Date post: | 26-Dec-2015 |
Category: |
Documents |
Upload: | leon-hampton |
View: | 212 times |
Download: | 0 times |
CLAS12
Pre-shower Calorimeter (PCAL) projectFall of 2010 to fall of 2014, a lot of person-hours
S. Stepanyan (JLAB)
Hall-B Meeting, March 24, 2014
Hall-B Meeting, March 24, 2014 4
CLAS EC at high energies
Two problems will arise at high energiesSeparation of clusters from high energy p0’ gg decay
Diminishing energy resolution due to leakage from the back
Both are important for successful execution of the CLAS12 physics program
One cluster with E=Ep
Hall-B Meeting, March 24, 2014 5
EC with additional finer segmented 5 layers
Energy resolution for electrons
EEE 1.0
Efficiency of two photon cluster reconstruction p0ggg decays
Hall-B Meeting, March 24, 2014 6
CLAS12 PCAL
Lead-scintillator sandwich with three stereo readout views, UVW (5 layers per readout view), 14 layers of 2.2 mm lead - total of 5.5 r.l.
Extruded scintillator strips with Titanium dioxide cover. Cross section 4.5x1 cm2, two holes along the strip for light readout
84 strips in U-layer, 78 strips in V- and W-layers
Light transport from the scintillator to PMT via 1 mm diameter green wave-shifting fibers inserted inside the holes in the scintillator (2 fibers per hole)
Total number of readout channels 1152 (6x192)
Hall-B Meeting, March 24, 2014 7
All single stripsU-double V&W-single
W-single V-singleU-
singl
e
W-single, U&V-doubleV-single, U&W-double
Readout with variable segmentation Beam
78 strips = 46s + 32d=62PMTs 78 strips = 46s + 32d=62PMTs
84 strips = 52s + 32d=68PMTs
Hall-B Meeting, March 24, 2014 8
PCAL construction
Assembly of PCAL modules started on April of 2011
It took 2.5 years to assemble and test all 6 modules
The assembly process included the following steps (at JLAB): Load test and mechanical assembly of the box, followed by assembly fiber retainers Cutting scintillator strips (JLAB/W&M) QC of long (>2.5 meters) strips and 20% of wave-length shifting fibers Test and assembly of PMTs and dividers are in progress (JMU) Stacking of scintillator strips and lead sheets, and assembly of fibers Fiber polishing and assembly of PMTs Fabrication of signal and HV cables is completed (OU) Fabrication of electronics cables is in progress (NSU)
Procedures were developed for each stage of the construction based on experience gained during prototyping
Hall-B Meeting, March 24, 2014 9
Mechanical assembly of modules
Dimensional checks and test fit of sidewalls on the window have been done before load test
The PCAL box consists of – • two composite windows, 2’’ ROHACELL structural foam core sandwiched between
two 2mm thick stainless steel sheets. The set is kept together by a stainless steel “L” frame welded around the perimeter
• Three aluminum (~2’’) sidewalls attached to the window’s frame • Retaining assembly inside the box to keep the lead and scintillator layers in place
and to allow enough space for the fibers to be routed out of the box
Hall-B Meeting, March 24, 2014
Scintillator strips
10
• Scintillator strips were extruded at FNAL in two lengths, 420 cm (1450 strips) and 450cm (2710 strips). Strips have 0.25mm titanium dioxide cover.
• The shorter strips were used for U-view, the longer strips were for V- and W-views. • PCAL layer has an isosceles triangular shape, strips in a layer have different lengths and
ends of strips must be cut in an angle • From each original strip, two PCAL strips were cut
Hall-B Meeting, March 24, 2014 11
QC of scintillator strip dimensionsFull width of strip thickness distribution is <0.3mm, requirement is 1mm
Full width of strip width distribution is <0.6mm, requirement is 1mm
Hall-B Meeting, March 24, 2014 12
Relative light yield and attenuation measurements• Light yield along the strip was measured for each strip with length > 2 m • Light yield and attenuation of 20% of fibers fro each batch is measured measured as well.• Total of 3600 strips and ~3000 fibers have been tested
Hall-B Meeting, March 24, 2014 13
Stacking of scintillators and fiber assembly
• Stacking of each modules starts from scintillators of U-layer
• After scintillators are laid, fibers are inserted. Ends of fibers (opposite to the readout) are glued to the scintillator, then scintillator strips are shimmed in place with springs
Hall-B Meeting, March 24, 2014 14
Lead sheets• Pre-cut lead shits have been used, 2 right angle triangular pieces per layer. Total of 168
sheets (about 175 sheets have been processed)• Lifting fixture with suction caps and a gantry crane were used to stack led sheets in the
box. While in the box, couple of mm thick shims have been used to fix the position of the lead layer
Hall-B Meeting, March 24, 2014 15
QC of lead sheetsBefore installing each sheet was examined for damage, dimensions (length and straightness of sides, and the thickness) have been measure. If required, sheets were cut to match the requirements. Only less than 5% of sheets found to be defective.
Hall-B Meeting, March 24, 2014 16
Cutting and polishing of fibers• PCAL fiber cutter-polisher is a custom built
small 3-axis milling machine with a diamond-cutting tip (from ATLAS Tilecal)
• Process was fully automated: U-view had to be cut in 3-4 settings, W,V-views were cut at the same time in two settings
• After cut no further processing was required
Hall-B Meeting, March 24, 2014 19
Signal readout and electronics
PMT Spliter FADC
TDC
DiscriminatorScaler
HV
• Each PMT (Hamamatsu R6095) will be furnished with HV power supply, ADC, discriminator and TDC channel
• Anode signal of the PMT will be split with 1:2 split
• PCAL response will be measured in FADC
• Time of the signal will be measure in multi-hit TDC
• Fast readout of FADC will be used in the trigger logic
Trigger logic
Hall-B Meeting, March 24, 2014 20
Few thing to consider for simulation and reconstruction
CLAS EC: U-, V-, and W-readout from each side
of the triangle fixed width of transvers segmentation
along the readout view fixed distance from scintillator strips
to PMTs
PCAL: V-, and W-readout from the same
side of the triangle (top) variable width of transverse
segmentation length of fibers from end of
scintillator to PMT depends on location of the scintillator strip
All single strips U-double V&W-single
W-single, U&V-double V-single, U&W-double
U
V
W V W
U
Hall-B Meeting, March 24, 2014 21
PCAL Transport
• Custom made rollers are used to move modules out of the assembly area
• First modules went for storage in ESB on a fork lift
• Then were transported into Hall on a trailer
Hall-B Meeting, March 24, 2014 22
PCAL installationo On November 12, first PCAL module has been
installed on Sector 5o The last one was install on December 2 in
Sector 4
Hall-B Meeting, March 24, 2014 23
CLAS12 PCAL - Summary• It took four years for the whole project • Construction itself started in April of 2011 • During 2.5 years of construction students,
postdocs, scientist, and staff of the collaborating institutions processed and assembled – 7200 scintillator strips – 28800 wave-length shifting fibers– 200 lead sheets – 1152 PMTs, voltage dividers, and housing
Hall-B Meeting, March 24, 2014 24
CLAS12 PCAL project (WBS 1.4.2.2.2) has been successfully completed
Efforts of 10 undergraduate (from JMU and NSU) and 4 graduate (from OU, W&M, and AANL) students, and number scientists and staff from participating institutions paid off
Jefferson Lab – overall design, work space, R&D, and module construction
The Collage of William and Mary –design and module assembly, scintillator processing, and purchase of fibers
Ohio University – purchase and fabrication of signal and HV cables, module assembly
James Madison University –PMTs and voltage dividers, PMT housing assembly, module assembly
Norfolk State University – purchase and assembly of electronic cables and signal splitters
Artem Alikhanian National Lab (formerly known as Yerevan Physics Institute) – simulation and reconstruction, R&D,, design, and module construction
University of Virginia – cosmic tests, installation
Thanks to JLAB 12 GeV project team for continuous support
Many thanks to NSF for MRI funds granted to PCAL consortium, OU, W&M, JMU, and NSU, in 2009.
Special recognition to be given to the Hall-B engineering group for an excellent support