Client: City of Breda/Breda Municipal Electric system Advisor: James D. Mcalley

Date post: 12-Feb-2016
Category:
Upload: manon
View: 26 times
Download: 0 times
Share this document with a friend
Description:
Senior Design: Team SD1101. Client: City of Breda/Breda Municipal Electric system Advisor: James D. Mcalley Team Members: David Mindham (EE), Rui Bai (EE), Anthony Tong(EE), Christopher Krantz (EE. TEAM NAME: “BREDA TRANSFORMERS”. Overview Project Plan. Problem Statement - PowerPoint PPT Presentation
Popular Tags:
26
Client: City of Breda/Breda Municipal Electric system Advisor: James D. Mcalley Team Members: David Mindham(EE), Rui Bai(EE), Anthony Tong(EE), Christopher Krantz(EE Senior Design: Team SD1101 TEAM NAME: “BREDA TRANSFORMERS”
Transcript
Page 1: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Client: City of Breda/Breda Municipal Electric systemAdvisor: James D. McalleyTeam Members: David Mindham(EE), Rui Bai(EE), Anthony Tong(EE), Christopher Krantz(EE

Senior Design: Team SD1101

TEAM NAME: “BREDA TRANSFORMERS”

Page 2: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Overview Project Plan

Problem Statement Conceptual Sketch Functional Requirements Non-functional Requirements Technical/Other Constraints/Considerations Market survey – articulate what makes your

project unique Potential Risks & Mitigation Resource/Cost Estimate Project Milestones & Schedule

Page 3: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Problem Statement

Create a functional one-line diagram using ETAP software

Collect, research, and report economic analysis of companies providing power to city of Breda

Advise and educate city of Breda on alternate sources of energy and money saving techniques

Page 4: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Concept Diagram

Page 5: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Market Survey

Phase 1 development of small town model power distribution system

Understand costs associated with small towns in Iowa

Page 6: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Economic Analysis Design Collect cost data for the following

areas: Generation, Transmission, Distribution, and Regulation.

Many costs are hidden. Once cost breakdown is complete,

we’ll know which areas we can have the greatest impact.

Page 7: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Cost Analysis

Generation Charges: MEAN and WAPA

Demand Charges: MEAN and Midwest ISO

Transmission Charges: MidAmerican and Midwest ISO

Page 8: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Functional Requirements One-line diagram of the power distribution system of Breda

Power analysis Harmonic distortion analysis Loss analysis

Model Requirements 7.2/12.74 kV 3 MW peak input power Primary line: 1 aluminum conductor steel reinforced(ASCR) Secondary line: 4 ASCR Transformers type: Liquid immersed Motors: 120-250 HP Line impedances

Page 9: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Non-Functional Requirements Safety

Electrical Travel

Team work Reliability Alternative energy IEEE Standards Power Factor Maintenance: +/- 5% of unity. Cost Effective Upgrades: All suggested improves

must pay for themselves in 15 years. Non Technical Document: All reports must be

easily understood by a non engineer (City Clerk.)

Page 10: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Constraints/Considerations Team learning how to use ETAP ETAP data is only as good as the

model developed Data for model continually requiring

updates Length of conductors Types of fuses

Page 11: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Technology

ETAP Power Distribution Analysis Software Provided by Iowa State University

Page 12: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Risks and Mitigation

Page 13: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Resource Cost Estimate

ETAP provided by Iowa State University: No Cost

Page 14: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Task Breakdown and Milestones (Updated)

Page 15: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Task Break Down (old)

Page 16: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Overview System Design

Functional Decomposition Detailed Design (functional modules design,

interface definition, user interfaces, etc.) HW/SW/Technology Platform used Test Plan – simulation, what tests, what

metrics, hypothesis, etc. Prototype Implementations or Basic building

block implementations (and applicable results)

Page 17: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Schematic Diagram

Page 18: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Detailed Functional Design 3-phase 7.2/12.47kV Single phase distribution lines 120/240 V Peak power of 1.2 MW Primary lines Aluminum conductor’s steel

reinforced (ACSR) type 1 Secondary lines type 4 ACSR 37 buses single phase 11 industries and business 3-phase power Capacitor bank, fuses, meters, and switches Motors 100 – 250 HP

Page 19: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Functional Decomposition Unbalanced load flow analysis Motor starting analysis Reliability assessment analysis

Page 20: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Prototype Implementations

Page 21: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Test Plan

Page 22: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Current Project Milestones

Page 23: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Contribution

Page 24: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Plan Aug-Dec 2011

Finish ETAP model 09/13/11 Begin Analysis 9/13/11 Finish Cost Analysis 11/15/11 Finish research on alternative energy

12/01/11 Finish reliability assessment

12/01/11 Compile total information and

present to client

Page 25: Client:  City of Breda/Breda Municipal Electric system Advisor:  James D.  Mcalley

Questions