+ All Categories
Home > Documents > City of Palm Coast, Florida City Council Meeting October 2, 2012.

City of Palm Coast, Florida City Council Meeting October 2, 2012.

Date post: 13-Dec-2015
Category:
Upload: gordon-johnson
View: 216 times
Download: 2 times
Share this document with a friend
Popular Tags:
14
City of Palm Coast, Florida City Council Meeting October 2, 2012
Transcript
Page 1: City of Palm Coast, Florida City Council Meeting October 2, 2012.

City of Palm Coast, Florida City Council Meeting

October 2, 2012

Page 2: City of Palm Coast, Florida City Council Meeting October 2, 2012.

Water Treatment Plant #3 (WTP#3) Phases

WTP#3 Facility and Phase One WellfieldWTP#3 Phase Two WellfieldWTP#3 Future Plant Expansion and Future

Phase Three Wellfield

Page 3: City of Palm Coast, Florida City Council Meeting October 2, 2012.
Page 4: City of Palm Coast, Florida City Council Meeting October 2, 2012.

WTP#3 Facility and Phase One Wellfield

• CPH Engineers complete design and permitting of Water Plant Facility and Phase One Wellfield in April of 2007.

• Wharton-Smith our general contractor begins construction July 2007.

• July 31, 2008 City Water Treatment Plant #3 is officially brought online with phase one wells. Plant can run at 1.5 million gallons a day (MGD) output, half it’s rated capacity.

Page 5: City of Palm Coast, Florida City Council Meeting October 2, 2012.
Page 6: City of Palm Coast, Florida City Council Meeting October 2, 2012.

WTP#3 Phase 2 Wellfield• City staff begins negotiation for specific

phase 2 well property rights in 2005.• Connect Consulting drills the twelve

phase 2 wells to service additional WTP#3 raw water source needs in 4th quarter of 2006.

• CPH Engineers complete design and permitting of phase 2 wells and raw water pipeline.

Page 7: City of Palm Coast, Florida City Council Meeting October 2, 2012.

WTP#3 Phase 2 Wellfield

• Well project completion will allow plant #3 to produce it’s permitted capacity of 3.0 MGD.

• City acquires warranty deed and easement rights from Rayonier April of 2010.

• Notice to Proceed issued for Palm Beach Grading to construct wells and raw water pipeline on June 21, 2010.

Page 8: City of Palm Coast, Florida City Council Meeting October 2, 2012.

SW-146

Page 9: City of Palm Coast, Florida City Council Meeting October 2, 2012.
Page 10: City of Palm Coast, Florida City Council Meeting October 2, 2012.
Page 11: City of Palm Coast, Florida City Council Meeting October 2, 2012.

Electrical DistributionCity provides for language in the

Rayonier agreement that Rayonier will work with FPL on electrical rights for the project.

City executes agreement with FPL for electrical service in Sept. 2010. Pays $421,243.00 in fees to FPL.

Talks begin to stall between Rayonier and FPL on property rights.

City begins to consider alternatives to FPL electrical supply.

Page 12: City of Palm Coast, Florida City Council Meeting October 2, 2012.

Electrical DistributionTalks fall apart between FPL and Rayonier.City determines it has the right to install

electrical lines within our existing easements.

City issues a Request for Qualifications for Electrical design services.

CPH Engineers/Fred Wilson and Associates are selected as best qualified firm to design electrical distribution system.

Page 13: City of Palm Coast, Florida City Council Meeting October 2, 2012.

Electrical DistributionElectrical Design is completed July 2012.Project bids are received Sept. 11, 2012. Three bidders provide responsive bids with C&C Power line (C&C) being the low bidder.City staff and the Design Engineer recommend approval of a construction contract with C&C to the City Council.

Page 14: City of Palm Coast, Florida City Council Meeting October 2, 2012.

Questions


Recommended