Clean TeQ Sunrise CCC Meeting 19 June 2020
Transcript
Page 1: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

CCC Meeting – 19 June 2020

Page 2: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Project Update

Community Engagement Update

Environmental Management Update

CCC Member Questions

Summary

CCC Meeting Presentation – 19 June 2020 Page 2

Page 3: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Project Update

Page 3

Page 4: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Project Update

Page 4

• COVID 19 Response– Risk assessments completed - Visitor declaration forms– Physical distancing (1.5m) - Temperature checks– Regular office sanitisation - Stay at home if feeling unwell– Meeting room limits - Hand sanitiser and regular hand washing

• Personnel Changes– Justine Fisher

• Project Execution Plan– Schedule and funding

• Raw Water Pipeline – Continue to work with the Lachlan and Forbes Shires on agreement

CCC Meeting Presentation – 19 June 2020

Page 5: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Project Update

Page 5

• 132kV Electrical Transmission Line from Parkes to Site– The ETL will supply the required grid connected power to Sunrise for the approved mine life– ETL is proposed at 132 kilovolts (kV) requiring a 45m wide corridor– ETL will be owned by the network service provider– Route options are currently being considered – Key stakeholders include:

• Parkes and Lachlan Shire Councils

• DPIE – Crown Lands

• Private landholders

• TransGrid

• Essential Energy

• Transport for NSW

– Approval sought via Part 5 of the EP&A Act by the network service provider

CCC Meeting Presentation – 19 June 2020

Page 6: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Community Engagement Update

Page 6

Page 7: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Community – Working Together

Page 7

• Sponsorship of Local Agricultural Shows– Pending plan to proceed due to Covid

• Education and Investment– Supporting the Condobolin Public school

through our education sponsorship program to assist with their Breakfast Club

• Fox Baiting Program – Commenced early June on ML 1770 with

other near neighbours

CCC Meeting Presentation – 19 June 2020

Page 8: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Voluntary Planning Agreement Funds

Page 8

• Lachlan Shire Council has constructed a new playground at Gum Bend Lake which is now open to the public

• This playground was funded by:– Clean TeQ VPA funds– NSW Government “Everyone Can Play” grant– Lachlan Shire Council funds

CCC Meeting Presentation – 19 June 2020

Photo courtesy of LSC Facebook page

Page 9: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Keeping People Informed

Page 9

• Community Communication– Transition to more regular updates via

online platforms such as Facebook– Newsletter published in December, next

edition expected later this year at a reduced frequency

– Steve Karaitiana profiled in Summer edition

– Parkes and Condobolin shopfronts will open regularly for enquiries when safe

• Clean TeQ Website– Complaints register published monthly,

zero complaints YTD– Community Complaints line listed on our

website – 1800 752 277

CCC Meeting Presentation – 19 June 2020

https://www.cleanteq.com/sunrise-

project/registering-a-complaint/

Page 10: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Environmental Management Update

Page 10

Page 11: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

• Annual Review– 2019 Annual Review was submitted and accepted by DPIE– No non-compliances identified– Copy can be found on the Clean TeQ website

• Annual Return – Submitted and accepted by NSW EPA– No non-compliances identified

Environmental Annual Reporting

Page 11CCC Meeting Presentation – 19 June 2020

Page 12: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

• A Mining Lease Compensation Agreement has been signed between Clean TeQ, DPIE-Crown Lands and Local Land Services (LLS) for the use of Crown Land within Mining Lease 1770

• ML 1770 varied to include land to the west of Wilmatha Road for ancillary mining activities

• Water Management Plan has been approved by DPIE– copy can be found on the Clean TeQ website

• Noise Management Plan revised– Monitoring suspended until construction

Secondary Approvals

Page 12CCC Meeting Presentation – 19 June 2020

Page 13: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

Environmental Monitoring – Air, Noise and Water

Page 13

• Continuing environmental monitoring in accordance with Development Consent, Environmental Protection Licence and relevant Environmental Management Plans:– Air Quality

– Noise

– Surface Water

– Groundwater

• Results are reported on the Clean TeQwebsite and within the Annual Review

• Particulate Matter monitors (PM10 and PM2.5)– Installed December 2019

– Commissioning underway

CCC Meeting Presentation – 19 June 2020

Page 14: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

• Vegetation screens– Additional 5,000 trees and shrubs planted early June to

replace seedlings that did not survive the drought

Vegetation Screens

Page 14CCC Meeting Presentation – 19 June 2020

Page 15: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

• Vegetation screen locations– Include Mining Lease 1770 and the

Fifield Bypass

Vegetation Screens

Page 15CCC Meeting Presentation – 19 June 2020

Page 16: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

CCC Member Questions

Page 16

Page 17: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise

• Nil received

CCC Member Questions

CCC Meeting Presentation – 19 June 2020 Page 17

Page 18: Clean TeQ Sunrise CCC Meeting 19 June 2020 · 6/19/2020  · CCC Meeting Presentation –19 June 2020. Clean TeQ Sunrise •Vegetation screens –Additional 5,000 trees and shrubs

Clean TeQ Sunrise CCC Meeting Presentation – 19 June 2020

Clean TeQ Holdings Limited

12/21 Howleys Road

Notting Hill VIC 3168

AUSTRALIA

www.cleanteq.com