+ All Categories
Home > Documents > Clause 51

Clause 51

Date post: 29-May-2018
Category:
Upload: osman-esa
View: 220 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 8/9/2019 Clause 51

    1/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2|OSMAN

    ESA

    |

    1

    CLAUSE 51:

    DETERMINATION OF

    CONTRACTOR EMPLYEMENT

  • 8/9/2019 Clause 51

    2/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    2

    INTRODUCTION

    In general, a job should run smoothly and not be stopped without

    any reason even if there is an extension of time.

    Proved significantly when the contractor could not complete the

    work or have expressed their refusal to complete the work the

    contractor work to be terminated.

    Before the certificate of termination of contractor work, a notice

    of intent should be issued to the contractor in advance.

  • 8/9/2019 Clause 51

    3/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    3

    Sub-clause (a)

    For that Officer Authority to take action.

    - Failure Cases.

    If the contractor commits breach of any one or more of the

    following:

    If without reasonable cause it is suspending the whole or any part

    of the work before the completion of the work.

    If it fails to continue to work with in sequences.

    If it fails to perform according to contract and negligent

    discharge of its obligations.

  • 8/9/2019 Clause 51

    4/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    4

    Continued ....

    If it fails, and repeatedly neglected to comply with a written

    notice of the Superintending Officer to replace or change any

    defective work or materials that are not suitable items.

    If it does not comply with the provisions of Clause 27 (a), (c), and

    (d) of sub-lease and Assignment

    Notice of intent shall be issued in advance where the contractor is

    given 14 days to meremedikan. If you are going then the

    termination notice sent by registered post or recorded delivery

    specifying delivery possible.

  • 8/9/2019 Clause 51

    5/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    5

    Sub clause (b)

    Bankruptcy Cases.

    If the bankruptcy of a contractor to do:

    Commits an act bankruptcy.

    Become insolvent or make a settlement with creditors, creditors

    and make arrangements with them.

    As a company facing a court order (an order winding up).

  • 8/9/2019 Clause 51

    6/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    6

    Continued ....

    Has a liquidator, receiver or temporary manager of the business oroperators properly appointed or surrender possession to be

    taken by or on behalf of creditors, creditors with a floating

    charge of any property comprised in or subject to a floating

    charge on it. The government does not need to send the notice

    of intention, but continue to only send a notice of termination.

  • 8/9/2019 Clause 51

    7/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    7

    Consideration should be taken into account to decide the

    termination of the employment contractor.

    Where the contractor resulted in her continuing inability to

    continue and complete the work, simple things should be done

    by the contractor is a contractor completed the work.

    Where the contractor defaults or fails to continue its

    obligations, especially the contractor fails to continue to work

    diligently, taking the results of the contractor should be

    terminated.

  • 8/9/2019 Clause 51

    8/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    8

    Continued ....

    In deciding whether to consider taking the contractor to be

    terminated based on the interests of employers, the

    administration and its implications in terms of social and

    political. However, the main purpose is to ensure that the

    completed in time.

  • 8/9/2019 Clause 51

    9/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    9

    Prosuder before the contractors removed.

    Government warned prior to the expiration of contractor thedefault within 14 days to take steps to contractor approprite..

    14 days

    If no action or positive measures from the contractor, the

    Superintending Officer to send a notice of intention to end the

    contract by registered mail.

    14 days

    If still no action from contractor, notice of termination sent by

    registered post and the contract will be abolished.

  • 8/9/2019 Clause 51

    10/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    10

    Next action.

    The new contractor will be appointed by the government.

    Assessment of the cost of fiber loss claimed from the old

    contractor not later than three months.

    Government issued a Final Certificate of termination of the

    employment contract the contractor.

    If the contractor fails to comply with such claims even warned the

    government would take legal actions against the Ministry of

    Public Works.

  • 8/9/2019 Clause 51

    11/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    11

    Sub clause (c)

    - Effect of Termination of Employment Contractors

    Sub clause (c) (i) Emergency Authority Officer.

    Employers will take over the site immediately.

    Contractor shall stop the activity immediately.

    Contractor shall leave the building while including material not install

    on site unless instructed in writing Authority of Officer to

    transfer a given time.

  • 8/9/2019 Clause 51

    12/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    12

    Sub clause (c) (ii), (iii) & (iv) further action by the government.

    The Government can complete the work completed by himself or

    others.

    The Contractor shall deliver the right or power to the government

    or employers on all matters of agreement the supply goods,

    materials, performing work implementation of the project work

    as specified in the project.

    Lists and direct the contractor to be transferred to any matter

    specified in sub clause (c) (iv).

  • 8/9/2019 Clause 51

    13/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HANBINA

    AN

    2

    13

    Continued ....

    Contractor shall pay any damages or loss to the government oremployer, if the officer had authority to issue a Final

    Certificate of the amount to be paid after the new contractor is

    appointed.

    Provide cost estimates will be required to complete the job has

    been terminated. For example, the cost of the bid call.

    Impose disciplinary action to the contractor. For example, black

    listed contractor.

  • 8/9/2019 Clause 51

    14/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HA

    NBINA

    AN

    2

    14

    Sub clause (c) (v) & (vi)

    When the government appointed a new contractor will make an

    assessment of costs and / or damage and a claim will be made to

    the original contractor under which the claim is made not later

    than nine months from the date of termination of its acquisition of

    the government will issue a certificate referred to in the Final

    Declaration of contract the termination of the employment of

    contractors.

    If the contractor fails to meet such demands even if copyright has

    been given a reminder, the government will take legal action with

    respect to the legal adviser Ministry of Works.

  • 8/9/2019 Clause 51

    15/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HA

    NBINA

    AN

    2

    15

    Things are in the Final Declaration

    (a) Cost of Completion.

    (A)

    Total interim payments paid to the original contractor.

    Total fees paid to kene Nominated Sub Contractors and Nominated

    Suppliers and others.

    Total Contract Price a new fee to be paid to another contractor to

    complete the work.

  • 8/9/2019 Clause 51

    16/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HA

    NBINA

    AN

    2

    16

    Continued ....

    The total cost of losses to the government as a result of theproject can not be completed, including the cost was calculated

    from the date of termination of employment of the contractor

    until the Completion Date by the new contractor.

    Charges "On Cost" will be imposed on the original contractor for

    the purpose of paying back the cost of administration incurred

    by the employer for the tender call. The value of this charge is

    usually already agreed (10% of the new contract or the total

    costs paid to the new contractor or other person who abandoned

    the job done).

  • 8/9/2019 Clause 51

    17/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HA

    NBINA

    AN

    2

    17

    (b) Adjusted Original Contract Price

    (b)

    The original Contract Sum.

    Net value adjustments in the original Contract Sum.

    Deduction for certain compensation and set the subject of the

    original contract.

    Other deductions that may be imposed by the government under the

    contract. For example, the payment insurance renewal premium.

  • 8/9/2019 Clause 51

    18/18

    ATURCAR

    A

    KONTRAK

    DAN

    BA

    HA

    NBINA

    AN

    2

    18

    THE END


Recommended