Date post: | 27-Dec-2015 |
Category: |
Documents |
Upload: | janis-hood |
View: | 220 times |
Download: | 7 times |
CLIC Staged Design October 2012
D. Schulte for the CLIC collaboration
2
CDR Accelerator Volume: 3TeVDrive Beam Generation Complex
Main Beam Generation Complex
CLIC staging, LCWS October 2012D. Schulte
Conceptual design andfeasibility of 3TeV CLIC
3
CDR Accelerator Volume: 500GeVDrive Beam Generation Complex
Main Beam Generation Complex
CLIC staging, LCWS October 2012D. Schulte
A parameter set for 500GeVSome first studies
4CLIC staging, LCWS October 2012
Timeline
D. Schulte
From Steinar
5CLIC staging, LCWS October 2012
Motivation
D. Schulte
Can operate 3TeV CLIC easilydown to 1TeV using full linac
But below 1TeV need bypasses to extract beam early or modify BDS
In this case seems a waste to not use most of the main linac
A staged approach has many advantages•Allows to have first physics earlier• Allows to optimise for each stage better• Stretches the budget• Can take into account lessons of earlier stages
Total cost might increase or mightIn practice decrease
6CLIC staging, LCWS October 2012
CDRVolume 3Staging Scenarios
• Illustrate stages with two cases– 0.5, ~1.5 and 3 TeV– Energy choices we will be
updated based on further LHC findings
– Design based on 3TeV technology
• The examples are:– Scenario A is optimised for
the luminosity at 500GeV– Scenario B is is cost
optimised for the total project cost
D. Schulte
7CLIC staging, LCWS October 2012
Parameter Drivers
D. Schulte
Based on usual luminosity formula:
8CLIC staging, LCWS October 2012
Parameter Drivers
D. Schulte
Upper limit fromLuminosity spectrum(classical regime)
At 3TeV maximum luminosity:L0.01/L>0.3 =>nγ=O(2)N/σx≈1x108/nm (for σz=44μm)
At 500GeV comparable to ISR:L0.01/L≈0.6 =>nγ=O(1)N/σx≈2.5x108/nm
9CLIC staging, LCWS October 2012
Parameter Drivers
D. Schulte
Lower limit from all systems
Upper limit frommain linac lattice and structure
Lower limit from Damping ringBDSRTML
10CLIC staging, LCWS October 2012
Parameter Drivers
D. Schulte
Lower limit from all systems
Upper limit frommain linac lattice and structure
Easier to get N/σx at high energy Ratio of 3TeV to 500GeV is sqrt(1/6)
Just what we need
Lower limit from Damping ringBDSRTML
For fixed structure the charge is independent of energy (almost)
Beamsizes roughly scale assqrt(1/E)
11CLIC staging, LCWS October 2012
Scenario B
Scenario is chosen to reduce cost at 500GeV and the total cost of all stages• Some main beam injector complex for all stages• BDS can be one decelerator sector shorter at 500GeV, fits in 3TeV tunnel•12 sectors powered in second stage is maximum with one drive beam generation complex• Scaled 3TeV BDS design used for stage 2• Can re-use all structures up to 3TeV
D. Schulte
12CLIC staging, LCWS October 2012
Scenario A
Scenario is chosen for luminosity at 500GeV, L=2.3x1034m-2s-1
•Special structure for 500GeV leads to N=6.8x109 vs. 3.7 x109, G=80MV/m vs. 100MV/m, L=2.3x1034m-2s-1vs.L=1.3x1034m-2s-1
•Main beam RF pulse lengths are the same and power is comparable => can use the same drive beam generation complex• Main beam injector at stage 1 needs some additional RF power•Can use 80MV/m structure with the train for CLIC_G (the nominal 3TeV structure) => lose a bit of energy for stage 2
D. Schulte
13
Parameter Comparisonunit Scenario A Scenario B
Ecms TeV 0.5 1.4 3.0 0.5 1.5 3.0G MV/m 80 80/
100100 100 100 100
N 109 6.8 3.7 3.7 3.7 3.7 3.7Nsect 5 12 24 4 12 24
L 1034cm-2s-1 2.3 3.2 5.9 1.3 1.7 5.9L1% 1034cm-2s-1 1.4 1.3 2.0 0.7 1.4 2.0
Pbeam MW 9.6 12.9 27.7 4.6 13.7 27.7Pwall MW 272 364 589 235 364 589η % 3.6 3.6 4.7 2.0 3.8 4.7
D. Schulte CLIC staging, LCWS October 2012
14CLIC staging, LCWS October 2012
Operation Scenarios
Stage Year 1 Year 2 Year 3 Year 4 Year 5
1 5% 25% 50% 75% 100%
2 and 3 25% 50% 100% 100% 100%
Assume 200 days/year50% useful luminosityi.e. 0.864x107s/year
D. Schulte
15CLIC staging, LCWS October 2012
Operation Scenarios
First stages takes two years longer in scenario BBut second stage is one year shorter in BTotal difference is only one year
Ecms Int(L) goal
0.5 TeV 500 fb-1
1.4/1.5 TeV 1500 fb-1
3 TeV 2000 fb-1
D. Schulte
16CLIC staging, LCWS October 2012
Luminosity Operating at Lower Energies
• Use 500GeV scenario A design
• Energy changed by gradient scaling
• Have to adjust bunch charge
• Can increase pulse length at certain energies
• More luminosity possible using extraction lines
D. Schulte
17CLIC staging, LCWS October 2012
Construction Schedule Scenario A
D. Schulte
18CLIC staging, LCWS October 2012
Construction Schedule Scenario A
D. Schulte
19CLIC staging, LCWS October 2012
Power Consumption 3TeV
D. Schulte
We optimised thispart• Largest contribution• Strongest dependence on structure design• Best understood at the time
20CLIC staging, LCWS October 2012
Power Consumption 500GeV (A)
D. Schulte
We considered thispart, which is now a much smaller fraction
• Need to review power consumption in many places• Options for savings exist
21CLIC staging, LCWS October 2012
Cost of the 500GeV StageSwiss francs of December 2010
Incremental cost for B:4MCHF/GeV-> Step to 1.5TeV is less than first stage
D. Schulte
22CLIC staging, LCWS October 2012
Goals for Next Phase• Iterate on energy choices
– 375GeV for the first stage to cover top– 1-2TeV depending on physics findings– 3TeV as current ultimate energy
• Focus on first energy stage– Consider upgrades
• Identify and review cost and power/energy saving options– Identify and carry out required R&D
• Re-optimise parameters– Develop an improved cost and power/energy consumption model– Iterations needed with saving options
• Study alternatives– E.g. first stage with klystrons
• Re-optimise the design
• Need to remain flexible, since we are waiting for LHC findings– But have some robustness of specific solutions and can anticipate this to some
extentD. Schulte
Simplified Parameter Diagram
Drive Beam Generation ComplexPklystron, Nklystron, LDBA, …
Main Beam Generation ComplexPklystron, …
Two-Beam Acceleration ComplexLmodule, Δstructure, …
Idrive
Edrive
τRF
Nsector
Ncombine
fr
Nnb
ncycle
E0
fr
Parameter RoutineLuminosity, …
Ecms, G, Lstructure
Variable Meaning Current value
Idrive Drive beam current 101A
Edrive Drive beam energy 2.37GeV
τRF Mainlianc RF pulse length 244ns
Nsector Number of drive beam sectors per linac
4
Ncombine Combination number 24
fr Repetition rate 50Hz
N Main beam bunch charge in linac
3.72e9
nb MB bunches per pulse 312
ncycle Spacing between MB bunches
6 cycles
E0 MB energy at linac entrance
9GeV
Ecms Centre-of-mass energy 500GeV
G Main linac gradient 100MV/m
24CLIC staging, LCWS October 2012
Some Examples of Saving Options for Current Design
• Cost– Alternative structure fabrication– Longer main linacmodules– Maybe do not need electron pre-damping ring– CVS overdesigned for 500GeV– Main beam sources RF power quite high– Shorter drive beam pulses in first stage can reduce cost of
modulator (modular design)– Combining pairs of drive beam accelerator klystrons– …
• Power– Permanent drive beam turn-around magnets– …
D. Schulte
25CLIC staging, LCWS October 2012
Exploration of Klystron-based First Stage
• The drive beam is necessary to reach high energies– Substantial improvement in scalability compared topreviousX-band designs
• At low energies klystronsmightbe competitive– Easier to qualify components
• No need of 100A beam for module reception tests
– Need klystrons for structure testing– And they are needed for the application of the technology at other
facilities (e.g. medical and light sources)
• Hence started to study a klystron-based first energy stage– As an alternative to a drive-beam based first energy stage– Currently at 500GeV
D. Schulte
26CLIC staging, LCWS October 2012
RF Unit DesignNLC RF unitChr. Adolphsen et al.
For the first exploration a copy of the NLC/GLC design
D. Schulte
27CLIC staging, LCWS October 2012
Structure Optimisation
50 60 70 80 90 1003000
3500
4000
4500
5000
5500
6000
6500
7000
7500
8000Klystron based 500 GeV CLIC
<Eacc
> [MV/m]
Cost
[a.u
.]
2/3: N
s=free, L
s>200mm, t
p=free
2/3: Ns=6, L
s=230mm, t
p=242ns
2/3: Ns=6, L
s=480mm, t
p=242ns
2/3: Ns=6, L
s=480mm, t
p=483ns
CLIC_G, tp=242ns
CLIC_G, tp=483ns
5/6: Ns=free, L
s>200mm, t
p=free
5/6: Ns=6, L
s=230mm, t
p=242ns
5/6: Ns=6, L
s=480mm, t
p=242ns
5/6: Ns=6, L
s=480mm, t
p=483ns
Selected structures from optimisation fordrive beam case
We use a simple cost modelFixed cost per• klystron/modulator/pulse compressor• unit length of linac
D. Schulte
28CLIC staging, LCWS October 2012
Cost vs. Figure of Merit
1 2 3 4 53000
3500
4000
4500
5000
5500
6000
6500
7000
7500
8000Klystron based 500 GeV CLIC
FoM
Cost
[a.u
.]
2/3: N
s=free, L
s>200mm, t
p=free
2/3: Ns=6, L
s=230mm, t
p=242ns
2/3: Ns=6, L
s=480mm, t
p=242ns
2/3: Ns=6, L
s=480mm, t
p=483ns
CLIC_G, tp=242ns
CLIC_G, tp=483ns
5/6: Ns=free, L
s>200mm, t
p=free
5/6: Ns=6, L
s=230mm, t
p=242ns
5/6: Ns=6, L
s=480mm, t
p=242ns
5/6: Ns=6, L
s=480mm, t
p=483ns
Good compromise structuresare marked by arrows
D. Schulte
F.o.M.: L/Imain [arb. units] 1 5
Cost
[arb
. uni
ts]
3000
8000
29
Potential Klystron-based CLIC 500GeV Parameters
D. Schulte CLIC staging, LCWS October 2012
Case 2 3 5 Sc. A CLIC_G NLC
G (loaded) [MV/m] 57 67 57 80 100 52Str. Length: [mm] 480 480 480 229 229 600Δz[RF cycles] 6 6 6 6 6 16Bunch population: N [109] 5.49 4.95 7.01 6.8 3.72 7
Bunches per train:nb 382 335 337 354 312 190Pulse length: τp [ns] 244 244 244 244 244 400Input power: Pin [MW] 76 84 89 74.2 61.3 54Structure efficiency: η [%] 49.5 41.9 48 39.6 28.5 ~31
Est. rel. lumi in peak @ 50 Hz 1.81 1.44 2.04 2.08 1.0 (1.15?)
Klystrons per linac 2454 2292 2850 3520 2359 2232Linac cost [arb. units] 2528 2150 2528 1801 1441 (2771?
)Power / two linacs [MW] 76.5 71.4 88.8 109.7 73.5 (167?)
Linac cost [arb. units] 4982 4442 5378 5321 3800 (5003?)
30CLIC staging, LCWS October 2012
Conclusion on Klystrons-based Stage
• Worthwhile to review– Could be somewhat cheaper solution at low energies– Easier to do full hardware prototyping, since no 100A
beam is needed
• Further steps are necessary to move from an exploration to a realistic design– E.g. do we need a second tunnel, or even more?– Will iterate on the design– Can profit from past studies
• Mightstart some technical developments if useful– High level of synergy with other applications
D. Schulte
31CLIC staging, LCWS October 2012
Conclusion• Have robust staged scenarios for CLIC
– Two examples, since input from physics is missing• Have to wait for LHC and other results
– Based on the feasibility demonstration for 3TeV• Lower energy stages are equally feasible
– Can adjust energy stages to different physics needs• This is the largest uncertainty in the concept
– But concept is not yet fully optimised
• Will further improve the design– Further development of the technical basis
• Adjust design to technical limitations to be neither too aggressive nor to leave too much margin
– More focus on first energy stage• Including alternative technological solution
– Investigation of cost and power/energy reduction options• Re-optimisation of parameters and design
– Systematic optimisation of the design– First results for the CLIC workshop January 2012
D. Schulte
32CLIC staging, LCWS October 2012
Reserve
D. Schulte
33CLIC staging, LCWS October 2012
Klystron-based 500GeV Parameters
D. Schulte
34CLIC staging, LCWS October 2012
Scenario A
D. Schulte
35CLIC staging, LCWS October 2012
Scenario B
D. Schulte
36
Higgs at 125GeV
CLIC staging, LCWS October 2012
~250GeV
D. Schulte
37
Example of Potential SUSY Scenario
CLIC staging, LCWS October 2012
Have to wait for further LHC results before a decision can be made
A strategy process is active in Europe to define future directions
Consistent with current LHC resultsD. Schulte
38CLIC staging, LCWS October 2012
Parameter Choice
D. Schulte
Luminosity can be expressed as
For the classical regime For the quantum regime
Limitation arises from beamstrahlung
39CLIC staging, LCWS October 2012
Luminosity Spectrum Choice
D. Schulte
At 3TeV:L0.01/L>0.3 =>nγ=O(2)For maximum luminosity
At 500GeV:L0.01/L≈0.6 =>nγ=O(1)To be comparable to ISR
40CLIC staging, LCWS October 2012
Comments
• Use BDS and post collision line designs for 500GeV and 3TeV– 500GeV design is shorter by one drive beam sector length– Both can be installed in the same tunnel (slightly different crossing angle)– 1.4/1.5 TeV is using the 3TeV design with magnet strengths scaled down
• Could be improved
• Use the same linac lattice, just shortened– Structure in scenario A is different from 3TeV, in scenario B it is the same
• Do not modify drive beam generation complex– Use only one for both linacs below 1.5 TeV– Shorten pulse length at 500GeV
• Main beam injectors, damping rings and RTML have the same layout– More RF power required at 500GeV in scenario A– Horizontal emittance relaxed in this scenario
D. Schulte
41
Conclusion (for SPC)
Drive beam scheme
Luminosity
OperationMachine Protection
Main linac gradient – Ongoing test close to or on target– Uncertainty from beam loading
– Generation tested, used to accelerate test beam, deceleration as expected
– Improvements on operation, reliability, losses, more deceleration (more PETS) to come
– Damping ring like an ambitious light source, no show stopper
– Alignment system principle demonstrated– Stabilisation system developed, benchmarked,
better system in pipeline– Simulations seem on or close to the target
– Start-up sequence defined– Most critical failure studied– First reliability studies– Low energy operation developed
We are ready for the next phase
CLIC staging, LCWS October 2012D. Schulte