+ All Categories
Home > Documents > City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of...

City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of...

Date post: 25-Aug-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
20
7/11/2012 1 Coordinated Infrastructure Improvements, Out of Sight, Out of Your Mind CIPP Lining of the Grand River Ave. Water Main Presented by: Gary M. Mekjian, P.E. Farmington Hills DPS Director John Thompson, LiquiForce Services City of Farmington Hills, MI
Transcript
Page 1: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

1

Coordinated Infrastructure Improvements,

Out of Sight, Out of Your Mind

CIPP Lining of the Grand River Ave. Water

Main

Presented by:

Gary M. Mekjian, P.E. Farmington Hills DPS Director

John Thompson, LiquiForce Services

City of Farmington Hills, MI

Page 2: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

2

City of Farmington Hills

Project location

Page 3: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

3

Project History

Project purpose was to replace a existing 8” cast

iron water main

Existing main was over 50 years old

City was experiencing a high number of breaks,

causing service interruptions

Water Main provides partial service to Botsford

Hospital

No capacity issues

Project History

City originally intended on replacing existing water

main using HDD 10” HDPE pipe.

MDOT scheduled reconstruction of Grand River Ave

from 8 Mile Road to approximately Tuck Road

City’s intent was to install new water main in advance

of the pending MDOT project scheduled for the

Spring/Summer 2011

HDD Project was designed, bid, and awarded in

August of 2010

Page 4: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

4

Troubles Ahead

Contract began field verifying utility locations

City plans showed existing AT&T duct banks per

information provided by the utility

Surprise!!!! Information provided was not

accurate, making constructability questionable.

Cutting Bait

Worked with AT&T and Contractor to explore adjusting duct banks. No relief

Contractor provided estimate for a change order to HDD pipe under pavement. Price was too high

Decision was made to cancel contract. City and contractor negotiated a settlement

Contractor was paid for time and material. City stored materials at it’s DPW facility for the following years project

Page 5: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

5

Plan B

City decided on bidding project with 2 options

Option A: design and bid a HDD HDPE

project.

Option B: rehabilitate the existing water main

with cured in-place pipe (CIPP) lining

technology

Bids were received and opened on April 15,

2011

Option A (HDD)

2 bids received ranging from $785,000 to $1,100,000 Drawbacks

Would be constructed under the outside curb lane of Grand River Ave

Would require extensive coordination with MDOT project scheduling

Impact to businesses along corridor

Potential for future O&M issues with water main being under pavement of a busy major street

Advantages Lower cost

Page 6: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

6

Option B (CIPP)

1 bid received at $1,050,000

Drawbacks

More expensive than low bid for Option A

Fire Protection modifications required

Potential for vandalism of temporary system

Advantages

Much less disruption to businesses

Less restoration

Less service interruptions

Minimal scheduling conflicts with MDOT project

Reuse of existing pipe (Green)

Moving Ahead

Staff recommended proceeding with Option B

although construction cost was higher

Decision was based on advantages of Option B

being greater that the additional cost

These points were communicated very clearly by

both staff and City Manager to the City Council

Page 7: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

7

CIPP Lining Process

Project Scope

Rehabilitate 4,600 ft of 8” diameter cast iron

Establish Temporary Water Supply

R&R 12 Gate Valves & Well

R&R 8 hydrants

R&R 8 Dbox

15 – 8” reconnections

2 – 6” reconnections

Vertical bend under 36” storm Sewer

Why Rehabilitate

Page 8: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

8

Temporary Supply System

Temporary Supply System

Page 9: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

9

Temporary Hydrant in Place of

Hydrant

Within the project limits was Farmington Hills Fire Station #3

Drive Approach or Entrance

Page 10: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

10

Temporary Service Connections

Access Points to Water Main

Access points are strategically placed to minimize the disruption

Page 11: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

11

Other Utilities within ROW

6 fiber duct banks and a high pressure gas main

were parallel to the water main

Pipe Cleaning Operations

All scale is removed

Page 12: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

12

Various Mechanical Devices are

Utilized to Clean the Pipe

Clean Pipe

Page 13: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

13

CIPP Materials

Stand-alone, structurally sound liner which can

take the place of the host pipe if gradual

deterioration leads to disintegration

Rehabilitate 6” thru 12” mains

Made up of two concentric, tubular, plain weave

polyester jackets

Inner jacket bonded with polyurethane layer

Page 14: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

14

Tube Impregnation

Liner Installation

Page 15: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

15

Liner Insertion

Forming Shoe

Page 16: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

16

Internal Service Reconnection

Service connections 2” and smaller are opened / reconnected

via internal means eliminating the need for excavations

Post CIPP Installation

Page 17: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

17

Before & After

MDEQ Requirements

Standard disinfection and sampling of both

temporary supply & lined pipe

Pressure testing will be to the greater of 1.25

times the normal operating pressure or 75 p.s.i.

Allowable leakage is 0gpm

Page 18: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

18

Pressure Test Considerations

Test is done prior to reinstatement of services

Test is done on each line segment lined

immediately following installation

Gate Well Replacement

Only 60” of width existed between duct banks

thus 48” gate wells were required.

Page 19: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

19

Gate Well Rehabilitation

To prevent having to close the hospital entrance a trenchless

structure rehabilitation process was used thus eliminating the

need for excavation

Trenchless Prevents

Page 20: City of Farmington Hills, MI 1 - Gary Mekjian.pdfCity of Farmington Hills, MI 7/11/2012 2 City of Farmington Hills Project location 7/11/2012 3 Project History Project purpose was

7/11/2012

20

Lessons Learned

When to use CIPP Water Main Rehabilitation No capacity issues

Utility conflicts

Tight construction limits

Environmental and neighborhood disruption

Historically significant areas.

Better Local Control Over Rights-of-Way Legislative challenges

Get accurate as-built location of utilities when possible (duh-stating the obvious)

Restoration May want to perform in-house (small areas = difficulty finding sub-

contractors)

Question & Answer

Contact information:

Gary M. Mekjian, P.E.

Director of Public Services

City of Farmington Hills, Michigan

Phone Number: (248) 871-2530

[email protected]

John Thompson

Liquiforce Services, USA

(734) 955-2508

[email protected]


Recommended