City of Raleigh Pleasant Valley Road Widening Project October 11, 2016 City Manager Presentation
Transcript
Page 1: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

City of Raleigh

Pleasant Valley Road Widening Project October 11, 2016

City Manager Presentation

Page 2: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Pleasant Valley RD 2016

Pleasant Valley Rd. Widening Project

Project Location

Page 3: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Purpose of Project Pleasant Valley RD 2016

• Reconstruct Damaged Pavement

• Widen to a Three-Lane Section (According to Comprehensive Plan)

• Add Facilities For Pedestrians and Bicycles on both sides of the road

• Add pedestrian refuge at signalized intersections (Duraleigh and Glenwood)

Page 4: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Project Challenges Pleasant Valley RD 2016

• Minimize Property Encroachment

• Proximity Parking Lots

• Existing Utilities

• Stormwater

Page 5: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Proposed Design Pleasant Valley RD 2016

6’ CONCRETE

SIDEWALK

VARIABLE WIDTH

PLANTING STRIP

TWO-WAY LEFT TURN

CENTER LANE

6’ CONCRETE

SIDEWALK

5’ BIKE LANE

Page 6: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Typical Section Pleasant Valley RD 2016

76’ (Varies) RIGHT-OF-WAY

6’ 2’ 6’ 2.5’ 5’ 11’ 11’ 11’

Note: Dimensions shown on right side of the road apply also to left side.

VA

RIE

S

Page 7: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Stormwater Design Pleasant Valley RD 2016

Water Quality Management • Nitrogen Treatment handled through City of Raleigh

credit bank from other projects

Water Quantity Management • Approximately 1000 ft3 of storage provided in

oversized pipes along Pleasant Valley Road

Page 8: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Funding & Schedule Pleasant Valley RD 2016

On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT for design , SUE, survey, landscaping, and geotechnical services.

Estimated Project Cost

$3.7 Million Including Construction and Right of Way

Project Schedule:

• Complete Right of Way Acquisition – Early 2018 (4-6 Month Duration)

• Award Construction Contract – Spring 2018

• Complete Construction – Spring 2019

Page 9: City of Raleigh City Manager Presentation...Pleasant Valley RD Funding & Schedule 2016 On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT

Pleasant Valley RD 2016

Thank you