+ All Categories
Home > Science > CLIC accelerator overview

CLIC accelerator overview

Date post: 23-Feb-2017
Category:
Upload: asafrona
View: 253 times
Download: 0 times
Share this document with a friend
28
1 Tunnel implementations (laser straight) Central MDI & Interaction Region CLIC near CERN Outline: •CLIC and the CLIC CDR (brief) •Strategy and programme 2013- 2018 •With emphasis on 2013 activities •Conclusion
Transcript
Page 1: CLIC accelerator overview

1

Tunnel implementations (laser straight)

Central MDI & Interaction Region

CLIC near CERN

Outline:•CLIC and the CLIC CDR (brief)•Strategy and programme 2013-2018•With emphasis on 2013 activities •Conclusion

Page 2: CLIC accelerator overview
Page 3: CLIC accelerator overview

Possible CLIC stages studied in

the CDR

3

Key features: •High gradient (energy/length)•Small beams (luminosity)•Repetition rates and bunch spacing (experimental conditions)

Page 4: CLIC accelerator overview

4

The key results of the CDR studies

Page 5: CLIC accelerator overview

5

CDR -> input to strategy processes

In addition a shorter overview document was submitted as input to the European Strategy update, available at:http://arxiv.org/pdf/1208.1402v1

Input documents to Snowmass 2013 has also been submitted:http://arxiv.org/abs/1305.5766 and http://arxiv.org/abs/1307.5288

Page 6: CLIC accelerator overview

European Strategy for Particle Physics

High-priority large-scale scientific activities

After careful analysis of many possible large-scale scientific activities requiring significant resources, sizeable collaborations and sustained commitment, the following four activities have been identified as carrying the highest priority (the point below is the one relating to very high energy machines)

d) To stay at the forefront of particle physics, Europe needs to be in a position to propose an ambitious post-LHC accelerator project at CERN by the time of the next Strategy update, when physics results from the LHC running at 14 TeV will be available. CERN should undertake design studies for accelerator projects in a global context, with emphasis on proton-proton and electron-positron high energy frontier machines. These design studies should be coupled to a vigorous accelerator R&D programme, including high-field magnets and high-gradient accelerating structures, in collaboration with national institutes, laboratories and universities worldwide.

Output: Post-LHC high energy frontier machines

Three stage operation scenario from the CDR

Page 7: CLIC accelerator overview

Strategy Output: what is means for CLIC Translated into goals for CLIC for the next European Strategy update (2018): Present a CLIC project that is a “credible” option for CERN beyond 2030-5:•Physics studies updated taking into account LHC-14 TeV (assume the physics case will be there for a high energy frontier machine – i.e. focus beyond the Higgs) •Physics ready after LHC programme completion (2030+) •Initial costs and upgrade costs for 2nd and 3rd stage in reasonable agreement with one could hope based on CERN resources with additional international help – considering a 20-30 year perspective

Three stage operation scenario from the CDR

In this perspective: issues for next phase:Design and Implementation studies:•CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery, not optimized cost, first power/energy estimates without time for reductions, limited industrial costing, very limited reliability studiesX-band developments: •CDR status: Single elements demonstrated – limited by test-capacitySystem-tests: •CDR status: CTF3 results initial phase (as of early 2012), ATF and FACET very little, no convincing strategy for further system verification, programmes for use of Xband techology for other applications in its infancy •CDR status concerning drive-beam FE: Nothing done beyond CTF3 Technology developments: •CDR status: alignment/stability partly covered, BBA assumed, wakefield mon. perf. assumed, no complete module

Page 8: CLIC accelerator overview

Main activities and goals for 2018

Page 9: CLIC accelerator overview

9

Physics at LC from 250 GeV to 3000 GeV• Physics case for the Linear Collider:

• Higgs physics (SM and non-SM)• Top• SUSY• Higgs strong interactions• New Z’ sector• Contact interactions• Extra dimensions• …. AOP (any other physics) …

Specific challenges for CLIC studies: • Need to address Higgs-studies, including gains

for measurements at higher energies • Reach for various “new physics” (list above)

options; comparative studies with HiLumi LHC and proton-proton at higher energies (FCC).

References:CLIC CDR andhttp://arxiv.org/pdf/hep-ex/0112004.pdf

Page 10: CLIC accelerator overview

10

Goal: •Optimize machine (beam parameters and compatible structures) wrt cost and power for 350 (well underway – see examples below), around 1500 (next) and 3000 GeV (CDR) – for various luminosities and safety factors (S)

- Expect significant cost and power reductions for the initial stages•Then we need to chose a new staged parameter set, with a corresponding consistent upgrade path (as done for the CDR), also considering the possibility of an initial klystron power stage See talk in the plenary session Friday

Re-baselining studies

Page 11: CLIC accelerator overview

Power/energy consumptions/reductions

11

CERN energy consumption 2012: 1.35 TWh On-going developments (design/technical developments):•Use of permanent or hybrid magnets for the drive beam (order of 50’000 magnets)•Optimize drive beam accelerator klystron system •Electron pre-damping ring can be removed with good electron injector•Dimension drive beam accelerator building and infrastructure are for 3 TeV, dimension to 1.5 TeV results in large saving•Systematic optimization of injector complex linacs in preparation•Power consumption:

– Optimize and reduce overhead estimates

See parallel session tomorrow on power/energy studies:http://indico.cern.ch/conferenceTimeTable.py?confId=275412#20140204.detailed

Possible paths for power reductions outlined in the CDR:Re-optimize parts

Reduced current density in normal-conducting magnetsReduction of heat loads to HVACRe-optimization of accelerating gradient with different objective function

EfficiencyGrid-to-RF power conversionPermanent or super-ferric superconducting magnets

Energy managementLow-power configurations in case of beam interruptionModulation of scheduled operation to match electricity demand: Seasonal and DailyPower quality specifications

Waste heat recoveryPossibilities of heat rejection at higher temperatureWaste heat valorization by concomitant needs, e.g. residential heating, absorption cooling

Beyond: Scale with inst. luminosity – i.e. running at the end of the project lifetime might be power limited - require more time.

L-band klystron optimization studies

Page 12: CLIC accelerator overview

Graphic User Interface:

Main Linac Tolerances

12

•Test of prototype shows• vertical RMS error of 11μm• i.e. accuracy is approx. 13.5μm

2) Beam-based alignment

Stabilise quadrupoleO(1nm) @ 1Hz

1) Pre-align BPMs+quadsaccuracy O(10μm) over about 200m

3) Use wake-field monitors accuracy O(3.5μm) – CTF3

CLIC performance verifications

FACET

Page 13: CLIC accelerator overview

NEXTEF at KEK

ASTA at SLAC

Very significant increase of test-capacity In addition several more collaborators have or plan to have X-band RF power capabilities

Previous:Scaled 11.4 GHztests at SLAC and KEK.

X-band test-stands

Page 14: CLIC accelerator overview

High-gradient accel. structure test status

Results very good – but: •numbers limited, industrial productions also limited •basic understanding of BD mechanics improving•condition time/acceptance tests need more work•use for other applications (e.g. FELs) needs verification In all cases test-capacity is crucial

Page 15: CLIC accelerator overview

Unloaded

Loaded (CLIC)

Incr

easin

g cu

rren

t

Gradient along the structureBeam loading reduces field locally in the structure

is it the break-down rate lower (or higher)?⇨

Use CTF3 drive beam and klystron driven X-band structure• Measure BDR with/without beam to get a direct

comparison

The effect of Beam-Loading on BD rate

Average gradient 100 MV/m

Drive beam, 1-3A, 100-50 MeV

50 mm circular waveguide

RF

T24 structure installed in CTF3

Page 16: CLIC accelerator overview

Beam loading/BDR experiment

Two-Beam Module, Wake-field monitors, Two-beam studiesRF pulse shaping

Power production, RF conditioning/testing with DB & further decelerator tests

Phase feed-forward,DB stability studies

CLIC Diagnostics tests

CTF3 programme 2013-2016

Page 17: CLIC accelerator overview

17

CTF3 programme 2013-2016

Page 18: CLIC accelerator overview

2013-18 Development PhaseDevelop a Project Plan for a staged implementation in agreement with LHC findings; further technical developments with industry, performance studies for accelerator parts and systems, as well as for detectors.

2018-19 DecisionsOn the basis of LHC data

and Project Plans (for CLIC and other potential projects), take decisions about next project(s) at

the Energy Frontier.

4-5 year Preparation PhaseFinalise implementation parameters, Drive Beam Facility and other system verifications, site authorisation and preparation for industrial procurement. Prepare detailed Technical Proposals for the detector-systems.

2024-25 Construction StartReady for full construction

and main tunnel excavation.

Construction Phase Stage 1 construction of CLIC, in parallel with detector construction.Preparation for implementation of further stages.

Commissioning Becoming ready for data-

taking as the LHC programme reaches

completion.

CLIC future system tests

Systemtests (inside-outside CERN), beyond CTF3, discussed in parallel session Wednesday and plenary session Friday.

Links to what is required in the period 2018 onwards to move towards construction

Page 19: CLIC accelerator overview

• First klystron development contract ready to be signed

• Lots of progress on the modulator design• Gun designed finished, ready to construct• SHB design finished, ready to be build• Overall DB injector design well advanced • Gun test facility under construction

Drive Beam injector front end developments

Page 20: CLIC accelerator overview

20

BI Type CLIC-3-DB CLIC-3-MB

Intensity 278 184

Position 46054 7187

Size 800 148

Energy (spread) 210 (210) 73 (23)

Bunch length 312 75

Beam loss / halo 45950 7790

Beam phase 208 96

Polarization 17

Tune 6

Luminosity 2

Key technology developments – in addition to the X-band related developments - crucial for performance and costs reasons, and hence need verification. Also essential for systemtests as described earlier (CTF3, ATF, Cornell … others). Some examples:•Pulsed, SC and warm magnets: Damping Rings Superconducting Wiggler and Kicker Development•Survey & Alignment, Stability, Magnet development, including PACMAN hardware•Beam Instrumentation and Control (see example of measurement numbers for instrumentation)•Two-Beam module development, for lab and CTF3 measurements •Vacuum systems, collimator studies

Technical Developments

Page 21: CLIC accelerator overview

21

Tech. Dev: Modules and DR related

Page 22: CLIC accelerator overview

22

Tech. Dev: PACMAN, stability (in ATF)

Page 23: CLIC accelerator overview

23

High Gradient technology – other applications

2012 Goals: Feasibility, hoping for LHC physics guidance for post-LHC project Today: •High Gradient Technology ready for use at a reasonable scale (look outside our field)•Explore possibilities where compactness, costs, performance etc can be favourable (session Thursday, examples in the FEL area on this slide) •Very large interest among existing and new collaborators, and our industrial contacts

Page 24: CLIC accelerator overview

29 Countries – over 70 Institutes

Acceleratorcollaboration

Detectorcollaboration

Accelerator + Detector collaboration

CLIC CollaborationSeven new collaboration partners have joined in 2013 (The Hebrew University Jerusalem, Vinca Belgrade, ALBA/CELLS, Tartu University, NCBJ Warsaw, Shandong University, Ankara University Institute of Accelerator Technologies (IAT)) Detector collaboration operative (see talk later of F.Simon)

Page 25: CLIC accelerator overview

25

Link: http://indico.cern.ch/conferenceDisplay.py?confId=275412

296 registered

Main elements:Open high energy frontier session session, including hadron options with FCC

Accelerator sessions focusing on collaboration efforts and plans 2013-2018, parallel sessions and plenary

High Gradient Applications for FELs, industry, medical

Physics and detector sessions on current and future activities Collaboration and Institute Boards

Dinner tomorrow

Page 26: CLIC accelerator overview

Summary

26

The goals and plans for 2012-18 are well defined for CLIC, focusing on the high energy frontier capabilities – well aligned with current strategies Main challenges related to system specifications and performance, system tests to verify performances, X-band test-capacity and general use, technical developments of key elements and technologies, implementation studies including power and costs•The progress in these areas very significant in 2013, and plans and collaborative agreements are (being) in place for the coming yearsA re-baselining of the machine stages with particular emphasis on optmising the staging of the machine, to be able react on LHC physics and possible guidance about the energy scales of new physics The programme combines the resources of collaborators inside the current collaboration, and the collaboration is increasing The use and plans/studies of use of X-band/High gradient technology, in fields outside CLIC, have increased very rapidly and represent many exiting possibilities in the coming years

•Thanks to the CLIC collaboration for the slides and work presented

Page 27: CLIC accelerator overview

27

Page 28: CLIC accelerator overview

Further reading: Main activities goals for 2018

Design and Implementation studies:•CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery, not optimized cost, first power/energy estimates without time for reductions, limited industrial costing, very limited reliability studies•Baseline design and staging strategy•Solid cost basis and more optimized power/energy (aim for 20% energy reduction)•Proof of industry basis for key components/units, in particular those specific for CLIC•Comprehensive reliability/robustness/uptime analysis •Pursue increased use of X-band for other machines/applications

System-tests: •CDR status: CTF3 results initial phase (as of early 2012), ATF and FACET very little, no convincing strategy for further system verification•Complete system-tests foreseen for next phase, and comprehensive documentation of the results at CERN (CTF3) and elsewhere, notably ATF and FACET •Strategy for further system verification before construction (XFEL, connected to light-sources, further drive-beam verifications) or as part of initial machine strategy. •CDR status concerning drive-beam FE: Nothing done beyond CTF3 •Demonstrator of drive beam FE and RF power unit based on industrial capacity – will open for larger facilities beyond 2018 if necessary

X-band developments: •CDR status: Single elements demonstrated – limited by test-capacity•Statistics for gradient and structure choice (energy reach) and other X-band elements

Technology developments: •CDR status: alignment/stability partly covered, BBA assumed, wakefield mon. perf. assumed, no complete module •Demonstration of critical elements and methods for machine performance and construction readiness:

DR, main linac, BDS with associated instrumentation and correction methods (combination of design, simulation, system-tests and technologies)

Stability/alignment (locally and over distances) Module including all parts

Some of the points have been partly addresses already in 2012-2013


Recommended