CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC UTILITIES CAPITAL IMPROVEMENT PROGRAM CONTENTS 2013 Capital Budget ................................................................................................................................................................................................................ AA1 Summary of Projects by Division All Years ........................................................................................................................................................................... AA3 Summary of Projects by Funding Source All Years .............................................................................................................................................................. AA6 General Manager ..................................................................................................................................................................................................................... AB1 Electric ..................................................................................................................................................................................................................................... AC1 Telecommunications ............................................................................................................................................................................................................... AD1 Water ..................................................................................................................................................................................................................................... AE1 i
Transcript
Page 1: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

CITY OF KETCHIKAN, ALASKA 2013 ‐ 2017 KETCHIKAN PUBLIC UTILITIES CAPITAL IMPROVEMENT PROGRAM 

 CONTENTS 

    2013 Capital Budget ................................................................................................................................................................................................................ AA‐1  Summary of Projects by Division ‐ All Years ........................................................................................................................................................................... AA‐3  Summary of Projects by Funding Source ‐ All Years .............................................................................................................................................................. AA‐6  General Manager ..................................................................................................................................................................................................................... AB‐1  Electric   ..................................................................................................................................................................................................................................... AC‐1  Telecommunications ............................................................................................................................................................................................................... AD‐1  Water   ..................................................................................................................................................................................................................................... AE‐1 

i

Page 2: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

2013 Capital Budget

Revenues/ Federal/State Loans/ Revenue 2013Department/Division/Project Reserves Grants Other Bonds Total

AdministrationFinancial & Accounting Information System 20,000 20,000

Administration Division Total 20,000 20,000Sales, Marketing & Customer Service

NoneSales, Marketing & Customer Service Division Total

Electric DivisionWhitman Lake Hydroelectric Plant 2,500,000 1,500,000 4,000,000Silvis Rock Bolt Repair 40,000 40,000Silvis Slip Ring Replacement 5,000 5,000Ketchikan Substation Switches 30,000 30,000Downtown Underground Vault Upgrade 29,345 29,345North Tongass/DOT Reconstruction Contribution 40,000 40,000Ketchikan Tunnel Penstock Valves Replacement 50,000 50,000Beaver Falls Powerhouse Exterior Coating 150,000 150,000ASD Metering and Load Management 35,000 35,000Regulator Controllers 10,000 10,000Vehicles & Moving Equipment 275,000 275,000Beaver Falls No. 1 Refurbishment 80,000 80,000Beaver Falls Unit 1 Exciter 12,190 12,190Transmission & Distribution Switches 20,000 20,000Mechanical Speed Switch Upgrade 30,000 30,000GIS Platform Migration 35,000 35,000Transformer Purchase 215,000 215,000Operating Equipment 272,150 272,150Lower Silvis Tuff Boom 36,000 36,000Electric Div. Headquarters - Pitched Roof and Siding Replacem 250,000 250,000Reimbursable Projects 80,000 80,000Additional Projects 150,000 150,000Raptor Protection Program 5,000 5,000Achilles Dam Diversion 150,000 150,000Energy Conservation & Efficiency Program 150,000 150,000

Electric Division Total 2,149,685 2,500,000 1,500,000 6,149,685

KPU CIP AA-1

Page 3: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

2013 Capital Budget

Revenues/ Federal/State Loans/ Revenue 2013Department/Division/Project Reserves Grants Other Bonds Total

Telecommunications DivisionNormal Growth and Repair - Buildings 20,000 20,000Normal Growth and Repair - Central Office Switching 12,750 12,750Normal Growth and Repair - Copper Cable 4,000 4,000Normal Growth and Repair - Fiber Cable 107,500 107,500Normal Growth and Repair - CO Transmission 411,500 411,500Normal Growth and Repair - Wireless 4,375 4,375Normal Growth and Repair - Provisioning 35,000 35,000Fiber to the Home 130,000 130,000Remote Cabinets for Advanced Services 30,000 30,000Core Network Upgrade 200,000 200,000Blade Server 95,000 95,000Multi-Dwelling Unit Project 26,250 26,250Operating Equipment 30,000 30,000PC Hardware and Software 10,000 10,000Structured Cabling Project 26,250 26,250Headend Expansion 222,950 222,950Video Set Top Boxes 120,000 120,0004G Mobile 3,100,000 3,100,000Microwave Link to Prince Rupert 1,900,000 1,900,000ISP email Server 21,875 21,875WiFi 15,000 15,000Heat Reclamation 35,700 35,700

Telecommunications Division Total 1,558,150 5,000,000 6,558,150Water Division

Chlorination Plant Improvements 127,900 127,900Raw Water Transmission Main 300,000 300,000Water Distribution Grid Improvements 60,000 60,000Additional Projects 60,000 60,000Water Service Upgrade 30,000 30,000Backflow Prevention Program 10,000 10,000Mill Street Water Improvements 75,000 75,000Sayles & Gorge Street Bridges Water Improvements 10,000 10,000Dunton Street Viaduct Water Improvements 10,000 10,000UV Disinfection Facility 100,000 100,000

Water Division Total 782,900 782,900

GRAND TOTAL 4,510,735 2,500,000 5,000,000 1,500,000 13,510,735

KPU CIP AA-2

Page 4: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Division - All Years

Prior Five Year ProjectDivision/Project Years 2013 2014 2015 2016 2017 Total Total

AdministrationFinancial & Accounting Information System 406,392 20,000 20,000 426,392

Administration Total 406,392 20,000 20,000 426,392

Sales, Marketing & Customer ServiceNone

Sales, Mrktng & Cust Service Total

Electric DivisionWhitman Lake Hydroelectric Plant 26,371,708 4,000,000 4,000,000 30,371,708Silvis Rock Bolt Repair 40,000 40,000 40,000Silvis Slip Ring Replacement 20,000 5,000 5,000 25,000Ketchikan Substation Switches 30,000 30,000 30,000Downtown Underground Vault Upgrade 171,114 29,345 135,655 150,000 240,000 100,000 655,000 826,114Pennock-KIA Upgrades 138,316 550,000 500,000 1,050,000 1,188,316North Tongass/DOT Reconstruction Contribution 40,000 40,000 40,000Ketchikan Tunnel Penstock Valves Replacement 50,000 420,000 470,000 470,000Beaver Falls Powerhouse Exterior Coating 150,000 150,000 150,000ASD Metering and Load Management 35,000 35,000 35,000Regulator Controllers 20,000 10,000 10,000 30,000Vehicles & Moving Equipment 275,000 375,000 250,000 400,000 250,000 1,550,000 1,550,000Beaver Falls #1 Referbish 80,000 80,000 80,000Beaver Falls Unit 1 Exciter 12,190 12,190 12,190Transmission & Distribution Switches 40,000 20,000 80,000 25,000 25,000 150,000 190,000Mechanical Speed Switch Upgrade 20,000 30,000 30,000 50,000GIS Platform Migration 35,000 35,000 35,000Bailey Exhaust Stack Painting 150,000 150,000 150,000Transformer Purchase 215,000 385,000 250,000 175,000 175,000 1,200,000 1,200,000Operating Equipment 272,150 200,000 200,000 200,000 200,000 1,072,150 1,072,150Lower Silvis Tuff Boom 36,000 36,000 36,000Electric Div. Headquarters - Pitched Roof & Sidin 15,450 250,000 250,000 265,450Reimbursable Projects 80,000 82,500 85,000 87,600 90,200 425,300 425,300Additional Projects 150,000 150,000 154,500 159,100 164,000 777,600 777,600Raptor Protection Program 86,119 5,000 5,000 5,000 5,000 5,000 25,000 111,119Generator Air Filtration Systems 25,000 25,000 25,000Property Acquisition - Materials & Equipment Storage 400,000 100,000 500,000 500,000Beaver Falls Switch Gear Replacement 500,000 500,000 500,000Silvis Hydro Runner Replacement 250,000 250,000 250,000Beaver Falls Governor Upgrade 3 & 4 ISOC. 80,000 170,000 250,000 250,000Ward Cove Substation Replacement 125,000 125,000 250,000 250,000Capacitor Bank Optimization 150,000 150,000 150,000LED Stret Lighting Program 20,000 30,000 30,000 30,000 30,000 120,000 140,000Energy Conservation & Efficiency Program 150,000 150,000 150,000Achilles Creek Diversion Dam 150,000 150,000 150,000

Electric Division Total 26,902,707 6,149,685 3,613,155 2,354,500 1,491,700 1,014,200 14,623,240 41,525,947

KPU CIP AA-3

Page 5: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Division - All Years

Prior Five Year ProjectDivision/Project Years 2013 2014 2015 2016 2017 Total Total

Telecommunications DivisionNormal Growth and Repair - Buildings 20,000 25,000 25,000 25,000 25,000 120,000 120,000Normal Growth and Repair - Central Office Switching 12,750 25,000 25,000 25,000 25,000 112,750 112,750Normal Growth and Repair - Copper Cable 4,000 25,000 25,000 25,000 25,000 104,000 104,000Normal Growth and Repair - Fiber Cable 107,500 250,000 250,000 250,000 250,000 1,107,500 1,107,500Normal Growth and Repair - CO Transmission 411,500 500,000 500,000 500,000 500,000 2,411,500 2,411,500Normal Growth and Repair - Wireless 4,375 15,000 15,000 15,000 15,000 64,375 64,375Normal Growth and Repair - Provisioning 35,000 25,000 25,000 25,000 25,000 135,000 135,000Fiber to the Home 709,136 130,000 200,000 100,000 100,000 100,000 630,000 1,339,136Remote Cabinets for Advanced Services 30,000 50,000 50,000 50,000 50,000 230,000 230,000Core Network Upgrade 75,000 200,000 150,000 350,000 425,000Blade Server 95,000 120,000 25,000 25,000 25,000 290,000 290,000Switch Upgrade 750,000 750,000 750,000Gravina Island Buildout 100,000 100,000 100,000 100,000 400,000 400,000Multi-Dwelling Unit Project 26,250 200,000 150,000 150,000 150,000 676,250 676,250Operating Equipment 30,000 35,000 25,000 25,000 25,000 140,000 140,000PC Hardware & Software 10,000 30,000 20,000 20,000 20,000 100,000 100,000Vehicle Acquisition 330,000 200,000 100,000 100,000 730,000 730,000Structured Cabling Project 25,000 26,250 26,250 51,250Headend Expansion 222,950 150,000 100,000 100,000 100,000 672,950 672,950Video Set Top Boxes 120,000 150,000 100,000 100,000 100,000 570,000 570,0004G Mobile 50,000 3,100,000 200,000 100,000 100,000 3,500,000 3,550,000Microwave Link to Prince Rupert 1,900,000 1,900,000 1,900,000Wi-Max 225,000 50,000 50,000 50,000 375,000 375,000ISP email Server 21,875 72,000 93,875 93,875Wi-Fi 15,000 60,000 40,000 40,000 40,000 195,000 195,000Heat Reclamation Project 35,700 35,700 35,700

Telecommunications Division Total 859,136 6,558,150 3,687,000 1,925,000 1,825,000 1,725,000 15,720,150 16,579,286

KPU CIP AA-4

Page 6: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Division - All Years

Prior Five Year ProjectDivision/Project Years 2013 2014 2015 2016 2017 Total Total

Water DivisionChlorination Plant Improvements 189,100 127,900 127,900 317,000Raw Water Transmission Main 300,000 300,000 300,000Water Distribution Grid Improvements 60,000 60,000 60,000 60,000 60,000 300,000 300,000Additional Projects 60,000 60,000 60,000 60,000 60,000 300,000 300,000Water Service Upgrade Program 30,000 30,000 30,000 30,000 30,000 150,000 150,000Backflow Prevention Program 10,000 10,000 10,000 10,000 10,000 50,000 50,000Potable Water Fill Station 90,000 90,000 90,000Water Street Trestle No. 2 - Utility Replacement 100,000 100,000 100,000Schoenbar Road Water Improvements 93,805 2,117,053 2,117,053 2,210,858Chatham Avenue Water Main Replacement 34,369 847,960 847,960 882,329Harris Street Water Improvements 71,678 685,000 685,000 756,678Mill Street Water Improvements 75,000 6,000,000 6,075,000 6,075,000Lund & Millar St. Water Improvements 50,000 50,000 50,000Denali Ave Water Improvements 35,000 35,000 35,000Sayles & Gorge Street Bridges Water Improvements 10,000 180,000 190,000 190,000Austin St. Water Improvements 60,000 773,000 833,000 833,0002nd Avenue Water & Sewer Improvements - Ph I 400,000 400,000 400,000Adams Street Water Improvements 15,000 15,000 15,000 30,000Dunton Street Viaduct Water Improvements 10,000 168,000 178,000 178,000Woodland Ave. Water Improvements 25,000 25,000 25,000Highlands Reservoir Replacement 100,000 100,000 100,000Confidence Reservoir Replacement 100,000 100,000 100,000Hoadley Creek/Jackson St Water Improvements 140,000 450,000 590,000 590,000Second Avenue Water & Sewer - Phase II 50,000 1,100,000 1,150,000 1,150,000UV Disinfection Facility 235,000 100,000 100,000 335,000

Water Division Total 638,952 782,900 3,600,013 6,603,000 1,425,000 2,498,000 14,908,913 15,547,865

TOTAL 28,807,187 13,510,735 10,900,168 10,882,500 4,741,700 5,237,200 45,272,303 74,079,490

KPU CIP AA-5

Page 7: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Funding Source - All Years

StateRevenue Drinking

Prior Generating Federal/State Local/ Revenue WaterDivision/Project Years Fund Grants Other Bonds Loan Fund Total

AdministrationFinancial & Accounting Information System 406,392 20,000 426,392

Administration Total 406,392 20,000 426,392

Electric DivisionWhitman Lake Hydroelectric Plant 26,371,708 2,500,000 1,500,000 30,371,708Silvis Rock Bolt Repair 40,000 40,000Silvis Slip Ring Replacement 20,000 5,000 25,000Ketchikan Substation Switches 30,000 30,000Downtown Underground Vault Upgrade 171,114 655,000 826,114Pennock-KIA Upgrades 138,316 1,050,000 1,188,316North Tongass/DOT Reconstruction Contribution 40,000 40,000Ketchikan Tunnel Penstock Valves Replacement 470,000 470,000Beaver Falls Powerhouse Exterior Coating 150,000 150,000ASD Metering and Load Management 35,000 35,000Regulator Controllers 20,000 10,000 30,000Vehicles & Moving Equipment 1,550,000 1,550,000Beaver Falls #1 Referbish 80,000 80,000Beaver Falls Unit 1 Exciter 12,190 12,190Transmission & Distribution Switches 40,000 150,000 190,000Mechanical Speed Switch Upgrade 20,000 30,000 50,000GIS Platform Migration 35,000 35,000Bailey Exhaust Stack Painting 150,000 150,000Transformer Purchase 1,200,000 1,200,000Operating Equipment 1,072,150 1,072,150Lower Silvis Tuff Boom 36,000 36,000Electric Div. Headquarters - Pitched Roof & Siding 15,450 250,000 265,450Reimbursable Projects 425,300 425,300Additional Projects 777,600 777,600Raptor Protection Program 86,119 25,000 111,119Generator Air Filtration Systems 25,000 25,000Property Acquisition - Materials & Equipment Storage 500,000 500,000Beaver Falls Switch Gear Replacement 500,000 500,000Silvis Hydro Runner Replacement 250,000 250,000Beaver Falls Governor Upgrade 3 & 4 ISOC. 250,000 250,000Ward Cove Substation Replacement 250,000 250,000Capacitor Bank Optimization 150,000 150,000LED Street Lighting Program 20,000 120,000 140,000Energy Conservation & Efficiency Program 150,000 150,000Achilles Creek Diversion Dam 150,000 150,000

Electric Division Total 26,902,707 10,623,240 2,500,000 1,500,000 41,525,947

KPU CIP AA-6

Page 8: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Funding Source - All Years

StateRevenue Drinking

Prior Generating Federal/State Local/ Revenue WaterDivision/Project Years Fund Grants Other Bonds Loan Fund Total

Telecommunications DivisionNormal Growth and Repair - Buildings 120,000 120,000Normal Growth and Repair - Central Office Switching 112,750 112,750Normal Growth and Repair - Copper Cable 104,000 104,000Normal Growth and Repair - Fiber Cable 1,107,500 1,107,500Normal Growth and Repair - CO Transmission 2,411,500 2,411,500Normal Growth and Repair - Wireless 64,375 64,375Normal Growth and Repair - Provisioning 135,000 135,000Fiber to the Home 709,136 630,000 1,339,136Remote Cabinets for Advanced Services 230,000 230,000Core Network Upgrade 75,000 350,000 425,000Blade Server 290,000 290,000Switch Upgrade 750,000 750,000Gravina Island Buildout 400,000 400,000Multi-Dwelling Unit Project 676,250 676,250Operating Equipment 140,000 140,000PC Hardware & Software 100,000 100,000Vehicle Acquisition 730,000 730,000Structured Cabling Project 25,000 26,250 51,250Headend Expansion 672,950 672,950Video Set Top Boxes 570,000 570,0004G Mobile 50,000 400,000 3,100,000 3,550,000Microwave Link to Prince Rupert 1,900,000 1,900,000Wi-Max 375,000 375,000ISP email Server 93,875 93,875Wi-Fi 195,000 195,000Heat Reclamation Project 35,700 35,700

Telecommunications Division Total 859,136 10,720,150 5,000,000 16,579,286

KPU CIP AA-7

Page 9: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Summary of Projects by Funding Source - All Years

StateRevenue Drinking

Prior Generating Federal/State Local/ Revenue WaterDivision/Project Years Fund Grants Other Bonds Loan Fund Total

Water DivisionChlorination Plant Improvements 189,100 127,900 317,000Raw Water Transmission Main 300,000 300,000Water Distribution Grid Improvements 300,000 300,000Additional Projects 300,000 300,000Water Service Upgrade Program 150,000 150,000Backflow Prevention Program 50,000 50,000Potable Water Fill Station 90,000 90,000Water Street Trestle No. 2 - Utility Replacement 100,000 100,000Schoenbar Road Water Improvements 93,805 1,481,937 635,116 2,210,858Chatham Avenue Water Main Replacement 34,369 593,572 254,388 882,329Harris Street Water Improvements 71,678 480,000 205,000 756,678Mill Street Water Improvements 75,000 4,200,000 1,800,000 6,075,000Lund & Millar St. Water Improvements 50,000 50,000Denali Ave Water Improvements 35,000 35,000Sayles & Gorge Street Bridges Water Improvements 10,000 127,000 53,000 190,000Austin St. Water Improvements 60,000 541,000 232,000 833,0002nd Avenue Water & Sewer Improvements - Phase I 280,000 120,000 400,000Adams Street Water Improvements 15,000 15,000 30,000Dunton Street Viaduct Water Improvements 10,000 117,600 50,400 178,000Woodland Ave. Water Improvements 25,000 25,000Highlands Reservoir Replacement 30,000 70,000 100,000Confidence Reservoir Replacement 30,000 70,000 100,000Hoadley Creek/Jackson St Water Improvements 140,000 315,000 135,000 590,000Second Avenue Water & Sewer - Phase II 50,000 770,000 330,000 1,150,000UV Disinfection Facility 235,000 100,000 335,000

Water Division Total 638,952 2,047,900 9,046,109 3,814,904 15,547,865

TOTAL 28,807,187 23,411,290 9,046,109 7,500,000 1,500,000 3,814,904 74,079,490

KPU CIP AA-8

Page 10: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Prior Reappro- New Total Project Title Priority Years priated Funding Total 2014 2015 2016 2017 Project

Financial & Accounting System Replacement 1 406,392 20,000 20,000 426,392

Total 406,392 20,000 20,000 426,392

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 406,392 20,000 20,000 426,392

Total 406,392 20,000 20,000 426,392

Adopted 2013 Projected Requirements

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Department: General Manager

Adopted 2013 Projected Requirements

KPU CIP AB-1

Page 11: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Department: KPU General Manager Project Priority: 1 Project Number:

Project Title: Financial & Accounting Information System Replacemen Start Date: 01/07 Estimated Project Cost: End Date: 12/13 Design Description: Land/Right-of-Way Consultation 41,975 Construction Equip, Software & Implementation Services 374,917

Other - Training 9,500Project Total 426,392

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 406,392 20,000 20,000 426,392

Total 406,392 20,000 20,000 426,392

Adopted 2013 Projected Requirements

The project involves the replacement of the City's financial and accounting information system. The City's current system is over 30years old. In 2011, the City awarded a contract to New World Systems to acquire a license to use their Logos Financial and AccountingSystem. Implementation began in September 2011 and the City expects to complete the project by December 2013. The total project isexpected to cost $892,000. Finance is requesting that remaining funds that have been appropriated for this proeject be carried over to2012 and an additional $20,000 in new funding. These funds will be used for hardware and software contingenices outside the contractwith New World resources to supplement the Finance Department during critical phases of the implementation process. We anticipatethat there will be a need to contract with local firms to provide data entry services and backfill some of our staff positions. The cost of thisproject is being funded equally by General Government and KPU.

KPU CIP AB-2

Page 12: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Prior Reappro- New Total Project Title Priority Years priated Funding Total 2014 2015 2016 2017 Project

Generation (Hydro and Diesel) Projects Whitman Lake Hydroelectric Plant Project 1 26,371,708 4,000,000 4,000,000 30,371,708Silvis Slip Rings Replacement 3 20,000 5,000 5,000 25,000Pennock-KIA Upgrades 6 138,316 550,000 500,000 1,188,316Ketchikan Tunnel Penstock Valves Replacement 8 50,000 50,000 420,000 470,000Beaver Falls #1 Refurbish 13 80,000 80,000 80,000Beaver Falls Unit 1 Exciter 14 12,190 12,190 12,190Mechanical Speed Switch Upgrade 16 20,000 10,000 20,000 30,000 50,000Generator Air Filtration Systems 26 25,000 25,000Beaver Falls Switch Gear Replacement 28 500,000 500,000Silvis Hydro Runner Replacement 29 250,000 250,000Beaver Falls Governor Upgrade 3 & 4 ISOC. 30 80,000 170,000 250,000Ward Cove Substation Replacement 31 125,000 125,000 250,000Achilles Creek Diversion Dam 35 150,000 150,000 150,000Transmission and Distribution ProjectsKetchikan Substation Switches 4 30,000 30,000 30,000Downtown Underground Vault Upgrade 5 171,114 29,345 29,345 135,655 150,000 240,000 100,000 826,114North Tongass Reconstruction Contribution 7 40,000 40,000 40,000ASD Metering and Load Management 10 35,000 35,000 35,000Regulator Controllers 11 20,000 10,000 10,000 30,000Transmission & Distribution Switches 15 40,000 20,000 20,000 80,000 25,000 25,000 190,000Transformer Purchase 19 215,000 215,000 385,000 250,000 175,000 175,000 1,200,000Reimbursable Projects 23 80,000 80,000 82,500 85,000 87,600 90,200 425,300Raptor Protection Program 25 86,119 5,000 5,000 5,000 5,000 5,000 5,000 111,119Capacitor Bank Optimization 32 150,000 150,000General Plant ProjectsSilvis Rock Bolt Repair 2 40,000 40,000 40,000Beaver Falls Powerhouse Exterior Coating 9 150,000 150,000 150,000Vehicles & Moving Equipment 12 275,000 275,000 375,000 250,000 400,000 250,000 1,550,000GIS Platform Migration 17 35,000 35,000 35,000Bailey Exhaust Stack Painting 18 150,000 150,000Operating Equipment 20 272,150 272,150 200,000 200,000 200,000 200,000 1,072,150Lower Silvis Tuff Boom 21 36,000 36,000 36,000Electric Division Headquarters - Pitched Roof & Siding 22 15,450 209,550 40,450 250,000 265,450Additional Projects 24 150,000 150,000 150,000 154,500 159,100 164,000 777,600Property Acquisition - Material & Equipment Storage 27 400,000 100,000 500,000LED Street Lighting Program 33 20,000 30,000 30,000 30,000 30,000 140,000Energy Conservation & Efficiency Program 34 150,000 150,000 150,000

Total 26,902,707 306,085 5,843,600 6,149,685 3,613,155 2,354,500 1,491,700 1,014,200 41,525,947

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 2,167,707 306,085 4,553,600 4,859,685 3,613,155 2,354,500 1,491,700 1,014,200 15,500,947State Grant 11,025,000 11,025,000Revenue Bond 13,710,000 1,290,000 1,290,000 15,000,000

Total 26,902,707 306,085 5,843,600 6,149,685 3,613,155 2,354,500 1,491,700 1,014,200 41,525,947

Adopted 2013 Projected Requirements

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Division: Electric

Adopted 2013 Projected Requirements

KPU CIP AC-1

Page 13: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 1 Project Number:

Project Title: Whitman Lake Hydroelectric Project Start Date: 01/11 Estimated Project Cost: End Date: 12/13 Design/License 3,715,770Description: Land/Right-of-Way 422,000 Construction Management 1,200,000 Construction 14,265,300 Equipment 4,960,000

Other (Hatchery) 1,520,000Other (Financing Costs) 1,578,638

Project Total 27,661,708

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 1,636,708 1,636,708State Grant 11,025,000 11,025,000Revenue Bond 13,710,000 1,290,000 1,290,000 15,000,000

Total 26,371,708 1,290,000 1,290,000 27,661,708

Adopted 2013 Projected Requirements

The 4.6 MW Whitman Lake Hydroelectric Project will use water from the existing Whitman Lake reservoir to generateup to 12,500,000 kWh of electricity for KPU customers. Projected load increases indicate that KPU will requireadditional generation and capacity within the next 3-4 years. FERC issued a project license in March 2009 and hasgranted KPU a two-year extension of time to commence construction. KPU must begin construction no later thanMarch 2013.

KPU CIP AC-2

Page 14: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 2 Project Number:

Project Title: Silvis Rock Bolt Repair Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/License 10,000Description: Land/Right-of-Way Construction Management Construction 25,000 Equipment 5,000

Other

Project Total 40,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 40,000 40,000 40,000

Total 40,000 40,000 40,000

Adopted 2013 Projected Requirements

The 2010 FERC Part 12 Inspection Report for the Beaver Falls Project recommended that the rock bolts on the slopeabove the Upper Silvis Powerhouse be tested, reset or replaced as necessary using approved procedures to the levelof their original specifications. In a plan submitted to FERC, KPU stated that it would investigate the originalspecifications for installation of the rock bolts, inspect the site and determine whether the work can be done by KPUpersonnel or whether it must be contracted. The work must be performed by 2013.

KPU CIP AC-3

Page 15: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 3 Project Number:

Project Title: Silvis Slip Ring Replacement Start Date: 01/12 Estimated Project Cost:End Date: 12/13 Design/License

Description: Land/Right-of-Way Construction Management Construction 25,000 Equipment

Other

Project Total 25,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 20,000 5,000 5,000 25,000

Total 20,000 5,000 5,000 25,000

Adopted 2013 Projected Requirements

The slip rings at Silvis are old and thinning from years of machining. A new set is necessary in the event that thecurrent rings fail.

KPU CIP AC-4

Page 16: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 4 Project Number:

Project Title: Ketchikan Substation Switches Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/LicenseDescription: Land/Right-of-Way Construction Management Construction Equipment 30,000

Other

Project Total 30,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 30,000 30,000 30,000

Total 30,000 30,000 30,000

Adopted 2013 Projected Requirements

The 12.47 kV switches in the 6 distribution feeder bays have been identified as a weak point in the system, with thepotential to cause extended outages to the downtown core, Pennock/Clam Cove and south to Oyster Avenue. Thereare 56 switches to be replaced.

KPU CIP AC-5

Page 17: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 5 Project Number:

Project Title: Downtown Underground Vault Upgrade Start Date: 01/11 Estimated Project Cost: End Date: 12/17 Design 50,000Description: Land/Right-of-Way 20,000 Construction Management Construction 399,114 Equipment 357,000

Other Project Total 826,114

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 171,114 29,345 29,345 135,655 150,000 240,000 100,000 826,114

Total 171,114 29,345 29,345 135,655 150,000 240,000 100,000 826,114

Adopted 2013 Projected Requirements

Work will continue to upgrade the downtown underground electrical system, including the underground vaults in theareas that are prone to tide and rainwater flooding, show signs of deteriorating structural integrity and presentcontinual maintenance issues. Vault No. 5, located under the intersection of Deermount & Stedman Streets, willbe the next facility to be upgraded. Vault No. 3 will be undertaken in conjunction with the City's Stedman StreetPromenade Project. Future years will include Vaults Nos. 0, 1, 2 and 4. Other aspects such as area switches,transformers, conduit, etc. will be upgraded as deemed necessary.

KPU CIP AC-6

Page 18: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 6 Project Number:

Project Title: Pennock-Ketchikan International Airport Start Date: 01/12 Estimated Project Cost: Upgrades End Date: 12/15 Design/License 150,000Description: Land/Right-of-Way Construction Management Construction 500,000 Equipment 538,316

Other

Project Total 1,188,316

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 138,316 550,000 500,000 1,188,316Proposed Grant

Total 138,316 550,000 500,000 1,188,316

Adopted 2013 Projected Requirements

A preliminary design study will be undertaken to provide material specifications, installation methods, costestimates, regulatory involvment, etc. to replace the armored 12.47 kV submarine cable that serves the airport.

KPU CIP AC-7

Page 19: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 7 Project Number:

Project Title: North Tongass/DOT Reconstruction Contribution Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/LicenseDescription: Land/Right-of-Way Construction Management Construction 40,000 Equipment

Other

Project Total 40,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 40,000 40,000 40,000

Total 40,000 40,000 40,000

Adopted 2013 Projected Requirements

DOT&PF is scheduled to peform work on North Tongass between Ward Cove and Refuge Cove in 2013. Work willinclude re-aligning portions of the existing overhead power lines, including replacing up to seventeen (17) poles.Funds will be tranferred to DOT&PF for a small portion of the work that has been determined to be KPU'sresponsibility.

KPU CIP AC-8

Page 20: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 8 Project Number:

Project Title: Ketchikan Tunnel Penstock Valves Replacement Start Date: 01/12 Estimated Project Cost: End Date: 12/14 Design 50,000Description: Land/Right-of-Way Construction Management Construction 280,000 Equipment 140,000

Other Project Total 470,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 50,000 50,000 420,000 470,000

Total 50,000 50,000 420,000 470,000

Adopted 2013 Projected Requirements

The gate valves on the penstocks at the downstream end of the Ketchikan power tunnel are old and are near the endof their reliable service life. They must be capable of closing under flow and are critical to penstock safety. Thevalves are embedded in concrete and will be difficult to remove or to replace them due to their location. As the tunnelprovides the City's only potable water supply, it cannot be drained during the work.

KPU CIP AC-9

Page 21: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 9 Project Number:

Project Title: Beaver Falls Powerhouse Exterior Coating Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design Description: Land/Right-of-Way Construction Management Construction 150,000 Equipment

Other Project Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 150,000 150,000 150,000

Total 150,000 150,000 150,000

Adopted 2013 Projected Requirements

The exterior shell of Beaver Falls Powerhouse, built in 1954, contains asbestos and is flaking off the building. Signsof water intrusion into the concrete walls is apparent. Further delay in remedial action is not prudent. Beaver Fallsis Ketchikan's top producing hydroelectric plant. This project will include exterior asbestos abatement of the 120 'x30' building and re-sealing the concrete structure with an asbestos-free coating. Exterior material to be removedduring this project include:

- Surface coat/sealer of concrete shell (friable)- Caulking around penetrations and doors (friable)

KPU CIP AC-10

Page 22: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 10 Project Number:

Project Title: ASD Metering and Load Management Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design Description: Land/Right-of-Way Construction Management Construction 10,000 Equipment 25,000

Other Project Total 35,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 35,000 35,000 35,000

Total 35,000 35,000 35,000

Adopted 2013 Projected Requirements

The revenue metering at Alaska Ship and Drydock located on the secondary side of the ASD owned transformer does notmeet metering standards. Specifically, the metering shares circuitry devices (protective relays) that can place a burden onthe circuitry and affect the accuracy of the meter readings. Further, the existing metering can not be serviced without ashutdown of the shipyard, which is almost impossible to schedule. New metering will be located on the KPU owned 34.5 kVprimary accessible, which will provide access to the division to maintain the metering at its convenience. SCADA feedback ofreal time data to Bailey will be added. Real time monitoring does not currently exist to allow for load management duringsystem tight supply events or system disturbances per the PSA. Further, a breaker will be added to support emergency loadshedding.

KPU CIP AC-11

Page 23: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 11 Project Number:

Project Title: Regulator Controllers Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 30,000

OtherProject Total 30,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 20,000 10,000 10,000 30,000

Total 20,000 10,000 10,000 30,000

Adopted 2013 Projected Requirements

A standard SCADA controller package has been implemented on voltage regulators in the Point Higgins Substation. Themove to SCADA control was required to improve voltage control and minimize losses. The budgeted amount is for continuingthis SCADA controller package for voltage regulators in the remaining substations.

KPU CIP AC-12

Page 24: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 12 Project Number:

Project Title: Vehicles & Moving Equipment Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 1,550,000

OtherProject Total 1,550,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 275,000 275,000 375,000 250,000 400,000 250,000 1,550,000

Total 275,000 275,000 375,000 250,000 400,000 250,000 1,550,000

Adopted 2013 Projected Requirements

This project is for the purchase of two new/replacement vehicles and moving equipment for the Electric Division. In order tomaintain an efficient and safe operating fleet, vehicles and equipment need to be replaced based on a regular cycle. Vehiclereplacement in previous years has been minimal. The following is a schedule of the vehicles approaching end of life:

1) Replace bucket truck #11 (1990) with a new 65' reach double bucket single-axle vehicle $255,0002) Replace flat bed truck #19 (1991) with a new vehicle $20,000

KPU CIP AC-13

Page 25: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 13 Project Number:

Project Title: Beaver Falls No. 1 Refurbishment Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design Description: Land/Right-of-Way Construction Management 15,000 Construction 50,000 Equipment 15,000

Other Project Total 80,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 80,000 80,000 80,000

Total 80,000 80,000 80,000

Adopted 2013 Projected Requirements

Unit No. 1 rotor dates back to 1904 and the insulation is in poor condition. Additionally, the pedestal bearings showexcessive thrust movement and will require rebabbiting.

KPU CIP AC-14

Page 26: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 14 Project Number:

Project Title: Beaver Falls Unit No. 1 Exciter Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 12,190

OtherProject Total 12,190

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 12,190 12,190 12,190

Total 12,190 12,190 12,190

Adopted 2013 Projected Requirements

Excitation equipment on Beaver Falls Unit No. 1 performs slowly and does not compensate with Unit Nos. 3 & 4during voltage changes. Unit No. 1 is a rotating exciter with a rheostat voltage regulator. Replacement of therheostat with a controller to work with the rotating exciter should improve response and compensation with UnitNos. 3 and 4 static exciters.

KPU CIP AC-15

Page 27: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 15 Project Number:

Project Title: Transmission & Distribution Switches Start Date: 01/11 Estimated Project Cost: End Date: 12/16 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 190,000

OtherProject Total 190,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 40,000 20,000 20,000 80,000 25,000 25,000 190,000

Total 40,000 20,000 20,000 80,000 25,000 25,000 190,000

Adopted 2013 Projected Requirements

Manual disconnect switches along the 34.5 kV sub-transmission and 12.47 kV distribution lines are deteriorated and difficultto operate. These switches are necessary for safety clearances during maintenance and outage periods. These funds willalso allow switches to be placed in new areas throughout the system for greater sectionalizing capability, which is critical tosystem integrity. This is a continuation of the program intended to address one aspect of the aging electrical system.

KPU CIP AC-16

Page 28: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 16 Project Number:

Project Title: Mechanical Speed Switch Upgrade Start Date: 01/12 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 50,000

OtherProject Total 50,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 20,000 10,000 20,000 30,000 50,000

Total 20,000 10,000 20,000 30,000 50,000

Adopted 2013 Projected Requirements

The mechanical speed switches on the Ketchikan and Beaver Falls hydroelectric plants require expensivereplacement parts and many hours of labor to maintain. This request is to replace them with an electronic unit asis installed at Silvis.

KPU CIP AC-17

Page 29: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 17 Project Number:

Project Title: GIS Platform Migration Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/License 5,000Description: Land/Right-of-Way Construction Management Construction 30,000 Equipment

Other

Project Total 35,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 35,000 35,000 35,000

Total 35,000 35,000 35,000

Adopted 2013 Projected Requirements

The divison's existing GIS platform, 4DL/Certalogic, has been in place since 2003. The company has abandoned theNorth American market and is no longer keeping up with current software revisions. Migration to anAutoDesk/AutoCAD based platform would standardize with the City PW's GIS software, utilizing existing hardware.GIS has proven invaluable for engineering/design, outage response and financial purposes.

KPU CIP AC-18

Page 30: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 18 Project Number:

Project Title: Bailey Exhaust Stack Painting Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/LicenseDescription: Land/Right-of-Way Construction Management Construction 150,000 Equipment

Other

Project Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 150,000 150,000

Total 150,000 150,000

Adopted 2013 Projected Requirements

This project is to paint all four stacks with a proper coating that can protect the exaust system from corrosion whilewithstanding the high temperatures. The current rust coated stacks emphasize the ongoing deterioration and areasthetically distressing to citizens and visitors of Ketchikan alike.

KPU CIP AC-19

Page 31: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 19 Project Number:

Project Title: Transformer Purchase Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 1,200,000

OtherProject Total 1,200,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 215,000 215,000 385,000 250,000 175,000 175,000 1,200,000

Total 215,000 215,000 385,000 250,000 175,000 175,000 1,200,000

Adopted 2013 Projected Requirements

KPU has historically seen demands of 3 to 5 kW per residence for residential service. Typically, a 25 kWdistribution transformer has been installed to serve 5 to 7 residences. Due to the rapid conversion from oil heat,many residences are requiring a 10 to 15 kW electric heating system, which will quickly overload existingdistribution service transformers. Many of KPU's existing service transformers will be overloaded and will requirereplacement. Many large commercial padmount transformers are nearing end of life and need to be replacedbefore they become an electrical hazard to the public or begin leaking oil.

KPU CIP AC-20

Page 32: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 20 Project Number:

Project Title: Operating Equipment Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction Equipment 1,072,150

Other Project Total 1,072,150

17810 12190

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 272,150 272,150 200,000 200,000 200,000 200,000 1,072,150

Total 272,150 272,150 200,000 200,000 200,000 200,000 1,072,150

Adopted 2013 Projected Requirements

Purchase of new or replacement equipment for the meter shop, warehouse and SCADA department. This equipment will beused for the operation and maintenance of electrical service.

1) SCADA Critical Parts $ 2,500 2) VHF Radios & Parts 1,350 3) Bailey Ops Weather Instrumentation 3,400 4) Bailey SCADA UPS Battery Replace 8,400 5) Skiff Outboard 7,500 6) Replacement Pallet Racks 25,000 7) Beaver Falls New Battery Charger 5,000 8) Recorder Equipment 10,000 9) Substation & Powerhouse Critical Spares 10,000

10) Capacitor Bank Potential Transformers 12,000 11) Ward Cove Substation Batter Bank Replacement 12,000 12) Test/Indication Equipment Repair & Recalibration 20,000 13) Substation & Powerhouse Electronic Meters 25,00014) Meters, Probes and Hand Tools 25,00015) Customer Current & Potential Transformers 35,00016) AMR Meters & Meter Replacement Parts 70,000

KPU CIP AC-21

Page 33: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 21 Project Number:

Project Title: Lower Silvis Tuff Boom Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 36,000

OtherProject Total 36,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 36,000 36,000 36,000

Total 36,000 36,000 36,000

Adopted 2013 Projected Requirements

This is to replace the original wooden log boom that prevents logs and debris from getting into the No. 3 and No. 4intake structures. The old one has been repaired several times and the logs are becoming saturated. This is aclean and long lasting replacement.

KPU CIP AC-22

Page 34: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 22 Project Number:

Project Title: Electric Division Headquarters - Pitched Roof Start Date: 01/11 Estimated Project Cost: and Siding Replacement End Date: 12/13 Design 15,450Description: Land/Right-of-Way Construction Management Construction 250,000 Equipment

OtherProject Total 265,450

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 15,450 209,550 40,450 250,000 265,450

Total 15,450 209,550 40,450 250,000 265,450

Adopted 2013 Projected Requirements

The roof over the entire Electric Division headquarters has leaked for years. The siding has developed holes and isshowing severe wear. Both the roof and siding are in need of replacement.

KPU CIP AC-23

Page 35: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 23 Project Number:

Project Title: Reimbursable Projects Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 425,300

OtherProject Total 425,300

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 80,000 80,000 82,500 85,000 87,600 90,200 425,300

Total 80,000 80,000 82,500 85,000 87,600 90,200 425,300

Adopted 2013 Projected Requirements

This account represents funds for materials for work that the division will be called upon to perform at the requestof outside agencies. Examples of reimbursable projects are new line extensions and damage to the electricalsystem resulting from accidents, negligence and vandalism. The division's expectation is that such work will bereimbursed 100%.

KPU CIP AC-24

Page 36: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 24 Project Number:

Project Title: Additional Projects Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction 777,600 Equipment

OtherProject Total 777,600

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 150,000 150,000 150,000 154,500 159,100 164,000 777,600

Total 150,000 150,000 150,000 154,500 159,100 164,000 777,600

Adopted 2013 Projected Requirements

This project represents funds for materials and labor for unidentified jobs that the division will be called upon toperform in 2012. Examples of additional projects include the installation of new transformers and banks oftransformers, upgrading existing transformers and banks and upgrading secondary lift poles. These non-reimbursable projects are O&M in nature but are capital since they represent new installations.

KPU CIP AC-25

Page 37: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 25 Project Number:

Project Title: Raptor Protection Program Start Date: 01/12 Estimated Project Cost: End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction Equipment 111,119

Other Project Total 111,119

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 86,119 5,000 5,000 5,000 5,000 5,000 5,000 111,119

Total 86,119 5,000 5,000 5,000 5,000 5,000 5,000 111,119

Adopted 2013 Projected Requirements

This regulatory driven program is ongoing and adds protective devices to the system at sites that have beendetermined to pose a risk to raptors as well as other wildlife, all while reducing the number of outages. Devicesinclude perch discouragers, conductor/insulator covers, bushing covers, insulated jumper wire and fused-cutoutcovers.

KPU CIP AC-26

Page 38: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 26 Project Number:

Project Title: Generator Air Filtration Systems Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 25,000

OtherProject Total 25,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 25,000 25,000

Total 25,000 25,000

Adopted 2013 Projected Requirements

Installation of a generator air filtration rack on each generator would minimize the amount of dirt and insects that gothrough the machines daily.

KPU CIP AC-27

Page 39: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 27 Project Number:

Project Title: Property Acquisition-Material & Equipment Storage Start Date: 01/14 Estimated Project Cost: End Date: 12/15 Design Description: Land/Right-of-Way 300,000 Construction Management Construction 125,000 Equipment 75,000

Other Project Total 500,000

17810 12190

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 400,000 100,000 500,000

Total 400,000 100,000 500,000

Adopted 2013 Projected Requirements

The Electric Divison will begin to look for property to purchase (approximately 1 to 2 acres) for the purpose ofconsolidating its material and equipment storage, which is currently spread between two smaller parcels. Powerpoles, wire reels, pad and pole-mount transformers, heavy equipment and the mobile substation would all bestored on the new secured property. Future improvements to the land would include fencing the entire perimeter,building containment for transformers and the bulk power pole areas, as well as a basic shed building to protect themobile substation from the weather. Currently, all transformers are stored near Ketchikan Powerhouse, locatedalongside Ketchikan Creek, presenting a spill hazard. The location needs access to the Tongass Highway systemfor large trucks and equipment, that does not run through residential neighborhoods and has at least basic sitepreparation already completed.

KPU CIP AC-28

Page 40: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 28 Project Number:

Project Title: Beaver Falls Switch Gear Replacement Start Date: 01/14 Estimated Project Cost: End Date: 12/15 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 500,000

OtherProject Total 500,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 500,000 500,000

Total 500,000 500,000

Adopted 2013 Projected Requirements

The Beaver Falls powerhouse switch gear has been in need of replacement for a number of years. It has beenidentified as containing asbestos and 2400 VAC breakers are contained within the cubicles. A recent HydroModernization study stated the need to replace the three generators excitation controllers and protection relays.Since there is no room within the control room to accommodate new machine breakers, the existing units wouldneed to be moved outside to the lower substation or onto the floor of the powerhouse. This is a major undertakingrequiring an established scope of work and detailed work schedule.

KPU CIP AC-29

Page 41: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 29 Project Number:

Project Title: Silvis Hydro Runner Replacement Start Date: 01/15 Estimated Project Cost: End Date: 12/15 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 250,000

OtherProject Total 250,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 250,000 250,000

Total 250,000 250,000

Adopted 2013 Projected Requirements

The division is again seeking to repair the original, aging steel runner for Silvis Hydro. This should work for sometime although a more permanent solution is needed. This would fund a new stainless steel runner.

KPU CIP AC-30

Page 42: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 30 Project Number:

Project Title: Beaver Falls Governor Upgrade (3&4 Isoc.) Start Date: 01/15 Estimated Project Cost: End Date: 12/16 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 250,000

OtherProject Total 250,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 80,000 170,000 250,000

Total 80,000 170,000 250,000

Adopted 2013 Projected Requirements

The current KPU hydro systems lack provision for isynchronous operation if islanded, as sometimes occurs duringoutages and restoration. This proposed upgrade would provide SCADA selection for isoc/droop governor operationfor Beaver Falls Nos. 3 & 4.

KPU CIP AC-31

Page 43: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 31 Project Number:

Project Title: Ward Cove Substation Replacement Start Date: 01/14 Estimated Project Cost: Engineering End Date: 12/15 Design/License 250,000Description: Land/Right-of-Way Construction Management Construction Equipment

Other

Project Total 250,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 125,000 125,000 250,000

Total 125,000 125,000 250,000

Adopted 2013 Projected Requirements

This project funds the engineering study to increase the capacity of the substation to meet growing loads. Theprospective change would double the present capacity.

KPU CIP AC-32

Page 44: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 32 Project Number:

Project Title: Capacitor Bank Optimization Start Date: 01/15 Estimated Project Cost: End Date: 12/15 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 150,000

OtherProject Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revnue Generating Fund 150,000 150,000

Total 150,000 150,000

Adopted 2013 Projected Requirements

This project funds a study to determine optimum placement and usage of cap banks on the KPU system. Thisassures stable voltage control during customer load changes.

KPU CIP AC-33

Page 45: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 33 Project Number:

Project Title: LED Street Lighting Program Start Date: 01/12 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 140,000

OtherProject Total 140,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 20,000 30,000 30,000 30,000 30,000 140,000

Total 20,000 30,000 30,000 30,000 30,000 140,000

Adopted 2013 Projected Requirements

LED street lighting and induction street lighting will be purchased and installed on an as yet to be chosen City street to gatherenergy consumption and maintenance data, as well as garner customer input to determine if LEDs are a viable alternative tothe standard high-pressure sodium lights. The program will be modeled after similar efforts being undertaken in Skagway,Anchorage, Fairbanks, and Sitka. If successful, a gradual migration to LEDs/induction lights on all City streets and ROWs willbe undertaken. It should be noted that neither LEDs nor induction lights arepermitted on State ROWs.

No new purchases will be made in 2013 to give time to observe the lights that were installed in the fall of 2012.

KPU CIP AC-34

Page 46: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 34 Project Number:

Project Title: Energy Conservation & Efficiency Program Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment

Other 150,000Project Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 150,000 150,000 150,000

Total 150,000 150,000 150,000

Adopted 2013 Projected Requirements

This project funds the energy conservation efforts provided by management or consulting service providers for the Energy Conservation and Efficiency Program project.  

KPU CIP AC-35

Page 47: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Electric Project Priority: 35 Project Number:

Project Title: Achilles Creek Diversion Dam Project Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design/LicenseDescription: Land/Right-of-Way Construction Management Construction 150,000 Equipment

Other (Hatchery)Other (Financing Costs)

Project Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 150,000 150,000 150,000

Total 150,000 150,000 150,000

Adopted 2013 Projected Requirements

This project funds the design of the Achilles Creek Diversion Dam project.

KPU CIP AC-36

Page 48: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Prior Reappro- New Total Project Title Priority Years priated Funding Total 2014 2015 2016 2017 Project

REGULATEDNormal Growth and Repair - Buildings 1 20,000 20,000 25,000 25,000 25,000 25,000 120,000Normal Growth and Repair - CO Switching 2 12,750 12,750 25,000 25,000 25,000 25,000 112,750Normal Growth and Repair - Copper Cable 3 4,000 4,000 25,000 25,000 25,000 25,000 104,000Normal Growth and Repair - Fiber Cable 4 107,500 107,500 250,000 250,000 250,000 250,000 1,107,500Normal Growth and Repair - CO Trnsmssn 5 411,500 411,500 500,000 500,000 500,000 500,000 2,411,500Normal Growth and Repair - Wireless 6 4,375 4,375 15,000 15,000 15,000 15,000 64,375Normal Growth and Repair - Provisioning 7 35,000 35,000 25,000 25,000 25,000 25,000 135,000Fiber to the Home 8 709,136 130,000 130,000 200,000 100,000 100,000 100,000 1,339,136Remote Cabinets for Advanced Services 9 30,000 30,000 50,000 50,000 50,000 50,000 230,000Core Network Upgrade 10 75,000 200,000 200,000 150,000 425,000Blade Server 11 95,000 95,000 120,000 25,000 25,000 25,000 290,000Switch Upgrade 12 750,000 750,000Gravina Island Buildout 13 100,000 100,000 100,000 100,000 400,000Multi-Dwelling Unit Project 14 26,250 26,250 200,000 150,000 150,000 150,000 676,250Operating Equipment 15 30,000 30,000 35,000 25,000 25,000 25,000 140,000PC Hardware & Software 16 10,000 10,000 30,000 20,000 20,000 20,000 100,000Vehicle Acquisition 17 330,000 200,000 100,000 100,000 730,000Structured Cabling Project 18 25,000 26,250 26,250 51,250Heat Reclamation 26 37,500 37,500 37,500

NON-REGULATEDHeadend Expansion 19 222,950 222,950 150,000 100,000 100,000 100,000 672,950Video Set Top Boxes 20 120,000 120,000 150,000 100,000 100,000 100,000 570,0004G Mobile 21 50,000 3,100,000 3,100,000 200,000 100,000 100,000 3,550,000Microwave Link to Prince Rupert 22 1,900,000 1,900,000 1,900,000Wi-Max 23 225,000 50,000 50,000 50,000 375,000ISP Email Server 24 21,875 21,875 72,000 93,875Wi-Fi 25 15,000 15,000 60,000 40,000 40,000 40,000 195,000

Total 859,136 21,875 6,538,075 6,559,950 3,687,000 1,925,000 1,825,000 1,725,000 16,581,086

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 859,136 21,875 1,538,075 1,559,950 3,687,000 1,925,000 1,825,000 1,725,000 11,581,086Interfund Loan 5,000,000 5,000,000 5,000,000

Total 859,136 21,875 6,538,075 6,559,950 3,687,000 1,925,000 1,825,000 1,725,000 16,581,086

Adopted 2013 Projected Requirements

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Division: Telecommunications

Adopted 2013 Projected Requirements

KPU CIP AD-1

Page 49: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 1 Project Number:

Project Title: Normal Growth and Repair - Buildings Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction 48,000 Equipment 72,000

Other Project Total 120,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 20,000 20,000 25,000 25,000 25,000 25,000 120,000

Total 20,000 20,000 25,000 25,000 25,000 25,000 120,000

Adopted 2013 Projected Requirements

This budget item provides funding for improvements to existing buildings, replacement of lighting fixtures and installation of building alarms or related security items.

KPU CIP AD-2

Page 50: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 2 Project Number:

Project Title: Normal Growth and Repair - Central Office Switching Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 7,125Description: Land/Right-of-Way Construction Management Construction 10,125 Equipment 97,750

Other Project Total 112,750

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 12,750 12,750 25,000 25,000 25,000 25,000 112,750

Total 12,750 12,750 25,000 25,000 25,000 25,000 112,750

Adopted 2013 Projected Requirements

This budget item purchases reliability upgrades and additional capacity equipment required for the division’stelecommunications switching and voice over internet protocol network.

KPU CIP AD-3

Page 51: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 3 Project Number:

Project Title: Normal Growth and Repair - Copper Cable Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 4,160Description: Land/Right-of-Way Construction Management Construction 41,600 Equipment 58,240

Other Project Total 104,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 4,000 4,000 25,000 25,000 25,000 25,000 104,000

Total 4,000 4,000 25,000 25,000 25,000 25,000 104,000

Adopted 2013 Projected Requirements

This budget item funds replacement of existing deteriorated cables and construction of minor cable projects,including line extensions. This budget item also funds cable, cross arms and miscellaneous hardware required toreconnect to poles replaced by the Electric Division.

KPU CIP AD-4

Page 52: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 4 Project Number:

Project Title: Normal Growth and Repair - Fiber Cable Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 22,150Description: Land/Right-of-Way Construction Management Construction 609,125 Equipment 476,225

Other Project Total 1,107,500

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 107,500 107,500 250,000 250,000 250,000 250,000 1,107,500

Total 107,500 107,500 250,000 250,000 250,000 250,000 1,107,500

Adopted 2013 Projected Requirements

This budget item funds additional fiber optic network for business data circuits including smaller fiber projectsnecessary for the efficient operation of the Utility. This item also includes materials and labor for continuedinstallation of fiber service drops for customers who order high bandwidth television services in areas served by thedivision's fiber cable network.

KPU CIP AD-5

Page 53: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 5 Project Number:

Project Title: Normal Growth and Repair - CO Transmission Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 24,115Description: Land/Right-of-Way Construction Management Construction 241,150 Equipment 2,146,235

Other Project Total 2,411,500

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 411,500 411,500 500,000 500,000 500,000 500,000 2,411,500

Total 411,500 411,500 500,000 500,000 500,000 500,000 2,411,500

Adopted 2013 Projected Requirements

This budget item funds purchase and installation of additional intelligent Network Interface Devices (NIDS) andOptical Network Terminals (ONTS) required to deliver service to IPTV customers served via fiber optic cable. Thisbudget item includes funding for required/associated internal network fiber ports. This budget item includes fundingfor network transmission electronics necessary to serve business customers with new private line servicesincluding digital data service, T1, etc.

KPU CIP AD-6

Page 54: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 6 Project Number:

Project Title: Normal Growth and Repair - Wireless Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 1,609Description: Land/Right-of-Way Construction Management Construction 6,438 Equipment 56,328

Other Project Total 64,375

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 4,375 4,375 15,000 15,000 15,000 15,000 64,375

Total 4,375 4,375 15,000 15,000 15,000 15,000 64,375

Adopted 2013 Projected Requirements

This budget item will provide funds to purchase 700 MHz radio equipment that will be used to serve remotelocations within the division's serving area.

KPU CIP AD-7

Page 55: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 7 Project Number:

Project Title: Normal Growth and Repair - Provisioning Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 135,000

Other Project Total 135,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 35,000 35,000 25,000 25,000 25,000 25,000 135,000

Total 35,000 35,000 25,000 25,000 25,000 25,000 135,000

Adopted 2013 Projected Requirements

This budget item funds the integration of the new access, middleware and subscriber management platforms intothe Virtual Telecommunications Connection (VTC) automated provisioning software (eliminating the requirement formanual/technician service order assignments).

KPU CIP AD-8

Page 56: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 8 Project Number:

Project Title: Fiber to the Home Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 33,478Description: Land/Right-of-Way Construction Management Construction 502,176 Equipment 803,482

Other Project Total 1,339,136

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 709,136 130,000 130,000 200,000 100,000 100,000 100,000 1,339,136

Total 709,136 130,000 130,000 200,000 100,000 100,000 100,000 1,339,136

Adopted 2013 Projected Requirements

This budget item funds contract labor to deploy fiber cable and terminals necessary to bring fiber to homes,businesses and multi-dwelling units throughout Ketchikan. In 2013, KPU’s primary focus will be extending fiberthroughout downtown the business core and to multi-dwelling units.

KPU CIP AD-9

Page 57: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 9 Project Number:

Project Title: Remote Cabinets for Advanced Services Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 5,750Description: Land/Right-of-Way Construction Management Construction 17,250 Equipment 207,000

Other Project Total 230,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 30,000 30,000 50,000 50,000 50,000 50,000 230,000

Total 30,000 30,000 50,000 50,000 50,000 50,000 230,000

Adopted 2013 Projected Requirements

This budget item funds the replacement of batteries in remote switching cabinets (RSC). Over time, RSC batteriesreach the end of useful life and require replacement. This project also equips RSC’s with remote monitoringsensors, ensuring technicians can remotely detect proper operation prior to failure.

KPU CIP AD-10

Page 58: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 10 Project Number:

Project Title: Core Network Upgrade Start Date: 01/13 Estimated Project Cost: End Date: 12/14 DesignDescription: Land/Right-of-Way Construction Management Construction 425,000 Equipment

OtherProject Total 425,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 75,000 200,000 200,000 150,000 425,000

Total 75,000 200,000 200,000 150,000 425,000

Adopted 2013 Projected Requirements

This budget item adds critical components to the division's Core MLX, in order to equip the core withredundant/fail safe protection. The Core MLX is the primary center of the KPU’s triple-play network. Critical Corecomponents lack redundancy. This project establishes full redundancy for key Core components, ensuringcontinued operation and triple-play service-delivery.

KPU CIP AD-11

Page 59: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 11 Project Number:

Project Title: Blade Server Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 2,000Description: Land/Right-of-Way Construction Management Construction 7,000 Equipment 281,000

OtherProject Total 290,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 95,000 95,000 120,000 25,000 25,000 25,000 290,000

Total 95,000 95,000 120,000 25,000 25,000 25,000 290,000

Adopted 2013 Projected Requirements

This budget item funds the acquisition of a single ("blade") server chassis appropriately sized to replace multiplestand alone servers (some of which are end-of-life). This project will increase the reliability of KPU’s network andincrease efficiency via simplifying and increasing the speed at which technicians configure and provision customeraccounts on the KPU network. The division's numerous existing stand alone servers require ongoing maintenanceand have problematic individual interfaces, which require specific knowledge across the division's technicalworkforce. Conversely, the new blade server will have a single interface and operating system, will be sized forgrowth simply via subsequent installation of additional "blades" and will eliminate the requirement for specializedtechnical server knowledge and skill sets.

KPU CIP AD-12

Page 60: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 12 Project Number:

Project Title: Switch Upgrade Start Date: 01/14 Estimated Project Cost: End Date: 12/14 Design 18,750Description: Land/Right-of-Way Construction Management Construction 75,000 Equipment 656,250

OtherProject Total 750,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 750,000 750,000

Total 750,000 750,000

Adopted 2013 Projected Requirements

This budget item purchases one new soft switch to replace two existing switches, the Taqua and the M6 switchingsystems. The M6 Hosted IP switch currently serves approximately 60 business customers (with over 1,000 lines)throughout Ketchikan. The M6 has been manufacturer discontinued and will require replacement in the future. KPU'sTaqua Softswitch provides dial tone service to residential and business customers throughout Ketchikan. TheTaqua’s manufacturer appears to be experiencing a series of financial issues, which has resulted in employeeturnover, lack of required upgrade development, poor support and other problematic issues threatening to result inlack of reliability in the Taqua switching platform. Given the ultimate need to replace the M6, the most efficient andpractical next-step will be to replace both switching platforms, consolidating Hosted IP and local dial tone switchingon a single switching platform.

KPU CIP AD-13

Page 61: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 13 Project Number:

Project Title: Gravina Island Build Out Start Date: 01/14 Estimated Project Cost: End Date: 12/17 Design 10,000Description: Land/Right-of-Way Construction Management Construction 40,000 Equipment 350,000

OtherProject Total 400,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 100,000 100,000 100,000 100,000 400,000

Total 100,000 100,000 100,000 100,000 400,000

Adopted 2013 Projected Requirements

This budget item provides funds to build fiber and related facilities on Gravina Island necessary to offer triple-playservices.

KPU CIP AD-14

Page 62: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 14 Project Number:

Project Title: Muti-Dwelling Unit Project Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 3,381Description: Land/Right-of-Way Construction Management Construction 13,525 Equipment 659,344

OtherProject Total 676,250

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 26,250 26,250 200,000 150,000 150,000 150,000 676,250

Total 26,250 26,250 200,000 150,000 150,000 150,000 676,250

Adopted 2013 Projected Requirements

This budget item funds purchase of multi dwelling unit (MDU) electronics, enabling provision of triple-play servicesto the 40% of KPU customers residing in apartment buildings via a single fiber (eliminating the need to runmultiple fibers into multi-dwelling units). This will eliminate the corresponding need to install and maintain the pereach fiber electronics required for multiple fiber installations.

KPU CIP AD-15

Page 63: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 15 Project Number:

Project Title: Operating Equipment Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 140,000

Other Project Total 140,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 30,000 30,000 35,000 25,000 25,000 25,000 140,000

Total 30,000 30,000 35,000 25,000 25,000 25,000 140,000

Adopted 2013 Projected Requirements

This budget item funds test equipment utilized by KPU technicians to test, repair and install high speed data andvoice circuits, particularly as it relates to KPU’s expanded fiber optic network.

KPU CIP AD-16

Page 64: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 16 Project Number:

Project Title: PC Hardware and Software Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 100,000

OtherProject Total 100,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 10,000 10,000 30,000 20,000 20,000 20,000 100,000

Total 10,000 10,000 30,000 20,000 20,000 20,000 100,000

Adopted 2013 Projected Requirements

This budget item funds replacement of outdated computers (identified by Information Technology for replacement)and purchases new hardware and software for the network operations control center.

KPU CIP AD-17

Page 65: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 17 Project Number:

Project Title: Vehicle Acquisition Start Date: 01/14 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 730,000

OtherProject Total 730,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 330,000 200,000 100,000 100,000 730,000

Total 330,000 200,000 100,000 100,000 730,000

Adopted 2013 Projected Requirements

This budget item funds replacement of aging vehicles to prevent excessive maintenance costs and productionaffecting breakdowns. The following vehicles, all of which are over 12 years old, will be replaced:

Veh# Year & Description Condition Replacement Cost#36 Flatbed Truck Poor $ 50,000#41 Installation and Repair Van Poor $ 35,000#42 Installation and Repair Van for PBX Poor $ 35,000#50 Bucket Truck Poor $110,000

KPU CIP AD-18

Page 66: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 18 Project Number:

Project Title: Structured Cabling Project Start Date: 01/13 Estimated Project Cost: End Date: 12/13 Design 1,281Description: Land/Right-of-Way Construction Management Construction 30,750 Equipment 19,219

OtherProject Total 51,250

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 415 25,000 26,250 26,250 51,250

Total 25,000 26,250 26,250 51,250

Adopted 2013 Projected Requirements

This budget item (Phase II) purchases fiber optic jack panels and patch cabling necessary to create a permanentstructured fiber cabling architecture within KPU’s host and remote offices. The structure is required to remove andreplace temporary cabling, which causes sporadic service quality issues and prevents focused and efficientanalysis and placement of additional network cabling.

KPU CIP AD-19

Page 67: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 19 Project Number:

Project Title: Headend Expansion Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 3,365Description: Land/Right-of-Way Construction Management Construction 33,648 Equipment 635,938

OtherProject Total 672,950

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 222,950 222,950 150,000 100,000 100,000 100,000 672,950

Total 222,950 222,950 150,000 100,000 100,000 100,000 672,950

Adopted 2013 Projected Requirements

This budget item provides funds for replacement of the division's end-of-life Astria equipment, the failure of whichwill cause dozens of KPU channels to ‘go dark’. Several failing Astria units were replaced in 2012. The balancemust be replaced in 2013. This budget item also provides funds to purchase new receivers and IRDs (IntergradedReceiver/Decoder), which are necessary to add new network channels.

KPU CIP AD-20

Page 68: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 20 Project Number:

Project Title: Video Set Top Boxes Start Date: 01/13 Estimated Project Cost: End Date: 12/17 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 570,000

OtherProject Total 570,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 120,000 120,000 150,000 100,000 100,000 100,000 570,000

Total 120,000 120,000 150,000 100,000 100,000 100,000 570,000

Adopted 2013 Projected Requirements

This budget item funds purchase of customer set top boxes (STB’s) utilized in the provision of CommVisiontelevision service. This account also funds purchase of Personal Video Recorders (PVRs) required to provide timeshifted television.

KPU CIP AD-21

Page 69: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 21 Project Number:

Project Title: 4G Mobile Start Date: 01/13 Estimated Project Cost: End Date: 12/16 Design 4,500Description: Land/Right-of-Way Construction Management Construction 67,500 Equipment 3,478,000

OtherProject Total 3,550,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 50,000 200,000 100,000 100,000 450,000Interfund Loan 420 3,100,000 3,100,000 3,100,000

Total 50,000 3,100,000 3,100,000 200,000 100,000 100,000 3,550,000

Adopted 2013 Projected Requirements

This budget item provides funding to construct KPU’s 4G Mobile network in Ketchikan. In 2002, KPU purchased the4G/LTE wireless license/spectrum for Southeast Alaska. In 2011, KPU engaged a consulting firm to evaluate bestpossible utilization of the spectrum. The study confirmed best possible utilization included selling the non-Ketchikanspectrum to deploy KPU 4G service in Ketchikan. Related options, strategic issues and other considerations havebeen reviewed with management and City Council prior to compilation of this budget item.

KPU CIP AD-22

Page 70: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 22 Project Number:

Project Title: Microwave Link to Prince Rupert Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction 1,900,000 Equipment

OtherProject Total 1,900,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 Intefund Loan 420 1,900,000 1,900,000 1,900,000

Total 1,900,000 1,900,000 1,900,000

Adopted 2013 Projected Requirements

This budget funds construction of a microwave radio link between Ketchikan and Canada. KPU presently leasesInternet backbone capacity to the lower ’48 from GCI. At present, KPU pays GCI $660,000 per year, an amountestimated to grow to approximately $800,000 to $900,000 per year over the next 2 years, depending upon customergrowth/demand. This project builds a microwave radio path between Ketchikan and Canada, creates significant roomfor future growth and creates significant circuit lease savings in both the short-term and long-term.

KPU CIP AD-23

Page 71: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 23 Project Number:

Project Title: Wi-Max Start Date: 01/14 Estimated Project Cost: End Date: 12/17 Design 9,375Description: Land/Right-of-Way Construction Management Construction 75,000 Equipment 290,625

OtherProject Total 375,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 225,000 50,000 50,000 50,000 375,000

Total 225,000 50,000 50,000 50,000 375,000

Adopted 2013 Projected Requirements

This budget item funds construction of Wi-Max antennas on High Mountain and Mountain Point. Wi-Max will enableKPU to offer ‘fiber-via-wireless’ high speed Internet and video service to residential, business, boat harbor andtransient customers within 20 miles line of sight.

KPU CIP AD-24

Page 72: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 24 Project Number:

Project Title: ISP email Server Start Date: 01/13 Estimated Project Cost: End Date: 12/14 Design 500Description: Land/Right-of-Way Construction Management Construction 2,500 Equipment 90,875

OtherProject Total 93,875

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 21,875 21,875 72,000 93,875

Total 21,875 21,875 72,000 93,875

Adopted 2012 Projected Requirements

This budget item funds replacement of KPU email server. The present server is antiquated and does not providethe level of security and service KPU Internet customers demand.

KPU CIP AD-25

Page 73: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 25 Project Number:

Project Title: WiFi Start Date: 01/13 Estimated Project Cost: End Date: 12/17 Design 4,875Description: Land/Right-of-Way Construction Management Construction 39,000 Equipment 151,125

OtherProject Total 195,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 15,000 15,000 60,000 40,000 40,000 40,000 195,000

Total 15,000 15,000 60,000 40,000 40,000 40,000 195,000

Adopted 2013 Projected Requirements

This budget item funds the second year of a multi-year project to place WIFI nodes in strategic locations throughoutdowntown Ketchikan. Ultimately the WIFI nodes will provide KPU customers with virtually seamless WIFI ‘roaming’for IPad-type tablets/wireless devices and enables the Utility to sell WIFI to tourists and enhanced WIFI relatedservices to business customers.

KPU CIP AD-26

Page 74: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Telecommunications Project Priority: 26 Project Number:

Project Title: Heat Reclamation Start Date: 01/13 Estimated Project Cost: End Date: 12/13 DesignDescription: Land/Right-of-Way Construction Management Construction Equipment 37,500

OtherProject Total 37,500

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 420 37,500 37,500 37,500

Total 37,500 37,500 37,500

Adopted 2013 Projected Requirements

This project is for the duct work and mechanical equipment to reclaim excessive heat in the Central Office fordistribution to the Administrative space in the AT&T Alascom building. Presently we need to run air conditioning yearround to keep the equipment in the Central Office within operating parameters, while at the same time running afurnace to heat the administrative space.

KPU CIP AD-27

Page 75: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Prior Reappro- New Total Project Title Priority Years priated Funding Total 2014 2015 2016 2017 Project

Chlorination Plant Improvements 1 189,100 67,900 60,000 127,900 317,000Raw Water Transmission Main 2 300,000 300,000 300,000Water Distribution Grid Improvements 3 60,000 60,000 60,000 60,000 60,000 60,000 300,000Additional Projects 4 60,000 60,000 60,000 60,000 60,000 60,000 300,000Water Service Upgrade Program 5 30,000 30,000 30,000 30,000 30,000 30,000 150,000Backflow Prevention Program 6 10,000 10,000 10,000 10,000 10,000 10,000 50,000Potable Water Fill Station 7 90,000 90,000Water Street Trestle No. 2 - Utility Replacement 8 100,000 100,000Schoenbar Road Water Improvements 9 93,805 2,117,053 2,210,858Chatham Avenue Water Main Replacement 10 34,369 847,960 882,329Harris Street Water Improvements 11 71,678 685,000 756,678Mill Street Water Improvements 12 75,000 75,000 6,000,000 6,075,000Lund & Millar St. Water Improvements 13 50,000 50,000Denali Ave. Water Improvements 14 35,000 35,000Sayles & Gorge Street Bridges Water Improve. 15 10,000 10,000 180,000 190,000Austin St. Water Improvements 16 60,000 773,000 833,0002nd Avenue Water & Sewer Improvements - Ph. I 17 400,000 400,000Adams Street Water Improvements 18 15,000 15,000 30,000Dunton Street Viaduct Water Improvements 19 10,000 10,000 168,000 178,000Woodland Ave. Water Improvements 20 25,000 25,000Highlands Reservoir Replacement 21 100,000 100,000Confidence Reservoir Replacement-Design 22 100,000 100,000Hoadley Creek/Jackson St Water Improvements 23 140,000 450,000 590,000Second Avenue Water & Sewer - Phase II 24 50,000 1,100,000 1,150,000UV Disinfection Facility 25 235,000 100,000 100,000 335,000

Total 638,952 252,900 530,000 782,900 3,600,013 6,603,000 1,425,000 2,498,000 15,547,865

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 638,952 252,900 530,000 782,900 495,000 435,000 160,000 175,000 2,686,852Proposed Revenue Bonds/Drinking Water Loans 889,504 1,850,400 378,000 697,000 3,814,904Proposed State Grants 2,215,509 4,317,600 887,000 1,626,000 9,046,109

Total 638,952 252,900 530,000 782,900 3,600,013 6,603,000 1,425,000 2,498,000 15,547,865

Adopted 2013 Projected Requirements

Ketchikan Public Utilities2013 - 2017 Capital Improvement Program

Division: WaterAdopted 2013 Projected Requirements

KPU CIP AE-1

Page 76: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 1 Project Number:

Project Title: Chlorination Plant Improvements Start Date: 1/12 End Date: 12/13 Design 157,000Description: Land/Right-of-Way Construction Management Construction 60,000 Equipment 100,000

Other Project Total 317,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 189,100 67,900 60,000 127,900 317,000

Total 189,100 67,900 60,000 127,900 317,000

Adopted 2013 Projected Requirements

As described in the division's Engineering & Architectural Services account narrative, Ketchikan needs advanceknowledge of changes in the UVT before the water reaches the UV Facility. UVT measurement and fullautomation at the Chlorination Plant a mile away will provide that information directly to the UV plant’s centralcontrol computer. It can then automatically start the second UV disinfection train so the flow through each unit ishalved, raise the chlorine addition to compensate for the amount destroyed by UV light,and adjust the amount ofammonia added to form chloramines. Design of the equipment was completed by CH2M Hill in 2012. Much of theequipment has been purchased already and this account will provide the funding for its installation.

KPU CIP AE-2

Page 77: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 2 Project Number:

Project Title: Raw Water Transmission Main Start Date: 1/13 End Date: 12/13 Design 50,000Description: Land/Right-of-Way Construction Management Construction 250,000 Equipment

Other Project Total 300,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 300,000 300,000 300,000

Total 300,000 300,000 300,000

Adopted 2013 Projected Requirements

In addition to the three steel penstocks supplying the Ketchikan hydroelectric generators that extend from the tunnel complexthat transports water from Ketchikan Lakes and then cross Ketchikan Creek on a suspended walkway, there are also two 16-inch steel water mains extending from the same concrete tunnel plug. These are the raw water supply to the KetchikanChlorination Plant and are the sole source of raw water for the entire community. These water supply mains were lastreplaced when the Ketchikan Lakes Dame was rebuilt in 1957. Although their exterior surfaces has been carefully protectedwith coal tar epoxies, they are now finally failing from the pipe interior. As they develop more and more leaks, they are beingpatched with wrap-around bands. These steel 16-inch transmission mains have reached the end of their service life.

KPU CIP AE-3

Page 78: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 3 Project Number:

Project Title: Water Distribution Grid Improvements Start Date: 01/13 End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction 300,000 Equipment

Other Project Total 300,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 60,000 60,000 60,000 60,000 60,000 60,000 300,000

Total 60,000 60,000 60,000 60,000 60,000 60,000 300,000

Adopted 2013 Projected Requirements

Each year the division has, in conjunction with the work of other agencies, unexpected opportunities to undertakerepairs to improve the municipal water system. This account provides the funding for such improvements.

KPU CIP AE-4

Page 79: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 4 Project Number:

Project Title: Additional Projects Start Date: 01/13 End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction 300,000 Equipment

Other Project Total 300,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2013 2014 2015 2016 Project

Revenue Generating Fund 60,000 60,000 60,000 60,000 60,000 60,000 300,000

Total 60,000 60,000 60,000 60,000 60,000 60,000 300,000

Adopted 2013 Projected Requirements

This account provides for the cost of fire hydrants and other related materials, which are provided by the Utility inwater line extensions and are then incorporated into the municipal water system. This account also provides asource of funds for raising or replacing valve boxes in City streets when General Government repaving projectsoccur. Although specific streets have not yet been selected for asphalt paving in 2013, there will be paving nextyear.

KPU CIP AE-5

Page 80: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 5 Project Number:

Project Title: Water Service Upgrade Start Date: 01/13 End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction 150,000 Equipment

Other Project Total 150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 30,000 30,000 30,000 30,000 30,000 30,000 150,000

Total 30,000 30,000 30,000 30,000 30,000 30,000 150,000

Adopted 2013 Projected Requirements

The water service upgrade program was initiated in 1997, in order to allow a number of residents to upgrade theirindividual water services. The division proposes to continue offering this program in 2013 and requests that the CityCouncil authorize funding. Numerous water services, from the main to the residence, are in need of replacement toKPU standards. After completion of the work and inspection by KPU, this program allows the customer to providecost documentation and receive a grant-in-aid. $500 is available for work undertaken on private property and up to$4,000 is available for work undertaken within the right-of-way. As a result of homeowners participating in theprogram, KPU will assume full responsibility for future repairs within the right-of-way as long as they are not causedby negligence by the property owner.

KPU CIP AE-6

Page 81: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 6 Project Number:

Project Title: Backflow Prevention Program Start Date: 01/13 End Date: 12/17 Design Description: Land/Right-of-Way Construction Management Construction 50,000 Equipment

Other Project Total 50,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 10,000 10,000 10,000 10,000 10,000 10,000 50,000

Total 10,000 10,000 10,000 10,000 10,000 10,000 50,000

Adopted 2013 Projected Requirements

This grant-in-aid program was established in 1995, in order to encourage businesses to install backflow preventersto help protect the municipal water system. The division proposes to continue offering this program in 2012 andrequests that the City Council authorize funding. This program is part of ADEC's mandated cross-connectioncontrol regulations, which require the Utility to be responsible for system-wide protection. Until 2001, Ketchikan'slack of adoption and enforcement of the Uniform Plumbing Code allowed many substandard installations to beconstructed within the community. These deficiencies are still being discovered and must be corrected by theproperty owner. Due to a lesser interest by businesses this past year, the proposed 2013 Budget remains at thereduced amount of $10,000.

KPU CIP AE-7

Page 82: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 7 Project Number:

Project Title: Potable Water Fill Station Start Date: 01/13 End Date: 12/13 Design 5,000Description: Land/Right-of-Way Construction Management Construction 85,000 Equipment

Other Project Total 90,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 90,000 90,000

Total 90,000 90,000

Adopted 2013 Projected Requirements

This project proposes the design and construction of a water fill station that allows bulk water haulers, recreationalvehicles, contractors and private parties to purchase potable water from a remote station without impacting the dailyoperations of the public works department. The current water fill station serving bulk water haulers is located in the backarea of the City Maintenance Facility. The area has become increasingly congested with equipment and experiencesdifficulty with traffic control and safety. Additionally, the Public Works Department does not allow private parties to fillpotable water tanks from the hose bib on the building. This method of tank filling provides no assurance ofdecontamination, nor does it allow the user to pay for the water obtained. Consideration will also be given to relocatingthe RV sewer dump station to the same location.

KPU CIP AE-8

Page 83: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 8 Project Number:

Project Title: Water Street Trestle No. 2 Utility Replacement Start Date: 01/14 End Date: 09/17 DesignDescription: Land/Right-of-Way Construction Management Construction 100,000 Equipment

OtherProject Total 100,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 100,000 100,000

Total 100,000 100,000

Adopted 2013 Projected Requirements

Replacement of Water Street's Trestle No. 2 beginning in 2014 and continuing for 2 1/2-years will also replace both the waterand sewer mains located beneath the 1,000-foot long trestle. Since the Water Division has requested changes from theoriginal 1962 construction in the exposed portion of the replacement water main and there will be additional changes requiredin the buried portions, the DOT&PF will likely determine that not all of this work is grant eligible and will look to KPU to fund aportion, particularly since the overall cost estimate is now $22,000,000. Consequently, $100,000 is included to fund the non-grant eligible portions and to purchase the fire hydrants and valves that are provided by KPU for every project. The 34.5 kVAtransmission line will also be relocated to 3rd Avenue with the 12.47 kVA distribution line remaining on Water Street.

KPU CIP AE-9

Page 84: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 9 Project Number:

Project Title: Schoenbar Road Water Improvements Start Date: 01/12 End Date: 12/15 Design 93,805Description: Land/Right-of-Way Construction Management Construction 2,117,053 Equipment

Other Project Total 2,210,858

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 93,805 93,805Proposed SFY 2014 70% Municipal Matching Grant 1,481,937 1,481,937Proposed Revenue Bonds/Drinking Water Loan Fund 635,116 635,116

Total 93,805 2,117,053 2,210,858

Adopted 2013 Projected Requirements

The Wastewater Division intends to replace the sewers along Schoenbar Road between the easterly intersection of FairyChasm and Park Avenue. Although some of the water mains have been replaced earlier, this project will allow 1,200 feet ofundersized cast-iron mains to be replaced between Valley Forge and Schoenbar Trail intersections. The Schoenbar Roadwater main is the primary route from the Bear Valley Reservoir to Stedman Street. The expanding fish processing industrieslocated along Stedman Street are consuming more water every year and supplying the fish processors is beginning to tax theability of the Utility to supply their needs. DOWL-HKM's 2012 design has been reviewed at the 65% level and should be 100%complete before year-end. The Water and Wastewater Divisions submitted an application in August 2012 under ADEC's 70%Municipal Matching Grant program requesting funds in SFY14. ADEC has already scored it quite well (975 points) and it islikely to be included within the Governor's Budget for consideration by the Legislature. The Drinking Water Loan request forthe remainder of the funding will be submitted in February of 2013. If approved, construction would start in 2014. Thesenumbers assume a 50/50 split between the Water & Wastewater Divisions for these funding sources.

KPU CIP AE-10

Page 85: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 10 Project Number:

Project Title: Chatham Avenue Water Main Replacement Start Date: 01/12 End Date: 10/15 Design 34,369Description: Land/Right-of-Way Construction Management Construction 847,960 Equipment

Other Project Total 882,329

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 34,369 34,369Proposed SFY 2014 70% Municipal Matching Grant 593,572 593,572Proposed Revenue Bond/ Drinking Water Loan Fund 254,388 254,388

Total 34,369 847,960 882,329

Adopted 2013 Projected Requirements

The storm drainage system in Chatham Avenue is an "immediate priority" in the recent storm drainage study. This is anothersegment of a multi-year program jointly developed by KPU and the General Government to replace substandard, defectiveutilities simultaneously whenever possible. In conjunction with the Wastewater and Streets Divisions, install 360-feet of 6-inchmain between Denali and Hill Road. DOWL-HKM's 2012 design has been reviewed at the 65% level and should be 100%complete before year-end. Although ADEC has already scored Ketchikan's 70% SFY14 Municipal Matching Grant requestwell down the list (840 points) but still entirely possible for inclusion in the Governor's Budget. The remaining funds would beobtained through Drinking Water & Clean Water Loan requests to be submitted in February 2013. If funding is approved byADEC, and the voters approve the bond issue in October's 2013 Municipal Election, construction would begin in 2014.These numbers assume a 50/50 split between the Water & Wastewater Divisions for these funding sources

KPU CIP AE-11

Page 86: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 11 Project Number:

Project Title: Harris Street Water Improvements Start Date: 01/12 End Date: 12/16 Design 71,678Description: Land/Right-of-Way Construction Management Construction 685,000 Equipment

Other Project Total 756,678

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 71,678 71,678Proposed SFY 2014 70% Municipal Matching Grant 480,000 480,000Proposed Revenue Bond/Drinking Water Loan Fund 205,000 205,000

`Total 71,678 685,000 756,678

Adopted 2013 Projected Requirements

In conjunction with the Wastewater Division, install 880 feet of 6-inch water main along Harris Street. This is another segmentof a multi-year program jointly developed by KPU and the General Government to replace substandard, defective utilitiessimultaneously whenever possible. DOWL-HKM's 2012 design has been reviewed at the 65% level and should be 100%complete before year-end. The Water and Wastewater Divisions intend to submit an application in August 2014 underADEC's 70% Municipal Matching Grant program requesting funds in SFY16. The remaining funds would be obtained througha Drinking Water & Clean Water Loan request submitted in February 2015. If funding is approved by ADEC, and the votersapprove the bond issue in October's 2013 Municipal Election, construction would begin in 2016. These numbers assume a50/50 split between Water & Wastewater Divisions for just the Harris Street portion, while the Park Avenue portion would bebuilt entirely by the Wastewater Division.

KPU CIP AE-12

Page 87: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 12 Project Number:

Project Title: Mill Street Water Improvements Start Date: 01/13 End Date: 12/16 Design 75,000Description: Land/Right-of-Way Construction Management Construction 6,000,000 Equipment

Other Project Total 6,075,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 75,000 75,000 75,000Proposed SFY 2014 70% Municipal Matching Grant 4,200,000 4,200,000Proposed Revenue Bond/Drinking Water Loan Fund 1,800,000 1,800,000

Total 75,000 75,000 6,000,000 6,075,000

Adopted 2013 Projected Requirements

The entire length of Mill Street is in need of replacement along with the utilities underneath. Replacement of Mill Street and notthe 40-year old utilities underneath has an estimated construction cost of $9,425,000 and is nominated for the 2012-2015Statewide Transportation Improvement Program (STIP). Funding for the utility replacement design appears in both 2013 Waterand Wastewater Divisions' Capital Improvement Programs at $75,000 each. If the design is completed by July 2013, the Waterand the Wastewater Divisions intend to submit an application in August 2013 under ADEC's 70% Municipal Matching Grantprogram requesting funds in SFY 2015. The remaining funds would be obtained through Drinking Water and Clean Water Loanrequests submitted in February 2014. This assumes that the October 2013 ballot utility bond measure is approved by thevoters. If funding sources are approved, construction would begin in 2015 and continue into 2016.

KPU CIP AE-13

Page 88: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 13 Project Number:

Project Title: Lund & Millar Street Water Improvements Start Date: 01/15 End Date: 12/18 Design 50,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 50,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 50,000 50,000Proposed SFY 2018 70% Municipal Matching GrantProposed Revenue Bond/Drinking Water Loan Fund

Total 50,000 50,000

Adopted 2013 Projected Requirements

These streets are in serious need of repair along with replacement of the utilities beneath. Funding for the design will appear inboth 2015 Water and Wastewater Divisions' Capital Improvement Programs with each utility sharing the design costs equally at$50,000 each. If the design is completed by December 2015, the Water and the Wastewater Divisions intend to submit anapplication for Drinking Water Loan and Clean Water Loan requests in February 2016. The Water and Wastewater Divisionsalso intend to submit an application in August 2016 under ADEC's 70% Municipal Matching Grant program requesting fundingin SFY 2018. If funding is approved, construction would begin in 2018 replacing 980-feet of 6-inch cast iron piping. Totalestimated project cost is $1,000,000.

KPU CIP AE-14

Page 89: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 14 Project Number:

Project Title: Denali Avenue Water Improvements Start Date: 01/15 End Date: 12/19 Design 35,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 35,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 35,000 35,000Proposed SFY 2017 70% Municipal Matching GrantProposed Revenue Bond/Drinking Water Loan Fund

Total 35,000 35,000

Adopted 2013 Projected Requirements

In conjunction with the Wastewater Division, install 650 feet of 6-inch water main along Denali Avenue between Tower to HillRoad. This is another segment of a multi-year program jointly developed by KPU and General Government to replacesubstandard, defective utilities simultaneously wherever possible. The Water and Wastewater Divisions intend to submit anapplication in August 2015 under ADEC's 70% Municipal Matching Grant program. The remaining funds would be obtainedthrough a Drinking Water Loan and Clean Water Loan requests submitted in February 2016. This assumes that the October2013 ballot utility bond measure was approved by the voters. If funding sources are approved, construction would start in2019. Total estimated project cost is $395,000.

KPU CIP AE-15

Page 90: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 15 Project Number:

Project Title: Sayles & Gorge Street Bridges Water Improv. Start Date: 01/13 End Date: 12/18 Design 10,000Description: Land/Right-of-Way Construction Management Construction 180,000 Equipment

Other Project Total 190,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 10,000 10,000 10,000Proposed SFY 2017 70% Municipal Matching Grant 127,000 127,000Proposed Revenue Bond/Drinking Water Loan Fund 53,000 53,000

Total 10,000 10,000 180,000 190,000

Adopted 2013 Projected Requirements

This viaduct is in need of replacement along with the utilities underneath. The Sayles & Gorge Viaduct has an estimatedconstruction cost of $1,280,000. It was nominated for the 2012-2015 Statewide Transportation Improvement Program (STIP),but wasn't included. Approximately 310' of the new 6-inch main will be buried and not eligible for being funded as part of theviaduct replacement. Funding for this design beyond the bridge abutments will appear in both 2013 Water and WastewaterDivisions' Capital Improvement Programs. If the design is completed in-house by December 2013, the Water and WastewaterDivisions intend to submit applications for Drinking Water Loan and Clean Water Loan requests in February 2014. The Waterand Wastewater Divisions also intend to submit an application in August 2014 under ADEC's 70% Municipal Matching Grantprogram in SFY17. The buried portion of the new 6-inch main is estimated to cost $180,000. Construction will begin in 2016.

KPU CIP AE-16

Page 91: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 16 Project Number:

Project Title: Austin Street Water Improvements Start Date: 01/14 End Date: 12/17

Description: Design 60,000

Land/Right-of-Way Construction Management Construction 773,000 Equipment

Other Project Total 833,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 60,000 60,000Proposed SFY 2017 70% Municipal Matching Grant 541,000 541,000Proposed Revenue Bonds/Drinking Water Loan Fund 232,000 232,000

Total 60,000 773,000 833,000

Adopted 2013 Projected Requirements

This project is driven primarily by the immediate need to replace the leaking and collapsing municipal sewers beneath thisstreet. In conjunction with the Wastewater Division, this project will replace both water and sewer mains in a three-blocksegment of Austin Street between Tongass and Third Avenues. If the design is completed by December 2014, the Waterand Wastewater Divisions intend to submit applications for Drinking Water and Clean Water Loan requests in February 2015.The Water and Wastewater Divisions also intend to submit an application in August 2015 under ADEC's 70% MunicipalMatching Grant program requesting funds in SFY 17. If funding is approved, construction would begin in 2017 replacing 720-feet of 8-inch and 285-feet of 6-inch cast iron piping.

KPU CIP AE-17

Page 92: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 17 Project Number:

Project Title: Second Avenue Water Improvements - Phase I Start Date: 01/12 End Date: 12/16 DesignDescription: Land/Right-of-Way Construction Management Construction 400,000 Equipment

OtherProject Total 400,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund Proposed SFY 2015 70% Municipal Matching Grant 280,000 280,000Proposed Revenue Bonds/Drinking Water Loan Fund 120,000 120,000

Total 400,000 400,000

Adopted 2013 Projected Requirements

The Wastewater Division intends to replace all of the sewer along 2nd Avenue between White Cliff and Water Street startingwith the first phase beginning where construction was completed in 2005 at the White Cliff intersection. Approximately 500-feetwill be replaced in the first phase which was designed in 2012. This is another segment of a multi-year program jointlydeveloped by KPU and General Government to replace substandard, defective utilities simultaneously whenever possible. TheWater and Wastewater Divisions intend to submit an application in August 2014 under ADEC's 70% Municipal Matching Grantprogram requesting funds in SFY16. If all funding requests are approved, construction would start in 2016.

KPU CIP AE-18

Page 93: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 18 Project Number:

Project Title: Adams Street Water Improvements Start Date: 1/12 End Date: 12/19 Design 30,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 30,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 15,000 15,000 30,000Proposed SFY 2019 70% Municipal Matching Grant

Total 15,000 15,000 30,000

Adopted 2013 Projected Requirements

In conjunction with the Wastewater Division, install 150 feet of 6-inch main between 4th and 5th Avenues. The remainder ofthe Adams Street water main between Tongass and 1st Avenue was rebuilt in 1987. Another segment between 2nd and 3rdAvenues was replaced in 2001. This is another segment of a multi-year program jointly developed by KPU and GeneralGovernment to replace substandard, defective utilities simultaneously whenever possible. If the design is completed by July2017, the Water and Wastewater Divisions intend to submit an application in August 2017 under ADEC's 70% MunicipalMatching Grant program. The remaining funding would be obtained through the Revenue Generating Fund. If all funding isapproved, construction would begin in 2019. Total estimated project cost is $145,000.

KPU CIP AE-19

Page 94: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 19 Project Number:

Project Title: Dunton Street Viaduct Water Improvements Start Date: 1/13 End Date: 12/16 Design 10,000Description: Land/Right-of-Way Construction Management Construction 168,000 Equipment

Other Project Total 178,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 10,000 10,000 10,000Proposed SFY 2015 70% Municipal Matching Grant 117,600 117,600Proposed Revenue Bonds/Drinking Water Loan Fund 50,400 50,400

Total 10,000 10,000 168,000 178,000

Adopted 2013 Projected Requirements

This viaduct is in need of replacement along with the utilities underneath. The Dunton Viaduct has an estimated constructioncost of $4,200,000. It was nominated for the 2012-2015 Statewide Transportation Improvement Program (STIP), but wasn'tincluded. Approximately 295' of the new 6-inch main will be buried and may not be eligible for being funded as part of theviaduct replacement. Funding for this design beyond the bridge abutments will appear in both 2013 Water & WastewaterDivisions' Capital Improvement Programs. If the design is completed in-house by December 2013, the Water and WastewaterDivisions intend to submit applications for Drinking Water Loan and Clean Water Loan requests in February 2014. The Waterand Wastewater Divisions also intend to submit an application in August 2014 under ADEC's 70% Municipal Matching Grantprogram. The buried water portion is estimated to cost $168,000..

KPU CIP AE-20

Page 95: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 20 Project Number:

Project Title: Woodland Avenue Water Improvements Start Date: 01/14 End Date: 12/18 Pre Design 25,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 25,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 25,000 25,000Proposed SFY 2016 70% Municipal Matching GrantProposed Revenue Bonds/Drinking Water Loan Fund

Total 25,000 25,000

Adopted 2013 Projected Requirements

The Wastewater Division intends to replace all of the sewer along Woodland Avenue between Deermount Street and ParkAvenue. Although the wood-stave half of Woodland's water main was replaced in 1988, this project will allow the remaining420 feet of undersized cast-iron mains to be replaced between the Nickey Way and Deermount Street intersections with 12-inch HDPE. If there was a failure in the Park/Fair route, it would provide an alternate route for water to Stedman Street. This isanother segment of a multi-year program jointly developed by KPU and General Government to replace substandard, defectiveutilities simultaneously whenever possible. The Water and Wastewater Divisions intend to submit an application in August2014 under ADEC's 70% Municipal Matching Grant program. The remaining funding would be obtained through DrinkingWater and Clean Water Loan requests submitted in February 2015. If funding is approved, construction would start in 2018.Total estimated project cost is $480,000.

KPU CIP AE-21

Page 96: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 21 Project Number:

Project Title: Highland Reservoir Replacement Start Date: 01/14 End Date: 12/22 Pre Design 100,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 100,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 30,000 30,000Proposed SFY 2016 State Grant 70,000 70,000

Total 100,000 100,000

Adopted 2013 Projected Requirements

Construct a modern replacement for the wooden reservoir located on the northerly slope above the intersection of ForestAvenue and the Third Avenue Extension. The existing reservoir is too small to provide adequate fire protection for the StateJail and adjacent residential area that the reservoir serves. Ketchikan is located in Seismic Zone 3 (major damage). Thistype of wooden reservoir will not survive a significant earthquake, nor can it be economically retrofitted with additional shearprotection. Beginning in 2014, site investigations of adjacent property needs to be investigated and acquired in order toconstruct a large, modern 650,000 gallon reservoir that will take about 8-10 years before completion. KPU intends to submitan application in August 2013 under ADEC's 70% Municipal Matching Grant program requesting funds in SFY15 to begin theproject. If approved, property would be purchased by 2016 and construction would start in about 2020.

KPU CIP AE-22

Page 97: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 22 Project Number:

Project Title: Confidence Reservoir Replacement Start Date: 01/14 End Date: 12/22 Pre Design 100,000Description: Land/Right-of-Way Construction Management Construction Equipment

OtherProject Total 100,000

Fund Prior Reappro- New Total Source of Funds No. Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 30,000 30,000Proposed SFY 2015 State Grant 70,000 70,000

Total 100,000 100,000

Adopted 2013 Projected Requirements

In the 1998 Comprehensive Plan, the cost of replacing the Confidence Zone Reservoir is estimated (in 1998 dollars) to cost$2.94 million dollars. The area that it serves was originally expected to be a commercial zone (3,500 gpm for 4 hours firefighting). Instead, it has become primarily a residential zone. Before investing significant amounts of money in a newreservoir, the sizing needs to be thoroughly investigated before design commences and suitable property acquired. Theexisting 21,380 gallon bolted steel reservoir was installed in 1992 as a temporary expedient planned to serve only the SolidWaste Handling Facility. Instead, this has become Ketchikan's fastest growing residential area. The division intends to submitan application in August 2013 (SFY 2015) under the 70% Municipal Matching Grant program requesting preliminary designfunds for the proper size reservoir. If approved, funds would be released in summer 2014 to establish the initial design criteriaalong with suitable site locations. Subsequent phases will include geotechnical work, property purchase, and site preparationbefore actual construction could begin about 2020.

KPU CIP AE-23

Page 98: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 23 Project Number:

Project Title: Hoadley Creek/Jackson St Water Improvements Start Date: 01/15 End Date: 12/17 Design 140,000Description: Land/Right-of-Way Construction Management Construction 450,000 Equipment

Other Project Total

590,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 140,000 140,000SFY 2016 70% Municipal Matching Grant 315,000 315,000Proposed Revenue Bonds/Alaska Drinking Water Loan Fund 135,000 135,000

Total 140,000 450,000 590,000

Adopted 2013 Projected Requirements

Replacing the Hoadley Creek culvert as it crosses Jackson Street will sever the sole arterial water main that supplies both theBaranof and Carlanna Reservoirs for a period of several weeks. Before this occurs, a temporary pump station has to be built at adifferent location to supply the Carlanna Zone since those mains will be severed as well. For the Baranof Zone, a secondaryroute has to be constructed either as a temporary main spanning Hoadley Creek away from the culvert construction area orperhaps a permanent installation made through an existing City street that doesn't presently have a water main and will connectthese two Baranof Zone segments. If the design is completed by July 2015, the Water and Wastewater Divisions intend to submitan application in August 2015 under ADEC's 70% Municipal Matching Grant program requesting funds in SFY17. The remainingfunds would be obtained through a Drinking Water and Clean Water Loan requests submitted in February 2016. If all funding isapproved, construction would begin in 2017..

KPU CIP AE-24

Page 99: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 24 Project Number:

Project Title: 2nd Avenue Water & Sewer - Phase II Start Date: 01/15 End Date: 12/17 Design 50,000Description: Land/Right-of-Way Construction Management Construction 1,100,000 Equipment

Other Project Total 1,150,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Generating Fund 50,000 50,000SFY 2017 70% Municipal Matching Grant 770,000 770,000Proposed Revenue Bonds/Alaska Drinking Water Loan Fund 330,000 330,000

Total 50,000 1,100,000 1,150,000

Adopted 2013 Projected Requirements

In conjunction with Wastewater Division both the water and sewer utilities will be replaced between the White Cliff and Adamsintersections. This is another segment of a multi-year program jointly developed by KPU and the General Government to replacesubstandard, defective utilities simultaneously whenever possible. If the design is completed by July 2015, the Water andWastewater Divisions intend to submit an application in August 2015 under ADEC's 70% Municipal Matching Grant programrequesting funds in SFY17. The remaining funds would be obtained through a Drinking Water and Clean Water Loan requestssubmitted in February 2016. If all funding is approved, construction would begin in 2017.

KPU CIP AE-25

Page 100: CITY OF KETCHIKAN, ALASKA 2013 2017 KETCHIKAN PUBLIC ... · 2013 - 2017 Capital Improvement Program 2013 Capital Budget Revenues/ Federal/State Loans/ Revenue 2013 Department/Division/Project

Division: Water Project Priority: 25 Project Number:

Project Title: UV Disinfection Facility Start Date: 01/12 End Date: 12/13 Design 35,000Description: Land/Right-of-Way Construction Management Construction 300,000 Equipment

Other Project Total 335,000

Prior Reappro- New Total Source of Funds Years priated Funding Total 2014 2015 2016 2017 Project

Revenue Bonds/Alaska Drinking Water Loan Fund 235,000 100,000 100,000 335,000

Total 235,000 100,000 100,000 335,000

Adopted 2013 Projected Requirements

Site development for the UV Disinfection Facility Project on Schoenbar Road opened up far more property than was originallyproposed. Once the overburden was stripped, substantially more rock was found than originally expected. Rather than simplydispose ofthe excess rock off-site, all of the underlying muskeg has been removed and replaced with shot rock for a minimaladditional expense. This proposed 40' x 60' building will be used to store chemicals, equipment, and maintenance spare parts forthe UV Facility along with the spare parts and chemicals used for pH adjustment. The feeders and pumps for the pH adjustmentare now located at the UV Facility buildling. The former pH Adjustment Building has been converted into a separate facility forammonium hydroxide addition which will change our disinfection chemistry and reduce haloacetic acid formation.

KPU CIP AE-26


Recommended