CITY WATER, LIGHT & POWER FY2021 BUDGET PRESENTATION January 23, 2020
Transcript
Page 1: CITY WATER, LIGHT & POWER

CITY WATER, LIGHT & POWER

FY2021 BUDGET PRESENTATION

January 23, 2020

Page 2: CITY WATER, LIGHT & POWER

DEPARTMENT OVERVIEW

2

Electric Division

ElectricGeneration

T&D Ops/ Engineering /Construction

Energy Services

ISD

Security

Water Division

Water Purification

Water Distribution

/Engineering

Land & Water Resources

Property Management

Lake Services

Finance Division

Commercial Office

Accounting

Purchasing

Fiscal Services

Regulatory Affairs

Environmental Health & Safety

Risk Management

Operations

Page 3: CITY WATER, LIGHT & POWER

HEADCOUNT TREND

3

MINORITIESWOMEN

FY20 65 12.3%FY20 93 17.4%

turnoverCut 20 vacancies

Page 4: CITY WATER, LIGHT & POWER

EMPLOYEE SAFETY

4

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019I.R. 17.28 21.3 17.34 16.12 16.06 15.99 11.63 11.89 8.84 8.56 8.17 6.85 5.85 5.27 7.11 3.02 3.55 2.5 3.61 2.35

0

5

10

15

20

25

OSHA Recordable Incidence Rate

Record setting year at 2.35

Page 5: CITY WATER, LIGHT & POWER

3,439 AMR Water Meters installed

1.88 miles of Water Main, 96 new

Water Services, 44 Fire Hydrants

and 95 Valves installed

224 miles of Water Main surveyed

for leaks

ACCOMPLISHMENTS

5

WATER DIVISION

Page 6: CITY WATER, LIGHT & POWER

WATER DIVISION

Lake area location signs for 911

updated

4,338 feet of Shoreline Stabilized

7 Lake Lease homes to Sanitary

Sewer, 5 on list to be completed this

spring

4 Lake Lanes Paved

60 Fish Habitat Structures

ACCOMPLISHMENTS

6

Page 7: CITY WATER, LIGHT & POWER

ELECTRIC DIVISION

Over 800 LED installations and 300 Pole change outs

Completed 4 Underground Rebuilds

– Hidden Valley, Hanover Hills, Johnson Park & West Woods

Jackson 20 Circuit Underground Feed replaced

SCADA Software upgraded

Solar Farm-Old Tippecanoe produced 317,000 kWh

ACCOMPLISHMENTS

7

Page 8: CITY WATER, LIGHT & POWER

ELECTRIC DIVISION

Electric Relocation for Laurel Street Rail Road Underpass

Began Installing Electric Fault Indicators

• 5 Feeders complete, 3 additional by spring

5 High Voltage Substation Circuit Breakers replaced

(62 yrs old)

Ethernet Fiber Service core network upgraded

ACCOMPLISHMENTS

8

Page 9: CITY WATER, LIGHT & POWER

Commercial Office/Customer Service

Avg. 15,000 Customer Assistance Contacts/mo

126,218 Online Payments

Reached over 22,000 myCWLP online account registrations

107 Families Received Project RELIEF bil l assistance

$23,984 Round Up Customer Donations for the Homeless

ACCOMPLISHMENTS

9

Page 10: CITY WATER, LIGHT & POWER

Energy Services Office

621 Energy Services Office Customer Assistance Contacts, Workshops and Events

179 Efficiency Rebates (Heat Pumps, HE Toilets)

78 Technical Assistance Evaluations, Usage Analyses

64 Home Energy Audits

14 Helping Homes Low Income Efficiency Retrofits

50% mySolar Subscribed from December 2018 launch

ACCOMPLISHMENTS

10

Page 11: CITY WATER, LIGHT & POWER

Begin• $7.1M Cash• 112 Days

Use• $3.9M Cash• 61 Days

End• $3.2M Cash• 51 Days

WATER FUND BUDGET HIGHLIGHTS

11

Projected FY21

Page 12: CITY WATER, LIGHT & POWER

• Expenses up $2.5 million

• ↑$1M Bond Projects (Water Filtration Project)

• ↑$1M Grant Projects (Lead Service Lines)

• ↑$400K Auxiliary Expenses

• ↑$285K Operating Expenses

WATER FUNDBUDGET HIGHLIGHTS

12

Page 13: CITY WATER, LIGHT & POWER

ELECTRIC FUNDBUDGET HIGHLIGHTS

13

Begin•$43.9M Cash•90 Days

Use•$1.85M Cash•4 Days

End•$42.1M Cash•86 Days

Projected FY21

Page 14: CITY WATER, LIGHT & POWER

• ↓ $1.25M Retail Revenues

• ↓ $900K Capacity Revenues (down ~$7M over 3 yrs.)

• ↑ $2M Transmission Line Upgrades

• ↑ $650K HVAC Upgrades

• ↑ $600K ERIRF Projects

ELECTRIC FUND BUDGET HIGHLIGHTS

14

Page 15: CITY WATER, LIGHT & POWER

ANTICIPATION OF ELECTRIC PILOT DECLINE

15

• Changes 2015-2019• 2015 PILOT Formula Changed to remove separate

Wholesale Revenue component – Now all revenues• 2019 PILOT increased from 3.35% to 3.75%• 2019 Shared Services was introduced adding about

$1.5M

• FY21 Electric PILOT transfer down by $800,000 • Drop in Retail Sales, Load is declining, and No Wind

Revenue -- drop in PILOT of $341k• Wholesale sales has dropped due to lower market

prices (units are not economic) -- drop in PILOT of $459k

• Added a Public Works Tree Crew - $310k

Page 16: CITY WATER, LIGHT & POWER

TRANSFERS TO CORPORATE FUND

16

FY2016 FY2017 FY2018 FY2019  FY2020  FY2021 ELECTRIC FUND:PILOT $8,058,000 $7,965,387 $7,958,106 $8,107,406 $8,795,863 $7,995,863Free Services $4,653,192 $4,449,904 $4,510,896 $4,534,582 $4,459,778 $4,384,973Shared Services Payment NA NA NA $1,009,763 $1,182,941 $1,242,087Public Works Tree Crew NA NA NA NA NA $310,000

Electric Total $12,711,192 $12,415,291 $12,469,002 $13,651,751 $14,438,582 $13,932,923

WATER FUND:PILOT $416,044 $439,950 $425,392 $431,237 $432,325 $433,381Free Services $385,126 $411,827 $394,847 $382,002 $400,824 $419,646Shared Services Payment NA NA NA $178,194 $246,740 $259,078Water Total $801,170 $851,777 $820,239 $991,433 $1,079,889 $1,112,105

CWLP Total $13,512,362 $13,267,068 $13,289,241 $14,643,184 $15,518,471 $15,045,028

Annual Increase $22,173 $1,353,943 $875,287 ($473,443)

Page 17: CITY WATER, LIGHT & POWER

Shared Services Breakdown

HR Reimbursement $540K

Corp. Counsel Legal Reimbursement $276K

OBM Purchasing Reimbursement $237K

Reimburse OBM for Consolidated AP $222K

OBM Payroll Reimbursement $138K

Mayor Admin Reimbursement $ 88K

(New) Public Works Tree Crew $310K

$1,811K

TRANSFERS TO CORPORATE FUND

17

Page 18: CITY WATER, LIGHT & POWER

WATER FUND

Page 19: CITY WATER, LIGHT & POWER

FY2021 WATER FUND EXPENSES

19

Page 20: CITY WATER, LIGHT & POWER

WATER FUND EXPENSES

20

FY2021 FY2020 $ VARIANCE % VARIANCEPERSONAL SERVICES 14,947,543$            14,541,923$            405,620$               2.8%CAPITAL IMPROVEMENTS 19,343,890              17,397,110              1,946,780             11.2%COMMODITIES/CONTRACTS 8,347,988                 8,158,130                 189,858                 2.3%DEBT SERVICE 6,267,483                 6,165,018                 102,465                 1.7%EQUIPMENT 441,499                    502,449                    (60,950)                  ‐12.1%TRANSFERS 433,381                    432,325                    1,056                      0.2%OTHER 1,678,636                 1,781,135                 (102,499)                ‐5.8%TOTAL 51,460,420$            48,978,090$            2,482,330$           5.1%

BUDGETED EXPENSES

Page 21: CITY WATER, LIGHT & POWER

FY2021 WATER FUND EXPENSES

21

From FY 20 to FY 21Distribution Down 1%Pumping & Purification Down 1%

Source of Supply up 1%Admin & General up 1%Lake Services/Construction up 1%

Page 22: CITY WATER, LIGHT & POWER

FY2021 WATER FUND RESOURCES

22

Page 23: CITY WATER, LIGHT & POWER

WATER FUND RESOURCES

23

FY2021 FY2020 $ VARIANCE %VARIANCERETAIL & OTHER OPERATING 26,411,452$            26,395,044$    16,408$         0.1%BOND/GRANT PROCEEDS 14,603,885              12,693,073       1,910,812      15.1%FUND BALANCE & OTHER 5,763,420                 5,298,451         464,969         8.8%WHOLESALE SALES 2,267,781                 2,370,497         (102,716)        ‐4.3%AUXILIARY SERVICES 1,302,489                 1,268,988         33,501            2.6%CONTRIBUTIONS 1,161,109                 992,957             168,152         16.9%TOTAL 51,510,136$            49,019,010$    2,491,126$   5.1%

BUDGETED RESOURCES

Page 24: CITY WATER, LIGHT & POWER

WATER RETAIL SALES TREND

24

Low customer charge – sensitive to changes in demand

Less revenue available for infrastructure

Page 25: CITY WATER, LIGHT & POWER

• Water Purification Plant Filter Additions - $7.5M (Bonds)

• Adding 4 fi lters & upgrading 12 existing fi lters

• Started July 2019 and expected completion is August 2021.

• Final project financed from 2012 bonds.

WATER FUND PROJECTS

25

Page 26: CITY WATER, LIGHT & POWER

• New Water Distribution Complex

• FY2021: Architectural Design &

Land Acquisition - $1.1M

• Mains, Meters, Hydrants/ Street

Maintenance

• Upgrades - $1,025,000

• Additions - $930,000

• Railroad Consolidation, Archer

Elevator, Stanford Ave – $530,000

WATER FUND PROJECTS

26

Page 27: CITY WATER, LIGHT & POWER

Lake Springfield Watershed - Best Management Practices $250k-$300k per year for 10-20 years

Promote Cover Crops, Filter Strip, Grass Waterways

Applied for three Grants

NWQI- National Water Quality Initiative (100%)

RCPP – Regional Conservation Partnership Program (50%)

IEPA 319 Grant

Lake Properties - Septic to Sewer Transition 302 Properties still on septic

$250k-$300k per year for 5-7 years ~ $1.8M

Chapter 96 changes will speed up conversion process

ANNUALWATER FUND PROJECTS

27

Page 28: CITY WATER, LIGHT & POWER

Installation of Automated Meter Reading

FY21 - 3,000 meters to AMR - $400,000

27,190 meters out of 52,406 to install

$400k-$700k Per year for 6-9 years ~ $4.5 M

Faster implementation would reduce labor costs & avoid technology

changes

ANNUALWATER FUND PROJECTS

28

Page 29: CITY WATER, LIGHT & POWER

Lead Service Line Replacement Program Future Requirement by USEPA and State Law Approximately 10,000 lead service lines in system $45M - $55M over next 30 years Applying for $1M Loan Forgiveness from IEPA

WATER FUND PROJECTS

29

Page 30: CITY WATER, LIGHT & POWER

Water Main Replacement Programs

$1M for 1 mile per year for next 20-30 years

10% of Mains over 100 years old and 25% over 75 years old

Supplemental Water Supply : $110M - $150M

• FY21 Land Purchases - $2.75 million

• FY21 Legal / Appraisal - $200,000

• FY21 Engineering - $3.5 million

Lime Sludge Ponds Relocation (CCR)

First step in closing Ash Ponds

Funding from ERIRF (Environmental Fund) $10-15M

WATER FUND PROJECTS

30

Page 31: CITY WATER, LIGHT & POWER

• Water Backhoe/Loader $120,000

• Water Work Truck $40,000

• Lake Services Equipment $139,750

(1) Truck 100% / (1) Truck 67% / (3) Trucks 50% / (1) Trailer 50%

• Lake Security: (1) Boat / (1) Boat Motor $48,000

• Security Vehicle (15% Water) $6,000

• Environmental Health & Safety (15% Water) $3,750

WATER FUND VEHICLES

31

Page 32: CITY WATER, LIGHT & POWER

ELECTRIC FUND

Page 33: CITY WATER, LIGHT & POWER

FY2021 ELECTRIC FUND EXPENSES

33

Page 34: CITY WATER, LIGHT & POWER

ELECTRIC FUND EXPENSES

34

Page 35: CITY WATER, LIGHT & POWER

FY2021 ELECTRIC FUND EXPENSES

35

From FY 20 to FY 21Generation down 4%Debt Service Down 1%Admin/Gen Down 1%

T&D up 3%Corporate Fund up 3%

Page 36: CITY WATER, LIGHT & POWER

FY2021 ELECTRIC FUND RESOURCES

36

Page 37: CITY WATER, LIGHT & POWER

ELECTRIC FUND RESOURCES

37

Page 38: CITY WATER, LIGHT & POWER

ELECTRIC RETAIL SALES TREND

38

Continuing load decline lowers revenue

16% load decrease since 2006.

Projected 8% decrease over next 10 yrs.

Page 39: CITY WATER, LIGHT & POWER

• Relocate Dispatch Center & MCW Data Center • Architectural Design & Land Acquisition - $750,000

• Energy & Capacity RFP

ELECTRIC FUND PROJECTS

39

Page 40: CITY WATER, LIGHT & POWER

Transmission & Distribution

• Overhead Projects• Line Clearance - $2,800,000

• Pole Replacement Program -$300,000

• LED Street Lighting Upgrade -$225,000

• Iron Bridge / Woodside Rd

Pole Relocation - $100,000

• Electric Fault Indicator Installation

• 25 locations across 10 feeders

ELECTRIC FUND PROJECTS

40

Page 41: CITY WATER, LIGHT & POWER

• Transmission & Distribution

• Underground Rebuilds

• Country Club Estates - $510,000

• Northgate - $315,000

• West Roads - $225,000

• Grand Valley Village - $50,000

ELECTRIC FUND PROJECTS

41

Page 42: CITY WATER, LIGHT & POWER

• Substation

• Synchronous Optical NETwork

(SONET) Upgrade $300,000

• Aging Circuit Breaker Replacements

$220,000

• System Relaying Upgrade/Replace

$212,000

ELECTRIC FUND PROJECTS

42

Page 43: CITY WATER, LIGHT & POWER

• Power Plants

• Environmental Compliance – Filter Press $2,250,000

• Unit 4 DCS Upgrade/Boiler Tuning - $750,000

• Unit 4 Mill Rebuilds - $600,000

• Interstate Generator Breaker

Replacement - $400,000

ELECTRIC FUND PROJECTS

43

Page 44: CITY WATER, LIGHT & POWER

• Unit Retirement

• 69kV Capacitor Bank Additions - $900,000

• Transmission Line 34 Upgrade - $795,000

• Spaulding Substation to Chatham Main

Substation

• HVAC Modifications - $750,000

ELECTRIC FUND PROJECTS

44

Page 45: CITY WATER, LIGHT & POWER

ELECTRIC FUND VEHICLES

45

• Dump Trucks (2) $175,000

• Lake Services Equipment $81,250

• (3) Trucks 50% / (1) Truck 33% / (1) Trailer 50%

• Relay Van $40,000

• Security Vehicle (85%) $34,000

• Environmental Health & Safety (85%) $21,250

• Power Plant Tractor/Mower $10,000

Page 46: CITY WATER, LIGHT & POWER

• No cost recovery mechanism – IOU’s can recover via rates

CWLP’S SHARE OF MISO PROJECTS

46

Page 47: CITY WATER, LIGHT & POWER

CWLP BUDGET HEARING

The End