CKOV1 at the MICE Experiment. TOF2. EMCAL. TOF0. TOF1. CKOV1. CKOV1 to perform mu/pi id w TOF0/TOF1. Progress since CM16 CKOV1 Fabrication and Installation. L. Cremaldi, CM17 CERN, Feb 24, 2007. 2 Threshold Aerogel Counters. Aerogel Counter. L. Cremaldi, CM17 CERN, Feb 24, 2007. - PowerPoint PPT Presentation
Popular Tags:
22
1 CKOV1 at the MICE Experiment CKOV1 to perform mu/pi id w TOF0/TOF1. Progress since CM16 CKOV1 Fabrication and Installation TOF0 CKOV1 TOF1 EMCAL TOF2 L. Cremaldi, CM17 CERN, Feb 24, 2007
Transcript
Page 1: CKOV1 at the MICE Experiment

1

CKOV1 at the MICE Experiment

•CKOV1 to perform mu/pi id w TOF0/TOF1.•Progress since CM16•CKOV1 Fabrication and Installation

TOF0 CKOV1 TOF1 EMCALTOF2

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 2: CKOV1 at the MICE Experiment

2

2 Threshold Aerogel Counters2 Threshold Aerogel Counters

Aerogel Counter

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 3: CKOV1 at the MICE Experiment

3

A

B

C

ISIS Beam Line ISIS Beam Line

Page 4: CKOV1 at the MICE Experiment

4

Magnetic Shielding- 2D Model

9.4%

4.6% 3.4%

3.3%

58%

48% 41%

17%

Btube = 10%BZ + 60% BBZg , B <5g

BZ

B

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 5: CKOV1 at the MICE Experiment

5

- H20 fraction is negligible.- Tested with low energy betas.- Background may be dominated by-rays, etc.

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 6: CKOV1 at the MICE Experiment

6

QuickTime™ and aTIFF (Uncompressed) decompressor

are needed to see this picture.

Rate Tests

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 7: CKOV1 at the MICE Experiment

7

Rate Tests

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 8: CKOV1 at the MICE Experiment

8

Number of Photo Electrons vs Frequency

0

10

20

30

40

50

60

70

0 1000 2000 3000 4000 5000 6000 7000

Frequency (kHz)

# of PE

8in 5PE8in 10PE8in 15PE8in 20PE8in 25PE5in 5PE8inTB

Transistor base prototype

Resistive base

RCA 8854 Transistor base

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 9: CKOV1 at the MICE Experiment

9

Transistor Base Transistor Base

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 10: CKOV1 at the MICE Experiment

10

CKOV1 Electronics

•CAEN V1724 8 Channel 14 bit 100 MS/s FlashADC 250-500 ps t resolution•CAEN V1290 TDC 25 ps t resolution

20 ns.div

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 11: CKOV1 at the MICE Experiment

11

-Machining- UM-Nickel Plating-Ready in Spring '07 for light tests

Light Box AssemblyLight Box Assembly

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 12: CKOV1 at the MICE Experiment

12

-Needed June/July ‘07.-Aerogel order in Mar’07-4mo lead time?-Assembly in Mississippi-Ship to RAL in Jul ’07

Radiator Box AssemblyRadiator Box Assembly

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 13: CKOV1 at the MICE Experiment

13L. Cremaldi, CM17 CERN, Feb 24, 2007

- CKOV1 Platform Design-GG -Decision should be made if RAL or US responsiblity.

Page 14: CKOV1 at the MICE Experiment

14

-Magnetic shields and PMT assemblies from Treste.-Mu-metal shield needs modification and re-annealing.-10 PMTs checked at Trieste before shipping to RAL. (UM)

PMT + Shield AssemblyPMT + Shield Assembly

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 15: CKOV1 at the MICE Experiment

15

Mirror Flashing Concept Mirror Flashing Concept

•Mirror aluminized in 2 sections.

•Large Vacuum vessel.

Page 16: CKOV1 at the MICE Experiment

16

Mirror Fabrication

•CERN Facility - Andre Braem - meeting next week•FNAL Facility - Eileen Hahn - Lab7

Large Vacuum Chamber- Off Line.Small Chamber- On Line.

90cm id

38cm id

L. Cremaldi, CM17 CERN, Feb 24, 2007

44cm id

60cm od

Page 17: CKOV1 at the MICE Experiment

17

quartz fiber PMT

DAQGate

LED Pulser

LED Pulser•Non-linear Response•Sensitive to LED Vapp•Adequate for Monitoring•Calibration of 1-Photon

•LEDs mounted near PMTs•Pulser fanned out at CKOV1•Two BNC control lines.

VME/NIMPULSER

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 18: CKOV1 at the MICE Experiment

18

Alignment & Self Calibration - 1,2 PE most probable in PMT 1-4.- Small correlation with muon x,y.- Data 1,2 pe signals self calibrating- Some Alignment of CKOV1 by balancing PMT light yield.

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 19: CKOV1 at the MICE Experiment

19

CKOV1 Services - 12 45m signal cables RG-58 type. 8 CKOV1 signals 2-Pulser 2 spare Should terminate at a patch panel in the Control Room.

- 10 SHV type high voltage cables. - HV supply not specified yet, may start with something simple Lecroy 4032??

-4 Low voltage Monitor cables for humidity sensor, gas flow, etc

-Dry air supply for mirror box or silica gel packs.

- NIM Crate for Pulser and checkout.

ckov1

Contr

Room

45m

Page 20: CKOV1 at the MICE Experiment

20

CKOV1 ScheduleCKOV1 Schedule

Mar Apr May Jun Jul Aug Sep Oct ‘07

Light Box

Aerogel Order

Mirror

Assemble

PMT Check + Housing to RAL

PMT Bases(FNAL)

Radiator Box

Mirror Assembly

Nickle Plate

CKOV1 Stand (RAL)

Mu-metal Shield Mod(??)

L. Cremaldi, CM17 CERN, Feb 24, 2007

Radiator Box

Page 21: CKOV1 at the MICE Experiment

21

Hardware/Software Experience

•TOF + CKV systems installed by hardware experts. H2 Testbeam CERN

• User analysis by software experts FNAL.

•Specialization, wave of the future!

L. Cremaldi, CM17 CERN, Feb 24, 2007

Page 22: CKOV1 at the MICE Experiment

22

Full Scale Model of the Royal Crown

L. Cremaldi, CM17 CERN, Feb 24, 2007