas to Aventura. This is the second segment of a three phased improvement project along Avenida Empresa identified in the City’s PMP, as well as field verified. The roadway is in need of repair, based on the current PCI of 58 for this area. The project will consist of a 2" cold mill of the existing pavement and a 2" ARHM cap. Isolated sections of the road will be identified for full depth removal and replacement. The first phase of the project, from Antonio Parkway to Avenida de las Banderas, was completed in FY 17-18. A future fiscal year phase will rehabilitate the remaining portion of Avenida Empresa to Santa Margarita Parkway.

Avenida Empresa, between Avenida de las Banderas and Aventura in the City of Rancho Santa Margarita 07/2018 08/2018 10 15 73 36

San Clemente Orange Road Maintenance & Rehabilitation

Avenida Vista Hermosa Rehabilitation

Rehabilitate Avenida Vista Hermosa, a four lane divided arterial, from Via Turqueza to Camino Vera Cruz (a distance of about 1/3 mile). The project will also repair damaged curb, gutter and sidewalk, and upgrade curb ramps as required by ADA.

Avenida Vista Hermosa, from Via Turqueza to Camino Vera Cruz, in the City of San Clemente. 09/2018 11/2018 20 25 73 36

San Clemente Orange Road Maintenance & Rehabilitation

Camino De Los Mares Rehabilitation

Rehabilitate pavement on Camino De Los Mares, a six-lane divided arterial street, from the I-5 freeway east to Avenida Vaquero (a distance of about 0.75 miles). The project will include repair of damaged curb, gutter and sidewalk, and upgrade of curb ramps as required by ADA.

Camino De Los Mares, from the I-5 freeway to Avenida Vaquero, in the City of San Clemente. 04/2019 06/2019 20 25 73 36

San Juan Capistrano Orange Road Maintenance & Rehabilitation

Meredith Canyon Neighborhood Local Streets Pavement Rehabilitation Project

The Meredith Canyon Neighborhood Local Streets Project is a multi-year project that is currently in the design phase and will complete construction by December 2020. The project includes pavement rehabilitation by overlay or complete reconstruction of 3 miles of roadway, construction of 42 ADA compliant curb ramps, repair and reconstruction of damaged curbs and gutters, reconstruction of 12 speed humps and new roadway signing and striping.

The Meredith Canyon Neighborhood Local Streets Pavement Rehabilitation Project includes the following streets within the City - Via De Agua, Avenida Calita, Avenida La Mirada, Calle Esparanza, Calle Miramar, Avenida Pescador, Paseo De Este and Calle Don Carlo.

07/2018 12/2020 15 30 73 36

San Juan Capistrano Orange Road Maintenance & Rehabilitation

Capistrano Villas I, II, and III Pavement Rehabilitation Project (17/18 Ongoing)

The project involves rehabilitation of approximately 2.2 miles of residential streets, construction of 5 ADA ramps, replacement of 10 speed humps, and construction of a raised channelization island and an additional street light at one major intersection. The rehabilitation will involve completed pavement reconstruction in some areas and pavement overlay in other areas.

The project area is in the northerly portion of the city, on the west side of the I-5 Freeway, and encompasses approximately 80 acres of medium density, low income housing with 799 condominium units. The neighborhood is known as the “Capistrano Villas.” The streets in the project are Avenida De La Vista, La Zanja Street, Los Rios Street, Calle Santa Barbara, Calle San Luis, Calle San Antonio and Calle San Diego.

01/2018 08/2018 15 30 73 36

Santa Ana Orange Road Maintenance & Rehabilitation

Raitt Street Rehabilitation: McFadden Avenue to Civic Center Drive

City's Pavement Management System has identified Raitt Street from McFadden Avenue to Civic Center Drive as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 1.18 miles of Raitt Street; replace damaged curbs, gutters, sidewalks, and driveway approaches; reconstruct approximately 31 curb ramps to conform to the latest ADA standards. The project will enhance the walkability and safety of motorists and pedestrians.

McFadden Avenue to Civic Center Drive 06/2019 03/2020 20 20 72 34

Santa Ana Orange Road Maintenance & Rehabilitation

Edinger Avenue Rehabilitation: Raitt Street to Bristol Street

City's Pavement Management System has identified Edinger Avenue from Raitt Street to Bristol Street as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 0.49 miles of Edinger Avenue; replace damaged curbs, gutters, sidewalks, and driveway approaches; reconstruct approximately 12 curb ramps to conform to the latest ADA standards; and incorporate bicycle lane elements. The project will enhance the walkability, rideability and safety of motorists, pedestrians and bicycle users.

Raitt Street to Bristol Street 06/2019 03/2020 20 20 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

Bristol Street Rehabilitation: MacArthur Boulevard to Railroad (N/O Alton)

City's Pavement Management System has identified Bristol Street from MacArthur Boulevard to Railroad as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 0.26 miles of Bristol Street; replace damaged curbs, gutters, sidewalks, and driveway approaches; reconstruct 4 curb ramps to conform to the latest ADA standards; and incorporate bicycle lane elements. The project will enhance the walkability, rideability and safety of motorists, pedestrians and bicycle users.

Bristol Street from MacArthur Boulevard to Railroad (N/O Alton) 06/2019 03/2020 20 20 69 34

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 63: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Santa Ana Orange Road Maintenance & Rehabilitation

Raitt Street Preventative Maintenance: Edinger Avenue to McFadden Avenue

Preventative street maintenance is one of the planned strategies prolonging the useful life of streets and reducing the costly alternative of reconstructing streets. The proposed improvements include the benefit of improving the texture of the asphalt wearing surface an reducing water infiltration under the pavement to delay the pavement deterioration process. Additionally, 0.5 mile segment of Raitt Street between Edinger Avenue and McFadden Avenue has been identified as high priority in need of preventative maintenance before it deteriorates beyond good condition, which would require a significantly more expensive treatment if prolonged.

Raitt Street from Edinger Avenue to McFadden Avenue 04/2019 10/2019 10 10 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

Main Street Rehabilitation: Dyer Road to Warner Avenue

City's Pavement Management System has identified Main Street from Dyer Road to Warner Avenue as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 0.5 mile of Main Street; replace damaged curbs, gutters, sidewalks, and driveway approaches; and incorporate bicycle lane elements as incorporation to our Bike Lane Master Plan. All curb ramps will be conformed to the latest ADA standards. The project will enhance the walkability, rideability and safety of motorists, pedestrians and bicycle users.

Main Street from Dyer Road to Warner Avenue 06/2019 03/2020 20 20 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

Alton Avenue Rehabilitation: Raitt Street to Bristol Street

City's Pavement Management System has identified Alton Avenue from Raitt Street to Bristol Street as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 0.66 miles of Alton Avenue; replace damaged curbs, gutters, sidewalks, and driveway approaches; and reconstruct 4 curb ramps to conform to the latest ADA standards. The project will enhance the walkability and safety of motorists and pedestrians.

Alton Avenue from Raitt Street to Bristol Street 06/2019 03/2020 20 20 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

McFadden Avenue Rehabilitation: Fairview Street to Raitt Street

City's Pavement Management System has identified McFadden Avenue from Fairview Street to Raitt Street as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age and heavy usage. This project will rehabilitate 3,800 linear feet; pavement rehabilitation, replace damaged curbs, gutters, sidewalks, and driveway approaches. The project will enhance the walkability and safety of motorists and pedestrians.

McFadden Avenue from Fairview Street to Raitt Street 07/2019 06/2020 20 20 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

Main Street Preventative Maintenance: 1st Street to Civic Center Drive

Preventative street maintenance is one of the planned strategies prolonging the useful life of streets and reducing the costly alternative of reconstructing streets. The proposed improvements include the benefit of improving the texture of the asphalt wearing surface an reducing water infiltration under the pavement to delay the pavement deterioration process. Additionally, this 1800-feet segment of Main Street from 1st Street to Civic Center Drive has been identified as high priority in need of preventative maintenance before it deteriorates beyond good condition, which would require a significantly more expensive treatment if prolonged.

Main Street from1st Street to Civic Center Drive 04/2019 10/2019 10 10 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

1st Street Preventative Maintenance: City Limit to Newhope Street

Preventative street maintenance is one of the planned strategies prolonging the useful life of streets and reducing the costly alternative of reconstructing streets. The proposed improvements include the benefit of improving the texture of the asphalt wearing surface an reducing water infiltration under the pavement to delay the pavement deterioration process. Additionally, this 3,900 linear feet of pavement have been identified as high priority and in need of preventative maintenance before. Also, damaged curbs, gutters, sidewalks, and driveway approaches will be replaced. The project will enhance the walkability and safety of motorists and pedestrians.

1st Street from City Limit to Newhope Street 04/2019 10/2019 10 10 69 34

Santa Ana Orange Road Maintenance & Rehabilitation

Westminster Avenue Rehabilitation: Construction 17/18 Ongoing

City's Pavement Management System has identified Westminster Avenue from Harbor Boulevard to Fairview Street as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age, and heavy usage. This project will rehabilitate 5300 feet of Westminster Avenue; replace damaged curbs, gutters, sidewalks, and driveway approaches; and reconstruct 20 curb ramps to conform to the latest ADA standards. The project will increase the rideability and safety of motorists and pedestrians.

Westminster Avenue Rehabilitation from Harbor Boulevard to Fairview Street. 06/2018 09/2018 20 20 72 34

Santa Ana Orange Road Maintenance & Rehabilitation

Euclid Street Rehabilitation: Design 17/18 Ongoing

City's Pavement Management System has identified Euclid Street from Hazard Avenue to Westminster Avenue as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age, and heavy usage. This project will rehabilitate 2700 feet of Euclid Street; replace damaged curbs, gutters, sidewalks, and driveway approaches; reconstruct 20 curb ramps to conform to the latest ADA standards; and restripe bike lanes. The project will increase the rideability and safety of motorists, pedestrians and bicycle users.

Euclid Street from Hazard Avenue to Westminster Avenue. 09/2018 12/2018 20 20 72 34

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 64: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Santa Ana Orange Road Maintenance & Rehabilitation

Euclid Street Rehabilitation: Construction 17/18 Carryover

City's Pavement Management System has identified Euclid Street from Hazard Avenue to Westminster Avenue as a priority for rehabilitation to prevent further deterioration of the pavement section due to weather, age, and heavy usage. This project will rehabilitate 2700 feet of Euclid Street; replace damaged curbs, gutters, sidewalks, and driveway approaches; reconstruct 20 curb ramps to conform to the latest ADA standards; and restripe bike lanes. The project will increase the rideability and safety of motorists, pedestrians and bicycle users.

Euclid Street from Hazard Avenue to Westminster Avenue. 09/2018 12/2018 20 20 72 34

Santa Ana Orange Road Maintenance & Rehabilitation

Flower Street and MacArthur Boulevard Preventative Maintenance: Construction 17/18 Ongoing

Ongoing Construction for 17/18 projects per LSR PM. Preventative street maintenance is one of the planned strategies prolonging the useful life of streets and reducing the costly alternative of reconstructing streets. The proposed improvements include the benefits of improving the texture of the asphalt wearing surface and reducing water infiltration under the pavement to delay the pavement deterioration process. Additionally, this 3700-feet segment of MacArthur Boulevard from Raitt Street to Bristol Street, and 2200-feet segment of Flower Street from Sunflower Avenue to MacArthur Boulevard have both been identified as high priority in need of preventative maintenance before it deteriorates beyond good condition, which would require a more expensive treatment.

Flower Street from Sunflower Avenue to MacArthur Boulevard; and MacArthur Boulevard from Raitt Street to Bristol Street. 05/2018 08/2018 10 10 72 34

Seal Beach Orange Road Maintenance & Rehabilitation Annual Slurry Seal Project ST1901 The work will consist of surface treatment and traffic pavement markings.

1 on 10TH ST from OCEAN AV to ELECTRIC AV 2 on 11TH ST from SEAL WY to OCEAN AV 3 on 12TH ST from SEAL WY to OCEAN AV 4 on 13TH ST from SEAL WY to OCEAN AV 5 on 14TH ST from OCEAN AV to ELECTRIC AV 6 on 4TH ST from OCEAN AV to MARINA DR 7 on 5TH ST from OCEAN AV to MARINA DR 8 on 6TH ST from (S) ELECTRIC AV to MARINA DR 9 on OCEAN AV from 13TH ST to MAIN ST 10 on OCEAN AV from MAIN ST to 5TH ST 11 on OCEAN AV from ELECTRIC AV to 13TH ST 12 on OCEAN AV from 5TH ST to 1ST ST 13 on BANYAN AV from CAMELIA ST to COLUMBINE ST 14 on BIRCHWOOD AV from OLEANDER ST to DAISY ST 15 on BLUEBELL ST from ALMOND AV to BIRCHWOOD AV 16 on CAMELIA ST from ALMOND AV to BANYAN AV 17 on CARNATION CR from ALMOND AV to Cul-de-sac 18 on COLUMBINE ST from ALMOND AV to BANYAN AV 19 on DAFFODIL CR from ALMOND AV to Cul-de-sac 20 on DAHLIA DR from ALMOND AV to Cul-de-sac 21 on FERN CR from ALMOND AV to Cul-de-sac 22 on GOLDENROD CR from ALMOND AV to Cul-de-sac 23 on IRIS CR from ALMOND AV to Cul-de-sac 24 on ROSSMOOR CENTER WY from SEAL BEACH BL to WEST RD 25 on ROSSMOOR CENTER WY from WEST RD to MONTECITO RD 26 on DAISY ST from CANDLEBERRY AV to DOGWOOD AV 27 on DOGWOOD AV from DAISY ST to IRONWOOD AV 28 on DOGWOOD AV from MARIGOLD ST to FUCHSIA ST 29on E LDER AVf romO LEANDER STto HE ATHER ST 30 on GOLDENROD ST from ELDER AV to Cul-de-sac 31 on HEATHER ST from HAZELNUT AV to LAMPSON AV 32 on MARIGOLD ST from CANDLEBERRY AV to DOGWOOD AV

04/2019 06/2019 10 24 72 34

Stanton Orange Road Maintenance & Rehabilitation

FY 18/19 City Wide Street Rehabilitation Project Street Rehabilitation throughout the City.

Cerritos Avenue (Dale Ave e/s City Limit); Knott Avenue (City Limit - City Limit); Lampson Avenue (City Limit - Beach Blvd w/s); Magnolia Avenue (City Limit n/o Cerritos City Limit n/o Syracuse); Orangewood Avenue (Beach Blvd e/s City Limit)

08/2018 09/2018 5 10 65 29

Tustin Orange Road Maintenance & Rehabilitation Newport Avenue Rehabilitation

Repave/resurface 1.43 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, and traffic striping.

Sycamore Avenue to Holt Avenue 06/2018 03/2019 20 30 68 37

Tustin Orange Road Maintenance & Rehabilitation Browning Avenue Rehabilitation

Repave/resurface 0.95 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, and traffic striping.

El Camino Real to Irvine Blvd. 09/2019 06/2020 20 30 68 37

Tustin Orange Road Maintenance & Rehabilitation Red Hill Avenue Rehabilitation

Repave/resurface 0.24 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, traffic striping, and median reconstruction to lengthen the northbound left turn pocket at Bryan Ave.

San Juan St. to Bryan Ave. 06/2020 03/2021 20 30 68 37

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 65: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Tustin Orange Road Maintenance & Rehabilitation Red Hill Avenue Rehabilitation

Repave/resurface 0.47 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, and traffic striping.

Walnut Ave. to Interstate 5 Freeway 06/2020 03/2021 20 30 68 37

Tustin Orange Road Maintenance & Rehabilitation Edinger Avenue Rehabilitation

Repave/resurface 0.23 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, and traffic striping.

Jamboree Road to Harvard Ave. 09/2020 06/2021 20 30 68 37

Tustin Orange Road Maintenance & Rehabilitation Jamboree Road Rehabilitation

Repave/resurface 1.6 miles of road, including localized removal and repair of asphalt concrete pavement failure areas, repair of sidewalk and curb & gutter, reconstruction of curb ramps to be ADA compliant, cold plane existing asphalt, construction of asphalt concrete overlay, traffic signal detector loops, and traffic striping.

Barranca Parkway to SCRRA Railroad 09/2021 06/2022 20 30 68 37

Tustin Orange Traffic Control Devices Parkcenter Lane and Bryan Avenue Traffic Signal Installation Installation of new traffic signals and equipment Parkcenter Lane / Bryan Avenue Intersection 03/2018 12/2018 15 25 68 37

Tustin Orange Traffic Control Devices Lansdowne Road and Valencia Avenue Traffic Signal Installation Installation of new traffic signals and equipment Lansdowne Road / Valencia Ave. Intersection 03/2018 12/2018 15 25 68 37

Villa Park Orange Road Maintenance & Rehabilitation

Street Rehabilitation Project (17/18 Carryover)

The project improvements of the nineteen streets sections include: •Rem ove and replace deteriorated pavement sections. •Crack seal as needed. •Edge or full grinding of the street pavement. •Overlay the full pavement section with a minimum 2 inches of rubberized asphalt.

the project location includes 19 street section within the City. The list is attached the approved resolution.Leigh Circle (Ridgeview Circle to Cul-de-sac); Ridgeview Circle (Cul-de-sac to Cul-de-sac); Daron (Taft Avenue to Cul-de-sac); Loma Street (Cerro Villa Drive to Valley Drive); Valley Drive (Cerro Villa Drive to Loma Street); Aubrey Circle (Valley Drive to Cul-de-sac); Montana Circle (Vida Circle to Cul-de-sac); Francisco Drive (Vida Circle to Cul-de-sac); Fernando Circle (Roberto to Cul-de-sac); Vida Circle (Francisco Drive to Fernando Circle); Roberto Street (Collins Avenue to Fernando Circle); Mesa Drive (Mesa Drive to Villa Isle Drive); Mesa Drive (Villa Isle Drive to Cerro Villa Drive); Park Villa Ln /Pl (Villa Park Road to Cul-de-sac); Hidden Valley Dr (Canyon Drive to Cul-de-sac); Durfee Circle (Lemon to Cul-de-sac); James Circle (James Road to Cul-de-sac); James Road (Center Road to James Circle); Christine Circle (James Road to Cul-de-sac)

07/2018 12/2018 15 25 68 37

Westminster Orange Road Maintenance & Rehabilitation Hoover Street Improvements

Remove deteriorated pavement and place new asphalt concrete overlay for the segment between Trask Avenue and Garden Grove Boulevard; apply type 2 slurry seal for the segment between Bolsa Avenue and Trask Avenue; remove and replace damaged curb, gutter, cross gutter, spandrel, sidewalk, ADA ramps, driveway approach, adjust manholes and water valves to grade; and install signing and striping.

Hoover Street from Bolsa Avenue to Garden Grove Boulevard 07/2018 04/2019 10 15 72 34

Westminster Orange Road Maintenance & Rehabilitation Bolsa Avenue Improvements

Remove existing pavement and place new asphalt concrete overlay; remove and replace damaged curb, gutter, cross gutter, spandrel, sidewalk, ADA ramps, driveway approach, bus pad; adjust manholes and water valves to grade; install signing and striping.

Bolsa Avenue from Brookhurst Street to Ward Street 10/2018 04/2019 15 20 72 34

Yorba Linda Orange Road Maintenance & Rehabilitation

On Going Street Maintenance Program/Annual Pavement Preservation Program (APPP) Zone 2

The project includes crack sealing, slurry sealing, asphalt overlays, and miscellaneous asphalt repair along with restriping of pavement markings. The City is divided into 7 zones and the program provides for treatment of one zone per year.

Zone 2 is located on the north side of the City generally bounded by Valley View Avenue on the West, Yorba Linda Boulevard on the South, Village Center Drive on the East, and the City boundary on the North. The zone consists of 76 lane miles of pavement which include a combination of arterials, collectors, and local streets.

06/2019 09/2019 5 7 55 29

Auburn Placer Road Maintenance & Rehabilitation

City of Auburn 2019 Street Overlay Project

Staff has identified the proposed FY18/19 projects based on the FY13/14 to FY22/23 Road Overlay Report Management System. Construction is anticipated from March through June 2019. With the proposed 2-inch overlays, the useful life is estimated at 20 years.

Auburn Folsom Rd. from Indian Hill Rd. to Lincoln Way; Hale St. from High St. to Orange St.; Marguerite Mine Rd. from Auburn Ravine to Hwy 49/ City limits; Auburn Ravine Rd. from Palm Ave. to Elm Ave.; Epperle Ln. from Auburn Ravine Rd. to End; Palm Ave. from Hwy 49 to Auburn Ravine Rd.; College Way from Knoll St. to High St.; Knoll St. from Pleasant Ave to College Way; Landis Cir. from end to End; Los Altos Ave. from end to end; Hoffman Ave. from High St. to Landis Cir.

04/2019 06/2019 20 30 5 1

Colfax Placer Road Maintenance & Rehabilitation

Rising Sun Road Pavement Resurfacing Project This project will resurface approximately 1400 feet of Rising Sun Road On Rising Sun Road between between Ben Taylor Road and West Grass Valley Road 06/2018 08/2018 20 20 1 1

Colfax Placer Road Maintenance & Rehabilitation Culver Street Reconstruction This project will reconstruct up to 600 feet of Culver Street On Culver Street from West Oak Street to Newman Street 06/2018 08/2018 20 20 1 1

Colfax Placer Safety South Auburn Street & I-80 Roundabout

This project will replace, realign, and reconstruct the existing South Auburn Street and I-80 on and off ramp intersection with a roundabout. On South Auburn Street between Hwy 174 and Whitcomb Avenue at I-80 on and off ramps. 10/2018 06/2019 20 20 1 1

Lincoln Placer Safety Lincoln Blvd Phase 2 & 1A

The project will maintain and preserve the local street and road system in good condition, reduce drive times and traffic congestion, improve bicycle safety and make the pedestrian experience safer with the following improvements: •Phase 2 - new curb, gutter, sidewalk, drainage facilities, bulbout curb returns, including compliant curb ramps, streetscape including new trees, landscaping and irrigation; and •Phase 1A - restriping, removal and replacement of loop detectors along Lincoln Blvd. from Sterling Parkway to 1st Street and the installation of new signals at 1st, 3rd and McBean Park Drive.

Lincoln Blvd. from Sterling Parkway to McBean Park Drive for the Phase 1A work. Lincoln Blvd from McBean Park Drive to 2nd Street for the Phase 2 work. 03/2018 11/2018 30 100 6 1

Loomis Placer Road Maintenance & Rehabilitation

Town Center Implementation Plan Phase 3

Town Center Implementation Plan Phase 3 – Taylor Rd from HSB to King Work consist of overlay and the addition of a bike/pedestrian path from Del Oro HS to North Town Limits as well as placing and replacing bike lanes, curb, gutter and sidewalk on Taylor Road from Horseshoe Bar to King.

Taylor Road from Horseshoe Bar Rd to North Town Limits 05/2019 06/2019 10 20 6 1

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 66: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rocklin Placer Road Maintenance & Rehabilitation

Sierra College Blvd. Reconstruction (Clover Valley to City Limits)

Reconstruct the portion Sierra College Blvd. that is failing and needs to be reconstructed. This will involve reconstruction of the travel way and will not include the shoulders.

Sierra College Blvd. Between Clover Valley and City Limits 12/2020 06/2021 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation

Sierra College Blvd. Reconstruction (Rocklin Road - El Don Drive

Reconstruct the portion Sierra College Blvd. that is failing and needs to be reconstructed. This will involve reconstruction of the travel way and will not include the shoulders.

Sierra College Blvd Between Rocklin Road and El Don Drive 12/2019 06/2020 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation Traffic Signal ITS

Acquire consultant through RFP process to study Rocklin's gaps in transportation infrastructure, and identify technologies to enhance Rocklin's safety and drivability. As past and forecasted future performance of investments continue to influence project decisions, the ability for Rocklin to implement systems to collect the data that can be used to generate measurable/comparable performance indicators will be critical. With an ITS Master Plan, Rocklin should have the ability to develop and evaluate mitigation measures for peak hour traffic congestion.

Rocklin and adjacent agencies 06/2018 06/2020 25 30 4 1

Rocklin Placer Road Maintenance & Rehabilitation Citywide Dig Outs (17/18 Carryover)

The removing and replacing of degraded asphalt needs to be done as part of general repairs and is necessary to preserve the roadways and prevent major rehabilitation in the coming years.

Granite Drive (Rocklin Road to Dominguez Road); Lonetree Blvd. (City Limit with Roseville to Sunset Blvd.); Blue Oaks Blvd. (City Limit with Roseville to Sunset Blvd.); Wildcat Blvd. (West Stanford Ranch Road to City Limit with Lincoln); Park Drive (City Limit with Roseville to Stanford Ranch Road); Park Drive (Stanford Ranch Road to Crest Drive); Sunset Blvd. (Stanford Ranch Road to Fairway Drive); Sunset Blvd. (Stanford Ranch Road to HWY 65); Sierra College Blvd. (Rocklin Road to Southside Ranch Road); Sierra College Blvd. (City Limit with Loomis to City Limit with Placer County); West Oaks Blvd. (Sunset Blvd. to Stanford Ranch Road).

12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation Mission Hills Reconstruction

The removing and replacing of degraded asphalt needs to be done as part of general repairs and is necessary to preserve the roadways and prevent major rehabilitation in the coming years.

Argonaut Avenue from Midas to end, Mountain View Drive from Midas Avenue to Sweetwater Drive, Mission Way from Mountain View Drive to Argonaut Avenue, Capistrano Way from Mountain View Drive to Argonaut Avenue, Verano Way from Mountain View Drive to Argonaut Avenue, Roble Way from Verano Way to Argonaut Avenue, Mesa Court from Verano Way to end, Piedra Court from Argonaut Avenue to end, Rio Court from Argonaut Avenue to end, Antelope Court from La Paloma Lane to end, La Paloma Lane from Argonaut Avenue to Antelope Way, Antelope Way from La Paloma Lane to Mountain View Drive, Sweetwater Drive from Antelope Way to Lemon Hill Drive, Sweetwater Court from Lemon Hill Drive to end, Hillside Drive from Sweetwater Drive to Pecan Court, Pecan Court from Hillside Drive to end, Baltic Circle from end to end, Chelsea Place from Sweetwater Drive to end, Chelsea Court from Chelsea Place to end, Lemon Hill Drive from Argonaut Avenue to end, David Court from Argonaut Avenue to end, Adam Court from Argonaut Avenue to end.

12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation Pacific Street Roundabout

Replace existing signalized intersection with a multilane roundabout, new pavement, and street lighting system. Current LOS is unacceptable due to the addition of new developments, i.e. Rocklin Commons and other developments in the vicinity along Granite Drive. Replacing the signals will lead to an acceptable LOS and reduced traffic conflicts. Rocklin Road pavement is deteriorated and has had no structural overlays in the last 10 years.

Pacific Street at Rocklin Road 12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation

Partial Road Reconstruction of Rocklin Ranch Industrial Park

Partial road reconstruction and resurfacing of the Rocklin Ranch Industrial Park. This is an industrial area and has a lot of regular and heavy vehicular traffic. The amount of traffic has increased over time causing the streets to become fatigued and susceptible to water damage.

Alvis Court, Del Mar Avenue, Monopoly Court, and Citrus Avenue 12/2018 06/2019 13 15 4 1

Rocklin Placer Road Maintenance & Rehabilitation

Rocklin Road Sidewalk and Center Island

Adjust Rocklin Road’s street alignment and construct sidewalk, center island, and intersection. This will improve Rocklin Road's traffic circulation and reduce traffic impediments.

Rocklin Road between Granite Drive and I‐80 North West Exit 12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation Sceptre and Camelot Drive Repair

Repair dips and undulations on the roadway. As a result of the natural road settling, along the creek crossing, undulations in the roadway and along the sidewalk have occurred which have created drainage issues and is creating ADA barriers on the sidewalk.

Along the creek crossing at Sceptre Drive and Camelot Drive 12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation

Sierra College Blvd. Reconstruction (Scarborough - Nightwatch)

Reconstruct the portion Sierra College Blvd. that is failing and needs to be reconstructed. This will involve reconstruction of the travel way and will not include the shoulders.

Sierra College Blvd. Between Scarborough and Nighwatch 12/2018 06/2019 17 20 4 1

Rocklin Placer Road Maintenance & Rehabilitation

Sunset Blvd. and Springview Intersection Upgrade

Lane extension and gutter redesign and construction. Existing conditions cause delays for the left turn lane from Sunset Blvd. to 3rd Street. By extending the turn lane, it will free the straight movement through the intersection, and by removing the valley gutter and constructing a smoother transition onto 3rd Street, traffic will not have to slow for the bump, and will proceed normally through the intersection. This will result in fewer delays for drivers using the traffic signal and will sustain a steady flow of traffic in a safe and secure manner.

Intersection of Sunset Blvd. and Springview Drive 12/2018 06/2019 17 20 4 1

Roseville Placer Road Maintenance & Rehabilitation

2019 Residential Resurfacing Project

The project includes the removal and replacement of failed asphalt concrete roadway sections and the application of a preventative maintenance surface treatment. The maintenance surface treatment will provide a waterproof membrane to protect the existing asphalt surfaces and extend the life of the underlying pavement.

The work will occur along various residential streets within the Woodcreek Oaks, Foothills Junction, Los Cerritos, Roseville Heights, South Cirby, and Maidu neighborhoods. 05/2019 10/2019 7 10 6 1, 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 67: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Roseville Placer Road Maintenance & Rehabilitation

2018 Roller Compacted Concrete Pavement Project

The project includes the removal and replacement of failed asphalt concrete pavement with roller compacted concrete pavement. The project also includes the reconstruction of the road base with cement treated base as well as curb ramp improvements.

The street segments identified for this project include: Washington Blvd. from Pleasant Grove Blvd. to just south of Blue Oaks Blvd.; Atkinson Street from Church Street to the Foothills Blvd. overcrossing; Denio Loop from Atkinson Street to Foothills Blvd.; Hickory Street from Church Street to Oakland Avenue.

05/2018 11/2018 20 40 6 1, 4

Portola Plumas Road Maintenance & Rehabilitation 18/19 Street Patching Citywide Grind out distressed areas along Commercial Street and pavement patch those grind-

outs with hot mix asphalt.

Various pothole locations along Commercial Street., Various pothole locations along Utah Street., Various pothole locations along Ridge Street., Various pothole locations along Third Ave., Various pothole locations along California Street.

06/2019 07/2019 2 4 3 1

Portola Plumas Road Maintenance & Rehabilitation

17/18 Street Patching Citywide (17/18 Carryover) Grind out distressed areas pavement patch those grind-outs with hot mix asphalt.

Various locations on West Street, Various locations on Joy Way, Various locations on Main Street, Various locations on Pacific Street, Various locations on 2nd Avenue, Various locations on Taylor Avenue.

06/2018 10/2018 2 4 3 1

Banning Riverside Road Maintenance & Rehabilitation

Various Streets Improvements (17/18 Carryover)

Grind and construct 2" asphalt concrete (AC) overlay and adjust water valves and sewer manhole covers go grade. First Street from Livington St to Williams St; Second Street from Hays St to Williams St. 08/2018 02/2019 10 15 42 23

Banning Riverside Road Maintenance & Rehabilitation

2018-19 Various Streets AC Overlay/Rehabilitation

Grind and construct 2" asphalt concrete; adjust water valve and sewer manhole covers; repair concrete curb and gutter, sidewalk, access ramps and cross gutter; and reinstall all existing striping and pavement markers.

Williams Street from 8th Street to 16th Street; 8th Street from Ramsey St to Nicolet St; Jacinto View Road from Omar St to Winchester Dr; Indian School Lane from San Gorgonio Ave to Blanchard St. 05/2019 11/2019 10 15 42 23

Banning Riverside Road Maintenance & Rehabilitation Jacinto View Road Slurry Seal

Crack seal and slurry seal existing asphalt concrete pavement; remove and replace deteriorated ac pavement to subbase; repair concrete curb and gutter, sidewalk, access ramps and cross gutter; and reinstall all existing striping and pavement markers.

Jacinto View Road from Winchester Drive to Sunset Avenue 03/2019 09/2019 5 7 42 23

Beaumont Riverside Road Maintenance & Rehabilitation

Beaumont Avenue Reconstruction Project Grind and overlay street reconstruction for Beaumont Ave Beaumont Ave from 6th to 11th Street 03/2019 05/2019 15 30 42 23

Beaumont Riverside Road Maintenance & Rehabilitation Annual Slurry Seal FY 18-19 Slurry Seal application on various streets in the City of Beaumont

Alexe St, Ana St, Cherry Valley Acres Ln, Citrus St. Jon Gilbert Ln, Lucille Ct, Monika Ct, Vasali Ln, Cherry Ave, Beaumont Ave, Palm Ave, Spruce Ct, Shasta Way, Roy Ct, Apple Canyon Rd, Cynthia St. 6th St, California Ave, Elm Ave, Moonlight Dr., Oak Valley Parkway, Olive Ave, Radka Ave, Veile Ave, Myrl Dr, 1st, 2nd, 3rd, 7th, 8th, 10th, 11th, 12th, 13th St.

09/2018 10/2018 5 7 42 23

Blythe Riverside Complete Streets Components

Barnard Street – Stormwater System Improvement Project

The project consists of installing 300 linear feet of underground stormwater storage system; installation of catch basins to capture stormwater from the street; piping to connect to the existing storm drain system, and street reconstruction. The estimated useful life of the project is 50 to 100 years according to industry standards, and the anticipated year of construction is 2018. The Engineer’s opinion of probable cost is 249,519.00 with the City furnishing 6 feet diameter corrugated pipe supplies for the construction of the underground stormwater retention.

Barnard St. and Lovekin Blvd., City of Blythe, Riverside 09/2018 11/2018 50 99 56 28

Calimesa Riverside Complete Streets Components

County Line Road Corridor Improvement Project

Joint improvement project with the City of Yucaipa to construct improvements on County Line Road fom Calimesa Blvd. to Bryant St. including 4 intersections, sidewalk, ADA Ramps, bike lanes, utility relocations and street widening.

County Line Road from Calimesa Rd. to Bryant St. 05/2018 06/2019 20 40 42 23

Canyon Lake Riverside Complete Streets Components

Catch Basin Trash Filters (Carry Over 17/18)

Install trash filters in existing storm drain catch basins. (This project has not yet commenced due to other higher priority 17/18 projects. This project is moving forward and will be completed.)

Railroad Canyon Road - Western City Boundary to Eastern City boundary - 2 Miles 10/2018 12/2018 20 25 67 28

Canyon Lake Riverside Safety Phase II Wrought Iron Fence Replacement Remove and replace existing wrought iron safety fencing. Railroad Canyon Road - between Canyon Lake Drive South and Sky Link Drive - south side 07/2018 09/2018 10 15 67 28

Cathedral City Riverside Road Maintenance & Rehabilitation

Date Palm Drive and Dinah Shore Intersection Reconstruction

The pavement approaching and through the intersection is requiring restoration and will be reconstructed using Asphalt and Portland Cement Concrete (PCC). The stopping lanes of all four legs of the intersection will be reconstructed using PCC.

Intersection of Date Palm Drive and Dinah Shore Drive in Cathedral City. 03/2018 03/2018 20 30 56 28

Cathedral City Riverside Road Maintenance & Rehabilitation

Avenida Ximino Neighborhood Street Reconstruction

The existing pavement on Avenida Ximino neighborhood streets requires reconstruction. The Project will reconstruct the streets and improve the respective street drainage.

Avenida Ximino between 30th Avenue and Vega Road, Susan Drive, Walker Avenue and Vega Road between Avenida Ximino and Avenida Juarez in Cathedral City. 03/2019 08/2019 15 20 56 28

Cathedral City Riverside SafetyLandau Boulevard and McCallum Way Intersection Traffic Signal Construction

This project will provide a signalized intersection near Mt. San Jacinto High School which gets significant pedestrian traffic from students. It was also the location of a pedestrian fatality in 2015.

The intersection of Landau Boulevard and McCallum Way in Cathedral City. 03/2020 08/2020 15 20 56 28

Coachella Riverside Road Maintenance & Rehabilitation

Peacock Palms Neighborhood Pavement Maintenance (17/18 Carryover)

The existing pavement throughout the neighborhood requires Maintenance/Reconstruction

Calle Leon, Paseo Laredo, Via Durango, Via Hermosa, Vera Cruz, Calle De Vega, Avenida Cortez, Pavon Palma 09/2018 10/2018 20 20 56 28

Coachella Riverside Road Maintenance & Rehabilitation

Harrison Street Maintenance/Reconstruction The existing pavement requires Maintenance/Reconstruction Harrison Street from Grapefruit Blvd. to Avenue 54 05/2018 09/2018 20 20 56 28

Coachella Riverside Road Maintenance & Rehabilitation

Avenue 54 Street Maintenance/Rehabilitation (17/18 Carryover)

The existing pavement requires Maintenance/Reconstruction Avenue 54 From Harrison Street to Grapefruit Blvd. 09/2018 10/2018 20 20 56 28

Coachella Riverside Road Maintenance & Rehabilitation

Avenida Del Oro Neighborhood Pavement Maintenance/Reconstruction (17/18 Carryover)

The existing pavement requires Maintenance/Reconstruction Avenida Del Oro, Avenida Del Parque, Corte Del Parque 09/2018 10/2018 20 20 56 28

Corona Riverside Road Maintenance & Rehabilitation

Rubberized Asphalt Concrete Rehab Project 2017-22 Rubberized Asphalt Concrete Rehabilitation Project Foothill Pkwy from Skyline to I-15, Green River from City limit to SR-91, Crestridge from Green River

to Prado Rd, Prado Rd from Crestridge to terminus 10/2018 04/2019 15 20 60 31

Corona Riverside Road Maintenance & Rehabilitation

2018 Local Streets Rehab Project 2017-13 Pavement Rehabilitation

Area 1 btwn Green River Rd, Palisades Dr. and Serfas Club Dr., Area 2 btwn Border Ave, Avenida Del Vista Ave, Via Del Rio Ave and Ontario Ave, Area 3 btwn Rimpau Ave, Kellogg Ave, Ontario Ave and Ridgewood Dr.

10/2017 04/2019 15 20 60 31

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 68: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Desert Hot Springs Riverside Road Maintenance & Rehabilitation

2018-2019 City-wide Asphalt Grind and Overlay, Slurry, and Road Reconstruction Project

Project will include grind and overlay of asphalt material, and crack seal and slurry seal. Replacement of striping and markings and addition of Bike lanes marking at various segments.

Various road segments City-wide(30.22 Square Miles) as recommended in the current Pavement Management Plan with PCI Ratings between 65 and 75. 11/2018 12/2018 5 10 56 28

Desert Hot Springs Riverside Safety Palm Drive Traffic Signal and Street Light Project

Project will include the installation of new traffic signals, street lights, bike lanes, traffic signal synchronization facilities, grind and overlay of asphalt material, and striping and markings and addition of bike lanes marking at various segments.

Palm Drive from Two Bunch Palms Trail to Pierson Blvd 08/2018 09/2018 5 10 56 28

Desert Hot Springs Riverside Complete Streets Components Desert View Sidewalk Project Project will include the installation of new curb and gutter, sidewalk, ADA ramps, grind

and overlay of asphalt material, and striping and markings Desert View Ave from Palm Dr to Verbena Dr 10/2018 11/2018 5 10 56 28

Desert Hot Springs Riverside Road Maintenance & Rehabilitation

Re-striping of Mission Lakes Blvd and Two Bunch Palms Trail Project

Project will include grind and overlay of asphalt material, and crack seal and slurry seal. Replacement of striping and markings and addition of Bike lanes marking at various segments.

Various road segments along Mission Lakes Blvd and Two Bunch Palms Trails 10/2018 11/2018 5 10 56 28

Eastvale Riverside Road Maintenance & Rehabilitation 2018 Annual Overlay Project AC improvement operations including grind & overlay, micro-surfacing , reconstruction

and traffic striping.

Schleisman Rd between Whitewell Rd and Archibald Ave; Archibald Ave between 65th St and Corbin Dr; Citrus St between Harrison Ave and Hamner Ave; Limonite Ave between Archibald Ave and Hamner Ave; Philadelphia Ave between Milliken Ave and I-15; Sumner Ave between Limonite Ave and Citrus St; Scholar Way between Limonite Ave and Citrus St

09/2018 06/2019 10 20 60 31

Hemet Riverside Road Maintenance & Rehabilitation

Pavement Management Program Phase 2 - Slurry Seal Project Pavement Management Program Phase 2 - Slurry seal project Agate St. to Corte Cercado with 38 Total Streets 05/2019 12/2019 5 15 42 23

Hemet Riverside Road Maintenance & Rehabilitation

Pavement Management Program Phase 1 Slurry Seal Pavement Management Project Phase One - Slurry Seal Yale St. to Winthrop Dr. with 65 Total Streets 05/2018 12/2018 5 15 42 23

Hemet Riverside Road Maintenance & Rehabilitation

Florida Avenue EVP/Opticom Hardware

Florida Avenue Emergency Vehicle Preemption Hardware Project- a hardware purchase only project to solicit bids for EVP hardware compatible with the City system to be installed on the Caltrans Median Project. Caltrans has already committed to installing and wiring any City provided EVP hardware on the 23 signals within the project boundary.S

Florida Avenue and Highway 74 08/2018 12/2018 5 8 42 23

Indian Wells Riverside Road Maintenance & Rehabilitation

Fred Waring Drive and Portola Avenue Slurry Seal (17/18 Ongoing)

This project with support the City's Pavement Management Program (PMP). The City's PMP identifies the street for scheduled slurry seal as a preventative maintenance to extend its useful life. Crack sealing will be applied prior to application of rubberized slurry seal and then pavement striping lines and markings will be installed.

Fred Waring Drive from eastern city limits to western city limits Portola Avenue from Mockingbird Trail to city limits south 05/2018 09/2018 5 10 42 28

Indian Wells Riverside Road Maintenance & Rehabilitation Highway 111 Slurry Seal

This project with support the City's Pavement Management Program (PMP). The City's PMP identifies the street for scheduled slurry seal as a preventative maintenance to extend its useful life. Crack sealing will be applied prior to application of rubberized slurry seal and then pavement striping lines and markings will be installed.

Highway 111 from eastern city limits to western city limits 07/2020 06/2021 5 10 42 28

Indian Wells Riverside Road Maintenance & Rehabilitation

Fairway Drive Slurry Seal and Miles Avenue Overlay (17/18 Ongoing)

This project with support the City's Pavement Management Program (PMP). The City's PMP identifies the street for scheduled slurry seal as a preventative maintenance to extend its useful life. Crack sealing will be applied prior to application of rubberized slurry seal and then pavement striping lines and markings will be installed. Overlay of Miles Avenue to include rubberized asphalt, road diet (through re-striping), and bike lanes

Fairway Drive from Cook Street to Indian Wells Lane 06/2018 06/2019 5 10 42 28

Indio Riverside Road Maintenance & Rehabilitation

Highway 111 Street Improvements from Madison Street to Rubidoux Street

The improvements will include widening Highway 111 from four to six lanes including pavement reconstruction, intersection improvements, and upgraded traffic signals at all intersections. Upgrade existing sidewalks and driveways to current ADA standards and add sidewalks to the bus stops near the intersection of Madison Street and Highway 111.

Highway 111 from Madison Street to Rubidoux Street 08/2017 09/2018 10 20 56 28

Indio Riverside Road Maintenance & Rehabilitation

North Indio Pavement Improvements

Add pavement along Rancho Los Cerritos Drive, Primrose Lane, Galindo Court and Sabrina Court. The improvements include constructing new asphalt pavement and aggregate base to these streets. Rolled curbs and drywells will be installed as necessary to mitigate drainage issues. The project limits include a 36ft street section for two lanes of traffic along Rancho Los Cerritos between Avenue 38 and Avenue 39, as well as for Galindo Court and Sabrina Court. Due to Right-of-Way constraints, Primrose Lane will be constructed as a temporary 20ft section from Avenue 38 to Lindy Lane.

Rancho Los Cerritos Drive, Primrose Lane, Galindo Court and Sabrina Court 05/2018 05/2018 10 20 56 28

Indio Riverside Road Maintenance & Rehabilitation

Miles Avenue Pavement Reconstruction from Deglet Noor Street to Oasis Street

Reconstruct the pavement along Miles Avenue between Deglet Noor Street and Oasis Street. The proposed improvements include removing the existing deteriorated asphalt and replacing with a new asphalt layer. The proposed improvements also include removing and replacing any deteriorated sub-base as necessary.

Miles Avenue between Deglet Noor Street and Oasis Street 03/2018 09/2018 10 20 56 28

Jurupa Valley Riverside Road Maintenance & Rehabilitation

Rubidoux Blvd Pavement Rehabilitation

The rehabilitation of approximately .85 centerline miles (275,000 SF) of AC pavement by grind and overlay with isolated removal and reconstruction Rubidoux Blvd - Mission Blvd to 29th St 09/2018 02/2019 15 20 60 31

Jurupa Valley Riverside Road Maintenance & Rehabilitation

Van Buren Blvd Pavement Rehabilitation - Ph. 2A

The rehabilitation of approximately .85 centerline miles (300,000 SF) of AC pavement by grind and overlay with isolated removal and reconstruction Van Buren Blvd - Jurupa Rd to Rutile St 07/2018 12/2018 15 20 60 31

Jurupa Valley Riverside Other Citywide Pavement Need Assessment 17/18 Ongoing

Completion of a pavement management program for the first time since the City's incorporation. Includes assessment of approximately 300 miles (road centerline).

City of Jurupa Valley Limits - Bounded as follows: North of Santa Ana River, East of I-15, South of Philadelphia Avenue/ El Rivino Road, West of Brown Avenue and the Santa Ana River. Phasing for improvements will be based on priority need throughout each year.

05/2018 12/2018 3 5 60 31

Jurupa Valley Riverside Complete Streets Components

Jurupa Valley High School Safe Routes to School - 17/18 Ongoing

Provides curb, gutter, sidewalk and dirt trails along with LED crosswalk flashers at the Martin/Bellegrave intersection and curb bump outs at the Martin St intersections. Martin St - 50th to Bellegrave, 48th St - Martin to Troth, Troth St - 48th to Bellegrave 05/2018 08/2018 10 20 60 31

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 69: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

La Quinta Riverside Complete Streets Components

La Quinta Village Complete Streets - A Road Diet Project

The proposed improvements will convert the La Quinta Village into a bicycle and pedestrian friendly, Complete Street atmosphere. The three major streets in the Village; Calle Tampico from Eisenhower Drive to Washington Street, Eisenhower Drive from Calle Tampico to Calle Sinaloa, and Calle Sinaloa/Avenue 52 from Eisenhower Drive to Washington Street; will be reduced from four lanes down to two lanes and include bicycle facilities and on-street parking. In addition, five roundabouts will be constructed in order to link the road diet segments together.

Calle Tampico from Eisenhower Drive to Washington Street, Eisenhower Drive from Calle Tampico to Calle Sinaloa, and Calle Sinaloa/Avenue 52 from Eisenhower Drive to Washington Street 04/2019 08/2020 20 30 42 28

La Quinta Riverside Complete Streets Components

Jefferson Street at Avenue 53 Roundabout

The proposed improvement will construct a modern roundabout at the intersection of Jefferson Street and Avenue 53. Jefferson Street at the intersection of Avenue 53. 12/2018 11/2019 20 30 42 28

La Quinta Riverside Complete Streets Components

FY 2017/28 Carryover from La Quinta Village Complete Streets - A Road Diet Project

Carryover of $175,874 from the previous year allocation. The proposed improvements will convert the La Quinta Village into a bicycle and pedestrian friendly, Complete Street atmosphere. The three major streets in the Village; Calle Tampico from Eisenhower Drive to Washington Street, Eisenhower Drive from Calle Tampico to Calle Sinaloa, and Calle Sinaloa/Avenue 52 from Eisenhower Drive to Washington Street; will be reduced from four lanes down to two lanes and include bicycle facilities and on-street parking. In addition, five roundabouts will be constructed in order to link the road diet segments together.

Calle Tampico from Eisenhower Drive to Washington Street, Eisenhower Drive from Calle Tampico to Calle Sinaloa, and Calle Sinaloa/Avenue 52 from Eisenhower Drive to Washington Street 04/2019 08/2020 20 30 42 28

Lake Elsinore Riverside Road Maintenance & Rehabilitation

Lincoln Street Pavement Rehabilitation

Pavement Rehabilitation of Lincoln Street from Riverside Drive to north end of Lincoln Street. The project consists of Slurry Seal Type II treatment or 2" mill and overlay depending on PCI condition of road segment.

Lincoln Street 10/2018 04/2019 10 12 67 28

Lake Elsinore Riverside Road Maintenance & Rehabilitation

Graham Ave Pavement Rehabilitation between Lakeshore and Langstaff (17/18 Carryover)

2" Grind and overlay W. Graham Ave between Lakeshore and Langstaff 04/2018 07/2018 7 10 67 28

Lake Elsinore Riverside Road Maintenance & Rehabilitation

Graham Ave Pavement Rehabilitation between Langstaff and Main (17/18 Carryover)

2" Grind and overlay Graham Ave between Langstaff and Main 04/2018 07/2018 7 10 67 28

Lake Elsinore Riverside Road Maintenance & Rehabilitation

Graham Ave Pavement Rehabilitation between Main and Heald (17/18 Carryover)

Slurry Seal II Graham Ave between Main and Heald 04/2018 07/2018 7 10 67 28

Menifee Riverside Road Maintenance & Rehabilitation

Rustler's Ranch Phase 2 (17/18 Carryover) repave/resurface 2.4 miles of neighborhood streets in severe condition Rustler's Ranch Neighborhood. North of Newport Rd and East of Bradley Rd 03/2019 04/2019 8 10 67 23

Menifee Riverside Road Maintenance & Rehabilitation

Murrieta Road Resurfacing (Newport to Ethanac) (17/18 Carryover)

repave/resurface 3.0 miles of local arterial road. Restripe bike/Neighborhood Electric Vehicle (NEV) lanes. Install additional signs. Murrieta Road from Newport Road to Rouse Road 09/2018 10/2018 15 20 67 23

Moreno Valley Riverside Road Maintenance & Rehabilitation

Citywide Pavement Rehabilitation Program Surface Remove/Replace and Slurry Seal

John F Kennedy Dr - Heacock St to Indian St; Iris Ave - Perris Blvd to Kitching St; Iris Ave - Kitching St to Lasselle St; Sunnymead Blvd - Frederick St to Heacock St; Pigeon Pass Rd - Sunnymead Blvd to Swan St; Moreno Beach Dr - Via Del Lago to John F Kennedy Dr; Hemlock Ave - Pigeon Pass Rd to Heacock St; Alessandro Blvd - Lasselle St to West of Darwin Dr; Alternative Streets:Moreno Beach Dr - Auto Mall Dr to Cottonwood Ave; Pigeon Pass Rd - Swan St to Western Ridge Dr; Moreno Beach Dr - Ironwood Ave to Locust Ave; Elder Ave - Morrison St to Foxhound Cir; Iris Ave - Indian St to Perris Blvd

10/2018 02/2019 5 10 61 31

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 70: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Moreno Valley Riverside Road Maintenance & Rehabilitation

Citywide Pavement Rehabilitation Program Slurry Seal

Abedul St - Buena Fortuna Ln to North End Ancladero Ct - Buena Fortuna Ln to North End Aslan Ct - Seafarer Wy to North End Avenida De Loring - Buena Fortuna Ln to North End Bayless St - Blooming Meadow Rd to Ironwood Av Betts Pl - Rockcrest Dr to Sylmar Dr Blooming Meadow Rd - Bayless St to Wild Flax Ln Bluntleaf Ct - Sweetleaf St to North End Bodega Ct - Napa Valley Ct to North End Briar Knoll Pl - Rhea Dr to Blooming Meadow Rd Broadleaf Ln - Bluntleaf Ct to Sunnymead Bl Brookstone Dr - Stonebridge Ct to Poppystone Dr Buena Fortuna Ln - Abedul St to Avenida De Loring Buena Village Ct - West End to Avenida De Loring Burd Ct - Plato Dr to South End Calabria Dr - Avenida De Loring to Abedul St Callita St - Abedul St to Avenida De Loring Camino Juanito - Buena Fortuna Ln to Kramera Av Candle Shoe Ct - End to Meadow Wood Wy Canyonstone Dr - Gentian Av to Poppystone Dr Cascada Cr - Avenida De Loring to West End Caspian Wy - Dome St to Yee St Challis Ct - Pattilynn Dr to East End Chiante Ct - Pattilynn Dr to Yee St Cinnamon Creek Ct - West End to Meadow Wood Wy Cobra Dr - Wedow Dr to Santiago Dr Cockatiel Dr - Swan St to McCylly Ct Cope Ct - Plato Dr to South End Copper Cove Ln - Cypress Sands Ln to Lasselle St Crane Ct - Rhea Dr to North End Creekstone Dr - Fugate Ct to Heacock St Cushenbury Dr - Running Deer Rd to East End Cypress Sands Ln - Copper Cove Ln to South End Dome St - Yee St to Caspian Wy Dunhill Dr - Nagai Dr to Cottonwood Av Elyce Ct - Running Deer Rd to East End Flamingo Bay Ln - Copper Cove Ln to Brodiaea Av Frente Caliente - Abedul St to East End Fugate Ct - Puddingstone Dr to North End Gemstone Ct - Puddingstone Dr to North End

07/2018 09/2018 3 5 61 31

Murrieta Riverside Road Maintenance & Rehabilitation

Pavement Resurfacing - Asphalt Overlay California Oaks Road from I-15 to Clinton Keith Road

The project proposes to resurface one mile of California Oaks Road from I-15 to Clinton Keith Road utilizing cold-in-place recycling paving method. This sustainable paving practice removes more of the surface damage, and the rehabilitated road lasts longer than roads resurfaced with conventional asphalt.

California Oaks Road from I-15 to Clinton Keith Road 12/2018 05/2019 10 20 67 28

Murrieta Riverside Road Maintenance & Rehabilitation

17/18 Carryover Project - Asphalt Overlay

Asphalt overlay of Jefferson Avenue from Date Street to Cherry Street and Murrieta Hot Springs Road from Jefferson Avenue to Madison Avenue. This project will rehabilitate the existing asphaltic concrete roadways through isolated dig out repairs and hot mix asphalt overlay.

Jefferson Avenue from Date Street to Cherry Street and Murrieta Hot Springs Road from Jefferson Avenue to Madison Avenue. 06/2018 07/2018 10 20 67 28

Norco Riverside Road Maintenance & Rehabilitation Second Street Widening Project

Street widening and improvement project on Second Street eastbound lane (between Hamner Avenue and 1-15 Freeway) to add a dedicated right turn lane onto the 1-15 southbound Freeway.

Second Street eastbound lane between Hamner Avenue and I-15 Freeway. 07/2018 06/2019 15 25 60 31

Norco Riverside Road Maintenance & Rehabilitation Sixth Street Widening Project

Street widening and improvement project on Sixth Street eastbound lane (between Hamner Avenue and 1-15 Freeway) to add a dedicated right turn lane onto the 1-15 southbound Freeway.

Sixth Street between Hamner Avenue and I-15 Freeway 07/2018 06/2019 15 25 60 31

Norco Riverside Road Maintenance & Rehabilitation River Rd Rehabilitation Project

Street rehabilitation (grind and overlay) project on River Road between Main Street and Corydon Avenue. Norco has half street maintenance requirements for River Road from Second Street to Corydon Avenue and this project will be conducted jointly with the City of Corona as the Lead Agency.

River Rd between Second St and Corydon Avenue 07/2018 06/2019 15 25 60 31

Palm Desert Riverside Road Maintenance & Rehabilitation

Monterey Avenue Repaving - Whitewater Channel to Hovely Lane West

Repave 3/4 mile of road using full depth reclamation street resurfacing Northbound Monterey Avenue from Whitewater Storm Channel to Hovley Lane West 07/2018 09/2018 20 25 42 28

Palm Desert Riverside Road Maintenance & Rehabilitation

Cook Street Resurfacing - Gerald Ford Drive to Frank Sinatra Drive Cold-in-place recycling with a warm mix cap Approximately 3,300 linear feet of Cook Street, from Gerald Ford Drive to Frank Sinatra Drive. 04/2019 06/2019 20 30 42 28

Palm Springs Riverside Safety Indian Canyon Traffic Safety ProjectPedestrian safety upgrades on the Indian Canyon Corridor through downtown Palm Springs, including upgrading signals, pedestrian crossings, bulb-outs, safety lighting, and reduction of pedestrian exposure time to traffic at ten intersections.

Indian Canyon Road between Tachevah Drive and Camino Parocela 07/2018 03/2019 10 20 42 28

Perris Riverside Road Maintenance & Rehabilitation Citywide Street Rehabilitation Grind & Overlay various City streets to provide smooth roadway surface. Total area of the city contains 31.5 square miles 01/2019 02/2019 5 10 61 31

Perris Riverside Road Maintenance & Rehabilitation A Street Rehabilitation Grind & Overlay existing pavement along A Street between 4th Street and Nuevo Road. A Street (between 4th Street and Nuevo Road) 01/2019 02/2019 5 10 61 31

Perris Riverside Road Maintenance & Rehabilitation

Asphalt to Concrete Transitions Rehabilitation

Grind & Overlay asphalt at locations where asphalt meets concrete to provide smooth surface Total area of the city contains 31.5 square miles 08/2018 09/2018 5 10 61 31

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 71: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Perris Riverside Road Maintenance & Rehabilitation Perris Boulevard Pavement Rehab Grind & Overlay Perris Blvd between Ramona Expressway and Orange Avenue Perris Boulevard (between Ramona Exwy and Orange Ave) 07/2019 08/2019 5 10 61 31

Perris Riverside Road Maintenance & Rehabilitation

Ramona Expressway Pavement Rehab Grind & Overlay Ramona Expressway between Webster Avenue and Rider Street Ramona Expressway (between Webster Ave and Rider St) 07/2019 08/2019 5 10 61 31

Perris Riverside Road Maintenance & Rehabilitation

Downtown Streets Pavement Rehabilitation Grind & Overlay various streets throughout the City's Downtown region Various streets throughout downtown 01/2020 02/2020 5 10 61 31

Rancho Mirage Riverside Road Maintenance & Rehabilitation

Dinah Shore Drive Pavement Rehabilitation

This project will include a full rehabilitation of existing pavement on the westbound #1 lane of a 3/4-mile half-street segment of Dinah Shore Drive that was recently annexed into the City of Rancho Mirage. The existing pavement has deteriorated over numerous years without the necessary maintenance, which has resulted in severe alligator cracking over the entire length and a Pavement Condition Index of 41 – the lowest in the City of Rancho Mirage. The City plans to utilize the cold in-place recycling method to reduce costs.

Dinah Shore Drive, north side, from Los Alamos Road to 1,320’ west of Bob Hope Drive (Total distance: 0.75 miles) 08/2018 09/2019 10 20 42 28

Rancho Mirage Riverside Road Maintenance & Rehabilitation

Monterey Avenue Street Pavement Rehabilitation

This project will include a full rehabilitation of existing pavement for ¾ of a mile on the southbound lanes of Monterey Avenue between Hovley Lane and the north edge of the bridge at the Whitewater Channel. The existing pavement has deteriorated over numerous years and is in poor condition over the entire length of the subject area. The City plans to utilize a cold in-place recycling method with a hot mix top course to reconstruct the ¾ mile stretch of roadway.

Monterey Avenue, west side, from Hovley Lane to the north edge of the bridge at the Whitewater Channel (Total distance: 0.75 miles) 04/2019 06/2019 10 20 42 28

Riverside Riverside OtherCarryover: 2017-2018 SB-1 Maintenance and Traffic Improvements

The Road Maintenance and Rehabilitation Project will consist of resurfacing 0.39 milesof Arterial and 3.68 miles of Local roads to provide a safer and quieter street network system; existing concrete sidewalk, curb/gutter, and driveways will be rehabilitated to eliminate tripping hazards; and pedestrian ramps will be improved to the current ADA standards.

The Traffic Signal Installation project (Mission Inn Avenue at Pine Street) would signalize the intersection of Mission Inn Avenue at Pine Street. As part of the project, the intersection would include crosswalks and dedicated left-turn lane on Mission Inn Avenue to improve safety and reduce delay to Pine Street. The Pedestrian HAWK Signal Installation project (Arlington Avenue at Arlington Regional Learning Center, east of Murray St) would construct a pedestrian HAWK signal directly in front of the Arlington Regional Learning Center so students can access the RTA bus stop on the southerly side of Arlington Avenue. The project will install a crosswalk, pedestrian ramps, and pedestrian indications to safeguard pedestrian crossings.

Cranford Avenue from Seventh St. (140' N'ly) to Everton Pl. (Maintenance) Presley Avenue from Linden St. to Seventh St. (Maintenance) Seventh Street from Chicago Ave. to End of Street (Maintenance) Seventh Street from Cranford Ave. to End of Street (Maintenance) Seventh Street from Presley Ave. to Cranford Ave. (Maintenance) Box Springs Blvd. from Sycamore Canyon Blvd. to River Crest Dr. (Maintenance) Quail Valley Court from Box Springs Blvd. to End of Street (Maintenance) Douglass Avenue from Linden St. to University Ave. (Maintenance) Rossbo Avenue from Wolfe Ave. to Young St. (Maintenance) Bingham Avenue from Hole Ave. to Mobley Ave. (Maintenance) Wolfe Avenue from Rossbo Ave. to Mobley Ave. (Maintenance) Young Street from Rossbo Ave. to Bingham Ave. (Maintenance) Pierce Street from Magnolia Ave. to Indiana St. (Maintenance) Tenby Court from Weatherby Dr. to End of Street (Maintenance) Heathrow Drive from Wickham Dr. to Weatherby Dr. (Maintenance) Keys Court from Weatherby Dr. to End of Street (Maintenance) Newmarket Drive from Wickham Dr. to Weatherby Dr. (Maintenance) Weatherby Drive from Heathrow Dr. to Newmarket Dr. (Maintenance) Hedrick Avenue from Wells Ave. to Hole Ave. (Maintenance) Mimosa Hill Court from Hedrick Ave. to End of Street (Maintenance) Mission Inn Avenue and Pine Street Intersection (Traffic Signal) Arlington Avenue and Murray Street (Pedestrian HAWK Signal)

06/2018 09/2018 15 20 61 31

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 72: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Riverside Riverside Other 2018-2019 SB-1 Maintenance and Traffic Improvements

The Road Maintenance and Rehabilitation Project will consist of resurfacing 4.19 miles of Arterial and 2.29 miles of Local roads to provide a safer and quieter street network system; existing concrete sidewalk, curb/gutter, and driveways will be rehabilitated to eliminate tripping hazards; and pedestrian ramps will be improved to the current ADA standards. The Traffic Signal Installation projects will makes it easier for pedestrians, bicyclists,motorists, and public transit to enter the intersection. Traffic signals reduce overall intersection delay and in general reduce emissions and congestion.

Pedestrian Scramble Improvement projects will modify the traffic cycles and install new diagonal crosswalks to temporarily stop all vehicular traffic and allow pedestrian movements in all directions including diagonally. Pedestrian scrambles safeguard pedestrian crossings, encourage active transportation, and would better serve the numerous special events held in the Downtown area. The Pedestrian HAWK Signal Installation project will benefit John W. North High School. The HAWK signal system would improve pedestrian crossings and would encourage parents to use Trade Center Drive as an alternate drop off and pickup location. The HAWK signal is a pedestrian beacon designed to stop traffic flow to allow pedestrians to cross safely.

Mission Inn Avenue and Redwood Drive Intersection (Traffic Signal Modifications)

Business Way from Russell Street to End of Street (Maintenance) Spruce Street from La Cadena Drive to Chicago Avenue (Maintenance) Prospect Avenue from Sedgwick Avenue to End of Street (Maintenance) Sycamore Canyon Boulevard from Box Springs Boulevard, northerly to City Limits (Maintenance) Victoria Avenue from Central Avenue to Horace Street (Maintenance) Van Buren Boulevard from Wood Road to Orange Terrace Parkway (Maintenance) Donald Avenue from California to Admiralty Avenue (Maintenance) Admiralty Avenue from Donald Avenue to Jackson Street (Maintenance) Texas Avenue from Arlington Avenue to Colorado Avenue (Maintenance) Arizona Avenue from Fillmore Street to La Sierra Avenue (Maintenance) Gramercy Place from Tilden Street to La Sierra Avenue (Maintenance) Adams Street and Lincoln Avenue Intersection (Traffic Signal Modifications) Magnolia Avenue and Briscoe Street Intersection (Traffic Signal Modifications) Magnolia Avenue and Palm Avenue/Tibbets Street Instersection (Traffic Signal Modifications) Magnolia Avenue and School Circle Intersection (Traffic Signal Modifications) Brockton Avenue and Tenth Street Intersection (Traffic Signal Modifications) Chicago Avenue and Spruce Street Intersection (Traffic Signal Modifications) Columbia Avenue and Mulberry Street/Primer Street Intersection (Traffic Signal Modifications) Mission Grove Parkway and Mission Village Drive Intersection (Traffic Signal Modifications) Mission Grove Parkway and Mission Village Place Intersection (Traffic Signal Modifications) Olivewood Avenue and Ramona Drive/Panorama Road Intersection (Traffic Signal Modifications) University Avenue and Pine Street Intersection (Traffic Signal Modifications) University Avenue and Campus Drive Intersection (Traffic Signal Modifications)

Cole Avenue and Krameria Avenue Intersection (New Traffic Signal) Arlington Avenue and Chadbourne Avenue Intersection (New Traffic Signal) Market Street and University Avenue Intersection (New Pedestrian Scramble) Market Street and Mission Inn Avenue Intersection (New Pedestrian Scramble) Third Street and Trade Center Drive (New Pedestrian HAWK Signal)

04/2019 08/2019 15 20 61 31

San Jacinto Riverside Road Maintenance & Rehabilitation Downtown Pavement Rehabilitation Pavement Rehabilitation of Downtown San Jacinto including several locations

throughout the city - construction scheduled to start in FY 2018/19.

SE corner of Cottonwood Ave & Palm Ave.; Enterprise Ave & Investors Pl.; Grand Ave, Industrial Way, Bissell Pl. & Greco Ct.; Chase St. off of Ramona Exp.; Raintree Ln. ; Hewitt St. from Esplanade Ave to Shaver; Quandt Ranch Rd. ; Irwin St., El Monte, Evans & El Centro; Old Mountain Rd.; Porterfield Dr. ; and Wateka St.

04/2018 06/2019 7 10 42 23

San Jacinto Riverside Road Maintenance & Rehabilitation

Mountain Road from Seventh to Esplanade Pavement rehabilitation. Mountain Road from Seventh to Esplanade. 04/2018 06/2019 7 10 42 23

Temecula Riverside Road Maintenance & Rehabilitation

Pavement Rehabilitation Program - Meadowview Loop (Via Norte/Del Rey)

This project encompasses rehabilitating the pavement of the Meadowview neighborhood loop, which include the entire lengths of Via Norte and Del Rey Road. Entire lengths of Via Norte and Del Rey Road. 01/2019 06/2019 10 20 75 28

Temecula Riverside Road Maintenance & Rehabilitation

Pavement Rehabilitation Program - Business Park Drive Loop

This project include rehabilitating the pavement of the Business Park Drive Loop, which include the entire lengths of Business Park Drive and Single Oak Drive.

The entire loop of Business Park Drive including Single Oak Drive (From Diaz Road to Rancho California Road/Ridge Park Drive) 02/2019 06/2019 10 20 75 28

Wildomar Riverside Road Maintenance & Rehabilitation

Clinton Keith Road Rehabilitation and Repair Road Rehabilitation and Repair Palomar to Renaissance Plaza 05/2018 07/2019 16 21 67 28

Wildomar Riverside Road Maintenance & Rehabilitation

Bundy Canyon Road Rehabilitation and Repair Road Rehabilitation and Repair Oak Creek to The Farm 05/2018 07/2019 5 10 67 28

Wildomar Riverside Road Maintenance & Rehabilitation

Grand Avenue Rehabilitation and Repair Road Rehabilitation and Repair Leslie to 2000' se'ly of McVicar 05/2018 07/2019 19 24 67 28

Wildomar Riverside Road Maintenance & Rehabilitation Lemon Street Road Rehabilitation and Repair 771' SW of Gafford to Gafford 05/2019 12/2019 20 25 67 28

Wildomar Riverside Road Maintenance & Rehabilitation Inland Valley Road Rehabilitation and Repair Clinton Keith Road to Prielipp 05/2018 07/2019 20 25 67 28

Wildomar Riverside Road Maintenance & Rehabilitation PCI Update Road Rehabilitation and Repair Pavement Management Assessment and Report Citywide 07/2018 12/2018 3 4 67 28

Citrus Heights Sacramento Road Maintenance & Rehabilitation

Citywide Pavement Management System Update (Carryover)

Update Citywide Pavement Management System. Re-evaluate all streets and utilize new system/program to better tack conditions of roadway segments and coordinate data pertaining to city owned/maintained assets.

Citywide - 235 miles of maintained roadway 08/2018 01/2019 15 20 8 4

Citrus Heights Sacramento Road Maintenance & Rehabilitation

2018 Residential Street Resurfacing Project Project will resurface 13 residential streets, with existing PCI's around 25.

Thirteen residential streets located in the City of Citrus Heights: Baranga Drive; Capricorn Drive; Cheval Court; Graham Circle; Halifax Street; Daly Avenue; Alma Mesa; Carrick Court; Coronet Court; Holm Oak Way; Longden Circle; Sunwood Way.

07/2018 08/2018 15 30 8 4

Citrus Heights Sacramento Road Maintenance & Rehabilitation

2017/2018 Residential Resurfacing Project (Carryover) Resurfacing of Residential Streets (6 planned) Auburn Frontage; Catamaran; Knisley Court, Tareyton; (list revised based on updated estimates and

streets moved to 18/19 SB1 project) 08/2018 09/2018 20 25 8 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 73: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Elk Grove Sacramento Road Maintenance & Rehabilitation

Bond Road Median Improvements and Resurfacing

The project will provide a two-inch overlay for the entire roadway from East Stockton Blvd. to the bridge at Laguna Creek (~4300 feet) including new striping, markings and traffic loops. The project will also construct about 2100 feet of raised center median on Bond Rd, between E. Stockton Blvd. and Egret Dr. And provide an EB left turn pocket into the shopping center’s eastern driveway. Carry-over project from FY17/18

Bond Road between East Stockton Blvd. & bridge at Laguna Creek. Raised Center Median; E. Stockton Blvd to Egret Dr. to create a physical separation between eastbound and westbound traffic. 11/2018 08/2019 15 24 9 6

Elk Grove Sacramento Safety Green Bike Lane Pilot Project Project would add about 3000 feet of green bike lane marking in the conflicted areas. Carry over project from FY17/18

Elk Grove Boulevard from the intersection of Auto Center Drive to E. Stockton Boulevard, & Laguna Boulevard at the intersection with Neosho Drive. 06/2018 09/2018 5 10 9 6

Elk Grove Sacramento Road Maintenance & Rehabilitation

2019 Pavement Slurry Seal and Resurfacing

Approximately 752,800 square feet of asphalt overlay streets. All non compliant ramps will be corrected as part of the asphalt overlay project. Approximately 6.7 million square feet of slurry or chip seal streets. All the above mentioned areas will receive new traffic striping.

Slurry & Chip Seal Streets Laguna Crest Way; Laguna Blvd to Sage Glen Way LAGUNA QUAIL WAY; RED DOG CREEK DR to RED DOG CREEK DR SITKA CT; WEEPING FIG WY to CDS-EAST END MOLINERO CT; LAGUNA QUAIL WAY to CDS-SOUTH END TEGAN RD; FRANKLIN BL to 1271 FT W/OF FRANKLIN BL WHISKEY CREEK DR; LAGUNA QUAIL WY to LAGUNA PARK DR SICKLE CT; LAGUNA QUAIL WY to CDS-EAST END SAGE GLEN WAY; LAGUNA CREST WAY to EAST DEAD END CANADEO CIR; CHAMBERLIN CIR to BLOSSOM RIDGE DR LEEMANS WAY; WATERFIELD DR to VAN BROCKLIN WAY CHAMBERLIN CIR; WATERFIELD DR to TITTLE WAY CLEARY CIR; WATERFIELD DR (SOUTH) to WATERFIELD DR (NORTH) MILLNER WAY; CHAMBERLIN CIR to BLOSSOM RIDGE DR JURGENSON WAY; LUCKMAN WAY to WATERFIELD DR TRAFTON CT; CHAMBERLIN CIR to CDS KINARD WAY; WATERFIELD DR to BLOSSOM RIDGE DR LUCKMAN WAY; BLOSSOM RIDGE DR to VAN BROCKLIN WAY VAN BROCKLIN WAY; JURGENSON WY to KINARD WAY WATERFIELD DR; WHITELOCK PKWY to KINARD WAY LAMBEAU CT; LEEMANS WAY to CDS TITTLE WAY; JURGENSON WY to BLOSSOM RIDGE DR CONZELMAN WAY; WATERFIELD DR to TITTLE WAY SIMONICH WAY; HITE CIR to SHOECH WAY SHOECH CT; SIMONICH WAY to CDS BENGAL CT; GILLIAM DR to CDS MILLNER WAY; BLOSSOM RIDGE DR to CANADEO CIR SIMOES CT; STOECKER WY to CDS BATTLES CT; CANADEO CIR to CDS HITE CIR; SIMONICH WAY to SIMONICH WAY LOTUS POND CT; GOLDEN GLORY WAY to CDS QUICK CT; GILLIAM DR to CDS VAN STEYN CT; STOCKMEN WY to CDS WARMERDAM CT; HITE CIR to CDS CANADEO CIR; E BLOSSOM RIDGE DR to W BLOSSOM RIDGE DR KNEPPLE CT; CANADEO CIR to CDS MATINA DR; WILLARD PKWY to GILLIAM DR SHOECH WAY; SIMONICH WAY to GILLIAM DR STOECKER CT; LUTTIG WAY to CDS STOECKER WAY; LUTTIG WAY to SHOECH WY

08/2018 06/2019 7 20 9 6

Folsom Sacramento Road Maintenance & Rehabilitation

Pavement Resurfacing Project FY 18-19 Microsurfacing treatment on various roadways.

Folsom-Auburn Road (Oak Avenue to Folsom Dam Road) Folsom Lake Crossing (Folsom-Auburn to E. Natoma Street) Blue Ravine Road (E. Natoma Street to Oak Avenue Parkway) Iron Point Road (Oak Avenue Parkway to E. Bidwell Street) American River Canyon North neighborhood

08/2018 06/2019 5 10 6 1

Folsom Sacramento Road Maintenance & Rehabilitation

Plaza Drive Pavement Rehabilitation Asphalt overlay of roadway, ADA upgrades. Plaza Drive loop 10/2018 06/2019 15 25 6 1

Folsom Sacramento Other Willow Creek Estates Storm Drain Lining Lining of deteriorated storm drain pipes Various locations within the Willow Creek Estates neighborhood 08/2018 06/2019 25 50 6 1

Galt Sacramento Road Maintenance & Rehabilitation

2018/19 Pavement Rehabilitation Project

Roadway rehabilitation as identified by the 2018/19 SB1 project list. The work, in general, will rehabilitate deteriorate roadways within the City of Galt city limits.

Project locations will be selected from the executed Resolution for SB1 2018/19 Project List as shown:1ST ST (F ST KOST RD 64 $481,600); MEADOWVIEW DR (CINDY LN KOST RD 37 $163,200); CREEKSIDE WAY (MEADOWVIEW DR KOST RD 75 $102,900 ; CINDY LN (1ST ST TUDOR ST 74 $45,300); DOVER DR (MEADOWVIEW DR TUDOR ST 79 $32,100); DOWNING DR (1ST ST W END 68 $46,400); TUDOR ST ( KENT ST KOST RD 68 $29,000); KENT ST (TUDOR ST CINDY LN 74 $12,600); KANDY ST (TUDOR ST CREEKSIDE WAY 74 $8,400); CARLO CT (1ST ST W END 79 $15,700); FAIRWAY DR (CAROLINE AVE GLENDALE AVE 52 $147,700); GLENDALE AVE (FAIRWAY DR MELADEE AVE 70 $39,500); CASADO DR (MELADEE AVE GLENDALE AVE 70 $27,700); MELADEE LN (CAROLINE AVE LINCOLN WY 77 $108,200); SOUTHDALE CT (MELADEE AVE LINCOLN WY 79 $30,900); HAPPY CT (CASADO DR S END 70 $9,200); B ST (4TH ST LINCOLN WY 36 $120,100); 6TH ST (A ST G ST 37 $155,100)

08/2018 09/2018 8 15 9 5

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 74: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Galt Sacramento Complete Streets Components

South Galt Safe Routes to School and Rehabilitation and SACOG Bicycle and Pedestrian Improvement Project (17/18 Ongoing)

South Galt Safe Routes to School and Rehabilitation and SACOG Bicycle and Pedestrian Improvement Project CIP #518C, project description includes repairs of pavement, restriping existing bicycle lanes and bike lanes gaps, adding pedestrian bulbouts and median refuge islands, adding signage and warning devices as well as adjusting utilities to grade. The project will also replace damaged sidewalk sections, upgrading to current ADA standards and adding sidewalks/walkways. The project location is bounded by SR99 to Pringle and South to Kost Road. The maximum useful life of the project is approximately 20 years. The anticipated year of construction is 2017-18.

The project is located in the City of Galt. The work is on A Street from the east to west City limits. 03/2018 07/2018 10 20 9 5

Isleton Sacramento Road Maintenance & Rehabilitation

Union St. from F St. to H St. (2017-2018 Carryover) Grind and Overlay - 534' x 30' - 3' x 534' 1-30" manhole Union St. from F St. to H St. 12/2018 01/2019 15 20 11 3

Isleton Sacramento Road Maintenance & Rehabilitation

3rd St from Jackson to C Street (2017-2018 Carryover) Grind and Overlay - 680' x 25' Grind and Overlay and 10 Handicap upgrades 3rd St from Jackson to C Street 01/2020 06/2020 15 30 11 3

Isleton Sacramento Road Maintenance & Rehabilitation

4th St from A St to B St (2017-2018 Carryover)

Grind and Overlay - 272' x 30' needs handicap ramps at B St. & gutter rehab (Cost estimate does not include gutter rehab) 4th St. from A St. to B Street 01/2020 06/2020 15 30 11 3

Isleton Sacramento Road Maintenance & Rehabilitation

B St. from 2nd to 5th Street (2017-2018 Carryover)

Grind and Overlay - 588' x 18' Roughly half has 3' sidewalks ADA should be 4'. 1-30"x30" stormgrate 2- 30"manholes, 1-monitoring well, 1 water service B St. from 2nd to 5th Street 01/2020 06/2020 15 20 11 3

Isleton Sacramento Road Maintenance & Rehabilitation

Everything West of Delta Avenue (2017-2018 Carryover) Slurry Seal - This is a actual quote for a slurry seal coat Everything West of Delta Avenue 06/2019 07/2019 15 20 11 3

Isleton Sacramento OtherPark & Ride Lot Parcel 15700260020000 (2017-2018 Carryover)

Grind and Overlay - Estimated 15,112 square feet pave for park & ride lot - stripe parking stalls - bicyle parking area, (3 handicap) 2nd & D Street - Parcel 15700260020000 09/2018 12/2018 15 20 11 3

Isleton Sacramento Road Maintenance & Rehabilitation

2nd Street - C to E Street (2017-2018 Carryover) Grind and Overlay - Estimated 11,915 square feet 2nd Street from C Street to E Street; curve to Hwy 160 01/2018 06/2019 15 20 11 3

Rancho Cordova Sacramento Complete Streets Components

Folsom Boulevard Enhancement Phase V

This project will construct complete streets components on Folsom Boulevard from Horn Road to Bradshaw Road including road rehabilitation, landscaped medians, construction of sidewalks, and streetscape improvements at intersections. The project will also include storm drain upgrades as necessary.

Folsom Boulevard between Horn Road and Bradshaw Road. 10/2018 04/2019 15 20 8 4, 8

Rancho Cordova Sacramento Road Maintenance & Rehabilitation Sunrise Rehabilitation - Phase 1

This project will rehabilitate Sunrise Boulevard from Folsom Boulevard to Citrus Road. The project will also include sidewalk upgrades/repairs and storm drain upgrades as necessary.

Sunrise Boulevard from Folsom Boulevard to Citrus Road 02/2019 05/2019 15 20 8 4, 8

Sacramento Sacramento Road Maintenance & Rehabilitation Natomas Boulevard Placement of Hot Mix Asphalt (HMA) over the existing pavement structure to extend the

life of the street and avoid major street reconstruction in the future. From North Park Drive to Elkhorn Boulevard 05/2018 10/2018 15 30 7 6

Sacramento Sacramento Road Maintenance & Rehabilitation Grand Avenue Placement of Hot Mix Asphalt (HMA) over the existing pavement structure to extend the

life of the street and avoid major street reconstruction in the future. Marysville Blvd to Rio LInda Blvd 05/2018 10/2018 15 30 7 6

Sacramento Sacramento Road Maintenance & Rehabilitation J Street Placement of Hot Mix Asphalt (HMA) over the existing pavement structure to extend the

life of the street and avoid major street reconstruction in the future. 16th Street to 30th Street 05/2018 10/2018 15 30 7 6

Sacramento Sacramento Road Maintenance & Rehabilitation Mack Road Placement of Hot Mix Asphalt (HMA) over the existing pavement structure to extend the

life of the street and avoid major street reconstruction in the future. Stockton Blvd to Morrison Creek bridge deck 05/2018 10/2018 15 30 9 6

Hollister San Benito Road Maintenance & Rehabilitation

Annual Road Rehabilitation FY 18/19--Design Phase

This is the Design Phase for the Annual Road Rehabilitation Project for Fiscal Year 2018/2019, involving a number of specific locations throughout the City of Hollister identified as needing improvement. Each of the specific areas listed have a current Pavement Condition Index (PCI) of 45-85, based upon the City's Pavement Management System. This is the first phase of the Annual Road Rehabilitation Project for FY 18/19, with an estimated project cost of $200,000 in RMRA funds. The Construction Phase will follow with an estimated $657,083 in RMRA funding and $542,927 in other identified funding for a total construction cost of 1.2 million. Together, the Design and Construction phases of the Annual Road Rehabilitation FY 18/19 are estimated to total 1.4 million.

Central Avenue--east of Graf Road to west of College Street Fifth Street--east of San Benito Street to west of Sally Street Seventh Street--west of Line Street to west of San Benito Street Ladd Lane--north of Talbot Drive to north of Southside Road Talbot Drive--west of Sunset Drive to east of Olga Drive Nora Drive--south of Tina Drive to north of Irma Drive Olga Drive--south of Talbot Drive to north of north of Majestic Drive Paul Drive--west of Ladd Lane to east of Nora Drive Hillock Drive--east of Ladd Lane to North of Sunset Drive

05/2018 06/2019 10 30 30 12

Hollister San Benito Road Maintenance & Rehabilitation

Annual Road Rehabilitation FY 18/19--Construction Phase

This is the Construction Phase of the Annual Road Rehabilitation Project for Fiscal Year 18/19, for a number of identified locations within the City of Hollister as having a current Pavement Condition Index (PCI) of 45-85, based upon the City's Pavement Management System. The goal of this project is to improve the PCI of these streets and extend the life expectancy of the pavement for these local roads. Total costs for the Construction Phase is estimated to be 1.2 million, with an estimated $457,083 in RMRA funding and $742,927 in other identified funding. Together, the Design and Construction phases of the Annual Road Rehabilitation FY 18/19 are estimated to total 1.4 million.

Central Avenue--east of Graf Road to west of College Street Fifth Street--east of San Benito Street to west of Sally Street Seventh Street--west of Line Street to west of San Benito Street Ladd Lane--north of Talbot Drive to north of Southside Road Talbot Drive--west of Sunset Drive to east of Olga Drive Nora Drive--south of Tina Drive to north of Irma Drive Olga Drive--south of Talbot Drive to north of north of Majestic Drive Paul Drive--west of Ladd Lane to east of Nora Drive Hillock Drive--east of Ladd Lane to North of Sunset Drive

05/2018 06/2019 10 30 30 12

San Juan Bautista San Benito Road Maintenance & Rehabilitation

San Juan/Hollister Road Pavement Project Resurface this roadway San Juan/Hollister Road (The Alameda is the closest cross street) 01/2019 05/2019 15 20 30 12

Adelanto San Bernardino Road Maintenance & Rehabilitation

Pavement Repair and Rehabilitation Project, Phase I

Apply crack seal & type II slurry over 237,000 square feet of existing asphalt pavement. Re-install all pavement markings.

•Muskrat Ave, Joshua St, Dennis St, Panther Ave. and Janine St. between Jay St. and Kay St. •Jay St. between Racoon Ave. and Muskrat Ave. •Kay St. between Janine St. and Muskrat Ave.

07/2018 09/2018 3 5 33 21

Adelanto San Bernardino Road Maintenance & Rehabilitation

Pavement Repair and Rehabilitation Project, Phase II

Apply crack seal & type II slurry over 184,000 square feet of existing asphalt pavement. Re-install all pavement markings.

•Stevens St. and Aster Rd. between Chamberlaine Way and Vintage Road. •Vintage Rd. and Chamberlaine Wy. Between Stevens St. and Aster Rd. •The east half of Mendicino Rd. between Stevens St. and Aster Rd. •Sonoma Rd, Zinfadel Dr, Bouquet Ave. and Napa Rd.

07/2018 09/2018 3 5 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Bear Valley Road Resurfacing Resurface Bear Valley Road from the western town limit to Joshua Road (5 miles). Bear Valley Road from the western town limit to Joshua Road 07/2018 10/2018 7 10 33 21

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 75: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Apple Valley San Bernardino Road Maintenance & Rehabilitation Yucca Loma Road Resurfacing Resurface Yucca Loma Road from Apple Valley Road to Navajo Road (3 miles). Yucca Loma Road from Apple Valley Road to Navajo Road 07/2018 10/2018 7 10 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Central Road Resurfacing Resurface Central Road from Bear Valley Road to Thunderbird Road (2 miles). Central Road from Bear Valley Road to Thunderbird Road 07/2018 10/2018 7 10 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Riverside Drive Resurfacing Resurface Riverside Drive from Shoshonee Road to Branding Iron (2.2 miles). Riverside Drive from Shoshonee Road to Branding Iron 07/2018 10/2018 7 10 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Rincon Road Resurfacing Resurface Rincon Road from Yucca Loma Road to Rancherias Road (1.4 miles). Rincon Road from Yucca Loma Road to Rancherias Road 07/2018 10/2018 7 10 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Shoshonee Road Resurfacing Resurface Shoshonee Road from Rincon Road to Tonawanda Road (.63 miles). Shoshonee Road from Rincon Road to Tonawanda Road 07/2018 10/2018 7 10 33 21

Apple Valley San Bernardino Road Maintenance & Rehabilitation Flathead Road Resurfacing Resurface Flathead Road from Tonawanda Road to Highway 18 (.6 miles). Flathead Road from Tonawanda Road to Highway 18 07/2018 10/2018 7 10 33 21

Barstow San Bernardino Road Maintenance & Rehabilitation

West Section 7 Rehabilitation Project - (17/18 Carryover) Reconstruct pavement approximately 23,401 center line feet of roadway. West Section 7 is defined north of Rimrock Road, east of Agarita Avenue, south of Interstate 15, and

West of Barstow Road (Route 247) 04/2019 08/2019 15 20 33 16

Barstow San Bernardino Road Maintenance & Rehabilitation

Pavement Preservation Project (17/18 Carryover) Placement of pavement preservation techniques on existing roadway The project location is defines as east of Muriel Drive, South of East Main Street, and north of

Interstate 15. 04/2019 07/2019 3 7 33 16

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

General Program Categories - Overlay

Annual program to overlay local streets as economies of scale opportunities present mid-year Locations based on the 90 miles of the roadway within the City limit 07/2019 07/2020 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

General Program Categories - Overlay

Annual program to overlay local streets as economies of scale opportunities present mid-year Locations based on the 90 miles of the roadway within the City limit 07/2020 07/2021 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation General Program Categories Annual program to overlay local streets as economies of scale opportunities present

mid-year Locations based on the 90 miles of the roadway within the City limit 07/2021 07/2022 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation General Program Categories Annual program to overlay local streets as economies of scale opportunities present

mid-year Locations based on the 90 miles of the roadway within the City limit 07/2022 07/2023 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Menlo Drive, Sheephorn Road, Villa Grove Avenue, Wolf Road Chip Seal

chip seal application of a local street Menlo Drive, Sheephorn Road, Villa Grove Avenue, Wolf Road Chip Seal - Entire Lengths 07/2018 07/2019 3 5 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Lagunita Pavement and Drainage Rehabilitation full depth reconstruction of a local street with drainage improvements Lakeview Drive To End 07/2019 07/2020 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Lower Moonridge Pavement and Sidewalk Rehabilitation full depth reconstruction of a local street with drainage improvements Elm Street To Big Bear Boulevard 07/2019 07/2020 20 25 33 23

Big Bear Lake San Bernardino SafetyATP grant for street improvements sidewalk and bike lane matching funds

construct missing link sidewalks and stripe additional bike lanes Big Bear Boulevard: Edgemoor Road to Cienega Road & Mig Bear Bear Boulevard: Stanfield Cutoff to Division Drive 07/2019 07/2020 15 20 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Talbot Drive - Pavement Reconstruction Pavement Reconstruction Big Bear Boulevard to North End 07/2020 07/2021 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Upper Moonridge Pavement and Sidewalk Rehabilitation Pavement and Sidewalk Rehabilitation Elm Street To Clubview Drive 07/2020 07/2021 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Summit Boulevard Pavement Reconstruction full depth reconstruction of a local street Big Bear Boulevard to Snow Summit Base Area 07/2021 07/2022 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation

Clubview Drive Pavement Reconstruction full depth reconstruction of a local street Moonridge Road to Bear Mountain Base Area 07/2022 07/2023 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation Cliff Drive Pavement Reconstruction full depth reconstruction of a local street Talmadge Road to Spruce Road 07/2022 07/2023 20 25 33 23

Big Bear Lake San Bernardino Road Maintenance & Rehabilitation FY 18/19 Street Improvements Full depth reconstruction and/or overlay of a local street

Balboa Lane- Santa Clara Boulevard To End, Berkley Lane-Pennsylvania Avenue To Marin Drive, Boulder Bay Court- Willow Landing To End, Bow Canyon Court- Bow Canyon Road To End, Bow Canyon Lane-Bow Canyon Road To End, Chipmunk Lane-Chincapin Road To Willow Landing,Elgin Road and Knoll Road- North Of Forest Road,Homestead Lane and Red Oak Lane- East of Knight Avenue, Lakeview Court-North Of Lakeview Drive, Manzanita Court- Rueda Lane To End, Marin Road-Pennsylvania Avenue To Berkley Lane, Meadowhill Place- West of Stony Creek Road, Mendocino Drive-Yosemite Drive To End, Sand Canyon Court-Sand Canyon Road To End, Short Lane-East Of Bonita Lane, Siskiyou Drive- Shasta Road To Deer Canyon Road, Swan Drive- Oriole Drive To Wren Drive, Clubview Drive- Goldmine Drive To Clover Drive

07/2018 07/2019 20 25 33 23

Chino San Bernardino Road Maintenance & Rehabilitation

Street Rehabilitation and TSM FY2018-19 - Riverside Drive

Street Grind and Overlay of Riverside Drive which also includes construction of approximately 40 ADA accessibility ramps and full depth reconstruction of some areas. Project will also include traffic signal modifications for two signalized intersections.

Riverside Drive (Central Ave. to 200 LF w/o Oaks St.) and traffic signal modifications @ Riverside Dr/Benson Ave and Riverisde Dr./10th St. 12/2019 06/2020 10 15 52 20

Chino San Bernardino Road Maintenance & Rehabilitation

FY 2018-19 Street rehabilitation Project - County Co-Op

Rehabilitation of Pipeline Avenue, Chino Avenue and East End Avenue utilizing Grind and Overlay. The project will also include the construction of approximately 37 ADA accessibility ramps. This project is in cooperation with The Count of San Bernardino Public Works Department.

Pipeline Avenue (Chino Ave to Philadelphia Ave.) and East End Avenue (Riverside Ave. to Philadelphia Ave.) and Chino Avenue (Pipeline Ave to SR71) 12/2020 06/2021 10 15 52 20

Chino San Bernardino Road Maintenance & Rehabilitation

El Prado Reconstruction Project (17/18 Carryover)

Reconstruction including but not limited to: grind and overlay of asphalt; selected removal of replacement of asphalt; concrete curb; gutter; spandrel and cross gutter; signing and striping and accessible ramps.

El Prado Road (Central Avenue to Kimball Avenue) 06/2018 06/2019 10 15 52 20

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 76: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Chino San Bernardino Complete Streets Components

TDA Bycicle, Pedestrian and Transit Accessibility Improvements

Construction of 53 pedestrian and transit ADA accesibility ramps along with approximately 4.3 miles of bicycle lanes which will include construction of sidewalk, street, curb& gutter, cross-gutter and spandrels for proper drainage. Installation/relocation of streetlight poles, vaults, valves, manholes and street signs to ensure safe, clear and compliant paths of travel for active transportation purposes.

Accessibility ramps along B Street and C Street between Monte Vista Avenue and 4th Street. Bicycle Lanes within our City of Chino Bicycle and Pedestrian Master Plan with priority rank 1-5. These bike lanes are along 12th Street, B Street, 10th Street and C Street. Total of approximately 4.3 miles

12/2018 06/2019 20 25 52 20

Chino Hills San Bernardino Road Maintenance & Rehabilitation Rolling Ridge Drive Rehabilitation

The work will include the removal and reconstruction of damaged pavement, curbs and gutters, ADA access ramps, grind and overlay of existing pavement, adjustment of manholes and water valves, striping, and signing

Rolling Ridge Drive from Chino Hills Parkway to Bayberry Drive, Chino Hills 12/2018 04/2019 10 15 55 29

Colton San Bernardino Road Maintenance & Rehabilitation

San Bernardino Ave. (Eucalyptus to Indigo Ave.) Pament Rehabilitation Project

Asphalt grinding and overlay with rubberized asphalt San Bernardino Ave. (West of Pepper Ave.), Colton, CA 92324 08/2018 01/2019 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

La Cadena Drive (Barton Road. to Iowa) Pavement Rehabilitation Project

Asphalt grinding and rubberized asphalt overlay La Cadena Drive (South of Barton Road), Colton, CA 92324 08/2018 01/2019 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

Mt. Vernon Ave (F St. to Colton Ave.) Pavement Rehabilitation Project

Asphalt grinding and rubberized asphalt overlay Mt. Vernon Ave. (north of F Street), Colton, CA, 92324 08/2018 01/2019 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

Santo Antonio Drive (Mt. Vernon Ave. to East End) Pavement Rehabilitation Project

Asphalt grinding and rubberized asphalt overlay Santo Antonio Drive (east of Mt. Vernon Ave), Colton, CA, 92324 08/2018 01/2019 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

Mill Street Paving Project (17/18 on-going) 1-1/2" to 2" thick grinding and rubberized asphalt overlay. Mill Street between Rancho Ave. and Michigan Ave. 03/2018 07/2018 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

Olive Street Paving Project (17/18 on-going) 1-1/2" to 2" thick grinding and rubberized asphalt overlay Olive Street between La Cadena and 6th Street 03/2018 07/2018 10 15 47 20

Colton San Bernardino Road Maintenance & Rehabilitation

San Bernardino Ave. Paving Project (17/18 On going) 1-1/2" to 2" thick grinding and rubberized asphalt overlay San Bernardino Ave. from Eucalyptus Avenue to Indigo Avenue 03/2018 12/2018 10 15 47 20

Fontana San Bernardino Road Maintenance & Rehabilitation

Pavement Rehabilitation SB-1 RMRA Project

Pavement Rehabilitation for the five streets as listed below and shall consist of cold plane/overlay asphalt pavement, pavement markings, manholes, and utility adjustments.

Hemlock Avenue -Slover to Santa Ana Poplar Avenue -Slover to Santa Ana Live Oak Avenue -Slover to Santa Ana Beech Avenue -Slover to Jurupa Santa Ana Avenue -Cherry to Live Oak

09/2018 06/2019 10 15 47 20

Grand Terrace San Bernardino Road Maintenance & Rehabilitation

Pavement Rehabilitation Project (2017-18 Carry Over)

Grind and overlay; pulverize, place pulverized miscellaneous base and pave; ADA ramps, slurry seal, and curb and gutter repair

Arliss Lane from Cul De Sac to Arliss Drive; Arliss Lane from Arliss Drive to Cul De Sac; McClarren Street from Vivienda Avenue to Canal Street; Orangewood Court from Observation Drive to End of Street; Mavis Street from Michigan Avenue to Vivienda Avenue; Vivienda Avenue from Cul De Sac to Van Buren Street; Dos Rios Avenue from Country Club Lane to De Berry Street; Franklin Street from Mirado Avenue to Mt. Vernon Avenue; Vista Grande Way from Grand Terrace Road to North of Dog Park; Minona Court from Minona Drive to Cul De Sac; Pascal Avenue from De Berry Street to Cul De Sac; Arliss Way from Cul De Sac to Arliss Drive; Eton Drive from Thames Street to Preston Street; Glendora Drive from Barton Road to End of Street; Palm Court from Palm Avenue to Cul De Sac; W. Litton Avenue from S. Rosedale Avenue to S. La Cadena Drive; Miriam Way from Arliss Drive to Kington Street; Robin Way from Warbler Avenue to Oriole Avenue; Vivienda Avenue from Terrace Avenue to Maple Avenue; Honey Hill Drive from Westwood Street to Palm Avenue; Jensen Court from Cul De Sac W. End to Observation Drive; De Soto Street from Kingston Street to Dos Rios Avenue; Lark Street from Reed Avenue to Cul De Sac; Siskin Court from Paradise Street to Cul De Sac; Willet Avenue from Mavis Street to Van Buren Street; Dutch Street from Pico Street to Tanager Street; Dos Rios Avenue from Palm Avenue to Country Club Lane; Rosedale Avenue from Palm Avenue to City Limit (South); Arliss Drive from Preston Street to End of Street; Mirado Avenue from Pico Street to Ladera Street; Flamingo Street from Michigan Avenue to Cul De Sac; Nandina Street from Preston Street to Canary Court; Pascal Avenue from Victoria Street to Carhart Avenue; Royal Avenue from Pico Street to End of Street

07/2018 10/2018 10 15 47 20

Grand Terrace San Bernardino Road Maintenance & Rehabilitation Pavement Rehabilitation Project Grind and Overlay 2.5" asphalt concrete, repair damaged curb and gutter, install ADA

ramps, and restore striping at various locations throughout the City of Grand Terrace.

Fremontia Avenue from Reed Avenue to W. Main Street; Terrace Avenue from Vivienda Avenue to Walnut Avenue; De Soto Street from Warbler Avenue to Oriole Avenue; Grand Terrace Court from Grand Terrace Road to Cul De Sac; Carhart Avenue from Vivienda Court to Canal Street; Oriole Avenue from La Paix Street to De Berry Street; Garden Avenue from Cul De Sac to Pico Street; Minona Drive from Eton Drive to Preston Street; Walnut Avenue from Terrace Avenue to Burns Avenue; Pico Street from Mount Vernon Avenue to Oriole Avenue

04/2019 06/2019 15 20 47 20

Hesperia San Bernardino Road Maintenance & Rehabilitation FY 2018-19 Slurry Seal Project Road Maintenance via slurry seal over selected roads in disrepair to extend their useful

life. 73.10 Square Miles Within the City limits 06/2018 08/2018 5 10 59 17

Hesperia San Bernardino Road Maintenance & Rehabilitation

FY 2018-19 Street Improvement Project

This project includes removal and replacement of asphalt as well as the remediation of severe drainage issues and a sag in the sewer line through this section of roadway. Main Street from La Junta Road to Pyrite Avenue 06/2018 08/2018 20 25 59 17

Highland San Bernardino Road Maintenance & Rehabilitation 4th Street Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay 4th Street from west end to east end 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation 6th Street Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay 6th Street from Tippecanoe Ave. to Del Rosa Dr. 07/2018 12/2018 10 15 40 23

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 77: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Highland San Bernardino Road Maintenance & Rehabilitation 9th Street Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay 9th Street from 600 feet east of Tippecanoe Ave. to Fairfax Ln. 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation

Del Rosa Avenue Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Del Rosa Ave. from 3rd Street to 4th Street 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation

Del Rosa Avenue Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Del Rosa Ave. from Base Line to Pacific St. 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation

Ditmar Ave. Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Ditmar Ave. from Union St. to Vine St. 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation

Marilyn Ave. Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Marilyn Ave. from 3rd Street to 4th Street 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation Rogers Ln. Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Rogers Ln. from Union St. to Vine St. 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation Vine St. Pavement Rehabilitation Rehabilitate pavement with localized reconstruction and overlay Vine St. from Sterling Ave. to East End 07/2018 12/2018 10 15 40 23

Highland San Bernardino Road Maintenance & Rehabilitation City-wide Minor Street Maintenance Repair potholes and perform minor pavement rehabilitation as necessary On 157.2 miles of arterials, collectors and local streets 07/2018 06/2019 2 5 40 23

Highland San Bernardino Safety City-wide Pavement Striping and Marking Maintain pavement striping and marking as necessary. On 157.2 miles of arterials, collectors and local streets 07/2018 06/2019 3 7 40 23

Highland San Bernardino Traffic Control Devices City-wide Traffic Signal Maintenance Maintain traffic signal systems as necessary Thirty nine (39) traffic signal systems located at arterial intersections 07/2018 06/2019 10 30 40 23

Highland San Bernardino Road Maintenance & Rehabilitation

Sterling Avenue Pavement Rehabilitation

Rehabilitate pavement with localized reconstruction and overlay (carried over from FY 2017-18) Sterling Avenue from 6th Street to Base Line 07/2018 06/2019 10 15 40 23

Loma Linda San Bernardino Road Maintenance & Rehabilitation Citywide Slurry seal 0.6 miles of roadway.

Oakwood Drive from Barton Road south to end; Khan Drive from Oakwood Drive to Vollmer Drive; Paulson Drive from Oakwood Drive to Vollmer Drive; Vollmer Drive from Khan Drive to Paulson Drive; Wareham Court from Vollmer Drive to end.

07/2018 08/2018 7 15 40 23

Loma Linda San Bernardino Road Maintenance & Rehabilitation Citywide Repave/resurface 1.4 miles of roadway

Daisy Street from Poplar Street to Benton Street; Iris Street from Lawton Avenue to Tulip Street; Aster Street from Lawton Avenue to Tulip Street; Starr Street from Anderson Street to Hillcrest Street; Hillcrest Street from Prospect Avenue to Barton Road; Campus Street from Barton Road to Lawton Avenue; Richardson Street from Starr Street to Barton Road.

07/2018 08/2018 7 15 40 23

Montclair San Bernardino Road Maintenance & Rehabilitation

Holt Boulevard Street Improvement Project

The project will repair any uplifted curb, gutter and sidewalk; replace non-compliant pedestrian ramps and resurface the asphalt pavement. 4000-4400 blk Holt Boulevard 11/2018 04/2019 15 20 52 20

Montclair San Bernardino Traffic Control DevicesNorth Montclair Traffic Signal Interconnect Improvement Project- Design Only

Design services for the installation of new conduit, fiber and traffic control hardware associated with a new traffic signal interconnect system north of the Interstate 10. This project will ultimately make a complete interconnect system Citywide.

Monte Vista Avenue, Moreno Street, Arrow Hwy and Central Avenue 02/2019 06/2020 15 20 52 20

Montclair San Bernardino Road Maintenance & Rehabilitation

Monte Vista Avenue Street Rehabilitation (Design Only)

Design services only. The project will repair curb, gutter and sidewalk, upgrade traffic signal equipment, resurface the pavement, and stripe the street.

The project limits include both northbound and southbound lanes from Pacific Electric Bicycle Trail (north city limits) to Phillips Street (south city limits) 01/2019 12/2019 10 20 52 20

Needles San Bernardino Road Maintenance & Rehabilitation River Road Re-Construction Project Complete reconstruction of road section Jack Smith Park to North K Street 02/2019 03/2019 20 40 33 16

Ontario San Bernardino Road Maintenance & Rehabilitation

2018 Pavement Rehabilitation Project

Grind & overlay asphalt street, repair fail asphalt areas, repair sidewalk, repair curb & gutter, upgrade all ramps to current ADA standards, restripe roadway. Milliken Avenue - Jurupa Street to Airport Drive (17/18 Carryover) 06/2018 12/2018 15 25 52 20

Ontario San Bernardino Road Maintenance & Rehabilitation

2019 Pavement Rehabilitation Project

Grind & overlay asphalt street, repair fail asphalt areas, repair sidewalk, repair curb & gutter, upgrade all ramps to current ADA standards, restripe roadway.

Archibald Avenue - SR 60 and Riverside Drive (17/18 Carryover) Philadelphia Street - Archibald Avenue to Haven Avenue (17/18 carryover) Concourse Avenue - Haven Avenue to Milliken Avenue Cedar Street - Campus Avenue to Euclid Avenue

06/2019 12/2019 15 25 52 20

Ontario San Bernardino Other TCC Mission Boulevard Improvements

Project design of 5 miles of bike lanes, street improvements, street lights, ADA ramps, sidewalks Mission Boulevard between Benson Avenue & Bon View Avenue 06/2019 12/2019 15 25 52 20

Ontario San Bernardino Traffic Control Devices 2018 Traffic Signal Improvements Upgrade to video detection equipment, intersection improvements, ADA improvements. Grove Avenue and Francis Street Vineyard and Sixth Street 06/2019 12/2019 15 25 52 20

Rancho Cucamonga San Bernardino Road Maintenance & Rehabilitation

FY17/18 SB1 Non-Local Street Pavement Rehabilitation at Two Locations

The project involves storm drain, localized asphalt repair, cold planning, crack sealing, asphalt rubber hot mix overlay, video detection signal upgrades, ADA ramp upgrades, utility adjustments and pavement striping for approximately 2.55 miles of roadway.

FY17/18 SB1 Non-Local Street Pavement Rehabilitation at Two Locations: 6th Street from Milliken Avenue to Charles Smith Avenue Jersey Boulevard from Haven Avenue to Rochester Avenue

07/2018 08/2018 20 30 40, 41 23

Rancho Cucamonga San Bernardino Road Maintenance & Rehabilitation

FY18/19 SB1 Non-Local Street Pavement Rehabilitation at Three Locations

The project includes cold planning, localized asphalt repair, crack sealing, asphalt rubber hot mix overlay, video detection signal upgrades, ADA ramp upgrades, utility adjustments and pavement striping for approximately 2.25 miles of roadway.

FY18/19 SB1 Non-Local Street Pavement Rehabilitation at Three Locations: Haven Avenue from Church Street to Base Line Road Hermosa Avenue from Banyan Street to 300 feet N/O Wilson Avenue Highland Avenue from Archibald Avenue to Haven Avenue

05/2019 06/2019 20 30 40, 41 23

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 78: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rancho Cucamonga San Bernardino Road Maintenance & Rehabilitation

FY18/19 SB1 Local Street Pavement Rehabilitation at Various Locations

The project includes cold planning, localized asphalt repair, crack sealing, asphalt concrete overlay, ADA ramp upgrades, utility adjustments and pavement striping for approximately 2.90 miles of roadway.

FY18/19 SB1 Local Street Pavement Rehabilitation at Various Locations: Alder Street from Lion Street to Candlewood Street Cabrini Court from North End to Delaware Street Calaveras Avenue from Arrow Route to 9th Street Concannon Street from Callaway Place to Barsac Place Creekbridge Street from Northgate Place to Brookside Road Deer Canyon Drive from Broken Arrow Road to Cobblestone Lane Fisher Drive from East Avenue to Mulberry Street Furman Court from West End to Chapman Place Galveston Place from Baltimore Drive to South End Highland Avenue from Sapphire Street to Sard Street Inspiration Drive from Crestview Place to Skyline Road Kalmia Street from North Victoria Windrows Loop to Santolina Place Kinlock Avenue from Church Street to Hemlock Street La Ronda Street from Avenida Leon to Lion Street Lomita Drive from Ramona Avenue to Teak Way Manzanita Drive from Hellman Avenue to Hillside Cove Matterhorn Court from North End to Chelsea Way Mt. Baldwin Court from West End to Hillview Loop Ridge Canyon Road from Valinda Avenue to Morning Star Drive Rockrose Avenue from Highland Avenue to Morning Glory Drive San Bernardino Road from Sauterne Drive to Spinel Avenue Silverberry Street from Carob Street to North Victoria Windrows Loop Spinel Avenue from North End to Estacia Street

05/2019 06/2019 10 20 40, 41 23

Redlands San Bernardino Complete Streets Components PIPP Implementation Install bike boulevards, high-visibility crosswalks, pedestrian bulbouts, and ADA

accessibility features around the Redlands Library and Redlands Bowl. Various locations along Grant Avenue, Cajon Street, and Vine Avenue 06/2018 12/2018 30 30 40 23

Redlands San Bernardino Road Maintenance & Rehabilitation PARIS Paving Program During the first phase of PARIS (5 stage program launched in 2012 and completing in

18/19) the City of Redlands will rehabilitate approximately 2/3 of city streets.

Programmed locations include the following street areas. Actual street segments may be adjusted during construction. No. Street Name From Street To Street 1 6TH ST COLTON AVE SUN AVE 2 6TH ST SUN AVE UNION AVE 3 6TH ST UNION AVE BROCKTON AVE 4 ALABAMA ST INDUSTRIAL PARK AVE ORANGE TREE LN 5 ALABAMA ST ORANGE TREE LN LUGONIA AVE 6 ALESSANDRO RD CREEKSIDE DR SAN TIMOTEO CANYON RD 7 ALLISON WAY LA SOLANA DR Dead End 8 ALVARADO ST OLIVE AVE CLARK ST 9 ALVARADO ST CLARK ST FERN AVE 10 ALVARADO ST FERN AVE HOME PL 11 ALVARADO ST HOME PL CYPRESS AVE 12 ALVARADO ST CYPRESS AVE PALM AVE 13 ALVARADO ST PALM AVE CHESTNUT AVE 14ALVARADO STCHESTNUT AVEWALNUT AVE 15 ALVARADO ST WALNUT AVE HIGHLAND AVE 16 ASH ST FERN AVE Dead End 17 ASH ST CLARK ST FLETCHER AVE 18 BEAUMONT AVE NEVADA ST SAN TIMOTEO CANYON RD 19 BERKELEY DR LUGONIA AVE SHARON RD 20 BERKELEY DR SHARON RD DELAWARE AVE 21 BERKELEY DR DELAWARE AVE NICKOLAS AVE 22 BERKELEY DR NICKOLAS AVE THOMAS AVE 23 BERKELEY DR THOMAS AVE PENNSYLVANIA AVE 24 CABALLERO LN CEDAR AVE CRESCENT AVE 25 CAJON ST HIGHLAND AVE CRESCENT AVE 26 CAJON ST CRESCENT AVE SUMMIT AVE 27 CAJON ST SUMMIT AVE GARDEN ST 28 CAJON ST GARDEN ST HILTON AVE 29 CAJON ST HILTON AVE FOUNTAIN AVE 30 CALVARY CIR ALABAMA ST Dead End 31 CANYON RD GARDEN ST SARRITA DR 32 CEDAR AVE CENTER ST PACIFIC ST 33 CEDAR AVE PACIFIC ST CABALLERO LN 34 CEDAR AVE CABALLERO LN MONTEREY ST 35 CEDAR AVE MONTEREY ST SAN JACINTO ST 36 CEDAR AVE SAN JACINTO ST SAN MATEO ST

04/2019 06/2019 5 20 23 20

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 79: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rialto San Bernardino Road Maintenance & Rehabilitation Annual Street Overlay Project

Pavement rehabilitation of the indicated existing street segments using one or more of the following methods: (1) Cold Milling and Asphalt Concrete (AC) Surface Course; (2) Full Depth AC removal and re-construction; (3) Full Depth Reclamation including in-place pulverization and mixing of the existing pavement to create a stablized base, followed by construction of AC Base and Surface Course; (4) Cold In-Place Recycling of existing pavement, followed by construction of an AC Surface Course. Addition of new and/or repair/upgrade of curbs and gutters, cross gutters, catch basins, and culverts. Addition of new and/or repair/upgrade of ADA curb ramps; and addition of new sidewalks and/or repair/replacement of damaged sidewalks. Replacing/Upgrading traffic striping and pavement markings.

Linden Ave. from Foothill Blvd. to Rialto Ave.; Merrill Ave. from Maple Ave. to Riverside Ave.; Rialto Ave. from Riverside Ave. to Sycamore Ave.; Valley Blvd. from Spruce Ave. to 640' east of Lilac Ave.; and Valley Blvd. from Riverside Ave. to East City Limit.

08/2018 01/2019 7 20 47 20

Rialto San Bernardino Road Maintenance & Rehabilitation Annual Street Overlay Project

Pavement rehabilitation of the indicated existing street segments using one or more of the following methods: (1) Cold Milling and Asphalt Concrete (AC) Surface Course; (2) Full Depth AC removal and re-construction; (3) Full Depth Reclamation including in-place pulverization and mixing of the existing pavement to create a stablized base, followed by construction of AC Base and Surface Course; (4) Cold In-Place Recycling of existing pavement, followed by construction of an AC Surface Course. Addition of new and/or repair/upgrade of curbs and gutters, cross gutters, catch basins, and culverts. Addition of new and/or repair/upgrade of ADA curb ramps; and addition of new sidewalks and/or repair/replacement of damaged sidewalks. Replacing/Upgrading traffic striping and pavement markings.

Lilac Ave. from Tahoe St. to Walnut Ave. Linden Ave. from Riverside Ave. to 155' south of Candlewood Ave. Linden Ave. from 374' south of Persimmon Ave. to Casmalia St. Locust Ave. from Riverside Ave. to Casa Grande Dr. Locust Ave. from Lowell St. to Casmalia St. Pepper Ave. from Baseline Rd. to Etiwanda Ave. Pepper Ave. from Foothill Blvd. to 2nd St. Summit Ave. from Maple Ave. to Apple Ave. Willow Ave. from Walnut Ave. to Chaparral St.

03/2019 09/2019 7 20 47 20

San Bernardino San Bernardino Road Maintenance & Rehabilitation

SS18-002 11 Street Segments1 (KOA)

Construction of asphalt pavement, replacement of Curb and Gutter, Sidewalk, Handicap Ramps, and Stripping.

Sierra Way - 9th Street to Baseline Street; Arrowhead Avenue - 7th Street to 9th Street; "J" Street PAvenuement - 8th Street to 11th Street; Davidson Street - 16th Street to 19th Street; Garner Avenue - Baseline Street to 14th Street; Evans Street - Western Avenue to Medical Center; Wilson Street - 9th Street to Baseline Street; 8th Street - Medical Center Drive to Mt Vernon Avenue; Union Street - Mt Vernon Avenue to Western Avenue; Western Avenue - Union Street to 9th Street; Little Mountain Drive - Kendall Drive to 30th Street

01/2019 03/2019 1 10 47 29

San Bernardino San Bernardino Road Maintenance & Rehabilitation

SS18-003 14 Street Segments1 (Willdan)

Construction of asphalt pavement, replacement of Curb and Gutter, Sidewalk, Handicap Ramps, and Stripping.

Waterman Avenue - Mill Street to Central Avenue; Commercial Road - Waterman Avenue to Steele Road; "H" Street - 48th Street to Northpark Blvd; Pumalo Street - Golden Avenue to Date Place; Hunts Ln - Harwick Drive to Commercial Dr; Arrowhead Avenue - 5th Street to 7th Street; Baseline Street - "H" Street to "E" Street; Central Avenue - Pacific Street to SR210; Pacific Street - City Limits (Olive) to Central Avenue; Central Avenue - SR210 to Highland Avenue.; Grand Avenue - College Avenue to Varsity Avenue; Western Avenue - Kendall Drive to 48th Street; California Street - 30th Street to Cajon Blvd; Inland Center Drive - G Street to Adell Street

01/2019 03/2019 1 10 47 23

San Bernardino San Bernardino Safety Bridge and Railing Repairs at Various Locations (17/18 Carryover)

Bridge and Railing Repairs at Various Locations in the City of San Bernardino. Coating with Methacrylate, Patching spalling concrete, repairing bridge seals, repairing damaged or vandalized bridge railing and related work.

Citywide within San Bernardino. 04/2018 06/2018 5 10 40, 47 20, 23

San Bernardino San Bernardino Road Maintenance & Rehabilitation

Pavement Rejuvenation at Various Locations (Annual Slurry) (17/18 Carryover)

Crack filing and slurry sealing at various locations citywide. Consists of cleaning and sealing cracks, grinding raised areas, and applying a slurry seal that protects the street against moisture intrusion into the subgrade.

Citywide with the City of San Bernardino 04/2018 06/2018 2 5 40, 47 20, 23

San Bernardino San Bernardino Road Maintenance & Rehabilitation

Inland Center Drive Pavement Rehab - "E" St & Adel St (17/18 Carryover)

Pavement Rehabilitation of Inland Center Drive Pavement Rehab - "E" St & Adel St in front of Inland Center mall to repair roadway, broken curb & gutter and sidewalk. also retrofitting or installing ADA access ramps as required by State/federal Guidelines. This project will grind 1-1/2 to 2 inches of existing asphalt ant overlay with new asphalt concrete pavement.

Inland Center Drive Pavement Rehab - "E" St & Adel St 08/2018 11/2018 5 10 47 20

San Bernardino San Bernardino Road Maintenance & Rehabilitation

Little Mtn. Drive Pavement Rehab - Kendall Dr to 30th St (17/18 Carryover)

Pavement Rehabilitation of Little Mtn. Drive Pavement Rehab - Kendall Drive to 30th St to repair roadway, broken curb & gutter and sidewalk. also retrofitting or installing ADA access ramps as required by State/federal Guidelines. This project will grind 1-1/2 to 2 inches of existing asphalt ant overlay with new asphalt concrete pavement.

Little Mtn. Drive Pavement Rehab - Kendall Dr to 30th St 08/2018 11/2018 5 10 40 23

Twentynine Palms San Bernardino Road Maintenance & Rehabilitation Street Overlays 2018/2019

Street (Start to End) Repair Length,Width SUMMIT DR (HILL SIDE AVE to BULLION AVE OL) 242, 27; HILLSIDE AVE (SUMMIT DR to OLD DALE ROAD OL) 1068, 21; BULLION AVE (29 PALMS HWY to OLD DALE ROAD OL) 1222, 22; PINE AVE (29 PALMS HWY to OLD DALE ROAD OL) 1197, 32; OASIS AVE (29 PALMS HWY to OLD DALE ROAD OL) 1206, 28; SPLIT ROCK AVE (29 PALMS HWY to OLD DALE RD OL) 1222, 30; DESERT QUEEN AVE (Cactus Dr to OLD DALE RD OL) 550, 26; TAMARISK AVE (Cactus Dr to OLD DALE ROAD OL) 550, 27; YUCCA AVE (Cactus Dr to OLD DALE ROAD OL) 550, 21; SMOKE TREE AVE (Cactus Dr to OLD DALE ROAD OL) 550, 24; CHOLLA AVE (Cactus Dr to OLD DALE ROAD OL) 550, 31; CACTUS DR (ADOBE ROAD to HILLSIDE Ave OL) 2900, 29; DIDSBURY ROAD (ADOBE ROAD to END OL) 2000, 24

Downtown South in The City of Twentynine Palms 10/2018 03/2019 9 12 42 16

Upland San Bernardino Road Maintenance & Rehabilitation

Arrow Highway Rehabilitation (Originally Listed in FY 2017-18, Forecasted Start in FY 2019-20)

1.13 miles of water main and service laterals replacement, asphalt pavement rehabilitation, replacement of damaged curbs, gutters, sidewalks, handicap ramps, and re-striping.

Arrow Highway, from Benson Avenue to San Antonio Avenue. 01/2019 06/2020 15 20 41 25

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 80: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Upland San Bernardino Road Maintenance & Rehabilitation

Mulberry Avenue Reconstruction (Originally Listed in FY 2017-18, Forecasted Start in FY 2019-20)

0.17 miles of water main and service laterals replacement, asphalt pavement rehabilitation, replacement of damaged curbs, gutters, sidewalks, handicap ramps, and re-striping.

Mulberry Avenue, from Foothill Blvd. to Pine Street. 01/2019 06/2020 20 25 41 25

Upland San Bernardino Road Maintenance & Rehabilitation

14th Street Rehabilitation (Originally Listed in FY 2017-18, Forecasted Start in FY 2020-21)

0.70 miles of asphalt pavement rehabilitation, replacement of damaged curbs, gutters, sidewalks, handicap ramps, and re-striping. 14th Street, from Campus Avenue to Grove Avenue. 01/2020 06/2021 15 20 41 25

Upland San Bernardino Road Maintenance & Rehabilitation

3rd Avenue Rehabilitation (Originally Listed in FY 2017-18, Forecasted Start in FY 2018-19)

0.58 miles of water main and service laterals replacement, asphalt pavement rehabilitation, replacement of damaged curbs, gutters, sidewalks, handicap ramps, and re-striping.

3rd Avenue, from 'A' Street to 11th Street. 08/2018 06/2019 15 20 41 25

Upland San Bernardino Road Maintenance & Rehabilitation

9th Street Rehabilitation (Originally Listed in FY 2017-18, Forecasted Start in FY 2018-19)

0.38 miles of water main and service laterals replacement, asphalt pavement rehabilitation, replacement of damaged curbs, gutters, sidewalks, handicap ramps, and re-striping.

9th Street, from 3rd Avenue to Campus Avenue. 08/2018 06/2019 15 20 41 25

Victorville San Bernardino Road Maintenance & Rehabilitation

Arrowhead Drive / 7th Avenue Improvement Project

Pavement reconstruction, asphalt overlays, widening at certain locations, restriping, and reconstructing access ramps to meet ADA current standards.

Arrowhead/7th Avenue from Green Tree Boulevard to Bear Valley Road, a distance of approximately 2.1 miles. 06/2018 10/2018 20 25 33 21

Victorville San Bernardino Road Maintenance & Rehabilitation Village Drive

Village Drive is a 4-lane arterial road, 4.3 miles long. This project will reconstruct existing pavement, add shoulders, install Class II bike lanes, upgrade access ramps and driveway approaches to meet ADA standards.

Village Drive between Mojave Drive and Air Expressway, a length of 4.3 miles. 02/2018 06/2018 20 25 33 21

Yucaipa San Bernardino Complete Streets Components

County Line Road Improvements (17/18 Carryover)

Rehabilitation of asphalt and curb/gutter. Construction of sidewalk, drainage improvements and associated street improvements. County Line Road from Bryant Street o I-10 Freeway 05/2018 02/2019 25 25 42 23

Yucaipa San Bernardino Complete Streets Components

Yucaipa Boulevard Improvements (17/18 Ongoing)

Rehabilitation of asphalt and curb/gutter. Construction of sidewalk, drainage improvements and associated street improvements. Yucaipa Blvd from 15th Street to I-10 Freeway 10/2017 03/2019 25 25 42 23

Yucaipa San Bernardino Complete Streets Components

Avenue E Intersection Improvements (17/18 Carryover)

Rehabilitation of asphalt and curb/gutter at intersections as part of the construction of roundabouts. Avenue E from Bryant Street to 5th Street 05/2019 05/2020 25 25 42 23

Yucca Valley San Bernardino Road Maintenance & Rehabilitation

Buena Vista Pavement Rehabilitation Project No. 7002 (17/18 Ongoing)

Pavement Rehabilitation Buena Vista Drive: SR-247 and Yucca Messa Road in the Town of Yucca Valley 05/2018 07/2018 10 15 42 16

Carlsbad San Diego Road Maintenance & Rehabilitation Pavement Management Program

The Pavement Management Program (PMP) annually resurfaces approximately 17 centerline miles of roadway with either slurry seal or rubberized asphalt concrete overlay.

The boundaries of the city's PMP are roughly from La Costa Ave to Interstate 78 and from the coast to Vista and San Marcos to the east. Specific streets selected for resurfacing are based on modeling analysis, prioritization, and engineering judgement. Each year, approximately 17 centerline miles of pavement is resurfaced as part of this program.

09/2018 06/2019 5 25 76 36

Carlsbad San Diego Complete Streets Components Concrete Repair Program

This annual maintenance project replaces broken, cracked, and uplifted concrete throughout the city to prevent trip hazards, increase safety, and to promote complete streets and accessibility for all pedestrians.

The boundaries of the city's Concrete Repair Program are roughly from La Costa Ave to Interstate 78 and from the coast to Vista and San Marcos to the east. Specific locations selected for concrete replacement are based on field review by staff, prioritization, budget, and engineering judgement.

09/2018 06/2019 40 60 76 36

Chula Vista San Diego Road Maintenance & Rehabilitation

RMRA Major Pavement Rehabilitation - FY2018/19 (STM396)

Project includes street overlays and street reconstruction on various streets in the City. The major rehabilitation treatments are based on the recommendations of the City's Pavement Management System.

E NAPLES ST (CRESCENT DR - MEDICAL CTR DR); THIRD AV (N FOURTH AV - D ST); NAPLES ST (FOURTH AV - THIRD AV); OXFORD ST (TOBIAS DR - HILLTOP DR); THIRD AV (L ST - NAPLES ST); F ST (FOURTH AV - THIRD AV); THIRD AV (ORANGE AV - ANITA ST); L ST (THIRD AV - FIRST AV); FIRST AV (H ST- I ST); HILLTOP DR (TELEGRAPH CYN RD - E L ST); I ST (SECOND AV - HILLTOP DR); BONITA RD CITY LIMIT (@ WILLOW ST - ALLEN SCHOOL RD)

03/2019 09/2019 20 25 79, 80 40

Chula Vista San Diego Road Maintenance & Rehabilitation

RMRA Major Pavement Rehabilitation – FY2017/18 (STM395)

Project includes street overlays and street reconstruction on various streets in the City. The major rehabilitation treatments are based on the recommendations of the City’s Pavement Management System.

E PALOMAR ST (HILLTOP DR - MELROSE AV); BAY BL (I-5 FREEWAY RAMP - PALOMAR ST); MOSS ST (FOURTH AV - THIRD AV); C ST (N GLOVER AV - SECOND AV) 06/2018 12/2018 20 25 79, 80 40

Coronado San Diego Road Maintenance & Rehabilitation

Street, Curb and Gutter Improvements FY18/19

Removal and replacement of 2-3" of existing asphalt surface; replacement of base material as necessary; replacement of damaged curb and gutter; and required replacement of adjacent pedestrian ramps that do not meet current ADA regulations.

Entire length of Adella Avenue; Jamaica Village Road; Spinnaker Way; and Flora Avenue 04/2019 05/2019 20 30 78 39

Del Mar San Diego Complete Streets Components

Del Mar 6 (DM06) Sidewalk, Streets and Drainage Improvements along Camino Del Mar

Sidewalk, roadway, pedestrian lighting and bike lane improvements, paving, and new striping. North and South bound Camino Del Mar from 9th to 15th Street 09/2018 05/2019 50 75 78 39

El Cajon San Diego Road Maintenance & Rehabilitation Overlay 2018 (17/18 Ongoing) Repave and restripe approximately 4 centerline miles of roads

Various streets in the City of El Cajon to the limits as noted: Airport Dr. - Wing Ave. to Magnolia Ave., Madison Ave - Ballantyne St. to Mollison Ave., El Cajon Blvd. - Murray Dr. to I-8 EB On-ramp, Franklin Ave. - El Cajon Blvd. to Johnson Ave., Granite Hills Dr. - Melody Ln. to Madison Ave., Grossmont Ave. - Chase Ave. to Wilson Ave., Johnson Ave. - Bradley Ave. to Fletcher Pkwy., Johnson Ave. - Washington Ave. to Chase Ave., Magnolia Ave. - Airport Dr. to north City Limit, Midway Dr. - Pine Dr. to Helix View Dr., Murray Dr. - Water St. to El Cajon Blvd., Nidrah St. - Chase Ave. to end, Nugent Ct. - Grossmont College Dr. to end, Avenida Cherylita - Horizon Hills Dr to End, Ballantyne St - Broadway to Hart Dr., Circo Del Cielo - Dewitt Dr to Cul-de-sac, Horizon Hills Dr - Circo Del Cielo to East City Limits,

09/2018 11/2018 13 20 71 38

El Cajon San Diego Road Maintenance & Rehabilitation Overlay 2019

Provides for the reconstruction and/or resurfacing of several collectors and thoroughfares. The work involves grinding asphalt and replacing it with TRMAC, grinding and replacing pavement markers, as well as adjusting manholes and survey monuments. The approximate length of work is 5.85 lane miles.

Granite Hills Dr, Graves Ave, Rex Hall St, Lloyd St, Greenfield Dr, E. Bradley Ave, Benedict Ave, Jackman St, N Marshall Ave, Fesler St, Pine Dr, Helix ViewDr, Brookhurst Dr, Oakbrook Ct, W/E Main St, W. Bradley Ave, N Second St, Cedar St, Ann St, Walter Way, June Way, Ednabelle Ct, Foote Path Way, Midway Dr, Nadeen Dr, Mary St, McWay St, Willowbrook Ct

03/2018 06/2019 12 15 71 38

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 81: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Encinitas San Diego Road Maintenance & Rehabilitation

Annual Overlay Program FY 2018-19 Overlay and Slurry Seal at various locations in the City of Encinitas

Village Park Way from Encinitas Bl to Gatepost Rd; N. Vulcan St from Leucadia Bl to Union St; Highway 101 from Encinitas BL to D Street: Cole Ranch Rd from 7th St to 5th St: N. Rancho Santa FE Rd from Peppertree Ln to 7th St; N. Vulcan St from Orpheus Av to Sunset Dr; N. Vulcan St from Union St to Orpheus Av; N. Rancho Santa FE Rd from Encinitas Bl to Peppertree Ln: Springwood lane from Morning Sun Dr to N. Cul-de-sac: Glascow Av from Birmingham Dr to North End; Wotan Drive from Santa Fe Dr to Melba; Peppertree Ln from Rancho Santa Fe Rd to SE End: Somerset Av from Warwick Av to Brighton Av: Orkney Ln from Faith Av to MacKinnon Av; Via Andalusia from Via Cantebria to Via Montecito; Justin Rd from Munevar Rd to Ocean Crest Rd: Morning Sun Dr from Morning Sun Ct to Springwood Ln: Bumann Road from Fortuna Ranch Rd to Rim Rock Circle; Bumann Road from Rim Rock Circle to Wildflower Drive; Somerset Av from Caretta Wy to Warwick Av; Red Coach Ln from Glen Arbor Dr to W. Cul-de-sac: Barbara Ln from Caudor St to W End: Leafwood Pl from Glen Arbor Dr to W. Cul-de-sac; Puebla St from Passiflora Av to E End; N. Willowspring Dr from Glen Arbor Dr to Village Park Wy; N. Willowspring Dr from Gardendale Rd to Glen Arbor Dr: Leucadia Bl from Quail Gardens Dr to Garden View Rd: Meadow Wood Pl from Orchard Wood Rd to W. Cul-de-sac; Neptune Ave from Grandview St to N END; Leucadia Bl from Saxony Rd to Sidonia St: Countryhaven rd from parkdale Lane to Glen Arbor Dr: Leucadia Bl from Garden View Rd to Town Center Pl; Orchard Wood Rd from Amargosa Dr to Village View Rd; Neptune Ave from Jasper St to Jason St: Ocean Crest Rd from MacKinnon Av to Justin Rd: Neptune Ave from Jason St to Avocado St; Cathy Ln from MacKinnon Av to Justin Rd; Eolus Ave from Hymettus Av to Hillcrest Dr/Andrew Av: Leucadia Bl from Sidonia St to Quail Gardens Dr: Woodside Ln from Morning Sun Dr to S. Cul-de-sac; Eolus Ave from E Glaucus St to Hymettus Av; Orchard Glen Cir from Orchard Wood Rd E to Orchard Wood Rd W; Countryhaven Rd from Village Wood Rd to Parkdale Ln: Eugenie Av from N CDS to Sidonia St: Village View Rd from Orchard Wood Rd to 515' S/O Orchard Wood Rd; Misty Cir from Countrywood Ln to Cul-de-sac; Willowood Ln from Glen Arbor Dr to W. Cul-de-sac: Capri St from Burgundy Road to Gascony Road: Orchard Wood Rd from W CDS to Amargosa Dr; Morning Sun Dr from Springwood Ln to Woodside Ln; Caudor St from Plato Place to Noma Lane: Morning Sun Dr from Woodside Ln to S. Cul-de-sac: Shadytree Ln from Glen Arbor Dr to W. Cul-de-sac; Via Monecito from Via Cantebria to E. Cul-de-sac; Eugenie Av from Sidonia St to Puebla St; Countryhaven Rd from Glen Arobor Dr to Willowspring Dr: Leora Lane from Noma Lane to Cul-de-sac: Neptune Ave from Avocado St to Grandview St; Morning Sun Dr from Rancho Santa Fe Rd to Morning Sun Ct; Green Orchard Pl from Orchard Wood Road to S. Cul-de-sac; Countryhaven Ct from Countryhaven Rd to Cul-de-sac: Rossini Dr from Montgomery Ave to Manchester Av: Cathy Ln from Orkney Ln to MacKinnon Av; Shady Acres Cir from Countrywood Ln to Cul-de-sac; Caudor St from Noma Lane to Barbara Lane: Rossini Dr from Stafford Av to N END: Countrywood Ct from Countrywood Ln to Cul-de-sac; Morning Sun Ct from Morning Sun Dr to W Cul-de-sac; Meadowhaven Ct from W CDS to Village View Rd: Woodmoss Ct from W CDS to Willowspring Dr: Eolus Ave from Naiad St to E Glaucus St: Eolus Ave from Leucadia Bl to Naiad St

08/2018 03/2019 5 25 76 36

Escondido San Diego Road Maintenance & Rehabilitation

2018 Street Rehabilitation & Maintenance Project

This project will remove and replace pavement in poor condition, and apply surface treatments to extend the life of our streets. The project remove/replaces curb and gutter, sidewalk, cross gutters, and loops that are in poor condition. The project restripes affected roadways, some have bike lanes added in compliance with our Bicycle Master Plan, and installs new video detection cameras at affected intersections to improve the efficiency of our traffic signal systems.

Maintenance Zone SO Bear Valley Parkway from Beethoven Drive to Las Palmas Avenue/Peet Lane Centre City Parkway from Felicita Road to S. Centre City Parkway entrance Citracado Parkway from Western City Limits to Centre City Parkway Del Lago Boulevard from I-15 to Via Rancho Parkway El Norte Parkway from Bourbon Road to Seven Oakes Road El Norte Parkway from Rose Street to Lincoln Avenue Escondido Boulevard from Brotherton Road to S. Centre City Parkway entrance Felicita Road from Brotherton Road to 520 s/o Monticello Drive Hamilton Lane from Bernardo Avenue to Felicita Road Pine Street from Valley Parkway to 15th Avenue Quince Street from Second Avenue to Thirteenth Avenue Rose Street from Lincoln Avenue to El Norte Parkway Via Rancho Parkway from Montesano Road to Beethoven Drive

07/2018 11/2018 5 20 75 38

Imperial Beach San Diego Road Maintenance & Rehabilitation RTIP FY 18-19 Street Improvements

Slurry Seal and Grind/Overlay over 20 streets city-wide that need attention based of the City's Pavement Management System. ADA compliant pedestrian ramps will also be proposed, if necessary, on all of the streets that get rehabilitated.

Boulevard Ave, Cypress Ave, Calla Ave, Donax Ave, Daisy Ave, Elkwood Ave, Ebony Ave, Imperial Beach Blvd, 8th St, Grove Ave, Holly Ave, Arriba Ave, Hemlock Ave, Iris Ave, California St, 7th St, 10th St, Emory St, 11th St, Florida St, 15th St, Citrus Ave

09/2018 01/2019 5 25 78 40

La Mesa San Diego Road Maintenance & Rehabilitation La Mesa Blvd Rehab Project 2A Asphalt Mill & Overlay La Mesa Blvd from Normal Ave to Acacia Ave 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation La Mesa Blvd Rehab Project 2B Asphalt Mill & Overlay La Mesa Blvd - From Randlett Dr. to Grossmont Blvd 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation La Mesa Blvd Rehab Project 2C Asphalt Mill & Overlay La Mesa Blvd - From Grossmont Blvd to I-8 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation Spring Street Rehab Project 2 Asphalt Mill & Overlay Spring St - From the Southern City Limit to I-8 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation University Ave Rehab Proj 2A West Asphalt Mill & Overlay University Ave - Western City Limit to Harbinson Ave 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation University Ave Rehab Proj 2B East Asphalt Mill & Overlay University Ave - From La Mesa Blvd to Baltimore Dr 01/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation 70th Street Rehab Project 1 Asphalt Mill and Overlay 70th Street from University Avenue to City Limits at Interstate 8 02/2019 06/2019 15 25 79 38

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 82: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

La Mesa San Diego Road Maintenance & Rehabilitation La Mesa Blvd. Rehab Project 1 Asphalt Mill and Overlay La Mesa Blvd from Lee Ave to University Ave and from Allison Ave to Randlett Dr 02/2019 06/2019 15 25 79 38

La Mesa San Diego Road Maintenance & Rehabilitation Palm Ave. Rehab Project 1 Asphalt Mill and Overlay Palm Ave from 4400 Palm Ave to Echo Drive 02/2019 06/2019 15 25 79 38

Lemon Grove San Diego Road Maintenance & Rehabilitation

FY 2018-19 Street Rehabilitation Projects Rehabilitate and Maintain City Streets and Roadways

The street list for FY 18/19 Street Rehab Project ($194,959) tentatively include: Adams Street, Alton Drive, Angelus Avenue, Baldwin Road, Bonita Street, Broadway, Buena Vista Avenue, Cameron Drive, Central Avenue, Citronella Street, College Avenue, Cuyamaca Avenue, Davison Street, Daytona Street, Dupont Drive, El Roy Street, Ensenada Street, Eppick Court, Fairfax Drive, Federal Blvd, Florine Road, La Puerta Place, Lansing Drive, Lawford Place, Lemon Grove Avenue, Lemon Grove Way, Lincoln Street, Loma Drive, Massachusetts Avenue, Morose Street, Mt. Vernon Street, North Avenue, Olive Street, Pacific Street, Palm Street, Roosevelt Avenue, Siegle Court, Washington StreetThe limits of the FY 18-19 streets are not confirmed at this time and will be further vetted after July 2018.

07/2018 12/2018 5 10 79 38

Lemon Grove San Diego Other Storm Drain Master Plan This project will create the City's first storm drain assessment, inventory, and prioritization for repairs.

The City maintains 70 Miles of roadway for roughly 450 plus streets within the City limits, this includes 47.5 miles of drainage to be assessed 07/2018 10/2018 5 10 79 38

Lemon Grove San Diego Road Maintenance & Rehabilitation

FY 2017-18 Street Rehabilitation Project (17/18 Ongoing)

Rehabilitate or maintenance city streets as a part of the City's annual paving rehabilitation project.

Anticipated streets included in the FY 17/18 Street Rehab Project ($150,000)which should be completed in June 2018 are: Dayton Drive (Englewood Drive to Nichals Street), Barton Drive (Ensenada Street to Englewood Drive), Palm Street (Skyline Drive to Golden Avenue), Lemon Grove Avenue (Palm Street to Southern City Limits), Buena Vista Avenue (San Miguel Avenue to Broadway)

04/2018 06/2018 5 10 79 38

National City San Diego Safety

FY 2018 Safe Routes to School (SRTS) Pedestrian and Bicycle Enhancements – Harbison Avenue Traffic Calming, Division Street to E. 4th Street (FY 2018 Carryover Project)

Construct traffic calming measures and bike sharrows on Harbison Avenue between Division Street and E. 4th Street Harbison Avenue between Division Street and E. 4th Street 09/2018 12/2018 20 30 79, 80 40

National City San Diego Safety

FY 2018 SRTS Pedestrian and Bicycle Enhancements – Division Street Traffic Calming, Euclid Avenue to Harbison Avenue (FY 2018 Carryover Project)

Provide street resurfacing and restriping to include a "road diet" for traffic calming converting four travel lanes to two travel lanes with a two-way left-turn center lane, Class II bike lanes, and new pedestrian curb ramps for ADA compliance on Division Street between Euclid Avenue and Harbison Avenue

Division Street between Euclid Avenue and Harbison Avenue 02/2018 06/2018 10 15 79, 80 40

National City San Diego Road Maintenance & Rehabilitation Euclid Avenue Street Resurfacing Provide pavement rehabilitation, grind and overlay on Euclid Avenue between

Cervantes Avenue and E. 24th Street Euclid Avenue between Cervantes Avenue and E. 24th Street 11/2018 06/2019 10 15 79, 80 40

National City San Diego Road Maintenance & Rehabilitation Palm Avenue Street Resurfacing Provide pavement rehabilitation, grind and overlay on Palm Avenue between Division

Street and E. 18th Street Palm Avenue between Division Street and E. 18th Street 11/2018 06/2019 10 15 79, 80 40

Oceanside San Diego Road Maintenance & Rehabilitation Slurry Sealing 18/19

Project 1- Slurry Sealing - Will assess and plan based on a potential of 212 streets Segments

Project 1- Slurry Sealing List 1 ADAMS STREET MADISON STREET HARRISON STREET 2 ARBOR COVE CIRCLE MYRTLE STREET SWEETSHADE STREET 3 ARISTA WAY WEST END SHARI WAY 4 ARISTA WAY SHARI WAY EAST END 193 VIA LAS ROSAS VIA SONORA GENEVA STREET 194 VIA LAS VILLAS SHADOW RIDGE ROAD VIA SEVILLE 195 VIA LAS VILLAS VIA SEVILLE SHADOW RIDGE ROAD 196 VIA PAUMA LUISENO AVENUE VIA YUHA 197 VIA RIO SE END VIA MARIA 198 VIA RIO VIA EMILY VIA MARIA 199 VIA RIO WEST END VIA EMILY 200 VILLAGE COURT VILLAGE DRIVE NW END 201 VOYAGER COURT SE END MAINSAIL ROAD 202 WALTON STREET KRAFT STREET LORETTA STREET 203 WEITZEL STREET CIVIC CENTER DRIVE SPORTFISHER DRIVE 204 WINDWARD WAY NORTH CLEVELAND STREET TREMONT STREET 205 WINDWARD WAY TREMONT STREET NORTH COAST HIGHWAY 206 WISCONSIN AVENUE SOUTH DITMAR STREET SOUTH NEVADA STREET 207 WISCONSIN AVENUE SOUTH CLEMENTINE STREET GRANT STREET 208 WISCONSIN AVENUE SOUTH FREEMAN STREET SOUTH DITMAR STREET 209 WISCONSIN AVENUE SOUTH DITMAR STREET SOUTH DITMAR STREET 210 WISCONSIN AVENUE SOUTH COAST HIGHWAY SOUTH FREEMAN STREET 211 WISCONSIN AVENUE SOUTH NEVADA STREET SOUTH CLEMENTINE ST 212 WOODBINE PLACE SOUTH END CASSIDY STREET

08/2018 06/2019 5 7 76 36

Oceanside San Diego Road Maintenance & Rehabilitation Asphalt Overlay

Preparatory work including patching, crack sealing. Asphalt overlaying to repair mainly arterial streets as they often carry truck traffic. Replace striping and pavement markings.

various streets (list attached) 08/2018 06/2019 15 20 76 36

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 83: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Oceanside San Diego Road Maintenance & Rehabilitation Slurry Sealing 17/18 Carryover Slurry Sealing of various streets throughout the City. (Streets named in project location

and attached list. Streets may be added and removed as project progresses).

GISID STREET FROM TO PCI CONDITION COND. WIDTH LENGTH AREA TYPE OF WORK A B RANK 319 AIRPORT ROAD SAN LUIS REY ROAD PRODUCTION AVENUE 77 Good Weak 37 462 17,109 Thin Overlay (1.5 - 2.0) 14.00 26,600 Local 499 AIRPORT ROAD PRODUCTION AVENUE ROYMAR ROAD 67 Good Moderate 46 612 28,173 Thin Overlay (1.5 - 2.0) 14.00 43,800 Local 501 AIRPORT ROAD ROYMAR ROAD HIGHWAY 76 EXPRESSWAY 47 Good Moderate 48 207 9,960 Thin Overlay (1.5 -2.0) 14.00 15,500 Local

917 ARTHUR AVENUE GOLD DRIVE LENORE STREET 64 Very Good Weak 37 699 25,879 Surface Treatment 4.00 11,500 Local 936 ARTHUR AVENUE LENORE STREET EAST PARKER STREET 56 Fair Weak 37 587 21,705 Mod Overlay (2.0 - 3.0) 16.00 38,600 Local 956 ARTHUR AVENUE EAST PARKER STREET CHARLES AVENUE 50 Good Moderate 38 756 28,717 Thin Overlay (1.5 - 2.0) 14.00 44,700 Local 970 ARTHUR AVENUE CHARLES AVENUE FLORA DRIVE 49 Fair Moderate 35 262 9,181 Mod Overlay (2.0 - 3.0) 16.00 16,300 Local 1412 ASH STREET SOUTH MYERS STREET NE END 51 Good Moderate 27 105 2,835 Thin Overlay (1.5 - 2.0) 14.00 4,400 Local 1801 AUTUMN DRIVE SUNBURST DRIVE MAPLE DRIVE 83 Very Good Weak 38 404 15,369 Surface Treatment 4.00 6,800 Local 1837 AUTUMN DRIVE MAPLE DRIVE NORTH AVENUE 40 Marginal Moderate 37 181 6,697 Thick Olay (> 2.0 - 3.0) 19.50 14,500 Local 6121 AUTUMN DRIVE SPRINGTIME DRIVE SUNBURST DRIVE 75 Good Weak 37 733 27,123 Thin Overlay (1.5 - 2.0) 14.00 42,200 Local 1742 AVENIDA ANDANTE SW END AVENIDA OCEANO 34 Marginal Moderate 38 374 14,209 Thick Olay (> 2.0 - 3.0) 19.50 30,800 Local 1748 AVENIDA ANDANTE AVENIDA OCEANO CORTE VERANO 62 Good Moderate 36 805 28,971 Thin Overlay (1.5 -2.0) 14.00 45,100 Local

1947 AVENIDA ANDANTE CORTE VERANO CORTE ANDANTE 61 Good Moderate 30 372 11,172 Thin Overlay (1.5 - 2.0) 14.00 17,400 Local 1973 AVENIDA ANDANTE CORTE ANDANTE AVENIDA OCEANO 59 Good Weak 34 520 17,688 Thin Overlay (1.5 - 2.0) 14.00 27,500 Local 3873 AVENIDA DE LA PLATA AVENIDA DEL ORO AVENIDA PLAZA REAL 74 Good Moderate 45 955 42,962 Thin Overlay (1.5 -

07/2018 06/2019 5 7 76 36

Poway San Diego Road Maintenance & Rehabilitation

FY 18/19 Street Maintenance Project

The FY 18/19 Street Maintenance Project will provide deep patching, skin patching, slurry sealing, utility lid raise to grade, and restriping for all of the streets in City of Poway street maintenance zone 1. This project includes 86 streets totaling approximately 20 centerline miles and approximately 5 million square feet of road surface. The project will greatly extend the life of these streets, and will include restriping with complete street striping features including continental crosswalk striping and the addition of bike lane buffers.

This project includes all of the streets in street maintenance zone 1, which includes 86 streets and approximately 20 center line miles. Zone 1 includes Espola Road from the west city limits to Sandhill Road, and includes all public streets north and east of Espola Road within these limits. The project also includes streets on the south and east sides of Espola Road in the Summerfield Estates and Bridlewood Neighborhoods.

07/2018 09/2018 15 20 77 38

San Diego San Diego Road Maintenance & Rehabilitation

Slurry Seal Group 1804 ‐ Option Renewal (1804B)

This project involves the application of a slurry seal on approximately 60 miles of roads throughout the city. Slurry seal is generally used on streets which are in good condition to protect them from deterioration. The application of a slurry seal, which consists of sand, emulsion and water applied in a thin layer up to 3/8 of an inch thick on a street surface, can protect and preserve the street pavement for approximately 3‐7 years.

Balboa Park, City Heights, Eastern Area, Greater North Park, Kearny Mesa, Linda Vista, Mira Mesa, Navajo, Otay Mesa, Otay Mesa‐Nestor, Pacific Beach, Peninsula, Rancho Encantada, San Ysidro, Skyline‐ Paradise Hills, Tierrasanta, Tijuana River Valley, University

10/2018 03/2019 3 7 77, 78, 79 38, 39, 40

San Diego San Diego Road Maintenance & Rehabilitation

Slurry Seal Group 1803 ‐ Option Renewal (1803B)

This project involves the application of a slurry seal on approximately 60 miles of roads throughout the city. Slurry seal is generally used on streets which are in good condition to protect them from deterioration. The application of a slurry seal, which consists of sand, emulsion and water applied in a thin layer up to 3/8 of an inch thick on a street surface, can protect and preserve the street pavement for approximately 3‐7 years.

Carmel Valley, City Heights, Clairemont Mesa, College Area, Kearny Mesa, Kensington‐Talmadge, Linda Vista, Midway‐ Pacific Highway, Mira Mesa, Mission Valley, Navajo, Otay Mesa, Otay Mesa‐Nestor, Peninsula, Rancho Bernardo, Rancho Encantada, Scripps Miramar Ranch, Skyline‐ Paradise Hills, Southeastern San Diego, Torrey Hills, Uptown

08/2018 12/2018 3 7 77, 78, 79 38, 39, 40

San Diego San Diego Road Maintenance & Rehabilitation Slurry Seal Group 1901

This project involves the application of a slurry seal on approximately 60 miles of roads throughout the city. Slurry seal is generally used on streets which are in good condition to protect them from deterioration. The application of a slurry seal, which consists of sand, emulsion and water applied in a thin layer up to 3/8 of an inch thick on a street surface, can protect and preserve the street pavement for approximately 3‐7 years.

Carmel Valley, Clairemont Mesa, La Jolla, Mira Mesa, Pacific Beach, Peninsula, Rancho Bernardo, University 08/2018 12/2018 3 7 77, 78, 79 38, 39, 40

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 84: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

San Diego San Diego Road Maintenance & Rehabilitation Slurry Seal Group 1902

This project involves the application of a slurry seal on approximately 60 miles of roads throughout the city. Slurry seal is generally used on streets which are in good condition to protect them from deterioration. The application of a slurry seal, which consists of sand, emulsion and water applied in a thin layer up to 3/8 of an inch thick on a street surface, can protect and preserve the street pavement for approximately 3‐7 years.

City Heights, College Area, Greater North Park, Kensington‐Talmadge, Linda Vista, Mission Valley, Navajo, Normal Heights, Otay Mesa, Otay Mesa‐Nestor, San Ysidro, Skyline‐Paradise Hills, Southeastern San Diego, Tierrasanta, Uptown

08/2018 12/2018 3 7 77, 78, 79 38, 39, 40

San Diego San Diego Road Maintenance & Rehabilitation AC Overlay 1901

This project involves repairing approximately 30 miles of roads throughout the city. The project includes removing 2"‐3" of deteriorated asphalt and replacing it with a fresh new asphalt surface. ADA improvements are made to curb ramps, sidewalks, and driveways. Damaged cross gutters, alley aprons, and curb & gutters are also replaced.

Carmel Valley, Clairemont Mesa, Mira Mesa, Rancho Bernardo, Rancho Penasquitos, Torrey Pines, University 09/2018 07/2019 20 20 77, 78, 79 38, 39, 40

San Marcos San Diego Road Maintenance & Rehabilitation

West San Marcos Boulevard Slope Reconstruction Project

Reconstruction of the embankment supporting the eastbound lanes of West San Marcos Boulevard from Acacia Drive to Viewpoint Drive. The existing embankment is moving to the south endangering the eastbound lanes, sidewalk, street lights, and fire hydrants.

In the City of San Marcos, on West San Marcos Boulevard, from Acacia Drive to Viewpoint Drive 11/2018 05/2019 25 50 75 38

San Marcos San Diego Road Maintenance & Rehabilitation Annual Surface Seal

Use of a Pavement Preservation Strategy in the placement of a Surface Seal of Roadways. This is a carryover of a FY 17/18 approved project that will be complete in FY18/19.

Mission Road, Twin Oaks Valley Road 02/2018 08/2018 5 8 75 38

Santee San Diego Other Illuminated Street Signs Lightung Replacement

To replace burnt out and/or obsolete bulbs for the internally illuminated street name signs by energy efficient LED bulbs which provides much longer service life with energy savings.

All signalized intersections in the city (60) 05/2018 08/2018 15 20 71 38

Santee San Diego Road Maintenance & Rehabilitation

Pavement Repair and Rehabilitation Citywide

Repair and rehabilitate streets as recommended by the City's Pavement Management Analysis Report. The project will focus on overlays and full reconstructions.

Includes streets identified in the City's Pavement Management Analysis Report within zones BF, BB, AA, CG, EE, BD, EB, CD, CD, FC, CI, CE, ED, AND EF. 04/2018 12/2018 20 25 71 38

Santee San Diego Road Maintenance & Rehabilitation

Pavement Roadway Maintenece Citywide

Conduct pavement maintenance on streets as recommended by the City's Pavement Management Analysis Report. The project will focus on crack-filling, and slurry sealing.

Includes streets identified on in the City's Pavement Management Analysis Report within zones BF, BB, AA, CG, EE, BD, EB, CB, CD, FC, CI, CE, ED, ED, and EF. 04/2018 12/2018 10 15 71 38

Santee San Diego Road Maintenance & Rehabilitation Bridge Restorations Citywide Provide maintenance and repair to City owned bridges. Including bridge deck seals,

deck sealing, and minor patching.Magnolia Avenue bridge, Cuyamaca Street bridge, Carlton Hills Boulevard bridge, Mast Boulevard bridge, and Prospect Avenue bridge. 06/2018 12/2019 25 30 71 38

Solana Beach San Diego Road Maintenance & Rehabilitation

2018/19 Annual Pavement Maintenance Project

The City's SB1 funds will be added to the annual pavement repair project so more streets could be repaired. As part of this project, it is estimated that 2" overlays will be placed on 425,000 square feet of roads and slurry seals will be placed on approximately 220,000 square feet of roads. A copy of the tentative street list is attached.

Since Solana Beach is only four square miles in size, each year, work typically covers all quadrants and most neighborhoods. The quadrants are determined by two main roads that bisect the City. These roads are Interstate 5 running north/south and Lomas Santa Fe Drive running east/west. Some of the main streets that are included in this project include Cliff Street from North Cedros Avenue to Rios Avenue; South Sierra Avenue from Border Street to Dahlia Drive; Seabright Lane – entire street; South Cedros Avenue from Marsolan Avenue to Cofair Avenue; South Granados Avenue from Palmitas Avenue to the southern end; and Santa Rosita from Santa Helena to Santa Florencia. In summary, this project will include four streets in the Northwest quadrant of the City, seven streets in the southwest quadrant, eight streets in the northeast project and two streets in the southeast quadrant.

05/2018 12/2018 15 25 78 39

Vista San Diego Road Maintenance & Rehabilitation

Street Rehabilitation, Construction, and Overlay-Biennial

Resurfacing and rehabilitation of deteriorated street pavement areas, including asphalt overlay of greater than one-inch in thickness, where identified as priorities in the Pavement Management System 5-Year Maintenance Plan. Work includes resurfacing 0.5 miles of Arterial roadways, 5.6 miles of Local streets; replacement of 35 curb ramps; repair of 2,500 square feet of sidewalks; and re-striping 1 mile of bike lanes.

E Bobier Dr from Anza Ave to Lynette Circle, W Vista Way from Cedar Rd to Grapevine Rd, W Vista Way from Santa Clara to WB SR-78 ramp @ Melrose, Bonita Dr at Bluegrass Rd, Camino Corto from Vista Village Dr to Camino Patricia, Caren Rd from Galaxy Dr to end, Cedar Rd from West Dr to W Vista Way, Valencia Dr from W Vista Way to end, Valencia Dr from Copper Dr to end, Yacon Cir from Yacon St to end, Yacon St from Hackamre Rd to Yacon Cir, Yacon St from Amador Ave to Tylee St

03/2019 10/2019 10 20 76 36

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 85: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Vista San Diego Road Maintenance & Rehabilitation

Citywide Storm Drain Relining / Replacement

Repair or replace storm-drain culverts throughout the city that have reached the end of their useful life, have failed as identified in the storm-drain inventory, or where needed prior to overlay or other pavement rehabilitation work.

Cypress Dr from Alta Vista Ter to Monte Vista Dr N/S Cypress Dr from Alta Vista Dr S/S to Alta Vista Ter Eucalyptus Av from Beaumont Dr to Alta Vista Dr Eucalyptus Av from Marlin Dr to Beaumont Dr Eucalyptus Av from Vista Glen Ln to Marlin Dr Bonair Rd from Palomar Pl N/S to 300' N/Palomar Pl Camino Loma Verde from Grandview Rd to City Limits Bonair Rd from Palomar Pl S/S to Foothill Dr Grandview Rd from Camino Loma Verde to End Meadow Lake Dr from Vista Way E E/S to Glenmere Rd E/S Cypress Dr from Loni Ln to Santa Fe Av S N/S Cypress Dr from Monte Vista Dr S/S to Loni Ln Meadow Lake Dr from Glenmere Rd E/S to End Vista Grande Dr from Elevado Rd to City Limits Vista Grande Dr from Warmlands Av to Elevado Dr W Vista Way from Cedar Rd to Grapevine Rd W Vista Way from Santa Clara to WB SR-78 ramp @ Melrose Durian St from Hill Dr to end Highland Dr from Olive Ave to Cielita Linda Dr Mistletoe St from Tylee St to 400' N/O Tylee St Palm Bark St from Tylee St to Cinchona St Rose Dr from Highland Dr to City Limits Tylee St from Durian St to Ann's Way Valencia Dr from W Vista Way to end Yacon St from Hackamre Rd to Yacon Cir

03/2018 10/2019 40 50 76 36

Vista San Diego Road Maintenance & Rehabilitation

Street Maintenance and Slurry Seal - Biennial

Repair and maintenance sealing of street surfaces using slurry seal, cape seal, chip seal, and asphalt concrete overlay less than one inch in thickness, where identified as priorities in the Pavement Management System 5-Year Maintenance Plan. Work includes 1.5 miles of slurry seal on Arterial roadways; 1.25 miles of Cape seal on Local streets; 5.4 miles of slurry seal on Local streets; and re-striping 2 miles of bike lanes.

Cypress Dr from Alta Vista Ter to Monte Vista Dr N/S Cypress Dr from Alta Vista Dr S/S to Alta Vista Ter Eucalyptus Av from Beaumont Dr to Alta Vista Dr Eucalyptus Av from Marlin Dr to Beaumont Dr Eucalyptus Av from Vista Glen Ln to Marlin Dr Ocean View Dr from Civic Center Dr to Terrace Dr Traci Ln from Eucalyptus Av to End Beverly Dr from Elm Dr to Foothill Dr Tacoma Ln from Beverly Dr to End Old Foothill Dr from San Clemente Dr (W) N/S to 160' NW Lion's Gate/End Via Christina from (SPUR) 510' S/Loop end to End Valley Dr from Monte Vista Dr to City Limits Peach Grove Ln from Hillway Dr to End Service Pl from Santa Fe Av S to End Bonair Rd from Palomar Pl N/S to 300' N/Palomar Pl Mesa Verde Dr from Alta Mesa Dr to End Capri Dr from Bel Air Dr E N/S to End Glenmere Rd from Oak Dr to Meadow Lake Dr N/S Shelsteve Ter from Alestar St to End Park Av from Ocean View Dr (S) to Eucalyptus Av (S) Alta Calle from Alta Vista Dr to 200' S/Alta Vista Dr Normark Ter from Alestar St to End Amber Ln from Eucalyptus Av to 220' S/Eucalyptus Av Sunrise Dr from Rudd Rd to City Limits Fireside Ln from Valley Dr W/S to End Independence Way from Monte Mar Rd to Elm Dr Bel Air Dr E from 130' N/Deerhaven Dr to 510' E/Capri Dr Orleavo Dr from Crescent Dr N/S to End Camino Loma V1erde from Grandview Rd to City Limits Palomar Pl from Vista Way E to Oak Dr Sierra Verde Dr from Civic Center Dr to Gate Bonair Rd from Palomar Pl S/S to Foothill Dr Peach Grove Ln from Beaumont Dr to Hillway Dr Rancho Pacifica Pl from Alta Vista Dr to End Crescent Ct from Crescent Ln W/S to End Donnan Pl from Glenmere Rd E/S to End Mesa Verde Dr from Beverly Dr to Alta Mesa Dr San Clemente Av from Calle Huerto to Luziero Dr Bel Air Dr W from Alta Vista Dr to End Crescent Ln from Crescent Dr S/S to End

05/2018 12/2018 4 6 76 36

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 86: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

San Francisco San Francisco Road Maintenance & Rehabilitation

(17/18 Carryover) PW Various Locations Pavement Renovation No. 29

The work scope for this project includes; - Construction of 38 ADA compliant curb ramps - Grind and Pave of 28 Street Segments - Grind and Pave of 13 Intersections - 2 new curb inlets with horizontal protection bar

Pavement Renovation on;Alpha St from Arleta Ave to Leland Ave, Bowdoin St from Mansell St to End, Brussels St from Mansell St to Ordway St, Calgary St from Sawyer St/Velasco Ave to End, Dartmouth St from Mansell St to End, Delta St from Campbell Ave to Leland Ave, Hahn St from Sunnydale Ave to Blythdale Ave, Harkness Ave from San Bruno Ave to Girard St, Jamestown Ave from Ignacio Ave to Griffith St, Ordway St from Goettingen St to Alder St/Ankeny St, Parque Dr from Esquina Dr to Geneva Ave, Pueblo St from Velasco Ave to End, Racine Lane from Beeman Lane/Wabash Terrace to San Bruno Ave, Raymond Ave from Bayshore Blvd to Alpha St, Redondo St from Ingerson Ave to Jamestown Ave, Sawyer St from Sunnydale Ave to Sunrise Way, Sunrise Way from End to End, Tubbs St from Tennessee St to Indiana St, Wilde Ave from San Bruno to Girard St

09/2017 01/2019 14 21 17 11

San Francisco San Francisco Road Maintenance & Rehabilitation

PW Various Locations Pavement Renovation No. 37

The work scope for this project includes: - Construction of 90 ADA compliant curb ramps - Grind and pave 35 Blocks - Grind and pave 22 Intersections

15th St : Potrero Ave to Hampshire St, 18th St : Missouri St to De Haro St, 20th St : 3rd St to Vermont St, Alameda St : Henry Adams St to Vermont St, Berry St : 7th St to De Haro St, Connecticut St : 16th St to 20th St, De Haro St : 16th St to 17th St, Guy Pl : 1st St to Lansing St, Henry Adams St : Alameda St to 15th St and Kansas St, Kansas St : 17th St to End, Vermont St : Division St to 20th St

04/2018 04/2020 14 21 17 11

San Francisco San Francisco Road Maintenance & Rehabilitation

Various Locations Pavement Renovation No. 35 and Sewer Replacement

The work scope for this project includes: - Construction of 77 ADA compliant curb ramps - Reconstruct 2 blocks of concrete pavement - Grind and pave 40 blocks - Grind and pave 25 instersections - Localized base repair

18th St : Vermont St to San Bruno Ave, Anza St : Park Presidio Blvd to 30th Ave, Central Ave : Waller St to Turk Blvd, Charter Oak Ave : Industrial St to End, Crestmont Dr : Christopher Dr and Glenhaven Ln to End, Gladeview Way : Olympia Way to Panorama Dr, Glenbrook Ave : Mountain Spring Ave to Palo Alto Ave, Knollview Way : Olympia Way to Panorama Dr, Roosevelt Way : 14th St and Alpine Ter to Loma Vista Ter, Skyview Way : Cityview Way to Marview Way, Sunnydale Ave : Hahn St to End

06/2018 06/2020 14 21 17, 19 11

San Francisco San Francisco Road Maintenance & Rehabilitation

Various Locations Pavement Renovation No 36 and Sewer Replacement

The work scope for this project includes: - Construction of 38 ADA compliant curb ramps - Grind and pave 26 Blocks - Grind and pave 9 Intersections

10th Ave : Judah St to Moraga St, 11th Ave : Judah St to Noriega St, 12th Ave : Judah St to 09th Ave and Rivera St, 15th Ave : Judah St to Kirkham St, Mendosa Ave : 09th Ave to End, Moraga St : 09th Ave to 11th Ave, Noriega St : 12th Ave to 16th Ave, Quesada Ave : Keith St to Newhall St

08/2018 05/2020 14 21 17, 19 11

San Francisco San Francisco Road Maintenance & Rehabilitation

Various Locations Pavement Renovation No 38 and Sewer Replacement

The work scope for this project includes: - Grind and pave 46 blocks - Construction of 104 ADA complaint curb ramps - Construction of 1 transit bulb-out

Dicha Aly : Lupine Ave to Wood St, Divisadero St : Broadway to Marina Blvd, Jackson St : Presidio Ave to Cherry St, Laurel St : Pacific Ave to Lupine Ave, Maple St : Sacramento St to California St, Sacramento St : Walnut St to Arguello Blvd, Spruce St : Pacific Ave to Mayfair Dr , Steiner St : Pine St to California St

09/2018 07/2020 14 21 17, 19 11

San Francisco San Francisco Road Maintenance & Rehabilitation

Various Locations Pavement Renovation No 40

The work scope for this project includes: - Construction of 62 ADA compliant ramps - Grind and pave 34 blocks - Grind and pave 20 intersections

Congo St : Circular Ave to Monterey Blvd, Cresta Vista Dr : Baxter Aly and Casitas Ave to Coventry Ct, Detroit St : Staples Ave to Stillings Ave and Vista Verde Ct, Hazelwood Ave : Brentwood Ave to Casitas Ave and Yerba Buena Ave, Judson Ave : Edna St to Phelan Ave, Lansdale Ave : Juanita Way to Dalewood Way, Myra Way, and Sherwood Ct, Los Palmos Dr : Teresita Blvd to Globe Aly and Hazelwood Ave, Malta Dr : Valletta Ct to Oshaughnessy Blvd, San Pablo Ave : Granville Way and Portola Dr to Yerba Buena Ave

01/2019 10/2020 14 21 17, 19 11

San Francisco San Francisco Road Maintenance & Rehabilitation

Various Locations Pavement Renovation No 41

The work scope for this project includes: - Grind and pave approximately 46 blocks - Construct 49 ADA compliant curb ramps - Grind and pave 18 Intersections

Bell Ct : End to Whitney Young Cir, Carpenter Ct : End to Hawkins Ln and Whitney Young Cir, Cashmere St : End to La Salle Ave, Commer Ct : End to Garlington Ct, Dukes Ct : Cashmere St to End, Galvez Ave : Newhall St to Phelps St, Garlington Ct : La Salle Ave to End, George Ct : Ingalls St to End, Hawkins Ln : End to Carpenter Ct and Whitney Young Cir, Hillview Ct : End to Lindsay Cir and Whitney Young Cir, Innes Ave : End to Newhall St, Jamestown Ave : Ingalls St to Jennings St, La Salle Ave : Ingalls St to Newhall St, Mabrey Ct : End to Richards Cir and Whitney Young Cir, Middle Point Rd : Evans Ave and Jennings St to Ingalls St and Innes Ave, Osceola Ln : La Salle Ave to La Salle Ave, Progress St : Whitney Young Cir to End, Reuel Ct : Hudson Ave to End, Whitfield Ct : La Salle Ave to End, Whitney Young Cir : Carpenter Ct and Hawkins Ln to Newcomb Ave, Youngs Ct : End to Whitney Young Cir

02/2019 01/2021 14 21 17 11

San Francisco San Francisco Road Maintenance & Rehabilitation

(17/18 Carryover) PW Palou Ave Infrastructure Improvements

The work scope for this project includes; - Grind and Pave 13 Street Segments - Construct 38 curb ramps - Construct 1,700 square feet of bus pad - Reconstruct approximately 20,000 square feet of base repair

Pavement Renovation on; On Newhall St from Oakdale ave to Palou Ave On Palou Ave from Crisp Road to Barneveld Ave

10/2017 06/2020 14 21 17 11

San Francisco San Francisco Road Maintenance & Rehabilitation

(17/18 Carryover) PW Various Locations Pavement Renovation No 39

The work scope for this project includes; -Construction of 148 ADA compliant curb ramps -Grind and pave 51 Street Segments -Grind and pave 32 Intersections -9 Curb Inlets -Construction of 6 Bus Pads

Pavement Renovation on; On Avila St from Chesnut St to Casa Way/Marina Blvd On Buchanan St from Clay St to North Point St On Capra Way from Mallorca Way to Scott St On Fern St from Van Ness Ave to Gough St On Laguna St from California ST to Bay St On Pine St from Van Ness Ave to Masonic Ave/Presidio Ave On Sacramento St from Van Ness Ave to Buchanan St

09/2016 04/2020 14 21 17 11

Escalon San Joaquin Road Maintenance & Rehabilitation Escalon Avenue Rehabilitated with new pavement overlay and thermoplastic striping, and reconstruction

of broken sidewalks. Escalon Avenue from State Route 120 to the northerly City Limits. 05/2018 06/2018 10 12 12 5

Lathrop San Joaquin Road Maintenance & Rehabilitation

City-wide Road Maintenance - FY 18/19 RHMA Allocation Rehabilitate existing pavement using Cold in-place recycling (CIR). Harlan Road between Louise Avenue and 1,000 feet south 06/2018 10/2018 10 15 9 12

Lathrop San Joaquin Road Maintenance & Rehabilitation

City-wide Road Maintenance - (17/18 Carryover)

Remove approx. 40,000 square feet of existing asphalt, install pavement fabric and install new top lift of asphalt. Intersection of Harlan Road / Warren Avenue 06/2018 10/2018 5 10 9 12

Lodi San Joaquin Road Maintenance & Rehabilitation

2018/2019 Pavement Resurfacing Project Rehabilitate streets with rubberized cape seal and slurry seal product.

Various Streets inside Park West and Sunwest Subdivision in City of Lodi: Applewood Dr, Bayberry Dr, Black Oak Way, Candlewood Dr, Elderica Wy, Glen Oak Dr, Live Oak, Way, Park Oak Dr, Park West Dr, Ponderosa Dr, Sweetwood Dr, White Oak Wy, Kramer Dr, Tilden Dr, Westwind Dr and Wightman Dr

11/2018 04/2019 5 10 9 5

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 87: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Lodi San Joaquin Road Maintenance & Rehabilitation

2017/2018 Oavement Resurfacing Project

Rehabilitate existing streets with rubberized cape seal/slurry seal with local digout (pavement repair); Project carryover from 2017

Church Street (Lodi to Kettleman); Hutchins Street (Kettleman to Harney); Vine Street (Beckman to Cluff); Cluff Avenue (Vine to Industrial); Industrial Way (Beckman to Cluff) 07/2018 09/2018 5 10 9 5

Manteca San Joaquin Road Maintenance & Rehabilitation

Yosemite Avenue: Main Street to Cottage Avenue Improvement Project (17/18 Carryover)

This project will rehabilitate, replace, or restore approximately 35,000 square yards of pavement that is aging, or beginning to fail. This project also includes the installing 10,000 linear feet of bicycle lanes.

The Project is located on Yosemite Avenue, between Main Street and Cottage Drive. 07/2018 03/2019 15 25 12 5

Manteca San Joaquin Road Maintenance & Rehabilitation

Main Street: Yosemite Avenue to Atherton Drive Improvement Project (17/18 Carryover)

This project will rehabilitate, replace, or restore approximately 42,000 square yards of pavement that is aging, or beginning to fail. This project also includes the installing 12,000 linear feet of bicycle lanes.

The Project is located on Main Street, between Yosemite Avenue to Atherton Drive. 07/2018 03/2019 15 25 12 5

Manteca San Joaquin Road Maintenance & Rehabilitation

2019 Annual Pavement Maintenance Project

The project will rehabilitate, replace, and/or restore pavement that is aging or beginning to fall. The project will include a combination of pavement maintenance methods including asphalt overlays, slurry seals, dig outs, base repair, crack seal, cape seal and/or microsurfacing at various locations throughout the region in accordance with the recommendations of the City Pavement Management Program (PMP). Project construction is scheduled for FY 2018-20. The useful life of the pavement rehabilitation is approximately 10-20 years.

Manteca Woodbridge Senior Community 1451 Americana St, Manteca, CA 95336 12/2018 05/2019 10 20 12 5

Manteca San Joaquin Road Maintenance & Rehabilitation

Mayor's Park Subdivision Pavement Project

This project will entail pavement repair including asphalt overlays, base repairs, crack seal, cape seal, microsurfacing, and other pavement repairs at the Mayor’s Park Subdivision. The project is consistent with the recommendation of the City Pavement Maintenance Program (PMP). Project construction is scheduled for FY 2018-20. The useful life of the pavement rehabilitation is approximately 10-12 years.

Mayor's Park Subdivision located at 1440 Kelley Drive, Manteca, CA 95336 12/2018 05/2019 10 20 12 5

Manteca San Joaquin Road Maintenance & Rehabilitation

Springtime Estates Improvemen Project (17/18 Carryover)

Pavement maintenance of 65,000 square yards of road surface. This could include asphalt overlays, slurry seals, dig outs, base repair, and other pavement repairs in accordance with the recommendations of the City Pavement Management Program.

This project area is East of Main Street, North of Louise Avenue, and South and West of State Highway 99. 09/2018 12/2018 15 25 12 5

Ripon San Joaquin Road Maintenance & Rehabilitation

Mulholand/California Resurface Project

Includes a micro-slurry and an asphalt rubber cape seal with isolated dig out and repair sections and striping Mulholand Drive, California Avenue and surrounding roads 02/2019 05/2019 10 15 12 5

Ripon San Joaquin Road Maintenance & Rehabilitation Orange/Palm Resurface Project Includes an asphalt rubber cape seal with isolated dig out and repair sections and

striping Orange Avenue, Palm Avenue and surrounding roads 07/2020 10/2020 10 15 12 5

Ripon San Joaquin Road Maintenance & Rehabilitation Denise/Baily Resurface Project Includes an asphalt rubber cape seal with isolated dig out and repair sections and

striping Denise Drive, Baily Drive and surrounding areas 02/2021 05/2021 10 15 12 5

Ripon San Joaquin Road Maintenance & Rehabilitation

River Road Overlay Project (17/18 Carryover)

Includes a grind and overlay on major arterial River Road for approximately 5,200 feet, isolated dig out and repair sections and striping. River Road between Jack Tone Road and North Ripon Road 07/2018 10/2018 15 25 12 5

Stockton San Joaquin Road Maintenance & Rehabilitation Local Street Resurfacing Includes multiple projects to provide approximately 45-centerline miles of slurry seal

resurfacing treatment.

Various Locations through 45- centerline miles, below is a sample of the 231 locations tht may be selected from: 1.) Alan Goldfien Ct - Kate Linde Ci To Cul-De-Sac 2.) Alee Ln - Gelley Wy To Squall Wy 100 Ft North 3.) Anastasia Ln - Mccook Wy To Cul-De-Sac 4.) Arthur Ct - Hydrangea Dr To Cul-De-Sac 5.) Asbury Wy - Wishon Dr To Cortina Ln 6.) Bartlett Ct - Cottrell Ln To Cul-De-Sac 7.) Belvedere Av - Oak St To Flora St 228.) Wishon Dr - Britton Av To Asbury Wy 229.) Wood Ridge Ct - Green Ridge Dr To Cul-De-Sac 230.) Yutan Ln - Togninali Ln To Estrella Av 231.) Zitlau Ct - Klemeyer Ci To Cul-De-Sac

06/2019 07/2019 5 7 13 5

Stockton San Joaquin Safety Curb, Gutter, and Sidewalk Replacement

Includes the removal and replacement of City tree-damaged curb, gutter, and sidewalk at approximately 398 locations.

Various Locations: Assess Approximately 398 below is a sample for reference. 1.) 1500 SYCAMORE ST 2.) 1600 SYCAMORE ST 3.) 6022 FILLMORE AVE 4.) 2770 EL DORADO ST 5.) 1551 MAIN ST 6.) 1415 SPRING ST 7.) 1231 N PERSHING AVE33.) 36 W POPLAR ST 34.) 1350 W ROBINHOOD DR 2290 E MARKET ST 194.) 117 E E ST 393.) 229 N AIRPORT WY 394.) W ROBINHOOD DR & N PERSHING AV 395.) 2816 CHAUNCY CI 396.) 6523 N EL DORADO ST 397.) 2011 S SACRAMENTO ST 398.) 2493 E PARK ST

08/2019 09/2019 40 50 13 5

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 88: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Stockton San Joaquin Road Maintenance & Rehabilitation

2018 Slurry Seal Project (17/18 Carryover)

This project includes resurfacing approximately 11 centerline miles of various local (residential) streets in Stockton. The project includes slurry sealing, fog sealing, and removal and replacement of pavement striping and markings.

Various Locations Citywide: 1.) Aft Court – Urchin Street to End of Cul-de-sac; 2.) Anchor Place – Jonathen Street to End of Cul-de-sac; 3.) Bard Drive – Fresno Avenue to Washo Way; 4.) Bard Drive – Fresno Avenue to Longdon Drive; 5.) Barge Court – Kay Bridges Place to End of Cul-de-sac; 6.) Barnacle Court – Urchin Street to End of Cul-de-sac; 7.) Beech Avenue – Jasmine Avenue to Sumac Avenue; 8.) Birch Avenue – Rosewood Drive to Westland Avenue; 9.) Blossom Circle – Horsetail Drive to End of Cul-de-sac; 10.) Broadway Avenue – Eleanor Avenue to Main Street; 11.) Brookstone Avenue – Woodbury Lane to Cypress Hill Lane; 12.) Burney Falls Drive – Oxwell Drive to Longdon Drive; 13.) Buttonwillow Avenue – Westland Avenue to Rosewood Drive; 14.) Cedarwood Court – Timberwood Lane to End of Cul-de-sac; 15.) Crown Peak Lane – EWS Woods Boulevard to Brookstone Avenue; 16.) Cypress Hill Lane – Woodhollow Avenue to Brookstone Avenue; 17.) David Avenue – Main Street to End of Cul-de-sac; 18.) Dune Place – Jonathen Street to End of Cul-de-sac; 19.) Edgebrook Avenue – Wateford Avenue to Windsail Lane; 20.) Fomosana Lane – Trident Street to End of Cul-de-sac; 21.) Formosan Lane – Horsetail Drive to Trident Street; 22.) Half Dome Court – Trident Street to End of Cul-de-sac; 23.) Horsetail Drive – Holman Road to Blossom Circle; 24.) Horsetail Drive – Formosana Lane to Holman Road; 25.) Jonathen Street – Stern Place to Anchor Place; 26.) Juniper Avenue – Peppertree Drive to Hammer Lane S. Frontage Road; 27.) Kay Bridges Place – Carolyn Weston Boulevard to Stern Place; 28.) Kyburz Court – Pajaro Way to End of Cul-de-sac; 29.) Longdon Drive – Burney Falls Drive to Platte Road; 30.) Manzanita Avenue – Westland Drive to Beech Avenue; 31.) Marciano Place – Dayton Herzog Lane to End; 32.) Netherton Avenue – Eleanor Avenue to Main Street; 33.) Ninth Street – Scribner Street to Airport Way; 34.) Old Spanish Drive – Oxwell Drive to Rouen Court; 35.) Ophir Street – Eighth Street to End of Cul-de-sac; 36.) Oxwell Drive – Platte Road to Rouen Court; 37.) Peat Way – Blossom Circle to Etcheverry Drive; 38.) Peppertree Drive – Meadow Avenue to Hammer Lane; 39.) Platte Road – Oxwell Drive to Longdon Drive;

06/2018 08/2018 5 7 13 5

Stockton San Joaquin Safety Street Lights Re-Wiring Project (17/18 Ongoing)

This project will replace stolen wire for approximately 100 non-functional street lights at various locations and includes securing pull boxes to prevent future vandalism.

Various Locations:Industrial Drive – Pock Lane to SR 99 Frontage Road; SR 99 Frontage Road – Approx. 800 LF North of Transworld Drive; SR 99 Frontage Road – Approx. 1,100 LF South of Transworld Drive; SR 99 Frontage Road – Approx. 1,000 LF North of Togninali Lane; SR 99 Frontage Road – Approx. 800 LF South of Togninali Lane; Zephyr Street – Approx. 700 LF West of Perlman Drive; Zephyr Street – Approx. 1,100 LF East of Perlman Drive; Perlman Drive – Approx. 2,300 LF North of Zephyr Street; Producers Drive – Industrial Drive to Zephyr Street; Industrial Drive – 1,500 LF West of Gibraltar Court; Industrial Drive – 600 LF East of Gibraltar Court; Gibraltar Court – Entire Court; Zephyr Street – Airport Way to B Street; Arch Road – SR 99 Frontage Road to Logistics Drive;Giannecchini Lane – Arch-Airport Road to Boeing Way; Quantas Lane – Transworld Drive to Boeing Way; Transworld Drive – Quantas Lane to SR 99 Frontage Road.

03/2018 07/2018 40 50 13 5

Stockton San Joaquin Safety Lighted Crosswalk Upgrades (17/18 Carryover)

This project will install Rectangular Rapid Flashing Beacons, upgrade existing crosswalks/signs, and install frontage improvements at two uncontrolled crossing to increase pedestrian and bicycle safety at two locations.

Two Mid-block Locations on Center Street: 1.) Between Main Street and Weber Avenue (Parker's Alley); and 2.) Between Weber Avenue and Miner Avenue (Channel Street).

03/2019 09/2019 15 20 13 5

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 89: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Stockton San Joaquin Traffic Control Devices Neighborhood Traffic Management Program (17/18 Carryover)

This project will install traffic calming measures such as speed humps, speed cushions, traffic circles, etc. in 8 neighborhoods. The project will develop and construct traffic calming plans that offer viable solutions to each neighborhood's specific traffic safety concerns.

Various: #1520 Acacia St - Stockton Street to Baker Street #1521 Lincoln - Vine St to Rose St #1522 Rose St - Stockton Street to Baker Street #1523 Rose St - Edison St to Harrison St #1524 Vine St - Baker St to Edison St #1525 Stockton St - Willow St to Vine St #1526 Stockton St - Rose St to Magnolia St #1527 Magnolia St - Baker St to Edison St #1528 Baker St - Rose St to Magnolia St #1529 Swain Rd - Percival Way to Ector Way #1530 Swain Rd - Ector Way to Village Green Dr #1531 Village Green Dr - Swain Rd to Winslow Way #1532 Village Green Dr - Swain Rd to Homewood Ct/Dr #1533 Village Green Dr - Tristan Cir to Homewood Ct/Dr #1534 Village Green Dr - Tristan Cir to Tristan Cir #1535 Winslow Wy - Lorraine Way to Village Green Dr #1536 Winslow Wy - Lorraine Way to Village Green Dr #1537 Ector Wy - Swain Rd to Homewood Ct/Dr #1538 Ector Wy - Swain Rd to Homewood Ct/Dr #1539 Percival Wy - Percival Ct to Homewood Ct/Dr #1540 Homewood Dr - Percival Way to Village Green Dr #1541 Tristan Ci - Village Green Dr to Village Green Dr #1542 Tristan Ci - Village Green Dr to Village Green Dr #1543 River Oaks Drive - River Park Cir to River View Cir #1544 River Oaks Drive - Whistler Way to AG Spanos Blvd #1545 River Bluff Lane - Whistler Way to Creek Trail Cir #1546 Eagle Rock Circle - Whistler Way to Whistler Way #1547 Eagle Rock Circle - Whistler Way to Whistler Way #1548 Creek Trail Court - River Bluff Lane to River Bluff Lane #1549 River Park Cir - River Oaks Dr to River Oaks Dr #1550 Laurel St - Sonora St to Marsh St #1551 Laurel St - Marsh St to Church St #1552 Marsh St - Laurel St to Ash St #1553 Sonora St - Laurel St to B St #1554 Sonora St - Laurel St to Ash St #1555 Ash St - Sonora St to Marsh St #1556 Ash St - Marsh St to Church St #1557 Ash St - Church St to Hazelton Av #1558 Church St - Laurel St to Ash St

07/2018 11/2019 15 20 13 5

Tracy San Joaquin Road Maintenance & Rehabilitation

Street Patch & Overlay Project FY 2018-19

Due to modest damage to the existing pavement structure, micro-surfaces and overlays will be applied. A total of 248,464 square feet of micro-surface and 1,165,391 square feet of overlay will be applied.

11th Street From Tracy Blvd to Central (Overlay); 12th Street From Holly Dr. to Adams St. (Overlay); Arbor Rd From MacArthur to Holly Dr. (Overlay); Bessie Ave. From Carlton Ave. to Grant Line Rd. (Overlay); Beverly From Lincoln Blvd to Schleiger Dr. (Overlay); Eaton From Holly Dr. to East St. (Micro-surface); Eaton From Richard Dr. to Tracy Blvd (Micro-surface); Eaton From Tracy Blvd to Holly Dr. (Micro-surface); El Portal From 11th St. to 100' N of Highland (Overlay); Grant Line Rd From Lincoln to N. Tracy Blvd (Overlay); Highland Ave. From Bessie Ave. to El Portal (Overlay); Highland Ave. From Holly Dr. to El Portal (Overlay); Hollywood From Holly Dr. to East St. (Overlay); Lincoln Blvd From Lowell Ave. to 195' S of Beverly (Overlay); Lincoln Blvd From 195' S of Beverly to 11th St. (Overlay); Lowell Ave. From Corral Hollow to Regency (Overlay); Paradise Bridge From City Limits to Pescadero (Overlay); Rehn Rd. From McDermott Dr. to Pavement Change (Overlay); Schulte Rd From Tracy Blvd to 530' W/O Central Ave. (Overlay); Schulte Rd From 530' W/O Central Ave. to Central (Overlay); W. Beverly From Bessie Ave. to Parker Ave. (Overlay); W. Beverly From W. Lowell Ave. to Wall St. (Overlay); Walnut From 11th St. to Highland Ave. (Overlay); Whittier Ave. From Holly Dr. to East St. (Micro-surface)

11/2018 01/2020 7 15 13 5

Tracy San Joaquin Complete Streets Components Lammers Road Sidewalk

To create a link between Kimball High School and the Redbridge neighborhood and provide a safe walking route to school for students, 4,100 linear feet of sidewalk will be installed.

On the East side of Lammers Road From Schulte Road to Kimball High School 11/2018 01/2020 10 15 13 5

Tracy San Joaquin Road Maintenance & Rehabilitation

MacArthur Drive Overlay (17/18 Carryover Project)

Due to modest damage to the existing pavement structure, a 284,000 square foot overlay will be applied. MacArthur Drive From Grant Line Road to I-205 06/2018 11/2018 10 15 13 5

Arroyo Grande San Luis Obispo Road Maintenance & Rehabilitation James Way Repairs Pavement repairs consisting of digouts on James Way prior to overlay James Way from Oak Park Boulevard to Tally Ho Road 08/2018 06/2019 10 10 35 17

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 90: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Atascadero San Luis Obispo Road Maintenance & Rehabilitation

El Camino Real Rehabilitation -North 17/18 Carryover Project

Major pavement rehabilitation for approximately 0.78 miles of arterial roadway to improve deteriorated pavement conditions and better define roadway configuration for all roadway users, including motorists, bicyclists, and pedestrians. This roadway section is heavily used and the City receives numerous complaints regarding its condition and inquiries of when it will be replaced. Project will include constructing approximately 250 feet of a “missing link” section of sidewalk on the west side to provide better pedestrian connectivity along the corridor.

El Camino Real from San Anselmo Road (East) to San Benito Road 06/2018 12/2018 15 25 35 17

El Paso de Robles San Luis Obispo Safety 13TH STREET PEDESTRIAN IMPROVEMENTS

INSTALL AND ENHANCED PEDESTRIAN CROSSINGS AT 2 LOCATIONS BY PROVIDING PED BUTTON ACTIVATED FLASHING SIGNS, ENHANCED PAINTED CROSSWALKS AND ADDITIONAL STREET LIGHTS. ALSO INCLUDES ROAD MAINTENANCE AND REHABILITATION

13TH STREET PINE TO PARK 06/2018 08/2018 10 20 33 15

El Paso de Robles San Luis Obispo Road Maintenance & Rehabilitation

DIG-OUT REPAIRS AT PASO ROBLES STREET DIG-OUT REPAIRS AT LOCALIZED LOCATIONS WHERE PAVEMENT HAS FAILED PASO ROBLES STREET NORTHBOUND OFF RAMP AT HWY 101 TO 13TH STREET. 06/2018 08/2018 10 12 33 15

El Paso de Robles San Luis Obispo Road Maintenance & Rehabilitation

DIG-OUT REPAIRS AT NIBLICK ROAD AT NICKLAUS DIG-OUT REPAIRS WHERE PAVING HAS FAILED AT NIBLICK ROAD BY NICKLAUS NIBLICK ROAD AT NICKLAUS 07/2018 09/2018 10 15 33 15

El Paso de Robles San Luis Obispo Road Maintenance & Rehabilitation

SHERWOOD ROAD REPAIRS--FONTANA TO CRESTON

REPAIR DETERIORATED ROAD SURFACE, REMOVE AND REPLACE CURB RAMPS TO MEET CURRENT ADA STANDARDS, INSTALL STREETLIGHTS, INSTALL NEW TRAFFIC SIGNAL, INSTALL LANDSCAPING AND IRRIGATION, UPGRADE AND UPSIZE OLD SEWER MAINS.

SHERWOOD ROAD--FONTANA TO CRESTON ROAD 04/2018 05/2018 10 15 33 15

Grover Beach San Luis Obispo Road Maintenance & Rehabilitation

CIP 2283 Major Street Maintenance Program 17/18 Carryover

The City Council of the City of Grover Beach has, through a public process, identified street rehabilitation as a top priority. The Council adopted a Capital Improvement Program in accordance with these identified priorities that includes the selected project. The selected project will include elements to improve bicycle and pedestrian safety, and improved pavement conditions will reduce travel times which leads to reduced vehicle emissions helping the State achieve its air quality and greenhouse gas emissions reductions goals.

S. Oak Park Blvd, El Camino Real, 4th Street, Farroll, Grand Ave and The Pike 08/2018 05/2019 15 20 35 17

Grover Beach San Luis Obispo Road Maintenance & Rehabilitation

CIP 2283 Major Street Maintenance Program

Rehabilitate local major streets to improve driver and pedestrian safety and meet the City's Circulation Plan. Oak Park Blvd, West Grand Avenue, N 4th Street, El Camino Real, Farroll Rd, The Pike 08/2018 09/2023 15 20 35 17

Morro Bay San Luis Obispo Road Maintenance & Rehabilitation

Streets Pavement Preservation-FY18_19

Pavement maintenance of portions of streets and avenues listed in the "Project Location" section using funding from SB1 and Local sources. Maintenance techniques include Triple Layer Cape Seal, Cape Seal, Chip Seal and Type II Microsurfacing. Striping , Signage and required perimeter improvements are also included. Estimated $191,000 provided through SB1 with $357,619.40 from local option sales tax and CalRecycle grant.

Segments of the following streets and avenues: Barlow, Beachcomber, Coral, Juniper, Little Morro Ck Rd, Main, Morro, Morro Bay Alley, Panay, Preston, Tahiti, Tide, Vashon, Verdon and West

09/2018 04/2019 6 10 35 17

Pismo Beach San Luis Obispo Complete Streets Components Shell Beach Streetscape

Streetscape project resurfacing an existing road, providing separate bike/pedestrian lane, bulbouts, landscaping, street furniture, LID features, LED lights, bulbouts, improved pedestrian safety, increased crosswalks

Shell Beach Road, Pismo Beach, CA 93449 12/2017 09/2019 20 50 35 17

San Luis Obispo San Luis Obispo Complete Streets Components Concrete Paver Sidewalk

The existing sidewalk is wood and has protruding screws and warped, rotted, and splintered boards. The project will replace the wood sidewalk with a concrete paver sidewalk that will eliminate the trip and fall hazards, provide a context appropriate sidewalk, reduce long-term maintenance costs and provide access to community members of all abilities.

Santa Barbara Street from Broad Street to Leff Street. 05/2018 12/2018 50 75 35 17

San Luis Obispo San Luis Obispo Complete Streets Components

Broad Street Bike Boulevard (17/18 Carryover)

The Broad Street Bike Boulevard connects Pacheco Elementary School to the neighborhood south of Foothill Boulevard by constructing a Class I bike path between Foothill and Ramona and installing a bicycle and pedestrian crossing at Foothill and Ferrini. This project is the first phase of a larger effort to provide a safe, low-stress route for bicyclists and pedestrians connecting the downtown core to the school, neighborhoods and shopping north of Foothill Boulevard. The estimated cost of this Phase I work is $900,000. The project is anticipated to start construction in early 2019.

Broad Street between Foothill Boulevard and Ramona Street. 05/2018 10/2019 20 50 35 17

San Luis Obispo San Luis Obispo Complete Streets Components El Capitan Bridge

The El Capitan Bridge connects El Capitan Way neighborhood to the Fuller Road / Poinsettia Street / French Park neighborhood via a trail. Several years ago, a large tree fell on the El Capitan Bridge catastrophically damaging the bridge. This project will replace the existing bridge with a new bridge. The estimated cost of this work is $100,000. The project is anticipated to start construction in fall 2018.

El Capitan Way 05/2018 06/2019 100 100 35 17

Atherton San Mateo Road Maintenance & Rehabilitation 2019 Street Overlay Project

The work to be completed includes removal and replacement of approximately 2 inches of asphalt concrete pavement on various streets. Once milling has been completed, the contractor and the Town's project engineer shall identify any pavement failures for repairs. Repave the entire street with a self-propelled paver & finish per Town Standard Specifications.

Patricia Drive – Between Serrano Drive and Austin Avenue Serrano Drive – (1) Between Selby Lane and Robleda Drive (2) Between Robleda Drive and Stockbridge Avenue Heather Drive - Between Linden Avenue and James Avenue

06/2019 12/2019 7 10 24 13

Atherton San Mateo Road Maintenance & Rehabilitation Street Overlay (17/18 Carryover) Grind 2" and overlay

Patricia Drive - Between Serrano Drive and Austin Avenue Serrano Drive Section 1 - Between Selby Lane and Robleda Drive Serrano Drive Section 2 - Between Robleda Drive and Stockbridge Avenue

06/2019 12/2019 15 20 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 91: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Atherton San Mateo Road Maintenance & Rehabilitation Street Slurry Seal (17/18 Ongoing) Slurry Seal and Restripe Existing Roadways

Alta Visa Drive - Between Ridgeview Drive and Fletcher Drive Arthur Lane - Between Selby Lane to end of cul-de-sac Austin Avenue - Between Selby Lane and Stockbridge Avenue Barry Lane - Between E/O 34 Barry Lane to South End Bergessen Court - Between Stockbridge Avenue to end of cul-de-sac Betty Lane - Between Polhemus Avenue to end of cul -de-sac Camino Por Los Arboles - Between Camino al Lago and Camino de Los Robles Catalpa Drive - Between Irving Avenue and James Avenue Clay Drive - Between Atherton Avenue to end of cul-de-sac Elizabeth Way - Between Shearer Drive to end of cul-de-sac Greenoaks Drive - Between Oak Grove Avenue to Rosewood Drive Heritage Court - Between Middlefield Road to end of cul-de-sac Irving Avenue - Between Heather Drive to end of cul-de-sac Jennings Lane Section 1 - Between Middlefield Road to end of cul -de-sac Jennings Lane Section 2 - Between Jennings Lane to end of cul-de-sac Mandarin Way - Between Alameda de Las Pulgas to end of cul -de-sac McCormick Lane - Between cut-de-sac and Watkins Avenue Middle Gate - Between Almendral Avenue and Park Drive Mosswood Avenue - Between Greenoaks Drive to end of cul-de-sac North Gate - Between Almendral Avenue and Park Drive Parker Avenue- Between Stockbridge Avenue to end of cul-de-sac Prado Secoya - Between Elena Avenue and end of cul-de-sac Polhemus Avenue Between Polhemus Avenue and end of cul-de-sac Ridgeview Drive - Between Alta Vista Drive and end of cul-de-sac Selby Lane - Between E/O 241 Selby Lane to North End of cul-sac Snowden Avenue - Between Wilburn Avenue and Belleau Avenue South Gate - Between Almendral Avenue and Park Drive Stockbridge Avenue -Between Stockbridge Avenue to end of cul-de-sac Surrey Lane - Between Middlefield Road to end of cul dle-sac

05/2018 10/2018 3 5 24 13

Atherton San Mateo Road Maintenance & Rehabilitation Street Slurry Seal (17/18 Carryover Slurry Seal and Restripe Existing Roadways Belbrook Way - Between Walsh Road to end of cul-de-sac

Mesa Court - Between Ridgeview Drive to end of cul-de-sac 06/2019 12/2019 3 5 24 13

Belmont San Mateo Road Maintenance & Rehabilitation 2019 Mill & Overlay

The project will provide for the preparation of contract documents and the construction costs for the mill and overlay of the following streets for FY 18/19: Belle Monte Ave. from Notre Dame Ave. to Alameda de las Pulgas, Ponce Ave. from Prindle Road to Cipriani Blvd., San Ardo Way from Monte Cresta Dr. to Barclay Way, Coronet Blvd., from Prindle Rd. to Ralston Ave., and Lincoln Ave. from Newlands Ave. to Cipriani Blvd.

Various streets in Belmont, CA including the following: Belle Monte Ave. from Notre Dame Ave. to Alameda de las Pulgas, Ponce Ave. from Prindle Road to Cipriani Blvd., San Ardo Way from Monte Cresta Dr. to Barclay Way, Coronet Blvd., from Prindle Rd. to Ralston Ave., and Lincoln Ave. from Newlands Ave. to Cipriani Blvd.

05/2019 09/2019 10 15 22 13

Belmont San Mateo Road Maintenance & Rehabilitation

RMRA Street Project (17/18 Ongoing)

The project will provide for the preparation of contract documents and the construction costs for the slurry seal of the following streets:North Road from Hillman Avenue to Notre Dame Avenue, Ralston Ranch Road from Christian Drive to Ralston Avenue, Mountain View Avenue from Hiller Street to Old County Road, Coronet Boulevard from Casa Bona Avenue to Lyon Avenue, Hasting Drive from Carlmont Avenue to San Carlos City Limits, Kedith Avenue from Ralston Avenue to O'Neill Avenue

North Road from Hillman Avenue to Notre Dame Avenue Ralston Ranch Road from Christian Drive to Ralston Avenue Mountain View Avenue from Hiller Street to Old County Road Coronet Boulevard from Casa Bona Avenue to Lyon Avenue Hasting Drive from Carlmont Avenue to San Carlos City Limits Kedith Avenue from Ralston Avenue to O'Neill Avenue

05/2018 09/2018 3 7 22 13

Brisbane San Mateo Road Maintenance & Rehabilitation Crack Seal of Various City Streets A citywide crack seal of various city streets.

Bayshore Boulevard from 650’ south of Old County Road to Geneva Avenue, Cypress Lane from Valley Drive to end, Main Street from Bayshore Boulevard to city limit, San Benito Road from Sierra Point to Glen Parkway, Silverspot from Golden Aster to Lily Court, Glen Parkway from Humboldt to Lake Street, Humboldt Road from Placer Way to Kings Road., Monterey Street from Solano to Visitacion Avenue, Solano Street from Monterey to Mendocino, Visitacion Avenue from Alvarado to Klamath, Guadalupe Canyon Parkway (north side) from city limits to Bayshore Boulevard and Valley Drive from Bayshore Boulevard to West Hill Drive.

05/2019 09/2019 2 2 22 13

Burlingame San Mateo Road Maintenance & Rehabilitation

2018 and 2019 Street Resurfacing Project

The work consists of street base failure repair and resurfacing on various streets within the city limit. Construction activities will include asphalt concrete “dig-out” repairs, surface milling, asphalt concrete overlay, traffic markings, new concrete and other related work.

The project streets include Albemarle Way, Alvarado Avenue, Benito Avenue, Castillo Avenue, Channing Road, Clarendon Road, Columbus Avenue, Corbitt Drive, Davis Drive, De Soto Avenue, Hillside Circle, Maple Avenue, Montero Avenue, Murchinson Drive, Park Avenue, Sequoia Avenue and Winchester Place.

07/2019 12/2019 24 30 22 13

Burlingame San Mateo Road Maintenance & Rehabilitation

2018 Street Resurfacing Project 17/18 Ongoing

The project consists of street base failure repair and resurfacing on various streets within the City limits. Several different types of activities will be used including asphalt concrete "dig-out" repairs, asphalt concrete overlay, street reconstruction, surface milling, traffic markings, traffic control, concrete base repair and related works.

City of Burlingame on California Drive, Trousdale, Cadalliac Way and Broadway 12/2018 12/2019 10 24 22 13

Colma San Mateo Complete Streets Components

Mission Road Bike/Pedestrian Improvements

Implementation of bicycle and pedestrian safety related improvements. The project scope includes: relocation and reconstruction of the existing curb, gutter, sidewalk, driveway approaches and non-ADA compliant ramps; addition of new continuous sidewalk; extension of Class II bicycle lanes with green pavement markings; construction of stormwater curb extension with bioretention/infiltration basins for stormwater treatment and high visibility crosswalks with rectangular rapid flashing beacons; installation of speed feedback signs and energy efficient street lights.

Mission Road, between El Camino Real and Lawndale Boulevard, Colma. 10/2018 10/2020 10 20 19 11

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 92: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Daly City San Mateo Road Maintenance & Rehabilitation

2018-19 Crocker/Hillside Street Slurry Seal

Application of latex-modified asphalt slurry seal on selected streets citywide per the 7-year Street Slurry Seal Master Plan.

Abbot Ave., Acton St., Alexander Ave., Alp Ave., Atlanta St., Bellevue Ave., Beta Ave., Bismarck St., Blossom Ct., Bonnie St., Brunswick Ct., Brunswick St., Castle St., Chelsea Ct., Clayton Ct., Cobblestone Ct., Como Ave., Cottonwood Dr., County St., Craig Ct., Crocker Ave., Deanne Ln., E. Cavour St., East Market St., East Moltke St., East Vista Ave., Eastlake Ave., Edgemar St., Edgewood Ct., Evergreen Ave., First Ave., Fisher St., Florence St., Ford St., Frankfort St., Gambetta St., Garibaldi St., Garwood Dr., Guadalupe Pkwy, Guttenberg St., Hanover St., Hillside Blvd., Irvington St., Lausanne Ave., Lisbon St., Linden St., Lowell St., Mar Vista Dr., Marshall Way, Muirwood Dr., Oliver St., Orange Ct., Parma St., Partridge Ln., Paul St., Peoria St., Peter St., Price St., Risel Ave., Roosevelt Ave., Royce Way, Second Ave., Sylvan St., Tallwood Dr., Templeton Ave., Templeton Ave., Teresa St., Thiers St., Third Ave., Valley St., Villa St., Wellington Ave., Whittier St., Winchester St., Wyandotte Ave.

01/2019 07/2019 5 8 19 11

Daly City San Mateo Road Maintenance & Rehabilitation

St. Francis Heights Street Slurry Seal

Application of latex-modified asphalt slurry seal on selected streets citywide per the 7-year Street Slurry Seal Master Plan.

Alta Loma Ave., Belhaven Ave., Belhaven Ct., Buena Vista Ave., Campana Ave., Carleton Ave., Castillejo Dr., Cerro Ct., Cerro Dr., Clarinada Ave., Del Prado Dr., Eastmoor Ave., Edgemont Dr., El Dorado Dr., Escuela Dr.,Glenbrook Ave., Grandview Ave., Higate Dr., Huntington Dr. , Lakeshire Dr., Larkspur Ave., Lincoln Ave., Mariposa Ave., Mayfield Ave., Midvale Dr., Monterey Dr., Northaven Dr., Olcese Ct., Pamela Ct., Portola Ave., Ridgefield Ave.,Rockridge Ave., San Fernando Way, San Miguel Ave., Santa Elena Ave., Santa Paula Dr., Santa Rita Ave., Savage Way, Shelbourne Ave., Southdale Ave., St. Catherine Dr., St. Francis Blvd, St. James Ct., St. Marks Ct., St. Michaels Ct.,Verano Dr., Woodland Ave., Woodside Ave., Zita Manor

01/2018 07/2018 5 8 19 11

East Palo Alto San Mateo Complete Streets Components ST-05A Bay Road Improvements

The Bay Road project will include street repaving; bicycle and pedestrian improvements; landscaping improvements; and replacement of storm drain and water trunk lines.

0.7 miles of Bay Road from Clarke Avenue to Cooley Landing 12/2018 01/2020 20 40 24 13

East Palo Alto San Mateo Road Maintenance & Rehabilitation

ST-08 University Ave Resurfacing & Signal Upgrade

This project provides for pavement resurfacing, restriping, upgrading of traffic signals and various other improvements on University Avenue. University Avenue from Woodland Avenue to Notre Dame Avenue 06/2020 12/2022 5 40 24 13

East Palo Alto San Mateo Safety ST-09 Bicycle & Pedestrian Improvements

This project is for the installation of street improvements to enhance vehicular, pedestrian and bicycle safety throughout the City.

University Avenue , Pulgas Avenue, Clarke Avenue, Cooley Avenue, Bay Road, Newbridge Ave, East Bayshore Rd, West Bayshore Rd ,Woodland Avenue, Donohoe St., Weeks Street 12/2018 12/2019 5 40 24 13

East Palo Alto San Mateo Traffic Control Devices ST-12 Traffic Calming ProgramThis project provides for the planning and construction of speed bumps, bulb-outs and other traffic calming devices to reduce speed through residential zones and to increase safety.

Pulgas Avenue, Clarke Avenue, Cooley Avenue, Bay Road, East Bayshore Rd, West Bayshore Rd, Woodland Avenue, Weeks Street, Runnymede St 08/2019 12/2022 20 40 24 13

East Palo Alto San Mateo Complete Streets Components

ST-14 University Avenue Interchange

This project will provide for the widening of the University Avenue/US 101 overpass to provide safer pedestrian and bicycle travel and more efficient vehicle travel. The project will include the widening of the overpass bridge and construction of a new diagonal off-ramp from southbound (SB) 101 onto SB University Avenue

University Avenue from Woodland Avenue to Donohoe Street 06/2020 12/2021 20 40 24 13

East Palo Alto San Mateo Complete Streets Components ST-17 New Loop Road

This project is to develop a new loop road around the north and east of the University Village neighborhood that will connect University Avenue to the Ravenswood Business District (RBD) and include a Class I bicycle and pedestrian trail.

Loop Road (new) - north and east of the University Village neighborhood that will connect University Avenue to the Ravenswood Business District (RBD) 09/2018 12/2027 20 40 24 13

East Palo Alto San Mateo Traffic Control Devices ST-19 Runnymede/ University Avenue Signal Upgrading of traffic signals and various other improvements Runnymede/University Avenue 12/2020 12/2021 10 20 24 13

East Palo Alto San Mateo Road Maintenance & Rehabilitation

ST-07 Street Resurfacing Program - Annual Project 2018-19

This project provides for the resurfacing of City streets during the ten-year life of the CIP. Roughly $1,000,000 needs to be expended annually on street resurfacing.

Gaillardia Way, (Azalia Drive - Pulgas Ave), Gardenia Way, (Azalia Drive - Verbena Drive), Lotus Way , (Cul-De-Sac - Wisteria Drive), Aster Way, (Wisteria Drive - Daphne Way), Verbena Drive (Camellia Drive - Cul-De-Sac), Notre Dame Ave (University Ave - Fordham Street), Georgetown St (Tulane Ave - Purdue Ave), Hunter Street (Purdue Ave - Georgetown Street), Purdue Ave (University Ave - Fordham Street), Ralmar Ave (Green Street - Donohoe Street), Ralmar Ave (Green Street - Cul-De-Sac), Donohoe Street (Menalto Ave - West Bayshore Road), Michigan Ave (University Ave - Illinois Street), Bell Street (University Ave Cooley Ave)

09/2018 06/2019 20 40 24 13

East Palo Alto San Mateo Road Maintenance & Rehabilitation

ST-13 Major Street Reconstruction - Annual Project 2018-19

This project provides for the reconstruction of damaged City streets during the ten-year life of the CIP Runnymede Street, Bay Road, Woodland Avenue 12/2018 06/2019 20 40 24 13

Foster City San Mateo Road Maintenance & Rehabilitation

Street Rehabilitation - OBAG2 (2018-2019)

Street rehabilitation including localized asphalt concrete repairs, surface overlays, and installation of bicycle route sharrow symbols, legends, and signage. The project also includes ADA ramp upgrades, and curb and gutter and sidewalk repairs as necessary, and pedestrian crosswalk improvements.

East Hillsdale Boulevard from the Rainbow Bridge to Gull Avenue, and Edgewater Boulevard from Beach Park Boulevard to East Hillsdale Avenue. 06/2019 09/2019 10 20 22 13

Foster City San Mateo Road Maintenance & Rehabilitation

Annual Pavement Rehabilitation Project

Project consists of pavement grinding, base repair, asphalt overlay, thermoplastic traffic striping and pavement markings, and new access. East Hillsdale Boulevard and Beach Park Boulevard 04/2018 07/2018 15 20 22 13

Half Moon Bay San Mateo Road Maintenance & Rehabilitation

Pavement Management & Traffic Safety Program

The project will look to reconstruct and preserve pavement throughout the City. Specifically for FY 18-19, the project will look at reconstruction of approximately 1 miles of pavement, reconstruct 6 ADA ramps, and other related improvements.

Belleville Boulevard neighborhood, Poplar Street, Downtown Half Moon Bay, with potential others based on available funding. 03/2019 02/2020 15 30 24 13

Half Moon Bay San Mateo Road Maintenance & Rehabilitation

Pavement Management & Traffic Safety Program (17/18 Carryover)

The project will look to reconstruct and preserve pavement throughout the City. Specifically for FY 17-18, the project will look at reconstruction of approximately 1 mile of pavement, reconstruct a dozen ADA ramps, and other related improvements.

Church Street - Mill Street to northerly cul-de-sac; Magnolia Street - Main Street to westerly terminus at Highway 1; Naples Avenue - Roosevelt Boulevard to southerly terminus; Railroad Avenue - Grove Street to Metzgar Street; Miramontes Point Road - Canada Cove entrance to Highway 1; Kelly Avenue - San Benito Street to easterly terminus; San Benito Street - Miramontes Street to end

05/2018 10/2018 15 30 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 93: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Hillsborough San Mateo Road Maintenance & Rehabilitation 2019 Street Resurfacing Project

The 2019 Street Resurfacing Project consists of street resurfacing and rehabilitation work for approximately 53 miles of rubberized asphalt overlay, asphalt overlay, cape seal, microsurfacing, and crack sealing. The primary factor for choosing the roadway segments included for rehabilitation is the Pavement Condition Index (PCI) of each roadway. PCI is a measure of a street's condition derived through field inspections that utilize scoring criteria developed by the Metropolitan Transportation Commission's (MTC) pavement management program. Field inspections were conducted in fall of 2018, and the roads with the lowest PCI rating were included in this project and will increase the Town's overall PCI. The improvement of the PCI will help to eliminate the need for vehicles to slow, swerve, or stop suddenly to avoid hazardous road conditions. Properly maintained streets also help to improve traffic flow and assist in preventing congestion, slow traffic, and generally unsafe driving conditions. The Town plans to continue to utilize ,where appropriate, recycled Rubberized Asphalt Concrete (RAC) to help reduce the accumulation of disposed tires occupying landfills in the State of California. The RAC also provides a smoother and quieter roadway surface than conventional asphalt and offers a better platform for outdoor activities such as cyclying and running, which in turn promotes the overall health of the community. Location of the Project: Selected streets are located in various areas within the Town's limit. Detailed locations of each street are summarized in Appendix A. Schedule of Completion: The project is expected to complete by September 2019. Estimated Useful Life: Current life expectancies of proposed streets are shown in Appendix A. Resurfacing and rehabilitation work will extend life expectancy of the these streets as shown below: 2" Mill and AC Overlay - 20 to 30 years 2" RAC Overly - 8 to 15 years 2" AC Overlay - 8 to 15 years Cape Seal - 6 to 8 years Microsurfacing - 4 to 6 years

Selected streets are located in various areas within the Town’s limit. Detailed locations of each street are summarized in the project list attached. 05/2019 09/2019 4 30 22 13

Menlo Park San Mateo Road Maintenance & Rehabilitation

2018 Street Preventive Maintenance Project

Biennial project to rehabilitate streets throughout the City. City’s Pavement Management Program assesses the condition of existing streets and assists in the selection process.

Item Street Name Begin Cross Street End Cross Street 1 Alder Pl Seminary Dr End of Place 2 Almanor Av Hamilton Av Terminal St 3 Atkinson Ln Santa Cruz Av Atkinson Ln (end) 4 Barton Pl Barton Wy End of Place 5 Barton Wy Concord Dr Gilbert Av 6 Bay Laurel Dr Olive St Amber Wy 7 Brady Pl Seminary Dr End of Place 8 Concord Dr Woodland Av Marmona Dr 9 Cornell Rd Creek Rd Cambridge Av 10 Eastcreek Dr Alma St Willow Rd 11 Elmwood Pl Hanna Wy End of Place 12 Garwood Wy Encinal Av 420' S of Encinal Av 13 Ginger St Hamilton Av Sandlewood St 14 Gloria Cir Seminary Dr End of Circle 15 Hanna Wy Seminary Dr End of Way 16 Haven Av Pave change (bend) Haven Ct 17 Haven Ct Haven Av End of Court 18 Hazel St Hamilton Av Sandlewood St 19 Henderson Av Bay Rd Van Buren Rd 20 Hollyburne Av Pierce Rd Newbridge St 21 Linfield Dr Waverly St Middlefield Rd 22 Market Pl Alpine Av Del Norte Av 23 Marmona Ct Marmona Dr End of Court 24 Modoc Av Hamilton Av Terminal St 25 Oakdell Dr Olive St Lemon Av 26 Oakland Av Bay Rd Van Buren Rd 27 Pepperwood Ct Seminary Dr End of Court 28 Poppy Av Evergreen St Magnolia St 29 Princeton Rd Creek Dr College Av 30 Riordan Pl Hanna Wy End of Place 31 Riordan Pl Coleman Wy Riordan Pl 32 Robin Wy Marmona Dr Lexington Dr 33 Sandlewood St 57' E of Chilco Av 145' E of Ginger St 34 Santa Monica Av Coleman Wy San Luis Dr 35 Saxon Wy Windsor Dr End of Way 36 Seminary Dr Middlefield Rd Alder Pl 37 Seminary Dr Alder Pl Monica Av 38 Sonoma Pl Sonoma Av Van Buren Rd 39 Stone Pine Ln El Camino Real 200' NE of El Camino Real

06/2018 11/2018 5 7 24 13

Menlo Park San Mateo Safety Chrysler Stormwater Pump Station Improvements (17/18 Carryover)

Project involves upgrading and/or replacing approximately 60 year old electrical equipment and pumps at the Chrysler Pump Station to reduce potential flooding of adjacent travel ways.

1221 Chrysler Drive, Menlo Park CA 94025 08/2019 11/2024 20 50 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 94: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Menlo Park San Mateo Safety On-Call Asphalt and Concrete Repair Services

Annual project to improve the timeliness of street repairs that ensure the safety of pedestrians and roadway users.

Live Oak Av and El Camino Real At the Northwest IntersectionNealon Park alley: 831 Roble AvJack Lyle Park: 570 Fremont Av15 Biltmore Ln Near Hallmark CircleAt or near 1155 Trinity DrIntersection of Pope & Elm Streets Start of Willow Rd and Bay RdFront of 4000 Bohannon Dr Laurel St (Between Cherry Av and Ravenswood Av). In front of 1064 Laurel StSouth side of Laurel St (Between Encinal Av and Laurel Pl) In front of 1555 Laurel StMiddlefield Rd (Crosswalk at Linfield Av )Encinal Av at the intersection with Laurel StRavenswood Av (Between El Camino Real and RR tracks)Market Pl Park from Plumas Av"Community Garden" Next to 1320 Hill AvSanta Cruz Av (Downtown) between University Dr and El Camino RealSanta Cruz Av Near the Intersections of Orange Av and Avy AvRavenswood Av (Several East of Tracks to Marcussen Dr)-West bound lane onlyWillow Rd (Clover Ln. Fire service crossing pavement settled )Laurel Av (end of road Near HWY 101 Caltrans sound wall)Intersection of Fanita Wy and Oakdale DrMenalto Av East from Walnut St-[Pothole repairs at various locations]Glenwood Ave. both East and West side of tracks-[From tracks to El Camino Real]"Intersection of El Camino Real and Creek DrAt Intersection of Hillview Pl and Hillview DrClose to Belle Haven School across from 1331 Alamanor Av The listed work locations provided above is subject to change due to available funding and may only be partially accomplished on a per year basis

05/2018 11/2019 12 15 24 13

Menlo Park San Mateo SafetyMulti-year Sidewalk Repair Program Replacement of speed humps (17/18 Carryover)

Project to eliminate sidewalk tripping hazards caused by City tree root damage at listed City Neighborhood

1. Belle Haven: Bounded by Willow on the East; Southern Pacific Railroad on the North; and by Pierce Road on the West. Total of 10 locations. 2. Suburban Park/Lorelei Manor Flood Triangle: Bounded by Van Buren Road on the North East, Bay Road on the South and Marsh Road on the West. Total of 20 locations. 3. The Willows: Bounded by Willow Road on the North West, by Middlefield on the South, Highway 101 on the North and the City Limit line on the North east and South East. Total of 15 locations. 4. Linfield Oaks: Bounded by Middlefield Road on the North, by Alma Street on the South, by Ravenswood Ave on the West, and by San Francisquito Creek/the City Limits on the East. Total of 18 locations. 5. West Menlo: Bounded by Valparaiso on the West, University Drive on the North, and San Francisquito Creek/City Limits on the South. Total of 30 locations. 6. Central Menlo: Bounded by the City Limit on the North, by Alma Street and Caltrain Right of Way on the South, and Ravenswood on the East. Total 10 locations. 7. Park Forrest; Bounded by El Camino Real, and Noel Drive on the South, on the North by the City Limits and Caltrain Right of Way, and by Ravenswood on the East. Total of 5 locations. 8. Downtown: Bounded by El Camino Real on the North, by Valparaiso Avenue on the West, by University Drive on the South, and by Middle Avenue on the East. Total of 15 locations. 9. Stanford Heights: Bounded by the City Limits/Alameda de Las Pulgas on the North, by Sand Hill Road, Alamida de Las Pulgas, and City Limits on the South, by the City Limits on the West. Total of 20 locations. 10. Stanford Hills: Bounded by Branner Drive and The City Limits on the West, Junipero Serra and mindering the City Limits on the East, by Sand Hill Road and the City Limits on the North. Total of 8 locations. The above listed locations may be subject to change due to unforeseen circumstances during planning and construction

05/2018 11/2019 25 30 24 13

Menlo Park San Mateo SafetyMulti-year Transportation Projects Replacement of Speed Humps (17/18 Carryover)

Annual project to replace speed humps.

Replacement of 4 speed humps along North Lemon Avenue between Santa Cruz Avenue and Valparaiso Ave; Replacement of 2 speed tables on Monte Rosa Drive, between Siskiyou Drive and Sand Hill Drive; Replace 2 speed humps on Carlton Avenue between Abby Drive and Hamilton Avenue.

05/2018 11/2019 10 30 24 13

Menlo Park San Mateo SafetyMiti-Year Transportation Project Flashing Beacons System (17/18 Carryover)

Installation of Rapid Rectangular Flashing Beacon Systems (RRFB)Crane Street 50 feet South of Valparaiso Avenue; Interception of Santa Cruz Avenue and Johnson Street; Interception of Ravenswood Avenue and Alma Street; Oak Grove Avenue, between Maloney Lane and Hoover Street; Interception of Middle Road and Linfield Drive.

05/2018 11/2019 10 30 24 13

Menlo Park San Mateo SafetyMulti-year Transportation Projects Adaptive Traffic Signal System (17/18 Carryover)

Deployment of Adaptive Traffic Signal system On Willow Road between Middlefield Road and Bayfront Expressway; Marsh Road, between Bay Road and Bayfront Expressway; Bayfront Expressway between Marsh Road and University Drive. 05/2018 11/2019 10 30 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 95: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Menlo Park San Mateo SafetyMulti-year Transportation Projects High Volume Series Ligth Circuit Conversion (17/18 Carryover)

High Voltage Series Street Light Circuit Conversion

Suburban Park/Lorelei Manor Flood Triangle: Bounded by Van Buren Road on the North East, Bay Road on the South and Marsh Road on the West; Linfield Oaks, bounded on the North by Middlefield Road, on the South by Alma Street/Caltrain Right of Way, on the East by San Francisquito Creek/City Limits, and on the West by Revenswood Avenue.

05/2018 11/2019 10 30 24 13

Millbrae San Mateo Road Maintenance & Rehabilitation

Crestview Drive Springfield Drive Valencia Drive and Toyon Drive repaving project 2019

Overlay of Crestview Drive, Springfield Drive, Valencia Drive, and Toyon Drive. Work includes signage striping, pavement legend, sidewalk replacement, and wheel chair curb ramps upgrade.

Crestview Drive, Springfield Drive, Valencia Drive, and Toyon Drive. 10/2018 02/2019 20 29 22 13

Millbrae San Mateo Road Maintenance & Rehabilitation Larkspur Drive Repaving 2019 Overlay of Larkspur Drive from Skyline Blvd to Helen Drive. Work includes signage

striping, pavement legend, sidewalk replacement, and wheel chair curb ramps upgrade. Larkspur Drive between 01/2019 05/2019 20 29 22 13

Millbrae San Mateo Road Maintenance & Rehabilitation

Slurry Seal Maintenance of various streets

Slurry seal of the following streets:Anita Drive from Geraldine Drive to Magnolia Avenue; Bayview Avenue from Lomita Avenue to Lomita Avenue; Cypress Avenue from Park Boulevard to Juanita Avenue; Henry Place; Dexter Place; Robert Place; Helen Drive from Brookside Lane to Banbury Lane; Helen Drive from Geraldine Drive to Magnolia Avenue; Juanita Avenue from Santa Susana Ave to Cypress Avenue; Lomita Avenue from Ridgewood Drive to Cypress Avenue; Rosalita Lane; Santa Florita Avenue from Park Boulevard to Lomita Avenue; Santa Susana Avenue from Park Boulevard to Juanita Avenue; Santa Teresa Avenue from Park Boulevard to Lomita Avenue Sequoia Avenue

Anita Drive from Geraldine Drive to Magnolia Avenue; Bayview Avenue from Lomita Avenue to Lomita Avenue; Cypress Avenue from Park Boulevard to Juanita Avenue; Henry Place; Dexter Place; Robert Place; Helen Drive from Brookside Lane to Banbury Lane; Helen Drive from Geraldine Drive to Magnolia Avenue; Juanita Avenue from Santa Susana Ave to Cypress Avenue; Lomita Avenue from Ridgewood Drive to Cypress Avenue; Rosalita Lane; Santa Florita Avenue from Park Boulevard to Lomita Avenue; Santa Susana Avenue from Park Boulevard to Juanita Avenue; Santa Teresa Avenue from Park Boulevard to Lomita Avenue Sequoia Avenue

07/2018 09/2018 5 9 22 13

Millbrae San Mateo Road Maintenance & Rehabilitation

Old Bayshore Highway Repaving 2018 (17/18 Carryover)

Overlay of Old Bayshore Highway from Burlingame City Limit to Millbrae Avenue. Work includes signage, striping, pavement legend, sidewalk and median replacement, and wheel chair curb ramps upgrade.

Old Bayshore Highway between Burlingame City Limit & Millbrae Avenue 06/2018 09/2018 20 29 22 13

Pacifica San Mateo Road Maintenance & Rehabilitation

FY 2017-18 Pavement Rehabilitation Project

The FY 2017-18 Pavement Rehabilitation Project will rehabilitate the pavement along Linda Mar Boulevard from Adobe Drive to Alicante Drive and Oceana Boulevard from Milagra Drive to Monterey Road by placing 2 inches of asphalt overlay. This project will also include pavement grinding for base repair as well as installation of thermoplastic traffic striping, markings, and pavement markers. This project was intended to start in 17/18 but were not able to and moved into 18/19. We request that you include this project on our 18/19 list (17/18 Carryover).

Linda Mar Boulevard from Adobe Drive to Alicante Drive and Oceana Boulevard from Milagra Drive to Monterey Road 08/2018 09/2018 15 20 22 13

Pacifica San Mateo Complete Streets Components Citywide Curb Ramp Project

The Citywide Curb Ramp Project will replace 100 curb ramps throughout the City of Pacifica. This project was intended to start in 17/18 but were not able to and moved into ODDSTAD BOULEVARD @ LINDA MAR BOULEVARD18/19. We request that you include this project on our 18/19 list (17/18 Carryover).

Citywide HICKEY BOULEVARD @ FAIRMONT SHOPPING CENTER GATEWAY DRIVE @ FAIRMONT SHOPPING CENTER GATEWAY DRIVE @ FAIRMONT SHOPPING CENTER GATEWAY DRIVE @ SPRINGDALE DRIVE PALMETTO AVENUE @ BILL DRAKE WAY PALMETTO AVENUE @ WEST AVALON DRIVE PALMETTO AVENUE @ MILAGRA PEDESTRIAN OVERCROSSING OCEANA BOULEVARD @ MILAGRA DRIVE OCEANA BOULEVARD @ PALOMA AVENUE CRESPI DRIVE @ ROBERTS ROAD CRESPI DRIVE @ LADERA WAY CRESPI DRIVE @ PERALTA ROAD CRESPI DRIVE @ ESCALERO ROAD CRESPI DRIVE @ SEVILLE DRIVE DE SOLO DRIVE @ ANZA DRIVE DE SOLO DRIVE @ ARGUELLO BOULEVARD PERALTA ROAD @ MONTEZUMA DRIVE FRANCISCO BOULEVARD @ CARMEL AVENUE

ODDSTAD BOULEVARD @ TOLEDO COURT ODDSTAD BOULEVARD @ SHOPPING CENTER DRIVEWAY ODDSTAD BOULEVARD @ PARK PACIFICA AVENUE TERRA NOVA BOULEVARD @ SHOPPING CENTER DRIVEWAY TERRA NOVA BOULEVARD @ ODDSTAD BOULEVARD ROSITA ROAD @ MONTE VERDE DRIVE ROSITA ROAD @ RIO VISTA DRIVE ROSITA ROAD @ PALOU DRIVE ROSITA ROAD @ GALVEZ DRIVE WEST ROSITA ROAD @ GALVEZ DRIVE EAST ROSITA ROAD @ CAPISTRANO DRIVE LINDA MAR BOULEVARD @ CAPISTRANO DRIVE LINDA MAR BOULEVARD @ MADEIRA DRIVE ROCKAWAY BEACH AVENUE @ DONDEE WAY REINA DEL MAR AVENUE @ RIECHLING AVENUE REINA DEL MAR AVENUE @ LAUREN AVENUE FRANCISCO BOULEVARD @ CLARENDON ROAD FRANCISCO BOULEVARD @ SANTA MARIA AVENUE FRANCISCO BOULEVARD @ SALADA AVENUE

08/2018 09/2018 20 30 22 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 96: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Pacifica San Mateo Complete Streets Components Palmetto Sidewalk Project

The project consists of the construction of 1,400 feet of sidewalk, curb and gutter along the west side of Palmetto Avenue. This project was intended to start in 17/18 but were not able to and moved into 18/19. We request that you include this project on our 18/19 list (17/18 Carryover).

Palmetto Avenue from Westline Drive to 100 Palmetto Avenue 10/2018 11/2019 20 30 22 13

Pacifica San Mateo Safety Cabrillo School Pedestrian Crossing Improvement Project

The Project will install vegetated curb extension at the midblock crossing directly in front of the school. The vegetated curb extensions will help increase safety and reduce or eliminate polluted stormwater runoff, reduce stormwater management costs, and increase the aesthetic value of streets and neighborhoods.

Crespi Drive at Cabrillo School 05/2019 06/2019 10 15 22 13

Portola Valley San Mateo Road Maintenance & Rehabilitation

Street resurfacing project in the Town of Portola Valley

1. Project Description: This proposed project consists of street resurfacing and rehabilitation work consisting of base repairs, crack sealing, and asphalt overlay or slurry/surface seals. The primary factor for choosing the roadway segments included is the Pavement Condition Index (PCI) of each roadway. PCI is a measurement of a street’s condition derived through field inspections that utilize scoring criteria developed by the Metropolitan Transportation Commission’s (MTC) pavement management program.

Location of the Project: Acorn Court: Entire length; Alamos Drive: Entire length; Goya Road: Entire length; Grove Court: Entire length; Groveland Street: Entire length; Los Trancos Road: Alpine Road to Palo Alto Town limits; Naranja Way: Entire length; Portola Green Circle: Entire length

05/2020 07/2020 4 6 24 13

Redwood City San Mateo Road Maintenance & Rehabilitation

2017-2018 Overlay Project - Twin Dolphin Drive (FY17-18 Carryover)

Preventative rehabilitation and pavement maintenance, including raising utilities covers to grade, ADA improvements and installation of associated markers and striping. Twin Dolphin Drive, Marine to Redwood Shores Parkway, in the City of Redwood City 04/2018 04/2019 8 15 22 13

Redwood City San Mateo Road Maintenance & Rehabilitation

Hopkins Avenue Overlay Project (FY17-18 Carryover)

Preventative rehabilitation and pavement maintenance, including raising utilities covers to grade, ADA improvements and installation of associated markers and striping. Hopkins Avenue, El Camino Real to Upland Road 12/2018 12/2019 8 15 22 13

Redwood City San Mateo Road Maintenance & Rehabilitation

FY2018-19 Pavement Management Program

This program addresses ongoing roadway pavement repair and replacement needs. The Roadway Management Program inventories, assesses, and tracks maintenance of the City’s roadways. Each year, streets are prepared for resurfacing with crack sealing and spot repairs before being resurfaced with an “overlay,” “cape seal,” or “slurry seal”. In Fiscal Year 2018-19, the City intends to use RMRA funding to overlay the below listed street locations.

Chestnut Street, El Camino Real to Railroad; Middlefield Road, Jefferson Avenue to Main Street; Spring Street, Woodside Road to Douglas Street; Warwick Street, Edgewood Road to City Limits 11/2018 06/2019 8 15 22 13

San Bruno San Mateo Road Maintenance & Rehabilitation 2018-19 Street Rehabilitation Rehabilitate pavement on three (3) streets by removing existing pavement section and

replacing with new asphalt and aggregate base.

Projects are located as follows: Santa Helena Avenue between San Antonio Avenue and El Camino Real, Mills Avenue between Kains Avenue and San Bruno Avenue, Eastburn Court between Whitman Way and Cul-de-sac.

08/2019 10/2019 20 20 22 13

San Bruno San Mateo Road Maintenance & Rehabilitation 2017-18 Street Rehabilitation

Rehabilitate pavement on one (1) street by removing existing pavement section and replacing with new asphalt and aggregate base. This is a carryover project from 2017-18 that due to contract approval delays will not be completed until fiscal year 2018-19.

On Masson Avenue between San Bruno Avenue and Angus Avenue West. 08/2018 10/2018 20 20 22 13

San Carlos San Mateo Road Maintenance & Rehabilitation 2018 Pavement Rehabilitation Pavement rehabilitation, maintenance, striping, and ADA ramps Arundel Rd, Palm Ave, Hillcrest Rd, Upland Ave, Vista Ave, Carmelita Dr, Prospect St, Knoll Dr,

Coronado Ave, and Hilltop Dr. 07/2018 10/2018 7 20 22 13

San Carlos San Mateo Road Maintenance & Rehabilitation

Brittan Avenue and Cedar Street Resurfacing Pavement rehabilitation, maintenance, striping, and ADA ramps Brittan Ave, from Elm St. to El Camino Real, and Cedar St. from San Carlos Ave. to end. 03/2019 07/2019 12 13 22 13

San Mateo San Mateo Road Maintenance & Rehabilitation

2018-19 Street Rehabilitation at Various Locations

Project work includes milling of pavement surface, asphalt concrete overlay, upgrade of curb access ramps, installation of pavement markings and striping and other incidental work.

Alameda de las Pulgas, from State Route 92 to 24th Avenue; Grand Boulevard, from Prospect Row to east end/railroad tracks; Pasadena Drive, from 39th Avenue to south end; Poplar Avenue, from Delaware Street to Amphlett Boulevard; Ottawa Street, from Trollman Avenue to Lorraine Avenue; and Rochester Street, from Monte Diable Avenue to York Avenue.

04/2019 09/2019 10 15 22 13

San Mateo San Mateo Road Maintenance & Rehabilitation

E. Hillsdale Boulevard Rehabilitation (17/18 Carryover)

The project will rehabilitate the pavement on E. Hillsdale Boulevard from Saratoga Drive to Norfolk Street (approximately 0.44 mile). The proposed treatment includes milling the existing pavement surface then applying an asphalt concrete overlay. Related work will include the upgrade of curb access ramps to current standards, installation of pavement striping and other markings, installation of traffic loops and adjust manhole to finished grade.

The project is located on E. Hillsdale Boulevard from Saratoga Drive to Norfolk Street in the City of San Mateo. 07/2018 11/2018 15 15 22 13

South San Francisco San Mateo Complete Streets Components

Grand Boulevard Initiative Phase 2 (Kaiser Way to McLellan Dr.)

The work consists of the installation of enhanced pedestrian crossings, corner bulbout and median refuges at two intersections, expand two bus stop/waiting areas, install approximately 2000 feet of new landscaped medians, and green infrastructure.

El Camino Real between Kaiser Way and McLellan Drive. 03/2018 03/2019 10 30 22 13

South San Francisco San Mateo Complete Streets Components

(17/18 Carryover) Grand Boulevard Project Phase 3 (Arroyo Drive to Kaiser Way)

Improve El Camino Real between Arroyo Drive and Kaiser Way by installing enhanced pedestrian crossings, bike lanes, corner bulb out and median refuges, expanded bus stop/waiting areas, a new landscaped median, and green infrastructure.

El Camino Real between Arroyo Drive and Kaiser Way 12/2018 12/2019 10 30 19, 22 13

South San Francisco San Mateo Complete Streets Components

(17/18 Carryover) North Access Road Bike and Pedestrian Improvements

Widen approximately 1,000 feet of bike and pedestrian pathways North Access Road beginning at South Airport Boulevard. 06/2018 06/2019 15 20 22 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 97: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Woodside San Mateo Road Maintenance & Rehabilitation 2019 Road Rehabilitation Project

Project includes pavement rehabilitation and replacement, digouts, roadside swale paving, new pavement striping and marking, and may include associated storm drainage and safety-related improvements on streets throughout the Town.

2019 Road Rehab (18/19 List): Oakhaven Way from Woodside Dr. to End; Greer Rd. from Kings Mountain Rd. to End; Roan from Patrol to End; Portola Rd. from Family Farm to 1231 Portola Rd. 2018 Road Rehab (17/18 Carryover): Crest Rd from Cinnabar to Cragmont; Harcross Rd from School to End; Normandy Lane from Woodside Dr to End; Hardwick Rd from Woodside dr to End; Canada Rd from Woodside Rd to Palm circle; Patrol Rd from Summit Springs to End; Ward Way from Alameda De las Pulgas to End; Eleanor Dr from 270 Eleanor to Eugenia; Glenwood Rd from Hillsdale Dr to End; Hillside Dr from Glenwood to Alta Mesa; Stadler Dr from End S to End N; Alta Mesa Rd from Highland Terrace to Hillside; West California from Jefferson to 1992 ft N of Jefferson; West Glen Way from W.California to Glencrag; Maple Way from East View to Glencrag; Portola Rd from Highland to Family Farm; Portola Rd from Sandhill to La Honda.

05/2019 07/2019 5 15 24 13

Buellton Santa Barbara Road Maintenance & Rehabilitation

FY 2018-19 Road Maintenance Project Type II Slurry Seal and localized R&R.

Calor Drive; La Lata Drive; La Lata Place; Terrace Court; Menlo Drive; Kim Sue Lane; Teri Sue Lane; Paula Ray Lane; La Pita Place; Irelan Drive; Dawn Drive; Sharon Place; Nina Place; Karen Place; Park Street; Second Street (Calor Drive to west of Central Avenue); Oak Tree Way; Twin Oaks Drive

06/2019 08/2019 15 25 37 19

Carpinteria Santa Barbara Road Maintenance & Rehabilitation Street Maintenance Program Road Maintenance & Rehabilitation (Carryover from FY 17/18 Project List)

6th St. (Yucca Ln. to Elm Ave.); 8th St. (Holly Ave. to End); 9th St. (Linden Ave. to Franklin Creek); Elm Ave. (8th St. to 7th St.); Holly Ave. (Carpinteria Ave. to 7th St.); Juniper Pl. (Yucca Ln. to Elm Ave.); Linden Ave. (Carpinteria Ave. to Railroad); Wullbrandt Wy. (Linden Ave. to Cactus Ln.); Yucca Ln. (Carpinteria Ave. to 6th St.); 6th St. (Palm Ave. to Walnut Ave. and East End to Olive Ave.); Cactus Ln. (8th St. to 7th St.); Citrus Pl. (Maple Ave. to Cactus Ln.); Maple Ave. (8th St. to Carpinteria Ave.); Olive Ave. (6th St. to South End); Walnut Ave. (6th St. to South End); Carpinteria Ave. (Linden Ave. to Holly St.); Reynolds Ave. (US 101 to Carpinteria Ave.); Casitas Pass Rd. (Foothill Rd. to Cameo Rd.); Via Real (Lemonwood Dr. to Calle Lagunitas); Cramer Circle (East Via Real to West Via Real); Santa Ynez Ave. (North End to Via Real)

12/2018 06/2019 5 20 37 19

Carpinteria Santa Barbara Road Maintenance & Rehabilitation

Parking Lot No. 2 & Cactus Lane Improvements

Reconstruction of Roadway Structural Section, Pedestrian Facilities, Drainage Structures, and Curb and Gutter (Carryover from FY 17/18 Project List) Cactus Lane from Carpinteria Avenue to Wullbrandt Way 12/2018 06/2019 5 20 37 19

Goleta Santa Barbara Road Maintenance & Rehabilitation

FY 2017/18 PAVEMENT REHABILITATION PROJECT– CATHEDRAL OAKS RD.

Full section pavement rehabilitation with lime & cement treated pulverized base under AC at vehicle travelways and mill & overlay at selected bikelanes. Median improvements and paint striping.

CATHEDRAL OAKS ROAD - EAST SIDE OF BRIDGE W/O CARLORLO DRIVE TO E/O SANTA MARGUERITA DRIVE CATHEDRAL OAKS ROAD - E/O SANTA MARGUERITA DRIVE TO FAIRVIEW AVENUE ALTERNATE 1- CATHEDRAL OAKS ROAD EAST SIDE OF BRIDGE TO N. LOS CARNEROS ROAD

06/2018 12/2018 20 30 37 19

Goleta Santa Barbara Road Maintenance & Rehabilitation

FY 18/19 Pavement Rehabilitation Project.

Staff is proposing that all the SB 1 funding programmed for FY 18/19 be used to fund the FY 18/19 Pavement Rehabilitation Project. The proposed list of project sites includes deep lift road reconstruction with an approximate new 5.5-inch asphalt surface for:Evergreen Drive between Cathedral Oaks Drive and Brandon Drive (Collector) Average PCI = 50; Hillview Drive (Residential/Local) PCI = 35; Forest Drive (Residential/Local) PCI = 39The estimated cost of the above work is approximately $1,011,000. The useful life of the improvements is expected to be at least 20 years.

Staff is proposing that all the SB 1 funding programmed for FY 18/19 be used to fund the FY 18/19 Pavement Rehabilitation Project. The proposed list of project sites includes deep lift road reconstruction with an approximate new 5.5-inch asphalt surface for:

The estimated cost of the above work is approximately $1,011,000. The useful life of the improvements is expected to be at least 20 years.

12/2018 06/2019 20 30 37 19

Guadalupe Santa Barbara Road Maintenance & Rehabilitation

2019 Pavement Maintenance Project

Crack Fill & Slurry Seal (Type B) and localized 4" removal and replacement of HMA on City roads as outlined in City's Pavement Management System document (2013) and any roads deferred from previous years. Projected to address 16 streets in the 18/19 slated project.

Streets included but not limited to: Calle Cesar E. Chavez St., La Purisma St., San Miguel Ct., Tognazzini Ave., Sixth St., Fourth, Holly, Fir, Elm, 3rd, Cedar, Birch, Second, Amber Streets and Flower Avenue.

05/2019 11/2019 3 5 35 19

Guadalupe Santa Barbara Road Maintenance & Rehabilitation

2018 Pavement Maintenance Project

Crack Fill & Slurry Seal (Type B) and localized 4" removal and replacement of HMA on City roads as outlined in City's Pavement Management System document (2013).

Plans available upon request. Section 1: Ibis Circle, Pacific Dunes Way from W. Main to Surfbird Ln, Sandpiper Lane from Pacific Dune Way to cul-de-sac, Point Sal Dunes Ln from W. Main to Surfbird Ln, Surfbird Ln from Pacific Dunes to Surfbird Ct., Egret Lane. Section 2: Garrett Street, Mary Knoll Drive. Section 3: 2nd St from Tognazzini Ave to Hwy 1, Campodonico Ave from 2nd St to 7th St, Alley between Campodonico Ave and Hwy 1 from 2nd to 7th St, 3rd Street, 7th St, Rubio St, Peralta St. from 10th St to 11th St, Escalante St.

05/2018 11/2018 3 5 35 19

Lompoc Santa Barbara Traffic Control Devices Maintenance of Traffic Control Signs, Striping, and Markings.

Maintenance of City owned traffic control signs, painting of lane line striping and roadway markings (arrows, stop bars, speed limit, etc.) by City Maintenance workers.

City wide within the boundaries of the Four (4) City Council Districts as follows:Maps of the City Council Districts are available on the City of Lompoc Website, http://www.cityoflompoc.com/Clerk/Graphics/DistrictMap.jpeg.All locations are subject to change and will be selected based on priority need and available resources throughout the year.

06/2018 07/2018 2 5 35 19

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 98: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Lompoc Santa Barbara Road Maintenance & Rehabilitation Pavement Repair Various pavement repairs of the City roadway network by City Maintenance workers.

City wide within the boundaries of the Four (4) City Council Districts as follows: City Council District 1 - all that portion of the City beginning at the intersection of North Avenue and the City’s western border near Z Street; thence proceeding easterly along North Avenue to 3rd Street; thence proceeding southerly along 3rd Street to the alley between North Avenue and Lemon Avenue; thence proceeding easterly along the alley to 7th Street; thence proceeding northerly along 7th Street to North Avenue; thence proceeding easterly along North Avenue to Riverside Drive; thence proceeding southeasterly along Riverside Drive to the intersection of Riverside Drive, Pine Avenue and the eastern border of the City; thence proceeding counter-clockwise along the City border, including the non-contiguous parcel along McLaughlin Road, until the point of origin. Ci ty Council District 2 - all that portion of the City beginning at the intersection of North Avenue and the City’s western border near Z Street; thence proceeding easterly along North Avenue to F Street; thence proceeding southerly along F Street to Pine Avenue; thence proceeding easterly along Pine Avenue to the alley between F Street and E Street; thence proceeding southerly along the alley to Airport Avenue; thence proceeding westerly along Airport Ave to F Street; thence proceeding southerly along F Street to College Avenue; thence proceeding westerly along College Avenue to H Street; thence proceeding southerly along H Street to Chestnut Avenue; thence proceeding westerly along Chestnut Avenue to U Street; thence proceeding northerly along U Street to Laurel Avenue; thence proceeding westerly along Laurel Avenue to the western City border; thence proceeding clockwise along the City border until the point of origin. Ci ty Council District 3 - all that portion of the City beginning at the intersection of the City’s southern border and the easterly extension of Oxford Drive along the southern border of Census Block 060830027083006, thence proceeding westerly along the easterly extension of Oxford Drive along the southern border of Census Block 060830027083006 until C Street; thence proceeding northerly along C Street until Willow Avenue; thence proceeding easterly along Willow Avenue until B Street; thence proceeding northerly along B Street until Hickory Avenue; thence proceeding westerly along Hickory Avenue until C Street; thence proceeding northerly along C Street until the Civic Center Plaza parking lot driveway; thence proceeding westerly and northerly through the Civic Center parking lot driveway to D Street; thence proceeding northerly along D Street until the east-west powerline right-of-way between Ocean Avenue and Walnut Avenue; thence proceeding easterly along the powerline right-of-way until the alley and north-south powerline right-of-way between D Street and C Street; thence proceeding northerly along that alley to Walnut Avenue; thence proceeding westerly along Walnut Avenue to D Street; thence proceeding northerly along D Street to College Avenue; thence proceeding westerly along College Avenue to F Street; thence proceeding northerly along F Street to Airport Avenue; thence proceeding easterly along Airport Avenue to the alley between F Street and E Street; thence proceeding northerly along the alley to Pine Avenue; thence proceeding westerly along Pine Avenue to F Street; thence proceeding northerly along F Street to North Avenue; thence proceeding easterly along North Avenue to 3rd Street; thence proceeding southerly along 3rd Street to the alley between North Avenue and Lemon Avenue; thence proceeding easterly along the alley to 7th Street; thence proceeding northerly along 7th Street to North Avenue; thence proceeding easterly along North

06/2018 07/2018 1 20 35 19

Santa Barbara Santa Barbara Road Maintenance & Rehabilitation Mission Street Overlay

The project will rehabilitate five blocks of Mission Street from US 101 to State Street by replacing failing traffic signal conduit at five signalized intersections; replacing damaged concrete curbs, gutters, and cross gutters; upgrading access ramps to meet Americans with Disabilities Act requirements; and grinding and overlaying the roadway surface.

Mission Street from US 101 to State Street in the City of Santa Barbara 04/2019 08/2019 15 20 37 19

Santa Barbara Santa Barbara Road Maintenance & Rehabilitation

FY 17/18 Ongoing Bath Street Overlay

Grind and overlay five blocks of Bath Street from Carrillo Street to Micheltorena Street. Access ramps along this corridor will also be upgraded to meet Americans with Disabilities Act requirements.

Bath Street from Carrillo Street to Micheltorena Street in Downtown Santa Barbara 05/2018 09/2018 15 20 37 19

Santa Maria Santa Barbara Road Maintenance & Rehabilitation 2018 Chip Seal Project

This project consists of placing a chip seal surface treatment and install pavement markings on various City streets in the City of Santa Maria. Chip seal is a preventive maintenance treatment for giving added life to pavement. It represents an important part of the City's annual street maintenance program because it "rejuvenates" the asphalt concrete pavement structure by replacing oil that has evaporated, worn away, or been lost to the elements. The project will provide a surface treatment for approximately 4,000,000 SF of roads.

Various Street throughout the City, some of which include: E. Alvin Avenue east of Suey Road, E. Donovan Road from Broadway to College Drive, N. Railroad Avenue from Canal to Atlantic, S. Miller Street from Main to Camino Colegio, S. Miller Street from McCoy to Orcutt Expressway, Santa Maria Way from Broadway to the City Limits, West Battles Road from Blosser to A Street.

09/2018 12/2018 5 10 35 19

Santa Maria Santa Barbara Road Maintenance & Rehabilitation

East Alvin Avenue and South College Drive Pavement Rehabilitation

This project will place a standard 2-inch asphalt overlay over two (2) distressed street sections. Work will include digging out and repairing failed pavement areas with new hot mix asphalt concrete. It will include grinding down the surface of the roadways to allow for an even transition from the overlaid roadway to the roadway edge. Then a glass grid will be placed followed by the hot mix asphalt. The project also includes installation of new striping and pavement markings. Approximately 165,000 SF of roadway, equivalent to 2 lane miles, will be renewed.

East Alvin Avenue from College Drive to Bradley Drive; South College Drive from Stowell Road to Enos Drive 09/2018 12/2018 15 25 35 19

Santa Maria Santa Barbara Road Maintenance & Rehabilitation Thin Maintenance Overlay (2017/18)

This project will place a rubberized asphalt overlay approximately 1.25" thick over five (5) existing roadways. The work involves grinding down the edges of the roadways to allow for an even transition from the overlaid roadway and the roadway edge. Once the overlay is complete, the roadway striping will be replaced. This project will resurface five (5) severely distressed roadways accounting for 364,000 square feet or the equivalent of 4-5 lane miles.

E. Cypress Street from S. Nicholson Avenue to S. Stratford Avenue, E. Cypress Street from S. Palisade Drive to S. Suey Road, N. Valerie Street from E. Main Street to E. Alvin Avenue, N. Palisade Drive from N. Valerie Street to E. Alvin Avenue, N. Lincoln Street from W. El Camino Street to W. Bunny Avenue, and W. Pershing Street from S. Blosser Road to S. Western Avenue.

05/2018 06/2018 7 15 35 19

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 99: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Santa Maria Santa Barbara Road Maintenance & Rehabilitation

North Miller Street Pavement Rehabilitation (2017/18)

This project will place a standard 2-inch asphalt overlay over a severely distressed section of Miller Street. Work will include digging out and repairing failed pavement areas with new hot mix asphalt concrete. It will include grinding down the surface of the roadways to allow for an even transition from the overlaid roadway to the roadway edge. Then a glass grid will be placed followed by the hot mix asphalt. The project also includes installation of new striping and pavement markings. Approximately 70,000 SF of roadway, equivalent to 0.8 lane miles, will be renewed.

North Miller Street from Chapel Street to Alvin Avenue 03/2019 06/2019 15 25 35 19

Solvang Santa Barbara Road Maintenance & Rehabilitation

FY 2018-19 Pavement Slurry Seal Project

Apply Type 2 slurry seal to asphalt surface to extend useful life of roadway pavement, and apply new striping and pavement markings.

Preliminary: Portions of Alisal Rd, Atterdag Rd, Birch Dr, Elverhoy Wy, Fifth St, First Crt, First St, Willow Dr, Mountain View Dr, Third St, Fjord Dr, Ironwood Wy, Juniper Dr, Pepperwood Wy, Sandalwood Wy, Aarhus Dr, Midten Hof, Oster Sted, Vester Sted, Aebeltoft Wy, Eucalyptus Dr, Fredensborg Canyon Rd, Laurel Av, Roskild Dr, Creekside Dr, Holly Ln, Rebild Dr, Nysted Dr, Ringsted Dr, Skagen Dr, Viborg Dr, Alamo Pintado Rd, Maple Av, and Windmill Crt.

09/2018 05/2019 6 9 35 19

Solvang Santa Barbara Road Maintenance & Rehabilitation

Alamo Pintado Rd & South Alisal Rd Full Depth Reclamation - Road Reconstruction Project FY 2020-21

Reconstruct segments of Alamo Pintado Road and South Alisal Road by recycling the existing asphalt pavement and road base using a process know as full depth reclamation. South Alisal Road will also be widened to include bike lanes on both sides of the road.

Alamo Pintado Road from Coyote Creek Road to the northerly City Limits, and south Alisal Road from the Santa Ynez River to the southerly City Limits. 03/2020 05/2021 25 40 35 19

Campbell Santa Clara Road Maintenance & Rehabilitation

ANNUAL STREET MAINTENANCE - WINCHESTER BLVD

Install asphalt concrete overlay, perform pavement digout repair and overlay preparation, reconstruct median islands, remove and replace pavement striping and markings, install ADA compliant curb ramps and relocation of traffic poles as needed, and other incidental work.

Winchester Blvd from northern city limit near Rosemary Ln to southern city limit at Knowles Drive and a portion of Campbell Ave from Winchester Blvd to Jeffers Way. 04/2019 04/2020 10 15 28 15

Campbell Santa Clara Road Maintenance & Rehabilitation

ANNUAL STREET MAINTENANCE - AUDREY AVENUE & HACK AVENUE_17/18 ONGOING

Install asphalt concrete over the width of the two traveled lanes (approximately 24 feet) and apply slurry seal from road edge to road edge. The project will also install ADA compliant accessibility ramps at the intersections of Audrey/Burrows and at Audrey/Oburn, and new striping.

Audrey Avenue - from Burrows Road to the eastern terminus east of Vale Avenue at the rear entrance to Capri elementary School, and Hack Avenue - from W. Parr Avenue to the northern terminus at Audrey Avenue

06/2018 12/2018 10 15 28 15

Cupertino Santa Clara Road Maintenance & Rehabilitation

2019 Pavement Maintenance Phase 1 Residential Asphalt Overlay

Hanford Dr., Moltzen Dr., Rodrigues Ave from Western Ave to De Anza Blvd, Paradise Dr., Leola Ct, N Portal Ave, Drake Ct, Stonydale Dr., Degas Ct, Voss Ave, El Prado Way, Salem Ave, Poppy Dr., Ruppell Pl,

08/2018 10/2019 25 25 24 10

Cupertino Santa Clara Road Maintenance & Rehabilitation

2018 Pavement Maintenance Phase 1

2018 Pavement Maintenance Phase 1 Project is a residential overlay project. The project includes approximately 40 street segments. Construction will begin in June 2018 and continue through September 2018

Approximately 40 residential street segments including Phar Lap Dr, Clifford Dr, Scofield Dr, Johnson Ave, Phil Ln, and Plum Tree Lane. 05/2018 09/2018 25 30 28 15

Gilroy Santa Clara Road Maintenance & Rehabilitation

FY 19 Pavement Maintenance Project

Pavement maintenance project, including digouts, crack seal, and rubberized cape seal surface treatment.

In the City of Gilroy, on the following street segments: Farrell Ave (from Wren to Monterey); Eighth St (from Princevalle to Church); Martin St (from Monterey to Chestnut); Murray Ave (from I.O.O.F to Leavesley), and; San Ysidro Ave (from 2250 ft. N of Leavesley to Las Animas);

08/2018 10/2018 6 8 30 17

Los Altos Santa Clara Road Maintenance & Rehabilitation

Los Altos Avenue and West Edith Avenue - Overlay

Base failure repair and thin overlay of Los Altos Avenue between Yerba Santa Avenue and El Camino Real. Class III bicycle pathway and pedestrian striping improvements. Base failure repair and thin overlay of West Edith Avenue between Los Altos Avenue and San Antonio Road. Class III bicycle pathway and pedestrian striping improvements.

Los Altos Avenue (Yerba Santa Avenue to El Camino Real); West Edith Avenue (Los Altos Avenue to San Antonio Road). 08/2018 10/2018 15 15 24 13

Los Altos Hills Santa Clara Safety Matadero Creek Restoration Project (On-Going)

Removal of a portion of the outfall apron below Page Mill Road box culvert, removal of 13 willow and walnut trees, grading of new channel, creation of a rock rip-rap and reinforced drop-pool habitat features, downstream enforcement of the creek banks, and replanting. Project will provide pavement stability of a portion of Page Mill Road improving pedestrian and vehicular access and safety.

Page Mill Road at Berry Hill Court 03/2019 04/2019 30 50 24 13

Los Altos Hills Santa Clara Complete Streets Components Estacada Way Pathway Project

This project is to construct a pathway on DeBell Road connecting Miranda and Manuella Road. The pathway connection will provide a safer route to school and improve pedestrian safety.

DeBell Road, Los Altos Hills 07/2018 05/2019 20 30 24 13

Los Altos Hills Santa Clara Complete Streets Components

Fremont Road to Redwood Grove Pathway Project

This project is to construct an off-road native pathway connecting Fremont Road and Redwood Grove in City of Los Altos. The pathway connection will improve pedestrian safety and connection to neighboring towns and existing routes.

Fremont Road 07/2018 05/2019 20 30 24 13

Los Altos Hills Santa Clara Road Maintenance & Rehabilitation

2018 Pavement Rehabilitation and Storm Drainage Improvement Project

This is an annual street resurfacing project that includes 1.5” and 2” overlay with digouts, microsurfacing, microsurfacing and digouts, 4” AC deep lift patching, 4” full grind and paving, pavement markings replacement, and micro-surfacing throughout various streets within Town limits. (See attached exhibit for street names.) The selected streets were determined by the recommendation from the Metropolitan Transportation Commission’s Pavement Management Program. Alternate streets were selected due to recent change of ownership from private to public, which allowed connectivity between public streets. The condition of the privately own streets required street reconstruction in order to allow safe public use. This project will extend the life span of streets throughout the Town between 5, 15 and 20 years depending of type of rehabilitation method.

Alejandro Drive (St. Francis Road-End (north); Altamont Road (Black Mountain Road-Taaffe Road); Ascension Drive (St. Francis Road-End); Bryne Park Lane (Alternate 1) (Altamont Road-w. of 27269 Byrne Park Ln); De Bell Road (Manuella Road-Estacada Drive); Deer Springs Way (Alternate 1) (Bryne Park Lane-1st Bulb); Edgerton Road (Black Mountain Road-end); El Monte Road (Moody Road-Fork at 950' West of Stonebrook Drive); Emerald Hill Lane (Prospect Avenue-End); Fremont Road (St. Francis Road-Concepcion Road); Julietta Lane (s. of 27340 Julietta Ln-End); La Cresta Court (La Cresta Drive-End); La Loma Court (Alternate 1) (La Loma Drive-End); La Loma Drive (Alternate 1) (Prospect Avenue-Summit Wood Road); Natoma Road (Elena Road-Black Mt. Road); O'Keefe Lane (350' West of Vista Serena-End); Page Mill Road (Baleri Ranch Road-Country Way); Purissima Road (Concepcion Road-Robleda Road); Ravensbury Avenue (Magdalena Road-Crestridge Drive); Ravensbury Avenue (Hillpark Lane-End); Roble Veneno Lane (Concepcion Road-End); Seven Acres Lane (Fremont Road-End); Viscaino Place (Viscaino Road-End)

07/2018 11/2018 5 20 24 13

Los Altos Hills Santa Clara SafetyPage Mill Road / Moon Lane Pedestrian Bridge Project (On-Going)

Design and construction for a pedestrian bridge to alleviate the congestion and safety between motorists and pedestrians.

Northbound of Page Mill Road, crossing the Matadero Creek between Paseo Del Roble and Moon Lane. 06/2018 06/2018 20 50 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 100: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Los Altos Hills Santa Clara Complete Streets Components

Summerhill Pathway Project (Design)

This project is to construct a pathway connecting Summerhill Avenue between El Monte Road and Nicole Lane to City of Los Altos. The pathway connection will improve pedestrian safety from high traffic speeds due to Summerhill Avenue being used as an alternate arterial road. This project is DESIGN only. Actual construction will be budgeted and scheduled beyond FY 2019-20

Summerhill Ave at Los Altos Hills side 07/2018 06/2019 20 30 24 13

Los Altos Hills Santa Clara Road Maintenance & Rehabilitation

Streets Operations and Maintenance Budget

This budget will support the necessary work on Various street repairs and maintenance throughout town on as needed basis

This streets operation and maintenance will cover town-wide public streets (total 216 streets) in general, the approximate boundary streets are listed below: Page Mill Road - Arastradero Road - Foothill Expressway - Edith Ave - Fremont Road - O'Keefe Ln - El Monte Road - Summerhill Avenue - Magdalena Avenue - Eastbrook Avenue - W Loyola Drive - Stone Brook Drive - Moody Road Then back on Page Mill Road.

07/2018 06/2019 5 10 24 13

Los Altos Hills Santa Clara Road Maintenance & Rehabilitation

Storm Drain Operating and Maintenance Budget

This budget will support the necessary work on various storm drain (public streets road side and a few facilities) cleaning and maintenance repairs throughout town on as needed basis

The storm drain operation, repair, annd maintenance will cover town-wide storm drainage on public streets (total 216 streets) and facilities, the approximate boundary streets are listed below: Page Mill Road - Arastradero Road - Foothill Expressway - Edith Ave - Fremont Road - O'Keefe Ln - El Monte Road - Summerhill Avenue - Magdalena Avenue - Eastbrook Avenue - W Loyola Drive - Stone Brook Drive - Moody Road Then back on Page Mill Road.

07/2018 06/2019 10 15 24 13

Los Altos Hills Santa Clara Complete Streets Components

Pathways Operating and Maintenance Budget

This budget will support the necessary work on various street side pathway maintenance throughout town on as needed basis for drainage and safety purposes

The pathways operation, repair, and maintenance will cover town-wide pathways along public streets (total 216 streets) in general, the approximate boundary streets are listed below: Page Mill Road - Arastradero Road - Foothill Expressway - Edith Ave - Fremont Road - O'Keefe Ln - El Monte Road - Summerhill Avenue - Magdalena Avenue - Eastbrook Avenue - W Loyola Drive - Stone Brook Drive - Moody Road Then back on Page Mill Road.

07/2018 06/2019 5 10 24 13

Los Gatos Santa Clara Road Maintenance & Rehabilitation Street Repair & Resurfacing (2019) Placement of rubber cape seal or overlay to maintain pavement surface. National Avenue from Samaritan Drive to Los Gatos-Almaden Road 04/2019 10/2019 10 25 28 15

Los Gatos Santa Clara Road Maintenance & Rehabilitation Street Repair & Resurfacing (2020) Placement of rubber cape seal or overlay to maintain pavement surface. Knowles Drive from Dardanelli Lane to Dell Avenue. 04/2020 10/2020 10 25 28 15

Los Gatos Santa Clara Road Maintenance & Rehabilitation Street Repair & Resurfacing (2021) Placement of rubber cape seal or overlay to maintain pavement surface. Union Avenue from Blossom Hill Road to Los Gatos-Almaden Road 04/2021 10/2021 10 25 28 15

Los Gatos Santa Clara Road Maintenance & Rehabilitation Street Repair & Resurfacing (2022) Placement of rubber cape seal or overlay to maintain pavement surface. Quito Road from Bicknell Road to Woodbank Way. 04/2022 10/2022 10 25 28 15

Milpitas Santa Clara Road Maintenance & Rehabilitation Street Resurfacing Project 2019

Roadway pavement repair including pavement maintenance treatments, AC overlay and reconstruction. Additionally, the project includes replacement and upgrade of curb, gutter, driveway, sidewalk, signage, striping, installation of ADA ramps, and implementation of bike facilities per the 2009 Bikeway Master Plan.

Roadway rehabilitation of McCarthy Boulevard from northern city limit to Tasman Drive, Murphy Ranch Road, Sandisk Drive, and Technology Drive in City of Milipitas 03/2019 09/2019 10 15 25 10

Milpitas Santa Clara Road Maintenance & Rehabilitation

2018 Street Resurfacing Project 17/18 Ongoing

Maintenance seal treatment, overlay, and/or reconstruction of city streets, construction of ADA curb ramps, and implementation of bike facility per city's bikeway masterplan

Project streets will be bounded by Milpitas Boulevard, I680, Jacklin Road, and Yosemite Drive. Specific streets and maintenance treatment to be incorporated into the project will be determined by pavement survey report to be completed by Dec. 2017.

12/2018 12/2018 5 15 25 10

Monte Sereno Santa Clara Road Maintenance & Rehabilitation Oak Noll Resurfacing Project Rehabilitating Oak Noll Drive Oak Noll is located off of Daves Aves between Kirkorian and and Kavin Ln. The Road ends on Daves

Ave. 06/2018 08/2018 3 7 28 15

Monte Sereno Santa Clara Road Maintenance & Rehabilitation Bruce Avenue Rehabilitation of Bruce Ave . The treatment will be contingent on the coring/further

research results. Bruce Ave beginning at San Benito Way and ending Poppy Lane 05/2019 06/2019 12 15 28 15

Morgan Hill Santa Clara Road Maintenance & Rehabilitation Pavement Resurfacing Project Remove and replace of failed pavement sections, a 2" asphalt concrete overlay and the

restriping of existing bike lanes, legends, crosswalks and lane lines.Monterey Road between Cochrane Road and Tilton Avenue; East Dune Avenue between Hill Road and Thomas Grade 04/2019 07/2019 5 10 29, 30 17

Morgan Hill Santa Clara Road Maintenance & Rehabilitation

Rehabilitation of Sutter Boulevard 17/18 Carryover

The removal and replacement of failed pavement sections, a 2” asphalt concrete overlay and the restriping of existing bike lanes, legends, crosswalks and lane lines. Sutter Boulevard between the intersections of Cochrane Road to Serene Drive 05/2018 07/2018 5 10 29, 30 17

Mountain View Santa Clara Road Maintenance & Rehabilitation

Streets Resurfacing and Slurry Seal Program

Install asphalt concrete and fog seal overlays, raise utilities and monuments, raise low median island where needed to standard, or apply slurry seal to selected street surfaces.

Resurfacing Project Locations:California Street from Castro Street to South Shoreline Boulevard; Velarde Street from Bush Street to Anza Street; North Shoreline Boulevard from Gatehouse to Kite Flying Area Slurry Seal or Microsurfacing Project Locations:Hollingsworth Drive from El Monte Avenue to East End; Kathy Way from Hollingsworth Drive to Lloyd Way; Melba Court from Kathy Way to East End; Dell Avenue from Alvin Street to West End; Doverton Square from Levin Avenue to Levin Avenue; Katrina Way from Levin Avenue to Fairbrook Drive; Pamela Drive from Phyllis Avenue to Bay Street; Bay Street from Pamela Drive to El Camino Real; Tulane Drive from Fordham Way to Columbia Drive; Columbia Drive from Tulane Drive to Sladky Avenue

07/2019 10/2020 8 10 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 101: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Mountain View Santa Clara Road Maintenance & Rehabilitation

17/18 Carryover Project: Street Resurfacing and Slurry Seal Program

Install asphalt concrete and fog seal overlays, raise utilities and monuments, or apply slurry seal to selected street surfaces

Project Location: Aitken Avenue from Solana to West End - OK Gretel Lane from Cuesta Drive to Hans Avenue - OK Nilda Avenue from Cuesta Drive to Hans Avenue - OK Garden Terrace/Woodleaf Way from (entire circle) Sleeper to Sleeper - OK Pioneer Way from Evelyn Avenue to South End - OK Bernardo Avenue from North End to Central Expressway – Deleted from list due to conflict with other project Ehrhorn Avenue from Church to El Camino Real – Deleted from list due to conflict with other project High School Way from Shoreline to Castro – Changed limit Jessie Lane from Paul to Calderon - OK Miller Avenue from San Antonio to Del Medio – Deleted from list due to conflict with other project San Pierre Way from Middlefield to Montecito - OK Sun-Mor Avenue from ‘Beginning of Improvement’ to Levin - OK Limetree Lane from Rose Avenue to Spencer Ct - OK Orangetree Lane from Rose to Sunnyvale City Limit - OK Peachtree Court from Walnut to end – Deleted from list due to conflict with other project Bernardo Avenue from Middlefield to Central Expressway Gladys Avenue from Easy Street to Whisman - OK Plymouth Street from Rengstorff to Amherst Way – Deleted from list due to conflict with other project Fordham Way from Orangetree to Limetree – Added to the list

06/2018 09/2018 8 10 24 13

Palo Alto Santa Clara Complete Streets Components

Charleston-Arastradero Corridor Project (Phase 3)

This project will install enhanced bicycle and pedestrian improvements, 42,000 square feet of landscaped median and bio-retention areas, bulb-outs, traffic signal modifications and installation of a new traffic signal and new rubberized pavement.

Arastradero Road from Coulombe Drive to El Camino Real and Charleston Road from El Camino Real to Alma Street and Middlefield Road to San Antonio Road (map included in the uploaded staff report). 07/2018 05/2020 25 35 24 13

Palo Alto Santa Clara Road Maintenance & Rehabilitation

17/18 Carryover Projects (FY 2018 Asphalt Paving Project)

The FY 2018 Asphalt Paving Project includes the replacment of broken sidewalks, driveways, damaged PCC slabs, and uplifted curb and gutter; installation of valley gutters and curb ramps; resurfacing of asphalt pavement and installation of new signage and striping.

Alma Street (Palo Alto Ave to Melville Ave); Barron Avenue (Laguna Ave. to Josina Ave); Guinda Street (Melville Ave to Addison Ave); Hale Street (Palo Alto Ave to University Ave); La Calle Court (Barron Ave to End, North/South); Lane 33 (Ruthven Ave to Cowper St); Bryant Street (Lincoln Ave to Kingsley Ave); Whitman Court (Bryant St to Waverley St); Kellogg Avenue (Alma St to Middlefield Rd); Quarry Road (El Camino Real to Arboretum Rd)

05/2018 11/2018 25 30 24 13

San Jose Santa Clara Road Maintenance & Rehabilitation

2019 MAJOR STREET SEALING PROJECT

This project will install microsurfacing sealant over streets that may have received spot "remove and replace" repairs.

10th Street (Between Highway 101 and Keyes Street); 11th Street (Between East Hedding Street and Keyes Street); Adrian Way (Between Ocala Avenue and Story Road); Almaden Boulevard (Between Santa Clara Street and Balbach Street); Coleman Road (Between Almaden Expressway and Santa Teresa Boulevard); De Anza Boulevard (Between Bollinger Road and Highway 85); East Empire Street (Between North 1st Street and North 22nd Street); Flint Avenue (Between Marten Avenue and Guluzzo Drive); Leigh Avenue (Between Moorpark Avenue and Hamilton Avenue); Lucretia Avenue (Between Story Road and Phelan Avenue); Murphy Avenue (Between Oakland Road and Lundy Avenue); San Antonio Street (Between 28th Street and Jackson Avenue)

05/2019 10/2019 5 7 25, 27, 28, 29 10, 15

San Jose Santa Clara Road Maintenance & Rehabilitation

2019 MAJOR STREET RESURFACING PROJECT

This project aims to resurface and rehabilitate the following section of road within the City of San Jose. The project will include work such as Cold In-Place Recycling (CIR), placing pavement fabric, applying a rubberized hot mix asphalt overlay, replacing traffic striping and markings, adding new/enhanced bike lanes, and installing bicycle detector loops.

Allen Avenue (Between Santa Teresa Boulevard and Steinbeck Drive) Beswick Drive (Between Blossom Hill Road and Cottle Road) Cypress Avenue (Between Moorpark Avenue and Williams Road) Echo Valley Drive (Between Hillcrest Drive and Glenview Drive) Flint Avenue (Between Guluzzo Drive and Norwood Avenue ) Koch Lane (Between Plummer Avenue and Almaden Road) Leigh Avenue (Between City limit and San Carlos Street) Leigh Avenue (Between Parkmoor Avenue and Scott Street) McKee Road (Between Highway 101 and King road) Phelps Avenue (Between Williams Road and City limit) Plummer Avenue (Between Foxworthy Avenue and Curtner Avenue) Prospect Road (Between Johnson Avenue and South De Anza Boulevard) East San Antonio Street (Between South 17th Street and 28th Street) San Jose Avenue (Between Monterey Road and Almaden Expressway) Story Road (Clayton Road and Fleming Avenue) East William Street (Between North 1st Street and 16th Street)

05/2019 10/2019 15 20 27, 28, 29 15, 17

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 102: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

San Jose Santa Clara Road Maintenance & Rehabilitation

2018 MAJOR STREET RESURFACING PROJECT (17/18 Ongoing)

This project aims to resurface and rehabilitate the following section of road within the City of San Jose. The project will include work such as Cold In-Place Recycling (CIR), placing pavement fabric, applying a rubberized hot mix asphalt overlay, replacing traffic striping and markings, adding new/enhanced bike lanes, and installing bicycle detector loops.

16th St (Between San Carlos St and Margaret St) 17th St (Between Santa Clara St and San Carlos St) Bird Ave (Between San Carlos St and Willow St) Payne Ave (Between Saratoga Ave and City Limit) Samaritan Dr (Between Bascom Ave and Union Ave) Willow St (Between Lincoln Av and 1360's Meridian Ave) Blaney Ave (Between Prospect Rd and Bollinger Rd) Canoas Garden Av (Between Almaden Rd and Almaden Ex) Mckean Rd (Between Almaden Rd and Mckean Ct) Mckean Rd (Between Harry Rd and City Limit) Mckean Rd (Between Bailey Ave and S City Limit) Mckee Rd (Between White Rd and Valley View Ave) Norwood Av (Between White Rd and Gurdwara Ave) Plumeria Dr (Between 1st St and Montague Ex) Ringwood Av (Between Trade Zone Bl and Birchmeadow Ln) San Salvador St (Between Market St and 10th St) Viola St (Between S Market St and Almaden Ave) Yerba Buena Rd (Between Silver Creek Rd and Deans Place Way)

05/2018 11/2018 15 20 28 15

Santa Clara Santa Clara Road Maintenance & Rehabilitation

Annual Street Maintenance and Rehabilitation Program Project

Pavement maintenance and rehabilitation for the existing street. The work includes treating the pavement with asphalt concrete, slurry seal, or cape seal. Ancillary work may include removal and replacement of failed pavement areas, and reconstruction of curbs, gutters, sidewalks, ADA curb ramps, traffic striping, markings, roadway legends and traffic detection loops as needed.

•De La Cruz Blvd. (Greenwood Dr. to Aldo Ave.) [DELCRZ 000002]; •De La Cruz Blvd. (Aldo Ave. to Laurelwood Rd.) [DELCRZ 000003]; •De La Cruz Blvd. (Laurelwood Rd. to Trimble Rd.) [DELCRZ 000004]; •De La Cruz Blvd. (Central Expwy. to 816 FT N of Martin Ave) [DELCRZ 000005]; •De La Cruz Blvd. (Martin Ave. to Reed St.) [DELCRZ 000006]; •De La Cruz Blvd. ((A) Coleman Ave. to Merge (De La Cruz NB Off-Ramp)) [DELCRZ 000007]; •De La Cruz Blvd. ((A) Merge (De La Cruz NB Off- Ramp) to Reed St.) [DELCRZ 000009]; •De La Cruz Blvd. ((B) Reed St. to Fork (De La Cruz SB On-Ramp)) [DELCRZ 000010]; •De La Cruz Blvd. ((D) Coleman Ave. to Merge (De La Cruz SB On-Ramp)) [DELCRZ 000012]; •De La Cruz Blvd. (816 FT N of Martin Ave to Martin Ave) [DELCRZ 000014]; •De La Cruz Blvd. ((C) Fork (El Camino Off-Ramp) to El Camino Real) [DELCRZ 000016]; •De La Cruz Blvd. ((F) Fork (El Camino Off-Ramp) to Lewis St.) [DELCRZ 000017]; •De La Cruz Blvd. ((B) Fork (De La Cruz Sb On-Ramp) to Coleman Ave.) [DELCRZ 000018]; •De La Cruz Blvd. ((E) El Camino Real to Merge (El Camino On- Ramp)) [DELCRZ 000019]; •De La Cruz Blvd. ((E) Fork (Coleman Off-Ramp) to Coleman Ave.) [DELCRZ 000020]; •De La Cruz Blvd. ((F) Merge (El Camino On- Ramp) to Fork (Coleman Off-Ramp)) [DELCRZ 000021];

04/2019 12/2019 3 20 25 10

Saratoga Santa Clara Road Maintenance & Rehabilitation

Annual Roadway Improvements 2018-2019

Pavement maintenance project to rehabilitate city roadways to improve PCI and safety. AC overlay, Repair Failed Street Sections, micro-surfacing , traffic loops, curb and gutter, ADA ramps and re-striping traffic lanes.

City wide various streets. All locations are projected and subject to change based on the City's annualneed and resources.

Street From To BOYCE LN CALLE MONTALVOCHESTER AVE FARWELL AVE MONTALVO RD MONTALVO RD MONTAUK CT MONTAUK DR MT EDEN RD OKANOGAN CT OKANOGAN DR PARK DR PARK DR PIERCE RD PRUNE BLOSSOM PURDUE DR TAMWORTH AVE TAOS DR TONI ANN PL VERDE CT VERDE VISTA LN WOODWARD CT WOOD DELL CT

VERDE VISTA LN END MONTALVO RD END VIA TESORO CT 14331 CHESTER AVE SARA-LG RD WILD OAK WAY SARATOGA-LG RD HILL AVE HILL AVE 76' N of HILL AVE MONTAUK DR END FRUITVALE AVE TAOS DR GARROD CITY LIMITS OKANOGAN DR END MONTAUK DR TAOS DR SARATOGA-LG RD HUME DR HUME DR PEPPER LN VINTAGE LN MASSON CT VERDE VISTA LN END BAYLOR AVE VILLA NOVA RD VERDE VISTA LN SEATON AVE MONTAUK DR OKANOGAN DR ERDE VISTA LN END VERDE VISTA LN END SARA-SUNNY RD SARAHILLS DR TAMWORTH AVE END SARATOGA AVE END

09/2018 06/2019 10 15 27 15

Sunnyvale Santa Clara Road Maintenance & Rehabilitation

ST 18-10 Slurry Seal of Arterial Streets 2019B Type 3 Slurry Seal

Tasman Dr - Fair Oaks e/s to Vienna; Tasman Dr - Vienna to Lawrence Expwy; Tasman Dr - Lawrence expwy e/s to Birchwood; Tasman Dr - Birchwood to Adobe Wells; Tasman Dr - Adobe Wells to Reamwood; Tasman Dr - Reamwood to w/side channel; Wolfe Rd - Evelyn to reed/OSFR; Wolfe Rd - Reed/OSFR to Iris; Wolfe Rd - Iris to Gary; Wolfe Rd - Gary to Maria; Wolfe Rd - Maria to El Camino Real; Java Ave. - Mathilda to Bordeaux; Java Ave. - Bordeaux to Borregas; Java Ave. - Borregas to Geneva; Java Ave. - Geneva to Crossman; Java Ave. - Crossman to 237 overpass

01/2019 08/2019 7 10 24 13

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 103: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Sunnyvale Santa Clara Road Maintenance & Rehabilitation

ST 18-10 Pavement Overlay of City Streets Pavement Overlay

Noranda Dr - Homestead to west end; Mango Dr - Heathersone s/s to Knickerbocker n/s; Britton Ave. - Wolfe to Taylor; Taylor Ave. - Fair Oaks e/s to Britton; Old San Francisco Road (OSFR) Fair Oaks e/s to Gail; OSFR - Gail to Wolfe w/s; Murphy - Olive s/s to El Camino Real n/s of island; Murphy - Iowa s/s to Olive n/s

01/2019 12/2019 10 15 24 13

Capitola Santa Cruz Road Maintenance & Rehabilitation

42nd Avenue Pavement Rehabilitation

Pavement rehabilitation of 42nd Avenue from Jade Street to Capitola Avenue, Diamond Avenue from 42nd Avenue to 45th Avenue and Ruby Court.

42nd Avenue from Jade Street to Capitola Road, Diamond Avenue from 42nd Avenue to 45th Avenue and Ruby Court. 04/2018 12/2019 15 25 29 17

Santa Cruz Santa Cruz Other Catch Basin Replacement Citywide Upgrade old catch basins within the city street system to reduce flooding and improve road user safety.

There are 1,452 catch basins within the city limits, of which 755 are older Type A catch basins that require replacement. 09/2018 11/2018 30 50 29 17

Santa Cruz Santa Cruz Other Corrugated Metal Pipe (CMP) Replacement Citywide

Replace deteriorated CMP storm drains within the city street system to reduce flooding, street caveins and improve road user safety. There are 54 miles of storm drains and approximately 10% are CMP.

There are 54 miles of storm drains within the City and approximately 10% are CMP. 09/2018 11/2018 30 50 29 17

Santa Cruz Santa Cruz Road Maintenance & Rehabilitation

Arterial and Collector Street Reconstruction (17/18 Carryover)

Replace sidewalks and access ramps to meet current standards concurrent with reconstructing Arterial and Collector streets. Cedar Street from Laurel to Lincoln 05/2018 11/2018 15 20 29 17

Santa Cruz Santa Cruz Complete Streets Components Riverside Avenue Streetscape

Reconstruct Riverside Avenue between Beach Street and Third Street in the City's popular main beach area in conjunction with a Rule 20A utility undergrounding project. Projects includes new sidewalks, streetlights, paving, bike lanes, crosswalks and the removal of a stop controlled intersection.

Riverside Ave, between Beach and Third. 09/2018 06/2019 15 50 29 17

Santa Cruz Santa Cruz Road Maintenance & Rehabilitation

Arterial and Collector Street Reconstruction

Reconstruct portions of River Street and Water Streets, both arterial streets near Downtown Santa Cruz. Projects includes new access ramps,CIR paving, green bike lanes, and crosswalks.

River Street, between Water and Highway and Water Street, between Branciforte and Pacific. 07/2018 06/2019 15 20 29 17

Santa Cruz Santa Cruz Road Maintenance & Rehabilitation Storm Damage (17/18 Carryover) Local match funding for FEMA and OES eligible federal storm damage restoration

projects on the City street and multi-use path system.Upper Park Road north of DelaVeaga Rd, West Cliff Drive at San Jose, East Cliff Drive at 3rd Ave, Ocean at Plymouth, Parkway north of Allerton. 05/2018 06/2019 30 50 29 17

Scotts Valley Santa Cruz Road Maintenance & Rehabilitation

Pavement Rehabilitation on Green Hills Road

This project will rehabilitate Green Hills Road from Glen Canyon Road to its terminus. The project will include bike lanes, road widening, new curb and gutter, restriping on Glen Canyon Road from Vern Hart Fish Park to Green Hills Road. The project will also include signage and sharrows on South Navarra Drive from Green Hills Road to Grant Creek Road.

Green Hills Road from Glen Canyon Road to its terminus, Glen Canyon Road from Vern Hart Fish Park to Green Hills Road, South Navarra Drive from Green Hills Road to Grant Creek Road 04/2018 08/2018 15 20 29 17

Scotts Valley Santa Cruz Road Maintenance & Rehabilitation

Annual Street Maintenance/Resurfacing Program

This project is an annual street overlay program that includes the resurfacing of various city-maintained streets on a rotating basis. Maintenance in FY 18/19 will consist of HMA overlays.

Blue Hills Court, Green Tree Way, Kentwood Court, Pinecone Lane, Purple Hills Court, Sageland Court, Taryn Court, Granite Creek Road, Nadia Court, Scotts Valley Drive, Lock hart Gulch Road 08/2018 06/2019 10 15 29 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation Airport Blvd Reconstruction PH2

Reconstruct roadway and bike lanes, install new sidewalk, upgrade curb ramps and driveway crossings, install median island, modify traffic signals to include additional pedestrian crossing and install flashing beacon at Holm Rd.

Airport Blvd from Westgate Dr/Larkin Valley Rd to Hangar Way 06/2018 09/2019 20 20 30 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation

Airport Blvd Pavement Reconstruction Reconstruct roadway due to failed pavement Airport Blvd from Freedom Blvd to 600 feet west 06/2019 09/2020 20 20 30 17

Watsonville Santa Cruz Traffic Control Devices Citywide Signal Upgrade - HSIP Upgrade traffic signals and pedestrian crossing facilities

Intersections of Rodriguez St & West Beach St, Rodriguez St & West Lake Ave, Freedom Blvd & Brennan St, Freedom Blvd & Alta Vista Ave, Freedom Blvd & Clifford Ave, Freedom Blvd & Davis Ave, Freedom Blvd & Green Valley Rd, Airport Blvd & Loma Prieta Ave, Airport Blvd & Hanger Way, Airport Blvd & Nielson St, Airport Blvd & Westgate Dr, Airport Blvd & Freedom Blvd, Green Valley Rd & Harkins Slough Rd, Green Valley Rd & Quiet Meadow Dr, Green Valley Rd & Kralj Dr, Green Valley Rd & Lawrence Ave, Green Valley Rd & Loma Prieta Ave/Pennsylvania Dr, Green Valley Rd & Carnation Dr, Green Valley Rd & Home Depot Driveway, Ohlone Parkway & Harkins Slough Rd

07/2018 07/2019 10 10 30 17

Watsonville Santa Cruz Complete Streets Components Downtown Revitalization

Provide complete streets improvements including but not limited to pedestrian facilities, bus stops, parking, bicycle facilities and traffic management. Includes design, environmental documentation and construction.

Main St from Freedom Blvd to Riverside Dr and Rodriguez St from Main St to Riverside Dr 06/2019 07/2020 20 20 30 17

Watsonville Santa Cruz Complete Streets Components Lincoln St Safety Improvements Pedestrian crossing enhancements that incorporate bulbouts, landscaping, lighting,

decorative pedestrian scale fencing, crosswalks, sidewalks and pedestrian amenities. Lincoln St from East Beach St to Riverside Dr 06/2019 03/2020 20 20 30 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation Maintain Road Pavement sealing

Blackburn St from East Lake Ave to East Beach St, Green Valley Rd from Harkins Slough Rd to Home Depot Entrance, Ohlone Parkway from railroad tracks to Main St, Longview Dr from Progress Ave to Pennsylvania Dr and Elm St Marchant St to Lincoln St.

07/2018 07/2019 8 8 30 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation Airport Blvd Improvements

Rehabilitate roadway and bikelanes, widen to accommodate extension of bicycle lanes and portion of travel lane, install bus pull out, new sidewalks and curb ramps, refuge island, flashing beacon and striping.

Airport Blvd from Freedom Blvd to City Limits 02/2018 06/2019 20 20 30 17

Watsonville Santa Cruz Other Citywide Bicycle Facilities Provide signage and traffic markings along bicycle corridors and provide educational programs

Bridge St from Beck St to East Lake Ave, Green Valley Road from Harkins Slough Rd to city limits, Harkins Slough Rd/Walker St from Green Valley Rd to Riverside Dr, Pennsylvania Dr from Green Valley Rd to Main St, Rodriguez St from Riverside Dr to Main St, West Beach from Lee Rd to Rodriguez St

07/2018 06/2019 10 10 30 17

Watsonville Santa Cruz Complete Streets Components Citywide Curb Ramp Program Replacement and/or installation of curb ramps and street crossings to comply with

current ADA standards

490 Auto Center Dr, 500 Auto Center Dr, 580 Auto Center Dr, Union St & Maple Ave, Peck St & Union St, Elm St & Union St, 65 Nielson St, Central Ave & Main St, Herman Ave, field approach opposite 173 Herman Ave, Roosevelt St & Herrick Ct, Roosevelt St & Cullumber Ct

07/2018 06/2019 20 20 30 17

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 104: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Watsonville Santa Cruz Traffic Control Devices Citywide Signs, Markings & Striping Remove, replace and/or upgrade existing roadway signs, markings and striping

Arthur Rd from Mariposa Ave to Freedom Blvd, Blackburn St from East Lake Ave to East Beach St, Elm St from Marchant St to Lincoln St, Green Valley Rd from Harkins Slough Rd to the Home Depot driveway, Longview Dr from Progress Ave to Pennsylvania Dr, Ohlone Parkway from the railroad tracks to Main St, West Beach St from Ohlone Parkway to west City limits, West Beach St from Walker St to Industrial Rd and the alley between Stanford St & East High St and parallel to Lincoln St & Jefferson St. The intersections of Central Ave & Main St, Elm St & Union St, Peck St & Union St, Roosevelt St & Herrick Ct, Roosevelt St & Cullumber Ct and Union St & Maple Ave.

07/2018 06/2019 10 10 30 17

Watsonville Santa Cruz Other Maintain Trails Maintain and enhance existing pedestrian and bicycle trails All or portions of Bay Breeze, Fed Ex, Stone Creek, Struve Slough, Upper Struve Slough and Watsonville Slough trails 07/2018 06/2019 10 10 30 17

Watsonville Santa Cruz Safety Pedestrian & Traffic Safety Educational/safety programs and installation of striping, markers, signage, flashing beacons, curb extensions, speed humps, etc. Roache Rd, Beach St near Harvest Dr, Harkins Slough Rd 07/2018 06/2019 15 15 30 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation Road Repair Repair roadway

Arthur Rd from Mariposa Ave to Freedom Blvd, West Beach St from Ohlone Parkway to west City limits, West Beach St from Walker St to Industrial Rd, alley between Stanford St & East High St and parallel to Lincoln St & Jefferson St

07/2018 06/2019 10 10 30 17

Watsonville Santa Cruz Traffic Control Devices Signals and Lighting Replacement and Maintenance Replace, upgrade or maintain traffic signals and lighting

Intersections of Main St and Second St/Maple Ave, Rodriguez St and West Beach St, Rodriguez St and West Lake Ave, Freedom Blvd and Brennan St, Freedom Blvd & Martinelli St, Freedom Blvd and Crestview Dr, Freedom Blvd and Alta Vista Ave, Freedom Blvd and Clifford Ave, Freedom Blvd and Davis Ave, Freedom Blvd and Green Valley Rd, Airport Blvd and Loma Prieta Ave, Airport Blvd and Ross Ave, Airport Blvd and Hanger Way, Airport Blvd and Nielson St, Airport Blvd and Westgate Dr, Airport Blvd & Freedom Blvd, Green Valley Rd and Harkins Slough Rd, Green Valley Rd and Quiet Meadow Dr, Green Valley Rd and Kralj Dr, Green Valley Rd and Lawrence Ave, Green Valley Rd and Loma Prieta Ave/Pennsylvania Dr, Green Valley Rd and Carnation Dr, West Beach St and Lee Rd, Green Valley Rd and Home Depot driveway, Ohlone Parkway and Harkins Slough Rd

07/2018 06/2019 10 10 30 17

Watsonville Santa Cruz Road Maintenance & Rehabilitation Green Valley Rd Improvements Reconstruct roadway and bikelanes, replace asphalt pedestrian path with curb, gutter

and sidewalk and ADA compliant curb ramps, upgrade signage and loop detectors Green Valley Rd from Struve Slough to Freedom Blvd 06/2018 06/2019 20 20 30 17

Anderson Shasta Road Maintenance & Rehabilitation Cape Seal of North Street Cape seal North Street North Street from SR273 to Sacramento River Bridge 04/2019 05/2019 6 10 1 1

Anderson Shasta Road Maintenance & Rehabilitation

Anderson Heights Cape Seal Project Cape seal streets in Anderson Heights neighborhood Pinion, Larch, Lodgepole, Aspen, Spruce, Hemlock, and Jefferies Streets 04/2019 05/2019 10 20 1 1

Anderson Shasta Road Maintenance & Rehabilitation City Wide Grinder Dig-out Remove and replace sections of failing pavement. North Street between McMurray and Stringy and South Street between SR273 and Emily Drive 06/2018 07/2018 20 30 1 1

Redding Shasta Road Maintenance & Rehabilitation 2017-18 Cape/Slurry Seal Residential cape and slurry seal project

Addressing 6 Streets in slated project Quail Ridge, Edgewood Drive, Lancer, Arroyo Manor, Hacienda Heights, and Stetson. 03/2018 08/2018 5 12 1 1

Redding Shasta Safety Quartz Hill Road ATP Widening Project includes installation of bike lanes and sidewalks along Quartz Hill Road. Also the addition of enhanced pedestrian crossings with rapid flashing beacons. Quartz Hill Road from Market Street to just south of Terra Nova. 01/2018 08/2018 10 20 1 1

Redding Shasta Safety Bechelli Lane ATP Improvements Project includes a road diet, sidewalk gap closure, ADA curb ramps, buffered bike lanes and enhanced pedestrian crossings. Bechelli Lane from Cypress Avenue on the North to Riverview Country Club. 02/2019 05/2022 10 15 1 1

Redding Shasta Road Maintenance & Rehabilitation 2018-19 Cape/Slurry Seal Residential cape and slurry seal.

Servicing at minimum 7 streetsCanby Rd., Browning St.,Old Alturas Rd., Victor Ave., Woodside Meadows, Alfreda Way, Reservoir Ln., and various other streets. 04/2019 07/2019 5 12 1 1

Redding Shasta Safety Bonnyview Safe Routes to School Widen Bidwell Lane and North Bonnyview Road to add bicycle and pedestrian facilities including sidewalk and enhanced crosswalks to/from Bonnyview Elementary School. Bidwell Lane and North Bonnyview road to East Bonnyview Road. 01/2019 08/2019 15 30 1 1

Shasta Lake Shasta Road Maintenance & Rehabilitation

Cascade Boulevard Improvements 2018 (17/18 Carryover Project)

Project generally consists of grinding, paving fabric installation, HMA placement, and thermoplastic striping and marking on Cascade Boulevard between Shasta Dam Boulevard and Grand Coulee Boulevard.

Cascade Boulevard between Shasta Dam Boulevard and Grand Coulee Boulevard. 07/2018 10/2018 20 30 1 1

Shasta Lake Shasta Other Churn Creek Bridge Methacrylate Deck Seal (17/18 Carryover Project)

Project generally consists of preparation for and application of high-molecular-weight methacrylate resin and thermoplastic striping on the Churn Creek bridge deck on Pine Grove Avenue.

Pine Grove Ave @ Churn Creek 07/2018 10/2018 20 30 1 1

Shasta Lake Shasta Other Moody Creek Bridge Replacement Project (17/18 Carryover Project)

Project generally consists of completing the civil and structural engineering, environmental, right-of-way, and PSE work related to the rehabilitation and/or replacement of the Moody Creek Bridge on Cascade Boulevard. Construction of project will follow completion of design.

Cascade Boulevard @ Moody Creek 06/2022 12/2025 50 75 1 1

Loyalton Sierra Road Maintenance & Rehabilitation City of Loyatlon

Chip Seal and Slurry on all city streets New Stop Signs Fix pothole on city streets

Street Boundaries Include: Poole Ln, Beckwith Rd, White St, Jones St, Zollinger St, Meeker St, 1st St, 2nd St, 3rd St, 4th St, E 2nd St, W 3rd St, N 5th St, Church St, Court Ln, Pine St, Railroad Ave, School St, Front St, E Lewis St, Mill St, Taylor Ave, Granite Ave, Patterson Ave, Cemetery Rd, Hill St All locations have yet to be finalized and are subject to change. Each location will be selected based on priority need and resources throughout the year.

07/2018 07/2019 5 10 1 1

Loyalton Sierra Road Maintenance & Rehabilitation

Railroad and Lewis (17/18 Carryover) Fixing curbs and road repair for wash out.

Street Boundaries Include: Poole Ln, Beckwith Rd, White St, Jones St, Zollinger St, Meeker St, 1st St, 2nd St, 3rd St, 4th St, E 2nd St, W 3rd St, N 5th St, Church St, Court Ln, Pine St, Railroad Ave, School St, Front St, E Lewis St, Mill St, Taylor Ave, Granite Ave, Patterson Ave, Cemetery Rd, Hill St All locations have yet to be finalized and are subject to change. Each location will be selected based on priority need and resources throughout the year.

05/2018 06/2018 3 5 1 1

Dorris Siskiyou Road Maintenance & Rehabilitation

2018-19 Street Rehabilitation Project (17/18 Carryover) Rehabilitation & maintenance of local roadway E. Fourth Street from Pine to Center

Juniper St. from Hwy 97 to Hazen St. 08/2018 04/2018 20 30 1 1

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 105: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Dunsmuir Siskiyou Complete Streets Components 2018 Sidewalk Project Remove and replace sidewalks and construct ADA-compliant curb ramps on Dunsmuir

Avenue. Dunsmuir avenue near Cedar and Oak Streets. 05/2018 12/2018 25 25 1 1

Dunsmuir Siskiyou Road Maintenance & Rehabilitation Asphalt crack sealing Crack seal existing streets

Various streets in Dunsmuir as funds allow. From east to west, the streets would include from “Castle” to “Sacramento.” And from south to north, the streets would include from “Vernie” to “Linda Place.” This area includes approximately 40 streets. The Public Works Director has a list of streets with the highest priority need for crack fill projects - with streets Gray, Branstetter, and Fourth having the most need.

06/2019 06/2019 3 3 1 1

Etna Siskiyou Road Maintenance & Rehabilitation Main Street 2018 (Carryover 17/18) Main Street Road Repair Main Street 05/2018 08/2018 5 20 1 1

Etna Siskiyou Road Maintenance & Rehabilitation

City of Etna Street Repair Multiple Locations

Repaving street repair along 4 street locations in the city of Etna as identified in the location field. Main Street, Charles Street, Bryan Street, Cleveland Street 06/2018 08/2019 5 20 1 1

Montague Siskiyou Road Maintenance & Rehabilitation Crack Sealing (17/18 Carryover) Projects will consist of crack sealing the streets with specialized high quality materials

to prevent the intrusion of water and incompressible materials. City of Montague West Webb, S 13th, Buell, Prather, 5th St, N 6th and 9th St. 07/2018 06/2019 1 1 1 1

Mount Shasta Siskiyou Road Maintenance & Rehabilitation Citywide Street Maintenance Street resurfacing, repair, paving overlay, crack seal, and chip seal Pine St, Sheldon Ave, Merritt Ave, Perry Ave, Eugene Ave, Ida St, Gaudenzio Ave, Shasta Ct, Smith

St, South A St, and South B St. 07/2018 08/2018 5 10 1 1

Mount Shasta Siskiyou Traffic Control Devices Alma Street Traffic Signal Project (17/18 ongoing)

Remove existing traffic signals and install new traffic signals at the intersection of Alma Street and North Mt. Shasta Blvd. Construct new ADA compliant curb ramps at the four corners of the intersection.

The intersection of Alma Street and North Mt. Shasta Blvd. 03/2018 10/2018 25 50 1 1

Tulelake Siskiyou Road Maintenance & Rehabilitation

Annual Citywide Crack Sealing (Ongoing 2017/2018)

Crack sealing of streets citywide at the following locations:crack sealing of Main Street between F and G Streets, crack sealing of Second Street between E and F Streets, and crack sealing Second Street between Modoc and B Streets.

City of Tulelake- surface of Main and Second Streets 04/2018 06/2018 15 20 1 1

Tulelake Siskiyou Road Maintenance & Rehabilitation

Annual Citywide Crack Seal 2018-2019

Crack sealing of streets citywide of the following locations:crack sealing C Street between Fourth Street and the Water Yard, crack sealing B Street between Main Street and the end of B Street, and crack sealing Second Street between B Street and E Street.

City of Tulelake- surface area of C, B and Second Streets 07/2018 06/2019 5 10 1 1

Weed Siskiyou Road Maintenance & Rehabilitation Parks Street Rehab of failing asphault Park Street from Main St to Tebbe St. 06/2018 11/2018 10 20 1 1

Weed Siskiyou Road Maintenance & Rehabilitation

Vista Drive Rehab 17/18 Carryover Project 17/18 Carryover Project Rehabilitation and maintenance of a local roadway Vista Drive 06/2018 09/2018 10 20 1 1

Yreka Siskiyou Road Maintenance & Rehabilitation

City of Yreka Strategic Paving, Preventive and Planning Project (17/18 Ongoing)

Strategic chipsealing and other appropriate maintenance of approximately 15,000 LF of city streets.

Various streets in City of Yreka locations TBD; Greenhorn Road – Main Street to Greenhorn Park entranceS. Phillipe from Hwy. 3 to City Limits and Limestone, Quarry, Helwig, Juniper, and Deer Creek Way

06/2018 12/2018 5 15 1 1

Benicia Solano Road Maintenance & Rehabilitation Street Resurfacing 2019 Project Grind & overlay

Noyes Ct.; Bayshore Rd (East Channel Rd. to Industrial Way); East Channel Rd (Channel Rd to Bayshore Rd); Denfield Ave (Military West to 650ft north of Military West); West 2nd St (W-N St to Raymond Dr.); Harbor Vista Ct; West 5th (Military to W-J St); West 6th (Cove Way to W-K St); East 3rd (I780 to Hillcrest); Shirley Dr (Raymond Dr to Bridgeview Ct); West I St (W-6th to W-5th)

04/2019 06/2019 20 25 14 3

Dixon Solano Road Maintenance & Rehabilitation

2018 Pavement Rehabilitation Project (17/18 Ongoing) Slurry seal and replace striping on various streets within the City of Dixon.

Street segments include: East C Street from North First Street to Doyle Lane; North Second Street from East C Street to Creekside Circle; South Almond Street from West A Street to Porter Road; South Lincoln Street from West A Street to south city limits; and West F Street from Pitt School Road to North First Street.

06/2018 08/2017 7 10 4 3

Dixon Solano Road Maintenance & Rehabilitation

2019 Pavement Rehabilitation Project

Slurry seal, crack seal and asphalt dig-out repairs and replacement of traffic striping on various streets within the City of Dixon.

Street segments include: West A Street at I-80; Porter Road from West A Street to south city limits; West H Street from Pitt School Road to Evans Road; Evans Road from West H Street to West A Street; Pitt School Road from West A Street to Stratford Avenue; Ary Lane from Pitt School Road to Market Lane; Market Lane from UPRR tracks to First Street (SR113).

04/2019 06/2019 7 10 4 3

Fairfield Solano Road Maintenance & Rehabilitation PW Maintenance Crews Pot hole and spot repairs

Location is bounded by I-80, Hwy 12, southern City Limits, E. Tabor Ave, Walters Rd, Air Base Pkwy, Laurel Creek Cement Hill Road, Dover Ave and Manuel Campos Pkwy which contains approximately 481 roadways.

07/2020 11/2022 5 7 11 3

Fairfield Solano Road Maintenance & Rehabilitation Safe Routes to School E. Tabor Ave Safe Routes to School Gap Closure West of RR tracks to East of Olive Ave 07/2020 11/2022 10 15 11 3

Fairfield Solano Road Maintenance & Rehabilitation

Pavement Maintenance Project 2018 - Phase 2 Cordelia & Green Valley

Repaving approximately 1,807,444 square feet

Business Center Dr (City Limit to Green Valley Rd), Business Center Dr (Green Valley Rd to Suisun Valley Rd), Business Center Dr (Dan Wilson Creek to Suisun Valley Rd), Business Center Dr (Suisun Parkway to Dan Wilson Creek), Central Way (Pittman Rd to City Limits), Central Place (Pittman Rd to End), Pittman Rd (Cordelia Rd to 1000' North of Redwood Meadows Ln), Pittman Rd (1000' North of Redwood Meadows Ln to Link Rd), Pittman Rd (Link Rd to Central Way), Pittman Rd (Central Way to I-80), Cordelia Rd (Monument to Link Rd), Cordelia Rd (Link Rd to City Limits), Suisun Valley Rd (Neitzel Rd to Mangels Blvd), Suisun Valley Rd (Mangels Blvd to City Limits)

08/2018 11/2018 5 16 11 3

Fairfield Solano Road Maintenance & Rehabilitation

Pavement Maintenance Project 2019 Repaving approximately 1,299,986 square feet

Chadbourne Rd (Highway 12 to Cordelia Rd), Beck Ave (Highway 12 to Cordelia Rd), Courage Dr (Chadbourne Rd to Beck Ave), Cordelia Rd (Ledgewood Creek to Beck Ave), Cordelia Rd (Beck Ave to Chadbourne Rd), Fulton Dr (Lopes Rd to Watt Dr), Fermi Dr (Watt Dr to Lopes Rd), Watt Dr (Fulton Dr to Redtop Rd)

07/2019 11/2019 7 16 11 3

Fairfield Solano Road Maintenance & Rehabilitation

Pavement Maintenance Project 2020-222 Repaving approximately 1,124,134 square feet

Cadenasso Dr (Beck Ave to Auto Mall Pkwy), North Texas Stt (Travis to Air Base Parkway), Huntington Dr (Peabody Rd to End), Capitola Way (Woodcreek Dr to Waterman Blvd), Air Base Parkway (250' West of Heath Dr to Heath Dr), Air Base Parkway (Peabody Rd to Parker Rd), E. Tabor Ave (Claybank Rd to Manor Pl)

07/2020 11/2022 5 16 11 3

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 106: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rio Vista Solano Complete Streets Components

Front Street Bicycle and Pedestrian Improvement Project

Install new bicycle and pedestrian crossing, ADA curb ramps, lighted crosswalk, pavement and slurry seal, sidewalks, and new striping. Front Street and near Hwy. 12 off and on ramp to Front Street. 06/2018 06/2018 20 40 11 3

Suisun City Solano Road Maintenance & Rehabilitation Asphalt Concrete Overlay Project Asphalt Concrete Overlay project for various streets citywide.

Altus Lane, Amber Drive, Andrews Circle, Beechwood Circle (959 Beechwood to Ashwood Drive), Beale Cir, Breakwater Circle, Bridgewater Circle, Catalina Circle, Cinnamon Way, Civic Center (Lotz to Driftwood), Cordelia St (Kellogg to Park), Deercreek Way, Dickey Court, Dover Circle, Fennie Court, Filbert Court, Fort Ord Court, Gunter Drive, Hickam Circle, Honker Lane, Kessler Circle, Little Rock Circle, Maxwell Circle, McClellan Drive, McGuire Circle, Newark Lane, Pensacola Lane, Perkins Court, Peytonia Lane, Redbud Way, Rocky Point Cove, Savannah Lane, Silk Oak Court, Tamarisk Circle, Tea Rose Way, Tuscon Circle, Vandenberg Circle, Victory Way, Vinewood Court, Walnut Street (School to Kellogg), Walnut Street (Kellogg to Slough) and Wesley Ave (140' SO Chyrl to 120' N Chyrl).

05/2018 07/2019 40 50 11 3

Suisun City Solano Road Maintenance & Rehabilitation 17/18 18/19 Cape Seal Project Cape Seal/Slurry Seal on various streets citywide

Canary Court, Crested Drive (Pintail to 110' N of Whistler), Hacienda Lane (Fortuna to Montebello), Heron Drive (Blue Jay to 430' S of Blue Jay), Jeanne Court (Chyrl to end), Lemonwood Drive (Mosswood to Redondo), Michael Court (Marcia to end), Ricky Court (Marcia to end), Swallow Court (Swallow Lane to end), Stellar Way (Longspur to end of cul de sac), Westwind Way (Emperor to end), Westwind Lane (Westwind Lane to cul de sac), Whippor Will Way (Swallow to Skylark) and Yuba Court (Pelican to end).Locations from 17/18 carry over:Marston Court, Driftwood Drive 015, Hillborn Court, Spence Court, Brookside Court, Flagstone Cir, Hibiscus Lane, Keyes Court, McNabe Court, Birchwood Court, Bottlebrush Court, Camellia Court, Dawn Rose Court, Dawn Rose Way, Driftwood Drive, Kinsmill Court, Limewood Drive, McCoy Creek Court and Peytonia Court.

04/2018 09/2018 25 50 11 3

Vacaville Solano Road Maintenance & Rehabilitation Vacaville RHMA Overlay

RHMA Overlay:Dobbins Street from East Monte Vista Ave to Merchant Street; Mason Street from Cernon Street to Davis Street; Hickory Street from I-80 to Davis Street; Arcadia Street from Ulatis Dr to Woodstock Cir; Lawrence Drive from Orange Drive to end; Tulare Drive from Marshall Road to Brookdale; California Drive from Los Robles Ct to Alamo Lane; replace non-compliant curb ramps, striping improvements

Dobbins St, Mason St, Hickory St, Arcadia St, Lawrence Dr, Tulare Dr, California Dr 10/2018 10/2019 10 25 11 3

Vacaville Solano Road Maintenance & Rehabilitation

East Monte Vista/Gibson Canyon Road Cold In-Place Recycle

Grind, adjust utilities, cold in-place recycle, replace traffic detection, stripe and place 1.5" RHMA overlay on East Monte Vista Ave. from County Airport Road to Aviation Drive and Gibson Canyon Road from Ulatis Creek Bridge to Fruitvale Drive

East Monte Vista Avenue 05/2018 09/2018 10 25 11 3

Vallejo Solano Complete Streets Components

Citywide Curb Ramp and ADA Improvement Project

Installation of curb ramps throughout the City where they are absent. Removal of ADA non-compliant sidewalk tripping hazards throughout the City in partnership with the residents.

The following intersections are targeted for as far as the allocated funding allows:Jennings Ave at Steffan St; Steffan St at Steffan St; Steffan St at Buss Ave; Brookwood Ave at Cottonwood Dr; Thelma Ave at Concord St; Rinaldo Dr at Roleen Dr; David Ct at Roleen Dr; Alice Dr at Roleen Dr ; York St at Alameda St; York St at El Dorado St; York St at Sutter St; York St at Napa St; Aden St at Parrott St; Werden St at Parrott St; Benicia Rd at Central Ave; Lassen St at Clark Dr; Michigan St at El Dorado St; Mississippi St at Couch St; Carolina St at Sutter St; Carolina St at Alameda St

01/2018 08/2018 25 40 14 3

Vallejo Solano Road Maintenance & Rehabilitation Citywide Slurry Seal Project Slurry seal a number of streets throughout the City.

The following streets are target for slurry sealing for as far as the funding allows:BETTY COURT (JACK LONDON DRIVE to END); DONNER PASS ROAD ( W/O EBBETTS PASS RD to 50' E/O TOBIN DR); OLYMPIC DRIVE (QUARTZ LN to WHITNEY AVE); BASALT DRIVE (80' WEST OF ZIRCON to OLYMPIC DRIVE); COPPER WAY (BASALT DRIVE to QUARTZ LANE); PERSIMMON DRIVE (PHOENIX CIRCLE to PHOENIX CIRCLE); PLATT COURT (TUOLUMNE STREET to END); RIVERVIEW DRIVE (TUOLUMNE STREET to MITCHELL COURT); AMBER AVENUE (HOLLY STREET to POWER DRIVE); EDGEHILL COURT (WOODSIDE ROAD to END); HOSPITAL DRIVE (TUOLUMNE STREET to 236' E/O TUOLUMNE ST); VALLE VISTA AVENUE (NORTH OF WHITECLIFF DR to FAIRGROUNDS DRIVE)

04/2018 09/2018 6 15 14 3

Vallejo Solano Road Maintenance & Rehabilitation Street Overlay/Preservation Various City Streets will be repaved to improve the conditions and increase the life span

of the streets.

Wilshire Ave. (Alhambra Ave. to Pacheco Dr.); Saunders Dr. (Keats Dr. to Delwood St.); Delwood St. (Saunders Dr. to Georgia St.); Barcelona St. (Cordova St. to Devlin Dr.); Dillon Dr. (Elliott Dr. to Diana Dr.); Rome Dr. (Elliott Dr. to Diana Dr.); Lorenzo Dr. (Stephen Ct. to Elliott Dr.); Diana Dr. (Stephen Ct. to Mini Dr.); Benson Ave. (Rodgers St. to C St.); Scenic Way (Daniels Ave. to Benson Ave.); Mayo Ave. (Rice St. to Campbell Ave.); Thirteenth St. (South End to Madigan Ave.); Calaveras St. (Solano Ave. to Springs Rd.); Calaveras St. (Springs Rd. to Tennessee St.); Castlewood Dr. (Springs Rd. to Westwood St.); Florence Ct. (N Camio Alto to End); Valle Vista Ave. (Redwood St. to Whitecliff Dr.)

01/2019 06/2019 15 20 14 3

Vallejo Solano Road Maintenance & Rehabilitation

Pavement Rehabilitation Rollingwood Drive

The project consists of ADA curb ramp upgrade, portions of sidewalk replacement, and installation of sub drain including rehabilitation of asphalt pavement. The project extends for approximately 1800 linear feet from Pope Drive to Baywood Drive.

Rollingwood Drive between Baywood Drive and Pope Drive 04/2018 06/2019 15 20 14 3

Cloverdale Sonoma Road Maintenance & Rehabilitation

4th Street Reconstruction - 17/18 Carryover

Reconstruct 4th Street from North Jefferson Street (eastern boundary) to street end (western boundary) with new AC paving - 17/18 Carryover.

City of Cloverdale, 4th Street from North Jefferson Street (eastern boundary) to street end (western boundary). 06/2019 07/2019 15 20 2 2

Cloverdale Sonoma Complete Streets Components

Rockydale Lane Reconstruction - 17/18 Carryover Reconstruct Rockydale Lane to include accessibility features - 17/18 Carryover. City of Cloverdale, Rockydale Lane from Lake Street (northern boundary) to 5 feet south of northern

boundary of Parcel 001-111-033 08/2020 09/2020 15 20 2 2

Cotati Sonoma Road Maintenance & Rehabilitation

Lincoln Avenue Rehabilitation Project

Repairs 725 feet of Lincoln Avenue, full width, from the intersection with La Salle Avenue easterly to the City limits. Project rehabilitates Lincoln Avenue within the City of Cotati, Sonoma County. 07/2018 10/2018 8 10 10 3

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 107: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Healdsburg Sonoma Road Maintenance & Rehabilitation

Healdsburg 2018 Pavement Preservation and Rehabilitation Projects

Pavement preservation/rehabilitation by Cape Seal (asphalt rubber chip seal under Microsurfacing)

Almond Way: s/o S Fitch Mtn. Rd to end; Center Street: s/o Matheson St to n/o Mill St; East Street: s/o Matheson St to end; First Street: s/o Matheson St to s/o Mason St; Fitch Street: s/o Matheson St to w/o Harmon St; Front Street: s/o Mason St to n/o Healdsburg Ave; Haydon Street: e/o East St to w/o University St

08/2018 11/2018 5 7 2 2

Healdsburg Sonoma Road Maintenance & Rehabilitation

Healdsburg 2018 Pavement Preservation and Rehabilitation Projects (17/18 Carryover)

Pavement Preservation & maintenance with cape seal (17/18 carryover)

Albert Court: Lupine Rd to end (cul de sac) Alexandria Drive: Monte Vista (west) to Monte Vista (east) Ferrero Drive: Healdsburg Ave to Linda View Foss Creek Circle: Grove St (north) to Grove St (south) Foss street: North St to end Jachetta Court: Ridgeview to end (cul de sac) Jasmine Court: Ferrero to end (cul de sac) Langhart Drive/Court: Alexandria to end (cul de sac) Linda View Drive: Ferrero to end (cul de sac) Lupine Road/Court: March Ave to end (cul de sac) Moore Lane: West North to end (cul de sac) North Street: Grove to Healdsburg Ave Ridgeview Drive: Powell to end (cul de sac) Robinson Court: Langhart to end (cul de sac) Smith Court: Langhart to end (cul de sac) Theresa Court: Lupine to end (cul de sac) Vista Via Drive: Powell to end (cul de sac) West North Street: Grove St to end (cul de sac)

08/2018 11/2018 5 7 2 2

Petaluma Sonoma Road Maintenance & Rehabilitation Pavement Restoration 18/19

The project includes approximately 13,208 square yards of High Volume Slurry Seal and approximately 3,125 SY yards of 2" grind and overlay. The project will include asphalt dig outs, new curb ramps, sidewalk repair, striping and signage. On average high volume slurry seal will extend the useful life by 5 to 8 years and a 2" Grind and Overlay will extend the useful life 18 to 22 years

Allegheny Court (Yarberry Drive to End of Cul-de-sac) Almanor Street (Rainier Circle to Downing Street) Belle View Avenue (Hayes Avenue to End of Street) Bond Avenue (McDowell Blvd South to Sartori Drive) Brainerd Avenue (North Fair Street to North Fair Street) Cardinal Way (Noriel Lane to Hawk Drive) Caulfield Lane (Saint Francis Drive to Payran Street) Covey Way (McDowell Blvd South to Daniel Drive) Doris Way (Payran Street to End of Street) Dover Lane (Reisling Road to Lansdowne Way) Dublin Court (WindsTechnology Lane (Casa Grande Road to End of Cul-de-sac) Turtle Creek Way (Sonoma Mountain Parkway to Noriel Lane) Vanessa Way (Schuman Lane to Cindy Lane) Walnut Street (West Street to Oak Street) West Payran Street (Petaluma Blvd North to NWPRR Railroad Xing) West Payran Street (Graylawn Avenue to Petaluma River Bridge) Westminister Lane (Winchester Lane to Lansdowne Way) Winchester Lane (Lansdowne Way to Westminister Lane) Windmill Lane (Sleepy Hollow Lane to Castle Drive) Wood Lane (Ponderosa Drive to Gumwood Lane)

05/2019 10/2019 5 23 10 3

Petaluma Sonoma Road Maintenance & Rehabilitation Pavement Restoration 17/18

The project includes approximately 89200 square yards of High Volume Slurry Seal. The project will include asphalt dig outs and striping On average high volume slurry seal will extend the useful life by 5 to 8 years

B Street (Petaluma Blvd South to El Rose Drive); I Street (Petaluma Blvd South to City Limits); Grant Street (I Street to Mountain View Ave); Madison Street (Arlington Drive Lakeville Street); McKenzie Avenue (McDowell Blvd S. to Stuart Drive); Kresky Way (Stuart Drive to Lindberg Lane); Lindberg Way (Saint Francis Drive to McDowell Blvd S.); St. Francis Drive (Lindberg lane to Lombardi Avenue); S. McDowell Blvd Ext (Lakeville Hwy to Bridge)

07/2018 11/2018 5 8 10 3

Rohnert Park Sonoma Road Maintenance & Rehabilitation

2019-2022 Pavement Management (Crack Seals and Slurry Seals)

Pavement preservation treatments including crack seals and slurry seals. Crack sealing prevents the intrusion of water and incompressible material into the cracks and reinforces the adjacent pavement. Slurry seals further seal the cracks, restore lost flexibility to the pavement surface, provide a deep, rich black pavement surface color, protect the underlying pavement and provide a new driving surface.

Southwest Boulevard between Adrian Drive and Snyder Lane; Snyder Lane between Holly Avenue and Golf Course Drive; Golf Course Drive between SMART Railroad Tracks and Fairway Drive; Commerce Boulevard between Enterprise Drive and Golf Course Drive.

02/2019 08/2019 4 6 4 3

Rohnert Park Sonoma Road Maintenance & Rehabilitation

Southwest Boulevard Reconstruction

Reconstruction of Southwest Boulevard between No Name Street and College View Drive. Southwest Boulevard between No Name Street and College View Drive 03/2020 11/2020 24 30 4 3

Rohnert Park Sonoma Road Maintenance & Rehabilitation Southwest Boulevard Cape Seal

Pavement preservation treatments including small areas of pavement repair (i.e. "digouts") and cape seal application (i.e. a combination of chip seal and thin slurry seal) . Cape seals are used when the pavement deterioration is greater than what a slurry seal or microsurfacing is designed to correct, yet the pavement has not deteriorated to the point of requiring an expensive asphalt overlay. A cape seal prevents water penetration, reducing subsequent damage to the road bed, along with providing a new wearing surface.

Southwest Boulevard between Commerce Boulevard and No Name Street 03/2020 11/2020 6 10 4 3

Rohnert Park Sonoma Road Maintenance & Rehabilitation

Martin Avenue Rehabilitation (17/18 Ongoing) Pavement rehabilitation (full depth reclamation) Martin Avenue between Redwood Drive and Dowdell Avenue 05/2017 06/2018 20 30 4 3

Rohnert Park Sonoma SafetySouthwest and Commerce Boulevard Intersection Improvements (17/18 Carryover)

Improvement of traffic flow through this intersection which may include lane reconfiguration and installation of various traffic devices (e.g. roundabout, signage, and pavement markings)

Intersection of Southwest Boulevard and Commerce Boulevard 01/2018 11/2020 25 30 4 3

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 108: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Rohnert Park Sonoma Road Maintenance & Rehabilitation

2019-2022 Pavement Management (Cape Seal Project)

Pavement preservation treatments including small areas of pavement repair (i.e. "digouts") and cape seal application (i.e. a combination of chip seal and thin slurry seal) . Cape seals are used when the pavement deterioration is greater than what a slurry seal or microsurfacing is designed to correct, yet the pavement has not deteriorated to the point of requiring an expensive asphalt overlay. A cape seal prevents water penetration, reducing subsequent damage to the road bed, along with providing a new wearing surface.

Country Club Drive between Rohnert Park Expressway and Eleanor Avenue; Golf Course Drive between Country Club Drive and Hillview Way; Snyder Lane between Golf Course Drive and Moura Lane

08/2018 06/2019 6 10 4 3

Rohnert Park Sonoma Road Maintenance & Rehabilitation

2019-2022 Pavement Management (Asphalt Overlay)

Asphalt overlay, which is a new pavement section (generally 1.5″ – 2″ thick) placed over the top of an existing pavement surface.

Country Club Drive between Eleanor Avenue and Ellen Street; Southwest Boulevard between College View Drive and Adrian Drive 08/2018 06/2019 12 17 4 3

Rohnert Park Sonoma Traffic Control DevicesTraffic Signals System Needs Implementation Project (17/18 Carryover)

Implementation of a central traffic management system, including interconnect media, local intersection hardware, and central system software and hardware

Golf Course Drive, Redwood Drive, Rohnert Park Expressway, Commerce Boulevard, Snyder Lane, East Cotati Avenue 06/2018 06/2019 10 15 4 3

Santa Rosa Sonoma Road Maintenance & Rehabilitation

Fulton Road Reconstruction - Occidental Road to W 3rd Street (17/18 Carryover)

This project will reconstruct Fulton Road between Occidental Road and W. 3rd Street using roller compacted concrete technology, updating pedestrian ramps to current ADA standards and maintaining existing Class II Bicycle lanes.

Fulton Road between Occidental Road and W. 3rd Street 04/2018 04/2019 20 20 2, 10 2

Santa Rosa Sonoma Road Maintenance & Rehabilitation

Pacific Avenue - Montecito Avenue to Humboldt Street (reconstruction/pavement rehabilitation)

The project will reconstruct Pacific Avenue between Montecito Avenue and Humboldt Street which involves removing the entire pavement section and replacing it with new asphalt concrete and underlying aggregate base to restore its life and serviceability. The project will also include upgrading pedestrian curb ramps to meet current state and federal accessibility standards. The reconstructed roadway will enhance the surface by replacing failing pavement and reduce ongoing maintenance costs. The estimated useful life of the planned pavement rehabilitation is expected to be 20 years.

Pacific Avenue - Montecito Avenue to Humboldt Street (reconstruction/pavement rehabilitation) 07/2018 12/2020 10 20 2 2

Santa Rosa Sonoma OtherSonoma Marin Area Rail Transit (SMART) Hearn Multi-Use Path (MUP) Crossing

The SMART Hearn Multi-Use Crossing is located at Hearn Avenue and the SMART railroad tracks. The project will connect two existing segments of the SMART Multi-Use path (MUP) in southwest Santa Rosa. The proposed signalized street connection will create an enhanced crossing at Hearn Avenue for bicyclists and pedestrians using the multi-use path along the SMART rail corridor. The project will design and install a signalized crosswalk at the SMART MUP intersecting with Hearn Avenue. In addition, the project will include construction of ADA curb ramps on each side of the street, minor modifications to the sidewalk, curb and gutter, and modification of the concrete median in Hearn Avenue to accommodate the pathway, signage and pavement markings. The estimated useful life of the planned pavement rehabilitation is expected to be 20 years.

Hearn Avenue and the SMART railroad tracks. 05/2017 06/2019 10 20 10 2

Sebastopol Sonoma Safety Roadway shoulder reconstruction, Bodega Avenue

Reconstruct and stabilize the south shoulder of Bodega Avenue along its shared boundary with a cemetery; this gains sufficient roadway width to accommodate bicycle lanes

South shoulder Bodega Ave between Pleasant Hill Rd & Virginia Ave. 07/2018 05/2019 20 30 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation

Pavement preservation,several City streets, later fiscal year

Recurring pavement preservation project, overlay and slurry seal as appropriate to location Abbott Ave. to Zimpher Rd. with 536 Total Streets 07/2022 06/2023 20 30 10 2

Sebastopol Sonoma Complete Streets Components

Class 1 bike path Bodega Ave Ragle Rd to City Line

Class 1 bicycle path along Bodega Ave between Ragle Rd and the City boundary at the Atascadero Creek. That is also a connection point to a County bicycle path. Sebastopol, CA Bodega Avenue west end 03/2021 07/2023 8 10 10 2

Sebastopol Sonoma Complete Streets Components

Class 1 Bicycle Path across Libby Park

Bicycle gap closure across Libby Park to connect end of Washington St. with Pleasant Hill road Libby Park 03/2021 08/2022 8 10 10 2

Sebastopol Sonoma Safety Upgrade intersection to a traffic signal

Upgrade intersection control from crosswalk flashing light warning system to full traffic signal Ragle Road - Bodega Avenue intersection 11/2020 09/2021 30 40 10 2

Sebastopol Sonoma Safety Redo intersection, Covert Lane and SR 116 Redo intersection with difficult left turns and poor sight distances and angles. Covert Lane and SR 116/Healdsburg Avenue 07/2021 09/2023 30 40 10 2

Sebastopol Sonoma Complete Streets Components

Bodega Corridor preliminary plan and design

Engineering Design: pavements, sidewalks, bicycle lanes, crosswalks, signals all along Bodega Avenue Bodega Avenue, entire length 06/2018 08/2018 30 40 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation

Laguna Preserve parking entry paving Parking entrance at Laguna Park needs rehab and improvement Laguna Wildlife Preserve Park 07/2021 06/2023 20 30 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation Ives Park pathways Park paved pathways need rehabilitation and improvement Ives Park 07/2021 06/2023 30 40 10 2

Sebastopol Sonoma Safety Bodega/Florence crosswalk & safety improvements Relocate crosswalk and create a raised pedestrian refuge island at the median Bodega Avenue - Florence Avenue Intersection 03/2018 08/2018 30 40 10 2

Sebastopol Sonoma Safety Bodega/Washington crosswalk and safety improvements Install a raised pedestrian refuge island within the existing center lane area. Bodega Avenue - Washington Avenue intersection 03/2018 06/8201 30 40 10 2

Sebastopol Sonoma Complete Streets Components ADA Curb Ramps

Bring curb ramps at crosswalks and intersections to current ADA standards; Gravenstein Hwy, north and south; Healdsburg ave, North and South Main Streets; and Petaluma Ave. This is a necessary first step prior to repaving then adding bicycle lanes on the same streets, which are separate but integral parts of a larger project.

30 crosswalk locations along SR 116 through Sebastopol 01/2018 06/2018 8 20 10 2

Sebastopol Sonoma Safety Bodega/Robinson crosswalk & safety improvements Restripe crosswalks and add a flashing light crosswalk warning system, "PAWB" Bodega Avenue - Robinson Road intersection 03/2018 08/2018 30 40 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation Bodega Avenue widening north side Widen Bodega Ave north side between Golden Ridge and Virginia Avenues by

replacing a non-standard sidewalk Between Golden ridge and Virginia Avenues along Bodega Avenue 07/2019 05/2020 20 30 10 2

Sebastopol Sonoma Safety Sidewalk gap closure Bodega Ave at Huntley Square Add sidewalk along Bodega Ave at the Huntley Square development; city contribution Bodega Ave at Huntley Square 08/2020 06/2021 20 30 10 2

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 109: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Sebastopol Sonoma SafetySidewalk gap closure mBodega Ave between Golden Ridge Ave and Pleasant Hill Rd

Add a sidwalk along Bodega ave between Golden ridge and Pleasant Hill where nothing currently exists Bodega Ave between golden Ridge and Pleasant Hill 09/2020 06/2021 20 30 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation

Repave Bodega Avenue Jewell to Pleasant Hill

Pavement preservation project, portion of Bodega ave between Jewell Ave and Pleasant Hill road Bodega ave between Jewell and Pleasant Hill 07/2020 06/2021 20 30 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation

Pavement preservation, several City streets

Recurring pavement preservation projects, overlay or slurry seal dependent on location. Specific streets determined by pavement evaluations closer to the time of bid lettings Locally owned streets within the City of Sebastopol 07/2022 06/2023 8 20 10 2

Sebastopol Sonoma Safety Sidewalk gap closure, Bodega Ave Nelson to Robinson

a portion of the sidewalk between Nelson and Robinson is non-standard, steep, and buckled. This sidewalk gap needs to be reconstructed to meet standards. Bodega Ave, between Nelson & Robinson 07/2020 06/2021 8 10 10 2

Sebastopol Sonoma Complete Streets Components

Bicycle Lanes and striping along Bodega avenue

After repaving, shoulder and sidewalk work, add bicycle lanes striping and signs. This should complete the planned bicycle system within the city of Sebastopol! Bodega Avenue from SR 116 to the west City Line. 07/2021 11/2021 8 10 10 2

Sebastopol Sonoma Road Maintenance & Rehabilitation

Repave Bodega Avenue, High Street to Jewell Avenue Pavement preservation project, portion of Bodega Avenue Bodega Avenue between High Street and Jewell avenue 07/2018 06/2019 20 30 10 2

Sonoma Sonoma Road Maintenance & Rehabilitation 2018 Citywide Slurry Seal Project

This project is a part of the City’s commitment to keeping the City’s streets in a safe and functional condition for multi-modal circulation. The project will provide slurry seal street surface treatment for various street segments throughout the City of Sonoma. Auxiliary work in support of the slurry seal treatment includes surface preparation; crack seal; removal and replacement of pavement striping markings; protection of existing utility structures, curb and gutter, and cross gutter; and other related work.

Various street segments throughout the City of Sonoma. Streets segments could include the following: Fifth Street East (City limits to Denmark Street), East Spain Street (First Street East to Second Street East), Andrieux Street (Fourth Street West to Third Street West), Engler Street (Brockman Drive to Fifth Street East), West MacArthur Street (Manor Drive to Second Street West), Third Street West (Robinson Street to West Napa Street), First Street West (Malet Street to House #19995), Montini Way (Fourth Street West to Fifth Street West), Denmark Street (Dead end west of Brockman Drive to Garry Lane), West Spain Street (Junipero Serra Drive to Fifth Street West), Avenue Del Oro (House #693 to Appleton Way), Berryessa Court (Berryessa Drive to Cul de Sac), and Fifth Street West (West MacArthur Street to Andrieux Street).

07/2018 11/2018 3 5 10 3

Windsor Sonoma Road Maintenance & Rehabilitation

Town-Wide Street Resurfacing (17/18 Ongoing)

Slurry seal to invest in on-going maintenance of Town streets to reduce deterioration of pavement and extend the useful life of the streets. This is part of the annual pavement maintenance plan and is considered a best management practice.

All streets east of Hembree Lane bounded on the north side by Arata Lane down south to the US 101 including streets in the Crosscreek, Wilson Estates, Jane's Meadow and Poole Creek neighborhood (e.g. Billington Lane, Wilson Lane, etc.)

06/2018 07/2018 5 10 2 2

Ceres Stanislaus Safety Roundabout Projects (17/18 Ongoing)

Construct two roundabout projects to increase safety, rehabilitate streets and reduce emissions within the community Central Ave. and Pine St., Morgan Ave. and Aristocrat Drive 06/2018 02/2019 18 25 21 12

Hughson Stanislaus Road Maintenance & Rehabilitation Santa Fe Avenue Overlay Project 2" pavement overlay on Santa Fe Avenue Santa Fe Avenue from Hatch Road to 7th Street 04/2018 08/2018 7 10 12 8

Hughson Stanislaus Road Maintenance & Rehabilitation Whitmore Avenue Slurry Seal Slurry Seal on Whitmore Avenue Whitmore Avenue from east of Tully Road to Charles Street 12/2018 06/2019 5 7 12 8

Modesto Stanislaus Road Maintenance & Rehabilitation

Crack Seal and Asphalt Digout Repairs

Cracks seal several street segments in preparation of slurry seal program, some areas need dig out asphalt repairs also. Approximately 100 lane miles of residential streets will be prepared.

Monticello / Crater Area; Girbaldi Ct. Cielito Dr. End of Court; Manor Oak Area; Capistrano Area; Hashem Area; Robin Hood Area Sheldon Area; Glenwood Area; Poust Area; Kavanagh Area

10/2018 05/2019 5 7 21 5

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 110: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Modesto Stanislaus Road Maintenance & Rehabilitation Modesto SB1 Projects Type II Slurry to approximately 92 lane miles of residential streets

Lakewood Area Street From To Mulholland Dr Lakewood Ave Staci Ln Lake Park Ct Mulholland Dr End Staci Ln Para Dr Shane Ln Olinda Ln Shane Ln E.Orangeburg Ave. Bella Terra Dr Shane Ln Para Dr Virlee Dr Para Dr Shane Ln Ocotillo Wy Virlee Dr Pepper Tree Ln Wild Palms Dr Dessert Willow Ln End Shane Ln Virlee Dr Staci Ln Desert Willow Ln Orangeburg Wild Palms Dr Joshua Wy Desert Willlow Ln Pepper Tree Ln Mesquite Wy Desert Willlow Ln Pepper Tree Ln Pepper Tree Ln Orangeburg Ave Wild Palms Dr Fransen Ln Orangeburg Ave Wild Palms Dr Traverler Ct Fransen Ln End Justin Ct Palmdale Dr End Zachary Ct Palmdale Dr End Prarie Dog Dr Saguaro Wy Wild Palms Dr Havasu Dr Orangeburg Ave Wild Palms Dr Saguaro Wy Prarie Dog Dr End Indian Butte Ct Havasu Dr End Tumbleweed Ct Havasu Dr End Sandy Ct Orangeburg Ave End Rumble Area Street From To Capbell Ln Robbie Ave Rumble Rd Brentwood Ct Campbell Ln End Dwight Ln Campbell Ln Rumble Rd Richmond Ct Dwight Ln End Bewhall Ct Dwight Ln End Thorton Ct Rumble Rd End Sharondell Dr Mount Vernon Dr Dwight Ln Robbie Ave Carver Rd Rockwood Pl Teri Ln Mount Vernon Dr Derek Wy Derek Wy Teri Ln Earlmar Ln Earlmar Ln Mount Vernon Dr Derek Wy Evona Ct Teri Ln End

05/2018 09/2018 5 7 21 5

Modesto Stanislaus Safety Traffic Signal and Street Lighting Maintenance

Maintain traffic signals and street lighting systems throughout Modesto 220 traffic signals, 11,575 street lights

Various locations throughout Modesto within the following boundaries:The northern boundary is Kiernan Avenue (State Highway 219) and Claribel Road. The eastern boundary is Claus Road to Santa Fe Avenue. The southern boundary is Whitmore Avenue. The western boundary is State Highway 99 on the north and Morse Road extended north and south.

07/2018 06/2019 5 7 21 5

Modesto Stanislaus Safety Traffic Sign and Striping Maintenance

Maintain traffic signs and street striping throughout Modesto 30,677 traffic signs, typically 2400 signs are replaced or repaired annually 4000 intersections, 2000 stop signs, 2100 marked cross walks, and 886 center lane miles of striping are maintained.

Various locations throughout Modesto within the following boundaries: The northern boundary is Kiernan Avenue (State Highway 219) and Claribel Road. The eastern boundary is Claus Road to Santa Fe Avenue. The southern boundary is Whitmore Avenue. The western boundary is State Highway 99 on the north and Morse Road extended north and south.

07/2018 06/2019 5 7 21 5

Newman Stanislaus Road Maintenance & Rehabilitation 2018-19 SB-1 Crack seal, slurry and stripe. Small pavement replacement (potholes).

T Street from Yolo Avenue to Inyo Avenue; Kern Street from Main Street to T Street; Fresno Street from Main Street to T Street; Tulare Street from Main Street to T Street; Mariposa Street from Main Street to T Street

07/2018 06/2019 5 10 21 12

Oakdale Stanislaus Road Maintenance & Rehabilitation

H Street (Between Oak Ave & Ash Street)(17/18 Carryover)

Grind, remove and replace pavement section of street with limited curb gutter and sidewalk replacements. H Street from Oak Avenue to Ash Street 07/2018 10/2018 15 25 12 8

Oakdale Stanislaus Road Maintenance & Rehabilitation

Ash Street ( Between J Street & H Street)

Grind, remove and replace pavement section of street with limited curb gutter and sidewalk replacements. Ash Avenue between H street and J Street 07/2018 10/2018 15 25 12 8

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 111: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Patterson Stanislaus Road Maintenance & Rehabilitation

Slurry and Crack Seal - Streets Submitted for FY 18/19 Slurry Seal and Crack Seal

W LAS PALMAS AVE - PLAZA CIR to N 9TH ST S DEL PUERTO AVE - PLAZA CIR to E ST S DEL PUERTO AVE - E ST to SPERRY AVE HOLLY HOCK CIR - LORELEI LN to MORNING GLORY DR LORELEI LN - MORNING GLORY DR to N HARTLEY ST EMILY CT - LORELEI LN to NW END LILY CT - LORELEI LN to NW END M ST - N 2ND ST to WARD AVE L ST - N 2ND ST to N 7TH ST K ST - N 2ND ST to N SALADO AVE J ST - N 2ND ST to N 3RD ST I ST - N 2ND ST to N 7TH ST H ST - N 4TH ST to N 7TH ST N SALADO AVE - PLAZA CIR to WARD AVE N 4TH ST - L ST to M ST N 5TH ST - L ST to M ST N 5TH ST - K ST to L ST N 5TH ST - W LAS PALMAS AVE to K ST N 7TH ST - W LAS PALMAS AVE to N SALADO AVE MAC DUFF WAY - CLOVER AVE TO MORAY WY *All locations subject to change, and will be selected based on priority, need and resources throughout the year.

03/2019 07/2019 5 7 21 12

Patterson Stanislaus Road Maintenance & Rehabilitation

FDR 2" HMA/9" AB - Streets Submitted FY 18/19 FDR 2" HMA/9" AB

N DEL PUERTO AVE - PLAZA CIR to N 2ND ST MORNING GLORY DR - LORELEI LN to PERIWINKLE DR PERIWINKLE DR - HANNAH DR to MORNING GLORY DR J ST - N 3RD ST to N 7TH ST N 3RD ST - K ST to M ST N 4TH ST - N SALADO AVE to I ST POPPY AVE - CLOVER AVE to S DEL PUERTO AVE CANYON CT - POPPY AVE to END HANSEN CT - POPPY AVE to END KINSHIRE WAY - CLOVER AVE to S DEL PUERTO AVE KLOPPING CT - KINSHIRE WAY to END S 9TH STREET - KINSHIRE WAY to SPERRY AVE DE LASH CT - KINSHIRE WAY to END AGADONI CT - KINSHIRE WAY to END CLOVER AVE - POPPY AVE to SPERRY AVE S DEL PUERTO AVE - POPPY AVE to SPERRY AVE AMBERINA CT - AMBERNIA DR to END AMBERINA DR - AMBERINA CT to S DEL PUERTO AVE BONNEAU CT - S 9TH STREET to END *All locations subject to change, and will be selected based on priority, need and resources throughout the year.

03/2019 07/2019 15 20 21 12

Patterson Stanislaus Road Maintenance & Rehabilitation

2.5" AC Overlay - Streets Submitted FY 18/19 2.5" AC Overlay

WARD AVE - W LAS PALMAS AVE to JAMES BURKE AVE WARD AVE - JAMES BURKE AVE to N SALADO AVE WARD AVE - N SALADO AVE to AMERICAN EAGLE AVE E LAS PALMAS AVE - 699 E/O N HARTLEY ST to N HARTLEY ST E LAS PALMAS AVE - LA LYNN DR to N HARTLEY ST E LAS PALMAS AVE - N. 1ST ST to LA LYNN DR HANNAH DR - PERIWINKLE DR to LORELEI LN ROSEMARY DR - HANNAH DR to MORNING GLORY DR SAFFRON WY - WALNUT AVE to PERIWINKLE DR N 3RD ST - PLAZA CIR to K ST N 4TH ST - I ST to L ST N 6TH ST - H ST to L ST N 6TH ST - W LAS PALMAS AVE to H ST N 7TH ST - N SALADO AVE to L ST SPERRY AVE - S AMERICA EAGLE AVE to WALKER RANCH PKWY SPERRY AVE - WALKER RANCH PKWY to BALDWIN RD *All locations subject to change, and will be selected based on priority, need and resources throughout the year.

03/2019 07/2019 10 15 21 12

Patterson Stanislaus Road Maintenance & Rehabilitation

Slurry Seal and Crack Seal - Streets Submitted FY 17/18 (17/18 Carryover)

Slurry Seal and Crack Seal

ORKNEY DR - TARLAND LN to WARD AVE; TIREE PL - NORTH END to ORKNEY DR; TARLAND LN - KIRKWALL WY to ORKNEY DR; KIRKWALL WY - MORAY WY to TARLAND LN; MORAY WY - KIRKWALL WY to MACKILHAFFY DR; MORAY CT - MORAY WY to WEST END; MACKILHAFFY DR - MORAY WY to D AVE; MC MURPHY CT - NORTH END to MACKILHAFFY DR; PITSCOTTIE LN - ORKNEY DR to MACKILHAFFY DR

06/2018 12/2018 5 7 21 12

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 112: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Riverbank Stanislaus Road Maintenance & Rehabilitation Crack Seal Repairs Crack Seal 57 road segments throughout Riverbank

Almondwood Drive - Rio Verde Drive to Rivergate Drive, Silver Rock Road - Oakdale Road to Patterson Road, Goldstone Way - Silverrock Road to High Mesa Way, South Gate Drive - Lonestar lane to Oakdale Road, High Mesa Way - Silverock Road to Goldstone Way, Rock Creek Road - Red Rock Lane to Patterson Road, Kentucky Avenue - Claus Road to Terminal Avenue, Sandy Ridge Drive - Rocky Point Way to Hot Springs Lane, Hot Springs Lane - Patterson Road to Sandy Ridge Drive, Rocky Point Way - Sandy Ridge Drive to Clearwater Way, Clearwater Way - Red Rock Lane to South End, Red Rock Lane - Sandy Ridge Drive to Clearwater Way, Crossroads Drive - Mc Cafrey Lane to Colony Manor Drive, Virginia Avenue - Tennessee Avenue to Castleberg Drive, McAllister Drive - Kasper Drive to Crossroads Drive, Deleon Way - McCaffrey Lane to McAllister Lane, Kasper Drive - McCaffrey Lane to McAllister Lane, McCaffrey Lane - Kasper Drive to Crossroads Drive, McDevitt Drive - Woodard Way to McAllister Lane, Woodard Way - McDevitt Drive to Falcon Ridge Lane, Howard Avenue - Morrill Road to Patterson Road, Newbrook Drive - Lindbrook Drive to Morrill Road, Linbrook Drive - Newbrook Drive to Carnwood Drive, Soares Place - Roselle Avenue to West End, Fern Court - Roselle Avenue to SW End, Ward Avenue - Howard Avenue to Don Avenue, Sierra Street - Eighth Street to First Street & Jackson to Callendar Avenue, St. Lakes Court - RiverCove Drive to South End, Olive Grove Court - Estelle Avenue to East End, River Mesa Drive - Stanislaus Street to Santa Fe Street, North Rose Brook Drive - Rose Brook Drive to Roselle Avenue, Rose Brook Drive - South Rose Brook Drive to North Rose Brook Drive, Story Brook Lane - Rose Brook Drive to Roselle Avenue, Second Street - Atchison Street to Sierra Street, Stanislaus Street - Third Street to Eighth Street, Texas Avenue - Terminal Avenue to Chief Tucker Avenue, Nevada Avenue - Terminal Avenue to Chief Tucker Avenue, Deer Ridge Place - Country Manor Drive to North End, Jaguar Court - Country Manor Drive to North End, Colony Manor Drive - Oakdale Road to Estelle Avenue, Heritage Manor Drive - Colony Park Drive to Estelle Avenue, 3rd Street - High Street to Atchison Street, 3rd Street - Riverside Drive to High Street, 4th Street - Atchison Street to Topeka Street, 4th Street - Topeka Street to Santa Fe Street, 5th Street - High Street to Atchison Street, 5th Street - Atchison Street to Santa Fe Street, 6th Street - Sierra Street to Stanislaus Street, 6th Street - Stanislaus Street to Santa Fe Street, Candlewood Circle - Candlewood Place to South End, Claus Road - Patterson Road to Santa Fe Street, Karen Alane Way - Stanley Allen Court to Oakdale Road, Kenneth Charles Court - North End to Karen Alane Way, Patterson Road - Hwy 108 to Railroad Avenue, Riverside Drive - 3rd Street to 4th Street, Stanley Allen Court - North End to Karen Alane Way, Topeka Street - 3rd Street to 5th Street

03/2018 06/2018 5 7 12 5

Turlock Stanislaus Safety Christoffersen Median Fencing (17/18 Ongoing)

Install median fence to prohibit pedestrians crossing at unmarked and uncontrolled locations. On Christoffersen Parkway from Walnut Road to the West approximately 1000'. 06/2018 08/2018 30 50 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Lander and Hawkeye Rehab

Road rehabilitation (inlay and overlay) of Lander Avenue and Hawkeye. Install missing segments of sidewalk and reconstruct curb ramps. Install new stripping and crosswalks.

On Lander Avenue from South Ave. to Glenwood and on Hawkeye Ave. from Olive to Daubenberger. 05/2019 12/2019 15 25 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Wayside Ave. Rehab Road rehabilitation (inlay and overlay) of Wayside Avenue. Install missing segments of

sidewalk and reconstruct curb ramps. Install new stripping and crosswalks. On Wayside from Geer to Olive 05/2019 08/2019 15 25 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation

2018 SB 1 Slurry Seal (17-18 Carryover) Place slurry seal and new striping

On 5th street 100' south of Ryker to Linwood; Ryker Ct; Federation Ct; Picard Ct; Crusher Ave; Warp Dr; Shadow Park Dr; Viscount Ct; Noble Ln; Victoria Ct; Royal Wood Ln; Ahern Ct; Button Ct; Pernet Ct; Kalland Ct; Callisto Ln; Bardini Way; Heartland Way; Rosenthal Dr; Avatar Ct; Andino Ct; Putnam Ct; Ceder Ridge; Milano Way; Milano Ct; Whispering Pines Dr; Whispering Pines Ct; Pine Valley Ct; Apple Blossom; Venture Ln; Alanta Ct; and Ellard Ct.

07/2018 10/2018 7 10 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Road Maintenance Worker 1 Labor costs for road maintenance worker (pot hole crew).

Address potholes throughout the City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

08/2018 06/2019 1 10 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Road Maintenance Worker 2 Labor costs for road maintenance worker (pot hole crew).

Potholes throughout the City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

08/2018 06/2019 1 10 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Hot Mix Asphalt Material costs for road maintenance (pot hole).

Potholes throughout City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

08/2018 06/2019 1 10 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Hot Mix Truck and Trailer Equipment costs for road maintenance (pot hole)(Truck and trailer for hauling and

placing HMA)

For potholes throughout the City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

07/2018 06/2019 10 20 12 8

Turlock Stanislaus Road Maintenance & Rehabilitation Thermoplastic Trailer Equipment costs for thermoplastic (striping)(increase visibility of striping)

throughout the City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

07/2018 06/2019 10 20 12 8

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 113: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Turlock Stanislaus Road Maintenance & Rehabilitation Thermoplastic Material Material costs for thermoplastic (striping)(increase visibility of striping)

Throughout the City of Turlock encompassed by Taylor Rd, Waring Rd, Glenwood Ave, and Washington Rd. for a total of 984 streets. Exact locations have yet to be determined by the City; all locations selected for service or improvements will be chosen based on priority need throughout the year.

07/2018 06/2019 5 10 12 8

Waterford Stanislaus Complete Streets Components

Summer Street Improvement Project

A full depth pavement placement with replacement of sidewalk, curb and gutter where necessary. Summer Street is the worst conditioned with a PCI of 3. Therefore, a total reconstruction is appropriate for this project.

Summer Street (between F St and La Gallina St) in Waterford, CA 95386 05/2018 08/2018 3 100 12 8

Waterford Stanislaus Road Maintenance & Rehabilitation

Summer Street Improvement Project

This is a full rehab of Summer Street which has been deemed the "worst street" in the City since the 2013 street survey with a PCI of 3. The full reconstruction and rehab will include replacing some curb, gutter and side walks which has also deteriorated over the years along with the street itself.

Summer Street in Waterford, CA. (Between F St and D Street) 06/2018 08/2018 45 100 12 8

Live Oak Sutter Road Maintenance & Rehabilitation

Pennington Road West Reconstruction (17/18 Carryover)

Reconstruct Pennington Road between Connecticut Ave and Broadway after the installation of a new water main. Pennington Road between Connecticut Ave and Broadway 10/2018 10/2019 20 20 3 4

Live Oak Sutter Road Maintenance & Rehabilitation Kola Street Reconstruction Reconstruct and improve Kola St from Larkin Rd to N St in coordination with the

Highway 99 Streetscape Project beginning in 2020 Kola Street from Larkin Rd to N St 07/2020 12/2023 20 20 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Franklin Avenue Rehabilitation .3' Mill and AC Overlay, ADA ramp improvements, striping improvements, safety

signage. Palora Avenue to Wilbur Avenue 04/2018 09/2018 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Sanborn Road Rehabilitation .3' Mill and AC Overlay, ADA ramp improvements, striping improvements, safety

signage. Bogue Road to Nand Drive 05/2018 10/2018 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Bridge Street Rehabilitation Widening and complete reconstruction, ADA ramp improvements, striping

improvements, safety signage. Gray Avenue to Cooper Avenue 04/2020 10/2020 30 50 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Garden Highway Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Lincoln Road to Shanghai Bend Road 04/2022 10/2022 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation S Walton Avenue Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Lincoln Road to Camino De Flores 04/2023 10/2023 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Tharp Road Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. SR 20 WB to Poole Boulevard 04/2024 10/2024 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation

Civic Center Boulevard Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. SR 20 WB to Butte House Road 04/2024 10/2024 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Queens Avenue Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Blevin Road to Stabler Lane 04/2025 10/2025 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Blevin Road Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Butte House Road to Queens Avenue 04/2025 10/2025 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation El Margarita Road Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Imperial Way to 1100' S/O Spirit Drive 04/2026 10/2026 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Littlejohn Road Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Hunn Road to Franklin Road 04/2026 10/2026 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Washington Avenue Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Gray Avenue to Live Oak Boulevard 04/2027 10/2027 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Railroad Avenue Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Lask Drive to Teesdale Road 04/2028 10/2028 20 30 3 4

Yuba City Sutter Road Maintenance & Rehabilitation Stabler Lane Rehabilitation .3' mill and AC overlay, ADA ramp improvements, striping improvements. Jamie Drive to Butte Vista Lane 04/2028 10/2028 20 30 3 4

Corning Tehama Road Maintenance & Rehabilitation

Hoag Street Overlay (17/18 Carryover) 2-inch asphalt overlay, ADA compliant curb returns and curb and gutter improvements Hoag Street between Solano and Tehama Streets 07/2018 08/2018 15 18 3 4

Red Bluff Tehama Road Maintenance & Rehabilitation Kimball Road Reconstruction Reconstruction/overlay of Kimball Road from Montgomery Street to the City of Red Bluff

Community Center, approximately 0.80 miles. Kimball Road from Montgomery Street to the Red Bluff Community Center, west of S. Jackson Street 08/2018 03/2019 7 10 3 4

Red Bluff Tehama Road Maintenance & Rehabilitation

Franklin Street & 1st Street Paving Complex

Overlay/resurfacing of a portion of Franklin Street, 1st Street, Union Street, Hickory Street, Johnson Street and Lincoln Street on the east side of Red Bluff High School, approximately 1 mile

Franklin Street, 1st Street, Union Street, Hickory Street, Johnson Street and Lincoln Street on the east side of Red Bluff High School. See exhibit attached. 08/2018 03/2019 7 10 3 4

Red Bluff Tehama Road Maintenance & Rehabilitation Walnut Ave. Overlay Microsurfacing of half width of Walnut Street between Paskenta and David. Complete

the resurfacing that has occurred as part of Courthouse project. Walnut Street between Paskenta and David 05/2018 08/2018 5 7 3 4

Tehama Tehama Road Maintenance & Rehabilitation Crack seal city streets Seal cracks in all city streets. City of Tehama C,D,E,F,G,H,I,2nd,3rd,4th,5th Sts.,Gyle Rd. 04/2019 08/2019 3 5 3 4

Dinuba Tulare Road Maintenance & Rehabilitation

Street Improvement Project (17/18 Carryover) Street Reconstruction and installation of curbs, gutters and sidewalk Pamela Ave from Lillie to Quail Run Drive for street reconstruction and M Street from Tulare to Fresno

Street curb, gutter and sidewalk improvements 03/2019 05/2019 20 30 26 14

Dinuba Tulare Road Maintenance & Rehabilitation Street Reconstruction Project Street Reconstruction

Intersection of Tulare Street and H Street, Intersection Nebraska and Crawford, Olive Way between Crawford and Randle, Sierra Way Between Monte Vista and Alta Ave., Euclid Ave Between Bloomingdale and Saginaw Ave.

12/2018 01/2018 20 30 26 14

Dinuba Tulare Road Maintenance & Rehabilitation

Street Improvement Project (17/18 Ongoing) Replace defective asphalt concrete adjacent to traffic circles Tulare & N , Tulare & L, Tulare & K, Fresno & L , and Kern & L 08/2018 10/2018 20 30 26 14

Exeter Tulare Road Maintenance & Rehabilitation Downtown Streets Project Rehabilitation of streets with Type 2 Slurry Seal and striping Pine Street (F Street to Kaweah Ave), Rocky Hill Drive (between Kaweah and C Street), B-F Street

(between Palm and Maple) 07/2019 09/2019 8 10 26 16

Farmersville Tulare Road Maintenance & Rehabilitation

Costner Street Road Repair Project 17/18 Ongoing

Includes pavement and drainage repairs, There are three project sections: A bus pad will be constructed on E. Costner St. Approximately 200’ east of N. Rose Ave, Roadway realignment and re-grading along Costner St. from N. Linnel Ave to N. Shasta Ave to improve drainage, and slurry seal and chip seal within the boundaries of W. Ash St. and W. Costner St., N. Ventura and N. Kern St.. All of which are in residential areas.

This project is in the City of Farmersville and is located in the boundaries of W. Costner St. and W. Ash St. to the north and south and N. Ventura and N. Kern St. to the West and East. 01/2018 04/2018 8 10 26 14

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 114: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Farmersville Tulare Complete Streets Components

East Walnut Repair and Improvement Project South sSide of Roadway 17/18 Ongoing

Includes road repair, and reconstruction, curb, gutter and sidewalk improvements and bicycle and pedestrian safety installations and enhancements

This project is located in the City of Farmersville on E. Walnut Ave between Farmersville Blvd. and N. Freedom Drive. This project is located next to the Farmersville High School. 12/2018 06/2020 20 25 26 14

Farmersville Tulare Road Maintenance & Rehabilitation CAPE Seal Project road maintenance to be performed using a chip seal and slurry seal known as a Cape

Seal. All ramps within the area will be upgraded to ADA standards (approximately 23)

The project is located in the City of Farmersville, CA. the project is on the east side of S. Farmersville Blvd. The project is located within the boundaries of E. Oakland St. which runs east to west and S. Camelia Ave which runs north to south. The interior streets are as follows; S. Rose Ave and South Avery Ave, both North to South running streets and are to the east of S. Camelia Ave E. Fresno St, E. Kirkland St., Grove St. and E. Tulare St. are all east to west running and are located south of E. Oakland St. The location is the most southeastern part of the City and is at the City Limits. The project is located in a residential area.

01/2020 01/2021 8 10 26 14

Farmersville Tulare Complete Streets Components

West Walnut Ave Full Depth Reconstruction Project

Will include 132,000 SF of full depth reconstruction which includes hot mix asphalt over aggregate base. 6 ADA curb returns will also be reconstructed.

The project is located in the City of Farmersville, CA along W. Walnut Ave between N. June Ave to the west and Farmersville Blvd to the east. Cross streets from west to east are N. Matthew Ave, Carolyn St., N. Ventura Ave, Franquette Ave, and Hartley Ave. This project is located in a residential zone.

01/2020 01/2021 25 30 26 14

Farmersville Tulare Complete Streets Components

East Walnut Ave Repair and Improvement Project North Side of Roadway

Will include construction of 2,300 LF of sidewalk, curb and gutter, construct 8 ADA curb returns, construct 15 drive approaches, a 7 foot bike lane, purchase additional right of way for a 12’ travel lane, a 5 foot wide sidewalk, 1 cross gutter, 10 street lights, curb and gutter, 3 storm drain inlets, and 1950 of 36” storm drain piping.

The project is located in the City of Farmersville, CA along E. Walnut Ave. between Farmersville Blvd to the west and Rd. 168 to the east. This project is located across the street From Farmersville High School near residential and some commercial areas.

01/2022 12/2023 25 30 26 14

Farmersville Tulare Complete Streets Components

West Walnut Repair and Improvement Project 17/18 Ongoing

Includes road repair, and reconstruction, curb, gutter and sidewalk improvements and bicycle and pedestrian safety installations and enhancements.

This project is located in the City of Farmersville on W. Walnut Ave between N. June St. and Farmersville Blvd. This project is located in a residential zone. 07/2018 06/2019 20 25 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Tulare Road (17/18 carryover) Surface seal of 2 miles of Tulare Road (arterial street). Restripe effected areas (bike

lanes and travel lanes). Oak Avenue to Foothill Avenue 01/2019 04/2019 5 10 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Westmore Court (17/18 carryover) Surface seal of .13 miles of Westmore Court (residential street). Mariposa Street south to alley 01/2019 04/2019 5 8 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Samoa Street (17/18 carryover) Surface seal of .12 miles of Samoa Street (commercial/residential street). Mirage Avenue to Homasell Avenue 01/2019 04/2019 5 8 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Elmwood/Mirage/Honolulu/Samoa surface seal, restripe, .7 miles Downtown Lindsay area 04/2020 06/2021 5 10 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Ashland/Frazier/Eastwood surface seal .28 miles Ashland/Frazier/Eastwood Streets 04/2020 06/2021 5 8 26 14

Lindsay Tulare Safety Hermosa/Westwood Roundabout New roundabout at Hermosa Street and Westwood Avenue Hermosa Street and Westwood Avenue 06/2018 12/2018 15 25 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Burem Lane Renovation Recycle and rehabilitate .1 mile Burem Lane, west of Westwood Avenue 04/2020 10/2021 15 18 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Hermosa Street (17/18 carryover) Surface seal of 2 miles of Hermosa Street (arterial street). Restripe effected areas (bike

lanes and travel lanes). Hwy. 65 to Mirage Avenue 04/2020 06/2021 15 18 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Mirage Avenue (17/18 carryover) Asphalt recycling of .1 miles of Mirage Avenue (arterial street). Restripe effected areas,

renovate concrete curbs, gutters and sidewalks. Samoa Street to Hermosa Street 04/2020 06/2021 15 18 26 14

Lindsay Tulare Road Maintenance & Rehabilitation Linda Vista Loop (17/18 carryover) Asphalt recycling of .25 miles of Linda Vista Avenue (residential street). Renovate

concrete curbs, gutters and sidewalks, minor storm drain upgrades. Valencia Street to Valencia Street 04/2020 06/2021 15 18 26 14

Porterville Tulare Road Maintenance & Rehabilitation

Henderson Avenue Cold Foam In-Place Recycling

Reconstruction of asphalt section of four-lane arterial roadway, 0.5 miles in length and 64 feet of width. Located between Indiana Street and Jaye Street. 08/2018 12/2018 15 20 26 14

Porterville Tulare Road Maintenance & Rehabilitation Plano Street Microsurfacing Rehabilitation of asphalt surface of four-lane arterial roadway, two miles in length and

64 feet of width. Located between State Route 190 and Henderson Avenue. 07/2018 09/2018 7 10 26 14

Porterville Tulare Road Maintenance & Rehabilitation Henderson Avenue Rehabilitation Rehabilitation of asphalt surface of four-lane arterial roadway, 0.5 miles in length and 64

feet of width. Located between Balmayne Drive and Patsy Street. 08/2018 12/2018 15 20 26 14

Porterville Tulare Road Maintenance & Rehabilitation

Orange Avenue Rehabilitation (17/18 Ongoing)

Rehabilitation of four-lane arterial road, half-mile in length, and 64 feet wide. The rehabilitation includes the removal and replacement of the asphalt pavement section and curb ramps, updating traffic signal components, and other related items to improve the deficiencies of the roadway.

Between Main Street and Plano Street, this is also a school route to Santa Fe Elementary School. 05/2018 10/2018 10 15 26 14

Porterville Tulare Road Maintenance & Rehabilitation Henderson Avenue Reconstruction Reconstruction of roadway section of four-lane arterial roadway, 0.35 miles in length

and 64 feet of width. Located between Second Street and Plano Street. 02/2019 06/2019 15 20 26 14

Porterville Tulare Road Maintenance & Rehabilitation Newcomb Street Reconstruction Reconstruction of roadway section of four-lane arterial roadway, 0.5 miles in length and

64 feet of width. Located between Olive Avenue and Morton Avenue. 02/2019 06/2019 15 20 26 14

Tulare Tulare Complete Streets Components Cross Ave. Improvements

Pavement Management System selected project to reconstruct Cross Ave. between W. Tulare Ave. and West St. In addition to replacing pavement, project includes ADA concrete work, ADA traffic signal improvements, and surface water infrastructure improvements.

Cross Ave. between W. Tulare Ave. and West St. in the City of Tulare 07/2018 12/2018 20 25 26 16

Tulare Tulare Complete Streets Components Maple Ave. Improvements

Pavement Management System project to reconstruct Maple Avenue between Sacramento Street and E Street. Includes ADA Concrete work, and improvements to the Water, Sewer and Surface Water infrastructure.

Maple Ave. between Sacramento and "E" Streets in the city of Tulare 02/2019 08/2019 20 25 26 16

Tulare Tulare Complete Streets Components Cartmill/Hillman Improvements

Pavement Management System / Traffic Safety project on Cartmill Avenue between the Cartmill/Highway 99 Interchange and De La Vina Street. Includes ADA Concrete work, signal upgrades, street reconstruction and improvements to the Water, Sewer and Surface Water infrastructure.

On Cartmill Ave. between State Route 99 and De La Vina Street in the City of Tulare. 12/2018 06/2020 20 25 26 16

Tulare Tulare Complete Streets Components Sonora Ave. Improvements

Pavement Management System project to reconstruct Sonora Avenue between West Street and E Street. Includes ADA Concrete work, and improvements to the Water, Sewer and Surface Water infrastructure.

Sonora Avenue between West Street and E Street in the City of Tulare. 02/2019 12/2019 20 25 26 16

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 115: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Tulare Tulare Complete Streets Components

Cherry St., Bash Alley, Lyndale Dr. Improvements

Pavement Management System project to reconstruct Cherry Street between Tulare Avenue and Merritt Avenue; Bash Alley between Auburn Street and Cherry Street; Lyndale Drive between Cherry Street and Blackstone Street. Includes ADA Concrete work, and improvements to the Water, Sewer and Surface Water infrastructure.

Cherry Street between Tulare Avenue and Merritt Avenue; Bash Alley between Auburn Street and Cherry Street; Lyndale Drive between Cherry Street and Blackstone Street in the City of Tulare. 03/2018 06/2019 20 25 26 16

Visalia Tulare Road Maintenance & Rehabilitation Cape Seal Cape Seal Road Maintenance. This project list was previously submitted for FY 17/18

but will begin work in June 2018.

Segments of Arlen Ave, Border Links Dr, Cambridge Ave, Chestnut Ct, Church St, Cindy St, Crescent Ct, Damsen Ave, Fairview Ave, Garden St, Gilmer Ct, Green View Ct, Highland St, Hillsdale Ave, Hillsdale Ct, Howard Ave, Hyde Ave, Judy Ave, Julieann St, and Keogh Ave.

06/2018 08/2018 6 10 26 16

Visalia Tulare Road Maintenance & Rehabilitation

FY 18-19 Pavement Rehabiliation SB1

Rehabilitation of approximately 3.29 miles of roads in the City of Visalia. The project also includes the upgrade of existing curb ramps to be ADA compliant, and the repair of miscellaneous damaged concrete structures such as curbs, gutters, and drain inlets.

Walnut Avenue from Central to Court, Murray Avenue from Giddings to Encina, Center Avenue from Encina to Burke, Demaree Street from Houston to Ferguson, and Main Street from Conyer to Hall 05/2019 06/2019 15 20 26 16

Woodlake Tulare Complete Streets Components

South Valencia Boulevard Improvements Project

Construct about 3,300 linear feet of curb, gutter, and 6 foot wide sidewalk on both sides of S. Valencia Blvd (SR 245). The improvements also include the installation of ADA ramps, drive approaches, storm drainage, paving, and landscape repair

The project is located in Woodlake, CA along its main road S. Valencia Blvd (SR 245). The cross street boundries that are containing the project site are Bravo Ave which is the northern cross street and Wutchumna ditch with is at the southern end on the project site. Within the project site you will also find the cross street Deltha Ave, Laguna Ave, and Ropes Ave going from south to north. The project is located in a high residential area and is towards the most southern part of town. The city yard is on the south of this project and just to the east is Bravo Lake.

06/2018 12/2018 15 20 26 14

Woodlake Tulare Complete Streets Components

Magnolia Street Improvements Project

Construct about 550 linear feet of curb, gutter, and decorative sidewalk along the east side of Magnolia St between Antelope Ave and Lakeside Ave. The sidewalk will be 10 feet wide and includes brick tree wells, two drive approaches, ADA ramps, decroative street lights, storm drainage, paveout, and stirping.

The project is located in Woodlake, CA in a commercial zone of the city. The location is Magnolia St between Antelope Ave and Lakeview Ave. The project is on the east side of Magnolia St in front of a commercial center. To the north of the project location across Lakeview Ave is residential area. To the west of the project is a transit center along with a commercial zone and the City's main road, N. Valencia Blvd (SR 245). To the south of the project, just past Antelope Ave, is a City park.

06/2018 12/2018 10 15 26 14

Woodlake Tulare Complete Streets Components

North Valenia Boulevard Extension Project

Construct about 620 linear feet of curb, gutter, and 6 foot wide sidewalk along N. Valencia Blvd (SR 245). The imrpovements also include drive approaches, 5 foot wide bike lanes, 30 foot radius curb return with ADA ramps, street lights, paveout, and striping. The project will also constrcut about 150 feet of 4 foot wide sidewalk along W Sequoia Ave to connect to existing sidewalk.

The project is located in Woodlake, CA in a high residential area along N Valencia Blvd (SR 245) towards the northern part of town. The cross streets are Sequoia Ave which is the northern cross street and Sierra Ave which is the southern cross street. One block to the west along Palm St is Woodlake Valley Middle School and all around the project site is residential. To the east is a proposed development site for more residential homes.

03/2019 12/2019 15 20 26 14

Sonora Tuolumne Road Maintenance & Rehabilitation FY 2019 Street Overlay Street overlay of approximately 0.5 to 0.75 miles depending on street width Snell Street between Bonanza Road and Spring Hill Drive 07/2019 10/2019 15 25 5 14

Sonora Tuolumne Road Maintenance & Rehabilitation

Centerline Striping and Street Markings 17/18 Carryover

Centerline Striping and Street Markings of various city streets including centerline and pavement markings using thermoplastic materials

Various City Streets: Snell-Washington Streetot City Limiits; Stewart Street-Lytton Street to Church Street; Lyons Street-Stewart Street to Greenley Raod; Mono Way-Greenley road to Sanguinetti Road; Sanguinetti Road-Grennley Road to Sanguinetti Loop Road; Saratoga Road-Shaws Falt to City limit; Guzzi Lane-Greenley Road to Paujline Court

08/2018 09/2018 3 5 5 14

Camarillo Ventura Road Maintenance & Rehabilitation Annual Resurfacing Asphalt Rubber Aggregate Membrane (ARAM), Slurry Seal, and appurtenant work

ADOBE WY from SANTA ROSA RD to CALLE ARENA; ALDER VIEW LN from HOLLYRIDGE DR to MISSION OAKS BL; ALIENTO WY from S END to N END; ALTA COLINA from COLONY DR to E END; ANDANTE CT from CALLE ARENA to N END; AQUA VERDE CT from ALIENTO WY to E END; ASHVIEW LN from HICKORY VIEW CR to WILLOW VIEW DR; BEECHVIEW CR from HOLLY VIEW to E END; BIRCH VIEW LN from ELDER VIEW LN to HOLLYRIDGE DR; BUENA MESA CT from W END to E END; BUENOS TIEMPOS DR from LADERA VISTA DR to COLONY DR; CALLE ARENA from CALLE CANON to CALLE BODEGA; CALLE BODEGA from CALLE CANON to N END; CALLE CANON from CALLE BODEGA to N END; CALLE MENDOTA from MISSION OAKS BL to VIA CUPERTINO; CARISSA CT from CALLE ARENA to N END; CD RD to CERVATO DR (E); VIA CARRANZA from CORTE VISTORA to MISSION OAKS BL; VIA CUPERTINO from S END to PASEO MONTELENA; VIA PACHECO from VIA CUPERTINO to N END; VILLA ADOBE from LOS PUEBLOS DR to COLONY DR; WILLOW VIEW DR from HOLLYRIDGE DR (W) to HOLLYRIDGE DR (E)

07/2018 10/2018 7 10 44 19

Fillmore Ventura Road Maintenance & Rehabilitation

Neighborhood Street Rehabilitation FY18-19

Pavement rehabilitation of various local streets to include patch repair, grinding, paving and appurtenant work.

BURSON LN, THIRD ST, ORANGE GROVE, OLD TELEGRAPH RD, WILEMAN, BARD, CLAY, MOUNTAIN VIEW, MAIN, LOS SERENOS, RIVE AND GOODENOUGH RD 09/2018 12/2018 15 20 37 19

Fillmore Ventura Road Maintenance & Rehabilitation

Sidewalk, Curb and Gutter Repairs (FY17-18 Carryover)

Repair of lifted/broken sidewalks, curb and gutter and ribbon gutter. Includes 4,000 square feet of sidewalks, 250 linear feet of curb and gutter and 220 square feet of ribbon gutter repairs.

Bard St (Saratoga to Clay); Clay St (Bard to Second); Mountain View St (Sespe to Main); Main St (Mountain View to Central); Los Serenos St (Ventura to Sierra Vista); River St (Sandalwood to Central); Goodenough Rd (Hinckley to Arrasmith)

09/2018 12/2018 20 30 37 19

Fillmore Ventura Road Maintenance & Rehabilitation

Street Resurfacing (FY17-18 Carryover)

Recycled Asphalt Pavement (RAP) Slurry Seal and crack sealing on 75,000 SF of pavement. Work is preventative maintenance to cost effectively extend the life on streets in good condition.

B St (s/o River); River St (B to A); Surrey Way; Carriage Place 09/2018 12/2018 10 20 37 19

Moorpark Ventura Road Maintenance & Rehabilitation Pavement Preservation General maintenance including but not limited to pavement maintenance and repairs

and repairs to adjacent facilities due to the work.Downtown area between Spring Road and Moorpark Avenue, north of Los Angeles Avenue and south of Wicks Road 07/2018 01/2019 5 10 44 27

Ojai Ventura Road Maintenance & Rehabilitation 2019 Road Rehabilitation Project The work comprises of street overlays, including cold planning, milling, placing

Rubberized Asphalt Concrete (RAC), concrete work, striping, and ADA curb ramps.

San Antonio St., Crestview Dr., Palomar Rd. Tico Rd., Rincon St., Santa Ana St., Lion St., Oak St., Ayers Ave., Fairway Lane, San Gabriel St., San Rafael St., Eucalyptus St., Summer St., Fairview Rd., McKee St., N. Montgomery St., Aliso St., Matilija St., Grandview Ave., Pleasant St., Douglas St.

05/2019 11/2019 15 25 37 19

Oxnard Ventura Road Maintenance & Rehabilitation

Rice Avenue Roadway Rehabilitation

The resurfacing project consists of a two-inch cold mill and 3/8-inch ARAM and finished with 2-inch ARHM. Rice Avenue from US Highway 101 to Fifth Street in the City of Oxnard. 03/2018 08/2018 10 15 44 19

Oxnard Ventura Road Maintenance & Rehabilitation

Cooper Road Roadway Rehabilitation

The resurfacing project will rehabilitate the neighborhood streets and improve pedestrian access. Cooper Road from Oxnard Boulevard to Juanita Avenue 05/2018 12/2018 10 15 44 19

Oxnard Ventura Road Maintenance & Rehabilitation

Auto Center Neighborhood Roadway Rehabilitation

Carryover Project from FY 17/18. The resurfacing project consists of a two-inch cold mill and 3/8 inch ARAM and finished with 2-inch ARHM.

The Auto Center Commercial Neighborhood area is east of US Highway 101, between N. Rose Avenue and Rice Avenue/Santa Clara Avenue in the City of Oxnard 01/2018 08/2018 15 20 44 19

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 116: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Port Hueneme Ventura Safety Pleasant Valley Crosswalk Intersection Upgrade

Accessibility Improvements and Crosswalk installation including signage, curb and gutter, sidewalk and bulb outs. Intersection Pleasant Valley & San Pedro St. 10/2018 02/2019 25 50 44 19

Port Hueneme Ventura Safety Citywide Pedestrian Safety (17/18 Ongoing)

Replacement of Cracked Sidewalks. Repair or replacement of uplifted sidewalks. Add additional Curb ramps in compliance with CALDAG and ADA.

Surfside Drive; Market Street; Hueneme Rd; N. Ventura Rd; Cindy; Bolder Drive; Patterson; West Channel Islands Blvd; Pleasant ValleyAll project locations are not final, each location will be selected based on priority need and resources throughout the year. Locations may be subject to change based on priority need and resources.

08/2018 04/2019 8 10 44 19

Port Hueneme Ventura Road Maintenance & Rehabilitation

Grind & Overlay for Select Streets (17/18 Carryover) Grind and 2-inch Overlay

Intersection of Park Ave & Ventura Rd. to Intersection of Park Ave & Bard Rd; Intersection of Joyce Dr. & N. 5th St. to Intersection of Joyce Dr. & Myrna Dr.; Intersection of Myrna Dr. & Florence Ave to Intersection of Myrna Dr. & S. J St.; Intersection of Scott St. & N. Ventura Rd. to Intersection of Scott St. & Willowbrook St.

07/2018 05/2019 2 10 44 19

Port Hueneme Ventura Road Maintenance & Rehabilitation Crackfill and Slurry (17/18 Ongoing) Fill Cracks and Slurry seal areas along Ventura Road. Intersection of E. Surfside Dr & N. Ventura Rd to Intersection of E. Channel Island Blvd & N. Ventura

Road 07/2018 09/2018 5 7 44 19

Port Hueneme Ventura Road Maintenance & Rehabilitation Microsurfacing (17/18 Carryover) Add a protective seal coat to extend the pavement life of Bolker Drive Intersection W. Channel Island & Bolker Dr. to Intersection W.Hemlock Rd & Bolker Dr.

Intersection W. Channel Island & Bolker Way to Intersection W.Hemlock Rd & Way 07/2018 09/2018 5 10 44 19

Port Hueneme Ventura Safety Citywide Crosswalk Upgrades (17/18 Ongoing)

Restripe Crosswalk with new highly reflective paint. Upgrade signs to highly reflective signs.

Bard Rd and N. 6th Pl.; Sunkist St and N. 6th St.; Bryce Canyon Ave & N. 6th St.; Bryce Canyon Ave and S. M St; Market St. and Port Hueneme Rd. 07/2018 10/2018 5 10 44 19

Port Hueneme Ventura Safety Market St. Crosswalk Intersection Upgrade New lighted crosswalk to be installed at intersection Intersection Market St & Hueneme Rd 09/2018 12/2018 10 15 44 19

Santa Paula Ventura Road Maintenance & Rehabilitation

Community Street Improvement Project

The project consists of pavement slurry seal, rehabilitation and resurfacing; curb ramp upgrades; traffic signal modifications (as needed) and curb and gutter repairs. Estimated design costs are $80,000.00 and estimated construction cost is $580,000.00.

Various City roads within the eastern and western City boundary along Telegraph Road and northern and southern City boundary along 10th Street and Hwy 150. 07/2018 05/2019 15 25 37 17

Santa Paula Ventura Complete Streets Components

Foothill/Hardison/Cameron Storm Drain Project

The project consists of installing a storm water quality treatment control BMP infiltration basin with 0.25-mile sediment capture chambers incorporating infiltration wells. Estimated design costs are $67,000.00 and estimated construction cost are $334,650.

Foothill Rd. from Ridge Crest Dr. to Steckel Dr. 07/2018 05/2018 10 20 37 17

Santa Paula Ventura Road Maintenance & Rehabilitation Community Sidewalk Repair Project The project consists of repairing 54,563-square feet sidewalk trip hazards. Estimated

design cost is $80,000.00 and estimated construction cost is $398,000.

Ventura St. (Seventh St. to Harvard Blvd.), High St. (Ojai Rd. to Guilberson St.), Orchard St. (Ojai Rd. to end), Virginia Terr. (Sixth St. to Ojai Rd.), Santa Barbara St. (Palm Ave. to Sixth St.), Peck Rd. (Harvard Blvd. to Santa Paula St.), Monte Vista Dr. (Sixth St. to Tenth St.), Oak St. (Ventura St. to Santa Barbara St.), Santa Paula St. (Palm Ave. to Sixth St.), Eleventh St. (Santa Paula St. to Saticoy St.), Twelfth St. (Saticoy St. to Santa Paula St.), Saticoy St. (Eleventh St. to Twelfth St.), Sixth St. (Santa Paula St. to Virginia Terr.), Santa Paula St. (Twelfth St. to Eleventh St.), Peralta Dr. (Santa Cruz St. to Santa Ana St.)

07/2018 02/2018 20 30 37 17

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 117: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Simi Valley Ventura Road Maintenance & Rehabilitation

FR 2018-19 Annual Minro Streets Rehabilitation Repave/Resurface streets pavements, and all appurtenant wor

Blackstock Avenue (Los Angeles Ave to Barnes St) Claudia Avenue (Heywood St to Lee St) Copley Street (Hilldale Ave to End) Elmdale Avenue (Brower St to Cochran St) Erica Street (Bridget Ave to Lee St) Fred Avenue (Sycamore Dr to Lee St) Garvin Avenue (Heywood St to Lee St) Golden Bear Court (Lake Park Dr to End) Golden Fern Court (Lake Park Dr to End) Golden Grove Court (Golden Park Pl to End) Goldenwood Circle (Lake Park Dr to Golden Moss Ct) Golden Moss Court (Lake Park Dr S to End) Golden Park Place (Lake Park Dr S to End) Golden Vine Court (Lark Park Dr S to End) Graceland Street (Elmdale Ave to Justin Ave) Hampton Avenue (Birchcroft St to Oak Haven Ave Hanley Avenue (Heywood St to Lee St) Harrington Road (Appleton Rd to E End) Heywood Street (Bridget Ave to Sycamore Dr) Hudspeth Avenue (Dakin Ave to Arcane St) Hudspeth Avenue (Kearney Ave to Dakin Ave) Hudspeth Avenue (Sutter Ave to Kearny Ave) Hudspeth Avenue (Wallace St to Fitzgerald Rd) Justin Avenue (Brower St to Cochran St) Knollhaven Street (Elmdale Ave to Justin Ave) Larch Street (Bigelow Ave to Wisteria St) Lawson Avenue (Sycamore Dr to Lee St) Lee Street (Marcella St to Lee St N) Lee Street North (Heywood St to Lee St) Marcella Street (Sycamore Dr to Sycamore Dr) Martha Morrison Drive North (Sycamore Ridge St to Cantrice St) Martha Morrison Drive North (Wood Ranch Parkway to Sycamore Ridge St) Martha Morrison Drive South (Cantrice St to Wood Ranch Parkway) Misty Falls Court (Lake Park Dr S to End) Misty Lake Court (Misty Trails Pl to End) Misty Trails Place (Lake Park Dr S to End) Racine Street (Sycamore Dr to Galena Ave) Ravenna Street (Racine St to Waldo St) School Street (Church St to Blackstock Ave) Silver Fern Court (Misty Trails Place to End)

09/2018 12/2018 15 20 38 27

Simi Valley Ventura Road Maintenance & Rehabilitation Carryover FY 2017/18 SB 1 Projects Repave/Resurface street paving and all appurtenant work

Ashley Dr. (Fourth St. to East End); Borden Ave. (Fitzgerald Rd. to Arcane); Brandon Ave. (Fitzgerald Rd. to South End); Hagen Court (Parkhurst St. to End); Heywood St. ( Sycamore Dr. to Bridget Ave.); Hudspeth Ave. (Fitzgerald Rd. to Sutter Ave.); Knollhaven St. (Elmdale Ave. to Justin Ave.); Smith Rd. (Kuehner Dr. to East End); Burnside St. (Elmdale Ave. to Justin Ave.); Hampton Ave. (Oak Haven Ave. to Birchcroft St.)

09/2018 12/2018 15 20 38 27

Thousand Oaks Ventura Road Maintenance & Rehabilitation

2018 Pavement Overlay and Resurfacing Program

Overlay and Resurface 34.1 miles of arterial and residential streets, reconstruction of 295 curb ramps to meet ADA compliance.

Streets City-Wide: Lynn Rd, Olsen Rd, Thousand Oaks Blvd, Townsgate Dr, Erbes Rd., Avenida de las Arboles, Valley Spring, Area 192, Area 197, Area 261, Area 41, Area 310, Area 308 and Area 32. 12/2017 12/2018 15 20 7 4

Ventura Ventura Road Maintenance & Rehabilitation Johnson Drive (Bristol to HWY 101)

This project consists of resurfacing Johnson Drive from Bristol Road to HWY 101. The project includes cold milling, pavement repairs, manhole and valve adjustments to grade, upgrading street signs, re-striping, replacement of traffic inductive loops, and asphalt overlay.

Along Johnson Drive from Bristol Road to HWY 101 southbound ramps 07/2018 06/2019 15 20 37 19

Ventura Ventura Road Maintenance & Rehabilitation

Victoria Avenue (Telephone to HWY 126)

This project consists of resurfacing Victoria Avenue from Telephone Road to HWY 126. The project includes cold milling, pavement repairs, manhole and valve adjustments to grade, upgrading street signs, re-striping, replacement of traffic inductive loops, concrete work, and asphalt overlay.

Along Victoria Avenue from Telephone Road to HWY 126 ramps 07/2018 06/2019 15 20 37 19

Ventura Ventura Road Maintenance & Rehabilitation Ralston Street (Portola to Victoria)

This project consists of resurfacing Ralston Street from Portola Road to Victoria Avenue. The project includes cold milling, pavement repairs, manhole and valve adjustments to grade, upgrading street signs, re-striping, replacement of traffic inductive loops, concrete work, and asphalt overlay.

Along Ralston Street from Portola Road to Victoria Avenue 07/2018 06/2019 15 20 37 19

Davis Yolo Complete Streets Components

Tim Spencer Alley Reconstruction 17/18 Carryover

Tim Spencer Alley, located between F and G and connecting Second and Third, has been in disrepair for several years. The sanitary sewer and the water mains are aging beyond repair and need replacing. Additionally the alley surface is damaged and does not flow properly. This project will replace the sewer and water mains and reconstruct the alley surface. The new development at 239 G Street desires a surface treatment similar to their property for a length near Third Street, along their property and will fund that portion of the project. Construction will have to be carefully implemented to minimize the businesses that use the alley for sewer, water, vehicle deliveries, etc.

Tim Spencer Alley - the Alley between F Street and G Street from Second Street to Third Street 03/2018 03/2019 18 20 4 3

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 118: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Davis Yolo Other H Street Project - DLL and Tunnel

Combining the scope of improvements near the Davis Little League fields and the H Street Tunnel entrance improvements, this project includes ADA compatible access along the Little League fields; resurface H Street from Eighth and north to the end; improved street lighting, especially near the fields; improving the west end of the tunnel entrance; improving the tunnel lighting; resurfacing the bike path from the east end of the tunnel to Drexel; and resolving the right of way issue at Drexel.

H Street between Eight Street parking lot south of Covell Blvd Bike/Ped Pathway between H Street and J Street 03/2018 05/2018 10 20 4 3

Davis Yolo Safety Birch Lane Elementary School Walk Bike Audit Report Improvements

High Priority infrastructure safety improvements for Birch Lane elementary school per the Walk Bike Audit Report. Includes safety improvements such as High visibility cross walks, curb ramps, curb extensions, mid-block crossings, refresh markings

Ponteverde and Tulip 06/2019 10/2019 8 10 4 3

Davis Yolo Safety Fifth Street Improvements (L to Pole Line) 17/18 Carryover

Design and construction of multi-modal and safety improvements including striping, Class IV bike lanes, transit stop improvements, mid-block, enhanced crossing. Fifth Street Improvements (L to Pole Line) 05/2019 09/2019 8 10 4 3

Davis Yolo Safety East Covell Bicycle Path - North Side

Install a bicycle path on the north side of East Covell Boulevard, from just west of J Street to Pole Line, roughly a half mile. This project was a result of the East Covell Corrider Plan (ECCP).

North side of E. Covell Blvd from Pole Line to J Street 05/2019 10/2019 10 20 4 3

Davis Yolo Road Maintenance & Rehabilitation

Transportation Infrastructure Rehab 17/18 Carryover

This CIP provides for a pavement management design and construction throughout the City. This is a multimillion dollar a year project to focus on maintaining and repairing streets throughout the City. In 17/18, two years worth of concrete was completed. The pavement and bike path package was not completed and is being carried over to 18/19.

Various locations/streets throughout Davis 11/2017 12/2018 10 20 4 3

Davis Yolo Road Maintenance & Rehabilitation

Mace Boulevard Corridor 17/18 Carryover

1) Resurface Mace Boulevard, and 2) increase non‐motorized transportation along the corridor and between the neighborhoods east and west of Mace Blvd, particularly increasing levels of bicycling to Pioneer Elementary School. The Project Scope includes resurfacing and restriping the entire corridor, reconstructing where needed, improving Mace/Cowell intersection for bicycles and pedestrians (e.g. remove free right turns/extend pedestrian refuge islands, installing bike boxes), installing two‐way protected, buffered cycle track on the east side, reconfiguring lanes from four to two plus turn lanes, installing a buffered bike lane on west side, and installing signal control (RRFB or HAWK) at San Marino.

Mace Blvdbetween Redbud Drive and Cowell Boulevard 03/2018 12/2018 8 10 4 3

Davis Yolo Road Maintenance & Rehabilitation Transportation Infrastructure Rehab

This CIP provides for pavement management design and construction throughout the City. This is a multi million dollar a year project to focus on maintaining and repairing streets throughout the City. This year's project includes a pavement rehabilitation and bike path package.

various locations in the city of Davis, CA consisting of 9.9 Square Miles 08/2018 06/2019 10 20 4 3

Davis Yolo Complete Streets Components

Fourteenth Street / Villanova Drive Improvements 17/18 Carryover

These improvements have been designated “High Priority” safety improvements for North Davis ES from the Walk Bike Audit Report and street resurfacing. Includes buffered bike lanes, intersection curb extensions, pedestrian refuge islands, restriping crosswalks, green bike lane striping alongside loading zones.

Fourteenth Street from F Street to Oak Avenue; and Villanova Drive from Anderson Road to Sycamore Lane 02/2019 06/2019 10 20 4 3

Davis Yolo Road Maintenance & Rehabilitation

L Street Improvements 17/18 Carryover

The work shall include reconstruction of L Street between 5th Street and Claremont Drive; a 1.3' full depth reclamation pavement section reconstruction, utility adjustments, curb and gutter, concrete flatwork, signage, striping and pavement markers on L Street from 5th Street to Claremont Drive.

L Street between Fifth Street and Claremont Drive. 05/2018 06/2019 8 10 4 3

West Sacramento Yolo Other Pavement Management System Update

Preparation of a multiyear Pavement Rehabilitation Program that includes updating PMS. The 2018 PMS update will include a comprehensive survey and inventory of City streets and roadway system.

The 2018 PMS update will survey and inventory the City streets and roadway system (approximately 200 centerline miles and 406 lane miles). 01/2018 01/2019 5 7 7 6

West Sacramento Yolo Road Maintenance & Rehabilitation

States Streets Neighborhood Pavement Rehabilitation

Rehabilitate the local street network including storm drainage repairs, ADA accessibility upgrades and pavement rehabilitation in an Old West Sacramento Neighborhood.

The project limits is bound by 15th Street (North), Jefferson Blvd (East), Stone Blvd (South) and Park Blvd (West). The streets within that boundary include Maryland Ave, Delaware Ave, Pennsylvania Ave, Alabama Ave, Virginia Ave Vermont Ave, Carolina Ave, Circle St, Alameda St, 16th St, 17th St, Regent St, Euclid St and 19th St.

01/2018 12/2019 5 10 7 6

West Sacramento Yolo Road Maintenance & Rehabilitation

West End of West Capitol Avenue Rehabilitation Design Phase of West Capitol Ave from I-80 to Enterprise Blvd (approximately 1 mile). West Capitol Avenue: I-80 to Enterprise Blvd 04/2018 12/2020 5 30 7 6

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).

Page 119: City- Fiscal Year 2018-19 Local Streets and Roads Proposed ... · City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List *The Proposed Project List will be finalized

City- Fiscal Year 2018-19 Local Streets and Roads Proposed Project List*The Proposed Project List will be finalized upon the Commission's adoption of the cities and counties eligible for funding.

August 3, 2018

Agency Name County Project Type Title Description Location Est. Project Start

Est. Project Completion

Est Useful Life Min

Est Useful Life Max

Assembly Districts Senate Districts

Winters Yolo Road Maintenance & Rehabilitation

Annual Road Maintenance Rehabilitation (FY 2018/19)

2.1 : (Anderson Avenue (From Railroad Avenue, West to Dead End) 111,456 square feet, Spot Repairs, Crack seals, Slurry Seals, Grind and Pave (Cracks) 2.2 : (Carrion Court, Priscilla Court) 39,420 SQUARE FEET, SPOT REPAIRS, CRACK SEALS, SLURRY SEALS2.3 : (THIRD STREET (ALL)) 80,532 SQUARE FEET, SPOT REPAIRS, CRACK SEALS, SLURRY SEALS2.4 : (MAIN STREET (GRANT AVENUE TO SECOND STREET)) 153,328 SQUARE FEET, SPOT REPAIRS, CRACK SEALS, SLURRY SEALS, GRIND AND PAVE CRACKS2.5 : (BETTY COURT (ALL)) 9,540 SQUARE FEET, SPOT REPAIRS, SLURRY SEALS, CRACK SEALS2.6 : (EAST BAKER STREET (RAILROAD AVENUE TO EAST MAIN STREET)), 113,596 SQUARE FEET, SLURRY SEAL, CRACK SEAL, SPOT REPAIR2.7 : (BAKER STREET (RAILROAD AVENUE, WEST TO DEAD END)) 65,052 SQUARE FEET, SLURRY SEALS, CRACK SEALS, SPOT REPAIRS2.8 : (EAST STREET (BETWEEN EAST ABKER STREET AND EAST MAIN STREET)) 29,472 SQUARE FEET, SLURRY SEAL, CRACK SEAL, SPOT REPAIR2.9 : (EAST STREET (EAST BAKER STREET TO DEAD END)) 11,808 SQUARE FEET, OVERLAY (GRIND AND PAVE)

2.1 : (Anderson Avenue (From Railroad Avenue, West to Dead End) 2.2 : (Carrion Court, Priscilla Court) 2.3 : (THIRD STREET (ALL)) 2.4 : (MAIN STREET (GRANT AVENUE TO SECOND STREET)) 2.5 : (BETTY COURT (ALL)) 2.6 : (EAST BAKER STREET (RAILROAD AVENUE TO EAST MAIN STREET)) 2.7 : (BAKER STREET (RAILROAD AVENUE, WEST TO DEAD END)) 2.8 : (EAST STREET (BETWEEN EAST ABKER STREET AND EAST MAIN STREET)) 2.9 : (EAST STREET (EAST BAKER STREET TO DEAD END)) *All locations are selected based on priority need and resources throughout the year, location may be subject to change.

11/2018 03/2019 5 15 4 3

Woodland Yolo Road Maintenance & Rehabilitation 2020 Road Rehabilitation Project

Roadway rehabilitation including asphalt roadway rehabilitation, repair damaged curb, gutter and sidewalk sections, improve ADA access at intersections, improve delineation of, and widen bike lanes. Project will improve access to shopping, school and neighborhoods within and through the project area.

Matmor Road from E. Main Street to Gibson Road and Gum Avenue from East Street to Matmor Road. 12/2019 12/2022 15 20 4 3

Marysville Yuba Road Maintenance & Rehabilitation Preventative Maintenance Program

Phase 1 includes sealing and maintenance repairs on roadway segments that are the highest traffic. Slurry Seal repair. First Street ‐ F Street to B Street

First Street ‐ F Street to B Street 02/2019 03/2019 5 10 3 4

Marysville Yuba Road Maintenance & Rehabilitation Preventative Maintenance Program

Phase 1 includes sealing and maintenance repairs on roadway segments that are the highest traffic. Slurry seal project. Yuba Street ‐ 6th Street to 10th Street

Yuba Street ‐ 6th Street to 10th Street 02/2019 03/2019 5 10 3 4

Marysville Yuba Road Maintenance & Rehabilitation Preventative Maintenance Program

Phase 1 includes sealing and maintenance repairs on roadway segments that are the highest traffic. Slurry seal project. D Street ‐ 1st Street to 3rd Street

D Street ‐ 1st Street to 3rd Street 02/2019 03/2019 5 10 3 4

Marysville Yuba Road Maintenance & Rehabilitation Preventative Maintenance Program

Phase 1 includes sealing and maintenance repairs on roadway segments. Slurry seal project. F Street ‐ 3rd Street to 10th Street

F Street ‐ 3rd Street to 10th Street 02/2019 03/2019 5 10 3 4

Marysville Yuba Road Maintenance & Rehabilitation Preventative Maintenance Program

Phase 1 includes sealing and maintenance repairs on roadway segments that are the highest traffic. Slurry seal project. H Street ‐ 3rd Street to 14th Street

H Street ‐ 3rd Street to 14th Street 08/2018 10/2018 5 10 3 4

Wheatland Yuba Other Malone Avenue Culvert at S. Grasshopper Slough

This project would replace a failed culvert on Malone Ave at S Grasshopper Slough and repave sections of Malone Avenue. New pavement would accommodate future Class I bikeway.

On Malone Avenue at S Grasshopper Slough crossing. 07/2018 10/2018 50 50 3 4

Wheatland Yuba Road Maintenance & Rehabilitation

Hooper Street Pavement Resurfacing

This project would resurface approximately 800 feet of Hooper Street, around Wheatland Elementary School and Virginia School. On Hooper Street between Hwy 65 and Olive Street. 04/2019 08/2019 20 20 3 4

Wheatland Yuba Road Maintenance & Rehabilitation G Street This project would level and seal a portion of G Street On G Street from Wheatland Road to 3rd Street 06/2018 08/2018 10 15 3 4

Wheatland Yuba Road Maintenance & Rehabilitation F Street This project would level and seal a portion of F Street On F Street between Wheatland Road and 3rd Street 06/2018 08/2018 10 15 3 4

Wheatland Yuba Road Maintenance & Rehabilitation 3rd Street This project would level and seal a portion of 3rd Street On 3rd Street between F Street and G Street 06/2018 08/2018 10 15 3 4

*All project detail is based on the Proposed Project Lists submitted to the Commission for Fiscal Year 2018-19 Program Funding and are consistent with Streets and Highways Code Sections 2030(b)(1) and 2034(a)(1).