CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 www.kirklandwa.gov MEMORANDUM To: Kurt Triplett, City Manager From: Dave Snider, P.E., Capital Projects Manager Ray Steiger, P.E., Public Works Director Date: May 24, 2012 Subject: NE 85 th STREET/114 th AVENUE NE INTERSECTION IMPROVEMENTS ACCEPT WORK RECOMMENDATION : It is recommended that City Council accept the work on the NE 85 th Street/114 th Avenue NE Intersection Improvements, as completed by Road Construction Northwest, Inc., of Renton, WA, and establish the statutory 45-day lien period. In addition, it is recommended that Council authorize a budget increase of $10,000 from the NE 85 th Street corridor contingency. BACKGROUND AND DISCUSSION : The NE 85 th Street Corridor Improvements combine several significant capital projects to provide enhancements for the entire NE 85 th Street corridor between 114 th and 132 nd Avenues NE. The NE 85 th Street/114 th Avenue NE Intersection Improvements, the subject of this memo, is one component of the overall corridor improvements. Other elements of the corridor improvements identified in the City’s Capital Improvement Program are: CST 0075 – NE 85 th Street Utility Underground Conversion (now under construction ) CTR 0078 – NE 85 th Street and 132 nd Avenue NE Intersection Improvements CTR 0080 – NE 85 th Street and 124 th Avenue NE Intersection Improvements CWA 0140 – NE 85 th Street watermain improvements (modified project in CIP) CNM 0051 – Rose Hill Business District Sidewalks CSD 0025 – NE 85 th Street Detention and Sediment Control CTR 0056 – NE 85 th Street Queue Bypass CST 0006 002 – NE 85 th Street Overlay The corridor improvements include the currently under construction undergrounding of a significant portion of the overhead utilities, the provision of continuous sidewalks and pedestrian improvements on both sides of NE 85 th Street, new sidewalks along both sides of 124 th Avenue NE between NE 80 th and NE 90 th Streets, traffic signal upgrades and additional capacity improvements at key intersections, and related utility improvements (Attachment A). The intersection improvements at NE 85 th Street & 114 th Avenue NE provide increased capacity for the southbound-to-eastbound left-turn movement with the Looking south at NE 85 th St/114 th Ave NE Council Meeting: 06/05/2012 Agenda: Establishing Lien Period Item #: 8. f. (1).
Transcript
Page 1: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 www.kirklandwa.gov

MEMORANDUM To: Kurt Triplett, City Manager From: Dave Snider, P.E., Capital Projects Manager Ray Steiger, P.E., Public Works Director Date: May 24, 2012 Subject: NE 85th STREET/114th AVENUE NE INTERSECTION IMPROVEMENTS ACCEPT WORK RECOMMENDATION: It is recommended that City Council accept the work on the NE 85th Street/114th Avenue NE Intersection Improvements, as completed by Road Construction Northwest, Inc., of Renton, WA, and establish the statutory 45-day lien period. In addition, it is recommended that Council authorize a budget increase of $10,000 from the NE 85th Street corridor contingency. BACKGROUND AND DISCUSSION: The NE 85th Street Corridor Improvements combine several significant capital projects to provide enhancements for the entire NE 85th Street corridor between 114th and 132nd Avenues NE. The NE 85th Street/114th Avenue NE Intersection Improvements, the subject of this memo, is one component of the overall corridor improvements. Other elements of the corridor improvements identified in the City’s Capital Improvement Program are:

• CST 0075 – NE 85th Street Utility Underground Conversion (now under construction ) • CTR 0078 – NE 85th Street and 132nd Avenue NE Intersection Improvements • CTR 0080 – NE 85th Street and 124th Avenue NE Intersection Improvements • CWA 0140 – NE 85th Street watermain improvements (modified project in CIP) • CNM 0051 – Rose Hill Business District Sidewalks • CSD 0025 – NE 85th Street Detention and Sediment Control • CTR 0056 – NE 85th Street Queue Bypass • CST 0006 002 – NE 85th Street Overlay

The corridor improvements include the currently under construction undergrounding of a significant portion of the overhead utilities, the provision of continuous sidewalks and pedestrian improvements on both sides of NE 85th Street, new sidewalks along both sides of 124th Avenue NE between NE 80th and NE 90th Streets, traffic signal upgrades and additional capacity improvements at key intersections, and related utility improvements (Attachment A). The intersection improvements at NE 85th Street & 114th Avenue NE provide increased capacity for the southbound-to-eastbound left-turn movement with the

Looking south at NE 85th St/114th Ave NE

Council Meeting: 06/05/2012 Agenda: Establishing Lien Period Item #: 8. f. (1).

Page 2: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

Memorandum to Kurt Triplett May 24, 2012

Page 2

construction of a second left-turn lane on the intersection’s north leg (Attachment B). Additional improvements to the intersection include a new traffic signal, video detection, CCTV cameras, fiber-optic connection to the future traffic control center (ITS), new traffic control signage, improved illumination and new electrical services. The intersection improvements also include surface water quality enhancements, new sidewalks, a new crosswalk, new curb ramps with ADA improvements, and the replacement of street trees. The NE 85th Street/114th Avenue NE Intersection Improvements originally included an eastbound to southbound I-405 queue by-pass component and had an overall approved budget of $3,166,000. However, during design of the improvements, coordination issues with the WSDOT reached an impasse which was delaying delivery of the balance of the intersection improvements. At their February 15, 2011, meeting, in order to proceed with the turn lane component of the Project, Council authorized the queue by-pass elements to be moved to a new project CTR 0056 -- NE 85th Street HOV Queue Bypass Project along with $841,000 in funding. Council also approved reprogramming of $1,005,000 to the overall 85th Street corridor contingency and awarded the construction contract to Road Construction Northwest for $560,012.03 (Attachment C). Signal mast arms and other long delivery lead-time items plus traffic control coordination with the adjacent (and now completed) intersection improvements at 6th Street & Central Way delayed the start of construction until late August, 2011; physical completion of the Project was achieved in March, 2012. The total amount paid to the Contractor was $587,970 which includes three change orders totaling $27,958. Change orders included a signal controller foundation modification, the relocation of existing junction boxes that were located in the WSDOT right-of-way, and changes to the signal programming in order to provide for post-construction level-of-service enhancements. Including additional inspection time and staff time to administer the Project; total costs exceed the February 15, 2011 budget by $10,000. Staff recommends using $10,000 of the overall 85th Street contingency on the Project. Attachments: (3)

Page 3: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

Complete Sidewalks

85th/114th Intersection Improvements

Complete SidewalksIntersectionImprovements

IntersectionImprovements

Utility UndergroundConversion Project120th Ave NE to 128th Ave NE

Surface WaterImprovement

NE 85TH ST

114T

H AVE

NE

Video Detection System: 120th Avenue NE 122nd Avenue NE 124th Avenue NE 128th Avenue NE 132nd Avenue NE

120th 124th 122nd 128th 132nd

Completed Oct., 2011

Completion: Mar., 2012

S I 40

5

N I 405

NE 85TH ST

NE 80TH ST

132N

D AV

E NE

128T

H AV

E NE

126T

H AV

E NE

124T

H AV

E NE

120TH AVE NE

122N

D AV

E NE

NE 92ND ST

NE 90TH ST

NE 87TH ST

NE 83RD ST2ND AVE

KIRKL

AND WAY

KIRKLAND AVE

OHDE AVE

SLAT

ER ST

S

NE 88TH ST

116T

H AV

E NENE 91ST ST

CEDA

R ST

NE 94TH ST

NE 7 8TH P L123R

D AV

E NE

131S

T AVE

NE

130T

H AV

E NE

122N

D CT NE

NE 94TH CT

SLAT

ER AV

E NE

127T

H PL

NE

NE 81ST PLNE 80T H PL

125T

H AV

E NE

NE 92ND PL

124T

H CT

NE

129T

H AVE

NE

NE 90TH ST

126T

H AV

E NE

NE 94TH ST

122N

D AV

E NE

NE 94TH ST

NE 90TH ST

±

Attachment A

Lake Washington

Forbes Lake

Totem Lake

Utility Conversion ProjectConduit Only128th Ave NE to 132nd Ave NE

Vicinity MapNE 85th Street Corridor Improvements

NE 85th Street at 114th Ave NE Intersection Improvements

Area Map

Page 4: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

116T

H AV

E NE

§̈¦405

NE 85TH ST

NE 90TH ST

NE 91ST ST

NE 88TH ST

NE 87TH ST

112T

H AV

E NE

KIRKLAND AVE

2ND AVE

O HDE AVE

KIRKL

AND W

AY

Produced by the City of Kirkland.© 2011, the City of Kirkland, all rights reserved.

No warranties of any sort, includ ing but not limited to accuracy, fitness or merchantability, accompany this product.

Vicinity Map0 500 1,000 1,500

Feet

0 8 16 24Feet

NE 85th St at 114th Ave NE Intersection Improvements

New Crosswalk

Add Addtional Turn Lane

New Bike Lane

New Curb Edge

Realigned Sidewalk

!e

New Signal Controller

-Location: \\SRV-GISF01\Vol1\PW\Mxds\CIP\ForDonAnderson\Jan2011\ctr0079000_2.mxd-Print Date: 2/4/2011

Airphoto 2009

ATTACHMENT BVICINITY MAP

Page 5: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

$- $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000

FINAL REVISION SHEET

ACCEPT WORK

AWARD CONTRACT

ORIGINAL BUDGET

ESTIMATED COST

PHAS

E

PROJECT BUDGET REPORT

ENGINEERING

RIGHT OF WAY

CONSTRUCTION

CONTINGENCY

NE 85th ST/114th AVE NE INTERSECTION IMPROVEMENTS (CTR-0079 )

(2009 - 2014 CIP)

(February 2011)

CITY OF KIRKLAND SOUND TRANSIT

Attachment C

move to CTR-0056 (2011 - 2016 CIP)

($841,000)

move to "Contingency" NE 85th St Corridor Project

($1,005,000)

ORIGINAL BUDGET

$3,166,000 CTR-0079 = $1,320,000

(This memo) propose utilizing $10,000 from corridor contingency

FINAL COSTS $1,330,000

Page 6: CITY OF KIRKLAND › Assets › City+Council › Council+Packets › ...CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 MEMORANDUM To:

3

$9,970,000

$- $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 $16,000,000 $18,000,000

ANTICIPATED EXPENSES

CURRENT BUDGET

ESTIMATED COST

PROJECT BUDGET REPORT NE 85th STREET CORRIDOR IMPROVEMENTS

(COMBINED)

Attachment D

Costs Bid Package 1: 1) TR-0079 $ 588,000 114th Intersection Bid Package 2: 2a) ST-0075 $ 34,100 Video detection Bid Package 3: 2b) ST-0075 $ 1,976,712 Undergrounding power [low bid] 2b) ST-0075 $ 480,000 Schedule 74 executed Sept., 2011 Bid Package 4: 3a) NM-0051 $ 1,100,000 124th Avenue NE Sidewalks Bid Package 5: 3b) NM-0051 $ 3,500,000 NE 85th Street Sidewalks 4) TR-0078 $ 300,000 132nd Intersection 5) TR-0080 $ 290,000 124th Intersection 6) SD-0025 $ 362,000 Storm drainage 7) WA-0140 $ TBD NE 85th Watermain Improvemtents Bid Package 6: 8) TR-0056 $ 500,700 114th Intersection (Phase 2) Bid Package 7: 9) ST-06/002 $ 865,100 Overlay of 85th Street

CITY OF KIRKLAND $12,270,800 SOUND TRANSIT $3,735,000

ENGINEERING RIGHT OF WAY CONSTRUCTION CONTINGENCY

1 2a 2b a 4 9

Timeline (Accept June, 2012)

(Accepted Nov., 2011)

(Award Dec., 2011)

4th quarter 2012 1st quarter 2012

4th quarter 2012

4th quarter 2013

4th quarter 2013

(This Memo)

NE 85th St Corridor Project, Construction Breakdown

APPROVED BUDGET

$16,005,800

54 3b 3 6 7 8


Recommended