+ All Categories
Home > Documents > CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine...

CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine...

Date post: 01-Mar-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
39
CO 2 Capture From Existing Coal-Fired Power Plants Capture Technology Choices and Costs March 6, 2008 Jared Ciferno National Energy Technology Laboratory
Transcript
Page 1: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

CO2 Capture From Existing Coal-FiredPower Plants

Capture Technology Choices and Costs

March 6, 2008 Jared Ciferno

National Energy Technology Laboratory

Page 2: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

2

Office of Systems Analysis and Planning (OSAP)Functional Teams

• Systems− oriented toward technologies and processes− focused on systems inside the plant boundary

• Situational Analysis− oriented toward issues and policies− focused on higher-level, macro-systems

• Benefits− oriented toward program metrics− focused on evaluation of R&D programs, assessment of national

benefits, “What if?” Studies

• Extensive Collaboration Among Teams

Page 3: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

3

Large Proportion of Total Coal-fired CO2 From Existing Plants

0

500

1,000

1,500

2,000

2,500

3,000

3,500

1995 2000 2005 2010 2015 2020 2025 2030

Unscrubbed SteamUnscrubbed Steam

Scrubbed SteamScrubbed Steam

New SteamNew Steam

IGCCIGCC

Existing units 90.1% of cumulative

coal-fired CO2 2007-2030

(74.6% of year 2030 coal-fired

CO2)

Tons

(mill

ions

)Coal-fired Generation CO2 Forecast

AEO’07 Reference Case

Page 4: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

4

If carbon constraints are mandated in the U.S. then…..1. What are the key challenges associated with PC retrofits?

2. What are the CO2 capture technology options available today for existing plants?

3. What are the economics of retrofitting an existing pulverized coal plant with various levels of CO2 capture?

4. Is there a way to significantly reduce CO2 capture cost for the existingfleet?

5. What level of CO2 recovery is economically optimal or necessary to meet proposed regulations?

Key Questions

Page 5: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

5

Key Challenges to PC CO2 Retrofits

1. Space limitations — acres needed for current scrubbing2. Major equipment modifications or redundancy3. Regeneration steam availability — can steam turbine operate

at part load?4. Sulfur — additional deep sulfur removal required for most

CO2 sorbents 5. Make-up power — satisfy need to maintain baseload output6. *Local storage availability (saline formation, EOR)7. *Scheduling outages for CO2 retrofits8. *Post-retrofit dispatch implications due to increase in COE9. *Retrofit triggering NSPS review10. *Proposed legislation

Page 6: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

6

Existing Pulverized Coal Power Plant

CO2 Capture Challenges:1. Dilute Flue Gas (10-14% CO2)2. Low Pressure CO23. Large volumne—1.5 Million scfm4. 10,000 to 15,000 ton CO2/day5. Large Parasitic Loads (Steam +

CO2 Compression)6. SOx/NOx contaminants

CO2 Capture Challenges:1. Dilute Flue Gas (10-14% CO2)2. Low Pressure CO23. Large volumne—1.5 Million scfm4. 10,000 to 15,000 ton CO2/day5. Large Parasitic Loads (Steam +

CO2 Compression)6. SOx/NOx contaminants

Page 7: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

7

Time to Commercialization

Amine solvents

Physical solvents

Cryogenic oxygen

Advancedphysical solvents

Advancedamine solvents

Ammonia

PBI membranes

Solid sorbents

Membrane systems

ITMs

Ionic liquids

MOFs

Enzymatic membranes

CAR process

Chemicallooping

OTM boiler

Biologicalprocesses

Cos

t Red

uctio

n B

enef

it

Present 5+ years 10+ years 15+ years 20+ years

Post-combustion

Pre-combustion

Oxycombustion

CO2 Capture Technology Options

Page 8: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

8

Carbon Sequestration From Existing Power Plants Feasibility Study (2007)

Randall Gas TechnologiesRandall Gas Technologies

Page 9: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

9

Location: AEP Conesville Unit #5• Total 6 units = 2,080 MWe• Unit #5:

− Subcritical steam cycle (2400psia/1005oF/1005oF)*− Constructed in 1976− 463 MW gross (~430 MW net)− ESP and Wet lime FGD (95% removal efficiency, 104 ppmv)

Ultimate Analysis (wt.%) As Rec’d

Moisture 10.1

Carbon 63.2

Hydrogen 4.3

Nitrogen 1.3

Sulfur 2.7

Ash 11.3

Oxygen 7.1

HHV (Btu/lb) 11,293

Mid-western bituminous coal

Page 10: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

10

Detailed Systems Analysis Scope

1. Assess 30%, 50%, 70%, 90% and CO2 capture levels

2. Employ CO2 scrubbing technology advances

3. Detailed steam turbine analysis by ALSTOM’s steam turbine retrofit group

4. Employ CO2 capture and compression heat integration

5. Site visits to specify exact equipment location

6. Include make-up power costs in economic analysis

Page 11: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

11

Design Basis: Assumptions

EconomicDollars (Constant) 2006Depreciation (Years) 20Equity (%) 55Debt (%) 45Tax Rate (%) 38After-tax Weighted Cost of Capital (%) 9.67Capital Charge Factor (%) 17.5 Capacity Factor (%) 85 Make-up Power Cost (¢/kWh) 6.40CO2 Transport and Storage Costs not included

Page 12: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

12

Existing Plant Modifications

Page 13: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

13

Modified FGD Process1. Second stage absorber added to achieve 99.7% SO2 removal efficiency

(6.5 ppmv)2. Estimated EPC cost for each case (30-90%) is $20.5MM3. Includes an SO2 Credit equal to $608/ton in the Variable O&M cost

Page 14: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

14

Amine Scrubbing Improvements EmployedSince ~2000

Potential Retrofit Options Outcome/Notes1. Heat Integration Steam Consumption

2. Minimize equipment needed Capital cost (ex. No flue gas cooler)

3. Lower cost of materials Capital cost (stainless vs. carbon steel)

4. Structured column packing Capital cost, Sorbent rate (ex. KS1)

5. Plate-and-frame HX Capital cost

6. ANSI Pumps vs. API Pumps Capital cost

7. Vapor-recovery system Steam Consumption

8. Large diameter absorbers # of Absorbers, Capital cost

9. Advanced solvents* Capital cost, Sorbent circ. rate (ex. KS1)

10. Lower re-boiler duty Steam Consumption

*Example:Current amines (MEA) require at least 1,600 Btu/lb CO2 capturedFluor Econamine FG+ requires 1,300-1,400 Btu/lb CO2 capturedMitsubishi’s KS-1 solvent requires 1,200 Btu/lb CO2 captured

Page 15: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

15

CO2 Capture Process Parameters

• Reboiler operated at 45 psia—reduced from 65 psia used in 2000 study• Absorber contains two beds of structured packing

Process Parameter Units 2007 2001 AES DesignPlant Capacity Ton/Day 9,350-3,120 9,888 200

CO2 Recovery % 90-30 90 96

CO2 in Feed mol % 12.8 13.9 14.7

SO2 in Feed ppmv 10 (Max) 10 (Max) 10 (Max)

Solvent MEA MEA MEA

Solvent Concentration Wt. % 30 20 17-18

Lean Loadingmol CO2/mol

amine 0.19 0.21 0.10

Rich Loadingmol CO2/mol

amine 0.49 0.44 0.41

Steam Uselbs Steam/lb

CO2 1.67 2.6 3.45

Stripper Feed Temp oF 205 210 194

Stripper Bottom Temp oF 247 250 245

Feed Temp to Absorber oF 115 105 108

Note: Additional data in “notes pages”

Page 16: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

16

CO2 Capture Process

Page 17: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

17

Flue Gas BypassBypass method determined to be least costly method to obtain lower

CO2 recovery levels

CO2 (Moles/hr) Case 1 (90%) Case 2 (70%) Case 3 (50%) Case 4 (30%)

# Trains 2 2 2

FLUE GAS 19,680

1

19,680 19,680 19,680

4,374 13,120

6,560

5,924 13,770

13,766 5,906CO2 PRODUCT 17,720

BYPASS 0

9,822

15,306

8,746

10,934ABSORBER FEED 19,680

STACK 1,962 9,846

Page 18: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

18

CO2 Capture, Compression, Dehydration, and Liquefaction

CO2 compression to 2,015 psia, EOR specifications

ppmvVol %Wt %Parameter

1000.010.006Moisture

2000.020.03Mercaptans and Other Sulfides

4000.040.03Oxygen

81000.810.3Methane92000.920.6Nitrogen127001.271Hydrogen Sulfide287002.872C2+ and Hydrocarbons94060094.0696Carbon Dioxide

ppmvVol %Wt %Parameter

1000.010.006Moisture

2000.020.03Mercaptans and Other Sulfides

4000.040.03Oxygen

81000.810.3Methane92000.920.6Nitrogen127001.271Hydrogen Sulfide287002.872C2+ and Hydrocarbons94060094.0696Carbon Dioxide

Four Stage Process:

Compression Drying Refrigeration Pumping

Dakota Gasification Pipeline EOR Specification

Page 19: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

19

CO2 Capture Compression, Dehydration and Liquefaction

1. Compression to 200 Psi 2. Drying to 100 ppmv H2O

3. Refrigeration to -10oF

4. Pump to 2,015 Psia

Page 20: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

20

CO2 Capture Process Equipment

CO2 scrubbing technology improvements lead to significant decrease in equipment requirements and capital cost!

CO2 scrubbing technology improvements lead to significant decrease in equipment requirements and capital cost!

2007 Study 2001 Study% CO2 Capture 90 96

ID/Height (ft) No. ID/Height (ft)

34/126 27/126

16/50

Reboilers 10 9

CO2 Compressor 2 7

Propane Compressor 2 7

TIC Cost $MM 370 670

Stripper CW Cond. 12 9

22/50

5

9

1,500 feet

No.

113

131

CO2 Capture Process No.

Absorber 2

Stripper 2

Distance from stack 100 ft

Heat Exchangers No.

Other Heat Exchangers 36

Total Heat Exchangers 58

Page 21: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

21

Steam Turbine Modifications

Design Assumptions:1. Existing turbine/generator required to operate at maximum load in

case of a trip of the MEA plant− All pressures to be within a level that no steam will be blown off

2. Feedwater system modifications to allow CO2 capture and compression system heat integration− CO2 compressor intercoolers, stripper overhead cooler, refrigeration

compressor cooler

3. Well within the LP turbine “lower load limit” after significant steam extraction for the 90% case (Conesville #5 instruction manual)

4. New Let Down turbine vs. modifying existing LP turbine

Page 22: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

22

Steam Turbine ModificationsNew Let Down Turbine

Existing 450 MWSteam Turbine

2,853,607 lbm/hr

3,131,619 lbm/hr

514275 lbm/hr

41.7 psia

269,341

kw

640768 lbm/hr

210.0 psia

293 Deg F Boiler

Feed Pump

ExistingGenerator

Existing

HP

Turbine

Existing

IP

Turbine

From SHTR

From RHTR

To RHTR

Existing

DFLP Turbine

DEA

COND

To Boiler ECON

SCAH

To Boiler

De-Sh Spray

195.0 psia

62,081 kW 716 Deg F

1935690 lbm/hr

65 psia

478 Deg F

64.7 psia

298 Deg F

Reboiler Steam

ABB LGI Scope

New Flow Control Valve

NewLetdownTurbine

MEA System

Reboiler

De-Superheater

New Generator

Condensate

Return Pump

1. New LT output between 15 MW (30%) and 62 MW (90%)2. EPC Cost ~ $10MM for each case

Page 23: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

23

P=90

psi

a

P=47

psi

a

Retrofit solution for 30% Case

Potential solution by properly matching MEA plant requirements and retrofit design

Steam Turbine ModificationsAlternatives to LDT?

Page 24: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

24

New Equipment Locations Identified

CO2 Absorbers

CO2 Strippers& Reboilers

CO2 Compression

Existing Unit #5 Boiler

Secondary SO2Absorber

Existing Unit #5 Turbine

New Letdown Turbine

Existing Unit #5 SO2 Scrubber

Page 25: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

25

Plant Electrical OutputPlant Auxiliary PowerPlant Thermal EfficiencyPlant CO2 Emissions

Plant Performance

Page 26: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

26

Power Output Distribution

434

392363

333303

0

50

100

150

200

250

300

350

400

450

500

Original Plant 90% Capture 70% Capture 50% Capture 30% Capture

Meg

awat

ts

Net BOP CO2 Capture CO2 Compression

463 388 406 424 441

MEASteam

Loss

Page 27: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

27

Base load (Net) Output ImpactLosses to Grid

0

50

100

150

200

250

300

350

400

450

500

Original Plant 90% Capture 70% Capture 50% Capture 30% Capture

Meg

awat

ts

303MW net

333MW net

363MW net

392MW net

434MW net 131 MW30% Loss

101 MW23% Loss

71 MW16% Loss

42 MW10% Loss

Page 28: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

28

Plant Thermal Efficiency(HHV Basis)

0

5

10

15

20

25

30

35

40

Original Plant 90% Capture 70% Capture 50% Capture 30% Capture

Net

Effi

cien

cy (%

HH

V)

24%

27%

29%

35%

32%

Page 29: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

29

CO2 Emissions

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

Original Plant 90% Capture 70% Capture 50% Capture 30% Capture

lbm

CO

2/MW

h

2,000

1,550

1,190

780

290

California Proposed

State-of-the-art NGCC

Page 30: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

30

Capital CostsIncremental COEMitigation CostsSensitivity Analyses

Economics

Page 31: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

31

Plant Retrofit Capital Costs

EPC Costs ($1000’s) 2001 2007 Study% CO2 Capture 96 90 70 50 30

Flue Gas Desulfurization 22,265 22,265 22,265 22,265 22,265

New Net Output (kW) 251,634 303,317 333,245 362,945 392,067

$/kW-Original Net Output* 1,616 922 842 647 488

CO2 Capture & Compression 668,277 368,029 333,406 186,694

9,400 8,900

0

280,655

773

0

365,070

1,095

10,516

0

701,057

2,786

134,509

Letdown Steam Turbine 9,800 8,500

Total Retrofit Costs 400,094 211,835

Boiler Modifications 0 0

$/kW-New Net Output 1,319 540

*Original net output = 433,778 kW

53% Reduction in Incremental Capital Costs

Note: Capital costs from 2001 study were escalated to 2006 dollars

Page 32: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

32

Total Cost of Electricity

0

1

2

3

4

5

6

7

8

9

10

11

12

13

90% Capture 70% Capture 50% Capture 30% Capture

Bas

e Pl

ant C

ost o

f Ele

ctric

ity (¢

/kW

h)

Note: Base power plant cost for the existing plant obtained from Energy Velocity

Base Power Cost = 2.5¢ per kWh

Page 33: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

33

Total Cost of Electricity

0

1

2

3

4

5

6

7

8

9

10

11

12

13

90% Capture 70% Capture 50% Capture 30% Capture

Bas

e +

Incr

emen

tal C

OE

(¢/k

Wh)

6.65.9

4.94.1

Notes: COE is based off Total Plant Cost (Bare Erected Cost + Project and Process Contingencies); Does not include owner’s costsBase power plant cost for the existing plant obtained from Energy Velocity

Base Power Cost = 2.5¢ per kWh

Capital

Fixed O&M

Variable O&M

Retrofit sub-total COE

Page 34: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

34

Total Cost of Electricity

0

1

2

3

4

5

6

7

8

9

10

11

12

13

90% Capture 70% Capture 50% Capture 30% Capture

Tota

l Cos

t of E

lect

ricity

(¢/k

Wh)

11.8

9.5

7.2

5.4

Notes: Greenfield plant is a supercritical PCCOE is based off Total Plant Cost (Bare Erected Cost + Project and Process Contingencies); Does not include owner’s costsRetrofit power plant make-up power assessed between 6.40 and 12 ¢/kWhBase power plant cost for the existing plant obtained from Energy Velocity

Retrofit Total COE

Base Power Cost = 2.5¢ per kWh

Capital

Fixed O&M

Variable O&M

Make-up Power(MUPR)

MUPR12 ¢/kWh

MUPR6.4 ¢/kWh

Page 35: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

35

Total Cost of Electricity

0

1

2

3

4

5

6

7

8

9

10

11

12

13

90% CaptureGreenfieldTotal COE

90% Capture 70% Capture 50% Capture 30% Capture

Tota

l Cos

t of E

lect

ricity

(¢/k

Wh)

11.8

9.5

7.2

5.4

Notes: Greenfield plant is a supercritical PCCOE is based off Total Plant Cost (Bare Erected Cost + Project and Process Contingencies); Does not include owner’s costsRetrofit power plant make-up power assessed between 6.40 and 12 ¢/kWhBase power plant cost for the existing plant obtained from Energy Velocity

Retrofit Total COE

Base Power Cost = 2.5¢ per kWh

Capital

Fixed O&M

Variable O&M

12

Make-up Power(MUPR)

MUPR12 ¢/kWh

MUPR6.4 ¢/kWh

Page 36: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

36

Economic ResultsCO2 Captured Cost

5964 67

77

5458 61

70

0

10

20

30

40

50

60

70

80

90% Capture 70% Capture 50% Capture 30% Capture

$/To

nne

CO

2 Rem

oved

$/To

n C

O2 R

emov

ed

$/Tonne Removed $/Ton Removed

Page 37: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

37

Economic ResultsCO2 Avoided Cost

8996 99

113

8187 90

103

0

10

20

30

40

50

60

70

80

90

100

110

120

90% Capture 70% Capture 50% Capture 30% Capture

$/To

nne

CO

2 Avo

ided

$/To

n C

O2 A

void

ed

$/Tonne Avoided $/Ton Avoided

Page 38: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

38

1. No major technical barriers found to retrofit with current state-of-the-art scrubbing technology

2. Compared to the 2001 study, this study with an advanced amine (90% CO2 Capture case) showed:• Marked improvement in energy penalty and reduction in

cost

3. Near linear decrease in incremental COE with reduced CO2capture level

4. Sufficient results to answer various definitions of “optimal CO2 capture” from existing plants

1. No major technical barriers found to retrofit with current state-of-the-art scrubbing technology

2. Compared to the 2001 study, this study with an advanced amine (90% CO2 Capture case) showed:• Marked improvement in energy penalty and reduction in

cost

3. Near linear decrease in incremental COE with reduced CO2capture level

4. Sufficient results to answer various definitions of “optimal CO2 capture” from existing plants

Conclusions

Page 39: CO2 Capture From Existing Coal-Fired Power Plants...Mar 06, 2008  · Existing 450 MW Steam Turbine 2,853,607 lbm/hr 3,131,619 lbm/hr 514275 lbm/hr 41.7 psia 269,341 kw 640768 lbm/hr

39

Thank You!

Email: [email protected]: 412-386-5862

NETL Energy Analysis Link:www.netl.doe.gov/energy-analyses


Recommended