+ All Categories
Home > Documents > Claus C Project 1300 MWe CCGT

Claus C Project 1300 MWe CCGT

Date post: 04-Jan-2017
Category:
Upload: hadung
View: 228 times
Download: 4 times
Share this document with a friend
157
Claus C Project 1300 MWe CCGT Dynaflow lecture 6-12-2012
Transcript
Page 1: Claus C Project 1300 MWe CCGT

Claus C Project 1300 MWe CCGTDynaflow lecture 6-12-2012

Page 2: Claus C Project 1300 MWe CCGT

Repowering of Unit B into Claus CE- power extension (640 MWe to 1300 MWe)

Maximum of re-used equipment (saving investment)

Cycling plant (daily start –stop)

Fully automated operation

Page 3: Claus C Project 1300 MWe CCGT
Page 4: Claus C Project 1300 MWe CCGT

Project Claus CNew;• 3 x Alstom GT26 gas turbine (3 x 270 MWe)> 380 KV Grid

• 3 Triple Pressure Reheat HRSG's (3x380 t/h steam)

• Retrofitted HP, IP, LP Steam turbine unit B (480 MWe) > 150 KV Grid

• Common Main Condensate system;

- 4 x 33% Main Condensate Pumps

- 1 Deaerator

- 4 x 33% HP/IP/LP Boiler Feed Water Pumps

- 3 x 33% Re-circulation Pumps

• Secondary Cooling water system:

• Closed Cooling Water System;

- 3 x 50% Coolers (shell and tube)

- 3 x 50% Circulation Pumps

• Demin Water Installation

• Natural Gas Reducing System.

Page 5: Claus C Project 1300 MWe CCGT

RE-use;

• ST Generator (partly) + Auxiliaries (H2, Seal Oil)

• Connection to 150 KV Grid

• Condenser (retubed)

• Vacuum system

• Step up trafo Steam Turbine Generator

• Main Cooling water system (incl. cooling tower)

• Lube Oil System Steam Turbine

• Existing Buildings and Infra Structure

Page 6: Claus C Project 1300 MWe CCGT
Page 7: Claus C Project 1300 MWe CCGT
Page 8: Claus C Project 1300 MWe CCGT
Page 9: Claus C Project 1300 MWe CCGT

Process Data:

2804325LP steam

56529302IP steam

565140265HP steam

T [°C]P [bar]m [kg/s]Full load (100% capacity)

%59.51(gross) Efficiency

MWe1300Total (3x GT + ST)

MWe490Steam Turbine

MWe270Gas turbine

Gross Power at full load

Page 10: Claus C Project 1300 MWe CCGT

Scoping

Page 11: Claus C Project 1300 MWe CCGT
Page 12: Claus C Project 1300 MWe CCGT

LOT's Non Alstom scope

Page 13: Claus C Project 1300 MWe CCGT

NON Alstom scope Packages:

.

ST generator, busduct, transformer& aux.

Contracted SiemensLOT 8

Cooling TowerContracted E&S Planbau

LOT 7

Contracted NEM-SFL

Contracted Gruenbeck

Cancelled

Contracted / Tenderingin coop with Stork

Contracted StorkThermeq

Contracted StorkThermeq

Aux BoilerLOT 6

WTULOT 5

Chemical unit MCW systemLOT 4

Main Cooling Water pumps - KSBLOT 3

Main Cooling Water Intake, outlet& recirculation

LOT 2

In house Main Cooling Water system incl Aux.

LOT 1

Page 14: Claus C Project 1300 MWe CCGT

Remaining M & E & C&I worksContractedCofely

LOT 16

Remaining civil worksTenderingBallast Nedam

LOT 15

Contracted

Ballast Nedam

Contracted

Hofstede

ContractedGasunie

ContractedTennet

Contracted NKT

ContractedAriva

Site preperationLOT 14

Dismantling unit BLOT 13

Gas Reducing Station by GTSLOT 12

Tennet Grid connectionLOT 11

380 KV cablingLOT 10

ST Generator Bus Circuit BreakerLOT 9

Page 15: Claus C Project 1300 MWe CCGT

Time Schedule

• Pre-engineering started; 2006

• Contracting; June 2008

• Start at Site January 2009

• Start Commissioning; July 2011

• PAC; December 2011

• AC; September 2012

Page 16: Claus C Project 1300 MWe CCGT

Project Team

Page 17: Claus C Project 1300 MWe CCGT

Gas Turbine

Page 18: Claus C Project 1300 MWe CCGT
Page 19: Claus C Project 1300 MWe CCGT
Page 20: Claus C Project 1300 MWe CCGT
Page 21: Claus C Project 1300 MWe CCGT
Page 22: Claus C Project 1300 MWe CCGT
Page 23: Claus C Project 1300 MWe CCGT
Page 24: Claus C Project 1300 MWe CCGT
Page 25: Claus C Project 1300 MWe CCGT
Page 26: Claus C Project 1300 MWe CCGT
Page 27: Claus C Project 1300 MWe CCGT
Page 28: Claus C Project 1300 MWe CCGT
Page 29: Claus C Project 1300 MWe CCGT
Page 30: Claus C Project 1300 MWe CCGT
Page 31: Claus C Project 1300 MWe CCGT
Page 32: Claus C Project 1300 MWe CCGT
Page 33: Claus C Project 1300 MWe CCGT
Page 34: Claus C Project 1300 MWe CCGT

HRSG’s

Page 35: Claus C Project 1300 MWe CCGT
Page 36: Claus C Project 1300 MWe CCGT
Page 37: Claus C Project 1300 MWe CCGT
Page 38: Claus C Project 1300 MWe CCGT
Page 39: Claus C Project 1300 MWe CCGT
Page 40: Claus C Project 1300 MWe CCGT
Page 41: Claus C Project 1300 MWe CCGT
Page 42: Claus C Project 1300 MWe CCGT
Page 43: Claus C Project 1300 MWe CCGT
Page 44: Claus C Project 1300 MWe CCGT
Page 45: Claus C Project 1300 MWe CCGT
Page 46: Claus C Project 1300 MWe CCGT
Page 47: Claus C Project 1300 MWe CCGT
Page 48: Claus C Project 1300 MWe CCGT
Page 49: Claus C Project 1300 MWe CCGT
Page 50: Claus C Project 1300 MWe CCGT
Page 51: Claus C Project 1300 MWe CCGT
Page 52: Claus C Project 1300 MWe CCGT
Page 53: Claus C Project 1300 MWe CCGT
Page 54: Claus C Project 1300 MWe CCGT
Page 55: Claus C Project 1300 MWe CCGT
Page 56: Claus C Project 1300 MWe CCGT
Page 57: Claus C Project 1300 MWe CCGT
Page 58: Claus C Project 1300 MWe CCGT
Page 59: Claus C Project 1300 MWe CCGT
Page 60: Claus C Project 1300 MWe CCGT
Page 61: Claus C Project 1300 MWe CCGT
Page 62: Claus C Project 1300 MWe CCGT
Page 63: Claus C Project 1300 MWe CCGT
Page 64: Claus C Project 1300 MWe CCGT
Page 65: Claus C Project 1300 MWe CCGT
Page 66: Claus C Project 1300 MWe CCGT
Page 67: Claus C Project 1300 MWe CCGT
Page 68: Claus C Project 1300 MWe CCGT
Page 69: Claus C Project 1300 MWe CCGT
Page 70: Claus C Project 1300 MWe CCGT
Page 71: Claus C Project 1300 MWe CCGT
Page 72: Claus C Project 1300 MWe CCGT
Page 73: Claus C Project 1300 MWe CCGT
Page 74: Claus C Project 1300 MWe CCGT
Page 75: Claus C Project 1300 MWe CCGT
Page 76: Claus C Project 1300 MWe CCGT
Page 77: Claus C Project 1300 MWe CCGT
Page 78: Claus C Project 1300 MWe CCGT
Page 79: Claus C Project 1300 MWe CCGT
Page 80: Claus C Project 1300 MWe CCGT

Steam Turbine

Page 81: Claus C Project 1300 MWe CCGT
Page 82: Claus C Project 1300 MWe CCGT
Page 83: Claus C Project 1300 MWe CCGT
Page 84: Claus C Project 1300 MWe CCGT
Page 85: Claus C Project 1300 MWe CCGT
Page 86: Claus C Project 1300 MWe CCGT
Page 87: Claus C Project 1300 MWe CCGT
Page 88: Claus C Project 1300 MWe CCGT
Page 89: Claus C Project 1300 MWe CCGT
Page 90: Claus C Project 1300 MWe CCGT
Page 91: Claus C Project 1300 MWe CCGT
Page 92: Claus C Project 1300 MWe CCGT
Page 93: Claus C Project 1300 MWe CCGT
Page 94: Claus C Project 1300 MWe CCGT
Page 95: Claus C Project 1300 MWe CCGT
Page 96: Claus C Project 1300 MWe CCGT
Page 97: Claus C Project 1300 MWe CCGT
Page 98: Claus C Project 1300 MWe CCGT
Page 99: Claus C Project 1300 MWe CCGT
Page 100: Claus C Project 1300 MWe CCGT
Page 101: Claus C Project 1300 MWe CCGT
Page 102: Claus C Project 1300 MWe CCGT
Page 103: Claus C Project 1300 MWe CCGT
Page 104: Claus C Project 1300 MWe CCGT
Page 105: Claus C Project 1300 MWe CCGT
Page 106: Claus C Project 1300 MWe CCGT
Page 107: Claus C Project 1300 MWe CCGT

Main Cooling Water (LOT 1,2,3)

Page 108: Claus C Project 1300 MWe CCGT
Page 109: Claus C Project 1300 MWe CCGT
Page 110: Claus C Project 1300 MWe CCGT
Page 111: Claus C Project 1300 MWe CCGT
Page 112: Claus C Project 1300 MWe CCGT
Page 113: Claus C Project 1300 MWe CCGT
Page 114: Claus C Project 1300 MWe CCGT
Page 115: Claus C Project 1300 MWe CCGT

Auxiliary Boiler (LOT 6)

Page 116: Claus C Project 1300 MWe CCGT
Page 117: Claus C Project 1300 MWe CCGT

Water Treatment Unit (LOT 5)

Page 118: Claus C Project 1300 MWe CCGT
Page 119: Claus C Project 1300 MWe CCGT
Page 120: Claus C Project 1300 MWe CCGT
Page 121: Claus C Project 1300 MWe CCGT
Page 122: Claus C Project 1300 MWe CCGT
Page 123: Claus C Project 1300 MWe CCGT
Page 124: Claus C Project 1300 MWe CCGT
Page 125: Claus C Project 1300 MWe CCGT

Proces Control;

Operating Phylosophy;• Fully automated installation (one/two operators)• Design Cock pit philosophy

Distributed Control System (DCS);• Integrated system for analogue and binary control and

protection of the combined cycle process.• Interfacing of GT and ST control system (ST integrated)• Interfacing of package control systems (minimalized for CCC)• Maintaining operation within safe operating limits• Ergonomic Human Machine Interface• Software structure and HMI according VGB guidelines

Page 126: Claus C Project 1300 MWe CCGT
Page 127: Claus C Project 1300 MWe CCGT

FeldgeräteFeldgeräte Feldgeräte

Page 128: Claus C Project 1300 MWe CCGT
Page 129: Claus C Project 1300 MWe CCGT

Recurrent issues

Piping systems

Page 130: Claus C Project 1300 MWe CCGT

Supporting

No U-bolts for hot lines

Page 131: Claus C Project 1300 MWe CCGT

Stop blocks

Page 132: Claus C Project 1300 MWe CCGT

Use no “Upside down rigid struts”

Page 133: Claus C Project 1300 MWe CCGT
Page 134: Claus C Project 1300 MWe CCGT

Installed stop blocks

Page 135: Claus C Project 1300 MWe CCGT

Agreement on stop blocks and U-boltsColdMax operating temp < 100 degr C

HotMax. operating temp >= 100 degr CPipe size <= DN25

HotOperating temp >= 100 degr CPipe size> DN25 and <= DN50

HotOperating temp >= 100 degr CPipe size > DN50

Stop blocks welded to pipe

No No

Yes (for displacements >= 40 mm) *

Yes (for displacements >= 40 mm)

" Cleats "Welded to secondary steel No No

Yes (for displacements >= 40 mm) *

Yes (for displacements < 40 mm)

Remark *) Preferred are stop blocks (due to constructability cleats can be installed)

General 1) No U-bolted pipe supports allowed , except for the HRSG scope U-bolts are allowed for fixed points of small bore lines and cold lines (operating temp. < 80 degr C). For STG, WSC and BOP U-

bolts will not be used except for external certified systems i.e. fire fighting.2) Stop blocks/cleats not applicable for rigid hangers, spring hangers, constant load hangers and

rigid struts

Page 136: Claus C Project 1300 MWe CCGT

Unstable supports

Page 137: Claus C Project 1300 MWe CCGT
Page 138: Claus C Project 1300 MWe CCGT
Page 139: Claus C Project 1300 MWe CCGT
Page 140: Claus C Project 1300 MWe CCGT
Page 141: Claus C Project 1300 MWe CCGT
Page 142: Claus C Project 1300 MWe CCGT
Page 143: Claus C Project 1300 MWe CCGT
Page 144: Claus C Project 1300 MWe CCGT
Page 145: Claus C Project 1300 MWe CCGT
Page 146: Claus C Project 1300 MWe CCGT

Cold and Hot settings

Page 147: Claus C Project 1300 MWe CCGT
Page 148: Claus C Project 1300 MWe CCGT

Unacceptable support constructions in GRP

Page 149: Claus C Project 1300 MWe CCGT

Specify GRP piping in full compliance to ISO 14691including1000 h test and perform dynamic calculation

Page 150: Claus C Project 1300 MWe CCGT
Page 151: Claus C Project 1300 MWe CCGT

Power Island Construction (webcam)

Page 152: Claus C Project 1300 MWe CCGT

Lessons Learned

Page 153: Claus C Project 1300 MWe CCGT

How the customerexplained it

How the project leader understood it

How the analystdesigned it

What the eventualowner expected

Page 154: Claus C Project 1300 MWe CCGT

Pipe supports;

Spring loaded supports (also constant spring loaded) , and sliding supports to be checked in cold (in advance of HC and after 1st shut down) and hot condition (during HC and after start-up first shit down) .

These so called Cold and Hot settings shall be indicated in a separate list indicating all applicable values (kks code support, kks branch, date of check, PED category, support type, preload, theoretical travel, actual travel, operating temperature, deviation between theoretical value and actual value (deviation of maximum +/- 10% is allowed))

Page 155: Claus C Project 1300 MWe CCGT

• Dynamic calculation shall be performed for those piping systems where water hammer can occur

• Pipe supports with travel; Cold offset (50% of max travel) shall be installed

• Overthrow devices to be installed to prevent damage due to waterhammer

• Pipe supports; Upside down rigid struts are not allowedPipe

Page 156: Claus C Project 1300 MWe CCGT

Pipe stress Calculations;

• Pipe stress calculation report shall at least contain;• Short description of the piping system and conclusion• Allowable stresses• Description of simulated cases• Line list• PID• Equipment drawings• Table with allowable nozzle loads• Stress Isometric• Pipe support drawings• Input pipe stress calculation program• Pipe support loads (output stress calculation)• Spring data (out put stress calculation)• Verification of nozzle loads• Maximum pipe stresses (output stress calculation)

Page 157: Claus C Project 1300 MWe CCGT

Recommended